To: Communities and Housing Policy Board 
On: 7 June 2022
___________________________________________________________________
Report by: Director of Communities and Housing Services
___________________________________________________________________
Heading: Greenspaces, Parks & Play Areas and Villages Investment Fund
___________________________________________________________________ 
1. Summary 
1.1 This report updates the Communities and Housing Policy Board on progress
made in supporting community projects through the Greenspaces, Parks &
Play Areas and Villages Investment fund and provides information on 4
projects approved under delegated authority since the last Board Meeting
totalling £13,423.10.   
1.2 The key objective in allocating funding is to work with, and support,
community groups to identify and deliver improvement projects in their local
communities, improve their local greenspaces (including parks and play
areas) and strengthen the identity, heritage, uniqueness and integrity of
village life. 
1.3 The Villages Investment Fund continues to be promoted to the relevant Local
Area Partnerships to encourage eligible communities to come forward to bid
for their share of the remaining funds.  Support for two village Gala days was
approved under delegated authority in this cycle.  The Villages Improvement
Fund still has a reasonable level of unallocated resources having received a
further allocation of £200,000 agreed at Council in March 2022. 
1.4 In addition, a further 2 Green Spaces projects have also been approved under
delegated authority, totalling £9,223.10.  Further information on each of the
projects funded under delegated authority is included in Appendix 1 to this
report. 
1.5 Since the last report, the installation of 2 new play parks at Sandyflats,
Johnstone and Barwood in Erskine has been completed.  The installation of
Spateston’s park is currently underway, with installation of parks at
Maxwellton and Kilbarchan both planned for June and Lochwinnoch’s
installation due to take place in August.

Page 2

1.6 The funding awarded from Green Spaces to support local volunteers has so
far seen twenty-five of the most active or willing Team Up to Clean Up
volunteers being provided with quality tools and protective clothing to support
their activities.  Further work is underway with Estates, Risk Management,
Environment & Infrastructure and Health and Safety, to ensure processes are
in place to permit relevant ground works to be taken forward where requested.   
1.7 Resource to deliver the priorities of both the Green Spaces and Team up to
Clean Up projects has increased as a result of Public Protections merge with
Community Learning and Development.  In addition to this, the service has
now advertised for 6 new team members to tackle environmental crime with
litter and flytipping ongoing priorities within Renfrewshire communities – in line
with the budget motion agreed by Council in March 2022. 
1.8 The increase in resource will allow additional support to be provided to
schools encouraging pupils to engage and deliver their own supported
community and environmental projects.  A recent visit from HMIE (Her
Majesty’s Inspector for Education) examining the impact of the pandemic on
community capacity development highlighted the positive impact of both Team
Up to Clean Up and the Greenspaces funding as best practice in community
capacity building with the inspectors also impressed by the strength of
partnership working made possible by the new joined up service structure.    
1.9 A further 5 projects are currently being developed by communities across
Renfrewshire.  Decisions will be required to identify successful applications in
due course as the Greenspaces Fund is now almost fully committed.  Priority
will go to areas which have not yet received awards. The current funding
position is detailed in Appendix 2.
________________________________________________________
2. Recommendations
2.1 It is recommended that the Communities and Housing Policy Board: 
(a) note the work currently being undertaken to support communities as
they develop projects to be funded using the Greenspaces, Parks &
Play Areas and Villages Investment Fund; 
(b) note the projects detailed in appendix 1 of this report and approved
by the Director of Communities and Housing under delegated
authority; and 
(c) note that the current projects being developed by communities and
listed in Section 3 will (when final applications are made) fully
commit the Green Spaces, Parks and Play areas element of the
fund.
_________________________________________________________

