Democracy Spraffa

Agenda Document Pack - Audit, Risk and Scrutiny Board - 23/09/2024

Renfrewshire Council · 23 September 2024
Back to Audit, Risk and Scrutiny Board — 23 September 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

Notice of Meeting and Agenda
Audit, Risk and Scrutiny Board 
Date Time  Venue
Monday, 23 September
2024
15:00 Council Chambers (Renfrewshire),
Council Headquarters, Renfrewshire
House, Cotton Street, Paisley, PA1 1AN 
MARK CONAGHAN
Head of Corporate Governance 
Membership 
Councillor Andy Doig (Convener):     Councillor Janis McDonald (Depute Convener):    
Councillor Jennifer Adam:  Councillor Chris Gilmour:  Councillor John Gray:  Councillor
Lisa-Marie Hughes:  Councillor Robert Innes:  Councillor James MacLaren:  Councillor
Ben Smith:   
Further Information 
This is a meeting which is open to members of the public. 
A copy of the agenda and reports for this meeting will be available for inspection prior
to the meeting at the Customer Service Centre, Renfrewshire House, Cotton Street,
Paisley and online
at http://renfrewshire.cmis.uk.com/renfrewshire/CouncilandBoards.aspx
For further information, please email
democratic-services@renfrewshire.gov.uk 
Members of the Press and Public 
Members of the press and public wishing to attend the meeting should report to the
customer service centre where they will be met and directed to the meeting. 
Hybrid Meeting 
Please note that this meeting is scheduled to be held in the Council
Chambers.  However, it is a hybrid meeting and arrangements have been made for
members to join the meeting remotely should they wish.

Page 2

Webcasting of Meeting 
This meeting will be filmed for live or subsequent broadcast via the Council’s internet
site – at the start of the meeting the Convener will confirm if all or part of the meeting
is being filmed.  To find the webcast please navigate to 
https://renfrewshire.public-i.tv/core/portal/home

Page 3

Apologies 
Apologies from members. 
Declarations of Interest and Transparency Statements 
Members are asked to declare an interest or make a
transparency statement in any item(s) on the agenda and to
provide a brief explanation of the nature of the interest or the
transparency statement. 
Monitoring & Reviewing Service Delivery Performance, Policies and
Practice 
1 Actions Monitoring Report - Dargavel Primary School 
Report by Director of Finance & Resources. 
1 - 50 
2 Best Value thematic work – Workforce innovation 
Report by Director of Finance & Resources. 
51 - 90 
Annual Programme 
3 Neighbour Disputes - Lead Officer Roz Smith 
Report by Lead Officer. 
91 - 110

Page 4

No embedded text on this page.

Page 5

To: Audit, Risk and Scrutiny Board 
On: 23 September 2024 
Report by: Chief Executive 
Heading: Actions Monitoring Report - Dargavel Primary School 
1. Summary 
1.1 Following the findings of an independent review into the circumstances
of the errors in planning and delivery of primary school provision in the
Dargavel area, a SMART action plan was developed detailing the
Council’s response with a commitment that updates on this plan would
be provided to Audit Risk & Scrutiny Board meetings going forward. 
1.2 At a meeting on 11th January 2024, the Accounts Commission was
presented with a statutory S.102 report, as circulated to Councillors on
5th January 2024, by the Controller of Audit on School Accommodation
for Dargavel. In the report, the Commission has set out its findings,
alongside several issues on which it requires further investigation. In
response, the Council developed an action plan based on the
recommendations. A follow-up report from the Controller of Audit was
published on 31 July and subsequently discussed at a meeting of the
Accounts Commission on 8 August 2024. The Accounts Commission
have since issued formal findings to the Council on 16 August. These
findings will be the subject of a report to full Council on 26 September
2024. This report will include the Council’s response to the Accounts
Commission, with further work being predominantly addressed through
continued engagement and monitoring by the local external audit team
through their Annual Audit work and upcoming Best Value audit. 
Item 1
Page 1 of 110

Page 6

1.3 On 29th February 2024, elected members at Council considered a report
on the outcome of the review of corporate governance arrangements by
the Cross Party Working Group and agreed a number of actions set out
in that report. Council further agreed that those actions would be
incorporated into the independent review response monitoring
arrangements reported to this Board.   
1.4 The appendices to this report provide an update in relation to the
Bowles independent review report, the Accounts Commission S.102
report, and the actions related to the report of the Cross Party Working
Group. Appendix 1 provides an update on remaining live actions while
Appendix 2 summarises all completed actions from each of the three
reviews. 
2. Recommendations 
2.1 Note and consider the update provided in Appendix 1 in relation to the
Council’s progress with live actions.
2.2 Note the completed actions outlined in Appendix 2. 
Implications of the Report 
1. Financial – whilst there will be significant capital and revenue
implications for the Council in resolving the Dargavel issue, there are no
financial implications for the Council as a result of this update report. 
2. HR & Organisational Development – the report outlines a leadership
development programme with a focus on key issues raised in the
independent review around governance, risk management, corporate
working and culture. 
3. Community/Council Planning – the report outlines ongoing action
being taken to develop an engagement and ongoing communication
process with affected communities. 
4. Legal – none 
5. Property/Assets – none
 
6. Information Technology – none
 
Page 2 of 110

Page 7

7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and
human rights. 
No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report as it is for noting only. If
required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.
8. Health & Safety – none 
9. Procurement – none 
10. Risk – the report outlines the action being taken in relation to risk
management.
11. Privacy Impact – none 
12. Climate Risk – none 
13. Children’s Rights – none 
14. COSLA Policy Position - none 
Author: Alan Russell, Chief Executive 
Page 3 of 110

Page 8

Page 4 of 110

Page 9

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Bowles Report Recommendation 1 
Build a more robust model of primary school need for Dargavel ‐ the Council should continue to refine its pupil forecast model for Dargavel. 
Response Objectives 
Deliver robust projection modelling for Dargavel and PMHS which: ‐ 
 considers live information arising from NHS, pupil & ELC registrations, the pace of development to date, certainty over development size and likely 
pace of future build out rate,
 utilises external data analytics and projection expertise to augment and enhance the Council’s in‐house forecasting approach to ensure modelling is 
robust, underpinned by external challenge and specialist input reflecting the complexity and significant portion of Dargavel that has yet to be 
developed out over a circa 10 year period,
 provides modelling output which considers potential future upper scenarios reflecting the high yield factors reflected in the 2023/24 P1 intake to 
inform immediate decisions on scale of capacity to be delivered as well as planning for potential additional interventions at a future time,
 delivers modelling output which provides a long‐term view beyond the anticipated completion timeline for Dargavel to ensure the long term impact of 
Dargavel is modelled and understood,
 provides modelling output over the long term which indicates both the scale, timing and shape of an anticipated peak in demand that will accompany 
a development of this scale and nature. This will provide visibility of the anticipated short‐lived peak in demand and long term settled demand to 
ensure this is appropriately reflected in estate/capacity decisions and in particular to mitigate against delivery of excessive long term / permanent 
increase in capacity that would result in excess unused surplus capacity over the long term.
 Provides modelling that can be tested and revised as necessary as new key data becomes available such as P1 and S1 registrations, actual scale and 
pace of the development and any new developments, which will continue to inform decisions on any future estate interventions if required.
Page 5 of 110

Page 10

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Update Edge Analytics modelling for newly released 
national Census data and expand across the whole 
school estate and establish modelling dashboard to 
support ease of updating and rapid re‐assessment of 
revised projection that will be utilised on an ongoing 
basis over future years, both for Dargavel / PMHS but 
also as part of the strategic Learning Estate programme. 
January 2024  Director of 
Children’s 
Services 
Members will note from the original monitoring report to the 
Board in November 2023 there were 5 sub‐actions in relation 
to recommendation 1. Recognising the breadth of work that 
needed to be progressed, each were planned to be dealt with 
in chronological order over a period. This programme of work 
was initially planned to be completed between October 2022 
per action 1 (now detailed in Appendix 2) through to January 
2024 per action 5 (ie this action), not January 2023 which has 
unfortunately been reflected in previous updates provided to 
the Board.  
 
The reference to updated national census information being 
incorporated into the initial work completed by Edge Analytics 
in January 2023 was accurate inasmuch as it was referring to 
updated annual educational census information as well as 
updated national demographic information available at that 
time – it was not a reference to the national population 
Census completed every 10 years and which was published in 
September 2023.  
 
In respect to this action, it did have different components, the 
first being updating of the Dargavel and Park Mains 
projections for the National Population Census information 
and the second principal component being developing the 
projection model to expand its coverage across the whole of 
the school estate. 
 
In respect to progress made in relation to this action point, the 
initial element was completed by January 2024 with Edge 
Analytics completing an update on the 15‐year projection 
model for both Dargavel and Park Mains and this was reported 
as part of the Education and Children’s Services Policy Board in 
January 2024. Development of the whole school estate model 
has taken longer to develop than the initial target date of 
January 2024 due to a combination of factors.  
Page 6 of 110

Page 11

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
 
Firstly, the delay in relation to some updated datasets being 
made available to support the Edge model construction for the 
whole estate, principally updated housing land audit 
information and secondly, the window of availability of Edge 
Analytics resources.  
 
Edge Analytics are a commissioned resource who support a 
range of clients across the UK in addition to Renfrewshire 
Council. The Council is not therefore able to control their 
availability to respond to changing needs. Like other 
comparable niche consultancies, they are highly specialised 
and consequently relatively small. In such circumstances, 
securing capacity slots can be challenging particularly with 
large demands in terms of their own scheduling that emerge 
from national data exercise requirements that exist in England 
in relation to school rolls and which form a large part of their 
own annual work programme at different points in the year.  
 
In terms of the timing of availability of Edge Analytics 
resources a revised timeline for initial completion of the whole 
school estate modelling was targeted for approximately May 
2024 and this was reported in the update provided to the 
Board in March 2024.   
 
Edge Analytics completed an initial iteration of the estate wide 
modelling utilising their standard modelling approach which 
was subject to engagement with the Council team during May 
and which identified the need for further work for the Edge 
modelling approach to be appropriately applied to a whole 
estate scenario within a Scottish context and alignment to 
school catchments. Based on the availability of Edge Analytics 
resources, the required additional work to the Edge model 
was estimated not to be deliverable until the back end of the 
summer period.  
 
 
 
Page 7 of 110

Page 12

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
The Board update in May indicated again, similar to the March 
update, that a circa 8 week estimated period remained for this 
work to be completed – however it would have been 
appropriate for this update to have provided more 
information for members to make clear that this was a further 
tranche of work emerging from the quality assurance 
engagement process that needed to be progressed over the 
summer period with Edge Analytics after the initial modelling 
exercise was completed. 
 
Revised whole estate modelling was received from Edge at the 
end of August 2024 which is now being considered by 
Education officers.  The updated data will be the subject of  
reporting to a future Education and Children’s Services Policy 
Board to support the development of the now agreed learning 
estate strategy. 
 
Page 8 of 110

Page 13

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Bowles Report Recommendation 8
Public confidence 
These recent events and the matters described in this report will dent public confidence in the Council. The Council should work in an open and transparent 
manner in the resolution of these issues and particularly with the residents of Dargavel, who have legitimate concerns about the implications for their children 
during both their primary and secondary education. 
Response Objectives 
The key aim has been to provide straightforward messaging and up to date sitreps to ensure publics (and council representatives) have the most up‐to‐date 
position and the complexity of the issue is explained in a simple and honest way and that parental/carer concerns in respect to the school and educational 
environment are able to be appropriately discussed through structured engagement arrangements with the parent councils with appropriate agreed actions 
taken forward. 
The strategy has been designed to: 
−  Improve the flow and regularity of information to parents and carers and the wider Dargavel community, so they are first to hear about decisions 
impacting their community. 
Page 9 of 110

Page 14

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
− Ensure parents and carers have access to all projection data available to the council. 
− Introduce direct communication channels with Dargavel residents, enabling all sections of the community to engage on matters that are important to 
them and making sure the latest information is accessible and easy to find. 
− Provide residents with a feedback loop to enable them to ask questions of the council in relation to the development and have questions answered 
quickly. 
− Include the community in formal planning and design of a new primary school and high school extension. 
It is recognised that effective communication and engagement is important to building a new relationship between the Council and the Dargavel community, 
but ultimately it will take the delivery of the solution and investment in long term engagement to reduce local anxiety and fully rebuild trust and confidence in 
the Council. 
Establish and track key indicators of community 
sentiment. 
Ongoing  Head of 
Marketing and 
Comms 
Ongoing  The council continues to deploy the Dargavel 
communication and engagement strategy and 
to provide regular updates to the community 
through a variety of channels – including face‐
to‐face forums, monitoring reach, engagement 
and feedback which is recorded and used to 
inform future communications.  
Community engagement groups have been 
established to help plan new school design and 
traffic and travel.  
We continue to grow membership of our opt‐in 
community newsletter.  
Recent and live community engagement activity 
includes focus groups and public meetings 
linked to school design that form part of the 
PAN process for Dargavel Primary School. This 
will be followed by a similar engagement 
programme for extending Park Mains High 
School.  
The community survey outlined below will help 
to develop a baseline satisfaction level that can 
be tracked ongoing.  
Page 10 of 110

Page 15

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – September 2024 
 
The Consultation Institute completed a review 
of the council’s communication and 
engagement strategy. The report concluded 
that the council’s process is thorough and 
showed ‘considerable good practice’. The 
Report made recommendations to inform 
future engagement and consultation, which 
will be used to develop a new corporate policy 
on engagement and consultation, to be 
delivered at the end of October.  
 
The recent findings by the Account Commission 
as part of their follow‐up S102 report, published 
on 20 August, stated that the council’s approach 
to its recent consultation and community 
engagement activity was appropriate and 
comprehensive.  
 
A Dargavel and Bishopton community survey is 
currently live to test:  
 Awareness of the Council’s engagement 
strategy and the formal statutory 
consultation which took place earlier this 
year. 
 Perceptions of the effectiveness of the 
Council’s engagement 
 Barriers to engaging with the Council 
 Has community trust in the Council 
improved as a result of the engagement 
strategy. 
 
The survey – 
www.researchresource.co.uk/Dargavelresidents
survey.html was launched on 6 August and will 
run to 9 September. 
Page 11 of 110

Page 16

Page 12 of 110

Page 17

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – May 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Develop, deploy (at appropriate key points post formal 
consultation period) and evaluate a community pulse 
survey to assess and track community sentiment and 
view of ongoing handling and satisfaction with delivery 
of key interventions within the community. 
Expected 
September 
2024 
Head of 
Marketing and 
comms 
In 
development 
As above, a community survey is currently live. 
This was launched on 6 August and will run to 
9 September, promoted through a Royal Mail 
door drop and through existing Dargavel and 
Bishopton community channels. Resource 
Research, an independent research company 
will analysis the survey responses and produce 
a final report by 20 September. This will 
provide a baseline for future surveys.  
 
 
Page 13 of 110

Page 18

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Bowles Report Recommendation 1
Build a more robust model of primary school need for Dargavel ‐ the Council should continue to refine its pupil forecast model for Dargavel. 
Response Objectives 
Deliver robust projection modelling for Dargavel and PMHS which: ‐ 
 considers live information arising from NHS, pupil & ELC registrations, the pace of development to date, certainty over development size and likely 
pace of future build out rate,
 utilises external data analytics and projection expertise to augment and enhance the Council’s in‐house forecasting approach to ensure modelling is 
robust, underpinned by external challenge and specialist input reflecting the complexity and significant portion of Dargavel that has yet to be 
developed out over a circa 10 year period,
 provides modelling output which considers potential future upper scenarios reflecting the high yield factors reflected in the 2023/24 P1 intake to 
inform immediate decisions on scale of capacity to be delivered as well as planning for potential additional interventions at a future time,
 delivers modelling output which provides a long‐term view beyond the anticipated completion timeline for Dargavel to ensure the long term impact of 
Dargavel is modelled and understood,
 provides modelling output over the long term which indicates both the scale, timing and shape of an anticipated peak in demand that will accompany 
a development of this scale and nature. This will provide visibility of the anticipated short‐lived peak in demand and long term settled demand to 
ensure this is appropriately reflected in estate/capacity decisions and in particular to mitigate against delivery of excessive long term / permanent 
increase in capacity that would result in excess unused surplus capacity over the long term.
 Provides modelling that can be tested and revised as necessary as new key data becomes available such as P1 and S1 registrations, actual 
scale and pace of the development and any new developments, which will continue to inform decisions on any future estate interventions if 
required. 
Page 14 of 110

Page 19

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Complete Council modelling through to the anticipated end 
date for the housing development (2033/34) based on 
assumed 4,300 units and available live data. 
October 
2022 
Director of 
Children’s 
Services 
Completed October 2022 
Engage and appoint Edge Analytics to deliver enhanced 
modelling approach for both Dargavel primary 
requirements as well as PMHS out to 2033/34 and updated 
live datasets. 
February 
2023 
Director of 
Children’s 
Services 
Completed February 2023 including additional upper forecast 
scenarios for Dargavel non‐denominational requirements to 
support management of risk associated with long term yield 
remaining at similar level to 2023/24. Informed reports to 
Education and Children’s Services Board in March and May 2023 
Extend Edge engagement to deliver an enhanced model 
projecting out to 2038 to provide longer term forecast to 
assess the full impact on the secondary sector and allow 
identification of likely timing and scale of peak demand 
encapsulating any relevant updates to live datasets. 
September 
2023 
Director of 
Children’s 
Services 
Modelling completed which has identified an anticipated peak 
period in both primary and secondary sectors and will be 
reported to Education and Children’s Services Board in November 
2023. 
Provide update to November Education & Children’s Service 
Policy Board. 
November
2023 
Director of 
Children’s 
Services 
Two update reports were taken to the November ECSPB: 
1. Learning Estate 
2. Dargavel Housing Development – Impact on 
Denominational Education Provision 
 
Bowles Report Recommendation 2
Use of Bishopton Primary - in its future plans the Council should reconsider how surplus capacity at Bishopton can be used effectively.
Response Objectives 
Page 15 of 110

Page 20

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Consider and assess how existing capacity within Bishopton Primary School may be best utilised to support the Dargavel catchment over the immediate term 
and potentially over the longer term, taking into consideration the uncertainty and risk over the long‐term demand levels that will ultimately emerge for 
primary education from Dargavel as well as the expectation of a temporary peak period of demand. 
Provide a report to Education and Children’s Services Board setting out a clear overview as to how Bishopton PS capacity will be utilised to support temporarily 
over the short term period and how it may be considered amongst other options for use to support Dargavel in the longer term (noting that any such longer 
term use will be subject to detailed consideration and decision at an appropriate point in future years). 
Complete assessment of anticipated P1 intake from 
Dargavel catchment and assess against revised DPS capacity 
availability, establish planned P1 intake capacity cap and 
anticipated P1 intake requiring accommodation at 
Bishopton Primary School. 
August 
2023 
Director of 
Children’s 
Services 
Planned use of Bishopton Primary School along with planned 
capped entry levels to Dargavel Primary School reported an 
approved at Education and Children’s Services Policy Board in 
August 2023. There will be a requirement to annually monitor 
anticipated and actual P1 intakes carefully to assess adequacy of 
short term capacity provision across both Dargavel and 
Bishopton Primary Schools to meet demand pending the second 
primary school in Dargavel coming on stream. 
Complete an exercise to assess the timing, scale and range 
of potential demand level scenarios, in particular 
understanding the scale and timing of the peak demand and 
likely settled long term demand. This information will be 
used to inform the assessment of how Bishopton Primary 
School could, if required, be potentially be utilised as an 
option in the longer term. 
January 
2024 
Director of 
Children’s 
Services 
Completion of the updated work with Edge Analytics has 
provided a view of the likely timing and length of the peak 
demand period – with peak primary demand being forecast in 
2033/34 which will fall over the second half of the 2030s to a 
more settled level. Further work is being progressed to update 
this information for the recently released 2023 census 
information and November registration data to inform an overall 
assessment. 
 
Revised roll projections for the entire learning estate are 
currently being produced. In anticipation of these, work is 
underway by utilizing current live data and matching this with 
draft roll projection data to run scenario planning for the short, 
medium, and long term capacity demand on both Dargavel 
Primary and Bishopton Primary. 
Page 16 of 110

Page 21

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Complete financial analysis to understand the potential 
financial context of utilising Bishopton Primary School 
Capacity 
May 
2023 
Director of 
Finance and 
Resources 
Bishopton PS is a predominantly 1960s construction and is more 
than 60 years old. This building will, along with the whole school 
estate, undergo an updated condition survey over coming 
months. Notwithstanding, given the underlying age of the 
building it will inevitably have a limited remaining lifespan 
before being considered for replacement. 
 
Existing surplus capacity if used permanently to reduce the 
required size of a second Dargavel primary school, will require to 
be replaced as part of a renewal programme. The determination 
of the timing of that will be subject to work progressed as part of 
the strategic learning estate programme. 
 
Consequently, it has been assessed that any financial advantage 
from utilising Bishopton PS will be restricted to a temporary time 
value of money benefit and consequently will be relatively 
limited. 
 
