Renfrewshire Strategic Housing Investment Plan 2026 to 2031 - Report

Renfrewshire Council · 28 October 2025
Back to Communities and Housing Policy Board — 28 October 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
___________________________________________________________________
To: Communities and Housing Policy Board
On: 28 October 2025
___________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure 
___________________________________________________________________
Heading: Renfrewshire Strategic Housing Investment Plan 2026 to 2031
___________________________________________________________________
1. Summary 
1.1 Following consultation, the Renfrewshire Strategic Housing Investment Plan
2026-2031, attached at Appendix 1, has been finalised for submission to the
Scottish Government. 
1.2  The Renfrewshire Strategic Housing Investment Plan 2026 to 2031 sets out a
development programme of affordable housing projects across Renfrewshire
that will be supported by Scottish Government funding through the Affordable
Housing Supply Programme. 
___________________________________________________________________
2. Recommendations 
It is recommended that the Communities and Housing Policy Board: 
2.1 Approves the Renfrewshire Strategic Housing Investment Plan 2026 to 2031,
set out in Appendix 1, for submission to the Scottish Government.
_________________________________________________________
3. Background 
3.1 The Renfrewshire Strategic Housing Investment Plan outlines how Scottish
Government funding for affordable housing will be targeted to help achieve the
priorities set out in Renfrewshire’s Local Housing Strategy, supporting the
delivery of a range of affordable housing projects across Renfrewshire. 
3.2 As part of the Affordable Housing Supply Programme process, the Scottish
Government allocates grant funding, known as Resource Planning
Assumptions, to individual Council areas.

Page 2

PUBLIC
3.3  The Scottish Government confirmed on 10th October 2025 that Renfrewshire
Council has received an additional £0.175 from the National Acquisitions Fund to
support affordable housing providers to acquire suitable homes for social rent
on the open market. This additional funding increases Renfrewshire’s Resource
Planning Assumption allocation for 2025/26 to £17.486 million. 
3.4 The Resource Planning Assumption for Renfrewshire is only confirmed for one
year and there remains uncertainty over the future level of future funding
allocations. This funding uncertainty means that delivery timescales for projects
may be subject to change. 
3.5  Resource Planning Assumptions support the delivery of new affordable homes
across Renfrewshire by providing grant support at benchmark rates. The
Scottish Government benchmark grant rates are set at £87,763 for newbuild
Council homes and £95,741 for newbuild social rented homes delivered by
housing association partners. 
3.6  Additional grant funding may be made available on top of the grant benchmark
rates where affordable housing developers include specific qualitative design
features related to zero emissions; the installation of automatic fire suppression
systems; electric vehicle charging points; space for home working; provision of
balconies and digital connectivity. 
3.7   The Strategic Housing Investment Plan contains funding provision for the
Council’s own newbuild development programme and projects being delivered
by housing association partners. 
3.8  The number of new homes and timescales for the delivery of individual projects
will be refined as development proposals are finalised and as actual grant
requirement is confirmed. All projects within the Strategic Housing Investment
Plan are kept under review to ensure that resources made available to
Renfrewshire can be fully utilised to add to the supply of high-quality affordable
homes. 
4.  Renfrewshire Strategic Housing Investment Plan 2026 to 2031 
4.1  The draft Strategic Housing Investment Plan 2026-2031 was approved for
consultation by the Communities and Housing Policy Board on 19 August 2025.
A 4-week consultation period followed which included all housing associations
operating in Renfrewshire, the Health and Social Care Partnership, local
stakeholder groups such as Community Councils and tenants’ and residents’
associations, community planning partners and Renfrewshire’s residents. 
4.2  The Strategic Housing Investment Plan 2026-2031 attached at Appendix 1
takes account of feedback received from respondents and from individual
meetings with housing association partners during the consultation period. 
4.3  A total of 4 representations were received during the consultation period. A
summary of the representations and associated amendments made in finalising
the Strategic Housing Investment Plan are attached at Appendix 2.

Page 3

PUBLIC
4.4 Renfrewshire Council continue to work closely with the Scottish Government
and Registered Social Landlords in the delivery of the Strategic Housing
Investment Plan. This includes quarterly tripartite meetings with developing
partners, the Scottish Government and Renfrewshire Council to monitor
progress and seeking monthly updates on individual projects. In addition, there
are opportunities for partners to engage at the Housing Provider Forum to
discuss any emerging housing strategy and development issues. 
4.5  Officers have met both Paisley Housing Association and Linstone Housing
Association to discuss their comments and any issues raised and to reinforce
that the Council welcome and support all Registered Social Landlords
delivering new affordable homes across Renfrewshire. 
4.6  The Strategic Housing Investment Plan has been updated to include: 
• A new site which will see Paisley Housing Association deliver 8 social
rented units at 123 Neilston Road, Paisley in 2026/27; and,
• Minor programming changes to projects to reflect updates received from
Housing Association partners. 
4.7 The Council continues to work closely with the Scottish Government, Housing
Associations and other developing partners to manage and deliver the
development programme and facilitate delivery of the affordable homes
throughout Renfrewshire.
___________________________________________________________________
Implications of the Report 
1. Financial - Provision has been made within the Housing Revenue Account
(HRA) Capital Budget in relation to the projects where the Council is the
developing organisation. An important assumption on this is that the Scottish
Government Grant will be allocated according to the Resource Planning
Assumptions outlined in the current plan. 
2. HR & Organisational Development - None. 
3. Community/Council Planning – 
The Local Housing Strategy is considered to support the Renfrewshire
Community Plan 2017-2027, particularly the theme of Our Renfrewshire is
thriving through encouraging people to stay here and attracting new people to
settle here; and making sure infrastructure (such as housing) is in place to
support growth in the local population. 
It is considered to support the Council Plan 2022-2027 (June 2024 refresh)
particularly the Place priority of ensuring Renfrewshire has a supply of green,
high-qulaity, affordable, cross-tenure homes in the right places to meet current
and future demands; and the Green priority of working towards a new zero
Renfrewshire by 2030.

Page 4

PUBLIC
4. Legal - Conveyancing work associated with land disposals, and any site
assembly and title changes or checks. All new Council contracts for new build
affordable housing will require input from the contracts and project legal
sections at the pre and post tender stages through to award. 
5. Property/Assets - None. 
6. Information Technology - None. 
7. Equality & Human Rights   
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website. 
8. Health & Safety - None. 
9. Procurement - None. 
10. Risk - There is a potential risk to these plans associated with the availability of
Scottish Government Grant in the absence of multi-year Resource Planning
Assumptions. 
11. Privacy Impact - None. 
12. Climate Risk - The Renfrewshire Strategic Housing Investment Plan aims to
deliver high quality, energy efficient homes in sustainable locations across
Renfrewshire. 
13. Children’s Rights – None. 
14. Cosla Policy Position - None.
_________________________________________________________
(a) Appendix 1 – Renfrewshire Strategic Housing Investment Plan 2026 to 2031
(b) Appendix 2 – Summary of consultation responses and amendments to SHIP
___________________________________________________________________ 
Author: Alan Williamson, Strategy and Place Manager
Tel: 07811 053968; Email: alan.williamson@renfrewshire.gov.uk

Page 5

1
PUBLIC   
Renfrewshire Strategic Housing Investment
Plan 2026 to 2031

Page 6

Strategic Housing Investment Plan 2026 to 2031   2
PUBLIC
Renfrewshire’s Strategic Housing Investment
Plan  
The Scottish Government’s Affordable Housing Supply
Programme (AHSP) sets out a national framework to support the
development of new affordable homes. 
As part of the Affordable Housing Supply Programme process,
local authorities are required to prepare a Strategic Housing
Investment Plan (SHIP) each year that outlines where grant
funding provided to Councils by the Scottish Government will be
used to the support delivery of new affordable homes.   
The Renfrewshire Strategic Housing Investment Plan 2026 to 2031
has been informed by discussions with the Scottish Government
and housing association partners operating in Renfrewshire. 
The Strategic Housing Investment Plan is submitted to the
Scottish Government and a Strategic Local Programme
Agreement (SLPA) for Renfrewshire will form the basis of
individual agreements between the Scottish Government,
Renfrewshire Council and housing association partners on
funding for specific affordable housing projects. 
Aligning with Renfrewshire’s Local Housing
Strategy and Development Plan 
The Strategic Housing Investment Plan takes account of the
Scottish Government’s Housing and Planning Delivery Framework
(HPDF) which promotes more efficient collaboration between
Housing and Planning Services in relation to the Local Housing
Strategy, Housing Need and Demand Assessment and national
planning policies. 
It provides details of affordable housing projects in Renfrewshire
that will assist in meeting the strategic priorities of Renfrewshire’s
Local Housing Strategy and support the delivery of the
Renfrewshire Local Development Plan 2. These projects are
expected to be supported by Scottish Government grant funding
over the short, medium and longer term. 
Projects included within the Strategic Housing Investment Plan
will assist in providing the right homes in the right places and
contribute to providing safe, warm and energy efficient homes
that meet people’s housing needs and contribute to the creation
of thriving sustainable communities.

