SIP Covering Report October 2025 - Report

Renfrewshire Council · 28 October 2025
Back to Communities and Housing Policy Board — 28 October 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC  
___________________________________________________________________ 
To:    Communities and Housing Policy Board 
On:    28 October 2025
___________________________________________________________________ 
Report by:  Director of Environment, Housing, and Infrastructure  
___________________________________________________________________ 
Heading:  Environment, Housing, and Infrastructure – Service Improvement
Plan 2025-28 Mid-Year Monitoring Report 
___________________________________________________________________ 
1. Summary 
1.1 The Environment, Housing and Infrastructure Service Improvement Plan 2025-
2028 was approved by the Communities and Housing Policy Board on 13 May
2025. The plan sets out the priorities for the development of the service over a
three-year period. 
1.2 The Service Improvement Plan is part of a suite of documents which describe
the strategic direction of the Service and the Council, and also includes the
Council Plan, Community Plan, Risk Management Plan and the Workforce Plan. 
1.3 The Service Improvement Plan sets out the actions which will ensure continuous
improvement across the service and the performance indicators which ensure
the impact can be measured. These reflect the priority themes of the new
Council Plan which was approved by Council on 29 September 2022. 
1.4 This report contains details of Environment, Housing and Infrastructure
performance and achievements over the period 1 April 2025 to 30 September
2025. The main purpose of the report is to provide: 
• details of the key achievements of the service over the period. 
• a progress update on implementing the action plan linked to the 2025-28
Service Improvement Plan. 
• an assessment of performance in relation to the service scorecard of core
performance indicators; and 
• an overview of priorities for the service over the next six months. 
1.5 Over the past six months, the service has made good progress in delivering
positive outcomes for Renfrewshire and its residents.

Page 2

PUBLIC 
1.6 To complement the six-monthly update on the Service Improvement Plan, a
Service Update report will be presented to each cycle of the Communities and
Housing Policy Board. This report will provide an overview of key service
activities, an operational performance update on the services and key projects
and updates on any other relevant changes to service areas covered within the
remit of the Board. 
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Communities and Housing Policy Board: 
2.1 Note the contents of this report, including updated performance information and
progress to date on delivering the actions contained within the Environment,
Housing, and Infrastructure - Service Improvement Plan.  
_________________________________________________________ 
3. Background 
3.1 The Service Improvement Plan is a comprehensive statement of the outcomes
the service aims to achieve, and the actions it will take to achieve these. It fits
within the wider planning framework of the Council by taking account of
Community Planning themes and Council priorities as set out in the new Council
Plan. It enables elected members to have oversight of developments within the
service and to consider and develop policy options which reflect customer need
and resource availability. 
The Service Improvement Plan also provides a mechanism by which elected
members can evaluate the performance of the service. The appendix to the plan
contains an action plan and performance indicators against which progress can
be measured. This mid-year monitoring report provides an update on progress
against the 2025-2028 Plan. 
3.2 Section 4 of this report gives details of service activity and achievements over
the period 1 April 2025 to 30 September 2025. Section 5 discusses actions
delayed or cancelled since the Service Improvement Plan was approved. Section
6 provides a narrative on performance against the scorecard included as
appendix 1, section 7 highlights the main priorities of the service over the next
six months. 
3.3 An outturn report detailing full-year performance will be brought before this board
in spring 2026. 
___________________________________________________________________ 
4. Service Update and Key Achievements 1 April 2025 to 30 September 2025   
4.1 Housing Services 
• Positive progress is being made across all areas of the Housing-led
Regeneration and Renewal Programme within the agreed timeline for
works scheduled in year 4 of this 10-year programme.

Page 3

PUBLIC
• The acquisition and rehousing strategy is performing as planned and
various phases of demolition are being taken forward as blocks become
fully council owned and vacant.   
• The percentage of stock meeting SHQS has increased significantly to
80.02% in 2024/25 from 68.6% in 2023/24. 
• New rent charging policy for temporary accommodation which was
approved by Policy Board in January 2025 has been implemented from
April 2025. 
• The findings from the independent assessment of MyLA (MyLife Ahead)
project has been reviewed, Complex Cases Working Group (which was
established via MyLA) continues to meet, and discussions now taking place
during August and September with Alcohol & Drug Partnership on how to
build upon the success of MyLA, and any funding opportunities. 
• Each of the four Local Area Housing Teams now has a trained “super-
user” in place to support Housing Officers in using the Anti-Social Behaviour
(ASB) app. Guidance has been issued covering key areas including: 
• Criteria for use
• Managing customer expectations
• Handling audio/visual images 
The guidance has been developed in consultation with Legal Services.  All
elected members attended the demonstration on 8th September 2025. The
Council’s website has been updated to reflect this. 
• Stock of temporary accommodation has been increased in response to
demand pressures, and the letting target is being met. Renfrewshire’s
Rapid Rehousing Transition funding continues to be utilised to deploy staff
to assist with resettlement from temporary to settled accommodation, and
upscaling of the use of the Housing First approach. 
• Care Inspectorate registration for Refugee Resettlement team has been
achieved. 
• We are continuing to deliver the Action Plan outcomes outlined in the
Tenant Participation Strategy 2022-2027, with the following results: 
• The new Quality Circle focusing on Estate Management has
undertaken six inspections.
• The Tenant Scrutiny Panel has completed an exercise on TRA funding.
• A new TRA has been established in Paisley; and
• We have acquired a further three hand-held devices to assist tenants
with the Quality Circle inspections.   
• A review of all lockups has been undertaken, and initial proposals are the
subject of a separate report to this meeting of the Policy Board.

