Renfrewshire Council · 16 August 2022
Back to Communities and Housing Policy Board — 16 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Communities and Housing Policy Board
On: 16 August 2022
___________________________________________________________________
Report by: Director of Communities and Housing Services
___________________________________________________________________
Heading: Housing-led Regeneration and Renewal Programme for
Renfrewshire – Year 1 Update
___________________________________________________________________
1 Summary 
1.1 Renfrewshire Council’s Housing Led Regeneration and Renewal Programme
will deliver modern, high quality, energy efficient, affordable Council housing
that will not only significantly enhance the Council’s housing stock but will also
contribute to the wider transformation of communities and will be central to the
economic and social recovery of Renfrewshire. 
1.2 This ambitious programme was approved by the Communities, Housing and
Planning Policy Board on 18 January 2022 with amended proposals for 3 of
the 8 regeneration areas also approved on 15 March 2022. The programme is
being taken forward as a key Council priority, designed to deliver maximum
benefits for residents and with the active involvement of services across the
Council and Community Planning partners. 
1.3 This report provides members with an update on the progress made to date in
year one of the Regeneration and Renewal programme and provides a
timeline for the delivery of works scheduled throughout this ten-year strategy.
__________________________________________________________________________________ 
 
2. Recommendations
2.1 It is recommended that the Policy Board: 
(i) Approve the baseline programme for delivery of works across all 8
areas of the ten-year Housing Led Regeneration and Renewal
Programme (appendix 1) and instruct the Director of Communities and
Housing Services to provide regular updates on progress against that
baseline. 
__________________________________________________________________________________

Page 2

3. Progress to Date
3.1 Following the approval of the ten-year programme by the Policy  Board in
January and March 2022,  tenants, residents and owners have been issued
with regular updates advising them of the plans that were approved for each
area by the Communities, Housing and Planning Board. The Council’s
website also has dedicated Housing Regeneration pages which are regularly
updated to ensure that residents are informed of progress.
3.2 Given the scope and complexity of the Regeneration Proposals, a phasing
strategy has been developed and is set out in appendix 1, which takes 
account of a number of factors including delivery timescales, rehousing
requirements, contractor availability, maximising grant support for owner
participation and consideration of development constraints. 
3.3 Neighbourhood Renewal Plans are being developed involving Council
Services and community representatives in each of the eight Regeneration
Areas which will operate in parallel with the physical regeneration plans.
These will be tailored to the needs and circumstances of each area, going
beyond housing and the immediate external environment and taking account
of broader issues such as links to health and wellbeing, access to outdoor
space and sustainable travel and employment or training opportunities to
maximise the benefits achievable for local residents. There will be ongoing
engagement with residents and Councillors will also be provided with
opportunities to view the areas and to discuss the improvements proposed. 
3.4 In this context, ‘pop-up’ events have been arranged in each regeneration area
to continue our active and ongoing engagement with tenants, residents,
owners and local communities.  These events will be held on the following
dates: 
Area Date
Ferguslie/Broomlands Thursday 25 August 2022
Auchentorlie & Howard Street Area Friday 26 August 2022
Howwood Road Area Monday 29 August 2022
Waverley Road Tuesday 30 August 2022
Thrushcraigs Wednesday 31 August 2022
Moorpark Thursday 1 September 2022
Springbank/Mossvale Friday 2 September 2022   
3.5 Feedback received during the consultation phases will continue to be utilised
to ensure issues raised by tenants and residents about property condition and
the wider environment are addressed in the programme of works for each
area.  This includes where tenants advised us of works that they feel should
be prioritised, including the internal and external fabric of their blocks,
condition of common areas and the external environment surrounding their
homes.

