___________________________________________________________________
To: Communities and Housing Policy Board
On: 25 October 2022
___________________________________________________________________
Report by: Director of Communities & Housing Services
___________________________________________________________________
Heading: Rapid Rehousing Transition Plan and Homelessness Update
___________________________________________________________________
1. Summary
1.1 An overview on the progress with the implementation of Renfrewshire’s Rapid
Rehousing Transition Plan (RRTP) was provided to the Policy Board in March
2022. RRTP’s aim to ensure that those who are homeless:
-  are provided with settled accommodation more quickly
-  spend less time in temporary accommodation
-  have greater access to an up-scaled use of the Housing First model, and /
or other support. 
This report provides a full review of the progress made in 2021/22 and reflects
on the impact of Renfrewshire’s RRTP since it was launched in 2019. 
1.2 This report also provides a further update on homelessness in Renfrewshire.   
___________________________________________________________________
2. Recommendations
2.1 It is recommended that the Policy Board 
(i) Note the progress made to date with meeting the needs of those who
are homeless or threatened with homelessness with the
implementation of Renfrewshire’s Rapid Rehousing Transition Plan,
detailed in Appendix 1 of this report

Page 2

3 Renfrewshire’s Rapid Rehousing Transition Plan – update 
3.1 Previous Policy Board reports have detailed the Scottish Government
requirement for all local authorities to consult on and produce a 5-year Rapid
Rehousing Transition Plan covering the period 2019 – 2024. 
3.2  These plans detail how local authorities plan to move to a situation where
those who are homeless:
- are provided with accommodation more quickly
- spend less time in temporary accommodation
- have greater access to an up-scaled use of the Housing First model, and /
or other support. 
3.3  Key partners such as local and national Housing Associations, Renfrewshire
Health & Social Care Partnership and a range of 3rd sector organisations were
fully consulted on the content of an RRTP for Renfrewshire, and the Scottish
Government has allocated funding from the ‘Ending Homelessness Together’
fund to support and assist local authorities in the implementation of their
RRTP’s. 
3.4  A review of progress to date and the challenges for Renfrewshire’s RRTP was
provided to the Policy Board in August 2021 and March 2022, and there
continues to be progress in implementing the plan. Funding from the Council
and annual allocations of funding from the Scottish Government have been
deployed for measures which are in line with the priorities within
Renfrewshire’s 5-year RRTP. 
3.5  A full review of the implementation of the RRTP in 2021/22 has now been
carried out and submitted to the Scottish Government and is attached as
Appendix 1 of this report. 
The review highlights the substantial evidence of innovative partnership
working, and of the implementation of several new measures to prevent
homelessness in Renfrewshire and positively meet the needs of those who
have nowhere to stay. This includes: 
 further upscaling of our Housing First model to support 65 individuals at
any one time via 3 different support providers, including a new ‘in-house’
Intensive Support service. This was an increase from 30 service users in
year 1 and 44 in year 2. 
 a very positive independent ‘annual check-up’ on our approach to Housing
First carried out by Homeless Network Scotland 
 we fully implemented our tenancy resettlement assistance initiatives using
existing resources and 3 temporary posts funded via RRTP funding, and
over 400 enhanced ‘Starter Packs’ were provided to those moving into new
tenancies 
 a further 6 temporary accommodation properties were ‘flipped’ from
temporary to settled accommodation for homeless applicants

Page 3

 we further developed and improved our Shared Living Initiative with Simon
Community Scotland to enable and promote ‘flat sharing’ by homeless
applicants. Eight new joint tenancies were established. 
 partnership with SAY Women developed further to provide support for
young woman (16 – 25years) who are survivors of child abuse and/or
survivors of other forms sexual violence and who are having
housing/homeless/tenancy related issues. We now fund a full-time post.  
 continued our inhouse ‘matching and resettlement team’ which was
established during the response to Covid-19, and enables homeless
applicants to better transition from temporary to settled accommodation 
 an annual stepped increase in the number of homeless lets from both the
Council and RSLs - a key element of our RRTP.  
 the satisfaction rate from service users with the temporary accommodation
provided increased from 94.7% in 2020/21 to 98.4%, and the tenancy
sustainment rate for homeless applicants living in settled Council tenancies
for more than 12 months, increased from 88.4% to 89.4% 
 The average length of time for the Council to conclude duty for those who
were homeless improved from 25.55 weeks to 22.25 weeks 
3.6  Our RRTP also highlights certain challenges that may impact on maintaining
progress with delivering the key outputs, such as the demand for social rented
accommodation from Ukraine Displaced Persons and other refugee
resettlement programmes.   
3.7 The Scottish Government have now confirmed that funding of £190,000 will
be provided for 2022/23 (year 4 of our RRTP), which is in line with the funding
awards in years 1 – 3, and the Policy Board will continue to be updated on
progress with the implementation of Renfrewshire’s RRTP. 
4 Homelessness update 
4.1 Implementation of the RRTP and the positive outcomes to date, and recovery
following COVID provides a springboard for tackling and preventing
homelessness in Renfrewshire. 
4.2 The total annual number of statutorily homeless households in Renfrewshire
has generally remained consistent in recent years and tends to be within the
850 – 900 band. The majority of homeless applicants continues to be single
person households (over 75%). Close attention will be paid to see any signs
that cost-of-living issues are impacting on homelessness nationally and
locally.

