Page 1

PUBLIC
___________________________________________________________________ 
To:  Communities and Housing Policy Board 
On:  19 May 2026
___________________________________________________________________ 
Report by: Director of Communities & Housing Services
___________________________________________________________________ 
Heading: Housing Landlord Compliance – Bi-annual Performance Report 
1. Summary 
1.1 All social landlords must ensure they meet all duties in relation to tenant and
resident safety and have an effective system in place to ensure compliance
with statutory, legislative and regulatory responsibilities. 
1.2 The Housing Landlord Compliance Strategy 2025-2028 was approved by the
Policy Board on 11th March 2025 and Section 7 of the strategy provided
details of the internal governance arrangements for performance
management, which includes a bi-annual report to be presented to the
Communities and Housing Policy Board.   
1.3 The six month report was presented to the Communities and Housing Policy
Board in October 2025. This report is the 12 month performance report for the
period from April 2025 to March 2026.
___________________________________________________________________
2. Recommendations 
It is recommended that the Communities and Housing Policy Board: 
2.1 Notes the content of the Landlord Compliance Performance Report and the
suite of Key Performance Indicators (KPIs) at Appendix 1 of the report.
___________________________________________________________________

Page 2

PUBLIC
3. Background 
3.1 The Housing Landlord Compliance Strategy 2025-2028, which sets out the
strategic approach to compliance across the six key areas of compliance
relating to Council Housing assets (gas safety, electrical safety, fire safety, lift
safety, asbestos management and water safety) was approved by the
Communities and Housing Policy Board on 11th of March 2025. 
3.2 There are six landlord compliance policies in place to support the Housing
Landlord Compliance Strategy, each with a suite of key performance
indicators and detailed performance reporting arrangements which include a
bi-annual report to the Communities and Housing Policy Board.  Each of the
policies is reviewed on a regular basis and further policies will be created for
any new areas of compliance regulation that are introduced.   
4.       Housing Landlord Compliance Performance Report 
4.1 The Housing Landlord Compliance Performance Report covering the period
April 2025 – Mar 2026 is set out in Appendix 1 of this report. 
There are 26 key performance indicators covering the six compliance areas. 
22 indicators are showing greater than 99% compliance, demonstrating an
improved position on the year-end report for 2024/25. 3 performance
indicators are designated amber status indicating a compliance level between
85% and 98% and 1 performance indicator is designated as a red status,
indicating a compliance level lower than 85%. 
The compliance indicators at amber and red status have actions in place for
improvement. The indicators are: 
• Domestic properties with a satisfactory EICR within its due date as % of
total dwellings requiring an EICR (amber)
• Percentage of properties with automated doors, gates, and barriers where
Maintenance visits have been completed (amber)
• Number of safety occurrences - including any reported asbestos related
occurrence reporting (e.g., to the HSE or Regulator) during the reporting
period (amber)
• Re-inspections of common areas with Asbestos Containing Materials (red)

Page 3

PUBLIC
4.2      The key points to note for each area of compliance are as follows: 
• Gas Safety 
The Council are required to carry out annual gas safety inspections on all
10551 residential properties that have a gas supply. There were 11
properties where the gas service was not completed within the 12-month
timescale during the 12-month period from 1 Apr 2026 – 31 March 2026. 
These cases were due to administrative errors (8), hazards (1) and
environmental issues (2). All 11 are now complete and, where possible,
actions have been taken to prevent similar cases occurring. 
There has been an increase in the number of enforcement letters issued,
partly due to ongoing issues with Royal Mail deliveries. As a result, we
have reviewed our processes and are working to improve communication
with tenants through greater use of email and text messaging. This will
become more easily facilitated when the new housing management ICT
system is live. 
All communal heating systems with gas boilers have had their annual
safety checks completed within timescale. 
• Electrical Safety 
Performance remains strong, with six of the eight indicators rated green
and the remaining two operating at 95–96% compliance. 
Between 1 April 2025 and 23 March 2026, a total of 3,495 EICRs were
completed. This is higher than a standard annual cycle (30% of stock) due
to the impact of the pandemic in 2020, which pushed a significant volume
of testing into 2021. From 2026/27 onwards, the aim will be to carry out
approximately 2,400 EICRs each year. 
There are currently 50 tenanted properties with EICRs overdue. 15 of
these are in progress with appointments being arranged.  35 are being
monitored due to on-going issues; environmental issues and no access.
The compliance team are engaging with colleagues across housing
services and other service areas to support tenants to ensure the EICR
can be completed as quickly as possible. In addition to this there are 238
void properties without a valid EICR, 199 of which are scheduled for
demolition and therefore the EICR is not required. The remaining 39 are
being actioned as part of the void property works.

Page 4

PUBLIC
Follow on work classed as C1 (danger present) is always addressed
immediately to make safe. Follow on work classed as C2 (potentially
dangerous) is, in most cases, carried out at the same appointment as the
electrical check. 
Automated letter production for EICRs went live on 1st September 2025
and has streamlined the previously manual labour-intensive process. The
success of this will be monitored over the coming months. However,
issues with Royal Mail delivery times have impacted on the scheduling of
the works and we are currently investigating electronic alternatives such
as text and email. 
A programme of common area electrical checks commenced in November
2024 with 100% of the 1373 common areas completed by 31 March 2026. 
• Fire Safety 
All Fire Risk Assessments (FRAs) required for multi-storeys, sheltered
complexes, HMOs and common areas of all blocks are up to date. 
Ongoing review will continue with some requiring 6 monthly review and
others 12 monthly.  Actions identified from FRAs are followed up promptly
with repairs instructed where required.   
Along with the EICR programme, the rollout of the fire safety detection
interlinked alarms in domestic properties has been ongoing. Robust
processes have been introduced to ensure that detectors are checked
during the annual gas service and that expiry dates are updated to enable
future replacements to be programmed. Feedback is also provided from
surveyors carrying out stock condition surveys where missing or faulty
detectors are identified.   
There is a quarterly meeting with Scottish Fire and Rescue Service and
other Council teams to discuss fire safety.   
The first two Single Building Assessments (SBAs) which provide a
technical review of fire safety in multi storey blocks have been completed
with the remaining fourteen being scheduled and due for completion by the
end of 2026. The first two reports are currently being reviewed and a cross
departmental working group, led by Corporate Health & Safety, has been
established to monitor and implement any actions arising. 
The compliance team continue to deliver fire safety training to staff across
Housing Services.

