Democracy Spraffa

Agenda Document Pack - Audit, Risk and Scrutiny Board - 19/08/2024

Renfrewshire Council · 19 August 2024
Back to Audit, Risk and Scrutiny Board — 19 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

Notice of Meeting and Agenda
Audit, Risk and Scrutiny Board 
Date Time  Venue
Monday, 19 August 2024 15:00 Council Chambers (Renfrewshire),
Council Headquarters, Renfrewshire
House, Cotton Street, Paisley, PA1 1AN 
MARK CONAGHAN
Head of Corporate Governance 
Membership 
Councillor Andy Doig (Convener):     Councillor Janis McDonald (Depute Convener):    
Councillor Jennifer Adam:  Councillor Chris Gilmour:  Councillor John Gray:  Councillor
Lisa-Marie Hughes:  Councillor Robert Innes:  Councillor James MacLaren:  Councillor
Ben Smith:   
Further Information 
This is a meeting which is open to members of the public. 
A copy of the agenda and reports for this meeting will be available for inspection prior
to the meeting at the Customer Service Centre, Renfrewshire House, Cotton Street,
Paisley and online
at http://renfrewshire.cmis.uk.com/renfrewshire/CouncilandBoards.aspx
For further information, please email
democratic-services@renfrewshire.gov.uk 
Members of the Press and Public 
Members of the press and public wishing to attend the meeting should report to the
customer service centre where they will be met and directed to the meeting. 
Hybrid Meeting 
Please note that this meeting is scheduled to be held in the Council
Chambers.  However, it is a hybrid meeting and arrangements have been made for
members to join the meeting remotely should they wish.

Page 2

Webcasting of Meeting 
This meeting will be filmed for live or subsequent broadcast via
the Council’s internet site – at the start of the meeting the
Convener will confirm if all or part of the meeting is being
filmed.  To find the webcast please navigate to 
https://renfrewshire.public-i.tv/core/portal/home 
Apologies 
Apologies from members. 
Declarations of Interest and Transparency Statements 
Members are asked to declare an interest or make a
transparency statement in any item(s) on the agenda and to
provide a brief explanation of the nature of the interest or the
transparency statement. 
AUDIT 
1 Summary of Internal Audit Reports for the period 14
May 2024 to 30 June 2024 
Report by Interim Chief Auditor. 
1 - 8 
2 Internal Audit and Counter Fraud Performance for the
Period ending 30 June 2024 
Report by Interim Chief Auditor. 
9 - 16 
3 Summary of Internal Audit Activity in Partner
Organisations for the Period Ending 01 May 2024 to 30
June 2024 
Report by Interim Chief Auditor. 
17 - 54

Page 3

MONITORING & REVIEWING SERVICE DELIVERY PERFORMANCE
POLICIES AND PRACTICE 
4 Actions Monitoring Report - Dargavel Primary School 
Report by Chief Executive. 
55 - 130 
5 Summary of recent Audit Scotland publications 
Report by Director of Finance & Resources. 
131 - 142 
AUDIT EXEMPT 
EXCLUSION OF PRESS AND PUBLIC 
The Board may by resolution exclude the press and public
from the meeting during consideration of the following
items of business as it is likely, in view of the nature of the
business to be transacted, that if members of the press and
public are present, there could be disclosure to them of
exempt information as defined in paragraphs 1 of Part I of
Schedule 7A of the Local Government (Scotland) Act, 1973. 
6 Summary of Internal Audit Investigation Reports for the
period 01 May 2024 to 30 June 2024 
Report by Interim Chief Auditor. 
DEVELOPMENT SESSION 
7 Governance Arrangements for the City Region 
Presentation by Programme Director (City Deal & Infrastructure). 
PLEASE NOTE THAT THIS SESSION WILL NOT BE
WEBCAST.

Page 4

No embedded text on this page.

Page 5

___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 19 August 2024
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Summary of Internal Audit Reports for period 14 May to 30 June
2024
___________________________________________________________________
1. Summary
1.1 In line with the Public Sector Internal Audit Standards, Internal Audit
must communicate the results of each engagement to the Board. To
comply with this requirement, Internal Audit submits regular reports
on the findings and conclusions of audit engagements to the Audit,
Risk and Scrutiny Board. 
1.2 Appendix 1 provides details those audit engagements completed
during the period 14 May to 30 June 2024 with the overall assurance
rating and the number of recommendations in each risk category.
The committee summary for each report is also attached. For each
audit assignment where recommendations have been made, the
relevant managers have put action plans in place to address the
issues raised. 
1.3 In addition to the reports listed in the Appendix, Internal Audit has an
ongoing commitment to: 
• A range of corporate and service initiatives;
• Progressing of information security matters in partnership with
ICT and Legal Services;
• The regular provision of advice to departmental officers;
• The provision of internal audit services to the associated
bodies for which Renfrewshire Council is the lead authority
and to OneRen and Renfrewshire Health and Social Care
Integrated Joint Board;
Item 1
Page 1 of 142

Page 6

• Co-ordination of the Council’s corporate risk management
activity;
• Management of the counter fraud team;
• Management of the risk management and insurance team.
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to consider and note the Summary of Internal Audit
Reports finalised during the period from 14 May to 30 June 2024. 
___________________________________________________________________
Implications of the Report
1. Financial - None 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of good
corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights – None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The summary reported relates to the delivery of the risk-based internal
audit plan. 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk - None 
________________________________________________________________
Author:           Karen Campbell, Interim Chief Auditor– 07768354651
Page 2 of 142

Page 7

Appendix 1 
Renfrewshire Council 
Internal Audit Service 
Update for Audit, Risk and Scrutiny Board 
Final Audit Reports issued from 14 May – 30 June 2024 
Category  Service  Engagement  Assurance
Rating
Recommendation Ratings
Critical Important Good
Practice
Service
Improvement
Assurance Finance &
Resources
Treasury Management Reasonable
Assurance 0 2 4 0  
Project Management Substantial
Assurance 0 0 0 0 
Note  – No assurance rating can be given in respect of investigation assignments                 
Assurance Level 
Substantial Assurance • There is a sound system of internal control designed to achieve the objectives of the area being reviewed. 
• The control processes tested are being consistently applied. 
Reasonable Assurance • The internal control processes are generally satisfactory with some areas of weakness being identified that could
put some objectives of the area being reviewed at risk
• There is evidence that the level of non-compliance with some of the control processes may put some of the
objectives of the area being reviewed at risk. 
Limited Assurance • Weaknesses in the system of internal controls are such as to put the objectives of the area being reviewed at risk. 
• The level of non-compliance puts the objectives of the area being reviewed at risk. 
No Assurance • Control processes are generally weak with significant risk to the achievement of the objectives of the area being
reviewed. 
Page 3 of 142

Page 8

• Significant non-compliance with control processes leaves the processes/systems open to error or abuse. 
Recommendation
Rating 
Service Improvement  Implementation will improve the efficiency / housekeeping of the area under review.
Good Practice  Implementation will contribute to the general effectiveness of control.
Important  Implementation will raise the level of assurance provided by the control system to acceptable levels.
Critical  Addresses a significant risk, impacting on the objectives of the area under review. 
Page 4 of 142

Page 9

Internal Audit Report
FINANCE & RESOURCES
Treasury Management (A0089/2024/001) 
Date: June 2024 
COMMITTEE SUMMARY 
Audit Objectives
A review was undertaken of the arrangements for making payments through the Treasury
team. The objectives of the review were to ensure that: 
1. Payments are only processed by the Treasury team where there is no other
suitable alternative method.
2. There are documented processes in place for the payment function within the
Treasury team.
3. Requests for payments are supported by properly completed documentation and
appropriately authorised by Service requesting them.
4. Payments are appropriately authorised prior to payment.
5. There is adequate separation of duties within the payment processes. 
Audit Scope
1. Interviewed the appropriate officers to ascertain the system in place in relation to
payment processes within the Treasury team.
2. Undertook a series of tests to ensure the system is adequate and operating as
intended. 
Key Audit Assurances
1. In the sample of payments made tested, requests for payments were supported by
properly completed documentation.
2. For the payments tested, there was adequate separation of duties in the Treasury
team between the officer who put forward each payment request and the officer
who approved the payments. 
Key Audit Risks
1. Where payment requests are not checked by Treasury officers to ensure they are
approved by an authorised signatory, there is a risk that payment requests from
services are not appropriately authorised.
2. When a manager with single authorisation access requests a payment and also
has the ability to authorise that payment, there is a risk of fraud or error. 
Overall Audit Opinion
Discussions are ongoing between Treasury supervisors and Purchase to Pay supervisors
as to which payment categories that would be more suitable for the Purchase to Pay team
to administer and where it is more appropriate for payments to be administered by the
Purchase to Pay team, they should be transferred across as soon as possible. 
Page 5 of 142

Page 10

Internal Audit Report
FINANCE & RESOURCES
Treasury Management (A0089/2024/001) 
Date: June 2024 
In order to improve the segregation of duties and approval controls in the payment
processes, recommendations were made in relation to the  Corporate Administrator user’s
access to the banking system and the approval request process for payments to be made. 
Management Commentary
Work is ongoing to transfer several categories of regular scheduled payments from
Treasury to the Creditors section to ensure they are processed through our main
purchasing/payment system.  We have also strengthened the approval checking
processes for payment requests received from Services by the Treasury Section and work
is ongoing to implement the other audit recommendations.   
Page 6 of 142

Page 11

Internal Audit Report
FINANCE & RESOURCES
Project Management (A0087/2024/001) 
Date: June 2024 
COMMITTEE SUMMARY 
Audit Objectives
In response to the concerns highlighted in the independent review of the provision of
Dargavel Primary School, the Council committed to undertake a health check assessment
on major capital programmes to provide reassurance in respect to all aspects of
governance, control, reporting and management of programmes. Internal Audit have
undertaken a review of the health check assessments carried out for the City Deal &
Infrastructure and the Housing Led Regeneration & Renewal Programmes to provide a level
of independent assurance. 
The objectives of the review were to ensure that:
1. The health check assessment process is robust and covers all the expected
elements of good project governance.
2. The reviews have been completed within a reasonable timescale.
3. There are plans for the assessment process to be rolled out across other
projects/programmes.
4. Actions arising from the assessment have been implemented or are planned to be
implemented. 
Audit Scope
1. Interviewed the relevant officers to obtain the required information and
documentation relating to the health checks undertaken on the City Deal &
Infrastructure and the Housing Led Regeneration & Renewal programmes.
2. Prepared and carried out a series of tests to meet the detailed audit objectives. 
Key Audit Assurances
1. The health check assessment process is robust and covers all the expected
elements of good project governance.
2. The health check assessments were completed and results presented to the
Corporate Management Team within a reasonable timescale. 
3. Plans to roll out the health check assessment process across other major projects
/ programmes, specifically the school estate programme, will be considered once
the governance arrangements which are currently being refreshed are established.
4. The actions arising from the assessments have been implemented with twice
yearly reports being prepared for the Corporate Management Team and the
relevant policy board appropriately scheduled. 
Key Audit Risks
There are no key risks to report. 
Page 7 of 142

Page 12

Internal Audit Report
FINANCE & RESOURCES
Project Management (A0087/2024/001) 
Date: June 2024 
Overall Audit Opinion
The health check assessments carried out on the City Deal & Infrastructure and the
Housing Led Regeneration & Renewal Programmes were found to be robust with actions
arising from the presentations to the Corporate Management Team being addressed.  The
auditor has no recommendations to make in this regard and has therefore provided a
substantial assurance rating in this area. 
Management Commentary
N/A as no key risks identified. 
Page 8 of 142

Page 13

___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 19 August 2024
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Internal Audit and Counter Fraud Progress and Performance for
Period to 30 June 2024
___________________________________________________________________
1. Summary
1.1 The Internal Audit Annual Plan was approved by the Audit, Risk and
Scrutiny Board on 18 March 2024. Internal Audit measures the progress
and performance of the team on a regular basis using a range of
performance indicators.  This report monitors progress from 1 April 2024
to 30 June 2024, in terms of the delivery of the Audit Plan for the year
and compares actual performance against targets set by the Director of
Finance and Resources. 
1.2 In terms of Counter Fraud, no formal performance targets for fraud
investigation have been established for the following reasons.  A major
part of their work involves being the single point of contact (SPOC) for
the Department for Work and Pension’s (DWP) Single Fraud
Investigation Service and the Service Level Agreement for this work
contains time targets for completing this work.  The types of fraud
referrals received to date are wide ranging and the team’s objective is to
concentrate on investigating those referrals considered to contain the
greatest fraud risk.  They are also involved in promoting fraud awareness
and assisting with the implementation of adequate fraud prevention
measures within the Council.  
1.3 All of the Internal Audit Team and Counter Fraud Team are currently
working on a hybrid basis and also undertake home/site visits when the
need arises.  We also provide advice and support where necessary to
council services.
Item 2
Page 9 of 142

Page 14

1.4 The report details progress against local and national initiatives involving
Internal Audit and the Counter Fraud Team from 1 April 2024 to 30 June
2024. 
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to note the Internal Audit and Counter Fraud Team
progress and performance to 30 June 2024. 
_________________________________________________________
3. Background
3.1 The progress and performance of the Internal Audit Team is subject to
regular monitoring using a number of performance measures.  The
Director of Finance and Resources has set annual targets for the team
to demonstrate continuous improvement. In terms of the Counter Fraud
team, there are time targets in place for responding to requests from the
DWP’s Single Fraud Investigation Service.  Due to the diverse nature of
fraud referrals no formal performance targets have been established and
the outcomes from investigations is regularly monitored by management. 
In addition, the Counter Fraud Team are heavily involved in fraud
prevention measures within the Council.
3.2 Internal Audit and the Counter Fraud Team support a variety of local and
national initiatives through participation in professional practitioner
groups and co-ordination of national initiatives such as the National
Fraud Initiative.
3.3 This report measures the progress and performance of both the Internal
Audit and Counter Fraud Team for the period from 1 April 2024 to 30
June 2024.
4.                 Internal Audit Resource
4.1  The Chief Auditor retired in June 2024.  Currently the Assistant Chief
Auditor is covering this post.  
4.2 Given both the size of the team and the composition, there is some risk
that given generally accepted difficulties with the recruitment of
professional audit and fraud prevention staff within local government  the
resilience of the team may be an issue should the situation arise where
even one or two staff leave the team. It is likely there would be an
immediate impact on the service’s ability to deliver the internal audit plan. 
Page 10 of 142

Page 15

4.3 Informal discussions have recently been held with the Chief Financial
Officers (Section 95 Officers) of Inverclyde Council and West
Dunbartonshire Council to consider these risks and to begin to explore
possible options which would address the resilience issues all three
councils are facing.  It should be noted that the delivery of financial
savings is not an objective of this exercise, and each Chief Financial
Officer is committed to maintaining the current level of resource.
4.4 As a result, a report was submitted and approved by the Finance,
Resources and Customer Services Policy Board on 13 June 2024 to
enable further  development work on potential  options  in conjunction
with these neighbouring councils  to be explored.  The aim is to develop
a list of potential models, highlighting the associated issues, risks and
benefits for consideration at a future Finance, Resources and Customer
Services Policy Board.
5.   Internal Audit Team Performance
(a) Percentage of audit plan completed as at 30 June 2024 
This measures the degree to which the Audit Plan has been completed.
Actual 2023/24 Annual Target
2024/25
Audit Plan
Completion
Target to 30
June 2024
Audit Plan
Completion
Actual 30
June 2024
93.2% 90.0% 25% 25.7% 
The Annual Target for this indicator in prior years was 95% which has
not been achieved for a few years. The Internal Audit Section  is a small
team.  It  was recognised that any unplanned absence or unplanned work
above the budgeted average can have a considerable effect on this
indicator.  For this reason, the Director of Finance and Resources has
agreed for the 2024/25 annual target to be reduced to a more realistic
but challenging target of 90%.
The current audit plan completion indicator is slightly above target.    
(b) Percentage of assignments complete by target date 
This measures the degree with which target dates for audit work have
been met.
Target 2024/25 Actual to 30 June 2024
95.0% 100%           
Actual performance is ahead of the target set for the year.  
(c) Percentage of audit assignments completed within time budget
Page 11 of 142

Page 16

This measures how well the time budget for individual assignments has
been adhered to. 
Target 2024/25 Actual to 30 June 2024  
95.0% 100%
Actual performance is ahead of the target set for the year, although this
is likely to reduce over the remainder of the year.   
(d) Percentage of audit reports issued within 6 weeks of completion of
audit field work 
This measures how quickly draft audit reports are issued after the audit
fieldwork has been completed.
Target 2024/25 Actual to 31 December 2024
95.0% 100%
Actual performance is ahead of the target set for the year, although this
is likely to reduce over the remainder of the year.  
6. Review of the 2024/25 Internal Audit Plan 
6.1 Our 2024/25 Audit Plan is subject to ongoing review in light of any
organisational risks arising, and also to determine whether any
assignments will have to be amended or cancelled as result of us being
unable, for any reason, to undertake the work planned. At this stage we
are not recommending any further amendments to the plan. 
6.2 Although a vacancy factor was built into the Audit Plan as it was known
that the Chief Auditor was retiring, this may result in assignments being
completed later than planned and therefore progress will continue to be
closely scrutinised by management. 
6.3 Any proposed amendments to the audit plan will be brought to this Board
for approval.
7   Counter Fraud Team Progress and Performance
7.1 In line with the Service Level Agreement, the Counter Fraud Team act
as the Single Point of Contact (SPOC) to route potential housing benefit
fraud referrals to the DWP, liaise with the Council’s Housing Benefit
Team and DWP Fraud Officers and retrieve the necessary evidence for
the DWP Fraud Officers from the Housing Benefit System.  Where a
suspicion of fraud arises, the team investigate and report their findings
to management. Where appropriate, follow-on action is taken, such as
reporting the matter to Police Scotland for further investigation, or directly
to the Procurator Fiscal. In addition, they also work jointly with DWP
Fraud Officers on criminal fraud investigations which focuses on the
investigation and prosecution of the Local Authority administered Council
Tax Reduction Scheme and Social Security benefit fraud. In addition to
investigation work the team also undertake fraud prevention work.
Page 12 of 142

Page 17

7.2 During this quarter, we have been working on the various fraud referrals.   
As part of our fraud prevention work, we are continuing to validate the
numerous bank account or remittance contact changes received from
the Council’s suppliers and contractors and the details supplied by new
Housing Applicants. 
7.3 A new Counter Fraud Officer was appointed in May 2024 into a vacant
position and the team is now fully staffed.
7.4 The financial and non-financial results for the period (April 2024 to June
2024) are noted in the table below. 
Financial Outcomes Period to 30 June 2024
(£)
Cash savings directly attributable to
preventative counter fraud intervention
2,201
Cash recoveries in progress directly
attributable to counter fraud
investigations
7,413 
Notional savings identified through
counter fraud investigation, (e.g. housing
tenancy and future council tax)
98,727
Housing Benefit Savings Attributable to
Joint Working by Counter Fraud and
DWP Counter Fraud Officers
7,841
Other DWP Benefit or Tax Credit
Savings identified through other Counter
Fraud work or through joint working with
DWP
5,955
Non-Financial Outcomes Period to 30 June 2024
Housing properties recovered 1
Housing applications amended/cancelled 2
Housing Allocation Priority Changed 0
Blue badge misuse warning letters
issued
6
Blue Badges Cancelled 2
Supplier/Contractor Checks Undertaken 45
7.5 Our notional savings are based on the methodology prepared by the
Cabinet Office. 
8.  Local and National Initiatives   
Scottish Local Authorities Chief Internal Auditors Group 
8.1 The Local Authorities Chief Internal Auditors Group met in June and
received updates from the Chairs of the various specialised audit
focused topic groups including sustainability/climate change group and
Page 13 of 142

Page 18

data analytics which have been established.  A presentation was also
given on the financial sustainability and the role of internal audit. 
Scottish Local Authorities Investigation Sub-Group 
8.2 The Local Authorities Investigation Sub-Group also met in June and
received a presentation from Audit Scotland on the forthcoming 2024/25
National Fraud Initiative. 
8.3 Preparation work for this exercise has just commenced by the Counter
Fraud team. and we will be required to submit the Council’s data in
October 2024. 
External Quality Assessment 
8.4  We have also finalised the external quality assessment of Inverclyde
Council Internal Audit Service and the final report has been submitted to
their management. 
_________________________________________________________
Implications of the Report
1. Financial - The Council has in place arrangements to recover the any
overpayments identified from the work of the Counter Fraud Team and
the National Fraud Initiative. 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of
good corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights - None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The progress and performance reported relates to the delivery of
the risk-based internal audit plan and the mitigation of the risk of fraud
and error. 
Page 14 of 142

Page 19

11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk - None 
________________________________________________________________
Author:           Karen Campbell, Interim Chief Auditor – 07768354651
Page 15 of 142

Page 20

Page 16 of 142

Page 21

___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 19 August 2024
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Summary of Internal Audit Activity in Partner Organisations May
2024 to June 2024
___________________________________________________________________
1. Summary 
1.1 Members of the Audit, Risk and Scrutiny Committee expressed an interest in
the outcomes of audits undertaken in partner organisations. A proposed
revision to the Audit, Risk and Scrutiny Board’s Terms of Reference, to
facilitate this, was agreed at Council on 4 May 2024. 
1.2 This report provides members with a summary of the internal audit activity
within each partner body from 1 May 2024 to 30 June 2024. 
1.3 Renfrewshire Valuation Joint Board –The 2023/24 Internal Audit annual
report, summarising the audit activity for the year and providing the Chief
Auditor’s annual opinion was considered by the Board on 24 May 2024 and
is attached in Appendix 1. 
1.4 Scotland Excel Joint Committee - The 2023/24 Internal Audit annual report,
summarising the audit activity for the year and providing the Chief Auditor’s
annual opinion was considered, by the Executive Sub-Committee on 17 May
2024 and is attached in Appendix 2. One audit is currently in progress in
relation to contract monitoring (implementation of collaborative
procurement), this is nearing completion and will be reported to their
Executive Sub-Committee once finalised. 
1.5 Renfrewshire Integration Joint Board - The 2023/24 Internal Audit annual
report, summarising the audit activity for the year and providing the Chief
Auditor’s annual opinion was considered, by their Audit, Risk and Scrutiny
Committee. on 21 June 2024 and is attached in Appendix 3. During the
Item 3
Page 17 of 142

Page 22

reporting period, one audit review was finalised in relation to compliance with
the Local Code of Corporate Governance and is attached in Appendix 4. 
1.6 Glasgow & the Clyde Valley Strategic Development Planning Authority Joint
Committee - The 2023/24 Internal Audit annual report, summarising the audit
activity for the year and providing the Chief Auditor’s annual opinion was
considered by the Joint Committee on 10 June 2024 and is attached in
Appendix 5. 
1.7 Glasgow City Region City Deal – Internal audit services are provided by
Glasgow City Council Internal Audit Services, finalised reports for each
completed audit engagement are reported to the Glasgow City Region
Cabinet and the reports are shared with member Council’s. The Chief
Auditor for Renfrewshire Council meets regularly with the City Region
Auditors and provides them with an annual assurance statement to support
the Glasgow City Region annual governance statement. During the reporting
period, no audit reviews were finalised. 
___________________________________________________________________ 
2. Recommendations
2.1 All of these Audit Reports and Summaries have been submitted and
considered by the partner organisations’ audit committees.  Members are
therefore invited to note the content of the audit reports and audit summaries.
__________________________________________________________________
Implications of the Report
1. Financial - None 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of good
corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights – None 
8. Health & Safety – None
Page 18 of 142