Page 4

Year  Total annual number of homeless applications in 
Renfrewshire 
2022/23  468 to end Sept 2022 
2021/22  909 
2020/21  834 
2019/20  874 
2018/19  849 
2017/18  860 
2016/17  777 
2015/16  843 
2014/15  838 
4.3 The Scottish Government has now scheduled the removal of the ‘local
connection’ criteria for homeless applicants from December 2022. It is anticipated
that this may result in some local authorities – particularly larger urban Councils -
experiencing an increase in the number of people presenting as homeless, and
this may be a factor which could contribute to an increase in homeless
applications in Renfrewshire. 
Lets to homeless 
4.4 Whilst there was an unavoidable reduction in the number of social rented
houses let during COVID and in the recovery period, there has since been a
continued strong focus in Renfrewshire on matching Council / RSL properties
to those who are homeless or in greater housing need. 
4.5 The increase in social rented lets in 2021/22 to those who were statutorily
homeless was in line with a key aim of the Rapid Rehousing Transition Plan
(RRTP) for Renfrewshire. The on-going demand for the limited number of
available 1 bedroom properties as well as the need to meet the needs of
individuals affected by resettlement and asylum programmes will present
challenges to ensure that the supply of properties continues to increase into
2022/23 and beyond. 
4.6 The Policy Board will continue to be provided with regular updates on
homelessness, homeless prevention measures and the implementation of
Renfrewshire’s RRTP over the remaining 18 months that the Plan has to run. 
___________________________________________________________________

Page 5

Implications of the Report 
1. Financial – funding from the Scottish Government will continue to be fully
used to support the transition to rapid rehousing 
2. HR & Organisational Development – any posts to support the
implementation of RRTP initiatives have been appointed in accordance with
current HR procedures and funded from Scottish Government allocations. 
3. Community/Council Planning – 
 Our Renfrewshire is fair - those who are homeless will be provided with
settled housing options more quickly.
 Building strong, safe and resilient communities – meeting the needs of
those who are homeless and providing access to settled housing helps
to support communities.
 Tackling inequality, ensuring opportunities for all – those who are in
housing need will be provided with settled housing options more quickly.
 Working together to improve outcomes – RRTP’s require local authorities
and partners to work together to improve outcomes for those in housing
need. 
4. Legal – none 
5. Property/Assets – none 
6. Information Technology - none 
7. Equality & Human Rights
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative impacts on
equality groups or potential for infringement of individuals’ human rights have
been identified arising from the recommendations contained in the report because
it is for noting only. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored, and
the results of the assessment will be published on the Council’s website. 
8. Health & Safety - none 
9. Procurement - none 
10. Risk – none. 
11. Privacy Impact - none 
12. COSLA Policy Position – not applicable 
13. Climate Risk – none
_________________________________________________________

Page 6

List of Background Papers 
a)  Background paper 1 ‘ Homelessness Update’ Communities, Housing &
Planning Policy Board on 15 March 2022 
b) Background paper 2 ‘Tenant Hardship Grant Fund’, Communities, Housing &
Planning Policy Board on 26 October 2021 
c) Background paper 3 ‘Rapid Rehousing Transition Plan and Homelessness
Update’ Communities, Housing & Planning Policy Board on 17 August, 2021 
d) Background Paper 4 ‘Rapid Rehousing Transition Plan – funding update’
Communities, Housing & Planning Policy Board on 19 January 2021. 
e) Background Paper 4 ‘RRTP for Renfrewshire update’ Communities, Housing &
Planning Policy Board on 20 August 2019. 
f)  Background Paper 5 ‘RRTP for Renfrewshire’ Communities, Housing &
Planning Services Policy Board on 30 October 2018. 
The foregoing background papers will be retained within Communities & Housing
Services for inspection by the public for the prescribed period of four years from the
date of the meeting. The contact officer within the service is Tom Irvine,
Tom.irvine@renfrewshire.gov.uk.
___________________________________________________________________
Author Tom Irvine - Tom.irvine@renfrewshire.gov.uk

Page 7

1 
	
	
Rapid Re-housing
Transition Plan for
Renfrewshire 2019-2024 
REVIEW
2021/22

Page 8

2 
1 Introduction         Page 3 
2 Summary of Year 3 progress – 2021/22    Page 4 
3 How our RRTP funding was used in Year 3 - 2021/22  Page 5 
4 Nature and scale of homelessness      Page 6 
5 Housing First initiatives       Page 7 
6 Other funded RRTP initiatives      Page 8 
6.1 Tenancy Resettlement 
6.2 Starter Packs 
6.3 ‘Flipping’ Tenancies 
6.4 Shared Living Initiative 
6.5 SAY Women Project 
6.6 RRTP Co-ordinator and Steering Group 
7 Let to homeless applicants      Page 12 
8 Temporary accommodation      Page 15 
9 Year 4 proposals 2022/23       Page 19 
10 Summary and conclusions      Page 20 
11 Appendix 1         Page 21 
12 Contact us         Page 23   
Contents