In addition, there is also a risk that utilising Bishopton PS 
permanently removes its availability to provide supporting 
capacity to manage both a temporary peak that may arise from 
upper end educational demand scenarios and longer term upper 
end demand. There could be the risk that in such circumstances if 
Bishopton capacity was no longer available this would lead to 
higher overall costs over the longer term for the Council. 
 
The financial considerations and risks were incorporated into the 
overall assessment reported as part of the Education & Children’s 
Services Board report in January. 
 
 
 
Page 17 of 110

Page 22

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Set out overview in a report to the Education and Children’s 
Services Policy Board in respect to the potential long‐term 
utilisation of Bishopton Primary School which will be subject 
to detailed consideration at an appropriate point in future 
years as actual long term demand trends increasingly 
emerge. 
January
2024 
Director of 
Children’s 
Services 
Work to allow appropriate recommendation to be made is 
progressing in line with plans and scheduled to be reported to 
Board in January 2024. A paper was presented to Board in 
January 2024 
Page 18 of 110

Page 23

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Bowles Report Recommendation 3
As the Council progresses its plans to issue supplementary guidance on developer contributions for education it should seek to learn from other Councils in 
Scotland. 
A development the size of Dargavel is exceptional and would need its own modelling techniques. However, for smaller developments the Council should create 
an evidence base to calculate specific yield factors derived from recent developments in Renfrewshire. Such robust data will ease future negotiations. 
Undertake a desk top review of other local authorities 
across Scotland and identify key best practice councils to 
engage. 
June 2023  Head of 
Economy and 
Development 
Completed 
Complete detailed engagement with identified best practice 
councils arising from desk top research 
Summer 
2023 
Head of 
Economy and 
Development 
Detailed engagement completed with Fife, Falkirk and West 
Lothian councils. 
Complete data analysis exercise of a range of datasets of 
mixed historic sites across Renfrewshire to provide 
empirical evidence to support actual pupil yields to inform 
establishment of appropriate yield factors to be used in 
future contribution policy. 
 Refresh % capacity of all schools (vs school rolls) 
 Sample research of Pupil Product Ratio (PPR) for developed housing 
sites (< 10 units) [min 10 site sample] 
 Sample research of PPR for developed housing sites (> 100 units)[min 
10 site sample] 
 Sample research of PPR for established / mature housing 
development to provide longer term perspective (eg. 15 years old) (> 
100 units)[min 4 site sample] 
 Identify individual schools where pupil capacity is above notional 
threshold (85%) 
October 
2023 
Head of 
Economy and 
Development 
Work on this is now complete, agreed new draft planning 
guidance presented to March 2024 PCC Board. 
Page 19 of 110

Page 24

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
 Identify all known undeveloped housing sites in individual school 
catchments
 [Subset of 5] identify all housing sites with current "live" planning 
application
 Identify schools where it is anticipated intervention would be required 
to increase capacity based on potential future housing to be delivered 
over next 10 years to inform likely future developer discussions.
Incorporate into the development of the draft contributions 
policy targeted to be presented to the Planning and Climate 
Change Policy Board in January 2024. 
March 2024  Head of 
Economy and 
Development 
Work on this is now complete, new draft planning guidance 
presented to March 2024 PCC Board. 
Bowles Report Recommendation 4
Council needs to work co‐operatively with BAE. Unless the Council and BAE can work together to resolve the current problems, BAE may face accusations, 
whether founded or not and regardless of Council incompetence, that it has increased its profits at the expense of Council taxpayers. 
Response Objectives 
Secure legal ownership of suitable land to facilitate delivery of a second school within Dargavel Village as well as additional land next to existing school site to 
provide increased flexibility to meet potential future extension of the school and or establishment of greater outdoor space. 
Secure legal commitment from BAE to provide land remediation and associated infrastructure requirements as part of legal agreement at nil cost to the 
Council. 
Secure as part of the legal agreement certainty on consented planning numbers and any associated adjustments to s.75 agreement to reflect revised 
agreement. 
Secure with BAE agreement on Heads of Terms for allow for 
mutual governance approval from each organisation to 
inform detailed legal agreement drafting and final sign off 
As soon as 
possible 
Chief 
Executive 
This was completed and approved by ILE Board end of August 
2023 
Page 20 of 110

Page 25

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
was 
targeted. 
Secure completed and signed legal missives to deliver in full 
the objectives outlined above to provide certainty and 
timing of availability of remediated and infrastructure 
proofed land to support wider school delivery planning and 
consultation arrangements that will be progressed by the 
Council team. 
August 
2023 
Chief 
Executive 
Legal missives concluded mid‐September 2023 
Proposed revisions to S.75 negotiated with BAE Systems 
were approved by ILE. Revised S.75 signed off by both the 
Council and BAE Systems to legally conclude matters. 
August 
2023 
Head of 
Economy & 
Development 
Approved by Planning and Climate Change Board August 2023 
Bowles Report Recommendation 5
Corporate working and organisational culture ‐ although I understand that the Council has sought to improve and strengthen corporate working in recent 
years, the evidence would suggest there is a long way to go; simply establishing corporate working groups is insufficient if staff are in a mindset of ‘not my 
problem’. 
The failure of management oversight, if symptomatic of the Council as a whole, would be deeply disturbing. The Council needs to consider a significant change 
programme, not just on the of issue of corporate working and personal responsibility, but also its organisational culture and values. It needs plans to build a 
stronger organisation where constructive challenge is welcomed and there is a clarity of what is expected of all of those in a leadership role. 
Response Objectives 
Provide assurance that established programme governance framework and operations of governance for other major capital investment programmes and 
specifically that the Bowles findings on the historic failings on the handling of Dargavel by officers are not representative of the Council’s current culture and 
approach to the management and delivery of major programmes. 
Page 21 of 110

Page 26

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
The Council is committed to living its values as a learning and collaborative organisation and post COVID was already in the process of re‐establishing an 
Leadership Development programme for senior leadership teams and managers across the Council in recognition that this required to be reinvigorated post 
COVID and that there has been significant turnover in management and senior positions over the past three years and this would support growing and 
maturing the current culture and collaborative connections across the organisation. 
In response to the Bowles recommendations, the objective is to ensure the new Leadership Development programme is appropriately cognisant and reflective 
of the key learning points from the Bowles report and takes the opportunity to ensure its coverage seeks to re‐enforce the development of skills related to 
governance, risk management, commercial risk, corporate working and culture etc and effectively utilises failures referenced in the Bowles report as key 
examples for learning throughout the programme. Collective reflection and learning of such significant failures – albeit historical – is recognised as an 
important element of building an effective future culture and ways of working across the organisation. 
Undertake a health check assessment on major capital 
programmes to provide reassurance in respect to all aspects 
of governance, control, reporting and management of 
programmes. 
October 
2023 
Chief 
Executive 
supported by 
CMT 
City Deal and Infrastructure Health Check report was submitted 
to CMT on 21 November 2023. 
Put in place arrangements to deliver a comprehensive 
Leadership Development Programme (circa 12 months + 
programme) for chief officers and senior managers which 
amongst other things will cover and key areas referenced in 
the Bowles report in respect to governance, accountability, 
risk management, collaborative working, member officer 
relations etc. 
Commence 
programme 
by 
September 
2023 
Director of 
Finance & 
Resources 
and Head of 
HR & OD 
Contract engagement in place and resources secured from 
SOLACE Enterprises to support co‐designed and co‐delivered 
programme. 
Initial Chief Officer programme launch event occurred on 3rd 
October with focusing on personal resilience. 
The programme has delivered sessions focussed on: 
 Effective Communications and Elected Member Relations 
 Programme Management, Leading and Navigating 
Strategic Change 
 Risk Management and Governance 
 Transformational Leadership 
 Delivering Corporate/Team Values and Vision 
Page 22 of 110

Page 27

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
This first leadership development programme has now been 
concluded with an evaluation process underway. Attendance 
was good throughout the programme and for any officers that 
were unable to attend parts of the programme, they will attend 
these specific modules during the next cohort grouping to ensure 
completion of the full programme. 
The next 2 Cohorts will be run from April to around September 
and with up to 60 places available for our next tier of 
management. There will be some revisions to content and 
emphasis based on feedback from the initial sessions, however 
the key themes of the programme will remain unchanged. 
 
UPDATE 
An evaluation of the leadership development programme for 
the first cohort of delegates (Chief Officers) has now been 
completed.  Positive feedback was received from both the 
delegates who attended and from the facilitator(s) who 
delivered the programmes.  This feedback has helped shape 
the programme for the next 2 cohorts of senior managers 
which are currently running, and due to complete October 
2024.  The evaluation feedback has been presented to the 
Council’s Corporate Management Team for noting. Following 
completion of these programmes, consultation with these 
cohorts will take place to explore how best to support our 
senior managers to continue their development and ensure 
their learning experience has a positive impact back in the 
workplace. 
 
Page 23 of 110

Page 28

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Design and undertake an evaluation process of the 
Leadership Development Programme for Chief Officer 
cohort to inform required changes / adjustments to 
programme delivery for next management cohort. 
March 2024  Head of HR 
and OD 
Initial feedback was requested as part of the final workshop of 
this first programme. An evaluation request, designed in 
partnership with SOLACE, will be sent out to each of the 
participants asking if their knowledge has increased, if they feel 
more confident and informed and what changes, if any, would 
participants suggest for the next cohort.  
 
Generally the feedback from cohort one (Chief Officer cohort) 
indicated a high level of satisfaction with the programme 
overall. Collaboration with other colleagues during the 
programme featured strongly with learning through shared 
experiences. There was positive feedback around learning from 
colleagues, strengthening networks across services and shared 
experiences, which will create consistent approaches around 
best practice. Some feedback was received around the content 
being more ‘Renfrewshire’ specific, including organisational 
challenges and use of case studies. Increased use of local 
examples and practical application is being incorporated into 
the programme for cohorts 2 and 3.   
 
A facilitated event for Chief Officers is scheduled for the end of 
September 2024.  This will be an opportunity to discuss and 
agree how this cohort of Chief Officers continues its learning 
journey, sharing their learning and practical experience to have 
a positive impact back at the workplace following the successful 
completion of the leadership development programme earlier 
this year.    
 
 
 
 
Bowles Report Recommendation 6
Risk management 
From documents I have seen the Council was unaware of the scale of risk it was taking in the calculation of pupil numbers. The identified risk in Council 
documents related to providing the school on time, not that the size of the school may prove to be inadequate.  The failure to identify that risk has had two 
consequences; first the Council has been slow to react to the increase in pupil numbers and second the Council did not negotiate with BAE with that risk in mind. 
Page 24 of 110

Page 29

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
The Council needs to review how it both identifies risk and manages it. 
Response Objectives 
Progress actions to provide reassurance in relation to the Council’s current risk management approach, in particular how this is approached, deployed and 
managed as part of major projects as well as considering and assessing the seniority / appropriateness of officer involvement and related skills across officers 
involved in the process. 
A review of risk profiles across all service departments to 
ensure visibility of all risks and confirmation of where 
certain risks are being monitored if outwith the standard 
Risk Reports to the Audit, Risk and Scrutiny Board (i.e., 
Health and Safety Planning Groups, Service Improvement 
Plans etc) 
October 
2023 
Director of 
Finance and 
Resources 
Risk report submitted to Audit, Risk & Scrutiny Board as planned 
on 6 November 2023. 
A review of the ‘service risk representative’ roles in each 
service department to ensure the representatives who sit 
on the Corporate Risk Management Group are sufficiently 
involved in risk matters within the service, to feed this into 
the Corporate Risk Management Group and that they also 
have authority within the service to provide challenge as a 
‘critical friend.’ 
October 
2023 
Director of 
Finance and 
Resources 
Action completed. CMT agreed (10 October 2023), that each 
Director will nominate a Head of Service and one other colleague 
to support the Head of Service in the role going forward. 
Delivery of a project risk management workshop specific to 
the planned new primary school in Dargavel (complete) 
August 
2023 
Director of 
Finance and 
Resources 
Workshop delivered covering nature of project risks, risk changes 
over lifecycle of the project; reminder of Council PM framework 
and PMU support; key issues re good governance. 
Delivery of project risk management training with all PMU 
colleagues (in a train the trainer format) so colleagues are 
delivering this as part of project kick‐offs to support a more 
risk focussed culture in the organisation. 
September 
2023 
Director of 
Finance and 
Resources 
This was completed on 12/10/2023. PMU staff received a ‘train 
the trainer’ session to enable them to cover running risk 
awareness sessions at project kick‐offs to support a more risk 
focussed culture in the organisation. 
Page 25 of 110

Page 30

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Undertaking a ‘health check’ of project management 
arrangements across the council to ensure governance, 
management, reporting and risk management is 
appropriate to the scale of the project. 
November
2023 
Director of 
Finance and 
Resources 
Compliance review of all PMU supported projects complete. All 
projects demonstrated a satisfactory level of risk governance and 
management. 
An update to the risk management course on iLearn and 
consideration of whether it should be a mandatory course. 
December
2023 
Director of 
Finance and 
Resources 
The course if now developed and ready to be launched to 
relevant staff on iLearn. 
In addition, face to face training of a new “Who’s risk is it 
anyway” half day course is also being delivered in February and 
May. 
Embed and deliver risk management training into the new 
leadership development programme that is currently under 
development, particularly in relation to commercial risk 
December
2023 
Director of 
Finance and 
Resources 
Session delivered 12 December 2023, and is included in the 
training programme for further cohorts. 
Reviewing governance documents to ensure delegations in 
relation to liability caps are clear and unambiguous. 
December
2023 
Director of 
Finance and 
Resources 
Consultation with Head of Corporate Governance concluded that 
governance documents do not require amendment, but rather, 
more training would be required on what was expected within 
existing delegations. The training was delivered to CMT on 28 
November 2023. Governance refresher training sessions have 
been delivered to every department senior management team in 
January. 
Deliver a targeted risk management development day for 
Chief Officers:‐ 
 Project risk management (and risk simulation exercise) 
 Risk horizon scanning and sustainability (the Global Risk 
Report) 
December
2023 
Director of 
Finance and 
Resources 
The training session has been prepared and was delivered to CMT 
on 28 November 2023. 
Page 26 of 110

Page 31

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
 Liability caps and their implications   
It is recognised that Dargavel Village has a significant 
amount of housing development yet to be delivered (circa 
2000 housing units over a 10 year period) and therefore 
many of the associated risk that existed at the beginning of 
the development continue to exist today albeit there is live 
data to inform future projections from the first circa 2,300 
units that have been delivered. Manage ongoing education 
demand risk relating to Dargavel through: 
The Council therefore continues to face risk and uncertainty 
in relation to accurately projecting the scale and timing of 
future education demand which will continue to have 
inherent uncertainty and risk. In recognition of this the 
Council will continue to progress the following actions to 
manage and mitigate this risk:‐ 
Securing robust long term demand projections which 
provide both a core projection, potential upper scenario 
and a long term view of the potential scale and timing of 
short term peak demand to inform decisions on capacity 
provision. 
September 
2023 
Director of 
Children’s 
Services 
Further updates will be completed in this respect for updated 
datasets available from November registration data and recently 
released NRS Census data. A full learning estate projection 
model has been delivered by Edge Analytics in August 2024. This 
will directly inform this action.   
Identify now a range of flexible options that are and will 
remain available to in future years to deliver, if required 
additional capacity (both temporary capacity and 
permanent long term capacity) to ensure the Council can be 
reassured of being able to respond appropriately to the 
potential for upper end demand scenarios and or 
temporary demand peaks to emerge. 
January 
2024 
Based on data and a range of scenarios, flexible additional 
capacity options have been outlined and shared with relevant 
boards. 
Page 27 of 110

Page 32

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Establish process and arrangements to support and provide 
detailed monitoring and updates to projections for updates 
to actual data sets to facilitate a continual re‐assessment of 
longer term trend and likely requirements / decision point 
required in relation to deployment of potential additional 
interventions. 
January 
2024 
A schedule is in place with timelines for detailed monitoring and 
updates to projections and actual data. This will ensure continual 
re‐assessment of long term trends and likely requirements / 
decision points required. 
Work has commenced to map out the next iteration of roll 
projection release for 2025 with Edge Analytics. This will inform 
what data sets are required and set a road map and responsibility 
matrix for who is accountable for obtaining and collating each 
data set or model input. This also requires input form the Head of 
Economy & Development to factor in the next iteration of the 
Housing Land Audit (HLA) to the projection model.  
 
Bowles Report Recommendation 7 
Whilst protecting the integrity of the planning process, the Council needs to ensure the appropriate involvement of members in such developments. 
Additional Council Motion 
Council agrees that in light of the Independent External Review of Dargavel that there is a requirement to convene a cross party body to discuss and review 
existing governance arrangements of Renfrewshire Council. 
Response Objectives 
Assess the extent to which major investment projects have provided sufficient engagement with elected members through both formal governance routes as 
well as through briefing sessions, engagement sessions, group presentations, site tours etc. Identify any adjustments or improvements required moving 
forward. 
Provide officer support to a cross party group to of elected members to agree the remit and progress a discussion and review of the Council’s formal 
governance arrangements in line with the motion approved. 
Carry out an assessment of the Audit Risk and Scrutiny Board against CIPFA’s published good practice guide for audit committees. 
Page 28 of 110

Page 33

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Undertake a health check assessment on major capital 
programmes to provide reassurance in respect to extent to 
which elected member involvement has been appropriately 
secured through formal governance reporting as well as via 
other appropriate informal engagement routes 
October 
2023 
Chief 
Executive 
supported by 
CMT 
City Deal and Infrastructure Health Check report was submitted 
to CMT on 21 November 2023. Other programmes to be reported 
to CMT through regular scheduled portfolio update sessions. 
Support Council Leader and other nominated elected 
members to determine a review remit, progress the review 
and develop suitable recommendations. 
March 2024  Head of 
Corporate 
Governance 
The Cross Party Working Group has been established and met 
five times. A report was submitted to the Council Meeting on 29 
February 2024 setting out the findings of the review. 
Carry out an assessment of the Audit Risk and Scrutiny 
Board against CIPFA’s published good practice guide for 
audit committees and identify any recommendations for 
change in remit or operational arrangements. 
December
2023 
Director of 
Finance and 
Resources 
The self assessment is complete with recommendations for 
improved clarity of roles and remits agreed by the ARSB, with 
formal final approval agreed by Council in May 2024.  
 
