4 - Actions Monitoring Report - Dargavel Primary School + Appendices

Renfrewshire Council · 18 March 2024
Back to Audit, Risk and Scrutiny Board — 18 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To:  Audit, Risk and Scrutiny Board
On:  18th March 2024
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Actions Monitoring Report - Dargavel Primary School Independent
Review and Accounts Commission Section 102 Report for School
Accommodation for Dargavel Village
___________________________________________________________________
1. Summary 
1.1 Following the findings of an independent review into the circumstances
of the errors in planning and delivery of primary school provision in the
Dargavel area, a SMART action plan was developed detailing the
Council’s response with a commitment that updates on this plan would
be provided to Board meetings going forward. 
1.2 Detailed in Appendix 1 to this report, is an update on the actions from
the independent review.   
1.3 At a meeting on 11th January 2024, the Accounts Commission was
presented with a statutory S.102 report, as circulated to Councillors on
5th January 2024, by the Controller of Audit on School Accommodation
for Dargavel. In the report, the Commission has set out their findings,
alongside several issues on which they require further information.   
1.4 At the Council’s Meeting of 29 February 2024, the Council considered
the Account Commission’s report and agreed a number of actions in
response to that report.

Page 2

Council further agreed that these actions would be incorporated into the
independent review response monitoring arrangements reported to this
Board. Appendix 2 sets out the Council’s response and planned actions. 
1.5 At the Council’s Meeting of 29 February 2024, the Council considered a
report on the outcome of the review of corporate governance
arrangements by the Cross Party Working Group and agreed a number
of actions set out in that report. Council further agreed that those actions
would be incorporated into the independent review response monitoring
arrangements reported to this Board. Appendix 3 sets out the planned
actions. 
2. Recommendations
2.1 Note and consider the update provided in Appendix 1 in relation to the
Council’s response actions to the independent review. 
2.2 Note and consider the plan provided in Appendix 2 in relation to the
Council’s response actions to the s.102 report.
2.3 Note and consider the plan provided in Appendix 3 in relation to the
report by the Council’s Cross Party Working Group. 
___________________________________________________________________
Implications of the Report
1. Financial – whilst there will be significant capital and revenue
implications for the Council in resolving the Dargavel issue, there are no
financial implications for the Council as a result of this update report. 
2. HR & Organisational Development – the report outlines a leadership
development programme with a focus on key issues raised in the
independent review around governance, risk management, corporate
working and culture. 
3. Community/Council Planning – the report outlines ongoing action
being taken to develop an engagement and ongoing communication
process with affected communities.  
4. Legal – none

Page 3

5. Property/Assets – none 
6. Information Technology – n/a 
7. Equality & Human Rights - The Recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified arising
from the recommendations contained in the report as it is for noting only.  
If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.  
8. Health & Safety – n/a
9. Procurement – n/a
10. Risk – the report outlines the action being taken in relation to risk
management. 
11. Privacy Impact – n/a 
12. Cosla Policy Position – n/a
13. Climate Risk – n/a 
___________________________________________________________________ 
Author:           Alan Russell, Chief Executive

Page 4

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Bowles Report Recommendation 1
Build a more robust model of primary school need for Dargavel - the Council should continue to refine its pupil forecast model for Dargavel. 
Response Objectives 
Deliver robust projection modelling for Dargavel and PMHS which: - 
• considers live information arising from NHS, pupil & ELC registrations, the pace of development to date, certainty over development size and likely
pace of future build out rate, 
• utilises external data analytics and projection expertise to augment and enhance the Council’s in-house forecasting approach to ensure modelling is
robust, underpinned by external challenge and specialist input reflecting the complexity and significant portion of Dargavel that has yet to be
developed out over a circa 10 year period, 
• provides modelling output which considers potential future upper scenarios reflecting the high yield factors reflected in the 2023/24 P1 intake to
inform immediate decisions on scale of capacity to be delivered as well as planning for potential additional interventions at a future time, 
• delivers modelling output which provides a long-term view beyond the anticipated completion timeline for Dargavel to ensure the long term impact of
Dargavel is modelled and understood, 
• provides modelling output over the long term which indicates both the scale, timing and shape of an anticipated peak in demand that will accompany
a development of this scale and nature. This will provide visibility of the anticipated short-lived peak in demand and long term settled demand to
ensure this is appropriately reflected in estate/capacity decisions and in particular to mitigate against delivery of excessive long term / permanent
increase in capacity that would result in excess unused surplus capacity over the long term.
• Provides modelling that can be tested and revised as necessary as new key data becomes available such as P1 and S1 registrations, actual scale and pace of the
development and any new developments, which will continue to inform decisions on any future estate interventions if required.

Page 5

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Complete Council modelling through to the anticipated end
date for the housing development (2033/34) based on
assumed 4,300 units and available live data.  
October
2022
Director of
Children’s
Services
Complete Completed October 2022
Engage and appoint Edge Analytics to deliver enhanced
modelling approach for both Dargavel primary
requirements as well as PMHS out to 2033/34 and updated
live datasets. 
February 
2023
Director of
Children’s
Services
Complete Completed February 2023 including additional
upper forecast scenarios for Dargavel non-
denominational requirements to support
management of risk associated with long term
yield remaining at similar level to 2023/24.
Informed reports to Education and Children’s
Services Board in March and May 2023  
Extend Edge engagement to deliver an enhanced model
projecting out to 2038 to provide longer term forecast to
assess the full impact on the secondary sector and allow
identification of likely timing and scale of peak demand
encapsulating any relevant updates to live datasets. 
September
2023
Director of
Children’s
Services
Complete Modelling completed which has identified an
anticipated peak period in both primary and
secondary sectors and will be reported to
Education and Children’s Services Board in
November 2023. 
Provide update to November Education & Children’s Service
Policy Board. 
November
2023
Director of
Children’s
Services 
Complete  Two update reports were taken to the November
ECSPB:
1. Learning Estate
2. Dargavel Housing Development – Impact
on Denominational Education Provision
Link 
Update Edge Analytics modelling for newly released
national Census data and expand across the whole school
estate and establish modelling dashboard to support ease
of updating and rapid re-assessment of revised projection
that will be utilised on an ongoing basis over future years,
January
2023
Director of
Children’s
Services
Ongoing  The Edge Analytics modelling for newly released
national census data was completed last year.  A
modelling dashboard was also designed last year
with further discussions to take place on how this
is used to inform the wider learning estate.

Page 6

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
both for Dargavel / PMHS but also as part of the strategic
Learning Estate programme. 
Edge have been commissioned to expand the
model to include the whole estate and we are
expecting a data output in 6-8 weeks.  A schedule
has been developed which outlines re-
assessment and monitoring timescales.  
Bowles Report Recommendation 2 
Use of Bishopton Primary - in its future plans the Council should reconsider how surplus capacity at Bishopton can be used effectively. 
Response Objectives 
Consider and assess how existing capacity within Bishopton Primary School may be best utilised to support the Dargavel catchment over the immediate term
and potentially over the longer term, taking into consideration the uncertainty and risk over the long-term demand levels that will ultimately emerge for
primary education from Dargavel as well as the expectation of a temporary peak period of demand. 
Provide a report to Education and Children’s Services Board setting out a clear overview as to how Bishopton PS capacity will be utilised to support temporarily
over the short term period and how it may be considered amongst other options for use to support Dargavel in the longer term (noting that any such longer
term use will be subject to detailed consideration and decision at an appropriate point in future years).  
Complete assessment of anticipated P1 intake from
Dargavel catchment and assess against revised DPS capacity
availability, establish planned P1 intake capacity cap and
anticipated P1 intake requiring accommodation at
Bishopton Primary School. 
August
2023
Director of
Children’s
Services
Complete Planned use of Bishopton Primary School along
with planned capped entry levels to Dargavel
Primary School reported an approved at
Education and Children’s Services Policy Board in
August 2023. There will be a requirement to
annually monitor anticipated and actual P1
intakes carefully to assess adequacy of short term
capacity provision across both Dargavel and
Bishopton Primary Schools to meet demand
pending the second primary school in Dargavel
coming on stream.