Page 9

3 
The Homelessness & Rough Sleeping Action Group (HARSAG) was established by
the Scottish Government in October 2017.   
One of the key recommendations made by HARSAG, which was accepted by the
Scottish Government, was that each local authority should, in consultation with
partners, develop and cost a 5-year Rapid Re-housing Transition Plan (RRTP). 
The guidance on the development of RRTP’s highlighted that where homelessness
cannot be prevented, rapid re-housing means:
 a settled mainstream housing outcome, with support, as quickly as possible,
 time spent in any form of temporary accommodation is reduced to a minimum,  
 when temporary accommodation is needed, the optimum type is mainstream,
furnished and within a community. 
The 5-year RRTP for Renfrewshire was produced in 2019 following extensive
consultation with our partners, including service users and those with lived
experience of homelessness. 
This paper reviews the progress made in the first 3 years of the implementation of
Renfrewshire’s RRTP. 
A summary and list of key conclusions are provided in Section 11, page 20. 
This Review should be read in conjunction with our ‘Rapid Rehousing
Transition Plan 2019 – 2024’, the associated costed action plan and the RRTP
Review 2021.   
1    Introduction

Page 10

4 
2    Summary of year 3 progress – 2021/22 
Please refer to Appendix 1 for summary of progress made in years 1 and 2 
During year 3:  
 we further upscaled our Housing First model to support 65 individuals at any
one time via 3 different support providers, including a new ‘in-house’ Intensive
Support service. 
This was an increase from 30 service users in year 1 and 44 in year 2. 
 a very positive ‘annual check-up’ on our approach to Housing First was
carried out by Homeless Network Scotland 
 we fully implemented our tenancy resettlement assistance initiatives using
existing resources and 3 temporary posts funded via RRTP funding 
 over 400 enhanced ‘Starter Packs’ were provided to those moving into new
tenancies 
 a further 6 temporary accommodation properties were ‘flipped’ from temporary
to settled accommodation for homeless applicants 
 we further developed and improved our Shared Living Initiative with Simon
Community Scotland to enable and promote shared living within
Renfrewshire, creating 8 new shared tenancies 
 partnership with SAY Women developed further to provide time limited
support for young woman (16 – 25years) who are survivors of child abuse
and/or survivors of other forms sexual violence and who are having
housing/homeless/tenancy related issues. We now fund a full-time post.  
 continued our inhouse ‘matching and resettlement team’ which was
established during the response to Covid-19, and enables homeless
applicants to better transition from temporary to settled accommodation 
 we delivered an annual stepped increase in the number of homeless lets from
both the Council and RSLs, a key element of our RRTP.  
 the satisfaction rate from service users with the temporary accommodation
provided increased from 94.7% in 2020/21 to 98.4% 
 the tenancy sustainment rate for homeless applicants living in settled Council
tenancies for more than 12 months, increased from 88.4% to 89.4% 
 The average length of time to conclude duty improved from 25.55 weeks to
22.25 weeks

Page 11

5 
RRTP funding from Scottish Government - YEAR 3 - 2021/22
Action
Plan Ref * Rapid Rehousing Proposal Annual Cost (£)
1,2,7 Upscaling of Housing First programme  £84,000
4 Tenancy resettlement £80,500
1, 3 Provision of enhanced starter packs £20,000
3 Temporary accommodation – ‘flip’ properties
from temp accommodation £10,000
all RRTP Coordinator Post  £47,000
6 Shared Living Initiative £26,000
8 Say Women project £8,000
TOTAL SPEND YEAR 3  £275,500 
3   How our RRTP Funding was used in Year 3     
2021/22

Page 12

6 
Our previous RRTPs provided substantial analysis on the nature, context, and scale
of homelessness in Renfrewshire in recent years. 
In 2021/22, we dealt with 2256 housing advice cases, which resulted in 909
homeless applications. 
This was an increase of almost 10% in homeless applications compared to the
previous year and is the highest number since 2013/14. 
As before, the largest demand is still from single applicant households, which
continue to represent nearly 80% of all applications. 
The average length of time to conclude duty improved from 25.55 weeks in 2020/21
to 22.25 weeks, largely as we were able to move households from temporary
accommodation into settled accommodation more quickly than before due to our in-
house ‘matching and resettlement team. 
Repeat homelessness figure has reduced to under 8%, from 9.8% in 2019/20. 
Those who state they have slept rough at some point in the 3 months before making
a homeless application has reduced to 4.4% of all applications from 5.3% in 2020/21
(it was 11.8% in 2019/20). 
There are challenges emerging in relation to the impact of the cost-of-living crisis on
homelessness, as well as being able to achieve a stepped increase in social rented
lets to homeless applicants, which may be impacted by factors such as the
regeneration programme for Renfrewshire and the demand for social rented
accommodation as part of Scotland’s Homes for Ukraine programme, see page 14. 
4    Nature and Scale of Homelessness in 2021/22

