Summary of Internal Audit Activity in Partner Organisations complete

Renfrewshire Council · 20 May 2024
Back to Audit, Risk and Scrutiny Board — 20 May 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 20 May 2024
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Summary of Internal Audit Activity in Partner Organisations April 2023
to April 2024
___________________________________________________________________
1. Summary 
1.1 Members of the Audit, Risk and Scrutiny Committee expressed an interest in
the outcomes of audits undertaken in partner organisations. A proposed
revision to the Audit, Risk and Scrutiny Board’s Terms of Reference, to
facilitate this, was agreed at Council on 4 May 2024. 
1.2 This report provides members with a summary of the internal audit
arrangements within each partner body and a summary of the internal audit
activity from April 2023 to April 2024. 
1.3 Renfrewshire Valuation Joint Board – Internal audit services are provided by
Renfrewshire Council’s Internal Audit Service A summary of each completed
audit engagement is reported to the Board, An annual report is also provided
to the Board, summarising the audit activity for the year and providing the
Chief Auditor’s annual opinion. The 2023/24 annual report will be considered
by the Board on 24 May 2024. During the reporting period, one audit review
was finalised in relation to information governance, a summary of this audit
engagement is included at appendix 1 of this report. 
1.4 Scotland Excel Joint Committee - Internal audit services are provided by
Renfrewshire Council’s Internal Audit Service A summary of each completed
audit engagement is reported to the Executive Sub-Committee. An annual
report is also provided to the Executive Sub-Committee, summarising the
audit activity for the year and providing the Chief Auditor’s annual opinion.
The 2023/24 annual report will be considered by the Sub-Committee on 17
May 2024. During the reporting period, one audit review was finalised in

Page 2

relation to contract management for social care contracts, a summary of
this audit engagement is included at appendix 2 of this report. One further
audit is currently in progress in relation to contract monitoring
(implementation of collaborative procurement), this is nearing completion
and will be reported to the Executive Sub-Committee once finalised. 
1.5 Renfrewshire Integration Joint Board - Internal audit services are provided by
Renfrewshire Council’s Internal Audit Service A summary of each completed
audit engagement is reported to their Audit, Risk and Scrutiny Committee.
An annual report is also provided to the Committee, summarising the audit
activity for the year and providing the Chief Auditor’s annual opinion. The
2023/24 annual report will be considered by the Sub-Committee on 21 June
2024. During the reporting period, one audit review was finalised in relation
to performance management, a summary of this audit engagement is
included at appendix 3 of this report. The annual review of compliance with
the Local Code of Corporate Governance is nearing completion and will be
reported to their Audit, Risk and Scrutiny Committee once finalised. 
1.6 Glasgow & the Clyde Valley Strategic Development Planning Authority Joint
Committee - Internal audit services are provided by Renfrewshire Council’s
Internal Audit Service A summary of each completed audit engagement is
reported to their Audit, Risk and Scrutiny Committee. An annual report is
also provided to the Committee, summarising the audit activity for the year
and providing the Chief Auditor’s annual opinion. The 2023/24 annual report
will be considered by the Joint Committee on 10 June 2024. No specific
audit engagements were planned during the reporting period. 
1.7 Glasgow City Region City Deal – Internal audit services are provided by
Glasgow City Council Internal Audit Services, finalised reports for each
completed audit engagement are reported to the Glasgow City Region
Cabinet and the reports are shared with member Council’s. The Chief
Auditor for Renfrewshire Council meets regularly with the City Region
Auditors and provides them with an annual assurance statement to support
the Glasgow City Region annual governance statement. During the reporting
period, three audit reviews were completed and have been included at
appendices 4-6. 
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to note the audit arrangements for each partner
organisation.
2.2 Members are invited to note the content of the audit reports and audit
summaries that have been considered by the partner bodies.
__________________________________________________________________
Implications of the Report

Page 3

1. Financial - None 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of good
corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights – None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The summary reported relates to the delivery of the risk-based internal
audit plans for the partner bodies 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk - None 
________________________________________________________________
Author:           Andrea McMahon