Page 7

Strategic Housing Investment Plan 2026 to 2031   3
PUBLIC
Renfrewshire’s Local Housing Strategy 
The fourth Local Housing Strategy for Renfrewshire was approved
at the Council’s Communities and Housing Policy Board in
October 2023. The Local Housing Strategy 2023-2028 looks to
build on past successes whilst aiming to meet need and demand
for both housing and housing related services. The Local Housing
Strategy includes 5 strategic priorities as shown below: 
1. The supply and delivery of housing is increased across all
tenures to meet the housing needs of different groups and
create attractive and sustainable places.
2. People live in high quality, well managed homes in
sustainable neighbourhoods.
3. Address the challenges of the climate emergency,
delivering homes that are warm, energy efficient and fuel
poverty is minimised.
4. Prevention of homelessness and providing support for
those in housing need.
5. People can live independently for as long as possible in
their own home and the different housing needs of people
across Renfrewshire are being met. 
Link/C~urb Housing Association, social rented development, Hawkhead, Paisley   
Development Plan for Renfrewshire 
Renfrewshire’s current Development Plan consists of National
Planning Framework 4 and the Renfrewshire Local Development
Plan 2021 (LDP2). 
Renfrewshire’s Development Plan supports the development of
new homes that improve affordability, choice, accessibility and
adaptability, including the provision of wheelchair accessible
homes.

Page 8

Strategic Housing Investment Plan 2026 to 2031   4
PUBLIC
When the Council is assessing projects included as part of this
Strategic Housing Investment Plan, it will consider proposals
against the policies in the National Planning Framework 4 and
Renfrewshire LDP2. 
The Scottish Government’s Housing Programme  
The Scottish Government ‘Housing to 2040 Strategy’ includes a
target to provide 110,000 affordable homes by 2032 with at least
70% of these homes to be developed for social rent. 
The Scottish Parliament declared a national housing emergency
in May 2024 recognising a range of challenges facing the housing
sector including pressures on homelessness services, high levels
of people in temporary accommodation and a lack of affordable
homes compared to high waiting lists. 
Renfrewshire Council are committed to contribute to addressing
the national housing emergency and affordable housing supply
targets. The Council will continue to work in partnership with the
Scottish Government, our housing association partners, private
developers and the construction industry to increase the delivery
affordable homes throughout Renfrewshire in line with available
funding. 
Sanctuary Scotland, social rented development, Sutherland Street, Paisley 
Resources for Affordable Housing Delivery
The national funding position for the delivery of affordable homes
improved in 2025. In 2025/26, Renfrewshire will receive a funding
allocation in line with past allocations prior to 2024/25. Funding
for 2025/26 is confirmed at £17.486 million compared to £13.181
million allocated in 2024/25.

Page 9

Strategic Housing Investment Plan 2026 to 2031   5
PUBLIC
Prior to 2024/25, the Scottish Government provided Councils with
multi-year Resource Planning Assumptions (RPA’s) to support
longer term planning and delivery of projects within the Strategic
Housing Investment Plan, providing some degree of certainty to
facilitate longer term planning by housing providers. 
Due to pressures on national budgets, RPA’s in 2024/25 and
2025/26 were issued on a single year basis rather than as multi-year
RPA’s. 
Scottish Government funding allocations beyond 2025/26 are still
to be confirmed. It is likely that funding awards will continue to be
made on a single year basis over the next few years. For the
purpose of programming a five-year plan, the Strategic Housing
Investment Plan estimates that an RPA of £15m will be available
each year from 2026/27 to support the delivery of new affordable
homes in Renfrewshire. 
Scottish Government Grant Benchmarks
New affordable homes developed as part of the Strategic Housing
Investment Plan are funded through a combination of Scottish
Government grant and the developers own financial resources. 
Scottish Government grant support is provided at flexible
benchmark rates for each affordable home developed. The
Scottish Government benchmark grant rate is currently set at
£87,763 for new build social rented Council homes and £95,741
for new build housing association homes. 
These grant rates are flexible which means projects may be
eligible for a higher grant award per property following a detailed
assessment of property mix, needs group, project viability and
development costs. 
Affordable housing providers who develop affordable homes
through a Section 75 Agreement on a larger private sector
housing site are required to deliver homes at the benchmark rate. 
Funding Additional Design Features
In addition to the basic flexible benchmark grant, additional grant
may be provided from the Councils existing Resource Planning
Assumption to support inclusion of specific quality and design
features in new affordable homes, these features include: 
o The delivery of homes to Silver Level of the 2019 Building
Regulations in respect of Energy for Space Heating;
o The provision of balconies within flatted developments where
the provision of private or communal outdoor space is not
possible;

Page 10

Strategic Housing Investment Plan 2026 to 2031   6
PUBLIC
o The provision of space for home working or study where it is not
possible to incorporate such space within the design of the
homes under current space standards; 
o Digitally enabled homes with tenants able to arrange for an
internet connection without the internet service provider having
to provide additional cabling to the premises;
o The installation of ducting infrastructure for electric vehicle
charge point connectors;  
o Installation of electric vehicle charge points;
o The installation of automatic fire suppression systems; and  
o Installation of heating systems which produce zero direct
emissions at the point of use.  
Any additional grant required to support inclusion of any of these
features is met from existing funding allocations from the Scottish
Government - this can have an impact on the number of new
affordable homes being delivered as the level of grant funding
required per property increases. 
Funding for Acquisition of Private Housing (Rental Off the
Shelf) and the National Acquisition Programme 
Provision has been included within the Strategic Housing
Investment Plan in recent years to assist affordable housing
providers to purchase appropriate properties for social rent on
the open market by utilising Scottish Government Grant. 
The Scottish Government announced a two-year £80 million
National Acquisitions Fund in April 2024, with additional funding
allocations made to Councils to support open market
acquisitions over the period 2024/25 and 2025/26. 
Renfrewshire Council received £346,000 from this national fund in
2025/26 which was supplemented by funding from the confirmed
Resource Planning Assumption to provide over £1.5m to support
affordable housing providers to acquire suitable homes for social
rent on the open market. 
This allowance is subject to continuous review depending on the
level of funding made available to Renfrewshire.

Page 11

Strategic Housing Investment Plan 2026 to 2031   7
PUBLIC
Scottish Government Charitable Bond Funding (ALLIA) 
In addition to funding made available to Renfrewshire through
the confirmed Resource Planning Assumption for 2025/26,
Renfrewshire projects have previously successfully accessed Allia
funding which is funding derived from the Scottish Governments
Charitable Bonds investments programme. This is managed by
Allia, a social investment charity. 
Each year income is generated from bonds which is then used by
the Scottish Government’s More Homes Scotland team to
support increasing the supply of homes by providing one off
grants to affordable housing providers who have projects that
align with the funds criteria. 
These additional funds have been used by Link/C~urb Housing
Association on their development of 68 social rented homes in
Johnstone Castle which are due to complete in June 2026. 
Council Tax on Empty and Second Homes 
In Renfrewshire, no direct funding is allocated to the affordable
housing programme from revenue raised from empty or second
homes with any revenue raised allocated to the Council’s General
Fund to support wider Council priorities. This approach will
continue due to ongoing pressures on overall Council budgets
with any ring fencing of funds only likely to be considered when it
is sustainable to do so. 
Meeting Renfrewshire’s Affordable Housing
Needs and LHS Strategic Priorities
The  Strategic Housing Investment Plan aims to deliver a range of
new affordable homes across Renfrewshire to meet housing
needs and support the delivery of strategic priorities set out in the
Renfrewshire Local Housing Strategy 2023-2028. 
When developing proposals for new affordable homes, the
Renfrewshire Local Development Plan (LDP2) requires
development to include a range of property types and sizes to
meet different housing needs, including smaller one bedroom
homes and larger three and four bedroom family homes
throughout Renfrewshire. This also includes the delivery of
accessible homes and homes designed to wheelchair accessible
standards.