Page 13

7 
5    Housing First initiatives   
Renfrewshire has developed a strong track record for the deployment of Housing
First initiatives, after becoming the first Scottish local authority to fund a Housing
First initiative back in 2013/14, in partnership with Turning Point Scotland. 
Here is a summary of the current provision :
WRAP (Working to Reconnect and Achieve Potential) 
Established in December 2019 in partnership with Blue Triangle Housing
Association, WRAP is a short-term, flexible, wraparound housing support service for
people who are homeless and wanting to engage with support staff in a person-
centred approach to resettle into the community, sustain their tenancy, and achieve
their own outcomes.   
WRAP provides support along the lines of a Housing First approach, via 3 workers
employed by BTHA. 
WRAP has been funded jointly from the Council’s Housing Support budget, (£26k
pa) and RRTP funding (£84k pa). 
An analysis our WRAP project was included in last years RRTP review.  
In April 2022, a total of 35 service users were being supported via WRAP and
benefitting from the Housing First approach that is applied.   
There are clear signs that WRAP is having a positive impact on tenancy sustainment
levels. 
As a result of the scale of success in the first two years of operation, WRAP is being
rolled forward to 2022/23.   
Housing First – Turning Point Scotland 
A total of 16 service users were being supported in April 2022 via our on-going
project operated in partnership with Turning Point Scotland and benefitting from the
Housing First approach that is applied.   
Intensive Support service 
Building on our successful track record of deploying a housing first approach via
partnerships with Blue Triangle Housing Association (WRAP) and Turning Point
Scotland, Renfrewshire Council have now established and funded our ‘Intensive
Support’ service from within our Housing Support Team using the lessons we have
learned. A full review of our Intensive Support service will be included in next year’s
RRTP review. 
At the end of 2021/22 14 service users were already accessing this new initiative.

Page 14

8 
6.1 Tenancy resettlement 
Our revised approach to tenancy resettlement was developed following customer
consultation and is a proactive and practical approach to help those who are
homeless to establish and sustain their settled tenancy. 
It has been further developed in response to the relatively low tenancy sustainment
rate for Council tenancies by homeless applicants, and the number of tenancies that
were subsequently abandoned. 
An enhancement of tenancy resettlement assistance is seen as a key principle in
meeting the overall aims of Renfrewshire’s RRTP, and it became a particularly
important during our response to COVID-19. 
In 2021/22, 527 service users were assisted to settle in their new homes using
existing resources from within the Council’s Homeless & Housing Support Services
teams, as well as 3 new temporary posts funded via Scottish Government RRTP
funding allocation. 
To date, a total of 817 service users have been assisted to settle into their new
homes via Homeless & Housing Support Services and our Resettlement service over 
2020/21 and 2021/22. 
This has built on the measures already in place which had already delivered
substantial improvement in tenancy sustainment – those who were homeless and
sustained a Council tenancy for more than 12 months increased to 89.4% in
2020/21* from 88.4% the previous year. This figure was at 72.1% in 2015/16. 
* this is the most recent year that tenancy sustainment figures are available for 
We continue to: 
 Assist households with the practical challenges of setting up a home
 Help services users to better understand their rights and responsibilities as a
tenant
 Set up utilities in new tenancies and clear any debts on the meters and liaise
directly with utility companies
 Coordinate the delivery of Community Care grant items and ‘starter pack’
 Ensure all welfare benefits are in place and no rent arrears are accruing at the
start of the tenancy
 Maintain regular access to advice and assistance for the service user
 Carry out tenancy ‘health’ checks on a quarterly basis for 1 year to help
identify early warning signs
 Liaise with other agencies when concerns are highlighted
6    Other Funded RRTP Projects

