Page 1

___________________________________________________________________
To: Communities and Housing Policy Board 
On: 20 August 2024
___________________________________________________________________ 
Report by: Director of Environment, Housing and Infrastructure
___________________________________________________________________ 
Heading: Draft Renfrewshire Strategic Housing Investment Plan 2025 to
2030  
___________________________________________________________________
1. Summary 
1.1 The draft Renfrewshire Strategic Housing Investment Plan 2025 to 2030
(attached at Appendix 1) sets out the housing investment priorities for projects
across Renfrewshire that will be supported by Scottish Government funding
through the Affordable Housing Supply Programme. 
1.2  Renfrewshire’s Strategic Housing Investment Plan is reviewed and updated
each year in partnership with developing Housing Associations and the
Scottish Government. 
1.3  The draft Renfrewshire Strategic Housing Investment Plan 2025 to 2030 is
attached and will be subject to a four week public consultation.
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Communities and Housing Policy Board: 
2.1 Approves the draft Renfrewshire Strategic Housing Investment Plan 2025 to
2030, as set out in Appendix 1, for consultation, before a finalised Plan is
presented to the October meeting of the Communities and Housing Policy
Board. 
___________________________________________________________________

Page 2

3. Background 
3.1 The draft Renfrewshire Strategic Housing Investment Plan outlines how
Scottish Government funding for affordable housing will be targeted to
achieve the priorities set out in Renfrewshire’s Local Housing Strategy and
support the delivery of a range of affordable housing projects across
Renfrewshire. 
3.2 As part of the Affordable Housing Supply Programme process, the Scottish
Government allocate grant funding, known as Resource Planning
Assumptions, to individual Council areas. 
3.3 The Scottish Government’s budget approved in February 2024 included a
reduction of £196 million in funding for the Affordable Housing Supply
Programme (AHSP) in Scotland. Following this budget announcement it has
been confirmed that the Resource Planning Assumption for Renfrewshire for
2024/2025 has reduced by £4.187 million (24%) to £13.013m. 
3.4 Resource Planning Assumptions support the delivery of new affordable
homes across Renfrewshire by providing grant support at benchmark rates.
The Scottish Government benchmark grant rates are set at £83,584 for new
Council homes and £91,182 for new social rented homes delivered by
housing association partners. 
3.5 It is currently challenging to deliver new social rented homes at benchmark
rates due to high development costs and inflationary pressures. Developers
can apply for higher levels of grant support that reflect higher development
costs for projects but the award of higher levels of grant is funded from the
existing Resource Planning Assumption. If higher levels of grant are approved
it will mean that fewer homes can be delivered each year which will increase
delivery timescales for the wider SHIP programme. 
3.6 Additional grant funding is also available on top of the grant benchmark rates
where affordable housing developers include specific qualitative design
features related to zero emissions; the installation of automatic fire
suppression systems; electric vehicle charging points; space for home
working; provision of balconies and digital connectivity. 
4.  Draft Renfrewshire Strategic Housing Investment Plan 2025 to 2030 
4.1 The draft Renfrewshire Strategic Housing Investment Plan includes a range of
housing projects that aim to deliver affordable homes of different types and
sizes throughout Renfrewshire to meet people’s housing needs, including
smaller and larger homes for both general and particular needs. 
4.2  The draft Renfrewshire Strategic Housing Investment Plan includes an
affordable housing programme to be delivered by the Council and its Housing
Association partners which is supported by Scottish Government grant
funding.

Page 3

4.3 The draft Strategic Housing Investment Plan contains funding provision for the
Council’s own ambitious newbuild development programme in the Councils
Housing Regeneration and Renewal areas. 
4.4 Formal offers of Scottish Government Grant for projects included within the
SHIP core programme have been issued by the Scottish Government to
developing social landlords for 2024/25 with future grant funding offers
expected to be issued on a rolling basis up to the value of the annual
Resource Planning Assumption. Projects in receipt of grant in 2024/25 include
the Council’s regeneration projects at Howwood Road, Johnstone and at
Gallowhill in Paisley. 
4.5  Delivery of the full development programme is projected to take longer than
previously anticipated in last year’s plan as the amount of funding being made
available through the Affordable Housing Supply Programme in 2024/25 has
been reduced by £4.187 million (24%). This reduction in funding is combined
with higher development costs and inflationary pressures which will result in
extended timescales for delivery of the full development programme.  At
current grant levels it is anticipated that the development programme will take
approximately 10-15 years to deliver. 
4.6 The Resource Planning Assumption for Renfrewshire has only been
confirmed for one year and there remains uncertainty over the future level of
funding allocations for Renfrewshire. This funding uncertainty means that
delivery timescales for projects may change and it will be challenging to add
new projects to the programme in the short to medium term. 
4.7 In approving the Strategic Housing Investment Plan 2024 to 2029 at the
Communities and Housing Board on 31 October 2023, it was reported to
Board that the Council and partners are working to identify new affordable
housing projects to address the 93 social rented unit reduction at Dargavel
Village that resulted from the decision of the Planning and Climate Change
Policy Board on 29 August 2023 in relation to the revision of the Section 75
Agreement that is attached to the approved Dargavel Village masterplan. 
4.8 Given the reduction in funding and the uncertainty over future levels of
funding, the ability to add new projects to the development programme to
address the 93 unit reduction at Dargavel Village is significantly constrained,
therefore the draft Strategic Housing Investment Plan focuses on the delivery
of existing sites within the programme. The Council and partners will work to
identify new affordable housing projects to address the reduction at Dargavel
Village should additional funding be made available. The draft Strategic
Housing Investment Plan does, however, continue to programme for the
delivery of 105 social rented units at Dargavel Village.

Page 4

4.9 The draft Strategic Housing Investment Plan has built in capacity to
accelerate affordable housing projects within the programme to take
advantage of any additional funding that may become available to
Renfrewshire or to mitigate any slippage on projects to ensure that all
available funding is fully utilised in supporting the delivery of the right homes
in the right places. 
___________________________________________________________________ 
5. Next Steps 
5.1 Consultation on the draft Renfrewshire Strategic Housing Investment Plan
2025 to 2030 will take place between August and September 2024. This will
involve further engagement with all developing housing associations operating
in Renfrewshire, local stakeholder groups such as Community Councils and
tenants and residents’ associations, community planning partners, other
stakeholder groups and Renfrewshire’s residents. 
5.2 Following the consultation and taking account of feedback received the
Renfrewshire Strategic Housing Investment Plan 2025 to 2030 will be
finalised and presented to this Policy Board for consideration.
___________________________________________________________________ 
Implications of the Report 
1. Financial - Provision has been made within the Housing Revenue Account
(HRA) Capital Budget in relation to the projects where the Council is the
developing organisation. 
2. HR & Organisational Development - None. 
3. Community/Council Planning – 
Building strong, safe and resilient communities by Increasing the supply of
affordable housing and regenerating communities.   
4. Legal - Conveyancing work associated with land disposals, and any site
assembly and title changes or checks. All new Council contracts for new build
affordable housing will require input from the contracts and project legal
sections at the pre and post tender stages through to award. 
5. Property/Assets - None. 
6. Information Technology - None.