Page 12

Strategic Housing Investment Plan 2026 to 2031   8
PUBLIC 
Williamsburgh Housing Association, social rented development, Albert Road, Renfrew    
All affordable housing must be built to Housing for Varying Needs
standards with flexibility built into the design to allow for future
adaptation and reconfiguration to meet tenant and resident’s
current and future needs. 
This Strategic Housing Investment Plan supports the
development of high quality energy efficient affordable homes, 
recognising that good quality affordable housing can positively
impact peoples’ lives and enhance Renfrewshire’s places. 
The Council will continue to work with housing association
partners to determine the most appropriate property mix on a
project by project basis taking account of Council and housing
association waiting list data and the findings from the Glasgow
Clyde Valley Housing Need and Demand Assessment (HNDA3)
and the Renfrewshire Housing Need and Demand study. 
A breakdown of property sizes for recently completed
developments and those that have planning consent is included
in Appendices 1 and 2. 
In recent years, Strategic Housing Investment Plans have
primarily focused on adding to the supply of new build affordable
homes for social rent, this will continue with this Strategic
Housing Investment Plan. 
Whilst the focus will remain on adding to the supply of social
rented homes in Renfrewshire, there is also a recognised need for
alternative affordable housing options such as shared equity
provision and Mid-Market Rent on larger affordable housing sites. 
The inclusion of new affordable homes, other than homes for
social rent, will be considered on a site by site basis taking
account of project viability and the availability of grant funding
from the Scottish Government.

Page 13

Strategic Housing Investment Plan 2026 to 2031   9
PUBLIC
The delivery of new affordable homes on private sector sites will
continue through the application of Renfrewshire’s Affordable
Housing Policy included in LDP2. 
Williamsburgh Housing Association, social rented development, Cartha Crescent, Paisley 
Particular Housing Needs 
The Local Housing Strategy emphasises the importance of
providing homes that meet the particular needs of different
groups with a focus on enabling people to live independently for
as long as possible in their own homes and also in preventing
homelessness. 
In recent years, Link/C~urb Housing Association completed a
mixed general and particular needs social rented development in
Paisley Town Centre that included 20 amenity standard homes
and 5 fully wheelchair accessible homes. In March 2025, Loretto
Housing Association also completed 4 fully wheelchair accessible
homes as part of their East Lane development in Paisley. 
This Strategic Housing Investment Plan includes projects that will
continue to contribute to meeting identified particular needs in
Renfrewshire with mixed amenity housing and purpose built
particular needs homes expected to be included across projects
supported by grant funding. 
When planning new developments, early-stage discussions will
take place with Renfrewshire Health and Social Care Partnership
(HSCP) to ensure that projects are viable, sustainable and
capable of meetings tenants and residents’ needs.

Page 14

Strategic Housing Investment Plan 2026 to 2031   10
PUBLIC 
Link/C~urb Housing Association, social rented General and Particular Needs, Paisley Town Centre   
Wheelchair Accessible Housing 
When preparing proposals for new build developments, housing
providers will be required to design homes that are able to meet
occupants changing needs over time as well as the needs of an
ageing population by incorporating design features that promote
accessible and adaptable homes. 
Targets for the inclusion of wheelchair accessible homes as part
of new build developments have been agreed and are included
within the current Local Housing Strategy. 
The Local Housing Strategy requires that:
New residential proposals must provide a minimum 10% of all
dwellings designed to be easily adaptable for residents who are
wheelchair users; and 
5% of all new homes must be designed to wheelchair accessible
standards. 
Rapid Rehousing Transition Plans 
Renfrewshire Council’s Rapid Rehousing Transition Plan (RRTP)
details how those who are homeless will be provided with settled
accommodation more quickly; spend reduced time in temporary
accommodation and have more access to up-scaled support. 
The Strategic Housing Investment Plan aims to support the
delivery of homes to meet the requirements of different needs
groups, household types and sizes. 
The Council together with Renfrewshire Health and Social Care
Partnership employ the Housing First Initiative to support those
with multiple and complex needs,

Page 15

Strategic Housing Investment Plan 2026 to 2031   11
PUBLIC
Who are socially excluded and who have experienced repeat
homelessness, with the Housing First Initiative an integral part of
the Rapid Rehousing Transition Plan, delivered by Turning Point
Scotland’s Support Workers to provide tenancies, in conjunction
with wrap-around support packages and provide assistance to
access Health and Social Care Services. 
Within Renfrewshire, both the Council and its housing association
partners continue to prioritise lets to homeless households with
52% of all available Council social rented homes and 39% of all
available housing association homes let to homeless households
in 2024/25. This includes lets to both existing and new build social
rented housing with available properties allocated in line with
applicant housing need and the housing providers allocation
policy. 
Child Poverty  
New housing development has a key role in tackling child poverty
through supporting the delivery of a range of property types and
sizes that meet the needs of families, and the creation of high-
quality energy efficient homes in sustainable communities that
support health, wellbeing and educational attainment. 
This Strategic Housing Investment Plan aligns with the priority
actions of Renfrewshire’s Local Child Poverty Action Report which
aims to support the next generation to thrive within high quality
affordable and accessible housing. 
Early discussions with housing association partners ensure that
the housing mix proposed for each project takes account of
housing waiting lists with this information reflected in terms of
house sizes and any agreed property mix. 
This approach should ensure that smaller homes are included to
meet the housing needs of individuals and smaller households as
well as larger family homes that meet the needs of larger families
and households with children to help address the needs of low-
income families. 
It is recognised that a wide range of property types and sizes are
required to meet identified housing needs on new affordable
housing developments. As plans progress on individual sites and
it becomes clearer what individual sites can accommodate, the
importance of including larger family homes will be central to
discussion with affordable housing providers in receipt of Scottish
Government grant funding. This approach will support the aims
of Renfrewshire’s Local Child Poverty Action Plan.

Page 16

Strategic Housing Investment Plan 2026 to 2031   12
PUBLIC
Key Worker Housing 
Renfrewshire Council does not have a key worker policy in
relation to access to affordable housing and has no specific
identified housing need for key worker housing locally. Projects
delivered through the Strategic Housing Investment Plan process
are accessible to all households with homes allocated in line with
the developing landlords local allocation policy. 
Refugee Resettlement 
Renfrewshire Council continues to work with the Scottish
Government and Convention of Scottish Local Authorities
(COSLA) to determine what Renfrewshire may provide in terms of
housing stock to support resettlement and asylum dispersal
programmes. 
So far, most of the accommodation required has been smaller
with one or two bedroom properties being used due to the
arriving household size. 
Renfrewshire has continued to play its part in the national
response by providing ongoing support. The number of homes
required to support Renfrewshire’s contribution towards the
national resettlement scheme will be kept under review. 
Gypsy/Travellers Provision 
The Council continues to review the need to allocate land or
identity and progress appropriate projects to meet any identified
housing needs of the Gypsy/Traveller community in Renfrewshire
taking account of the Scottish Government’s Improving the lives
of Scotland’s Gypsy/Travellers 2 Action Plan 2024-2026 published
in September 2024. 
The Council notes the Scottish Government’s decision to manage
potential Gypsy/Traveller sites and associated funding allocations
alongside the existing Resource Planning Assumption model
traditionally used to support settled development. 
This approach will support longer term planning and delivery of
Gypsy/Traveller sites in Renfrewshire should a need be identified. 
At present, no projects are included within this plan. Should a
requirement for accommodation/sites be identified, future
updates of the Strategic Housing Investment Plan will include
details of these projects.

Page 17

Strategic Housing Investment Plan 2026 to 2031   13
PUBLIC
Travelling Showpeople Provision 
There are currently no permanent Travelling Showpeople sites in
Renfrewshire. Through delivery of the strategic priorities included
within the Local Housing Strategy 2023-2028 and the use of the
Scottish Governments Accommodation Needs Toolkit (when
available), the Council will identify if there is a need to allocate
land to meet the housing needs of Travelling Showpeople with
any identified need addressed through the Renfrewshire Local
Development Plan/Action Delivery Programme. 
Renfrewshire Council Regeneration and Renewal
Programme 
This plan continues to support the Council’s new build
programme following the completion of new Council homes in
Bishopton, Johnstone and at Ferguslie Park in Paisley. 
Over the period of the next Strategic Housing Investment Plan,
Renfrewshire Council will continue to invest in its own new build
social rented development programme to deliver high quality
energy efficient homes to replace existing low demand housing or
to add to the supply of Council housing with plans progressing to
deliver homes in identified regeneration areas. 
This Strategic Housing Investment Plan includes these new build
Council projects with Scottish Government grant funding
expected to be made available to supplement the Council’s own
investment in these new homes for social rent. 
As well as adding to the supply of new Council housing, the
Council will make best use of its existing housing stock through
targeted and enhanced investment – including works to the
external fabric of properties as well as environmental
improvements. 
More information on the Council’s Regeneration and Renewal
Programme can be found on the Council’s website by visiting: 
Housing regeneration in Renfrewshire – Renfrewshire Website 
Town Centre Living
As with previous Strategic Housing Investment Plans, investing in
town centre residential development remains a key objective of
this t Strategic Housing Investment Plan. 
Investment in affordable housing to support the wider
regeneration of our town centres helps deliver population
growth, improve the vitality and environment of town centres and
can help support the creation of sustainable communities.