Page 23

9. Procurement - None 
10.  Risk - The summary reported relates to the delivery of the risk-based internal
audit plans for the partner bodies 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk - None 
________________________________________________________________
Author:           Karen Campbell, Interim Chief Auditor
Page 19 of 142

Page 24

Appendix 1 
Renfrewshire Valuation Joint Board
Internal Audit Annual Report 
2023-2024 
Renfrewshire Council
Internal Audit 
May 2024  
Page 20 of 142

Page 25

Page 21 of 142

Page 26

Renfrewshire Valuation Joint Board 
Internal Audit Annual Report 2023/2024 
Contents 
Page 
1.    Introduction  1 
2.  Responsibilities of Management and Internal Audit  2 
3.    Internal Audit Activity in 2023/24  2 
4.      Internal Audit Performance    4 
5.  Planned Audit Work for 2024/25  5 
6.  Audit Assurance Statement  5 
Page 22 of 142

Page 27

- 1 -
Renfrewshire Valuation Joint Board
Internal Audit Annual Report   
1 April 2023 – 31 March 2024 
1. Introduction 
1.1 Renfrewshire Council provides an internal audit service to Renfrewshire
Valuation Joint Board.  This includes: 
• The compilation of an annual audit plan following consideration and
evaluation of those areas of greatest risk in the organisation’s
operation, and consultation with the Assessor and Electoral
Registration Officer, Renfrewshire Valuation Joint Board; 
• Delivery of the planned audit assignments;
• Follow up of previous audit recommendations;
• Provision of any ongoing advice and support on audit and risk
management related matters;
• Provision of an Annual Report and Assurance Statement, and
presentation to elected members at the board of Renfrewshire
Valuation Joint Board. 
1.2 The Service operates in accordance with the Public Sector Internal Audit
Standards which defines Internal Audit’s role as: 
“......an independent, objective assurance and consulting activity designed to
add value and improve an organisation’s operations. It helps an organisation
accomplish its objectives by bringing a systematic, disciplined approach to
evaluate and improve the effectiveness of risk management, control and
governance processes.” 
1.3 In line with the Standards, the purpose of this Annual Report is to report on: 
• The outcome of the planned Internal Audit reviews 2023/24 relating to  
Renfrewshire Valuation Joint Board;
• The outcome of Internal Audit reviews of supporting Renfrewshire
Council corporate systems;
• Internal audit performance;
• Planned audit work for 2024/25;
• The annual assurance statement which provides an opinion on the
overall adequacy and effectiveness of the Board’s internal control
environment. 
Page 23 of 142

Page 28

- 2 -
2. Responsibilities of Management and Internal Audit 
2.1 It is the responsibility of management to ensure that the areas under their
control are adequate and effective and that there is a sound system of internal
control which facilitates the effective exercise of the organisation’s functions
and which includes arrangements for the management of risk. 
2.2 Internal Audit is not a substitute for effective control exercised by
management as part of their responsibilities. Internal Audit’s role is to
independently assess the adequacy of the risk management, internal controls
and governance arrangements put in place by management and to undertake
sufficient work to evaluate and conclude on the adequacy of those controls for
the period under review. 
2.3 The internal audit team will ensure that independence and objectivity are
maintained in line with the PSIAS including where non-audit work is
undertaken. Internal auditors will have no operational responsibilities. There
have been no impairments impacting on the Chief Auditor’s independence
and the team has been adequately resourced during the year. 
3. Internal Audit Activity during 2023/2024 
3.1 One specific engagement was undertaken during 2023/24, which related to
risk management. A summary of the report was considered by the Board on
17 November 2023, the conclusion this review is summarised in table 1
below: 
Table 1 
Audit Area Conclusion
Information Governance • Substantial Assurance 
The review identified that satisfactory
arrangements in place for the handling of personal
information within Renfrewshire Valuation Joint
Board. The systems in place for the Electoral
Register, Valuation Roll and Council Tax dwellings
are well controlled and regularly reviewed. Staff are
regularly trained and made aware of their
responsibilities for handling personal data.
As a result, there were no audit findings identified
during this review and the auditor has made a
provision of substantial assurance for the areas
tested. 
3.2 The Annual Report for 2022/2023 was submitted to the Authority on 26 May
2023. 
Page 24 of 142

Page 29

- 3 -
3.5 The implementation rate of audit recommendations is a measure of
operational culture and effectiveness.  During 2023/24, there were no
recommendations that required to be followed up. 
3.5 Internal Audit also carried out reviews of the main corporate systems
operating within Renfrewshire Council which support the Board’s activity. The
main findings in relation to these are summarised in Table 2 below and
Renfrewshire Council management have agreed to implement the audit
recommendations made in relation to each review: 
Table 2 
Audit Area Conclusion
Debt Management Reasonable Assurance 
Minor improvements have been
recommended in relation to timeous
raising of invoices and documenting the
strategy for debt management. 
Disaster Recovery Limited Assurance
The audit identified scope for
improvement in the existing
arrangements. Recommendations were
made to enhance and strengthen
controls; including development of a
central register of critical systems,
formalizing ICT procurement guidance,
and seeking assurance from software as
a service providers regarding their ability
to meet disaster recovery requirements.
Payroll Overpayment Process Reasonable Assurance 
Improvements in processes and
increased awareness over recent years
has resulted in the value of
overpayments being significantly
reduced. By far, the main reason for
overpayments occurring is late
notification of changes by managers
within the employing service. The auditor
has recommended that clear and
accessible guidance should be made
available to service management, along
with regular communications to ensure
that newer managers are aware of the
deadlines and where they can access
relevant guidance.   
4. Review of Internal Audit Performance 
4.1 Internal Audit produces regular reports on its performance during the year to
the Renfrewshire Council, Audit, Risk and Scrutiny Board, against a range of
measures set annually by the Director of Finance and Resources. These
Page 25 of 142

Page 30

- 4 -
targets are set for all internal audit engagements and include Renfrewshire
Council and other associated bodies, for which the team provides internal
audit services. Table 3 shows the actual performance against targeted
performance for the year. 
Table 3 
Internal Audit Performance 2023/24 
Performance measure  Target 2023/24 Actual 2023/24
% of audit assignments         
completed by target date
95% 92%
% of audit assignments completed
within time budget
95% 98.5%
% completion of audit plan for the
year*
95% 98.5%
* this measures the completion percentage as at 31 March.  100% of the plan is ultimately delivered through the
finalisation of the outstanding elements in the new financial year.  
4.2 The percentage completion of the audit plan is slightly below the target set for
the year.  This was due to the level of unplanned leave and the additional time
attributed to unplanned work. It should be noted that this had no effect on the
planned reviews for the RVJB for 2023/24 which are 100% complete.  The
actual performance for the year for the two other indicators, is above the
target performance level. 
4.3 The PSIAS require the Chief Auditor to develop and maintain a quality
assurance and improvement programme (QAIP) that covers all aspects of the
internal audit activity. The QAIP must include both periodic internal self-
assessments and five-yearly external assessments, carried out by a qualified,
independent assessor from outwith the organisation. 
4.4 We continued to participate in the Scottish Local Authorities Chief Internal
Auditors’ Group peer review process. Our most recent external assessment
was reported to the Council’s Audit, Risk and Scrutiny Board in May 2023 and
included 7 recommendations for improvement, all recommendations have now
been completed. The annual internal self-assessment process has concluded
that the internal audit service fully complies with the PSIAS. 
Risk Management 
4.6 The internal audit service through the Risk Manager, provides advice and
support to the RVJB officers, as required. 
5. Planned Work for 2024/25 
5.1 Following a risk based assessment of the activities of the Renfrewshire
Valuation Joint Board, the audit plan for 2024/2025 provides for a review of
the valuation system for non-domestic rates and ad-hoc internal control
Page 26 of 142

Page 31

- 5 -
advice, reactive investigative work, follow-up of previous audits and risk
management advice. 
6. Audit Assurance Statement 
6.1 Internal Audit has performed its work in accordance with the role defined in
paragraph 1.2.  The audit work performed has been reported to the Assessor
and Electoral Registration Officer, and to the Board. Where areas for
improvement in internal control have been identified appropriate
recommendations have been made and accepted for action by management.  
6.2 In view of the continued challenges common to all public bodies, there will be
a requirement for the council and the bodies for which it is host authority to
exercise very close scrutiny over expenditure over financial management and
compliance with overarching governance arrangements, and this area will
continue to receive due internal audit attention.  
6.3 It is not feasible for the system of internal control to be without any weakness. 
It is important to balance the risks involved in accepting systems limitations
with the consequences if a problem emerges. Internal Audit recognises this
and assesses this in its reporting mechanism.   
6.4 There are corporate systems and processes within Renfrewshire Council that
the Renfrewshire Valuation Joint Board rely upon. It can be seen from Table 2
above that some of these processes require to be improved to provide a
reasonable level of assurance. Renfrewshire Council management has
agreed to implement the recommendation made by internal audit, in relation
to these reviews. In this context, it is considered that reasonable assurance
can be placed upon the adequacy and effectiveness of the Renfrewshire
Valuation Joint Board’s internal control, risk management and governance
arrangements, as evidenced by:- 
• The results of the audit work in 2023/24 in relation to the corporate      
systems which supported the Renfrewshire Valuation Joint Board’s
activities, and to specific work carried out in relation to those activities. 
• Management action in response to audit recommendations. 
• Management’s self-assessment of internal control, risk management
and governance arrangements. 
• The regular review and updating of the Local Code of Corporate
Governance by the Council in accordance with the CIPFA/SOLACE
framework for corporate governance requirements, and of the
corporate governance arrangements within Renfrewshire Valuation
Joint Board. 
Page 27 of 142

Page 32

- 6 -   
Signed     
Chief Auditor     
Date          24 May 2024  
Page 28 of 142

Page 33

Scotland Excel
Internal Audit Annual Report 
2023-2024 
Renfrewshire Council
Internal Audit 
May 2024  
Page 29 of 142

Page 34

Scotland Excel 
Internal Audit Annual Report 2023/2024 
Contents 
Page 
1.    Introduction  1 
2.  Responsibilities of Management and Internal Audit  2 
3.    Internal Audit Activity during 2023/24  2 
4.      Review of Internal Audit Performance    3 
5.  Planned Audit Work for 2024/25  4 
6.  Audit Assurance Statement  5 
Page 30 of 142

Page 35

- 1 -
Scotland Excel 
Internal Audit Annual Report   
1 April 2023 – 31 March 2024 
1. Introduction 
1.1 As host Authority, Renfrewshire Council provides an internal audit service to
Scotland Excel.  This includes: 
• The compilation of an annual audit plan following consideration and
evaluation of those areas of greatest risk in the organisation’s
operation, and consultation with the Chief Executive; 
• Delivery of the planned audit assignments;
• Follow up of previous audit recommendations;
• Provision of any ongoing advice and support on audit and risk
management related matters;
• Provision of an Annual Report and Assurance Statement, and
presentation to elected members of Scotland Excel. 
1.2 The Service operates in accordance with the Public Sector Internal Audit
Standards (PSIAS) which defines Internal Audit’s role as: 
“......an independent, objective assurance and consulting activity designed to
add value and improve an organisation’s operations. It helps an organisation
accomplish its objectives by bringing a systematic, disciplined approach to
evaluate and improve the effectiveness of risk management, control and
governance processes.” 
1.3 In line with the Standards, the purpose of this Annual Report is to report on: 
• The status/outcome of the planned Internal Audit reviews 202324
relating to Scotland Excel; 
• The outcome of Internal Audit reviews of supporting Renfrewshire
Council corporate systems;
• Internal audit performance; 
• Planned audit work for 2024/25;
• The annual assurance statement which provides an opinion on the
overall adequacy and effectiveness of the organisation’s internal control
environment. 
Page 31 of 142

Page 36

- 2 -
2. Responsibilities of Management and Internal Audit 
2.1 It is the responsibility of management to ensure that for the areas under their
control there is an adequate and effective system of internal control which
facilitates the effective exercise of the organisation’s functions and which
includes arrangements for the management of risk. 
2.2 Internal Audit is not a substitute for effective control exercised by
management as part of their responsibilities. Internal Audit’s role is to
independently assess the adequacy of the risk management, internal controls
and governance arrangements put in place by management and to undertake
sufficient work to evaluate and conclude on the adequacy of those controls for
the period under review. 
2.3 The internal audit team will ensure that independence and objectivity are
maintained in line with the PSIAS including where non-audit work is
undertaken. Internal auditors will have no operational responsibilities. There
have been no impairments impacting on the Chief Auditor’s independence
and the team has been adequately resourced during the year. 
3. Internal Audit Activity during 2023/2024 
3.1 One specific engagement on the contract monitoring – implementing
collaborative procurement is nearing completion and will be reported to
management as soon as possible. The 2022/23 review of contract
management of Social Care Contracts was completed during the year and
reported to the Executive Sub-Committee on 17 November 2023. The main
findings in relation to this review is summarised in table 1 below: 
Table 1 
Audit Area Conclusion
Contract Management –
Social Care Contracts
Substantial Assurance 
• The audit has identified that satisfactory
arrangements were in place to develop
social care framework contracts and 
there were no recommendations made
during the review. 
3.2 The Annual Report for 2022/2023 was submitted to the Executive Sub-
committee on 19 May 2023. 
3.3 The implementation rate of audit recommendations is a measure of
operational culture and effectiveness.  During 2023/24, one recommendation
was followed up and found to be completed. 
Page 32 of 142

Page 37

- 3 -
3.4 Internal Audit also carried out reviews of the main corporate systems
operating within Renfrewshire Council which support Scotland Excel’s activity.
The main findings in relation to these are summarised in Table 2 below and
Renfrewshire Council management have agreed to implement the audit
recommendations made in relation to each review: 
Table 2 
Audit Area Conclusion
Debt Management Reasonable Assurance 
Minor improvements have been
recommended in relation to timeous
raising of invoices and documenting
the strategy for debt management. 
Disaster Recovery Limited Assurance
The audit identified scope for
improvement in the existing
arrangements. Recommendations
were made to enhance and
strengthen controls; including
development of a central register of
critical systems, formalizing ICT
procurement guidance, and seeking
assurance from software as a service
providers regarding their ability to
meet disaster recovery requirements.
Payroll Overpayment Process Reasonable Assurance 
Improvements in processes and
increased awareness over recent
years has resulted in the value of
overpayments being significantly
reduced. By far, the main reason for
overpayments occurring is late
notification of changes by managers
within the employing service. The
auditor has recommended that clear
and accessible guidance should be
made available to service
management, along with regular
communications to ensure that newer
managers are aware of the deadlines
and where they can access relevant
guidance.
Health and Safety Limited Assurance 
The corporate arrangements for
health and safety require to be
improved. It was identified that
procedures require to be reviewed
and updated.  Improvements are
required in terms of corporate
oversight, compliance and
performance reporting.  
Purchasing Processes (Corporate Limited Assurance 
The review focused on corporate
Page 33 of 142

Page 38

- 4 -
Purchase Cards) purchase card procedures. The main
areas for improvement identified
relates to purchasing goods outwith
the agreed procurement routes and
the authorisation of goods ordered. 
There was also a lack of evidence
relating to the authorisation of the
increase of PCard spend limits.   
4. Review of Internal Audit Performance 
4.1 Internal Audit produces regular reports on its performance during the year to
the Renfrewshire Council, Audit, Risk and Scrutiny Board, against a range of
measures set annually by the Director of Finance and Resources. These
targets are set for all internal audit engagements and include Renfrewshire
Council and other associated bodies, for which the team provides internal
audit services. Table 3 shows the actual performance against targeted
performance for the year. 
Table 3 
Internal Audit Performance 2023/24 
Performance measure  Target 2023/24 Actual 2023/24
% of audit assignments         
completed by target date
95% 92%
% of audit assignments completed
within time budget
95% 98.5%
% completion of audit plan for the
year*
95% 98.5%
* this measures the completion percentage as at 31 March.  100% of the plan is ultimately delivered
through the finalisation of the outstanding elements in the new financial year.  
4.2 The percentage completion of the audit plan is slightly below the target set for
the year.  This was due to the level of unplanned leave and the additional time
attributed to unplanned work. It should be noted that this had no effect on the
planned reviews for Scotland Excel for 2023/24.  The actual performance for
the year for the two other indicators, is above the target performance level. 
4.3  The PSIAS require the Chief Auditor to develop and maintain a quality
assurance and improvement programme (QAIP) that covers all aspects of the
internal audit activity. The QAIP must include both periodic internal self-
assessments and five-yearly external assessments, carried out by a qualified,
independent assessor from outwith the organisation. 
4.4 We continued to participate in the Scottish Local Authorities Chief Internal
Auditors’ Group peer review process. Our most recent external assessment
was reported to the Council’s Audit, Risk and Scrutiny Board in May 2023 and
Page 34 of 142

Page 39

- 5 -
included 7 recommendations for improvement, all recommendations have now
been completed. The annual internal self-assessment process has concluded
that the internal audit service fully complies with the PSIAS. 
Risk Management 
4.6 The internal audit service through the Risk Manager, provides advice and
support to Scotland Excel officers, as required. 
5. Planned Audit Work for 2024/25 
5.1 Following a risk based assessment of the activities of Scotland Excel and
consultation with the Chief Executive, the following internal audit work has
been agreed for 20243/25: 
• A review of contract monitoring – contract delivery plan; 
• Follow up of previous audit work;
• Ad-hoc internal audit and risk management advice. 
6. Audit Assurance Statement 
6.1 Internal Audit has performed its work in accordance with the role defined in
paragraph 1.2.  The audit work performed and completed has been reported
to the Chief Executive, and to the Executive Sub Committee in this annual
report. Where areas for improvement in internal control have been identified
appropriate recommendations have been made and accepted for action by
management.   
6.2 In view of the continued challenges common to all public bodies, there will be
a requirement for the council and the bodies for which it is host authority to
exercise very close scrutiny over revenue spending over financial
management and compliance with overarching governance arrangements,
and this will continue to receive due internal audit attention.  
6.3 It is not feasible for the system of internal control to be without any weakness. 
It is important to balance the risks involved in accepting systems limitations
with the consequences if a problem emerges. Internal Audit recognises this
and assesses this in its reporting mechanism.   
6.4 There are corporate systems and processes within Renfrewshire Council that
Scotland Excel rely upon. It can be seen from Table 2 above that some of
these processes require to be improved to provide a reasonable level of
assurance. Renfrewshire Council management has agreed to implement the
recommendation made by internal audit, in relation to these reviews. In this
context, it is considered that reasonable assurance can be placed upon the
adequacy and effectiveness of Scotland Excel Joint Committee’s internal
control, risk management and governance arrangements, as evidenced by:-  
• The results of the audit work in 2023/24 in relation to the corporate      
systems which supported Scotland Excel’s activities.
Page 35 of 142

Page 40

- 6 - 
• Management action in response to audit recommendations. 
• Management self assessment of internal control, risk management and
governance arrangements. 
• The regular review and updating of the Local Code of Corporate
Governance by the Council in accordance with the Chartered Institute
of Public Finance and Accountancy and Society of Local Authority
Chief Executives framework for corporate governance requirements,
and of the corporate governance arrangements within Scotland Excel. 
Signed.                 
Chief Auditor     
Date        17 May 2024   
Page 36 of 142

Page 41

Renfrewshire Health and Social
Care Integration Joint Board 
Internal Audit Annual Report 
2023-2024 
June 2024  
Page 37 of 142

Page 42

Page 38 of 142

Page 43

Renfrewshire Health and Social Care Integration Joint Board 
Internal Audit Annual Report 2023/2024 
Contents 
Page 
1.    Introduction  1
2. Responsibilities of Management and Internal Audit 2 
3.    Internal Audit Activity in 2023/24  2 
4.      Review of Internal Audit Performance    2 
5.  Planned Audit Work for 2024/25  3 
6.  Audit Assurance Statement  4 
Appendix 1 – Summary of Assurances  5 
Page 39 of 142

Page 44

- 1 -
Renfrewshire Health and Social Care Integration Joint Board 
Internal Audit Annual Report   
1 April 2023 – 31 March 2024 
1. Introduction 
1.1 Renfrewshire Council provides an internal audit service to the Renfrewshire
Health and Social Care Integration Joint Board (IJB).  This includes: 
• The compilation of an annual audit plan following consideration 
and evaluation of those areas of greatest risk in the organisation’s
operation, and consultation with the Chief Officer and Senior
Management;
• Delivery of the planned audit assignments;
• Follow up of previous audit recommendations;
• Provision of any ongoing advice support and training on audit and
risk related matters;
• Provision of an Annual Report and Assurance Statement to the IJB. 
1.2 The Service operates in accordance with the Public Sector Internal Audit
Standards which defines Internal Audit’s role as: 
“......an independent, objective assurance and consulting activity designed to
add value and improve an organisation’s operations. It helps an organisation
accomplish its objectives by bringing a systematic, disciplined approach to
evaluate and improve the effectiveness of risk management, control and
governance processes.” 
1.3 In line with the Standards, the purpose of this Annual Report is to report on: 
• The outcome of the planned Internal Audit reviews 2023/24 relating to
the IJB;
• The outcome of Internal Audit reviews undertaken by partner bodies;
• Internal audit performance; 
• Planned audit work for 2024/25;
• The annual assurance statement which provides an opinion on the
overall adequacy and effectiveness of the IJB’s internal control
environment. 
1.4 The operational delivery of services within the Health Board and Local Authority
on behalf of the Integration Joint Board will be covered by their respective
internal audit arrangements. In concluding on the overall opinion, the Chief
Internal Auditor has conducted a review of the internal audit reports issued to
the IJB in the year, the internal audit annual report from Renfrewshire Council
and progress summaries from NHS Greater Glasgow and Clyde. (Appendix 1) 
Page 40 of 142

Page 45

- 2 -
2. Responsibilities of Management and Internal Audit 
2.1 It is the responsibility of management to ensure that the areas under their
control are adequate and effective and that there is a sound system of internal
control which facilitates the effective exercise of the organisation’s functions
and which includes arrangements for the management of risk. 
2.2 Internal Audit is not a substitute for effective control exercised by management
as part of their responsibilities. Internal Audit’s role is to independently assess
the adequacy of the risk management, internal controls and governance
arrangements put in place by management and to undertake sufficient work to
evaluate and conclude on the adequacy of those controls for the period under
review. 
3. Internal Audit Activity during 2023/2024 
3.1 The Internal Audit Plan for the IJB for 2023/2024 provided for a review of
performance management and the annual review of the adequacy and
compliance with the Local Code of Corporate Governance. The review of
performance management was reported to the IJB Audit, Risk and Scrutiny
Committee on 15 March 2024. The review of compliance with the Local Code
of Corporate Governance is included on today’s agenda. 
3.2 The Annual Report for 2022/2023 was submitted to the Integration Joint Board
on 23 June 2023. 
3.3 The implementation rate of audit recommendations is a measure of operational
culture and effectiveness.  During 2023/24, 3 recommendations were followed
up and all have been fully implemented. 
4. Review of Internal Audit Performance 
4.1 Internal Audit produces regular reports on its performance during the year to
Renfrewshire Council’s Audit, Risk and Scrutiny Board, against a range of
measures set annually by Renfrewshire Council’s Director of Finance and
Resources. These targets are set for all internal audit engagements and include
Renfrewshire Council and other associated bodies, for which the team provides
internal audit services. Table 1 shows the actual performance against targeted
performance for the year. 
Table 1 
Internal Audit Performance 2023/24 
Performance measure  Target 2023/24 Actual 2023/24
% completion of audit plan for the year* 95% 92%
% engagements completed by target
date
95% 98.5%
% engagements completed within time
budget
95% 98.5%
Page 41 of 142