Page 5

7. Equality & Human Rights   
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website. 
8. Health & Safety - None. 
9. Procurement - None. 
10. Risk - Scottish Government funding for affordable housing development does
not carry forward into the next financial year. There is therefore a risk that
funding could be lost to Renfrewshire if there is slippage in the delivery of any
of the projects. This is mitigated by ongoing monitoring of projects and the
prior identification of alternative projects for funding to be spent on if slippage
occurs. 
11. Privacy Impact - None. 
12. Climate Risk - The Draft Strategic Housing Investment Plan aims to deliver
high quality, energy efficient homes in sustainable locations across
Renfrewshire. 
13. Children’s Rights – None. 
14. Cosla Policy Position - None. 
___________________________________________________________________ 
List of Background Papers
(a)  Appendix 1 – Draft Renfrewshire Strategic Housing Investment Plan 2025 to
2030 
___________________________________________________________________ 
Author: Alan Williamson, Strategy and Place Manager
Email: alan.williamson@renfrewshire.gov.uk, Tel: 07811 053968

Page 6

1   
Draft Renfrewshire Strategic Housing
Investment Plan 2025 to 2030

Page 7

Draft Strategic Housing Investment Plan 2025 to 2030   2
Preparation and Consultation 
This draft Renfrewshire Strategic Housing Investment Plan 2025
to 2030 has been prepared for consultation following on-going
discussions with the Scottish Government and housing
association partners operating in Renfrewshire. 
Individuals, groups and stakeholders are encouraged to
comment and provide feedback to help shape the finalised
Strategic Housing Investment Plan to ensure that it reflects the
views of Renfrewshire’s communities and partners. 
The finalised Strategic Housing Investment Plan will be submitted
to the Council’s Communities and Housing Policy Board on the
29th October 2024, after which it will also be submitted to the
Scottish Government.   
Following submission of the finalised Strategic Housing
Investment Plan to the Scottish Government, a Strategic Local
Programme Agreement (SLPA) for Renfrewshire will form the
basis of individual agreements between the Scottish Government,
Renfrewshire Council and housing association partners on
funding for specific affordable housing projects as detailed in the
finalised Strategic Housing Investment Plan. 
Public consultation on this Draft Strategic Housing
Investment Plan will open on 21st August 2024 with
the consultation closing on 18th September 2024. 
Comments should be returned by email or by post
to:
Email: strategyandplace@renfrewshire.gov.uk
Economy and Development Team, Chief Executives
Service, Renfrewshire Council, Renfrewshire House,
Cotton Street, Paisley, PA1 1WB 
This draft Strategic Housing Investment Plan can be viewed on
the Council’s website by visiting: 
https://www.renfrewshire.gov.uk/article/4232/Strategic-Housing-
Investment-Plan

Page 8

Draft Strategic Housing Investment Plan 2025 to 2030   3
Renfrewshire’s draft Strategic Housing Investment Plan  
The Scottish Government’s Affordable Housing Supply
Programme (AHSP) sets out a national framework to support
development of new affordable homes. 
As part of the Affordable Housing Supply Programme process,
local authorities are required to prepare a Strategic Housing
Investment Plan (SHIP) each year that outlines where grant
funding provided to Councils by the Scottish Government will be
used to support delivery of new affordable homes developed by
the Council or one of its housing association partners.   
Renfrewshire’s new draft Strategic Housing Investment Plan
provides details of affordable housing projects in Renfrewshire
that will assist in meeting the strategic priorities of Renfrewshire’s
Local Housing Strategy with these projects expected to be
supported by Scottish Government grant funding over the short,
medium and longer term. 
Projects included within the draft Strategic Housing Investment
Plan will continue to assist in providing the right homes in the
right places and contribute to providing safe, warm and energy
efficient homes that meet people’s housing needs and contribute
to the creation of thriving sustainable communities. 
The Scottish Government’s Housing Programme  
The Scottish Government published their ‘Housing to 2040
Strategy’ in March 2021 with the strategy setting out the Scottish
Government’s approach to increasing the supply of homes across
all tenures in the period to 2040. 
When published, the ‘Housing to 2040 Strategy’ included a target
to provide 110,000 affordable homes by 2032 with at least 70% of
these homes to be developed for social rent. 
However, as a result of wider financial pressures - the Scottish
Government significantly reduced funding for the Affordable
Housing Supply Programme as part of the draft Budget published
in December 2023 and approved in February 2024 with £196
million less funding than anticipated being made available
nationally to support the delivery of affordable homes in the year
April 2024 to March 2025. 
The recent reduction in funding will have a significant impact on
timescales for delivery of affordable housing projects in both
Renfrewshire and nationally. The scale of the reduction in
Renfrewshire’s is around £4.2 million in 2024/25 with a similar
level of funding anticipated in 2025/26.

Page 9

Draft Strategic Housing Investment Plan 2025 to 2030   4
For now, the Scottish Government have retained their ambitious
targets set out in the ‘Housing to 2040 Strategy’. 
Renfrewshire Council remain committed to contributing to
national targets and will continue working in partnership with our
housing association partners, private developers, the
construction industry and the Scottish Government to deliver
affordable homes across Renfrewshire. 
This draft Strategic Housing Investment Plan rolls forward
affordable housing projects identified as priorities in previous
Strategic Housing Investment Plans whilst acknowledging that
timescales for the delivery of projects may take significantly
longer than previously anticipated as a direct result of the
reduction in available funding, inflationary pressures, additional
costs associated with improving standards and the general rising
cost of development. 
Ongoing financial support in terms of future funding
commitments from the Scottish Government that recognise the
scale of Renfrewshire’s affordable housing development
programme and acknowledge the significant inflationary
pressures on development and tender costs will be essential to
supporting the ongoing delivery of new affordable homes
throughout Renfrewshire. 
Link Group social rented development, Millarston, Paisley 
The Scottish Government’s Housing and Planning
Delivery Framework (HPDF) 
This draft Strategic Housing Investment Plan takes account of the
Scottish Government’s Housing and Planning Delivery Framework
(HPDF) which promotes more efficient collaboration between
Housing and Planning Services in relation to the Local Housing
Strategy, Housing Need and Demand Assessment and national
planning policies.

Page 10

Draft Strategic Housing Investment Plan 2025 to 2030   5
Renfrewshire's draft Strategic Housing Investment Plan, Local
Housing Strategy and the Renfrewshire Development Plan
(including Renfrewshire’s Local Development Plan 2021 and
National Planning Framework 4) support the implementation of
the Housing and Planning Delivery Framework and aim to
increase the supply of housing; make the housing system more
responsive to demand; improve long term housing affordability
and contribute to reducing volatility in the housing market. 
Development Plan for Renfrewshire 
Renfrewshire’s current Development Plan consists of National
Planning Framework 4 and the Renfrewshire Local Development
Plan 2021. 
Renfrewshire’s Development Plan supports the development of
new homes that improve affordability and choice as well as
increasing access to homes for all which are accessible and
adaptable, including wheelchair accessible homes. 
When the Council is assessing projects included as part of this
draft Strategic Housing Investment Plan, it will consider proposals
against the policies in the National Planning Framework 4 and the
Renfrewshire Local Development Plan 2021. 
Williamsburgh Housing Association social rented development, Albert Road, Renfrew   
Renfrewshire’s Local Housing Strategy 
The fourth Local Housing Strategy for Renfrewshire was approved
in October 2023 following consultation with local communities,
housing association partners, tenants and resident’s associations,
community councils, the third sector, Renfrewshire’s Health and
Social Care Partnership and other key stakeholders. 
The Local Housing Strategy 2023-2028 takes account of local and
national policy priorities, as well as new research and evidence
and looks to build upon past successes whilst aiming to meet
need and demand for both housing and housing related services.

Page 11

Draft Strategic Housing Investment Plan 2025 to 2030   6
The Local Housing Strategy includes 5 strategic priorities as
shown below. 
Affordable Homes for Renfrewshire 
Renfrewshire Council worked with local authorities across the
Glasgow City Region to finalise the third Housing Need and
Demand Assessment (HNDA3). 
In addition to HNDA3, a comprehensive local affordable housing
study of the Renfrewshire area was produced as part of the
development of the current Local Housing Strategy (LHS) with
this local study complementing the wider HNDA3 by providing a
robust evidence base by identifying housing need at a lower level
geography across Renfrewshire’s towns and villages. 
This comprehensive evidence base will also be used to inform the
application of Renfrewshire’s Affordable Housing Policy. 
The Council has taken account of the outputs of HNDA3 and the
local affordable housing study to estimate housing need for both
private and affordable housing with progress in meeting this need
monitored as part of the annual update of Renfrewshire’s Local
Housing Strategy. 
The headline results from the local affordable housing study are
included within the Local Housing Strategy. 
Local Housing Strategy 2023-2028 Strategic Priorities
1.  The supply and delivery of housing is increased across
all tenures to meet the housing needs of different groups
and create attractive and sustainable places. ; 
2.  People live in high quality, well managed homes in
sustainable neighbourhoods. ; 
3.  Address the challenges of the climate emergency,
delivering homes that are warm, energy efficient and
fuel poverty is minimised ; 
4.  Prevention of homelessness and providing support for
those in housing need ; and 
5.  People can live independently for as long as possible
in their own home and the different housing needs of
people across Renfrewshire are being met .

