PUBLIC   
___________________________________________________________________     
To:   Communities and Housing Policy Board       
On:               19 May 2026    
___________________________________________________________________      
Report by:  Director of Environment, Housing and Infrastructure     
___________________________________________________________________     
Heading:   Service Update Report     
___________________________________________________________________     
1. Summary     
1.1 This report provides an overview of key service activities since the last Policy
Board report on 10 March 2026 and an update on the services and key
projects delivered during this period.     
1.2  Further information and details of service delivery can be found in a number of
other reports being presented to the Communities and Housing Policy Board
today. 
1.3 Specifically, the report requests that the Policy Board homologate the decision
of the Head of Housing Services, in consultation with the Convener, to accept
Scottish Government grant funding to support the delivery of housing led
regeneration programme and Rental Off The Shelf (ROTS).
___________________________________________________________________     
2.    Recommendations     
It is recommended that the Communities and Housing Policy Board:   
2.1 Note the contents of this report.   
2.2   Homologate the decision of the Head of Housing Services, in consultation with
the Convener, to accept Scottish Government grant funding totalling
£1,221,074.22 to support the delivery of housing led regeneration programme
open market purchases as set out in paragraph 3.2.4 of this report. 
___________________________________________________________________

Page 2

PUBLIC
Updates for Communities and Housing Policy Board     
3.   Housing Services     
3.1     Housing Innovation Project (HIP)   
3.1.1  Phase 1 of the project continues to progress, with an additional data migration
exercise now scheduled for May 2026, in advance of the second test cycle
which will take place during July 2026. On satisfactory completion of these
stages, it is anticipated Phase 1 of the project will go live during Q3 2026. 
3.1.2  Preparations for Phase 2 continue, with workshops underway and recruitment
of team members to the project team for this second phase of the project in
progress. 
3.2 Housing-Led Regeneration and Renewal   
3.2.1 Improvement works continue across the project area with ongoing dialogue
with owners in mixed tenure blocks to discuss further participation where
possible, including the option of buying back properties where this would allow
works to be progressed. The installation of triple glazed windows also
continues to progress well, with 351 Council homes within housing-led
regeneration and renewal areas now in receipt of their new windows.
Feedback to date has been very positive with tenants commenting on the
difference the windows have made to the properties both in terms of comfort
and aesthetics. 
3.2.2  The design work for Waverley Road retention blocks has been completed. The
tenant event that took place in March for the Waverley Road area was
received extremely well by those who attended. Officers were able to
showcase the designs for the external improvement of the blocks and the
surrounding common areas, including the new balconies and waste
management arrangements proposed. The programme for the delivery of
these works on site will be agreed once all statutory approvals are in place. 
3.2.3  Buy backs in advance of demolition works continues to progress well. 33 of
the 99 blocks approved for demolition have now either been demolished (23)
or are part of the tendering process (10) for progression over the summer
months. Further phased demolition will take place across the programme as
blocks become fully Council owned and vacant. 
3.2.4  The Board is asked to homologate the decision of the Head of Housing
Services, in consultation with the Convener of the Communities and Housing
Policy Board, to accept Scottish Government grant funding of £1,221,074.22,
details of each project amount are provided below: 
• Springbank Ph1 - £270,651.12 
• Springbank Ph2 - £32,500 
• Broomlands - £247,591.60
• Regeneration Open Market purchases - £294,084.50
• Rental Off The Shelf - £376,247