Page 4

PUBLIC
• We are continuing to work in partnership with teams across the Council to
expand the Neighbourhood Environment Trainee Teams and have
increased capacity from 2 squads to 4. 
4.2 Public Protection   
• Exploring the expansion of solar PV and other renewables on council
buildings is now approved as part of a 25/26 Climate Capital Programme.
Energy Team is currently liaising with procurement as a first step in the
project. 
• The Single Use Vapes ban came into force on Sunday 1 June 2025. While
the legislation imposes no statutory duty on the Authority, Officers from
Trading Standards contacted all 240 approximately registered suppliers of
vapes in the area with email advice and followed up any ‘bouncebacks’
(current email addresses are mandatory aspect of registration). This
includes online sellers, and cash and carries. 
• To date 6 complaints have been received and none have been found to be
justified upon investigation. Compliance levels therefore appear to be high,
with these requirements is now ‘business as usual’, and implementation is
considered complete. 
• The Carbon Management Plan is 90% complete and will be submitted to
the ILE Board in November 2025 with the final project details for each
service area. 
• There are currently several Officers completing training: 
• one to qualify as an Environmental Health Officer, 
• one as a Food Safety Officer and
• two others who are undertaking training to complete the Modern
Apprentice in Regulatory Services qualification. 
5. Areas where actions have been delayed or cancelled. 
5.1 As detailed in Appendix 1. 
• We will deliver any new duties with partners in relation to prevention of
homelessness following the introduction of the new Housing (Scotland) Act
during 2025/26, and this will include new duties in relation to homeless
prevention. This legislation has still to be enacted by the Scottish
Government. 
• New animal licensing requirements have not been progressed to date by
the Scottish Government. Officers are continuing to review and modernise
where appropriate, conditions on animal licenses to ensure these remain fit
for purpose and in accordance with relevant legislation and guidance.   
• We are awaiting final approvals for Howwood Road Area (70 units) from
Scottish Water, prior to commencement on site.

Page 5

PUBLIC
6. Progress against performance measures  
6.1 Environment, Housing, and Infrastructure Services reports on 22 performance
indicators, 9 are reported annually and 13 reported quarterly. This report contains
data pertaining to Quarter 1 and Quarter 2 of 2025 with annual figures referring
to 2024/25.  
6.2 The following indicators show areas which are currently performing better than
their respective targets.   
• The average length of time taken to complete non-emergency repairs
continues to improve. For Q2 it was an average of 6.1 days, which is an
improvement from Q1 and also an improvement on the overall figure for
2024/25 which was 6.9 days. 
• Average length of time taken to re-let properties in the last year (in days)
continues to improve. For Quarter 2 it was 30.1 days which is an
improvement from Quarter 1 and also an improvement on the overall
figure of 2024/2025 which was 37 days. 
• Percentage of rent loss due to voids for Q2 was 0.92% which continues to
be better than the target of 1.5%. 
• In the first six months of 2025/26 Environment, Housing & Infrastructure
received 4,934 elected member enquiries of which 87%% were
responded to within timescale. This was against a target of 85%. 
6.3 The following Performance indicators are showing as areas which are not on
target. 
• In the first six months of 2025/26 Environment, Housing & Infrastructure
received 5,240 front line resolutions of which 68% were responded to
within timescale. 
• In the first six months of 2025/26, Environment, Housing & Infrastructure
received 289 investigations of which 56% were responded to within
timescale. 
7. Priorities over the next six months 
7.1 Housing Services 
• There is ongoing work on the housing repairs operating model.   
• We will continue to ensure effective participation and support for all refugee
programmes.

Page 6

PUBLIC
• Implement NEC Housing Management System as part of the Housing
Innovations Project in 2 phases. Phase 1 will comprise of Rents, Service
Charges, Allocations, Tenancy Management, ASB, Customer Relationship
Management, Customer Services, Property Lifecycle, Servicing and Support
Services modules. 
• Deliver the key outputs from the 7th year of Renfrewshire’s Rapid Rehousing
Transition Plan (RRTP) and ensure the supply of temporary accommodation,
provision of support to those in need, and the number of social rented
housing lets meets the homeless pressures and the Council plays its part in
relation the provision of accommodation in response to changes in national
migration and resettlement policies and programmes. We will continue to use
RRTP funding to deploy staff to assist with resettlement from temporary to
settled accommodation, and upscaling of the use of the Housing First
approach. 
• We will continue investment in current housing stock for 2025/26, which
includes: 
• Kitchen, bathroom, and rewiring replacement – 600 properties
• Window and door improvement programme – 250 properties
• Heating renewals – 750 properties
• External improvements – 500 
• Continue to progress with year 4 of the 10-year Housing-led regeneration
programme. 
• Officers are progressing to deliver the Action Plan outcomes outlined in the
Tenant Participation Strategy 2022-2027. We anticipate the Strategy will be
complete by December 2027. 
• Year 2 of the stock condition survey is scheduled to be completed by May
2026.  
• Stakeholder and public consultation responses on the Strategic Housing
Investment Plan will be considered, and a finalised version will be presented
to the Board on 28th October 2025. 
• Officers from both Housing Services and the Chief Executive’s service are
working with COSLA to develop a new online participatory budgeting
platform that will be used to assist in the delivery of environmental and
neighbourhood projects. Elected member and staff briefing sessions are
being prepared for roll out over the coming weeks. The initial funding
allocation for 2025/26 has been divided across the four local area housing
teams to encourage participation across Renfrewshire. Further updates will
be reported to the Communities and Housing Policy Board as this fund
develops.

Page 7

PUBLIC 
7.2  Public Protection 
• We will implement full recycling facilities within Renfrewshire House.
Sustainability Team is progressing with scoping of work required including
completing a bin audit within Renfrewshire House and liaising with key
colleagues including Facilities Management and Procurement. 
• We will continue to explore the expansion of solar PV and other renewables
on council buildings is now approved as part of a 25/26 Climate Capital
Programme. Energy Team is currently liaising with procurement as a first step
in the project. 
• Developing Climate Change Impact Assessments process across appropriate
projects. Currently being piloted across a number of Project Management
Unit led projects to help inform further development of the process and
criteria prior to being finalised and rolled out across the Council. 
• We are currently reviewing our current approach to dog fouling enforcement
and use community engagement and data to map out ‘hot spots’ to target
enforcement in addition to the awareness campaign which is being developed
with input from our Marketing team and new signage to be used within
advertising space over the coming months to highlight dog fouling issues. 
• Deliver a programme of enhanced operational environmental and community
support activities for environment and place. 
• The Energy Team is liaising with procurement as a first step to expansion of
solar PV and other renewals on council buildings as part of the 2025/2026
Climate Capital Programme. 
• We are developing the following strategies and plans: 
• Renfrewshire’s Adaptation Plan
• Renfrewshire’s Circular Economy Strategy
• Renfrewshire Council’s Carbon Management Plan (CMP) 
• A part of our cross-cutting theme EHI will work towards Keeping The Promise
and support our Care Experienced Community.   
___________________________________________________________________
Implications of the Report 
1. Financial -The Service Improvement Plan highlights resourcing pressures
arising from increasing demand for services and the current financial
environment.   
2. HR & Organisational Development – The Service Improvement Plan also
highlights workforce development and wellbeing considerations.