Page 12

Draft Strategic Housing Investment Plan 2025 to 2030   7
Resources for Housing Delivery
It is vital that an ambitious and flexible affordable housing
development programme is maintained to ensure that sites can
be progressed to meet local need while making the best use of
available funding and resources. 
Until this year, the Scottish Government provided Councils with
multi-year Resource Planning Assumptions (RPA’s) to support
longer term planning and delivery of projects within Strategic
Housing Investment Plans. In recent years, multi-year funding
allocations of between £15 million and £17 million per year were
made available to Renfrewshire Council by the Scottish
Government. 
As part of the Scottish Government’s draft budget published  in
December 2023 and approved on 27th February 2024, there was an
unexpected reduction of more than £196 million in funding for the
Affordable Housing Supply Programme (AHSP) in Scotland. 
In Renfrewshire, this means that funding from the Scottish
Government has been reduced significantly from £17.200 million to
£13.013 million in 2024/25  with a similar level of funding
anticipated in 2025/26. 
Scottish Government funding allocations beyond 2024/25 are still
to be confirmed. However, it is likely that funding awards will be
made on a single year basis over the next few years as opposed to
the recent multi-year resource planning assumption which
provided some degree of certainty and facilitated longer term
planning. 
Scottish Government Charitable Bond Funding  (ALLIA) 
In addition to the funding being made available to Renfrewshire
through the confirmed Resource Planning Assumption in 2024/25,
Renfrewshire has successfully attracted Allia funding which is
funding derived from the Scottish Governments Charitable Bonds
investments programme. This is managed by Allia, a social
investment charity. 
Each year income is generated from bonds which is then used by
the Scottish Government’s More Homes Scotland team to
support increasing the supply of homes by providing one off
grants to affordable housing providers who have projects that
align with the funds criteria.

Page 13

Draft Strategic Housing Investment Plan 2025 to 2030   8
Funding new Affordable Homes and Scottish
Government Grant Benchmarks
New affordable homes developed as part of the Strategic Housing
Investment Plan are funded through a combination of Scottish
Government grant and the developers own financial resources. 
Scottish Government grant support is provided at flexible
benchmark rates for each affordable home developed with the
Scottish Government benchmark grant rate set at £83,584 for new
build social rented Council homes and £91,182 for new build
housing association homes. 
These grant rates are flexible which means that projects may be
eligible for a higher grant award per property following a detailed
assessment of property mix, project viability and development
costs. 
In recent years, costs to develop affordable homes have risen
significantly due to inflationary pressures and increases in both
employee and material costs. 
This has had a negative impact on overall development activity
with higher levels of grant support required per property to make
developments viable with projects also taking longer than
expected to deliver. 
Alongside inflationary pressures and the general increase in
development costs, the incorporation of new design features,
whilst welcome, have added to the cost of development.   
These issues, when combined with a reduction in Scottish
Government grant funding, will reduce the number of new
affordable homes that can be completed each year and will
extend the timescales for delivery of projects included within this
draft Strategic Housing Investment Plan. 
Appendix 3 of this draft Strategic Housing Investment Plan
includes details of the estimated grant funding requirement for
each project. 
Additional Affordable Housing Design Features
In addition to the basic flexible benchmark grant made available
to developers of affordable housing, additional grant may be
provided from the Councils existing Resource Planning
Assumption to support inclusion of specific quality and design
features in new affordable homes, these features include:

Page 14

Draft Strategic Housing Investment Plan 2025 to 2030   9
The delivery of homes to Silver Level of the 2019 Building
Regulations in respect of Energy for Space Heating;
The provision of balconies within flatted developments where
the provision of private or communal outdoor space is not
possible; 
The provision of space for home working or study where it is not
possible to incorporate such space within the design of the
homes under current space standards; 
Digitally enabled homes with tenants able to arrange for an
internet connection without the internet service provider having
to provide additional cabling to the premises;
The installation of ducting infrastructure for electric vehicle
charge point connectors;  
Installation of electric vehicle charge points;
The installation of automatic fire suppression systems; and  
Installation of heating systems which produce zero direct
emissions at the point of use.   
Any additional grant required to support inclusion of any of these
features must be met from the existing funding allocation from the
Scottish Government - this may have an impact on the number of
new affordable homes being delivered as the level of grant funding
required for each property increases. 
Meeting Renfrewshire’s Housing Need 
When developing proposals for new affordable housing,
developers are required to aim for balanced mixed communities
that include a range of property types and sizes to meet a range
of different housing needs, including the provision of accessible
homes and homes designed to wheelchair standard. 
All affordable housing must be built to Housing for Varying Needs
standards and should have flexibility built into the design to allow
for future adaptation and reconfiguration to meet tenant and
resident’s current and future needs. 
In 2022, Renfrewshire had a population of 184,340 people living
across 88,749 different households with an average household
size of just over two people (National Records of Scotland). 
By 2028, the number of households is expected to increase to
around 90,600 through small projected increases in the
population combined with an increasing number of people living
alone (National Records of Scotland). 
Renfrewshire’s population, like Scotland’s, is ageing with people
living longer. In 2022, almost one fifth (19.6%) of Renfrewshire’s
population was 65 years of age or older (National Records of Scotland).

Page 15

Draft Strategic Housing Investment Plan 2025 to 2030   10
Renfrewshire Affordable Housing Investment Priorities 
Projects included within this draft Strategic Housing Investment
Plan have clear links to the Strategic Priorities set out in the
Renfrewshire Local Housing Strategy 2023-2028. 
This draft Strategic Housing Investment Plan supports the
development of high quality affordable homes that are energy
efficient and recognises that good quality affordable housing can
positively impact peoples’ lives and enhance Renfrewshire’s
places. 
Projects identified within this draft Strategic Housing Investment
Plan will meet housing needs with affordable housing developers
expected to provide a range of property types and sizes on each
development to meet the housing needs of different groups,
including smaller one bedroom homes and larger family homes
throughout Renfrewshire. 
The Council will continue to work with housing association
partners to determine the most appropriate property mix on a
project by project basis taking account of Council and housing
association waiting list data and the findings from the Glasgow
Clyde Valley Housing Need and Demand Assessment (HNDA3)
and the Renfrewshire Housing Need and Demand study.
A breakdown of property sizes for recently completed
developments and those that have planning consent is included
in Appendices 1 and 2. 
Projects included as part of this draft Strategic Housing
Investment Plan will assist in meeting the needs of individuals,
families and those who require accommodation to meet a
particular housing need such as housing for older people and
housing to meet the needs of households with physical
disabilities. 
New homes developed as part of this draft Strategic Housing
Investment Plan are also expected to meet people’s needs and
aspirations now and in the future with homes expected to be
adaptable to meet people’s changing needs over time. 
Projects for both general and particular needs provision are
included as both standalone purpose-built accommodation as
well as within mainstream general needs developments. 
Particular needs provision alongside appropriate support can
assist people to live independently and successfully in their own
homes and communities.