Page 46

- 3 -
* this measures the completion percentage as at 31 March.  100% of the plan is ultimately delivered through the
finalisation of the outstanding elements in the new financial year.  
4.2 The percentage completion of the audit plan is slightly below the target set for
the year.  This was due to the level of unplanned leave and the additional time
attributed to unplanned work. It should be noted that this had no effect on the
planned reviews for the IJB for 2023/24 which are 100% complete.  The actual
performance for the year for the two other indicators, is above the target
performance level. 
4.3 The PSIAS require the Chief Auditor to develop and maintain a quality
assurance and improvement programme (QAIP) that covers all aspects of the
internal audit activity. The QAIP must include both periodic internal self-
assessments and five-yearly external assessments, carried out by a qualified,
independent assessor from outwith the organisation. 
4.4 We continued to participate in the Scottish Local Authorities Chief Internal
Auditors’ Group peer review process. Our most recent external assessment
was reported to the Council’s Audit, Risk and Scrutiny Board in May 2023 and
included 7 recommendations for improvement, all recommendations have now
been completed. The annual internal self-assessment process has concluded
that the internal audit service fully complies with the PSIAS. 
5. Planned Work for 2024/25 
5.1 Following a risk-based assessment of the activities of the IJB and consultation
with the senior management team, the Internal Audit Plan for 2024/2025
provides for 40 days of Internal Audit resource to undertake: 
• A review of financial planning; and 
• The annual review of the adequacy and effectiveness of the Local Code
of Corporate Governance. 
The plan also provides time for planning and reporting, follow up on previous
recommendations, the annual self-assessment of the Audit Committee
arrangements, ad-hoc advice, consultancy and training. The Internal Audit Plan
for 2024/2025 was approved by the IJB Audit, Risk and Scrutiny Committee on
15 March 2024. 
6. Audit Assurance Statement 
6.1 The audit work performed in relation to the 2023/24 internal audit plan has been
reported to the Chief Officer. Relevant audit work undertaken by partner
organisations is reported to the Audit, Risk and Scrutiny Committee. Where
areas for improvement in internal control have been identified, appropriate
recommendations have been made and accepted for action by management.   
6.2 There are no significant matters arising in relation to those audit engagements
specific to the IJB and there have been no impairments impacting on the Chief
Page 42 of 142

Page 47

- 4 -
Auditor’s independence and the team has been adequately resourced during
the year. 
6.3 It is not feasible for the system of internal control to be without any weakness. 
It is important to balance the risks involved in accepting systems limitations with
the consequences if a problem emerges. Internal Audit recognises this and
assesses this in its reporting mechanism.  
6.4 There are corporate systems and processes within Renfrewshire Council and
NHS Greater Glasgow and Clyde that the IJB rely upon. It can be seen from
Appendix 1, that some of these processes require to be improved to provide a
reasonable level of assurance. 
6.5 In this context, it is considered that a reasonable level of assurance can be
placed upon the adequacy and effectiveness of the Integration Joint Board’s
internal control, risk management and governance arrangements, as evidenced
by:- 
• The results of the audit work in 2023/24 and the opinion’s contained in
the Internal Audit Annual Reports of the Local Authority and progress
reports from the Health Board. 
• Management self-assessment of internal control, risk management and
governance arrangements. 
• Management action to respond to audit recommendations. 
Chief Internal Auditor     
21 June 2024 
Page 43 of 142

Page 48

- 5 -
Appendix 1 
Summary of Internal Audit Assurances for the IJB and Partner Organisations,
Renfrewshire Council and NHS Greater Glasgow and Clyde 
Integration Joint Board
Audit Engagement Assurance
Level
Significant Matters
Local Code of Corporate
Governance
Substantial • None
Performance Management Substantial • None
Renfrewshire Council
Audit Engagement Assurance
Level
Significant Matters
Cyber Security Reasonable • None
Information Asset Register Limited • There was a requirement to
improve accountability by services
for the upkeep of the Information
Asset Register and oversight of
the completeness of the register
could be improved. All
recommendations have now been
implemented.
Disaster Recovery Limited • There is scope to improve the
existing arrangements.
Recommendations were made to
enhance and strengthen controls;
including development of a central
register of critical systems,
formalising ICT procurement
guidance, and seeking assurance
from software as a service
providers regarding their ability to
meet disaster recovery
requirements.
Care at Home Processes Substantial • None
Debt Management Reasonable • None
Payroll Overpayment
Process
Reasonable • None
Health and Safety Limited • The corporate arrangements for
health and safety require to be
improved. It was identified that
procedures require to be reviewed
and updated.  Improvements are
required in terms of corporate
oversight, compliance and
performance reporting.  
Purchasing Processes
(Corporate Purchase
Cards)
Limited • The review focused on corporate
purchase card procedures. The
main areas for improvement
identified relates to purchasing
goods outwith the agreed
Page 44 of 142

Page 49

- 6 -
procurement routes and the
authorisation of goods ordered. 
There was also a lack of evidence
relating to the authorisation of the
increase of PCard spend limits.  
NHS Greater Glasgow and Clyde
Audit Engagement Overall Audit
Rating
Significant Matters
Public Protection
Arrangements
Substantial
Improvement
Required
• Improvements were required in
relation to guidance documents
and training. 
Use of Agency Staff Substantial
Improvement
Required
• The use of agency staff in some
area could not be explained by
increased vacancy levels.
Moving Forward Together
Implementation
High risk  • The risk reflects the ability to
progress with transformational
activity within an extremely
challenging operating environment,
with increased pressure on
services and both resourcing and
financial constraints, remains an
area of significant uncertainty. 
Infection Prevention and
Control
Minor
improvement
required
• None
Consultant Job Planning Substantial
improvement
required
• Improvements are required in
relation to job planning and
monitoring the delivery of these
plans.
eHealth Application Access
Management
Minor
improvement
required
• None
Public Health Screening  Minor
improvement
required
• None
Managing Staff Attendance  Minor
improvement
required
• None 
Page 45 of 142

Page 50

Appendix 4
Internal Audit Report
IJB - Governance Arrangements (B0017/2024/001)
Date:  May 2024
COMMITTEE SUMMARY
Audit Objectives
The Renfrewshire Integrated Joint Board (IJB) have developed local governance
arrangements that are designed to ensure compliance with, ‘Delivering Good Governance
in Local Government: Framework,’ published by CIPFA. The objectives of this audit were
to review independently and report annually to the IJB Audit, Risk and Scrutiny Committee: 
• To provide assurance on the adequacy and effectiveness of the Local Code of
Corporate Governance and the extent of compliance with it. 
• To support the Chief Internal Auditor’s annual opinion included in the Internal Audit
Annual Report and the Governance Statement included in the Annual Accounts. 
Audit Scope
1. Obtained an up-to-date copy of the IJB’s Local Code of Corporate Governance and
selected a sample of elements for compliance testing. 
2. Obtained the appropriate evidence to confirm compliance with the Code.here was
adequate management oversight for the selected performance indicators. 
Key Audit Assurances
1. The Local Code and Sources of Assurance for Governance Arrangements was
updated and submitted to the Renfrewshire Integration Joint Board on the 23rd of June
2023. 
2. Based on our sample check of the evidence used to demonstrate compliance, we
would confirm that the IJB complies with the requirements of the Local Code of
Corporate Governance. 
Key Risks
• No key risks were identified as a result of this audit. 
Page 46 of 142

Page 51

Overall Audit Opinion
Internal Audit has reviewed the adequacy and effectiveness of the revised Code which was
presented to the Renfrewshire Integration Joint Board on the 23rd of June 2023. Based on our
sample check of the evidence used to demonstrate compliance, we would confirm that the IJB
complies with the requirements of the Local Code of Corporate Governance. In addition, it is
evident that the Local Code has been subject to regular review and updating in line with
developments in best practice. 
Management Commentary
N/A as no key risks identified. 
Page 47 of 142

Page 52

Glasgow and Clyde Valley Strategic
Development Planning Authority 
Annual Report 
2023-2024 
Renfrewshire Council
Internal Audit 
June 2024 
Page 48 of 142

Page 53

Glasgow and Clyde Valley Strategic Development Planning Authority 
Internal Audit Annual Report 2023/2024 
Contents 
Page 
1.    Introduction  1
2. Responsibilities of Management and Internal Audit 2 
3.    Internal Audit Activity in 2023/24  2 
4.      Internal Audit Performance    4 
5.  Planned Audit Work for 2024/25  5 
6.  Audit Assurance Statement  5 
Page 49 of 142

Page 54

- 1 -
Glasgow and Clyde Valley Strategic Development Planning Authority 
Internal Audit Annual Report   
1 April 2023 – 31 March 2024 
1. Introduction 
1.1 As host Authority, Renfrewshire Council provides an internal audit service to
Glasgow and Clyde Valley Strategic Development Planning Authority.  This
includes: 
• The compilation of an annual audit plan following consideration 
and evaluation of those areas of greatest risk in the organisation’s
operation, and consultation with the Strategic Development Plan
Manager;
• Delivery of the planned audit assignments;
• Follow up of previous audit recommendations;
• Provision of any ongoing advice and support on audit and risk
management related matters;
• Provision of an Annual Report and Assurance Statement, and
presentation to elected members at the Glasgow and Clyde Valley
Strategic Development Planning Authority. 
1.2 The Service operates in accordance with the Public Sector Internal Audit
Standards which defines Internal Audit’s role as: 
“......an independent, objective assurance and consulting activity designed to
add value and improve an organisation’s operations. It helps an organisation
accomplish its objectives by bringing a systematic, disciplined approach to
evaluate and improve the effectiveness of risk management, control and
governance processes.” 
1.3 In line with the Standards, the purpose of this Annual Report is to report on: 
• The outcome of any planned Internal Audit reviews in 2023/24 relating
to the Glasgow and the Clyde Valley Strategic Development Planning
Authority;
• The outcome of Internal Audit reviews of supporting Renfrewshire
Council corporate systems;
• Internal audit performance; 
• Planned audit work for 2024/25;
• The annual assurance statement which provides an opinion on the
overall adequacy and effectiveness of the Planning Authority’s internal
control environment. 
Page 50 of 142

Page 55

- 2 -
2. Responsibilities of Management and Internal Audit 
2.1 It is the responsibility of management to ensure that the areas under their
control are adequate and effective and that there is a sound system of internal
control which facilitates the effective exercise of the organisation’s functions
and which includes arrangements for the management of risk. 
2.2 Internal Audit is not a substitute for effective control exercised by
management as part of their responsibilities. Internal Audit’s role is to
independently assess the adequacy of the risk management, internal controls
and governance arrangements put in place by management and to undertake
sufficient work to evaluate and conclude on the adequacy of those controls for
the period under review. 
2.3 The internal audit team will ensure that independence and objectivity are
maintained in line with the PSIAS including where non-audit work is
undertaken. Internal auditors will have no operational responsibilities. There
have been no impairments impacting on the Chief Auditor’s independence
and the team has been adequately resourced during the year. 
3. Internal Audit Activity during 2023/2024 
3.1 The Annual Report for 2022/2023 was submitted to the Joint Board on 12
June 2023. 
3.2 There were no outstanding audit recommendations which required to be
followed up as part of the 2023/24 annual follow up exercise. 
3.3 Internal Audit also conduct reviews of the main corporate systems operating
within Renfrewshire Council which support the Committee’s activity. The main
findings in relation to these are summarised in Table 1 below and
Renfrewshire Council management have agreed to implement the audit
recommendations made in relation to each review:
Table 1 
Audit Area Conclusion
Debt Management Reasonable Assurance 
Minor improvements have been
recommended in relation to timeous
raising of invoices and documenting
the strategy for debt management. 
Disaster Recovery • Limited Assurance
The audit identified scope for
improvement in the existing
arrangements. Recommendations
were made to enhance and
strengthen controls; including
development of a central register of
critical systems, formalizing ICT
procurement guidance, and seeking
Page 51 of 142

Page 56

- 3 -
assurance from software as a service
providers regarding their ability to
meet disaster recovery requirements.
Payroll Overpayment Process • Reasonable Assurance 
Improvements in processes and
increased awareness over recent
years has resulted in the value of
overpayments being significantly
reduced. By far, the main reason for
overpayments occurring is late
notification of changes by managers
within the employing service. The
auditor has recommended that clear
and accessible guidance should be
made available to service
management, along with regular
communications to ensure that newer
managers are aware of the deadlines
and where they can access relevant
guidance. 
4. Review of Internal Audit Performance 
4.1 Internal Audit produces regular reports on its performance during the year to
the Renfrewshire Council, Audit, Risk and Scrutiny Board, against a range of
measures set annually by the Director of Finance and Resources. These
targets are set for all internal audit engagements and include Renfrewshire
Council and other associated bodies, for which the team provides internal
audit services. Table 2 shows the actual performance against targeted
performance for the year. 
Table 2 
Internal Audit Performance 2023/24 
Performance measure  Target 2023/24 Actual 2023/24
% completion of audit plan for the
year*
95% 92%
% of audit assignments completed
within time budget
95% 98.5%
% of audit assignments         
completed by target date
95% 98.5%
* this measures the completion percentage as at 31 March.  100% of the plan is ultimately delivered through the
finalisation of the outstanding elements in the new financial year.
Page 52 of 142

Page 57

- 4 -  
4.2 The percentage completion of the audit plan is slightly below the target set for
the year.  This was due, in the main, to a higher than anticipated level of
unplanned leave and the additional time attributed to unplanned work. It
should be noted that the planned internal audit activity within the planning
authority is 100% complete. The actual performance for the year for the two
other indicators, is above the target performance level. 
4.3 The PSIAS require the Chief Auditor to develop and maintain a quality
assurance and improvement programme (QAIP) that covers all aspects of the
internal audit activity. The QAIP must include both periodic internal self-
assessments and five-yearly external assessments, carried out by a qualified,
independent assessor from outwith the organisation. 
4.4 We continued to participate in the Scottish Local Authorities Chief Internal
Auditors’ Group peer review process. Our most recent external assessment
was reported to the Council’s Audit, Risk and Scrutiny Board in May 2023 and
included 7 recommendations for improvement, all recommendations have now
been completed. The annual internal self-assessment process has concluded
that the internal audit service fully complies with the PSIAS. 
External Audit 
Risk Management 
4.6 The internal audit service through the Risk Manager, provides advice and
support to the GCVSDPA officers, as required. 
5. Planned Work for 2023/24 
5.1 Following a risk based assessment of the activities of the Glasgow and Clyde
Valley Strategic Development Planning Authority and consultation with the
Head of Economy and Development the following internal audit work has
been agreed for 2023/24: 
• Ad-hoc internal audit and risk management advice;
• Annual report to support the Governance Statement. 
6. Audit Assurance Statement 
6.1 Internal Audit has performed its work in accordance with the role defined in
paragraph 1.2.  The audit work performed has been reported to the Strategic
Development Plan Manager, and to the Joint Committee in this annual report.
Where areas for improvement in internal control have been identified,
appropriate recommendations have been made and accepted for action by
management.   
6.2 In view of the continued challenges common to all public bodies, there will be
a requirement for the council and the bodies for which it is host authority to
Page 53 of 142

Page 58

- 5 -
exercise very close scrutiny over expenditure, and both areas will continue to
receive due internal audit attention.  
6.3 It is not feasible for the system of internal control to be without any weakness. 
It is important to balance the risks involved in accepting systems limitations
with the consequences if a problem emerges. Internal Audit recognises this
and assesses this in its reporting mechanism.   
6.4 There are corporate systems and processes within Renfrewshire Council that
the Planning Authority rely upon. It can be seen from Table 2 above that some
of these processes require to be improved to provide a reasonable level of
assurance. Renfrewshire Council management has agreed to implement the
recommendation made by internal audit, in relation to these reviews. In this
context, it is considered that a reasonable level of assurance can be placed
upon the adequacy and effectiveness of the Glasgow and Clyde Valley
Strategic Development Planning Authority’s internal control, risk management
and governance arrangements, as evidenced by:-  
• The results of the audit work in 2023/24 in relation to the corporate
systems which supported the Glasgow and Clyde Valley Strategic
Development Planning Authority’s activities. 
• Management action in response to audit recommendations. 
• Management self assessment of internal control, risk management and
governance arrangements. 
• The regular review and updating of the Local Code of Corporate
Governance by the Council in accordance with the CIPFA/SOLACE
framework for corporate governance requirements and of the corporate
governance arrangements within the Glasgow and Clyde Valley
Strategic Development Planning Authority. 
Signed           
Chief Auditor     
Date          10 June 2024       
Page 54 of 142

Page 59

To: Audit, Risk and Scrutiny Board
On: 19 August 2024
Report by: Chief Executive
Heading: Actions Monitoring Report - Dargavel Primary School
1. Summary
1.1 Following the findings of an independent review into the circumstances
of the errors in planning and delivery of primary school provision in the
Dargavel area, a SMART action plan was developed detailing the
Council’s response with a commitment that updates on this plan would
be provided to Audit Risk & Scrutiny Board meetings going forward.
1.2 At a meeting on 11th January 2024, the Accounts Commission was
presented with a statutory S.102 report, as circulated to Councillors on
5th January 2024, by the Controller of Audit on School Accommodation
for Dargavel. In the report, the Commission has set out its findings,
alongside several issues on which it requires further investigation. In
response, the Council have developed an action plan based on the
recommendations. A follow-up report (attached at Appendix 3) from the
Controller of Audit was published on 31 July and subsequently
discussed at a meeting of the Accounts Commission on 8 August 2024.
At the time of drafting this report, there has been no formal indication
from the Accounts Commission as to any further action or investigation
being required.
1.3 On 29th February 2024, elected members at Council considered a report
on the outcome of the review of corporate governance arrangements by
the Cross Party Working Group and agreed a number of actions set out
in that report. Council further agreed that those actions would be
incorporated into the independent review response monitoring
arrangements reported to this Board.
Item 4
Page 55 of 142

Page 60

1.4 Appendix 1 provides an update on open actions related to the Bowles
independent review report, the Accounts Commission S.102 report, and
the actions related to the report of the Cross Party Working Group.
Appendix 2 is a summary of all completed actions from each of these
three reviews. 
2. Recommendations 
2.1 Note and consider the update provided in Appendix 1 in relation to the
Council’s progress with live actions.
2.2 Note the completed actions provided in Appendix 2, and the follow-on
report from the Controller of Audit in Appendix 3. 
Implications of the Report 
1. Financial – whilst there will be significant capital and revenue
implications for the Council in resolving the Dargavel issue, there are no
financial implications for the Council as a result of this update report. 
2. HR & Organisational Development – the report outlines a leadership
development programme with a focus on key issues raised in the
independent review around governance, risk management, corporate
working and culture. 
3. Community/Council Planning – the report outlines ongoing action
being taken to develop an engagement and ongoing communication
process with affected communities. 
4. Legal – none 
5. Property/Assets – none
 
6. Information Technology – none 
7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and
human rights. 
No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report as it is for noting only. If
required following implementation, the actual impact of the
Page 56 of 142

Page 61

recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.
8. Health & Safety – none
9. Procurement – none
10. Risk – the report outlines the action being taken in relation to risk
management.
11. Privacy Impact – none
12. Climate Risk – none
13. Children’s Rights – none
14. COSLA Policy Position - none
Author: Alan Russell, Chief Executive 
Page 57 of 142

Page 62

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Bowles Report Recommendation 1 
Build a more robust model of primary school need for Dargavel ‐ the Council should continue to refine its pupil forecast model for Dargavel. 
Response Objectives 
Deliver robust projection modelling for Dargavel and PMHS which: ‐ 
 considers live information arising from NHS, pupil & ELC registrations, the pace of development to date, certainty over development size and likely 
pace of future build out rate,
 utilises external data analytics and projection expertise to augment and enhance the Council’s in‐house forecasting approach to ensure modelling is 
robust, underpinned by external challenge and specialist input reflecting the complexity and significant portion of Dargavel that has yet to be 
developed out over a circa 10 year period,
 provides modelling output which considers potential future upper scenarios reflecting the high yield factors reflected in the 2023/24 P1 intake to 
inform immediate decisions on scale of capacity to be delivered as well as planning for potential additional interventions at a future time,
 delivers modelling output which provides a long‐term view beyond the anticipated completion timeline for Dargavel to ensure the long term impact of 
Dargavel is modelled and understood,
 provides modelling output over the long term which indicates both the scale, timing and shape of an anticipated peak in demand that will accompany 
a development of this scale and nature. This will provide visibility of the anticipated short‐lived peak in demand and long term settled demand to 
ensure this is appropriately reflected in estate/capacity decisions and in particular to mitigate against delivery of excessive long term / permanent 
increase in capacity that would result in excess unused surplus capacity over the long term.
 Provides modelling that can be tested and revised as necessary as new key data becomes available such as P1 and S1 registrations, actual scale and 
pace of the development and any new developments, which will continue to inform decisions on any future estate interventions if required.
Page 58 of 142

Page 63

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Update Edge Analytics modelling for newly released 
national Census data and expand across the whole 
school estate and establish modelling dashboard to 
support ease of updating and rapid re‐assessment of 
revised projection that will be utilised on an ongoing 
basis over future years, both for Dargavel / PMHS but 
also as part of the strategic Learning Estate programme. 
January 
2023 
Director of 
Children’s 
Services 
The Edge Analytics modelling for newly released national 
census data was completed in 2023. A modelling dashboard 
was also designed last year with further discussions to take 
place on how this is used to inform the wider learning estate. 
Edge have been further commissioned to expand the model to 
include the whole estate. A schedule has been developed 
which outlines re‐ assessment and monitoring timescales. 
Update August 2024 – Edge Analytics currently modelling the 
entire learning estate and projections due in early September 
2024. 
 
