___________________________________________________________________
To: Communities and Housing Policy Board
On: 20 August 2024
___________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Housing-led Regeneration and Renewal Programme for
Renfrewshire – Year 3 Update
___________________________________________________________________ 
1. Report Summary 
1.1 Renfrewshire Council’s Housing-Led Regeneration and Renewal Programme
was approved by the Communities, Housing and Planning Policy Board on 18
January 2022 with amended proposals for three of the eight regeneration
areas also approved on 15 March 2022. 
1.2 This programme is being taken forward as a key Council priority, designed to
deliver maximum benefits for residents and with the active involvement of
services across the Council and Community Planning partners, to deliver
modern, high quality, energy efficient, affordable Council housing that will not
only significantly enhance the Council’s housing stock but will also contribute
to the wider transformation of communities across Renfrewshire. 
1.3 As our plans for investment and improvement are developing, it is becoming
clear that meeting Scottish Government Energy Efficiency targets will be
particularly difficult in blocks where the Council are a minority owner. This
report therefore sets out proposals to offer resident owners within
regeneration areas the opportunity to sell to the Council and become a
Council tenant in that same property, subject to qualifying criteria outlined
further in the report. 
1.4 The board are provided with regular updates on the Housing-Led regeneration
and renewal programme in the service update reports throughout the course
of each year. This annual report provides more detailed information and a
summary of progress over the last year and also provides information around
the governance structure in place with regards to officer membership and
reporting methods for the programme Board and Thematic Groups
established as part of the project delivery mechanisms.

Page 2

1.5 This report seeks authority to make amendments to the Council’s Acquisition
Scheme for Private Housing, as set out in Section 5 of this report.
__________________________________________________________________________________ 
2. Recommendations 
It is recommended that the Communities and Housing Policy Board:
2.1 Notes the positive progress made in each of the eight regeneration and
renewal areas within this ambitious ten-year programme. 
2.2 Approves amendments to the Council’s Acquisition Scheme for Private
Housing outlined in paragraph 5.4 below.
__________________________________________________________________________________ 
3. Progress Summary 
3.1 The scope of regeneration activity and timescales for delivery differ in each of
the regeneration areas across this ten-year programme, with some more
complex than others. A phasing strategy was developed to take account of a
number of factors including, delivery timescales, rehousing requirements,
contractor availability, maximising grant support for owner participation and
consideration of wider development constraints. The timeline for the Housing-
Led Regeneration and Renewal programme was presented to the Board in
August 2023 and is shown below with a vertical line added to highlight the
position as at the end of June 2024. All regeneration areas remain on
schedule as previously reported, with the exception of the delivery of newbuild
homes for the first phase of the Broomlands area as detailed further in
paragraph 4.5.4 below.

