Page 1

Minute of Meeting
Communities and Housing Policy Board 
Date Time Venue
Tuesday, 25 October 2022 13:00 Council Chambers (Renfrewshire), Council
Headquarters, Renfrewshire House, Cotton
Street, Paisley, PA1 1AN 
Present: Councillor Jacqueline Cameron, Councillor Gillian Graham, Councillor Lisa-Marie
Hughes, Councillor Robert Innes, Councillor Alec Leishman, Councillor Mags MacLaren,
Councillor Colin McCulloch, Councillor Janis McDonald, Councillor Cathy McEwan,
Councillor Marie McGurk, Councillor Iain McMillan, Councillor John McNaughtan, Councillor
Emma Rodden 
Chair
Councillor McGurk, Convener, presided. 
In Attendance
L McIntyre, Head of Policy & Commissioning, A Armstrong-Walter, Strategic Partnership &
Inequalities Manager, M Kirk, Assistant Planning & Policy Development Officer, S Marklow,
Strategy & Place Manager and D McLavin, Senior Communications Officer (all Chief
Executives); J Trainer, Head of Child Care & Criminal Justice (Children’s Services); F
Carlin, Head of Housing Services, O Reid, Head of Communities & Public Protection, N
Drummond, Lead Officer (Environmental Co-ordination), L Feeley, Housing Asset &
Investment Manager, T Irvine, Homeless & Housing Support Services Manager, D Murray,
Area Housing Manager, C Robertson, Warden Services Manager and R Walkinshaw,
Housing Regeneration & Development Manager (all Communities & Housing Services);
and J Kilpatrick, Finance Business Partner, G Dickie, Partnering & Commissioning
Manager, D Pole, End User Technician, R Devine and C MacDonald both Senior
Committee Services Officers and D Cunningham, Assistant Democratic Services Officer
(all Finance & Resources). 
The item of this minute against which is set the prefix ND is a non-delegated item   
Webcasting of Meeting
Prior to the commencement of the meeting the Convener intimated that this meeting of the
Board would be filmed for live or subsequent broadcast on the Council's internet site.

Page 2

Apologies
Councillor Hood and Councillor McGuire.  
Declarations of Interest
There were no declarations of interest intimated prior to the commencement of the
meeting. 
1 Police and Fire & Rescue Services Scrutiny Sub-committee
There was submitted the Minute of the meeting of the Sub-committee held on 16
August 2022, which forms the Appendix to this Minute. 
DECIDED: That the Minute be approved. 
2 General Services Revenue, Housing Account and Capital Budget
Monitoring Report
There was submitted a General Services Revenue, Housing Account and Capital
Budget Monitoring report by the Director of Finance & Resources for the period 1 April
to 16 September 2022.  
The report stated that the projected outturn as at  31 March 2023 for all services
reporting to this Policy Board was an overspend position of £0.028 million. The
projected capital outturn for projects reporting to this Policy Board was a breakeven
position against the revised budget for the year. Summaries were provided over the
relevant services in the tables within the report, together with further analysis. It was
also highlighted that following changes in responsibilities, agreed at the meeting of
Renfrewshire Council held on 29 September 2022, the report excluded reference to
Building Standards, which now reported to the Planning & Climate Change Policy
Board and highlighted the consequential budget adjustment of £0.189m to reflect this
transfer of responsibility. It was also noted that the report incorporated Regulatory
Services responsibilities which had previously reported to the Infrastructure, Land and
Environment Policy Board and that the budget had been increased by £1.775m to
reflect this transfer of responsibilities. In addition, the report indicated that further
revenue expenditure budget adjustments totalling £0.464 million, comprising
adjustments of £0.037 million in respect of Housing Support Pay Uplifts, £0.194
million transferred from the Tenant Hardship Grant Fund Reserve and £0.233 million
relating to the Summer Holiday Food & Child Care Programme, had been processed
since consideration of the previous report by the Policy Board. 
DECIDED: 
(a) That the projected Revenue outturn position, detailed in table 1 of the report, be
noted; 
(b) That the projected Capital outturn position, detailed in table 2 of the report, be

