Page 1

1 
___________________________________________________________________
To: Communities and Housing Board
On: 16th August 2022
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Community Empowerment Fund
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek approval from the Communities
and Housing Board for the award of grants from the Community
Empowerment Fund. 
1.2 The key objective of the fund is to support community organisations to
acquire and develop community assets. The fund aims to support and
develop community organisations, with a specific focus on assisting
those organisations that wish to acquire and develop community
assets. 
1.3 Three new applications were received through this round as detailed
within Section 2 and Appendix 1.   
1.4 The next deadline for applications is 18 September 2022.

Page 2

2 
2. Recommendations 
2.1 It is recommended that the board approves the recommendation as
detailed in Section 4 and Appendix 1, to award: 
• £50,000 to Renfrew Victoria to refurbish and upgrade the internal
areas of the Kirklandneuk Pavilion.
_________________________________________________________
3. Background
3.1 At its meeting on 2 March 2018, Council agreed to commit £1.5million
(£0.5million in revenue and £1million in capital) to establish a
Community Empowerment Fund that will be used to support community
asset transfers, by providing up-front investment in the condition of
assets prior to transfer. It should be noted that the £1.5million
represents a one-off investment fund.
3.2 On 20th June 2018, Leadership Board agreed the key objectives and
criteria of the fund, and agreed that applications to the Community
Empowerment Fund be submitted to Communities and Housing Board
for final approval.
3.3 The key objectives of the fund are to support and develop community
organisations with a specific focus on assisting those organisations that
wish to acquire and develop community assets in three ways: 
• Project: Support the development of the Business Plan for an asset 
• Organisation: Develop the organisational capacity to manage and
develop an asset
• Property: Upfront investment in assets prior to or after transfer 
3.4 The fund is comprised of £0.5million in revenue funding and £1million
in capital funding. As such, it is anticipated that revenue funding will
support applications to develop the project or organisation, and the
capital funding will be used to support property costs. 
3.5                It will be important applicants to the fund are able to demonstrate the
following: 
• Able to demonstrate positive impact for local communities
• The community are involved in the design and delivery of the
project
• Good working relationships and partnership with others

Page 3

3 
• The project is financially sustainable 
• Strategic fit with the fund objectives and criteria 
• Value for money and leverage of additional funding and/or
resources 
3.6 The award of funding from the Community Empowerment Fund does
not commit the Council to a particular outcome as part of the Asset
Transfer process, which will be subject to a separate decision making
process through relevant governance arrangements.
4.  Summary of applications 
4.1 Three new applications were received by the deadline date of 4 July
2022.  The total value of requested grants through this round is
£101,321.00. 
4.2 A cross-service panel of officers has been established to review and
assess the applications against the agreed objectives and criteria
outlined at Section 3.2 and 3.3 of this report. 
4.3 The officer recommendation is:
•  To approve the application submitted by: Renfrew Victoria Youth
Football Club (£50,000.00) for refurbishment and upgrading of
internal areas within the Kirklandneuk Pavilion.  
•   To defer the applications submitted by Lochwinnoch Community
Development Trust and Western Desert Recce Group SCIO to allow
for further work to be carried out with groups relating to their
proposals. 
4.4 A summary of the recommendation for award can be found at Appendix
1. 
___________________________________________________________________
Implications of the Report
1. Financial - Council approved the allocation of £1.5million to establish
the Community Empowerment Fund in March 2018. 
2. HR & Organisational Development – Not applicable 
3. Community/Council Planning –                       
The Renfrewshire Community Plan 2017-2027 states “There are new
opportunities for communities to use, manage or take ownership of

Page 4

4 
public sector assets and also to participate in the planning and delivery
of services through the Community Empowerment Act.  Over the last
few years, there are over a dozen examples of community groups that
have taken over public sector buildings or land in Renfrewshire, and
more community groups are now thinking about assets and
participation requests. As a partnership, we are committed to
supporting this wherever we can.”                                                                                         
The Renfrewshire Council Plan also has a number of relevant priorities
as part of the ‘Building strong, safe and resilient communities’ outcome.
These include: 
• Strengthening existing community networks and empowering local
people to become more involved in their area and the services
delivered there. 
• Working with communities to support the regeneration of some of
our most disadvantaged areas. 
• Ensuring all towns and villages in Renfrewshire are better
connected and able to participate in social, cultural or economic
activities across the Renfrewshire area. 
4. Legal- The establishment of this fund supports the delivery of a number
of the Council’s obligations as part of the Community Empowerment
Act 2015. 
5. Property/Assets - The development of this fund will support Asset
Transfer and support the Council to meet its obligations as part of the
Community Empowerment Act. 
6. Information Technology – None  
7. Equality & Human Rights - It is anticipated that the fund will have a
positive impact on equality and human rights, and applications for the
fund will be assessed to ensure they take relevant equalities
implications into account.
8. Health & Safety – None 
9. Procurement – None
10. Risk – None 
11. Privacy Impact – None 
12. Cosla Policy Position – None

Page 5

5 
______________________________________________
List of Background Papers 
(a)  Background  Paper 1 – None 
_____________________________________________________ 
Author:           Annabelle Armstrong-Walter, Strategic Partnerships and Inequalities
Manager, 0141 618 5968

Page 6

1 
Appendix 1: Recommendation for award 
Organisation Amount
Requested
Purpose Recommendation  Additional Info and/or Areas of Concern
Renfrew
Victoria
Football Club 
£50,000.00 
The purpose of the project is to regenerate and
refurbish the pavilion built in 1976, with a
Community Asset Transfer agreed in 2019. 
The purpose of the project is to enable the club to
follow the Scottish Football Association playing
pathway by starting a girls’ section and growing this
to levels of the boys’ group. The project will allow a
greater match and training day experience by
increasing the size of the changing area and
refurbishment of the shower areas to Sport Scotland
standards. This refurbishment will allow the club to
increase membership and usage of the playing fields
by having facilities to change and shower after
activities. 
The refurbishment will have an environmental
impact as the project will provide 100% renewable
energy for lighting and heating due to the
installation of 21 solar panels and 2 battery units. 
£50,000  The Panel felt that funding would allow Renfrew
Victoria Football Club to progress their plans to
upgrade the facilities at Kirklandneuk Pavilion, and
progress capital works required to split utility
provision with the Community Centre in line with
the Community Asset Transfer agreement. The panel
also felt the funding package would support the
group to lever in additional external funding, for
example from Sport Scotland.