Democracy Spraffa

General Services Revenue, Housing Revenue Account (HRA) and Capital Budget Monitoring as at 13 September 2024

Renfrewshire Council · 29 October 2024
Back to Communities and Housing Policy Board — 29 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Communities and Housing Policy Board
On: 29 October 2024
___________________________________________________________________
Report by: Director of Finance and Resources & Director of Environment, Housing
and Infrastructure
___________________________________________________________________
Heading: General Services Revenue, Housing Revenue Account (HRA) and
Capital Budget Monitoring as at 13 September 2024
___________________________________________________________________
1. Summary
1.1 At the close of reporting period 6 on 13 September 2024, the projected revenue
outturn at 31 March 2025 for those services reporting to the Communities and
Housing Policy Board, including the Housing Revenue Account, is break-even
against the revised budget for the year in General Services and a break-even
position in the HRA. 
1.2 The projected capital outturn at 31 March 2025 for projects reporting to the
Communities and Housing Policy Board, is a break-even position. 
1.3  This is summarised over the relevant services in the table below and further
analysis is provided in the report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
Housing Revenue Account (HRA) 0 0 0 0.0%
Housing – General Services (Non-HRA)  4,626 4,626 0 0.0%
Communities and Public Protection 5,832 5,832 0 0.0%
Criminal Justice 4,171 4,171 0 0.0%
Total 14,629 14,629 0 0.0%

Page 2

Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Capital    
Housing Revenue Account (HRA) 30,769 30,769 0 0.0%
Other Housing PSHG 526 526 0 0.0%
Total 31,295 31,295 0 0.0% 
2. Recommendations
It is recommended that the Communities and Housing Policy Board: 
2.1 Note the projected Revenue outturn break-even position
2.2 Note the projected Capital outturn break-even position
2.3 Agree to homologate the budget adjustments detailed at sections 6.2 and 7.2
2.4 Approve the budget adjustments proposed at sections 6.3 
3. Revenue Budget Projection – break-even by 31 March 2025
3.1 The tables in Appendix 1 present the projected year-end position for all services
reporting to this board, by both subjective analysis (what the budget is spent on)
and objective analysis (which division is spending the budget). Significant variances
affecting the projected position are analysed further below. 
3.2 It should be noted that the projected outturn position reported here is based on the
latest information available, which is subject to change during the financial year.
The impact of any change on this projection will be updated at each board cycle
until the close of reporting period 10. Budget holders are obliged to seek mitigating
action to minimise significant budget variances. 
4. Objective Analysis – Significant Variances
4.1 Housing Revenue Account (HRA) - break-even by 31 March 2025
The HRA is projected to break even overall for 2024-25. The demand for repairs to
HRA properties, including Void properties, is currently expected to be managed
within the revised budget levels, although it remains an area of potential pressure. A
favourable £0.346 million is anticipated within the Transfer Payments budget due to
a reduced projected drawdown from reserves. It is proposed that these excess
funds be allocated to the Housing Management System Replacement project. 
4.2 Housing – General Services (Non-HRA) - break-even by 31 March 2025
The projected outturn for Homelessness within Housing – General Services Non-
HRA, continues to be a risk over the remainder of the financial year. Demand on
services is currently being managed within existing resources, including additional

Page 3

staffing, being supported through migration and asylum funding streams allocated
to the Council by the UK and Scottish Government. The significant potential
increase in homeless presentations linked to asylum population in Renfrewshire
and more widely across the West of Scotland, continues to create additional
potential long-term financial pressures for Council services. Projections of these
pressures will continue to be reviewed and reported to future Communities and
Housing Policy Boards as required. 
4.3 Communities and Public Protection - break-even by 31 March 2025
Employee costs are projected to underspend due to vacancies within the service,
this area is under review by management. The underspend has been allocated
against spend across other budget lines and overall, the service is projected to
break-even at year end. 
5. Subjective Analysis – Significant Variances 
GENERAL SERVICES (excluding HRA)
5.1 Employee costs - £0.209m underspend by 31 March 2025
This is a combination of underspends across services, for example, in Public
Protection underspends are due to vacancies which are currently under review.
Underspends in Criminal Justice and Homelessness are offset by minor overspends
across their service areas. 
5.2 Supplies and Services - (£0.198m) overspend by 31 March 2025
This includes £0.168m for one-off software and licencing costs within the Public
Protection Service, funded by underspends in employee costs as noted above.
Furniture costs within the Homelessness Service are projected to overspend and
this is consistent with the overall demand on Homelessness services. 
5.3 Transfer Payments - £0.060m underspend by 31 March 2025
The underspend within the Homelessness budget for payments to service providers
is being managed to cover small overspends in other areas of the Homelessness
Service.
HOUSING REVENUE ACCOUNT (HRA)
5.4 Employee costs - £0.155m underspend by 31 March 2025
The projected underspend in Employee costs reflects the timing of recruitment and
the level of vacancies across the service, in particular within Housing Management.
Projected staff costs for the new Housing Management system are included in the
overall projection, as are additional costs associated with the Single Voids Team.
An underspend in the timing of recruitment within the Regeneration Team is offset
by a reduction in recharges to capital, therefore a temporary transfer to adjust for
both variances is proposed. 
5.5 Premises Related costs - £0.032m underspend by 31 March 2025
The level of demand for Repairs and Maintenance of HRA Properties remains high,
especially within Void properties, however at present this is forecast to be managed
within the revised budget. Additional focus will continue on this area to understand