Page 3

noted; and 
(c) That the budget adjustments, detailed in sections 4 and 6 of the report, be noted. 
3 Greenspace, Parks and Play Park Funding
There was submitted a report by the Director of Communities & Housing Services
relative to the Greenspaces, Parks & Play Areas and Villages Investment Fund. The
report indicated that the key objective in allocating funding was to work with, and
support, community groups to identify and deliver improvement projects in their local
communities, improve their local greenspaces, including parks and play areas, and
strengthen the identity, heritage, uniqueness and character of village life. 
An update on progress made in supporting community projects through the
Greenspaces, Parks & Play Areas and Villages Investment Fund, detailed, in
Appendix 1 of the report, projects approved by the Director of Communities & Housing
Services in terms of delegated authority and outlined projects currently being
developed by communities across Renfrewshire. It was highlighted that the current
projects being developed by communities, and referred to in section 3 of the report,
would almost fully commit the available Greenspaces, Parks and Play areas element
of the fund. It was also noted that as the Greenspaces fund moved toward closure in
terms of the development of new projects and bids, the work of the team had been
increasingly focused on supporting successful community projects to be delivered. In
this connection challenges impacting on expected delivery dates and costs which, in
turn, provided challenges for communities in realising their aspirations as quickly as
anticipated were referenced. The report advised that Lochfield Bowling Club Bowling
Club wished to repurpose the funding previously awarded for a synthetic green and
feasibility study, to improve drainage, create new banking, steps and fencing, repairs
to the irrigation system and replacement of the clubhouse kitchen; and Corseford
Tenants' & Residents' Association wished to use funding, previously awarded to
purchase tools and a container for storage, to create a butterfly boulevard in the
community with wildflowers. The specific reasons why the original proposals were no
longer being pursued were provided.   
DECIDED: 
(a) That the work currently being undertaken to support communities as they
developed and delivered projects to be funded using the Greenspaces, Parks & Play
Areas and Villages Investment Fund be noted; 
(b) That the project, detailed within section 3 of the report and Appendix 1, be
awarded grant funding totalling £50,000; 
(c) That the proposals from Lochfield Bowling Club and Corseford Tenants' &
Residents' Association to repurpose the funding previously awarded, as set out in
section 1 of the report, be agreed; 
(d) That the positive impact of the funding and the benefits to the wider communities
delivered by the projects, as set out in section 4 of the report, be noted; and

Page 4

(e) That it also be noted that the projects currently being developed by communities,
and listed in section 3 of the report, would almost fully commit the available
Greenspaces, Parks and Play areas element of the fund. 
4 Community Empowerment Fund
There was submitted a report by the Chief Executive relative to applications
considered for funding from the Community Empowerment Fund in the current round
of funding. The total value of the requested grant funding was £16,920. A cross-
service panel of officers had been established to review and assess applications to
the Community Empowerment Fund against agreed objectives and criteria. The report
outlined the key objectives and aims of the Fund and indicated that one new
application had been received in the current round and had been considered along
with one application which had previously been deferred. Summaries of the
applications for funding, together with recommendations, were provided within an
appendix to the report. 
The report also intimated that following the award of Community Empowerment
Funding of £50,000 to Renfrew Victoria FC in the previous round, the group had
secured a further £83,000 from Sports Scotland to upgrade the facilities at
Kirklandneuk. 
DECIDED: That the recommendations, detailed in Section 4 and Appendix 1 of the
report, to (a) award £7,720 to Inchinnan Development Trust for support with legal fees
relating to the Community Asset Transfer lease for India Tyres Playing Fields; and (b)
award £9,200 to Lochwinnoch Development Trust for soil testing on the Lochhead
Gardens site be approved. 
5 Renfrewshire Strategic Housing Investment Plan 2023/28
There was submitted a joint report by the Chief Executive and Director of
Communities & Housing Services relative to the Renfrewshire Strategic Housing
Investment Plan 2023/28. 
The report indicated that the Strategic Housing Investment Plan (SHIP), which
detailed how the Council and partners would deliver new affordable homes across
Renfrewshire over the next five-year period and how the delivery of existing projects
currently included within the Plan would be maximised. It was noted that funding for
affordable housing would be targeted to achieve the objectives contained within
Renfrewshire’s Local Housing Strategy and be reviewed and updated annually. The
Renfrewshire SHIP 2023/28, a copy of which was appended to the report, had been
developed following consultation and took cognisance of projects which were
expected to complete, potential slippage and estimates of when new projects could
potentially be brought forward. The finalised Plan incorporated issues raised via the
comments received during the consultation process. Details of the Future Resource
Planning Assumptions for the period 2022/26 were also provided. It was noted that,
subject to approval, the Renfrewshire SHIP 2023/28 would be submitted to the
Scottish Government. 
DECIDED: That the Renfrewshire Strategic Housing Investment Plan 2023/28 be
approved for submission to the Scottish Government.

