Page 1

10/08/2026 
Notice of Meeting and Agenda
Audit, Risk and Scrutiny Board 
Date Time Venue
Monday, 17 August 2026 10:00 Council Chambers (Renfrewshire),
Council Headquarters, Renfrewshire
House, Cotton Street, Paisley, PA1 1AN               
Membership 
Councillor Andy Doig (Convener): Councillor Janis McDonald (Depute Convener):  
Councillor Jennifer Adam: Councillor Gillian Graham: Councillor Lisa-Marie Hughes: Councillor
Robert Innes: Councillor James MacLaren: Councillor Will Mylet: Councillor Ben Smith: 
Members of the Press and Public
Members of the press and public wishing to attend the meeting should report to the customer
service centre where they will be met and directed to the meeting. 
Further Information
This is a meeting which is open to members of the public. 
A copy of the agenda and reports for this meeting will be available for inspection prior to the
meeting at the Customer Service Centre, Renfrewshire House, Cotton Street, Paisley and online
at  http://renfrewshire.cmis.uk.com/renfrewshire/CouncilandBoards.aspx
For further information, please email
democratic-services@renfrewshire.gov.uk   
Hybrid Meeting
Please note that this meeting is scheduled to be held in the Council Chambers.  However, it is a
hybrid meeting and arrangements have been made for members to join the meeting remotely
should they wish.
MARK CONAGHAN
Head of Corporate Governance
Page 1 of 120

Page 2

10/08/2026 
Webcasting of Meeting
This meeting will be filmed for live or subsequent broadcast via the Council’s internet site – at
the start of the meeting the Convener will confirm if all or part of the meeting is being filmed.  To
find the webcast please navigate to 
https://renfrewshire.public-i.tv/core/portal/home 
Page 2 of 120

Page 3

10/08/2026 
Items of business      
Apologies
Apologies from members. 
Declarations of Interest and Transparency Statements
Members are asked to declare an interest or make a transparency
statement in any item(s) on the agenda and to provide a brief
explanation of the nature of the interest or the transparency statement. 
1 Summary of Internal Audit Reports for period 01 May to
30 June 2026
Report by Chief Auditor. 
5 - 14 
2 Summary of Internal Audit Activity in Partner
Organisations - 1 May 2026 to 30 June 2026
Report by Chief Auditor. 
15 - 76 
3 Internal Audit and Counter Fraud Progress and
Performance for Period to 30 June 2026
Report by Chief Auditor. 
77 - 92 
4 Lead Piping in Public and Private Housing in
Renfrewshire
Report by Lead Officer. 
93 - 106 
5 Accounts Commission: Transformation: How councils
are redesigning and delivering more efficient services
Report by Director of Finance & Resources. 
107 - 114 
6 Audit Scotland: Local Government Budgets 2026/27
Report by Director of Finance & Resources. 
115 - 120 
7 Partner Bodies Risks 
Exclusion of Press and Public
The Board may by resolution exclude the press and public from the
meeting during consideration of the following items of business as
it is likely, in view of the nature of the business to be transacted,
that if members of the press and public are present, there could be
disclosure to them of exempt information as defined in paragraph 1 
Page 3 of 120

Page 4

10/08/2026 
of Part I of Schedule 7A of the Local Government (Scotland) Act
1973.  
Exempt Item
Exempt documents are no longer available in print format.  You will
require to log in to cmis to access documents.  Please note that access
to exempt documents is now restricted. 
8 Summary of Internal Audit Investigation/Review Reports
for period 01 May to 30 June 2026
Report by Chief Auditor. 
Page 4 of 120

Page 5

PUBLIC
___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 17 August 2026
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Summary of Internal Audit Reports for period 01 May to 30 June
2026
___________________________________________________________________
1. Summary
1.1 In line with the Global Internal Audit Standards in the UK Public Sector,
Internal Audit must communicate the results of each engagement to
the Board. To comply with this requirement, Internal Audit submits
regular reports on the findings and conclusions of audit engagements
to the Audit, Risk and Scrutiny Board.
1.2 Appendix 1 provides details of audit engagements completed during
the period 01 May to 30 June 2026 with the overall assurance rating
and the number of recommendations in each risk category. The
committee summary for each report is also attached. For each audit
assignment where recommendations have been made, the relevant
managers have put action plans in place to address the issues raised.
1.3 In addition to the reports listed in the Appendix, Internal Audit has an
ongoing commitment to:
• A range of corporate and service initiatives;
• Progressing of information security matters in partnership with
ICT and Legal Services;
• The regular provision of advice to departmental officers;
• The provision of internal audit services to the associated bodies
for which Renfrewshire Council is the lead authority and to
OneRen and Renfrewshire Integration Joint Board;
• Co-ordination of the Council’s corporate risk management
activity;
• Management of the counter fraud team;
Item 1
Page 5 of 120

Page 6

PUBLIC
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to consider and note the Summary of Internal Audit
Reports finalised during the period from 01 May to 30 June 2026. 
___________________________________________________________________
Implications of the Report
1. Financial - None 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of good
corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights – None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The summary reported relates to the delivery of the risk-based internal
audit plan. 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk – None 
14. Children’s Rights - None 
________________________________________________________________
Author:           Karen Campbell, Chief Auditor– 07768354651
Page 6 of 120

Page 7

PUBLIC
Appendix 1 
Renfrewshire Council 
Internal Audit Service 
Update for Audit, Risk and Scrutiny Board 
Final Audit Reports issued from 01 May – 30 June 2026 
Category  Service  Engagement  Assurance
Rating
Recommendation Ratings
Critical Important Good
Practice
Service
Improvement
Assurance Children’s Services School Transport Reasonable 0 2 1 0 
Finance & Resources Programme
Management
Reasonable 0 1 3 0
Governance Adult Services Security of Paper
Documentation
Reasonable 0 1 4 1 
Page 7 of 120

Page 8

PUBLIC 
Assurance Level 
Substantial Assurance • There is a sound system of internal control designed to achieve the objectives of the area being reviewed. 
• The control processes tested are being consistently applied. 
Reasonable Assurance • The internal control processes are generally satisfactory with some areas of weakness being identified that could
put some objectives of the area being reviewed at risk.
• There is evidence that the level of non-compliance with some of the control processes may put some of the
objectives of the area being reviewed at risk. 
Limited Assurance • Weaknesses in the system of internal controls are such as to put the objectives of the area being reviewed at risk. 
• The level of non-compliance puts the objectives of the area being reviewed at risk. 
No Assurance • Control processes are generally weak with significant risk to the achievement of the objectives of the area being
reviewed. 
• Significant non-compliance with control processes leaves the processes/systems open to error or abuse. 
Recommendation
Rating 
Service Improvement  Implementation will improve the efficiency / housekeeping of the area under review.
Good Practice  Implementation will contribute to the general effectiveness of control.
Important  Implementation will raise the level of assurance provided by the control system to acceptable levels.
Critical  Addresses a significant risk, impacting on the objectives of the area under review. 
Page 8 of 120

Page 9

Internal Audit Report
Children’s Services
School Transport (A0058/2026/001) 
Date: May 2026 
PUBLIC
COMMITTEE SUMMARY 
Audit Objectives
The audit objectives were to: -
1. Assess whether school transport policies are up-to-date, clearly documented, and
aligned with national guidance and meet any legal obligations.
2. Verify that transport is only provided for pupils who are entitled to it based upon
relevant criteria as outlined in the policies.
3. Ascertain that the appropriate provider and mode of transport have been selected
for non-mainstream pupils.
4. Ensure payments to transport providers are timely, accurate and appropriately
authorised.
5. Ensure quarterly and annual reports are received from Strathclyde Passenger
Transport in relation to contract monitoring which highlight any issues that have
arisen and ensure that appropriate actions have been taken in these instances. 
Audit Scope
1. Through discussions with relevant officers, documented the processes followed in
relation to school transport.
2. Prepared a series of tests to enable appropriate sample testing to be undertaking to
meet the above objectives. 
Key Audit Assurances
1. Transport arrangements for all pupils were appropriately aligned with their assessed
needs, with suitable provisions put in place that were matched to requirements and
operated effectively in practice.
2. Audit testing confirmed that payments to transport providers were calculated
accurately, aligned with contract rates, were properly authorised, and supported by
adequate documentation, demonstrating that financial controls were operating
effectively.
3. Quarterly and annual contract‑monitoring reports are received from Strathclyde
Passenger Transport, providing appropriate oversight of contractor performance
and any issues arising through this monitoring are identified, reported, and
addressed through the Council’s established processes. 
Key Audit Risks
1. A lack of documented policy reviews, when national guidance is updated, and absence
of version control creates a risk that school transport policies are out of date or
non‑compliant with national standards.
Page 9 of 120

Page 10

Internal Audit Report
Children’s Services
School Transport (A0058/2026/001) 
Date: May 2026 
PUBLIC
2. Not retaining evidence of transport assessments undertaken and inconsistently
evidencing that the assessments have been reviewed by a second officer increases the
risk of errors, inconsistent decisions, and potential challenge. 
Overall Audit Opinion
The audit concluded that controls operating across policy governance, eligibility
assessment, transport mode selection, provider payments, and contract monitoring were
generally effective in supporting the delivery of school transport services.
It was found that the Council does not have a formal mechanism to ensure that all school
transport policies are reviewed and updated whenever national guidance, statutory
requirements, or relevant legislation changes. Evidence of assessment of eligibility checks
is not retained, and secondary review procedures are applied inconsistently. In addition, the
Transport Eligibility Address List is not routinely updated to reflect new routes or
infrastructure changes. 
Recommendations have been made in the report to address these issues. 
Management Commentary
Children’s Services are currently working with a Contractor to review all school walking
routes to ensure they are acceptable and this task should be undertaken by Autumn 2026. 
Following completion, the Home to School Transport Policy will be reviewed and updated
as necessary.  With regards to evidencing quality assurance checks, we are investigating
ways of carrying out quality assurance checks on digital forms. 
Page 10 of 120

Page 11

Internal Audit Report
Finance and Resources
Programme Management (A0087/2025/001) 
Date: June 2026 
PUBLIC
COMMITTEE SUMMARY 
Audit Objectives
The objectives of the audit were to:- 
1. Determine the availability and accessibility of information/tools and support which
may be obtained by Services when initiating service led projects/programmes,
assess for adequacy and ascertain the level of uptake of those resources. 
2. Ensure that authorised Options Appraisals and Business Cases have been
appropriately prepared which take into account value for money and that these have
included consultation with relevant stakeholders and subject matter experts and are
aligned with the Council’s strategic objectives. 
3. Ensure that there is clear senior management ownership of projects and that robust
governance arrangements are in place over service led projects. 
Audit Scope       
1.  Through discussion with officers within Services and the Project Management Unit
(PMU) and review of available documentation, established what
projects/programmes were running in Services that do not have PMU involvement. 
2. Selected a sample of three service led projects for review and prepared a series of
tests that enabled the objectives of the audit to be met. 
Key Audit Assurances
1. Governance arrangements for sampled projects were generally satisfactory, with
clear ownership and regular reporting to service oversight groups. 
2. Business cases for the projects reviewed demonstrated alignment with strategic
objectives, considered value for money, consulted with stakeholders and subject
matter experts where necessary. 
3. Further audit assurance was obtained through review of Heads of Services
responses to the Business As Usual Risk Assessment Module relating to
Programme and Project Management. 
Key Audit Risks
There were no key risks identified in the audit. 
Page 11 of 120

Page 12

Internal Audit Report
Finance and Resources
Programme Management (A0087/2025/001) 
Date: June 2026 
PUBLIC
Overall Audit Opinion
Based on the work undertaken, Internal Audit concludes that the processes in relation to
service led project management are generally adequate and operating effectively.  There is
clear ownership and regular service oversight, and business cases reviewed were aligned
with strategic objectives and demonstrated consideration of value for money and
stakeholder engagement. 
While opportunities for enhancement have been identified, such as formally documenting
the remit of the Transformation Board and updating the guidance available on the intranet,
the current process provides a reasonable level of assurance that projects are managed in
a controlled and transparent manner. 
Management Commentary
The Terms of Reference of the Transformation Board has been shared with Board
Members and will be made available to all Managers.  Arrangements are currently being
made to update the Programme Management Unit pages on the Intranet to assist staff
undertaking projects. 
Page 12 of 120

Page 13

Internal Audit Report
Adult Services
Security of Paper Documentation (B0010/2026/001)
Date: May 2026 
PUBLIC
COMMITTEE SUMMARY 
Audit Objectives
The objectives of the review were to ensure that:
1. Paper documentation is handled in line with legislation and council policies when working on
and off site, including at home and on client visits, and stored securely when not being used.
2. Paper documentation is not left unattended in vehicles during the day or overnight, and secure
alternatives are used where transportation or temporary storage is required.
3. Officers involved in handling paper documentation have received adequate training and there
is supporting evidence to ensure that there is management oversight of training records.
4. Any loss, theft or unauthorised access to documentation is reported in line with council
procedures.
5. • Confidential paper documentation is disposed of in line with council procedures. 
Audit Scope
1. Interviewed the appropriate officers to ascertain the systems in place for security of paper
documentation.
2. For a sample of four Adult Services locations, prepared and carried out a programme of tests
to enable the audit objectives to be met. 
Key Audit Assurances
1. Managers at each location visited stated that although they are aware of the Information
Security incident procedure, there had not been any loss, theft or unauthorised access to
documentation that required to be reported to the council’s Information Governance team.
2. Discussions with staff and review of documentation, at each location visited, showed that
confidential paper documentation is generally disposed of in line with the council’s
Confidential Waste policy. 
Key Risks
1. For service departments where paper records are left unattended in vehicles, there is a
risk that sensitive service user data could be subject to unauthorised access. 
Overall Audit Opinion
The audit highlighted a weakness in the system of internal control at some of the locations visited
with regard to the storage of paper documentation containing personal data when visiting service
users.  In addition, there were some staff who have not completed their Information Governance
refresher training. 
Page 13 of 120

Page 14

Internal Audit Report
Adult Services
Security of Paper Documentation (B0010/2026/001)
Date: May 2026 
PUBLIC
Management Commentary
We  are currently implementing an electronic system for responding to calls within one of the services
visited by the Auditors and this will eliminate the need for paper documentation to be taken out on
visits.  For other services, deed boxes have now been fitted to vehicles and paperwork will be locked
away when visits are being undertaken.  In addition all services have been directed to ensure all staff
have completed their refresher training. 
Page 14 of 120

Page 15

___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 17 August 2026
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Summary of Internal Audit Activity in Partner Organisations - 1
May  2026 to 30 June 2026
___________________________________________________________________
1. Summary
1.1 This report provides members with a summary of the internal audit activity
within each partner body from 1 May 2026 to 30 June 2026.
1.2 Renfrewshire Valuation Joint Board –The summary of the internal audit
engagement reviewing Purchasing Processes and the 2025/26 Internal Audit
Annual Report, summarising the audit activity for the year and providing the
Chief Auditor’s annual opinion was considered by the Board on 22 May 2026
and is attached in Appendices 1 and 2. 
1.3 Scotland Excel Joint Committee – A summary of  internal audit engagement
reviewing Contract Delivery Plan Processes and  the 2025/26 Internal Audit
Annual Report, summarising the audit activity for the year and providing the
Chief Auditor’s annual opinion was considered, by the Executive Sub-
Committee on 19 June 2026 and is attached in Appendices 3 and 4. 
1.4 Renfrewshire Integration Joint Board - The engagement summary for
reviewing the processes in operation for preparing their Strategic Plan and
the 2025/26 Internal Audit Annual Report, summarising the audit activity for
the year and providing the Chief Auditor’s annual opinion was considered, by
their Audit, Risk and Scrutiny Committee on 12 June 2026 and is attached in
Appendices 5 and 6. 
1.5 Glasgow City Region– Internal audit services are provided by Glasgow City
Council Internal Audit Services, finalised reports for each completed audit
engagement are reported to the Glasgow City Region Cabinet and the
Item 2
Page 15 of 120

Page 16

reports are shared with member Councils. During the reporting period, the
internal audit reviews of Fair Work First Compliance and Clyde Mission Heat
Decarbonisation Fund Governance – Phase One  were finalised and the
reports  are attached at Appendices 7 and 8. 
___________________________________________________________________ 
2. Recommendations
2.1  Members are invited to note the content of the audit reports and audit
summaries that have been considered by the partner bodies.
__________________________________________________________________
Implications of the Report
1. Financial - None 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of good
corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights – None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The summary reported relates to the delivery of the risk-based internal
audit plans for the partner bodies 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk – None 
14.  Children’s Rights – None. 
________________________________________________________________
Author:           Karen Campbell, Interim Chief Auditor
Page 16 of 120

Page 17

PUBLIC 
RENFREWSHIRE VALUATION JOINT BOARD 
To: Renfrewshire Valuation Joint Board 
On: 22 May 2026
___________________________________________________________________ 
Report by: Chief Auditor 
___________________________________________________________________ 
Heading: Internal Audit Engagement – Purchasing Processes
___________________________________________________________________ 
1. Summary
1.1 In line with the Global Internal Audit Standards in the UK Public Sector,
Internal Audit must communicate the results of each engagement to the
Board. 
1.2 The Chief Auditor will report summaries of completed audit engagements
to the Joint Board on the conclusion of each engagement for formal
consideration by member in line with the best practice referred to above. 
1.3 This report provides detail of the audit engagement completed in
February 2026 with the overall assurance rating and the number of
recommendations in each risk category. The detailed board summary for
the report is also attached. 
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to consider and note the summary for the internal
audit review of the purchasing processes in operation within the Joint
Board. 
_________________________________________________________ 
For further information please contact Karen Campbell on 0141 487 0678
Or via e-mail at karen.campbell@renfrewshire.gov.uk 
Page 17 of 120

Page 18

No embedded text on this page.

