To: Communities and Housing Policy Board 
On: 17 January 2023
___________________________________________________________________
Report by: Director of Communities and Housing Services
___________________________________________________________________
Heading: Building Communities, Greenspaces, Parks & Play Areas and
Villages Investment Fund Update
___________________________________________________________________ 
1. Summary 
1.1 This report updates the Communities and Housing Policy Board on progress
made in supporting communities including projects funded through the
Greenspaces, Parks & Play Areas and Villages Investment fund. It provides
updates for the Board on projects awarded under delegated authority over the
last 3 months; and on other work undertaken by the Building Communities
service to support active and engaged communities.  
1.2 The key objective of the Green Spaces and Villages Investment funding is to
work with, and support, community groups to identify and deliver improvement
projects in their local communities, improve their local greenspaces (including
parks and play areas) and strengthen the identity, heritage, uniqueness and
character of village life. 
1.3 The Villages Investment Fund is promoted to members of the relevant Local
Partnerships to encourage eligible communities to come forward to bid for
their share of the remaining funds.   
Review of Allocated Funding
1.4 As the programme has developed it is clear that a number of projects have
either completed without requiring the full grant allocation or have had
difficulty in developing their project fully in the way that they originally
anticipated. In order to ensure that funding is available for projects that can be
implemented, a review of successful applicants, whose funds have not yet
been released is being undertaken and applicants have been contacted to
ascertain the status of their project.  This has resulted in a return of £12,000
to the Villages Investment Fund, and £5,000 to the Green Spaces Fund so
far. The return of £12,000 is from Bishopton Community Development Trust
who have been unsuccessful in procuring the open green space at Rossland
Crescent from the private landowner and will therefore not be able to proceed.

Page 2

Pachedu have not drawn on their approved £5,000 for their RAMH
Community Garden Project. Despite repeated emails and a deadline, no
response has been received and it is anticipated that this funding will now be
returned to the unallocated Green Spaces funding. 
1.5 As the Green Spaces Fund is almost fully committed, it is proposed 50% of
the allocated funding ringfenced for school projects be returned into the wider
Fund. Only 3 schools, to date, have expressed an interest in applying. 
1.6 As both funds draw to a close, it is proposed smaller, grass roots community
projects are prioritised over larger applications.  Additionally, areas who have,
to date, benefitted less from the fund, will be favoured if bidding in competition
with a community who have benefitted significantly in previous funding
applications.   
1.7 Three projects have been approved under delegated authority since the last
Board report and details are included in Appendix 1.  Taking account of these
three projects, and all awarded projects to date, £30,000 is currently
unallocated in the Villages Investment Fund and £55,000 unallocated in the
Green Spaces Fund. Where community projects being developed submit
applications, remaining funds will be committed. 
1.8 Kilbarchan Public Park, Lochwinnoch and Ferguslie Park Gardens have all
been upgraded since the last report.  Communities using the new facilities are
appreciative of the award and the positive impact on their communities.  
Building Communities
1.9 Team Up to Clean Up volunteers continue to be grateful for the provision of
heavy-duty gardening gloves and protective, comfortable clothing and
footwear to support their activity.  2 leaf blowers have been provided to keen
volunteers as well as other hand tools.  The Team have nominated volunteers
for Provost Awards to recognise and celebrate some of the most active
members of the group. 
1.10 Reflecting on the success of the Celebrating Renfrewshire Fund, over 2,000
young people voted across Renfrewshire in which projects they wanted to see
delivered in their community.  With all funding allocated, the objective is to
deliver proposed activities before the end of the financial year. The
Celebrating Renfrewshire Steering Group were all recognised for their
volunteering, with each of them receiving a Saltire Award. The cross-service
Council Team, together the Steering Group, is undertaking a review of the
evaluation process to ensure fairness and transparency are central to the
awards. Plans are underway to recruit 2023’s Celebrating Renfrewshire
Steering Group with the aim of launching the Fund soon as possible after the
new financial year.