Page 5

6  Paisley West End - Regeneration Update
There was submitted a report by the Director of Communities & Housing Services
relative to progress made in terms of the implementation of the regeneration
masterplan for the West End area of Paisley. 
The report made reference to the Regeneration Masterplan for the West End area of
Paisley, approved at the meeting of the Leadership Board held on 12 December
2017, which was to be implemented by Sanctuary (Scotland) Housing Association
Limited in partnership with the Council and Scottish Government. The plan required
the acquisition of 129 private properties which would thereafter be demolished to
facilitate the delivery of new development. It was highlighted that despite considerable
effort by Council officers, Sanctuary and its agents to engage with the local
community and those within the wider West End area it had not been possible to
contact all of the property owners. Sanctuary’s appointed agent had successfully
negotiated the acquisition of a number of privately owned residential and commercial
property interests throughout the masterplan area and continued to actively negotiate
terms with private owners, with transactions at various stages of the legal process.
Sanctuary’s application for planning permission for 35 new residential units on sites at
Sutherland Street, Paisley and Underwood Lane, Paisley had been granted on 21
April 2021 and Sanctuary was currently procuring a contract for the erection of the
housing.  Provision was included within Renfrewshire Council’s Strategic Housing
Investment Plan (SHIP) for grant funding from the Scottish Government to support
their delivery. It was noted that architects had been appointed to design the
subsequent phases of development and that this process would consider
arrangements for issues such as traffic, cleansing and waste services, geotechnical &
land remediation, parking, open space, tenure, archaeology and demolition &
conservation. These proposals would be progressed to a detailed design and be
subject to community consultation and stakeholder engagement with a view to
submitting an application for full planning permission for the remainder of the
masterplan area. 
Updates were also provided in respect of the acquisition process for properties at 1, 2
and 4 Underwood Lane, 2-20, 13-17, 22, 26, and 30-34 Well Street, Paisley, 1-5
Clavering Street, Paisley and an area of land behind 2-20 Well Street, Paisley.
Authorisation was now sought to progress Compulsory Purchase Order procedures to
cover all private properties in the Masterplan area, where no previous approval had
been granted, provided that all reasonable attempts to contact owners and agree
voluntary acquisition were made by Sanctuary and its agents. It was noted that these
Compulsory Purchase Order processes would run in parallel with continued efforts to
acquire the properties on a voluntary basis and where an acquisition was successful,
the property would be removed from the list of those subject to the Compulsory
Purchase Order. 
DECIDED: 
(a) That the positive progress made in implementing the Regeneration Masterplan for
the West End area of Paisley, in partnership with Sanctuary Housing Limited, be
noted; 
(b) That the progress being made in acquiring properties within the Masterplan area,
including through Compulsory Purchase Order no. 1, be noted; and

Page 6

(c) That the use of Compulsory Purchase Order procedures be authorised where
voluntary acquisition could not be secured to ensure the acquisition of properties in
the area, as indicated and detailed within the Appendix. 
7 Review of Tenant Participation
There was submitted a report by the Director of Communities & Housing Services
relative to the outcome of consultation undertaken in connection with the Draft Tenant
Participation Strategy following the last meeting of this Policy Board. 
The report reminded members that following consideration of the Draft Tenant
Participation Strategy at the meeting of this Policy Board held on 16 August 2022 the
Director of Communities & Housing had been authorised to undertake consultation
and to submit a report in relation to the outcome of that consultation and the proposed
final Tenant Participation Strategy. The report indicated that tenant representatives
had played a central role in developing the Strategy and had contributed to the
proposed content at all stages of the process. Following the Policy Board meeting a
further digital consultation exercise had been undertaken, between 12 -30 September
2022, seeking comments from tenants and all tenants’ groups on the proposed
Strategy. It was noted that members of the Policy Board had also had opportunities to
comment on the Strategy. These additional consultation exercises had now ended
and the Renfrewshire Council Tenant Participation Strategy 2022/27, a copy of which
was attached as Appendix 1 of the report, was submitted for approval.  It was
highlighted that annual updates regarding the Strategy would be provided to Members
for consideration and review. 
DECIDED: 
(a) That the Renfrewshire Council Tenant Participation Strategy 2022/27, as set out in
Appendix 1, be approved; and 
(b) That the Director of Communities & Housing Services be authorised to progress
the Action Plan set out in the Strategy, in partnership with tenants and relevant
agencies, and provide an Annual Report on progress to the Policy Board. 
8 Annual Housing Performance Benchmarking Report 2021/22 and
Tenant Satisfaction Survey 2022
There was submitted a report by the Director of Communities & Housing Services
relative to the annual Housing Performance Benchmarking Report 2021/22, a copy of
which was appended to the report, and which had been submitted to the Scottish
Housing Regulator during May 2022. The report also provided further information in
relation to the Tenant Satisfaction Survey which would be used to inform the ongoing
improvement work of the Service. 
The report provided information and analysis on the Council’s performance during
2021/22 in relation to key Housing Charter indicators, such as tenant satisfaction,
housing quality and maintenance, customer and landlord relationship, estate
management, anti-social behaviour, neighbourhood nuisance, tenant disputes,
homelessness, rents and services charges. Comparative information together with
analysis was provided in respect of other local authorities and Registered Social