Page 3

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Staff and resources
Rehousing Strategy
Demolition
Investment Pilot Project
Investment On-site
Demolition
Investment On-site
Investment On-site
Demolition (Phase 1) Demolition (Phase 2)
Investment On-site
New Build (Phase 1)
Pre-contract (Phase 2) New Build (Phase 2)
Demo (Ph 1)
Investment Pre-contract
New Build (Phase 1)
Pre-contract (Ph 2) New Build (Phase 2)
Rehousing (Ph 1) RH (Ph 2)
Demolition (Ph 1) Demolition (Ph 2)
Pre-contract (Ph 1) New Build (Ph 1)
Pre-contract (Ph 2) NB (Ph 2)
Demolition
Pre-contract New Build
D Investment Pre-contract Investment On-site
2030/31 2031/32
2029/30 2031/32
Approved August 2023
2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
Applicable to all areas
2030/31
Auchentorlie
Investment & Demolition
2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30
2030/31 2031/32
Ferguslie/Broomlands
Investment (inc pre-1919 tenements), Demolition & New Build
2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Howard Street Area
Investment & Demolition
2025/26 2026/27 2027/28 2028/29 2029/302021/22 2022/23 2023/24 2024/25
2031/32
Howwood Road Area
Investment, Demolition & New Build (including on school sites)
2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
Moorpark
Investment
2026/27 2027/28 2028/29 2029/30 2030/312021/22 2022/23 2023/24 2024/25 2025/26
2030/31 2031/32
Waverley Road
Investment & Demolition
2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32
2025/26 2026/27 2027/28 2028/29 2029/30
Thrushcraig
Demolition & New Build
2021/22 2022/23 2023/24 2024/25
2031/32
Springbank/Mossvale
Investment, Demolition & New Build
2026/27 2027/28 2028/29 2029/30 2030/312021/22 2022/23 2023/24 2024/25 2025/26
OwnershipConsolidation
Inv Pre-Contract
Ownership Consolidation
Inv Pre-contract
OwnershipConsolidation
Ownership Consolidation
Ownership Consolidation
OwnershipConsolidation
InvestmentOn-site
Demolition
RehousingStrategy
Rehousing(Ph 1)
Ownership Consolidation
RehousingStrategy
RehousingStrategy
Rehousingstrategy
Investment On-site
Pre-Contract(Ph 1)
InvestmentPre-contract
Demo (Ph2)
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation`
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Stakeholder Engagement
Benefits Realisation
Rehousing(Ph 2)
OwnershipConsolidation
RehousingStrategy
Pre-Contract (Phase 1)

Page 4

3.2 Each regeneration area has a dedicated Housing Regeneration Officer and
Development Officer with responsibility for the delivery of key actions,
including the effective communication with tenants, residents, and private
owners. The Council’s website has a dedicated Housing Regeneration and
Renewal section, and this is updated regularly to ensure that residents can
access current and up to date information as and when they require it. 
3.3 A new approach to Community Neighbourhood Renewal is being established
with community representatives, across Council Services and with third party
partners to operate in parallel with the physical regeneration plans. The
neighbourhood renewal approach will be tailored to the needs and
circumstances of each area, going beyond housing and the immediate
external environment, and taking account of broader issues such as links to
health and wellbeing, access to outdoor space and sustainable travel and
employment or training opportunities that maximise the benefits achievable for
local residents. This approach aims to strengthen community voices and
improve place-based decision making across all regeneration areas in
Renfrewshire to enhance and measure the offering and impact of the
programme. 
4. Regeneration and Renewal Area Update   
4.1  The annual Regeneration and Renewal update report provides an opportunity
to highlight the progress that has been made in each of the regeneration
areas, including successful negotiations for the acquisition of private
properties required for demolition. 
4.2 Discussions continue with owners across seven of the eight regeneration
areas, where acquisition is required to facilitate demolition. Of the 89 privately
owned properties identified for acquisition and demolition, 52 have been
acquired by the Council, a further 7 are agreed and with legal services to
conclude, 24 are at various stages of the negotiation process and 6 remain to
be valued. Table 1 below highlights the current position across the seven
areas where demolition is planned. 
Table 1    
Total
at
Outset Acquired
With Legal
Services to
conclude
Valued and
neg cont.
Valuation
to be
instructed
Auchentorlie 1 0 0 1 0
Howard Street 11 7 0 1 3
Thrushcraigs 6 3 0 3 0
Broomlands 16 9 1 6 0
Waverley 4 3 0 1 0
Springbank 36 20 6 7 3
Howwood Road 15 10 0 5 0  
89 52 7 24 6