Page 4

Appendix 1
Internal Audit Report
Renfrewshire Valuation Joint Board
Governance Arrangements - Information
Governance (B0005/2024/001)    
Date: September 2023
BOARD SUMMARY 
Audit Objectives
The objectives of the review were to ensure that:
1. Personal information is kept secure, accurate and up to date.
2. Appropriate measures and records are in place to demonstrate compliance with key
Data Protection Principles.
3. Arrangements are in place to ensure that Data Privacy Impact Assessments are
undertaken when required.
4. Arrangements are in place to provide training on GDPR to relevant employees.
5. Procedures are in place to identify data breaches and report them to Renfrewshire
Valuation Joint Board’s (RVJB) Data Protection Officer. 
Audit Scope
1. Ascertained the information that RVJB holds, how sensitive the information is and
how it is stored.
2. Discussed with appropriate staff the arrangements in place to demonstrate
compliance with information security good practice.
3. Reviewed and assessed the evidence to support compliance and identified any
possible improvements. 
Key Audit Assurances
1. Personal information is kept secure through physical access controls and passwords;
and is kept accurate and up to date through regular reviews.
2. Appropriate measures and records are in place to demonstrate compliance with key
Data Protection Principles, including application of the Data Protection and
Information Handing policies.
3. Arrangements are in place to ensure that Data Privacy Impact Assessments are
undertaken for new initiatives or change of business practices involving personal
data.
4. Arrangements are in place to provide training on GDPR to relevant employees
through annual refresher training, regular bulletins and awareness emails.
5. An Information Security Incident Log is in place but there have been no recorded
data breaches. 
Key Risks
There were no key risks identified during the audit.

Page 5

Appendix 1
Internal Audit Report
Renfrewshire Valuation Joint Board
Governance Arrangements - Information
Governance (B0005/2024/001)    
Date: September 2023 
Overall Audit Opinion
The audit identified that satisfactory arrangements in place for the handling of personal
information within the RVJB. The systems in place for the Electoral Register, Valuation Roll
and Council Tax dwellings are well controlled and regularly reviewed. Staff are regularly
trained and made aware of their responsibilities for handling personal data.

Page 6

Appendix 2
Internal Audit Report
Scotland Excel
Social Care Contracts (A0008/2023/001)
Date: September 2023 
COMMITTEE SUMMARY 
Audit Objectives
The objectives of the audit were to: -
1. Evaluate the extent to which Scotland Excel's care contracts support the principles relevant
to commissioning and procurement as set out in the recommendations detailed in the
Feeley Review. 
2. Identify any areas for improvement and outline actions to address these. 
Audit Scope
1. Obtained a copy of the publication, 'An Independent Review of Adult Social Care in
Scotland', by Derek Feeley. 
2. Interviewed relevant officers within Scotland Excel and obtained information relating to
social care contracts. 
3. Prepared a series of tests to meet the detailed audit objectives. 
Key Audit Assurances
1. Scotland Excel were able to evidence that for the contracts selected for testing, work has
been undertaken to ensure that, where possible, the commissioning and procurement
recommendations as set out in the Feeley Review have been or will be implemented.
2. Stakeholder engagement and market research, including service users and people with
lived experience has been carried out to ensure that there has been a collaborative, rights
based and participative approach.
3. The Procurement Strategy and Service Specifications documentation also include ethical
and fair work requirements as set out in the Feeley Review recommendations. 
Key Risks
There were no key risks arising from the audit review. 
Overall Audit Opinion
In the care frameworks currently being created by Scotland Excel, the commissioning and
procurement recommendations set out in the Feeley Review have been incorporated, where
possible, to include areas such as a collaborative, rights based and participative approach and ethical
and fair work requirements.  Work has been undertaken to ensure that the additional processes
outlined in the Feeley Review will be included in future frameworks.

Page 7

Appendix 3
Internal Audit Report
INTEGRATION JOINT BOARD
IJB – Performance Management (B0017/2024/002)
Date: January 2024
COMMITTEE SUMMARY
Audit Objectives
The objectives of the review were to ensure that:
• Roles and responsibilities for performance management are clear and understood.
• A performance management strategy / framework is in place and details the key
performance indicators.
• Key performance indicators set are SMART and are aligned to organisational
objectives.
• Performance is reviewed regularly by management and the Board.
• Arrangements are in place to ensure that where targets are not being achieved there
are mechanisms to review and improve performance. 
Audit Scope
1. Checked that an adequate system was in place to record the required performance
information for each indicator selected and evaluated for adequacy.
2. For a sample of underperforming indicators, ascertained the review process, what
actions were being taken to address these and if the actions taken were sufficient,
3. Checked that there was adequate management oversight for the selected
performance indicators. 
Key Audit Assurances
1. Roles and responsibilities for performance management within the Planning and
Performance team are clear and understood.
2. A performance management strategy / framework is in place through strategic plans
and performance reports that detail the key performance indicators.
3. Key performance indicators tested from the Annual Performance Report were SMART
and were aligned to organisational objectives in the strategic plan. 
4. Performance scorecards are reviewed annually by management to ensure the
indicators are meaningful with realistic and achievable targets and are reported to
Board.

