Page 1

___________________________________________________________________
To: Communities and Housing Policy Board
On: 19 August 2025
___________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure 
___________________________________________________________________
Heading: Draft Renfrewshire Strategic Housing Investment Plan 2026 to
2031
___________________________________________________________________
1. Summary 
1.1  The draft Renfrewshire Strategic Housing Investment Plan 2026 to 2031
(attached at Appendix 1) sets out the housing investment priorities for projects
across Renfrewshire that will be supported by Scottish Government funding
through the Affordable Housing Supply Programme. 
1.2   Renfrewshire’s Strategic Housing Investment Plan is reviewed and updated
each year in partnership with developing Housing Associations and the
Scottish Government. 
1.3   The draft Renfrewshire Strategic Housing Investment Plan 2026 to 2031 will
be subject to a four-week public consultation.
___________________________________________________________________
2. Recommendations 
It is recommended that the Communities and Housing Policy Board: 
2.1 Approves the draft Renfrewshire Strategic Housing Investment Plan 2026 to
2031, as set out in Appendix 1, for consultation, before a finalised Plan is
presented to the October Communities and Housing Policy Board. 
_________________________________________________________

Page 2

3. Background 
3.1 The draft Renfrewshire Strategic Housing Investment Plan outlines how
Scottish Government funding for affordable housing will be targeted to
achieve the priorities set out in Renfrewshire’s Local Housing Strategy and
support the delivery of a range of affordable housing projects across
Renfrewshire. 
3.2  As part of the Affordable Housing Supply Programme process, the Scottish
Government allocate grant funding, known as Resource Planning
Assumptions, to individual Council areas. 
3.3  The Scottish Government allocated Renfrewshire a Resource Planning
Assumption allocation of £17.311 million in 2025/26, which includes £0.171
million from the National Acquisitions Fund to support affordable housing
providers to acquire suitable homes for social rent on the open market. 
3.4  Resource Planning Assumptions support the delivery of new affordable
homes across Renfrewshire by providing grant support at benchmark rates.
The Scottish Government benchmark grant rates are set at £87,763 for
newbuild Council homes and £95,741 for newbuild social rented homes
delivered by housing association partners. These benchmark rates are flexible
to allow projects to be eligible for higher grant award per property following
detailed assessment. 
3.5  Additional grant funding is also available on top of the grant benchmark rates
where affordable housing developers include specific qualitative design
features related to zero emissions; the installation of automatic fire
suppression systems; electric vehicle charging points; space for home
working; provision of balconies and digital connectivity. 
4.   Draft Renfrewshire Strategic Housing Investment Plan 2026 to 2031 
4.1  The draft Renfrewshire Strategic Housing Investment Plan includes a range of
housing projects that aim to deliver affordable homes of different types and
sizes throughout Renfrewshire to meet people’s housing needs, including
smaller and larger homes for both general and particular needs.  
4.2   The draft Renfrewshire Strategic Housing Investment Plan includes an
affordable housing programme to be delivered by the Council and its Housing
Association partners supported by Scottish Government grant funding. 
4.3  The Resource Planning Assumption for Renfrewshire has only been
confirmed for one year and there remains uncertainty over the future level of
future funding allocations for Renfrewshire. This funding uncertainty means
that delivery timescales for projects may be subject to change.

Page 3

4.4  The draft Strategic Housing Investment Plan has built in capacity to
accelerate affordable housing projects within the programme to take
advantage of any additional funding that may become available to
Renfrewshire or to mitigate any slippage on projects to ensure that all
available funding is fully utilised in supporting the delivery of the right homes
in the right places. 
4.5   The draft Strategic Housing Investment Plan also contains funding provision
for the Council’s own ambitious newbuild development programme in the
Councils Housing Regeneration and Renewal areas. 
4.6  In preparing the draft Strategic Housing Investment Plan, Housing Association
partners proposed projects for consideration which could add to the
programme of affordable housing sites. 
4.7  These sites were considered in relation to amount of funding likely to be
available during the five-year period of the plan, alignment with Renfrewshire
Local Housing Strategy strategic priorities and deliverability of the projects. 
4.8  Provision has been included in the programme to deliver approximately 100
new affordable homes in Paisley town centre. A number of development
opportunities in and around Paisley Town Centre are currently being reviewed
in terms of their viability and deliverability with new projects likely to be
progressed over the next five-year period. 
4.9  One new site has also been added to the draft Strategic Housing Investment
Plan. The site will deliver approximately 30 affordable homes at Rannoch
Road, Johnstone.
___________________________________________________________________
5. Next Steps 
5.1  Consultation on the draft Renfrewshire Strategic Housing Investment Plan
2026 to 2031 will take place between August and September 2025. This will
involve further engagement with all developing housing associations operating
in Renfrewshire, local stakeholder groups such as Community Councils and
tenants and residents’ associations, community planning partners, other
stakeholder groups and Renfrewshire’s residents. In addition, paper copies of
the draft Strategic Housing Investment Plan will be made available at the
Customer Service Centre in Renfrewshire House and local libraries during the
consultation. 
5.2  Following the consultation and taking account of feedback received the
Renfrewshire Strategic Housing Investment Plan 2026 to 2031 will be finalised
and presented to the October meeting of Policy Board for consideration.
___________________________________________________________________
Implications of the Report 
1. Financial - Provision has been made within the Housing Revenue Account
(HRA) Capital Budget in relation to the projects where the Council is the
developing organisation.

Page 4

2. HR & Organisational Development - None. 
3. Community/Council Planning – 
Renfrewshire Community Plan 2017-2027 – the SHIP is considered to align
with the Renfrewshire is Thriving priority as additional housing supply will
encourage people to stay in Renfrewshire and attract new people to settle in
Renfrewshire, and by making sure the infrastructure is in place to support
growth in the local economy and population. 
Renfrewshire Council Plan – the SHIP is considered to align with the Place
outcome by contributing to Renfrewshire having a supply of green, high-quality,
affordable, cross-tenure homes in the right places to meet current and future
demands. 
4. Legal - Conveyancing work associated with land disposals, and any site
assembly and title changes or checks. All new Council contracts for new build
affordable housing will require input from the contracts and project legal
sections at the pre and post tender stages through to award. 
5. Property/Assets - None. 
6. Information Technology - None. 
7. Equality & Human Rights   
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website. 
8. Health & Safety - None. 
9. Procurement - None. 
10. Risk - Scottish Government funding for affordable housing development does
not carry forward into the next financial year. There is therefore a risk that
funding could be lost to Renfrewshire if there is slippage in the delivery of any
of the projects. This is mitigated by ongoing monitoring of projects and the prior
identification of alternative projects for funding to be spent on if slippage occurs. 
11. Privacy Impact - None. 
12. Cosla Policy Position - None.