Page 8

PUBLIC
3. Community/Council Planning – The report details a range of activities which
reflect Council and Community Planning themes and direct link to the delivery of
the Council Plan.   
4. Legal – none.   
5. Property/Assets – none.   
6. Information Technology – Service Improvement relating to information
technology are key enablers of service improvement and modernisation and
support service – level and corporate objectives.   
7. Equality & Human Rights - The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights.
No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual impact of
the recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website. 
8. Health & Safety – none.   
9. Procurement – none.   
10. Risk– Risks related to the delivery and management of services are regularly
monitored and included in Renfrewshire Council’s Corporate and Strategic Risk
Registers. 
11. Privacy Impact – none.   
12. Climate Risk – A section of the actions and performance indicators within the
SIP covers the ‘Green’ theme of Renfrewshire’s Council Plan which highlights
activities across the Council to tackle climate change. 
13. Children’s Rights – none. 
14. Cosla Policy Position – none. 
___________________________________________________________________ 
List of Background Papers: Communities and Housing Policy Board, 13 May 2025,
Agenda Item 4: “Environment, Housing and Infrastructure – 2025-2028 Service 
Improvement Plan”  
___________________________________________________________________ 
Author:          Gordon McNeil, Director of Environment, Housing and Infrastructure,
Email: gordon.mcneil@renfrewshire.gov.uk

Page 9

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ENVIRONMENT,  HOUSING AND
INFRASTRUCTURE SERVICES
SERVICE IMPROVEMENT PLAN 2025-2028
Six monthly progress update
October 2025
Communities and Housing Policy Board

Page 10

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
WELCOME TO OUR SIX-MONTHLY UPDATE
• This update reflects on the first six months of our Service Improvement Plan, highlighting areas where we
are already making progress and some areas we want to focus on more, perhaps because performance
isn’t moving in the direction we anticipated or because of other pressures or factors that makes this even
more of a priority for us.
• The following pages shine a spotlight on some great projects or practice and highlight areas where we’d
like to improve or develop further.  At a service level, there is a stronger focus on some of the Council Plan
Strategic Outcomes than others. Towards the end of this document, you’ll find a full update against all the
actions and performance indicators we use to measure progress.
• We report on 22 performance indicators, 9 are reported annually and 13 reported quarterly. This report
contains data pertaining to Quarter 1 and Quarter 2  of 2025/26 with annual figures referring to 2024/25.

Page 11

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ABOUT US
This update covers the Environment, Housing and Infrastructure service areas within the remit
of the Communities and Housing Policy Board. These are:
• Housing Services
• Responsibilities include:
• As at, 31 March 2025  the
housing stock being managed is
12,078
• Providing services to Council
tenants, alongside housing
advice and support
• Assisting homeless people and
those threatened with
homelessness
• Ensuring people have safe and
healthy places to live
Public Protection
• Responsibilities include:
• Regulatory and Public
Protection services including
partnership working with
police, fire and other
multiagency partners
• Helping to keep people safe
through the Community Safety
Hub
• Safeguarding the public and
protecting consumers through
Trading Standards and
Environmental Health
Civil Contingencies
• Responsibilities include:
• Providing support to all services
across the Council to ensure they
have robust arrangements in place
for the continued delivery of essential
services in the event of significant
incidents such as disruptive weather
or widespread power outage.
• Civil Contingencies service has
provided emergency planning for
Renfrewshire, and on behalf of East
Renfrewshire, Inverclyde and West
Dunbartonshire council areas

Page 12

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE COUNCIL PLAN
Place Green
• The first 6 months of this financial year has seen a further increase in homelessness with
13% more homeless applications compared to the same period last year. This increase in
applications is understandably again presenting significant challenges in terms of the
provision of temporary accommodation.
• The homeless services are working closely with local area housing teams and Registered
Social Landlords to match applicants to suitable tenancies as quickly as possible.
• Positive progress  is being made across all areas of the
Housing-led Regeneration and Renewal Programme within
the agreed timeline for works scheduled in year 4 of this 10-
year programme. The acquisition and rehousing strategy is
performing as planned and various phases of demolition are
being taken forward as blocks become fully council owned
and vacant. 
• The percentage of stock meeting SHQS has increased
significantly to 80.02% in 24/25 from 68.6% in 23/24.
• We will implement full recycling facilities within Renfrewshire
House. Sustainability Team is progressing with scoping of work
required including completing a bin audit within Renfrewshire
House and liaising with key colleagues including Facilities
Management and Procurement.
• Exploring expansion of solar PV and other renewables on
council buildings is now approved as part of a 25/26 Climate
Capital Programme. Energy Team is currently liaising with
procurement as a first step in the project.

Page 13

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
PLACE: WORKING TOGETHER TO ENHANCE WELLBEING ACROSS COMMUNITIES
Achievements
Priorities and areas for improvement
• The new rent charging policy for temporary
accommodation has been implemented from April
2025
• The Complex Cases Working Group (which was
established via MyLA) continues to meet, and
discussions now taking place during August and
September with Alcohol & Drug Partnership on
how to build upon the success of MyLA, and any
funding opportunities.
• Each of the four Local Area Housing Teams now has a
trained “super-user” in place to support Housing Officers in
using the Anti Social Behaviour (ASB) app. The Council’s
website has been updated ensuring transparency and
confirms that the system is being used overtly in line with
agreed procedures.
• A review of all lockups has been undertaken
and initial proposals are the subject of a
separate report to this meeting of the Policy
Board.
• The new Housing (Scotland) Act will be introduced during 2025/26, and this will include new duties in relation to homeless prevention. This legislation
has still to be enacted by the Scottish Government.
• There is ongoing work on the housing repairs operating model.

Page 14

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ECONOMY: BUILDING AN INCLUSIVE, GREEN AND RESILIENT ECONOMY
Achievements
Priorities and Areas for Improvement
• Work in partnership with teams across the Council to expand
the Neighbourhood Environment Trainee Teams  - increasing
capacity from 2 squad to 4.
• New animal licensing requirements have not been progressed to date by the Scottish Government. Officers are continuing to review and modernise
where appropriate, conditions on animal licenses to ensure these remain fit for purpose and in accordance with relevant legislation and guidance.
The Single Use Vapes ban came into force on Sunday 1 June 2025.
• While the legislation imposes no statutory duty on the Authority, Officers from
Trading Standards contacted all 240 approximately registered suppliers of vapes in
the area with email advice and followed up any ‘bouncebacks’ (current email
addresses are mandatory aspect of registration). This includes online sellers, and
cash and carries.’
• To date 6 complaints have been received and none have been found to be justified
upon investigation. Compliance levels therefore appear to be high, with these
requirements is now ‘business a usual’, and implementation is considered complete.