Page 16

Draft Strategic Housing Investment Plan 2025 to 2030   11
Developers of affordable homes will be expected to include
accessible and adaptable homes on all new build developments. 
In recent years, Strategic Housing Investment Plans have
primarily focused on adding to the supply of new build affordable
homes for social rent, this will continue under this new draft
Strategic Housing Investment Plan. 
Whilst the focus will remain on adding to the supply of social
rented homes, there is a recognised need for some limited shared
equity provision on larger affordable housing sites. The inclusion
of new homes for shared equity will be considered on a site by
site basis taking account of the availability of grant funding from
the Scottish Government. 
The delivery of new affordable homes on private sector sites will
continue through the application of Renfrewshire’s Affordable
Housing Policy, in order to promote the development of mixed
tenure communities. The focus will be to increase the supply of
social rented homes, however, this will be subject to the level of
Scottish Government funding to support delivery. 
As well as adding to the supply of affordable housing, this draft
Strategic Housing Investment Plan places a strong emphasis on
making best use of existing stock where possible and addressing
issues in terms of housing quality and sustainability. 
Sanctuary Scotland development, Napier Crescent, Linwood

Page 17

Draft Strategic Housing Investment Plan 2025 to 2030   12 
Renfrewshire Council Regeneration and Renewal
Programme 
This draft Strategic Housing Investment Plan continues to
support the Council’s new build programme following the
completion of new Council homes in Dargavel Village, Johnstone
and Ferguslie Park in Paisley. 
Over the next 10 years, Renfrewshire Council will continue to
invest in its own newbuild programme to develop high quality
energy efficient homes that replace existing low demand housing
or add to the supply of Council housing with plans progressing to
deliver homes in identified regeneration areas or on nearby sites. 
This draft Strategic Housing Investment Plan identifies these new
build Council projects as strategic priorities with Scottish
Government grant expected to be made available as part of the
Strategic Housing Investment Plan process to supplement the
Council’s own investment in these new homes for social rent. 
This draft Strategic Housing Investment Plan supports
delivery of the strategic priorities of the Local Housing
Strategy by: 
1. Supporting the Council’s housing Regeneration and Renewal
programme by including new affordable housing projects to
replace social rented housing that is no longer fit for purpose; 
2. Increasing the provision of affordable housing in areas where
there is demand but limited supply; 
3. Addressing the mismatch between the supply of social rented
housing and the housing people need and want to live in,
taking account of type, size, quality and location; 
4. Supporting the development of sustainable mixed
communities by making use of the Council’s Affordable
Housing Policy; 
5. Increasing the supply of housing for older people and those
with particular needs, including those who are homeless; and 
6. Supporting town centre regeneration through residential
development.

Page 18

Draft Strategic Housing Investment Plan 2025 to 2030   13
Initial Council new build projects identified within this draft
Strategic Housing Investment Plan for social rent include: 
Howwood Road, Johnstone.  
Gallowhill, Paisley; 
Thrushcraigs, Paisley; 
Springbank, Paisley 
Additional regeneration areas will be included in the later years of
the Strategic Housing Investment Plan as proposals are refined
and Scottish Government funding becomes available. 
As well as adding to the supply of new Council housing as part of
the Strategic Housing Investment Plan process, the Council will
target enhanced investment in its existing housing stock –
including works to the external fabric of properties and
environmental improvements. 
More information on the Council’s Regeneration and Renewal
Programme can be found on the Council’s website by visiting: 
Housing regeneration in Renfrewshire – Renfrewshire Website 
New Affordable Homes to be delivered  
An overview of new build affordable housing developments both
currently underway and proposed is provided in Appendix 1. 
Appendix 3 outlines the proposed new build programme for
delivery by both the Council and its housing association partners
with delivery of core priority projects expected in the earlier years
of the programme and shadow and longer term projects
expected to be delivered in the later years of this programme and
beyond with timescales for delivery subject to the availability of 
Scottish Government grant funding.   
The continued significance of strategic regeneration is reflected in
the projects currently on site or proposed to be taken forward as
part of the proposed development programme. 
Delivering New Affordable Homes in North and West
Renfrewshire 
Affordable housing development in the villages of North and West
Renfrewshire can be challenging as most land for development is
in private ownership.

Page 19

Draft Strategic Housing Investment Plan 2025 to 2030   14
The Council recognises that there is unmet demand and limited
supply of affordable housing in these areas and will continue to
pursue all opportunities to increase the supply of affordable
housing in both North and West Renfrewshire, working with
housing association partners and private developers to include
social rented housing as either standalone developments or as
part of mixed tenure private sector developments delivered as
part of the Council’s Affordable Housing Policy. 
Affordable housing provision within Dargavel Village will continue
with 138 homes for social rent developed by the Council and
Loretto Housing Association. 
Loretto Housing Association were progressing plans to deliver a
further 62 social rented homes with Stewart Milne Homes but
following the administration of Stewart Milne Homes – these 62
affordable homes have been delayed pending another developer
progressing this site. 
Discussions are also ongoing between housing association
partners and private developers to deliver a further 43 homes for
social rent within Dargavel Village across two sites. 
An additional 93 social rented units that were to be delivered at
Dargavel Village were removed from the SHIP programme to
reflect the minute of agreement reached between the Council
and BAE in September 2023 which supports the development of
the community growth area. 
The ability to address the 93 unit reduction has been impacted
significantly by the reduction in funding available through the
Affordable Housing Supply Programme. It is not known how long
this reduction in funding will remain or whether it will be reduced
further during the next 5 years. Should additional funding
become available, opportunities for additional social rented
homes in North Renfrewshire will be explored building on what is
already planned in the SHIP. 
In West Renfrewshire, a number of sites are being assessed by
housing association partners with these sites potentially
including homes for social rent as part of the Councils Affordable
Housing Policy. 
The Council will continue to work with our housing association
partners to increase the supply of social rented housing in these
areas, taking account of housing waiting list data and the outputs
from the Renfrewshire Housing Need and Demand study.

Page 20

Draft Strategic Housing Investment Plan 2025 to 2030   15
Particular Housing Needs 
The Local Housing Strategy highlights the importance of
providing homes that meet the particular needs of different
groups with a focus on homelessness prevention and enabling
people to live independently for as long as possible in their own
home. 
In December 2023, Link Housing Association completed a mixed
general and particular needs development comprising of 81 new
homes for social rent in Paisley Town Centre. This development
included 20 amenity standard homes and 5 fully wheelchair
accessible homes. 
This draft Strategic Housing Investment Plan includes projects
that will continue to contribute to addressing identified particular
needs in Renfrewshire. 
One project being carried forward from the previous Strategic
Housing Investment Plan, that if delivered will contribute to
meeting identified particular needs, includes a purpose built
development of older persons housing in Erskine.   
This proposed development would include 24 new older persons
homes to replace existing provision that is no longer suitable. 
This site was being progressed in a partnership between Stewart
Milne Homes and Bridgewater Housing Association. However,
following the administration of Stewart Milne Homes, this project
may be delayed pending the outcome of the administration
process. 
When planning new developments, early stage discussions will
take place with Renfrewshire Health and Social Care Partnership
(HSCP) to ensure that projects are viable, sustainable and
capable of meetings tenants and residents’ needs. 
Wheelchair Accessible Housing 
Affordable housing providers in Renfrewshire are expected to
provide a range of property types and sizes to meet people’s
different housing needs - this includes the development of
wheelchair accessible homes. 
When preparing proposals for new build development, housing
providers will be required to design homes that are able to meet
occupants changing needs over time as well as the needs of an
ageing population by incorporating design features that promote
accessible and adaptable homes.