Bowles Report Recommendation 8 
Public confidence 
These recent events and the matters described in this report will dent public confidence in the Council. The Council should work in an open and transparent 
manner in the resolution of these issues and particularly with the residents of Dargavel, who have legitimate concerns about the implications for their children 
during both their primary and secondary education. 
Response Objectives 
The key aim has been to provide straightforward messaging and up to date sitreps to ensure publics (and council representatives) have the most up‐to‐date 
position and the complexity of the issue is explained in a simple and honest way and that parental/carer concerns in respect to the school and educational 
environment are able to be appropriately discussed through structured engagement arrangements with the parent councils with appropriate agreed actions 
taken forward. 
The strategy has been designed to: 
− Improve the flow and regularity of information to parents and carers and the wider Dargavel community, so they are first to hear about decisions 
impacting their community. 
− Ensure parents and carers have access to all projection data available to the council. 
Page 29 of 110

Page 34

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
− Introduce direct communication channels with Dargavel residents, enabling all sections of the community to engage on matters that are important to 
them and making sure the latest information is accessible and easy to find. 
− Provide residents with a feedback loop to enable them to ask questions of the council in relation to the development and have questions answered 
quickly. 
− Include the community in formal planning and design of a new primary school and high school extension. 
It is recognised that effective communication and engagement is important to building a new relationship between the Council and the Dargavel community, 
but ultimately it will take the delivery of the solution and investment in long term engagement to reduce local anxiety and fully rebuild trust and confidence in 
the Council. 
Develop communication plan to drive tactical engagement, 
ensuring the Dargavel community and specifically parents 
and carers kept updated on progress and the decisions 
being made by Council Boards. 
November
2022 
Head of 
Marketing 
and Comms 
The strategy has directed media and stakeholder engagement in 
relation to council decisions pertaining to Dargavel, the initial 
announcement and short‐term mitigation arrangements, and the 
publication of the Independent external review by David Bowles. 
The specific activities delivered include: 
 Arranging and hosting two parent and carer meetings, 
attended by council officers and more than 220 parents or 
carers. 
 Attending several parent council meetings with all primary 
schools and PMHS to support direct engagement, discussion 
on key activities, immediate estate decisions in respect to 
deployment of modular classrooms and post occupancy 
adjustments at Dargavel Primary, sharing and discussion of 
revised projection data and modelling, key council decision 
points, independent review outcomes. 
 Attending several community meetings from community 
council, Community Liaison Group as well as supporting 
coordination and delivery of wider community representative 
Page 30 of 110

Page 35

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
round table session to maintain ongoing engagement, 
sharing of information and data sharing. 
 Updating parents and carers at Dargavel Primary on progress 
and all reports to Council Boards and decision making in 
relation to immediate solutions to address capacity issues at 
Dargavel/ 
 Updating Bishopton Community Council on progress above. 
 Responding to media enquiries, requests for interview and 
ensuring the media were proactively updated on progress. 
 Ensuring the wider area stakeholders were kept up to date 
on progress – this includes community representatives, wider 
Parent Council groups and local and national politicians. 
 Maintaining updated information on the council website 
 Delivered a creative partnership with Glasgow School of Art 
and Dargavel Primary School to support pupils design the 
interiors of the new modular classroom block. 
Deliver a revised comms and engagement strategy to 
coincide with the return to school period along with timing 
of key milestone points in relation to post independent 
review and moving towards confirmation of progress with 
BAE systems and moving more significantly into a delivery 
phase. This will ensure long term engagement process 
continues to build pro‐active and positive engagement to 
continue to re‐establish trust and confidence across the 
Dargavel community. 
August 
2023 
Head of 
Marketing 
and Comms 
The Dargavel communication and engagement strategy was 
reviewed following the publication of the Bowles Report. The 
strategy covers the development of long‐term solutions to 
increase primary and secondary capacity. The key aim has been 
to provide straightforward messaging and up to date sitreps to 
ensure publics (and council representatives) have the most up‐to‐ 
date position and the complexity of the issue is explained in a 
simple and honest way. We committed from the outset to ensure 
those members of the community directly impacted (and their 
representatives) are first to hear about the steps being taken to 
deliver a solution and the decision‐making process involved. The 
strategy has been designed to: 
 Improve the flow and regularity of information to parents 
and carers and the wider Dargavel community, so they are 
Page 31 of 110

Page 36

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
first to hear about decisions impacting their community. 
Ensure parents and carers have access to all projection data 
available to the council. 
 Introduce direct communication channels with Dargavel 
residents, enabling all sections of the community to engage 
on matters that are important to them and making sure the 
latest information is accessible and easy to find. 
 Provide residents with a feedback loop to enable them to ask 
questions of the council in relation to the development and 
have questions answered quickly. 
 Include the community in formal planning and design of a 
new primary school and high school extension. 
Activity delivered from October 2022 to present includes: 
 Planned and hosted 2 public meetings 
 Monthly updates to the council website 
 13 update letters issued to parents and carers at 
Dargavel Primary School and shared with community 
stakeholders. 
 3 proactive media updates and the handing of almost 50 
media enquiries to ensure the council’s right of reply ‐ 
including arrangements for broadcast interviews. 
 Ongoing Elected Member briefings and MP/MSP 
briefings to ensure all political representatives are kept 
up to date on matters relating to the Dargavel 
Community. 
 Following publication of the Review, individual meetings 
took place with four local community representatives 
who were interviewed for the Review to include next 
steps. Ongoing engagement continues with two 
Page 32 of 110

Page 37

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
representatives to provide a sounding board for 
communication and engagement. 
 August 4, the council’s senior team attended a Round 
Table Meeting with Bishopton Community to discuss 
education provision and leisure and recreation provision. 
 From August, introduced a new opt‐in community 
newsletter, promoted locally to encourage resident sign 
up. 
 Established the Park Mains Liaison Group, attended by 
the Parent Council Chairs of all Park Mains catchment 
primary schools, to ensure we can collectively plan the 
high school extension and effectively engage with the 
wider school. 
 Space Planning Activity for Dargavel Primary School 
 Preparation of communications plan to encourage 
community engagement (those directly impacted and 
those affected) with the forthcoming statutory 
consultation, to be launched in January. 
Establish a new parent council liaison group to provide a 
single PC forum (at the request of PC chairs) to provide a 
streamlined opportunity for consistent engagement and 
communication with the whole PC community for all 
schools associated with Dargavel / Bishopton and PMHS and 
all feeder primaries. 
August 
2023 
Head of 
Education 
Group has been established and has met following school 
summer 2023 break with positive feedback from Parent Council 
Chairs with engagement to date. 
Establish regular opt‐in digital community newsletter to 
facilitate regular communication updates direct to 
interested members of the community. 
August 
2023 
Head of 
Marketing 
and Comms 
Take up of opt‐in digital channel newsletter is currently sitting at 
over 500 and it is expected that this will continue to grow in the 
coming months. 
Page 33 of 110

Page 38

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
ACCOUNTS COMMISSION SECTION 102 REPORT – FINDINGS & COUNCIL RESPONSE/UPDATE
Community and Other Engagement 
The  council  must,  as  a  matter  of  urgency,  conduct  a 
robust and transparent assessment of the effectiveness of 
its  community  engagement  and  then  move  swiftly  to 
implement any improvements needed. 
February 2024  Head of 
Communications 
and Marketing 
Please see response to Bowles report recommendation 8 above 
 
The Commission is particularly concerned by the council’s 
failure both to transparently consider alternative options 
in relation to expanding secondary school capacity in the 
area, and to consult or engage appropriately with the 
community, whom their decision directly affects. 
This 
engagement 
activity will 
remain 
ongoing as 
part of the 
PMHS 
extension 
project 
through to 
August 2027 
and beyond 
recognising 
the long‐term 
monitoring 
of school roll 
projections at 
the high 
school. 
Director of 
Children’s 
Services 
It is accepted that the report to the Education and Children’s 
Services Policy Board in May 2023 could have articulated the 
reasons  why  no  other  options  to  address  secondary  school 
capacity beyond an extension to Park Mains High School were 
deemed viable for detailed consideration. 
Additionally,  although  engagement  in  relation  to  updated 
school projections and developing plans for a larger extension 
to PMHS were shared and discussed with the PMHS parent 
council  prior  to  the  May  report,  plans  to  expand  this 
engagement process to a wider group to encapsulate all feeder 
primaries following the board meeting could have been outlined 
in the report and or considered earlier in the process. 
Council officers have since May 2023 been progressing positive 
and ongoing community engagement in relation to the Park 
Mains  extension,  principally  through  the  Park  Mains  Liaison 
Group which was established to provide a single engagement 
forum with representatives from the Parent Councils of Park 
Mains High School and all associated feeder primaries. 
August 2024  
This engagement process has shared and explained detailed 
pupil projection data, the underlying rationale for the proposed 
extension  decision  as  well  as  listening  and  responding  to 
Page 34 of 110

Page 39

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
concerns and or requests for further information from the wider 
parent and  carer community.  This included sharing detailed 
information  on  an  option  promoted  by  some  community 
representative  from  Dargavel  and  Bishopton  for  a  new 
secondary  school  for  Dargavel,  Bishopton  and  Langbank.  As 
reported through the Education and Children’s Services Policy 
Board in August 2023, such an option had significant negative 
implications from a financial, educational, value for money and 
school estate perspective that discounted it as a credible option 
for detailed consideration. 
The Park Mains Liaison Group is proving to be a highly valuable 
engagement forum, providing a single route of engagement 
across the wider community as well as a key route to assist the 
Council  to  disseminate  consistent  key  messages  and 
information  updates  across  communities  through  trusted 
Parent  Council  communication  channels.  This  engagement 
approach  will  inform  how  non  statutory  and  informal 
engagement in relation to potential school estate changes and 
long‐term strategic learning estate work may be taken forward 
in the future by the Council. 
Additionally,  high  levels  of  positive  engagement  are  being 
secured  as  part  of  the  space  planning  process  for  the  new 
extension, supporting active parental and carer participation 
and influence in the design process of the new extension and 
wider changes to the school that are planned to be delivered. 
This is increasingly building a positive community commitment 
and level of direct participation in the delivery of the school 
extension and improvement project. 
Page 35 of 110

Page 40

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Director of 
Children’s 
Services 
The review of the Council’s engagement strategy as referred to 
above will include a qualitative assessment of the effectiveness 
of the Park Mains Liaison Group. 
Lastly, work is being progressed by officers to research how 
other  councils  have  approached  school  extension  projects, 
where a statutory consultation process is not required. The 
objective of this work is to inform the design of a framework to 
inform any future approach to early informal engagement that 
can  be  adopted  by  the  Council  in  relation  to  school  estate 
considerations or changes. 
Desk top work completed to date has identified a mixed picture 
with several councils having adopted a similar approach to that 
employed by the Council for the PMHS extension. However, 
there  are  some  examples  of  the  use  of  published  options 
appraisals as part of Council reports and identified examples of 
planned informal engagement strategies deployed as part of 
long‐term strategic school estate planning which provide some 
good practice approaches for reference. 
These individual elements of good practice that are evident 
across other councils can be collectively brought together and 
used  to  inform  and  guide  the  development  of  a  proposed 
framework for use by the Council in its future learning estate 
strategy (where appropriate this will pay due regard to the 
Scottish Government guidance on informal engagement that 
may occur prior to a statutory consultation process). 
In completing this work consideration will be given to sharing 
the output across the local authority sector given what appears 
Page 36 of 110

Page 41

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
to be a level of mixed and inconsistent approaches deployed 
across the country. 
We note that the new primary school is subject to a full 
public consultation. 
We expect the council to engage meaningfully with the 
community  on  this  issue,  and  other  decisions  on  the 
school estate. 
Again, we ask that the Controller monitors this situation, 
and reports to us in June 2024 on progress and earlier if 
necessary. 
Consultation 
process has 
completed as 
reported to 
the Education 
and Children’s 
Services Policy 
Board in May 
2024 
Director of 
Children’s 
Services 
The Education and Children’s Services Policy board approved 
the planned consultation programme in January with a report 
on the outcome of the consultation planned to be brought back 
to Policy Board in May. 
A  full  programme  of  planned  consultation  and  engagement 
activity has been developed with input from the Institute of 
Consultation  to  bring  to  the  design  process  experience  of 
recognised best practice deployed across the UK. 
Full details of the planned consultation process and activity will 
be provided to the external auditors as well as the opportunity 
to observe any of the planned information events and or formal 
consultation meetings. 
The  consultation  has  now  been  completed  with  817 
respondents  to  the  online  questionnaire  and  a  further  150 
attending the events which were held: 
6 informal drop in sessions 
4 Information exchanges 
2 public meetings 
Meetings with Parent Councils of both primary schools 
Meetings with staff and children from both primary schools. 
Education Scotland also engaged with the community and 
produced their report of their findings. 
A final consultation report has been finalised and presented to 
the Policy Board in May 2024 with approval granted to 
construct a new primary school on the recommended location. 
Page 37 of 110

Page 42

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Learning Lessons and Building Capacity 
While the council’s initial response to the Bowles report 
was high level, we are assured by the Controller that its 
action plan in response is now sufficiently detailed and 
includes SMART objectives 
It will be important that this action plan is well‐managed 
by  senior  officers  and  closely  scrutinised  by  elected 
members of the council. 
Complete  Director of 
Finance and 
Resources 
This action plan and subsequent action plan relating to the s102 
report are closely monitored and reported to each cycle of the 
Audit, Risk & Scrutiny Board. 
However, there are still significant uncertainties relating 
to 
 the capacity needed in the long term, and 
 to the completion of the two building projects – 
the new primary school and the secondary school 
extension. 
We  therefore  request  that  these  matters  are  closely 
monitored in the annual audit work, and the Controller 
uses her powers to report any slippage or other issues to 
us if necessary. 
March 2024  Director of 
Children’s 
Services 
Managing the Risk of Future Capacity Uncertainty 
The inherent uncertainty in relation to long term (15 year) pupil 
growth projections has been widely reported by the Council 
over the past year as an ongoing risk through both formal board 
reports,  as  well  as  engagement  and  communications  with 
communities and in sharing data and reports with the external 
auditors. This is particularly recognised by the Council in the 
context of Dargavel Village having approximately 10 years of 
development still to deliver before achieving completion. It has 
also been trailed that the Council’s projection work to date with 
Edge  Analytics  has  identified  an  expectation  of  a  peak  in 
demand to be reached which will then fall to a stabilised long‐ 
term level of demand – a similar pattern of demand growth has 
been  evidenced  across  other  similar  long  term  community 
growth areas in the UK. 
The Council will regularly monitor actual pupil numbers and 
update long term projections on a regular basis over coming 
years as a key response to being able to pro‐actively manage 
this risk moving forward. 
Page 38 of 110

Page 43

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
This monitoring process will be key to assess the extent to which 
actual  demand  and  revised  projections  is  or  is  not  tracking 
against the current projections that have informed the planned 
capacity levels that will be delivered by the current learning 
estate interventions and provide early indication of any risk of 
material  deviation.  The  planned  annual  monitoring  and 
updating approach that will be deployed over coming years will 
be shared with the External Auditors as required. 
Long  term  projection  work  completed  to  date  has  already 
modelled a range of potential demand scenarios for the primary 
sector and identified an expected peak of demand in 2033/34. 
Options that can be considered for deployment in future years 
to  manage  upper  demand  scenarios  that  would  exceed  the 
planned capacity being delivered for primary sector education 
within  Dargavel  village,  have  already  been  identified  and 
reported through the Education and Children’s Services Policy 
Board  in  November  2023  and  shared  with  community 
representatives. 
Should the monitoring arrangements over the coming years 
highlight projection of sustained demand trending towards the 
upper demand scenarios, an appraisal will be required to assess 
which of the options is most appropriate for consideration to be 
deployed to meet the scale and nature of the additional future 
demand. This process will include early community engagement 
with school communities and will require timely assessment 
and associated decision making to allow planned delivery of any 
additional intervention well ahead of the developing need. 
In  relation  to  the  secondary  sector,  the  impact  of  higher 
demand scenarios will take longer to emerge (mid to late 2030s) 
and similarly it has been well trailed in Council reports and with 
Page 39 of 110

Page 44

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
the  community  that  long  term  monitoring  and  projection 
modelling  may  identify  the  need  to  consider  options  at  an 
appropriate  future  point  in  time  in  respect  to  any  further 
intervention and or decisions in relation to secondary sector 
provision across West Renfrewshire. 
Similarly, the long‐term monitoring arrangements will facilitate 
early  identification  of  such  risks  and  will  support  early 
engagement  with  the  appropriate  primary  and  secondary 
schools  that  may  be  impacted  by  any  future  school  estate 
changes. 
Delivery of New School Facilities 
It has been recognised by the Council that as a result of the very 
late identification of the significant under‐capacity problems 
within both the primary and secondary sectors serving Dargavel, 
the Council has since late 2023 been operating within a highly 
compressed non‐typical timeline to undertake all the associated 
capacity  planning,  land  assembly,  community  engagement, 
statutory  consultation,  space  planning,  procurement 
arrangements before moving into project delivery in order to 
achieve  operational  delivery  of  the  new  facilities  by  August 
2027. 
In broad terms, the Council is seeking to achieve all that is 
associated with the long‐term strategic planning, engagement, 
consultation and operational delivery of a new school and major 
extension of a secondary school in a 4 ½ year period, when such 
an end‐to‐end process would normally run over a much longer 
period – a timeline of around 6‐8 year would not be an untypical 
Page 40 of 110

Page 45

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
period  of  timeframe.  Consequently,  the  Council  is  parallel 
running several activities that would in most circumstances be 
delivered in a broadly consecutive manner. 
The  Council  has  established  governance,  programming,  and 
resource arrangements in place to support the delivery of the 
new primary school and secondary school extension over the 
remaining 3 ½ year period through to the operational target 
date of August 2027. 
To date the external auditors have not undertaken any detailed 
scrutiny  of  the  delivery  programme  or  the  arrangements  in 
place. To provide assurance officers will provide a full overview 
of the current arrangements for the external auditors for their 
review and will support whatever audit work is required to allow 
them to assess the Council’s current approach. 
Impact on Service Provision 
We note that the council has assessed that currently there 
has been no detriment to either teaching delivery or pupil 
education in the Dargavel and Bishopton areas from the 
interim measures introduced. 
We consider it critical that the council reports the results 
of  these  assessments  publicly,  regularly  and  in  an 
accessible  way,  to  maintain  and  rebuild  community 
confidence. 
Ongoing as 
part of the 
Service’s 
Quality 
Assurance 
Framework 
Ongoing and 
will be 
incorporated 
into parent 
and school 
Director of 
Children’s 
Services 
Head of 
Marketing and 
Communications 
Renfrewshire Council has a robust Quality Assurance framework 
involving regular meetings with Education Managers and school 
staff and planned school visits which focus in on the national 
quality assurance indicators (reviews). 
DPS had a visit in January as part of this process where key 
strengths under the national Quality Assurance indicators from 
How Good is Our School were evaluated, self‐improvement and 
self‐evaluation and Learning, Teaching and Assessment and a 
report was produced. In addition, Bishopton Primary School and 
Park Mains High School were both recently inspected by HMI, 
receiving very positive reports. 
Page 41 of 110

Page 46

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
newsletters at 
appropriate 
points. 
Further, every school submits a school improvement plan and a 
school improvement report (published on website) and their 
evaluations under the 4 key Quality Indicators (QIs) of their 
performance, based on data gathered through self‐evaluation, 
HMI visits, internal visits and stakeholder input is submitted to 
Children’s Services in April. 
These  are  shared  with  the  parent  councils  and  will  also  be 
published on the school website as part of the self‐evaluation 
process. This is in line with Education Scotland guidelines, the 
National Improvement Framework and statutory requirements. 
This communication with parents will be an ongoing process. 
The Commission is also concerned at the possible wider 
impacts of the council’s failings regarding the estimation 
of pupil numbers and whether this has had any impact on 
services provided by the council in the Dargavel area. 
We request that the Controller seeks further information 
on these issues so that we can understand the work that 
the council has done to understand these impacts. 
In line with 
requests 
emerging 
from defined 
audit 
programme to 
be set by 
Azets 
Chief Executive  Full details of all the additional areas of potential service 
impact (noted below) considered by the Council have been 
shared and discussed in detail with the External Auditor to 
support the Controller of Audit’s follow‐up report to the 
Accounts Commission. 
Support to Schools 
Early Learning & Childcare Provision 
Children’s social Care support 
NHS Service Provision & facilities 
Community Leisure & Recreation within wider Masterplan 
Transport & Active Travel Infrastructure Provision 
Public Bus Transport Provision 
Page 42 of 110

Page 47

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
Financial Management and Consequences 
The financial impact of these failings on the council is 
significant. The council capped the risk and contributions 
from BAE Systems under the Section 75 agreement, and 
as a direct result faces estimated net additional capital 
costs of £60 million, to be met by borrowing. This is a 
substantial sum of public money. The council needs to 
clarify the opportunity costs of this in terms of its overall 
capital programme. The council projects that it will have 
a revenue budget deficit of up to £50 million by 2026/27 
and will need to make difficult decisions on prioritising its 
spending, compounded by the financial consequences of 
this issue 
The council has recently negotiated a transfer of land 
from BAE for the construction of a new primary school. 
The Controller’s report indicates that this was in exchange 
for amendments to the extent and composition of the 
housing units for which planning permission has been 
granted. 
Given the reported determination of BAE to fully protect 
their commercial interests in the development, and the 
absence of alternative solutions for the council, it will be 
important to ensure and demonstrate that this exchange 
represents Best Value for the public purse. 
Ongoing 
March 2024 
Director of 
Finance and 
Resources 
Head of 
Economy and 
Development 
The Council will be required to manage the financial impact of 
the unplanned  delivery  of a new primary school and larger 
extension at PMHS through the delivery of its wider financial 
strategy  and  any  opportunity  costs  articulated  as  part  of 
developing and delivering that strategy. Regular reports with 
regards  the  Council’s  financial  position  and  outlook  are 
provided to Council, which include the financial consequences 
of the Dargavel failings. The next report to Council updating the 
financial outlook will be in September 2024. 
The financial and wider factors considered by officers as part 
of the negotiation process with BAE systems to secure the 
associated  land  agreement  and  adjustments  to  the  S.75 
agreement have been shared with the external auditors.  
Council Leadership, Governance, and Culture 
The  council’s  action  plan  will  be  hugely  important  in 
further  embedding  improvements  in  this  area.  In 
particular, the following elements must be progressed 
urgently and transparently: 
February 2024 
and ongoing 
in relation to 
the outcomes 
Director of 
Finance and 
Resources 
This report and combined action plan provides the Audit, Risk & 
Scrutiny  Board  with  an  overarching  view  of  all  progress 
associated with the Dargavel issue, subsequent investigations, 
reviews and agreed actions. 
Page 43 of 110

Page 48

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
• the council’s review of its scrutiny arrangements against 
CIPFA good practice guidelines 
• the council’s review of its approach to risk management 
• the council’s leadership development programme for 
officers. 
To be satisfied of progress in these areas, the Commission 
requires  the  Controller  to  request  further  information 
from the council on the scope and timing of these actions, 
and  report  back  to  the  Commission  in  the  update 
requested for June 2024, or earlier if she thinks necessary. 
We also expect these issues to be covered in the 
accelerated Best Value report. 
associated 
with each 
action. 
The Commission is also concerned about the culture of 
the council and whether it has truly learned the lessons it 
needs to. 
We expect organisational culture to be an area of focus in 
the accelerated Best Value report. 
In particular, we request an update on whether the 
 culture of the organisation is appropriately open 
and transparent, 
 encourages continuous improvement, 
December 
2024 (ie the 
confirmed 
timescale for 
BV audit work 
to conclude) 
Chief Executive  The  Council’s  auditors  concluded  that  the  Council  has 
appropriate  governance  arrangements  in  place  with 
improvements  over  the  years  in  member  and  officer 
relationships and effective leadership overall and were satisfied 
through  their  detailed  audit  work  that  the  Council  had 
demonstrated that the governance failings identified by the 
Bowles report were limited to the historic handling of Dargavel. 
The  auditors  did  not  highlight  any  concerns  over  the  wider 
organisational  culture  in  the  Council  or  in  its  approach  to 
managing major capital programmes but did identify that the 
role of the Audit, Risk and Scrutiny Board in ensuring effective 
scrutiny is not sufficiently clear.  The Council has recognised this 
and has completed a review of the Audit,  Risk  and  Scrutiny 
Board  governance  and  operating  arrangements,  with 
recommended  changes  being  agreed  by  the  Board  and 
subsequently by full Council.  
 