Page 7

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Complete an exercise to assess the timing, scale and range
of potential demand level scenarios, in particular
understanding the scale and timing of the peak demand and
likely settled long term demand. This information will be
used to inform the assessment of how Bishopton Primary
School could, if required, be potentially be utilised as an
option in the longer term. 
January
2024
Director of
Children’s
Services 
Complete  Completion of the updated work with Edge
Analytics has provided a view of the likely timing
and length of the peak demand period – with
peak primary demand being forecast in 2033/34
which will fall over the second half of the 2030s
to a more settled level. Further work is being
progressed to update this information for the
recently released 2023 census information and
November registration data to inform an overall
assessment. 
Complete financial analysis to understand the potential
financial context of utilising Bishopton Primary School
Capacity 
May
2023
Director of
Finance and
Resources
Complete Bishopton PS is a predominantly 1960s
construction and is more than 60 years old. This
building will, along with the whole school estate,
undergo an updated condition survey over
coming months. Notwithstanding, given the
underlying age of the building it will inevitably
have a limited remaining lifespan before being
considered for replacement. 
Existing surplus capacity if used permanently to
reduce the required size of a second Dargavel
primary school, will require to be replaced as part
of a renewal programme. The determination of
the timing of that will be subject to work
progressed as part of the strategic learning estate
programme. 
Consequently, it has been assessed that any
financial advantage from utilising Bishopton PS

Page 8

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
will be restricted to a temporary time value of
money benefit and consequently will be relatively
limited. 
In addition, there is also a risk that utilising
Bishopton PS permanently removes its availability
to provide supporting capacity to manage both a
temporary peak that may arise from upper end
educational demand scenarios and longer term
upper end demand. There could be the risk that
in such circumstances if Bishopton capacity was
no longer available this would lead to higher
overall costs over the longer term for the Council. 
The financial considerations and risks will be
incorporated into the overall assessment
scheduled to be reported as part of the Education
& Children’s Services Board report in January. 
Set out overview in a report to the Education and Children’s
Services Policy Board in respect to the potential long-term
utilisation of Bishopton Primary School which will be subject
to detailed consideration at an appropriate point in future
years as actual long term demand trends increasingly
emerge.
January
2024
Director of
Children’s
Services
Complete  Work to allow appropriate recommendation to
be made is progressing in line with plans and
scheduled to be reported to Board in January
2024.  A paper was presented to Board in January
2024

Page 9

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Bowles Report Recommendation 3 
As the Council progresses its plans to issue supplementary guidance on developer contributions for education it should seek to learn from other Councils in Scotland. 
A development the size of Dargavel is exceptional and would need its own modelling techniques. However, for smaller developments the Council should create an evidence base to calculate specific yield
factors derived from recent developments in Renfrewshire. Such robust data will ease future negotiations.
Undertake a desk top review of other local authorities
across Scotland and identify key best practice councils to
engage. 
June 2023 Head of
Economy and
Development
Complete 
Complete detailed engagement with identified best practice
councils arising from desk top research
Summer
2023
Head of
Economy and
Development
Complete Detailed engagement completed with Fife, Falkirk
and West Lothian councils.
Complete data analysis exercise of a range of datasets of
mixed historic sites across Renfrewshire to provide
empirical evidence to support actual pupil yields to inform
establishment of appropriate yield factors to be used in
future contribution policy.
• Refresh % capacity of all schools (vs school rolls)
• Sample research of Pupil Product Ratio (PPR) for developed housing
sites (< 10 units) [min 10 site sample]
• Sample research of PPR for developed housing sites (> 100 units)[min
10 site sample]
• Sample research of PPR for established / mature housing
development to provide longer term perspective (eg. 15 years old) (>
100 units)[min 4 site sample]
• Identify individual schools where pupil capacity is above notional
threshold (85%) 
• Identify all known undeveloped housing sites in individual school
catchments
• [Subset of 5] identify all housing sites with current "live" planning
application
October
2023 
Head of
Economy and
Development
Complete Work on this is now complete and will feed into
new draft planning guidance to be presented to
March 2024 PCC Board.

Page 10

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
• Identify schools where it is anticipated intervention would be required
to increase capacity based on potential future housing to be delivered
over next 10 years to inform likely future developer discussions.
Incorporate into the development of the draft contributions
policy targeted to be presented to the Planning and Climate
Change Policy Board in January 2024. 
January
2024
March 2024
Head of
Economy and
Development
Complete Work on this is now complete and will feed into
new draft planning guidance to be presented to
March 2024 PCC Board. 
Bowles Report Recommendation 4 
Council needs to work co-operatively with BAE. Unless the Council and BAE can work together to resolve the current problems, BAE may face accusations, whether founded or not and regardless of
Council incompetence, that it has increased its profits at the expense of Council taxpayers. 
Response Objectives 
Secure legal ownership of suitable land to facilitate delivery of a second school within Dargavel Village as well as additional land next to existing school site to
provide increased flexibility to meet potential future extension of the school and or establishment of greater outdoor space. 
Secure legal commitment from BAE to provide land remediation and associated infrastructure requirements as part of legal agreement at nil cost to the
Council. 
Secure as part of the legal agreement certainty on consented planning numbers and any associated adjustments to s.75 agreement to reflect revised
agreement. 
Secure with BAE agreement on Heads of Terms for allow for
mutual governance approval from each organisation to
inform detailed legal agreement drafting and final sign off 
As soon as
possible
was
targeted. 
Chief
Executive
Complete This was completed and approved by ILE Board
end of August
Secure completed and signed legal missives to deliver in full
the objectives outlined above to provide certainty and
August
2023
Chief
Executive
Complete Legal missives concluded mid-September