Page 3

3.6 The programme aligns to the Council’s wider net zero ambitions. Newbuild
houses will be built to a standard specification evolved in partnership with the
University of Strathclyde and John Gilbert Architects, which will see new build
homes that are “net-zero” in terms of their embodied, operational and end-of-
life carbon emissions. 
4. Timescales for Delivery of the Investment Programme.
4.1  The information provided below is summarised to provide an update on
progress in each area to date, with appendix 1 providing information on the
anticipated timeline for the investment, demolition, newbuild and rehousing
initiatives where this is relevant for each individual area. (An extract of
appendix 1 is also included at the start of the discussion below of each of the
eight Regeneration Areas.) Where newbuild housing is proposed, a key
objective of the regeneration programme will be to deliver homes of a suitable
type and size to meet current and future needs and to enable existing
households to remain in the area where possible.
4.2 All Council tenants affected by demolition will be offered suitable alternative
accommodation in line with the Council’s housing allocation policy and will be
entitled to apply for home-loss and disturbance payments subject to
qualification criteria where the move is in accordance with the phasing
strategy that facilitates this regeneration initiative.  
4.2.1 Howard Street Area, Paisley 
Addresses Council Private Total 
Investment – on site target date Q4 2022–23
Clarence Street 19, 21, 22 and 24
Howard Street 11, 13, 15 and 17  
Ladyburn Street 10, 12 and 14
Lang Street 11, 13, 15 and 17
Violet Street 2 and 4 
Demolition:
McKerrell Street 35, 37, 39, 41 and 43
Ladyburn Street 9
Howard Street 8, 10, 12, 14 and 16 
Total 
79 
55 
134 
29 
11 
40 
108 
66 
174
Pre‐cont
2025/26 2026/27 2027/28 2028/29 2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25
Ownership Consolidation
Demolition
RehousingStrategy
Investment ‐ On‐site
Stakeholder Engagement
Benefits Realisation

Page 4

Subject to owner participation, this regeneration area will see up to 17 blocks
receiving a package of enhanced capital investment to include improvements
to the external environment and common areas, including closes, backcourts,
bin stores and recycling facilities as well as the external fabric of the buildings.   
The plans for the Howard Street Area will also see 11 blocks being
demolished to provide a new area of amenity open space and to reduce the
overall building density. While there are no plans at present for newbuild on
that site, given the density in the surrounding area, there may be newbuild
provision on another nearby site. 
Officers have commenced liaison with tenants in the Howard Street area to
discuss their rehousing requirements and with owners to discuss their options
where voluntary acquisition is being sought. 
4.2.2 Auchentorlie, Paisley   
Addresses Council Private Total 
Investment – on site target date Q4 2022–23
Auchentorlie Quadrant 1, 2, 3, 4, 6, 8, 10, 11
and 13
Seedhill Road 74 
Demolition: 
Auchentorlie Quadrant 5, 7 and 9 
Total 
44 
17 
61 
16 
1
17 
60 
18 
78 
Subject to owner participation, this regeneration area will see up to 10 blocks
receiving a package of enhanced capital investment to include improvements
to the external environment and common areas, including closes, backcourts,
bin stores and recycling facilities as well as the external fabric of the buildings. 
Fabric works will be tailored to the buildings in each area and will adopt a
whole house retrofit approach with measures to improve energy efficiency and
help reduce energy costs for tenants and residents. 
Demolition
Pre‐cont
2025/26 2026/27 2027/28 2028/29 2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25
OwnershipConsolidation
RehousingStrategy
Investment ‐On‐site
Stakeholder Engagement
Benefits Realisation