Page 15

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
FAIR: NURTURING BRIGHT, HAPPY AND HEALTHY FUTURES FOR ALL
Achievements
Priorities and areas for improvement
• Care Inspectorate registration for Refugee Resettlement team has been achieved.
• Ensure effective participation and support for all refugee programmes.
Delivering the Action Plan outcomes outlined in the Tenant Participation Strategy 2022‐2027.
 The new Quality Circle focusing on Estate Management has undertaken six inspections;
 The Tenant Scrutiny Panel has completed an exercise on TRA funding;
 A new TRA has been established in Paisley; and
 We have acquired a further three hand-held devices to assist tenants with the Quality Circle inspections. 
• We will now monitor the effectiveness and popularity of Digital Noticeboards the new method for keeping tenants informed
• Implement NEC Housing Management System as part of the Housing Innovations Project in 2 phases. Phase 1 will comprise of Rents, Service Charges, Allocations,
Tenancy Management, ASB, Customer Relationship Management, Customer Services, Property Lifecycle, Servicing and Support Services modules
• The project remains on target, workshops and solution design/build are largely complete as anticipated by end of September 2025.
• Reconfiguration of letters (c200) to be built within NEC Housing has commenced; and integrations to software systems continues to progress well.
• New Training Manager in post from September 2025 and work has commenced for Training Needs Analysis (TNA) to be in place for all system users.

Page 16

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
GREEN: LEADING RENFREWSHIRE TO NET ZERO
• The Carbon Management Plan is 90% complete and will be submitted to the ILE Board in November 2025 with the final
project details for each service area.
• The full recycling facilities within Renfrewshire House will be implemented. Sustainability Team progressing with scoping of work required including completing a bin
audit within Renfrewshire House and liaising with key colleagues including Facilities Management and Procurement.
• Exploring expansion of solar PV and other renewables on council buildings. This is now approved as part of a 25/26 Climate Capital Programme. Energy Team is
currently liaising with procurement as a first step in the project.
• Develop Climate Change Impact Assessments process across appropriate projects. Currently being piloted across a number of Project Management Unit led
projects to help inform further development of the process and criteria prior to being finalised and rolled out across the Council.
Achievements
Priorities and areas for improvement
• The percentage of stock meeting SHQS has increased significantly to 80.02% in 24/25 from
68.6% in 23/24.

Page 17

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Priorities and areas for improvement
Living our Values: making a difference together
Achievements
• We continue to maintaining the commitment to eradicating youth homelessness, aligning with strategic priorities and local initiatives.
• There are 380 Renfrewshire Promise Keepers across the network, and we are continuing to raise awareness and promote awareness of
The Promise across homeless and housing services, embedding/aligning its principles where appropriate.
• Public Protection - There are currently several Officers completing training
• one as a Food Safety Officer and
• two others who are undertaking training to complete the Modern Apprentice in Regulatory Services qualification
• Our new Environmental Health Officer qualified in October 2025.
• Direct support by the EHI senior leadership Team to the Renfrewshire Promise Team.
• Ongoing support for Renfrewshire’s Promise Approach through active participation in: Renfrewshire’s Promise Oversight Group Relevant
workstreams and strategic groups.
• The service has continued collaboration with partners to develop tailored, affordable Housing Pathways for Care Experienced young
people.
• Actively raise awareness of Renfrewshire’s Promise Keeper Network and Renfrewshire’s Language Policy.
• Encouraged team-wide completion of The Promise i-learn module across EHI.
• Supported council-led initiatives to recruit Care Experienced young people, including: The Guaranteed interviews for Care Experienced applicants meeting
essential criteria.

Page 18

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
ACTIONS AND INDICATORS
C&H Policy Board October 2025

Page 19

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE
What we will do Due Date Status Progress Update
The new Housing (Scotland) Act will be introduced
during 2025/26, and this will include new duties in
relation to homeless prevention.
March 2026 This legislation has still to be enacted by the Scottish Government.
Continuing to meet the challenges of the local/
national pressures around homelessness. March 2026
Regular updates provided to Policy Board on the measures being taken in relation to lets to
homeless applicants, the establishment of new temporary accommodation and the support being
provided to homeless applicants.
A detailed report on progress and the key challenges for the Council and partners is being
submitted to  Policy Board in October 2025.
Implement new rent charging policy for temporary
accommodation April 2026 New policy implemented from April 2025
Review the findings from independent assessment
of MyLA (My Life Ahead) project, and ensure the
lessons learned are incorporated in the support
provided to those whose settled housing may be
affected by drug / alcohol use.
March 2026
Evaluation has been reviewed, Complex Cases Working Group (which was established via
MyLA) continues to meet, and discussions now taking place during August and September with
Alcohol & Drug Partnership on how to build upon the success of MyLA, and any funding
opportunities.
Deliver the key outputs from the 7th year of
Renfrewshire’s Rapid Rehousing Transition Plan
(RRTP) and ensure the supply of temporary
accommodation, provision of support to those in
need, and the number of social rented housing lets
meets the homeless pressures and the Council
plays its part in relation the provision of
accommodation in response to changes in national
migration and resettlement policies and
programmes.
March 2026.
Stock of temporary accommodation being increased in response to demand pressures, and
lettings target being met. Continuing to use RRTP funding to deploy staff to assist with
resettlement from temporary to settled accommodation, and upscaling of the use of the
Housing First approach.
Policy Board regularly updated, with further progress report being submitted in October.