Page 11

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
timing of availability of remediated and infrastructure
proofed land to support wider school delivery planning and
consultation arrangements that will be progressed by the
Council team.   
Proposed revisions to S.75 negotiated with BAE Systems
were approved by ILE. Revised S.75 signed off by both the
Council and BAE Systems to legally conclude matters. 
August
2023
Head of
Economy &
Development 
Complete Approved by planning and Climate Change Board
end of August
Bowles Report Recommendation 5 
Corporate working and organisational culture - although I understand that the Council has sought to improve and strengthen corporate working in recent years, the evidence would suggest there is a
long way to go; simply establishing corporate working groups is insufficient if staff are in a mindset of ‘not my problem’. 
The failure of management oversight, if symptomatic of the Council as a whole, would be deeply disturbing. The Council needs to consider a significant change programme, not just on the of issue of
corporate working and personal responsibility, but also its organisational culture and values. It needs plans to build a stronger organisation where constructive challenge is welcomed and there is a
clarity of what is expected of all of those in a leadership role. 
Response Objectives 
Provide assurance that established programme governance framework and operations of governance for other major capital investment programmes and
specifically that the Bowles findings on the historic failings on the handling of Dargavel by officers are not representative of the Council’s current culture and
approach to the management and delivery of major programmes. 
The Council is committed to living its values as a learning and collaborative organisation and post COVID was already in the process of re-establishing an
Leadership Development programme for senior leadership teams and managers across the Council in recognition that this required to be reinvigorated post
COVID and that there has been significant turnover in management and senior positions over the past three years and this would support growing and
maturing the current culture and collaborative connections across the organisation. 
In response to the Bowles recommendations, the objective is to ensure the new Leadership Development programme is appropriately cognisant and reflective
of the key learning points from the Bowles report and takes the opportunity to ensure its coverage seeks to re-enforce the development of skills related to
governance, risk management, commercial risk, corporate working and culture etc and effectively utilises failures referenced in the Bowles report as key

Page 12

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
examples for learning throughout the programme. Collective reflection and learning of such significant failures – albeit historical – is recognised as an
important element of building an effective future culture and ways of working across the organisation. 
Undertake a health check assessment on major capital
programmes to provide reassurance in respect to all aspects
of governance, control, reporting and management of
programmes.
October
2023
Chief
Executive
supported by
CMT 
Complete  City Deal and Infrastructure Health Check report
was submitted to CMT on 21 November 2023.
Put in place arrangements to deliver a comprehensive
Leadership Development Programme (circa 12 months +
programme) for chief officers and senior managers which
amongst other things will cover and key areas referenced in
the Bowles report in respect to governance, accountability,
risk management, collaborative working, member officer
relations etc. 
Commence
programme
by
September
2023
Director of
Finance &
Resources
and Head of
HR & OD 
Contract engagement in place and resources
secured from SOLACE Enterprises to support co-
designed and co-delivered programme.  
Initial Chief Officer programme launch event
occurred on 3rd October with focusing on
personal resilience. 
The programme has delivered sessions focussed
on: 
• Effective Communications and Elected
Member Relations
• Programme Management, Leading and
Navigating Strategic Change
• Risk Management and Governance
• Transformational Leadership
• Delivering Corporate/Team Values and
Vision  
This first leadership development programme has
now been concluded with an evaluation process
underway.   Attendance was good throughout the
programme and for any officers that were unable

Page 13

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
to attend parts of the programme, they will
attend these specific modules during the next
cohort grouping to ensure completion of the full
programme. 
The next 2 Cohorts will be run from April to
around September and with up to 60 places
available for our next tier of management.  There
will be some revisions to content and emphasis
based on feedback from the initial sessions,
however the key themes of the programme will
remain unchanged. 
Design and undertake an evaluation process of the
Leadership Development Programme for Chief Officer
cohort to inform required changes / adjustments to
programme delivery for next management cohort. 
March 2024  Head of HR
and OD 
Initial feedback was requested as part of the final
workshop of this first programme.  An evaluation
request, designed in partnership with SOLACE,
will be sent out to each of the participants asking
if their knowledge has increased, if they feel
more confident and informed and what changes,
if any, would participants suggest for the next
cohort.   The formal evaluation will be sent out
w/c 20/02/24 and will have a 2-week completion
window.  There will a further evaluation on what
changes have been made as a result of the
programme will also be carried out 6 months
each cohort completion.

Page 14

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Bowles Report Recommendation 6 
Risk management 
From documents I have seen the Council was unaware of the scale of risk it was taking in the calculation of pupil numbers.  The identified risk in Council documents related to providing the school on
time, not that the size of the school may prove to be inadequate.  The failure to identify that risk has had two consequences; first the Council has been slow to react to the increase in pupil numbers and
second the Council did not negotiate with BAE with that risk in mind. 
The Council needs to review how it both identifies risk and manages it. 
Response Objectives 
Progress actions to provide reassurance in relation to the Council’s current risk management approach, in particular how this is approached, deployed and
managed as part of major projects as well as considering and assessing the seniority / appropriateness of officer involvement and related skills across officers
involved in the process. 
A review of risk profiles across all service departments to
ensure visibility of all risks and confirmation of where
certain risks are being monitored if outwith the standard
Risk Reports to the Audit, Risk and Scrutiny Board (i.e.,
Health and Safety Planning Groups, Service Improvement
Plans etc) 
October
2023
Director of
Finance and
Resources
Complete Risk report submitted to Audit, Risk & Scrutiny
Board as planned on 6 November 2023.
A review of the ‘service risk representative’ roles in each
service department to ensure the representatives who sit
on the Corporate Risk Management Group are sufficiently
involved in risk matters within the service, to feed this into
the Corporate Risk Management Group and that they also
have authority within the service to provide challenge as a
‘critical friend.’ 
October
2023
Director of
Finance and
Resources
Complete Action completed.  CMT agreed (10 October),
that each Director will nominate a Head of
Service and one other colleague to support the
Head of Service in the role going forward.

Page 15

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Delivery of a project risk management workshop specific to
the planned new primary school in Dargavel (complete) 
August
2023
Director of
Finance and
Resources 
Complete Workshop delivered covering nature of project
risks, risk changes over lifecycle of the project;
reminder of Council PM framework and PMU
support; key issues re good governance. 
Delivery of project risk management training with all PMU
colleagues (in a train the trainer format) so colleagues are
delivering this as part of project kick-offs to support a more
risk focussed culture in the organisation. 
September
2023
Director of
Finance and
Resources
Complete This was completed on 12/10/2023.  PMU staff
received a ‘train the trainer’ session to enable
them to cover running risk awareness sessions at
project kick-offs to support a more risk focussed
culture in the organisation. 
Undertaking a ‘health check’ of project management
arrangements across the council to ensure governance,
management, reporting and risk management is
appropriate to the scale of the project. 
November
2023
Director of
Finance and
Resources
Complete Compliance review of all PMU supported projects
complete.  All projects demonstrated a
satisfactory level of risk governance and
management.
An update to the risk management course on iLearn and
consideration of whether it should be a mandatory course. 
December
2023 
Director of
Finance and
Resources
Complete The course if now developed and ready to be
launched to relevant staff on iLearn.
In addition, face to face training of a new “Who’s
risk is it anyway” half day course is also being
delivered in February and May. 
Embed and deliver risk management training into the new
leadership development programme that is currently under
development, particularly in relation to commercial risk 
December
2023 
Director of
Finance and
Resources
Complete Session delivered 12 December.
Reviewing governance documents to ensure delegations in
relation to liability caps are clear and unambiguous. 
December
2023
Director of
Finance and
Resources 
Complete Consultation with Head of Corporate Governance
concluded that governance documents do not
require amendment, but rather, more training
would be required on what was expected within