Page 19

PUBLIC 
Renfrewshire Council 
Internal Audit Service 
Update for Renfrewshire Valuation Joint Board on the Audit
Engagement concluded in February 2026 
Category  Engagement  Assurance Rating Recommendation Ratings
Critical Important Good
Practice
Service
Improvement
Assurance Purchasing Processes Limited 1 2 1 0 
Assurance Level 
Substantial Assurance • There is a sound system of internal control designed to achieve the
objectives of the area being reviewed. 
• The control processes tested are being consistently applied. 
Reasonable Assurance • The internal control processes are generally satisfactory with some
areas of weakness being identified that could put some objectives
of the area being reviewed at risk.
• There is evidence that the level of non-compliance with some of the
control processes may put some of the objectives of the area being
reviewed at risk. 
Limited Assurance • Weaknesses in the system of internal controls are such as to put
the objectives of the area being reviewed at risk. 
• The level of non-compliance puts the objectives of the area being
reviewed at risk. 
No Assurance • Control processes are generally weak with significant risk to the
achievement of the objectives of the area being reviewed. 
• Significant non-compliance with control processes leaves the
processes/systems open to error or abuse. 
Recommendation
Rating 
Service Improvement  Implementation will improve the efficiency / housekeeping of the
area under review.
Good Practice  Implementation will contribute to the general effectiveness of
control.
Important  Implementation will raise the level of assurance provided by the
control system to acceptable levels.
Critical  Addresses a significant risk, impacting on the objectives of the
area under review. 
Page 19 of 120

Page 20

Internal Audit Report
Valuation Joint Board
RVJB - Purchasing Processes (A0011/2026/001)
Date:  February 2026
BOARD SUMMARY 
Audit Objectives
The audit review was included in the 2025/26 audit plan at the request of the Assessor & Electoral
Registration Officer to highlight any disparities in alignment between their current purchasing processes
and those being introduced within Renfrewshire Council during the implementation of the Purchase to Pay
Policy.
The objectives of the audit were to ensure that:- 
1. Purchasing processes comply with relevant legislation and internal policies and procedures,
including Standing Orders and Scheme of Delegation. 
2. There is an adequate process in place for selecting, evaluating, and monitoring suppliers. 
3. There is an adequate separation of duties within purchasing processes. 
4. Purchase orders, invoices, and payments are properly authorised and accurately recorded. 
5. Budgetary controls are in place and monitored throughout the procurement cycle. 
Audit Scope
1.  Interviewed relevant officers to obtain the system in place regarding purchasing processes. 
2.  Prepared a series of tests to meet the above objectives. 
Key Audit Assurances
1. Purchase Orders in the sample tested were appropriately approved.
2. There is adequate budget monitoring throughout the purchase order and invoice payment process
whereby each budget line is reviewed each period by RVJB management and accountants. 
Key Risks
1. In the absence of documented operational purchasing guidance, officers may lack clarity on their
roles and responsibilities, increasing the risk of non-compliance with governance requirements.
2. There is a lack of controls in relation to the use of credit cards which could lead to a risk of fraud
and lack of accountability.
3. Where goods and services are purchased without an official purchase order, this increases the risk
of unauthorised, non-compliant, or unnecessary spending. 
Overall Audit Opinion
At the time of the audit review, there was no documented operational guidance covering the current RVJB
purchasing process. While purchase orders are used for many transactions, and budgets are closely
monitored each period, some purchases tested lacked an official purchase order, which is not considered
to be good practice.  Additionally, although it is acknowledged that credit card expenditure is low,
processes followed in relation to credit card usage were found to be unsatisfactory and these were ended
immediately by management.  Recommendations have been made within this report to address the control
weaknesses. 
Page 20 of 120

Page 21

Internal Audit Report
Valuation Joint Board
RVJB - Purchasing Processes (A0011/2026/001)
Date:  February 2026
Management Commentary
Management are actively in the process of implementing the audit recommendations. New procedures
have been drawn up and approved by management for the use of credit cards and sent to all the relevant
staff. We are now preparing guidance for all the other purchasing processes and an official order form  will
now be completed and sent to the Supplier for any goods and services required 
Page 21 of 120

Page 22

RENFREWSHIRE VALUATION JOINT BOARD 
___________________________________________________________________
To: Renfrewshire Valuation Joint Board
On: 22 May 2026
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: INTERNAL AUDIT ANNUAL REPORT 2025/26
___________________________________________________________________ 
1. SUMMARY 
1.1 The Global Internal Audit Standards in the UK Public Sector require the Chief
Auditor to prepare a report, at least annually, to senior management and the Board
on the internal audit activity’s purpose, authority, and responsibility, as well as
performance relative to its plan. 
1.2 The annual report must also provide an annual audit opinion on the overall
adequacy and effectiveness of the Renfrewshire Valuation Joint Board’s internal
control environment. 
1.3 The Annual Report for Renfrewshire Valuation Joint Board is attached at Appendix
1 and outlines the role of Internal Audit, the performance of the Internal Audit
Team, the main findings from the internal audit work undertaken in 2025/26 and
contains an audit assurance statement. 
2. RECOMMENDATIONS 
2.1 Members are invited to consider and note the contents of the Internal Audit Annual
Report.   
Page 22 of 120

Page 23

Appendix 1 
Renfrewshire Valuation Joint Board
Internal Audit Annual Report 
2025/2026 
Renfrewshire Council
Internal Audit 
Page 23 of 120

Page 24

Renfrewshire Valuation Joint Board 
Internal Audit Annual Report 2025/2026 
Contents 
Page 
1.    Introduction  1 
2.  Global Internal Audit Standards in the UK Public Sector  1 
3.  Responsibilities of Management and Internal Audit  2 
3.    Internal Audit Activity in 2025/26  2 
4.                                                                            Internal Audit Performance    4 
5.  Planned Audit Work for 2026/27  5 
6.  Audit Assurance Statement  5 
Page 24 of 120

Page 25

- 1 -
Renfrewshire Valuation Joint Board
Internal Audit Annual Report   
1 April 2025– 31 March 2026 
1. Introduction 
1.1 Renfrewshire Council provides an internal audit service to Renfrewshire Valuation
Joint Board. This includes: 
• The compilation of an annual audit plan following consideration and
evaluation of those areas of greatest risk in the organisation’s operation,
and consultation with the Assessor and Electoral Registration Officer,
Renfrewshire Valuation Joint Board. 
• Delivery of the planned audit assignments.
• Follow up of previous audit recommendations.
• Provision of any ongoing advice and support on audit and risk
management related matters.
• Provision of an Annual Report and Assurance Statement, and
presentation to elected members at the board of Renfrewshire Valuation
Joint Board. 
1.2 The Internal Audit Section is an independent and objective assurance and advisory
service designed to add value and improve the operations of Renfrewshire Council
and its Partners. It assists the RVJB in accomplishing its objectives by bringing a
systematic and disciplined approach to evaluate and improve the effectiveness of the
organisation's risk management, control, and governance processes and enhances
the RVJB’s decision making and oversight arrangements. 
1.3 The purpose of this Annual Report is to report on: 
• The outcome of the planned Internal Audit reviews 2025/26 relating to  
Renfrewshire Valuation Joint Board.
• The outcome of Internal Audit reviews of supporting Renfrewshire Council
corporate systems.
• Internal audit performance.
• Planned audit work for 2026/27.
• The annual assurance statement which provides an opinion on the overall
adequacy and effectiveness of the Board’s internal control environment. 
2. Global Internal Audit Standards in the UK Public Sector 
2.1 At the start of 2025/26, new Public Sector Internal Audit Standards  “Global Internal
Audit Standards in the UK Public Sector” came into force.  These Standards require
the Chief Auditor to develop and maintain a quality assurance and improvement
programme (QAIP) that covers all aspects of the internal audit activity. The QAIP
must include ongoing monitoring of compliance with the standards,  periodic internal
self-assessments and five-yearly external assessments, carried out by a qualified,
independent assessor from outwith the organisation. 
Page 25 of 120

Page 26

- 2 -
2.2 With regards to the ongoing monitoring to ensure compliance, the  work undertaken
during an assignment is  reviewed by a senior audit team member. 
2.3 The Chief Auditor undertook a self-assessment exercise to determine what actions
were required to ensure compliance.  The conclusion of this exercise was that in the
main, Internal Audit complied with the spirit of the standards but required to
undertake some actions throughout the year to achieve full compliance or enhance
the processes already in place.  The main actions were to update the Internal Audit
Charter and Mandate and ensure staff were fully trained as to the requirements of the
new standards. 
2.4 These actions have been completed.  Staff training sessions were held during the
year and a  revised Internal Charter and Mandate was prepared and is attached at
Appendix 1.  A further formal self-assessment is planned for the forthcoming year. 
3. Responsibilities of Management and Internal Audit 
3.1 It is the responsibility of management to ensure that the areas under their control are
adequate and effective and that there is a sound system of internal control which
facilitates the effective exercise of the organisation’s functions and which includes
arrangements for the management of risk. 
3.2 Internal Audit is not a substitute for effective control exercised by management as
part of their responsibilities. Internal Audit’s role is to independently assess the
adequacy of the risk management, internal controls and governance arrangements
put in place by management and to undertake sufficient work to evaluate and
conclude on the adequacy of those controls for the period under review. 
3.3 The internal audit team will ensure that independence and objectivity are maintained
in line with the Global Internal Audit Standards in the UK Public Sector including
where non-audit work is undertaken. Internal auditors will have no operational
responsibilities. There have been no impairments impacting on the Chief Auditor’s
independence. 
4. Internal Audit Activity during 2025/2026 
4.1 One specific engagement was undertaken during 2025/26, which related to the
arrangements for purchasing goods and services in operation within the Board. A
summary of the report was considered by the Board on 22 May 2026 and the
conclusion of this review is summarised in Table 1 below: 
Page 26 of 120

Page 27

- 3 - 
Table 1 
Audit Area Conclusion  
Purchasing Processes Limited Assurance 
At the time of the audit review, there was no
documented operational guidance covering the 
RVJB purchasing process. While purchase orders
are used for many transactions, and budgets are
closely monitored each period, some purchases
tested lacked an official purchase order, which is
not considered to be good practice.  Additionally,
although it is acknowledged that credit card
expenditure is low, processes followed in relation to
credit card usage were found to be unsatisfactory
and these were ended immediately by
management.  Recommendations were made to
address the control weaknesses identified. 
4.2 The Annual Report for 2024/2025 was submitted to the Joint Board on 23 May 2025. 
4.3 The implementation rate of audit recommendations is a measure of operational
culture and effectiveness. During 2025/26, there was one recommendation that
required to be followed up and it was fully implemented. 
4.4 Internal Audit also carried out reviews of the main corporate systems operating within
Renfrewshire Council which support the Board’s activity. The main findings in relation
to these are summarised in Table 2 below and Renfrewshire Council management
have agreed to implement the audit recommendations made in relation to each
review: 
Table 2 
Audit Area Conclusion
Financial Planning Substantial Assurance
The arrangements in place for financial
planning were found to be robust.
Assumptions and financial risks related
to cost pressures were reported to the
Council. 
Page 27 of 120

Page 28

- 4 -
Main Financial Systems – Key
Controls
Limited Assurance
The audit identified that satisfactory
controls are in place for system
documentation and budget monitoring
across the main financial systems. 
Some control weaknesses were
identified in relation to segregation of
duties and in relation to reconciliation of
feeder systems. In addition, there was a
substantial backlog of unresolved
Accounts Receivable transactions in the
ERP system, with systemic workflow and
error-handling issues which required
management attention. 
Petty Cash Reasonable Assurance
Whilst there are some establishments
that would continue to require petty cash
imprests, we identified some other
imprests that could be closed as they
have not been used for some time and
others could be decreased as their use
seems to have declined.   
5. Review of Internal Audit Performance 
5.1 Internal Audit produces regular reports on its performance during the year to
Renfrewshire Council’s, Audit, Risk and Scrutiny Board, against a range of measures
set annually by the Director of Finance and Resources. These targets are set for all
internal audit engagements and include Renfrewshire Council and other associated
bodies, for which the team provides internal audit services. Table 3 shows the actual
performance against targeted performance for the year. 
Table 3 
Internal Audit Performance 2025/26
Performance measure  Target 2025/26 Actual 2025/26
% of audit assignments          completed
by target date
95% 98.3%
% of audit assignments completed within
time budget
95% 98.3%
% completion of audit plan for the year* 90% 90.1%
* this measures the completion percentage as at 31 March. 100% of the plan is
ultimately delivered through the finalisation of the outstanding elements in the new
financial year.  
5.2 The percentage completion of the audit plan met target set for the year. It should be
noted that the planned review for the RVJB for 2025/26 is 100% complete. The actual
performance for the year for the two other indicators is above the target performance
level.
Page 28 of 120

Page 29

- 5 - 
5.3 The Assistant Chief Auditor was appointed permanently to the post of Chief Auditor
in August 2025 and one of the Senior Auditors is covering the Assistant Chief
Auditors post on an interim basis.  In addition, the Senior Counter Fraud Officer post
is currently vacant due to the retiral of the previous post holder. 
5.4 It was recognised that there have been difficulties in recruiting Internal Auditors
recently within some other Local Authorities and it was agreed that as the
opportunity has arisen,  the Chief Auditor in conjunction with the Director of Finance
and Resources  would carry out a review to determine the staffing and skillset
required to deliver an adequate and efficient Internal Audit and Counter Fraud
Service, taking into consideration future corporate plans and priorities and  workforce
and resilience planning issues.  
5.5 This revised structure has been agreed upon and we are currently in the process of
implementing this revised structure  with the assistance of HR staff.  It has been
designed to give current and new staff the opportunity to further develop their skills
and study for a professional qualification.  The number of staff will remain
unchanged and it is planned to recruit a  trainee internal auditor.   
5.6 Due to the vacancies being carried, this has been a challenging year for the Internal
Audit Service and some of our developmental and administration work has been
carried forward into 2026/27 to enable priority to be given to operational reviews.
Some of the available resources have also been used to cover some counter fraud
tasks.  The service had adequate financial resources which can be used flexibly and
was utilised for some staff overtime to ensure  adequate operational work was
undertaken to enable the Chief Auditor to provide their assurance opinion on the
internal control environment in operation. It is therefore considered that the team has
been sufficiently resourced during the year to undertake the operational work
required. 
6. Planned Work for 2026/27 
6.1 Following a risk-based assessment of the activities of the Renfrewshire Valuation
Joint Board, the audit plan for 2026/2027 provides for a review of payroll processes,
preparation of an annual report, ad-hoc internal control advice, reactive investigative
work and a follow-up of previous audits recommendations.  
7. Audit Assurance Statement 
7.1 Internal Audit has performed its work in accordance with the role defined in
paragraph 1.2.  The audit work performed has been reported to the Assessor and
Electoral Registration Officer, and to the Board. Where areas for improvement in
internal control have been identified appropriate recommendations have been made
and accepted for action by management.  
7.2 In view of the continued challenges common to all public bodies, there will be a
requirement for the council and the bodies for which it is host authority to exercise
very close scrutiny over expenditure, financial management and compliance with
overarching governance arrangements, and these areas will continue to receive due
internal audit attention.   
Page 29 of 120

Page 30

- 6 -
7.3 It is not realistic for the system of internal control to be without any weakness. It is
important to balance the risks involved in accepting systems limitations with the
consequences if a problem emerges. Internal Audit recognises this and assesses this
in its reporting mechanism. 
7.4 There are corporate systems and processes within Renfrewshire Council that the
Renfrewshire Valuation Joint Board relies upon. It can be seen from Table 1 & 2
above that some actions were recommended to improve the processes in operation.
Renfrewshire Valuation Joint Board and Renfrewshire Council management have
agreed to implement the recommendations made by internal audit, in relation to
these reviews. 
7.5 In this context, it is considered that reasonable assurance can be placed upon the
adequacy and effectiveness of the Renfrewshire Valuation Joint Board’s internal
control, risk management and governance arrangements, as evidenced by: - 
• The results of the audit work in 2025/26 in relation to the corporate      
systems which supported the Renfrewshire Valuation Joint Board’s activities,
and to specific work carried out in relation to those activities. 
• Management action in response to audit recommendations. 
• Management’s self-assessment of internal control, risk management and
governance arrangements. 
• The regular review and updating of the Local Code of Corporate Governance
by the Council in accordance with the CIPFA/SOLACE framework for
corporate governance requirements, and of the corporate governance
arrangements within Renfrewshire Valuation Joint Board. 
Page 30 of 120