Page 20

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Further develop training and communications on the ASB App based
on learning from the pilot project and extend use across all Local Area
Housing Teams.
June  2025
Each of the four Local Area Housing Teams now has a
trained “super-user” in place to support Housing Officers in using the
Anti Social Behaviour (ASB) app. The Council’s website has been
updated ensuring transparency and confirms that the system is
being used overtly in line with agreed procedures.
The revised Housing Asset Management Strategy will be presented to
the Communities and Housing Policy Board this year.
The Housing Asset
Management Strategy is
currently being reviewed and
will be brought to a future
meeting of the policy board for
approval.
Draft asset management strategy and action plan has been
completed and will be presented at the October board.
Ongoing work on the housing repairs operating model. Review to be completed in
2025. Actions may continue
beyond this timescale
There is ongoing review on the housing repairs operating model. 
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 21

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Investment in current housing stock including for 2025/26
• Kitchen, bathroom, and rewiring replacement – 600 properties
• Window and door improvement programme – 250 properties
• Heating renewals – 750 properties
• External improvements – 500
March 2026
180 properties have been completed to date by contractors and
Building Services. Poor performance has resulted in Housing closing
their contract with Bell Group who failed to complete the target
outputs.
370 properties have benefitted from replacement windows in
regeneration areas and across the wider authority. Further
installations are continuing.
111 Boiler/heating installs have been completed by Building Services
and contractors to date.
234 properties have had external improvements completed in their
property to date
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 22

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Howwood Road (70 units) and Gallowhill (65 units)
new build developments on site and underway March 2026 Statutory approvals are now in place at Gallowhill which enabled a site start on the 4 August
2025. We are still awaiting final approvals for Howwood Road Area prior to commencement
on site.
Continue with year 4 of the 10-year Housing-led
regeneration programme.
March 2026
Overall, the ten-year programme is running as per the agreed timeline with the exception of
the Ferguslie/Broomlands area, where the delivery of the newbuild homes on the cleared
Carbrook Street site has had to be retendered.
Owner acquisitions are progressing well with 64 of the 89 privately owned properties
identified for acquisition for demolition now within Council ownership. A further 13 owners
have agreed to the sale of their properties and are with legal services to conclude.
Tenant Rehousing programmes and demolition of vacant blocks is progressing well across
each area as per the delivery timeline set out.
Several neighbourhood pop up events have taken place in the Auchentorlie and Howard
Street areas and further events are being planned for each of the other regeneration areas
in line the project delivery timeline.
Officers will work together to review the delivery and
turnaround of void properties across Renfrewshire
to minimise times, wherever possible, to allow
properties to be re-let.
The Single Voids
Team pilot has been
extended until 31st
March 2026
Performance against targets for 2024–2026 is so far:
 Void rent loss (excluding Homeless Persons’ Units) reduced from 4.45% to 2.93%
(target 2.75%) – success rate 89%;
 Void numbers reduced from 518 to 350 (target 227) – success rate 57%; and
 Turnaround time reduced from 50.40 to 30.49 (target 45.00) – success rate 100%
Review our current approach to dog fouling
enforcement and use community engagement and
data to map out ‘hot spots’ to target enforcement March 2026
Planned days of action have been taking place over recent months to focus on dog fouling
and these will continue for the rest of the year. Staff across Public Protection are supporting
this work. The awareness campaign is being developed with input from our Marketing team
and new signage will be used within advertising space over the coming months to highlight
dog fouling issues.
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 23

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
A review of Council owned lock ups and
associated policy and procedures is being
undertaken
Ongoing review of the
Council’s owned lock-
up estate, Consultation
is expected to be
undertaken in late
Spring/early summer
2025, and a plan for
the implementation will
be prepared
A review of all lock-ups has been undertaken. Initial proposals for the retention / demolition of
lock-ups are being further reviewed for presentation to a future Communities and Housing
Policy Board. This Board report will also consider a proposal to review rent levels based on a
Business Plan for lockups that has been developed. A lockups policy has been drafted and will
also be covered in the report.
Through the HRA, £600k will be used for
Participatory Budgeting for environmental
and neighbourhood projects. This will be split
with £150k for each of the local area housing
teams
The Participatory
Budgeting will be
utilised over the next 3
years. The full details
of this initiative will be
developed and brought
to the Policy Board for
approval prior to
implementation
Officers from both Housing Services and the Chief Executive’s service are working with COSLA
to develop a new online participatory budgeting platform that will be used to assist in the
delivery of environmental and neighbourhood projects. Elected member and staff briefing
sessions are being prepared for roll out over the coming weeks. The initial funding allocation for
2025/26 has been divided across the four local area housing teams to encourage participation
across Renfrewshire. Further updates will be reported to the Communities and Housing Policy
Board as this fund develops.
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 24

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current
Status
2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
Private Water Supplies –
100% of type A supplies risk
assessed and sampled
100% 100% 100%
Not measured for
quarters
Not measured for
quarters
All regulated private water supplies have
been sampled and risk assessed as is
required by the Regulations during the year
Air Quality - Annual average
PM10 value across all
continuous monitoring sites
13.2ug/m3 18ug/m3 18ug/m3 Not measured for
quarters
Not measured for
quarters
The average value is significantly below the
target for the year.
Air Quality - average
nitrogen dioxide value of
monitoring sites, within
AQMA(s) exceeding limits
0ug/m3 40ug/m3 40ug/m3 Not measured for
quarters
Not measured for
quarters
There were no exceedances of the target
value of 40ug/m3 at any monitoring location
and as this has been the case for several
years, all AQMAs across Renfrewshire
have now been revoked.
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 25

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
Indicator Current Status 2024/25 2025/26 Q1 Q2 Explanation of
performance
Value Target Target Value Value
Percentage of reactive repairs
carried out in the last year
complete right first time (Housing)
90.1% 93% 93%
Not measured for
quarters
Not measured for
quarters The value for 2024/2025 is
slightly below target of 93%
Percentage of Overall Repairs
Completed Within Target (Housing
Services)
93.2% 95% 95% 93.36% 94.24%
Please note this is 5-month
position and just under
annual target.
Average length of time taken to
complete non-emergency repairs
(days) (Housing Services)
6.9 days 15 days 15 days 6.68 days 6.1 days
This indicator has improved
since year end.  Please
note this is 5-month
position.
Average time from household
presenting themselves as
homeless to completion of duty
(number of weeks)
21.96 weeks 26 26 21.38 weeks 22.51
Similar to the national
picture the demand for
Homeless Services in
Renfrewshire remains
consistently high, however
Renfrewshire Council are
continuing to deliver on
their commitment to
allocate 55% of their lets to
Homeless families, but due
to increasing demand we
expect to the time to
conclude duty to come
under increasing pressure
in the short to medium
term.
DELIVERING THE SERVICE IMPROVEMENT PLAN– PLACE