Page 5

PUBLIC
• Lift Safety 
All lifts examinations and maintenance are fully up to date. The
compliance team have been pro-active in ensuring that access is ensured
for all regulatory lift examinations carried out by our appointed insurance
contractor. 
• Water Safety 
Statutory legislation requires Legionella Risk Assessments (LRAs) to be in
place with water safety management plans and monitoring in place for
those identified as high risk. This includes carrying out temperature checks
where communal water tanks or heating cylinders are present such as in
sheltered complexes and multi-storey buildings. 
There is a contract in place for water sampling and LRAs for multi storeys,
sheltered housing and non-domestic premises. Building Services carry out
the monthly, quarterly, six-monthly and annual monitoring of all sites as
prescribed within the guidance. 
There is also a requirement to carry out LRA’s within all domestic
properties. Current performance indicators show full compliance with water
safety management with LRAs for domestic properties currently in place
by archetype. The intention is to update these LRAs on an individual
property basis and preparations are progressing for a procurement
exercise to be undertaken this year. 
• Asbestos Safety  
Housing Services have contracts in place for asbestos surveying,
asbestos removal and analytical services within domestic properties.
There are currently two short term contracts, one for void properties and
general repairs and the other for capital investment external works. Longer
term contracts are in the process of being procured and a contract for
common area asbestos management will be procured on conclusion of the
review which is being undertaken as part of the Asbestos Management
Action Plan. 
The Asbestos Management Action Plan was submitted to the Scottish
Housing Regulator is being progressed with the assistance of consultancy
support to provide expertise and independent advice.

Page 6

PUBLIC
The Asbestos Management Policy was approved by the policy board on
28th October 2025 and a briefing session for policy board members was
held in February 2026. A gap analysis is underway to review asbestos
management working practices and training provisions and requirements. 
An asbestos management module will be developed in the new housing
management ICT system. 
5.0  2025/26 Key Actions Update 
The key actions identified in the October 2025 bi-annual report to board are
noted below with progress updated: 
Action Progress Update
The 2025/26 Scottish Housing Regulator engagement
plan notes that in October 2024 in our annual
assurance statement that we said were taking steps to
review and consolidate our tenant and resident safety
responsibilities. In addition to further updates on EICR
and fire detection compliance, the Regulator is seeking
further information and assurance about our asbestos
management processes and planned improvements.
Action plan for
asbestos submitted
and SHR kept
updated throughout
2025/26.
Ongoing review of policies, procedures and processes
including the identification of new policy requirements.
A Damp and Mould policy is being developed and will
be brought to Board in early 2026.
Draft policy
undergoing external
review.
Longer term contracts will be put in place for asbestos
surveys. The contract awards for both external and
internal surveys is targeted for Spring 2026.
Procurement in
progress
A contract will be put in place for domestic legionella
risk assessments, with contract award targeted for
April 2026.
Procurement in
progress
A contract will be put in place for common area
asbestos management following the conclusion of the
external review of asbestos management
arrangements described above.
Procurement in
progress 
6.0 2026/27 Key Actions 
• Servicing is part of Phase 1 of the Housing Innovations Project (HIP)
which will see a new housing management ICT system being introduced
and which will incorporate gas servicing and electrical testing. Training will
be required on the new system and transition plan for moving to the new
system. 
• Longer term contracts will be put in place for asbestos surveys including
common area asbestos management surveys.

Page 7

PUBLIC
• A contract will be put in place for domestic legionella risk assessments. 
• Ongoing monitoring and progression of actions within the Asbestos
Management Action Plan 
• Monitor outcomes of Single Building Assessments and implement any
further fire safety measures identified as responsibility of compliance team.
_________________________________________________________________
Implications of the Report 
1. Financial - Compliance costs are met from the HRA budget. 
2. HR & Organisational Development - None 
3. Community/Council Planning:
• Our Renfrewshire is safe - ensuring tenants have a safe place to live. To
manage risk to for staff, contractors or members of the public within
council housing properties. 
4. Legal - None 
5. Property/Assets - Ensuring assets are protected from risk.   
6. Information Technology - None 
7. Equality & Human Rights 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be reviewed
and monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health & Safety - The strategy and policies align with the Council’s Corporate
Health and Safety Policy. 
9. Procurement - None 
10. Risk - Failing to meet KPIs could put the Council at risk of failing to comply
with statutory duties for landlord compliance and could be reputationally
damaging. 
11. Privacy Impact - None 
12. Climate Risk - None 
13. Children’s Rights - None

Page 8

PUBLIC
14. COSLA Policy Position – None
___________________________________________________________________
List of Background Papers
Appendix A - Performance Monitoring Report - Housing Landlord Compliance,
April 2025-March 2026
___________________________________________________________________
Author:      Karen Sillars, Housing Asset & Investment Manager
Email: karen.sillars@renfrewshire.gov.uk