Bowles Report Recommendation 2
Use of Bishopton Primary ‐ in its future plans the Council should reconsider how surplus capacity at Bishopton can be used effectively. 
Response Objectives 
Consider and assess how existing capacity within Bishopton Primary School may be best utilised to support the Dargavel catchment over the immediate term 
and potentially over the longer term, taking into consideration the uncertainty and risk over the long‐term demand levels that will ultimately emerge for 
primary education from Dargavel as well as the expectation of a temporary peak period of demand. 
Provide a report to Education and Children’s Services Board setting out a clear overview as to how Bishopton PS capacity will be utilised to support temporarily 
over the short term period and how it may be considered amongst other options for use to support Dargavel in the longer term (noting that any such longer 
term use will be subject to detailed consideration and decision at an appropriate point in future years). 
ALL ACTIONS COMPLETE FOR RECOMMENDATION 2 
Bowles Report Recommendation 3
As the Council progresses its plans to issue supplementary guidance on developer contributions for education it should seek to learn from other Councils in 
Scotland. 
Page 59 of 142

Page 64

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
A development the size of Dargavel is exceptional and would need its own modelling techniques. However, for smaller developments the Council should create 
an evidence base to calculate specific yield factors derived from recent developments in Renfrewshire. Such robust data will ease future negotiations. 
ALL ACTIONS COMPLETE FOR RECOMMENDATION 3 
Bowles Report Recommendation 4
Council needs to work co‐operatively with BAE. Unless the Council and BAE can work together to resolve the current problems, BAE may face accusations, 
whether founded or not and regardless of Council incompetence, that it has increased its profits at the expense of Council taxpayers. 
Response Objectives 
Secure legal ownership of suitable land to facilitate delivery of a second school within Dargavel Village as well as additional land next to existing school site to 
provide increased flexibility to meet potential future extension of the school and or establishment of greater outdoor space. 
Secure legal commitment from BAE to provide land remediation and associated infrastructure requirements as part of legal agreement at nil cost to the 
Council. 
Secure as part of the legal agreement certainty on consented planning numbers and any associated adjustments to s.75 agreement to reflect revised 
agreement. 
ALL ACTIONS COMPLETE FOR RECOMMENDATION 4 
Bowles Report Recommendation 5
Corporate working and organisational culture ‐ although I understand that the Council has sought to improve and strengthen corporate working in recent 
years, the evidence would suggest there is a long way to go; simply establishing corporate working groups is insufficient if staff are in a mindset of ‘not my 
problem’. 
Page 60 of 142

Page 65

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
The failure of management oversight, if symptomatic of the Council as a whole, would be deeply disturbing. The Council needs to consider a significant change 
programme, not just on the of issue of corporate working and personal responsibility, but also its organisational culture and values. It needs plans to build a 
stronger organisation where constructive challenge is welcomed and there is a clarity of what is expected of all of those in a leadership role. 
Response Objectives 
Provide assurance that established programme governance framework and operations of governance for other major capital investment programmes and 
specifically that the Bowles findings on the historic failings on the handling of Dargavel by officers are not representative of the Council’s current culture and 
approach to the management and delivery of major programmes. 
The Council is committed to living its values as a learning and collaborative organisation and post COVID was already in the process of re‐establishing an 
Leadership Development programme for senior leadership teams and managers across the Council in recognition that this required to be reinvigorated post 
COVID and that there has been significant turnover in management and senior positions over the past three years and this would support growing and 
maturing the current culture and collaborative connections across the organisation. 
In response to the Bowles recommendations, the objective is to ensure the new Leadership Development programme is appropriately cognisant and reflective 
of the key learning points from the Bowles report and takes the opportunity to ensure its coverage seeks to re‐enforce the development of skills related to 
governance, risk management, commercial risk, corporate working and culture etc and effectively utilises failures referenced in the Bowles report as key 
examples for learning throughout the programme. Collective reflection and learning of such significant failures – albeit historical – is recognised as an 
important element of building an effective future culture and ways of working across the organisation. 
ALL ACTIONS COMPLETE FOR RECOMMENDATION 5 
Bowles Report Recommendation 6
Risk management 
Page 61 of 142

Page 66

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
From documents I have seen the Council was unaware of the scale of risk it was taking in the calculation of pupil numbers. The identified risk in Council documents 
related to providing the school on time, not that the size of the school may prove to be inadequate. The failure to identify that risk has had two consequences; 
first the Council has been slow to react to the increase in pupil numbers and second the Council did not negotiate with BAE with that risk in mind. 
The Council needs to review how it both identifies risk and manages it. 
Response Objectives 
Progress actions to provide reassurance in relation to the Council’s current risk management approach, in particular how this is approached, deployed and 
managed as part of major projects as well as considering and assessing the seniority / appropriateness of officer involvement and related skills across officers 
involved in the process. 
ALL ACTIONS COMPLETE FOR RECOMMENDATION 6 
Bowles Report Recommendation 7
Whilst protecting the integrity of the planning process, the Council needs to ensure the appropriate involvement of members in such developments. 
Additional Council Motion 
Council agrees that in light of the Independent External Review of Dargavel that there is a requirement to convene a cross party body to discuss and review 
existing governance arrangements of Renfrewshire Council. 
Response Objectives 
Assess the extent to which major investment projects have provided sufficient engagement with elected members through both formal governance routes as 
well as through briefing sessions, engagement sessions, group presentations, site tours etc. Identify any adjustments or improvements required moving 
forward. 
Page 62 of 142

Page 67

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Provide officer support to a cross party group to of elected members to agree the remit and progress a discussion and review of the Council’s formal 
governance arrangements in line with the motion approved. 
Carry out an assessment of the Audit Risk and Scrutiny Board against CIPFA’s published good practice guide for audit committees. 
ALL ACTIONS COMPLETE FOR RECOMMENDATION 7 
Bowles Report Recommendation 8
Public confidence 
These recent events and the matters described in this report will dent public confidence in the Council. The Council should work in an open and transparent 
manner in the resolution of these issues and particularly with the residents of Dargavel, who have legitimate concerns about the implications for their children 
during both their primary and secondary education. 
Response Objectives 
The key aim has been to provide straightforward messaging and up to date sitreps to ensure publics (and council representatives) have the most up‐to‐date 
position and the complexity of the issue is explained in a simple and honest way and that parental/carer concerns in respect to the school and educational 
environment are able to be appropriately discussed through structured engagement arrangements with the parent councils with appropriate agreed actions 
taken forward. 
The strategy has been designed to: 
− Improve the flow and regularity of information to parents and carers and the wider Dargavel community, so they are first to hear about decisions
impacting their community.
Page 63 of 142

Page 68

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
− Ensure parents and carers have access to all projection data available to the council. 
− Introduce direct communication channels with Dargavel residents, enabling all sections of the community to engage on matters that are important to 
them and making sure the latest information is accessible and easy to find. 
− Provide residents with a feedback loop to enable them to ask questions of the council in relation to the development and have questions answered 
quickly. 
− Include the community in formal planning and design of a new primary school and high school extension. 
It is recognised that effective communication and engagement is important to building a new relationship between the Council and the Dargavel community, 
but ultimately it will take the delivery of the solution and investment in long term engagement to reduce local anxiety and fully rebuild trust and confidence in 
the Council. 
Establish and track key indicators of community 
sentiment. 
Ongoing  Head of 
Marketing and 
Comms 
Ongoing  The council continues to deploy the Dargavel 
communication and engagement strategy and 
to provide regular updates to the community 
through a variety of channels – including face‐
to‐face forums, monitoring reach, engagement 
and feedback which is recorded and used to 
inform future communications. From those 
insights community engagement groups are 
being established to help plan new school 
design and traffic and travel. We continue to 
grow membership of our opt‐in community 
newsletter. Recent and live community 
engagement activity includes focus groups and 
public meetings linked to school design that 
form part of the PAN process for Dargavel 
Primary School. This will be followed by a similar 
engagement programme for extending Park 
Mains High School. The community survey 
outlined below will help to develop a baseline 
satisfaction level that can be tracked ongoing.  
 
 
Page 64 of 142

Page 69

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
The Consultation Institute has completed a 
review of the council’s communication and 
engagement strategy. The report concluded 
that the council’s process has been thorough 
and showed ‘considerable good practice’. The 
Report made recommendations to inform 
future engagement and consultation, which 
have been captured in an Action Plan and will 
be used to develop a corporate policy on 
engagement and consultation, to be delivered 
at the end of October.  
Following the statutory consultation and exit 
interviews on the effectiveness of the 
programme (over 800 people submitted formal 
responses and over 150 individuals attended 
events that were part of the consultation 
programme), a community survey was 
developed to get feedback from residents in 
Dargavel and Bishopton community on the 
Council’s wider communication and 
engagement approach regarding local school 
capacity. The survey asks for views on all 
communications from November 2022 and will 
test: 
 Awareness of the Council’s engagement
strategy and the formal statutory
consultation which took place earlier this
year.
 Perceptions of the effectiveness of the
Council’s engagement
 Barriers to engaging with the Council
 Has community trust in the Council
improved as a result of the engagement
strategy.
Page 65 of 142

Page 70

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
The survey – 
www.researchresource.co.uk/Dargavelresidents
survey.html was launched on 6 August and will 
run to 2 September, promoted through a Royal 
Mail door drop and through existing Dargavel 
and Bishopton community channels. Resource 
Research, an independent research company 
will analysis the survey responses and produce a 
final report by 13 September. 
Page 66 of 142

Page 71

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Action  Target 
Completion 
Responsible
Officer 
Update 
Develop, deploy (at appropriate key points post formal 
consultation period) and evaluate a community pulse 
survey to assess and track community sentiment and 
view of ongoing handling and satisfaction with delivery 
of key interventions within the community. 
Expected 
September 
2024 
Head of 
Marketing and 
comms 
In 
development 
As above, a community survey is currently live. 
This was launched on 6 August and will run to 
2 September, promoted through a Royal Mail 
door drop and through existing Dargavel and 
Bishopton community channels. Resource 
Research, an independent research company 
will analysis the survey responses and produce 
a final report by 13 September. This will 
provide a baseline for future surveys.  
Page 67 of 142

Page 72

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
ACCOUNTS COMMISSION SECTION 102 REPORT – FINDINGS & COUNCIL RESPONSE/UPDATE
Community and Other Engagement 
The  council  must,  as  a  matter  of  urgency,  conduct  a 
robust and transparent assessment of the effectiveness of 
its  community  engagement  and  then  move  swiftly  to 
implement any improvements needed. 
February 2024  Head of 
Communications 
and Marketing 
Please see response to Bowles report recommendation 8 above 
 
The Commission is particularly concerned by the council’s 
failure both to transparently consider alternative options 
in relation to expanding secondary school capacity in the 
area, and to consult or engage appropriately with the 
community, whom their decision directly affects. 
This 
engagement 
activity will 
remain 
ongoing as 
part of the 
PMHS 
extension 
project 
through to 
August 2027 
and beyond 
recognising 
the long‐term 
monitoring 
of school roll 
projections at 
the high 
school. 
Director of 
Children’s 
Services 
It is accepted that the report to the Education and Children’s 
Services Policy Board in May 2023 could have articulated the 
reasons  why  no  other  options  to  address  secondary  school 
capacity beyond an extension to Park Mains High School were 
deemed viable for detailed consideration. 
Additionally,  although  engagement  in  relation  to  updated 
school projections and developing plans for a larger extension 
to PMHS were shared and discussed with the PMHS parent 
council  prior  to  the  May  report,  plans  to  expand  this 
engagement process to a wider group to encapsulate all feeder 
primaries following the board meeting could have been outlined 
in the report and or considered earlier in the process. 
Council officers have since May 2023 been progressing positive 
and ongoing community engagement in relation to the Park 
Mains  extension,  principally  through  the  Park  Mains  Liaison 
Group which was established to provide a single engagement 
forum with representatives from the Parent Councils of Park 
Mains High School and all associated feeder primaries. 
August 2024  
This engagement process has shared and explained detailed 
pupil projection data, the underlying rationale for the proposed 
extension  decision  as  well  as  listening  and  responding  to 
Page 68 of 142

Page 73

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
concerns and or requests for further information from the wider 
parent and  carer community.  This included sharing detailed 
information  on  an  option  promoted  by  some  community 
representative  from  Dargavel  and  Bishopton  for  a  new 
secondary  school  for  Dargavel,  Bishopton  and  Langbank.  As 
reported through the Education and Children’s Services Policy 
Board in August 2023, such an option had significant negative 
implications from a financial, educational, value for money and 
school estate perspective that discounted it as a credible option 
for detailed consideration. 
The Park Mains Liaison Group is proving to be a highly valuable 
engagement forum, providing a single route of engagement 
across the wider community as well as a key route to assist the 
Council  to  disseminate  consistent  key  messages  and 
information  updates  across  communities  through  trusted 
Parent  Council  communication  channels.  This  engagement 
approach  will  inform  how  non  statutory  and  informal 
engagement in relation to potential school estate changes and 
long‐term strategic learning estate work may be taken forward 
in the future by the Council. 
Additionally,  high  levels  of  positive  engagement  are  being 
secured  as  part  of  the  space  planning  process  for  the  new 
extension, supporting active parental and carer participation 
and influence in the design process of the new extension and 
wider changes to the school that are planned to be delivered. 
This is increasingly building a positive community commitment 
and level of direct participation in the delivery of the school 
extension and improvement project. 
Page 69 of 142

Page 74

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Director of 
Children’s 
Services 
The review of the Council’s engagement strategy as referred to 
above will include a qualitative assessment of the effectiveness 
of the Park Mains Liaison Group. 
Lastly, work is being progressed by officers to research how 
other  councils  have  approached  school  extension  projects, 
where a statutory consultation process is not required. The 
objective of this work is to inform the design of a framework to 
inform any future approach to early informal engagement that 
can  be  adopted  by  the  Council  in  relation  to  school  estate 
considerations or changes. 
Desk top work completed to date has identified a mixed picture 
with several councils having adopted a similar approach to that 
employed by the Council for the PMHS extension. However, 
there  are  some  examples  of  the  use  of  published  options 
appraisals as part of Council reports and identified examples of 
planned informal engagement strategies deployed as part of 
long‐term strategic school estate planning which provide some 
good practice approaches for reference. 
These individual elements of good practice that are evident 
across other councils can be collectively brought together and 
used  to  inform  and  guide  the  development  of  a  proposed 
framework for use by the Council in its future learning estate 
strategy (where appropriate this will pay due regard to the 
Scottish Government guidance on informal engagement that 
may occur prior to a statutory consultation process). 
In completing this work consideration will be given to sharing 
the output across the local authority sector given what appears 
Page 70 of 142

Page 75

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
to be a level of mixed and inconsistent approaches deployed 
across the country. 
We note that the new primary school is subject to a full 
public consultation. 
We expect the council to engage meaningfully with the 
community  on  this  issue,  and  other  decisions  on  the 
school estate. 
Again, we ask that the Controller monitors this situation, 
and reports to us in June 2024 on progress and earlier if 
necessary. 
Consultation 
process has 
commenced 
and will fully 
complete with 
a report to 
the Education 
and Children’s 
Services Policy 
Board in May 
2024 
Director of 
Children’s 
Services 
The Education and Children’s Services Policy board approved 
the planned consultation programme in January with a report 
on the outcome of the consultation planned to be brought back 
to Policy Board in May. 
A  full  programme  of  planned  consultation  and  engagement 
activity has been developed with input from the Institute of 
Consultation  to  bring  to  the  design  process  experience  of 
recognised best practice deployed across the UK. 
Full details of the planned consultation process and activity will 
be provided to the external auditors as well as the opportunity 
to observe any of the planned information events and or formal 
consultation meetings. 
The  consultation  has  now  been  completed  with  817 
respondents  to  the  online  questionnaire  and  a  further  150 
attending the events which were held: 
6 informal drop in sessions 
4 Information exchanges 
2 public meetings 
Meetings with Parent Councils of both primary schools 
Meetings with staff and children from both primary schools. 
Education Scotland also engaged with the community and 
produced their report of their findings. 
A final consultation report has been finalised and presented to 
the Policy Board in May 2024 with approval granted to 
construct a new primary school on the recommended location. 
Page 71 of 142

Page 76

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Learning Lessons and Building Capacity 
While the council’s initial response to the Bowles report 
was high level, we are assured by the Controller that its 
action plan in response is now sufficiently detailed and 
includes SMART objectives 
It will be important that this action plan is well‐managed 
by  senior  officers  and  closely  scrutinised  by  elected 
members of the council. 
Complete  Director of 
Finance and 
Resources 
This action plan and subsequent action plan relating to the s102 
report are closely monitored and reported to each cycle of the 
Audit, Risk & Scrutiny Board. 
However, there are still significant uncertainties relating 
to 
 the capacity needed in the long term, and 
 to the completion of the two building projects – 
the new primary school and the secondary school 
extension. 
We  therefore  request  that  these  matters  are  closely 
monitored in the annual audit work, and the Controller 
uses her powers to report any slippage or other issues to 
us if necessary. 
March 2024  Director of 
Children’s 
Services 
Managing the Risk of Future Capacity Uncertainty 
The inherent uncertainty in relation to long term (15 year) pupil 
growth projections has been widely reported by the Council 
over the past year as an ongoing risk through both formal board 
reports,  as  well  as  engagement  and  communications  with 
communities and in sharing data and reports with the external 
auditors. This is particularly recognised by the Council in the 
context of Dargavel Village having approximately 10 years of 
development still to deliver before achieving completion. It has 
also been trailed that the Council’s projection work to date with 
Edge  Analytics  has  identified  an  expectation  of  a  peak  in 
demand to be reached which will then fall to a stabilised long‐ 
term level of demand – a similar pattern of demand growth has 
been  evidenced  across  other  similar  long  term  community 
growth areas in the UK. 
The Council will regularly monitor actual pupil numbers and 
update long term projections on a regular basis over coming 
years as a key response to being able to pro‐actively manage 
this risk moving forward. 
Page 72 of 142

Page 77

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
This monitoring process will be key to assess the extent to which 
actual  demand  and  revised  projections  is  or  is  not  tracking 
against the current projections that have informed the planned 
capacity levels that will be delivered by the current learning 
estate interventions and provide early indication of any risk of 
material  deviation.  The  planned  annual  monitoring  and 
updating approach that will be deployed over coming years will 
be shared with the External Auditors as required. 
Long  term  projection  work  completed  to  date  has  already 
modelled a range of potential demand scenarios for the primary 
sector and identified an expected peak of demand in 2033/34. 
Options that can be considered for deployment in future years 
to  manage  upper  demand  scenarios  that  would  exceed  the 
planned capacity being delivered for primary sector education 
within  Dargavel  village,  have  already  been  identified  and 
reported through the Education and Children’s Services Policy 
Board  in  November  2023  and  shared  with  community 
representatives. 
Should the monitoring arrangements over the coming years 
highlight projection of sustained demand trending towards the 
upper demand scenarios, an appraisal will be required to assess 
which of the options is most appropriate for consideration to be 
deployed to meet the scale and nature of the additional future 
demand. This process will include early community engagement 
with school communities and will require timely assessment 
and associated decision making to allow planned delivery of any 
additional intervention well ahead of the developing need. 
In  relation  to  the  secondary  sector,  the  impact  of  higher 
demand scenarios will take longer to emerge (mid to late 2030s) 
and similarly it has been well trailed in Council reports and with 
Page 73 of 142

Page 78

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
the  community  that  long  term  monitoring  and  projection 
modelling  may  identify  the  need  to  consider  options  at  an 
appropriate  future  point  in  time  in  respect  to  any  further 
intervention and or decisions in relation to secondary sector 
provision across West Renfrewshire. 
Similarly, the long‐term monitoring arrangements will facilitate 
early  identification  of  such  risks  and  will  support  early 
engagement  with  the  appropriate  primary  and  secondary 
schools  that  may  be  impacted  by  any  future  school  estate 
changes. 
Delivery of New School Facilities 
It has been recognised by the Council that as a result of the very 
late identification of the significant under‐capacity problems 
within both the primary and secondary sectors serving Dargavel, 
the Council has since late 2023 been operating within a highly 
compressed non‐typical timeline to undertake all the associated 
capacity  planning,  land  assembly,  community  engagement, 
statutory  consultation,  space  planning,  procurement 
arrangements before moving into project delivery in order to 
achieve  operational  delivery  of  the  new  facilities  by  August 
2027. 
In broad terms, the Council is seeking to achieve all that is 
associated with the long‐term strategic planning, engagement, 
consultation and operational delivery of a new school and major 
extension of a secondary school in a 4 ½ year period, when such 
an end‐to‐end process would normally run over a much longer 
period – a timeline of around 6‐8 year would not be an untypical 
Page 74 of 142

Page 79

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
period  of  timeframe.  Consequently,  the  Council  is  parallel 
running several activities that would in most circumstances be 
delivered in a broadly consecutive manner. 
The  Council  has  established  governance,  programming,  and 
resource arrangements in place to support the delivery of the 
new primary school and secondary school extension over the 
remaining 3 ½ year period through to the operational target 
date of August 2027. 
To date the external auditors have not undertaken any detailed 
scrutiny  of  the  delivery  programme  or  the  arrangements  in 
place. To provide assurance officers will provide a full overview 
of the current arrangements for the external auditors for their 
review and will support whatever audit work is required to allow 
them to assess the Council’s current approach. 
Impact on Service Provision 
We note that the council has assessed that currently there 
has been no detriment to either teaching delivery or pupil 
education in the Dargavel and Bishopton areas from the 
interim measures introduced. 
We consider it critical that the council reports the results 
of  these  assessments  publicly,  regularly  and  in  an 
accessible  way,  to  maintain  and  rebuild  community 
confidence. 
Ongoing as 
part of the 
Service’s 
Quality 
Assurance 
Framework 
Ongoing and 
will be 
incorporated 
into parent 
and school 
Director of 
Children’s 
Services 
Head of 
Marketing and 
Communications 
Renfrewshire Council has a robust Quality Assurance framework 
involving regular meetings with Education Managers and school 
staff and planned school visits which focus in on the national 
quality assurance indicators (reviews). 
DPS had a visit in January as part of this process where key 
strengths under the national Quality Assurance indicators from 
How Good is Our School were evaluated, self‐improvement and 
self‐evaluation and Learning, Teaching and Assessment and a 
report was produced. In addition, Bishopton Primary School and 
Park Mains High School were both recently inspected by HMI, 
receiving very positive reports. 
Page 75 of 142

Page 80

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
newsletters at 
appropriate 
points. 
Further, every school submits a school improvement plan and a 
school improvement report (published on website) and their 
evaluations under the 4 key Quality Indicators (QIs) of their 
performance, based on data gathered through self‐evaluation, 
HMI visits, internal visits and stakeholder input is submitted to 
Children’s Services in April. 
These  are  shared  with  the  parent  councils  and  will  also  be 
published on the school website as part of the self‐evaluation 
process. This is in line with Education Scotland guidelines, the 
National Improvement Framework and statutory requirements. 
This communication with parents will be an ongoing process. 
The Commission is also concerned at the possible wider 
impacts of the council’s failings regarding the estimation 
of pupil numbers and whether this has had any impact on 
services provided by the council in the Dargavel area. 
We request that the Controller seeks further information 
on these issues so that we can understand the work that 
the council has done to understand these impacts. 
In line with 
requests 
emerging 
from defined 
audit 
programme to 
be set by 
Azets 
Chief Executive  Full details of all the additional areas of potential service 
impact (noted below) considered by the Council have been 
shared and discussed in detail with the External Auditor to 
support the Controller of Audit’s follow‐up report to the 
Accounts Commission. 
Support to Schools 
Early Learning & Childcare Provision 
Children’s social Care support 
NHS Service Provision & facilities 
Community Leisure & Recreation within wider Masterplan 
Transport & Active Travel Infrastructure Provision 
Public Bus Transport Provision 
Page 76 of 142