Page 21

Draft Strategic Housing Investment Plan 2025 to 2030   16
Targets for the inclusion of wheelchair accessible homes as part
of new build developments have been agreed and are included
within the Local Housing Strategy. 
The Local Housing Strategy confirms that:
New residential proposals must provide a minimum 10% of all
dwellings designed to be easily adaptable for residents who are
wheelchair users; and 
5% of all new homes must be designed to wheelchair accessible
standards. 
Link Group social rented development, General and Particular Needs, Paisley Town Centre   
Rapid Rehousing Transition Plans 
Renfrewshire Council and partners worked together to prepare a
Rapid Rehousing Transition Plan (RRTP) that details how those
who are homeless will be provided with settled accommodation
more quickly; spend reduced time in temporary accommodation
and have more access to up-scaled support. 
The strategic housing priorities contained within this draft
Strategic Housing Investment Plan align with the Rapid
Rehousing Transition Plan, supporting the delivery of homes to
meet the requirements of different needs groups, household
types and sizes. 
Child Poverty (Scotland) Act 2017 
This draft Strategic Housing Investment Plan recognises the
fundamental role housing has in tackling child poverty and aims
to support the delivery of a range of property types and sizes that
meet the needs of families of all sizes through the creation of high
quality energy efficient homes in sustainable communities that
support health, wellbeing and educational attainment. 
Early discussions with housing association partners ensure that
the housing mix proposed for each project takes account of

Page 22

Draft Strategic Housing Investment Plan 2025 to 2030   17
housing waiting lists with this information reflected in terms of
any agreed property mix and house sizes. 
Refugee Resettlement 
Renfrewshire Council continues to work with the Scottish
Government and Convention of Scottish Local Authorities
(COSLA) to determine what Renfrewshire may provide in terms of
housing stock to support the Afghan resettlement and asylum
dispersal programmes. 
To date, most accommodation required has been smaller with
one or two bedrooms being used due to the arriving household
size. 
Renfrewshire has continued to play its part in the national
response though the extent of ongoing support in terms of the
number of homes required to support Renfrewshire’s
contribution towards the national resettlement scheme is unclear
and will be kept under review. 
Gypsy/Travellers 
The Council continues to review the need to allocate land to meet
the housing needs of Gypsy/Travellers taking account of the Joint
Action Plan published by the Scottish Government and
Convention of Scottish Local Authorities (COSLA). 
The Council will make use of Scottish Government research into
Gypsy/Travellers and use the Scottish Government toolkit
intended to assist local authorities build an understanding of the
changing needs of Gypsy/Travellers in our area, in particular in
relation to accommodation, services and supporting travel
throughout Renfrewshire and beyond. 
All available information will inform the current Gypsy/Travellers
assessment work that has been undertaken by Renfrewshire
Council and will allow for both a strategic and local insight into
the Gypsy/Traveller community and the implications for
Renfrewshire. 
This work will be undertaken as an on-going action in the Local
Housing Strategy. This on-going work will identify the potential
needs and support requirements of the Gypsy/Traveller
community and whether site provision is required. If

Page 23

Draft Strategic Housing Investment Plan 2025 to 2030   18
accommodation is required, this could be in the form of seasonal,
transit, a permanent site or stopping place. 
Cross boundary and regional implications continue to be
explored in partnership with neighbouring authorities as part of
the Glasgow City Region Housing Market Partnership and will look
at the potential of utilising negotiated stopping in defined areas
to meet transient needs. 
If there is a need to allocate land to meet the accommodation
need of Gypsy/Travellers, this will be addressed through the
Renfrewshire Local Development Plan and its associated Delivery
Programme.   
Should a requirement for accommodation/sites be identified to
meet the needs of Gypsy/Travellers, future updates of the
Strategic Housing Investment Plan will include details of these
projects with funding potentially also being sought from the
Gypsy/Traveller Accommodation Fund where appropriate. 
Travelling Showpeople
There are currently no permanent Travelling Showpeople sites in
Renfrewshire. Through delivery of the strategic priorities included
within the Local Housing Strategy 2023-2028, the Council will
identify if there is a need to allocate land to meet the housing
needs of Travelling Showpeople with any identified need
addressed through the Renfrewshire Local Development
Plan/Action Delivery Programme.   
Addressing the Climate Crisis in Renfrewshire 
Tackling the Climate Crisis is a priority for Renfrewshire Council
with work currently being progressed as part of Renfrewshire’s
Plan for Net Zero and Local Heat and Energy Efficiency Strategy. 
It is recognised that the changing climate has a direct impact on
Renfrewshire’s housing stock and that some residents will be
more vulnerable to this than others. 
The Council’s Climate Change Action Fund supports innovative
projects and initiatives, encouraging engagement and
partnership working across Renfrewshire to tackle the climate
crisis.

Page 24

Draft Strategic Housing Investment Plan 2025 to 2030   19
Climate Change Adaptations 
Both Renfrewshire Council and its housing association partners
are incorporating additional energy efficiency measures as part of
new build design which will actively target reduced carbon
emissions from new build development. 
Projects included within this draft Strategic Housing Investment
Plan aim to tackle fuel poverty by maximising opportunities for
innovative energy efficient development, with greener measures
included within new build developments. 
Link Group social rented development, Thrushcraigs, Paisley     
Acquisition of Private Housing (Rental Off the Shelf) 
In recent years, Scottish Government grant provision has been
included as part of the Strategic Housing Investment Plan to
assist affordable housing providers to purchase appropriate
properties for social rent on the open market. 
This provision has supported acquisition of a range of property
types including empty homes and other types of property where
the acquisition of these properties has aligned with Local Housing
Strategy priorities and the Council’s Acquisitions Strategy. 
However following the significant reduction in Scottish
Government grant funding announced in December 2023 and the
resulting pressure on available resources to fund ongoing and
planned new build affordable housing development – no funding
provision from Renfrewshire’s £13.013 million Resource Planning
Assumption will be included for open market acquisitions in the
years 2024/25 and 2025/26 unless there is unplanned slippage on
new build projects and funding becomes available. 
Available resources will be prioritised to support delivery of new
build affordable homes with individual affordable housing
providers able to continue to make open market acquisitions
where their own resources allow.

Page 25

Draft Strategic Housing Investment Plan 2025 to 2030   20
National Acquisition Programme 
On the 26th April 2024, the Scottish Government announced
funding of £80 million across 2024/25 and 2025/26 to support the
continuation of the National Acquisition Programme to assist
affordable housing providers to expand the supply of affordable
homes and reduce homelessness through open market
acquisition. 
This national fund has the potential to modestly increase the
supply of affordable homes in Renfrewshire with the Scottish
Government still to confirm the criteria for accessing this funding. 
It is anticipated that any funds will be in addition to existing
resource commitments from the Scottish Government and that
affordable housing providers in Renfrewshire will be able to
acquire properties with assistance from this national fund with
Renfrewshire Council awaiting further detail from the Scottish
Government. 
Any additional resources for open market acquisitions would be
funded out with the Council confirmed Resource Planning
Assumption of £13.013 million in 2024/25. 
Council Tax on Empty and Second Homes 
There is currently no direct funding allocated to the affordable
housing programme in Renfrewshire from revenue raised from
empty homes with the Council actively using other mechanisms
to promote delivery of affordable homes. 
This includes the role of the Council’s dedicated ‘More Homes
Officer’ who works with owners of long-term empty properties to
provide advice and assistance with a view of bringing long term
empty properties back into productive use. 
The More Homes Officer also manages the Councils buy back
scheme where properties that meet strategic objectives may be
purchased and added to the Council’s lettable housing stock
utilising the Council’s own resources. 
The Council also continues to monitor developments in terms of
the Scottish Government’s ‘Housing to 2040’ Strategy proposals
to support bringing empty homes back into productive use
through enhanced powers for Councils and funding potentially
being made available to support Councils in bringing empty
homes back into use, or to convert suitable vacant commercial
premises in town centre locations.