Page 3

1.11 Building Communities is also supporting community engagement for the
voting stage of the #YouDecide project.  Officers have been involved in
reaching out to all ages through primary & secondary school engagements, as
well as ROAR and Sheltered Housing complexes, to ensure the initiative
outcomes are directed by a Renfrewshire wide and intergenerational
audience. 
________________________________________________________
Recommendations
2.1 It is recommended that the Communities and Housing Policy Board: 
(a) note the work currently being undertaken to support communities as
they develop and deliver projects funded using the Greenspaces,
Parks & Play Areas and Villages Investment Fund; 
(b) note the impact of the funding and the benefits to the wider
communities delivered by the projects set out in section 4 of this
report; 
(c) note the return of unspent grant awards by Pachedu, (£5,000 to the
Green Spaces Fund), and Bishopton Community Development
Trust, (£12,000 to the Villages Investment Fund); 
(d) approve the intention to prioritise awards to communities who have
benefitted less from previous grant awards; and 
(e) agree a 50% reduction of the ringfenced school fund to boost
available Green Spaces funding for smaller projects. 
_________________________________________________________
3. Summary of Applications under Construction 
3.1 Renfrewshire Council has supported 90 community projects since October
2018 which have met the criteria for this fund.  Further projects continue to be
developed within communities with the following potential applicants currently
active and expected to apply: 
 The Darkwood Crew – Teen Shelter
 Millview Park, Renfrew – Play Park Equipment
 Inchinnan Development Trust – equipment to support maintenance of
green areas in and around Inchinnan
 Kilbarchan Primary Parent Council – replacement play equipment in
school which is accessible to all children in the village. 
3.2 Reports will be brought back for the consideration of the Board in relation to
these projects at future meetings of the Communities and Housing Policy
Board. 
_________________________________________________________

Page 4

4 Building Communities 
4.1 Building Communities’ focus on community engagement is recognised and
being harnessed by wider Council Services.  Support was recently delivered
encouraging public participation in voting for projects listed within Environment
& Infrastructure’s #YouDevide Project.  Team Up to Clean Up volunteers
promoted the project to their own local community by appearing in
photographs online and on leaflets.   
4.2 Officers undertook significant engagement with schools and young people to
support, steer and deliver Chief Executives Celebrating Renfrewshire project.   
4.3 Early conversations are ongoing with Social Work considering the
implementation of Neighbourhood Hubs.   
Team Up to Clean Up 
4.4 In October 2022, Team Up to Clean Up celebrated it’s 5-year anniversary. 
This was well received by the community:

Page 5

Environmental Task Force 
4.5 Delivered under the Team Up to Clean Up banner, the Environmental Task
Force is now operational, undertaking daily patrols to key identified hotspot
areas.  Close links, already firmly established with StreetScene, are being
leaned upon to ensure processes to maximise the opportunity to identify the
flytipping source, are followed.  Officers and Operatives are working well
together, presenting a public united front and adopting orange high vis
branded workwear, as opposed to standard Council yellow. 
4.6 Building Communities has taken on responsibility for recording all reported
instances of flytipping on one software system.  Historically the Community
Safety Partnership recorded on one software system, while StreetScene
adopted another.  One source of data will increase the quality of flytipping
information and intelligence, as well as offer more accurate data to extract and
report on.  This improved data can be monitored to provide a greater
opportunity to focus resources where evidence dictates.  Future reports to
elected members will include data on overall instances of fly tipping activity
and the success of initiatives to identify and take enforcement action against
perpetrators and ultimately to change public expectations and behaviours. 
Hot Food Retailer Incentive Scheme 
4.7 Building Communities is taking action to support businesses to reduce their
reliance on single use plastics.  The project also supports the Scottish
Government ban on single use plastics implemented into legislation in August
2022. 
4.8 Building Communities, with the support of Sweco, an external organisation,
have undertaken to visit every take-away premise in Renfrewshire.  Sweco
have employed students, studying environmental topics from the Paisley
Campus of the University of the West of Scotland, to deliver this work.  The
survey, designed to capture the onsite availability of banned single use
plastics, will also identify other sustainable practices.  The outcomes will be
shared with Environmental Health and Economic Development who are also
supporting the project.

Page 6

4.9 Awareness of expectations on businesses as a result of the prescribed ban
will be increased by way of an in-person survey, as well as a booklet which
will be provided.  The booklet details alternative packaging options and tips to
increase a business’s sustainability. 
4.10 A ratings scheme will be adopted enabling the most sustainable businesses to
be identified.  Such businesses will be celebrated and customers, inclined to
be influenced by these good habits, will be supported to recognise these
businesses more easily.   
4.11 The business survey will take place throughout January, after students
December exams.  The project is expected to be concluded in in March 2023,
embedding the scheme thereafter. Further information on the development
and implementation of the ratings scheme will be provided at the next meeting
of the Policy Board.    
Celebrating Renfrewshire 
4.12 2022’s Celebrating Renfrewshire project commenced with the recruitment of a
brand-new Youth Steering Group.  The Group were tasked with leading on the
design of the Fund, such as themes, the award sum available, as well as the
overall Fund theme. The recruitment event was delivered in August and
included an advice and information session from former steering group
members.  
 