Page 5

13. Climate Risk - The Draft Strategic Housing Investment Plan aims to deliver
high quality, energy efficient homes in sustainable locations across
Renfrewshire. 
14. Children’s Rights – None. 
_________________________________________________________
(a)  Appendix 1 – Draft Renfrewshire Strategic Housing Investment Plan 2026 to
2031
___________________________________________________________________ 
Author: Alan Williamson, Strategy and Place Manager
Tel: 07811 053968; Email: alan.williamson@renfrewshire.gov.uk

Page 6

1
Draft Renfrewshire Strategic Housing
Investment Plan 2026 to 2031

Page 7

Draft Strategic Housing Investment Plan 2026 to 2031   2
Renfrewshire’s draft Strategic Housing
Investment Plan  
The Scottish Government’s Affordable Housing Supply
Programme (AHSP) sets out a national framework to support the
development of new affordable homes. 
As part of the Affordable Housing Supply Programme process,
local authorities are required to prepare a Strategic Housing
Investment Plan (SHIP) each year that outlines where grant
funding provided to Councils by the Scottish Government will be
used to the support delivery of new affordable homes.   
This draft Renfrewshire Strategic Housing Investment Plan 2026
to 2031 has been informed by discussions with the Scottish
Government and housing association partners operating in
Renfrewshire. 
The Council are inviting local communities, housing associations
and other stakeholders to comment and provide feedback on the
draft plan to help shape the finalised Strategic Housing
Investment Plan. 
Once finalised the Strategic Housing Investment Plan is
submitted to the Scottish Government and a Strategic Local
Programme Agreement (SLPA) for Renfrewshire will form the
basis of individual agreements between the Scottish Government,
Renfrewshire Council and housing association partners on
funding for specific affordable housing projects. 
This draft Strategic Housing Investment Plan can be viewed on
the Council’s website by visiting: 
https://www.renfrewshire.gov.uk/article/4232/Strategic-Housing-
Investment-Plan 
The Strategic Housing Investment Plan 2026-2031 will be
available on the Renfrewshire Council website for four weeks for
interested parties to review and comment on.
Public consultation on this Draft Strategic Housing
Investment Plan will open on 20st August 2025 with
the consultation closing on 19th September 2025. 
Comments should be returned by email or by post
to:
Email: strategyandplace@renfrewshire.gov.uk
Place Strategy Team, Chief Executives Service,
Renfrewshire Council, Renfrewshire House, Cotton
Street, Paisley, PA1 1WB

Page 8

Draft Strategic Housing Investment Plan 2026 to 2031   3
Aligning with Renfrewshire’s Local Housing
Strategy and Development Plan 
The draft Strategic Housing Investment Plan takes account of the
Scottish Government’s Housing and Planning Delivery Framework
(HPDF) which promotes more efficient collaboration between
Housing and Planning Services in relation to the Local Housing
Strategy, Housing Need and Demand Assessment and national
planning policies. 
The draft Strategic Housing Investment Plan provides details of
affordable housing projects in Renfrewshire that will assist in
meeting the strategic priorities of Renfrewshire’s Local Housing
Strategy and support the delivery of the Renfrewshire Local
Development Plan 2. These projects are expected to be
supported by Scottish Government grant funding over the short,
medium and longer term. 
Projects included within the draft Strategic Housing Investment
Plan will assist in providing the right homes in the right places
and contribute to providing safe, warm and energy efficient
homes that meet people’s housing needs and contribute to the
creation of thriving sustainable communities. 
Renfrewshire’s Local Housing Strategy 
The fourth Local Housing Strategy for Renfrewshire was approved
at the Council’s Communities and Housing Policy Board in
October 2023. The Local Housing Strategy 2023-2028 looks to
build on past successes whilst aiming to meet need and demand
for both housing and housing related services. The Local Housing
Strategy includes 5 strategic priorities as shown below: 
1. The supply and delivery of housing is increased across all
tenures to meet the housing needs of different groups and
create attractive and sustainable places.
2. People live in high quality, well managed homes in
sustainable neighbourhoods.
3. Address the challenges of the climate emergency,
delivering homes that are warm, energy efficient and fuel
poverty is minimised.
4. Prevention of homelessness and providing support for
those in housing need.
5. People can live independently for as long as possible in
their own home and the different housing needs of people
across Renfrewshire are being met.

Page 9

Draft Strategic Housing Investment Plan 2026 to 2031   4
Development Plan for Renfrewshire 
Renfrewshire’s current Development Plan consists of National
Planning Framework 4 and the Renfrewshire Local Development
Plan 2021 (LDP2). 
Renfrewshire’s Development Plan supports the development of
new homes that improve affordability, choice, accessibility and
adaptability, including the provision of wheelchair accessible
homes. 
When the Council is assessing projects included as part of this
draft Strategic Housing Investment Plan, it will consider proposals
against the policies in the National Planning Framework 4 and
Renfrewshire LDP2. 
Link/C~urb Housing Association, social rented development, Hawkhead, Paisley   
Sanctuary Scotland, social rented development, Sutherland Street, Paisley

Page 10

Draft Strategic Housing Investment Plan 2026 to 2031   5
The Scottish Government’s Housing Programme  
The Scottish Government ‘Housing to 2040 Strategy’ includes a
target to provide 110,000 affordable homes by 2032 with at least
70% of these homes to be developed for social rent. 
The Scottish Parliament declared a national housing emergency
in May 2024 recognising a range of challenges facing the housing
sector including pressures on homelessness services, high levels
of people in temporary accommodation and a lack of affordable
homes compared to high waiting lists. 
Renfrewshire Council are committed to contribute to addressing
the national housing emergency and affordable housing supply
targets. The Council will continue to work in partnership with the
Scottish Government, our housing association partners, private
developers and the construction industry to increase the delivery
affordable homes throughout Renfrewshire in line with available
funding. 
Resources for Affordable Housing Delivery
The national funding position for the delivery of affordable homes
improved in 2025. In 2025/26, Renfrewshire will receive a funding
allocation in line with past allocations prior to 2024/25. Funding
for 2025/26 is confirmed at £17.311 million compared to £13.181
million allocated in 2024/25. 
Prior to 2024/25, the Scottish Government provided Councils with
multi-year Resource Planning Assumptions (RPA’s) to support
longer term planning and delivery of projects within the Strategic
Housing Investment Plan, providing some degree of certainty to
facilitate longer term planning by housing providers. 
Due to pressures on national budgets, RPA’s in 2024/25 and
2025/26 were issued on a single year basis rather than as multi-year
RPA’s. 
Scottish Government funding allocations beyond 2025/26 are still
to be confirmed. It is likely that funding awards will continue to be
made on a single year basis over the next few years. For the
purpose of programming a five-year plan, the draft Strategic
Housing Investment Plan estimates that an RPA of £15m will be
available each year from 2026/27 to support the delivery of new
affordable homes in Renfrewshire.