Page 5

The plans for this area will also see the removal of 3 blocks to reduce the
overall density in the area and improvements made to the surrounding
environment in and around the Auchentorlie area. This could include
opportunities for Growing Grounds/Allotments on the neighbouring land if this
is considered as being a priority for the local community. 
Officers have commenced the rehousing of tenants in properties identified for
demolition in the Auchentorlie area (some of which have been affected by fire
damage) and negotiations have also commenced where voluntary acquisition
is being sought. 
4.2.3 Waverley Road, Paisley 
Addresses Council Private Total 
Investment – on site target date Q2 2023–24
Waverley Road 18, 20, 22, 24, 26, 28, 30 and
32 
Demolition:
Waverley Road 34, 36, 38, 40, 42, 44, 46, 48,
50, 52, 54 and 56 
Total 
47 
68 
115 
1
4
5
48 
72 
120 
This regeneration area will see 8 blocks receiving a package of enhanced
capital investment to include improvements to the external environment and
common areas, including closes, back courts, bin stores and recycling
facilities as well as the external fabric of the buildings. Fabric works will be
tailored to adopt a whole house retrofit approach with measures to improve
energy efficiency and help reduce energy costs for tenants and residents. 
The plans for the Waverley Road area will also see 12 blocks being
demolished to reduce the overall density in the area and improvements made
to the surrounding environment. 
Officers will commence liaison with tenants in the properties highlighted for
demolition on Waverley Road in line with the phasing strategy shown on
appendix 1, with a view to discussing their rehousing requirements.   
Negotiations are ongoing with private owners to discuss their individual
circumstances and options where voluntary acquisition is being sought.
Pre‐contract
2025/26 2026/27 2027/28 2028/29 2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25
Ownership Consolidation
Demolition
RehousingStrategy
Inv ‐On‐site
Stakeholder Engagement
Benefits Realisation

Page 6

As previously detailed to the board, the assessment of the viability of the area
to be cleared at this location indicates that the steep topography of the land
would make the construction of housing expensive and uneconomic, due to
the requirement for retaining walls and ongoing maintenance costs.  It was
therefore agreed that replacement housing be built on nearby sites in the
Foxbar Rivers area which were previously identified for housing in the Local
Development Plan and Strategic Housing Investment Plan. 
4.2.4 Moorpark, Renfrew 
Addresses Council Private Total 
Investment – on site target date Q2 2024–25
Barclay Square
Birmingham Road
Jessiman Square
Knockhill Road
Mitchell Avenue
Paisley Road 168–170, 200–208, 214, 220–224,
236, 242 and 248–254 
170  147  317 
The Moorpark area has a high proportion of private owners and participation
of owners will be essential to ensure the successful delivery of the investment
programme.  Given that investment work is not scheduled until year 3 of this
10-year programme, officers are reviewing the Council’s ownership and block
make up to identify any ownership consolidation opportunities  to assist in the
future delivery of investment works. 
Subject to owner participation, this regeneration area will see blocks receiving
a package of enhanced capital investment to include improvements to the
external environment and common areas, including closes, backcourts, bin
stores and recycling facilities as well as where possible, the external fabric of
the buildings. Fabric works will be tailored to the buildings in each area and
will adopt a whole house retrofit approach with measures to improve energy
efficiency and help reduce energy costs for tenants and residents. 
Officers are continuing to explore opportunities for funding which may be
available to assist in reducing the cost of participation for owners. 
D Pre‐contract
2025/26 2026/27 2027/28 2028/29 2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25
Inv ‐On‐site
Ownership Consolidation
Stakeholder Engagement
Benefits Realisation