Page 16

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
existing delegations.  The training was delivered
to CMT on 28 November 2023. Governance
refresher training sessions have been delivered to
every department senior management team in
January.
Deliver a targeted risk management development day for
Chief Officers:-  
• Project risk management (and risk simulation exercise) 
• Risk horizon scanning and sustainability (the Global Risk
Report) 
• Liability caps and their implications 
December
2023
Director of
Finance and
Resources
Complete The training session has been prepared and was
delivered to CMT on 28 November 2023.
It is recognised that Dargavel Village has a significant
amount of housing development yet to be delivered (circa
2000 housing units over a 10 year period) and therefore
many of the associated risk that existed at the beginning of
the development continue to exist today albeit there is live
data to inform future projections from the first circa 2,300
units that have been delivered. Manage ongoing education
demand risk relating to Dargavel through:
The Council therefore continues to face risk and uncertainty
in relation to accurately projecting the scale and timing of
future education demand which will continue to have
inherent uncertainty and risk. In recognition of this the
Council will continue to progress the following actions to
manage and mitigate this risk:-     
Director of
Children’s
Services

Page 17

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update 
Securing robust long term demand projections which
provide both a core projection, potential upper scenario
and a long term view of the potential scale and timing of
short term peak demand to inform decisions on capacity
provision. 
Identify now a range of flexible options that are and will
remain available to in future years to deliver, if required
additional capacity (both temporary capacity and
permanent long term capacity) to ensure the Council can be
reassured  of being able to respond appropriately to the
potential for  upper end demand scenarios and or
temporary demand peaks to emerge. 
Establish process and arrangements to support and provide
detailed monitoring and updates to projections for updates
to actual data sets to facilitate a continual re-assessment of
longer term trend and likely requirements / decision point
required in relation to deployment of potential additional
interventions. 
September
2023 
January
2024 
January
2024 
Complete 
Complete 
Complete 
Further updates will be completed in this respect
for updated datasets available from November
registration data and recently released NRS
Census data 
Based on data and a range of scenarios, flexible
additional capacity options have been outlined
and shared with relevant boards.   
A schedule is in place with timelines for detailed
monitoring and updates to projections and actual
data.  This will ensure continual re-assessment of
long term trends and likely requirements /
decision points required.

Page 18

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Bowles Report Recommendation 7 
Whilst protecting the integrity of the planning process, the Council needs to ensure the appropriate involvement of members in such developments. 
Additional Council Motion
Council agrees that in light of the Independent External Review of Dargavel that there is a requirement to convene a cross party body to discuss and review existing governance arrangements of
Renfrewshire Council. 
Response Objectives 
Assess the extent to which major investment projects have provided sufficient engagement with elected members through both formal governance routes as
well as through briefing sessions, engagement sessions, group presentations, site tours etc. Identify any adjustments or improvements required moving
forward. 
Provide officer support to a cross party group to of elected members to agree the remit and progress a discussion and review of the Council’s formal
governance arrangements in line with the motion approved. 
Carry out an assessment of the Audit Risk and Scrutiny Board against CIPFA’s published good practice guide for audit committees. 
Undertake a health check assessment on major capital
programmes to provide reassurance in respect to extent to
which elected member involvement has been appropriately
secured through formal governance reporting as well as via
other appropriate informal engagement routes
October
2023
Chief
Executive
supported by
CMT 
Complete City Deal and Infrastructure Health Check report
was submitted to CMT on 21 November 2023.
Other programmes to be reported to CMT
through regular scheduled portfolio update
sessions.
Support Council Leader and other nominated elected
members to determine a review remit, progress the review
and develop suitable recommendations. 
March 2024  Head of
Corporate
Governance 
The Cross Party Working Group has been
established and met five times. A report to
Council will be submitted to the Council Meeting
on 29 February 2024 setting out the findings of
the review.

Page 19

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Carry out an assessment of the Audit Risk and Scrutiny
Board against CIPFA’s published good practice guide for
audit committees and identify any recommendations for
change in remit or operational arrangements. 
December
2023
Director of
Finance and
Resources 
An initial assessment against the CIPFA guidance
has been undertaken by the Chief Auditor, which
has been discussed with members of the Board at
a full day reflection session on 19 January. The
output from this session will be further discussed
with the Board members, with a final report to be
formally presented to the Board on 18 March,
which will include recommendations for Council
to consider. 
Bowles Report Recommendation 8 
Public confidence 
These recent events and the matters described in this report will dent public confidence in the Council.  The Council should work in an open and transparent manner in the resolution of these issues and
particularly with the residents of Dargavel, who have legitimate concerns about the implications for their children during both their primary and secondary education. 
Response Objectives 
The key aim has been to provide straightforward messaging and up to date sitreps to ensure publics (and council representatives) have the most up-to-date
position and the complexity of the issue is explained in a simple and honest way and that parental/carer concerns in respect to the school and educational
environment are able to be appropriately discussed through structured engagement arrangements with the parent councils with appropriate agreed actions
taken forward. 
The strategy has been designed to: 
- Improve the flow and regularity of information to parents and carers and the wider Dargavel community, so they are first to hear about decisions
impacting their community. 
- Ensure parents and carers have access to all projection data available to the council.

Page 20

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
- Introduce direct communication channels with Dargavel residents, enabling all sections of the community to engage on matters that are important to
them and making sure the latest information is accessible and easy to find. 
- Provide residents with a feedback loop to enable them to ask questions of the council in relation to the development and have questions answered
quickly. 
- Include the community in formal planning and design of a new primary school and high school extension. 
It is recognised that effective communication and engagement is important to building a new relationship between the Council and the Dargavel community,
but ultimately it will take the delivery of the solution and investment in long term engagement to reduce local anxiety and fully rebuild trust and confidence in
the Council. 
Target
Completion
Date
Responsible
Officer
RAG Status Update
Develop communication plan to drive tactical engagement,
ensuring the Dargavel community and specifically parents
and carers kept updated on progress and the decisions
being made by Council Boards. 
November
2022 
Head of
Marketing
and Comms
Complete The strategy has directed media and stakeholder
engagement in relation to council decisions
pertaining to Dargavel, the initial announcement
and short-term mitigation arrangements, and the
publication of the Independent external review
by David Bowles. The specific activities delivered
include: 
• Arranging and hosting two parent and carer
meetings, attended by council officers and
more than 220 parents or carers.
• Attending several parent council meetings
with all primary schools and PMHS to support
direct engagement, discussion on key
activities, immediate estate decisions in
respect to deployment of modular

Page 21

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
classrooms and post occupancy adjustments
at Dargavel Primary, sharing and discussion of
revised projection data and modelling, key
council decision points, independent review
outcomes.
• Attending several community meetings from
community council, Community Liaison
Group as well as supporting coordination and
delivery of wider community representative
round table session to maintain ongoing
engagement, sharing of information and data
sharing.
• Updating parents and carers at Dargavel
Primary on progress and all reports to Council
Boards and decision making in relation to
immediate solutions to address capacity
issues at Dargavel/
• Updating Bishopton Community Council on
progress above.
• Responding to media enquiries, requests for
interview and ensuring the media were
proactively updated on progress. 
• Ensuring the wider area stakeholders were
kept up to date on progress – this includes
community representatives, wider Parent
Council groups and local and national
politicians. 
• Maintaining updated information on the
council website