Page 5

4.3 Demolition will be carried out on a phased basis, in line with the rehousing
and acquisition strategy for each regeneration area. Where newbuild housing
is proposed on the cleared sites, a key objective of this programme is to
deliver homes of a suitable type and size that will meet current and future
needs and to enable existing households to remain in the area where they
choose to do so. 
4.4 As previously reported, all Council tenants affected by demolition will be
offered suitable alternative accommodation in line with the Council’s housing
allocation policy and will be entitled to apply for home-loss and disturbance
payments, subject to qualification criteria, where the move is in accordance
with the phasing strategy that facilitates this regeneration initiative. 
4.5 Officers are reviewing the mixed tenure nature of blocks within retention and
investment areas to identify any opportunities where the Council may want to
consider increasing their ownership in some blocks where this would allow
investment works to proceed. More information on the current ownership
profile in each retention area is contained in the area updates detailed further
below. 
4.5.1 Auchentorlie, Paisley 
Investment & Retention Properties
The Auchentorlie investment area includes 3 blocks in full Council ownership
and 7 mixed tenure blocks where the investment proposals are subject to
owner consultation and agreement to participate. The Housing Investment
team are currently contacting owners in these blocks to discuss their
individual circumstances, have conversations around the costs for
improvement works and advise them of any available grants they may be
eligible for, to assist them to participate in the investment programme for this
area. 
A commission for landscaping design has been carried out in the Auchentorlie
area that will take into consideration the boundary treatments, bin storage and
recycling requirements as well as design of open areas/amenity spaces. 
A submission has been made to secure funding for owners in this area from
Energy Efficient Scotland: Area Based Schemes (EES: ABS), where grants
are made available to eligible owners to contribute towards the costs of
energy efficiency improvement works.  This funding is subject to qualifying
criteria, with the proposed investment works subject to owner agreement. 
A range of energy efficient improvement options have been developed, with a
view to facilitating an uptake in owner participation. The options available for
the Auchentorlie area will be discussed with each of the 16 private owners in
this retention area in the coming weeks.

Page 6

Pilot Project - 74 Seedhill Road 
In order to showcase the improvement works that will be delivered through
investment in retained blocks, a pilot project has been identified at 74 Seedhill
Road involving a range of preliminary investigations and surveys which have
informed the detailed design and specification of works. The Building Warrant
application process is underway, and works will commence on site following
approval of the design and technical specification. We have been in contact
with the tenants at this address to advise them of the extent of the programme
of works internally and externally for this block and it is anticipated there may
be the requirement for a period of temporary decant for 4 tenants to ensure
the effective delivery of all improvement measures. 
Demolition Properties 
Members will note that a separate report is being considered by the Board in
relation to the condition of the block identified for demolition within this
regeneration area.   
All properties within 5, 7 and 9 Auchentorlie Quadrant are now vacant
following the successful rehousing of Council tenants, in line with the
rehousing strategy agreed for this regeneration area. 
4.5.2 Howard Street Area, Paisley 
Investment & Retention Properties 
The Howard Street investment area includes 6 blocks in full Council
ownership and 12 mixed tenure blocks where the investment proposals are
subject to owner consultation and agreement to participate. 
Similar to the Auchentorlie area, a submission has been made to secure
funding for owners in this area from Energy Efficient Scotland: Area Based
Schemes (EES: ABS), where grants are made available to eligible owners to
contribute towards the costs of energy efficiency improvement works.  This
funding is subject to qualifying criteria, with the proposed investment works
subject to owner agreement. 
The Housing Investment team will contact owners in these blocks later this
year, to discuss their individual circumstances, have conversations around the
costs for improvement works and advise of any available grants they may be
eligible for, to assist them to participate in the investment programme for this
area. 
Demolition Properties 
The Howard Street area includes the demolition of 11 blocks of flats.  7 of 11
privately owned properties required to facilitate demolition have now been
acquired by the Council and discussions are ongoing with the remaining 4
owners with a view to voluntarily acquiring these properties.