Page 7

Landlords (RSLs). 
A copy of the executive summary of the tenant satisfaction survey was attached as
Appendix 2 to the report. A summary of the headline results relating to customer &
landlord relationships; housing quality and maintenance; estate management, anti-
social behaviour, neighbourhood nuisance, tenant disputes; housing options and
access to housing; homelessness; and value in terms of rents and service charges
was provided.  It was noted that the outcome of the survey and performance and
benchmarking updates would be used to inform the programme of improvements and
commitments required to meet the needs of tenants 
DECIDED: 
(a) That the Council’s performance during 2021/22, in relation to key Housing Charter
indicators compared to other Social Landlords and the terms of Tenant Satisfaction
Survey, set out in Appendix 1 of the report, be noted; and 
(b) That the Director of Communities & Housing Services be authorised to use the
information set out in the benchmarking report, tenant satisfaction survey and other
performance related documents to continue the programme for ongoing improvement
in the delivery and operations of the Council’s housing function to ensure that the
quality of service to meet the needs of tenants was maintained and enhanced. 
9 Regulation of Social Housing - Assurance Statement 2022
There was submitted a report by the Director of Communities & Housing Services
relative to the Annual Assurance Statement 2022 which the Council required to
submit to the Scottish Housing Regulator in terms of the Scottish Housing Regulator’s
Framework for the Regulation of Social Housing in Scotland 
The report referred to the regular reports submitted to this Policy Board on housing
services performance and benchmarking which demonstrated continuing strong
performance across most areas of the housing service during 2021/22 and identified
areas for improvement. Reference was made to the continuing impact of the
Coronavirus pandemic on housing services and highlighted areas where Covid-19
continued to impact. Appendix 1 of the report detailed the Regulator’s Framework
requirements for all local authorities and Registered Social Landlords (RSLs) and
provided evidence to demonstrate Renfrewshire Council’s compliance. A copy of the
proposed Annual Assurance Statement 2022 for Renfrewshire Council was attached
as Appendix 2 of the report, for approval. 
DECIDED: 
(a) That the regulatory requirements and evidence of Renfrewshire Council’s
compliance, as detailed in Appendix 1 of the report, be noted; and 
(b) That the Renfrewshire Council Annual Assurance Statement 2022, attached as
Appendix 2 of the report, be approved for submission to the Scottish Housing
Regulator.