Page 11

Draft Strategic Housing Investment Plan 2026 to 2031   6
Scottish Government Grant Benchmarks
New affordable homes developed as part of the Strategic Housing
Investment Plan are funded through a combination of Scottish
Government grant and the developers own financial resources. 
Scottish Government grant support is provided at flexible
benchmark rates for each affordable home developed. The
Scottish Government benchmark grant rate is currently set at
£87,763 for new build social rented Council homes and £95,741
for new build housing association homes. 
These grant rates are flexible which means projects may be
eligible for a higher grant award per property following a detailed
assessment of property mix, needs group, project viability and
development costs. 
Affordable housing providers who develop affordable homes
through a Section 75 Agreement on a larger private sector
housing site are required to deliver homes at the benchmark rate. 
Funding Additional Design Features
In addition to the basic flexible benchmark grant, additional grant
may be provided from the Councils existing Resource Planning
Assumption to support inclusion of specific quality and design
features in new affordable homes, these features include: 
o The delivery of homes to Silver Level of the 2019 Building
Regulations in respect of Energy for Space Heating;
o The provision of balconies within flatted developments where
the provision of private or communal outdoor space is not
possible; 
o The provision of space for home working or study where it is not
possible to incorporate such space within the design of the
homes under current space standards; 
o Digitally enabled homes with tenants able to arrange for an
internet connection without the internet service provider having
to provide additional cabling to the premises;
o The installation of ducting infrastructure for electric vehicle
charge point connectors;  
o Installation of electric vehicle charge points;
o The installation of automatic fire suppression systems; and  
o Installation of heating systems which produce zero direct
emissions at the point of use.

Page 12

Draft Strategic Housing Investment Plan 2026 to 2031   7
Any additional grant required to support inclusion of any of these
features is met from existing funding allocations from the Scottish
Government - this can have an impact on the number of new
affordable homes being delivered as the level of grant funding
required per property increases. 
Funding for Acquisition of Private Housing (Rental Off the
Shelf) and the National Acquisition Programme 
Provision has been included within the Strategic Housing
Investment Plan in recent years to assist affordable housing
providers to purchase appropriate properties for social rent on
the open market by utilising Scottish Government Grant. 
The Scottish Government announced a two-year £80 million
National Acquisitions Fund in April 2024, with additional funding
allocations made to Councils to support open market
acquisitions over the period 2024/25 and 2025/26. 
Renfrewshire Council received £171,000 from this national fund in
2025/26 which was supplemented by funding from the confirmed
Resource Planning Assumption to provide over £1m to support
affordable housing providers to acquire suitable homes for social
rent on the open market. 
This allowance is subject to continuous review depending on the
level of funding made available to Renfrewshire. 
Scottish Government Charitable Bond Funding (ALLIA) 
In addition to funding made available to Renfrewshire through
the confirmed Resource Planning Assumption for 2025/26,
Renfrewshire projects have previously successfully accessed Allia
funding which is funding derived from the Scottish Governments
Charitable Bonds investments programme. This is managed by
Allia, a social investment charity. 
Each year income is generated from bonds which is then used by
the Scottish Government’s More Homes Scotland team to
support increasing the supply of homes by providing one off
grants to affordable housing providers who have projects that
align with the funds criteria. 
These additional funds have been used by Link/C~urb Housing
Association on their development of 68 social rented homes in
Johnstone Castle which are due to complete in June 2026.

Page 13

Draft Strategic Housing Investment Plan 2026 to 2031   8
Council Tax on Empty and Second Homes 
In Renfrewshire, no direct funding is allocated to the affordable
housing programme from revenue raised from empty or second
homes with any revenue raised allocated to the Council’s General
Fund to support wider Council priorities. 
This approach will continue due to ongoing pressures on overall
Council budgets with any ring fencing of funds only likely to be
considered when it is sustainable to do so. 
Williamsburgh Housing Association, social rented development, Albert Road, Renfrew   
Meeting Renfrewshire’s Affordable Housing
Needs and LHS Strategic Priorities
The draft Strategic Housing Investment Plan aims to deliver a
range of new affordable homes across Renfrewshire to meet
housing needs and support the delivery of strategic priorities set
out in the Renfrewshire Local Housing Strategy 2023-2028. 
When developing proposals for new affordable homes, the
Renfrewshire Local Development Plan (LDP2) requires
development to include a range of property types and sizes to
meet different housing needs, including smaller one bedroom
homes and larger three and four bedroom family homes
throughout Renfrewshire. This also includes the delivery of
accessible homes and homes designed to wheelchair accessible
standards. 
All affordable housing must be built to Housing for Varying Needs
standards with flexibility built into the design to allow for future
adaptation and reconfiguration to meet tenant and resident’s
current and future needs.

Page 14

Draft Strategic Housing Investment Plan 2026 to 2031   9
This draft Strategic Housing Investment Plan supports the
development of high quality energy efficient affordable homes, 
recognising that good quality affordable housing can positively
impact peoples’ lives and enhance Renfrewshire’s places. The
Council will continue to work with housing association partners
to determine the most appropriate property mix on a project by
project basis taking account of Council and housing association
waiting list data and the findings from the Glasgow Clyde Valley
Housing Need and Demand Assessment (HNDA3) and the
Renfrewshire Housing Need and Demand study. 
A breakdown of property sizes for recently completed
developments and those that have planning consent is included
in Appendices 1 and 2. 
In recent years, Strategic Housing Investment Plans have
primarily focused on adding to the supply of new build affordable
homes for social rent, this will continue with this new draft
Strategic Housing Investment Plan. 
Whilst the focus will remain on adding to the supply of social
rented homes in Renfrewshire, there is also a recognised need for
alternative affordable housing options such as shared equity
provision and Mid-Market Rent on larger affordable housing sites. 
The inclusion of new affordable homes, other than homes for
social rent, will be considered on a site by site basis taking
account of project viability and the availability of grant funding
from the Scottish Government. 
The delivery of new affordable homes on private sector sites will
continue through the application of Renfrewshire’s Affordable
Housing Policy included in LDP2. 
Williamsburgh Housing Association, social rented development, Cartha Crescent, Paisley

Page 15

Draft Strategic Housing Investment Plan 2026 to 2031   10
Particular Housing Needs 
The Local Housing Strategy emphasises the importance of
providing homes that meet the particular needs of different
groups with a focus on enabling people to live independently for
as long as possible in their own homes and also in preventing
homelessness. 
In recent years, Link/C~urb Housing Association completed a
mixed general and particular needs social rented development in
Paisley Town Centre that included 20 amenity standard homes
and 5 fully wheelchair accessible homes. In March 2025, Loretto
Housing Association also completed 4 fully wheelchair accessible
homes as part of their East Lane development in Paisley. 
This draft Strategic Housing Investment Plan includes projects
that will continue to contribute to meeting identified particular
needs in Renfrewshire with mixed amenity housing and purpose
built particular needs homes expected to be included across
projects supported by grant funding. 
Link/C~urb Housing Association, social rented General and Particular Needs, Paisley Town Centre   
When planning new developments, early stage discussions will
take place with Renfrewshire Health and Social Care Partnership
(HSCP) to ensure that projects are viable, sustainable and
capable of meetings tenants and residents’ needs. 
Wheelchair Accessible Housing 
When preparing proposals for new build developments, housing
providers will be required to design homes that are able to meet
occupants changing needs over time as well as the needs of an
ageing population by incorporating design features that promote
accessible and adaptable homes.