Page 44 of 110

Page 49

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
 effective  joint  working  between  officers  and 
members,  effective  scrutiny  and  challenge 
(especially by elected members), and 
 engagement and discussion with stakeholders. 
In addition, we request an assessment of 
 whether it has the right skills in the right places to 
deliver on its responsibilities, and 
 whether issues are escalated to the right level. 
Despite the finding of the Council’s auditors, the Commission 
has expressed concern in relation to the Council’s culture and 
have sought further assurances in relation to a wide range of 
organisational issues. 
It has been confirmed that consideration and assessment of 
such  issues  will  form  part  of  the  planned  Best  Value  Audit 
process and subject to confirmation of the planned detailed 
best value audit programme. 
Council  officers  will  provide  all  the  necessary  support, 
assistance,  and  information  to  allow  the  audit  team  to 
appropriately assess all key areas of interest and are actively 
progressing an internal self‐assessment and evidence process to 
support this element of the audit engagement in due course 
over the anticipated 2024 audit programme. 
Finally,  the  Commission  notes  that  the  auditor  has 
concluded  that  the  council  has  obtained  appropriate 
external legal advice and determined there is no potential 
for any form of action against former senior employees 
involved in the Dargavel School decision‐making. 
In addition, no disciplinary action has been taken against 
any senior officer involved in decision‐making relevant to 
the Section 75 approval process for the Dargavel Village 
development. 
The  Commission  accepts  that  these  are  management 
issues. 
March 2024  Head of 
Corporate 
Governance 
No senior officers involved in the Dargavel S.75 decision making 
process and identified in the Bowles Report remain employed 
by the Council or remained employed at the time of the Bowles 
report publication. In this context no senior officer could be 
subject to any form of internal Council disciplinary investigation 
or action. 
Full details of the process of consideration and legal advice that 
was sought regard to any other form of external legal action has 
been shared with the local external audit team as requested by 
the Commission. 
Page 45 of 110

Page 50

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
However, we request that the Controller asks the council 
for further information on the process followed and 
factors taken into account by the council in considering 
disciplinary action against staff involved. 
In addition, and looking forward, the Commission asks for 
information on 
 the council’s approach to performance 
management and 
March 2024  Head of HR & 
OD 
A full package of information in relation to current HR policies 
and procedures and future planned revisions has been 
provided to the external auditor. 
 
In June 2024, the Council in consultation with key 
stakeholders and trade unions revised both its people, 
performance and talent policy and discipline policy.   
Additional guidance and training is currently being developed 
for managers and employees, with an expected role out in 
the Autumn 2024. 
 its current policy on disciplinary action,   
so we can be assured that appropriate arrangements are 
in place to ensure that staff have the necessary skills and 
that  senior  officers  are  properly  accountable  for  their 
areas of responsibility. 
Page 46 of 110

Page 51

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
CROSS PARTY WORKING GROUP AGREED ACTIONS
Refresher training for management teams across all of the 
Council’s  directorates  on  the  operation  of  delegated 
authority should be implemented. 
April 2024  Head of 
Corporate 
Governance 
and 
Chief Auditor 
Training was delivered to all directorates by the Head of 
Corporate Governance and the Council’s Chief Auditor in 
January 2024 to Chief Officers and tier 3 managers. A further 
“catch up” session was held on 23 April 2024. 
Refresher training for management teams across all of the   
Council’s directorates on the operation of the Protocol for   
Relationships between Political Groups, Elected Members   
and Officers should be implemented.   
That the Bulletin be issued with the minutes of each Council 
and board meeting for the meetings of Full Council. 
May 2024  Head of 
Corporate 
Governance 
The Bulletin is now issued with the minutes pack at each Full 
Council Meeting commencing with the meeting of 9 May 2024. 
All major projects and programmes will report to the 
appropriate board at least twice a year. 
Any such reports will include a note of all project groups 
involved. 
May 2024  Chief Executive  Update reports on City Deal Projects and cultural Infrastructure 
programmes have gone to boards in December and February 
respectively as part of twice yearly reporting cycles. Housing 
investment programme update provided as part of update 
report at each cycle with an additional full update provided in 
august of each year. 
The content of the Protocol for Relationships between 
Political Groups, Elected Members and Officers be refreshed. 
February 
2024 
Head of 
Corporate 
Governance 
The Revised Protocol was approved at the Council Meeting of 29 
February 2024 
A health check of all major projects will be completed and 
reported through the Audit, Risk and Scrutiny Board 
March 
2024 
Chief 
Executive 
This has separately been reported to the ARS Board as part of the 
independent review action plan 
A  structure  chart  for  all  Council  directorates  should  be 
prepared and circulated to all Elected Members. This should 
be regularly updated and recirculated as necessary. 
March 
2024 
Chief 
Executive 
The structure chart was circulated to all Elected Members, and 
the first updated version was issued in March 
That a Chief Planning Officer report brought to the Planning 
and Climate Change Policy Board at least twice a year advising 
on the position in respect of s75 Agreements. Planning 
applications, or where officers cannot not reach agreement 
May 2024  Head of 
Economy and 
Development 
Arrangements have been put in place by officers for this bi‐ 
annual reporting 
Page 47 of 110

Page 52

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
on substantive matters in a specific s75 Agreement 
negotiation will also be brought back to the Board for further 
consideration. 
The outcome of the management training programme will 
be reported to the Audit, Risk and Scrutiny Board 
Sept 
2024 
Director of 
Finance and 
Resources 
and Head of 
HR & OD 
The first cohort of the programme has concluded the programme, 
with  feedback  from  this  first  round  being  used  to  inform  the 
delivery of the programme to the next cohorts of senior staff. 
Delivery of the programme will continue over the course of 2024.  
UPDATE ‐ Delegate and facilitator feedback on the first cohort has 
been presented to the Council’s Corporate Management Team for 
noting, along with proposed changes arising from feedback for the 
next scheduled cohorts of senior managers.    
 
The modules covered in the programme are: 
 
 Introduction to Personal Resilience; 
 Module 1 ‐ Effective Communication and Officer/Member 
Relationships; 
 Module 2 ‐ Governance, Risk and Financial Accountability; 
 Module 3 ‐ Managing Projects and Managing Change; 
 Module 4 ‐ Transformational Leadership 
 Module 5 ‐ Values, Vision and Planning for the Future 
 
Generally the feedback from cohort one (Chief Officer cohort) 
indicated a high level of satisfaction with the programme overall. 
Collaboration with other colleagues during the programme 
featured strongly with learning through shared experiences.
There was positive feedback around learning from colleagues, 
strengthening networks across services and shared experiences, 
which will create consistent approaches around best practice. 
Some feedback was received around the content being more 
‘Renfrewshire’ specific, including organisational challenges and 
use of case studies. Increased use of local examples and practical 
application is being incorporated into the programme for cohorts 
2 and 3.  A facilitated event for Chief Officers is scheduled for the 
end of September 2024.  This will be an opportunity to discuss 
and agree how this cohort of Chief Officers continues its learning 
journey, sharing their learning and practical experience to have a 
Page 48 of 110

Page 53

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – September  2024 
positive impact back at the workplace following the successful 
completion of the leadership development programme earlier 
this year.    
 
 
Page 49 of 110

Page 54

Page 50 of 110

Page 55

___________________________________________________________________
To:  Audit, Risk & Scrutiny Board
On:  23 September 2024
___________________________________________________________________
Report by: Director of Finance & Resources
___________________________________________________________________
Heading: Best Value thematic work – Workforce innovation
___________________________________________________________________
1. Summary 
1.1 The Accounts Commission’s Strategy (2021-26) sets out its priorities to
focus on inequalities, funding, communities and recovery.  The Code of
Audit practice sets out the Best Value work required to report on these
priorities.  The Accounts Commission’s approach to Best Value
involves reporting on individual local government bodies and
thematically across the local government sector through performance
reports. 
1.2 The Accounts Commission reports nationally on thematic aspects of
local government bodies’ approaches to, and performance in, meeting
their Best Value and community planning duties.  Local government
appointed auditors report locally on any such Best Value thematic work
prescribed by the Accounts Commission. 
1.3 The Commission has directed auditors to report on workforce
innovation and how councils are responding to workforce challenges. 
In carrying out the work auditors have considered the following
questions: 
 How effectively are the council’s workforce plans integrated with
its strategic plans and priorities? 
Item 2
Page 51 of 110

Page 56

 How effectively has digital technology been used to support
workforce productivity and improve service quality and
outcomes?
 How effectively is the council using hybrid and remote working
and other innovative working practice such as a four-day week
to achieve service and staff benefits?
 What innovative practice is the council using to develop its
future workforce capacity and skills needs and manage staff
reductions in line with its priorities?
 What progress has the council made with sharing roles or
functions across its services and/or with other councils and
partners?  
 How effectively is the council measuring the impact of its
workforce planning approach? 
1.4 The report attached at Appendix 1 outlines the external auditors’
(Azets) findings in relation to the above questions within Renfrewshire
Council. The report outlines key messages, detailed findings and
suggested areas for improvement. The report also includes an
indication of planned management actions in response to the
recommendations made by Azets.
___________________________________________________________________ 
2. Recommendations
It is recommended that the Board: 
2.1 Note the report from the Council’s external auditor in relation to
workforce innovation and agree the accompanying action plan.
___________________________________________________________________
Implications of the Report
1. Financial – none   
2. HR & Organisational Development – as outlined in the report. 
3. Community/Council Planning –   
Working together to improve outcomes – the report outlines several
examples of how the Council works in partnership with other
stakeholders to ensure the workforce is supported and developed to
remain healthy, well trained and able to deliver quality Council services. 
Page 52 of 110

Page 57

4. Legal – none 
5. Property/Assets – none. 
6. Information Technology - none. 
7. Equality & Human Rights - the recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified. 
8. Health & Safety - none
9. Procurement – none
10. Risk - none
11. Privacy Impact - none 
12. Climate Risk – not applicable
13. Children’s Rights – none
14. Cosla Policy Position – not applicable 
___________________________________________________________________ 
Author:           Raymond Cree, Head of People and OD 
Page 53 of 110

Page 58

Renfrewshire Council
Workforce Innovation – how councils are
responding to workforce challenges
Best Value thematic work in councils 2023-24 
September 2024
Page 54 of 110

Page 59

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
2
Table of Contents
Key messages 3
Scope of the audit 9
Workforce strategy and priorities 11
Digital technology and the workforce 14
Flexible working and other innovative staff deployment 21
Developing future skills and capacity 24
Joint workforce arrangements across services and partners 28
Measuring the impact of workforce planning 33
Appendix 1- Improvement Action Plan 35
Page 55 of 110

Page 60

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
3
Key messages
How effectively are the
council’s workforce plans
integrated with its
strategic plans and
priorities?
Auditor judgement
Effective and appropriate arrangements
are in place 
Renfrewshire Council has a comprehensive high level
workforce strategy and People Strategy supported by
a number of other high level policies and strategies.
The Council adopted a flexible approach to its
strategy, by setting up clear priorities for the first two
years and by delegating the responsibility and
ownership for workforce management to the individual
Services to better meet their needs. Therefore, the
workforce risk assessment, operational priorities and
implementation, and monitoring are done at service
level though Service Improvement Plans.
How effectively has digital
technology been used to
support workforce
productivity and improve
service quality and
outcomes?
Auditor judgement
Risks exist to the achievement of
operational objectives 
Appropriate arrangements are in place to enable the
delivery of the Council’s digital strategy. The Council
implemented a number of automatic processes to
drive efficiency and innovation in its workforce. A key
challenge for the Council is the creation of capacity
within its workforce to enable the review, exploration
and development of digital opportunities.  
The Council offers a variety of digital training to its
workforce. It also acknowledges that a more recent
digital skills assessment is required to better
understand any skill gaps.
The Council actively engages with its communities to
deliver services in more innovative way to tackle
digital exclusion. The Council’s work has been
recognised as best practice example in Accounts
Commission report on digital exclusion. There is
Page 56 of 110

Page 61

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
4
awareness of the need, and drive for continuous
improvement in this area.
Page 57 of 110

Page 62

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
5
How effectively is the
council using hybrid and
remote working and other
innovative working
practice such as a four-
day week to achieve
service and staff benefits?
Auditor judgement
Risks exist to the achievement of
operational objectives 
The Council continuously reviews its approach to
flexible working and provides staff with support and
guidance.
Staff feedback is obtained in variety of ways and
considers impact of flexible working on staff wellbeing.
The Council considers staff benefits and wider
sociological changes when considering new ways of
working.  Evidence of measurable efficiencies tracking
has been limited and the Council has not been able to
demonstrate efficiencies from flexible working
through, for example, an impact on productivity. 
Page 58 of 110

Page 63

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
6
What innovative practice
is the council using to
develop its future
workforce capacity and
skills needs and manage
staff reductions in line
with its priorities?
Auditor judgement
Risks exist to the achievement of
operational objectives 
The Council makes good use of its existing workforce
and is developing the skills needed to deliver future
services.
The Council engages with the local education
providers to develop and support its workforce skills.
The Council has to yet develop comprehensive
measurable performance indicators to demonstrate
the benefits it provides through its work on developing
workforce skills and capacity. 
What progress has the
council made with sharing
roles or functions across
its services and/or with
other councils and
partners?  
Auditor judgement
Effective and appropriate arrangements
are in place 
The Council works collaboratively with its partners
and continues to explore opportunities for working
together.  Through collaborative working, the Council
shares knowledge and learns from partners, leading
to enhanced service delivery and outcomes.  
An example of a partnership working is where the
Council works in collaboration with Inverclyde Council,
East Renfrewshire Council, and West Dunbartonshire
Council to deliver a civil contingencies service which
supports business continuity and emergency planning
across these Council areas. 
Page 59 of 110

Page 64

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
7
How effectively is the
council measuring the
impact of its workforce
planning approach?
Auditor judgement
Risks exist to the achievement of operational
objectives
The Council’s monitoring of progress in implementing
its Workforce People Strategy could be improved in
terms of its clarity over the status of individual
objectives and the wider use of measurable
performance indicators.
Reporting in Service Improvement Plans currently
provides limited information on progress against
People Strategy objectives.
Benefits tracking of the Council’s workforce approach
is done only at a high level. 
Page 60 of 110

Page 65

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
8
Definition
We use the following gradings to provide an overall assessment of the arrangements
in place as they relate to best value.  The text provides a guide to the key criteria we
use in the assessment, although not all of the criteria may exist in every case. 
There is a fundamental absence or failure of arrangements
There is no evidence to support necessary improvement
Substantial unmitigated risks affect achievement of corporate
objectives.
Arrangements are inadequate or ineffective
Pace and depth of improvement is slow / needs to be
extended further
Significant unmitigated risks affect achievement of
corporate objectives
No major weaknesses in arrangements but scope for
improvement exists
Pace and depth of improvement are adequate
Risks exist to the achievement of operational objectives
Effective and appropriate arrangements are in place
Pace and depth of improvement are effective
Risks to the achievement of objectives are managed
Page 61 of 110

Page 66

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
9
Scope of the audit
The Audit Scotland 2023 Local Government Overview (LGO) Report notes that
councils have never faced such a challenging situation.  Service demands have
increased after the Covid-19 pandemic and funding is forecast to reduce in real
terms.  Workforce pressures including recruitment in a competitive labour market,
employee retention and high sickness absence levels are putting councils under
continued cost and resource pressure.  
This report sets out how the council is responding to current workforce challenges
through building capacity and increasing productivity and innovation.
The Accounts Commission’s Strategy (2021-26) sets out its priorities to focus on
inequalities, funding, communities and recovery.  The Code of Audit practice sets out
the Best Value work required to report on these priorities.  
Code of Audit Practice 2020 Best Value reporting requirements
Best Value reporting – extract from the Code
The Accounts Commission’s approach to Best Value involves reporting on
individual local government bodies and thematically across the local government
sector through performance reports:
• As part of their integrated wider-scope annual audit work appointed
auditors use a risk-based approach to assess and report whether the
audited body has made proper arrangements for securing Best Value
and is complying with its community planning duties, including
reporting progress against previous Best Value findings and
recommendations.
• The Accounts Commission also requires the Controller of Audit to
report to the Accounts Commission on each council or Integration
Joint Board (IJB) at least once over the five-year audit appointment
on the body’s performance on its Best Value duty.  This enables the
Accounts Commission to make findings for improvement where
appropriate.
• The Accounts Commission reports nationally on thematic aspects of
local government bodies’ approaches to, and performance in,
meeting their Best Value and community planning duties.  Local
government appointed auditors report locally on any such Best Value
thematic work prescribed by the Accounts Commission. 
Page 62 of 110

Page 67

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
10
This report covers the thematic aspect of our Best Value audit requirements in
relation to workforce.  The Commission has directed auditors to report on workforce
innovation and how councils are responding to workforce challenges.  In carrying out
the work auditors have considered the following questions: 
• How effectively are the council’s workforce plans integrated with its
strategic plans and priorities? 
• How effectively has digital technology been used to support workforce
productivity and improve service quality and outcomes?
• How effectively is the council using hybrid and remote working and
other innovative working practice such as a four-day week to achieve
service and staff benefits?
• What innovative practice is the council using to develop its future
workforce capacity and skills needs and manage staff reductions in line
with its priorities?
• What progress has the council made with sharing roles or functions
across its services and/or with other councils and partners?  
• How effectively is the council measuring the impact of its workforce
planning approach? 
An improvement action plan is included at Appendix 1 of this report.  This sets out
audit recommendations in key areas, and the Council’s planned response including
responsible officers and dates for implementation.
The coverage of the work is in line with the expectations for council’s arrangements
for the seven Best Value themes in the Local Government in Scotland Act 2003,
Best Value Statutory Guidance 2020.   
Page 63 of 110

Page 68

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
11
Workforce strategy and
priorities
Workforce planning involves identifying and addressing future capacity and skills
gaps, at operational and leadership levels.  It requires strategic thinking,
comprehensive workforce data and ongoing consultation and engagement with staff
and trades unions.
A council focused on achieving Best Value will have a workforce strategy that sets
out expectations on how the local authority’s staff will deliver its vision, priorities and
values.
To be effective, workforce planning must be integrated across the organisation. 
Workforce strategies need to support the council in achieving its strategic priorities. 
They must support other key plans including financial, asset, digital and
transformation planning.  They need to be under-pinned with detailed workforce
plans within services.
Renfrewshire Council has a workforce of 8,500 people across its five services and
people costs represent a significant proportion of overall Council expenditure..
Renfrewshire council has a comprehensive high level People
Strategy, supported by a flexible approach to priorities with
ownership of workforce objectives set at the service line level. 
This Strategy was approved in 2021 by the Finance, Resources and Customer
Services Policy Board and its themes were aligned to the new Council Plan strategic
priorities during its first review in 2023. The Strategy contains three strategic
outcomes as shown below.
Page 64 of 110

Page 69

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
12 
Source: The People Strategy 2021-26
During the development of the Strategy the Council engaged with its service
departments, employees and trade unions. There has been training on virtual
working and a set of new and revised policies created to support new ways of
working.
The Council adopted a flexible approach to its strategy, by setting up clear priorities
for the first two years and by delegating the responsibility and ownership for
managing of the workforce to the individual Services to better meet their needs.
Therefore, the workforce risk assessment, operational priorities and implementation,
and monitoring are done at this level though Service Improvement Plans.
The first two years of the strategy were focused on tackling COVID-19 related
challenges:
1. The health and wellbeing of the staff
2. Exploring new ways of working post COVID-19
3. Building on staff communication and engagement.
In addition to the main workforce strategy and Service Improvement Plans, the
Council has in place a number of other documents to support its workforce planning.
These additional documents include:
• Equality Outcomes and Mainstreaming Equality 2021-2025 which
provides a statutory biannual update on our equality progress and
outlines new equality outcomes, including a range of workforce
planning and organisational development activity.
Page 65 of 110