Page 3

PUBLIC
3.3  Newbuild Update 
Following the Board’s approval on 21 May 2024 to accept Scottish
Government grant funding of £10,022,083 and £9,630,795 for the housing
regeneration projects at Howwood Road and Gallowhill respectively grant
drawdown for the 2025/26 newbuild programme amounted to £4,597,641.68
at Gallowhill and £2,333,668.78 at Howwood Road. 
3.4  Service Improvement:  Renfrewshire Council Housing Policy in relation
to Domestic Abuse – Consultation 
3.4.1  Following enactment of the Housing (Scotland) Act 2025, there is now a legal
requirement for social landlords to develop and implement a policy that sets
out how they will support tenants at risk of homelessness due to domestic
abuse. 
3.4.2 As such the Service has been developing a draft Housing Policy in relation to
Domestic Abuse. This draft policy has been produced through close working
with various services across the council, partners, external organisations and
other groups who support victims and survivors of domestic abuse. 
3.4.3 The service will shortly undertake a consultative exercise to gauge final views
on the draft policy. This consultation will run for between four and six weeks,
where views on the draft policy will be sought from partners, interested
agencies, tenants and other stakeholders. 
3.4.4 Following conclusion of consultation, a finalised Housing Policy in relation to
Domestic Abuse will be presented to the policy board for approval. 
3.5 Housing Asset and Investment   
Stock Condition Survey Update 
3.5.1  As previously reported to the Board, a programme of stock condition surveys
is underway to meet the Scottish Housing Regulator’s requirements for review
every five years and to validate our Scottish Housing Quality Standard
(SHQS) compliance rates. Whilst the surveys completed to date have had little
impact on overall SHQS compliance rates, the overall quality and accuracy of
data held on the condition of individual blocks and properties has been
improved. This helps to define future investment requirements and informs our
business plan. 
Year 1 Year 2 Total
External Surveys  4086 2976 7062
Internal Surveys  2101 1741 3842
EPCs (for properties with no valid EPC
or where due within 2 years) 
1384 1139 2523

Page 4

PUBLIC
3.5.2  The data from Year 2 surveys has been interfaced into our asset management
database system Apex and analysed. For external building condition, the main
areas of change to data held in Apex are in relation to the condition of
communal doors, door entry systems and communal windows. This is a similar
pattern to Year 1. Internally, some changes to data for kitchens, bathrooms,
heating, smoke and heat detection. Any identification of specific repairs from
the surveys, including the identification of mould, are followed up by our
repairs team. 
3.5.3  Over the first two years, access for external surveys is over 90%, access rates
for internal surveys remain lower than expected at around 50% (target: 67%),
despite tenant notifications and follow-up calling cards. Surveyors attempt
access three times before marking a property as ‘no access’. Optional Years 4
and 5 of the contracts,  will allow revisits to be made for these properties. 
3.5.4  The stock condition survey is now in Year 3 of a 5-year programme, focusing
on our multi storey and sheltered housing blocks, plus homes in Johnstone
and the villages. The surveys will be arranged in phases from April 2026 to
March 2027 and tenants will be lettered a few weeks prior to each phase in
their area, to let them know that our surveyors will be requiring access.   
When access is unsuccessful, cards are left with contractor contact details for
tenants to make alternative arrangements for access. 
HRA Roads, Walkways and Footpaths 
3.5.5  There is a significant network of unadopted roads, walkways and footpaths
held within the Housing Revenue Account (HRA) across Renfrewshire which is
the responsibility of the housing service in terms of repairs and maintenance.
This comprises approximately to 5km of carriageway, 36km of footway, and 27
km of footpath. 
3.5.6 Historically, enquiries and complaints relating to roads, walkways and
footpaths have been complex for customers, elected members and internal
service teams, as the service area responsible for maintenance depends on
ownership and adoption status. This has resulted in delays, inconsistent
responses, and variation in approaches to inspection, maintenance, and
repair. 
3.5.7   To improve the service, arrangements have now been made to have all roads
inspections and repairs carried out by the Roads team, with Housing Services
retaining responsibility for managing the budget and prioritising planned
maintenance.