Page 18

Strategic Housing Investment Plan 2026 to 2031   14
PUBLIC
Significant cross tenure new build development has taken place
in town centres in recent years. In preparing the Strategic Housing
Investment Plan there has been significant interest expressed by
Housing Association partners to deliver new affordable homes
primarily in and around Paisley Town Centre. 
A project line is included within Appendix 3 of this  Strategic
Housing Investment Plan in order to support further affordable
housing development in Paisley town centre. Provision is
included in the programme to deliver approximately 100 new
affordable homes in and around the town centre should funding
be confirmed by the Scottish Government. 
A number of development opportunities are currently being
reviewed in terms of their viability and deliverability with new
projects likely to be progressed over the next five-year period. 
Delivering New Affordable Homes in North and West
Renfrewshire 
Affordable housing development in the North and West
Renfrewshire villages can be challenging as most of the available
land is in private ownership. 
The Council recognises that there is an unmet demand and
limited supply of affordable housing in these areas. The Council
will continue to pursue all opportunities to increase the supply of
affordable housing in both North and West Renfrewshire, working
with housing association partners and private developers to
include social rented housing as either standalone developments
or as part of mixed tenure private sector developments.
Affordable housing provision within Dargavel Village will continue
with 138 affordable homes completed so far by the Council and
Loretto Housing Association for social rent. 
Loretto Housing Association are currently progressing a two stage
development of a further 62 social rented homes in partnership
with Dundas Homes. 
The first stage of development includes 46 homes which are due
to complete in March 2027 with a further 16 homes also to be
progressed at this location. 
Discussions are ongoing with Loretto Housing Association,
Sanctuary Scotland and private developers to deliver a further 43
homes for social rent within Dargavel Village across two sites.

Page 19

Strategic Housing Investment Plan 2026 to 2031   15
PUBLIC
In West Renfrewshire, three private sector sites that are allocated
for residential use in the Renfrewshire Local Development Plan
2021 (LDP) offer the potential to deliver new social rented homes
in Houston, Kilbarchan and Lochwinnoch through utilising the
LDP’s affordable housing policy, subject to planning approval.
The Council will continue to work with our housing association
partners to increase the supply of social rented housing in West
Renfrewshire, taking account of housing waiting list data and the
outputs from the Renfrewshire Housing Need and Demand study
prepared in support of the current Renfrewshire Local Housing
Strategy 2023-2028. 
Tackling the Climate Crisis in Renfrewshire 
Tackling the Climate Crisis continues to be a priority for
Renfrewshire Council with work progressing as part of
Renfrewshire’s Plan for Net Zero and Local Heat and Energy
Efficiency Strategy. 
It is acknowledged that the changing climate has a direct impact
on Renfrewshire’s housing and that some residents will be more
vulnerable to this than others. 
Both Renfrewshire Council and its housing association partners
are incorporating additional energy efficiency measures as part of
new build design which will actively target reduced carbon
emissions from new build development. 
Projects included within this Strategic Housing Investment Plan
aim to tackle fuel poverty by maximising opportunities for
innovative energy efficient development, with greener measures
included within new build developments. 
Bringing Empty Homes Back into use
The Council has a dedicated ‘More Homes Officer’ who works
with owners of long-term empty properties to provide advice and
assistance to support owners to bring long term empty properties
back into productive use. 
The Council’s More Homes Officer also manages the Councils buy
back and acquisitions scheme where properties that meet
strategic objectives may be purchased and added to the Council’s
lettable housing stock.

Page 20

Strategic Housing Investment Plan 2026 to 2031   16
PUBLIC
Over the last five years, the Council’s More Homes Officer has
successfully helped to bring more than 60 long term empty
homes back into the effective housing supply with these homes
adding to the supply of available homes in the affordable and
private sectors. 
Programme Management and Project
Prioritisation 
This Strategic Housing Investment Plan splits projects into three
groups: 
(i) ‘Core Projects’; 
(ii) ‘Shadow Projects’ and 
(iii) ‘Longer Term Projects’. 
Projects within each group are shown in Appendix 3. 
The methodology used to prioritise projects is based on the
potential availability of Scottish Government grant funding as
well as the developers’ ability to progress each project at key
milestones in term of site acquisition, design work, planning
approval, procurement and potential site start date. 
This approach supports the programming of individual projects in
terms of anticipated grant availability and the potential delivery
timescales. 
These projects together form the proposed Strategic Housing
Investment Plan with projects being delivered as funding
becomes available. 
Delivery timescales are dependent on future funding allocations
from the Scottish Government and the developer’s own capacity
to progress sites.   
Projects included within the ‘Core Projects’ group will be
progressed in the earlier years of the programme. 
Projects included within the ‘Shadow Projects’ group will be
progressed as ‘Core Projects’ complete or as any additional
funding becomes available or where the developing landlords has
the capacity to ‘front fund’ projects to allow projects to proceed
earlier than otherwise possible.

Page 21

Strategic Housing Investment Plan 2026 to 2031   17
PUBLIC
Projects included in the ‘Longer Term Projects’ group are
expected to progress over the longer term with grant funding only
likely to become available towards the end of or indeed beyond
the current five year Strategic Housing Investment Plan period. 
In terms of front funding, the Council or housing association
partner may initially fund project development costs from their
own resources, with grant being paid to developing organisation
at the first available opportunity as funding becomes available. 
The use of a three tier project priority approach supports the
effective management of available resources whilst permitting
some flexibility that assists in addressing any slippage of projects
in any given year. 
Projects in the ‘Shadow Projects’ group and in particular the
‘Longer Term Projects’ group may require extended lead in times
to allow for site investigation works, value engineering works, site
assembly or to arrange the necessary private finance to enable a
development to proceed. All of which influence how projects are
prioritised within the programme with all projects subject to
regular review. 
The Strategic Housing Investment Plan development programme
must be capable of adapting and responding to both delays in
the delivery of projects and new affordable housing development
opportunities to ensure that all funding available to Renfrewshire
can be fully utilised. 
This may result in existing project delivery timescales changing or
new opportunities being added to the programme between
annual Strategic Housing Investment Plan updates.   
Any additional projects brought forward must align with the
strategic priorities of the Local Housing Strategy with a clear
funding mechanism in place that does not impact other ‘Core
Projects’. 
Delivery 
Both the Council and its housing association partners will
continue to look for efficiencies in construction methods and
work with design teams to determine the suitability of non-
traditional construction methods for projects included within this
Strategic Housing Investment Plan.

Page 22

Strategic Housing Investment Plan 2026 to 2031   18
PUBLIC
The Council will continue to explore options for joint working
around innovative delivery mechanisms that support the delivery
of affordable homes throughout Renfrewshire. 
Projects included within the ‘core’ element of the Strategic
Housing Investment Plan are either currently progressing on site
or are due to start on site soon with site investigation works
already completed for these projects.   
Site investigation works for the majority of projects in the
‘shadow’ and ‘longer term’ programme have still to take place
with the results of these investigations informing project viability. 
Housing Infrastructure Fund 
The Housing Infrastructure Fund provides Councils and housing
association partners with additional grant to support the
unlocking of challenging sites where the scale and nature of
infrastructure costs would prevent these sites from being
progressed as part of the Strategic Housing Investment Plan. 
In recent years, a number of Renfrewshire projects have
successfully accessed the Housing Infrastructure Fund with
housing association partners continuing to look at options to bid
for support from the Housing Infrastructure Fund as and when
required. 
At present, no project developer within this Strategic Housing
Investment Plan is looking to access Housing Infrastructure Fund
support, however this may change as developments conduct
more detailed site investigations. 
Vacant and Derelict Land Investment Programme 
At present, no project within this Strategic Housing Investment
Plan is currently utilising or been identified to seek funding from
the Scottish Government’s Vacant and Derelict Land Investment
Programme. 
Monitoring Project Progress 
To monitor progress in delivering individual projects and ensure
that resources are managed effectively, a range of project
management activities are employed. This includes:  
• ongoing liaison between services within the Council and
between the Council and housing association partners on
specific projects; 
• quarterly tripartite meetings between the Council, individual
housing association partners and the Scottish Government;