Page 26

Draft Strategic Housing Investment Plan 2025 to 2030   21
Over the last five years, the Council’s More Homes Officer has
successfully helped to bring more than 60 long term empty
homes back into the effective housing supply. 
Programme Management and Project Prioritisation 
This draft Strategic Housing Investment Plan splits projects in to
three groups: 
(i) ‘Core Projects’; 
(ii) ‘Shadow Projects’ and 
(iii) ‘Longer Term Projects’. 
Projects within each group are shown in Appendix 3. 
The methodology used to prioritise projects is based on the
potential availability of Scottish Government grant funding as
well as the developers’ ability to progress each project at key
milestones in term of site acquisition, design work, procurement
and potential site start date. 
This approach supports the programming of individual projects in
terms of anticipated grant availability and the potential delivery
timescales of individual projects. 
These projects together form the proposed Strategic Housing
Investment Plan with projects being delivered as funding
becomes available with delivery timescales dependent on future
funding allocations from the Scottish Government.   
Projects included within the ‘Core Projects’ group will be
progressed in the early years of the programme. 
Projects included in the ‘Shadow Projects’ group will be
progressed as ‘Core Projects’ complete or when additional
funding becomes available or where there is the ability to ‘front
fund’ projects to allow projects to proceed earlier. 
Projects included in the ‘Longer Term Projects’ will be delivered
over the longer term with grant funding only likely to become
available beyond the current five year Strategic Housing
Investment Plan period. 
In terms of front funding, the Council or housing association 
partner may initially fund the early stages of project development
costs from their own resources, with grant being paid to
developing organisations at the first available opportunity as
funding becomes available.

Page 27

Draft Strategic Housing Investment Plan 2025 to 2030   22
The use of a three tier project priority approach supports the
effective management of available resources whilst permitting
some flexibility that assists in addressing any slippage of projects
in any given year. 
Projects in the ‘Shadow Projects’ group and in particular ‘Longer
Term Projects’ group may require extended lead in times to allow
for site investigation works, value engineering works, site
assembly or to arrange the necessary private finance to enable a
development to proceed – all of which influence how projects are
prioritised within the programme with all projects subject to
regular review. 
Due to the significant financial constrains around grant funding
availability, there is limited scope to add new projects to the
programme prior to the next update of the Strategic Housing
Investment Plan in 2025. 
Any additional projects brought forward would need to align with
the strategic priorities of the Local Housing Strategy with a clear
funding mechanism in place that does not impact other ‘Core
Projects’. 
Due to the reduction in grant funding from the Scottish
Government and current high tender and development costs -
timescales for the progression of projects may change depending
on the developing organisations financial position and ability to
proceed in a high inflationary environment. 
This may cause movement within the development programme
with projects moving between the three tier project priority
groups to ensure all funding available to Renfrewshire can be fully
utilised. 
Delivery 
Both the Council and its housing association partners will
continue to look for efficiencies in construction methods and
work with design teams to determine the suitability of non-
traditional construction methods for projects included within this
draft Strategic Housing Investment Plan. 
The Council will continue to explore options for joint working
around innovative delivery mechanisms that support the delivery
of affordable housing throughout Renfrewshire.

Page 28

Draft Strategic Housing Investment Plan 2025 to 2030   23
Housing Infrastructure Fund 
As part of the Scottish Government’s Housing to 2040
strategy, Scottish Ministers agreed to continue with the Housing
Infrastructure Fund (HIF) in the period up to 2026.   
The Housing Infrastructure Fund provides both Councils and
housing association partners with additional grant to support the
unlocking of challenging sites where the scale and nature of
infrastructure costs would prevent these sites from being
progressed as part of the Strategic Housing Investment Plan
where projects can deliver affordable homes in line with the
Council’s strategic priorities. The funding allocated to the
Housing Infrastructure Fund nationally is around £50 million in
the 2021-2026 period. 
In recent years, a number of Renfrewshire projects have
successfully accessed the Housing Infrastructure Fund with
housing association partners continuing to look at options to bid
for support from the Housing Infrastructure Fund as and when
required. 
At present, no project developer within this draft Strategic
Housing Investment Plan is looking to access Housing
Infrastructure Fund support, however this may change as
developments move on site. 
Monitoring Progress 
To monitor progress in delivering individual projects and ensure
that resources are managed effectively, a range of project
management measures are employed. 
These include ongoing liaison between services within the
Council and between the Council and housing association
partners on specific projects; quarterly tripartite meetings
between the Council, individual housing association partners and
the Scottish Government; regular internal officer group meetings
to review progress in delivering the overall development
programme and a monthly review of project progress with all
developers of affordable housing. 
Strategic Housing Investment Plan Appendices 
Appendix 1 details progress with projects currently on site as well
as proposals for future projects identified as part of this draft
Strategic Housing Investment Plan.  
Appendix 2 shows recent affordable housing completions with a
breakdown of property size delivered on each site. 
Appendix 3 lists projects that are currently progressing and/or
expected to require grant funding as part of the Strategic Housing
Investment Plan process.

Page 29

Draft Strategic Housing Investment Plan 2025 to 2030   24
Equalities 
This draft Strategic Housing Investment Plan includes housing
provision for a range of different needs groups including housing
for older people and those with physical disabilities. 
This draft Strategic Housing Investment Plan has been prepared
in consultation with the Health and Social Care Partnership to
ensure that projects take account of opportunities to deliver
housing that meets the needs of a range of households with
specific needs. 
In line with The Equality Act 2010 and the associated protected
characteristics, an Equality and Human Rights Impact Assessment
has been prepared alongside the preparation of this draft 
Strategic Housing Investment Plan to identify the likely or actual
effects of it on people. 
The assessment includes identifying where there will be a positive
impact and further opportunities to promote equality. The
assessment did not identify any negative impacts on people in
relation to this draft Strategic Housing Investment Plan. 
Viewing this draft Strategic Housing Investment Plan
This draft Strategic Housing Investment Plan can be viewed on
the Council’s website by visiting: 
https://www.renfrewshire.gov.uk/article/4232/Strategic-Housing-
Investment-Plan 
If you require a printed copy of this draft Strategic Housing
Investment Plan, please email:
strategyandplace@renfrewshire.gov.uk 
Renfrewshire Council development, Ferguslie Park, Paisley

Page 30

25
Appendix 1: Renfrewshire Affordable Housing Project Updates 
1A: Projects completed in 2023/24 
Development Units Status Comment
Ferguslie Park, Paisley 101 Completed
July 2023
101 new social rented homes from Renfrewshire Council that contribute to the regeneration of
the Ferguslie Park area. The final homes were completed in July 2023 with the development
consisting of  22 x 1 Bed, 67 x 2 Bed, 10 x 3 Bed and 2 x 4+ Beds homes. 
Abbey Quarter Phase
IV, Paisley Town
Centre 
81 Completed
December 2023
81 new homes for social rent from Link Group. This fourth phase of development completes the
redevelopment of the former Arnott’s site, a key strategic location in Paisley Town Centre. The
final homes were completed in December 2023 with the development consisting of  10 x 1 Bed
and 71 x 2 Bed homes.
Woodend House,
Houston, West
Renfrewshire
14 Completed
January 2024
14 new homes for social rent from Link Group within a larger private sector development in
Houston, West Renfrewshire which was delivered as part of the Council’s Affordable Housing
Policy. The final homes were completed in January 2024 with the development consisting of 14 x
2 Bedroom homes.

Page 31

Draft Strategic Housing Investment Plan 2025 to 2030   26
1B: Projects currently on site or due to start on site 
Development Units Status Comment
Napier Street,
Linwood  51
On site, due
to complete
September
2024
This social rented development of 51 homes by Sanctuary Scotland Housing Association will add
to the affordable housing supply in Linwood. This project is expected to be completed by the end
of September 2024. Property sizes include 37 x 2 Bed, 14 x 3 Bed. 
Paisley West End,
Sutherland Street 35
On site, due
to complete
February
2025
Sanctuary Scotland are on site developing 35 new homes for social rent as part of the regeneration
of Paisley’s West End. Property sizes include 28 x 2 Bed, 7 x 3 Bed. 
East Lane, Paisley
Town Centre  48
On site, due
to complete
March 2025
This social rented development of 48 homes by Loretto Housing Association will add to the
affordable housing supply in central Paisley. Property sizes include 16 x 1 Bed, 32 x 2 Bed.
Orchard Street,
Paisley   46
On site, due
to complete
mid to late
2025
Work has now started on the Comprehensive Tenement Improvement (CTI) project at Orchard
Street/Causeyside Street, Paisley following 5 blocks of flats being designated as a Housing Renewal
Area (HRA) in March 2017. The overall development is expected to complete in the second half of
2025. Property sizes still to be confirmed. 
Cartha Crescent,
Paisley 33
On site, due
to complete
April 2025
Williamsburgh Housing Association are now on site developing 33 homes for social rented that will
add to the affordable housing supply in central Paisley. Property sizes include 12 x 2 Bed, 21 x 3
Bed. 
Hawkhead, Paisley 30
On site, due
to complete
May 2025
Link Group are onsite developing 30 homes for social that will add to the affordable housing supply
in Paisley. Property sizes include 30 x 2 Bed.