Page 31

PUBLIC
AGENDA ITEM NO..... 
Scotland Excel 
To: Executive Sub-committee 
On: 19 June 2026
Report 
by 
Chief Auditor 
Internal Audit Engagement – Contract Delivery Plan 
1. Summary
1.1 In line with the Public Sector Internal Audit Standards, Internal Audit
must communicate the results of each engagement to the Board. 
1.2 The Chief Auditor will report summaries of completed audit
engagements to the Executive Sub Committee on the conclusion of
each engagement for formal consideration by members in line with the
best practice referred to above.   
1.3 This report provides detail of the audit engagement completed in
2025/26 with the overall assurance rating and the number of
recommendations in each risk category. The detailed committee
summary for the engagement is also attached. 
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to consider and note the summary for the Internal Audit
engagement reviewing the governance arrangements in terms of the contract
delivery planning process to ensure defined milestones are adhered to when
contracts are being established. 
___________________________________________________________________
Page 31 of 120

Page 32

PUBLIC
Appendix 1 
Scotland Excel 
Internal Audit Service 
Summary of Internal Audit Reports issued 
Category  Engagement  Assurance
Rating
Recommendation Ratings
Critical Important Good
Practice
Service
Improvement
Assurance Contract
Delivery Plan 
Substantial 0 0 1 0 
.
Assurance Level 
Substantial
Assurance
• There is a sound system of internal control designed to achieve the
objectives of the area being reviewed. 
• The control processes tested are being consistently applied. 
Reasonable
Assurance
• The internal control processes are generally satisfactory with some
areas of weakness being identified that could put some objectives of
the area being reviewed at risk
• There is evidence that the level of non-compliance with some of the
control processes may put some of the objectives of the area being
reviewed at risk. 
Limited Assurance • Weaknesses in the system of internal controls are such as to put the
objectives of the area being reviewed at risk. 
• The level of non-compliance puts the objectives of the area being
reviewed at risk. 
No Assurance • Control processes are generally weak with significant risk to the
achievement of the objectives of the area being reviewed. 
• Significant non-compliance with control processes leaves the
processes/systems open to error or abuse. 
Recommendation
Rating 
Service Improvement  Implementation will improve the efficiency / housekeeping of the area
under review.
Good Practice  Implementation will contribute to the general effectiveness of control.
Important  Implementation will raise the level of assurance provided by the
control system to acceptable levels.
Critical  Addresses a significant risk, impacting on the objectives of the area
under review. 
Page 32 of 120

Page 33

PUBLIC
Internal Audit Report
Scotland Excel
Contract Delivery Plan
(A0008/2025/010)
July 2025
Audit Objectives
A review of   the governance arrangements in terms of the contract delivery plan was undertaken
to ensure it  was being progressed as planned. The objective of the review was to ensure that
there are adequate governance arrangements in place for a sample of defined milestones in the
procurement process to ensure they are achieved and appropriate evidence is maintained to
support these arrangements. 
Audit Scope
1. Interviewed the appropriate officers to obtain the required information relating to relevant
procedures and guidance. 
2. Selected a sample of milestones for review to ensure that adequate governance
arrangements are in place. The auditor selected the following milestones, that are
required to be approved by the Contract Steering Group, from the Governance Gateways
and Contract Steering Group Approval Policy and Process: 
a) Approval for Participation and Benchmarking and Sustainable Procurement Duty; 
b) Evaluation Methodology and Weightings Approved; 
c) Recommendation and Benchmarking Approved; 
d) Executive Sub Committee Report Approved 
3. The auditor tested whether there was evidence to demonstrate that these milestones
were achieved and approved by the Contract Steeing Group SG for a sample of contracts 
selected from the Contract Delivery Plan. 
Key Audit Assurances
For the sample of milestones and contracts tested, adequate governance arrangements were
in place and there was evidence that each milestone had been achieved. 
Key Risks
No key risks were identified during the audit. 
Overall Audit Opinion
There were adequate governance arrangements in place for the sample of governance gateway
milestones and contracts tested. However, minor improvements could be made regarding
recording confirmation that all other prior Gateway approvals by relevant officers have been
received. 
Management Commentary
The recommendation made was implemented.  Checklists have been developed and form part
of the contract documentation to evidence that all required approvals have been obtained.  In
Page 33 of 120

Page 34

PUBLIC
addition, a process to track action agreed at the Contact Steering Group has been introduced.
This Referral Form tracks actions and approvals from defined signatories at each gateway. 
Page 34 of 120

Page 35

AGENDA ITEM NO..... 
Scotland Excel 
To: Executive Sub-Committee 
On: 19 June 2026
Report 
by 
Chief Auditor   
INTERNAL AUDIT ANNUAL REPORT 2025/26 
1. Summary 
1.1 The Global Internal Audit Standards in the UK Public Sector require the Chief
Auditor to prepare a report, at least annually, to senior management and the Board
on the internal audit activity’s purpose, authority, and responsibility, as well as
performance relative to its plan. 
1.2 The annual report must also provide an annual audit opinion on the overall
adequacy and effectiveness of Scotland Excel’s internal control environment. 
1.3 The Annual Report for Scotland Excel is attached at Appendix 1 and outlines the
role of Internal Audit, the performance of the Internal Audit Team, the main findings
from the internal audit work undertaken in 2025/26 and contains an audit
assurance statement.   
2. Recommendations 
2.1 Members are invited to consider and note the contents of the Internal Audit Annual
Report. 
Page 35 of 120

Page 36

No embedded text on this page.

Page 37

PUBLIC 
Scotland Excel
Internal Audit Annual Report 
2025/2026 
Renfrewshire Council
Internal Audit 
Page 37 of 120

Page 38

PUBLIC 
Scotland Excel 
Internal Audit Annual Report 2025/2026 
Contents 
Page 
1.    Introduction  1 
2.  Global Internal Audit Standards in the UK Public Sector  1 
3.  Responsibilities of Management and Internal Audit  2 
4.    Internal Audit Activity during 2025/26  2 
5.                                                                            Review of Internal Audit Performance    4 
6.  Planned Audit Work for 2026/27  5 
7.  Audit Assurance Statement  5 
Page 38 of 120

Page 39

- 1 -
PUBLIC
Scotland Excel 
Internal Audit Annual Report   
1 April 2025 – 31 March 2026 
1. Introduction 
1.1 As host Authority, Renfrewshire Council provides an internal audit service to
Scotland Excel. This includes: 
• The compilation of an annual audit plan following consideration and
evaluation of those areas of greatest risk in the organisation’s
operation, and consultation with the Chief Executive and other Senior
Management Team Members; 
• Delivery of the planned audit assignments;
• Follow up of previous audit recommendations;
• Provision of any ongoing advice and support on audit and risk
management related matters;
• Provision of an Annual Report and Assurance Statement, and
presentation to elected members of Scotland Excel. 
1.2 The Internal Audit Section is an independent and objective assurance and
advisory service designed to add value and improve the operations of
Renfrewshire Council and its Partners. It assists Scotland Excel in
accomplishing its objectives by bringing a systematic and disciplined approach
to evaluate and improve the effectiveness of the organisation's risk
management, control, and governance processes and enhances Scotland
Excel’s decision making and oversight arrangements.  
1.3 In line with the Standards, the purpose of this Annual Report is to report on: 
• The status/outcome of the completed Internal Audit reviews 2025/26
relating to Scotland Excel; 
• The outcome of Internal Audit reviews of supporting Renfrewshire
Council corporate systems;
• Internal audit performance; 
• Planned audit work for 2026/27;
• The annual assurance statement which provides an opinion on the
overall adequacy and effectiveness of the organisation’s internal control
environment. 
2.        Global Internal Audit Standards in the UK Public Sector 
2.1    At the start of 2025/26, new Public Sector Internal Audit Standards “Global
Internal Audit Standards in the UK Public Sector” came into force. These
Standards require the Chief Auditor to develop and maintain a quality
assurance and improvement programme (QAIP) that covers all aspects of the
Page 39 of 120

Page 40

- 2 -
PUBLIC
internal audit activity. The QAIP must include ongoing monitoring of compliance
with the standards, periodic internal self-assessments and five-yearly external
assessments, carried out by a qualified, independent assessor from outwith the
organisation. 
2.2  With regards to the ongoing monitoring to ensure compliance, the work
undertaken during an assignment is reviewed by a senior audit team member. 
2.3  The Chief Auditor undertook a self-assessment exercise to determine what
actions were required to ensure compliance. The conclusion of this exercise
was that in the main, Internal Audit complied with the spirit of the standards but
required to undertake some actions throughout the year to achieve full
compliance or enhance the processes already in place.  The main actions were
to update the Internal Audit Charter and Mandate and ensure staff were fully
trained as to the requirements of the new standards. 
2.4  These actions have been completed. Staff training sessions were held during
the year and a revised Internal Charter and Mandate was prepared and is
attached at Appendix 1. A further formal self-assessment is planned for the
forthcoming year. 
3.       Responsibilities of Management and Internal Audit 
3.1 It is the responsibility of management to ensure that for the areas under their
control there is an adequate and effective system of internal control which
facilitates the effective exercise of the organisation’s functions and which
includes arrangements for the management of risk. 
3.2 Internal Audit is not a substitute for effective control exercised by management
as part of their responsibilities. Internal Audit’s role is to independently assess
the adequacy of the risk management, internal controls and governance
arrangements put in place by management and to undertake sufficient work to
evaluate and conclude on the adequacy of those controls for the period under
review. 
3.3 The internal audit team ensured that independence and objectivity are
maintained in line with the Global Internal Audit Standards in the UK Public
Sector including where non-audit work is undertaken. Internal auditors have no
operational responsibilities. There have been no impairments impacting on the
Chief Auditor’s independence. 
4         Internal Audit Activity during 2025/26 
4.1 An engagement reviewing the methodoloy employed by Scotland Excel  to
identify, calculate, measure and report the value it provides to members in the
Annual Value Report  has been completed and is currently being reviewed by
Internal Audit Management prior to a draft report being issued to Scotland
Excel’s Senior Management. 
Page 40 of 120

Page 41

- 3 -
PUBLIC
4.2 The internal audit engagement reviewing the governance arrangements
surrounding the Contract Delivery Plan was completed. A summary of this
report was considered by the Executive Sub-Committee on 19 June 2026. And
the conclusion of this review is summarised in Table 1 below.
Table 1 
Audit Area Conclusion
Contract Delivery Plan Substantial Assurance
There were adequate governance
arrangements in place for the sample of
governance gateway milestones and contracts
tested. However, minor improvements could be
made regarding recording confirmation that all
other prior Gateway approvals by relevant
officers have been received. 
4.3 The Annual Report for 2024/25 was submitted to the Executive Sub-committee
on 20 June 2025. 
4.4 The implementation rate of audit recommendations is a measure of operational
culture and effectiveness. During 2025/26, there was one recommendation that
required to be followed up and it was fully implemented. 
4.5 Internal Audit also carried out reviews of the main corporate systems operating
within Renfrewshire Council which support Scotland Excel’s activity. The main
findings in relation to these are summarised in Table 2 below and Renfrewshire
Council management have agreed to implement the audit recommendations
made in relation to each review: 
Table 2 
Audit Area Conclusion
Financial Planning Substantial Assurance 
The arrangements in place for financial
planning were found to be robust.
Assumptions and financial risks related to
cost pressures were reported to the
Council. 
Main Financial Systems – Key
Controls
Limited Assurance 
The audit identified that satisfactory
controls are in place for system
documentation and budget monitoring
across the main financial systems. 
Some control weaknesses were identified
in relation to segregation of duties and in
relation to reconciliation of feeder
Page 41 of 120

Page 42

- 4 -
PUBLIC
systems. In addition, there was a
substantial backlog of unresolved
Accounts Receivable transactions in the
ERP system, with systemic workflow and
error-handling issues which required
management attention. 
5.      Review of Internal Audit Performance 
5.1 Internal Audit produces regular reports on its performance during the year to
the Renfrewshire Council, Audit, Risk and Scrutiny Board, against a range of
measures set annually by the Director of Finance and Resources. These
targets are set for all internal audit engagements and include Renfrewshire
Council and other associated bodies, for which the team provides internal audit
services. Table 3 shows the actual performance against targeted performance
for the year. 
Table 3 
Internal Audit Performance 2025/26
Performance measure  Target 2025/26 Actual 2025/26
% completion of audit plan for the
year*
90% 90.1%
% of audit assignments completed
within time budget
95% 98.3%
% of audit assignments         
completed by target date
95% 98.3%
* this measures the completion percentage as at 31 March. 100% of the plan is ultimately delivered through
the finalisation of the outstanding elements in the new financial year.  
5.2 The percentage completion of the audit plan met target set for the year. It should
be noted that the planned reviews for Scotland Excel for 2025/26 will be fully
completed by 30 June 2026. The actual performance for the year for the two
other indicators is above the target performance level. 
5.3 The Assistant Chief Auditor was appointed permanently to the post of Chief
Auditor in August 2025 and one of the Senior Auditors is covering the Assistant
Chief Auditors post on an interim basis. In addition, the Senior Counter Fraud
Officer post is currently vacant due to the retiral of the previous post holder. 
5.4 It was recognised that there have been difficulties in recruiting Internal Auditors
recently within some other Local Authorities and it was agreed that as the
opportunity has arisen,  the Chief Auditor in conjunction with the Director of
Finance and Resources  would carry out a review to determine the staffing and
skillset required to deliver an adequate and efficient Internal Audit and Counter
Page 42 of 120

Page 43

- 5 -
PUBLIC
Fraud Service, taking into consideration future corporate plans and priorities
and  workforce and resilience planning issues.   
5.5 This revised structure has been agreed upon and we are currently in the
process of implementing this revised structure  with the assistance of HR staff.
It has been designed to give current and new staff the opportunity to further
develop their skills and study for a professional qualification. The number of
staff will remain unchanged and it is planned to recruit a  trainee internal auditor. 
5.6 Due to the vacancies being carried, this has been a challenging year for the
Internal Audit Service and some of our developmental and administration work
has been carried forward into 2026/27 to enable priority to be given to
operational reviews. Some of the available resources have also been used to
cover some counter fraud tasks.  The service had adequate financial resources
which can be used flexibly and was utilised for some staff overtime to ensure 
adequate operational work was undertaken to enable the Chief Auditor to
provide their assurance opinion on the internal control environment in
operation. It is therefore considered that the team has been sufficiently
resourced during the year to undertake the operational work required. 
5.7 The Counter Fraud Section of the team have mainly been working on referrals
received from various internal and external sources and investigation of
National Fraud Initiative Data Matches received from the Cabinet Office 
6.      Planned Audit Work for 2026/27 
6.1 Following a risk-based assessment of the activities of Scotland Excel and
consultation with the Chief Executive and other Senior Management Team
Members, the following internal audit work has been agreed for 2026/27: 
• A review of the governance arrangements for services provided to
external organisations; 
• Follow up of previous audit work;
• Ad-hoc internal audit and risk management advice
• Annual Reporting. 
7.      Audit Assurance Statement 
7.1 Internal Audit has performed its work in accordance with the role defined in
paragraph 1.2.  The audit work performed and completed has been reported to
the Chief Executive and to the Executive Sub Committee. Where areas for
improvement in internal control have been identified appropriate
recommendations have been made and accepted for action by management. 
7.2 In view of the continued challenges common to all public bodies, there will be
a requirement for the council and the bodies for which it is host authority to
exercise very close scrutiny over revenue spending, over financial
management and compliance with overarching governance arrangements, and
this will continue to receive due internal audit attention.  
Page 43 of 120

Page 44

- 6 -
PUBLIC
7.3 It is not realistic for the system of internal control to be without any weakness.
It is important to balance the risks involved in accepting systems limitations with
the consequences if a problem emerges. Internal Audit recognises this and
assesses this in its reporting mechanism. 
7.4 There are corporate systems and processes within Renfrewshire Council that
Scotland Excel rely upon. It can be seen from Table 2 above that some actions
were recommended to improve the processes in operation. Renfrewshire
Council management has agreed to implement the recommendations made by
internal audit, in relation to these reviews. In this context, it is considered that
reasonable assurance can be placed upon the adequacy and effectiveness of
Scotland Excel Joint Committee’s internal control, risk management and
governance arrangements, as evidenced by: -  
• The results of the audit work in 2025/26 in relation to the corporate      
systems which supported Scotland Excel’s activities and to specific work
carried out in relation to those activities. 
• Management action in response to audit recommendations. 
• Management self-assessment of internal control, risk management and
governance arrangements. 
• The regular review and updating of the Local Code of Corporate
Governance by the Council in accordance with the Chartered Institute of
Public Finance and Accountancy and Society of Local Authority Chief
Executives framework for corporate governance requirements, and of
the corporate governance arrangements within Scotland Excel. 
Chief Auditor     
19 June 2026
Page 44 of 120

Page 45

PUBLIC 
To: Renfrewshire Integration Joint Board Audit, Risk and Scrutiny Committee
On: 12 June 2026 
Report by:  Chief Internal Auditor 
Heading: Summary of Internal Audit Reports 
1.   Summary
1.1 A risk based Internal Audit Plan for 2025/26 was approved by the IJB Audit
Committee on 14 March 2025. In line with the Global Internal Audit Standards
in the UK Public Sector, Internal Audit must communicate the results of each
engagement to the Board. 
1.2 Appendix 1 provides details of the completed audit engagement reviewing the
Strategic Plan process along with the overall assurance rating and the number
of recommendations in each risk category. The committee summary is also
attached at Appendix 2.                                                                                                                                                                                                                                                                                                                                                     
2.   Recommendations
2.1 That the Integration Joint Board Audit, Risk and Scrutiny Committee are asked to note
the content of the report. 
Implications of the Report
1. Financial - none. 
2. HR & Organisational Development - none. 
3. Community Planning - none. 
4. Legal - none. 
Page 45 of 120

