To: Audit, Risk and Scrutiny Board
On: 22 August 2022
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Internal Audit and Counter Fraud Progress and Performance for
Period to 30 June 2022
___________________________________________________________________
1. Summary
1.1 The Internal Audit Annual Plan was approved by the Audit, Risk and
Scrutiny Board on 13 June 2022. Internal Audit measures the progress
and performance of the team on a regular basis using a range of
performance indicators.  This report monitors progress from 1 April
2022 to 30 June 2022, in terms of the delivery of the Audit Plan for the
year and compares actual performance against targets set by the
Director of Finance and Resources. 
1.2 In terms of Counter Fraud, no formal performance targets for fraud
investigation have been established for the following reasons.  A major
part of their work involves being the single point of contact for
Department for Work and Pension’s (DWP) Single Fraud Investigation
Service and the Service Level Agreement for this work contains time
targets for completing this work.  In addition, the types of fraud referrals
received from Council services to date are wide ranging and the team’s
objective is to concentrate on investigating those referrals considered
to contain the greatest fraud risk. We are also involved in promoting
fraud awareness within the Council.    
1.3 All of the Internal Audit Team and Counter Fraud Team are currently
working on a hybrid basis and also undertake home/site visits when the
need arises.

Page 2

1.4 The report details progress against local and national initiatives
involving Internal Audit and the Counter Fraud Team from 1 April 2022
to 30 June 2022 
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to note the Internal Audit and Counter Fraud
Team progress and performance to 30 June 2022. 
_________________________________________________________
3. Background
3.1 The progress and performance of the Internal Audit Team is subject to
regular monitoring using a number of performance measures.  The
Director of Finance and Resources has set annual targets for the team
to demonstrate continuous improvement. In terms of the Counter Fraud
team, there are time targets in place for responding to requests from
the DWP’s Single Fraud Investigation Service.  Due to the diverse
nature of fraud referrals no formal performance targets have been
established and the outcomes from investigations is regularly
monitored by management.
3.2 Internal Audit and the Counter Fraud Team support a variety of local
and national initiatives through participation in professional practitioner
groups and co-ordination of national initiatives such as the National
Fraud Initiative.
3.3 This report measures the progress and performance of both the
Internal Audit and Counter Fraud Team for the period from 1 April 2022
to 30 June 2022.
4.                 Internal Audit Team Performance
(a) Percentage of audit plan completed as at 30 June 2022 
This measures the degree to which the Audit plan has been completed
Actual 2021/22 Annual Target
2022/23
Audit Plan
Completion
Target to 30
June 2022
Audit Plan
Completion
Actual to 30
June 2022
92.1% 95.0% 19%   21.9%          
Actual performance is currently ahead of target.

Page 3

(b) Percentage of assignments complete by target date 
This measures the degree with which target dates for audit work have
been met.
Target 2022/23 Actual to 30 June 2022
95.0% 100%           
Actual performance is ahead of the target set for the year.  It should be
noted that target dates have been extended where necessary as it is,
on occasions, taking longer to obtain information due to the
practicalities of hybrid working by internal audit and service staff.
(c) Percentage of audit assignments completed within time
budget 
This measures how well the time budget for individual assignments has
been adhered to. 
Target 2022/23 Actual to 30 June 2022  
95.0% 100% 
Actual performance is ahead of the target set for the year, although this
is likely to reduce over the remainder of the year.   
(d) Percentage of audit reports issued within 6 weeks of
completion of audit field work 
This measures how quickly draft audit reports are issued after the audit
fieldwork has been completed.
Target 2022/23 Actual to 30 June 2022
95.0% 100% 
Actual performance is ahead of the target set for the year, although this
is likely to reduce over the remainder of the year.   
5. Review of the 2022/23 Internal Audit Plan 
5.1 All of our staff are currently working on a hybrid basis and utilising the
Council’s various tools to continue to undertake audit assignments. The
priorities for the team this quarter is to undertake any investigations that
have arisen and also to complete the work outstanding from 2021/22.
5.2 Our 2022/23 Audit Plan is subject to regular review in light of any risks
arising from the Council’s organisational recovery or otherwise and also
to determine whether any assignments will have to be amended or
cancelled as result of being unable, for any reason, to undertake the
work planned. No amendments or cancellations to our planned
assignments are deemed necessary at this stage.  However, it is worth
noting that 1 member of staff has been on sick leave for the quarter and