Page 3

3. Expected Applications 
3.1 Renfrewshire Council has supported 73 projects since October 2018 that met
the criteria for this fund.  Further projects continue to be developed within
communities with the following potential applicants currently active and
expected to apply: 
 Howwood Parent Council – Multi-use Games Area in school
 Elderslie Community Council – Phase 3 Queens Road Park
Improvements
 Howwood Road Tenants & Residents Association – tables, benches
and planters
 The Darkwood Crew – Teen Shelter
 Knockhill Park – extension to pathway to support local runners 
3.2 Reports will be brought back for the consideration of the Board in relation to
these projects at future meetings of the Communities and Housing Policy
Board. 
3.3 In this round, 4 applications have been approved which meet the criteria for
approval of grant funding.  More information on these projects is detailed in
the summary included in appendix 1 to this report. 
_________________________________________________________
Implications of the Report 
1. Financial - Council approved the allocation of £2.020 million to establish the
Greenspaces, Parks & Play Parks and Villages Investment Fund in March
2018.  Due to the capital works being undertaken, Officers are ensuring that
there are minimal recurring revenue costs to Services in the coming years. 
2. HR & Organisational Development – None 
3. Community/Council Planning – 
The Greenspaces, Parks & Play Parks and Village Investment Fund will be
important to achieving and assisting the Community Plan by ensuring that
Renfrewshire is thriving, well, fair and safe for residents, workers and visitors. 
4. Legal - All legislative requirements will be taken cognisance of during this
process wherever required e.g. health and safety requirements. 
5. Property/Assets - There is the potential for property/assets to be included as
part of this fund. 
6. Information Technology – None 
7. Equality & Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the

Page 4

report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website. 
8. Health & Safety - Cognisance will be taken of health and safety requirements
wherever required e.g. for play park equipment. 
9. Procurement - There is no potential for the Council to be procuring and
installing equipment of behalf of a community group as part of this grant
funding process. 
10. Risk - Discussions with the Council Risk Manager are on-going to ensure that
the risk to the Council, as part of this grant funding process, is minimised. 
11. Privacy Impact - None. 
12. COSLA Policy Position – Not Applicable 
13. Climate Risk – Not Applicable
_________________________________________________________ 
List of Background Papers
None 
___________________________________________________________________
Author:  Oliver Reid, Head of Communities and Public Protection.

Page 5

Appendix 1
June 2022 Applications – Delegated Authority 
Applicant Project Description Requested Recommendation Reason Geographical Area
1. Bridge of Weir
Festival
Committee
This local gala day has been a longstanding
event in the BoW community.  Funding will
pay for the provision of onsite first aid staff,
portable toilets, piper, children’s entertainer
and a birds of prey show, as well as
temporary parking measures required to
facilitate vehicle access to the park.     
£2,500 Approved under
delegated authority 
The Villages Investment
Fund is designed to support
the villages deliver such
traditions, harnessing pride
and village identity, 
Bridge of Weir
2. Lilias Day
Committee 
A traditional annual event in the Kilbarchan
villages calendar.  Funds will support onsite
entertainment, football markings,
bunting/decorations as well as onsite toilet
provision. 
£1,700 Approved under
delegated authority
The Villages Investment
Fund is designed to support
the villages deliver such
traditions, harnessing pride
and village identity
Kilbarchan
3. Create Paisley Create is an active group supporting young
people delivering activism work focusing on
bullying, discrimination, and mental health
and wellbeing.  The group have
commissioned an artist and alongside the
artist they will design and paint a fitting
mural on a boundary wall within Fountain
Gardens. Funds received will pay for the
artist, a gazebo, paints and refreshments.  
£4,250 Approved under
delegated authority
The young people of Create
have successfully delivered
a mural in the Shortroods
area of Paisley.  They
partner with the Star Project
which deal with similar
issues. 
The mural should increase
the appeal of Fountain
Gardens. 
Paisley
4. Pachedu PACHEDU is a charity working with
diverse minority ethnic groups, refuges
and asylum seekers.  The have an
interest in growing foods that are
appropriate to their own cultures.  The
seek to teach and feed their community
as well as reconnect with nature and
learn new skills.  Pachedu have
partnered with RAMH. 
£4,973.10 Approved under
delegated authority
Together with RAMH the
group will benefit in a range
of areas.  Education, health
and wellbeing and
integrating into their local
communities.
Paisley

Page 6

Appendix 2
Greenspace, Parks and Play Areas Funding 
Project Funding
proposed
External Funding (or other Council funding)
Bridge of Weir Gala £2,500 n/a
Lilias Day Gala £1,700 n/a
Fountain Gardens Mural £4,250 n/a
Growing Grounds/RAMH £4,973.10 n/a 
Funding Allocated Budget Committed Budget Unallocated Budget Value of Potential
Additional Projects
Greenspace, Parks and Play
Areas
£1,280,000 £1,228,872 £51,128 £35,000
Village Investment Fund £520,000 £424,625 £95,375 £40,000
Staffing costs £220,000 £220,000 - -
Total £2,020,000 £1,873,497 146,503 £75,000