Page 81

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
Financial Management and Consequences 
The financial impact of these failings on the council is 
significant. The council capped the risk and contributions 
from BAE Systems under the Section 75 agreement, and 
as a direct result faces estimated net additional capital 
costs of £60 million, to be met by borrowing. This is a 
substantial sum of public money. The council needs to 
clarify the opportunity costs of this in terms of its overall 
capital programme. The council projects that it will have 
a revenue budget deficit of up to £50 million by 2026/27 
and will need to make difficult decisions on prioritising its 
spending, compounded by the financial consequences of 
this issue 
The council has recently negotiated a transfer of land 
from BAE for the construction of a new primary school. 
The Controller’s report indicates that this was in exchange 
for amendments to the extent and composition of the 
housing units for which planning permission has been 
granted. 
Given the reported determination of BAE to fully protect 
their commercial interests in the development, and the 
absence of alternative solutions for the council, it will be 
important to ensure and demonstrate that this exchange 
represents Best Value for the public purse. 
Ongoing 
March 2024 
Director of 
Finance and 
Resources 
Head of 
Economy and 
Development 
The Council will be required to manage the financial impact of 
the unplanned  delivery  of a new primary school and larger 
extension at PMHS through the delivery of its wider financial 
strategy  and  any  opportunity  costs  articulated  as  part  of 
developing and delivering that strategy. Regular reports with 
regards  the  Council’s  financial  position  and  outlook  are 
provided to Council, which include the financial consequences 
of the Dargavel failings. The next report to Council updating the 
financial outlook will be in September 2024. 
The financial and wider factors considered by officers as part 
of the negotiation process with BAE systems to secure the 
associated  land  agreement  and  adjustments  to  the  S.75 
agreement have been shared with the external auditors.  
Council Leadership, Governance, and Culture 
The  council’s  action  plan  will  be  hugely  important  in 
further  embedding  improvements  in  this  area.  In 
particular, the following elements must be progressed 
urgently and transparently: 
February 2024 
and ongoing 
in relation to 
the outcomes 
Director of 
Finance and 
Resources 
This report and combined action plan provides the Audit, Risk & 
Scrutiny  Board  with  an  overarching  view  of  all  progress 
associated with the Dargavel issue, subsequent investigations, 
reviews and agreed actions. 
Page 77 of 142

Page 82

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
•the council’s review of its scrutiny arrangements against
CIPFA good practice guidelines
• the council’s review of its approach to risk management
• the council’s leadership development programme for
officers.
To be satisfied of progress in these areas, the Commission 
requires  the  Controller  to  request  further  information 
from the council on the scope and timing of these actions, 
and  report  back  to  the  Commission  in  the  update 
requested for June 2024, or earlier if she thinks necessary. 
We also expect these issues to be covered in the 
accelerated Best Value report. 
associated 
with each 
action. 
The Commission is also concerned about the culture of 
the council and whether it has truly learned the lessons it 
needs to. 
We expect organisational culture to be an area of focus in 
the accelerated Best Value report. 
In particular, we request an update on whether the 
 culture of the organisation is appropriately open
and transparent,
 encourages continuous improvement,
December 
2024 (ie the 
confirmed 
timescale for 
BV audit work 
to conclude) 
Chief Executive  The  Council’s  auditors  concluded  that  the  Council  has 
appropriate  governance  arrangements  in  place  with 
improvements  over  the  years  in  member  and  officer 
relationships and effective leadership overall and were satisfied 
through  their  detailed  audit  work  that  the  Council  had 
demonstrated that the governance failings identified by the 
Bowles report were limited to the historic handling of Dargavel. 
The  auditors  did  not  highlight  any  concerns  over  the  wider 
organisational  culture  in  the  Council  or  in  its  approach  to 
managing major capital programmes but did identify that the 
role of the Audit, Risk and Scrutiny Board in ensuring effective 
scrutiny is not sufficiently clear.  The Council has recognised this 
and has completed a review of the Audit,  Risk  and  Scrutiny 
Board  governance  and  operating  arrangements,  with 
recommended  changes  being  agreed  by  the  Board  and 
subsequently by full Council.  
Page 78 of 142

Page 83

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
 effective  joint  working  between  officers  and 
members,  effective  scrutiny  and  challenge 
(especially by elected members), and 
 engagement and discussion with stakeholders. 
In addition, we request an assessment of 
 whether it has the right skills in the right places to 
deliver on its responsibilities, and 
 whether issues are escalated to the right level. 
Despite the finding of the Council’s auditors, the Commission 
has expressed concern in relation to the Council’s culture and 
have sought further assurances in relation to a wide range of 
organisational issues. 
It has been confirmed that consideration and assessment of 
such  issues  will  form  part  of  the  planned  Best  Value  Audit 
process and subject to confirmation of the planned detailed 
best value audit programme. 
Council  officers  will  provide  all  the  necessary  support, 
assistance,  and  information  to  allow  the  audit  team  to 
appropriately assess all key areas of interest and are actively 
progressing an internal self‐assessment and evidence process to 
support this element of the audit engagement in due course 
over the anticipated 2024 audit programme. 
Finally,  the  Commission  notes  that  the  auditor  has 
concluded  that  the  council  has  obtained  appropriate 
external legal advice and determined there is no potential 
for any form of action against former senior employees 
involved in the Dargavel School decision‐making. 
In addition, no disciplinary action has been taken against 
any senior officer involved in decision‐making relevant to 
the Section 75 approval process for the Dargavel Village 
development. 
The  Commission  accepts  that  these  are  management 
issues. 
March 2024  Head of 
Corporate 
Governance 
No senior officers involved in the Dargavel S.75 decision making 
process and identified in the Bowles Report remain employed 
by the Council or remained employed at the time of the Bowles 
report publication. In this context no senior officer could be 
subject to any form of internal Council disciplinary investigation 
or action. 
Full details of the process of consideration and legal advice that 
was sought regard to any other form of external legal action has 
been shared with the local external audit team as requested by 
the Commission. 
Page 79 of 142

Page 84

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
However, we request that the Controller asks the council 
for further information on the process followed and 
factors taken into account by the council in considering 
disciplinary action against staff involved. 
In addition, and looking forward, the Commission asks for 
information on 
 the council’s approach to performance 
management and 
March 2024  Head of HR & 
OD 
A full package of information in relation to current HR policies 
and procedures and future planned revisions has been 
provided to the external auditor. 
 
In June 2024, the Council in consultation with key 
stakeholders and trade unions revised both its people, 
performance and talent policy and discipline policy.   
Additional guidance and training is currently being developed 
for managers and employees, with an expected role out in 
the Autumn 2024. 
 its current policy on disciplinary action,   
so we can be assured that appropriate arrangements are 
in place to ensure that staff have the necessary skills and 
that  senior  officers  are  properly  accountable  for  their 
areas of responsibility. 
Page 80 of 142

Page 85

APPENDIX 1 
Action Plan Response Monitoring (Open Items) – August 2024 
CROSS PARTY WORKING GROUP ACTIONS
The outcome of the management training programme 
will be reported to the Audit, Risk and Scrutiny Board 
December
2024 
Director of 
Finance and 
Resources and 
Head of HR & 
OD 
The  first  cohort  of  the  programme  has  concluded  the 
programme, with feedback from this first round being used to 
inform the delivery of the programme to the next cohorts of 
senior staff. Delivery of the programme will continue over the 
course of 2024.  UPDATE ‐ Delegate and facilitator feedback on 
the first cohort has been presented to the Council’s Corporate 
Management Team for noting, along with proposed changes 
arising from feedback for the next scheduled cohorts of senior 
managers.    
 
The modules covered in the programme are: 
 
 Introduction to Personal Resilience; 
 Module 1 ‐ Effective Communication and 
Officer/Member Relationships; 
 Module 2 ‐ Governance, Risk and Financial 
Accountability; 
 Module 3 ‐ Managing Projects and Managing Change; 
 Module 4 ‐ Transformational Leadership 
 Module 5 ‐ Values, Vision and Planning for the Future 
 
Generally the feedback from cohort one (Chief Officer cohort) 
indicated a high level of satisfaction with the programme 
overall. Collaboration with other colleagues during the 
programme featured strongly with learning through shared 
experiences. There was positive feedback around learning 
from colleagues, strengthening networks across services and 
shared experiences, which will create consistent approaches 
around best practice. Some feedback was received around the 
content being more ‘Renfrewshire’ specific, including 
organisational challenges and use of case studies. Increased 
use of local examples and practical application is being 
incorporated into the programme for cohorts 2 and 3.   
Page 81 of 142

Page 86

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – May 2024 
Page 82 of 142

Page 87

Consultation Review
Dargavel School Consultation
Introduction
As part of a broader review of Renfrewshire Council’s consultation practice,
The Consultation Institute was commissioned to review consultation practice
in relation to the Dargavel School consultation in particular and across the
Council more generally. The aim was to identify areas of good practice and
make recommendations for improvement.
The first recommendation is that the Council adopt the Consultation
Readiness Framework as a tool to help structure consultations.
The review uses the Consultation Institute’s Consultation Readiness Framework
as a baseline. The review aims to understand how effective the consultation
practices deployed by Renfrewshire Council in respect of the new school at
Dargavel were, and to develop broader recommendations for the Council
more generally. To do this the Consultation Readiness Framework was used as
an interrogatory tool. Normally this framework is used with public authorities
preparing for a consultation, and its use would be assisted by an advisor from
The Consultation Institute who guides the authority through the process.
The case law on consultation is guided by the “Gunning Principles” which set
out how consultors should act. The Consultation Readiness Framework aims to
operationalise these principles. The Gunning Principles are:
Gunning 1:
Proposals are still at a formative stage A final decision has not yet been
made, or predetermined, by the decision-makers.
Gunning 2:
There is sufficient information to give ‘intelligent consideration’. The
information provided must relate to the consultation and must be available,
accessible, and easily interpretable for consultees to provide an informed
response.
Page 83 of 142

Page 88

Gunning 3:
There is adequate time for consideration and response. There must be
sufficient opportunity for consultees to participate in the consultation. There is
no set timeframe for consultation, despite the widely accepted twelve-week
consultation period, as the length of time given for consultee to respond can
vary depending on the subject and extent of impact of the consultation.
Gunning 4:
‘Conscientious consideration’ must be given to the consultation responses
before a decision is made. Decision-makers should be able to provide
evidence that they took consultation responses into account.
Methodology
The Framework is designed for consultations not covered by statutory
requirements, and therefore the review takes into account the requirements
placed on the Council by the Schools (Consultation) (Scotland) Act
2010 (hereafter ‘the Act’), which imposes different requirements, such as the
selection of a single option for consultation.
The Council has gone beyond the requirements of the Act in consulting on,
for instance, the Park Mains extension. And the aim of consultation is at least
twofold. One is to comply with the existing legislation in order to act within the
law. The other is to improve the quality of decisions made. It is in this latter
area that learning could lead to enhancement. By effectively identifying the
community and service user needs and designing solutions to fit those needs
more efficient and effective services with more public support can be
delivered.
The Consultation Readiness Framework covers the stages required to comply
with best practice and case law on consultation. It therefore allows a public
authority to achieve both the aim of remaining within the law and to fully
considering both the range of options and how to choose between them.
The timescales in the case of Dargavel Primary School are extremely
compressed and many of the questions about the status quo are answered
by the situation. But there are important lessons to be learned about how to
explore the status quo and the appropriate solutions.
One element of the consultation that points to this need was the late
emergence of requests for a joint campus High School-Primary School-Nursery
on the suggested site. The decision had already been made that this would
be an additional Primary School. This was, in no small part a function of the
reduced time available to do pre-consultation. It is not a failing of this
process. But it points to one of the ways in which the consultation could have
been better focused on the issue being consulted upon.
Page 84 of 142

Page 89

Page 85 of 142

Page 90

The Consultation Framework is designed to ensure that any consultation is
fully documented, structured and transparent. It breaks the process down
into a number of stages:
 Status quo exploration;
 Solutions exploration;
 Solutions development;
 Options appraisal;
 Status quo exploration;
 Solutions exploration.
We should note that stages of the process will overlap, and fit with the linear
process recommended by The Consultation Institute, represented in
“Consultation in Change Management”.
Figure 1: Consultation in Change Management
Preconsultation - Phase 0
0.1 This stage is one of engagement with key stakeholders, selected service
users and wider public, to offer the opportunity to provide feedback on the
current situation, the proposed objectives for change, and to provide
feedback on what currently works well, what needs to change and any
concerns held.
0.2 Further engagement with key stakeholders, selected service users and
wider public regarding what should be considered in developing solutions.
Development of an initial long-list of potential solutions which meet the
objectives for change, challenges and issues raised.
Page 86 of 142

Page 91

0.3 Working with key stakeholders, selected service users and wider public to
refine potential solutions into a set of more practical solutions based on
learning from engagement to date and sense checking of ideas.
0.4 Engagement with key stakeholders, selected service users and wider
public to appraise options and eliminate those least viable. The intent is to
establish a ranked set of potential options that can be taken forward to
public consultation.
Comments:
The Consultation Readiness Framework offers a clear pathway to
operationalise the Gunning Principles and other good consultation practice,
this review is based on those principles and practice and the Framework
helps authorities to structure consultation activities.
The pre-consultation stage of the Dargavel consultation is well evidenced
and meets the requirements of the Framework in the provision of published
scope and purpose of change. It clearly sets out the current data and
pointed to the need for further evidence. This was a key learning from
previous mistakes.
The Equality Impact Assessment process was completed and informed other
aspects of the process, showing effective implementation of equalities
thinking.
The stakeholder analysis and identification was well conducted and
evidenced with some stakeholders being required in legislation and others
identified through the Equality Impact Assessment.
The options and the hurdle criteria were developed by experts, working on
the basis of the requirements of the relevant legislation in the Act. This meets
the legal requirements, but an approach that included engagement with a
stakeholder reference group, or other deliberative approach may have
identified the issues around the desire for a joint primary-high school campus
earlier in the process, allowing for better consideration of options.
The invitation to the community to suggest sites for the new Dargavel Primary
is helpful and increased involvement in the development of options will help.
Institutionalising these approaches will help to make them more effective.
There was a concerted and well-structured approach to including the
seldom heard, including intelligence from Primary School Head Teachers,
and a thorough communications plan which adopted multi-channel
approaches to ensuring that as wide a group of stakeholders as possible was
engaged.
Page 87 of 142

Page 92

The information sources, including option definition, appraisal criteria,
equalities assessments, accessibility assessments are all available, but should
be collated so that they are accessible to participants.
Recommendations:
1. Adopt the Consultation Readiness Framework as a structure for
consultations;
2. Consider establishing a stakeholder reference group for consultation.
You may wish to consider this on wider issues on a Council-wide basis to
help with processes like the development of stakeholder analysis,
options appraisal and ensuring the seldom heard are involved;
3. Consider a deliberative process for the development of stakeholder
lists and for mapping stakeholders by interest and influence;
4. Bring together all relevant data sources and documentation in a single
website, so that they can be easily accessed by participants.
Consultation scoping and governance - Phase 1:
A clear definition of who is accountable for the public consultation and how
decisions will be taken.
A clear statement of the scope, purpose and objectives for the public
consultation, and this has been agreed by decision makers.
Comments:
The case for change is fairly clear in the Dargavel context, and therefore
required little scrutiny. But for wider learning, it may be important to develop
processes like a consultation mandate, scope of change and potential
options. There should be a clear process for the development of both options
and the criteria by which options will be chosen.
The range of options developed and examined was really comprehensive
and the criteria clear, but there was little deliberation on the development of
criteria for selecting the site.
In other contexts the Council may wish to use the Consultation Institute’s
“Consultation Mandate” which identifies the following steps as a way of
defining the scope of the consultation:
 Identity (of consultor)
 Target (likely impacted groups)
 Issue (reason/purpose for consulting)
 Actor (decision maker)
 Action (decision(s) to be taken)
 Date (by when)
Page 88 of 142

Page 93

 Wider Aim (of policy)
In the case of the new Dargavel Primary School, much of this was defined in
advance by the situation, but as an exercise for the consultation team and
the pre-consultation, this can help to provide definition.
Roles and responsibilities for the management of the consultation were
clearly laid out in the Communications Strategy and Stakeholder
Engagement documents.
There has been a clear report of the findings from each stage which meets
the legislative requirements required of a school consultation.
Recommendations:
5. The consultation mandate should be adopted to help define future
consultations and to clarify responsibilities;
6. There should be consideration given to taking deliberative approaches
to option development and deciding criteria;
7. The governance documents should be made available for
consideration to stakeholders at this point.
Project Planning – Phase 2
Phase 2.1 Structure and Resourcing
The project plan should offer a clear structure for the management of each
stage of the consultation process and this should include who undertakes the
consultation and whether this is by an external organisation or internally.
Identifying ownership and resources available for delivery at each stage of
the consultation process.
Comments:
There is a clear project plan for the New Dargavel PS project, which is well
defined in the Act. For other, less defined consultations the development of
project plans is vital.
There are clear resources available for each stage of the process and there
are owners for all the tasks.
There is sufficient time for the consultation to enable all to be involved, given
the constraints of time in providing a new facility.
There are clear resources allocated and there is a clear owner for each risk.
As part of the learning, Project plans should include:
Page 89 of 142

Page 94

 Clear milestones;
 A timeline covering the 3 main stages of the consultation process;
 The key post-consultation tasks are identified and resourced from the
beginning – analysis, feedback and decision-making are accounted
for;
 There needs to be appropriate time for impacted groups to engage
and respond;
 Data handling policy and processes;
 Risk analysis and mitigation plan.
Recommendations:
8. Add an explicit indication of who will undertake analysis at an early
stage, and whether this will be an internal or external analyst;
9. Adopt a checklist if not already in place covering the points above;
10. Create a risk register and mitigation plan for each project.
Phase 2.2 Stakeholder analysis
The stakeholder landscape and impacted groups should be identified and
prioritised to inform the communications and dialogue activities.
Comments
This has been largely dealt with above under ‘Stage 0’. There was a clear
attempt to diversify messages in order to reach the widest possible range of
groups and a focus on the seldom heard. This could be more closely linked to
the stakeholder analysis for clarity.
Recommendation:
11. Mapping the communication strategy against the stakeholder analysis
will allow for clear approaches to be developed to segment
communication more effectively.
Phase 2.3 Engagement and Communication
The project plan outlines appropriate engagement and communications
approaches to enable stakeholders and impacted groups to engage with
the consultation and provide feedback.
Comments:
The engagement and communication plan is comprehensive and covers
much of what is expected, including the details of proposed engagement
Page 90 of 142

Page 95

approaches and how they align to stakeholder groups. This is one of the
strongest parts of the programme.
The community could be assured that there is a detailed response
mechanism and data journey, even if these are not described as such.
There is a strong social media policy that covers the requirements. Similarly,
the complaints handling policy covers the relevant points.
Recommendation:
12. Set out the data journey and response mechanism on the consultation
website.
Phase 2.4 Post consultation activities
The project plan identifies the activities to be undertaken post-consultation
and explains how this will support decision-making.
Comments
To give greater confidence in the impartiality of the analysis and to help build
trust an external consultant was contracted to analyse the consultation
response data. This report separated quantitative and qualitative data to
ensure that the strength and salience of arguments could be assessed.
For other consultations there should be a clear statement of how this analysis
will be undertaken and how both strength and salience of arguments will be
assessed.
This should include provisions to ensure that data integrity is maintained.
The timelines for decision makers are set out in the act, and conform to
Council meeting cycles, but in other consultations this should be set out, with
contingency plans where deadlines might not be met.
The process meets the requirements of the Equality Act and future
consultations should ensure that this is a clear part of the process, integrated
from the start.
The communications plan sets out how the decision will be publicised and
communicated and this should be a core part of any future consultation.
Page 91 of 142

Page 96

13. A data analysis plan be prepared for any given consultation, outlining
how and by whom data will be analysed. The plan should set out how
different data sets will be analysed and reported;
14. There is a statement of the information to be made available to
decision-makers so that the data analysis plan and report structure
meet these requirements;
15. The plan should set out how decision-makers will be allowed sufficient
time to ensure conscientious consideration of the feedback;
16. There is feedback approach to ensure that ‘due regard’ for equalities
requirements is met by decision-makers;
17. There is a clear statement of how the decision will be publicised and
communicated.
Phase 3.1: Documentation Development
The consultation has supporting documentation and materials which allow
intelligent consideration of the issues and proposals in line with the Gunning
principles.
Comments:
The materials in this consultation offer both sufficient detail for effective
comment by citizens and consideration by decision-makers. They allow for
the Gunning 4 requirement of intelligent consideration. The materials are also
based on meeting the requirement of the Equality Act 2010, but this could be
made more explicit in the text.
Copies of all consultation materials to be published are available for review
and can demonstrate they have met tCI requirements of integrity,
accessibility and transparency.
Accessible versions of documents, in plain English, EasyRead or similar formats
have been prepared and are available upon request by email.
The consultation website meets tCI requirements.
The Equality impact analysis demonstrates that the requirements of the
Equality Act 2010 have been considered. Though again, using a stakeholder
reference group as a sounding board for these exercises would help to make
the analysis more robust and to ensure that the lived experience of people
with protected characteristics is included.
Digital media (mainly charts and maps) are provided with an explanation of
how they align with the requirement to provide similar information on the
proposals and likely impacts. 
Recommendations:
Page 92 of 142

Page 97

The website is easy to find with good SEO and demonstrates accessibility and
ease of navigation.
Recommendation:
18. There should be clearer reference to the Equality Impact Assessment in
the documentation, and where it has influenced changes in the
process and outputs.
Phase 3.2 Consultation Questions
The consultation questions are designed to enable feedback appropriate for
the objectives of the consultation and the decisions to be taken, and are
drafted in a neutral and open manner.
Comments
The consultation questions were clear and unambiguous. They were checked
with an external advisor before publication and allowed for a full and free
expression of citizens’ views.
The questions could have been supplemented with more explanatory
material to help respondents to understand the reasoning behind the
question, but the material provided in the consultation more broadly did this
effectively. It is still something that would add clarity to future consultations.
The questionnaire was available in digital format and could be printed off for
a paper response. It was available through trusted outlets such as libraries.
Recommendation:
19. Questionnaire questions should be placed in the decision-making
context to allow for more effective responses.
Conclusions
The consultation on the Dargavel Primary School gives a clear example of
work under pressure and in circumstances that test consultation practice.
There is considerable good practice, and the consultation effectively
allowed citizens to voice their preferences.
A number of areas offer the opportunity for improvement, particularly greater
citizen involvement in options development. While the very constrained
timelines may have made more involvement feel difficult to deliver, the
Page 93 of 142