Page 70

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
13
• Equality, Diversity and Inclusion Plan which outlines the plan tod
deliver inclusion, enhancing the staff experience and become the best
place for people to work.
• ‘Your Health Matters’ – Health and Wellbeing Plan 2024 – 2029 which
sets out our vision for employee health and wellbeing.
• Renfrewshire Health & Social Care partnership – Shaping our
workforce’ Workforce Plan 2022-2025 which aim to make sure they
have a workforce which is fit for purpose and is enabled to deliver to
meet the current and future needs of those who rely upon their
services.
The focus of the strategy is currently  shifting from post COVID reaction to different
objectives in line with the changing needs of the workplace. The priorities for the next
two years were set as follows:
• Improve employee experience to evolve the Council's culture.
• Workforce Planning to support service redesigns.
• Equality, Diversity, and Inclusion.
At the beginning of 2024 the Council established  the Corporate Workforce Planning
Group, consisting of  heads of services and  with the main aim to drive and monitor
the Council’s People Strategy priorities and outcomes. The first task will be to focus
on the objectives for the next two years.
In September 2023 a progress report on the People Strategy was provided to Trade
Unions and Elected Members. The report to Elected Members outlined discussions
with the Trade Unions to reset the Council’s People Strategy priorities for the next 2
years. The recommendations contained within the progress report were approved by
Elected Members. It was agreed that the next progress report would be provided to
Elected Members on 31st March 2025, however plans are in place to bring this
progress report forward to the November Finance, Resources and Customer
Services Policy Board. This report will contain progress across the key themes
outlined above and work undertaken by officers to refresh the People Strategy with a
new future framework and vision, looking beyond 2026.
All service reviews are carried out in consultation with staff. Trade unions are
involved throughout the process and agree to the workforce changes. Any new
operating model proposed within services will consider future skills requirements of
the workforce. On occasion, the Council may seek to transfer staff in or out of the
organisation using TUPE regulations, which would include statutory consultation with
trade unions and staff impacted by the transfer.  
Page 66 of 110

Page 71

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
14 
Digital technology and the
workforce
The 2023 Local Government Overview report notes that digital technology will make
councils’ future workforces look and work quite differently.  In order to achieve the
change required, councils need to make good use of digital technology and use the
workforce in flexible ways.
Digital technology has a strong bearing on a council’s workforce needs.  It can be
used to re-shape jobs to increase productivity and reduce back-office functions while
improving service quality.  Technology solutions include online services, customer
relationship management systems, mobile digital services and more recently,
artificial intelligence (AI) applications.
Councils need to be innovative in their use of technology and build on new working
practices that emerged during the pandemic.  In doing so, they must also consider
service quality and the needs of people experiencing digital exclusion.
Appropriate arrangements are in place to enable the delivery of
the Council’s digital strategy. The Council implemented a
number of automatic processes to drive efficiency and
innovation in its workforce. A key challenge for the Council is
the creation of capacity within its workforce to enable the
review, exploration and development of digital opportunities.  
Implementing new ways of working post pandemic is one of the key priorities of the
People Strategy. Closely aligned to this are priorities, agreed in the council’s Digital
Strategy to equip staff to work smarter, understanding where to invest in skills and
training, closing current and future digital skills gaps and reducing digital
barriers/exclusion. 
The council was prepared well for the pandemic by having the IT infrastructure in
place before we were forced to work from home and:
• ICT infrastructure was already configured to accommodate secure
home working, and was quickly upscaled to meet the significantly
increased requirement when the pandemic started.
• It allowed the Council to continue to deliver services when everyone
was required to work from home during lockdown. This readiness was
not common across the whole of Scotland.
Page 67 of 110

Page 72

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
15
The Council established the Digital Board three years ago to oversee all the projects
within the digital portfolio, understand and prioritise resource requirements within the
existing constraints, and to support successful delivery, helping to overcome
challenges and barriers that may impede progress. The Digital Board has a broad
remit to support the project owner in providing overall direction and management for
the portfolio, embracing a corporate approach to delivering on digital outcomes and
in turn Council outcomes. This Board sits in the governance structure at the strategic
level, is chaired by the head of Digital, Transformation and Customer Services, with
a councillor as a digital champion, and a number of specialists from other services,
including HR and Finance. In practical terms the board prioritises and supports
project deliverables, signs off business cases, monitors the progress and provides
support and expertise. Reporting to the Digital Board there are two layers of digital
programme delivery:
1. Programme managers and the Programme Management Office responsible
for identification and tracking of the benefits. 
2. Project delivery teams resourced from service teams.
The Council has an internal digital programme in place to support its objectives and
split into seven individual projects that focus on improving customer experience and
making work of the council more efficient and innovative. The key initiatives relating
to the workforce include:
• Promoting digital leaders as role models to lead by example and
change the appetite for digital working.
• Issued a Digital Strategy Questionnaire to its leaders to understand
current digital capabilities and challenges to inform on the digital
strategy and roadmap.
• Introduced Digital Champions to provide peer support and build digital
confidence and capacity across the workforce. Digital Champions are
employees with an interest in technology, systems or new ways of
working and are passionate about helping colleagues grow their digital
skills. Digital Champions will often already be a go to for digital
questions within their team. They provide peer-to-peer support within
their services and teams to support digital enablement.
• Introduced online safety ambassadors who are volunteers who have
been trained to help their colleagues and friends stay safe online. Over
140 Online Safety Ambassadors have been trained so far with more
training sessions lined up.
The Council introduced a number of internal digital tools to support better workforce:
1. Enterprise Resource Planning (ERP) with multi-business functionality. It is
predominantly a people and organisational development and management
Page 68 of 110

Page 73

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
16
system containing people data, with a reporting capability on people metrics,
absence, ethnicity, establishment/FTEs, leavers, etc. This system has been
integrated with the iLearn so managers have live visibility of training
undertaken by every staff member and can monitor uptake, progress and
completion of mandatory training.
2. Electronic payslips for most of its workforce, with the target of providing it to
all employees by 2025. It generates savings and supports the green agenda.
3. MS Teams is widely used for virtual meetings, collaboration and calls, recently
replacing desk phones. 
4. Absence statistics are now generated from our Business World ERP system,
eliminating the need for lots of manual interventions across several teams to
generate information. 
5. P2P is a new strategic council project, which is improving the set of processes
that covers the activities of requesting, purchasing, receiving, paying, and
accounting for goods, services and works. 
Recruitment automation and digital improvements
A Robotic Process Automation capability was utilised to automate the indexing of
references to NEC Document Management, which is the electronic document
management system, significantly reducing processing times for obtaining
references and enabling managers to review references on the same day they
were received. This automation minimised manual interventions and accelerated
the overall recruitment process. 
The use of ‘Dash’, an online form capability, for requesting candidates ID
documents, which are automatically uploaded by the robotics team, along with
sending references and automated chasers to referees every 48 hours, greatly
improved the efficiency of obtaining references and ensured timely follow-ups. The
reduction in the average number of days to complete a recruitment pack from 79 in
2022 to 19 in 2023 is a clear indicator of the efficiency gains from utilising Dash
and robotics. 
Leveraging NECDM to pre-populate employment contracts reduced manual entry
errors and expedited the contract creation process, enhancing overall recruitment
efficiency. 
Processing advert requests through Business World ERP via the vacant position
form function allowed for seamless updates on advert status and streamlined
workflows from managers, to HR, and back to the recruitment team, ensuring
smoother communication and quicker processing times. 
More efficient processes that reduced and mitigated delays through implementing
an internal ‘MyJobScotland’ (MJS) online recruitment portal, which sends
Page 69 of 110

Page 74

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
17
automated emails to managers when a job is posted and closed, improved
communication and ensured all stakeholders are promptly informed, reducing the
risk of delays. 
The Council offers a variety of digital training to its workforce. It
also acknowledges that a more recent digital skills assessment
is required to better understand any skill gaps.
The Council relaunched iLearn in Summer 2024 which is an online staff learning
management system that helps the Council to deliver on its values and aligns to
People Strategy ‘Our skills strengthen’ objective. It includes mandatory training
modules and reporting functionality and a wide range of accessible employment-
related courses, including corporate induction and a comprehensive information
resource for all people joining the Council. Training on various mandatory and non-
mandatory modules can be accessed on a range of different devices (work and
personal), such as a laptop, desktop, tablet or even handheld devices such as
smartphones. Recent data shows that 37% of total workforce have accessed
training.
Using the Government’s Flexible Workforce Development Fund and funding secured
from the trade union Unison, the Council partnered with West College Scotland to
deliver courses on basic digital skills for frontline workforce.
In 2018 the Council assessed the digital training needs of its workforce through an
internal survey. The results were formally considered by the Council’s Leader’s
Forum during an interactive session on ‘A Skilled Workforce’ which enabled
feedback on Digital and ICT areas such as Business World ERP, MS Office,
specialised systems such as Building Information Modelling and GIS, social media
and infographics.  
In 2021 the Council performed a Digital Maturity Assessment which acknowledges
the priority need for a digital skills assessment to be carried out on the wider
workforce, which will be enabled through workforce plans and utilising Digital
Champions networks to better understand the skills gaps across the workforce.
The Digital Champions group was set up as a result of the insights gained from this
assessment.
The recruitment team recognised a need for creating more efficiency through
reducing the time taken from advertising to filling vacant positions across the
Council. They identified a barrier to this reduction was in obtaining references from
candidates’ nominated referees. This resulted in a number of new digital solutions
being implemented to address this identified obstacle to efficient recruitment.
The Council actively engages with its communities to deliver
services in more innovative way to tackle digital exclusion. The
Page 70 of 110

Page 75

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
18
Council’s work has been recognised as best practice example
in Accounts Commission report on digital exclusion. There is
awareness of the need, and drive for continuous improvement
in this area.
The Customer Strategy for the Council was developed following consultation with
customers and senior staff across the Council. The strategy aims to build on the
successes of the previous Customer Strategy and is developed across four key
themes of Customer Contact, Technology and Innovation, Service Design and
Culture and Skills. This aligns to People Strategy ‘Our Skills Strengthen’ outcome,
combining 2 areas of activity - digital skills and front-line core skills, developing the
skills of our Customer Services staff to support customers who need more complex,
sensitive or urgent assistance. A number of initiatives and projects in this area is
outlined below.
The Chief Executives Service have been working collaboratively, using Co-Design
methodologies to shape Council services with residents. This involves gaining
insights from residents for each iteration of a new design to ensure it meets their
needs. Organised in partnership by between Renfrewshire Council and the Third
Sector Interface “Engage Renfrewshire” employees, the DigiRen network
collaborates across multiple sectors, including closely with residence, public
sector, third sector, social housing sector, academia and local business. The goal
is to aid individuals in navigating online, acquiring essential digital skills, and
promoting internet safety.
Enabling Digital Inclusion in Renfrewshire through #DigiRen was highlighted in the
recently published Audit Scotland report on “Tacking Digital Exclusion” as a Case
Study.
Citizens Voice Forum was established by Renfrewshire Council and seeks to co-
design digital inclusion solutions by taking a person-centred and place-based
approach and by working with organisations involved in delivering digital inclusion
as well as those impacted by digital exclusion.
The Forum brings together Public and Third Sector organisations and is
progressing the following priorities:
• Building Confidence, Capability and Capacity through Digital Champions
and a Digital Champions Network 
• Develop and implement Digizones – a place where people can Connect,
Learn & Explore through having online access and offers a variety of
services to enhance a person’s digital experience – these are being rolled
out from October 2024.
• Linked to employability, establish a community-led secure device recycling
initiative – in progress.
Page 71 of 110

Page 76

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
19
Get Safe Online works with the police force and local communities to provide up-
to-date online safety advice. Provider of Renfrewshire’s Online Safety Ambassador
programme “RenSafeOnline” training helps volunteers from the community as well
as the workforce support friends and colleagues with online safety advice. This
also supports New Ways of Working objective of the People Strategy with
employees who work within the hybrid working model and other remote locations.
Digital Operations is a project encourages residents in the community to interact
with the Council digitally when accessing council services. 
These changes and initiatives have led to a considerable shift towards digital self-
service, creating capacity and resulting in significantly fewer calls and requests for
face-to-face appointments with customer service staff.
The Council has also created a community of volunteers to support those who are
digitally excluded by providing help with upskilling residents/service users.  Since
May 2023, the Digital Champions programme has:
• Supported 619 Learners across 6 libraries.
• Issued 121 pre-loaded data SIMs to families from a low-income household.
• Built a team of 17 Committed Digital Champion volunteers.
• Collectively delivered 864.5 Vol hours. 739 this year alone.
A Digital Champions Network has now launched, and is available to all Digital
Champions, or organisations hosting Digital Champions across Renfrewshire.
The space aims to:
• Connect Digital Champions with other Digital Champions and provide a space
for Peer-to-Peer support and networking.
• Provide up to date information to all Digital Champions or local third sector
groups and training offers.
• Povide space for organisations to request the support of other Digital
Champions in the area.
The Council aims to improve its digital systems further. Renfrewshire.gov.uk,
MyAccount, the intranet, and the emails can be improved by several changes it
wants to make based on the communities feedback on the user experience,
information access, clarity and variety of sources being available. As part of the
council's Digital Experience programme, which has been identified by Elected
Members, citizens, and the Council Management Team as a priority, the Council is
looking to fix these challenges and go further with a more innovative digital
experience for our users. 
Page 72 of 110

Page 77

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
20
Robotic Process Automation
As part of the Council’s Customer Strategy approved in November 2023, the
Council has been exploring Integrated Robotic Process Automation (RPA). This
will enhance the choice the council offers to its customers via Customer Service
Centre, expanding some services to a 24/7 operation for certain routine
transactional services. RPA is running 52 processes mostly within the Business
Services area and now branching out to the rest of the council. The automated
assistant will support further reduction in telephone demand to the Council and has
the potential to release recurring savings from the Customer Operations team.  
Page 73 of 110

Page 78

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
21
Flexible working and other
innovative staff deployment
During the pandemic councils needed to make the best use of their existing
workforce while continuing to monitor employee wellbeing.  Councils continue to look
to new ways of working to improve job satisfaction and reduce sickness absence and
staff turnover.  
Home-working and hybrid working (a combination of office and home-based working)
have now become commonplace.  Some councils are also considering more radical
working practice such as a standard four-day working week.  However, whatever the
working practice, employers need to ensure that service quality and productivity are
maintained.  
The Council continuously reviews its approach to flexible
working and provides staff with support and guidance.
Renfrewshire Council, in line with other councils and organisations, had to change
workstyles and work locations during the COVID-19 pandemic.  The Council offers a
blended working approach which allows eligible employees to work from a
combination of home and office work, in line with the requirements of their specific
service and role.
The council has a wide range of flexible working arrangements across the teams,
using non-standard working hours, compressed working hours and developing a
supportive, people-centred team, support colleagues returning from long-term sick or
managing significant health concerns. The Council also operates a flexi time scheme
for staff to provide flexibility with start and finish times out with the Council’s core
working hours.
The flexible working policy is seeking to:
• Embrace new ways of working which can support improved work-life balance
and maintain health and wellbeing.
• Help attract and retain a skilled and diverse workforce.
• Embed a culture across the Council where flexible working is seen by all
levels as a benefit with positive outcomes and can support the needs of
modern families and lifestyles.
• Provide consistency for managing flexible working requests equally, fairly,
reasonably and without undue delay in accordance with legislation.
Page 74 of 110

Page 79

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
22
• Support the Council with organisational change to ensure future, sustainable
service delivery.
The Council operates a hybrid working model which is an informal flexible working
arrangement within the flexible working policy. This model was first adopted in
response to COVID19 challenges and has been positive, benefiting colleagues,
communities, and the Council, helping to maintain an agile and sustainable working
environment and supporting a positive work-life balance. 
The Council has invested significantly in future-proofing its infrastructure through its
Connectivity as a Service Framework.  This provision has enabled its workforce to
work from any Council venue across Renfrewshire and once fully rolled out will
broadcast free secure public access Wi-Fi from up to 180 council venues, including
in 3 of its town centres, further enabling digital inclusion opportunities to
Renfrewshire citizens and communities.
The Council has committed to continue with these arrangements, allowing ongoing
flexibility, without the need to formally apply for hybrid working. Guidance on
managing hybrid working issued in June 2022 for managers consideration, outlining
the key factors in applying hybrid working and best practice from the past
experiences.
Following that period the Council has also reflected on the current practices and the
Head of HR together with other leaders considered the post pandemic ways of
working, the types of the tasks and roles, facilities available including collaboration
space and key factors influencing creating culture of flexible workforce.
Remote/Fixed/Hybrid positions have been verified with heads of services. 
The Supporting Menopause at Work Policy
The Supporting Menopause at Work Policy was approved by elected members in
August 2022 as part of the ongoing HR&OD Policy Review, was a proactive
approach taken by the council for supporting colleagues’ wellbeing at every stage
of life. Almost three quarters of our workforce are female and therefore we
recognise that many female colleagues will be working through the perimenopause
and menopause transition and managing the symptoms at work. We know that
many people feel uncomfortable talking about the perimenopause and
menopause, which means that some women suffer in silence while experiencing a
wide range of symptoms that can affect their physical as well as mental health.
The Council obtains staff feedback in variety of ways and
considers impact of flexible working on staff wellbeing.
A staff survey was carried out in June 2021 to capture how staff were feeling and
coping coming out of covid restrictions. Analysis of the data helped to inform the
New Ways of Working Board on actions to be implemented, to help a return to the
office work environment post-pandemic.
Page 75 of 110

Page 80

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
23
A new staff engagement survey is planned to be undertaken during the month of
September 2024, to capture staff feedback on the following themes: ‘The Council as
my employer’, ‘Me and my job’, ‘My performance’, ‘development and recognition’,
‘My working environment and my well-being at work’, ‘Hybrid working’,
‘Communications across the council’, ‘team meetings’, ‘Our internet and online
presence’, ‘My supervisor/manager and me’ and ‘workplace policies and
procedures’.
New staff engagement forums are in the process of being established in all services
with a view to engaging with staff to help the council effect decision making and drive
positive change through sharing views and ideas, encouraging fairness and
inclusion.
The Health and Well-Being Plan’s key areas of focus in the plan arose directly from
the smarter ways of working survey. The trade unions were engaged with and given
a presentation of the council’s plans for new ways of working post Covid.
Maintaining a sense of team culture under the blended working approach is a
challenge that does not impact solely on Renfrewshire Council.  Services have
implemented well established methods to mitigate the risk of this challenge including
through requesting that all team members are working in the office on the same days
to increase collaborative working alongside creation of village area on of the floors in
the main council building, repurposing desks and low budget decorations to make
more welcoming environment.
The Council considers staff benefits and wider sociological
changes when considering new ways of working.  Evidence of
measurable efficiencies tracking has been limited and the
Council has not been able to demonstrate efficiencies from
flexible working through, for example, an impact on productivity.
Services within the Council are facing the challenge of being able to measure
productivity of workers that have opted into the new ways of working, including
flexible working approach and to be able to conclude on whether employees are
more or less productive under this style of working.
While the Council is able to present the overall results of the voluntary schemes and
how it impacts the workforce and savings it provides this is not specifically linked to
innovation or flexible working arrangements. We have not seen evidence of direct
productivity measures and there is further work required in this area before an output
to allow productivity of new ways of working to be measured is available to be
implemented across services.  The resource and capacity challenges are the main
factor preventing further progress being made in this area of workforce planning.
Recommendation 1  
Page 76 of 110

Page 81

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
24
Developing future skills and
capacity
Councils need to find innovative ways to ensure the workforce capacity and skills
they need to deliver services in the future.  Training and development opportunities
can help to attract and retain employees and ensure skills are in place.  Many
councils work with their partners to offer apprenticeship schemes or vocational
qualifications.  Succession planning is also important to develop future leaders and
ensure that essential skills are in place.
Jobs can be re-designed to optimise the workforce and improve services.  For
example generic roles across health and social care disciplines.  Leaders need to
engage with staff and trade unions over fundamental workforce reform.  This is
particularly challenging in an environment of potential job losses.
The Council makes good use of its existing workforce and is
developing the skills needed to deliver future services.
The Corporate Workforce Planning Group works closely with services to identify
skills gaps and equip managers with tools to enable the up-skilling of staff supporting
new and innovative ways of working and addressing recruitment challenges. 
The Council has effective and appropriate arrangements in place for building future
capacity through schemes including:
• Workforce Development Plan - Economic Development.
• International Recruitment Pilot.
• DFN Project SEARCH.
• Keeping the Promise.
• Developing the Young Workforce.
• Apprenticeships programme.
• Various management and leadership training.
In this section of our report, we have highlighted specific examples which
demonstrate the innovative schemes and initiatives produced by the Council to
develop a resilient workforce. 
Page 77 of 110