Page 16

Draft Strategic Housing Investment Plan 2026 to 2031   11
Targets for the inclusion of wheelchair accessible homes as part
of new build developments have been agreed and are included
within the current Local Housing Strategy. 
The Local Housing Strategy requires that:
New residential proposals must provide a minimum 10% of all
dwellings designed to be easily adaptable for residents who are
wheelchair users; and 
5% of all new homes must be designed to wheelchair accessible
standards. 
Rapid Rehousing Transition Plans 
Renfrewshire Council’s Rapid Rehousing Transition Plan (RRTP)
details how those who are homeless will be provided with settled
accommodation more quickly; spend reduced time in temporary
accommodation and have more access to up-scaled support. 
The Strategic Housing Investment Plan aims to support the
delivery of homes to meet the requirements of different needs
groups, household types and sizes. 
The Council together with Renfrewshire Health and Social Care
Partnership employ the Housing First Initiative to support those
with multiple and complex needs, who are socially excluded and
who have experienced repeat homelessness, with the Housing
First Initiative an integral part of the Rapid Rehousing Transition
Plan, delivered by Turning Point Scotland’s Support Workers to
provide tenancies, in conjunction with wrap-around support
packages and provide assistance to access Health and Social
Care Services. 
Within Renfrewshire, both the Council and its housing association
partners continue to prioritise lets to homeless households with
52% of all available Council social rented homes and 39% of all
available housing association homes let to homeless households
in 2024/25. This includes lets to both existing and new build social
rented housing with available properties allocated in line with
applicant housing need and the housing providers allocation
policy.

Page 17

Draft Strategic Housing Investment Plan 2026 to 2031   12
Child Poverty  
New housing development has a key role in tackling child poverty
through supporting the delivery of a range of property types and
sizes that meet the needs of families, 
and the creation of high quality energy efficient homes in
sustainable communities that support health, wellbeing and
educational attainment. 
This draft Strategic Housing Investment Plan aligns with the
priority actions of Renfrewshire’s Local Child Poverty Action
Report which aims to support the next generation to thrive within
high quality affordable and accessible housing. 
Early discussions with housing association partners ensure that
the housing mix proposed for each project takes account of
housing waiting lists with this information reflected in terms of
house sizes and any agreed property mix. 
This approach should ensure that smaller homes are included to
meet the housing needs of individuals and smaller households as
well as larger family homes that meet the needs of larger families
and households with children to help address the needs of low-
income families. 
It is recognised that a wide range of property types and sizes are
required to meet identified housing needs on new affordable
housing developments. As plans progress on individual sites and
it becomes clearer what individual sites can accommodate, the
importance of including larger family homes will be central to
discussion with affordable housing providers in receipt of Scottish
Government grant funding. This approach will support the aims
of Renfrewshire’s Local Child Poverty Action Plan. 
Key Worker Housing 
Renfrewshire Council does not have a key worker policy in
relation to access to affordable housing and has no specific
identified housing need for key worker housing locally. Projects
delivered through the Strategic Housing Investment Plan process
are accessible to all households with homes allocated in line with
the developing landlords local allocation policy.

Page 18

Draft Strategic Housing Investment Plan 2026 to 2031   13
Refugee Resettlement 
Renfrewshire Council continues to work with the Scottish
Government and Convention of Scottish Local Authorities
(COSLA) to determine what Renfrewshire may provide in terms of
housing stock to support resettlement and asylum dispersal
programmes. 
So far, most of the accommodation required has been smaller
with one or two bedroom properties being used due to the
arriving household size. 
Renfrewshire has continued to play its part in the national
response by providing ongoing support. The number of homes
required to support Renfrewshire’s contribution towards the
national resettlement scheme will be kept under review. 
Gypsy/Travellers Provision 
The Council continues to review the need to allocate land or
identity and progress appropriate projects to meet any identified
housing needs of the Gypsy/Traveller community in Renfrewshire
taking account of the Scottish Government’s Improving the lives
of Scotland’s Gypsy/Travellers 2 Action Plan 2024-2026 published
in September 2024. 
The Council notes the Scottish Government’s decision to manage
potential Gypsy/Traveller sites and associated funding allocations
alongside the existing Resource Planning Assumption model
traditionally used to support settled development. 
This approach will support longer term planning and delivery of
Gypsy/Traveller sites in Renfrewshire should a need be identified. 
At present, no projects are included within the draft Strategic
Housing Investment Plan. Should a requirement for
accommodation/sites be identified, future updates of the
Strategic Housing Investment Plan will include details of these
projects. 
Travelling Showpeople Provision 
There are currently no permanent Travelling Showpeople sites in
Renfrewshire. Through delivery of the strategic priorities included
within the Local Housing Strategy 2023-2028 and the use of the
Scottish Governments Accommodation Needs Toolkit (when
available), the Council will identify if there is a need to allocate
land to meet the housing needs of Travelling Showpeople with
any identified need addressed through the Renfrewshire Local
Development Plan/Action Delivery Programme.

Page 19

Draft Strategic Housing Investment Plan 2026 to 2031   14
Renfrewshire Council Regeneration and Renewal
Programme 
This draft Strategic Housing Investment Plan continues to
support the Council’s new build programme following the
completion of new Council homes in Bishopton, Johnstone and
at Ferguslie Park in Paisley. 
Over the period of the next Strategic Housing Investment Plan,
Renfrewshire Council will continue to invest in its own new build
social rented development programme to deliver high quality
energy efficient homes to replace existing low demand housing or
to add to the supply of Council housing with plans progressing to
deliver homes in identified regeneration areas. 
This draft Strategic Housing Investment Plan includes these new
build Council projects with Scottish Government grant funding
expected to be made available to supplement the Council’s own
investment in these new homes for social rent. 
As well as adding to the supply of new Council housing, the
Council will make best use of its existing housing stock through
targeted and enhanced investment – including works to the
external fabric of properties as well as environmental
improvements. 
More information on the Council’s Regeneration and Renewal
Programme can be found on the Council’s website by visiting: 
Housing regeneration in Renfrewshire – Renfrewshire Website 
Town Centre Living
As with previous Strategic Housing Investment Plans, investing in
town centre residential development remains a key objective of
this draft Strategic Housing Investment Plan. 
Investment in affordable housing to support the wider
regeneration of our town centres helps deliver population
growth, improve the vitality and environment of town centres and
can help support the creation of sustainable communities.
Significant cross tenure new build development has taken place
in town centres in recent years. In preparing the draft Strategic
Housing Investment Plan there has been significant interest
expressed by Housing Association partners to deliver new
affordable homes primarily in and around Paisley Town Centre. 
A project line is included within Appendix 3 of this draft Strategic
Housing Investment Plan in order to support further affordable
housing development in Paisley town centre.