Page 8

5. For underperforming indicators tested, arrangements were in place to ensure that
where targets were not being achieved, there were mechanisms to review and improve
performance. 
Key Risks
• No key risks were identified as a result of this audit. 
Overall Audit Opinion
The audit identified that satisfactory arrangements are in place for performance management
within the Renfrewshire Health and Social Care Partnership. The systems in place for monitoring
and reviewing key performance indicators are well controlled.
As a result, there were no audit findings identified during this review and the auditor has made
a provision of substantial assurance for the areas tested. 
Management Commentary
N/A as no key risks identified.

Page 9

Internal Audit | Education Services | Gateway Shared Services 
0 Introduction Audit Opinion Main Findings Action Plan 
Internal Audit
Glasgow City Region City Deal
Project Procurement Strategies
Final Report
April 2023
FS 57095

Page 10

Internal Audit | Glasgow City Region City Deal | Project Procurement Strategies 
1 Introduction Audit Opinion Main Findings Action Plan
1 Introduction
1.1 As part of the agreed Internal Audit plan, we have undertaken
a review across the Glasgow City Region Programme
Management Office (the PMO) and member authorities in
relation to Project Procurement Strategies. 
1.2 The new Regional Sustainable Procurement Strategy was
approved by the Cabinet on 1 June 2021.  The Procurement
Support Group (PSG), made up of representatives from each
of the eight member authorities and the PMO is responsible
for translating the Sustainable Procurement Strategy into
action by monitoring performance of core elements of delivery
and undertaking reviews. The group continues to provide
guidance on best practice to the PMO and other stakeholders
and assists member authorities in understanding the impact
procurement will have on the City Deal Programme. 
1.3 We have been advised that in recent times member
authorities have found that construction and materials costs
have significantly increased. This is because procurement
exercises are attracting fewer bids than anticipated, and / or
higher value bids are being submitted. 
1.4 The purpose of the audit was to review the project
procurement strategies in place.  These strategies aim to
achieve competitive bids and ensure value for money during
procurement exercises. The audit also sought to gain
assurance that there are sufficient and appropriate controls in
place in relation to procurement and that these are being
complied with. The scope of the audit included: 
• A review of documented procurement strategies in place.
• Reviewing a sample of project procurement exercises to
ensure a sufficient number of bids were obtained.
• Ensuring that there is appropriate attendance at PSG
meetings, workshops and sub-groups.
• Ensuring regular communication takes place between
officers from the different member authorities and the
PMO.
• Checking that due diligence arrangements are in place for
suppliers.
• Reviewing the arrangements in place to provide suitable
management information to the appropriate groups for
scrutiny. 
• Reviewing the arrangements in place for supplier chain
risk management.
1.6 The sample of member authorities that were selected for this
review were: 
• Glasgow City Council
• Renfrewshire Council
• South Lanarkshire Council