Page 23

Strategic Housing Investment Plan 2026 to 2031   19
PUBLIC
• regular internal officer group meetings to review progress in
delivering the overall development programme; and,
• a monthly review of project progress with all developers of
affordable housing. 
Strategic Housing Investment Plan Appendices 
Appendix 1 details progress with projects currently on site as well
as proposals for future projects identified. 
Appendix 2 shows recent affordable housing completions with a
breakdown of property size delivered on each site. 
Appendix 3 lists projects that are currently progressing and/or
expected to require grant funding as part of the Strategic Housing
Investment Plan process. 
Equalities 
This Strategic Housing Investment Plan 2026-2031 includes
housing provision for a range of different needs groups including
housing for older people and those with physical disabilities. 
It has been informed by ongoing partnership working with the
Health and Social Care Partnership (HSCP) to ensure that projects
take account of opportunities to deliver housing that meets the
needs of a range of households with specific needs. 
In line with The Equality Act 2010 and the associated protected
characteristics, an Equality and Human Rights Impact Assessment
has been prepared alongside the preparation of this Strategic
Housing Investment Plan to identify the likely or actual effects of
it on people. 
The assessment includes identifying where there will be a positive
impact and further opportunities to promote equality. The
assessment did not identify any negative impacts on people in
relation to this Strategic Housing Investment Plan.

Page 24

20
PUBLIC 
Appendix 1: Renfrewshire Affordable Housing Project Updates 
1A: Projects completed in financial year 2024/25 
Development Units Status Comment
Napier Street, Linwood 51 Completed October
2024
51 social rented homes from Sanctuary Scotland Housing Association that add to
the affordable housing supply in Linwood. This project completed in October 2024.
Property sizes included 37 x 2 Bed, 14 x 3 Bed properties. 
East Lane, Paisley Town
Centre  48 Completed March 2025
48 social rented homes by Loretto Housing Association which add to the affordable
housing supply in central Paisley. 
Property sizes included 16 x 1 Bed, 32 x 2 Bed properties. 
Hawkhead, Paisley 5 Completed March 2025
5 New build terraced house acquisitions by Link/C~urb Housing Association as part
of a large mixed tenure development. These complement 30 new social rented flats
being developed at this location by Link Group. 
Property sizes included 5 x 3 Bed properties.

Page 25

Strategic Housing Investment Plan 2026 to 2031   21
PUBLIC 
1B: Projects completed in financial year 2025/26, currently on site or due to start on site 
Development Units Status Comment
Hawkhead, Paisley 30 Completed May 2025
30 social rented homes by Link/ C~urb Housing Association which add to the affordable
housing supply in Paisley. 
Property sizes include 30 x 2 Bed properties. 
Paisley West End,
Sutherland Street 35 Completed June 2025
35 social rented homes Sanctuary Scotland which add to the affordable housing supply
in central Paisley.
Property sizes include 28 x 2 Bed, 7 x 3 Bed properties. 
Cartha Crescent,
Paisley 33 Completed July 2025
33 social rented homes by Williamsburgh Housing Association which add to the
affordable housing supply in central Paisley. 
Property sizes include 12 x 2 Bed, 21 x 3 Bed properties. 
Johnstone Castle
Phase II 68 On site, due to
complete June 2026
Link/C~urb Housing Association are onsite delivering the second phase of affordable
housing in Johnstone Castle. This development will provide 68 homes for social rent as
well as infrastructure and green spaces. 
Property sizes include 40 x 2 Bed, 28 x 3 Bed properties. 
Orchard Street,
Paisley   50
On site, due to
complete September
2026
Work is progressing on the Comprehensive Tenement Improvement (CTI) project at
Orchard Street/Causeyside Street, Paisley following 5 blocks of flats being designated as
a Housing Renewal Area (HRA) in March 2017. The overall development is expected to
complete in September 2026. 
Property sizes include 37 x1 bed, 13 x 2 bed properties 
Bishopton, Phase 3A 46 On site, due to
complete March 2027
Loretto Housing Association are now on site developing 46 new homes for social rent
that will add to the affordable housing supply in Dargavel Village, Bishopton.

Page 26

Strategic Housing Investment Plan 2026 to 2031   22
PUBLIC
Development Units Status Comment
This site is expected to provide 62 new homes for social rent across two phases (3A & 3B)
with Phase 3B expected to include 16 additional homes for social rent following
completion the 46 new homes that comprise Phase 3A. 
Property sizes include 12 X 1 bed, 27 x 2 bed, 7 x 3 bed properties
Gallowhill, Paisley 65
On site, due to
complete December
2026
Renfrewshire Council commenced on site in August 2025 and developing 65 new
Council homes for social rent that will add to the affordable housing supply in the
Gallowhill area. The overall development is expected to complete in December 2026. 
Property sizes include 9 x 1 bed, 23 x 2 bed, 26 x 3 bed, 4 x 4 bed, 3 x 5 bed properties
Howwood Road,
Johnstone (Site 1 of 2) 70 Off site, Due to start on
site in November 2025
Renfrewshire Council regeneration area. Plans are being progressed to deliver 70 new
Council homes in this first phase of development in the Howwood Road Area Johnstone
with a site start expected later in 2025.
Property sizes include 11 x 1 bed, 29 x 2 bed, 19 x 3 bed, 11 x 4 bed properties
Bishopton, Phase 4 20 Off site, Due to start on
site in September 2025
Loretto Housing Association are progressing plans for 20 new social rented homes that
will add to the affordable housing supply in Dargavel Village, Bishopton. 
Property sizes include 20 x 2 bed properties

Page 27

Strategic Housing Investment Plan 2026 to 2031   23
PUBLIC 
1C: Projects expected to start on site in 2026/27 or later or when a projected site start date has still to be confirmed 
Development Units Status Comment
West End - Remaining Sites 120 Off site, Start date tbc
Sanctuary Scotland are progressing plans for approximately 120 affordable new
homes developed as part of the regeneration of Paisley’s West End.
Property sizes still to be confirmed. 
Bishopton, Phase 3B  16 Off site, Due to start on
site around January 2027
Loretto Housing Association will progress development of 16 new homes for
social rent following the completion of Bishopton Phase 3A which will provide an
initial 46 new homes for social rent.
Property sizes still to be confirmed. 
Bishopton, Phase 5 23 Off site, Start date tbc
Sanctuary Scotland Housing Association are progressing plans for 23 new social
rented homes that will add to the affordable housing supply in Dargavel Village,
Bishopton.
Property sizes still to be confirmed. 
Springbank, Paisley (Phase 1
of 2)  65 Off site, Due to start on
site around January 2027 
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 65 new Council homes in this first phase of development in the
Springbank Road Area of Paisley. 
Property sizes still to be confirmed. 
Foxbar Rivers, Paisley 45 Off site, Due to start on
site around January 2027
This social rented development of around 45 homes by Renfrewshire Council will
add to the affordable housing supply in the Foxbar area of Paisley and bring
vacant sites back in to use. 
Property sizes still to be confirmed.

Page 28

Strategic Housing Investment Plan 2026 to 2031   24
PUBLIC
Development Units Status Comment
Broomlands & Carbrook
Street, Paisley 43 Off site, Due to start on
site around January 2027
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 43 new Council homes in Paisley’s Broomlands and Carbrook Street area. 
Property sizes still to be confirmed. 
Thrushcraigs, Paisley 50 Off site, Due to start on
site around July 2027
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 50 new Council homes in the Thrushcraigs Area of Paisley. 
Property sizes still to be confirmed. 
Howwood Road, Johnstone
(Site 2 of 2) 60 Off site, Due to start on
site around January 2028
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 60 new Council homes in this second phase of development in the
Howwood Road Area of Johnstone. 
Property sizes still to be confirmed. 
West Renfrewshire Villages  62 Off site, Start date tbc
Three potential sites identified for progression by Housing Association partners
for approximately 62 social rented homes as part of mixed tenure developments
proposed in West Renfrewshire. 
Property sizes still to be confirmed. 
Flourish Road, Erskine, Older
Persons Housing
Reprovisioning  
18
Off site, Due to start on
site around February
2027 
Bridgewater Housing Association are progressing plans for a new purpose built
older persons housing development of around 18 units that will replace existing
scattered older persons housing provision across Erskine. 
Property sizes still to be confirmed. 
Gibson Crescent, Johnstone 28 Off site, Start date tbc
Options are being explored for this social rented development of around 28
social rented homes by Williamsburgh Housing Association in Johnstone. 
Property sizes still to be confirmed.