Page 22

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
• Delivered a creative partnership with
Glasgow School of Art and Dargavel Primary
School to support pupils design the interiors
of the new modular classroom block.  
Deliver a revised comms and engagement strategy to
coincide with the return to school period along with timing
of key milestone points in relation to post independent
review and moving towards confirmation of progress with
BAE systems and moving more significantly into a delivery
phase. This will ensure long term engagement process
continues to build pro-active and positive engagement to
continue to re-establish trust and confidence across the
Dargavel community. 
August
2023
Head of
Marketing
and Comms
Complete The Dargavel communication and engagement
strategy was reviewed following the publication
of the Bowles Report. The strategy covers the
development of long-term solutions to increase
primary and secondary capacity. The key aim has
been to provide straightforward messaging and
up to date sitreps to ensure publics (and council
representatives) have the most up-to-date
position and the complexity of the issue is
explained in a simple and honest way. We
committed from the outset to ensure those
members of the community directly impacted
(and their representatives) are first to hear about
the steps being taken to deliver a solution and
the decision-making process involved. The
strategy has been designed to: 
• Improve the flow and regularity of
information to parents and carers and the
wider Dargavel community, so they are first
to hear about decisions impacting their
community. Ensure parents and carers have
access to all projection data available to the
council.
• Introduce direct communication channels
with Dargavel residents, enabling all sections

Page 23

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
of the community to engage on matters that
are important to them and making sure the
latest information is accessible and easy to
find.
• Provide residents with a feedback loop to
enable them to ask questions of the council
in relation to the development and have
questions answered quickly.
• Include the community in formal planning
and design of a new primary school and high
school extension. 
Activity delivered from October 2022 to present
includes: 
• Planned and hosted 2 public meetings
• Monthly updates to the council website
• 13 update letters issued to parents and
carers at Dargavel Primary School and
shared with community stakeholders.
• 3 proactive media updates and the
handing of almost 50 media enquiries to
ensure the council’s right of reply -
including arrangements for broadcast
interviews. 
• Ongoing Elected Member briefings and
MP/MSP briefings to ensure all political
representatives are kept up to date on
matters relating to the Dargavel
Community.

Page 24

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
• Following publication of the Review,
individual meetings took place with four
local community representatives who
were interviewed for the Review to
include next steps. Ongoing engagement
continues with two representatives to
provide a sounding board for
communication and engagement.
• August 4, the council’s senior team
attended a Round Table Meeting with
Bishopton Community to discuss
education provision and leisure and
recreation provision.
• From August, introduced a new opt-in
community newsletter, promoted locally
to encourage resident sign up.
• Established the Park Mains Liaison Group,
attended by the Parent Council Chairs of
all Park Mains catchment primary
schools, to ensure we can collectively
plan the high school extension and
effectively engage with the wider school.
• Space Planning Activity for Dargavel
Primary School
• Preparation of communications plan to
encourage community engagement
(those directly impacted and those

Page 25

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
affected) with the forthcoming statutory
consultation, to be launched in January. 
Establish a new parent council liaison group to provide a
single PC forum (at the request of PC chairs) to provide a
streamlined opportunity for consistent engagement and
communication with the whole PC community for all
schools associated with Dargavel / Bishopton and PMHS and
all feeder primaries. 
August
2023
Head of
Education 
Complete Group has been established and has met
following school summer break with positive
feedback from Parent Council Chairs with
engagement to date.
Establish regular opt-in digital community newsletter to
facilitate regular communication updates direct to
interested members of the community. 
August
2023
Head of
Marketing
and Comms
Complete Take up of opt-in digital channel newsletter is
currently sitting at over 500 and it is expected
that this will continue to grow in the coming
months. 
Establish and track key indicators of community sentiment.  Ongoing Head of
Marketing
and Comms
Ongoing Assessment of the range of indicators and metrics
suggest ongoing interest in Dargavel, albeit
across the wider community this has settled
through formalised engagement routes with
constructive and positive discussion. There
remain some ongoing aspects of concern
expressed from some community representatives
and is being collated through the statutory
consultation process which will conclude at the
end of March. Engagement with the consultation
process has been steady and positive, but so far,
the numbers of people engaging is lower than
expected.

Page 26

APPENDIX 1
Dargavel Independent Review
Action Plan Response Monitoring – February 24
Action  Target
Completion
Responsible
Officer
RAG Status Update
Develop, deploy (at appropriate key points post formal
consultation period) and evaluate a community pulse survey
to assess and track community sentiment and view of
ongoing handling and satisfaction with delivery of key
interventions within the community. 
Expected
April/May
2024
Head of
Marketing
and comms
In
development 
Community sentiment is being tracked through
the formal consultation process and the
Consultation Institute have been commissioned
to support a study/survey to assess if the
engagement strategy is building public trust.
Anecdotal feedback during the consultation
process is pointing to a community view of
improved engagement. The results of the study
will be reported for June 2024.

Page 27

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
Community and other engagement 
The council must, as a matter of urgency, conduct a robust
and transparent assessment of the effectiveness of its
community engagement and then move swiftly to
implement any improvements needed. 
A full update of all completed and planned communication
and engagement activity since late 2022 as at end February
2022 will be provided to the External Audit team. 
The Consultation Institute – a recognised sector leading best
practice Institute promoting high-quality cross sector public
and stakeholder consultation standards – has been
commissioned to conduct a robust and independent review
of the council’s engagement strategy and activities. 
This will include assessment of the engagement strategy; the
variety of mechanisms implemented from October 2022 to
communicate and engage with the local community and the
effectiveness of activity. This will include qualitative
feedback from the community.
The commission will also extend to providing advice and
quality assurance on the statutory consultation
arrangements on the proposal for a new primary school in
Dargavel, its proposed site and catchment arrangements. 
This independent assessment process will be robust and
significant and carried out over several months. It is expected
to take until into June to fully complete all planned activities 
February 2024  Head of
Communications
and Marketing

Page 28

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
and provide a full evaluation report, albeit any key emerging
findings, learning and recommendations for improvement
identified as the evaluation progresses will be actioned as
soon as possible and shared on an ongoing basis with the
local audit team ahead of the planned report to the
Commission in June. 
The output of this commission and all associated
recommendations will assist in informing the design of future
engagement and consultation activity both within the
education estate but also across future consultation and
engagement activity associated with service / policy change
etc which the Council will be increasingly required to
consider moving forward as part of addressing its financial
sustainability challenges. 
February –
June 2024 
Head of
Communications
and Marketing
The Commission is particularly concerned by the council’s
failure both to transparently consider alternative options
in relation to expanding secondary school capacity in the
area, and to consult or engage appropriately with the
community, whom their decision directly affects. 
It is accepted that the report to the Education and Children’s
Services Policy Board in May 2023 could have articulated the
reasons why no other options to address secondary school
capacity beyond an extension to Park Mains High School
were deemed viable for detailed consideration.  
Additionally, although engagement in relation to updated
school projections and developing plans for a larger
extension to PMHS were shared and discussed with the
PMHS parent council prior to the May report, plans to expand
this engagement process to a wider group to encapsulate all
feeder primaries following the board meeting could have