Page 32

Draft Strategic Housing Investment Plan 2025 to 2030   27
Johnstone Castle
Phase II 68
On site, due
to complete
August 2026
Link Group are onsite delivering the second phase of affordable housing in Johnstone Castle. This
development will provide 68 homes for social rent as well as infrastructure and green spaces.
Property sizes include 40 x 2 Bed, 28 x 3 Bed. 
Gallowhill, Paisley 65
Off site, Due
to start on
site in
January 2025
Following public consultation, plans are being progressed to deliver this development of around 65
new Council homes for social rent that will add to the affordable housing supply in the Gallowhill
area.
Howwood Road,
Johnstone (Site 1 of 2) 70
Off site, Due
to start on
site in
January 2025
Renfrewshire Council regeneration area. Following public consultation, plans are being progressed
to deliver 70 new Council homes in this first phase of development in the Howwood Road Area of
Johnstone. 
1C: Projects expected to start on site in 2025/26 or later or when a projected site start date has still to be confirmed 
Development Units Status Comment
West End - Remaining Sites 120 Offsite - Start date
tbc
Sanctuary Scotland are progressing plans for approximately 120 affordable
new homes developed as part of the regeneration of Paisley’s West End.
Bishopton, Phase 3  62 Offsite - Start date
tbc
The third phase of development at Bishopton Dargavel Village is expected to
provide 62 new homes for social rent. Construction of these homes was due to
start in 2023 but has been delayed following the administration of Stewart
Milne Homes who were the developer of these homes for Loretto Housing
Association.

Page 33

Draft Strategic Housing Investment Plan 2025 to 2030   28
Bishopton, Phase 4A 20 Offsite - Start date
tbc
Potential site identified for progression by Loretto Housing Association and a
Private Developer for approximately 20 social rented homes within Bishopton
Community Growth Area (CGA) (Dargavel Village). 
Bishopton, Phase 4B 23 Offsite - Start date
tbc
Potential site identified for progression by a Housing Association and a Private
Developer for approximately 23 social rented homes within Bishopton
Community Growth Area (CGA) (Dargavel Village).
Foxbar Rivers, Paisley 40 Offsite - Start date
tbc
This social rented development of around 40 homes by Renfrewshire Council
will add to the affordable housing supply in the Foxbar area of Paisley and
bring vacant sites back in to use. 
Thrushcraigs, Paisley 50 Offsite, Due to start
on site in July 2027
Renfrewshire Council regeneration area. Following public consultation, plans
are being progressed to deliver around 50 new Council homes in the
Thrushcraigs Area of Paisley. 
Springbank, Paisley (Phase
1 of 2)  65
Offsite, Due to start
on site in October
2026 
Renfrewshire Council regeneration area. Following public consultation, plans
are being progressed to deliver around 65 new Council homes in this first phase
of development in the Springbank Road Area of Paisley. 
Broomlands (West
Campbell Street), Paisley 25 Offsite - Start date
tbc
Renfrewshire Council regeneration area. Following public consultation, plans
are being progressed to deliver around 25 new Council homes in the
Broomlands Area of Paisley. 
Howwood Road, Johnstone
(Site 2 of 2) 60
Offsite, Due to start
on site in October
2027 
Renfrewshire Council regeneration area. Following public consultation, plans
are being progressed to deliver around 60 new Council homes in this second
phase of development in the Howwood Road Area of Johnstone. 
Carbrook Street, Paisley 18 Offsite - Start date
tbc
Renfrewshire Council regeneration area. Following public consultation, plans
are being progressed to deliver 18 new Council homes in the Carbrook Street
Area of Paisley.

Page 34

Draft Strategic Housing Investment Plan 2025 to 2030   29
Older Persons Housing
Reprovisioning, Erskine  24 Offsite - Start date
tbc
Bridgewater Housing Association are progressing plans for a new purpose built
older persons housing development of around 24 units that will replace
existing scattered older persons housing provision across Erskine. Construction
of these homes was due to start in early 2024 but has been delayed following
the administration of Stewart Milne Homes who were the developer of these
homes for Bridgewater Housing Association. Property sizes were likely to
include 6 x 1 Bed, 18 x 2 Bed homes but this may change when a new
development partner is identified. 
Stirling Drive, Linwood  65 Offsite - Start date
tbc
This social rented development of around 65 homes by Linstone Housing
Association will add to the affordable housing supply in Linwood. 
Springbank, Paisley (Phase
II)  35
Offsite, Due to start
on site in January
2030
Renfrewshire Council regeneration area. Following public consultation, plans
are being progressed to deliver around 35 new Council homes in this second
phase of development in the Springbank Road Area of Paisley. 
MacDowall Street,
Johnstone  35 Offsite - Start date
tbc
Discussions will take place to identify an affordable housing provider to
develop this gap site for affordable housing. 
Ryefield, Johnstone  36 Offsite - Start date
tbc
This social rented development of approximately 36 homes by Linstone
Housing Association will add to the affordable housing supply of houses in the
Johnstone area. 
Gibson Crescent, Johnstone 28 Offsite - Start date
tbc
This social rented development of around 28 homes by Williamsburgh Housing
Association will add to the affordable housing supply in Johnstone. 
Garthland Lane, Paisley 32 Offsite - Start date
tbc
This social rented development of around 32 homes by Renfrewshire Council
will add to the affordable housing supply in central Paisley.
West Renfrewshire Villages  62 Offsite - Start date
tbc
Three potential sites identified for progression by Housing Association partners
for approximately 62 social rented homes as part of mixed tenure
developments proposed in West Renfrewshire.

Page 35

Draft Strategic Housing Investment Plan 2025 to 2030   30
Foxbar Rivers, Paisley 40 Offsite - Start date
tbc
This social rented development of around 40 homes by Paisley Housing
Association will add to the affordable housing supply in the Foxbar area of
Paisley and bring vacant sites back in to use.
Westburn
Avenue/Blackstoun Road,
Ferguslie Park, Paisley
22 Offsite - Start date
tbc
This social rented development of around 22 homes by a developer still to be
identified will add to the affordable housing supply in the Ferguslie Park area of
Paisley and bring a vacant site back in to use.
East Lane, Paisley (Site 2 of
2) 30 Offsite - Start date
tbc Site identified for longer term development. 
Supported Housing, Paisley
(Site tbc) 14 Offsite - Start date
tbc
Efforts will continue to identify a potential site for supported housing in Paisley
Town Centre.  
Town Centres tbc Offsite - Start date
tbc
Efforts will continue to identify potential site(s) for affordable housing in Town
Centre locations to promote mixed tenure communities and the growth of
resident town centre populations. 
West Renfrewshire Villages  tbc Offsite - Start date
tbc
Efforts will continue to identify additional potential site(s) for affordable
housing in West Renfrewshire to promote mixed tenure communities. 
North Renfrewshire Villages  tbc Offsite - Start date
tbc
Efforts will continue to identify additional potential site(s) for affordable
housing in North Renfrewshire to promote mixed tenure communities. 
Local Development Plan Affordable Housing Policy Future
Requirements
Subject to the availability of Scottish Government grant, this draft Strategic
Housing Investment Plan will support the development of new affordable
homes within private sector sites as part of Renfrewshire’s Affordable Housing
Policy.