Page 7

4.2.5 Ferguslie/Broomlands, Paisley
 
Addresses Council Private Total 
Investment – on site target date Q2 2023–24 
Ferguslie Walk 21–25 and 16–28
Ferguslie 2, 3, 4, 6 and 8
Broomlands Street 56–62 and 64–70
West Campbell Street 2–8 
Carbrook Street 1–7 
Demolition:
Ferguslie 18–20 and 22–24 
Knox Street 2–8
West Campbell Street 1–7 and 10–16 
Total 
77 
64 
141 
82 
16 
98 
159 
80 
239 
Newbuild: 
Ph 1 – site at Carbrook St (approx 25 units) – on site target date Q4 2023–24 
Ph 2 – brownfield site (approx 25 units) – on site target date Q1 2027–28 
The Ferguslie/Broomlands area has a large number of private owners and
owner participation will be necessary if we are to deliver the investment
required successfully.   
This regeneration area will see mixed tenure blocks (subject to owner
participation) receiving a package of enhanced capital investment to include
improvements to the external environment, bin storage and recycling facilities
as well as the external fabric of the buildings. Fabric works will be tailored to
adopt a whole house retrofit approach with measures to improve energy
efficiency and help reduce energy costs for tenants and residents. 
A technical assessment has been carried out to assess the viability and cost
of newbuild housing on the former Carbrook nursery site, taking account of
any constraints and capacity issues, and this indicates that approximately 25
newbuild affordable units could be constructed.   
Demolition
Pre‐contract  
Newbuild (Ph 1)
Pre‐cont (Ph 2) Newbuild (Ph 2)
2025/26 2026/27 2027/28 2028/29 2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25
OwnershipConsolidation
RehousingStrategy
Investment ‐ On‐site
Pre‐Cont (Ph 1)
Stakeholder Engagement
Benefits Realisation

Page 8

This area will be further transformed with the later removal of 5 deck-access
blocks and the development of a further mix of newbuild Council homes on
the cleared sites as shown on appendix 1.   
The community will be invited to contribute to development plans for this area,
including the future of the communal laundries and, possibly, a proposed new
entrance to Ferguslie Gardens. 
Properties at 21 to 25 Ferguslie Walk require further site appraisals and
geotechnical survey work and will be subject to an update to a later meeting
of this Policy Board. 
4.2.6 Howwood Road Area, Johnstone 
Addresses Council Private Total 
Investment – on site target date Q4 2024–25
Craigbog Avenue
Craigview Avenue 
Craigview Terrace
Duncraig Crescent
Dundonald Avenue
Greenend Avenue
Highcraig Avenue 
Demolition:
Craigenfeoch Avenue 1–47
Dundonald Avenue 52–122 
Greenend Avenue 34–64, 121–199, 211–289 
Highcraig Avenue 1–23, 2–24 and 41 & 47 
Plus 4no commercial properties in Highcraig
Avenue (2no Council, 2no Private) 
Total 
124 
163 
287 
71 
15 
86 
195 
178 
373
Newbuild: 
Ph 1 – former school (approx 75 units) – on site target date Q3 2024–25 
Ph 2 – brownfield site (approx 75 units) – on site target date Q2 2028–29 
Demo (Ph 1)
Pre‐contract
Newbuild (Ph 1)
Pre‐contract (Ph 2) Newbuild (Ph 2)
2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
OwnershipConsolidation
Rehousing(Ph 1)
Investment ‐On‐site
Pre‐Contract(Ph 1)
Demo (Ph 2)
Stakeholder Engagement
Benefits Realisation
Rehousing(Ph 2)

Page 9

It is proposed that a first phase of newbuild homes will be constructed on the
former Cochrane Castle school site.  A technical assessment has been
carried out to assess the viability and cost of newbuild on this site and early
indications show that up to 75 newbuild Council homes of varying sizes could
be delivered in this first phase of development.   
When developing plans for the newbuild housing for this area, we will gather
the views, needs and preferences of people who currently live in the area and
are affected by these regeneration proposals.
It is anticipated that rehousing of tenants displaced will take place on a
phased basis following completion of the first set of newbuild homes, with two
phases of demolition and at least one phase of newbuild thereafter as detailed
in appendix 1: the first phase of demolition comprising properties between
Craigbog and Highcraig Avenues; and the second properties between
Highcraig and Craigenfeoch Avenues. 
There are 15 privately-owned properties to be acquired in the Howwood Road
area. Officers have commenced discussions with private owners to identify
any re-housing needs and coordinate the voluntary acquisition of privately
owned properties in the area as required. 
Along with the development of the former Cochrane Castle Primary School
site, officers are addressing wider flood-risk and drainage issues around the
site of the former St David’s Primary School. Treatment may provide
opportunities to provide enhanced open space in this location in addition to
the possible location for new shopping provision in the area. 
Subject to owner participation, this regeneration area will also see significant
investment in existing stock with a package of enhanced capital investment 
including improvements to the external environment, garden areas, bin
storage and recycling facilities as well as the external fabric of the buildings. 
Fabric works will be tailored to adopt a whole house retrofit approach with
measures to improve energy efficiency and help reduce energy costs for
tenants and residents. 
4.2.7 Springbank/Mossvale, Paisley 
 