Page 29

Strategic Housing Investment Plan 2026 to 2031   25
PUBLIC
Development Units Status Comment
Springbank, Paisley (Phase II)  35 Off site, Due to start on
site around January 2030
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 35 new Council homes in this second phase of development in the
Springbank Road Area of Paisley. 
Property sizes still to be confirmed. 
Stirling Drive, Linwood  65
Off site, site start 2027
subject to future grant
application being
approved by SG. 
Options are being explored for this social rented development of around 65
homes by Linstone Housing Association that will add to the affordable housing
supply in Linwood. 
Property sizes still to be confirmed. 
Ryefield, Johnstone  36
Off site, site start 2029
subject to future grant
application being
approved by SG. 
Options are being explored for this social rented development of approximately
36 homes by Linstone Housing Association in Johnstone. 
Property sizes still to be confirmed. 
MacDowall Street, Johnstone  35 Off site, Start date tbc
Options are being explored to identify an affordable housing provider to develop
this gap site for affordable housing. 
Property sizes still to be confirmed. 
Rannoch Road, Johnstone 30 Off site, Start date tbc
Options are being explored for this social rented development of around 30
homes by Loretto Housing Association in Johnstone. 
Property sizes still to be confirmed.
Garthland Lane, Paisley 32 Off site, Start date tbc
This social rented development of around 32 homes by Renfrewshire Council will
add to the affordable housing supply in central Paisley.
Property sizes still to be confirmed.

Page 30

Strategic Housing Investment Plan 2026 to 2031   26
PUBLIC
Development Units Status Comment
Foxbar Rivers, Paisley 45 Off site, Start date tbc
This social rented development of around 45 homes by Paisley Housing
Association will add to the affordable housing supply in the Foxbar area of
Paisley and bring vacant sites back in to use.
Property sizes still to be confirmed. 
Westburn
Avenue/Blackstoun Road,
Ferguslie Park, Paisley
22 Off site, Start date tbc
This social rented development of around 22 homes by a developer still to be
identified will add to the affordable housing supply in the Ferguslie Park area of
Paisley and bring a vacant site back in to use. 
Property sizes still to be confirmed. 
East Lane, Paisley (Site 2 of 2) 30 Off site, Start date tbc
Site identified for longer term development. 
Property sizes still to be confirmed. 
Supported Housing, Paisley
(Site tbc) 14 Off site, Start date tbc
Efforts will continue to identify a potential site for supported housing in Paisley
Town Centre. 
Property sizes still to be confirmed.
Paisley Town Centre
(including edge of centre
locations, future sites tbi)
100 Off site, Start date tbc
A number of opportunities in and around the town centre are currently being
reviewed in terms of their viability and deliverability with new projects likely to be
progressed over the next five-year period
West Renfrewshire Villages  tbc Off site, Start date tbc Efforts will continue to identify additional potential site(s) for affordable housing
in West Renfrewshire to promote mixed tenure communities. 
North Renfrewshire Villages  tbc Off site, Start date tbc Efforts will continue to identify additional potential site(s) for affordable housing
in North Renfrewshire to promote mixed tenure communities.

Page 31

Strategic Housing Investment Plan 2026 to 2031   27
PUBLIC
Development Units Status Comment
Neilston Road, Paisley 8 Off site, Start date tbc.
Due to complete 2026/27.
Paisley Housing Association will deliver 8 units at benchmark grant rate. 
Property sizes still to be confirmed.
Local Development Plan Affordable Housing Policy Future
Requirements
Subject to the availability of Scottish Government grant, this Strategic Housing
Investment Plan will support the development of new affordable homes within
private sector sites as part of Renfrewshire’s Affordable Housing Policy.

Page 32

Strategic Housing Investment Plan 2026 to 2031   28
PUBLIC
Completions between 2020 and 2025 & estimated completions 2025/26 Appendix 2
2020/21       
Link/C~urb Smithhills Street, Paisley 26x 2 Bed 26  
Renfrewshire Council Bishopton Phase I 10x 1 Bed, 34x 2 Bed, 34x 3 Bed, 2x 4+ Beds 80  
Williamsburgh HA Milliken Road, Kilbarchan 14x 1 Bed, 4x 2 Bed 18 124
2021/22     
Renfrewshire Council Johnstone Castle, Johnstone 4x 1 Bed, 67x2 Bed, 20x 3 Bed, 4x 4+ Beds 95  
Link/C~urb Amochrie Road, Foxbar, Paisley 34x 2 Bed, 2x 3 Bed 36  
Link/C~urb Thrushcraigs Phase II (St Ninians), Paisley 12x 2 Bed, 11x 3 Bed  23  
Paisley HA Westerfield House, Paisley 16x 1 Bed  16 170
2022/23     
Sanctuary/Paisley HA Glenburn, Paisley 8x 1 Bed, 73x 2 Bed, 50x 3 Bed  131  
Link/C~urb Millarston, Paisley 16x 1 Bed, 62x 2 Bed, 2x 3 Bed, 19x 4+ Beds 99  
Renfrewshire Council Auchengreoch Road, Johnstone 8x 1 Bed, 17x 2 Bed, 12x 3 Bed, 2x 4+ Beds 39  
Loretto Bishopton Phase II 12x 1 Bed, 14x 2 Bed, 32x 3 Bed 58  
Williamsburgh HA Albert Road, Renfrew 13x 2 Bed, 29x 3 Bed  42 369
2023/24    
Renfrewshire Council Ferguslie Park, Paisley 22x 1 Bed, 67x 2 Bed, 10x 3 Bed, 2x 4+ Beds 101 
Link/C~urb Abbey Quarter Phase 4 (AQP4), Paisley 10x 1 Bed, 71x 2 Bed  81 
Link/C~urb Woodend House, Houston  14x 2 Bed 14 196
2024/25    
Sanctuary Napier Street, Linwood  37x 2 Bed, 14x 3 Bed  51 
Loretto East Lane, Paisley 16x 1 Bed, 28x 2 Bed  48 
Link/C~urb Hawkhead, Paisley 5x 3 Bed  5 104    
963
2025/2026 - Estimated Completions  
Link/C~urb Hawkhead, Paisley 30 x 2 Bed 30  
Sanctuary Sutherland Street, Paisley  28x 2 Bed, 7x 3 Bed  35  
Williamsburgh HA Cartha Crescent, Paisley 12x 2 Bed, 21x 3 Bed 33 98

Page 33

29
PUBLIC 
Appendix 3      £ Million   
Homes 
Total
Est
Grant
Req
(£M) 
Est Spend
by of End
March
2026 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req
Core Projects     (Yr 1)
2026/27
(Yr 2)
2027/28
(Yrs 3-5)
2028/29-
2030/31
(Yrs 6+)
2031/32 &
Beyond
Johnstone Castle Phase II*  68  £1.864  £1.864  N/A N/A N/A N/A
Cartha Crescent   33  £3.233  £3.233  £0.000 £0.000 £0.000 £0.000
Orchard St/Causeyside St (HRA)  50  £5.003  £5.003  £0.000 £0.000 £0.000 £0.000
Bishopton Phase 3A  46  £5.475  £5.475  £0.000 £0.000 £0.000 £0.000
Bishopton Phase 4  20  £1.915  £1.915  £0.000 £0.000 £0.000 £0.000
Gallowhill, Paisley  65  £9.634  £4.227  £5.407 £0.000 £0.000 £0.000
Howwood Road, Johnstone (Site 1 of 2)  70  £10.431  £3.106  £7.325 £0.000 £0.000 £0.000
West End - Remaining Sites  120  £11.489  £6.341  £1.764 £1.764 £1.620 £0.000
Bishopton Phase 3B  16  £1.532  £0.000  £1.532 £0.000 £0.000 £0.000
Bishopton Phase 5  23  £2.500  £0.000  £2.500 £0.000 £0.000 £0.000
Neilston Road, Paisley  8  £0.770  £0.000  £0.770 £0.000 £0.000 £0.000
Open Market Acquisitions   tbc  £1.575  £1.575  tbc tbc tbc tbc
Affordable Housing Policy Future Reqs  tbc  tbc  tbc  tbc tbc tbc tbc
*Funded without Grant from RPA   519  £55.421  £32.739  £19.298 £1.764 £1.620 £0.000