Page 15

9 
 Assist service users to engage in wider community support
 Liaise directly with local Housing Officers to support a positive working
relationship and take a joint approach to deal with any emerging issues. 
Impact of Tenancy Resettlement Assistance 
The positive impacts for service users and housing providers since the introduction
and enhancement of the tenancy resettlement measures are:
 enabled customers to move from temporary accommodation into settled
accommodation during lockdown 
 prevented customers having to stay in bed and breakfast accommodation
 staff ‘took up the strain’ of dealing with utility companies
 reduction in new tenant rent arrears 
 improved communication with local housing officers and other partner
agencies
 improved engagement with wider community-based support services
 property in move-in condition for the service user
 practical assistance available to customers
 early warning signs of possible un-sustained tenancy 
6.2 Starter packs 
In 2018/19, we conducted a survey of homeless service users on what items they
thought were essential to help them maintain and sustain their tenancy. 
In years 1, 2 and 3, we have annually provided over 400 enhanced Starter Packs
based around customer feedback. The packs now include a double rather than a
single bed, a microwave, kettle, toaster, cutlery, and plates. 
We also give service users the option of having their new home ‘powered up’ prior to
occupation. This ‘credit’ allows individuals to be able to use either gas or electricity
immediately and further increases the chances of the tenant smoothly moving into
their settled housing, and go on to sustain the tenancy (dealing with utility companies
was regularly featuring as a ‘stresser’ by those who had moved to new tenancies).   
6.3 ‘Flipping’ Tenancies 
We have tended to ‘flip’ furnished properties on occasion from temporary
accommodation to secure tenancies, when the property has already been used for
over 7 years as furnished temporary accommodation for homeless applicants. 
In the first 3 years of our RRTP, 28 temporary accommodation properties were
‘flipped’ from temporary to secure tenancies – 6 in year 1, 16 in year 2 and 6 in year
3, and we intend to continue this, where feasible, in partnership with housing
providers.

Page 16

10 
‘Flipping’ is best applied when it forms part of a planned reduction in a stock of
temporary accommodation – see discussion on the reduction of temporary
accommodation in Section 7. 
6.4 Shared Living Initiative 
The Shared Living Initiative is a flat sharing initiative delivered in partnership with
Simon Community Scotland which is designed to allow service users to self-select
and / or be supported to ‘match’ with each other. 
This empowers applicants to improve their housing options and provides new
opportunities to find settled accommodation. 
It has been designed to mitigate concerns from a landlord perspective, as well as an
opportunity for individual homeless people to have the option of flat-sharing and is a
positive response to the mismatch between the high proportion of single person
homeless households and low availability of one bedroom accommodation. 
‘Shared Living’ has been made more challenging over recent years due to staff
turnover within Simon Community and COVID restrictions, however we are hopeful
that this will be a viable option for some of our service users going forward,
particularly those who struggle with loneliness and isolation. 
Strong links have been established with Renfrewshire’s ‘Invest’ programme which
will be a valuable resource to assist service users into training and employment. 
In 2021/22, 8 shared tenancies were created and since it launched, 32 service users
have been supported resulting in 14 Shared Living tenancies being created with a
further 4 awaiting offers that are expected to shortly become shared tenancies.  
“Shared living for me has been a dream! I've got help splitting our bills, managing our
costs and always someone to rely on at home! This opportunity has allowed me to
feel so comfortable and secure within my environment I cannot thank the team
enough" 
Comment from Shared Living service user. June 2022 
6.5 SAY Women Project 
Say Women offers emotional support for young women aged 16 to 25 who are
survivors of sexual abuse, rape, or sexual assault and who are homeless, or
threatened with homelessness. 
Through our RRTP, we initially funded a 0.5 post via Say Women, however more
recently this has increased to a full-time position due to the demands on the project
to enhance the support to service users and provide key staff in homeless / housing
services with increased capacity through Say Women’s specialised training and
consultation.

Page 17

11 
With continued engagement, Say Women aim to prevent repeated cycles of
homelessness and increasing tenancy sustainment for the young woman they work
with, and a detailed plan has been established on how the service can develop. 
To date they have assisted over 20 young women. 
6.6 RRTP Coordinator 
Our RRTP Coordinator liaises with senior officers within the Council, partner
organisations as well as the Scottish Government in order to ensure that all required
agreements, services and ongoing monitoring arrangements are in place to oversee
the successful delivery of Renfrewshire’s Rapid Rehousing Transition Plan, within
budget. 
The postholder will be moving to a new post in early 2022/23, and it is proposed to
terminate this position, and incorporate the role and the lessons learned within the
Council’s Homeless Services team. 
Rapid Rehousing Steering Group 
We established a Rapid Rehousing Steering Group of key stakeholders chaired by
the Council’s Head of Housing Services, with the aim of assisting in the delivery and
implementation of the aims and objectives of Renfrewshire’s Rapid Rehousing
Transition Plan. 
The Steering Group regularly reviews an agreed ‘dashboard’ of all key performance
areas to track the impact of Renfrewshire’s Plan. 
Rapid Rehousing Steering Group meetings will continue to be held over the
remaining 2 years of our RRTP. 
Joint approach 
We have continued with one-to-one meetings with the senior housing managers of
Renfrewshire Council and the Registered Social Landlords to discuss key aspects of
the RRTP and highlight/agree where their contribution could assist in the delivery of
the RRTP. 
This has involved producing and sharing individual, tailored reports for each
stakeholder, and was a key factor in driving the stepped increase in lets to homeless
applicants over the first 3 years of our RRTP.