Page 36

31
Completions between 2019 and 2024 & estimated completions 2024/25 Appendix 2
2019/20      
Sanctuary Paisley West End (Phase I (Co-op), Paisley  9x 1 Bed, 18x 2 Bed, 12x 3 Bed 39  
Sanctuary Love Street, Paisley 47x 2 Bed, 85x 3 Bed  132  
Link New Sneddon Street, Paisley 24x 2 Bed 24 195
2020/21       
Link Smithhills Street, Paisley 26x 2 Bed 26  
Renfrewshire Council Bishopton Phase I 10x 1 Bed, 34x 2 Bed, 34x 3 Bed, 2x 4+ Beds 80  
Williamsburgh HA Milliken Road, Kilbarchan 14x 1 Bed, 4x 2 Bed 18 124
2021/22     
Renfrewshire Council Johnstone Castle, Johnstone 4x 1 Bed, 67x2 Bed, 20x 3 Bed, 4x 4+ Beds 95  
Link Group Amochrie Road, Foxbar, Paisley 34x 2 Bed, 2x 3 Bed 36  
Link Group Thrushcraigs Phase II (St Ninians), Paisley 12x 2 Bed, 11x 3 Bed  23  
Paisley HA Westerfield House, Paisley 16x 1 Bed  16 170
2022/23     
Sanctuary/Paisley HA Glenburn, Paisley 8x 1 Bed, 73x 2 Bed, 50x 3 Bed  131  
Link Group Millarston, Paisley 16x 1 Bed, 62x 2 Bed, 2x 3 Bed, 19x 4+ Beds 99  
Renfrewshire Council Auchengreoch Road, Johnstone 8x 1 Bed, 17x 2 Bed, 12x 3 Bed, 2x 4+ Beds 39  
Loretto Bishopton Phase II 12x 1 Bed, 14x 2 Bed, 32x 3 Bed 58  
Williamsburgh HA Albert Road, Renfrew 13x 2 Bed, 29x 3 Bed  42 369
2023/24    
Renfrewshire Council Ferguslie Park, Paisley 22x 1 Bed, 67x 2 Bed, 10x 3 Bed, 2x 4+ Beds 101 
Link Group Abbey Quarter Phase 4 (AQP4), Paisley 10x 1 Bed, 71x 2 Bed  81 
Link Group Woodend House, Houston  14x 2 Bed 14 196    
1,054
2024/2025 - Estimated Completions  
Sanctuary Napier Street, Linwood  37x 2 Bed, 14x 3 Bed  51  
Sanctuary Sutherland Street, Paisley  28x 2 Bed, 7x 3 Bed  35  
Loretto East Lane, Paisley 16x 1 Bed, 28x 2 Bed  48

Page 37

Draft Strategic Housing Investment Plan 2025 to 2030   32
Appendix 3       £ Million  
Homes 
Total Est
Grant Req
(£M) 
Est Spend
by of End
March 2025 
Est Grant
Req 
(Yr 1)
2025/26 
Est Grant
Req 
(Yr 2)
2026/27
Est Grant
Req 
(Yrs 3-5)
2027/28-
2029/30
Est Grant
Req
(Yrs 6+)
2030/31 &
Beyond      Core Projects    
Johnstone Castle Phase II*  68  N/A  N/A  £0.000 £0.000 £0.000 £0.000
Cartha Crescent, Paisley  33  £3.233  £3.233  £0.000 £0.000 £0.000 £0.000
Hawkhead, Paisley  30  £3.102  £1.951  £1.150 £0.000 £0.000 £0.000
Orchard Street/Causeyside Street (HRA)  46  £5.003  £5.003  £0.000 £0.000 £0.000 £0.000
East Lane, Paisley   48  £6.044  £6.044  £0.000 £0.000 £0.000 £0.000
Howwood Road, Johnstone (Site 1 of 2)  70  £10.431  £1.315  £5.997 £3.119 £0.000 £0.000
Gallowhill, Paisley  65  £9.634  £0.707  £5.000 £3.927 £0.000 £0.000
West End - Remaining Sites  120  £10.942  £4.655  £0.000 £2.100 £4.191 £0.000
Affordable Housing Policy Future Reqs  tbc  tbc  tbc  tbc tbc tbc tbc
*Funded without Grant from RPA   480  £48.389  £22.908  £12.147 £9.146 £4.191 £0.000      
£ Million        
Homes 
Total Est
Grant Req
(£M) 
Est Spend
by of End
March 2025 
Est Grant
Req 
(Yr 1)
2025/26 
Est Grant
Req 
(Yr 2)
2026/27
Est Grant
Req 
(Yrs 3-5)
2027/28-
2029/30
Est Grant
Req
(Yrs 6+)
2030/31 &
Beyond      Shadow Projects    
Bishopton Phase 3  62  £5.653  £0.000  £0.000 £2.000 £3.653 £0.00
Bishopton, Phase 4A  20  £1.824  £0.000  £0.000 £1.824 £0.000 £0.000
Bishopton, Phase 4B  23  £2.097  £0.000  £0.000 £0.000 £2.097 £0.000
Springbank, Paisley (Phase 1 of 2)  65  £5.433  £1.352  £0.450 £1.000 £2.631 £0.000
Foxbar Rivers, Paisley  40  £3.343  £0.050  £0.500 £1.000 £1.793 £0.000
Howwood Road, Johnstone (Site 2 of 2)  60  £5.015  £0.400  £0.400 £0.400 £3.815 £0.000
Thrushcraigs, Paisley  50  £4.179  £0.119  £0.600 £1.000 £2.460 £0.000

Page 38

Draft Strategic Housing Investment Plan 2025 to 2030   33 
Springbank, Paisley (Phase 2 of 2)   35  £2.925  £0.350  £0.000 £0.000 £2.575 £0.000
Older Person's Reprovisioning, Erskine  24  £2.578  £0.000  £0.578 £1.000 £1.000 £0.000
Stirling Drive, Linwood  64  £6.936  £0.859  £1.000 £1.500 £3.577 £0.000
Broomlands & Carbrook Street, Paisley  43  £6.130  £0.287  £0.000 £0.000 £5.843 £0.000  
486  £46.113  £3.417  £3.528 £9.724 £29.444 £0.000  
Homes 
Total Est
Grant Req
(£M) 
Est Spend
by of End
March 2025 
Est Grant
Req 
(Yr 1)
2025/26 
Est Grant
Req 
(Yr 2)
2026/27
Est Grant
Req 
(Yrs 3-5)
2027/28-
2029/30
Est Grant
Req
(Yrs 6+)
2030/31 &
Beyond      Longer Term Projects    
Ryefield, Johnstone  36  £3.664  £0.150  £0.000 £0.000 £3.514 £0.000
Gibson Crescent/North Road, Johnstone   28  £2.553  £0.000  £0.000 £0.000 £2.553 £0.000
West Renfrewshire Villages (3 sites)   62  £5.653  £0.000  £0.000 £0.000 £1.641 £4.012
Garthland Lane, Paisley  32  £2.675  £0.225  £0.000 £0.000 £0.000 £2.450
Foxbar Rivers, Paisley  45  £3.647  £0.000  £0.000 £0.000 £0.000 £3.647
Westburn Avenue/Blackstoun Road, Paisley  22  £1.839  £0.143  £0.000 £0.000 £0.000 £1.696
East Lane, Paisley (Site 2 of 2)  30  £2.735  £0.000  £0.000 £0.000 £0.000 £2.735
MacDowall Street, Johnstone  35  £3.191  £0.000  £0.000 £0.000 £0.000 £3.191
Supported Housing, Paisley (Site tbi)  14  £1.277  £0.000  £0.000 £0.000 £0.000 £1.277
Town Centres (Future sites tbi)  tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc
West Ren Villages (Future sites tbi)   tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc
North Ren Villages (Future sites tbi)  tbc  £tbc  £tbc  £tbc £tbc £tbc £tbc  
304  £27.234  £0.518  £0.000 £0.000 £7.708 £19.008              
1,270  £121.736  £26.843  £15.675 £18.870 £41.343 £19.008