Page 7

Several phases of rehousing priority have been added in this area with 41 of
the 66 properties now vacant, in line with the rehousing strategy agreed for
this regeneration area. 
4.5.3  Waverley Road, Paisley 
Investment & Retention Properties 
The Waverley Road investment area is majority Council owned with only one
block in mixed tenure, however, investment proposals in that block remain
subject to owner consultation and agreement to participate in the scheme of
improvements. 
The Housing Investment team have been reviewing options for the blocks
being retained on Waverley Road including options for new balconies where
applicable. Once the specification of works for this area is agreed and costed,
tenants and residents will be invited to a neighbourhood renewal event where
the programme of works will be discussed in more detail and partner
organisations can take the opportunity to offer their services and find out what
residents would like to see included as part of the enhanced environmental
improvements surrounding their homes. 
Demolition Properties 
The Waverley Road area includes 12 blocks for demolition. 3 of the 4 privately
owned properties within the demolition blocks have now been acquired by the
Council with negotiations with the last remaining owner ongoing. 
Several phases of rehousing priority have been added in this area with only a
small number of remaining tenants requiring suitable alternative
accommodation. This is in advance of the timeline set out for the rehousing
strategy for this regeneration area. 
Given the increased number of vacant blocks within this area, arrangements
are now being made to procure a contractor to deliver a programme of
demolition for 8 of the 12 vacated blocks at this location. 
Procurement of a demolition contractor for these 8 blocks is underway with
officers working with utility companies to organise the removal of gas and
electricity meters from each property in advance of service disconnections.
Regular visits are being carried out to ensure these vacant properties remain
secure and identify and report any instances of fly tipping.

Page 8

4.5.4 Ferguslie/Broomlands, Paisley 
Investment & Retention Properties 
The Ferguslie/Broomlands investment area includes 82 privately owned
properties across a number of blocks, with 3 in full Council ownership and 13
in mixed tenure (6 of these are Council minority ownership) where the
investment proposals are subject to owner consultation and agreement to
participate. Some of the blocks within this area are of traditional sandstone
construction and the Housing Investment team are reviewing options and
costs associated with the works required for these properties to enable them
to be enhanced to meet the Energy Efficiency standards proposed. 
Once the specification of works for this area is agreed and costed, tenants
and residents will be invited to a neighbourhood renewal event where the
programme of works will be discussed in more detail and partner
organisations can make themselves available to offer their services and find
out what residents would like to see included as part of the enhanced
environmental improvements for the areas surrounding their homes and into
Ferguslie Gardens. 
Demolition Properties 
The Ferguslie/Broomlands area includes the demolition of 5 blocks of flats.  9
of the 16 privately owned properties required to facilitate demolition have now
been acquired by the Council and discussions are ongoing with the remaining
7 owners with a view to voluntarily acquiring these properties in advance of
demolition. 
Newbuild Housing 
It had originally been planned that a first phase of newbuild development
consisting of 18 units at Carbrook Street would be delivered in advance of
demolition within this area. 
Following a reduction in the Resource Planning Assumptions for Renfrewshire
and the relatively high tendered costs for the Carbrook Street development,
this project has been reprofiled within the draft Strategic Housing Investment
Plan for 2025 – 2030 which is the subject of a separate report presented to
this meeting of the Communities and Housing Board.  Tender options for the
development of the Carbrook Street site will be reviewed further following
approval of the draft SHIP for 2025 – 2030 and reported to a future meeting of
this Board.

Page 9

4.5.5 Howwood Road Area, Johnstone 
Investment & Retention Properties 
The Howwood Road investment area has 122 Council properties and 74
privately owned across 45 blocks. Investment proposals in mixed tenure
blocks remain subject to owner consultation and agreement to participate in
the scheme of improvements. 
This includes 5 blocks that are not included within our investment proposals
as although they are within the regeneration and renewal boundary for the
Howwood Road area, the Council has no ownership interest as these blocks
are wholly privately owned. Private Sector Housing Grant from the Council is
only available to owners within communal blocks where the Council also owns
property within block (mixed tenure). Owners within the solely privately owned
blocks have been made aware that they are unable to access PSHG
assistance and officers will work with the owners to signpost them to advice
and assistance from partner agencies where they indicate they would like this
assistance. 
The Housing Investment team have been reviewing options for the blocks
being retained in the Howwood Road area including consideration of options
for enclosing the balconies to make the homes more energy efficient. Once
the specification of works for this area is agreed and costed, tenants and
residents will be invited to a drop in event locally to discuss the proposed
programme of works in more detail. 
Neighbourhood Renewal Event 
Section 3.3 of this report highlighted a new approach being rolled out for
Neighbourhood renewal and the Howwood Road area was selected as a pilot
for this new approach, with a specific focus on promoting health and well-
being, employability, and energy advice, along with community capacity
building. 
The first Neighbourhood Renewal meeting for this area took place on 22nd
May 2024 and was well attended and received by the local community with
over 140 individuals in attendance. Linking in with the newbuild consultation
event planned for this date, we were able to work collaboratively across
Council services, with third sector partners to use the newbuild consultation
event as a platform to launch the Neighbourhood Renewal Group for this
area. 
The event provided tenants and residents with the opportunity to speak to
Council officers and partners about the development plans and receive advice
on matters such as employability, health and wellbeing and energy advice.