Page 18

12 
7    Lets to homeless applicants 
Introduction 
In the 5-year RRTP for Renfrewshire, it was highlighted that a stepped increase in
the number and proportion of social rented lets to those who were statutorily
homeless would be a key factor in meeting the objective of providing a settled
mainstream housing outcome, with support, as quickly as possible. 
Table 1 below compares the number of Council lets to homeless applicants in
2019/20, 2021/22 and 2020/21. 
Table 1 
Source – Renfrewshire Council house allocation records 
In 2019/20 the Council made 352 lets to homeless applicants. 
In 2020/21 they made 245 lets and in 2021/22 the figure improved to 368 – an
increase of 16 from 2019/20 and an increase of 123 lets from 2020/21. 
Table 2 overpage compares the number of RSL lets to homeless applicants in
2019/20, 2020/21 and 2021/22. 
0
50
100
150
200
250
300
350
400
Paisley North Paisley South Renfrew Johnstone Combined
Number of Council lets to homeless 
2019/20 ‐ 2021/22
19/20 20/21 21/22

Page 19

13 
Table 2 
Source – Records provided by RSLs 
In 2019/20, RSLs made 138 lets to homeless applicants. 
In 2020/21 they were 164 lets to homeless applicants and in 2021/22 the figure was
172 - an increase of 34 lets from 2019/20 and an increase of 8 lets from 2020/21. 
The combined total number of Council and RSL lets for 2019/20, 2020/21 and
2021/22 has been 490, 409 and 540 respectively. 
Our forecast via the RRTP Data and Analysis Template completed in 2019, was that
455, 600 and 600 social rented lets in Years 1, 2 and 3 respectively would be
required in order to deliver a substantial and meaningful improvement. 
We also modelled in our original RRTP 2019 – 2024, how the relationship between a
stepped increase in the number of lets could impact on a reduction in the length
of time to conclude duty. 
In the model, reproduced on the next page, we showed the impact of a gradual
increase in the annual number of lets (approximately 10% each year) spread over
the 5 years of the RRTP. 
0
20
40
60
80
100
120
140
160
180
200
WHA PHA Linstone Sanctuary FPHA Loretto Link Bridgewater Combined
Number of RSL lets to homeless 
2019/20 ‐ 2021/22
19/20 20/21 21/22

Page 20

14 
Table 3 
Source : Renfrewshire’s RRTP 2019 – 2024 
The impact on the average length of time a household would be homeless is that it
reduces gradually from 24 weeks (which was already considerably below the
Scottish average) to 16.6 weeks by 2023/24. 
A further stepped increase in the number of social rented lets to homeless applicants
in 2022/23 is required. 
Impact of Renfrewshire Council’s Regeneration Programme in
years 4 – 5 
A substantial Regeneration Programme covering a large proportion of Renfrewshire
Council’s housing stock commenced in 2022/23. 
This will include some demolition of stock and may have an impact on the supply of
accommodation due to the need to provide properties for those who are moved /
decanted. 
Close liaison with the Regeneration team will help minimise the impact this may have
on the implementation of this RRTP in terms of available Council lets.   
Impact of resettlement of Ukraine Displaced People 
There are 377 UDPs staying in hotel accommodation across Renfrewshire by July
2022. This will place a new additional demand for social rented accommodation.
There may also be an impact on the demand for furnished temporary
accommodation and to record homeless applications for UDPs who do not have
24.0 24.0
21.6
19.6
18.0
16.6 16.6
0.0
5.0
10.0
15.0
20.0
25.0
30.0
0
100
200
300
400
500
600
700
2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Impact of annual additional lets phased over 5 years
TOTAL of Council/RSL/Private Lets Length of time taken to complete duty (weeks)

Page 21

15 
suitable accommodation at the time when their sponsor arrangement ends. 
8    Temporary accommodation 
It was made clear in our RRTP how the fluctuating nature of the demand for
temporary accommodation can present challenges. 
It requires significant effort, planning and resourcing to meet the high standards we
place on delivering on the duty to provide temporary accommodation for those who
are homeless, in terms of the location, type, and quality of the properties, and how
they are managed. 
We have never used hostels in Renfrewshire, and all our temporary accommodation
properties already met the vision set out within the RRTP Guidance, which was: 
‘the optimum type of temporary accommodation is mainstream, furnished
and within a community.’
At the time of producing our original RRTP, we had a total stock of 233 temporary
accommodation properties, and B&B had not been used for a number of years. 
Table 8 Comparison of temporary accommodation type / number – 2019 – 2022
(snapshot figs)
Accommodation
Type Location Accommodation
provider
No. of
properties
2019
No. of
properties
June 2020
No. of
properties
April 2021
No. of
properties
April 2022
Local Authority
owned furnished
flats
across R/shire Renfrewshire
Council 116 136 124 129
Households
placed in B&B Paisley B&B proprietors 0 25
placements 0 0
RSL owned
furnished flats across R/shire Various RSLs 24 30 31 31
*Local Authority
owned
supported
accommodation 
1 location in
Paisley
Renfrewshire
Council 16 16 16
16

