Minute of Meeting
Audit, Risk and Scrutiny Board 
Date Time Venue
Monday, 21 August 2023 15:00 Council Chambers (Renfrewshire), Council
Headquarters, Renfrewshire House, Cotton
Street, Paisley, PA1 1AN 
Present: Councillor Andy Doig, Councillor Chris Gilmour, Councillor John Gray, Councillor
Lisa-Marie Hughes, Councillor Robert Innes, Councillor Janis McDonald, Councillor Kevin
Montgomery 
In Attendance
A MacArthur, Director of Finance & Resources; L McIntyre, Head of Policy & Partnerships,
L Fingland, Service Planning & Policy Development Manager and L McGuiness,
Communications Business Lead (Transformation) (all Chief Executive’s); G Hutton, Head
of Operations & Service Development and C Dalrymple, Head of Head of Facilities &
Property Services (both Environment, Housing & Infrastructure); J Calder, Head of Early
Years & Broad General Education (Children’s Services); C McCourt, Head of Finance &
Procurement, M Boyd, Head of People & Organisational Development, M Conaghan, Head
of Corporate Governance, A McMahon, Chief Auditor, K Campbell, Assistant Chief Auditor,
P Feeney, Architecture & Technology Manager, S Fanning, Principal HR & OD Adviser, A
Black, Managing Solicitor (DPO), D Pole, End User Technician, D Low, Democratic
Services Manager and C McDonald, Senior Committee Services Officer and D
Cunningham, Assistant Committee Services Officer (all Finance & Resources). 
Also in Attendance
G Devlin, Partner & National Head of Internal Audit (Azets). 
Webcasting of Meeting
Prior to the commencement of the meeting the Convener intimated that this meeting of the
Board would be filmed for live or subsequent broadcast via the Council's internet site.

Page 2

Apology
Councillor J Adam.  
Declarations of Interest and Transparancy Statements
There were no declarations of interest or transparency statements made prior to the
commencement of the meeting. 
1 Summary of Internal Audit Reports for period 01 April to 30 June
2023
There was submitted a report by the Chief Auditor relative to the requirement in terms
of the Public Sector Internal Audit Standards (PSIAS) that Internal Audit
communicated the results of each engagement to the Board. 
The appendix to the report detailed the category of assurance, service, assurance
rating and gave recommended risk ratings for each engagement as either critical,
important, good practice or service improvement. A summary of findings was also
provided in relation to final reports issued for those engagements completed during
the period 1 April to 30 June 2023. 
The report intimated that in addition to the reports listed in the appendix, Internal Audit
had an ongoing commitment to arrange corporate and service initiatives, progress
information security matters in partnership with ICT and Legal Services, provide
regular advice to officers, provide Internal Audit services to the associated bodies for
which Renfrewshire Council was the lead authority and to Renfrewshire Leisure and
Renfrewshire Health & Social Care Integration Joint Board, co-ordination of the
Council’s Corporate Risk Management activity and management of the counter fraud,
risk management and insurance team. 
DECIDED:  That the summary of Internal Audit findings report for the period 1 April to
30 June 2023 be noted. 
2 Internal Audit and Counter Fraud Progress and Performance for
Period to 30 June 2023
There was submitted a report by the Chief Auditor relative to Internal Audit and
Counter Fraud performance between 1 April and 30 June 2023 in terms of the
delivery of the Audit Plan for the year and outlining actual performance against targets
set by the Director of Finance & Resources.