 
Rehousing (Ph 1) RH (Ph 2)
Demolition (Ph 1) Demolition (Ph 2)
Pre‐contract (Ph 1) Newbuild (Phase 1)
Pre‐contract (Ph 2) NB (Ph 2)
2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
OwnershipConsolidation
Investment ‐On‐site
Rehousingstrategy
Inv ‐pre‐contract
Stakeholder Engagement
Benefits Realisation

Page 10

Addresses Council Private Total 
Investment – on site target date Q4 2023–24
Russell Street 1–19
Mossvale Street 24–38, 40–52, 54–66, 31–35
and 37–55 
Demolition:
Springbank Road 47–53, 55–61, 63–69 and 71–
77
Russell Street 6–20
Mossvale Square 1–19, 2–20 and 22–48
Mossvale Street 2–22
(Plus 16no lockups at 1-16 Russell St) 
Total 
31 
118 
149 
66 
36 
102 
97 
154 
251 
Newbuild: 
Ph 1 – brownfield site (approx 35 units) – on site target date Q1 2026–27 
Ph 2 – brownfield site (approx 65 units) – on site target date Q3 2029–30   
The Springbank/Mossvale area has the largest number of private owners
where acquisition is required to facilitate demolition.  Rehousing of tenants
and private acquisitions will therefore be phased to allow the clearance of land
for each phase of newbuild development. 
Housing options advice will be provided to tenants and residents of demolition
properties on a phased basis as detailed on appendix 1, the first phase
comprising the five blocks nearest the town centre and the second phase four
of the others. Displaced tenants will be provided with a permanent tenancy
elsewhere while reserving their rights to be considered for the newbuild
homes following their completion if desired. (This replicates the process
successfully delivered in Johnstone Castle where rehousing was necessary to
allow development of the newbuild homes on the footprint of the former flats.)   
Officers have been working with private owners to identify any re-housing
needs and coordinate the voluntary acquisition of privately owned properties
as required to facilitate development. 
This area will be further transformed with the investment in the remaining
stock (subject to owner participation in mixed tenure blocks) including
surrounding environmental improvements.

Page 11

4.2.8 Thrushcraigs, Paisley 
Addresses Council Private Total 
Demolition:
Thrushcraig Crescent 12, 14, 16, 18, 20, 22, 24,
26, 28, 30, 32, 34, 51 and 53
Rowan Street 101 and 103 
90  6  96 
Newbuild – brownfield site (approx 50 units) – on site target date Q2 2026–27 
The plans for the Thrushcraigs area involve the demolition of 16 blocks to
make way for new affordable housing on the cleared sites. The newbuild
housing to be delivered will be planned taking account of the views, needs
and preferences of people affected by these regeneration proposals.   
The regeneration work in this area will include enhancements to the
surrounding environment and will reduce the overall density.  
Officers have commenced liaison with tenants in the Thrushcraigs area to
discuss their rehousing requirements and with owners where voluntary
acquisition is being sought.
___________________________________________________________________
Implications of the Report
1. Financial – the financial background to this investment programme was
detailed in the report to Council on 17 December 2020. 
2. HR & Organisational Development – None.
3. Community/Council Planning  
 Our Renfrewshire is well – this investment programme is contributing to
improved wellbeing and quality of life for residents.
 Our Renfrewshire is thriving – this investment programme will deliver a
diverse range of economic and community benefit packages over the
lifetime of the project
 Our Renfrewshire is safe – ensuring our neighbourhoods are safe and
attractive 
Pre‐contract Newbuild
2030/312029/30 2031/322021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
Ownership 
Demo
RehousingStrategy
Stakeholder Engagement
Benefits Realisation