Page 29

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
been outlined in the report and or considered earlier in the
process.   
Council officers have since May 2023 been progressing
positive and ongoing community engagement in relation to
the Park Mains extension, principally through the Park Mains
Liaison Group which was established to provide a single
engagement forum with representatives from the Parent
Councils of Park Mains High School and all associated feeder
primaries. 
This engagement process has shared and explained detailed
pupil projection data, the underlying rationale for the
proposed extension decision as well as listening and
responding to concerns and or requests for further
information from the wider parent and carer community.
This included sharing detailed information on an option
promoted by some community representative from Dargavel
and Bishopton for a new secondary school for Dargavel,
Bishopton and Langbank.  As reported through the Education
and Children’s Services Policy Board in August 2023, such an
option had significant negative implications from a financial,
educational, value for money and school estate perspective
that discounted it as a credible option for detailed
consideration. 
The Park Mains Liaison Group is proving to be a highly
valuable engagement forum, providing a single route of
engagement across the wider community as well as a key
route to assist the Council to disseminate consistent key 
This
engagement
activity will
remain
ongoing as
part of the
PMHS
extension
project
through to
August 2027
and beyond
recognising
the long-term
monitoring of
school roll
projections at
the high
school. 
Director of
Children’s Services

Page 30

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
messages and information updates across communities
through trusted Parent Council communication channels.
This engagement approach will inform how non statutory
and informal engagement in relation to potential school
estate changes and long-term strategic learning estate work
may be taken forward in the future by the Council. 
Additionally, high levels of positive engagement are being
secured as part of the space planning process for the new
extension, supporting active parental and carer participation
and influence in the design process of the new extension and
wider changes to the school that are planned to be delivered.
This is increasingly building a positive community
commitment and level of direct participation in the delivery
of the school extension and improvement project. 
The review of the Council’s engagement strategy as referred
to above will include a qualitative assessment of the
effectiveness of the Park Mains Liaison Group. 
Lastly, work is being progressed by officers to research how
other councils have approached school extension projects,
where a statutory consultation process is not required. The
objective of this work is to inform the design of a framework
to inform any future approach to early informal engagement
that can be adopted by the Council in relation to school
estate considerations or changes.

Page 31

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility 
Desk top work completed to date has identified a mixed
picture with several councils having adopted a similar
approach to that employed by the Council for the PMHS
extension. However, there are some examples of the use of
published options appraisals as part of Council reports and
identified examples of planned informal engagement
strategies deployed as part of long-term strategic school
estate planning which provide some good practice
approaches for reference. 
These individual elements of good practice that are evident
across other councils can be collectively brought together
and used to inform and guide the development of a proposed
framework for use by the Council in its future strategic school
estate planning programme (where appropriate this will pay
due regard to the Scottish Government guidance on informal
engagement that may occur prior to a statutory consultation
process). 
In completing this work consideration will be given to sharing
the output across the local authority sector given what
appears to be a level of mixed and inconsistent approaches
deployed across the country. 
August 2024  Director of
Children’s Services

Page 32

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
We note that the new primary school is subject to a full
public consultation. 
We expect the council to engage meaningfully with the
community on this issue, and other decisions on the school
estate. 
Again, we ask that the Controller monitors this situation,
and reports to us in June 2024 on progress and earlier if
necessary. 
The Education and Children’s Services Policy board approved
the planned consultation programme in January with a
report on the outcome of the consultation planned to be
brought back to Policy Board in May. 
A full programme of planned consultation and engagement
activity has been developed with input from the Institute of
Consultation to bring to the design process experience of
recognised best practice deployed across the UK. 
Full details of the planned consultation process and activity
will be provided to the external auditors as well as the
opportunity to observe any of the planned information
events and or formal consultation meetings. 
The approach specifically developed for this consultation
process as well as the evaluation of its effectiveness will be
used to inform a best practice approach for use in any future
statutory and non-statutory school consultation processes as
well as wider consultation and engagement activities the
Council may undertake in relation to any future service or
policy changes.   
Consultation
process has
commenced
and will fully
complete with
a report to the
Education and
Children’s
Services Policy
Board in May
2024 
Director of
Children’s Services

Page 33

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
Learning lessons and building capacity 
While the council’s initial response to the Bowles report
was high level, we are assured by the Controller that its
action plan in response is now sufficiently detailed and
includes SMART objectives 
It will be important that this action plan is well-managed
by senior officers and closely scrutinised by elected
members of the council. 
The action plan is regularly monitored by senior officers
through existing officer governance arrangements in relation
to Dargavel with an update on progress reported to each
cycle of the Audit Risk and Scrutiny Board and updates will be
shared with the external auditors on an ongoing basis.
Ongoing Director of Finance
and Resources
However, there are still significant uncertainties relating to 
• the capacity needed in the long term, and 
• to the completion of the two building projects –
the new primary school and the secondary school
extension. 
We therefore request that these matters are closely
monitored in the annual audit work, and the Controller
uses her powers to report any slippage or other issues to
us if necessary. 
Managing the Risk of Future Capacity Uncertainty 
The inherent uncertainty in relation to long term (15 year)
pupil growth projections has been widely reported by the
Council over the past year as an ongoing risk through both
formal board reports, as well as engagement and
communications with communities and in sharing data and
reports with the external auditors. This is particularly
recognised by the Council in the context of Dargavel Village
having approximately 10 years of development still to deliver
before achieving completion. It has also been trailed that the
Council’s projection work to date with Edge Analytics has
identified an expectation of a peak in demand to be reached
which will then fall to a stabilised long-term level of demand
– a similar pattern of demand growth has been evidenced
across other similar long term community growth areas in
the UK.

Page 34

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
The Council has heavily trailed the need to regularly monitor
actual pupil numbers and update long term projections on a
regular basis over coming years as a key response to being
able to pro-actively manage this risk moving forward. 
This monitoring process will be key to assess the extent to
which actual demand and revised projections is or is not
tracking against the current projections that have informed
the planned capacity levels that will be delivered by the
current learning estate interventions and provide early
indication of any risk of material deviation. The planned
annual monitoring and updating approach that will be
deployed over coming years will be shared with the External
Auditors. 
Long term projection work completed to date has already
modelled a range of potential demand scenarios for the
primary sector and identified an expected peak of demand in
2033/34. Options that can be considered for deployment in
future years to manage upper demand scenarios that would
be exceed the planned capacity being delivered for primary
sector education within Dargavel village, have already been
identified and reported through the Education and Children’s
Services Policy Board in November and shared with
community representatives. 
Should the monitoring arrangements over the coming years
highlight projection of sustained demand trending towards
the upper demand scenarios, an appraisal will be required to
assess which of the options is most appropriate for 
March 2024  Director of
Children’s Services

Page 35

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
consideration to be deployed to meet the scale and nature of
the additional future demand. This process will include early
community engagement with school communities and will
require timely assessment and associated decision making to
allow planned delivery of any additional intervention well
ahead of the developing need. 
In relation to the secondary sector, the impact of higher
demand scenarios will take longer to emerge (mid to late
2030s) and similarly it has been well trailed in Council reports
and with the community that long term monitoring and
projection modelling may identify the need to consider
options at an appropriate future point in time in respect to
any further intervention and or decisions in relation to
secondary sector provision across West Renfrewshire.   
Similarly, the long-term monitoring arrangements will
facilitate early identification of such risks and will support
early engagement with the appropriate primary and
secondary schools that may be impacted by any future school
estate changes. 
Delivery of New School Facilities 
It has been recognised by the Council that as a result of the
very late identification of the significant under-capacity
problems within both the primary and secondary sectors
serving Dargavel, the Council has since late 2023 been
operating within a highly compressed non-typical timeline to
undertake all the associated capacity planning, land