Page 10

Positive feedback was received regarding the newbuild development and the
advice and assistance that was available at the event, including energy
advice, health and wellbeing support, employability, and information on how to
be involved in the project going forward. 
As part of this neighbourhood renewal process for this area, residents were
asked for ideas or suggestions for the development of the former St. Davids
school site as it is not envisaged that this will be developed for housing due to
site constraints previously highlighted to the Board. A number of the ideas
collated for consideration for the vacant site are listed below: 
• Garden area with benches
• Outdoor learning area that could be utilised by local schools
• Football park/pitches
• Wooded or wild park with path network and space for the elderly to meet
• Enclosed area for dogs/agility area. 
Another suggestion that has been considered and developed further since the
event in May, is the use of a property for a local drop-in surgery where tenants
and residents can speak with officers about the programme of works in the
area and could potentially hold a number of advice or wellbeing surgeries to
support or in association with the partners we are working with, across this
area. A suitable centrally located property has been identified for this purpose
and following completion of the required changes to facilitate the use as a
drop in venue, officers will promote the location and times this service will be
available to residents within the Howwood Road regeneration and renewal
area.   
Newbuild Housing 
McTaggart Construction have been appointed to design and build 70 new
homes on the site of the former Cochrane Castle school and land adjacent to
the Highcraig Avenue shops.  The development will provide a mix of property
types, with many wheelchair-accessible and include a wide range of property
types and sizes ranging from 1 to 5-bedroom homes. 
These new homes are part of the first phase of newbuild planned for this area
and will be built to meet the highest standards in energy efficiency, coming
complete with air source heat pumps and solar panels. As this is classed as a
major development (50+ homes), two pre-application community consultation
events have been held in May and June to inform the community of the
proposals ahead of submission of the formal Planning Application in July. 
As originally reported to this Policy Board, rehousing of tenants displaced in
this area will take place on a phased basis following completion of the first set
of 70 newbuild homes, with phased demolition and at least one further phase
of newbuild thereafter.  Officers will soon commence the application process
for households within the first demolition phase to allow a matching exercise
to be undertaken for those who choose to remain within the area.