4.13 The Steering Group was made up of young people who live or work in
Renfrewshire.  They were provided with support from a number of Services,
including Community Learning and Development Youth Services, Chief
Executives and Street Stuff’s Youth Diversion Project.  Keith Lasley, St
Mirren’s Chief Operating Officer also attended offering advice and support
from St Mirren football club.

Page 7

4.14 Applications were encouraged from young people aged 12-24 years old
throughout September.  Received applications were checked for compliance
against the approved criteria by the Steering Group and sorted into Local
Partnership areas to facilitate voting.  Environment & Infrastructure assisted
by building a voting platform.   
4.15 Building Communities undertook a 2-week engagement exercise engaging
with secondary school pupils to encourage maximum voting potential. Almost
2,200 votes were received. 
4.16 Over 100 local people attended the event held in late October, which
confirmed the successful projects.  The event was arranged by the Youth
Steering group at the Student Union, University of West of Scotland, Paisley
Campus. Feedback provided on the night revealed that attendees enjoyed the
event.   
#YouDecide 
4.17 Building Communities provided significant support engaging with communities
for Environment & Infrastructure’s #YouDecide participatory budgeting project
throughout late November/early December.  The launch of #YouDecide’s
community engagement programme coincided with the start of the
Environmental Taskforce, as such the team provided a valuable support and
resource whilst bonding and getting to know one another. 
4.18 Team Up to Clean Up volunteers were instrumental in promoting voting in
their areas and #YouDecide closed with over 4,000 votes cast in communities.   
Local Partnerships

Page 8

4.19 The wider Community Learning and Development Team (CLD) consisting of
Youth Services, Adult and Families and Building Communities, delivered a
series of input sessions to Local Partnerships.  The role and functions of CLD
were explained, as well as how the service can support Local Partnerships in
delivering their local priorities.   
4.20 Each local partnership is being provided with a single point of contact within
the Building Communities service to ensure communities and members of the
partnership can access relevant Council Services and support easily.  These
contacts will ensure enquiries and local concerns are resolved or directed to
the appropriate Council Service and will seek to drive forward work and
priorities identified by local partnerships within their area. 
4.21 Working in partnership with Renfrewshire Health and Social Care Partnership,
a database detailing ongoing and aspirational community projects is currently
under construction.  Key community individuals, groups and organisations are
being identified and will be included on the database to create a focus on
building nurturing, mutually beneficial relationships between Council and
communities.    
___________________________________________________________________ 
Implications of the Report 
1. Financial - Council approved the allocation of £2.020 million to establish the
Greenspaces, Parks & Play Parks and Villages Investment Fund in March
2018.  Due to the capital works being undertaken, Officers are ensuring that
there are minimal recurring revenue costs to Services in the coming years. 
2. HR & Organisational Development – None 
3. Community/Council Planning – 
The Greenspaces, Parks & Play Parks and Village Investment Fund will be
important to achieving and assisting the Community Plan by ensuring that
Renfrewshire is thriving, well, fair and safe for residents, workers and visitors. 
4. Legal - All legislative requirements will be taken cognisance of during this
process wherever required e.g. health and safety requirements. 
5. Property/Assets - There is the potential for property/assets to be included as
part of this fund. 
6. Information Technology – None 
7. Equality & Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website.

Page 9

8. Health & Safety - Cognisance will be taken of health and safety requirements
wherever required e.g. for play park equipment. 
9. Procurement - There is no potential for the Council to be procuring and
installing equipment of behalf of a community group as part of this grant
funding process. 
10. Risk - Discussions with the Council Risk Manager are on-going to ensure that
the risk to the Council, as part of this grant funding process, is minimised. 
11. Privacy Impact - None. 
12. COSLA Policy Position – Not Applicable 
13. Climate Risk – Not Applicable
_________________________________________________________ 
List of Background Papers
None 
___________________________________________________________________
Author:  Oliver Reid, Head of Communities and Public Protection.

Page 10

Appendix 1 
Current Greenspace, Parks and Play Areas & Villages Investment Funding 
Project Funding
proposed
External Funding (or other Council funding)
Friends of Jenny’s Well Mural
painting on container  £2,500
Miller Homes £250
Taylor Wimpy £100 
Glencorse Community
Woodland
£5,000 n/a
Cross Road Community Group £2,000 n/a 
Funding Allocated Budget Committed Budget Available Budget Potential Additional
Projects
Greenspace, Parks and Play
Areas
£1,280,000 £1,224,943 £55,057 £55,000
Village Investment Fund £740,000 £709,826 £30,174 £25,00
Staffing costs £220,000 £220,000 £0 -
Total £2,240,000 £2,154,769 £85,231 £80,000