Page 8

10  Rapid Rehousing Transition Plan and Homelessness Update
There was submitted a report by the Director of Communities & Housing Services
relative to progress made in terms of implementation during 2021/22 of
Renfrewshire’s Rapid Rehousing Transition Plan 2019/24, together with a general
update on homelessness in Renfrewshire 
The report advised that the five-year Rapid Re-housing Transition Plan (RRTP)
demonstrated how each local authority and its partners would ensure that those who
were homeless were provided with accommodation as quickly as possible, minimise
the need to stay in temporary accommodation and have greater access to an up-
scaled use of the Housing First model and/or other support. Key partners including
local and national Housing Associations, Renfrewshire Health & Social Care
Partnership and a range of third sector organisations had been consulted on the
content of Renfrewshire’s RRTP. A review of the implementation of the RRTP during
2021/22 had been undertaken and submitted to the Scottish Government.  A copy of
the review findings, which highlighted evidence of innovative partnership working,
measures to prevent homelessness in Renfrewshire, together with a summary of the
challenges that impacted on maintaining progress in delivering key outputs, was
attached as Appendix 1 of the report. Confirmation had been received from the
Scottish Government that funding of £190,000 would be provided for 2022/23, year 4
of the Renfrewshire RRTP, which was in line with the funding awards in years 1 – 3.
Arrangements would be made to continue to update this Policy Board on progress
with the implementation of Renfrewshire’s RRTP.  
The report also detailed Renfrewshire’s response to homelessness and provided a
general update on homelessness and the support services provided in Renfrewshire. 
DECIDED: That the progress made to date, in terms of meeting the needs of those
who were homeless or threatened with homelessness, with the implementation of
Renfrewshire’s Rapid Housing Transition Plan, a copy of which was appended to the
report, be noted. 
11  Cost of Living (Tenant Protection) (Scotland) Bill 2022
There was submitted a report by the Director of Communities & Housing Services
relative to the emergency measures contained within the Cost of Living (Tenant
Protection) (Scotland) Bill 2022 
The report detailed the two main emergency measures contained within the Bill, the
first relating to the establishment of a rent cap until at least March 2023, which applied
to the majority of tenancies across the private and social rented sector. It was
highlighted that the rent cap had initially been set at 0% and was therefore in effect a
rent freeze. The second emergency measure was a temporary moratorium on
evictions. It was noted that the moratorium would prevent enforcement action for
individual evictions, for a maximum of six months, in the private and social rented
sector except in a number of limited circumstances. The report advised that the Bill
had been passed by the Scottish Parliament on 6 October 2022. 
DECIDED: That the report be noted.

Page 9

12  Communities and Housing Services -  Service Improvement Plan
2022/22 Mid-Year Monitoring Report
There was submitted a report by the Director of Communities & Housing Services
relative to the performance and achievements of Communities & Housing Services
during the period 1 April to 30 September 2022. 
The report stated that the Service Improvement Plan 2022/25 for Communities and
Housing Services, approved at the meeting of this Policy Board held on 7 June 2022,
sets out the priorities for the development of the service over a three-year period, the
actions which would ensure continuous improvement across the service and the
performance indicators which ensured the impacts could be measured. Since the
Service Improvement Plan had been developed, Council had approved a new five-
year Council Plan at its meeting held on 29 September 2022. Consequently, minor
changes had been made to the Service Improvement Plan to align it to the themes in
the new Council Plan and the refreshed Community Plan. 
The report provided details of the key achievements of the Service during the period;
an update on changes made to the action plan and scorecard to reflect the new
Council Plan themes; a progress update on implementing the action plan linked to the
2022/25 Service Improvement Plan; an assessment of performance in relation to the
service scorecard of core performance indicators; and an overview of priorities for the
service over the next six months.  The report also indicated that the Service had made
good progress in delivering positive outcomes for Renfrewshire and its residents. This
included through the actions within the Service Improvement Plan and additional
areas of priority/ focus which had subsequently arisen over the first six months of
2022/23, such as the increasing support and participation of the Council in dealing
with refugee and resettlement programmes and the cost of living crisis. 
DECIDED: 
(a) That the progress to date on delivering the actions contained within the
Communities & Housing Services Service Improvement Plan 2022/25 be noted; 
(b) That the current performance of the service, as measured by the scorecard
indicators, be noted; and 
(c) That otherwise the report be noted. 
13  Prohibition of Smoking Outside Hospital Buildings
There was submitted a report by the Director of Communities & Housing Services
relative to The Prohibition of Smoking Outside Hospital Buildings (Scotland)
Regulations 2022 and the proposed local enforcement approach to be adopted. 
The report advised that during 2017, the Scottish Government had informed of the
intention to introduce new legislation to address concerns about persons smoking
within the immediate environs of hospital buildings. The benefits, in terms of the public
health agenda, of introducing statutory no-smoking areas around hospital buildings
were detailed.  It was noted that progress on the introduction of the legislation had
been suspended due to the Covid-19 pandemic. The Prohibition of Smoking Outside