Page 20

Draft Strategic Housing Investment Plan 2026 to 2031   15
Provision is included in the programme to deliver approximately
100 new affordable homes in and around the town centre should
funding be confirmed by the Scottish Government. 
A number of development opportunities are currently being
reviewed in terms of their viability and deliverability with new
projects likely to be progressed over the next five-year period. 
Delivering New Affordable Homes in North and West
Renfrewshire 
Affordable housing development in the North and West
Renfrewshire villages can be challenging as most of the available
land is in private ownership. 
The Council recognises that there is an unmet demand and
limited supply of affordable housing in these areas. The Council
will continue to pursue all opportunities to increase the supply of
affordable housing in both North and West Renfrewshire, working
with housing association partners and private developers to
include social rented housing as either standalone developments
or as part of mixed tenure private sector developments. 
Affordable housing provision within Dargavel Village will continue
with 138 affordable homes completed so far by the Council and
Loretto Housing Association for social rent. 
Loretto Housing Association are currently progressing a two stage
development of a further 62 social rented homes in partnership
with Dundas Homes. The first stage of development includes 46
homes which are due to complete in March 2027 with a further 16
homes also to be progressed at this location. 
Discussions are ongoing with Loretto Housing Association,
Sanctuary Scotland and private developers to deliver a further 43
homes for social rent within Dargavel Village across two sites. 
In West Renfrewshire, three private sector sites that are allocated
for residential use in the Renfrewshire Local Development Plan
2021 (LDP) offer the potential to deliver new social rented homes
in Houston, Kilbarchan and Lochwinnoch through utilising the
LDP’s affordable housing policy, subject to planning approval.

Page 21

Draft Strategic Housing Investment Plan 2026 to 2031   16
The Council will continue to work with our housing association
partners to increase the supply of social rented housing in West
Renfrewshire, taking account of housing waiting list data and the
outputs from the Renfrewshire Housing Need and Demand study
prepared in support of the current Renfrewshire Local Housing
Strategy 2023-2028.
Tackling the Climate Crisis in Renfrewshire 
Tackling the Climate Crisis continues to be a priority for
Renfrewshire Council with work progressing as part of
Renfrewshire’s Plan for Net Zero and Local Heat and Energy
Efficiency Strategy. 
It is acknowledged that the changing climate has a direct impact
on Renfrewshire’s housing and that some residents will be more
vulnerable to this than others. 
Both Renfrewshire Council and its housing association partners
are incorporating additional energy efficiency measures as part of
new build design which will actively target reduced carbon
emissions from new build development. 
Projects included within this draft Strategic Housing Investment
Plan aim to tackle fuel poverty by maximising opportunities for
innovative energy efficient development, with greener measures
included within new build developments. 
Bringing Empty Homes Back into use
The Council has a dedicated ‘More Homes Officer’ who works
with owners of long-term empty properties to provide advice and
assistance to support owners to bring long term empty properties
back into productive use. 
The Council’s More Homes Officer also manages the Councils buy
back and acquisitions scheme where properties that meet
strategic objectives may be purchased and added to the Council’s
lettable housing stock. 
Over the last five years, the Council’s More Homes Officer has
successfully helped to bring more than 60 long term empty
homes back into the effective housing supply with these homes
adding to the supply of available homes in the affordable and
private sectors.

Page 22

Draft Strategic Housing Investment Plan 2026 to 2031   17
Link/C~urb Housing Association, mixed tenure development, Houston 
Programme Management and Project
Prioritisation 
This draft Strategic Housing Investment Plan splits projects into
three groups: 
(i) ‘Core Projects’; 
(ii) ‘Shadow Projects’ and 
(iii) ‘Longer Term Projects’. 
Projects within each group are shown in Appendix 3. 
The methodology used to prioritise projects is based on the
potential availability of Scottish Government grant funding as
well as the developers’ ability to progress each project at key
milestones in term of site acquisition, design work, planning
approval, procurement and potential site start date. 
This approach supports the programming of individual projects in
terms of anticipated grant availability and the potential delivery
timescales. 
These projects together form the proposed Strategic Housing
Investment Plan with projects being delivered as funding
becomes available. 
Delivery timescales are dependent on future funding allocations
from the Scottish Government and the developer’s own capacity
to progress sites.   
Projects included within the ‘Core Projects’ group will be
progressed in the earlier years of the programme.

Page 23

Draft Strategic Housing Investment Plan 2026 to 2031   18
Projects included within the ‘Shadow Projects’ group will be
progressed as ‘Core Projects’ complete or as any additional
funding becomes available or where the developing landlords has
the capacity to ‘front fund’ projects to allow projects to proceed
earlier than otherwise possible. 
Projects included in the ‘Longer Term Projects’ group are
expected to progress over the longer term with grant funding only
likely to become available towards the end of or indeed beyond
the current five year Strategic Housing Investment Plan period. 
In terms of front funding, the Council or housing association
partner may initially fund project development costs from their
own resources, with grant being paid to developing organisation
at the first available opportunity as funding becomes available. 
The use of a three tier project priority approach supports the
effective management of available resources whilst permitting
some flexibility that assists in addressing any slippage of projects
in any given year. 
Projects in the ‘Shadow Projects’ group and in particular the
‘Longer Term Projects’ group may require extended lead in times
to allow for site investigation works, value engineering works, site
assembly or to arrange the necessary private finance to enable a
development to proceed. All of which influence how projects are
prioritised within the programme with all projects subject to
regular review. 
The Strategic Housing Investment Plan development programme
must be capable of adapting and responding to both delays in
the delivery of projects and new affordable housing development
opportunities to ensure that all funding available to Renfrewshire
can be fully utilised. 
This may result in existing project delivery timescales changing or
new opportunities being added to the programme between
annual Strategic Housing Investment Plan updates.   
Any additional projects brought forward must align with the
strategic priorities of the Local Housing Strategy with a clear
funding mechanism in place that does not impact other ‘Core
Projects’.

Page 24

Draft Strategic Housing Investment Plan 2026 to 2031   19
Delivery 
Both the Council and its housing association partners will
continue to look for efficiencies in construction methods and
work with design teams to determine the suitability of non-
traditional construction methods for projects included within this
draft Strategic Housing Investment Plan. 
The Council will continue to explore options for joint working
around innovative delivery mechanisms that support the delivery
of affordable homes throughout Renfrewshire. 
Projects included within the ‘core’ element of the draft Strategic
Housing Investment Plan are either currently progressing on site
or are due to start on site soon with site investigation works
already completed for these projects.   
Site investigation works for the majority of projects in the
‘shadow’ and ‘longer term’ programme have still to take place
with the results of these investigations informing project viability. 
Housing Infrastructure Fund 
The Housing Infrastructure Fund provides Councils and housing
association partners with additional grant to support the
unlocking of challenging sites where the scale and nature of 
infrastructure costs would prevent these sites from being
progressed as part of the Strategic Housing Investment Plan. 
In recent years, a number of Renfrewshire projects have
successfully accessed the Housing Infrastructure Fund with
housing association partners continuing to look at options to bid
for support from the Housing Infrastructure Fund as and when
required. 
At present, no project developer within this draft Strategic
Housing Investment Plan is looking to access Housing
Infrastructure Fund support, however this may change as
developments conduct more detailed site investigations. 
Vacant and Derelict Land Investment Programme 
At present, no project within this draft Strategic Housing
Investment Plan is currently utilising or been identified to seek
funding from the Scottish Government’s Vacant and Derelict Land
Investment Programme.