Page 22

16 
*  support is commissioned from specialist provider
** this supported accommodation no longer provided. 
As can be seen in the table above, the current stock is 247 properties. 
This overall increase of 4 properties from 2021 is due to the sustained high demand
for temporary accommodation resulting from the increase in homeless applications
as highlighted in part 4 (Nature and Scale of Homelessness). Whilst the number of
lets increased, this was matched by an increase in homeless applications. 
Temporary Accommodation – Review of 5 Year Vision / Projections 
At the time of submitting our RRTP, we anticipated that the overall capacity for
temporary accommodation could reduce from an overall stock of 233 units to 177
units by year 5 - and this would be achieved by a combination of: 
 A phased increase in the number of lets to homeless applicants 
 The introduction / enhancement of the range of support improvements and
innovations detailed in the RRTP action plan 
Comments on our view on the need for the each of the temporary accommodation
property types are provided below : 
Local authority and RSL owned furnished flats 
In our 5-year RRTP, we set a target of reducing the number of properties to 121. 
The number increased during COVID recovery, and currently stands at 160. 
All properties will remain at our existing high standard, continue to be fully furnished
and spread throughout communities amongst mainstream social rented housing, and
*RSL owned
supported
accommodation 
Paisley and
Renfrew
Williamsburgh HA
Sanctuary HA
Loretto HA **
Paisley HA
42 37 37  37
Local Authority
owned staffed
accommodation
2 locations in
Paisley
Renfrewshire
Council 33 33 33 32
Private sector
leased –
furnished
Paisley Private landlords 2 2 2 2
TOTAL 233 279 243 247

Page 23

17 
now does not feel like the appropriate time to reduce the number of properties (see
also ‘staffed accommodation’ comments, on next page).   
Bed & Breakfast 
We ceased using B&B as a form of temporary accommodation for a number of years
however, in line with many other local authorities, the COVID-19 pandemic and
recovery period regrettably meant we were left with no option but to use this form of
temporary accommodation for a period. 
We have however once again ceased our reliance on B&B and remain committed to
the position that it is not a suitable form of temporary accommodation and with the
anticipated increase in lets over the coming years from housing providers and a joint
effort to enhance services that prevent homelessness via this RRTP, we have
returned to the position that B&B is no longer used from Year 3 onwards. 
Supported Accommodation 
This has already reduced from 58 properties to 53. 
We estimated that this could reduce to 40 properties by 2024, and the ‘flow’ of
applicants requiring this accommodation by year 5 could drop from 191 in 2017/18 to
133. 
This was however based on a costed proposal to upscale our capacity for Housing
First from 20 to around 65 - 80 individuals using RRTP funding. To date, the RRTP
funding has not been sufficient to allow such an increase. 
We are currently re-assessing what the need for supported accommodation may be
by year 5. 
Staffed Accommodation 
In our original RRTP, we envisaged a reduction from 32 to 24 properties, but now
aim to reduce 16 properties 
This will be delivered by a planned closure of one of our existing staffed
accommodation units during 2022/23. 
An increase in the number/proportion of lets to homeless applicants, and increase in
the capacity of housing first initiatives, as well as the sustained enhancement of our
resettlement service will reduce the number of repeat homeless cases, that often rely
on this direct access staffed accommodation. 
Private sector leasing

Page 24

18 
We intend to cease using the 2 properties during 2022/23 
Satisfaction with temporary accommodation 
We continually seek the views of those who are placed in all forms of temporary
accommodation. 
In 2021/22, the proportion of homeless applicants satisfied with their temporary
accommodation increased to 98.4% from 94.7% the previous year. The figure was
74.5% in 2015/16.

Page 25

19 
9    Year 4 proposals – 2022/23 
The Scottish Government funding allocation for year 4 has recently been confirmed
as £190,000, and our unavoidable ‘carry forward’ from Year 3 is £148,850. 
We anticipate we will be able to fully fund the initiatives set out in the table below: 
Table 9
YEAR 4 - 2022/23
Action
Plan Ref * Rapid Rehousing Proposal Annual Cost (£)
1,2,7 Housing First programme £124,000 (1)
4 Tenancy resettlement Service £120,000 (2)
1,3 Provision of enhanced starter packs £25,000 (3)
3 Use of temporary accommodation – ‘flip’
properties from temp accommodation £15,000
6 Shared Living Initiative £32,000
8 Say Women initiative £37,000
TOTAL ESTIMATED COST YEAR 4  £353,000 
* Reference numbers are taken from original RRTP action plan submitted in 2019
(1) The total annual cost of Housing First will be £250,000. The Council will contribute over
£100,000 – plus an in-house Intensive Support service
(2) This will fund an upscaling of the in-house provision of a number of posts already deployed
within the Council and RSLs 
(3) This topped-up a budget of £50,000 already used for the provision of starter packs