Page 10

Hospital Buildings (Scotland) Regulations 2022, effective from 5 September 2022,
introduced new offences for knowingly permitting smoking and for smoking within
fifteen metres of hospital buildings, with an additional offence for not displaying
signage at hospitals to make persons aware of the requirement.  Local authorities and
Police Scotland had enforcement powers to issue fixed penalty notices where persons
breached the requirements of the Regulations and to report offences to the Procurator
Fiscal. The report indicated that locally it was the intention that enforcement would be
intelligence-led and follow the 4E’s approach, engage, educate, encourage and
enforce, with a principle focus on Education and Encouragement. The report
highlighted that enforcement would only be actioned as a last resort. It was noted that
NHS Greater Glasgow & Clyde Health Board was working with the four local
authorities which had hospitals within the Board area to ensure consistency of
approach and to resolve potential issues with compliance in terms of the legal
obligations placed upon.  
DECIDED: That implementation of the new Regulations be noted and that it also be
noted that a further report providing an update on enforcement activity in respect of
the new legislation would be submitted to a future meeting of this Policy Board. 
14  The Introduction of the Environmental Protection (Single-use Plastic
Products) (Scotland) Regulations 2021
There was submitted a report by the Director of Communities & Housing Services
relative to the Environmental Protection (Single-use Plastic Products) (Scotland)
Regulations 2021. 
The Clerk advised that an additional recommendation required to be added to those
detailed within the report. The terms of the additional recommendation were “That the
Environmental Protection Act 1990 be added to undernote B which followed
paragraph 56 of the delegations to the Director of Communities & Housing Services in
the Council’s Scheme of Delegated Functions.”  
The report made reference to the perceived need to address littering and the ‘throw
away’ culture in the UK and create a shift towards a circular economy in Scotland.  In
this connection the Scottish Government had brought into force the Environmental
Protection (Single-use Plastic Products) (Scotland) Regulations 2021, which from 12
August 2022 banned the commercial manufacture and supply of single-use plastic
items in Scotland unless an exemption applied. A full list of the single-use plastic
items banned in terms of the Regulations was provided within the report together with
a summary of the exemptions applicable. It was noted that supply also included
businesses making donations or gifts of items. Furthermore, it was highlighted that an
exemption from the UK Internal Market Act had been granted to avoid conflicts. The
report also highlighted that the introduction of the legislation was not as a statutory
function and would lead to increased demand on resources and would not be funded
by Government at a time when demand on business regulation services was already
exceedingly high. 
DECIDED: 
(a) That the introduction of the Environmental Protection (Single-use Plastic Products)
(Scotland) Regulations 2022 be welcomed and noted; 
(b) That the support for businesses and enforcement approach to be implemented, as

Page 11

set out in section 3 of the report, be agreed; 
(c) That the inspection of premises be aligned to other planned interventions to
minimise additional resource demands; 
(d) That authority be delegated to the Director of Communities & Housing Services to
authorise officers under the Environmental Protection (Single-use Plastic Products)
(Scotland) Regulations 2021; and 
ND (e) That the Environmental Protection Act 1990 be added to undernote B which
followed paragraph 56 of the delegations to the Director of Communities & Housing
Services in the Council’s Scheme of Delegated Functions.” 
15  Year 1 Progress - Community Learning and Development Strategy
2021/24
There was submitted a report by the Director of Communities & Housing Services
relative to delivery, during 2021/22, of the Renfrewshire’s Community Learning and
Development (CLD) Strategy 2021/24. 
The report advised that in Scotland the actions and activities of CLD services were
underpinned by the shared values identified by the Community Learning and
Development Standards Council: It was highlighted that Renfrewshire’s Community
Learning and Development Strategy 2021/24 and Action Plan had been considered
and approved at the meeting of the former Communities, Housing and Planning Policy
Board held on 17 August 2021 and that the strategy had been developed in
partnership with a wide range of statutory, voluntary and community groups, including
individuals, to enable successful delivery of community learning development
activities aligned to Renfrewshire’s Community Plan Vision and priorities. The report
was the first annual update and detailed the significant progress achieved during
2021/22, the first year of the CLD Strategy, in terms of delivery of the agreed
outcomes and actions. The report provided a summary update on the progress
achieved during 2021/22, which was detailed more fully within the Appendix to the
report. It was noted that progress achieved during 2021/22 was structured across the
themes of Service Review; Service Development and Service Achievements; Digital
Inclusion; Universal Provision; Targeted Provision; and Community
Capacity/Connecting Communities. There had been a focus on working actively and
collaboratively with a wide range of partners towards the recovery of local
communities and building back services from the impact of the Covid-19 pandemic to
achieve better outcomes and opportunities for everyone in Renfrewshire. It was
highlighted that the report also formed part of the governance and monitoring
arrangements and referenced the significant contribution made by a wide range of
partners to deliver on the actions, priorities, and vision of the CLD Strategy 2021/24. 
The report intimated that a service review and restructure had been completed to
ensure that resources and capacity were in place to continue to support communities
and build their capacity.  In addition, individual, family and lifelong learning had been
developed to ensure that all residents could have the opportunity to grow and thrive
within their community. 
DECIDED: 
(a) That the progress achieved during 2021/22, as a result of the support and