Page 11

Internal Audit | Glasgow City Region City Deal | Project Procurement Strategies 
2 Introduction Audit Opinion Main Findings Action Plan
2 Audit Opinion
2.1 Based on the audit work carried out a reasonable level of assurance can be placed upon the control environment. The audit has identified
some scope for improvement in the existing arrangements and two recommendations which management should address.
3 Main Findings
3.1 We are pleased to report that key controls are in place and
generally operating effectively. We found that the Regional
Sustainable Procurement Strategy aligns with member
authorities’ needs and strategic drivers. The Action Plan is
reviewed annually, and reasonable arrangements are in place
to monitor tasks and report progress against actions outlined
in the strategy. 
3.2 Suitable arrangements are in place within the three member
authorities reviewed to provide support and attendance at the
PSG meetings. There are appointed representatives from
each member authority in attendance at the PSG, whose role
is to provide operational support & guidance within their own
organisation and to feed information through at different
levels and provide feedback to the PSG. 
3.3 However, we identified some areas where improvements
should be made. Within the sample of nine procurement
activities reviewed, we identified one exercise where the
Sourcing Strategy had not been appropriately approved. 
We also identified one procurement activity where initially no
bids were received for the required works. Although we were
advised there many factors had contributed to this, a lack of
early engagement with potential suppliers and failing to utilise
the Prior Information Notice (PIN) may have also played a
factor. 
3.4 An action plan is provided at section four outlining our
observations, risks and recommendations.  We have made
three recommendations for improvement. The priority of each
recommendation is:  
Priority Definition Total
High
Key controls absent, not being
operated as designed or could be
improved. Urgent attention
required.
0
Medium
Less critically important controls
absent, not being operated as
designed or could be improved.
2

Page 12

Internal Audit | Glasgow City Region City Deal | Project Procurement Strategies 
3 Introduction Audit Opinion Main Findings Action Plan
Low
Lower level controls absent, not
being operated as designed or
could be improved.
0
Service
Improvement
Opportunities for business
improvement and/or efficiencies
have been identified.
0
3.5 The audit has been undertaken in accordance with the Public
Sector Internal Audit Standards. 
3.6 We would like to thank officers involved in this audit for their
cooperation and assistance. 
3.7 It is recommended that the Head of Audit and Inspection
submits a further report to Cabinet on the implementation of
the actions contained in the attached Action Plan.

Page 13

Internal Audit | Glasgow City Region City Deal | Project Procurement Strategies 
4 Introduction Audit Opinion Main Findings Action Plan
4 Action Plan
No. Observation and Risk Recommendation Priority Management Response
Key Control: Procurement exercises are undertaken in compliance with the documented procedures.
1 Procurement policies and procedures
require member authorities to develop a
sourcing strategy and obtain appropriate
approvals to agree the route to market. 
Through sample testing of nine
procurement exercises, we identified that
one sourcing strategy was not approved
by the project lead, the procurement lead
or the resource senior manager. For all
other eight procurement exercises, the
sourcing strategy had been completed
and approved where required. 
If sourcing strategies are not correctly
approved there is an increased risk that
an appropriate procurement exercise
may not be undertaken.
The PMO should remind all member authorities
that sourcing strategies should be appropriately
approved, and details of this approval retained
for audit purposes. 
Medium Response: 
Accepted. Reminder will be issued
to Lead Officers and Procurement
Support Group members. 
Officer Responsible for
Implementation: 
Head of City Region Programme
Management Office 
Timescales for Implementation: 
To be discussed at 24 April 2023
Lead Officer Group (LOG) meeting
and 18 May 2023 Procurement
Support Group meeting.

Page 14

Internal Audit | Glasgow City Region City Deal | Project Procurement Strategies 
5 Introduction Audit Opinion Main Findings Action Plan
No. Observation and Risk Recommendation Priority Management Response
2 Through discussions at PSG meetings, it
was highlighted to member authority
representatives that the current status of
the construction market means that
suppliers are generally in positions to be
able to choose which contracts to bid for. 
Within the sample of nine procurement
activities, we identified one case where no
bids were initially received for required
works. We were advised that a new tender
exercise is currently underway and a Prior
Information Notice (PIN) is now being
utilised to assist in attracting bidders. 
Market saturation increases the risk of a
lack of tender responses, which in turn
may result in failed tender exercises. To
ensure best practice, early engagement
with the market and utilising PINs may
improve tender exercises conducted.   
The PMO should raise the construction market
issue at the PSG and ask members to consider
utilising PINs where appropriate. 
Medium Response: 
Accepted. Reminder will be issued
to Lead Officers and Procurement
Support Group members. 
Officer Responsible for
Implementation: 
Head of City Region Programme
Management Office 
Timescales for Implementation: 
To be discussed at 24 April 2023
Lead Officer Group (LOG) meeting
and 18 May 2023 Procurement
Support Group meeting.