Page 11

Feedback from the local community at the consultation events highlighted
concerns about the condition and appearance of the four retail units on
Highcraig Avenue. Two of the four retail units are privately owned and
operational, with the remaining units in Council ownership and currently void. 
The Assets and Estates team have approached the private owners of both
units with a view to voluntarily acquiring these commercial units, however,
negotiations have been unsuccessful to date, and it is likely voluntary
acquisition of these units will not be possible in the short to medium term.
Negotiations to voluntarily acquire these properties will continue in the
meantime and any potential requirement for CPO will be presented to a future
board. 
As part of the overall regeneration and ahead of Phase 2 of the newbuild
programme, the Council are currently procuring a market feasibility and
overview report to assess the suitability of demolishing the existing retail units
to be replaced with 1-2 new retail units. On completion of this feasibility, the
Regeneration Team will assess the options available to the Council.   
4.5.6 Springbank/Mossvale, Paisley 
Investment & Retention Properties 
The Springbank/Mossvale investment area includes 31 Council properties and
66 privately owned properties across 6 mixed tenure blocks and one where
the Council have no ownership interest. Investment proposals are subject to
owner consultation and agreement to participate and like the Howwood Road
area, where we have a fully privately owned block, officers will work with these
owners to signpost them to advice and assistance from partner agencies,
where they indicate they would like this assistance. 
Once the specification of works for this area is agreed and costed, tenants
and residents will be invited to a neighbourhood renewal event where the
programme of works can be discussed in more detail and partner
organisations can make themselves available to offer their services and find
out what residents would like to see included as part of the enhanced
environmental improvements for the areas surrounding their homes. 
Demolition Properties 
The Springbank/Mossvale area includes the demolition of 9 blocks of flats. 16
properties within these blocks remain in private ownership at this time,
however positive negotiations continue as we seek rehousing opportunities for
some of the residents who are being displaced as part of this project prior to
the blocks being demolished.

Page 12

Following the successful rehousing and acquisition of privately owned
properties within the block at 1 – 19 Mossvale Square, officers were able to
take forward the advance demolition of this block which had begun to attract
anti-social behaviour.  Officers from the regeneration and development team
are working collaboratively with the wardens and neighbourhood services and
Police and Fire Scotland to highlight and address any concerns raised
regarding vacant dwellings as they await demolition. 
Newbuild Housing 
On completion of demolition, a feasiblity study will be carried out, together
with a site investigation, to assess the site ahead of the tender issue for new
build construction. 
Due to the size and scale of development for the Springbank area, re-housing
of tenants and private acquisitions have been phased to allow the clearance
of land for each phase of newbuild development. Officers have weekly drop-in
surgeries within the Beechwood Community Centre to be available for tenants
and residents to answer any questions or queries they have regarding the
regeneration programme for this area. 
Housing options advice is offered to tenants and residents of demolition
properties on a phased basis in line with the rehousing strategy for the
Springbank area. 
4.5.7 Thrushcraigs, Paisley 
Demolition Properties 
The Thrushcraigs area includes the demolition of all 16 blocks of flats within
the regeneration boundary.  3 of the 6 privately owned properties required to
facilitate demolition have now been acquired by the Council and discussions
are ongoing with the remaining owners with a view to voluntarily acquiring
these properties prior to demolition. 
Several phases of rehousing priority have been added with 40 of the 96
properties now vacant, in line with the rehousing strategy agreed for this
regeneration area. 
The Thrushcraigs area includes a number of properties that are utilised by
Homeless Services as temporary accommodation. Given the current high
level of demand for this type and size of accommodation, the rehousing
strategy for this area has been amended to allow ongoing use of this facility at
this time. This will be reviewed on a regular basis while actively rehousing
tenants from other blocks at this location and proceeding with the acquisition
strategy to allow clearance of the blocks for future newbuild development.