Page 36

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
assembly, community engagement, statutory consultation,
space planning, procurement arrangements before moving
into project delivery in order to achieve operational delivery
of the new facilities by August 2027. 
In broad terms, the Council is seeking to achieve all that is
associated with the long-term strategic planning,
engagement, consultation and operational delivery of a new
school and major extension of a secondary school in a 4 ½
year period, when such an end-to-end process would
normally run over a much longer period – a timeline of
around 6-8 year would not be an untypical period of
timeframe. Consequently, the Council is parallel running
several activities that would in most circumstances be
delivered in a broadly consecutive manner. 
The Council has established governance, programming, and
resource arrangements in place to support the delivery of the
new primary school and secondary school extension over the
remaining 3 ½ year period through to the operational target
date of August 2007. 
To date the external auditors have not undertaken any
detailed scrutiny of the delivery programme or the
arrangements in place. To provide assurance officers will
provide a full overview of the current arrangements for the
external auditors for their review and will support whatever
audit work is required to allow them to assess the Council’s
current approach. 
March 2024  Director of
Children’s Services

Page 37

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
Impact on service provision 
We note that the council has assessed that currently there
has been no detriment to either teaching delivery or pupil
education in the Dargavel and Bishopton areas from the
interim measures introduced. 
We consider it critical that the council reports the results
of these assessments publicly, regularly and in an
accessible way, to maintain and rebuild community
confidence. 
Renfrewshire Council has a robust Quality Assurance
framework involving regular meetings with Education
Managers and school staff and planned school visits which
focus in on the national quality assurance indicators
(reviews). 
DPS had a visit in January as part of this process where key
strengths under the national Quality Assurance indicators
from How Good is Our School were evaluated, self-
improvement and self-evaluation and Learning, Teaching and
Assessment and a report was produced. In addition,
Bishopton primary School and Park Mains High School were
both recently inspected by HMI, receiving very positive
reports. 
Further, every school submits a school improvement plan
and a school improvement report (published on website) and
their evaluations under the 4 key Quality Indicators (QIs) of
their performance, based on data gathered through self-
evaluation, HMI visits, internal visits and stakeholder input is
submitted to Children’s Services in April. 
These are shared with the parent councils and will also be
published on the school website as part of the self-evaluation
process. This is in line with Education Scotland guidelines, the
National Improvement Framework and statutory
requirements. 
Ongoing as
part of the
Service’s
Quality
Assurance
Framework 
Director of
Children’s Services

Page 38

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
The opportunity will be taken through the wider engagement
channels established with the Dargavel, Bishopton and wider
PMHS communities to sign post and raise awareness of
parents and carers to this information to provide an ongoing
understanding and reassurance in respect to the school
evaluation arrangements and outputs. 
Ongoing and
will be
incorporated
into parent
and school
newsletters at
appropriate
points. 
Head of Marketing
and
Communications 
The Commission is also concerned at the possible wider
impacts of the council’s failings regarding the estimation of
pupil numbers and whether this has had any impact on
services provided by the council in the Dargavel area. 
We request that the Controller seeks further information
on these issues so that we can understand the work that
the council has done to understand these impacts. 
The Council has considered a range of service provision and
other issues for Dargavel Village in addition to addressing
both primary and school provision. This has included the
following which will be shared with the external audit team
as part of their audit work: 
Leisure provision – the new primary school is planned to
incorporate a full-sized floodlight synthetic pitch with
associated changing facilities appropriate for community use
recognising the removal of similar facilities through the
history of the S.75 process since 2009, and the growing scale
and demand for such facilities from children, youth and
ultimately adult football within Dargavel and Bishopton
which is expected to expand further as Dargavel develops.
This facility will complement the resurfacing and
improvement of two floodlight synthetic pitches at PMHS
which will also serve the area as well as working with the
local Community Trust to progress their sport provision
ambitions within Bishopton. Beyond organised football, it
would be expected that this facility would be capable of
In line with
requests
emerging from
defined audit
programme to
be set by Azets
Chief Executive

Page 39

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
supporting a range of potential community uses in the
future. 
Community Facilities & planned play and recreation space –
a key part of the planned design ethos of the new primary
school is to create maximum flexibility to support delivery of
a community asset that will be able to offer facilities for a
wide range of community uses for all ages outwith school
hours. This was identified through the space planning
engagement stage and will address the failure to incorporate
wider community use into the design of the existing Dargavel
Primary School. This also recognises the future demand for
such facilities as the development progresses and will
provide useful insight for the Council as to how community
use can be more effectively incorporated into the design of a
new school and position such new facilities as attractive
community hubs for active use beyond the school day. 
A review of planned play and recreation spaces within the
masterplan / S.75 Leisure Strategy was also undertaken –
although there have been issues identified with the scale and
quality of play equipment provided to date at individual
designated play park areas that has been raised with BAE
Systems, the overall scale of provision was not influenced by
the Council’s calculations of school roll projection. 
Transport and travel infrastructure and bus service provision
– the Council has commissioned an external review of active
travel and traffic modelling as part of planning for a second
school within the masterplan area. A range of

Page 40

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
recommendations for consideration in relation to the
masterplan infrastructure have been made and which will be
progressed in discussion with BAE systems to enhance and
improve the opportunity for active travel.  
In addition, detailed engagement has been undertaken with
the Community to adapt proposals to utilise a financial
contribution from the S.75 to establish a bus service, partly
reflecting consideration of the anticipated number young
people that will emerge from the development and the range
of facilities they would most likely wish to travel to by public
transport. 
Support to schools – arrangements to provide appropriate
enhancement to management support to the school
recognising the additional demand being placed on the
school management teams were put in place early in the
process. Moving forward, normal arrangements to assess
and align both central support services to school as well as
school management teams as school rolls expand will be
undertaken in years to come. 
By way of example, there is a CAMHS officer who works as
the link for Children’s Services and who is currently working
with a group of schools in Linwood as part of a pilot to assess
demand and how that is being met. The next cluster
identified to receive this additional support will be Park
Mains and we are working closely with Educational
Psychologists and Family Wellbeing teams to ensure that, if

Page 41

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
there is an increase in expected demand, that this is being
met and indeed planned for as the school roll expands over
future years. Education Managers are monitoring and
working closely with the school and the CAMHS officer will
provide us with the data. 
NHS facilities and services – engagement has taken place
with IJB/HSCP colleagues as the Dargavel review unfolded. In
terms of data, pupil projection data relies on NHS data
flowing to support the pupil projection modelling – pupil data
does not conversely inform or influence NHS data and
planning and therefore there was no identified risk to any
under sizing of NHS planning as a consequence of pupil
projection errors by the Council. IJB/HSCP colleagues have
however considered the issue of planning for uncertainty in
respect population growth at Dargavel in terms planning the
design and delivery of the new health facility which will be
future proofed for potential future extension if required. 
Financial management and consequences 
The financial impact of these failings on the council is
significant. The council capped the risk and contributions
from BAE Systems under the Section 75 agreement, and as
a direct result faces estimated net additional capital costs
of £60 million, to be met by borrowing. This is a substantial
sum of public money. The council needs to clarify the
opportunity costs of this in terms of its overall capital
programme. The council projects that it will have a revenue
budget deficit of up to £50 million by 2026/27 and will
The Council will be required to manage the financial impact
of the unplanned delivery of a new primary school and larger
extension at PMHS through the delivery of its wider financial
strategy and any opportunity costs articulated as part of
developing and delivering that strategy. 
Will be
considered in
February 2024
as part of the
Council’s
annual budget
considerations
and updated
Director of Finance
and Resources