Page 15

Internal Audit | Glasgow City Region City Deal | Stakeholder Engagement & Managing Relationships 
1 Introduction Audit Opinion Main Findings Action Plan 
Internal Audit
Glasgow City Region City Deal
Stakeholder Engagement and
Managing Relationships 
Final Report
December 2023
FS 57095

Page 16

Internal Audit | Glasgow City Region City Deal | Stakeholder Engagement & Managing Relationships 
2 Introduction Audit Opinion Main Findings Action Plan
1 Introduction
1.1 The Glasgow City Region Local Authorities (Member
Authorities) entered into a City Deal with the UK and Scottish
Governments in August 2014 (the City Deal). All Projects
within the City Deal programme are monitored, scrutinised
and challenged by, and are accountable to, the Glasgow City
Region Programme Management Office (PMO). 
1.2 To successfully deliver the programme, member authority
City Deal project teams are required to work closely with other
parties, both internally and externally, therefore appropriate
stakeholder engagement and relationship management
arrangements are crucial. 
1.3 The purpose of the audit was to gain assurance that these
arrangements are in place across the City Region, and for
individual City Deal projects. The scope of the audit included: 
• Arrangements between member authorities, the PMO
and other parties involved in City Deal projects across the
region.
• Availability of documented guidance and awareness of
City Deal stakeholder engagement requirements.
• Roles & responsibilities of key officers and teams.
• Identification of key stakeholders within business cases.
• Stakeholder engagement, including consideration of
dependencies/interdependencies and risk associated
with each stakeholder.
• Monitoring and management of associated risks and
dependencies. 
• Confirming that engagement arrangements with other
parties are working as expected.
• Training or experience gaps.
• The impact of project dependencies with other parties on
a sample of City Deal projects.
• Lessons learned arrangements.
• Best practice arrangements. 
1.4 The sample of projects that were selected for review were: 
• Glasgow City Council – Holland St/Pitt St and
Windmillcroft Quay.
• Renfrewshire Council – Glasgow Airport Investment
Area.
• South Lanarkshire Council – A72/M74 Signalisation and
Jackton Primary School.
• West Dunbartonshire Council – Exxon Site Development.

Page 17

Internal Audit | Glasgow City Region City Deal | Stakeholder Engagement & Managing Relationships 
3 Introduction Audit Opinion Main Findings Action Plan
2 Audit Opinion
2.1 Based on the audit work carried out a reasonable level of assurance can be placed upon the control environment.  The audit has identified
some scope for improvement in the existing arrangements and two recommendations which management should address. 
3 Main Findings
3.1 We are pleased to report that a number of key controls are in
place and generally operating effectively. We found that all
member authorities conduct stakeholder analysis, which is
included within the business case for each City Deal project. 
The business case is subject to an appraisal by the PMO
using a standardised set of questions, which includes
confirming that the main stakeholder groups and
dependencies on internal and external factors have been
identified and details of how these will be managed.
3.2 We were advised that Project Managers and relevant Project
Officers within member authorities are PRINCE2 certified and
undertake the Better Business Case training course when this
is offered by the PMO – this is an HM Treasury approach to
public spending and includes aspects of relationship
management and stakeholder engagement.  We confirmed
that the next round of Better Business Case training is being
scheduled by the PMO for early 2024 and member authorities
have been invited to elect City Deal Project Officers to attend
this course. 
3.3 Member authorities have adequate internal arrangements in
place for monitoring the progress of City Deal projects and
addressing issues as they arise – examples include a City
Deal and Infrastructure Programme Board in Renfrewshire
Council and a City Deal Infrastructure Group in South
Lanarkshire Council. There are also adequate reporting and
escalating processes in place to ensure that any issues
relating to managing relationships and stakeholder
engagement are scrutinised by the appropriate senior
officers. 
3.4 We confirmed that member authorities produce a quarterly
Project Status Report for each City Deal project which is
submitted to the PMO, providing key updates on the project
progress including issues and actions, financial information
and benefits tracking, change control requests and updates
on projects risks. This report would also highlight any issues
in relation to stakeholder engagement and relationship
management.
3.5 We also found that there were adequate arrangements in
place for member authorities to escalate issues to the PMO
between Project Status Report reporting dates. This includes
providing an update to the project commentary reported in the
PMO Interim Performance Report on an exception basis, and