Page 82

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
25
Workforce Development Plan - Economic Development 
The Council has a designated team of 9 people within its Economic Development
department responsible for promoting “Council Employer” role in employability with a
much larger team offering employability support to around 2000 unemployed people
per year across Renfrewshire. The Council is one of the largest employers in the
area and plays a significant role in its local community and has been involved in
number of activities in the area in the last decade:
Providing apprenticeship opportunities for local people to gain both skills and
qualifications at Renfrewshire Council with the aim of sustained future employment
(around 25 new posts per year, 80 at any point of time due to apprenticeships
being from 1-4 years duration).
Providing fully paid trainees with opportunities (paid work experience) in entry
level job roles in Council departments with a high turnover of staff / level of staff
vacancies to allow longer term unemployed people lacking skills and experience
(or people with a specific disadvantage) to gain these with Renfrewshire Council.
The posts work alongside existing staff in key job roles, developing new skills. The
participant to secure entry level positions on completion and provide a ready pool
of new recruits (already employed by the council and so internal applicants) for
vacancies (currently around 80 per year but this has previously been up to 250
during economic downturns).
Supporting those with additional learning needs to enter employment. The Council
has been delivering Project Search for 10 years, facilitating 10-12 young people
with a learning disability or autism to undertake work experience across three
council services (each) for up to 9 months. The majority of Project Search trainees
go on to future employment, many with the Council.
Internship opportunities for unemployed or underemployed local graduates to
gain work experience relating to their degree and to allow them to progress in their
chosen career. Currently only supporting a few graduates due to the buoyancy of
the labour market but previously 60 per year during economic downturns. 
In addition, various recruiting departments work with the wider council employability
service for local recruitment drives, support with council application forms and
supporting local job fairs and recruitment events supporting unemployed people
finding local employment.
DFN Project SEARCH
The Council works in partnership with Glasgow Clyde College to deliver specific DFN
Project Search training to those in the DFN project. The Project provides a structured
traineeship programme to better prepare people for the world of work, providing on
job training and mentoring and identifying workplace adjustments required which will
lead to trainees becoming job ready and able to fulfil their employment prospects.
For entry level job roles, the Council is currently considering guaranteeing an
Page 78 of 110

Page 83

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
26
interview to those who meet the essential criteria, to help remove barriers into
employment. 
Keeping the promise
The Council along with its partners have committed to delivering on the Scottish
Government’s Keeping the promise commitment. The Promise is the outcome of
Scotland's three-year Independent Care Review, where more than 5,500 care
experienced children and adults took part, to transform the wellbeing of infants,
children, young people, and adults. It is one of seven concluding reports published in
2020 and organisations, communities, and groups across the country have all
pledged to #KeepThePromise. 
The Council has appointed a Promise Lead Officer and established a Promise
Oversight group involving representatives from the council and its partners. Through
this initiative, the Promise remains at the forefront of our service delivery and design.
For entry level job roles, the council is currently considering guaranteeing an
interview to those who meet the essential criteria, to help remove barriers into
employment. This is one way the Council is demonstrating our commitment to
supporting care experienced people into work. 
Developing Young Workforce 
Developing the Young Workforce West (DYW West) regional group has been
established to help employers to shape their future workforce, covering
Renfrewshire, East Renfrewshire, Inverclyde and West Dunbartonshire. The Council
has school’s transitions group who meet regularly with a robust focus on supporting
vulnerable learners into positive destinations. 
Apprenticeships
The Council has arrangements in place for delivering employability programmes
including foundation and modern apprenticeships.  The Council’s employability team
‘Invest in Renfrewshire’ provide lots of different support to help young people
prepare for work, learn new skills and get a job. The Council has tailored
programmes to support everyone, including people who are care experienced,
people with a disability or health condition, school leavers, working parents and
people with criminal convictions. The evidence attached provides details on the
various types of apprenticeships and traineeships available at the Council, including
foundation, modern, graduate and trades and traineeships.
The Council engages with the local education providers to
develop and support its workforce skills.
The Council had a number of initiatives where it works with the education providers:
• Partnerships with West College Scotland for digital training provisions for basic
digital skills needs, and to provide accredited Mental Health First Aider training.
Page 79 of 110

Page 84

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
27
• The Chief Executive’s service is working with UWS on the new pathways
programme. Showing people the range of roles available within a sector, for
example, in a theatre for a variety of roles.
• The Council worked collaboratively with University of the West of Scotland (UWS)
and Glasgow City Region to develop training specifically for planners to help
develop and recruit talent into these hard to fill roles. The Council will create a
trainee planner role for participation in the 2025 intake.
The Council has a partnership with the UWS and Glasgow Caledonian University
(GCU) to deliver the Graduate Apprenticeship programme. 
Graduate Apprenticeship
This programme offers staff access to graduate level apprenticeships (degree and
masters level courses) providing learning and upskilling opportunities in the areas
of business management, accountancy, AI and data science, project management
quantity surveying, early learning and childcare. The Council have also recently
committed to working with GCU on a new pain research project, which will result in
enhanced support provision for people who are in work but within pain thresholds. 
Castlehead High School 
Castlehead High School in Paisley has been in the limelight since it joined
forces with The Glasgow School of Art (GSA) back in 2017, becoming
Scotland’s first ‘School of Creativity’. The partnership was part of a unique
collaboration between GSA and Renfrewshire Council, designed to unlock
potential in pupils, encourage innovative thinking, increase attainment and
develop skills needed to thrive not just at school and work but in broader
society.
The Council has to yet develop comprehensive measurable
performance indicators to demonstrate benefits it provides
through its work on developing its skills and capacity.
Currently the Council has limited number of examples where it clearly tracks benefits
realised or expected from the above initiatives. It is at the stage of considering
introducing key performance indicators in this area to monitor the effectiveness of its
workforce programmes.
Recommendation 2  
Page 80 of 110

Page 85

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
28
Joint workforce
arrangements across
services and partners
Councils should look to work collaboratively with their partners to make the best use
of their existing workforces and plan for the particular workforce needs in their areas. 
They should also work across traditional service department roles within councils to
deliver improved services and outcomes.
Examples of this include generic working across health and social care, professional
posts or functions between councils, and services delivered through empowered
communities.
The Council works collaboratively with its partners and
continues to explore opportunities for working together. 
Through collaborative working, the Council shares knowledge
and learns from partners, leading to enhanced service delivery
and outcomes.  
The Council recognises the benefits from working collaboratively with partners. 
Such workforce benefits include, for example:
• Resource savings particularly in respect of duplication of effort.
• Consistent approaches.
• Building communities of practice.
• Knowledge transfer, sharing, learning and supporting each other.  
Systems and information sharing protocols are a key barrier to shared working. 
Where barriers can’t be overcome easily, creative solutions are developed to
overcome the barriers.
Examples of collaborative working
An example of a partnership working is where the Council
works in collaboration with Inverclyde Council, East
Renfrewshire Council, and West Dunbartonshire Council to
deliver a civil contingencies service which supports business
continuity and emergency planning across these Council areas.
Page 81 of 110

Page 86

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
29 
This joint service approach ensures that civil contingencies functions are made
more resilient and improve local co-operation and coordination between the four
councils, emergency response partners such as Police Scotland, Scottish Fire and
Rescue Service, NHS Greater Glasgow & Clyde through the West of Scotland
Regional Resilience Partnership (WoS RRP). The Civil Contingencies Service
works closely with multi-agency partners and bases activities on meeting the
duties under the Civil Contingencies Act, as follows: 
Risk Assessment - working in partnership with other local authorities, and with
the other Category 1 and 2 responders, a Community Risk Register covering the
west area of the WoSRRP has been produced and can be viewed at the following
web address: www.firescotland.gov.uk/your-safety/community-risk-register.aspx 
Emergency Planning - the Council’s functional and specific plans are continually
being revised and developed in cooperation with our multi-agency partners.
Familiarisation with all of the plans is essential. Training and exercising takes
place at regional and local levels. Multi-agency and cross-boundary exercises
ensure that those with a duty to respond to incidents are fully aware of the roles
and responsibilities of each partner agency. 
Arrangements to Warn and Inform the Public - in the event of an emergency,
the Council’s Communications Team will work with multi-agency partners to give
information to the public using social media, the Council website, call centres etc
and through the use of local broadcast media and press. Depending on the
circumstances, Council employees may attend at the perimeter of the scene and
assist in providing advice and directions to the public where they can shelter. Local
notices and posters may also be displayed. The Scottish Government’s Ready
Scotland website provides general advice to the public on steps they can take to
protect themselves, family and property when considering some of the risks facing
Scotland. 
Information Sharing and Co-operation with other local Responders - the West
of Scotland Regional Resilience Partnership (WoS RRP) is chaired by Police
Scotland and good partnership relationships continue to be developed with local
responders, and key stakeholders. Members of the WoS RRP participate in and
deliver multi-agency tabletop exercises and emergency preparedness training
events. 
Business Continuity - each council has a duty to continue to deliver their
essential services during an emergency. To help prepare for this, and because it is
good business practice, the Council has put in place a business continuity
planning process, which includes testing arrangements. 
Provision of Advice and Assistance to Businesses and Voluntary Agencies -
this duty came into force in May 2006 and is continually being developed to
address current needs. Guidance to businesses and voluntary organisations is
discussed at the WoS Business & Community Resilience Sub-Group. 
Page 82 of 110

Page 87

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
30 
There are also examples of collaborative work with other local authorities and
Scottish Government.
The Glasgow City Region City Deal: is an agreement between the UK
Government, the Scottish Government and eight local authorities across the
Glasgow City Region. The City Deal is expected to bring tens of thousands of jobs
to the Glasgow City Region through major infrastructure projects, drive innovation
and growth through the support of key sectors such as life sciences and address
challenges in the region's labour market.
The Council works in collaboration with neighbouring councils to provide
context on the regional labour market and impact of the Scottish Government’s
Fair Work First principles. The group identify specific actions for joint working that
will seek to address issues such as hard to fill posts in local government, retention
challenges, career pathways apprenticeship opportunities and strengthening the
connection between HR Services and Employability services, promoting local
authorities as employer of choice.
The Council has drafted a Fair Work First Statement which is being currently
consulted with our recognised trade unions.
The Council has senior representation on several national working groups
(for example SPDS Executive Group) which exist to provide specialist professional
knowledge and focus on key national workforce planning challenges. These
groups provide joint approaches to be rolled out across local authority
organisations in Scotland.
The Council participated in Scottish Government feasibility study with 5 other
care providers to establish a model for recruiting to healthcare roles that are
increasingly difficult to fill from the UK Labour Market using international
recruitment processes. 
The Council worked in partnership with Inclusive Employers to deliver its equality,
diversity and inclusion agenda.
Inclusive Employers
The Council recognised they needed to make this more of a priority and it was
therefore important we asked our staff how they felt about Equality, Diversity, and
Inclusion at Renfrewshire Council. As a result, the Council partnered with subject
matter experts in Equality, Diversity, and Inclusion, Inclusive Employers in 2023,
who helped us seek views from our staff and helped us analyse the feedback
given.
Page 83 of 110

Page 88

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
31
This work included conducting a cross-organisational culture review to better
understand staff experiences at Renfrewshire Council. The review found pockets
of good practice across Renfrewshire Council as well as clear areas for
improvement and has provided the Council with a path forward as we aim to
become the best place for people to work. The findings from this review have now
been analysed and form the basis of our refreshed approach to inclusion at
Renfrewshire Council found within this five-year Inclusion Plan. 
The Council has also services delivered through its partners. include delivery of:
• Occupational health service and employee assistance programme
(counselling service) through procured 3rd party providers.
• Digital skills basics training, mental health first aiders training as well as
trade apprenticeships with WCS, Digital Champions Programme.
• A range of services that contribute towards improving the health and
wellbeing of our employees and the wider Renfrewshire Communities
through its partnership with OneRen. These services include use of
Paisley Town Hall for events and functions, Paisley Central Library ,
Paisley Arts Centre and Paisley Museum for delivery of cultural
heritage and local knowledge/information. A range of sports and leisure
facilities across Renfrewshire are available for our employees to use.
OneRen staff have assisted the Council with operations related to
Covid Testing Station staffing, vaccination queue marshalling, etc.
• Carrying out the valuation functions of Renfrewshire, East
Renfrewshire and Inverclyde Councils by the Renfrewshire Valuation
Joint Board.
• Using Scotland Excel, which is a centre of procurement expertise, to
deliver procurement services on behalf of the Council.
Future Paisley 
Future Paisley: is a programme of cultural events and activity based around
Paisley and Renfrewshire's unique and internationally significant story which uses
targeted investment to deliver positive change.  
The programme is putting culture at the heart of Paisley and Renfrewshire's
regeneration and harnessing the power of culture to support people's lives for the
better, by integrating its benefits through key public services such as health and
social care, education and housing. The programme is led by the council and
OneRen, in partnership with a wide range of organisations, including Renfrewshire
Health and Social Care Partnership, the University of the West of Scotland,
Engage Renfrewshire and NHS Greater Glasgow and Clyde. 
Page 84 of 110

Page 89

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
32
It is governed by a partnership board which features representatives from the
above, as well as organisations including the STAR Project, Paisley First, Creative
Scotland, Arts & Business Scotland, Scottish Future Trust, Skills Development
Scotland, Visit Scotland, EventScotland, Glasgow School of Art, Scottish
Enterprise, NHS Greater Glasgow and Clyde, Renfrewshire Chamber of
Commerce, Police Scotland, Glasgow Airport, West College Scotland and
University of Glasgow. 
Page 85 of 110

Page 90

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
33  
Measuring the impact of
workforce planning
Councils should monitor the impact of their workforce planning and delivery
approaches.  This should include cost, service quality and productivity benefits as
well as employee wellbeing.  This in-turn should inform their workforce planning
approach.  Councils and their partners should also understand the wider impact of
their employment practice on the local economy.
The Council monitoring against progress in implementing its
Workforce People Strategy could be improved in terms of its
clarity over the status of individual objectives and wider use of
measurable performance indicators.
Reporting in Service Improvement Plans gives limited
information on progress against People Strategy objectives’
progress.
The first report on the People Strategy progress was presented to the Finance,
Resources and Customer Services Policy Board in September 2023, two years after
the Strategy has been approved. The purpose of this report was to provide the
members with an update on the progress made, and to set the key workforce
planning priorities over the next 2 years.
In March 2023 the council performed a mid-review of the People Strategy and re-
aligned it to the new Council Plan 2022-27 strategic priorities. The Council made 
good progress against the Strategy priorities (Health and Wellbeing, New Ways of
Working Post Pandemic and Staff Communication and Engagement). 
The Council reported the progress against its priorities as at 50% during the interim
review and reported on a number of actions undertaken in line with is 2 year period
priorities. The reports had no specific reporting on what actions are still outstanding,
which are delayed or specifically replaced. This should be improved to allow
appropriate scrutiny.
Recommendation 3
Going forward more frequent (annual) reviews and monitoring reports on People
Strategy are planned to be presented to the relevant Board. The next one is
expected in November 2024.
Page 86 of 110

Page 91

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
34
As mentioned at the beginning of this report workforce risk assessment, operational
priorities and implementation, and monitoring are done at the service level through
Service Improvement Plans. We have reviewed the progress update reports for a
sample of services, and while services highlight different areas in those (as expected
for such flexible reporting), none of them had clear performance measures reported
beyond the rate of sickness absence. There is a scope to develop and report a set of
performance indicators to support scrutiny on the progress against People Strategy.
Recommendation 3
The Council tracks benefits of its workforce approach at a high
level.
The Council realised savings from its service redesign, service integration and
resulting roles reviews. Staff in these situations may be offered a severance package
in terms of their eligibility for early retirement or redundancy. Voluntary
Redundancy/Early Retirements Scheme have generated annual savings of £5.5
million in the last three years with 139 employees leaving the council as a result.
The evolvement of hybrid working practices has created more flexibility for staff to
work when and where they choose to, realising benefits such as reduced parking,
travel time and commuting costs. Hybrid working has also supported the Council to
reconfigure its office and wider estates plan resulting in more efficient use of office
space and resources. It has allowed the Council to maximise its digital capabilities
through online public Council meetings and corporate training delivery, via MS
Teams. The Council is currently in negotiation with the recognised trade unions to
review the terms and conditions of employment for approximately 6,500 staff. The
review focuses on implementing a modernised and fit for purpose package of
conditions, supporting the council to be an employer of choice whilst making savings
from legacy conditions with a view to being implemented during 2025.
Harmonisation of Craft Workers Conditions of Service
As part of its People Strategy and Workforce Planning approaches, the Council
harmonised the pay and conditions of service of approximately 230 Craft Workers
(Trades) thus aligning this group of staff with 6,500 staff on Local Government
Conditions of Service. Harmonisation eradicated previous legacy arrangements for
pay and grading and terms and conditions of employment for Craft employees
which had been in place since 2006, and now enables this group of staff being
able to take advantage of incremental pay progression and the same annual leave
provisions alongside thousands of other local government employees. Additionally,
harmonisation mitigates the likelihood of any employee relations issues that may
be caused by applying differences in pay and conditions of service whilst working
alongside each other. This also reduced the number of collective bargaining
groups that the Council has to consult and negotiate on, from 4 to 3 groups.
Page 87 of 110

Page 92

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
35
Appendix 1- Improvement
Action Plan
Issue / risk Recommendation Agreed management
action / timing
1. Efficiencies and impact
on productivity.
We have not seen evidence
of direct productivity
measures and there is
further work required in this
area before an output to
enable the productivity of
flexible working to be
measured is available to be
implemented across
services.  
There is a risk that the
Council is unable to
demonstrate clearly impact
on the productivity from its
efficiencies implemented.
We recommend that
the Council
implements clear
productivity
measures.
The Council will investigate
what measures may be
relevant in order to inform a
consistent and robust
understanding of
productivity in a local
government context,
recognising that services
are delivered from a range
of workplaces and that
specific measures may not
be appropriate given the
Council’s objective of
creating a Fairer
Renfrewshire.
March 2025 
Page 88 of 110

Page 93

Renfrewshire Council: Workforce Innovation – how councils are
responding to workforce challenges (Best Value thematic work in
councils 2023-24) 
36
Issue / risk Recommendation Agreed management
action / timing
2. Performance indicators
for skills and
development.
Currently the Council has
limited number of examples
where it clearly tracks
benefits realised or
expected from the skills
development initiatives. It is
at the stage of considering
introducing key
performance indicators in
this area to monitor the
effectiveness of its
workforce programmes.
We recommend that
the Council tracks its
impact of the skills
and development
measures with a set
of performance
indicators.
The Council will develop a
range of suitable people
metrics which will provide a
more empirical evidence
base against which the
success of training and
skills development will be
measured. 
March 2025
3. People Strategy
monitoring.
The Council reported its
progress against its people
strategy priorities as at 50%
during the interim review
and reported on a number
of actions undertaken in line
with its 2 year period
priorities. The reports had
no specific reporting on
what actions are still
outstanding, which are
delayed or specifically
replaced. 
Reporting on workforce
related performance in
Service Improvement Plans
(SIP) is limited. 
We recommend that
the Council improves
the quality of the
reporting presented to
the relevant Board
and members.
This should include
considering how the
Council is reporting
those at a service
level in SIPs.
The Council has been
developing a suite of
people metrics information
which will be the base data
used to inform update
reports to elected
members. This data will
support the move to
standardised annual
reporting of progress
against the People
Strategy. 
March 2025 
Page 89 of 110

Page 94

We are an accounting, tax, audit, advisory and business services group that delivers a
personal experience both digitally and at your door.
Accounting | Tax | Audit | Advisory | Technology 
© Azets 2024.  All rights reserved.  Azets refers to Azets Audit Services Limited. 
Registered in England & Wales Registered No.  09652677.  VAT Registration No.  219
0608 22.  Registered to carry on audit work in the UK and regulated for a range of
investment business activities by the Institute of Chartered Accountants in England and
Wales.
Page 90 of 110

Page 95

___________________________________________________________________
To:  Audit, Risk and Scrutiny Board 
On:  23 September 2024
___________________________________________________________________
Report by: Lead Officer
___________________________________________________________________
Heading: Neighbour Disputes
___________________________________________________________________    
1. Summary 
1.1 At the meeting on 22nd August 2022, members of the Audit, Risk and Scrutiny Board
agreed an annual programme of activity for the Board for 2022/23. This included an
investigation into neighbour disputes in Renfrewshire. 
1.2 Reports have been presented to the Board by the Lead Officer as the review has
progressed on the subject of neighbour disputes in its widest sense, including
antisocial behaviour. The final element to be considered was Estate Management.  
1.3 This report concludes the review, outlining the key outcomes from the Estate
Management workshop and setting out the key findings and recommendations in the
appended draft Council report.
___________________________________________________________________
2.  Recommendations 
2.1 The Board is asked to:
• note the outcomes from the Estate Management workshop;
• consider the key findings and recommendations;
• approve the appended draft Council report for submission on 12th December
2024; and
• note the Lead Officer’s appreciation for all who assisted in the review.
___________________________________________________________________    
3.  Background 
3.1 At the Audit, Risk and Scrutiny Board in August 2022 it was agreed that a review of
Neighbour Disputes should be undertaken in the widest sense and that this should
also include consideration of issues relating to antisocial behaviour. It was agreed
that the purpose of the investigation into neighbour disputes would be fourfold: 
1. Try to establish the scale and nature of neighbour disputes in
Renfrewshire,
2. Set out the current arrangements and approaches the Council and other
stakeholders have for responding to neighbour disputes,
Item 3
Page 91 of 110