Page 25

Draft Strategic Housing Investment Plan 2026 to 2031   20
Monitoring Project Progress 
To monitor progress in delivering individual projects and ensure
that resources are managed effectively, a range of project
management activities are employed. This includes:  
 ongoing liaison between services within the Council and
between the Council and housing association partners on
specific projects; 
 quarterly tripartite meetings between the Council, individual
housing association partners and the Scottish Government; 
 regular internal officer group meetings to review progress in
delivering the overall development programme; and,
 a monthly review of project progress with all developers of
affordable housing. 
Draft Strategic Housing Investment Plan
Appendices 
Appendix 1 details progress with projects currently on site as well
as proposals for future projects identified as part of this draft
Strategic Housing Investment Plan.  
Appendix 2 shows recent affordable housing completions with a
breakdown of property size delivered on each site. 
Appendix 3 lists projects that are currently progressing and/or
expected to require grant funding as part of the Strategic Housing
Investment Plan process.

Page 26

Draft Strategic Housing Investment Plan 2026 to 2031   21
Equalities 
This draft Strategic Housing Investment Plan 2026-2031 includes
housing provision for a range of different needs groups including
housing for older people and those with physical disabilities. 
This draft Strategic Housing Investment Plan has been informed by
ongoing partnership working with the Health and Social Care
Partnership (HSCP) to ensure that projects take account of
opportunities to deliver housing that meets the needs of a range of
households with specific needs. 
In line with The Equality Act 2010 and the associated protected
characteristics, an Equality and Human Rights Impact Assessment
has been prepared alongside the preparation of this draft
Strategic Housing Investment Plan to identify the likely or actual
effects of it on people. 
The assessment includes identifying where there will be a positive
impact and further opportunities to promote equality. The
assessment did not identify any negative impacts on people in
relation to this draft Strategic Housing Investment Plan. 
Appendix 1: Renfrewshire Affordable Housing Project Updates 
1A: Projects completed in financial year 2024/25 
Development Units Status Comment
Napier Street, Linwood 51 Completed October
2024
51 social rented homes from Sanctuary Scotland Housing Association that add to
the affordable housing supply in Linwood. This project completed in October 2024.
Property sizes included 37 x 2 Bed, 14 x 3 Bed properties. 
East Lane, Paisley Town
Centre  48 Completed March 2025
48 social rented homes by Loretto Housing Association which add to the affordable
housing supply in central Paisley. 
Property sizes included 16 x 1 Bed, 32 x 2 Bed properties.

Page 27

Draft Strategic Housing Investment Plan 2026 to 2031   22
Development Units Status Comment
Hawkhead, Paisley 5 Completed March 2025
5 New build terraced house acquisitions by Link/C~urb Housing Association as part
of a large mixed tenure development. These complement 30 new social rented flats
being developed at this location by Link Group. 
Property sizes included 5 x 3 Bed properties. 
1B: Projects completed in financial year 2025/26, currently on site or due to start on site 
Development Units Status Comment
Hawkhead, Paisley 30 Completed May 2025
30 social rented homes by Link/ C~urb Housing Association which add to the affordable
housing supply in Paisley. 
Property sizes include 30 x 2 Bed properties. 
Paisley West End,
Sutherland Street 35 Completed June 2025
35 social rented homes Sanctuary Scotland which add to the affordable housing supply
in central Paisley.
Property sizes include 28 x 2 Bed, 7 x 3 Bed properties. 
Cartha Crescent,
Paisley 33 Completed July 2025
33 social rented homes by Williamsburgh Housing Association which add to the
affordable housing supply in central Paisley. 
Property sizes include 12 x 2 Bed, 21 x 3 Bed properties. 
Johnstone Castle
Phase II 68 On site, due to
complete June 2026
Link/C~urb Housing Association are onsite delivering the second phase of affordable
housing in Johnstone Castle. This development will provide 68 homes for social rent as
well as infrastructure and green spaces. 
Property sizes include 40 x 2 Bed, 28 x 3 Bed properties.

Page 28

Draft Strategic Housing Investment Plan 2026 to 2031   23
Development Units Status Comment
Orchard Street,
Paisley   50
On site, due to
complete September
2026
Work is progressing on the Comprehensive Tenement Improvement (CTI) project at
Orchard Street/Causeyside Street, Paisley following 5 blocks of flats being designated as
a Housing Renewal Area (HRA) in March 2017. The overall development is expected to
complete in September 2026. 
Property sizes include 37 x1 bed, 13 x 2 bed properties 
Bishopton, Phase 3A 46 On site, due to
complete March 2027
Loretto Housing Association are now on site developing 46 new homes for social rent
that will add to the affordable housing supply in Dargavel Village, Bishopton. This site is
expected to provide 62 new homes for social rent across two phases (3A & 3B) with
Phase 3B expected to include 16 additional homes for social rent following completion
the 46 new homes that comprise Phase 3A. 
Property sizes include 12 X 1 bed, 27 x 2 bed, 7 x 3 bed properties
Gallowhill, Paisley 65
On site, due to
complete December
2026
Renfrewshire Council commenced on site in August 2025 and developing 65 new
Council homes for social rent that will add to the affordable housing supply in the
Gallowhill area. The overall development is expected to complete in December 2026. 
Property sizes include 9 x 1 bed, 23 x 2 bed, 26 x 3 bed, 4 x 4 bed, 3 x 5 bed properties
Howwood Road,
Johnstone (Site 1 of 2) 70 Off site, Due to start on
site in August 2025
Renfrewshire Council regeneration area. Plans are being progressed to deliver 70 new
Council homes in this first phase of development in the Howwood Road Area Johnstone
with a site start expected around August 2025. 
Property sizes include 11 x 1 bed, 29 x 2 bed, 19 x 3 bed, 11 x 4 bed properties
Bishopton, Phase 4 20 Off site, Due to start on
site in September 2025
Loretto Housing Association are progressing plans for 20 new social rented homes that
will add to the affordable housing supply in Dargavel Village, Bishopton. 
Property sizes include 20 x 2 bed properties