Page 26

20 
11    Summary and conclusions 
1 There has been significant progress in the implementation of Renfrewshire’s 5-
year RRTP. 
2 Funding from the Council and annual allocations of funding from the Scottish
Government have been deployed for measures which are in line with the
priorities within Renfrewshire’s 5-year RRTP. 
3 The funding from the Scottish Government has not been sufficient to allow
Renfrewshire’s costed RRTP to be fully implemented. 
4 There is however substantial evidence of innovative partnership working, and a
range of new measures in place to prevent homelessness and meet the needs of
those who have nowhere to stay. 
5 The use of a Housing First approach has been upscaled from 18 service users at
any one time at the start of our RRTP, to 65 at the end of year 3 using both
RRTP and Council funding. 
6 A stepped increase in the number of social rented lets to homeless applicants
was achieved in 2021/22 - this needs to continue in years 4 and 5 of our RRTP,
though there will be pressures. 
7 The collective effort to resettle homeless applicants from temporary
accommodation to settled tenancies during COVID-19 restrictions was
successful, and many of the lessons learned continue to be deployed. 
8 Tenancy sustainment figures show an increase in the proportion of homeless
applicants who go on to sustain a Council tenancy for at least 12 months to
89.4% in 2020/21 from 88.4% the previous year. This figure was 72.1% in
2015/16 
9 Repeat homelessness has reduced to under 8%, from 9.8% in 2019/20. 
10. Applications from those who state they had slept rough at some point in the 3
months preceding application has reduced to 4.4% of all applications from 5.3%
in 2020/21, and 11.8% in 2019/20. 
11 Temporary accommodation is still being provided in the form of furnished
mainstream flats in the community – the optimum type according to the Scottish
Government RRTP Guidance. The recorded satisfaction level has increased to
98.4% in 2021/22 from 94.7% in 2020/21.

Page 27

21 
12    Appendix 1 
Summary of year 1 progress – 2019/20: 
 we upscaled our Housing First model - up to 30 individuals being supported at
any one time from the previous total of 18 
 we recruited 3 x Resettlement Officers on a temporary basis to expand and
develop the assistance provided to those moving from temporary
accommodation 
 enhanced ‘Starter Packs’ were launched, based around customer feedback 
 6 of our temporary accommodation properties were ‘flipped’ from temporary
accommodation to being settled tenancies for homeless applicants 
 we developed a unique Shared Living Initiative mobile phone App, and
worked with Simon Community Scotland to roll this out to enable and promote
shared living within Renfrewshire 
 we appointed a RRTP Co-ordinator to ensure that all required agreements,
initiatives, and ongoing monitoring arrangements were in place to oversee the
successful delivery of Renfrewshire’s Rapid Rehousing Transition Plan within
budget 
 we established a RRTP Steering Group with key stakeholders, and chaired by
Head of Housing Services, to support the delivery and implementation of the
aims and objectives of Renfrewshire’s RRTP 
 we established close working relationships with senior housing managers
from Renfrewshire Council and Registered Social Landlords to regularly focus
on and review key aspects of our RRTP and jointly agree their contribution in
the delivery of the RRTP objectives 
Summary of year 2 progress – 2020/21: 
 we further upscaled our Housing First model to support 44 individuals via 2
different support providers, from 30 being supported in Year 1 
 we fully implemented our tenancy resettlement assistance initiatives using
existing resources and 3 new temporary posts funded via RRTP funding 
 239 enhanced ‘Starter Packs’ were provided 
 a further 16 temporary accommodation properties were ‘flipped’ from
temporary to settled accommodation for homeless applicants

Page 28

22 
 we fully implemented our Shared Living Initiative with Simon Community
Scotland to enable and promote shared living within Renfrewshire 
 we funded 0.5 post via Say Women to provide emotional support for young
women aged 16 to 25 who are survivors of sexual abuse, rape, or sexual
assault 
 we established an inhouse ‘matching and resettlement team’ to enable
homeless applicants to better transition from temporary to settled
accommodation during the Covid-19/ Lockdown restrictions 
 all homeless services and housing support frontline staff were deemed
‘essential workers’, and risk assessments and provision of PPE ensured these
workers provided assistance and support throughout the COVID19 response.
All these officers were also offered COVID19 vaccinations 
 we continued with one-to-one meetings with the housing managers of
Renfrewshire Council and the Registered Social Landlords to discuss key
aspects of the RRTP and highlight where their contribution can support and
assist in the delivery of the RRTP – especially during COVID19 crisis and
recovery 
 there was an increase in the number and proportion of RSL lets to homeless
applicants  
 number of Council tenancies let to homeless applicants which were
abandoned within a year reduced to 14, from 69 in 2019/20. 
 the satisfaction rate from service users with the temporary accommodation
provided increased to 94.7%, a record level 
 the average number of days spent in different types of temporary
accommodation decreased from 93 days to 72 days 
 the tenancy sustainment rate for homeless applicants living in settled Council
tenancies for more than 12 months, increased

Page 29

23 
13    Contact us 
The contact persons in relation to our RRTP are: 
Tom Irvine
Homeless & Housing Support Services Manager 
Email: Tom.irvine@renfrewshire.gov.uk 
and 
Kevin Thomas
RRTP Co-ordinator 
Email: Kevin.thomas@renfrewshire.gov.uk