Page 96

3. Review the current disposals/actions that are available to the Council and
others to resolve neighbour disputes, and
4. Identify any other approaches, policy changes or mitigating actions that
could be available to the Council within existing resources. 
3.2 The review initially focused on Category B and C complaints (which relate to
antisocial behaviour and neighbour nuisance). In the course of the review, and in
particular speaking with those with lived experience of neighbour nuisance and
antisocial behaviour, an additional focus on Category D incidents (classed as estate
management) emerged. 
3.3 At the Audit, Risk and Scrutiny Board in May 2024, it was agreed there was a need
for a focus on Category D complaints in more detail in order to identify and optimise
early intervention opportunities. It was also agreed a workshop would be held, with
key services and departments in attendance, in order to take a collective approach
with a focus on estate management. Details of the workshop can be found in Section
5. 
3.4 The aim of the workshop was to highlight approaches and opportunities for early
intervention in order to prevent the escalation into more serious issues or dispute,
help to identify any potential gaps in service provision and/or areas in processes
where improvements could be made from a departmental, community and service
user point of view.   
3.5 It was agreed that the next report to the Audit, Risk and Scrutiny Board would provide
a final summary of the overall review and seek approval for its submission to full
Council. 
3.6 The attached draft report to Council describes the purpose and scope of the
investigation into neighbour disputes in Renfrewshire. It includes a summary of the
information reported to each meeting of the Audit, Risk and Scrutiny Board, and
concludes with the key findings and proposed recommendations. 
3.7 Previous related Board reports have been recorded as background papers for the
Council report. 
4.  Current Renfrewshire Council Estate Management Initiatives 
4.1 The Council’s approach to estate management and community safety is underpinned
by the strategic outcomes in the Renfrewshire Council Plan 2022-2027. A key
strategic outcome is Place and working together to enhance wellbeing across
communities. 
4.2 Actions and interventions in the Council’s approach to estate management and
community safety align with key outcomes in the Council Plan, including:
- encouraging kind and connected communities: where our citizens take pride in their
place and where others are excited to move here
- a fair place: where all our people have the best chances to live happy, healthy and
fulfilled lives, to feel safe, supported and empowered
- working with partners to ensure our neighbourhoods are safe, vibrant and attractive
places to live
- working closely with our key partners to provide care, support and to protect our
most vulnerable citizens
- ensuring person-centred and trauma informed practice, building trust and respect
with the people we engage with, listen to and support
Page 92 of 110

Page 97

- working towards a greener future: including taking steps to protect the natural
environment that supports and benefits us all, and
- working together to get it right for children, families and communities 
4.3 Neighbourhood Environmental Trainee Team (NETT): The NETT programme is
mainly funded through the Housing Revenue Account (HRA) with Invest in
Renfrewshire funding the majority of salary costs for the Work Experience
Programme team:
• NETT is made up of a Supervisor and a number of trainees seeking employment
(aged 16-65) who carry out work 1 day per week in each of the 4 Housing
Neighbourhoods, with a particular focus on known ‘hot spots’. 
• All attendees voiced the importance of the work the NETT team do in maintaining
our local communities. They were highlighted as a valuable additional resource,
with the delivery model working well for both clients and the Service.
• The NETT team are a highly valued resource and discussions included exploring
opportunities to expand this team and to look at a wider range of training
opportunities for the NETT team operatives, bringing additional value to
individuals for future employment opportunities. 
4.4 Renfrewshire Council’s Tenant Satisfaction Survey: a valuable measure of
success (although responses are from Council tenants only, not all tenures). The
Council has a duty to carry out the survey every 2 years and this information can be
used to compare results of initiatives in future years. 
4.5 Moorpark Regeneration Project: An example of the Council’s commitment to
enhancing the local environment and improving the quality of life for our residents -
the Neighbourhood Services team, in collaboration with Housing Services, carried
out a targeted intervention in the Moorpark area, focusing on environmental
maintenance tasks including comprehensive hedge trimming and maintenance to
improve visibility and safety; intensive street sweeping operations; deep cleaning of
pavements; the removal of significant amounts of fly tipping; and increased litter
picking, targeting high traffic areas to reduce litter accumulation. The success of the
Moorpark Regeneration project has provided a model for similar interventions across
Renfrewshire. The lessons learned and best practices developed have been
integrated into the Council’s broader environmental management strategies, helping
to ensure sustained improvements in other communities. 
4.6 Cross-Service Collaboration: to ensure ongoing success, regular meetings take
place to discuss Neighbourhood Operations. These meetings provide Housing
Services, Neighbourhood Services, Public Protection and Waste Services a platform
for continuous dialogue, allowing emerging issues to be addressed promptly and
adapting strategies as needed. This includes tailoring support to meet the needs of
Council Housing tenants through garden assistance, open space management and
improving the general presentation of Council-owned property grounds.   
4.7 Team Up 2 Clean Up: the valuable work that Team Up 2 Clean Up carry out in
communities was noted, as well as potential opportunities to link in more widely
around prioritisation.   
4.8 Take the Lead Campaign: an initiative to encourage responsible dog ownership and
working together to reduce dog fouling and anti-social behaviour across
Renfrewshire. 
4.9 Data Sharing and Continuous Improvement: data is shared between all key
Services to support ongoing development and refinement of maintenance
programmes. This ensures operations are responsive to the needs of the community
and allows immediate concerns to be addressed, but also to shape future work within
Page 93 of 110

Page 98

the 4 Housing Neighbourhood areas, contributing to long-term improvements in the
maintenance and presentation of Council-owned property grounds. 
5.  Progress Update: Estate Management Workshop 
5.1 Alongside acknowledging the good practice and high quality services that are
delivered daily, a key action in the Council Plan 2022-2027 is around ensuring we
understand our service delivery, potential gaps in our approaches and have plans for
improvement through ongoing self-assessment. 
5.2 A workshop was held in August 2024, with key internal stakeholders represented
from Housing Services; Environmental Health; Community Safety; Neighbourhood
Services; Waste Services; and Procurement. Procurement are currently reviewing a
renewed Council Wide Specialist Cleaning, Clearing and Ad Hoc Services framework
which deals with areas such as specialised cleaning services (including needle
sweeps, trauma/biohazard/specialist cleaning, graffiti removal and contaminated
substances), general cleaning services, special uplifts and clearances, pest control
and bin chute cleaning. 
5.3 A collective approach was undertaken to work through the key aspects of Estate
Management that the data (complaints formally logged and speaking with those with
lived experience of neighbour disputes) had raised most commonly: 
• gardens and hedges – both individual gardens and communal garden areas
• waste - including misuse of bins/contamination of bins; excess black bags
• general nuisance – including dog fouling; bird feeding; and dog barking 
5.4 The areas identified involve potentially different teams across these Services and
officers worked collaboratively to identify: 
- existing good practice across a range of neighbourhood initiatives
- opportunities for improvement
- potential approaches and targeting of activity within existing resources 
5.5 The workshop was really positive, with officers identifying opportunities for improved
flow of information, such as procedures that can be put in place to contribute to
improved outcomes, including potential areas for process and/or service
improvements and a cross-departmental commitment to take forward and embed
procedural changes particularly in work areas that straddle multiple departments,
with key points as follows: 
5.5.1 Grass Cutting:
• Renfrewshire Council has a 14 day grass cutting and grounds maintenance cycle
between April and October and tackle a different area of Renfrewshire each day,
maintaining open spaces, school playing fields, public parks, sports pitches and
cemeteries as well as grass cutting and hedge cutting for residents and Council
Housing tenants who require garden assistance or have common maintenance
areas.
• It was acknowledged that conditions within estates are influenced by a number of
factors and the mixed tenure nature of estates is a factor. Council Housing makes
up 14% of housing stock across Renfrewshire.
• It was highlighted that in addition to those that are eligible for and take up support
within the garden assistance scheme, there are some tenants and residents who
do not have the capacity, for a wide variety of reasons, to be able to maintain a
garden. This can contribute to the overall appearance within neighbourhoods.
• Issues were highlighted of dog fouling preventing grass being able to be cut in
communal gardens and open spaces, as well as instances of accumulation of
waste in communal gardens. 
Page 94 of 110

Page 99

• It was acknowledged that there are limited powers available to deal with gardens
belonging to private owners and private landlords (unless there is potential
vermin/rat or fire risk).
→ Agreed action: Housing Services and Neighbourhood Services to continue to
share information on trends and planned activity, alongside sharing knowledge
between all Services operating within Estates, to enhance the collaborative
approach to scheduling and deployment of existing resources to streamline
activity.   
5.5.2 Hedge Cutting:
• Cutting hedges twice per year led previously to issues with maintenance. Before
the workshop took place, Neighbourhood Services had already implemented
hedge cutting in their winter programme with hedges to be cut back at this point,
balancing the maintenance in order to manage hedges more effectively.
• In some areas, hedges have been removed and replaced with board fencing.
This has led to issues with weeds at the fence line in some instances. 
→ Agreed action: Neighbourhood Services advised of the need for both a
summer and winter spray to prevent weeds coming back and it was agreed that
this spraying could be included in the Neighbourhood Services winter works
programme, working with Housing Services to look at the areas where this is
needed. 
5.5.3 Empty Council Housing Properties:
• General Voids: There is a programme agreed for Neighbourhood Services to
maintain grounds of Council Housing vacated through natural turnover and the
ongoing regeneration programme as well as the garden assistance scheme and
open spaces. 
→ Agreed action: Housing Services and Neighbourhood Services to continue to
work in collaboration to forecast and plan resources to deal with ground
maintenance requirements around vacated stock. 
5.5.4 Procurement Contract:
The Council Wide Specialist Cleaning, Clearing and Ad Hoc Services framework
which deals with specialised cleaning services, general cleaning services, special
uplifts and clearances and aspects of pest control is currently under review. This is a
framework contract, not direct spend, with contractors working within set Service
Level Agreements (SLAs) to carry out agreed tasks. Opportunities were discussed to
explore the specification of this contract in the future to optimise service delivery. 
6.  Key Actions and Next Steps 
6.1 The key actions proposed by the group to be considered for further exploration are
set out below. These proposed actions would require to be fully costed, with robust
business case development. Viable proposals with impacts or changes in budget or
policy would then be taken to the appropriate Board(s) for approval:
• Housing Services to work together with Neighbourhood Services on work
programming to identify an optimum service delivery model that meets the needs
of both Services. This includes reviewing deployment of existing resources to
consider a dedicated team to work across properties and grounds related to
Council Housing for grass cutting and cyclical maintenance, including winter
works programming, and coordination ahead of recruitment to ensure sufficient
resourcing. 
• Housing Services, Neighbourhood Services, Waste Services and the Invest in
Renfrewshire team to explore the potential expansion of the NETT team.
Page 95 of 110

Page 100

• Procurement, Neighbourhood Services, Housing Services and Environmental
Health to review the Council Wide Specialist Cleaning, Clearing and Ad Hoc
Services framework, to explore the specification of this contract and identify
opportunities to optimise service delivery.
Page 96 of 110

Page 101

Implications of the Report 
1. Financial - None directly arising from this report.  
2. HR & Organisational Development - None directly arising from this report. 
3. Community/Council Planning - None directly arising from this report.   
4. Legal - None directly arising from this report. 
5. Property/Assets – None directly arising from this report. 
6. Information Technology – None directly arising from this report. 
7. Equality and Human Rights - The Recommendations contained within this report
have not been assessed in relation to their impact on equalities and human rights- as
the paper sets out the scope for a review process rather than proposing any changes
to services. If any change to policy or service position were to be considered in
future, a full equality and human rights impact assessment will be undertaken.     
8. Health and Safety - None directly arising from this report. 
9.  Procurement - None directly arising from this report. 
10. Risk - None directly arising from this report. 
11.  Privacy Impact - None directly arising from this report. 
12. Climate Risk - None directly arising from this report. 
13. Children’s Rights - None directly arising from this report. 
14. COSLA Policy Position - No impacts directly arising from this report.
___________________________________________________________________ 
List of Background Papers: 
Audit, Risk and Scrutiny Board Annual Programme
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, January 2023
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, March 2023
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, January 2024
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, March 2024 
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, May 2024 
The foregoing background papers will be retained within Chief Executive’s Service for
inspection by the public for the prescribed period of four years from the date of the meeting.
The contact officer within the Service is the Climate Emergency Lead Officer, Roz Smith,
who can be contacted at roz.smith@renfrewshire.gov.uk   
Author:   Roz Smith, Climate Emergency Lead Officer, Chief Executive’s Service 
Page 97 of 110

Page 102

___________________________________________________________________
To:  Council 
On:  12 December 2024
___________________________________________________________________
Report by: Lead Officer on behalf of the Audit, Risk and Scrutiny Board
___________________________________________________________________
Heading: Neighbour Disputes
___________________________________________________________________    
1. Summary 
1.1 At the meeting on 22nd August 2022, members of the Audit, Risk and Scrutiny Board
agreed an annual programme of activity for the Board for 2022/23. This included a
review into neighbour disputes in Renfrewshire as part of the programme of activity. 
1.2 Over a period of months and as part of the annual programme, reports have been
presented to the Board by the Lead Officer on the subject of neighbour disputes in its
widest sense, including antisocial behaviour. 
1.3 In undertaking this review, the Lead Officer interviewed Elected Members, key
Council officers involved in different aspects of neighbour disputes and antisocial
behaviour, local Housing Associations, Police Scotland and 17 other Scottish Local
Authorities, as well as speaking to residents with lived experience of neighbour
disputes and antisocial behaviour. 
1.4 This report describes the purpose and scope of the review, including summaries of
information reported to each Board meeting, and concludes with the key findings and
recommendations. 
1.5 The review has provided assurance to the Audit, Risk and Scrutiny Board. The Board
agreed the final report at its 23rd September 2024 meeting.
___________________________________________________________________
2.  Recommendations 
2.1 Members are asked to:
• note the findings and approve the recommendations within this report
___________________________________________________________________     
3.  Background 
3.1 There is no single agreed definition for what constitutes a neighbour dispute. For the
purposes of the review, the definition used is a “disagreement between neighbours
that causes stress or friction”. A range of neighbour disputes may not reach a
Page 98 of 110

Page 103

threshold where they would be dealt with through antisocial behaviour legislation,
such as disputes over communal areas, misuse of bins or storage of waste, parking,
high hedges and boundary disputes. 
3.2  In some instances of neighbour disputes a statutory nuisance may occur, when the
activity of an individual or business on their own premises unreasonably detracts
from another’s enjoyment of their property or causes a risk to public health. This can
include noise, artificial light, odour, keeping of animals and accumulation of waste.
3.3  Some neighbour disputes can be classified as antisocial behaviour as defined in the
Antisocial Behaviour (Scotland) Act 2004, whereby a person acts “in a manner that
causes or is likely to cause alarm or distress; or pursues a course of conduct that
causes or is likely to cause alarm or distress to at least one person who is not of the
same household as them”. 
3.4  The Antisocial Behaviour (Scotland) Act 2004 requires all local authorities to
publish a strategy jointly with the Chief Constable of Police Scotland for their
Council area. Renfrewshire Council approved a new Anti-Social Behaviour Strategy
2022-25 in March 2022, setting out how the Council and its key Community Safety
partners will address antisocial behaviour in Renfrewshire. 
4.  Purpose and Scope of the Review 
4.1 At the Audit, Risk and Scrutiny Board in August 2022 it was agreed that the review of
neighbour disputes be looked at in the widest sense and should also include
antisocial behaviour. It was agreed that the purpose of the investigation into
neighbour disputes would be fourfold: 
1. Try to establish the scale and nature of neighbour disputes in
Renfrewshire,
2. Set out the current arrangements and approaches the Council and other
stakeholders have for responding to neighbour disputes,
3. Review the current disposals/actions that are available to the Council and
others to resolve neighbour disputes, and
4. Identify any other approaches, policy changes or mitigating actions that
could be available to the Council within existing resources. 
4.2 Following the initial report to the Audit, Risk and Scrutiny Board in March 2023, there
was a change in Lead Officer. This change in Lead Officer impacted the original
timescales of the review. 
5.  Antisocial Behaviour National Review 
5.1  During this local review for the Audit, Risk and Scrutiny Board, the Scottish
Government Review on Antisocial Behaviour was published (7th November 2023).
The national review advocates a refreshed, long-term approach to antisocial
behaviour, with a more preventative and supportive focus in preventing antisocial
behaviour from occurring in the first place. 
5.2  There is recognition of the age of the antisocial behaviour legislation and societal
changes over the past 20 years. The national review recommended an independently
chaired group of experts, including statutory, non-statutory and voluntary service
providers and key community representatives, to develop a long-term framework for
addressing antisocial behaviour with a strong focus on steps that can be taken to
prevent antisocial behaviour in the first place as well as considering the effectiveness
of current approaches to tackling antisocial behaviour that does occur.
Page 99 of 110

Page 104

5.3  Further consideration as part of the national refresh may also include:    
- the definition of antisocial behaviour    
- legislation and guidance    
- increased powers 
- reporting, including support and outcomes    
- general approach, including partnership working and public information    
- person-centred and trauma-informed approaches 
6.  The Scale of Neighbour Disputes within Renfrewshire 
6.1  Within Renfrewshire, there is no single source of data relating to neighbour disputes.
Data for the initial stage of the review was drawn from public and voluntary services
who have a responsibility relating to neighbour disputes, including Citizen’s Advice
Bureau, the Council and Police Scotland.   
6.2  It is acknowledged there will be additional neighbour disputes which services remain
unaware of. Also, there may be overlap across datasets, e.g. cases where the Police
respond initially then Community Safety or Housing investigate more fully and record. 
6.3  Analysis showed that, with the exception of domestic noise complaints reported to
the Council, there has been a sustained increase in the number of
incidents/complaints of neighbour disputes in Renfrewshire over the last 3-4 years.
This aligned with the national picture, based on responses from 17 other Scottish
Local Authorities. 
6.4  Renfrewshire Council Officers (as well as other Local Authorities, Housing
Associations and Police Scotland) reported that changes in levels and nature of
disputes was found to be initially due to the pandemic and lockdown, with people at
home more. This links with a clash of lifestyles, which was reported as a major factor
in neighbour disputes, and noise complaints, including situations such as different
working patterns, where one party may leave early for work, or return late at night. 
7.  Domestic CCTV 
7.1 An area of growth in neighbour disputes relates to the use of domestic CCTV
systems, including smart doorbells, fitted by individuals in their homes. 
7.2 The data protection regulator is the Information Commissioner. Privacy concerns
about the use of devices (including individuals involved in a neighbour dispute over
domestic CCTV) should be raised with the Information Commissioner’s Office (ICO). 
7.3 The Council’s powers in relation to domestic CCTV are limited to its installation by
Council tenants. Under the tenancy agreement, tenants should not make any
changes to fixtures and fittings in and around their home until they have received
written permission from the Council. Although permission may be needed for the
erection of CCTV cameras, the Council’s remit does not extend to approving or
policing the processing of personal data by private individuals and the Council does
not have any enforcement powers in relation to privacy infringement. 
8.  Review of Processes Across Scottish Local Authorities 
General Neighbour Disputes Findings
8.1 Contact was made with the other 31 Scottish Local Authorities and a range of local
Housing Associations, with questions on neighbour disputes and anti-social
Page 100 of 110

Page 105

behaviour. 17 local authorities responded (55%) and 3 local housing associations. A
Renfrewshire Local Authority Liaison Officer representative from Police Scotland also
assisted the review on processes within Renfrewshire. 
8.2 There are differences across the 32 local authorities in how neighbour disputes are
dealt with. Renfrewshire Council support and respond to all tenures. This is not the
case across Scotland. Some local authorities will support and respond to all tenures;
others would support and respond to Council Housing tenants only (where they have
Housing stock) and signpost other tenures to alternative organisations; and others
support and respond to all social housing tenants only. 
8.3 The most common sources of neighbour disputes were similar across all local
authorities and housing associations – relating to noise, waste (misuse of bins,
including not putting out for collection, using bins belonging to others and placement
of bins when out for collection) and issues relating to gardens and communal spaces. 
Mediation and Conflict Resolution
8.4 Mediation is a recognised early intervention tool to help neighbours resolve
difficulties, with around 90% success rate1 for sustainable outcomes, i.e. did not have
to contact the local authorities again. 
8.5 Again, there were differences in provision of service – some Local Authorities
(including Renfrewshire Council) provide mediation free of charge to all tenures.
Others charge for non-Council Housing tenants, including charging Registered Social
Landlords who refer to the service. The remainder either provided no service or
would signpost to mediation services offered by SACRO (a Scottish community
justice organisation) at the residents’ cost. 
Trauma Informed and Responsive Services
8.6 Being a victim of neighbour nuisance or anti-social behaviour can have a huge
impact on people’s lives and affect mental health and wellbeing. It is key to ensure
that support is available for those suffering from unreasonable behaviour. The need
to support those perpetrating anti-social behaviour to change behaviours was also
raised. Reasons behind this behaviour can be complex – the behaviour can be driven
by trauma as well as triggering a trauma response in those that it is affecting. 
8.7 Renfrewshire Council has recognised the importance of trauma informed and
responsive services, and training has been rolled out across Housing Services and
Community Safety teams due to the front-facing nature of their roles. 
Noise Monitoring
8.8 Noise nuisance was reported as one of the top complaints of neighbour disputes
and/or anti-social behaviour across local authorities and housing associations. 
8.9 When noise issue is persistent over time, residents are encouraged to keep a diary of
dates and times of noise disturbance. MATRON (or similar) formal noise recording
systems may then be used to gain corroboration for difficult to prove noise nuisance
cases, with the system being installed in the house of the complainer to monitor
noise levels and used to take further action against perpetrators where appropriate. 
8.10 In addition to formal noise recording systems, a number of local authorities use a
‘noise app’. Renfrewshire Council is exploring this option, which enables residents to
submit noise complaints via mobile devices as it is happening without the need for a
formal recording system to be installed in the property, enabling local authorities to
identify areas of need for MATRON system to be installed. 
1 Figures provided via the Antisocial Behaviour Officers’ Forum (ASBOF) 
Page 101 of 110