Page 18

Internal Audit | Glasgow City Region City Deal | Stakeholder Engagement & Managing Relationships 
4 Introduction Audit Opinion Main Findings Action Plan
individual quarterly meetings with the PMO in which member
authorities provide an update for each project including any
risks or issues that may have arisen.
3.6 We confirmed that best practice arrangements are shared
between the PMO and member authorities at Lead Officer
Group meetings.
3.7 However, we noted that there are some areas where
improvements could be made.  Although member authorities
conduct stakeholder analysis and consultations as part of the
business case formulation, and while a Programme
Management Toolkit is maintained by the PMO and made
available to member authorities, there is no specific guidance
notes or documentation in place to assist member authorities
with stakeholder analysis requirements and in the production
of a stakeholder matrix which maps a stakeholder’s
relationship/role with the project and their ability to impact it. 
3.8 We also found that lessons learned exercises are conducted
by member authorities at the end of a project or at key
milestones during a project’s lifespan. However, we found
that two of the member authorities did not maintain a lessons
learned log throughout the duration of the projects reviewed. 
3.9 An action plan is provided at section four outlining our
observations, risks and recommendations.  We have made
two recommendations for improvement. The priority of each
recommendation is:   
Priority Definition Total
High
Key controls absent, not being
operated as designed or could be
improved. Urgent attention
required.
0
Medium
Less critically important controls
absent, not being operated as
designed or could be improved.
1
Low
Lower level controls absent, not
being operated as designed or
could be improved.
1
Service
Improvement
Opportunities for business
improvement and/or efficiencies
have been identified.
0
3.10 The audit has been undertaken in accordance with the Public
Sector Internal Audit Standards. 
3.11 We would like to thank officers involved in this audit for their
cooperation and assistance. 
3.12 It is recommended that the Head of Audit and Inspection
submits a further report to Cabinet on the implementation of
the actions contained in the attached Action Plan.

Page 19

Internal Audit | Glasgow City Region City Deal | Stakeholder Engagement & Managing Relationships 
5 Introduction Audit Opinion Main Findings Action Plan
4 Action Plan
No. Observation and Risk Recommendation Priority Management Response
Key Control: Stakeholder engagement procedures and guidance are kept up to date to ensure they accurately reflect current working practices.
1 Member authorities conduct stakeholder
analysis which is included within the
business case for each City Deal Project.
A Programme Management Toolkit and
business case appraisal template are
available to member authorities to assist
in the production of business cases. 
However, there is no formal guidance on
the actions required, or the
considerations that should be given in
completion of a stakeholder analysis
including the production of a stakeholder
matrix and the development of a
communication and engagement plan for
each stakeholder group. 
This increases the risk that stakeholders
may not be identified in a timely manner
and appropriate arrangements are not put
in place to manage the expectations of,
and relationship with, key stakeholder
groups including those where project
dependencies exist.
The PMO should update the Programme
Management Toolkit to assist member
authorities with stakeholder engagement and
relationship management. 
The Toolkit should outline the expectations of
member authorities and provide assistance with
the production of a stakeholder matrix and a
communication and engagement plan for key
stakeholder groups. 
Once the Toolkit has been updated this should
be shared with City Deal member authorities.   
Medium Response: 
Recommendation accepted. Toolkit
will be updated as per
recommendation.   
Officer Responsible for
Implementation: 
Communication and Marketing
Manager 
Timescales for Implementation: 
April 2024

Page 20

Internal Audit | Glasgow City Region City Deal | Stakeholder Engagement & Managing Relationships 
6 Introduction Audit Opinion Main Findings Action Plan
No. Observation and Risk Recommendation Priority Management Response
Key Control: Adequate arrangements are in place to capture and record lessons learned.
2 We found that lessons learned exercises
are conducted by member authorities at
the end of a project or at key milestones
during a project’s lifespan. 
However, we found that two of the
member authorities do not maintain a
lessons learned log throughout the
project. 
The City Deal Project Management
Toolkit requires that a lessons learned log
is maintained. This is particularly
important for long term projects and those
with a high volume of sub-projects. 
Without documenting these at key
milestones and recording in a log, there is
an increased risk that key points or factors
that could be classed as a lesson learned
are missed. 
The PMO should remind all member authorities
of the requirement to record and maintain a
lessons learned log throughout the duration of a
project. 
Low Response: 
Recommendation accepted. Reminder
will be issued to Lead Officers, Will be
discussed at 29 January 2024 Lead
Officer Group (LOG) meeting. 
Officer Responsible for
Implementation: 
City Deal Programme Manager 
Timescales for Implementation: 
January 2024