Page 29

Draft Strategic Housing Investment Plan 2026 to 2031   24
1C: Projects expected to start on site in 2026/27 or later or when a projected site start date has still to be confirmed 
Development Units Status Comment
West End - Remaining Sites 120 Off site, Start date tbc
Sanctuary Scotland are progressing plans for approximately 120 affordable new
homes developed as part of the regeneration of Paisley’s West End.
Property sizes still to be confirmed. 
Bishopton, Phase 3B  16 Off site, Due to start on
site around January 2027
Loretto Housing Association will progress development of 16 new homes for
social rent following the completion of Bishopton Phase 3A which will provide an
initial 46 new homes for social rent.
Property sizes still to be confirmed. 
Bishopton, Phase 5 23 Off site, Start date tbc
Sanctuary Scotland Housing Association are progressing plans for 23 new social
rented homes that will add to the affordable housing supply in Dargavel Village,
Bishopton.
Property sizes still to be confirmed. 
Springbank, Paisley (Phase 1
of 2)  65 Off site, Due to start on
site around January 2027 
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 65 new Council homes in this first phase of development in the
Springbank Road Area of Paisley. 
Property sizes still to be confirmed. 
Foxbar Rivers, Paisley 45 Off site, Due to start on
site around January 2027
This social rented development of around 45 homes by Renfrewshire Council will
add to the affordable housing supply in the Foxbar area of Paisley and bring
vacant sites back in to use. 
Property sizes still to be confirmed. 
Broomlands & Carbrook
Street, Paisley 43 Off site, Due to start on
site around January 2027
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 43 new Council homes in Paisley’s Broomlands and Carbrook Street area. 
Property sizes still to be confirmed.

Page 30

Draft Strategic Housing Investment Plan 2026 to 2031   25
Development Units Status Comment
Thrushcraigs, Paisley 50 Off site, Due to start on
site around July 2027
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 50 new Council homes in the Thrushcraigs Area of Paisley. 
Property sizes still to be confirmed. 
Howwood Road, Johnstone
(Site 2 of 2) 60 Off site, Due to start on
site around January 2028
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 60 new Council homes in this second phase of development in the
Howwood Road Area of Johnstone. 
Property sizes still to be confirmed. 
West Renfrewshire Villages  62 Off site, Start date tbc
Three potential sites identified in Lochwinnoch, Houston and Kilbarchan for
progression by Housing Association partners for approximately 62 social rented
homes as part of mixed tenure developments proposed in West Renfrewshire. 
Property sizes still to be confirmed. 
Flourish Road, Erskine, Older
Persons Housing
Reprovisioning  
18 Off site, Due to start on
site around August 2026 
Bridgewater Housing Association are progressing plans for a new purpose built
older persons housing development of around 18 units that will replace existing
scattered older persons housing provision across Erskine. 
Property sizes still to be confirmed. 
Gibson Crescent, Johnstone 28 Off site, Start date tbc
Options are being explored for this social rented development of around 28
social rented homes by Williamsburgh Housing Association in Johnstone. 
Property sizes still to be confirmed. 
Springbank, Paisley (Phase II)  35 Off site, Due to start on
site around January 2030
Renfrewshire Council regeneration area. Plans are being progressed to deliver
around 35 new Council homes in this second phase of development in the
Springbank Road Area of Paisley. 
Property sizes still to be confirmed.

Page 31

Draft Strategic Housing Investment Plan 2026 to 2031   26
Development Units Status Comment
Stirling Drive, Linwood  65 Off site, Start date tbc
Options are being explored for this social rented development of around 65
homes by Linstone Housing Association that will add to the affordable housing
supply in Linwood. 
Property sizes still to be confirmed. 
Ryefield, Johnstone  36 Off site, Start date tbc
Options are being explored for this social rented development of approximately
36 homes by Linstone Housing Association in Johnstone. 
Property sizes still to be confirmed. 
MacDowall Street, Johnstone  35 Off site, Start date tbc
Options are being explored to identify an affordable housing provider to develop
this gap site for affordable housing. 
Property sizes still to be confirmed. 
Rannoch Road, Johnstone 30 Off site, Start date tbc
Options are being explored for this social rented development of around 30
homes by Loretto Housing Association in Johnstone. 
Property sizes still to be confirmed.
Garthland Lane, Paisley 32 Off site, Start date tbc
This social rented development of around 32 homes by Renfrewshire Council will
add to the affordable housing supply in central Paisley.
Property sizes still to be confirmed. 
Foxbar Rivers, Paisley 45 Off site, Start date tbc
This social rented development of around 45 homes by Paisley Housing
Association will add to the affordable housing supply in the Foxbar area of
Paisley and bring vacant sites back in to use.
Property sizes still to be confirmed. 
Westburn
Avenue/Blackstoun Road,
Ferguslie Park, Paisley
22 Off site, Start date tbc
This social rented development of around 22 homes by a developer still to be
identified will add to the affordable housing supply in the Ferguslie Park area of
Paisley and bring a vacant site back in to use.

Page 32

Draft Strategic Housing Investment Plan 2026 to 2031   27
Development Units Status Comment
Property sizes still to be confirmed. 
East Lane, Paisley (Site 2 of 2) 30 Off site, Start date tbc
Site identified for longer term development. 
Property sizes still to be confirmed. 
Supported Housing, Paisley
(Site tbc) 14 Off site, Start date tbc
Efforts will continue to identify a potential site for supported housing in Paisley
Town Centre. 
Property sizes still to be confirmed.
Paisley Town Centre
(including edge of centre
locations, future sites tbi)
100 Off site, Start date tbc
A number of opportunities in and around the town centre are currently being
reviewed in terms of their viability and deliverability with new projects likely to be
progressed over the next five-year period
West Renfrewshire Villages  tbc Off site, Start date tbc Efforts will continue to identify additional potential site(s) for affordable housing
in West Renfrewshire to promote mixed tenure communities. 
North Renfrewshire Villages  tbc Off site, Start date tbc Efforts will continue to identify additional potential site(s) for affordable housing
in North Renfrewshire to promote mixed tenure communities. 
Local Development Plan Affordable Housing Policy Future
Requirements
Subject to the availability of Scottish Government grant, this draft Strategic
Housing Investment Plan will support the development of new affordable homes
within private sector sites as part of Renfrewshire’s Affordable Housing Policy.