Page 106

Multi-Agency Meetings
8.11 All local authorities who responded hold multi-agency meetings – with key
organisations including Police Scotland, Scottish Fire and Rescue Service, Housing
Associations and other local partners such as those involved in mental health support
services and addiction services. The aim is to ensure early intervention and a
coordinated partnership approach to ensure solutions are delivered effectively and
efficiently and with knowledge sharing and input across organisations. 
8.12 The frequency of these scheduled multi-agency meetings varied across local
authorities. Renfrewshire’s model involves daily tasking meetings, whereas some
local authorities met with partner agencies every other day, or every 3 days. 
8.13 Renfrewshire has established a Community Safety Partnership Hub consisting of
statutory, voluntary and community organisations based on the MARAC model (multi-
agency risk assessment conference). This approach is recognised as best practice
and combines a broad range of services to support communities through targeting
anti-social behaviour, its causes and effects and ensures a robust approach to
tackling public protection issues affecting residents in Renfrewshire. 
9.  Legislation and Regulatory Processes 
9.1 Across local authorities different teams are involved with different aspects of
neighbour disputes and antisocial behaviour. This is true of Renfrewshire Council,
whereby specific teams deal with different aspects of neighbour disputes and
antisocial behaviour, dependent on the legislation it falls under and/or potential
actions – between Housing Services, Community Safety and/or Environmental
Health teams. 
9.2 There is a close working relationship between the teams, as well as with the Multi
Agency Community Safety Partnership Hub to ensure patterns are picked up and
responses can be targeted where needed. 
9.3 Actions taken in all cases must be proportionate to the incident and complaints are
classified using 4 key categories. The category the incident falls under will determine
the process followed and the legislation that is applied: 
Category Definition Example
A Serious antisocial behaviour Drug dealing, hate crime, violence
B Antisocial behaviour Frequent disturbances, excessive noise
C Nuisance Cases Vandalism, infrequent disturbances and
private ownership
D
Estate management as a
result of either complaints
or observations
Dispute over communal areas, including
cleaning close; use of drying green; dog
fouling; misuse of bins or storage of waste 
Housing Services Processes & Legislation: Neighbour Disputes & Antisocial
Behaviour
9.4 Renfrewshire Council’s Housing Service follows a set of procedural steps in
proportion to the incident in question. This ranges from visits to both parties;
mediation referrals; support agency referrals; and verbal and written warnings, up to
reducing tenancy rights and eviction in the most serious cases. 
9.5 Most cases are resolved in the early steps of the process, through the early
intervention measures of visits and warnings. For more persistent or serious cases of
nuisance and antisocial behaviour, social landlords, including Renfrewshire Council,
have two main levers that can be used:  
Page 102 of 110

Page 107

1. The Housing (Scotland) Act 2001: the key statutory guidance aimed at
social landlords, including allowing landlords to issue Short Scottish Secure
Tenancies (SSSTs) to address antisocial behaviour and Streamlined
Evictions where there has been a recent criminal conviction punishable by
imprisonment for tenancy related antisocial or criminal behaviour within the
previous 12 months.
2. Tenancy Agreements: set out the legal rights and responsibilities of both
the tenant and the landlord, including levels of behaviour expected from
tenants, members of their household and visitors to their home. 
9.6 Renfrewshire Council’s tenancy agreements make it clear that breaches as a result
of antisocial behaviour may result in legal action to evict, or a reduction in tenancy
rights. A reduction in tenant’s rights is a result of converting a tenancy from a Scottish
Secure Tenancy (whereby tenants have the right to stay in the home for as long as
they wish provided they do not breach the terms of the tenancy) to a Short Scottish
Secure Tenancy (SSST), where tenants only have security for the specified period of
the tenancy (a minimum of 6 months, up to 12 months) because of particular
circumstances, including antisocial behaviour. Tenants must then comply with
specified conditions in order to retain the tenancy. 
9.7 At the end of the specified term of a SSST conversion due to antisocial behaviour, if
issues have been resolved and no further action is required/taken the tenancy
converts automatically back to a Scottish Secure Tenancy again. 
9.8 Following a request, an order for eviction may be granted by the Sheriff Court under
Section 14 of the Housing (Scotland) Act 2001 on any of the grounds within Section 2
of the Act, which includes antisocial behaviour in relation to an action or course of
conduct that causes or is likely to cause alarm, distress, nuisance or annoyance. 
9.9 Local authorities have a statutory duty to rehouse and eviction is a last resort. There
are often more complex needs, and cross-agency working is key to ensure access to
services and support, and to prevent people from falling through the gaps in services. 
Environmental Health: Key Processes and Legislation
9.10 In cases of statutory nuisance (which can include issues with noise, accumulations of
waste, artificial light), procedural steps are followed ranging from visits to the source
of the issue, mediation referrals and verbal and written warnings, to issuing
abatement notices and Fixed Penalty Notices. 
9.11 Most cases are resolved in the early steps of the process without the need for further
escalation. For the more persistent or serious cases of statutory nuisance the main
levers that can be used by the Council are:  
1. The Environmental Protection Act 1990: provisions within Section 79 of
the Environmental Protection Act 1990 set out what can and can’t be dealt
with as statutory nuisance.
2. Abatement Notice: a legal document that imposes specific requirements
on the recipient with timescales, to abate the nuisance or mitigate to a point
that it is no longer causing a nuisance, including noise abatement. 
3. Fixed Penalty Notice: before a Fixed Penalty Notice is issued under the
Environmental Protection Act, an Abatement Notice must have been served.
The Abatement Notice must have expired without the problem being resolved
and there must be a further breach of the Abatement Notice before a Fixed
Penalty Notice can be served. These are generally used for low level
nuisances. 
Page 103 of 110

Page 108

Community Safety Team: Key Processes and Legislation
9.12 The Community Safety Team and multi-agency partners within the Community
Safety Partnership deal with antisocial behaviour. 
9.13 Most complaints are resolved in the earlier stages of the process through early
intervention measures and cross-service working in the Council and in the
Community Safety Hub. For persistent antisocial behaviour the main levers are:  
1. The Antisocial Behaviour (Scotland) Act 2004: the Act makes provision
in connection with antisocial behaviour to deal with people who cause alarm,
distress or annoyance to members of the public. The Act also gives powers to
address neighbour noise issues, such as from parties and loud music which
causes undue nuisance.
2. Interim Antisocial Behaviour Orders: allow the Sheriff Courts to grant an
order to provide more immediate protection from antisocial behaviour prior to
a full court hearing (around 6 weeks).
3. Antisocial Behaviour Orders (ASBOs): preventative orders intended to
protect people in the community affected by antisocial behaviour from further
acts or conduct that would cause them alarm or distress. ASBOs are court
orders which prohibit, either indefinitely or for a specified period of time, the
individual from doing anything described in the order. An ASBO is made in
the civil court, however, breach of an order is a criminal offence. 
9.14 While registered social landlords, including Renfrewshire Council’s Housing Service,
may seek antisocial behaviour orders or even eviction as a last resort, they have no
powers to evict private tenants and/or owner occupiers. However, other services
within the Council and Police Scotland may have some powers that can be used to
influence people to modify their behaviour depending on the nature and severity of
the complaint, e.g. a private landlord who fails the ‘fit and proper’ test by not dealing
with antisocial behaviour of tenants could have their landlord registration revoked
under Section 8 of the Antisocial Behaviour (Scotland) Act 2004. 
10.  Current Estate Management Initiatives and the Estate Management Workshop
10.1 The Council’s approach to estate management and community safety is underpinned
by the strategic outcomes in the Renfrewshire Council Plan 2022-2027. A key
strategic outcome is Place and working together to enhance wellbeing across
communities. 
10.2 The review initially focused on Category B and C antisocial behaviour and neighbour
nuisance complaints. In the course of the review, and in particular speaking with
those with lived experience of neighbour nuisance and antisocial behaviour, the
opportunity for an additional focus on Category D incidents (classed as estate
management) emerged. 
Current Estate Management Initiatives
10.3 There are a large number of examples of good practice being delivered by the
Council across estate management and community safety. Examples include: 
- the Neighbourhood Environmental Trainee Team (NETT): made up of a
Supervisor and a number of trainees seeking employment (aged 16-65) who carry
out work 1 day per week in each of the 4 Housing Neighbourhoods, with a particular
focus on known ‘hot spots’.
- Renfrewshire Council’s Tenant Satisfaction Survey: carried out every 2 years,
this is a valuable measure of success (although responses are from Council tenants
only, not all tenures) that can be used to compare results of initiatives in future years.
- Moorpark Regeneration Project: Neighbourhood Services team, in collaboration
with Housing Services, carried out a targeted intervention in the Moorpark area,
Page 104 of 110

Page 109

focusing on environmental maintenance tasks. This provided a model for similar
interventions across Renfrewshire, with lessons learned and best practices
developed being integrated into the Council’s broader environmental management
strategies, helping to ensure sustained improvements in other communities.
- Cross-Service Collaboration: regular meetings to discuss Neighbourhood
Operations, providing Housing Services, Neighbourhood Services, Public Protection
and Waste Services a platform for continuous dialogue, allowing emerging issues to
be addressed promptly and adapting strategies as needed.
- Team Up 2 Clean Up: an exemplar Council and community partnership working to
create a brighter, more attractive Renfrewshire through community initiatives
including community litter picks and Take the Lead campaign (an initiative to
encourage responsible dog ownership and working together to reduce dog fouling
and anti-social behaviour across Renfrewshire).
- Grass Cutting and Grounds Maintenance: Renfrewshire Council has a 14 day
grass cutting and grounds maintenance cycle between April and October and tackle
a different area of Renfrewshire each day, maintaining open spaces, school playing
fields, public parks, sports pitches and cemeteries as well as grass cutting and hedge
cutting for some residents and Council Housing tenants who require garden
assistance or have common maintenance areas. 
- Data Sharing and Continuous Improvement: between all key Services to support
ongoing development and refinement of maintenance programmes, ensuring
operations are responsive to the needs of the community and allows immediate
concerns to be addressed, but also to shape future work within the 4 Housing
Neighbourhood areas, contributing to long-term improvements. 
10.4 Alongside acknowledging the good practice and high quality services that are
delivered daily, a key action in the Council Plan 2022-2027 is around ensuring we
understand our service delivery, potential gaps in our approaches and have plans for
improvement through ongoing self-assessment. 
10.5 A workshop was held in August 2024, with key internal stakeholders represented
from Housing Services; Environmental Health; Tasking and Development;
Neighbourhood Services; Waste Services; and Procurement. Key areas discussed
included individual and communal gardens and hedges, waste (including misuse of
bins, storage of waste), communal areas and general nuisance, such as dog fouling
and dog barking. 
10.6 The workshop was extremely positive, with officers highlighting opportunities for
improved flow of information and working collaboratively to identify: 
- existing good practice across a range of neighbourhood initiatives 
- opportunities for improvement   
- potential approaches and targeting of activity within existing resources 
10.7 The key actions proposed by the group to be considered for further exploration are
set out below. These proposed actions would require to be fully costed, with robust
business case development. Viable proposals with impacts or changes in budget or
policy would then be taken to the appropriate Board(s) for approval:
-  Housing Services to work together with Neighbourhood Services on work
programming to identify an optimum service delivery model that meets the needs of
both Services. This includes reviewing the deployment of existing resources to
consider a dedicated team to work across properties and grounds related to Council
Housing for grass cutting and cyclical maintenance, including winter works
programming, and coordination ahead of recruitment to ensure sufficient resourcing. 
- explore the potential expansion of the Neighbourhood Environmental Trainee Team
alongside additional potential training opportunities.  
- Procurement, Neighbourhood Services, Housing Services and Environmental
Health to review the Council Wide Specialist Cleaning, Clearing and Ad Hoc Services
Page 105 of 110

Page 110

framework, to explore the specification of this contract and identify opportunities to
optimise service delivery. 
11.  Key Findings of the Review 
11.1 Overall Approach: Renfrewshire Council’s processes and partnership working when
dealing with neighbour disputes and antisocial behaviour are of a high standard
across all key areas. This has been assessed based on benchmarking taking into
account research and interviews with other local authorities, local Housing
Associations and Police Scotland. Processes are clear; assistance is available to all
tenures; Renfrewshire Council provides services which are not consistently provided
across all local authorities; and trauma informed training has been rolled out to
frontline staff to assist when dealing with those impacted by neighbour disputes
and/or antisocial behaviour, as well as dealing with those who may be perpetrating
the behaviour. 
11.2 Early Intervention: The majority of complaints received by staff are resolved at an
early stage and do not escalate to formal stages. All organisations interviewed as
part of the review agreed that preventative work, community relations and early
intervention are key to resolve issues and prevent potential future escalation. 
11.3 Estate Management: Interviews with other local authorities and also with residents
with lived experience of neighbour disputes and antisocial behaviour, highlighted
issues related with estate management as a common source of neighbour disputes.
Issues, including storage of waste, misuse of bins, dog fouling and communal spaces
can be a source of initial tension which, if not captured early, have the potential to
cause neighbour relationships to break down and/or lead to disputes escalating. The
Estate Management workshop highlighted a range of good practice examples that
are already being undertaken collaboratively with regards to estate management,
with some additional opportunities to share knowledge between Services operating
within Estates being considered in scheduling and deployment to streamline and
enhance activity. 
11.4 Communication: 
1. early intervention includes a need for cases to be reported as early as possible.
Information to members of the public around how to report issues, with the options
available to different tenures was believed to be key. Clear advice on how to make a
complaint and who should be contacted can avoid delays in the early stages of the
process, improving the process for the complainer. 
2. it is important to manage expectations and be clear on when the Council can and
can’t take action. It can be frustrating for the complainer if their complaint doesn’t
meet the threshold for further action (or if corroboration can’t be secured).
Communication should include ensuring complainers are aware of potential next
steps or alternative options (e.g. civil action) and any cost implications this may have.
3. for complaints where investigations/follow up action is being taken, keeping
complainers informed is key at all stages of the process. Gathering evidence can be
a painstaking and time consuming process and when regular updates are not given,
it can lead to frustration on the part of the complainer and a feeling that they are not
being listened to or their case is not being dealt with, when this is not the case.
4. staff turnover is unavoidable but can be a source of uncertainty for those whose
home lives and/or mental health are being impacted by antisocial behaviour and/or
neighbour disputes. Handovers, including informing complainers of any changes to
case officers or impacts to timescales, helps to maintain strong relationships.   
Page 106 of 110

Page 111

11.5 Partnership Working: 
1. Partnership working is key to tackling anti-social behaviour. The importance of
cross-agency collaboration in understanding and responding to incidents of anti-
social behaviour was highlighted by all organisations and a whole system approach
with partnership solutions was agreed to be the most effective way of preventing and
addressing antisocial behaviour. 
2. Renfrewshire’s Community Safety Hub model is seen as best practice due to the
joined up working of services collectively address the widespread issues that need to
be taken account of in a holistic way to address antisocial behaviour. This
collaborative approach has a preventative focus alongside support for victims, but
also includes support for those involved in antisocial behaviour, including ensuring
access to recovery services and mental health support services where needed. 
11.6 Complex Root Causes: many organisations highlighted mental health being
impacted by the pandemic and further exacerbated by the cost of living crisis. They
are seeing a rise in complex cases, particularly in relation to mental health and
addiction. Cross-agency working is pivotal to ensure access to services and support,
and prevent people from falling through the gaps in services. Trauma informed
training to frontline staff at Renfrewshire Council has been well received and of great
value to assist officers in their roles, and cases of increasing complexities. 
11.7 Current Legislation: there was consensus when speaking with Local Authorities
and other key stakeholders and organisations that community safety has changed
over the last ten years and that there may be areas of legislation that could be
strengthened to assist frontline staff in their roles. 
12.  Recommendations 
12.1 Overall Approach: the Council has been engaged in the process of the national
refresh to prevent and tackle antisocial behaviour, and it is recommended that this
continues through all channels to influence improved outcomes; improved resources
and tools for dealing with neighbour disputes and antisocial behaviour; and
identification of potential improvements to legislation that could enhance the work
undertaken at a local level. It should be noted that once these national outcomes are
determined, a local refresh of processes and/or training may be required. 
12.2 Estate Management: It is recommended that the following actions are undertaken
as a result of cross-departmental discussions. These proposed actions would require
to be fully costed, with robust business case development. Viable proposals with
impacts or changes in budget or policy would then be taken to the appropriate
Board(s) for approval:
• a collaborative approach to identify an optimum service delivery model to meet
the needs of Neighbourhood Services and Housing Services, including exploring
allocation of a Housing-specific resource for grass cutting and cyclical
maintenance and maintenance of void properties.
• exploration of delivery models which could enable the expansion of grass cutting
service provision for Council Housing tenants who are unable to maintain a
garden.
• exploration of the expansion of the Neighbourhood Environmental Trainee Team
to support the Council alongside additional potential training opportunities.
• Cross-Service review of the Council Wide Specialist Cleaning, Clearing and Ad
Hoc Service framework, exploring impacts on internal capacity, resourcing and
cost/saving implications of delivery of these work packages to current Service
Level Agreements (SLAs) and opportunities to optimise service delivery. 
Page 107 of 110

Page 112

12.3 Training and Development around Complex Root Causes: It is recommended
that trauma informed training is extended to include Environmental Health Officers (in
addition to Housing Officers and the Community Safety team), as EHOs are
experiencing an increase in complex cases and instances where mental health is a
factor in behaviours and/or responses. Refresher training for all Officers is also
recommended on a set rolling programme, from a staff development point of view as
well as a strategic point of view as principles are transferable and can be applied in a
range of community settings. 
12.4 Additional Tools and Technology: It is recommended that Services continue to
explore additional tools to assist reporting, including the use of digital technology that
may be available to increase options for reporting. 
12.5 Communication: It is recommended that the Service:
- carries out a review of correspondence letters issued at each stage of the process
from a trauma-informed perspective to align with findings of the benefits of this
approach highlighted as part of the enhanced training from Officers, as well as
findings from across other areas of the Council. 
- carries out a refresh of the website content to ensure that it is as informative and
accessible as possible. This includes encouraging early reporting through clearly
identified channels to assist early interventions; signposting to agencies and support;
inclusive and clear language; and information to assist understanding of where follow
up action can and can’t be taken by the Council and partner organisations to ensure
clarity for those seeking advice online. This should include promotion of availability of
guidance in different languages to ensure access for all within our multi-lingual
communities. 
- continues to recognise the need for traditional methods of reporting and
communication and the need for services to be promoted through non-digital means,
e.g. how to report issues and support that is available, including mediation and victim
support to assist early intervention and encourage early reporting through tenant
newsletters, community newsletters, posters in community spaces, libraries, etc. This
aligns with recent findings in the Tenant Satisfaction Survey which found that just
over a third of Council tenants did not use the internet and should include promotion
of availability of guidance in different languages to ensure access for all within our
multi-lingual communities. 
12.6 As this report does not propose any policy or service change, no equality and human
rights impact assessments are required at this time. However, if any change to policy
or service position were to be proposed, then full equality and human rights
assessments would be required and assessment made in line with the Council’s
Fairer Scotland Duty by the service responsible.
Page 108 of 110

Page 113

Implications of the Report 
1. Financial - None directly arising from this report.  
2. HR & Organisational Development - None directly arising from this report. 
3. Community/Council Planning - None directly arising from this report.   
4. Legal - None directly arising from this report. 
5. Property/Assets – None directly arising from this report. 
6. Information Technology – None directly arising from this report. 
7. Equality and Human Rights - The Recommendations contained within this report
have not been assessed in relation to their impact on equalities and human rights- as
the paper sets out the scope for a review process rather than proposing any changes
to services. If any change to policy or service position were to be considered in
future, a full equality and human rights impact assessment will be undertaken.     
8. Health and Safety - None directly arising from this report. 
9.  Procurement - None directly arising from this report. 
10. Risk - None directly arising from this report. 
11.  Privacy Impact - None directly arising from this report. 
12. Climate Risk - None directly arising from this report. 
13. Children’s Rights - None directly arising from this report. 
14. COSLA Policy Position - No impacts directly arising from this report.
___________________________________________________________________ 
List of Background Papers: 
Audit, Risk and Scrutiny Board Annual Programme
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, January 2023
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, March 2023
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, January 2024
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, March 2024
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, May 2024
Neighbour Disputes Paper - Audit, Risk and Scrutiny Board, September 2024 
The foregoing background papers will be retained within Chief Executive’s Service for
inspection by the public for the prescribed period of four years from the date of the meeting.
The contact officer within the Service is the Climate Emergency Lead Officer, Roz Smith,
who can be contacted at roz.smith@renfrewshire.gov.uk   
Author:   Roz Smith, Climate Emergency Lead Officer, Chief Executive’s Service 
Page 109 of 110

Page 114

Page 110 of 110