Page 26

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – ECONOMY
What we will do Due Date Status Progress Update
Work in partnership with teams across the
Council to expand the Neighbourhood
Environment Trainee Teams  - increasing
capacity from 2 squad to 4.
June 2025
The Neighbourhood Environmental Training Team (NETT) is now fully operational following the
successful expansion from two to four squads earlier this year. A new shift pattern has been
implemented, enabling seven-day service delivery across neighbourhoods. This enhancement has
significantly improved visibility, responsiveness, and overall impact within our communities.
An initial review is scheduled for mid August to evaluate the progress of the service expansion. The
review will focus on:
• Identifying early benefits
• Highlighting any challenges
• Gathering insights from implementation
Feedback will be collected from officers, key services, and tenants as part of this process to ensure
a well-rounded evaluation.
An award application has been submitted to COSLA on behalf of the NETT under the category
of ‘Improving Partnership Working’. This submission highlights the strong
collaboration between Housing Services, Neighbourhood Services, and Invest in Renfrewshire,
showcasing how these teams have worked together effectively to improve outcomes for the local
community.
Complete the review of animal license
conditions across all licences March 2026
New animal licensing requirements have not been progressed to date by the Scottish Government.
Officers are continuing to review and modernise where appropriate, conditions on animal licenses
to ensure these remain fit for purpose and in accordance with relevant legislation and guidance.
Implement the proposed ban on the sale and
supply of single use nicotine vaping products.
March 2026
The Single Use Vapes ban came into force on Sunday 1 June 2025.
While the legislation imposes no statutory duty on the Authority, Officers from Trading Standards
contacted all 240 approximately registered suppliers of vapes in the area with email advice and
followed up any ‘bouncebacks’ (current email addresses are mandatory aspect of registration). This
includes online sellers, and cash and carries.’
To date 6 complaints have been received and none have been found to be justified upon
investigation. Compliance levels therefore appear to be high, with these requirements is now
‘business a usual’, and implementation is considered complete.

Page 27

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – FAIR
What we will do Due Date Status Progress Update
Ensure effective participation and
support for all refugee programmes. March 2026 and
on-going
Range of support and integration events / activities has been broadened, and Health & Wellbeing Co-ordinator
appointed.
Consultation with user groups and individuals carried out May – August, and feedback now being used to
inform our next steps
Obtain Care Inspectorate registration for
Refugee Resettlement team March 2026 Registration achieved.
Pilot the installation of ‘digital
noticeboards’ at the reception areas of
sheltered complexes and obtain
feedback from tenants.
March 2026
Digital Noticeboards now installed at Monkdykes and Speirsfield Gardens complexes.
We will now monitor the effectiveness and popularity of this new method for keeping tenants informed
Work with Advice Services to maximise
opportunities for Council tenants to access
specialist income advice. March 2026
The referral process is monitored monthly to ensure:
• All available support is being utilised
• Support is effective and beneficial
Over the past six months, a total of 341 referrals have been made on behalf of council tenants to various
agencies including: Advice Works – Employability Services (invest in Renfrewshire, Energy Management Unit,
Citizens Advice Bureau, Social Work and Housing Support.
Work with  relevant stakeholders and
Council Tenants scheduled to migration to
Universal Credit to mitigate against
avoidable delays and loss of housing cost
contributions.
March 2026
Universal Credit (UC) Migration Support Process
• Housing Benefit colleagues provide details of tenants expected to migrate to UC in the next financial year.
• Officers attempt to contact identified tenants to confirm if they’ve received a migration letter from the DWP,
make them aware of process and make appropriate referrals
• The process is working effectively, with officers successfully identifying and supporting tenants through the
UC migration.
• As the number of tenants on UC increases, there is also a rise in tenants making direct rent payments to
landlords, helping to minimise the impact on the Housing Revenue Account (HRA).
Deliver the Action Plan outcomes outlined
in the Tenant Participation Strategy
2022‐2027 The strategy will
be complete by
Dec 2027
Officers are working through the specific actions detailed in the Action Plan. Since the last update:
 The new Quality Circle focusing on Estate Management has undertaken six inspections;
 The Tenant Scrutiny Panel has completed an exercise on TRA funding;
 A new TRA has been established in Paisley; and
 We have acquired a further three hand-held devices to assist tenants with the Quality Circle inspections.

Page 28

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – FAIR
What we will do Due Date Status Progress Update
Continue with next phase of stock condition survey. Year 1 - May 2025
Year 2 – May 2026
Year 3 - May 2027.
Year 1 completed; half of Year 2 has been
completed by September 2025. On schedule to
complete Year 2 by May 2026.
Access rate is at circa 50% but additional years
in 2028 and 2029 can be used to return to ‘no
access’ properties.
Update the SHIP to set out Renfrewshire’s new build affordable
housing investment priorities utilising grant funding made
available from the Scottish Government’s Affordable Housing
Supply Programme’
The SHIP is a rolling programme that covers a five-year
period and is refreshed annually. This annual review
takes account of Scottish Government funding availability
and progress in delivering existing affordable housing
sites and  provides an opportunity to add new sites in
order to meet the housing needs of Renfrewshire’s
residents.
Each year a draft SHIP is prepared and submitted to the
Communities and Housing Policy Board in August for
approval for public consultation. The final SHIP is
presented back to Board in October for approval  before
being submitted to the Scottish Government.
An updated draft SHIP 2026-2031 was
presented to the Communities and Housing
Policy Board on 19th August 2025. The draft was
approved and is subject to stakeholder and
public consultation for the period 20th August to
19th September 2025.  Responses will be
considered, and a finalised version will be
presented to the Board on 28th October 2025
Implement NEC Housing Management System as part of the
Housing Innovations Project in 2 phases – which will incorporate
Rents, Repairs, Service Charges, Allocations, Tenancy
Management, ASB, Customer Relationship Management,
Customer Services, Property Lifecycle, Homelessness and
Support Services modules.
Phase 1 will comprise of Rents, Service Charges, Allocations,
Tenancy Management, ASB, Customer Relationship
Management, Customer Services, Property Lifecycle, Servicing
and Support Services modules
Phase 1 May 2026
The project remains on target, workshops and
solution design/build are largely complete as
anticipated by end of September 2025.
Reconfiguration of letters (c200) to be built within
NEC Housing has commenced; and integrations
to software systems continues to progress well.
New Training Manager in post from September
2025 and work has commenced for Training
Needs Analysis (TNA) to be in place for all
system users.

Page 29

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – FAIR
What we will do Due Date Status Progress Update
We will implement Phase 2 of the NEC Housing Management
System. Phase 2 July 2027
Commences February 2026.
Preparatory work has commenced – set up of Phase 2
Working Group in May 2025 to assess fully the
needs/requirements to ensure successful completion of
Phase 2 by July 2027.