Page 46

PUBLIC
5. Property/Assets - none. 
6. Information Technology - none. 
7. Equality & Human Rights - none 
8. Health & Safety - none. 
9. Procurement - none. 
10. Risk - The subject matter of this report related to the delivery of the risk-based Audit Plan
for the IJB. 
11. Privacy Impact - none. 
List of Background Papers – none. 
Author:   Karen Campbell, Chief Internal Auditor 
Page 46 of 120

Page 47

PUBLIC 
Appendix 1 
Integration Joint Board Audit, Risk and Scrutiny Committee 
Internal Audit Service 
Summary of Final Audit Reports Issued 
Engagement  Assurance Rating  Recommendation Ratings
Critical Important Good
Practice
Service
Improvement
Review of the Strategic
Plan Process
Reasonable 0 1 2 1 
.
Assurance Level 
Substantial
Assurance
• There is a sound system of internal control designed to achieve the
objectives of the area being reviewed. 
• The control processes tested are being consistently applied. 
Reasonable
Assurance
• The internal control processes are generally satisfactory with some areas
of weakness being identified that could put some objectives of the area
being reviewed at risk.
• There is evidence that the level of non-compliance with some of the
control processes may put some of the objectives of the area being
reviewed at risk. 
Limited Assurance • Weaknesses in the system of internal controls are such as to put the
objectives of the area being reviewed at risk. 
• The level of non-compliance puts the objectives of the area being
reviewed at risk. 
No Assurance • Control processes are generally weak with significant risk to the
achievement of the objectives of the area being reviewed. 
• Significant non-compliance with control processes leaves the
processes/systems open to error or abuse. 
Recommendation
Rating 
Service Improvement  Implementation will improve the efficiency / housekeeping of the area under
review.
Good Practice  Implementation will contribute to the general effectiveness of control.
Important  Implementation will raise the level of assurance provided by the control
system to acceptable levels.
Critical  Addresses a significant risk, impacting on the objectives of the area under
review. 
Page 47 of 120

Page 48

PUBLIC
Appendix 2    Internal Audit Report
IJB
Review of the Strategic Plan Process (A0114/2026/001)
Date:  March 2026 
COMMITTEE SUMMARY
Audit Objectives
The objectives of the audit were to: - 
1. Determine the arrangements in place for refreshing the Strategic Plan and assess for
adequacy. 
2. Confirm that the Strategic Plan has been refreshed in line with legislative requirements. 
3. Ensure that stakeholders were sufficiently engaged during the preparation, publication
and review stages of the refresh and this is reflected in the Plan. 
4. Ascertain the monitoring and reporting arrangements in place for the delivery of the
Plan’s objectives and review these for adequacy. 
Audit Scope
1. Interviewed the appropriate officers to ascertain the arrangements in place for the
Strategic Plan refresh and to establish available evidence. 
2. Prepared and carried out a programme of tests to enable the audit objectives to be met. 
Key Audit Assurances
1. The Strategic Plan refresh process was supported by documented action plans and
active oversight through Strategic Planning Group meetings. 
2. Consultation activity was robust, using multiple engagement methods, and feedback was
clearly documented and incorporated into the final Strategic Plan. 
3. Performance monitoring arrangements were in place, with management oversight at
regular operational team meetings. Performance Managers plan to provide the first 6
monthly update relating to the refreshed Strategic Plan, supported by dashboards, to the
SMT in the near future as well as annual reporting to the Integration Joint Board. 
Key Audit Risks
By not complying with the Statutory Guidance in relation to locality arrangements and
publishing a Consultation Statement, stakeholders may not have sufficient information to fully
challenge Strategic Plan outcomes. 
Overall Audit Opinion
The audit found that the Strategic Plan refresh process was well-governed, supported by
effective consultation, had established performance monitoring arrangements, and was
broadly aligned with statutory guidance.   The main areas identified for improvement relate to 
Page 48 of 120

Page 49

PUBLIC
the inclusion of localities, publication of a Consultation Statement and production of a Joint
Strategic Needs Assessment (JSNA).  Recommendations were also made to enhance the
monitoring arrangements. 
Management Commentary
These areas are being addressed.  IJB Officers are working with Renfrewshire Council and
Community Planning colleagues to develop a joint approach to locality planning. These
discussions are underway and may result in a change to the number of localities reflected
within the next Strategic Plan.  IJB Management will also work with partners to develop an
updated Joint Strategic Needs Assessment aligning with development of the IJB’s Strategic
Plan, the Council Plan and Community Plan  Whilst, the contents of a consultation statement
were included in both the refreshed Strategic Plan 2025-27 and the supporting cover paper
considered by the IJB,  the HSCP will publish a separate consultation statement alongside the
next Strategic Plan. 
Page 49 of 120

Page 50

No embedded text on this page.

Page 51

PUBLIC 
To: Renfrewshire Health and Social Care Integration Joint Board Audit, Risk
and Scrutiny Committee 
On: 12 June 2026 
Report by:  Chief Internal Auditor 
Heading:  Internal Audit Annual Report 2025/2026 
1.   Summary
1.1 The Global Internal Audit Standards in the UK Public Sector which were in
operation during 2025/26 requires that the Chief Internal Auditor must deliver an
annual internal audit opinion, on the overall adequacy and effectiveness of the
governance, risk management and internal control framework, that can be used
by the organisation to inform its governance statement. 
1.2 The purpose of this report is to advise the Committee of the Internal Audit Annual
Report including the annual opinion. The Internal Audit Annual Report also outlines
the internal audit work we have carried out for the year ended 31 March 2026 and
provides details of the performance of Internal Audit. 
1.3 The report attached, includes the Chief Internal Auditor’s independent and
objective opinion as to the adequacy and effectiveness of the internal control
environment. In forming the opinion, the Chief Internal Auditor has conducted a
review of the Internal Audit reports issued to the IJB in the year and the internal
audit annual report from Renfrewshire Council and internal audit progress reports
from NHS Greater Glasgow and Clyde.                                                                                                                                                                                                                                                                                                                                                     
2.   Recommendations
2.1 Members are asked to consider and note the contents of the IJB’s Internal Audit Annual
Report for 2025/26. 
Page 51 of 120

Page 52

PUBLIC
Implications of the Report
1. Financial - none 
2. HR & Organisational Development - none. 
3. Community Planning - none. 
4. Legal - none. 
5. Property/Assets - none. 
6. Information Technology - none. 
7. Equality & Human Rights - none 
8. Health & Safety - none. 
9. Procurement - none. 
10. Risk - The report provides an opinion on the overall internal control environment including
governance and risk management of the Integration Joint Board. 
11. Privacy Impact - none. 
List of Background Papers – none. 
Author:   Karen Campbell, Chief Internal Auditor
Page 52 of 120

Page 53

PUBLIC 
Renfrewshire Integration Joint
Board 
Internal Audit Annual Report 
2025-2026 
June 2026  
Page 53 of 120

Page 54

PUBLIC  
Page 54 of 120

Page 55

PUBLIC 
Renfrewshire Integration Joint Board 
Internal Audit Annual Report 2025/2026 
Contents 
Page 
1.    Introduction  1
2. Responsibilities of Management and Internal Audit 2 
3.    Internal Audit Activity in 2025/26  2 
4.                                                                            Review of Internal Audit Performance and Improvement Activity    2 
5.  Planned Audit Work for 2026/27  4 
6.  Audit Assurance Statement  4 
Appendix 1 – Summary of Assurances  6 
Page 55 of 120

Page 56

- 1 -
PUBLIC
Renfrewshire Integration Joint Board 
Internal Audit Annual Report   
1 April 2025 – 31 March 2026 
1. Introduction 
1.1 Renfrewshire Council provides an internal audit service to the Renfrewshire
Health and Social Care Integration Joint Board (IJB).  This includes: 
• The compilation of an annual audit plan following consideration 
and evaluation of those areas of greatest risk in the organisation’s
operation, and consultation with the Chief Officer and Senior
Management;
• Delivery of the planned audit assignments;
• Follow up of previous audit recommendations;
• Provision of any ongoing advice support and training on audit and
risk related matters;
• Provision of an Annual Report and Assurance Statement to the IJB. 
1.2 The Service operates in accordance with the Global Internal Audit Standards in
the UK Public Sector for 2025/26.  Internal Audit’s is an independent, objective
assurance and consulting activity designed to add value and improve an
organisation’s operations. It assists an organisation in accomplishing its
objectives by bringing a systematic, disciplined approach to evaluate and
improve the effectiveness of the organisation’s risk management, control and
governance processes. 
1.3 In line with the Standards, the purpose of this Annual Report is to report on: 
• The outcome of the planned Internal Audit reviews 2025/26 relating to
the IJB;
• The outcome of Internal Audit reviews undertaken by partner bodies;
• Internal audit performance; 
• Planned audit work for 2026/27;
• The annual assurance statement which provides an opinion on the
overall adequacy and effectiveness of the IJB’s internal control
environment. 
1.4 The operational delivery of services within the Health Board and Local Authority
on behalf of the Integration Joint Board will be covered by their respective
internal audit arrangements. In concluding on the overall opinion, the Chief
Internal Auditor has conducted a review of the internal audit reports issued to
the IJB in the year, the internal audit annual report from Renfrewshire Council
and progress summaries from NHS Greater Glasgow and Clyde. (Appendix 1). 
Page 56 of 120

Page 57

- 2 -
PUBLIC
2. Responsibilities of Management and Internal Audit 
2.1 It is the responsibility of IJB management to ensure that the areas under their
control are adequate and effective and that there is a sound system of internal
control which facilitates the effective exercise of the organisation’s functions
and which includes arrangements for the management of risk. 
2.2 Internal Audit is not a substitute for effective control exercised by management
as part of their responsibilities. Internal Audit’s role is to independently assess
the adequacy of the risk management, internal controls and governance
arrangements put in place by management and to undertake sufficient work to
evaluate and conclude on the adequacy of those controls for the period under
review. 
3. Internal Audit Activity during 2025/2026 
3.1 The Internal Audit Plan for the IJB for 2025/2026 provided for a review of the
strategic planning arrangements and the annual review of the adequacy and
compliance with the Local Code of Corporate Governance. (Appendix 1). The
Corporate  Governance review was reported to the IJB Audit, Risk and Scrutiny
Committee in March 2026 and the Strategic Planning review was reported in
June 2026. 
3.2 The Annual Report for 2024/2025 was submitted to the Integration Joint Board
on 20 June 2025. 
3.3 The implementation rate of audit recommendations is a measure of operational
culture and effectiveness.  During 2025/26, one recommendation was followed
up and found to be fully implemented. 
4. Review of Internal Audit Performance  and Improvement Activity 
4.1 Internal Audit produces regular reports on its performance during the year to
Renfrewshire Council’s Audit, Risk and Scrutiny Board, against a range of
measures set annually by Renfrewshire Council’s Director of Finance and
Resources. These targets are set for all internal audit engagements and include
Renfrewshire Council and other associated bodies, for which the team provides
internal audit services. Table 1 shows the actual performance against targeted
performance for the year. 
Table 1 
Internal Audit Performance 2025/26 
Performance measure  Target 2025/26 Actual 2025/26
% completion of audit plan for the year* 90% 90.1%
% engagements completed by target
date
95% 98.3%
% engagements completed within time
budget
95% 98.3%
Page 57 of 120

Page 58

- 3 -
PUBLIC
* This measures the completion percentage as at 31 March.  100% of the plan is ultimately delivered through the
finalisation of the outstanding elements in the new financial year.  
4.2 The percentage completion of the audit plan met the target set for the year.  In
addition, the actual performance for the year for the two other indicators is
above the target performance level.  It should be noted that the Internal Audit
Plan for the IJB for 2025/26 is 100% complete.   
4.3 The Assistant Chief Auditor was appointed permanently to the post of Chief
Auditor in August 2025 and one of the Senior Auditors is covering the Assistant
Chief Auditors post on an interim basis. In addition, the Senior Counter Fraud
Officer post is currently vacant due to the retiral of the previous post holder. 
4.4 It was recognised that there have been difficulties in recruiting Internal Auditors
recently within some other Local Authorities and it was agreed that as the
opportunity has arisen, the Chief Auditor in conjunction with the Director of
Finance and Resources would carry out a review to determine the staffing and
skillset required to deliver an adequate and efficient Internal Audit and Counter
Fraud Service, taking into consideration future corporate plans and priorities
and workforce and resilience planning issues. 
4.5 This revised structure has been agreed upon and we are currently in the
process of implementing this revised structure with the assistance of HR staff.
It has been designed to give current and new staff the opportunity to further
develop their skills and study for a professional qualification. The number of
staff will remain unchanged and it is planned to recruit a trainee internal auditor. 
4.6 Due to the vacancies being carried, this has been a challenging year for the
Internal Audit Service and some of our developmental and administration work
has been carried forward into 2026/27 to enable priority to be given to
operational reviews. Some of the available resources have also been used to
cover some counter fraud tasks. The service had adequate financial resources
which can be used flexibly and was utilised for some staff overtime to ensure
adequate operational work was undertaken to enable the Chief Auditor to
provide their assurance opinion on the internal control environment in
operation. It is therefore considered that the team has been sufficiently
resourced during the year to undertake the operational work required. 
4.7 The Global Internal Audit Standards in the UK Public Sector require the Chief
Auditor to develop and maintain a quality assurance and improvement
programme (QAIP) that covers all aspects of the internal audit activity. The
QAIP must include ongoing monitoring of compliance with the standards, 
periodic internal self-assessments and five-yearly external assessments,
carried out by a qualified, independent assessor from outwith the organisation. 
4.8 With regards to the ongoing monitoring to ensure compliance, the  work
undertaken during an assignment is  reviewed by a senior audit team member. 
4.9 We undertook a self-assessment against these new standards and reported the
results and required actions to the Audit, Risk and Scrutiny Committee in
Page 58 of 120

Page 59

- 4 -
PUBLIC
September 2025.  An updated Charter and Mandate was approved by the
Committee in November 2025 and staff training on the revised standards has
also been undertaken. It is now considered that Internal Audit comply with the
standards.  A further formal self-assessment is planned for the forthcoming year
and the outcomes will be reported to the Audit, Risk and Scrutiny Committee.   
4.10 We continued to participate in the Scottish Local Authorities Chief Internal
Auditors’ Group peer review process and our next external assessment is not
due until 2028/29. 
5. Planned Work for 2026/27 
5.1 Following a risk-based assessment of the activities of the IJB and consultation
with the senior management team, the Internal Audit Plan for 2026/27 provides
for 42 days of Internal Audit resource to undertake: 
• A review of Clinical Governance; and 
• The annual review of the adequacy and effectiveness of the Local Code
of Corporate Governance. 
5.2 The plan also provides time for planning and reporting, follow up on previous
recommendations, the annual self-assessment of the Audit Committee
arrangements, ad-hoc advice, consultancy and training. The Internal Audit Plan
for 2026/27 was approved by the IJB Audit, Risk and Scrutiny Committee on 20
March 2026. 
6. Audit Assurance Statement 
6.1 The audit work performed in relation to the 2025/26 internal audit plan has been
reported to the Chief Officer and the Audit, Risk and Scrutiny Committee.
Relevant audit work undertaken by partner organisations is reported to their
respective Audit Committees. Where areas for improvement in internal control
have been identified, appropriate recommendations have been made and
accepted for action by management.   
6.2 There are no significant matters arising in relation to those audit engagements
specific to the IJB and there have been no impairments impacting on the Chief
Auditor’s independence and the team has been sufficiently resourced during
the year to undertake the planned assignments. 
6.3 In view of the continued challenges common to all public bodies, there will be
a requirement for the council and the bodies for which it is host authority to
exercise very close scrutiny over expenditure, over financial management and
compliance with overarching governance arrangements, and this area will
continue to receive due internal audit attention. 
6.4 It is not realistic for the system of internal control to be without any weakness. 
It is important to balance the risks involved in accepting systems limitations with
Page 59 of 120

Page 60

- 5 -
PUBLIC
the consequences if a problem emerges. Internal Audit recognises this and
assesses this in its reporting mechanism.  
6.5 There are corporate systems and processes within Renfrewshire Council and
NHS Greater Glasgow and Clyde that the IJB rely upon. It can be seen from
Appendix 1 that some of these processes require to be improved to provide a
reasonable level of assurance. 
6.6 In this context, it is considered that a reasonable level of assurance can be
placed upon the adequacy and effectiveness of the Integration Joint Board’s
internal control, risk management and governance arrangements, as evidenced
by:- 
• The results of the audit work in 2025/26 and the opinions contained in
the Internal Audit Annual Reports of the Local Authority and progress
reports from the Health Board. 
• Management self-assessment of internal control, risk management and
governance arrangements. 
• Management action to respond to audit recommendations. 
Karen Campbell             
Chief Internal Auditor     
12 June 2026. 
Page 60 of 120