Page 4

ongoing demand levels. All premises related costs, including utilities and estate
management, are subject to fluctuations, and will continue to be closely monitored
throughout the year. 
5.6 Supplies - £0.043m underspend by 31 March 2025
A reduction in projected telephone system costs is contributing to this underspend.
This is reflected in the reduced level of transfer from reserves. 
5.7 Transfer Payments – (£0.101m) overspend by 31 March 2025
Due to improvements in void rent loss performance since the last report, there is an
underspend of £0.246m now projected within the overall Transfer Payments budget.
It is proposed to decrease the previously allocated temporary budget and move
these funds to reserves also contained within the Transfer Payments budget and
noted below. 
A temporary budget transfer is recommended to decrease the void rent loss
budget by (£0.246m). 
The Transfer Payments budget also accommodates transfers between reserves.
This includes a forecasted reduction reflecting the current levels of underspend
across the wider service, resulting in a (£0.346m) under recovery of funding
required from reserves. The underspend noted in void rent loss is proposed to be
temporarily allocated to the reserves budget.
A temporary budget transfer is recommended to decrease the contribution
from Reserves by £0.246m. 
5.8 Income - under recovery of (£0.127m) by 31 March 2025
The underspend in the Regeneration Team employee budget, as noted above, is
offset by a reduction in recharges to capital. 
6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors, and their nominated officers, in
consultation with the Director of Finance and Resources, have certain delegated
authority to transfer sums between subjective budget headings within a service
division to enable budget management throughout the financial year. This is known
as ‘budget virement’. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised by the
respective service Director and the Director of Finance and Resources for
submission to the relevant policy board for approval. 
The Director now seeks homologation from the Board for the following affected
virements, actioned since the last board reporting period: 
Revenue Budget Adjustments
Objective
Heading 
Subjective Heading  Amount
(£m)
Reason

Page 5

Housing -
General
Services (Not
HRA)
Employee Costs 0.029 Private Sector Housing Grant
alignment to reflect the profile of
expenditure and allocation of
funding from Capital and
Reserves.
Supplies & Services 0.294
Transfer Payments (0.284)
Income (0.039)  
Housing -
General
Services (Not
HRA)
Supplies & Services 1.700 Expenditure and offsetting
income under the Scottish
Government’s Home Energy
Efficiency Programme.
Income (1.700)  
Housing -
General
Services (Not
HRA)
Premises Related  0.262 Alignment of Homelessness
Services Income and
Expenditure to match expected
rental and void costs.
Supplies & Services 0.050
Transfer Payments (0.200)
Income (0.112)  
HRA Premises Related (0.815) Alignment of Insurance Budgets
between expenditure lines. Support Costs 0.815  
Criminal Justice Supplies & Services 1.046 Additional funding outwith
settlement aligned to relevant
expenditure budgets.
Transfer Payments 0.448
Income (0.448)   
6.3. Budget holders are obliged to seek mitigating action to minimise significant budget
variances. The Board is therefore asked to approve the following virements, which
are not currently applied to the budget: 
Revenue Budget Adjustments
Objective
Heading 
Subjective Heading  Amount
(£m)
Reason
HRA Transfer Payments  0.246 Transfer of budget to
Reserves, funded by
reduction in Void Rental Loss
costs.
Reserves (0.246)   
7. Capital Budget Projection – break-even position by 31 March 2025
7.1 The Non-Housing Capital Investment Programme 2024/25 to 2028/29 was
approved by the Council on 29 February 2024. For Communities and Housing
Service the revised capital spend for 2024/25 is £31.295m. 
7.2 The in-year Capital budget is forecast to break-even by 31 March 2025, a budget
adjustment between years has taken place, to reflect revised programming of some
capital projects. Details of the adjustment, which amount to (£10.467m), are as
follows:

Page 6

Capital Budget Adjustments
Project Amount
(£m)
Reason
Improvements to Existing Properties 0.337 Net acceleration from 2025/26 to
reflect start time of projects related to
External Improvements, Heating and
Rewiring.
Regeneration (10.174) Deceleration to 2025/26 as expected
start time of various projects including,
Howwood Road, Auchentorlie,
Howard Street and Waverley, will now
be towards the later part of 2024/25
and extend into 2025/26.
Other Assets (0.690) Deceleration to 2025/26 to reflect
updated cash flows for various
projects including fire alarms and
electrical work within sheltered
housing now not expected to
complete until 2025/26.
Non Property Expenditure 0.500 Acceleration from 2025/26 to 2024/25
for timing of condition surveys now
that the contacts have been agreed.
Council House New Build (0.390) Deceleration to 2025/26 to reflect
updated cashflows for 
Professional Fees (0.050) Decelerated to 2025/26 for timing of
work carried out by Property Services
Total (10.467) 
Implications of the Report
1. Financial
The projected budget outturn position for the Communities and Housing Revenue
budget is a break-even position at 31 March 2025. Income and expenditure will
continue to be monitored closely for the rest of the financial year and as far as
possible, steps will be taken to mitigate any overspend. 
The projected outturn position for Communities and Housing Services Capital budget
is break-even, after the adjustments outlined at section 7. 
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue budgets,
there are no direct implications arising from the recommendations in this report. 
3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for purpose
and safe for the community, to maximise
accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair

Page 7

Our Renfrewshire is safe
Council Plan
Reshaping our place, our economy
and our future The Council’s revenue and capital spend
ensures that its facilities are fit for purpose
and safe for the community, to maximise
accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable Renfrewshire
for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good financial
management so that the Council has
resources now and in the future for continued
service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this report. 
5. Property/Assets 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets and infrastructure. 
6. Information Technology 
ICT assets and revenue costs are included within these reported budgets, and the
costs associated with the replacement of the Housing Management system will have
both an ongoing revenue and capital budget impact. 
7. Equality & Human Rights 
While new areas of spend may impact on particular groups, any such impact would be
assessed prior to the spend being incurred, therefore there are no direct implications
arising from the recommendations in this report. 
8. Health & Safety 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets, which may in
some cases rectify health and safety issues. 
9. Procurement 
While Procurement is an important consideration prior to the Council incurring any
revenue or capital spend, there are no direct implications arising from the
recommendations in this report. 
10. Risk

Page 8

The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive and
Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this report. 
12. Cosla Policy Position 
N/a 
13. Children’s Rights 
There are no direct implications arising from the recommendations in this report. 
14. Climate Change
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in this
report. 
List of Background Papers 
• Housing Revenue Account Budget & Rent Levels 2024/25 and Housing Capital
Investment Plan 2024/25 to 2028/29, Council 29 February 2024.
• Non-housing Capital Investment Programme, prudential Framework and
Treasury Management Strategy, and Capital Strategy 2024/25 – 2028/29,
Council 29 February 2024. 
Author:        John Kilpatrick, Finance Business Partner; Geoff Borland, Finance Manager.

Page 9

RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 13 September 2024                  
POLICY BOARD:  COMMUNITIES AND HOUSING - All SERVICES                  
Objective Summary
Annual
Budget at
Period 3
Budget
Adjustments
Revised
Annual
Budget at
Period 6
Projected
Outturn
Budget
Variance 
(Adverse)
or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Housing Revenue Account (HRA) 0 0 0 0 0 0.0% 0 0
Housing - General Services (Not HRA) 4,613 13 4,626 4,626 0 0.0% 0 0
Communities and Public Protection (including
Regulatory Services) 5,861 (29) 5,832 5,832 0 0.0% 0 0
Criminal Justice 3,125 1,046 4,171 4,171 0 0.0% 0 0
NET EXPENDITURE 13,599 1,030 14,629 14,629 0 0.0% 0 0