Page 34

Strategic Housing Investment Plan 2026 to 2031   30
PUBLIC 
Homes 
Total
Est
Grant
Req
(£M) 
Est Spend
by of End
March
2026 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req
Shadow Projects     (Yr 1)
2026/27
(Yr 2)
2027/28
(Yrs 3-5)
2028/29-
2030/31
(Yrs 6+)
2031/32 &
Beyond
Springbank, Paisley (Phase 1 of 2)   65  £5.706  £1.194  £0.000 £0.500 £4.012 £0.000
Foxbar Rivers, Paisley  45  £3.949  £0.050  £0.000 £0.500 £3.399 £0.000
Broomlands & Carbrook Street, Paisley  43  £6.130  £0.412  £0.000 £0.000 £5.718 £0.000
Thrushcraigs, Paisley  50  £4.388  £0.119  £0.000 £0.500 £3.769 £0.000
Howwood Road, Johnstone (Site 2 of 2)  60  £5.266  £0.444  £0.000 £0.500 £4.322 £0.000
West Renfrewshire Villages (3 sites)   62  £5.936  £0.000  £0.000 £2.000 £3.936 £0.000
Older Persons Housing, Erskine  18  £2.455  £0.000  £0.455 £2.000 £0.000 £0.000
Gibson Crescent, Johnstone   28  £2.681  £0.000  £0.000 £0.000 £2.681 £0.000
Springbank, Paisley (Phase II)   35  £3.072  £0.351  £0.000 £0.000 £2.722 £0.000
Rannoch Road, Johnstone  30  £2.872  £0.000  £0.000 £2.000 £0.872 £0.000
Paisley Town Centre  - sites tbc  100  £9.580  £0.000  £0.000 £3.000 £6.580 £0.000
Stirling Drive, Linwood   65  £10.818  £0.859  £0.000 £5.000 £4.959 £0.000
Ryefield, Johnstone   36  £5.983  £0.150  £0.000 £0.000 £5.833 £0.000  
637  £68.836  £3.579  £0.455 £16.000 £48.803 £0.000

Page 35

Strategic Housing Investment Plan 2026 to 2031   31
PUBLIC 
Homes 
Total Est
Grant
Req
(£M) 
Est Spend
by of End
March
2026 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req
Longer Term Projects     (Yr 1)
2026/27
(Yr 2)
2027/28
(Yrs 3-5)
2028/29-
2030/31
(Yrs 6+)
2031/32 &
Beyond
Foxbar Rivers, Paisley  45  £4.308  £0.000  £0.000 £0.000 £4.308 £0.000
MacDowall Street, Johnstone   35  £3.351  £0.000  £0.000 £0.000 £3.351 £0.000
Garthland Lane, Paisley  32  £3.033  £0.225  £0.000 £0.000 £2.808 £0.000
Westburn Avenue, Ferguslie Park, Paisley  22  £1.931  £0.143  £0.000 £0.000 £0.000 £1.788
East Lane, Paisley (Site 2 of 2)  30  £2.872  £0.000  £0.000 £0.000 £0.000 £2.872
Supported Housing, Paisley (Site tbc)  14  £1.340  £0.000  £0.000 £0.000 £1.340 £0.000
West Renfrewshire Villages Opportunities  tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc
North Renfrewshire Villages Opportunities    tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc  
178  £16.835  £0.368  £0.000 £0.000 £11.807 £4.660              
1334  £141.092  £36.686  £19.753 £17.764 £62.230 £4.660

Page 36

32
PUBLIC 
Environment, Housing and Infrastructure
Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA1 1BR

Page 37

PUBLIC
Strategic Housing Investment Plan 2026-2031 Consultation Responses 
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
Houston Community
Council
Houston Community Council feels that the Strategic
Housing Investment Plan requires to take far greater
cognisance of: 
1. Specific demographic needs of communities
when determining housing. 
2. Consider needs of ageing population. 
3. Make provision for private sector downsizer
homes within West Renfrewshire Villages. 
4. Consider measures to enable older residents in
private and rented accommodation to move to
smaller homes to free up larger homes by
building affordable homes for them to downsize
to. 
5. Support reuse and refurbishment of existing
stock particularly for families by supporting
downsizing. 
6. Agree with town centre living and brownfield
development. All new developments should give
greater consideration to active travel
connectivity and access to local amenities. 
Officers from Renfrewshire Council will arrange a meeting with
Houston Community Council to discuss their comments. 
The Community Council’s comments are welcomed however
they relate more to the Local Housing Strategy or Local
Development Plan process than the Strategic Housing
Investment Plan, in that they are mostly planning matters.
Therefore we will consider these up in future reviews of the Local
Housing Strategy and Local Development Plan process.

Page 38

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
The Community Council believe that the
Council’s support for edge of centre retail
development undermines this. 
7. The Strategic Housing Investment Plan requires
to be driven by needs rather than securing
numbers. Requires to move to a local place
making agenda and cognisance of the
demographics of individual communities to
create ‘whole life towns and villages’. 
8. Recognition to be given to the specific spatial
qualities of communities with less generic
volume housing design and a Places for People
place led approach. 
9. Significant planning applications over 50 units
should be accompanied by an EIA. 
Paisley Housing
Association
1. Role of local providers: 
Paisley Housing Association feel the Strategic
Housing Investment Plan is weighted towards
national Registered Social Landlords and
Renfrewshire Council to the detriment of local
Registered Social Landlords. They feel that the
Strategic Housing Investment Plan should have
explicitly recognise the role of local Registered
Social Landlords and given a stronger role in
project delivery. 
1. There are a number of projects in the programme for both
local and national Registered Social Landlords. The focus
of development projects in the Strategic Housing
Investment Plan is to meet housing needs and the
priorities of the Local Housing Strategy taking into
account the deliverability of projects.

Page 39

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan 
2. Section 75 sites:
Paisley Housing Association feel the Strategic
Housing Investment Plan does not give enough
detail to Section 75 sites and requires a clear
approach to be set out and showing how they will
be programmed and allocated. The Association
want to see more explicit detail in the Strategic
Housing Investment Plan. 
Paisley Housing Association wish the Strategic
Housing Investment Plan to set out a pipeline of
anticipated Section 75 sites linked to the Local
Development Plan and introduce a transparent
process for allocating these sites to Registered
Social Landlord partners ensuring local
Registered Social Landlords are prioritised. 
3. Programme balance – core, shadow and
longer term projects: 
Paisley Housing Association feels that the
Strategic Housing Investment Plan is heavily
weighted towards core projects that are already
committed, with delivery dominated by national
Registered Social Landlords and Renfrewshire
Council sites and that this structure leaves little
space for new local projects to feature in the
early years of the programme. 
2. The Strategic Housing Investment Plan refers to the
opportunity provided by Section 75 agreements to deliver
affordable homes on larger private sites. We note Paisley
Housing Association’s comments, however Renfrewshire
Council are not in the position to identify a pipeline of
future Section 75 sites until they have been through the
planning process. Through the planning process the
Council will determine the appropriate provision of
affordable housing on a site-by-site basis in accordance
with the Local Development Plan. 
3. The development programme is based around three time
periods that reflects the anticipated availability of
funding, project delivery and current status of projects.
The Strategic Housing Investment Plan programme
includes a degree of over-programming to ensure
Renfrewshire Council can maximise grant spend
wherever possible.

Page 40

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
Paisley Housing Association are concerned that
this approach risks locking out deliverable local
projects and fails to make full use of the capacity
of community based providers and heightens the
risk of grant underspend if core projects slip. 
Paisley Housing Association recommend the
Strategic Housing Investment Plan introduces a
formal mechanism that allows deliverable local
Registered Social Landlord projects to be
promoted to the core if: 
* Other core projects are delayed
*Additional funding becomes available
*A local provider can evidence readiness to         
process more quickly 
4. Funding certainty and benchmarks:
Paisley Housing Association acknowledge the
single year Resource Planning Assumptions and
uncertainty around this. Paisley Housing
Association state that if funding is constrained in
future years that the Strategic Housing
Investment Plan should explicitly prioritise local
providers. 
In relation to benchmark rates, Paisley Housing
Association acknowledges that these are set by
the Scottish Government. 
4. Projects within the Strategic Housing Investment Plan are
programmed at benchmark rates until the point when an
offer of grant is issued by the Scottish Government. The
Council do not decide the level of grant that will be
provided to support the delivery of projects. Above
benchmark rates may be provided by the Scottish
Government to deliver specific quality and design
features, however, it is up to the Registered Social
Landlord to submit detailed costs with their application
of grant to the Scottish Government and the Government
will decide on the level of grant that will be provided
following a value for money assessment.