Page 61

- 6 -
PUBLIC  
Appendix 1 
Summary of Internal Audit Assurances for the IJB and Partner Organisations,
Renfrewshire Council and NHS Greater Glasgow and Clyde 
Integration Joint Board
Audit Engagement Assurance
Level
Significant Matters
Local Code of Corporate
Governance
Substantial • None
Strategic Planning Reasonable • The audit found that the Strategic Plan
refresh process was well-governed,
supported by effective consultation, had
established performance monitoring
arrangements, and was broadly aligned
with statutory guidance.   The main areas
identified for improvement relate to the
inclusion of localities, publication of a
separate Consultation Statement and
production of a Joint Strategic Needs
Assessment (JSNA) to full comply with
the guidance.
Renfrewshire Council
Audit Engagement Assurance
Level
Significant Matters
Housing Adaptation Grants  Reasonable • Some grants had been awarded by an
officer where the value of the grant was
in excess of that officer’s authority
expenditure limit.  
• There was no monitoring process in
place to ensure owners adhere to the
grant conditions. 
Surplus Building Security  Limited • There was no formal, standardised
procedure relating to the closedown and
management of the surplus buildings
and roles and responsibilities were not
clear. 
• The insurance conditions for unoccupied
buildings regarding property inspections
were not being met for one of the
properties tested.  There was no
evidence of risk assessments being
completed. 
Main Financial Systems –
Key Controls Limited
• A substantial backlog of unresolved
Accounts Receivable transactions in the
ERP system, with systemic workflow and
error-handling issues.
• In addition, one of the feeder ordering
systems lacks appropriate segregation
of duties.
Review of Petty Cash
Imprests N/A • Whilst there are some establishments
that would continue to require petty cash
Page 61 of 120

Page 62

- 7 -
PUBLIC
imprests, there were some other
imprests that could be closed as they
have not been used for some time and
others could be decreased as their use
seems to have declined.  Management
agreed to review the necessity and value
of their imprests.
NHS Greater Glasgow and Clyde
Audit Engagement Overall
Audit Rating
Significant Matters
Strategic and Operational
Planning
Minor
Improvement
Required
• There was not an estates strategy in
place supporting priorities.
Staff Training and
Development
Substantial
Improvement
Required
• Role-specific training for all job families
had not been clearly outlined, agreed
and communicated to both managers
and employees.  Staff training was also
not being adequately monitored.
Freedom of Information Minor
Improvement
Required
• The quality review process for responses
required to be improved and
consideration should be given to a case
management system. 
Property Transaction
Monitoring
Effective • None
Waiting List Management  Minor
improvement
required
• Staff had not been made aware that
parts of the Access and Waiting Times
Policy could not yet be implemented at
the time of the review.
• On some occasions, patients’ waiting list
priority had not been vetted per the
guidance
Risk Management Substantial
Improvement
Required
• Certain aspects of the risk improvement
project required to be formalised. 
• The recording and monitoring of risks
required to be standardised. 
Whistleblowing Substantial
improvement
required
• Guidance documents and training
required update and version control and 
triage decisions could be documented
more clearly. 
• Better protocols and proactive
controls/records over sharing personal
and special category data should be
implemented.  
• Aspects of Action tracking and reporting
could be improved upon.
Internal Communications
Strategy
Minor
Improvement
Required
• Management should establish a formal
process for gathering and documenting
progress against actions more regularly
than annually
Workforce Planning Minor
Improvement
Required
• None
Page 62 of 120

Page 63

- 8 -
PUBLIC
Information Governance Minor
Improvement
Required
• The recording of Subject Access
Requests required to be amended to fully
comply with the guidance 
Page 63 of 120

Page 64

No embedded text on this page.

Page 65

0 Introduction Audit Opinion Main Findings Action Plan 
Glasgow City Region
Fair Work First Compliance
Final Report
April 2026
FS 57095
Page 65 of 120

Page 66

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Fair Work First Compliance 
1 Introduction Audit Opinion Main Findings Action Plan
1 Introduction
1.1 As part of the agreed Internal Audit plan, we have carried out
a review of compliance with the Scottish Government’s Fair
Work First (FWF) policy across the City Deal Programme. 
1.2 FWF is a Scottish Government policy for promoting fair work,
and workforce diversity by applying a criteria to grants, other
funding and public contracts being awarded across the public
sector. The conditions came into effect for public sector
grants awarded after 1st July 2023 and must be met by the
Glasgow City Region Project Management Office (PMO) and
the eight member authorities (MAs) when allocating City Deal
funding. 
1.3 For the PMO, FWF is applicable to their role as the
distributers of the City Deal grant funding to the MAs. It is the
PMO’s responsibility to act in accordance with both the terms
and conditions of the Scottish Government, as set out in the
Grant Offer Letter and with the financial section of the GCR
City Deal Assurance, Governance and Programme
Management Framework (the Assurance Framework). 
1.4 As grant recipients, the MAs are required to comply with the
terms and conditions set out in the Scottish Government’s
Grant Offer letter, which requires them to pay at least the real
living wage (RLW) and demonstrate that all workers, including
agency staff, have access to appropriate channels for
effective workers’ voice channel(s), such as trade union
recognition. 
1.5 When MAs are awarding contracts related to City Deal
projects or are passing the grant to a third-party organisation,
they are required to follow the Scottish Government’s
guidance on FWF requirements in public sector procurement
and grant awards. 
1.6 The scope of the audit was to ensure there are sufficient and
appropriate arrangements in place covering the PMO and
MAs. The scope of the audit included:
• Awareness of the FWF requirements at both PMO and
MA level.
• Documented guidance and roles and responsibilities,
developed by the PMO.
• Internal documented procedures within member
authorities, including arrangements and approval
processes for all payments associated with the delivery
of City Deal projects.
• The reporting arrangements both internally within
member authorities and to the Region PMO regarding
compliance with the FWF requirements.
• Record keeping arrangements to maintain an audit trail
and ensure compliance with Scottish Government
requirements. 
Page 66 of 120

Page 67

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Fair Work First Compliance 
2 Introduction Audit Opinion Main Findings Action Plan
2 Audit Opinion
2.1 Based on the work carried out a reasonable level of assurance can be placed upon the control environment. The audit has identified some
scope for improvement in the existing arrangements and two recommendations which management should address.
3 Main Findings
3.1 Through discussion we found that officers within the PMO
demonstrated awareness and understanding of the FWF
policy and how it applies to their role as distributor of City Deal
grant funding to MAs. 
3.2 Furthermore, from discussion with Lead Officers across the
eight MAs we found an awareness of FWF requirements and
how it applies to the MA as both a grant recipient and as a
contracting authority.   
3.3 In accordance with the Assurance Framework, the PMO is
supported by the GCR City Deal Procurement Support Group
(PSG), whose membership includes a procurement officer
from each MA. The PSG has developed a Buyer’s Guide, to
provide operational guidance to MAs on how to apply the
FWF policy when carrying out procurement exercises relating
to City Deal projects. From discussions with procurement
officers from the MAs, we were advised that they are aware
of the guide and that it is applied when carrying out
procurement exercises. 
3.4 As FWF should be considered in all public sector
procurement exercises, we were advised that MAs will follow
their own standing orders and corporate procedures,
including the payment of contractors/suppliers, which will be
made in accordance with the conditions of the contracts
awarded.  We confirmed via discussion and review of
documents that FWF is considered at the tendering stage and
as part of the ongoing contract management for City Deal
projects at the MAs. 
3.5 Sample testing was performed on 14 contracts awarded since
the introduction of FWF in July 2023, across seven of the
MAs, to ensure that FWF had been adequately considered
when tendering for contracts relating to City Deal projects. 
The remaining MA had not awarded any contracts in the
applicable timeframe. We found evidence that in all 14 cases
that FWF had been suitably considered and applied at the
tender and evaluation stage as expected. Where MAs have
used an existing framework agreement, we noted that the
FWF checks have already been carried out as part of the
Page 67 of 120

Page 68

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Fair Work First Compliance 
3 Introduction Audit Opinion Main Findings Action Plan
supplier selection when establishing the framework and MAs
are not required to reperform these checks.   
3.6 We found that there are no specific reporting requirements
regarding compliance with FWF at either a PMO to Scottish
Government level, or at an MA to PMO level, however the
requirement for compliance is outlined in the grant offer letter
issued to all MAs. 
3.7 In addition, there are no specific FWF record keeping
requirements for either the PMO or MAs. The PMO must
retain adequate records of all grant monies received and
distributed for the GCR City Deal programme overall, in
accordance with the Scottish Government’s Grant Offer. We
were advised by procurement officers from each MA that City
Deal procurement records are held in line with their own
authority’s Record Retention and Disposal policy. 
3.8 However, we did identify some areas for improvement in
existing arrangements.  We were advised through discussion
with officers from all eight MAs that they are all compliant with
FWF and we were provided with public statements detailing
their compliance.  It was noted through discussion and review
of the FWF statement for one MA that they are not currently
an accredited RLW employer.  We were advised that the MA
pay the Scottish Local Government Living Wage which is
currently higher than the current RLW and therefore meet the
FWF Requirements.   However, as the RLW is adjusted in the
future there is a risk that the MA may not continue to meet
this requirement.  The MA noted in a committee report in
August 2025 to continue to monitor the RLW and their
compliance with this requirement. 
3.9 Furthermore, from review of Scottish Government guidance
we identified that if an MA uses a third-party organisation to
deliver the grant funded activity the organisation must be a
RLW employer in order to meet FWF requirements.  Through
examination of evidence and discussions with the eight MAs,
we identified three instances where third-party agreements
were established after the introduction of FWF requirements.
In all three cases, the original grant agreements did not
reference the FWF condition; however, each third-party
organisation was already an accredited RLW employer and
therefore met the required standard. 
3.10 Furthermore, the Scottish Government guidance specifies
that where a grant agreement was established prior to the
introduction of Fair Work First (FWF) requirements and spans
multiple years, the FWF condition should be incorporated at
an appropriate break point in the agreement. Through our
review of performance reports and discussion with Lead
Officers, we identified one MA with such an arrangement
which is progressing to stage two of the project. FWF
requirements should therefore be considered before the
project progresses to phase two; through discussion with the
Lead Officer we were advised that this will be included in the
agreement. 
3.11 An action plan is provided at section four outlining our
observations, risks and recommendations.  We have made
two recommendations for improvement. The priority of each
is noted below:   
Page 68 of 120

Page 69

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Fair Work First Compliance 
4 Introduction Audit Opinion Main Findings Action Plan 
Priority Definition Total
High
Key controls absent, not being
operated as designed or could be
improved. Urgent attention
required.
0
Medium
Less critically important controls
absent, not being operated as
designed or could be improved.
1
Low
Lower level controls absent, not
being operated as designed or
could be improved.
1
Service
Improvement
Opportunities for business
improvement and/or efficiencies
have been identified.
0
3.12 The audit has been undertaken in accordance with the Global
Internal Audit Standards in the UK public sector. 
3.13 We would like to thank officers involved in this audit for their
cooperation and assistance. 
3.14 It is recommended that the Head of Audit and Inspection
submits a further report to Committee on the implementation
of the actions contained in the attached Action Plan. 
Page 69 of 120

Page 70

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Fair Work First Compliance 
5 Introduction Audit Opinion Main Findings Action Plan
4 Action Plan 
No. Observation and Risk Recommendation Priority Management Response
Key Control: Arrangements are in place across all Member Authorities to ensure compliance with all Fair Work First Requirements 
1 From review of Scottish Government
guidance documents, we confirmed that
when a grant recipient uses a third-party
organisation to carry out the grant funded
activity, that organisation must pay at
least the RLW to workers directly
engaged in the delivery of the funded
activity in order to comply with FWF
requirements. 
it is the responsibility of the MA to seek
confirmation that the third-party
organisation pays at least the RLW by
including this in the agreement between
the two parties. 
We found three instances where an
agreement had been in place between
and MA and a third party and FWF was
not included in the initial agreement.  in
one case a phase two agreement was put
in place which did include FWF, the MA
obtained evidence to support this.  In the
other two cases the third party is an
PMO Management should ensure that the
requirement for third-party organisations to
comply with FWF is included in the appraisal
table which is used when assessing business
cases. 
In addition, the PMO should remind MAs of the
requirement to add FWF conditions to project
agreements where a pause or future phase
allows. 
Medium Response: Accepted 
Recommendation will be
implemented. 
Reminder to Lead Officers to add
FWF conditions where a
pause/future phase allows – to be
issued by end of April 2026 
Officer Responsible for
Implementation: 
Head of Glasgow City Region
Programme Management Office 
Timescales for Implementation: 
30 April 2026 
Page 70 of 120

Page 71

Glasgow City Council Internal Audit | Glasgow City Region City Deal | Fair Work First Compliance 
6 Introduction Audit Opinion Main Findings Action Plan
No. Observation and Risk Recommendation Priority Management Response
accredited RLW employer and therefore
met FWF requirements. 
We also noted one MA had entered into a
joint venture with a third-party
organisation prior to the introduction of
FWF. Scottish Government guidance
states that where multi-year funding
arrangements include a suitable review
point, FWF conditionality should be
incorporated into grant agreements for
subsequent years. Through discussion
the MA advised that this will now be
included in the phase two agreement. 
Without the inclusion of FWF
requirements for third party grant
agreements there is an increased risk that
Scottish Government conditions of
funding are not being met. 
Page 71 of 120

Page 72

7 Introduction Audit Opinion Main Findings Action Plan
No. Observation and Risk Recommendation Priority Management Response
Key Control: Arrangements are in place across all Member Authorities to ensure compliance with all Fair Work First Requirements 
2 As grant recipients, MAs are required to
comply with the terms and conditions set
out in the Scottish Government’s Grant
Offer letter, which requires them to pay at
least the real living wage (RLW). 
Through discussion and review of
documents we were advised that seven of
the MAs are accredited RLW employers
and therefore reliance can be placed on
the accreditation that this requirement is
being met. 
One MA advised that they are not an
accredited RLW employer which is
recognised in their FWF statement.  We
were advised by Officers and provided
with committee papers that state the
authority currently pay the Scottish Local
Government Living Wage which is higher
than the RLW.   
Without the additional assurance of a
grant recipient being an accredited RLW
employer there is an increased risk that in
the future FWF requirements are not met.
The PMO should obtain confirmation of
compliance with the RLW requirement of FWF
from the non-accredited member authority in
the form of an anonymised pay band report. 
This should be provided on an annual basis
while the MA is non-accredited before the pass
down letter is agreed, to ensure alignment with
the Grant Offer Letter conditions. 
Low Response: Accpeted 
Recommendations accepted and to
be implemented When issuing
2026/27 Pass Down Grant Letter
(estimated July 2026) 
Officer Responsible for
Implementation: 
Glasgow City Region Finance
Manager 
Timescales for Implementation: 
30 July 2026 
Page 72 of 120

Page 73

Internal Audit | Education Services | Gateway Shared Services 
0 Introduction Audit Opinion Main Findings Action Plan 
Glasgow City Region
Clyde Mission Heat
Decarbonisation Fund
Governance – Phase One
Final Report
April 2026
FS 57095
Page 73 of 120

Page 74

Glasgow City Council Internal Audit | Glasgow City Region | Clyde Mission and Heat Decarbonisation Governance -Phase one 
1 Introduction Audit Opinion Main Findings Action Plan
1 Introduction
1.1 As part of the agreed Internal Audit plan, we have carried out
a review of the Clyde Mission Heat Decarbonisation Fund
(CM-HDF) Governance arrangements within the Glasgow
City Region (GCR). 
1.2 CM-HDF is a three-year investment programme being
administered by GCR and funded by The Scottish
Government (SG).  Its purpose is to accelerate the
replacement of fossil fuel heating systems with low and zero
carbon alternatives across the Clyde Mission corridor, in line
with local, regional and national policy objectives. 
1.3 The scheme was launched on 10 December 2025 after
gaining approval at cabinet on 18 November 2025.  The
application process is underway for eligible projects to apply
for funding.  At least one element of project infrastructure (e.g.
generation, storage, distribution, use) must be located within
the Clyde Mission corridor. 
1.4 The scope of the audit was to ensure there are sufficient and
appropriate arrangements in place covering the CM-HDF. 
The scope of the audit included a review of:
• The documented policies and procedures, roles and
responsibilities.
• The governance and operational management
arrangements.
• The reporting activities to track progress and adherence
to the Assurance Framework.  
• Reporting to the Scottish Government 
• Monitoring Arrangements 
• Risk Management 
• Record keeping arrangements to maintain an audit trail
and ensure compliance with retention requirements. 
1.5 A second phase of this review is included in the 2026/27 audit
plan to consider the operational activities and ensure they
comply with the governance arrangements.
Commented [CM1]: Quarterly Reporting and Annual
Reporting
Page 74 of 120