Page 33

Draft Strategic Housing Investment Plan 2026 to 2031   28
Completions between 2020 and 2025 & estimated completions 2025/26 Appendix 2
2020/21       
Link/C~urb Smithhills Street, Paisley 26x 2 Bed 26  
Renfrewshire Council Bishopton Phase I 10x 1 Bed, 34x 2 Bed, 34x 3 Bed, 2x 4+ Beds 80  
Williamsburgh HA Milliken Road, Kilbarchan 14x 1 Bed, 4x 2 Bed 18 124
2021/22     
Renfrewshire Council Johnstone Castle, Johnstone 4x 1 Bed, 67x2 Bed, 20x 3 Bed, 4x 4+ Beds 95  
Link/C~urb Amochrie Road, Foxbar, Paisley 34x 2 Bed, 2x 3 Bed 36  
Link/C~urb Thrushcraigs Phase II (St Ninians), Paisley 12x 2 Bed, 11x 3 Bed  23  
Paisley HA Westerfield House, Paisley 16x 1 Bed  16 170
2022/23     
Sanctuary/Paisley HA Glenburn, Paisley 8x 1 Bed, 73x 2 Bed, 50x 3 Bed  131  
Link/C~urb Millarston, Paisley 16x 1 Bed, 62x 2 Bed, 2x 3 Bed, 19x 4+ Beds 99  
Renfrewshire Council Auchengreoch Road, Johnstone 8x 1 Bed, 17x 2 Bed, 12x 3 Bed, 2x 4+ Beds 39  
Loretto Bishopton Phase II 12x 1 Bed, 14x 2 Bed, 32x 3 Bed 58  
Williamsburgh HA Albert Road, Renfrew 13x 2 Bed, 29x 3 Bed  42 369
2023/24    
Renfrewshire Council Ferguslie Park, Paisley 22x 1 Bed, 67x 2 Bed, 10x 3 Bed, 2x 4+ Beds 101 
Link/C~urb Abbey Quarter Phase 4 (AQP4), Paisley 10x 1 Bed, 71x 2 Bed  81 
Link/C~urb Woodend House, Houston  14x 2 Bed 14 196
2024/25    
Sanctuary Napier Street, Linwood  37x 2 Bed, 14x 3 Bed  51 
Loretto East Lane, Paisley 16x 1 Bed, 28x 2 Bed  48 
Link/C~urb Hawkhead, Paisley 5x 3 Bed  5 104    
963
2025/2026 - Estimated Completions  
Link/C~urb Hawkhead, Paisley 30 x 2 Bed 30  
Sanctuary Sutherland Street, Paisley  28x 2 Bed, 7x 3 Bed  35  
Williamsburgh HA Cartha Crescent, Paisley 12x 2 Bed, 21x 3 Bed 33 98

Page 34

29
Appendix 3      £ Million   
Homes 
Total
Est
Grant
Req
(£M) 
Est Spend
by of End
March
2026 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req
Core Projects     (Yr 1)
2026/27
(Yr 2)
2027/28
(Yrs 3-5)
2028/29-
2030/31
(Yrs 6+)
2031/32 &
Beyond
Johnstone Castle Phase II*  68  £1.864  £1.864  N/A N/A N/A N/A
Cartha Crescent   33  £3.233  £3.233  £0.000 £0.000 £0.000 £0.000
Orchard St/Causeyside St (HRA)  50  £5.003  £5.003  £0.000 £0.000 £0.000 £0.000
Bishopton Phase 3A  46  £5.475  £5.475  £0.000 £0.000 £0.000 £0.000
Bishopton Phase 4  20  £1.915  £1.915  £0.000 £0.000 £0.000 £0.000
Gallowhill, Paisley  65  £9.634  £4.227  £5.407 £0.000 £0.000 £0.000
Howwood Road, Johnstone (Site 1 of 2)  70  £10.431  £3.106  £7.325 £0.000 £0.000 £0.000
West End - Remaining Sites  120  £11.489  £6.341  £1.764 £1.764 £1.620 £0.000
Open Market Acquisitions   tbc  £1.400  £1.400  tbc tbc tbc tbc
Affordable Housing Policy Future Reqs  tbc  tbc  tbc  tbc tbc tbc tbc
*Funded without Grant from RPA   472  £50.444  £32.564  £14.496 £1.764 £1.620 £0.000

Page 35

Draft Strategic Housing Investment Plan 2026 to 2031   30
Homes 
Total
Est
Grant
Req
(£M) 
Est Spend
by of End
March
2026 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req
Shadow Projects     (Yr 1)
2026/27
(Yr 2)
2027/28
(Yrs 3-5)
2028/29-
2030/31
(Yrs 6+)
2031/32 &
Beyond
Bishopton Phase 3B  16  £1.532  £0.000  £1.532 £0.000 £0.000 £0.000
Bishopton Phase 5  23  £2.500  £0.000  £2.500 £0.000 £0.000 £0.000
Springbank, Paisley (Phase 1 of 2)   65  £5.706  £1.194  £0.000 £0.500 £4.012 £0.000
Foxbar Rivers, Paisley  45  £3.949  £0.050  £0.000 £0.500 £3.399 £0.000
Broomlands & Carbrook Street, Paisley  43  £6.130  £0.412  £0.000 £0.000 £5.718 £0.000
Thrushcraigs, Paisley  50  £4.388  £0.119  £0.000 £0.500 £3.769 £0.000
Howwood Road, Johnstone (Site 2 of 2)  60  £5.266  £0.444  £0.000 £0.500 £4.322 £0.000
West Renfrewshire Villages (3 sites)   62  £5.936  £0.000  £0.000 £5.936 £0.000 £0.000
Older Persons Housing, Erskine  18  £2.455  £0.000  £0.000 £2.000 £0.455 £0.000
Gibson Crescent, Johnstone   28  £2.681  £0.000  £0.000 £0.000 £2.681 £0.000
Springbank, Paisley (Phase II)   35  £3.072  £0.351  £0.000 £0.000 £2.722 £0.000
Rannoch Road, Johnstone  30  £2.872  £0.000  £0.000 £2.000 £0.872 £0.000
Paisley Town Centre(including edge of
centre) - sites tbc  100  £9.580  £0.000  £0.000 £3.000 £6.580 £0.000
Stirling Drive, Linwood   65  £10.818  £0.859  £0.000 £0.000 £9.959 £0.000
Ryefield, Johnstone   36  £5.983  £0.150  £0.000 £0.000 £5.833 £0.000  
676  £72.868  £3.579  £4.032 £14.936 £50.322 £0.000

Page 36

Draft Strategic Housing Investment Plan 2026 to 2031   31
Homes 
Total Est
Grant
Req
(£M) 
Est Spend
by of End
March
2026 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req 
Est Grant
Req
Longer Term Projects     (Yr 1)
2026/27
(Yr 2)
2027/28
(Yrs 3-5)
2028/29-
2030/31
(Yrs 6+)
2031/32 &
Beyond
Foxbar Rivers, Paisley  45  £4.308  £0.000  £0.000 £0.000 £4.308 £0.000
MacDowall Street, Johnstone   35  £3.351  £0.000  £0.000 £0.000 £3.351 £0.000
Garthland Lane, Paisley  32  £3.033  £0.225  £0.000 £0.000 £2.808 £0.000
Westburn Avenue, Ferguslie Park, Paisley  22  £1.931  £0.143  £0.000 £0.000 £0.000 £1.788
East Lane, Paisley (Site 2 of 2)  30  £2.872  £0.000  £0.000 £0.000 £0.000 £2.872
Supported Housing, Paisley (Site tbc)  14  £1.340  £0.000  £0.000 £0.000 £1.340 £0.000
West Renfrewshire Villages Opportunities  tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc
North Renfrewshire Villages Opportunities    tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc  
178  £16.835  £0.368  £0.000 £0.000 £11.807 £4.660              
1326  £140.147  £36.511  £18.528 £16.700 £63.749 £4.660

Page 37