Page 42

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
need to make difficult decisions on prioritising its spending,
compounded by the financial consequences of this issue 
The council has recently negotiated a transfer of land from
BAE for the construction of a new primary school. The
Controller’s report indicates that this was in exchange for
amendments to the extent and composition of the housing
units for which planning permission has been granted. 
Given the reported determination of BAE to fully protect
their commercial interests in the development, and the
absence of alternative solutions for the council, it will be
important to ensure and demonstrate that this exchange
represents Best Value for the public purse. 
The financial and wider factors considered by officers as part
of the negotiation process with BAE systems to secure the
associated land agreement and adjustments to the S.75
agreement will be set out in detail and shared with the
External Auditors and will be reported through updates to
the Audit Risk and Scrutiny Board and subsequently. 
financial
strategy. 
March 2024 
Head of Economy
and Development 
Council leadership, governance, and culture 
The council’s action plan will be hugely important in
further embedding improvements in this area. In
particular, the following elements must be progressed
urgently and transparently: 
• the council’s review of its scrutiny arrangements against
CIPFA good practice guidelines 
• the council’s review of its approach to risk management 
Officers will provide the current scope and timings of the
associated actions and current progress in relation to each
action being progressed through the Council’s existing action
plan to the Audit Risk and Scrutiny Board and where required
will also be reported through any other appropriate
governance route within the Council. 
February 2024
and ongoing in
relation to the
outcomes
associated
with each
action.
Director of Finance
& Resources

Page 43

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
• the council’s leadership development programme for
officers. 
To be satisfied of progress in these areas, the Commission
requires the Controller to request further information from
the council on the scope and timing of these actions, and
report back to the Commission in the update requested for
June 2024, or earlier if she thinks necessary. 
We also expect these issues to be covered in the
accelerated Best Value report.
The Commission is also concerned about the culture of the
council and whether it has truly learned the lessons it
needs to. 
We expect organisational culture to be an area of focus in
the accelerated Best Value report. 
In particular, we request an update on whether the 
• culture of the organisation is appropriately open
and transparent, 
• encourages continuous improvement, 
• effective joint working between officers and
members, effective scrutiny and challenge
(especially by elected members), and 
• engagement and discussion with stakeholders. 
The council’s auditors concluded that the council has
appropriate governance arrangements in place with
improvements over the years in member and officer
relationships and effective leadership overall and were
satisfied through their detailed audit work that the Council
had demonstrated that the governance failings identified by
the Bowles report were limited to the historic handling of
Dargavel. 
The auditors did not highlight any concerns over the wider
organisational culture in the Council or in its approach to
managing major capital programmes but did identify that the
role of the Audit, Risk and Scrutiny Board in ensuring
effective scrutiny is not sufficiently clear and the Council has
recognised this and is already significantly progressed with a
review of the Audit Risk and Scrutiny Board and the outcome
of this review will be shared with the local audit team.

Page 44

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility 
In addition, we request an assessment of 
• whether it has the right skills in the right places to
deliver on its responsibilities, and 
• whether issues are escalated to the right level. 
Despite the finding of the Council’s auditors, the Commission
has expressed concern in relation to the Council’s culture and
have sought further assurances in relation to a wide range of
organisational issues. 
It is expected that the assessment of such issues will form
part of the planned Best Value Audit process and subject to
confirmation of the planned detailed best value audit
programme, Council officers will provide all the necessary
support, assistance and information to allow the audit team
to appropriately assess all key areas of interest. 
Subject to
confirmation
of the planned
best value
audit
programme
and approach 
Chief Executive 
Finally, the Commission notes that the auditor has
concluded that the council has obtained appropriate
external legal advice and determined there is no potential
for any form of action against former senior employees
involved in the Dargavel School decision-making. 
In addition, no disciplinary action has been taken against
any senior officer involved in decision-making relevant to
the Section 75 approval process for the Dargavel Village
development. 
The Commission accepts that these are management
issues. 
However, we request that the Controller asks the council
for further information on the process followed and 
No senior officers involved in the Dargavel S.75 decision
making process and identified in the Bowles Report remain
employed by the Council or remained employed at the time
of the Bowles report publication. In this context no senior
officer could be subject to any form of internal Council
disciplinary investigation or action. 
Full details of the process of consideration and legal advice
that was sought regard to any other form of external legal
action will be shared with the local external audit team as
requested by the Commission. 
Equally, arrangements will be made to provide the external
audit team with the Council’s disciplinary policy and
procedures as well as the overall approach to performance
management across the Council and support any further 
March 2024 
March 2024 
Head of Corporate
Governance 
Head of Policy and
Partnerships and
Head of HR & OD

Page 45

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
factors taken into account by the council in considering
disciplinary action against staff involved. 
In addition, and looking forward, the Commission asks for
information on 
• the council’s approach to performance
management and 
• its current policy on disciplinary action, 
so we can be assured that appropriate arrangements are in
place to ensure that staff have the necessary skills and that
senior officers are properly accountable for their areas of
responsibility. 
request that may emerge from their planned audit work in
this regard.

Page 46

APPENDIX 3
Cross Party Working Group Agreed Actions 
Cross Party Working Group Action  Update  Timeline  Responsibility 
Refresher training for management teams across all of the Council’s
directorates on the operation of delegated authority should be
implemented. 
Refresher training for management teams across all of the Council’s
directorates on the operation of the Protocol for Relationships
between Political Groups, Elected Members and Officers should be
implemented. 
Training was delivered to all directorates
by the Head of Corporate Governance and
the Council’s Chief Auditor in January 2024
to Chief Officers and tier 3 managers. A
further “catch up” session will be held for
those that missed the original session. 
April 2024  Head of Corporate
Governance and Chief
Auditor 
The content of the Protocol for Relationships between Political
Groups, Elected Members and Officers be refreshed. 
The Revised Protocol was approved at the
Council Meeting of 29 February 2024
Complete Head of Corporate
Governance
That the Bulletin be issued with the minutes of each Council and
board meeting for the meetings of Full Council. 
May 2024 Head of Corporate
Governance
A health check of all major projects will be completed and reported 
through the Audit, Risk and Scrutiny Board
This has separately been reported to the
ARS Board as part of the independent
review action plan 
Complete  Chief Executive
All major projects and programmes will report to the appropriate
board at least twice a year. 
Any such reports will include a note of all project groups involved. 
May 2024 Chief Executive

Page 47

APPENDIX 3
Cross Party Working Group Agreed Actions 
Cross Party Working Group Action  Update  Timeline  Responsibility
The outcome of the management training programme will be
reported to the Audit, Risk and Scrutiny Board 
This is separately being reported to the
ARS Board as part of the independent
review action plan 
Director of Finance &
Resources and Head of
HR & OD
A structure chart for all Council directorates should be prepared and 
circulated to all Elected Members. This should be regularly updated
and recirculated as necessary. 
The structure chart was circulated to all
Elected Members, and the first updated
version was issued in March
Complete Chief Executive 
That a Chief Planning Officer report brought to the Planning and
Climate Change Policy Board at least twice a year advising on the
position in respect of s75 Agreements, or where officers cannot not
reach agreement on substantive matters in a specific s75
Agreement negotiation. 
May 2024 Head of Economy &
Development Services