Page 75

Glasgow City Council Internal Audit | Glasgow City Region | Clyde Mission and Heat Decarbonisation Governance -Phase one 
2 Introduction Audit Opinion Main Findings Action Plan
2 Audit Opinion
2.1 Based on the audit work carried out, assurance can be taken that the control environment is satisfactory.
3 Main Findings
3.1 We are pleased to report that key controls are in place in
relation to the governance arrangements for the CM-HDF
Through discussion and review of documentation we found
that key officers are aware their roles and responsibilities.
3.2 From review of documentation and discussion with the
Programme Manager, we found that there is a clear
governance structure in place with regards to the CM-HDF.
We confirmed that there are planned reporting arrangements
in place to comply with the governance structure once the
projects are approved and progress. Additionally, we found
that the governance arrangements are provided to the
applicants via an application guidance document, these are
publicly available through the GCR website.  
3.3 Through review of documentation and discussion, we found
that there are clear and reasonable monitoring and reporting
arrangements in place for projects and GCR. These
requirements are set out in the application guidance and in
the grant offer letter which will be issued to approved projects.
In addition, internal documentation is in place that details the
monthly monitoring and reporting arrangements and the roles
and responsibilities required for both the approved projects
and relevant GCR officers.
3.4 Through discussion with the Programme Manager and review
of Internal documentation we found that arrangements are in
place for consistent reporting to SG regarding CM-HDF. This
includes quarterly grant claims which will be provided to the
SG by GCR based on the grant claims provided by projects. 
3.5 We were advised that there is a document retention policy of
6 years in place in line with SG requirements. All
documentation relating to projects is saved in a secured drive
which is only accessible by relevant officers and will be
disposed of at the end of the retention period. The retention
period is also in alignment with the council’s data retention
policy.
3.6 We were advised through discussion that there are risk
management arrangements in place; this includes a monthly
review of the risk register. However, through review of
documentation we found a discrepancy in the frequency of
how often the risk register would be reviewed. This has since
been addressed by the Programme Manager and updated to
Page 75 of 120

Page 76

Glasgow City Council Internal Audit | Glasgow City Region | Clyde Mission and Heat Decarbonisation Governance -Phase one 
3 Introduction Audit Opinion Main Findings Action Plan
reflect the monthly review.  We found that all other internal
documentation was accurate to the intended working
practices. 
3.7 In addition, we found through review of the application
guidance document that applicants are not made aware of the
change control process.  We were able to confirm through
review of internal documentation that there is a change
control process in place. We have been advised that this was
an oversight and that the Programme Manager has updated
the application guidance to include the change control
process.
3.8 The audit has been undertaken in accordance with the Global
Internal Audit Standards in the UK public sector. 
3.9 We would like to thank officers involved in this audit for their
cooperation and assistance. 
3.10 It is recommended that the Committee notes the contents of
this report. 
Page 76 of 120

Page 77

PUBLIC
___________________________________________________________________
To: Audit, Risk and Scrutiny Board
On: 17 August 2026
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Internal Audit and Counter Fraud Progress and Performance for
Period to 30 June 2026
___________________________________________________________________
1. Summary
1.1 The Internal Audit Annual Plan was approved by the Audit, Risk and
Scrutiny Board on 16 March 2026. Internal Audit measures the progress
and performance of the team on a regular basis using a range of
performance indicators.  This report monitors progress from 1 April 2026
to 30 June 2026 in terms of the delivery of the Audit Plan for the year
and compares actual performance against targets set by the Director of
Finance and Resources.
1.2 In terms of Counter Fraud, no formal performance targets for fraud
investigation have been established for the following reasons.  Part of
their work involves being the single point of contact (SPOC) for the
Department for Work and Pension’s (DWP) Single Fraud Investigation
Service and the Service Level Agreement for this work contains time
targets for completing this work.  The types of fraud referrals received to
date are wide ranging and the team’s objective is to concentrate on
investigating those referrals considered to contain the greatest fraud risk.
They are also involved in promoting fraud awareness and assisting with
the implementation of adequate fraud prevention measures within the
Council.
1.3 We also provide advice and support where necessary to council services
and partner bodies.
Item 3
Page 77 of 120

Page 78

PUBLIC
1.4 The report details progress against local and national initiatives involving
Internal Audit and the Counter Fraud Team from 1 April 2026 to 30 June
2026.
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to note the Internal Audit and Counter Fraud Team
progress and performance to 30 June 2026.
_________________________________________________________
3. Background
3.1 The progress and performance of the Internal Audit Team is subject to
regular monitoring using a number of performance measures.  The
Director of Finance and Resources has set annual targets for the team
to demonstrate continuous improvement. In terms of the Counter Fraud
team, there are time targets in place for responding to requests from the
DWP’s Single Fraud Investigation Service.  Due to the diverse nature of
fraud referrals no formal performance targets have been established and
the outcomes from investigations are regularly monitored by
management.  In addition, the Counter Fraud Team are heavily involved
in fraud prevention measures within the Council.
3.2 Internal Audit and the Counter Fraud Team support a variety of local and
national initiatives through participation in professional practitioner
groups and co-ordination of national initiatives such as the National
Fraud Initiative.
3.3 This report measures the progress and performance of both the Internal
Audit and Counter Fraud Team for the period from 1 April 2026 to 30
June 2026.
4.                 Internal Audit Service Resource
4.1 Work is currently ongoing to implement the new approved structure
within the Internal Audit Service.  To further enhance the team in terms
of succession planning, the aim of the restructure is to provide
opportunities for our current staff and for  someone to train as an Internal
Auditor. 
4.2 The Assistant Chief Auditor post has been re designated to Internal Audit
Service Manager to reflect duties of the post better.  Recruitment for this
post has taken place and an officer has accepted this post, subject to
post interview checks being satisfactory. In addition, the Senior Counter
Fraud Investigator’s post has been advertised and interviews are to take
place in mid-August 2026.  Our current two Internal Auditors have just
commenced studying for relevant professional qualifications and a
Senior Auditor post is going to be replaced with a trainee post.  Work has
now commenced in drawing up a job description and person
specification for this post which will be advertised as soon as these
Page 78 of 120

Page 79

PUBLIC
documents have been finalised and the post grade formally approved by
the Job Evaluation Team. 
5.   Internal Audit Team Performance
(a) Percentage of audit plan completed as at 30 June 2026 
This measures the degree to which the Audit Plan has been completed.
Actual
2025/26
Annual
Target
2026/27
Audit Plan
Completion
Target to 30
June 2026
Audit Plan
Completion Actual
30 June 2026
90.1% 90.0% 18% 22.0% 
The current audit plan completion indicator is above target for the
quarter. 
(b) Percentage of assignments complete by target date 
This measures the degree with which target dates for audit work have
been met.
Target 2026/27 Actual to 30 June 2026
95.0% 100%           
Actual performance is ahead of the target set for the year.  
(c) Percentage of audit assignments completed within time budget 
This measures how well the time budget for individual assignments has
been adhered to. 
Target 2026/27 Actual to 30 June 2026  
95.0% 100%
Actual performance is ahead of the target set for the year, although this
could reduce over the remainder of the year.   
(d) Percentage of audit reports issued within 6 weeks of completion of
audit field work 
This measures how quickly draft audit reports are issued after the audit
fieldwork has been completed. 
Target 2026/27 Actual to 30 June 2026
95.0% 100%
Actual performance is ahead of the target set for the year, although this
is likely to reduce over the remainder of the year.  
Page 79 of 120

Page 80

PUBLIC 
6. Review of the 2026/27 Internal Audit Plan 
6.1 Our main focus this quarter has been on the completion of last year’s
audits which were carried forward.  It is planned to have these fully
completed by 30 September 2026.  
6.2 We have commenced our 2026/27 Audit Plan and this is subject to
ongoing review in light of any organisational risks arising, and also to
determine whether any assignments will have to be amended or
cancelled as result of us being unable, for any reason, to undertake the
work planned. At this stage we are not recommending any further
amendments to the plan. 
6.3 Although a vacancy factor was built into the Audit Plan, the vacancies in
this quarter  may result in assignments being completed later than
planned and therefore progress will continue to be closely scrutinised by
management. We also have had a number of Freedom of Information
requests to deal with in this quarter which is not considered the norm for
Internal Audit. 
6.4 Any proposed amendments to the Audit Plan will be brought to this Board
for approval. 
7.   Counter Fraud Team Progress and Performance
7.1 In line with the Service Level Agreement, the Counter Fraud Team act
as the Single Point of Contact (SPOC) to route potential housing benefit
fraud referrals to the DWP, liaise with the Council’s Housing Benefit
Team and DWP Fraud Officers and retrieve the necessary evidence for
the DWP Fraud Officers from the Housing Benefit System.  Where a
suspicion of fraud arises, the team investigate and report their findings
to management. Where appropriate, follow-on action is taken, such as
reporting the matter to Police Scotland for further investigation, or directly
to the Procurator Fiscal. In addition, they also work jointly with DWP
Fraud Officers on criminal fraud investigations which focuses on the
investigation and prosecution of the Local Authority administered Council
Tax Reduction Scheme and Social Security benefit fraud. In addition to
investigation work the team also undertake fraud prevention work.
7.2 Until the Senior Counter Fraud  Investigator post is filled in August
supervisory duties of the team are currently being covered by the Chief
Auditor and Internal Audit Service Manager. 
7.3 The Counter Fraud Officers have been working on the various fraud
referrals and are finalising the 2024/25 National Fraud Initiative matches
which were chosen for investigation as any information requested from
other Authorities/Organisation is received. A full report on the results of
the National Fraud Exercise will be brought to this Board for information
once Audit Scotland’s national report, which is due August/September,
Page 80 of 120

Page 81

PUBLIC
has been published.  We have now commenced preliminary work for
submission of the data for the 2026/27 initiative. 
7.4 As part of our fraud prevention work, we are continuing to validate any
bank account changes received from the Council’s suppliers and
contractors and the details supplied by new Housing Applicants. 
7.5 The financial and non-financial results for the period (April 2026 to June
2026) are noted in the table below. 
Financial Outcomes Period to 30 June 2026
(£)
Cash savings directly attributable to
preventative counter fraud intervention
44,302
Cash recoveries in progress directly
attributable to counter fraud
investigations
35,956 
Notional savings identified through
counter fraud investigation, (e.g. housing
tenancy and future council tax)
145,435
Housing Benefit Savings Attributable to
Joint Working by Counter Fraud and
DWP Counter Fraud Officers
0
Other DWP Benefit or Tax Credit
Savings identified through other Counter
Fraud work or through joint working with
DWP
0
Non-Financial Outcomes Period to 30 June 2026
Housing properties recovered 1
Housing applications amended/cancelled 6
Housing Allocation Priority Changed 0
Blue badge misuse warning letters
issued
11
Blue Badges Cancelled 0
Supplier/Contractor Checks Undertaken 18
7.6 Our notional savings are based on the methodology prepared by the
Cabinet Office. 
8.  Local and National Initiatives   
Scottish Local Authorities Chief Internal Auditors Group 
8.1 The Local Authorities’ Chief Internal Auditors Group last met in June
2026 with Audit Scotland colleagues to discuss the effect on Internal
Audit Plans of additional checking by Internal Audit if errors are identified
in the Housing Benefit  Subsidy checks undertaken by External Audit. 
This matter is now resolved as the Department for Work and Pensions
have now agreed that this additional checking can be carried out by
Page 81 of 120

Page 82

PUBLIC
Revenue and Benefits staff.  In addition, this group held a bytesize Cyber
Conference which we attended and found to be beneficial. 
8.2 The Annual Report of this group is attached at Appendix 1. The Vision of
SLACIAG is set out in the Introduction and the remainder of the report
provides an overview of its work throughout the year. 
Scottish Local Authorities Investigation Sub-Group 
8.3   The Local Authorities Investigation Sub-Group also met in June 2026
and the main presentation focused on the progress of the National Fraud
Initiative. 
Information Security Group 
8.4 The Information Security Group, chaired by the Chief Auditor and
attended by the Senior Managers from Information Governance,
Information Management and Cyber Security teams met in April 2026
and updates from all the teams were provided. 
8.5 Global Internal Audit Standards in the Public Sector 
Work is still ongoing to ensure all our guidance documentation reflects 
the requirements of these standards. 
_________________________________________________________
Implications of the Report
1. Financial - The Council has in place arrangements to recover any
overpayments identified from the work of the Counter Fraud Team and
the National Fraud Initiative. 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of
good corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights - None 
8. Health & Safety – None
Page 82 of 120

Page 83

PUBLIC
9. Procurement - None 
10.  Risk - The progress and performance reported relates to the delivery of
the risk-based internal audit plan and the mitigation of the risk of fraud
and error. 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk – None 
14. Children’s Rights - None 
________________________________________________________________
Author:           Karen Campbell, Chief Auditor – 07768354651
Page 83 of 120

Page 84

No embedded text on this page.

Page 85

1 
PUBLIC 
ANNUAL REPORT FROM THE CHAIR – 2025 
“WORKING TOGETHER TO SUPPORT THE KEY ROLE OF INTERNAL AUDIT” 
1. INTRODUCTION
1.1 Membership of the CIPFA Scottish Local Authorities Chief Internal Auditors’ Group (SLACIAG) is open
to the chief internal auditor from each Scottish local authority and the Strathclyde Partnership for
Transport (SPT).  SLACIAG is a Special Interest Group of CIPFA in Scotland, with operational
arrangements, vision, and objectives set out in a formal Constitution.
1.2 SLACIAG’s Vision is to be the voice of internal audit across Scottish local authorities and a driving
force for best practice in respect of local authority and public transport bodies internal audit,
governance, and operations.
1.3 In support of that Vision, SLACIAG has the following objectives:
• Secure a quality and responsive service for members of the group.
• Develop the influence of the group with key decision makers and institutions in Scotland, as the
key representative body for internal audit in local government with a particular emphasis on
governance, risk, control and assurance matters.
• Strengthen links and build long term relationships across the internal audit community within
the public service.
• Provide an effective group for the discussion of issues of common concern, sharing of good
practice and commissioner of work to develop advanced practice.
• Consider the development and training needs of our people as a collective to ensure that the
best available products are procured at the best price.
• Uphold the group’s key values, including: respect; openness and honesty; adding value;
professional team working; sharing best practice; integrity; continuous improvement.
1.4 The purpose of this annual report to key stakeholders is to provide an update on SLACIAG’s activities
and achievements over the course of 2025 and to recognise actions required to achieve its Vision.
1.5 SLACIAG has two long-established sub-groups whose activity is reflected in this report:
• the Computer Audit Sub-Group (CASG); and
• the Scottish Local Authorities Investigators’ Group (SLAIG).
1.6 Further sub-groups were established by SLACIAG in 2023 to lead on development actions arising from
the SLACIAG Conference held in June 2023 within specific themes, including risk, data analytics,
resourcing, and sustainability/climate change. Their activity in 2025 is also referenced in this report.  
Page 85 of 120

Page 86

PUBLIC
2. MANAGEMENT COMMITTEE
2.1 I, Chief Officer Audit & Risk, Scottish Borders Council, was appointed as Chair of SLACIAG at the AGM
in March 2025, continuing as Chair following a 2-year term during 2022-2023 to facilitate succession
planning within the Management Committee. I previously served as Chair of SLACIAG during 2014-
2015. In accordance with SLACIAG’s Constitution, my term of office will expire after serving 2 years at
the SLACIAG AGM in March 2026. The Chair of SLACIAG joins the meetings of the CIPFA Scotland Branch
Executive Committee, as SLACIAG is a special interest group of CIPFA in Scotland.
2.2 Internal Audit Manager, South Lanarkshire Council, was re-elected as Treasurer of SLACIAG at the AGM
March 2025 having initially been appointed to the role in June 2020. Treasurer provided regular
updates on the financial position of SLACIAG to enable the Management Committee to plan activity.
2.3 The appointments to the SLACIAG Management Committee were approved at the AGM March 2025.
New members were welcomed to the Management Committee, including each sub-group Lead to
ensure all sub-groups were represented. The Chairs of both CASG and SLAIG participate in the
Management Committee meetings to derive benefits from their sectoral expertise and to ensure
synergy when forward planning the regular meetings. 
2.4 There were some membership changes during 2025, as follows:
SLACIAG MANAGEMENT COMMITTEE 2025
Chief Officer Audit & Risk  Scottish Borders Council Chair SLACIAG
Internal Audit Manager South Lanarkshire Council Treasurer SLACIAG
Service Manager Audit and
Risk Management   Fife Council Member; Lead for EQA and Risk
Sub-Groups
Audit & Risk Manager (stood
down June 2025 secondment) East Dunbartonshire Council Member
Service Manager Internal
Audit East Lothian Council Member; Lead for Sustainability/
Climate Change Sub-Group
Head of Audit (stood down
June 2025 due to new job role)
Glasgow City and Shetland
Islands Councils
Member; Lead for Data Analytics
Sub-Group
Audit Service Manager Stirling Council Member; EQA Moderation Panel
Chief Internal Auditor Aberdeenshire and Aberdeen
City Councils Member
Chief Internal Auditor City of Edinburgh Council Member; Lead for Resourcing
Sub-Group
Senior Manager (Audit, Fraud,
Safety, Risk and Insurance) North Ayrshire Council Chair CASG
Corporate Fraud Team Leader East Dunbartonshire Council  Chair SLAIG
2.5 There were Management Committee virtual meetings held in March, July and August 2025. The
purpose of these meetings was to forward plan the SLACIAG Conference and SLACIAG and Sub-Group
meetings, considering topics, setting dates and arranging speakers. 
2.6 The Management Committee also oversees the External Quality Assessment (EQA) process, which is a
peer review process established by SLACIAG to enable external validation of compliance with the
Global Internal Audit Standards in the UK Public Sector (GIAS). The Management Committee monitors
progress with completion against a recommended programme of reviews each year to ensure that all
participating organisations comply with the requirement to undertake an EQA once every 5 years.
Page 86 of 120