Page 4

this impacts on our available resource.  In addition, a substantial
amount of our contingency time has been utilised in the first quarter
and this may lead to future audit plan amendments being submitted for
approval to this Board. There are several reasons for this. Specifically,
that some of last year’s assignments are taking longer than planned
and had to be carried forward into this year due to the revised working
arrangements and priorities of both client and our own staff and also we
have had to undertake  a number of investigations this quarter which
will be reported to this Board upon completion.   
6   Counter Fraud Team Progress and Performance
6.1 In line with the Service Level Agreement, the Counter Fraud Team act
as the Single Point of Contact (SPOC) to route potential housing
benefit fraud referrals to the DWP, liaise with the Council’s Housing
Benefit Team and DWP Fraud Officers and retrieve the necessary
evidence for the DWP Fraud Officers from the Housing Benefit System. 
In addition, we also work jointly work with DWP Fraud Officers on
criminal fraud investigations which focuses on the investigation and
prosecution of the Local Authority administered Council Tax Reduction
Scheme (CTRS) and Social Security benefit fraud.  
6.2 During this quarter, we have mainly been working on the various fraud
referrals received and completing investigations into matches identified
by the previous National Fraud Initiative which is administered by Audit
Scotland.   
6.3 The financial and non-financial results for quarter 1 (April 2022 to June
2022) are noted in the table below. 
Financial Outcomes Quarter 1
(£)
Cash savings directly attributable to
preventative counter fraud intervention 
Cash recoveries in progress directly
attributable to counter fraud investigations
25,280
Housing Benefit savings directly
attributable to counter fraud investigation
1,815
Housing Benefit Savings Attributable to
Joint Working by Counter Fraud and
DWP Counter Fraud Officers
30,933
Notional savings identified through
counter fraud investigation, (e.g. housing
tenancy and future council tax)
14,407
Non-Financial Outcomes Quarter 1 
Housing properties recovered 0
Housing applications amended/cancelled 0
Blue badge misuse warning letters issued 5
Licences revoked 0

Page 5

6.4 An i-learn package for staff is being developed for staff to increase their
awareness of fraud. 
7.   Local and National Initiatives 
National Fraud Initiative 
7.1 The guidance and timetable for the next National Fraud Initiative has
just been published and we are about to commence actioning planning
the tasks that have to be undertaken in order to participate in this
exercise. The data sets will be submitted in October 2022. 
Scottish Local Authorities Chief Internal Auditors’ Group 
7.2  This Group met virtually in June and received a presentation from a
representative from the Scottish Government on Fraud Risk and
Counter Fraud Controls during the pandemic. 
7.3 The Local Authorities Investigation Sub-Group was also attended
virtually during this quarter.  Speakers from the Cabinet Office and
Scottish Government gave a presentation on fraud data sharing powers
and our Housing Manager gave a presentation on housing issues to the
group. 
External Quality Assessment 
7.4 The Public Sector Internal Audit Standards requires that an External
Assessment should be undertaken on the InternaI Audit Service at
least every 5 years to ensure conformance with the definition of Internal
auditing and the standards, along with an evaluation of whether internal
auditors comply with the code of ethics. 
7.5 Our second assessment is due to be undertaken this year by the Chief
Auditor at South Ayrshire Council and the results along with any actions
will be reported to this Board. 
Training 
7.6 A training course, provided by an External Provider is going to be run in
August 2022 for our Internal Audit Staff to ensure we keep our audit
skills and techniques up to date. 
_________________________________________________________
Implications of the Report
1. Financial - The Council has in place arrangements to recover the any
overpayments identified from the work of the Counter Fraud Team and
the National Fraud Initiative.

Page 6

2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of
good corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights - None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The progress and performance reported relates to the delivery of
the risk-based internal audit plan and the mitigation of the risk of fraud
and error. 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk - None 
________________________________________________________________
Author:           Karen Campbell – 07768354651