Page 98

emergence of an un-scoped (joint campus) option in the final consultation
shows the risks of expert-only options development. While this option was
already covered by an existing catchment High School, understanding the
case for a joint campus would have helped to focus the consultation on the
issue at hand.
One key element of practice that could clearly improve is the development
of risk assessments and risk ownership, which can help to manage dynamic
changes that may emerge through the consultation or in other parallel
processes.
Comments specific to the Dargavel Consultation:
The clearest learning from the Dargavel Primary School Consultation is that:
1. Options appraisal benefits from citizen input to allow better
consideration of possible approaches;
2. Very constrained timelines should be avoided, unless, as in this case
strictly necessary;
3. Risk assessment can help to prepare the authority for dynamic
changes in the consultation process;
4. A clear Consultation Mandate would have helped to structure the
process and offer clarity to participants about what was being
consulted upon;
5. An analysis plan should have been set out at the beginning of the
process to identify how the responses from the consultation would be
handled.
The other recommendations are broader and can be used to guide future
consultation practice.
Peter McColl
Senior Associate
The Consultation Institute
May 2024
Page 94 of 142

Page 99

Appendix 1 Collated recommendations
Preconsultation
1. Consider establishing a stakeholder reference group for consultation
You may wish to consider this on wider issues on a Council-wide basis to
help with processes like the development of stakeholder analysis,
options appraisal and ensuring the seldom heard are involved;
2. Consider a deliberative process for the development of stakeholder lists
and for mapping stakeholders by interest and influence;
3. Bring together all relevant data sources and documentation in a single
website, so that they can be easily accessed by participants.
Consultation Scoping and Governance
4. The Consultation Institute’s “Consultation Mandate” should be adopted
to help define future consultations and to clarify responsibilities;
5. There should be consideration given to taking deliberative approaches
to option development and deciding criteria;
6. The governance documents should be made available for
consideration to stakeholders at this point.
Project Planning
7. Adopt a checklist if not already in place covering the points above;
8. Add an explicit indication of who will undertake analysis at an early
stage, and whether this will be an internal or external analyst;
9. Create a risk register and mitigation plan for each project.
Stakeholder Analysis
10. Mapping the communication strategy against the stakeholder analysis
will allow for clear approaches to be developed to segment
communication more effectively.
Engagement and Communication
11. Set out the data journey and response mechanism on the consultation
website.
Post Consultation Activities
12. A data analysis plan be prepared for any given consultation, outlining
how and by whom data will be analysed. The plan should set out how
different data sets will be analysed and reported;
Page 95 of 142

Page 100

13. There is a statement of the information to be made available to
decision-makers so that the data analysis plan and report structure
meet these requirements;
14. The plan should set out how decision-makers will be allowed sufficient
time to ensure conscientious consideration of the feedback;
15. There is feedback approach to ensure that ‘due regard’ for equalities
requirements are met by decision-makers;
16. There is a clear statement of how the decision will be publicised and
communicated.
Documentation Development
17. There should be clearer reference to the Equality Impact Assessment in
the documentation, and where it has influenced changes in the
process and outputs.
Consultation Questions
18. Questionnaire questions should be placed in the decision-making
context to allow for more effective responses.
Page 96 of 142

Page 101

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Bowles Report Recommendation 1
Build a more robust model of primary school need for Dargavel ‐ the Council should continue to refine its pupil forecast model for Dargavel. 
Response Objectives 
Deliver robust projection modelling for Dargavel and PMHS which: ‐ 
 considers live information arising from NHS, pupil & ELC registrations, the pace of development to date, certainty over development size and likely
pace of future build out rate,
 utilises external data analytics and projection expertise to augment and enhance the Council’s in‐house forecasting approach to ensure modelling is
robust, underpinned by external challenge and specialist input reflecting the complexity and significant portion of Dargavel that has yet to be
developed out over a circa 10 year period,
 provides modelling output which considers potential future upper scenarios reflecting the high yield factors reflected in the 2023/24 P1 intake to
inform immediate decisions on scale of capacity to be delivered as well as planning for potential additional interventions at a future time,
 delivers modelling output which provides a long‐term view beyond the anticipated completion timeline for Dargavel to ensure the long term impact of
Dargavel is modelled and understood,
 provides modelling output over the long term which indicates both the scale, timing and shape of an anticipated peak in demand that will accompany
a development of this scale and nature. This will provide visibility of the anticipated short‐lived peak in demand and long term settled demand to
ensure this is appropriately reflected in estate/capacity decisions and in particular to mitigate against delivery of excessive long term / permanent
increase in capacity that would result in excess unused surplus capacity over the long term.
 Provides modelling that can be tested and revised as necessary as new key data becomes available such as P1 and S1 registrations, actual scale and pace of the
development and any new developments, which will continue to inform decisions on any future estate interventions if required.
Page 97 of 142

Page 102

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Complete Council modelling through to the anticipated end 
date for the housing development (2033/34) based on 
assumed 4,300 units and available live data. 
October 
2022 
Director of 
Children’s 
Services 
Completed October 2022 
Engage and appoint Edge Analytics to deliver enhanced 
modelling approach for both Dargavel primary 
requirements as well as PMHS out to 2033/34 and updated 
live datasets. 
February 
2023 
Director of 
Children’s 
Services 
Completed February 2023 including additional upper forecast 
scenarios for Dargavel non‐denominational requirements to 
support management of risk associated with long term yield 
remaining at similar level to 2023/24. Informed reports to 
Education and Children’s Services Board in March and May 2023 
Extend Edge engagement to deliver an enhanced model 
projecting out to 2038 to provide longer term forecast to 
assess the full impact on the secondary sector and allow 
identification of likely timing and scale of peak demand 
encapsulating any relevant updates to live datasets. 
September 
2023 
Director of 
Children’s 
Services 
Modelling completed which has identified an anticipated peak 
period in both primary and secondary sectors and will be 
reported to Education and Children’s Services Board in November 
2023. 
Provide update to November Education & Children’s Service 
Policy Board. 
November
2023 
Director of 
Children’s 
Services 
Two update reports were taken to the November ECSPB: 
1. Learning Estate 
2. Dargavel Housing Development – Impact on 
Denominational Education Provision 
 
Bowles Report Recommendation 2
Use of Bishopton Primary - in its future plans the Council should reconsider how surplus capacity at Bishopton can be used effectively.
Response Objectives 
Page 98 of 142

Page 103

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Consider and assess how existing capacity within Bishopton Primary School may be best utilised to support the Dargavel catchment over the immediate term 
and potentially over the longer term, taking into consideration the uncertainty and risk over the long‐term demand levels that will ultimately emerge for 
primary education from Dargavel as well as the expectation of a temporary peak period of demand. 
Provide a report to Education and Children’s Services Board setting out a clear overview as to how Bishopton PS capacity will be utilised to support temporarily 
over the short term period and how it may be considered amongst other options for use to support Dargavel in the longer term (noting that any such longer 
term use will be subject to detailed consideration and decision at an appropriate point in future years). 
Complete assessment of anticipated P1 intake from 
Dargavel catchment and assess against revised DPS capacity 
availability, establish planned P1 intake capacity cap and 
anticipated P1 intake requiring accommodation at 
Bishopton Primary School. 
August 
2023 
Director of 
Children’s 
Services 
Planned use of Bishopton Primary School along with planned 
capped entry levels to Dargavel Primary School reported an 
approved at Education and Children’s Services Policy Board in 
August 2023. There will be a requirement to annually monitor 
anticipated and actual P1 intakes carefully to assess adequacy of 
short term capacity provision across both Dargavel and 
Bishopton Primary Schools to meet demand pending the second 
primary school in Dargavel coming on stream. 
Complete an exercise to assess the timing, scale and range 
of potential demand level scenarios, in particular 
understanding the scale and timing of the peak demand and 
likely settled long term demand. This information will be 
used to inform the assessment of how Bishopton Primary 
School could, if required, be potentially be utilised as an 
option in the longer term. 
January 
2024 
Director of 
Children’s 
Services 
Completion of the updated work with Edge Analytics has 
provided a view of the likely timing and length of the peak 
demand period – with peak primary demand being forecast in 
2033/34 which will fall over the second half of the 2030s to a 
more settled level. Further work is being progressed to update 
this information for the recently released 2023 census 
information and November registration data to inform an overall 
assessment. 
 
Revised roll projections for the entire learning estate are 
currently being produced. In anticipation of these, work is 
underway by utilizing current live data and matching this with 
draft roll projection data to run scenario planning for the short, 
medium, and long term capacity demand on both Dargavel 
Primary and Bishopton Primary. 
Page 99 of 142

Page 104

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Complete financial analysis to understand the potential 
financial context of utilising Bishopton Primary School 
Capacity 
May 
2023 
Director of 
Finance and 
Resources 
Bishopton PS is a predominantly 1960s construction and is more 
than 60 years old. This building will, along with the whole school 
estate, undergo an updated condition survey over coming 
months. Notwithstanding, given the underlying age of the 
building it will inevitably have a limited remaining lifespan 
before being considered for replacement. 
 
Existing surplus capacity if used permanently to reduce the 
required size of a second Dargavel primary school, will require to 
be replaced as part of a renewal programme. The determination 
of the timing of that will be subject to work progressed as part of 
the strategic learning estate programme. 
 
Consequently, it has been assessed that any financial advantage 
from utilising Bishopton PS will be restricted to a temporary time 
value of money benefit and consequently will be relatively 
limited. 
 
In addition, there is also a risk that utilising Bishopton PS 
permanently removes its availability to provide supporting 
capacity to manage both a temporary peak that may arise from 
upper end educational demand scenarios and longer term upper 
end demand. There could be the risk that in such circumstances if 
Bishopton capacity was no longer available this would lead to 
higher overall costs over the longer term for the Council. 
 
The financial considerations and risks were incorporated into the 
overall assessment reported as part of the Education & Children’s 
Services Board report in January. 
 
 
 
Page 100 of 142

Page 105

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Set out overview in a report to the Education and Children’s 
Services Policy Board in respect to the potential long‐term 
utilisation of Bishopton Primary School which will be subject 
to detailed consideration at an appropriate point in future 
years as actual long term demand trends increasingly 
emerge. 
January
2024 
Director of 
Children’s 
Services 
Work to allow appropriate recommendation to be made is 
progressing in line with plans and scheduled to be reported to 
Board in January 2024. A paper was presented to Board in 
January 2024 
Page 101 of 142

Page 106

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Bowles Report Recommendation 3
As the Council progresses its plans to issue supplementary guidance on developer contributions for education it should seek to learn from other Councils in 
Scotland. 
A development the size of Dargavel is exceptional and would need its own modelling techniques. However, for smaller developments the Council should create 
an evidence base to calculate specific yield factors derived from recent developments in Renfrewshire. Such robust data will ease future negotiations. 
Undertake a desk top review of other local authorities 
across Scotland and identify key best practice councils to 
engage. 
June 2023  Head of 
Economy and 
Development 
Completed 
Complete detailed engagement with identified best practice 
councils arising from desk top research 
Summer 
2023 
Head of 
Economy and 
Development 
Detailed engagement completed with Fife, Falkirk and West 
Lothian councils. 
Complete data analysis exercise of a range of datasets of 
mixed historic sites across Renfrewshire to provide 
empirical evidence to support actual pupil yields to inform 
establishment of appropriate yield factors to be used in 
future contribution policy. 
 Refresh % capacity of all schools (vs school rolls) 
 Sample research of Pupil Product Ratio (PPR) for developed housing 
sites (< 10 units) [min 10 site sample] 
 Sample research of PPR for developed housing sites (> 100 units)[min 
10 site sample] 
 Sample research of PPR for established / mature housing 
development to provide longer term perspective (eg. 15 years old) (> 
100 units)[min 4 site sample] 
 Identify individual schools where pupil capacity is above notional 
threshold (85%) 
October 
2023 
Head of 
Economy and 
Development 
Work on this is now complete, agreed new draft planning 
guidance presented to March 2024 PCC Board. 
Page 102 of 142

Page 107

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
 Identify all known undeveloped housing sites in individual school 
catchments
 [Subset of 5] identify all housing sites with current "live" planning 
application
 Identify schools where it is anticipated intervention would be required 
to increase capacity based on potential future housing to be delivered 
over next 10 years to inform likely future developer discussions.
Incorporate into the development of the draft contributions 
policy targeted to be presented to the Planning and Climate 
Change Policy Board in January 2024. 
March 2024  Head of 
Economy and 
Development 
Work on this is now complete, new draft planning guidance 
presented to March 2024 PCC Board. 
Bowles Report Recommendation 4
Council needs to work co‐operatively with BAE. Unless the Council and BAE can work together to resolve the current problems, BAE may face accusations, 
whether founded or not and regardless of Council incompetence, that it has increased its profits at the expense of Council taxpayers. 
Response Objectives 
Secure legal ownership of suitable land to facilitate delivery of a second school within Dargavel Village as well as additional land next to existing school site to 
provide increased flexibility to meet potential future extension of the school and or establishment of greater outdoor space. 
Secure legal commitment from BAE to provide land remediation and associated infrastructure requirements as part of legal agreement at nil cost to the 
Council. 
Secure as part of the legal agreement certainty on consented planning numbers and any associated adjustments to s.75 agreement to reflect revised 
agreement. 
Secure with BAE agreement on Heads of Terms for allow for 
mutual governance approval from each organisation to 
inform detailed legal agreement drafting and final sign off 
As soon as 
possible 
Chief 
Executive 
This was completed and approved by ILE Board end of August 
2023 
Page 103 of 142

Page 108

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
was 
targeted. 
Secure completed and signed legal missives to deliver in full 
the objectives outlined above to provide certainty and 
timing of availability of remediated and infrastructure 
proofed land to support wider school delivery planning and 
consultation arrangements that will be progressed by the 
Council team. 
August 
2023 
Chief 
Executive 
Legal missives concluded mid‐September 2023 
Proposed revisions to S.75 negotiated with BAE Systems 
were approved by ILE. Revised S.75 signed off by both the 
Council and BAE Systems to legally conclude matters. 
August 
2023 
Head of 
Economy & 
Development 
Approved by Planning and Climate Change Board August 2023 
Bowles Report Recommendation 5
Corporate working and organisational culture ‐ although I understand that the Council has sought to improve and strengthen corporate working in recent 
years, the evidence would suggest there is a long way to go; simply establishing corporate working groups is insufficient if staff are in a mindset of ‘not my 
problem’. 
The failure of management oversight, if symptomatic of the Council as a whole, would be deeply disturbing. The Council needs to consider a significant change 
programme, not just on the of issue of corporate working and personal responsibility, but also its organisational culture and values. It needs plans to build a 
stronger organisation where constructive challenge is welcomed and there is a clarity of what is expected of all of those in a leadership role. 
Response Objectives 
Provide assurance that established programme governance framework and operations of governance for other major capital investment programmes and 
specifically that the Bowles findings on the historic failings on the handling of Dargavel by officers are not representative of the Council’s current culture and 
approach to the management and delivery of major programmes. 
Page 104 of 142

Page 109

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
The Council is committed to living its values as a learning and collaborative organisation and post COVID was already in the process of re‐establishing an 
Leadership Development programme for senior leadership teams and managers across the Council in recognition that this required to be reinvigorated post 
COVID and that there has been significant turnover in management and senior positions over the past three years and this would support growing and 
maturing the current culture and collaborative connections across the organisation. 
In response to the Bowles recommendations, the objective is to ensure the new Leadership Development programme is appropriately cognisant and reflective 
of the key learning points from the Bowles report and takes the opportunity to ensure its coverage seeks to re‐enforce the development of skills related to 
governance, risk management, commercial risk, corporate working and culture etc and effectively utilises failures referenced in the Bowles report as key 
examples for learning throughout the programme. Collective reflection and learning of such significant failures – albeit historical – is recognised as an 
important element of building an effective future culture and ways of working across the organisation. 
Undertake a health check assessment on major capital 
programmes to provide reassurance in respect to all aspects 
of governance, control, reporting and management of 
programmes. 
October 
2023 
Chief 
Executive 
supported by 
CMT 
City Deal and Infrastructure Health Check report was submitted 
to CMT on 21 November 2023. 
Put in place arrangements to deliver a comprehensive 
Leadership Development Programme (circa 12 months + 
programme) for chief officers and senior managers which 
amongst other things will cover and key areas referenced in 
the Bowles report in respect to governance, accountability, 
risk management, collaborative working, member officer 
relations etc. 
Commence 
programme 
by 
September 
2023 
Director of 
Finance & 
Resources 
and Head of 
HR & OD 
Contract engagement in place and resources secured from 
SOLACE Enterprises to support co‐designed and co‐delivered 
programme. 
Initial Chief Officer programme launch event occurred on 3rd 
October with focusing on personal resilience. 
The programme has delivered sessions focussed on: 
 Effective Communications and Elected Member Relations 
 Programme Management, Leading and Navigating 
Strategic Change 
 Risk Management and Governance 
 Transformational Leadership 
 Delivering Corporate/Team Values and Vision 
Page 105 of 142

Page 110

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
This first leadership development programme has now been 
concluded with an evaluation process underway. Attendance 
was good throughout the programme and for any officers that 
were unable to attend parts of the programme, they will attend 
these specific modules during the next cohort grouping to ensure 
completion of the full programme. 
The next 2 Cohorts will be run from April to around September 
and with up to 60 places available for our next tier of 
management. There will be some revisions to content and 
emphasis based on feedback from the initial sessions, however 
the key themes of the programme will remain unchanged. 
 
UPDATE 
An evaluation of the leadership development programme for 
the first cohort of delegates (Chief Officers) has now been 
completed.  Positive feedback was received from both the 
delegates who attended and from the facilitator(s) who 
delivered the programmes.  This feedback has helped shape 
the programme for the next 2 cohorts of senior managers 
which are currently running, and due to complete October 
2024.  The evaluation feedback has been presented to the 
Council’s Corporate Management Team for noting. 
 
 
 
 
 
 
 
 
 
Page 106 of 142

Page 111

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Design and undertake an evaluation process of the 
Leadership Development Programme for Chief Officer 
cohort to inform required changes / adjustments to 
programme delivery for next management cohort. 
March 2024  Head of HR 
and OD 
Initial feedback was requested as part of the final workshop of 
this first programme. An evaluation request, designed in 
partnership with SOLACE, will be sent out to each of the 
participants asking if their knowledge has increased, if they feel 
more confident and informed and what changes, if any, would 
participants suggest for the next cohort.  
 
Generally the feedback from cohort one (Chief Officer cohort) 
indicated a high level of satisfaction with the programme 
overall. Collaboration with other colleagues during the 
programme featured strongly with learning through shared 
experiences. There was positive feedback around learning from 
colleagues, strengthening networks across services and shared 
experiences, which will create consistent approaches around 
best practice. Some feedback was received around the content 
being more ‘Renfrewshire’ specific, including organisational 
challenges and use of case studies. Increased use of local 
examples and practical application is being incorporated into 
the programme for cohorts 2 and 3.   
Bowles Report Recommendation 6
Risk management 
From documents I have seen the Council was unaware of the scale of risk it was taking in the calculation of pupil numbers. The identified risk in Council 
documents related to providing the school on time, not that the size of the school may prove to be inadequate.  The failure to identify that risk has had two 
consequences; first the Council has been slow to react to the increase in pupil numbers and second the Council did not negotiate with BAE with that risk in mind. 
Page 107 of 142

Page 112

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
The Council needs to review how it both identifies risk and manages it. 
Response Objectives 
Progress actions to provide reassurance in relation to the Council’s current risk management approach, in particular how this is approached, deployed and 
managed as part of major projects as well as considering and assessing the seniority / appropriateness of officer involvement and related skills across officers 
involved in the process. 
A review of risk profiles across all service departments to 
ensure visibility of all risks and confirmation of where 
certain risks are being monitored if outwith the standard 
Risk Reports to the Audit, Risk and Scrutiny Board (i.e., 
Health and Safety Planning Groups, Service Improvement 
Plans etc) 
October 
2023 
Director of 
Finance and 
Resources 
Risk report submitted to Audit, Risk & Scrutiny Board as planned 
on 6 November 2023. 
A review of the ‘service risk representative’ roles in each 
service department to ensure the representatives who sit 
on the Corporate Risk Management Group are sufficiently 
involved in risk matters within the service, to feed this into 
the Corporate Risk Management Group and that they also 
have authority within the service to provide challenge as a 
‘critical friend.’ 
October 
2023 
Director of 
Finance and 
Resources 
Action completed. CMT agreed (10 October 2023), that each 
Director will nominate a Head of Service and one other colleague 
to support the Head of Service in the role going forward. 
Delivery of a project risk management workshop specific to 
the planned new primary school in Dargavel (complete) 
August 
2023 
Director of 
Finance and 
Resources 
Workshop delivered covering nature of project risks, risk changes 
over lifecycle of the project; reminder of Council PM framework 
and PMU support; key issues re good governance. 
Delivery of project risk management training with all PMU 
colleagues (in a train the trainer format) so colleagues are 
delivering this as part of project kick‐offs to support a more 
risk focussed culture in the organisation. 
September 
2023 
Director of 
Finance and 
Resources 
This was completed on 12/10/2023. PMU staff received a ‘train 
the trainer’ session to enable them to cover running risk 
awareness sessions at project kick‐offs to support a more risk 
focussed culture in the organisation. 
Page 108 of 142

Page 113

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Undertaking a ‘health check’ of project management 
arrangements across the council to ensure governance, 
management, reporting and risk management is 
appropriate to the scale of the project. 
November
2023 
Director of 
Finance and 
Resources 
Compliance review of all PMU supported projects complete. All 
projects demonstrated a satisfactory level of risk governance and 
management. 
An update to the risk management course on iLearn and 
consideration of whether it should be a mandatory course. 
December
2023 
Director of 
Finance and 
Resources 
The course if now developed and ready to be launched to 
relevant staff on iLearn. 
In addition, face to face training of a new “Who’s risk is it 
anyway” half day course is also being delivered in February and 
May. 
Embed and deliver risk management training into the new 
leadership development programme that is currently under 
development, particularly in relation to commercial risk 
December
2023 
Director of 
Finance and 
Resources 
Session delivered 12 December 2023, and is included in the 
training programme for further cohorts. 
Reviewing governance documents to ensure delegations in 
relation to liability caps are clear and unambiguous. 
December
2023 
Director of 
Finance and 
Resources 
Consultation with Head of Corporate Governance concluded that 
governance documents do not require amendment, but rather, 
more training would be required on what was expected within 
existing delegations. The training was delivered to CMT on 28 
November 2023. Governance refresher training sessions have 
been delivered to every department senior management team in 
January. 
Deliver a targeted risk management development day for 
Chief Officers:‐ 
 Project risk management (and risk simulation exercise) 
 Risk horizon scanning and sustainability (the Global Risk 
Report) 
December
2023 
Director of 
Finance and 
Resources 
The training session has been prepared and was delivered to CMT 
on 28 November 2023. 
Page 109 of 142

Page 114

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
 Liability caps and their implications   
It is recognised that Dargavel Village has a significant 
amount of housing development yet to be delivered (circa 
2000 housing units over a 10 year period) and therefore 
many of the associated risk that existed at the beginning of 
the development continue to exist today albeit there is live 
data to inform future projections from the first circa 2,300 
units that have been delivered. Manage ongoing education 
demand risk relating to Dargavel through: 
The Council therefore continues to face risk and uncertainty 
in relation to accurately projecting the scale and timing of 
future education demand which will continue to have 
inherent uncertainty and risk. In recognition of this the 
Council will continue to progress the following actions to 
manage and mitigate this risk:‐ 
Securing robust long term demand projections which 
provide both a core projection, potential upper scenario 
and a long term view of the potential scale and timing of 
short term peak demand to inform decisions on capacity 
provision. 
September 
2023 
Director of 
Children’s 
Services 
Further updates will be completed in this respect for updated 
datasets available from November registration data and recently 
released NRS Census data. 
As of July 2024, a full learning estate projection model is 
expected to be delivered by Edge Analytics in September 2024. 
This will directly inform this action.   
Identify now a range of flexible options that are and will 
remain available to in future years to deliver, if required 
additional capacity (both temporary capacity and 
permanent long term capacity) to ensure the Council can be 
reassured of being able to respond appropriately to the 
potential for upper end demand scenarios and or 
temporary demand peaks to emerge. 
January 
2024 
Based on data and a range of scenarios, flexible additional 
capacity options have been outlined and shared with relevant 
boards. 
Page 110 of 142

Page 115

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Establish process and arrangements to support and provide 
detailed monitoring and updates to projections for updates 
to actual data sets to facilitate a continual re‐assessment of 
longer term trend and likely requirements / decision point 
required in relation to deployment of potential additional 
interventions. 
January 
2024 
A schedule is in place with timelines for detailed monitoring and 
updates to projections and actual data. This will ensure continual 
re‐assessment of long term trends and likely requirements / 
decision points required. 
Work is due to commence in August 2024 to map out the next 
iteration of roll projection release for 2025 with Edge Analytics. 
This will inform what data sets are required and set a road map 
and responsibility matrix for who is accountable for obtaining and 
collating each data set or model input. This also requires input 
form the Head of Economy & Development to factor in the next 
iteration of the Housing Land Audit (HLA) to the projection model.  
 