Page 87

PUBLIC
3. SCOTTISH LOCAL AUTHORITIES’ CHIEF INTERNAL AUDITORS GROUP (SLACIAG)
SLACIAG Conference 2025 
a) The biennial SLACIAG Conference was held on Thursday 5 and Friday 6 June 2025 at Edinburgh
Napier University (ENU) Craiglockhart Campus, an incredible learning campus with superb
location and facilities, hosted by the Chair of SLACIAG. The event was attended each day by 95+
delegates from nearly all Scottish Councils’ internal audit, risk management and counter fraud
functions to invest in their learning and development.
b) The Keynote speaker was the Director of Finance and Procurement at City of Edinburgh Council
(CEC) outlining the Important Role of Internal Audit in Challenging times ‘Navigating a New Era’.
They shared their perspectives on the rapid changes and challenges in the local government
sector and the profession of Internal Audit, setting out the opportunity to evolve and respond to
these challenges using the new global internal audit standards to continue to add value through
its vital role in councils across the country (not only in terms of providing assurance, but through
insight and advice on a whole range of areas of work), and reflected on the road map of the
future including the new skills requirements for audit and other assurance functions in a more
digitised environment. This keynote speech acted as a catalyst for the workshop connections
and collaborations over the two days.
c) Furthermore, guest speakers were welcomed to cover key areas over the two days, including:
o Chief Internal Auditor, City of Edinburgh Council: Coordination and Resilience - Assurance
Mapping
o Insurance Manager, City of Edinburgh Council: Areas of emerging risk – Insurance Lead
Officer perspective
o Head of Technical Content and Research, Chartered Institute of Internal Auditors: Topical
Requirements in new Global Internal Audit Standards in the UK public sector: Cyber security
(approved; implementation February 2026); Third Party Supply Chain (being finalised;
implementation 12 months from approval); and Organisational Behaviour (out for
consultation)
o SLACIAG Resourcing Sub-Group: Coaching and Mentoring Awareness Session - Overview of
the proposed approach  
o Head of IT, Fife Council: Generative Artificial Intelligence (AI) – threat or opportunity for
audit and fraud professionals in public sector, governance of AI  
o Account Manager and Senior AI Solution Engineer, Microsoft: Generative AI – the art of the
possible
o Chief Officer (People Resources), North Lanarkshire Council: Building a Sustainable Scottish
Local Government Workforce for the Future – national developments in 2025
o Director CIFAS: Failure to Prevent Fraud: New legislation and Fraud Risk assessments &
Fraud Prevention Strategies 
d) There were excellent networking opportunities for all delegates, significant sharing of
knowledge and practice during the workshop sessions, and lots of suggestions for improvement
actions in keeping with the conference title ‘Connections Collaborations Catalysts’. This will help
all delegates to collectively improve, challenge and strengthen the approaches and practices
within their respective organisations in Scottish local government.    
Page 87 of 120

Page 88

PUBLIC
SLACIAG Meetings 2025
3.1 The Treasurer produced the 2024 annual accounts, which were considered in draft by the Group at
the AGM in March 2025. Thanks to those at South Ayrshire Council for completing the independent
audit of the 2024 Accounts. Thanks to SLACIAG Treasurer for her professionalism in fulfilling the
Treasurer role and providing regular updates during 2025 on the financial position of SLACIAG which
is important to ensure the Group remains financially sustainable. 
3.2 There were three SLACIAG virtual meetings in 2025 with topics/speakers set out in the table below in
addition to core business. The network continues to be strongly supported by members with a focus
on significant and current issues.
Date Topics / Speakers
21 March
2025 
AGM
• SLACIAG Annual Report 2024 (Chair)
• SLACIAG Annual Accounts 2024 (Treasurer)
• SLACIAG Subscriptions
Accounts Commission report IJB Finances
• The IJB CIAs from NHS boards were invited to the virtual meeting to discuss
common issues raised within the Accounts Commission report (published 6
March 2025) Integration Joint Boards Financial Bulletin 2023/24 with key
message “Reform urgently needed to tackle precarious health and social care
finances”.
Updates from Sub-Groups
• External Quality Assessment (EQA), Data Analytics, Resourcing,
Sustainability/Climate Change, Risk
5 September
2025
CIIA Internal Auditing Competency Framework
• Head of Technical Content and Research, Chartered Institute of Internal
Auditors (CIIA), provided an overview of the Internal Auditing Competency
Framework (published July 2025) using CIIA Global website. The overview
covered: Competency in the Global Internal Audit Standards (Domains II, III, IV,
V); Components of the Competency Framework; Using the Competency
Framework.  
SLACIAG Mentoring approach
• Chief Internal Auditor (Resourcing Sub-Group Lead and CAE City of Edinburgh
Council) presented an overview of Mentoring, the recent work of the sub-
group, the next steps in setting up the Mentoring approach for SLACIAG
members (CAEs and their teams) and evaluating it in 2026.
External Quality Assessment (EQA)
• Service Manager Audit and Risk Management (EQA Sub-Group Lead and CAE
Fife Council) provided an update on External Quality Assessment (EQA),
completing the EQA2 programme and the March 2026 target date for the EQA
Sub-Group to update the guidance and templates for the SLACIAG EQA3
process to meet the requirements of the Global Internal Audit Standards in the
UK Public Sector (GIAS).
Page 88 of 120

Page 89

PUBLIC
Date Topics / Speakers
5 December
2025
Risk Assurance Module 
• Risk Manager, Renfrewshire Council, presented an overview of the ‘Business As
Usual Risk Assurance Module’ which they developed, and how this is used to
obtain the annual assurances from Services to assist in formulating the Annual
Governance Statement.
Strategic Risk Analysis in Scottish Councils
• Risk Sub-Group presented an analysis of corporate risks on Scottish Councils’
risk registers highlighting the themes of significant current risks as well as
emerging risks. Risk focus to inform CAE horizon scanning for the development
of Internal Audit Strategies and Plans 2026/27 for Scottish Councils.
Strategic Audit Review
• Director of Audit Services, Audit Scotland, provided an outline of the strategic
audit review process, timescales and any opportunity for SLACIAG, Councils
and/or CAE engagement. 
Accounts Commission S102 Report - Comhairle nan Eilean Siar Cyber-attack
• Chief Internal Auditor, CAE City of Edinburgh Council, chaired a discussion on
the learnings from the cyber-attack affecting operations and services at
Westerns Isles Council, and used this to consider the GIA Topical Requirement
on Cyber Security to assess risks and controls in Councils. 
External Quality Assessment (EQA)
3.3 The EQA Sub-Group members set out below have been active in 2025 to oversee the completion of
the EQA2 schedule and to plan the EQA3 schedule. The schedule of EQA3 peer reviews (involves 29
Councils with 21 CAEs due to shared services arrangements) was approved. Appointment to the
vacancy on the Moderation Panel will be considered at March 2026 AGM.
EQA Sub-Group Moderation Panel
Service Manager Audit
and Risk Management   Fife Council Chief Internal Auditor Argyll & Bute Council
Chief Internal Auditor Orkney Islands Council Audit Service Manager Stirling Council
Chief Internal Auditor South Ayrshire Council vacancy 
3.4 Responsibility is on the reviewee Council CAE to meet EQA requirements and to keep their Audit
Committee informed of any delays in meeting the 5-year timeframe. Access to the SLACIAG peer EQA
process through SLACIAG membership provides a potential financial saving benefit with costs to have
a similar exercise completed by an external supplier or body likely to be more than £5,000.  
Sub-Groups
3.5 At each of the quarterly SLACIAG meetings during 2025 updates were received from the Sub-Groups
in accordance with their respective terms of reference to derive significant benefits from them. The
Data Analytics Sub-Group has fulfilled its purpose and was stood down in June 2025.
SLACIAG Knowledge Hub and Teams Channel
3.6 All Agendas, Minutes, and Presentations of SLACIAG meetings, Conference, EQA Framework Guidance,
and other relevant documents are uploaded to the SLACIAG Knowledge Hub to enable access by all
members in a secure way. New Members have been registered on the SLACIAG Knowledge Hub,
including new starts from within audit teams of Councils, thus enabling greater participation. A new
SLACIAG MS Teams channel hosted by Aberdeenshire Council has been created and used during 2025
to enable discussion content and document sharing, though there is scope for greater participation.
Page 89 of 120

Page 90

PUBLIC
4. COMPUTER AUDIT SUB-GROUP
4.1 The main aim of the Computer Audit Sub-Group (CASG), which is a permanent sub-group of SLACIAG,
is to provide a forum to share and discuss computer audit practices and developments.  This includes
raising awareness of new standards, updates to legislation, new and current topics of interest, and
computer audit developments, resources, and techniques.
4.2 The role and outputs of CASG have been expanded during 2025 to cover IT/Cyber Security, Artificial
Intelligence (AI), Data Analytics and Digital Transformation, in addition to core Computer Audit work
to ensure the sustainability of the sub-group. 
4.3 The Computer Audit Sub-Group (CASG) met two times in 2025, all meetings were virtual to ensure
participation in the group remains good, with topics/speakers as follows:
Date  Topics / Speakers 
09 April 2025
Cyber Security Maturity Assessments Frameworks
• Head of Public Sector Cyber Resilience, National Cyber Resilience
Unit, Scottish Government, was welcomed to deliver a presentation to
the group, which was followed up by Questions and Discussions on
how this could be used to comply with the GIAS Cyber Security Topical
requirement which is mandatory by February 2026. 
SEEMiS Audit Report Presentation
• Internal Auditor, Midlothian Council, highlighted key findings to the
group from each of the control objectives from the audit report, and
outlined the data analytics work which was undertaken to identify
system users who were still on the system but were leavers.
05 November
2025
Cyber Assurance and Data Analytics
Internal Auditor, Strathclyde Partnership for Transport (SPT), delivered a
presentation followed by group discussion, covering the following key
elements:
• Begin the audit with an overview of cybersecurity standards.
• Consider IIA guidance on cybersecurity, including topical issues and
budget constraints. If complying with the Scottish Government
framework then most likely you are complying with the IIA topical
requirements.
• Ensure policies and procedures are communicated to the right
stakeholders and roles and responsibilities are clearly defined.
• Check industrial control measures to safeguard assets and data flows
across infrastructure components and preventing unauthorized access.
• Undertake a self-assessment to identity gaps and control failures
Group discussion on use of AI across the Councils and to discuss about
the recent AI training from Fife Council and Microsoft
Group acknowledged that Council teams are all are different levels whilst
the development of AI products is fast paced. Some Council teams are
using free version whilst others have licenced version of CoPilot. There’s an
opportunity to learn from other Councils as AI Policies are developed.
4.4 The Agendas, Minutes, and Presentations for CASG meetings 2025, where available, are uploaded to
the SLACIAG Knowledge Hub (CASG sub-folder) to enable access by all members in a secure way.
Page 90 of 120

Page 91

PUBLIC
5. SCOTTISH LOCAL AUTHORITY INVESTIGATORS GROUP (SLAIG)
5.1 The main aim of the Scottish Local Authority Investigators Group (SLAIG), which is a permanent sub-
group of SLACIAG, is to provide a forum to share and discuss counter fraud practices and
developments.  This includes raising awareness of updates to legislation, new and current topics of
interest, and developments in counter fraud activities.
5.2 The Scottish Local Authority Investigators Group (SLAIG) met four times in 2025, all meetings were
virtual, with topics/speakers as follows in addition to core business:
Date Topics / Speakers
12 March 2025 
Polygamous Working Presentation on case at Stirling Council. Sharing of
red flags identified during the investigation and of steps required to ensure
similar cases are suitable for criminal proceedings.  
• Stirling Council
12 June 2025 
NHS Bribery Presentation on a recent case involving employees of NHS and
of directors of a company who had been awarded a contract by NHS. 
Details provided of investigation methods deployed and red flags identified
by the investigation.
• NHS Scotland
NFI Data Matching exercise Update on the current position and sharing of
good practice for the sifting and investigation of matches. 
• Audit Scotland 
25 September 2025
Proposed Fraud Landscape Report and Fraud Apprenticeship Scheme
Input from Scottish Government providing an overview of a proposed
Fraud Landscape Report and of a proposed Fraud Apprenticeship Scheme
in partnership with Skills Scotland. 
• Scottish Government  
10 December 2025
Tenancy Fraud detection tool Presentation on a tool developed by Lintels
which searches online booking platforms. 
• Lintels 
NFI Data Matching exercise Presentation on current position of the NFI
data matching exercise, deadline for completion of exercise for inclusion in
next report, tips on investigation of creditors matches and of forthcoming
pilot with Airbnb.  
• Audit Scotland 
5.3 One specific task assigned to SLAIG was the Benchmarking on fraud activity and resources to align with
the vison and objectives of SLACIAG and SLAIG’s Terms of Reference. The proposal was agreed in
March 2025 that all local authorities will participate in a benchmarking exercise which is ongoing.  The
core content of the exercise will include resources, training, and outcomes.
5.4 All Agendas, Minutes, and Presentations of SLAIG meetings, and other relevant documents are
uploaded to the SLAIG Knowledge Hub to enable access by all members in a secure way. Articles and
discussion forums are shared to provide fraud risk insights relevant to the local government sector. 
Page 91 of 120

Page 92

PUBLIC
6. CONCLUSION 
6.1 Notwithstanding the challenges that continue to affect our organisations, SLACIAG and its Sub-Groups
have had another successful year, as evidenced by the number of delegates investing in their learning
and development through their engagement during the 2-day in-person Conference in June 2025 and
through participation in our virtual meetings, the range of topics discussed and the outputs created.
This provides significant benefits to our members and their teams. 
6.2 During the year Chief Audit Executives (CAE) considered significant matters facing our organisations
such as Financial Sustainability Risks and Cyber Security Risks, shared approaches being taken to
implement the new Global Internal Audit Standards, assessed their impact on the provision of
assurance and advisory services, discussed key issues facing our assurance functions, including
resourcing, workforce planning, skills and knowledge mix, and shared approaches being taken to
address these, and focussed on specialist themes including data analytics, counter fraud and crime,
climate change and sustainability.
6.3 In line with their remits the CASG and SLAIG Sub-Groups focussed on matters that are affecting our
organisations and our functions/individuals. The Sub-Groups are excelling in their exploration of
specific matters to the benefit of the wider Group and its members. I give thanks to those who
volunteer their time to achieve this.
6.4 I would like to thank the Management Committee and the Leads of our Sub-Groups for their work in
organising meetings and responding to the challenges that have arisen. I would also like to thank our
speakers for giving up their time to join us at our virtual meetings during 2025 and assist us in
enhancing our effectiveness as providers of assurance and compliance services.
6.5 My thanks are also extended to our members for their support, as evidenced by engaging in the 2-day
in-person Conference in June 2025 and participating in our virtual meetings during 2025, but also by
the generous advice and assistance provided in relation to the myriad of audit, risk and governance
questions which have arisen within our membership during the year. SLACIAG relies on the dedicated
and hard-working public sector professionals within its membership, recognising the time and effort
of those members who volunteer their time to plan and deliver these events. We look forward to the
learning and development opportunities in 2026 to support us in fulfilling the roles and responsibilities
of CAE and Internal Audit functions, and the wider functions covered in some organisations.
6.6 CAEs are asked to distribute the SLACIAG Annual Report 2025 to key stakeholders within their
organisations, in particular the Audit Committee or equivalent, to highlight the value of this forum. 
Chief Officer Audit & Risk, Scottish Borders Council
Chair of SLACIAG
10 March 2026 
Page 92 of 120

Page 93

PUBLIC
___________________________________________________________________
To:    Audit, Risk and Scrutiny Board
On: 17 August 2026
__________________________________________________________________
Report by:   Lead Officer
___________________________________________________________________
Heading:    Lead Piping in Public and Private Housing in Renfrewshire
___________________________________________________________________
1. Summary
At its meeting on 18 May 2026, members of the Audit, Risk and
Scrutiny Board agreed the purpose and scope of the above review.
This paper provides a report on progress made and information that
has been prepared for the Board’s interest to date.
________________________________________________________
2. Recommendations
2.1 The Board is asked to:
• note the progress of the review;
• note the information presented at this stage of the review; and,
• note the next steps.
___________________________________________
3. Background
3.1  At the Audit, Risk and Scrutiny Board in May 2026 it was agreed that
the purpose of the review into Lead Piping in Housing within
Renfrewshire would be:
(1) set out the strategies in place to identify and replace lead pipes in
housing across all tenures, in Renfrewshire.
Item 4
Page 93 of 120

Page 94

PUBLIC
(2) set out the council’s current arrangements for addressing lead
piping within council housing stock.
(3) identify any recommendations that the council could pursue, within
the available resources, to support replacement of lead piping in both
private and council housing by providing non-financial assistance. 
___________________________________________
4. Progress to date
4.1  Since the Board approved the purpose and scope of the review in May
2026, the Lead Officer has undertaken a review of relevant legislation
and guidance available and the existing framework to support the
identification and replacement of lead pipes. 
4.2 Key legislation/guidance reviewed:
• Water (Scotland) Act 1980
• Housing (Scotland) Act 1987
• Housing (Scotland) Act 2006
• Antisocial Behaviour etc. (Scotland) Act 2004
• The Public Water Supplies (Scotland) Regulations 2014 
• The Water Intended for Human Consumption (Private Supplies)
(Scotland) Regulations 2017 
• The Private Water Supplies (Scotland) Regulations 2006
• The Water Intended for Human Consumption (Private Supplies)
(Scotland) Regulations 2017 Guidance for Local Authorities
2018- Ver 3.0
• Repairing Standard: statutory guidance for private landlords
• Landlord registration: statutory guidance for local authorities
2017
• Public health management of elevated lead levels in drinking
water - PHS
• Scottish Housing Quality Standard (SHQS) 
Key websites reviewed:
• Scottish Water – Lead and your water
• Drinking Water Quality Regulator – Lead in Drinking Water
• Renfrewshire Council website- Lead in drinking water
• DWQR annual report
• Housing and Property Chamber – Scotland 
4.3  The Lead Officer has engaged with Scottish Water, NHS Public
Protection Unit, Renfrewshire Council’s Environmental Health team,
Renfrewshire Council’s Housing team and 3 Housing Associations.
Page 94 of 120