Page 5

PUBLIC
3.5.8 The key advantages of this are: 
- Dedicated officer with expertise in roads, walkways and footpath inspection
and maintenance.
- Improved customer services through the streamlining of the management
of enquiries and complaints in relation to HRA roads, walkways and
footpaths.
- Earlier identification of safety-critical defects and faster progression of
urgent repairs.
- Improved condition data to inform the Housing Business Plan and future
investment decisions. 
- Delivering the action within the Housing Asset Management Plan; to
capture the extent of unadopted HRA assets on GIS and carry out a
condition survey to provide a baseline for adding to APEX.
- Release of capacity within the Housing Repairs and Maintenance team to
focus on other core housing repair and maintenance services. 
3.5.9  The new arrangements will be subject to ongoing monitoring and review to
ensure they continue to deliver improved performance, value for money, and
better customer outcomes. 
4.    Public Protection         
4.1 Environmental Health   
4.1.1 To support the delivery of Environmental Health Services, and in the current
national challenges of recruiting Environmental Health Officers, the Service
has been looking toward ‘growing our own’ Officers. As part of this, a Trainee
Technical Officer (Food Law) has successfully completed their scheme of
practical training and passed their professional exams. The Officer is now
working as a food law enforcement Officer, and the Service is looking to
employ a further trainee to continue the training and development of staff to
work in this specialised field. 
4.1.2 The Environmental Task Force, which sat within the Team Up to Clean Up
service has, from 1 April, moved into the Environmental Health Team. This
restructure forms part of the wider Public Protection Review and as the
Officers within the Task Force already work very closely with Environmental
Health staff, significant benefits will be realised by bringing these functions
under one Service. The Task Force will continue to have a focus on fly-tipping,
including exploring how the use of emerging technologies can assist with the
prevention and detection of such crime. Officers will also be involved in
ensuring commercial premises comply with their statutory duties in respect of
waste production, segregation for recycling, secure storage, and disposal.
Officers will be provided with training to support them in this role.

Page 6

PUBLIC
4.2 Community Safety   
4.2.1 Following continued Greater Resilience in Partnership (GRIP) meetings with
Police Scotland and partner agencies, a month-long violence prevention and
awareness campaign has been delivered across Renfrewshire throughout
April 2026. The campaign aimed to highlight the dangers and long-term
consequences of violence and to signpost young people, parents, carers and
teachers to appropriate support and educational resources. 
4.2.2   The initiative was delivered in partnership with Fearless, the youth service of
Crimestoppers, and No Knives, Better Lives (NKBL). Activity took place online,
within secondary schools and at community events. As part of this work,
awareness activity took place at the St Mirren v Aberdeen match on 4 April
2026, supported by NKBL messaging and Police Scotland Youth Volunteers. 
4.2.3  Information and resources is also being shared with parents, carers and
teachers across Renfrewshire schools to encourage early intervention and
preventative conversations. 
4.2.4  Renfrewshire Council’s Warden Service supported the campaign through local
engagement, visibility within communities and by reinforcing key messages
during routine patrols and interactions with young people and families. 
__________________________________________________________________   
Implications of the Report         
1. Financial – Any financial elements referenced in this report will be progressed
through the Council’s financial & budget planning process.           
2. HR & Organisational Development – None.         
3. Community/Council Planning – The report details a range of activities which
reflect local community and council planning themes.         
4. Legal – None.           
5. Property/Assets – None.         
6. Information Technology – None.         
7. Equality & Human Rights – The recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights.  No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following implementation,
the actual impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be published
on the Council’s website.      
8. Health & Safety – None.         
9. Procurement – None.

Page 7

PUBLIC     
10. Risk – None.         
11. Privacy Impact – None.         
12. Climate Risk – there are a range of actions and activities throughout the
Service Update Report which support the Council’s Plan for Net Zero.         
13. Children’s Rights – None.         
14. Cosla Policy Position – None.   
__________________________________________________________________   
List of Background Papers:  None.     
___________________________________________________________________         
Author: Gordon McNeil, Director of Environment, Housing & Infrastructure     
Email: Gordon.mcneil@renfrewshire.gov.uk