Page 12

contribution of a wide range of partners, be noted; and 
(b) That it be agreed further updates on progress in terms of the Community Learning
and Development Strategy be provided on an annual basis. 
16  Summer of Fun 2022
There was submitted a report by the Director of Communities & Housing Services
relative to the multi-agency, universal and targeted work developed and delivered
across Renfrewshire throughout the summer holiday period as part of the 2022
Summer Holiday Provision initiative. 
The report made reference to the £10 million allocated to local authorities by CoSLA
in line with the Scottish Government’s commitment for targeted provision of
accessible activities, childcare and food for 5–14 year-old children from low-income
families during the 2022 school summer holiday period. It was highlighted that the
Scottish Government wanted a particular focus to be on 6 main targeted groups who
were especially vulnerable to falling into poverty: (i) lone parent families; (ii) ethnic
minority families; (iii) those with a disability; (iv) mothers under 25; (v) those with a
child under one year of age; and (vi) those with more than 3 children. Renfrewshire
Council had been allocated £292,415 of the funding, which had been used to deliver a
highly successful programme of activities for children, families and young people,
which encouraged them to access a wide range of activities and healthy food. Almost
1,000 individual children had benefitted from activities over the summer period. A
summary of the final detailed evaluation report, which had been submitted to the
Scottish Government, was attached as an appendix to the report. 
DECIDED: 
(a) That the ambitious and successful Summer of Fun programme, set out in section 3
of the report, developed and delivered during the summer of 2022 in Renfrewshire be
noted; and 
(b) That the summarised version of the comprehensive evaluation report, a copy of
which was appended to the report, submitted to the Scottish Government in
compliance with the submission deadline date, be noted. 
17  Community Justice update and annual return 2021/22
There was submitted a report by the Director of Children’s Services relative to the
Community Justice Renfrewshire Annual Report 2021/22, a copy of the template for
which was appended to the report. 
The report advised that the Renfrewshire Community Justice Outcomes Improvement
Plan (CJOIP) 2018/21, outlined how the Community Justice Renfrewshire Partnership
would reduce re-offending locally. The document also highlighted key local priorities,
which had been identified through needs assessment and interaction with
stakeholders, and national priorities which required to be reported against and were
contained within the National Strategy for Community Justice and the Outcomes,
Performance and Improvement Framework. 
The Community Justice Renfrewshire Annual Report, covering the period 1 April 2021

Page 13

to 31 March 2022, required to be published and submitted to Community Justice
Scotland by 30 September 2022. The template for the annual report had been
produced by Community Justice Scotland to assist local partnerships to capture a
range of data in a way that allowed local partners to highlight key aspects of
community justice activities, outcomes and improvements over the specified period
without it being onerous or time/resource demanding. It was highlighted that
maintaining and recovering operational services during the Covid-19 pandemic and
the continued inability to recruit to the Lead Officer Community Justice Position, had
resulted in delays The report also indicated that Renfrewshire’s CJOIP had been due
to be updated by April 2021, however in recognition of the impact of the Covid-19
pandemic on taking forward actions, it had been agreed by Community Justice
Scotland (CJS) that Plans due for submission in 2021 could continue until 31
December 2021. The Scottish Government (SG) and CJS had issued a joint
statement during May 2021 in relation to the review of the National Strategy for
Community Justice and Review of the Outcomes, Performance, and Improvement
Framework. This had been planned for March 2022 but had been published on 30
June 202. Given that local authorities required to review their CJOIPs after the
publication of these frameworks it had been agreed that it was pragmatic for local
authorities to delay publication. On that basis it was proposed that Renfrewshire
utilised this time to develop its CJOIP for 2023/26 
DECIDED: 
(a) That the Reporting Template for the Community Justice Renfrewshire Annual
Report 2021/22, a copy of which was appended to the report, be approved; 
(b) That it be noted that the Community Justice Renfrewshire Annual Report Template
2021/22 had been submitted to Community Justice Scotland in draft format and,
subject to approval and/or amendment by this Policy Board, the finalised Report
would be submitted and published; 
(c) That the Criminal Justice Services Manager be authorised to make minimal
changes to the report if required, prior to publication; and 
(d) That it be noted that Community Justice Renfrewshire was set to begin a strategic
needs and strengths assessment to develop the Renfrewshire Community Justice
Outcome Improvement Plan 2023/26, following the review of the National Strategy for
Community Justice and Outcomes, Performance and Improvement Framework. 
18  Disposal of Land to the Rear of 18 Blackstoun Avenue, Linwood
There was submitted a report by the Chief Executive relative to the proposed disposal
of land to the rear of 18 Blackstoun Avenue, Linwood. 
The report advised that the occupiers of 18 Blackstoun Avenue, Linwood had
expressed an interest in acquiring the Council’s title for land to the rear of 18
Blackstoun Avenue, Linwood, identified on the plan appended to the report, which
was currently allocated for use by the occupiers of 16 Blackstoun Avenue, Linwood.
The area of land, which was held on the Housing Revenue Account, extended to
101m2 and was an area of garden ground. The proposed acquisition would facilitate
additional garden ground for use by the owner of 18 Blackstoun Avenue, Linwood.
The occupiers of number 16 did not use the land as there was sufficient garden
ground located directly to the rear of their property. The Head of Economy &