Page 13

Newbuild Housing 
On completion of demolition, a feasiblity study will be carried out, together
with a site investigation, to assess the site ahead of the tender issue for new
build construction. 
4.5.8 Moorpark, Renfrew 
The Moorpark investment area has a high proportion of private owners with
144 private flats across 75 blocks, 16 of which where the Council have no
ownership interest. The Council have 175 properties within the area with full
ownership in 8 of the 75 blocks. To ensure the successful delivery of the
investment programme, it will be essential to reach agreement with a number
of owners to ensure as many mixed tenure blocks progress with investment
as possible.   
Given investment work are not scheduled until later in the ten-year
programme, officers have developed an initial action plan for this area,
identifying areas for improvement in relation to the external environment and
roads that will be addressed in advance of the wider investment programme. 
Officers are also reviewing the Council’s ownership and block make up in the
area to identify any ownership consolidation opportunities that could assist the
future delivery of the investment programme. 
As we approach the delivery timescales for this area, officers will explore
funding opportunities available at that time, to assist owners in mixed tenure
blocks to reduce the cost of participation. 
5. Acquisition Scheme for Private Housing 
5.1 The Communities, Housing and Planning Policy Board on 20 August 2019
approved the Acquisition of Private Housing Scheme to be overseen by the
then Director of Communities, Housing & Planning. This Scheme formed part
of the HRA Capital Investment Programme and was to be targeted at the
purchase of properties which would meet identified needs and increase the
supply of good quality Council housing in areas where there is need and
recognised demand. The Housing and Community Safety Policy Board on
13 May 2014 approved the Last-in-the-block Sale Policy which set out
arrangements for the disposal of Council properties which become void, at no
less than market value, where the property is the last one owned by the
Council in a block of five or more flats. 
5.2 Amendments to both the Acquisition of Private Housing Scheme and the Last-
in-the-block Sale Policy in respect of Housing Regeneration Areas were
approved by the Communities and Housing Policy Board on 16 August 2022.
The sale of the last house in a block in certain circumstances in accordance
with the Last-in-the-block Sale and Acquisition Policy have been highly useful
negotiating positions for the Council in agreeing the voluntary acquisition of
properties to deliver the Housing-led Regeneration and Renewal Programme.

Page 14

5.3 The Housing-Led Regeneration and Renewal Programme is an opportunity to
meet Scottish Government Energy Efficiency targets within the blocks being
retained in Housing Regeneration Areas. However, it is recognised that the
costs of these measures are significant, even when grant funding is
applicable. Accordingly, authorisation is sought for the amendments to the
Council’s Acquisition Scheme for Private Housing outlined in paragraph 5.4
below enabling the Council to offer resident owners within Housing
Regeneration areas the opportunity to sell to the Council and become a
Council tenant in their existing home. 
5.4 It proposed for the Communities and Housing Policy Board amendments to
the Council’s Acquisition Scheme for Private Housing, in full accordance with
the approved Council Scheme of Delegation and Financial Regulations, to
authorise the voluntary acquisition of privately-owned properties in mixed
tenure blocks where:   
• the privately-owned properties are located within Housing Regeneration
Area boundaries and are situated in a mixed-tenure block that has
been identified for retention and capital investment; and 
• the owner-occupiers are unable or unwilling to contribute their share of
the costs of works and want to become Council tenants. 
The Council would acquire these privately-owned properties to allow
investment works to progress and the existing owner-occupiers would
continue to reside in their existing properties with them converting to a Council
tenancy. 
This would apply where the privately owned property is situated within a
mixed tenure block that has been identified for retention and capital
investment and the owner-occupier(s) are unable or unwilling to contribute
their share of the works costs and with them choosing to become Council
Tenants and allow investment works to progress. 
5.5 Presently, where an owner is unable or unwilling to contribute their share of
the costs for the investment to their block and to allow the improvement works
to proceed this would result in no works being carried out to the block. This
ability to acquire additional privately owned properties within mixed tenure
blocks In Housing Regeneration Areas identified for retention and investment
as part of the wider Housing-Led Regeneration and Renewal Programme will
be a valuable negotiating position for officers that will allow investment works
to proceed, as well as facilitating the owner to remain within their home as a
tenant and therefore benefitting from the investment works.  More widely, this
will also benefit tenants and residents through facilitating the delivery of
improvement works where they otherwise may have been undeliverable.