Page 10

RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 13 September 2024                  
POLICY BOARD:  COMMUNITIES AND HOUSING - GENERAL SERVICES (excluding HRA)         
Subjective Summary (General Services – excl HRA)
Annual
Budget at
Period 3
Budget
Adjustments
Revised
Annual
Budget at
Period 6
Projected
Outturn
Budget
Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Employees 11,439 292 11,731 11,522 209 1.8% 95 114
Premises Related 1,895 536 2,431 2,445 (14) (0.6%) (438) 424
Transport Related 187 0 187 208 (21) (11.1%) (25) 4
Supplies and Services 2,631 3,051 5,682 5,880 (198) (3.5%) (287) 89
Third Party Payments 87 0 87 74 13 14.9% 2 11
Transfer Payments 2,709 (36) 2,673 2,613 60 2.2% (6) 66
Support Services 54 0 54 49 5 9.2% 0 5
Depreciation and Impairment Losses (23) 0 (23) (11) (12) (52.2%) (12) 0
GROSS EXPENDITURE 18,979 3,843 22,822 22,780 42 0.2% (671) 713
Income (5,380) (2,813) (8,193) (8,151) (42) (0.5%) 671 (713)
NET EXPENDITURE 13,599 1,030 14,629 14,629 0 0.0% 0 0

Page 11

RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 13 September 2024                  
POLICY BOARD:  COMMUNITIES, HOUSING AND PLANNING SERVICES - Housing Revenue Account (HRA) Only                  
Subjective Summary
Annual
Budget at
Period 3
Budget
Adjustments
Revised
Annual
Budget at
Period 6
Projected
Outturn
Budget
Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Employees 11,586 (25) 11,561 11,406 155 1.3% 258 (103)
Premises Related 24,075 275 24,350 24,318 32 0.1% (955) 987
Transport Related 53 0 53 63 (10) (18.9%) (6) (4)
Supplies and Services 908 0 908 865 43 4.7% 15 28
Third Party Payments 0 0 0 0 0 0.0% 0 0
Transfer Payments 4,837 680 5,517 5,618 (101) (1.8%) (1,051) 950
Support Services 2,456 866 3,322 3,314 8 0.2% 1 7
Depreciation and Impairment Losses 17,909 0 17,909 17,909 0 0.0% 0 0
GROSS EXPENDITURE 61,824 1,796 63,620 63,493 127 0.2% (1,738) 1,865
Income (61,824) (1,796) (63,620) (63,493) (127) (0.2%) 1,738 (1,865)
NET EXPENDITURE 0 0 0 0 0 0.0% 0 0

Page 12

Prior Years Approved  Budget Revised Projected Total Approved Projected
Expenditure Budget Adjustments Budget Outturn Budget Outurn
to 31/03/2024 2024-25 in 2024-25 2024-25 2024-25 to 31-Mar-29 to 31-Mar-29
Project Title
£000 £000 £000 £000 £000 £000 £000
HOUSING(HRA)
Improvements To Existing Properties 0 15,420 337 15,757 15,757 0 0% 111,757 111,757 0 0%
Regeneration 10,743 19,401 (10,174) 9,227 9,227 0 0% 109,369 109,369 0 0%
Other Assets 0 3,115 (690) 2,425 2,425 0 0% 4,550 4,550 0 0%
Non Property Expenditure 0 400 500 900 900 0 0% 10,860 10,860 0 0%
Council House New Build 42,665 1,000 (390) 610 610 0 0% 74,690 74,690 0 0%
Professional Fees 0 1,900 (50) 1,850 1,850 0 0% 9,700 9,700 0 0%
Total Housing (HRA) Programme 53,408 41,236 (10,467) 30,769 30,769 0 0% 320,926 320,926 0 0%
HOUSING(PSHG)
Private Sector Housing Grant Programme 0 526 0 526 526 0 0% 2,926 2,926 0 0%
Total Housing (PSHG) Programme 0 526 0 526 526 0 0% 2,926 2,926 0 0%
TOTAL COMMUNITIES, HOUSING & PLANNING
BOARD 53,408 41,762 (10,467) 31,295 31,295 0 0% 323,852 323,852 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Budget Variance
(Adverse) or Favourable
Budget Variance
(Adverse) or
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY
1st April to 13th September 2024
POLICY BOARD: COMMUNITES & HOUSING
Current Year 2024-25 Full Programme - All years