Page 30

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due
Date
Status Progress Update
Deliver a programme of enhanced operational environmental and
community support activities for environment and place.
March 2026 Team Up to Clean Up facilitates almost 8,400 community members to actively discuss
environmental issues and promote responsible behaviours.
At the conclusion of Keep Scotland Beautiful’s Big Spring Clean, the Renfrewshire
Campaign was recognised as delivering the highest level of litterpicking events across the
country.
The Spotless September initiative facilitated engagement with almost half of Renfrewshire’s
school estate, empowering young people to take a pride in their surroundings by cleaning up
their local communities.
New materials and infographics are being shared across social media platforms to reduce
flytipping and raise awareness of “white van man” activity, offering practical tips to
encourage the responsible disposal of waste. 
The Environmental Taskforce’s suite of cameras were redeployed to new locations in
response to data analysis of local flytipping hotspots.
To date footage has offered evidence to facilitate Fixed Penalty Notices, as well as
highlighted the level of ongoing issues with unregistered vehicles illegally depositing waste. 
Implement full recycling facilities within Renfrewshire House March 2026 Sustainability Team progressing with scoping of work required including completing a bin
audit within Renfrewshire House and liaising with key colleagues including Facilities
Management and Procurement.
Exploring expansion of solar PV and other renewables on council
buildings
March 2026 This is now approved as part of a 25/26 Climate Capital Programme. Energy Team is
currently liaising with procurement as a first step in the project.
Development of investment grade business cases for 2 potential
district heating networks. 1 Paisley central, 1 expansion of AMIDS.
Summer 2025 The development of Business Cases for both networks continues and has now progressed
to a key final phase of the project. The programme timeline has been extended from the
initial agreed plan due to the requirement for further exploration and analysis activity.
Delivering the Council Plan - GREEN

Page 31

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
What we will do Due Date Status Progress Update
Looking to expand Building Management Systems to reduce energy
use and water use.
March 2026 This was approved as part of a 25/26 Climate Capital Programme. The project has
been planned into 3 phases of building installations, and phase 1 implementation is
nearing completion. Phase 2 is planned to begin in September/October 25.
Develop the following strategies and plans - 
• Renfrewshire’s Adaptation Plan
• Renfrewshire’s Circular Economy Strategy
• Renfrewshire Council’s Carbon Management Plan (CMP)
March 2026 • Sustainability Strategy Lead Officer now in post and will lead on the
development of this plan. Key themes have been identified through previous
engagement, with further external, community engagement to follow.
• Sustainability Strategy Lead Officer now in post and will lead on the
development of this plan. Key themes have been identified through previous
engagement, with further external, community engagement to follow.
• The CMP is currently being finalised with the final project details for each
service area. The plan will be submitted to the next ILE board for approval.
Develop Climate Change Impact Assessments process across
appropriate projects.
March 2026 Currently being piloted across a number of Project Management Unit led projects.
This will help to inform further development of the process and criteria prior to being
finalised and rolled out across the Council.
Delivering the Council Plan - GREEN

Page 32

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
GREEN
Indicator Current
Status
2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
Percentage of Council
housing stock which meets
the Scottish Housing Quality
Standard
80.02% 71.15% 82.23%
Not measured for
quarters
Not measured
for quarters
The percentage of stock meeting SHQS
has increased significantly to 80.02% in
24/25 from 68.6% in 23/24. Performance
for this indicator changed to include
compliance with the 5-yearly Electrical
Installation Condition Report (EICR), as
well as the new smoke and heat detector
standard.

Page 33

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
What we will do Due Date Status Progress Update
We will continue to develop and support our
workforce through training and development
demonstrating our value as a learning
organisation.
March 2026
• The Service Development Team continue to support employees to undertake a range of training
including mandatory training.
• To date 49% of frontline employee have completed mandatory toolbox talks and 85% of network
staff have completed mandatory training on iLearn.
• Training courses have included driver training, First Aid, Health & Safety and specific role specific
training such as Chainsaw training.
• Soft FM “job characteristic” project is still at an early stage and will be progressed subject to
further discussion with Corporate Teams, in the second half of 2025/26. Longer term this work will
be used to inform identification of training requirements across EHI.
We will support wider employee health and
wellbeing across Environment, Housing,
Infrastructure.
March 2026
• In response to the Employee Survey 2024 to support the opportunity fore more regular time and
engagement between managers/ supervisors and employees a “Personal Development Plan”
(PDP) for networked staff has recently been launched.  This template supports employees to
reflect on achievements and challenges, agree objectives and identify training support required. 
• Work is ongoing to promote health and wellbeing across EHI and more front-line staff are trained
as Metal Health First Aiders.
• The NHS Wellbeing Calendar themes will be considered to deliver more focussed and
appropriate activities to increase awareness and offer support to the health and wellbeing of staff.
We recognise that Health & Safety is an
integral part of our business.  We will deliver
our actions outlined in the Environment,
Housing & Infrastructure (EHI) Health & Safety
Plan 2025 – 2028. March 2026
• The review of the EHI Quality, Health and Safety manual and related documentation will be
undertaken in the second half of 2025/26.
• IOSH Managing Safely has been rolled out to 56 managers, supervisors and employees across
EHI. An additional 9 Senior Managers undertook IOSH Leading Safely. Further courses will be
run during 2025/26, and Housing Services are progressing similar training focused on that
service needs.
• Work to undertake health and safety internal audits will be undertake in the second half of
2025/26.

Page 34

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
Indicator Current
Status
2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
Average number of workdays lost through
sickness absence per employee (FTE)
(cumulative)
15.41 13.7 13.7 3.25 TBC Awaiting Quarter 2 from HR.
% of Members enquiries completed within
timescale 89.2% 85% 85% 86% 87%
In the first six months of 2025/26 Environment, Housing &
Infrastructure received 4,934 members enquiries of which
87% were responded to within timescale.
% of frontline resolutions dealt with within
timescale
62% 85% 85% 58% 79%
In the first six months of 2025/26 Environment, Housing &
Infrastructure received 5,240 front line resolutions of which
68% were responded to within timescale.  Please note for
September there are 14 frontline complaints still outstanding
but are within timescale – and have not been included in Q2
figure.
% of complaint investigation completed
within timescale 
50% 85% 85% 45% 67%
In the first six months of 2025/26, Environment, Housing &
Infrastructure received 289 investigations of which 56% were
responded to within timescale.  Please note for September
there are 62 complaint investigations still outstanding but are
within timescale – and have not been included in Q2 figure.
% of FOI request completed within
timescale
99% 100% 100% 97% 95%
In the first six months of 2025/26 Environment, Housing &
Infrastructure dealt with 498 Freedom of Information requests
of which 96% were responded to within timescale. 85 of
these requests were cross departmental and 413 were
departmental.
Training – Percentage of staff training
undertaken in relation to qualifications
(Public  Protection)
100% 100% 100% 100% 100%
Staff training is provided on a structured basis as needs are
identified to ensure that they have the correct skills and
qualifications to undertake their duties. There are currently
several Officers completing training: one to qualify as an
Environmental Health Officer, one as a Food Safety Officer
and two others who are undertaking training to complete the
Modern Apprentice in Regulatory Services qualification.