Bowles Report Recommendation 7 
Whilst protecting the integrity of the planning process, the Council needs to ensure the appropriate involvement of members in such developments. 
Additional Council Motion 
Council agrees that in light of the Independent External Review of Dargavel that there is a requirement to convene a cross party body to discuss and review 
existing governance arrangements of Renfrewshire Council. 
Response Objectives 
Assess the extent to which major investment projects have provided sufficient engagement with elected members through both formal governance routes as 
well as through briefing sessions, engagement sessions, group presentations, site tours etc. Identify any adjustments or improvements required moving 
forward. 
Provide officer support to a cross party group to of elected members to agree the remit and progress a discussion and review of the Council’s formal 
governance arrangements in line with the motion approved. 
Carry out an assessment of the Audit Risk and Scrutiny Board against CIPFA’s published good practice guide for audit committees. 
Page 111 of 142

Page 116

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
Undertake a health check assessment on major capital 
programmes to provide reassurance in respect to extent to 
which elected member involvement has been appropriately 
secured through formal governance reporting as well as via 
other appropriate informal engagement routes 
October 
2023 
Chief 
Executive 
supported by 
CMT 
City Deal and Infrastructure Health Check report was submitted 
to CMT on 21 November 2023. Other programmes to be reported 
to CMT through regular scheduled portfolio update sessions. 
Support Council Leader and other nominated elected 
members to determine a review remit, progress the review 
and develop suitable recommendations. 
March 2024  Head of 
Corporate 
Governance 
The Cross Party Working Group has been established and met 
five times. A report was submitted to the Council Meeting on 29 
February 2024 setting out the findings of the review. 
Carry out an assessment of the Audit Risk and Scrutiny 
Board against CIPFA’s published good practice guide for 
audit committees and identify any recommendations for 
change in remit or operational arrangements. 
December
2023 
Director of 
Finance and 
Resources 
The self assessment is complete with recommendations for 
improved clarity of roles and remits agreed by the ARSB, with 
formal final approval agreed by Council in May 2024.  
 
Bowles Report Recommendation 8 
Public confidence 
These recent events and the matters described in this report will dent public confidence in the Council. The Council should work in an open and transparent 
manner in the resolution of these issues and particularly with the residents of Dargavel, who have legitimate concerns about the implications for their children 
during both their primary and secondary education. 
Response Objectives 
The key aim has been to provide straightforward messaging and up to date sitreps to ensure publics (and council representatives) have the most up‐to‐date 
position and the complexity of the issue is explained in a simple and honest way and that parental/carer concerns in respect to the school and educational 
environment are able to be appropriately discussed through structured engagement arrangements with the parent councils with appropriate agreed actions 
taken forward. 
The strategy has been designed to: 
− Improve the flow and regularity of information to parents and carers and the wider Dargavel community, so they are first to hear about decisions 
impacting their community. 
− Ensure parents and carers have access to all projection data available to the council. 
Page 112 of 142

Page 117

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
− Introduce direct communication channels with Dargavel residents, enabling all sections of the community to engage on matters that are important to 
them and making sure the latest information is accessible and easy to find. 
− Provide residents with a feedback loop to enable them to ask questions of the council in relation to the development and have questions answered 
quickly. 
− Include the community in formal planning and design of a new primary school and high school extension. 
It is recognised that effective communication and engagement is important to building a new relationship between the Council and the Dargavel community, 
but ultimately it will take the delivery of the solution and investment in long term engagement to reduce local anxiety and fully rebuild trust and confidence in 
the Council. 
Develop communication plan to drive tactical engagement, 
ensuring the Dargavel community and specifically parents 
and carers kept updated on progress and the decisions 
being made by Council Boards. 
November
2022 
Head of 
Marketing 
and Comms 
The strategy has directed media and stakeholder engagement in 
relation to council decisions pertaining to Dargavel, the initial 
announcement and short‐term mitigation arrangements, and the 
publication of the Independent external review by David Bowles. 
The specific activities delivered include: 
 Arranging and hosting two parent and carer meetings, 
attended by council officers and more than 220 parents or 
carers. 
 Attending several parent council meetings with all primary 
schools and PMHS to support direct engagement, discussion 
on key activities, immediate estate decisions in respect to 
deployment of modular classrooms and post occupancy 
adjustments at Dargavel Primary, sharing and discussion of 
revised projection data and modelling, key council decision 
points, independent review outcomes. 
 Attending several community meetings from community 
council, Community Liaison Group as well as supporting 
coordination and delivery of wider community representative 
Page 113 of 142

Page 118

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
round table session to maintain ongoing engagement, 
sharing of information and data sharing. 
 Updating parents and carers at Dargavel Primary on progress 
and all reports to Council Boards and decision making in 
relation to immediate solutions to address capacity issues at 
Dargavel/ 
 Updating Bishopton Community Council on progress above. 
 Responding to media enquiries, requests for interview and 
ensuring the media were proactively updated on progress. 
 Ensuring the wider area stakeholders were kept up to date 
on progress – this includes community representatives, wider 
Parent Council groups and local and national politicians. 
 Maintaining updated information on the council website 
 Delivered a creative partnership with Glasgow School of Art 
and Dargavel Primary School to support pupils design the 
interiors of the new modular classroom block. 
Deliver a revised comms and engagement strategy to 
coincide with the return to school period along with timing 
of key milestone points in relation to post independent 
review and moving towards confirmation of progress with 
BAE systems and moving more significantly into a delivery 
phase. This will ensure long term engagement process 
continues to build pro‐active and positive engagement to 
continue to re‐establish trust and confidence across the 
Dargavel community. 
August 
2023 
Head of 
Marketing 
and Comms 
The Dargavel communication and engagement strategy was 
reviewed following the publication of the Bowles Report. The 
strategy covers the development of long‐term solutions to 
increase primary and secondary capacity. The key aim has been 
to provide straightforward messaging and up to date sitreps to 
ensure publics (and council representatives) have the most up‐to‐ 
date position and the complexity of the issue is explained in a 
simple and honest way. We committed from the outset to ensure 
those members of the community directly impacted (and their 
representatives) are first to hear about the steps being taken to 
deliver a solution and the decision‐making process involved. The 
strategy has been designed to: 
 Improve the flow and regularity of information to parents 
and carers and the wider Dargavel community, so they are 
Page 114 of 142

Page 119

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
first to hear about decisions impacting their community. 
Ensure parents and carers have access to all projection data 
available to the council. 
 Introduce direct communication channels with Dargavel 
residents, enabling all sections of the community to engage 
on matters that are important to them and making sure the 
latest information is accessible and easy to find. 
 Provide residents with a feedback loop to enable them to ask 
questions of the council in relation to the development and 
have questions answered quickly. 
 Include the community in formal planning and design of a 
new primary school and high school extension. 
Activity delivered from October 2022 to present includes: 
 Planned and hosted 2 public meetings 
 Monthly updates to the council website 
 13 update letters issued to parents and carers at 
Dargavel Primary School and shared with community 
stakeholders. 
 3 proactive media updates and the handing of almost 50 
media enquiries to ensure the council’s right of reply ‐ 
including arrangements for broadcast interviews. 
 Ongoing Elected Member briefings and MP/MSP 
briefings to ensure all political representatives are kept 
up to date on matters relating to the Dargavel 
Community. 
 Following publication of the Review, individual meetings 
took place with four local community representatives 
who were interviewed for the Review to include next 
steps. Ongoing engagement continues with two 
Page 115 of 142

Page 120

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
Action  Target 
Completion 
Responsible 
Officer 
Update 
representatives to provide a sounding board for 
communication and engagement. 
 August 4, the council’s senior team attended a Round 
Table Meeting with Bishopton Community to discuss 
education provision and leisure and recreation provision. 
 From August, introduced a new opt‐in community 
newsletter, promoted locally to encourage resident sign 
up. 
 Established the Park Mains Liaison Group, attended by 
the Parent Council Chairs of all Park Mains catchment 
primary schools, to ensure we can collectively plan the 
high school extension and effectively engage with the 
wider school. 
 Space Planning Activity for Dargavel Primary School 
 Preparation of communications plan to encourage 
community engagement (those directly impacted and 
those affected) with the forthcoming statutory 
consultation, to be launched in January. 
Establish a new parent council liaison group to provide a 
single PC forum (at the request of PC chairs) to provide a 
streamlined opportunity for consistent engagement and 
communication with the whole PC community for all 
schools associated with Dargavel / Bishopton and PMHS and 
all feeder primaries. 
August 
2023 
Head of 
Education 
Group has been established and has met following school 
summer 2023 break with positive feedback from Parent Council 
Chairs with engagement to date. 
Establish regular opt‐in digital community newsletter to 
facilitate regular communication updates direct to 
interested members of the community. 
August 
2023 
Head of 
Marketing 
and Comms 
Take up of opt‐in digital channel newsletter is currently sitting at 
over 500 and it is expected that this will continue to grow in the 
coming months. 
Page 116 of 142

Page 121

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
CROSS PARTY WORKING GROUP AGREED ACTIONS
Refresher training for management teams across all of the 
Council’s  directorates  on  the  operation  of  delegated 
authority should be implemented. 
April 2024  Head of 
Corporate 
Governance 
and 
Chief Auditor 
Training was delivered to all directorates by the Head of 
Corporate Governance and the Council’s Chief Auditor in 
January 2024 to Chief Officers and tier 3 managers. A further 
“catch up” session was held on 23 April 2024. 
Refresher training for management teams across all of the   
Council’s directorates on the operation of the Protocol for   
Relationships between Political Groups, Elected Members   
and Officers should be implemented.   
That the Bulletin be issued with the minutes of each Council 
and board meeting for the meetings of Full Council. 
May 2024  Head of 
Corporate 
Governance 
The Bulletin is now issued with the minutes pack at each Full 
Council Meeting commencing with the meeting of 9 May 2024. 
All major projects and programmes will report to the 
appropriate board at least twice a year. 
Any such reports will include a note of all project groups 
involved. 
May 2024  Chief 
Executive 
Update reports on City Deal Projects and cultural Infrastructure 
programmes have gone to boards in December and February 
respectively as part of twice yearly reporting cycles. Housing 
investment programme update provided as part of update 
report at each cycle with an additional full update provided in 
august of each year. 
The content of the Protocol for Relationships between 
Political Groups, Elected Members and Officers be refreshed. 
February 
2024 
Head of 
Corporate 
Governance 
The Revised Protocol was approved at the Council Meeting of 29 
February 2024 
A health check of all major projects will be completed and 
reported through the Audit, Risk and Scrutiny Board 
March 2024  Chief 
Executive 
This has separately been reported to the ARS Board as part of the 
independent review action plan 
A  structure  chart  for  all  Council  directorates  should  be 
prepared and circulated to all Elected Members. This should 
be regularly updated and recirculated as necessary. 
March 2024  Chief 
Executive 
The structure chart was circulated to all Elected Members, and 
the first updated version was issued in March 
Page 117 of 142

Page 122

APPENDIX 2 
Action Plan Response Monitoring (Completed Items) – August 2024 
That a Chief Planning Officer report brought to the Planning 
and Climate Change Policy Board at least twice a year advising 
on the position in respect of s75 Agreements. Planning 
applications, or where officers cannot not reach agreement on 
substantive matters in a specific s75 Agreement negotiation 
will also be brought back to the Board for further 
consideration. 
May 2024  Head of 
Economy and 
Development 
Arrangements have been put in place by officers for this bi‐ 
annual reporting 
 
Page 118 of 142

Page 123

Renfrewshire
Council
Statutory follow-up report 
Page 119 of 142

Page 124

Contents | 2   
Contents 
1. Introduction 3 
2. Update on progress                                                                    4 
3. Conclusions                                                                                10 
Page 120 of 142

Page 125

Introduction | 3   
Introduction 
Background
1.  In June 2023 Renfrewshire Council received the findings of an independent
report (the Bowles report) that highlighted significant historic failings of
leadership, oversight and risk management in relation to the provision of school
accommodation for Dargavel Village. The council accepted the findings in full
and apologised to the local community for the errors made. In January 2024, I
reported to the Accounts Commission on the actions taken by the council to
respond to the issues identified in the Bowles report. 
2.  The Commission asked me to report back by June 2024 on progress with the
issues raised in the Commission’s findings. Following the announcement of the
UK general election on 4 July 2024, reporting was delayed to August 2024 due
to restrictions on the publication of reports during the pre-election period.
Specifically, the Commission asked that I seek further information and updates
from the council on the following:
• the council’s review of its approach to community engagement
• its approach to consultation on the additional primary school at
Dargavel, and other decisions on the school estate
• the council’s work on understanding the wider service impacts on the
failings regarding school capacity
• the council’s reviews of scrutiny and risk management, and its
leadership development programme
• the process followed and factors taken into account by the council in
considering disciplinary action against senior staff, and its approach and
policy on performance management and accountability. 
3.  The council’s appointed auditor has carried out additional work to gather
information and assess progress to date in relation to the five areas of interest
identified by the Commission.
4.  I submit this follow-up report under section 102(1) of the Local Government
(Scotland) Act 1973 as a matter that the Controller of Audit considers should be
brought to the attention of the Accounts Commission for Scotland.
5.  The auditor will provide a further update on progress with some of these
issues in the annual audit report, due to be published in September 2024, and
the Best Value report, which has been brought forward from 2027 to December
2024.
Page 121 of 142

Page 126

Update on progress | 4   
Update on progress 
Community engagement
6.  In my previous report I reported that the council recognises the significant
challenges it faces to rebuild the trust and confidence of local communities. In
its findings, the Commission asked me to undertake further audit work to enable
me to update the Commission on recent actions taken by the council to improve
its consultation and engagement with communities over its planned new primary
school at Dargavel and planned extension at Park Mains High School. I was
also asked to update the Commission on the council’s progress in reviewing the
effectiveness of its strategy and approach to community engagement. I cover
each of these areas separately. 
School-based community engagement and consultation
7.  The auditor has carried out a high-level review of community engagement
activity undertaken by the council with Dargavel and Park Mains High School 
communities since publication of the Bowles report. The auditor has concluded
that the council has taken steps to increase its engagement activity with local
communities. 
8.  From the end of January to the end of March 2024, the council carried out a
statutory consultation on the proposal to build a new primary school in Dargavel
village and a review of the catchment areas for both the new and existing
primary schools. Activity as part of this consultation included two public
meetings, four information sessions, drop-in sessions and opportunities to
provide online and written feedback. The council wrote to statutory consultees
and others in the local community to publicise the consultation. Information on
the consultation and how people could get involved was also available on a
dedicated page on the council website. The auditor has confirmed that the
council’s consultation on the new Dargavel primary school meets the
requirements of the Schools (Consultation) (Scotland) Act 2010.
9.  There is no statutory requirement for the council to consult on any proposal
to extend an existing school. There has therefore been no statutory consultation
on the proposal to extend Park Mains High School. The council has, however,
been carrying out a programme of community engagement on the extension.
This is principally through the Park Mains Liaison Group and community
newsletters. The council reports that it has developed a plan for the next phase
of engagement on the extension to Park Mains High School and the new
Dargavel primary, from July to September 2024. 
10.  The final report from the statutory consultation was discussed at the
Education and Children’s Services Policy Board in May 2024. The consultation
Page 122 of 142

Page 127

Update on progress | 5   
was about delivery of a new non-denominational primary school within Dargavel
Village for 800 pupils and revised catchment arrangements between Dargavel
primary school and the new school. The majority of responses to the
consultation agreed with the need for a new school but views were split on the
proposed site (40 per cent agreed and 41 per cent disagreed). There was also
no consensus on the proposed catchment area (44 per cent agreed, 12 per cent
disagreed and 44 percent did not express a preference). The main concern
raised by respondents to the consultation was about the increase in traffic and
the availability of safe active travel routes to school. Although it was outwith the
scope of the consultation, a third of respondents also raised the option of a new
high school or a joint primary and secondary campus. This option was not
presented in the consultation because the council had agreed in May 2023 to
extend Park Mains High School, which is the existing non-denominational
secondary school for the Dargavel and Bishopton catchment, to provide
additional capacity. 
11.  The board also considered an Education Scotland report prepared as part
of the consultation process. This report concludes that the council’s proposal
has the potential to provide educational benefits. It also highlights the significant
concerns raised by stakeholders, both through consultation responses and
conversations with HM inspectors. It recommends that the council should:
• develop robust plans to manage the expected increase in traffic and
ensure that there are improved and safe active travel routes to school
• develop contingency plans to address any potential slippage in
timescales for construction of the new school
• continue to work with stakeholders to mitigate their concerns and
involve them, as appropriate, in the development of the new school.
12.  In response to concerns raised during pre-engagement activity about traffic
at the new school site, the council commissioned an independent transport and
travel study in January 2024. This concluded that the planned road
infrastructure will accommodate the additional traffic. It also made some
recommendations to maximise active travel. The council is currently engaging
with BAE Systems about planning access and travel routes as part of the
design of the school site.
13.  The council recognises that there is still work to do to repair its relationship
with the Dargavel community and reports that it has developed plans for
ongoing community engagement during the design and planning of the new
school. 
14.  The auditor will continue to monitor how the council acts on the findings
from the consultation and the Education Scotland report. 
The council’s review of its approach to consultation and engagement
15.  The council commissioned an external consultant to:
Page 123 of 142

Page 128

Update on progress | 6   
• provide support and guidance on best practice to support its statutory
consultation activity in relation to the new primary school. This was to
include support for staff delivering the consultation, advice on the
effective running of public events, support for the senior team and a
review mid-way through the consultation to advise on any
improvements that could be made.
• carry out a review of the effectiveness of the wider engagement
strategy, including the statutory consultation and engagement on plans
to expand Park Mains High School. This included a community opinion
survey, carrying out meetings with stakeholders to discuss their
engagement with the council and a review of exit surveys and
transcriptions from the statutory consultation. This review was
completed in June and a report will be taken to the council’s Audit, Risk
and Scrutiny Board in August 2024.
16.  The consultant’s report considered how the council carried out the Dargavel
consultation, but did not look at the issues raised or how the council has
responded. It identified considerable good practice in the consultation process,
concluding that it effectively allowed citizens to voice their preferences. It also
concluded that the council’s engagement and communication plan was
comprehensive. The consultant made a series of recommendations, some of
which are specific to the Dargavel consultation and some which are broader
and apply to the council’s future consultation activity. 
17.  The scope and methodology of the work the council commissioned from the
external consultant was appropriate and the findings provide assurance that the
council’s approach to the Dargavel consultation was robust. It is too early,
however, to comment on how the council has responded to the consultant’s
recommendations. 
18.  The council reports that it has now also secured external support to help
deliver a new corporate engagement policy and toolkit and establish an
engagement oversight group. It is important that the council continues to work
to rebuild trust among the Dargavel and Bishopton communities, by acting
quickly to implement any recommendations arising from the conclusion of its
review. It should also consider how the lessons learned can be applied to its
corporate approach to consultation and engagement. The auditor will continue
to monitor progress and developments in this area.
19.  I am satisfied that the council’s approach to its recent consultation and
community engagement activity has been appropriate and comprehensive. The
council is responding appropriately to the issues raised through the consultation
process in its decision making.
Wider impacts on service provision
20.  As I noted in my previous report, the council has implemented interim
arrangements to address primary school capacity issues and monitors the
quality of educational delivery and measures of pupil attainment through its
existing quality monitoring arrangements. The Commission emphasised in
Page 124 of 142

Page 129

Update on progress | 7   
January the importance of openness and transparency in the council’s
consideration of options and decision-making in relation to the school estate.
The council continues to report issues and decision-making on the school
estate and education provision through the Education and Children’s Services
Policy Board.
21.  The Commission also raised concerns about the potential impacts on other
services as a result of the errors in the estimation of pupil numbers in Dargavel.
The council has established a Dargavel working group, made up of council
senior management, to manage operational issues related to the new primary
school and extension of Park Mains High School. Any wider service impacts
identified through the work of this group would be considered as part of the
council’s regular business planning, financial planning and annual budget
processes. 
22.  The council has not identified any significant impact on local service
provision as many other local services are not impacted by the size of the
school roll. Of the 4,300 new houses planned in the Dargavel area, 2,400 have
been built and the rest will be built in batches over the next 10 years, so the
council is confident that it will be able to adapt to any service impacts as they
arise through its wider corporate planning processes. 
23.  The auditor is satisfied that the council has appropriate arrangements in
place for considering the potential wider impact of its planning failure linked to
school accommodation for Dargavel Village on non-education services. The
auditor has also found no evidence of any negative impacts on wider council
services being demonstrated through the council’s routine performance
management processes. 
Governance and scrutiny 
24.  The Bowles report, while restricted to the historical handling of the Dargavel
development, raised a concern in relation to the council’s governance
arrangements. In my earlier report I highlighted that, while auditors concluded
that overall the council has appropriate governance arrangements in place, the
role of the Audit, Risk and Scrutiny Board (ARSB) in ensuring effective scrutiny
is not sufficiently clear. The council committed to review its governance and
scrutiny arrangements as part of a wider review of corporate governance.
25.  The council has taken steps to review its governance and scrutiny
arrangements, including:
• a self-assessment against CIPFA guidance for local authority audit
committees
• an exercise benchmarking the council’s governance arrangements
against other councils
• a cross-party working group review of governance arrangements
• a review of the council’s risk management arrangements. 
Page 125 of 142

