Electric Vehicle Charging Strategy

Argyll and Bute Council · 10 December 2025
Back to Oban Lorn & The Isles Area Committee — 10 December 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Electric Vehicle
Charging Strategy
MEMBER SEMINAR
20TH OCTOBER 2025
This Photo by Unknown Author is
licensed under CC BY-SA-NC
This Photo by Unknown Author is licensed
under CC BY

Page 2

Background
 2022 – Strategy approved: aim to fill geographic
gaps and achieve equitable coverage.
 2023–24 – Expansion plan and methodology
developed – 55 sites identified
 2024 – Committee reaffirmed direction while
awaiting EVIF funding.

Page 3

Current expansion plan
 In 2022 the Council approved an EV
Charging Strategy based on two delivery
themes:
 Charging on the Move – ensuring drivers
can travel through Argyll confidently.
 Destination Charging – providing chargers
where people dwell.
 That approach assumed further funding
would follow

Page 4

Funding secured
 We now have £1.033million
secured for the next phase – so
the key question is how best to
invest it?
 In Dec 2022 our 55-site plan
was estimated at £1.65million,
based on previous average
costs plus inflationary
adjustment

Page 5

A hub-based approach
 The original 55-site plan (Dec 2022) costed at £1.65m can’t be
delivered in full with the £1.033m now secured.
 We therefore need to prioritise investment where it has the
greatest impact.
 We are therefore proposing a hub-based approach – clusters
of chargers in key towns and island centres – providing:
 Reliability: multiple chargers reduce the risk of faults or queues.
 Better use of funds: higher usage = better cost recovery and
maintenance value.
 Visitor and local benefit: located where people already spend
time and money.
 Platform for future growth: once hubs are established, we can
extend outwards to smaller communities and ferry points
(“spokes”
 This hub-first model does not remove the ‘Charging on the
Move’ theme — it remains central to ensuring through and
onward connectivity along all major corridors

Page 6

Proposed hub methodology
Strategic principle: Build reliable, visible hubs first, then
expand to smaller “spokes” once the network backbone is
established, ensuring full route coverage across Argyll and
Bute. This also complements the existing network.
 Identify sites that deliver strategic coverage – locations
where people visit, shop and work
 Potential for high utilisation
 Represent value for money
 Access to local amenities
 Avoid duplicating private provision
 Resilience and cluster logic

Page 7

Proposed hub methodology
 We have a proposed criteria for this based on population. The
hub (single-site) methodology is:
*when not near an existing large town
 We will add in an element of population swell through tourist
locations where they would therefore move up to the next
bracket:
 Population centres proposed for hubs reflect places where
visitors and residents visit, rather than domestic users charging
at home
Population Rapid Fast Total
10k plus 5 5 10
5k to 10k 3 3 6
2k to 5k* 2 2 4

Page 8

Proposed hub methodology
Town/area Pop Tourist swell Hub/cluster
Helensburgh 13k N 5R; 5F
Oban 8.5k Y 5R; 5F
Dunoon 8.9k N 3R; 3F
Lochgilphead 2.3k N 2R; 2F
Campbeltown 4.5k N 2R; 2F
Islay – Bowmore 3k island Y 3R; 3F
Mull – Craignure 3k island Y 3R; 3F
Bute – Rothesay 6k island N 3R; 3F

Page 9

Proposed hub methodology
To progress this we have asked our consultants to:
 Assess the current provision in each location
including non ABC operated publicly available
chargers. That assessment should consider as a
‘’hub’’ any chargers within a cluster area less than
one mile  from the hub site identified in the above
table
 Focus on new hubs/expansion of existing to be on a
single site
 Identify the number and type of chargers required
to meet the above hub targets, after accounting for
existing provision both Council and non-Council.

Page 10

Proposed hub methodology
 Assuming hubs/clusters will be developed on
existing sites, base on following as the core
deliverability criteria on the basis we are trying to
assess if sites pass or fail:
 Proximity to existing electrical infrastructure;
 Compliance with accessibility standards;
 No flood risk
 Strong data connectivity
 To assess in binary terms whether the sites pass or fail

Page 11

Proposed hub methodology
 Include usage information on existing chargers at
current sites.
 Determine total costs for any additional EVCs
required to meet the above requirement. Assume
mid range costs
 Assess scalable expansion options at each site

Page 12

Proposed approach
 Total funding secured: £1.033 million
 £100k reserved for repairs and maintenance (de-
risking current network)
 £100k held as contingency for cost fluctuations.
 That leaves £833k for new delivery.
 Proposal:
 Deliver Phase 1 Hubs from this £833k.
 Once hub costs are known, apply the roads capital
percentage split to the remaining balance for Phase 2
(smaller “spoke” sites)

Page 13

Proposed approach
Phase 1 – Strategic Hubs
 Priority delivery of key sites across Argyll and the islands.
 Exact costs dependent on DNO connection estimates.
 Focus on reliability, visibility and usage.
Phase 2 – Local delivery
 Remaining balance after hubs delivered.
 Split by the roads capital percentage to maintain equity:
 Bute & Cowal – 19.78%
 Helensburgh & Lomond – 10.67%
 Mid Argyll, Kintyre & Islay – 32.71%
 Oban, Lorn & the Isles – 36.84%
 Phase 2 decisions at local level (area committees)

Page 14

Phase Two – local delivery
 Phase 2 delivery will focus on individual chargers
and smaller sites (‘spokes’) that maintain network
continuity and local access.
 These sites could be selected and prioritised by Area
Committees within their allocated share, to support
local decision-making and flexibility under the
strategic framework.
 Ensures alignment with the original thematic
principles and equitable access across rural routes
and communities.

Page 15

Proposed next steps
 Finalise consultant outputs (deliverability-only).
 Confirm hub costs with DNO.
 Draft full delivery plan for EDI Committee (Dec
2025).
 Ongoing engagement with Members through area
committees.

Page 16

Risks and dependencies
 Hub costs unknown – DNO connection and ground
conditions may vary widely.
 Private sector overlap – expansion by supermarkets,
forecourts, etc. must be tracked to avoid duplication.
 Maintenance load – the growing network is managed
by one officer; current resource may not be
sustainable.
 Tariff sustainability – need to balance affordability with
cost recovery.
 Back-office transition – migration to Scottish
Power/Fuuse underway; minor risk of disruption during
switchover.

Page 17

Operational update
 37 Council-operated public chargers currently in
place across Argyll and Bute.
 New regional back-office contract through Scottish
Power (Fuuse platform):
 Improves automation and fault reporting.
 Allows dynamic tariffs and local control.
 Tariff remains £0.70/kWh – good balance between
recovery and affordability.
 Improved uptime under new maintenance
arrangements.

Page 18

Cross-footway charging
 Growing number of residents requesting to charge from
home over public pavements.
 No national guidance from Transport Scotland.
 Local phased approach:
 Short-term: trial approved cable protectors.
 Medium-term: ducting pilot (2026).
 Long-term: formal policy and asset register.
 Working with disability groups to ensure accessibility
compliance
 This could be a potential source of modest future
income – in a similar way to drop kerbs

Page 19

Discussion
 Is the hub-first, theme-led model the right direction?
 Are the proposed funding splits fair?
 Any concerns on rural coverage?
 What role should private providers play?