Page 35

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
Indicator Current Status 2024/25 2025/26 Q1 2025/26 Q2 2025/26 Explanation of performance
Value Target Target Value Value
Gross rent arrears (all
tenants) as at 31 March each
year as a percentage of rent
due for the reporting year.
7.10% 7.5% 7.5% 6.2% 7.34% Gross Arrears are £4,306,175 as a
percentage of rent due of £58,694,728. 
Rent collected as percentage
of total rent due in the
reporting year. 100.7% 98% 98% 99.1% 98.9% Performance remains similar to this point
last year.
Average length of time taken
to re-let properties in the last
year (in days) 37 53 45 30.6 30.1 There was a total of 387 relets between April
and the end of September.
Percentage of rent loss due to
voids 1.3% 1.8% 1.5% 0.92% 0.92% Improvement in this indicator reflects
improvement in voids performance.

Page 36

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE SERVICE IMPROVEMENT PLAN – LIVING OUR VALUES
Indicator Current Status 2024/25 2025/26 Q1 Q2 Explanation of performance
Value Target Target Value Value
% of corporate induction completed
within 30 days of starting employment
with the Council N/A TBC Not measured for
quarters
Not measured for
quarters
These are four new indicators.  Evaluation of
progress will take place midway through 2025/26,
and this will help inform the creation of
targets/timescales across the whole service.
Progress will be reported annually.
Although these will be reported annually, for
information, as of 30 September 2025 49% of
frontline employee have completed mandatory
toolbox talks and 85% of network staff have
completed mandatory training on iLearn.
% of mandatory training courses for
frontline employees completed N/A TBC Not measured for
quarters
Not measured for
quarters
% of mandatory training courses for
employees with access to the
Council’s network completed N/A TBC Not measured for
quarters
Not measured for
quarters
% of Personal Development Plans
completed N/A TBC Not measured for
quarters
Not measured for
quarters

Page 37

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DATA STRATEGY: PRIORITY ACTIVITIES
What we will do Due Date Status Progress Update
Strategic: We will align service data activities with the Digital Strategy for
Renfrewshire objective: Data is a critical asset.  Ensure visibility of data
activities at Directorate (Director & Head of Service Level)
March 2026
The Directorate (Director and 4 Heads of Service) regularly
consider a range of data which is used to inform decision making. 
There is ongoing support for data activities and training to enhance
this capability across the Department.
Skills: We will identify skills gaps (eg data input, data analysis) and training
needs across EHI and address through our Workforce Development plan in
line with the Renfrewshire Council People Strategy.
March 2026
Information on skills gaps and training needs will be identified as
part of the Personal Development Plan (PDP) currently being rolled
out for networked employees. 
Internal training on data analysis tools has been undertaken to
support knowledge and understanding of our data.
Data Quality: We will review data quality in key business systems and
processes and develop an improvement plan. December 2025
As part of wider projects data for Roads and Waste Services has
been reviewed and the quality of data (accuracy, completeness
and up to date) will be improved, supporting data driven decision.
Further work to review data quality in key systems will be
undertaken in the second half of 2025/26.
Analysis: We will further define analysis requirements to improve decision-
making and build capabilities locally within services where required. December 2025
Work is ongoing to improve how data is presented including using
standard tools.  Although at an early stage it is hoped this work will
improve how our data is presented to Services allowing them to make
more informed decisions
ERP: We will work with Corporate Teams to promote and increase the use
of standard dashboards as business as usual. March 2026
Work is underway to support services to ensure that the data held in the
ERP in accurate.  This has included asking employees to review their
personal details and update as required.
Data Advisory Group (DAG): We will ensure EHI representation at the
DAG to ensure our data activities align with the Data Strategy Framework;
cross-service data sharing opportunities are identified and that data
improvement activities are carried out in a consistent manner across the
organisation.
March 2026 The Senior Service Development Manager represents EHI at the
DAG and will continue to ensure that data is used collaboratively
across services where appropriate.

Page 38

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
DELIVERING THE COUNCIL PLAN – CROSS CUTTING THEME
IMPROVING OUTCOMES FOR CHILDREN AND FAMILIES
“Across all of our work and all of our efforts, we hope for loving and happy lives for Renfrewshire’s children - working
together to get it right for children, families and communities – protecting, learning, achieving and nurturing.  Every priority of
this Council Plan will contribute to improving  the lives of Renfrewshire’s children and their families.  It is our fundamental duty
as an organisation and our shared responsibility as citizens of this place to ensure that our children inherit a Renfrewshire
where their wellbeing is nurtured, their futures are bright, and their environment is safe and healthy.’
What we will do Due Date Status Progress Update
EHI will work towards Keeping The Promise
and support our Care Experienced
Community.
March 2026
• The service has continued collaboration with partners to develop tailored, affordable
Housing Pathways for Care Experienced young people.
• Maintained commitment to eradicating youth homelessness, aligning with strategic
priorities and local initiatives.
• Ongoing support for Renfrewshire’s Promise Approach through active participation in:
Renfrewshire’s Promise Oversight Group Relevant workstreams and strategic groups.
• Direct support by the EHI senior leadership Team to the Renfrewshire Promise Team.
• Promoted awareness of The Promise across homeless and housing services,
embedding/aligning its principles where appropriate .
• Actively raised awareness of Renfrewshire’s Promise Keeper Network and Renfrewshire’s
Language Policy.
• Encouraged team-wide completion of The Promise i-learn module across EHI.
• Supported council-led initiatives to recruit Care Experienced young people, including: The
Guaranteed interviews for Care Experienced applicants meeting essential criteria.

Page 39

Title can go here
• Click to edit Master text styles
• Second level
• Third level
• Fourth level
• Fifth level
EHI SERVICE IMPROVEMENT PLAN
For more information, please contact:
Douglas.morrison@renfrewshire.gov.uk
6 Monthly Progress Update
October 2025