Page 12

4. Legal – work will be required with respect to acquisitions, disposals,
conveyancing and title changes as necessary. 
5. Property/Assets – as we progress through the phases of the investment
programme, there is an element of property acquisitions and disposals and
demolition of some existing properties as approved by the Board.   
6. Information Technology – N/A 
7. Equality & Human Rights –
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website.
8. Health & Safety – N/A
9. Procurement – a Procurement Strategy has been developed to ensure the
delivery of the investment, demolition and newbuild programmes and to
ensure community benefits are delivered locally from each contract.
10. Risk – a risk register has been developed to consider various risks including
those relating to financial and procurement as referred to in the implications
section of this report. This risk register  will be maintained throughout the
delivery of the Housing led Regeneration and Renewal programme. 
11. Privacy Impact – N/A 
12. COSLA Policy Position – N/A
13. Climate Risk – the investment programme will contribute towards meeting
the Council’s targets on climate change.
_________________________________________________________
List of Background Papers
Report to the Communities, Housing and Planning Policy Board, 15 March 2022, ‘Housing-led
Regeneration and Renewal Programme for Renfrewshire’
Report to the Communities, Housing and Planning Policy Board, 18 January 2022, ‘Housing-led
Regeneration and Renewal Programme for Renfrewshire’
Report to the Communities, Housing and Planning Policy Board, 18 May 2021, ‘Housing-led
Regeneration and Renewal Programme for Renfrewshire’
Report to Council, 17 December 2020, ‘Housing-led Regeneration and Renewal Programme for
Renfrewshire’   
Author:   Ray Walkinshaw, Housing Regeneration and Development Manager,
ray.walkinshaw@renfrewshire.gov.uk, 07483 146814.

Page 13

Appendix 1 – Baseline timescale 
 
Staff and resources
Pre‐cont
Demolition
Pre‐cont
Pre‐contract
D Pre‐contract
Demolition
Pre‐contract  
Newbuild (Ph 1)
Pre‐cont (Ph 2) Newbuild (Ph 2)
Demo (Ph 1)
Pre‐contract
Newbuild (Ph 1)
Pre‐contract (Ph 2) Newbuild (Ph 2)
Rehousing (Ph 1) RH (Ph 2)
Demolition (Ph 1) Demolition (Ph 2)
Pre‐contract (Ph 1) Newbuild (Phase 1)
Pre‐contract (Ph 2) NB (Ph 2)
Pre‐contract Newbuild
Thrushcraig
Demolition & Newbuild
Springbank/Mossvale
Investment, Demolition & Newbuild
Auchentorlie
Investment & Demolition
Howard Street Area
Investment & Demolition
Waverley Road
Investment & Demolition
Moorpark
Investment
Ferguslie/Broomlands
Investment (inc pre‐1919 tenements), Demolition & Newbuild
Howwood Road Area
Investment, Demolition & Newbuild, including on school site(s)
2025/26 2026/27 2027/28 2028/29
Applicable to all areas
2030/31
Regeneration Area
2029/30 2031/322021/22 2022/23 2023/24 2024/25
OwnershipConsolidation
Ownership Consolidation
OwnershipConsolidation
Inv ‐ On‐site
Ownership 
Ownership Consolidation
OwnershipConsolidation
Investment ‐ On‐site
OwnershipConsolidation
Demolition
Demo
Demolition
RehousingStrategy
RehousingStrategy
RehousingStrategy
Rehousing(Ph 1)
Ownership Consolidation
RehousingStrategy
RehousingStrategy
Rehousingstrategy
Investment ‐ On‐site
Investment ‐ On‐site
Pre‐Contract(Ph 1)
Investment ‐ On‐site
Pre‐Cont (Ph 1)
Inv ‐ pre‐contract
Investment ‐ On‐site
Inv ‐ On‐site
Demo (Ph 2)
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Rehousing(Ph 2)