Page 15

6. Programme Governance
6.1 To ensure robust programme governance, a Housing-Led Regeneration and
Renewal Programme Board was established and is attended by Chief Officers
and senior officers from across Council Services, meeting quarterly to monitor
the programme’s performance. This information is then reported to
Communities and Housing Policy Board, within the regular Service Update
Reports and the annual update each August. 
6.2 Four Thematic Groups have been established as detailed above, with
membership and remit recently refreshed as we move from the planning
phase into the implementation stages of the programme. These groups of 2nd
and 3rd tier officers meet quarterly and more regularly if required. 
Thematic Groups Attendee Remit: 
• Stay informed about how the HR&R impacts service delivery and feedback
opportunities/constraints to service and HR&R team. 
• Act as a key link to service delivery departments to review designs,
proposals, and consultations from external consultants on the HR&R
programme.  
• Identify opportunities for services and work collaboratively to contribute to
place based activities in regeneration areas. 
• Identify and agree benefits monitoring and evaluation indicators tied to
corporate objectives. 
• Attend Neighbourhood Renewal Groups where necessary. 
__________________________________________________________________________________

Page 16

Implications of the Report
1. Financial – The financial background to this investment programme was
detailed in the report to Council on 17 December 2020 by the Chief Executive,
Director of Communities and Housing and Director of Finance and Resources
highlighting that it will be funded through financial sustainable borrowing on
the HRA. A strategic review of the 30-year HRA business plan model
confirmed there was sufficient headroom to support this investment
programme. The review identified £100 million of additional investment
capacity which can be relied upon for long term planning and investment
purposes, and this is subject to ongoing review as part of the annual update of
the HRA 30-year business plan. The acquisition of private homes to add to
Council stock will be funded from the income received from the sale of last in
the block properties, as previously approved by the Board. 
2. HR & Organisational Development – None.
3. Community/Council Planning 
• Our Renfrewshire is well – this investment programme is contributing to
improved wellbeing and quality of life for residents.
• Our Renfrewshire is thriving – this investment programme will deliver a
diverse range of economic and community benefit packages over the
lifetime of the project.
• Our Renfrewshire is safe – ensuring our neighbourhoods are safe and
attractive places to live. 
4. Legal – work will be required with respect to acquisitions, disposals,
conveyancing, and title changes as necessary. 
5. Property/Assets – as we progress through the phases of the investment
programme, there is an element of property acquisitions and disposals and
demolition of some existing properties as approved by the Board.   
6. Information Technology – N/A
7. Equality & Human Rights –
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be
published on the Council’s website.

Page 17

8. Health & Safety – N/A
9. Procurement – a Procurement Strategy has been developed to ensure the
delivery of the investment, demolition and newbuild programmes include
locally deliverable community benefits from each contract.
10. Risk – a risk register has been developed to consider various risks including
those relating to financial and procurement as referred to in the implications
section of this report. This risk register is monitored and regularly updated
throughout the delivery of the Housing led Regeneration and Renewal
programme. 
11. Privacy Impact – N/A 
12. Climate Risk – the investment programme will contribute towards meeting
the Council’s targets on climate change. 
13. Children’s Rights – None 
14. COSLA Policy Position – N/A
_________________________________________________________
List of Background Papers
Report to the Communities and Housing Policy Board, 22 August 2023, ‘Housing-led
Regeneration and Renewal Programme for Renfrewshire – Year 2 Update’
Report to the Communities, Housing and Planning Policy Board, 16 August 2022,
‘Housing-led Regeneration and Renewal Programme for Renfrewshire – Year 1
Update’
Report to the Communities, Housing and Planning Policy Board, 15 March 2022,
‘Housing-led Regeneration and Renewal Programme for Renfrewshire’
Report to the Communities, Housing and Planning Policy Board, 18 January 2022,
‘Housing-led Regeneration and Renewal Programme for Renfrewshire’
Report to the Communities, Housing and Planning Policy Board, 18 May 2021,
‘Housing-led Regeneration and Renewal Programme for Renfrewshire’
Report to Council, 17 December 2020, ‘Housing-led Regeneration and Renewal
Programme for Renfrewshire’   
Report to Communities, Housing and Planning Policy Board, 20 August 2019,
‘Acquisition of Private Housing’
Report to Housing and Community Safety Policy Board, 13 May 2014, ‘Single
Council Dwellings in Larger Common Blocks’   
___________________________________________________________________ 
Author: Jennifer Murdoch, Housing Regeneration and Development Manager (acting)