Page 14

Development had confirmed that the area of land had no operational requirement and
he was not opposed to the land being declared surplus to the Council’s requirements.
Discussions had taken place with the occupiers of 16 Blackstoun Avenue, Linwood
and a purchase price agreed subject to the ground being declared surplus to the
Council’s requirements by this Policy Board. It was noted that the Head of Economy &
Development would utilise his delegated authority, in view of the value of the land,
should it be deemed surplus to requirements by the Policy Board. 
DECIDED: 
(a) That the area of land located to the rear of 18 Blackstoun Avenue, Linwood, as
shown on Plan E3166, a copy of which was appended to the report, be declared as
surplus to requirements, with a view to disposing to the adjacent owner; 
(b) That the sale thereof to the adjoining propertier of 18 Blackstoun Avenue, Linwood
on such terms and conditions as may be negotiated by the Head of Economy &
Development utilising delegated powers be authorised; 
(c) That the Head of Corporate Governance be authorised to conclude the sale
incorporating into the bargain such terms and conditions as may be deemed
necessary to protect the Council’s interest; and 
(d) That it be noted that the Chief Planning Officer would place an advert in the local
press, in terms of the Town and Country Planning (Scotland) Act 1959, for the
proposed sale of an area of open space. 
19  Disposal of Land to the Rear of 14 New Street Kilbarchan
There was submitted a report by the Chief Executive relative to the proposed disposal
of land to the rear of 14 New Street, Kilbarchan. 
The report advised that the owners of 14 New Street, Kilbarchan had expressed an
interest in acquiring the Council’s title for land to the rear of 14 New Street,
Kilbarchan, identified on the plan appended to the report and that the occupiers of the
adjoining properties on Steeple Street, Kilbarchan had confirmed that they did not
wish to acquire the site. The area of land, which was held on the Housing Revenue
Account, extended to 90m2 and was an area of open ground. The proposed
acquisition would facilitate off street parking and an electric charging point. It was
highlighted that the land sold would be subject to an obligation to pay a share of
maintenance and repair costs for the adjacent access lane, which is within Council
ownership. The Head of Economy & Development had confirmed that the area of land
had no operational requirement and he was not opposed to the land being declared
surplus to the Council’s requirements. Discussions had taken place with the owners of
14 New Street, Kilbarchan and a purchase price agreed subject to the ground being
declared surplus to the Council’s requirements by this Policy Board. It was noted that
the Head of Economy & Development would utilise his delegated authority, in view of
the value of the land, should it be deemed surplus to requirements by the Policy
Board. 
DECIDED: 
(a) That the area of land located to the rear of 14 New Street, Kilbarchan , as shown
on Plan E3187, a copy of which was appended to the report, be declared as surplus

Page 15

to requirements, with a view to disposing of to the adjacent owner; 
(b) That the sale thereof to the adjoining propertier of 14 New Street, Kilbarchan on
such terms and conditions as may be negotiated by the Head of Economy &
Development utilising delegated powers be authorised; 
(c) That the Head of Corporate Governance be authorised to conclude the sale
incorporating into the bargain such terms and conditions as may be deemed
necessary to protect the Council’s interest; and 
(d) That it be noted that the Chief Planning Officer would place an advert in the local
press, in terms of the Town and Country Planning (Scotland) Act 1959, for the
proposed sale of an area of open space.