Page 3

No formal performance targets for fraud investigation had been established as a
major part of the team’s work involved being the single point of contact for the
Department for Work and Pensions (DWP) Single Fraud Investigation Service and the
Service Level Agreement for the work contained time targets for completing this work.
It was noted that the types of fraud referrals received to date were wide-ranging and
the team’s objective was to concentrate on investigating those referrals considered to
contain the greatest fraud risk. 
The report also detailed the progress made against local and national initiatives
involving Internal Audit and the Counter Fraud Team in the period. 
The report advised that the Internal Audit Team and the Counter Fraud Team were
currently working on a hybrid basis and were undertaking home/site visits when the
need arose. 
DECIDED: That the Internal Audit and Counter Fraud Team progress and
performance from 1 April to 30 June 2023 be noted. 
3 2022/23 Complaints Handling Performance
There was submitted a report by the Chief Executive relative to the annual complaints
report 2022/23. 
The report intimated that the Council’s complaint-handling procedure aimed to have
quicker, simpler and more streamlined complaints handling with early response by
capable, well-trained staff. As part of the procedure, all complaints were recorded and
monitored. 
The report provided information on complaints closed during the year from 1 April
2022 to 31 March 2023 and performance on key indicators and highlighted
improvements made to the complaints handling procedure over the past year to
ensure that complaints were handled well, and the organisation learned from them
and improved services. 
It was noted that 9,155 complaints were received in 2022/23 compared with 9,193 in
2021/22; 88.3% of the complaints were dealt with as frontline responses; 83.8% of
frontline complaints and 89.5% of investigation complaints received were completed
within target timescales; the average time to respond to frontline complaints met the
target of 4 days and was an improvement from the previous year figure of 5 days. 
The average time to respond to an investigation was 14 days, an improvement on the
2021/22 figure of 16.5 days, though this was still well within the SPSO target of 20
days. The 2022/23 breakdown of complaints received by services continued to be
broadly reflective of the volume of services provided with Environment and
Infrastructure delivering the highest volume and widest scope of frontline Council
services and consequently having the highest volume of customer interactions. 
A performance scorecard was included within the appendix to the report to provide
additional data. It was noted that all indicators would continue to be monitored
regularly and support and guidance would be provided to all services to assist with
analysing and improving performance where required. 
DECIDED: That the report be noted.

Page 4

4  Audit Scotland - Local Government in Scotland - Overview 2023
There was submitted a report by the Chief Executive relative to Audit Scotland’s
report on behalf of the Accounts Commission, a copy of which was appended to the
report. 
The report identified five key challenges for local government in Scotland – financial
sustainability, community needs, collaboration, leadership and workforce.  Each of the
key themes were considered in respect of the impact of the pandemic, the current
challenges, and how councils were responding. A number of case studies were
included to show how different councils dealt with the many challenges arising. 
DECIDED: 
(a) That the contents of the report be noted; and 
(b) That the contents of the Audit Scotland Overview which was appended to the
report be noted. 
5 Absence Statistics – Annual report 22/23 and Quarter 1 of 23/24
There was submitted a report by the Director of Finance & Resources relative to the
Absence Statistics annual report and the Council’s absence statistics for quarter 1 of
2023/24 ending 30 June 2023. 
The report provided information in relation to absence targets and how services and
categories of staff had performed against them. An analysis of the reasons for
absence for the period was included in the report. Information was also provided on
supporting attendance activity levels by service and costs of sick pay and the overall
number of days lost. 
DECIDED: That the report be noted. 
6 Audit, Risk & Scrutiny Annual Report 2022/23 and Annual
Programme 2022/23 - 2023/24
There was submitted a report by the Director of Finance & Resources relative to the
Board’s 2022/23 Annual Report and the Annual Programme 2023/24.  The Annual
Report was prepared in terms of the Council’s Code of Corporate Governance, which
highlighted the issues considered by the Board during the period August 2022 to June
2023. 
The report intimated that during the period, the Board examined different topics
including the programme of reviews; audit related matters; and annual reports by
other bodies. The report advised that in terms of the guidelines for the operation of the
Annual Programme, the Board was required to prepare an annual programme of
activities.  It was noted that the Bulk Items review was currently ongoing but the
Neighbour Disputes review had paused due to the Lead Officer leaving his post and
an exercise was currently underway to find a replacement Lead Officer.

Page 5

The report proposed that four reviews go forward as part of the Annual Programme of
Reviews for 2023/24 namely:  charges for bulk items; neighbour disputes; lack of
house and garden maintenance by some tenants and residents; and lead piping in
public and private housing in Renfrewshire.  It was agreed that these reviews be
included in the 2023/24 programme. 
DECIDED: 
(a)  That the Audit, Risk & Scrutiny Board Annual Report 2022/23 be noted; 
(b)  That it be agreed that four reviews go forward as part of the Annual Programme of
Reviews for 2023/24 namely:  charges for bulk items uplift for the elderly; neighbour
disputes; lack of house and garden maintenance by some tenants and residents; and
lead piping in public and private housing in Renfrewshire.