Page 21

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Financial Monitoring 
0 Introduction Audit Opinion Main Findings Action Plan
Will 
Glasgow City Region City Deal
Financial Monitoring
Final Report
April 2024
FS 57095

Page 22

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Financial Monitoring 
1 Introduction Audit Opinion Main Findings Action Plan
1 Introduction
1.1 As part of the agreed Internal Audit plan, we have carried out
a review of the financial monitoring arrangements in place
across the Glasgow City Region City Deal Programme. 
1.2 The Glasgow City Region Project Management Office (PMO)
is responsible for the financial monitoring and reporting for the
overall City Deal programme. The role of the PMO includes
collating the project status updates from all member
authorities and reporting to various senior officer groups and
the Cabinet. The current financial pressures being
experienced by all member authorities along with external
factors which may affect the progression of City Deal projects,
makes it even more vital to ensure that financial monitoring
and reporting is being carried out effectively and in line with
expected timescales in order to highlight any key issues as
soon as possible. 
1.3 The purpose of the audit was to gain assurance that there are
adequate controls in place covering financial monitoring and
reporting carried out by the PMO and member authorities,
and that these are operating effectively. The scope of the
audit included: 
• Documented procedures, roles and responsibilities.
• The financial monitoring process and reporting to
Cabinet.
• The process for identifying variances.
• The arrangements and approval processes for the
amendments of budgets.
• The PMO budget monitoring processes.
• The year-end processes.
• The internal monitoring processes and arrangements for
reporting to the PMO.
• The escalation processes in place. 
1.4 Four member authorities were selected for review were: 
• Inverclyde Council
• East Renfrewshire Council
• East Dunbartonshire Council
• North Lanarkshire Council 
The remaining four member authorities will be reviewed in the
second phase of this audit in 2024/25.

Page 23

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Financial Monitoring 
2 Introduction Audit Opinion Main Findings Action Plan
2 Audit Opinion
2.1 Based on the audit work carried out, assurance can be taken that the control environment is satisfactory.
3 Main Findings
3.1 We are pleased to report that key controls are in place and
operating effectively. Guidance on the financial monitoring
requirements for City Deal projects is available to member
authorities through the ‘Assurance Governance and
Programme Management Framework’ (the Framework) and
the supporting Project Management Toolkit. The PMO is
responsible for updating both documents and an annual
schedule of review and approval routes for changes to the
documents is in place. We were advised by senior officers
within the PMO, that a full review of both documents is
planned upon conclusion of Phase 2 of the Glasgow City
Region Governance Review. 
3.2 The PMO has satisfactory arrangements in place surrounding
the development and approval of the annual PMO Budget.
Regular budget monitoring is undertaken as expected, with
the overall position being reported to Cabinet as part of the
Quarterly Programme Report. 
3.3 In accordance with the Framework, we found that member
authorities provide the PMO with the expected quarterly
updates, detailing progress of their projects, which includes
financial information regarding expenditure, claims and
projected cashflows, in the form of Project Status Reports. 
We found satisfactory budget monitoring processes are in
place within the four sampled member authorities, to identify
budget variances and allow adequate review of all their
project financial positions through established reporting
arrangements. Adequate arrangements are in place to ensure
that scrutiny by relevant senior management and committees
is conducted in line with the agreed timescales. We found that
there are adequate processes for collating financial data for
reporting to the PMO and that there is a good working
relationship between the PMO and member authorities, which
includes regular meetings prior to the submission of the
quarterly returns. 
3.4 We found that the four sampled member authorities are
compliant with the established change control process in
respect of budget amendments. Satisfactory arrangements
are also in place across each member authority in respect of
the escalation and approval routes of internal change control
requests, as well as to the PMO as part of the quarterly
Project Status Report. This is to ensure that changes are also
approved or rejected at the appropriate programme level. A

Page 24

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Financial Monitoring 
3 Introduction Audit Opinion Main Findings Action Plan
central register of all approved change control requests
across the Region is adequately maintained by the PMO. 
3.5 The audit has been undertaken in accordance with the Public
Sector Internal Audit Standards. 
3.6 We would like to thank officers involved in this audit for their
cooperation and assistance. 
3.7 It is recommended that Cabinet note the content of this report.