Page 130

Update on progress | 8   
26.  At its meeting in May 2024, the council considered the results of the ARSB’s
self-assessment against CIPFA good practice on audit committees. The self-
assessment identified a number of areas of good practice and 11 action points,
including proposed changes to the governance of the ARSB. The council
approved the results of this review, the action plan and a number of changes to
the way the ARSB operates in relation to its terms of reference, guidance and
role descriptions. All the action points were implemented by the end of June.
The cross-party review of governance also identified a number of actions,
including a review of the council’s Scheme of Delegation. An action plan was
developed compiling actions from the reviews, with progress against actions
monitored by the ARSB. All but one of the actions have now been delivered,
with the final action to be completed by December 2024.
27.  All actions in response to the Bowles report in relation to risk management
have been completed, as reported to the ARSB in March 2024. The auditor will
continue to monitor progress in improving governance and scrutiny
arrangements and report further as part of their annual audit and Best Value
work.
28.  The council has developed a leadership programme in conjunction with
SOLACE. The programme covers areas including risk management, good
governance and engaging with the public. The council initially plans to run the
programme in three cohorts. The first cohort, consisting of the extended
Corporate Management Team has completed the programme and the second
cohort began in April 2024. The programme is ongoing so it is too early to reach
a conclusion on its effectiveness. SOLACE has collated feedback from the first
cohort and the council has used this to update the programme for subsequent
cohorts. The auditor has concluded that the scope and timing of the programme
is appropriate and will provide a further update in the Best Value report. 
Performance and accountability
29.   The Bowles report concluded that there had been historic failures of
leadership and corporate oversight of decisions relating to the Dargavel
development. This meant that decision-making was not sufficiently scrutinised
or challenged by senior management. Bowles also concluded that junior staff in
the Education and Children’s Services department were asked to make
assessments on pupil demand that were beyond their expertise and experience,
with no appropriate support or supervision. This led to the errors in school
capacity planning going unidentified. As part of the independent investigation,
David Bowles provided the Chief Executive with a supplementary report
considering his views on the accountability of the individuals involved in
decision-making in relation to Dargavel. He found that the key individuals had
either left the Council or were too junior to merit formal disciplinary action. 
30.  In my previous report I noted that the auditor concluded that the council
obtained appropriate external legal advice and determined there is no potential
for any form of action against former senior employees involved in the Dargavel
School decision-making. The auditor has carried out further work to look at the
processes followed by the council in deciding not to take disciplinary action
Page 126 of 142

Page 131

Update on progress | 9   
against any of the staff involved. The auditor has also reviewed the council’s
policies and procedures on performance management.
31.  The council considered whether disciplinary or other action could be taken
against individual council officers. The auditor has concluded that the council
took the appropriate action, based on the powers available to it, but that action
was limited due to officers involved having left the council.
32.  In his supplementary report, David Bowles suggested that the council carry
out an independent review into the handling of specific planning applications
related to Dargavel. The council reports that it had been undertaking its own
review of Dargavel planning alongside the work of David Bowles and
information from this work had led the council to conclude that the planning
process had been followed appropriately. On receipt of the supplementary
report, the Chief Executive asked the Head of Corporate Governance to confirm
that the concerns identified by Bowles were not supported by evidence. The
council has shared details of this work with auditors but has not been able to
provide a contemporaneous written record of the scope or findings of its
additional work. In the interests of transparency and good governance, I would
have expected officers to have kept a written record of decision-making on such
a serious matter.
33.  The auditor has concluded that, overall, the council has appropriate and
comprehensive performance management policies and disciplinary procedures
in place. Greater clarity is needed, however, on how the council’s disciplinary
procedure applies if an officer goes on sick leave during a disciplinary
investigation and occupational health determines the individual is not fit to be
investigated. The council is currently in discussions with trade unions regarding
a revised disciplinary policy, including changes to address this issue. The
council will need to secure agreement from all the trade unions to revise the
policy. 
34.  In light of the Bowles report’s findings about historic failures of management
oversight and organisational culture, the council has carried out town hall
events and other activity across all council departments to promote
understanding of and compliance with performance management policies.
Page 127 of 142

Page 132

Conclusions | 10   
Conclusions 
35.  The council continues to demonstrate that it is taking action to respond to
the issues highlighted in the Bowles report. The auditor has carried out further
work to look at council actions and progress in the five particular areas of
concern identified by the Commission and I am satisfied that the actions being
taken by the council are timely and appropriate.
36.  The council carried out its consultation on the proposed new primary school
in line with statutory requirements and the independent consultant found that
the process was robust. The consultation found significant support for a new
school, however, there is no clear consensus on the proposed site and some
respondents continued to highlight high school provision as a pressing issue
although that was outwith the consultation scope. The council has recognised
that there is still work to do and reports it has developed plans for ongoing
community engagement on the design and planning of the new school. The
auditor will continue to monitor progress and developments in this area. 
37.  The council has now concluded its review of risk management and has
largely completed the actions arising from its review of governance
arrangements. It has also completed its review of its Dargavel consultation and
community engagement activity. The council has made progress in its response
to the issues raised in the Bowles report, but it is too early to conclude on the
impact and effectiveness of some of the actions taken by the council. The
auditor will continue to monitor the impact of changes to governance and
scrutiny arrangements, the leadership programme, and the council’s response
to the review of its community engagement activity. There continues to be
significant public interest in the council’s response to the Bowles report. It is
critical that the council is as transparent as possible about how it reaches key
decisions and that appropriate records are kept. The auditor will provide further
updates through the annual audit and Best Value reports. 
Page 128 of 142

Page 133

Conclusions | 11    
Renfrewshire Council
Statutory follow-up report 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh  EH3 9DN
Phone: 0131 625 1500  Email: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk
AS.4.0 
Page 129 of 142

Page 134

Page 130 of 142

Page 135

___________________________________________________________________
To: Audit, Risk and Scrutiny Board 
On: 19 August 2024
___________________________________________________________________
Report by:  Director of Finance and Resources
___________________________________________________________________
Heading:  Summary of recent Audit Scotland Publications
___________________________________________________________________
1. Summary 
1.1 Audit Scotland regularly publish national reports on matters relating to local
government in Scotland.  This report provides an overview on a recent blog
post from the Chair of the Accounts Commission and on two newly published,
which officers have summarised for Board members. 
1.2 The report on local government budgets summarises some of the challenges
facing all local authorities in Scotland and is covered in Section 3.  Audit
Scotland have collated information to show the scale of budget gaps across
the sector, and to show how the gaps are being addressed. 
1.3 Section 4 gives an overview on the report on leadership is the first Best Value
thematic report to be published since Audit Scotland adopted a new approach
to Best Value in 2022.  It draws out some commonalities arising from the
focus on effective leadership in setting strategic priorities. 
1.4 Section 5 of the report summarises a blog post was written by the Chair of the
Accounts Commission highlighting the importance of the role of Chief
Financial Officer in councils.  It notes that these officers must have a
leadership role that transcends the finance function, in order that all decisions
are based on sound financial management.  It also notes the importance of
having sufficient capacity within finance teams to enable the level of
information and support that is needed for good decision-making.
Item 5
Page 131 of 142

Page 136

2. Recommendations 
2.1 It is recommended that members of the Audit, Risk and Scrutiny Board: 
• Note the content of this report. 
3. Audit Scotland briefing on Local Government Budgets 2024/25 
3.1 In May 2024, Audit Scotland produced a briefing summarising the key issues
it identified after analysing the 2024/25 budgets for each of Scotland’s 32 local
authorities.  The briefing considers how Scottish councils are addressing the
ongoing budget challenges and ensuring long-term financial sustainability. 
3.2 The report notes that, although there was a real terms rise in the revenue
settlement to local government in Scotland, much of the increase is funding
which was previously ring-fenced but has transferred to the general revenue
grant in line with the Verity House Agreement.  The report also notes that the
increase is largely to support pay awards, and to deliver Scottish Government
priorities including the funding to support a Council Tax freeze.  Audit
Scotland considers that freezing Council Tax added complexity to budget
setting by removing the main lever for income generation. 
3.3 The cumulative budget gap for Scottish councils in 2024/25 is noted as being
around £585 million, ranging from £3.1m in Glasgow to £65.6m in Highland.  It
notes that Glasgow City Council are taking a multi-year approach to their
budget gap and so the figure is an outlier and not truly reflective of the actual
position; the multi-year plan identifies £34.7m of savings due to be delivered
in 2024/25. 
3.4 The figure below shows the reported budget gap for each local authority,
excluding any expected savings for 2024/25.  Renfrewshire Council’s figure
equates to the revised budget deficit of £4.3m, as reported to Council in May
2024, less mitigating savings of £8.8m. 
3.5 Audit Scotland have also compiled information on how councils are
addressing these budget gaps, and found that, as in Renfrewshire Council,
the use of reserves and the agreement of recurring savings are making the
biggest contribution.  These are expected to generate £159m and £168m
respectively across all Scottish councils.  Non-recurring savings are expected
to generate a further £45m.  The report notes that the use of reserves and
non-recurring measures is not sustainable.  The report also notes the
Page 132 of 142

Page 137

challenges some councils have faced in regard to public opposition to
proposed savings measures. 
3.6 Most councils have indicated the amount they expect to raise from fees and
charges in 2024/25, which amounts to £1.3bn. This includes new charges for
garden waste, bulk uplifts, harbour fees and low emission zones. 
Page 133 of 142

Page 138

3.7 Information on the expected budget gap for the next two years was available
for 30 councils, and Audit Scotland have calculated this to be £393m in
2025/26 and £387m in 2026/27.  Although Glasgow City has the highest
cumulative gap in monetary terms, Shetland and Clackmannanshire have the
largest gap as a proportion of their revenue budget, at 22% and 12%
respectively. Renfrewshire Council’s budget gap for the three years is
£25.29m, which equates to 4.6% of the revenue budget.  This figure, for
planning purposes, assumes Council Tax increases of 6% in 2025/26 and 5%
in 2026/27, and that £8m savings will be delivered in each of these years. 
The outlook will be updated and reported to Council in September 2024. 
3.8 The report highlights an overall rise in capital budgets but with considerable
variation; 18 councils increased the capital budget and 13 reduced it.  The
proportion of capital spend funded by borrowing grew from 53% to 64% and
the proportion funded by the Scottish Government fell from 27% to 20% in
one year.  The allocation of capital funding from the Scottish Government
decreased by 23.6% in real terms from 2023/24. 
3.9 Audit Scotland, in the report, draw attention to the importance of consulting
with residents as part of the budget setting, and note that 24 councils
(including Renfrewshire) did undertake some form of consultation on financial
pressures.  The importance of carrying out equality impact assessments on
budget proposals is also noted, to support compliance with the general
equality duty. 
3.10 In terms of identifying issues with the budget process, the timing of the
Council Tax freeze is highlighted as having limited the time available to adapt
budget plans and proposals.  The timing of the publication of the Scottish
Government Financial Circular also created a challenge for some councils as
it was released on 29 February, after many budget meetings had already
taken place. 
4. Audit Scotland:  Delivering for the Future – why leadership matters 
4.1 As part of the new approach to Best Value Audit, Audit Scotland are carrying
out a thematic audit of all 32 councils each year.  The first such thematic
report was published in July 2024 and focuses on leadership.  Specifically,
auditors were asked, as part of their annual work, to consider the
effectiveness of leadership in the development of the council’s strategic
priorities.  This took place in the second half of 2022.  The findings were
included in each Council’s Annual Audit reports, and this new summary report
highlights some areas of commonality.  In Renfrewshire, findings were
reported to the Audit, Risk and Scrutiny Board in November 2023 as part of
Page 134 of 142

Page 139

the wider Best Value reporting.   Given the time that has elapsed between the
audit work and the publication of the report, the position in many councils may
have changed. 
4.2 The report finds that all councils have a clear vision, with most revising their
Council Plans after the 2022 election. All councils also have clear plans for
tackling poverty and inequalities, and reflect environmental sustainability in
their priorities.  There was evidence that all councils had included the views of
citizens and communities when setting priorities. 
4.3 Performance management was in need of further development in around one-
third of councils.  In Renfrewshire Council, we have long-standing
arrangements for regular reporting to elected members and citizens through
our Council Plan, Service Improvement Plans, annual Public Performance
report and many other operational and strategic reports considered at Boards. 
4.4 The report notes that aligning financial strategies to priorities is important, as
is aligning resources, which includes the workforce.   The way in which
councils direct and develop their workforce will be the focus for the second
thematic review report, and work is underway on this at present. 
4.5 Audit Scotland stress the importance of collaborative leadership and effective
working between officers and members.  The significant turnover in senior
officers across councils is noted, as are the challenges and risks that can
bring.  Auditors reflected the work of many councils to support new elected
members in 2022 and restate the importance of elected members making use
of opportunities provided for training and development. 
4.6 Most councils had cited community empowerment as a priority, and auditors
highlight the need for engagement to be meaningful, and to understand the
reasons for low take-up of engagement opportunities.  They also note that
allocating 1% of revenue budgets to participatory budgeting is aspirational for
many councils, though there is good work being done to include citizens in the
budget-setting process. 
4.7 The report identifies common improvement actions which apply to multiple
councils:
• Clarifying outcome measures and targets for council priorities;
• Improving arrangements for monitoring and reporting on progress to
elected members;
• Making performance reporting more accessible to the public;
• Ensuring workforce, assets, digital, capital and service plans are
aligned to corporate priorities;
Page 135 of 142

Page 140

• More encouragement and support for citizens to engage meaningfully;
• Ensuring equality impact assessments are undertaken at an early
stage to inform strategy and decision making, and that these
assessments are published;
• Building on Net Zero plans, with more detail on project costs and
budgets;
• Demonstrating how budget decisions and financial plans align to
priorities;
• Reviewing the affordability of proposed capital plans and their revenue
implications. 
4.8 The publication of the report was accompanied by a blog from a member of
the Accounts Commission.  This re-iterated the findings that local government
had a clear vision with priorities that are shaped by the views of the
communities served.  However, it also notes that “financial pressures and
increasing demand mean continuing as we are is not sustainable, and
therefore not an option.”  It highlights the criticality of effective collaboration
between officers and elected members, and of workforce planning to ensure
the capacity and capability of the local government workforce into the future. 
For this reason, workforce innovation is the focus of the current thematic
review. 
4.9 The report on Renfrewshire Council concluded “We are satisfied that the
Council has appropriate arrangements in place to demonstrate Best Value
under each reported area of the 2022/23 thematic review.” The table below
provides information on practice within Renfrewshire Council in relation to
each of the national leadership themes. 
National leadership
theme 
Renfrewshire Council Practice
Clarifying outcome
measures and targets
around Council priorities
Following work with the Corporate Management
Team from February 2024 onwards, and as reflected
as minor action in our own local audit report last year,
a refreshed Council Plan was approved by
Leadership Board in June 2024, with significantly
reduced and refined priorities, actions and indicators.
The refreshed Council Plan, clarifies Council
priorities, particularly reflecting the current context
locally and for local government more broadly.
Page 136 of 142

Page 141

A new overview dashboard of progress towards the
Strategic Outcomes was also included in the 6-month
performance update, also approved by the June
2024 Leadership Board. 
Renfrewshire’s Community Plan priorities were also
refreshed last year, providing some assurance that
the organisation continues to focus on the right
areas, while recognising these need to remain
flexible and agile. 
Monitoring and reporting
progress to elected
members
Renfrewshire Council’s clear performance framework
was positively highlighted by the thematic audit work
– the organisation has a well established and robust
calendar of progress reporting to Elected Members,
including 6 monthly updates on Council Plan
progress, Service Improvement Plan progress and
also operational performance as appropriate to the
service area. 
Accessibility of
performance reporting
Renfrewshire Council has used Storymaps with
embedded PowerBI functionality to present the
annual performance reporting, underpinned by the
Local Government Benchmarking Framework data,
showing a mix of interesting case studies, images
and videos, alongside the ability to drill down into the
local, family group and national data. Given this is
now established practice, we will commit to testing
this with citizens over the coming year, to ensure it
covers the areas of most interest to our communities
and is inclusive and accessible. 
Since 2022, and aligned to the Council Plan
approach, 6-montly performance reporting on the
Council Plan and on SIPs has used a much more
attractive and accessible format, with a mixture of
case studies and infographics alongside the full suite
of actions and performance indicators. 
As noted above, a new overview dashboard of
progress towards the Council Plan Strategic
Outcomes has also been developed to a give a ’one
glance’ picture of overall progress.
Page 137 of 142

Page 142

Alignment of key plans to
corporate priorities 
The thematic audit work highlighted the alignment of
Renfrewshire Council’s key plans to the Council Plan.
There is a clear golden thread between the Service
Improvement Plans as a delivery element of the
Council Plan alongside the financial planning, to
deliver the key priorities. Following the refresh of the
Council Plan noted above, further work (including the
development of a plan on a page approach) is being
planned to raise awareness, and mainstream cross-
service understanding, of the corporate priorities and
to ensure continued close alignment of future plans
and strategies. We will also seek to continue to
strengthen the ‘golden thread’ approach, particularly
in relation to our people and workforce planning. 
Citizen engagement There are a range of good practice examples across
Council services demonstrating the Council’s
commitment to effective citizen engagement, which
was highlighted in the thematic audit work. 
As well as the overall commitment through the Fairer
Renfrewshire and the Connecting Communities
programmes, some service specific examples
including You Decide, Celebrating Renfrewshire,
Local Partnerships, the work of the Lived Experience
Panel, Local Development Plan and Housing
Regeneration engagement and Ren Zero
engagement including the citizens’ panel. 
As part of our self-evaluation activities and also the
lessons learned from Renfrewshire’s Section 102
Audit, we have reflected on our practice and
recognised the need to continue to develop and
strengthen our approach. Extensive work is currently
underway to develop a Council-wide Consultation
and Engagement strategy, building on best practice
to create an accessible, contemporary source of
advice and best practice for all Council areas that
plan and run these types of exercises.
Equality impact
considerations
The Council has a range of processes and resources
in place to support officers and Elected Members to
consider equality impacts as part of planning and
subsequent decision-making processes.  This
Page 138 of 142

Page 143

includes a toolkit and training for staff and Elected
Members. 
There are a number of more recent developments
including the UNCRC, alongside our corporate self-
assessment undertaken which identified a need to
continue to build and develop our approaches,
recognising factors such as turnover in staff, for
example, may mean there is a need for more training
and development in this area. 
Work is therefore currently underway to strengthen
the Council’s approach to equality considerations,
with recent training to the Corporate Management
Team and a ‘rapid review’ of current practice being
undertaken across each service area. A
strengthened approach is also being progressed,
working alongside the Director of Finance and the
wider CMT,  to integrate equality assessments more
robustly within the Financial Sustainability and
Transformation programme and this will link with the
enhanced governance arrangements (see below). 
A dedicated resource is also being recruited to
support the strengthened approach to equalities
within the organisation. 
Building on Net Zero plans The thematic audit work highlighted the Council’s
clear commitment to tackling the climate crisis and
the development of Renfrewshire’s Plan for Net Zero,
which represented phase 1 of our approach. Phase 2
builds on those plans, with a costed delivery plan and
route map to net zero. Both elements of this work
were underpinned by community engagement
through surveys, workshops and Renfrewshire’s
Climate Panel. 
Aligning budget decisions
and financial planning to
Council priorities
The thematic audit highlighted the well-established
financial sustainability and transformation
programmes, which are cross-cutting and aligned to
Council priorities. 
This work is ongoing and extensive, with a recent
enhancing of the governance support for this area -
one Corporate Management Team meeting per
Page 139 of 142

Page 144

month has now been dedicated to the Financial
Sustainability and Transformation Board. 
As noted above, financial planning aligns to the
organisation’s overall strategic direction (as set by
the refreshed Council Plan), and the delivery of these
priorities, as detailed and monitored through the
Service Improvement Plan process.
Reviewing affordability of
capital plans and revenue
implications 
The affordability of capital plans is reflected in the
‘ratio of financing costs to net revenue stream’, which
was reported at 31 March 2024 as 3.1%. This means
that 3.1% of the 2023/24 General Services revenue
budget was used to pay loan charges for existing
borrowing related to capital projects. 
At capital planning stage, there is careful
consideration of the impact on the revenue budget of
potential borrowing costs or proposed capital spend,
and these revenue implications are reported to
Council where they arise. The Medium-term Financial
Outlook also takes account of any future borrowing
requirements, and their impact on the revenue
budget. 
4.9 In Renfrewshire Council, we have recently refreshed and streamlined our
Council Plan priorities.  As our overarching plan, the themes identified therein
are reflected in other strategic documents, to make it clear the actions we are
taking to deliver on our priorities, and the measures we will use to determine
success.  As noted above, our approach to performance has been to provide
regular updates to elected members and this is done chiefly, but not solely,
through six monthly progress updates on delivery of Service Improvement
Plans.  Senior management teams in services and the Corporate
Management Team also consider performance regularly. 
5. Audit Scotland view on the role of the Chief Financial Officer 
5.1 On 16 July, the Chair of the Accounts Commission published a blog on the
criticality of the role of Chief Financial Officer (CFO) in local authorities.  The
CFO is a statutory role set out in the Local Government (Scotland) Act 1973 –
also referred to as section 95.  The blog post notes that the CFO role requires
the postholder to not only lead the finance function but to have a prominent
Page 140 of 142

Page 145

leadership role across the organisation, in light of the growing complexity of
public services and the ongoing financial challenges.  The author states: 
“As the challenges across the public sector intensify, the role of CFOs
is increasingly in the spotlight. As CIPFA highlight, with existing
frameworks on governance and decision-making being pushed to their
limits, with public services becoming more complex, the CFO is
expected to take an active leadership role, not just within the finance
function, but across their organisation, sector and public services as a
whole.” 
5.2 The Chair notes that corporate functions have been subject to budget
reductions in recent years in order to protect frontline services but is clear that
the CFO must be supported by a finance function that is suitable resourced. 
There is a clear direction to auditors that they should consider the capacity
and skills of the CFO and finance teams during the annual audit process,
given the need to provide timely and accurate financial information to inform
and support decision-making. 
__________________________________________________________________ 
Implications of the Report 
1. Financial – none arising from the report, but Audit Scotland publications note
the financial challenges facing local government in Scotland. 
2. HR & Organisational Development – none arising from the report but
section 5 notes the importance of workforce planning. 
3. Community/Council Planning – none arising from the report, though Section
5 notes the importance of aligning activity with Council and Community Plan
strategic priorities. 
4. Legal - none 
5. Property/Assets – none 
6. Information Technology - none 
7. Equality & Human Rights – none arising from the report, though it notes that
requirement for equality impact assessments to inform budget decisions. 
8. Health & Safety – none 
9. Procurement – none
Page 141 of 142

Page 146

10. Risk – none arising, though the publications referred to highlight the
challenges and risks in relation to budget gaps and financial sustainability. 
11. Privacy Impact – none 
12. COSLA Policy Position – none 
13. Climate Risk-  none arising from this report, though Audit Scotland in the
leadership report welcome the inclusion of environmental sustainability by all
councils in their strategic priorities. 
14.  Children’s Rights: none
_______________________________________________________
List of Background Papers: 
Audit Scotland report:  Local Government Budgets 2024/25
Audit Scotland report: Delivering for the future – why leadership matters
Audit Scotland: The important role of the CFO