Page 41

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
However they note that the draft Strategic
Housing Investment Plan states that flexibility is
available for higher grant support where justified.
Paisley Housing Association wants Renfrewshire
Council to strengthen the Strategic Housing
Investment Plan by being more transparent
about how the flexibility will be applied in
practice. 
5. Town centre living and regeneration: 
Paisley Housing Association reference the line in
the Strategic Housing Investment Plan for 100
affordable homes in Paisley Town Centre and
that no delivery partner is noted. Paisley Housing
Association wish to be considered for the
delivery of these homes and feel that it should be
a local provider that takes this forward. 
The Scottish Government require that any site that is
being delivered as part of a Section 75 legal agreement on
a larger private housing site must be delivered at
benchmark rates. 
5. In preparing the draft Strategic Housing Investment Plan,
all Registered Social Landlords were offered the
opportunity to submit proposed sites to the Council. A
number of proposals have been submitted for Paisley
Town Centre. 
A project line is included within Appendix 3 of the
Strategic Housing Investment Plan in order to support
further affordable housing development in Paisley town
centre. Provision is included in the programme to deliver
approximately 100 new affordable homes in and around
the town centre should funding be confirmed by the
Scottish Government. 
A number of development opportunities are currently
being reviewed in terms of their viability and deliverability
with new projects likely to be progressed over the next
five-year period.

Page 42

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
6. Neilston Road, Paisley – omission from the
draft Strategic Housing Investment Plan:
Paisley Housing Association state that they are
extremely concerned that this site has been left
out of the draft Strategic Housing Investment
Plan.  They state that their site is ‘oven ready’ and
aligns with the Strategic Housing Investment
Plan’s priority for town centre and edge of centre
regeneration. Paisley Housing Association are
unhappy that they have worked with the
developer and kept Renfrewshire Council
updated on progress over recent months. Paisley
Housing Association wish this site to be added to
the Strategic Housing Investment Plan. 
7. North and West Renfrewshire villages: 
Paisley Housing Association note that the
Strategic Housing Investment Plan
acknowledges unmet need in North and West
Renfrewshire villages but offers little detail on
how this will be addressed. They state that whilst
larger Registered Social Landlords may prioritise
major urban sites, smaller scale village
developments are often overlooked despite clear
housing need and that Paisley Housing
Association are well placed to contribute to this
agenda. 
6. Following discussion with Paisley Housing Association
regarding this site since the draft Strategic Housing
Investment Plan was prepared, the Council has now
included the site at 123 Neilston Road, Paisley in the
Strategic Housing Investment Plan programme for 8 units
for an anticipated 2026/27 delivery. 
7. A number of sites are identified within North Renfrewshire
and social rented housing is being delivered in this area
via the Strategic Housing Investment Plan. The Strategic
Housing Investment Plan also includes funding to deliver
future affordable housing projects in West Renfrewshire
but these sites will only be identified following the
outcome of the planning process, should planning
permission be granted. 
Renfrewshire Council are continuing to look at any other
opportunities in West Renfrewshire.  We would also
welcome any Registered Social Landlord who wish take a
proactive role in enabling more affordable housing
delivery in these locations.

Page 43

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
Paisley Housing Association state that they
believe the Strategic Housing Investment Plan
should set out a clear pathway for enabling local
associations to play a more proactive role in
delivering affordable sites in these locations. 
8. Rental off the shelf (ROTS) – strategy and
refurbishment funding: 
Paisley Housing Association acknowledge the
funding for Rental Off the Shelf and National
Acquisitions Fund but state the delivery is
currently ad-hoc. They feel that given the volume
of vacant homes in Paisley Town Centre and
surrounding areas that the Strategic Housing
Investment Plan should establish a clear,
strategy led Rental Off the Shelf programme with
priority given to local Registered Social
Landlords. 
Paisley Housing Association state that the Rental
Off the Shelf budgets must cover acquisition and
also essential refurbishment costs required to
properties that typically require investment
before they can be relet to the Scottish Housing
Quality Standard and their letting standard. 
However we note that no opportunities were identified in
the recent call for sites process that was asked of all
Registered Social Landlord in Renfrewshire as part of the
Strategic Housing Investment Plan consultation. 
No changes are required to the Strategic Housing
Investment Plan to address comments. 
8. Funding is currently allocated within the programme to
support the delivery of Rental Off the Shelf. Should future
funding allocations be made available by the Scottish
Government, we will consider with all Registered Social
Landlords operating within Renfrewshire whether a
strategy or guiding criteria in terms of need, is required to
support the delivery of the Strategic Housing Investment
Plan. At present we do not intend to change the Strategic
Housing Investment Plan.

Page 44

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
Paisley Housing Association recommend that
Rental Off the Shelf is fully integrated with the
Council’s empty homes and buy-back work and
subject to quarterly review alongside Strategic
Housing Investment Plan delivery, ensuring ready
acquisitions can backfill any core project
slippage and project grant spend. 
9. Strategic Housing Investment Plan and
monitoring: 
Paisley Housing Association note the monitoring
arrangements in place but feel that this
approach risks excluding local providers unless
they already have a project in the programme. 
Paisley Housing Association state that to ensure
the Strategic Housing Investment Plan remains
flexible and inclusive that they believe that there
should be a more structured role for local
Registered Social Landlords in programme
monitoring and pipeline development. This
would allow potential new opportunities to be
identified early, help safeguard grant spend if
core projects slip and ensure that delivery is not
concentrated in the hands of a small number of
national providers. 
9. Renfrewshire Council continue to work closely with the
Scottish Government and Registered Social Landlords in
the delivery of the Strategic Housing Investment Plan and
the delivery programme. 
This includes quarterly tripartite meetings with
developing partners, the Scottish Government and
Renfrewshire Council to monitor progress and monthly
updates on individual projects. In addition, there are
opportunities for Housing Associations to engage at the
Housing Provider Forums where the Strategic Housing
Investment Plan is a standing agenda item. 
Council officers met with Paisley Housing Association
during the consultation period of the draft Strategic
Housing Investment Plan and on 08/10/25 to discuss their
comments and liaison going forward. The Council
welcome Paisley HA wanting to take a more prominent
role in the delivery of social housing across Renfrewshire.

Page 45

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
Paisley Housing Association states they are
committed to playing a constructive role in this
process and would welcome greater involvement
in programme oversight. 
CALA Homes CALA are progressing the site and planning application
for Lochwinnoch, Burnfoot Road is currently subject to a
live application 24/0892/PP.  The nominated RSL is Link
HA. A site start is anticipated in Summer 2026, with first
private units in late summer/autumn 2027 and all the
affordable homes delivered in 3 phases in early 2028. 
CALA purchased the site in Erskine, Sandielands Road in
July 2025. There is currently a live application
22/0178/PP going through the system, targeting the
November 2025 Board. CALA are actively engaging with
Bridgewater HA to deliver 18 older person homes for
social rent.  This would allow a spring 2026 site start,
with first private units around easter 2027 and the
affordable delivered over two phases from autumn
2027. 
Provision has been included within the Strategic Housing
Investment Plan programme for sites within West Renfrewshire.
Should the site at Burnfoot Road be granted planning consent it
will be identified within the programme. 
The site at Sandielands Road (Northbar Phase 2), is included
within the Strategic Housing Investment Plan programme.
Linstone Housing
Association
Linstone Housing Association request clarification on
the following: 
• Stirling Drive: This is listed as “TBC” for proposed
start date. 
We welcome the update from Linstone Housing Association and
have amended as requested the previous timescales provided by
Linstone Housing Association for the delivery of sites at Stirling
Drive, Linwood and Ryefield, Johnstone. 
The Council have updated the Strategic Housing Investment Plan
to identify anticipated site start for Stirling Drive to 2027 subject
to a future application of grant being approved by the Scottish
Government.

Page 46

PUBLIC
Respondent Summary of representation Renfrewshire Council Response/Changes required to
Strategic Housing Investment Plan
We are actively in the process of acquiring the
additional land from Renfrewshire Council this
financial year, with a view to commencing on site
in 2027 pending some final clarifications. Can
you clarify why this date has been omitted?
• Ryefield: We expect to commence on site in 2029
as per previous update, yet the draft shows
“TBC.”
• Station Road: The project has been removed
entirely from the draft. Please note that
Springfield submitted a planning pre application
enquiry, and the project remains very much on
the agenda for the SHIP period. 
The Council have updated the SHIP to an anticipated site start for
Ryefield to 2029 subject to a future application of grant being
approved by the Scottish Government. 
The Station Road site is not currently within Strategic Housing
Investment Plan programme, however this will be revised should
planning permission be obtained for the site. 
Council officers met Linstone Housing Association on 16/10/25
to discuss their comments and updated timescales for their
projects.