Page 95

PUBLIC
These organisations/services all have a role in the identification and
replacement of lead piping.  
____________________________________________
5. Regulation of Drinking Water Quality in Scotland
5.1  The Drinking Water Quality Regulator for Scotland (DWQR) is the
independent regulatory body responsible for ensuring that drinking
water in Scotland is safe for consumption. Its remit covers both public
water supply, provided by Scottish Water, and private water supplies. In
relation to the public water supply, the DWQR monitors the quality of
water samples taken by Scottish Water, verifies that samples are being
taken and analysed in accordance with regulatory requirements, and
inspects Scottish Water’s assets and operational activities. The
regulator also oversees the investment programme and has powers to
serve enforcement notices where serious breaches of regulations have
occurred. 
5.2  In respect of private water supplies, the DWQR reports on water quality
performance and ensures that local authorities are effectively
discharging their regulatory responsibilities within their respective
areas. Furthermore, the DWQR ensures that accurate and impartial
information on drinking water quality in Scotland is available and
promotes the use of scientific evidence to inform regulation, policy and
practice.
5.3  The Water (Scotland) Act 1980, sets the duties relating to water supply
and water quality in Scotland. It defines the responsibilities of the water
authority (Scottish Water), Scottish ministers and local authorities. The
Act details that the water authorities (Scottish Water) must supply safe,
wholesome water for domestic purposes. It makes it a criminal offence
to supply water unfit for human consumption. It also places a
responsibility on Scottish ministers to take action if Scottish Water fails
to supply wholesome water, unless the failure is trivial or Scottish
Water is trying to remedy it. 
5.4 The Act also places a duty on local authorities to take appropriate steps
to stay informed on the wholesomeness of the public and private water
supplies in their area. If the local authority is unsatisfied with the
wholesomeness of the public water supply, they must first notify
Scottish Water and if not satisfied with remedial actions, then report to
the DWQR. Local authorities also have a duty to ensure that
improvements are made to private water supplies where necessary.
__________________________________________
Page 95 of 120

Page 96

PUBLIC 
6. Role of Scottish Water
6.1 The Lead Officer engaged with Lorna Macarthur, Technical Team
Leader of the Water Strategy Team and Robyn Dunne, Senior Service
Planner in the Water Strategy Team at Scottish Water. 
6.2 Scottish Water has a statutory duty under section 76A of the Water
(Scotland) Act 1980 to provide wholesome water for domestic use,
supported by relevant secondary legislation. “Wholesomeness” is
defined through the Public Water Supplies (Scotland) Regulations 2014
(as amended), which establish quality standards, including limits for
substances such as lead at the consumer’s tap. Scottish Water is
therefore responsible for ensuring that any pipework under its control is
free from lead, including both the water mains and the communication
pipe. The communication pipe runs from the mains pipe to the property
boundary. Any pipes from the stopcock at the property boundary to
inside the property and any internal pipework is the responsibility of the
property owner (or by the number of owners for the common elements
of a shared supply). 
6.3 Scottish Water carries out a sampling programme for lead in drinking
water. Each year they carry out approximately 4500 samples in
Scotland. For each property sampled, 2 samples are taken from kitchen
cold tap, the first sample is the 1st draw and a second sample from the
tap once flushed. The 1st draw sample will contain the water that has
been in the pipework for an extended period and exposed to potential
leaching of lead from internal plumbing.  The flushed sample contains
fresher water from the communications or mains pipe. If the first draw
sample exceeds the lead standard but the flushed sample complies,
this indicates that the source of lead is most likely within the property’s
plumbing system rather than from the mains supply.
6.4 Since 2023 the samples have been collected using a risk-based system
following a statistical survey completed in 2012. The survey allocated
‘estimated risk zone’. The area of each zone is based around a water
treatment works so is not necessarily assigned to a town or local
authority area. Based on the estimated level of risk, a set number of
samples is allocated to each zone at the start of the year. These
samples are then collected randomly within the designated zone.
6.5 Prior to 2023, samples were collected based on population size. Since
the introduction of the new risk-based system, the number of samples
taken has increased fourfold. The results of these samples are
published in the DWQR annual report (Annual Report). 
Page 96 of 120

Page 97

PUBLIC
6.6 The Public Water Supplies (Scotland) Regulations 2014 specifies
acceptable levels of certain elements and substances in drinking water.
It sets the maximum acceptable level for lead as 10 μg/l. 
6.7  In the event of a sample failure, Scottish Water carry out an inspection
of the connection to the public water mains (i.e. the side of the
boundary stopcock for which Scottish Water is responsible). Any lead
fittings or pipes found in this area are replaced and the drinking water
resampled.
6.8 Scottish Water’s Public Health Team issue a customer notice to the
address where the sample was taken. The letter advises of the failure
and recommends the resident investigates whether any pipe work
within their area of responsibility (i.e. internal pipe work and pipe work
within the property boundary) is lead and arrange for it to be replaced.
It also recommends using bottles water or flushing for 1-2 mins prior to
using the water, until the issue is resolved.  If the property is part of a
shared block a further customer notice is sent to the other addresses
within the same block to advise of the sample failure and provide
advice.
6.9 Scottish Water’s Public Health Team also issue an event notice to the
local authority (Environmental Health) and NHS board (Health
Protection) for that property.
6.10 If the sample result is between 5-10 μg/l, Scottish Water’s Public Health
team send an advisory letter to the address sampled. Scottish Water
has advised that the regulatory limit is anticipated to decrease from 10
µg/l to 5 µg/l in the coming years, and its procedures will be updated
accordingly.
6.11 In addition to the routine sampling, additional samples will be
completed by Scottish Water if a customer request is received. There is
no charge for customer requested samples. 
6.12 No grants are available from Scottish Water for homeowners to assist
replacement of lead pipes within their property. 
6.13 Samples results for Renfrewshire postcodes between 1st December
2021 - 11th May 2026 (Renfrewshire Postcodes):
Total samples taken: 1351
Total samples >3 µg/l: 48
Total samples >5 µg/l: 30
Total Samples >10 µg/l: 14
Page 97 of 120

Page 98

PUBLIC
6.14 A review of the Scottish Water and Drinking Water Quality Regulator
public websites on lead in water was undertaken by the Lead Officer.
Both were found to offer clear guidance, supported by factsheets,
videos, and visual materials. They also included information on how
members of the public could request water sampling from Scottish
Water if there were concerns regarding lead in their water pipes.
___________________________________________ 
7. Role of Environmental Health 
7.1  The Environmental Health team within Renfrewshire Council and other
local authorities play an important part in mitigating the risk from lead
piping within housing. For this report the Lead Officer engaged with
Renfrewshire Council’s Environmental Health team within Environment,
Housing and Infrastructure. Their role in relation to Private Water
Supplies is detailed in Section 8 of this report, this section focusses on
public supplies. 
7.2 If a drinking water sample fails the lead standard, Scottish Water
notifies the address from which the sample was taken. However, where
the property is not owner-occupied, Environmental Health assists in
ensuring that this information is passed on to the property owner who is
ultimately responsible for any identification and replacement of the lead
pipes.
7.3 Where the sample failure has occurred in a Renfrewshire Council
property, the Environmental Health team will notify the Housing team.
Similarly, where the sample failure occurs in a Housing Association
property or a privately rented property, the Environmental Health team
will notify the relevant organisation/owner, advise them of their
responsibilities, provide guidance and encourage that they take
appropriate action. 
7.4 In Scotland, all houses must meet a minimum standard to be
considered fit for human habitation. This is called the Tolerable
Standard as set out in the Housing (Scotland) Act 1987 s86. One of
these standards states that ‘the property must have an adequate piped
supply of wholesome water within the house’. A drinking water sample
failure due to lead would constitute a failure of this standard and the
property would be considered to be below the Tolerable Standard. 
7.5 If the Environmental Health team are made aware that a house is
below the Tolerable Standard due to lead piping in the property, they
Page 98 of 120

Page 99

PUBLIC
can take action to require the owner of the property to take steps, within
a reasonable time period by serving a Works Notice. However, in
practice, an advisory and supportive approach is generally taken in the
first instance with owner occupied properties, with owners encouraged
to replace lead pipework and take interim measures to reduce any
potential risk to health.
7.6 Local authorities also have powers to serve a Closing or Demolition
Order on properties which do not meet the Tolerable Standard. These
notices require the property to be vacated or demolished and would
only be served in extreme circumstances. This would not be
appropriate in response to lead pipes within a property as pipe
replacement would bring the property up to standard and alternative
measures can be used in the interim (such as flushing the water before
drinking or using bottled water). 
7.7 Renfrewshire Council’s Environmental Health team will provide advice
and information on sampling if they are contacted by a member of the
public. In the last 5 years the Environmental Health team has received
and responded to four enquiries from members of the public regarding
concern of lead pipes within their private property. 
7.8 Sampling and support is also provided by Environmental Health, when
requested by NHS GGC Public Health Protection unit, where an
individual has elevated blood lead levels of lead. Environmental Health
will take water samples and other samples as required to assist in the
investigation. 
7.9  A review of the Renfrewshire Council’s public website on ‘Lead in
Drinking Water’ was undertaken by the Lead Officer. The website
contained information on practical steps to reduce lead in drinking
water if there was lead pipes present and contact information for
Environmental Health. 
___________________________________________ 
8. Private Water Supplies
8.1 In Scotland, a private water supply (PWS) is any drinking water supply
not provided by Scottish Water. These supplies are regulated under
The Water Intended for Human Consumption (Private Supplies)
(Scotland) Regulations 2017 and The Private Water Supplies
(Scotland) Regulations 2006. Local authorities must keep a register of
private supplies in their area. Some PWS are classed as ‘regulated
Page 99 of 120

Page 100

PUBLIC
supplies’ - such as those serving commercial or rented premises, more
than 50 people, or more than 10m³ per day. These supplies are
regulated under The Water Intended for Human Consumption (Private
Supplies) (Scotland) Regulations 2017 which replaced The Private
Water Supplies (Scotland) Regulations 2006 for regulated supplies.
Local authorities’ Environmental Health team must carry out a risk
assessment and monitoring, typically sampling at least annually for
each regulated supply. Responsibility for maintaining the supply,
ensuring the water is safe, and notifying users when there is a potential
risk to health rests with the owner of the property or properties. The
Environmental Health team can investigate and require improvements
through enforcement action if required. 
8.2 In Renfrewshire there are 15 regulated supplies, and they are sampled
annually by the Environmental Health team for a number of criteria
including lead. The Water Intended for Human Consumption (Private
Supplies) (Scotland) Regulations 2017 sets a limit of 10 μg/l of lead in
drinking water samples. The owners of the properties are charged for
these samples as they are generally commercial properties. 
8.3 If Renfrewshire Council’s Environmental Health team identifies that a
regulated water supply sample has failed for lead, the result is first
communicated verbally to the property owner, followed by formal
confirmation in writing. The owners are advised that the water should
not be consumed, and they should seek further advice from Public
Health Protection Unit (PHPU) at NHS GGC. The owners are asked to
investigate the presence of lead piping and replace as necessary.
Environmental Health will carry out a resample to check that the
appropriate works have been carried out. There can be multiple
properties on the same supply, and the Environmental Health team will
also notify the other property owners and provide advice. The failure
will also be reported to NHS PHPU and the Environmental Health team
will follow the guidelines set out in PHS Public health management of
elevated lead levels in drinking water. 
8.4  If a sample fails, the property owner can apply for a PWS improvement
grant to assist with carrying out the necessary remedial works. The
grant is set at £800 per property by the Scottish Government. The grant
is applied through the local Environmental Health team but funded by
the Scottish Government. 
8.5 Under The Water Intended for Human Consumption (Private Supplies)
(Scotland) Regulations 2017 local authorities have the power to serve
various notices on relevant persons to require improvements of a PWS.
Non-compliance with these notices is an offence and if convicted, the
Page 100 of 120

Page 101

PUBLIC
individual is liable for an unlimited fine. Renfrewshire Council’s
Environmental Health team will use these notices following a lead
sample failure, where appropriate, however this has not been required
to date. In the first instance, the Environmental Health team will seek to
resolve matters through an informal advisory approach.
8.6 There are 82 Type B (or not regulated) PWS in Renfrewshire, these
supplies are regulated under The Private Water Supplies (Scotland)
Regulations 2006 and not routinely sampled. They are sampled upon
request, if a concern is raised, the house is sold, or they apply for a
grant where a sample is relevant. 
8.7  Renfrewshire Council’s Environmental Health service has recorded
lead failures at two properties served by PWS within the last five years.
One property, which failed a sample in 2025, has remained unoccupied
and therefore no further action has been taken. The second property,
which failed a sample in 2024, has since undertaken improvements and
achieved a satisfactory result on resampling.
___________________________________________ 
9. Privately Rented Properties 
9.1 Local authority Environmental Health services have additional powers
to address lead piping issues in privately rented properties. Private
landlords are required to register with their local authority under the
Antisocial Behaviour etc. (Scotland) Act 2004, and this requires the
landlord to be "fit and proper". Landlord registration: statutory guidance
for local authorities 2017 published by the Scottish government states
that Local Authorities must consider if the landlord has contravened any
provision of housing law or landlord and tenant law, material which
relates to any acts of the relevant person regarding antisocial behaviour
affecting the house and repairing standard enforcement orders.
Therefore, if the landlord has failed to comply with relevant housing law
the landlord’s registration could be refused or revoked. When
Renfrewshire Council’s Environmental Health service considers that a
landlord does not meet ‘fit and proper’ standard they will apply to the
Regulatory Functions Board to refuse/revoke the landlord’s registration,
if refused/revoked a Rent Penalty Notice can be served. For the period
the notice is in force, no rent is payable by the tenant for that property. 
9.2  In addition to the registration requirements, all privately rented
properties, unless specifically exempt, are required to comply with the
Repairing Standard as set out in Chapter 4 of the Housing (Scotland)
Page 101 of 120

Page 102

PUBLIC
Act 2006 throughout the duration of a tenancy. This legislation is
supported by the statutory guidance document Repairing Standard:
statutory guidance for private landlords, published by the Scottish
Government, which came into force in March 2024 and strengthened
the requirements in relation lead piping in rented properties. The
statutory guidance states – 
‘In order to comply with the Repairing Standard, lead pipes and lead
lined storage tanks or fittings should not be present in the drinking
water supply of any privately rented property from the boundary
stopcock to the kitchen tap. This includes: drinking water outlets,
pipework to drinking water outlets, water storage tanks within the
dwelling and water storage tanks in the loft space, including any
common storage tanks located in tank rooms or in the roof space.’
Unless the landlord is unable to replace the pipes, due to lack of
consent from other owners, lead pipes and tanks must be removed to
comply with the Repairing Standard.
9.3  The Repairing Standard now also puts an onus on private landlords to
check visible pipework within the house to assess whether the supply
runs through lead pipes, gives advice on how to do this and information
on sampling requirements. Private landlords are also required to notify
and provide advice to the tenant if they are aware or uncertain of the
risk from lead pipes in the property. 
9.4  If a privately rented property is found not to comply with the Repairing
Standard, an application can be made to the First Tier Tribunal (FTT)
for Scotland (Housing and Property Chamber). This can be made by
either the tenant or the local authority on their behalf. Renfrewshire
Council’s Environmental Health service will apply for a tenant where
they believe the tenant to be vulnerable or not having the capacity to
undertake the referral process on their own. The FTT can enforce
repairs by issuing a Repairing Standard Enforcement Order (RSEO) to
the landlord. It is a criminal offence to fail to carry out repairs required
under an RSEO without reasonable excuse. If the tribunal decides
there has been a failure to comply with the RSEO, the tribunal will send
a copy of the failure to comply decision to the local authority, who can
decide to carry out work and recover costs from the landlord. If there is
a tribunal decision that the private landlord has failed to comply with
the RSEO, the tribunal may also issue a Rent Relief Order restricting
the rent payable until the RSEO has been complied with. The FTT can
refer the case to Police Scotland if the landlord does not comply with
the RSEO.
Page 102 of 120

Page 103

PUBLIC
9.5 Renfrewshire Council Environmental Health have received zero
complaints regarding non-compliance with the Repairing Standard due
to the presence of lead pipes, since the changes to the Repairing
Standard were introduced.  
___________________________________________ 
10. Next Steps
10.1 The next stage of the review will focus on the current arrangements
within the Public Sector, in council owned properties and Housing
Associations. The Lead Officer will review the relevant legislation and
standards relevant to the public sector and liaise with representatives
from this group. 
10.2 The Lead Officer will engage with a representative of NHS GGC PHPU
to gain insight into their role in addressing the health risks from lead
piping.
10.3  The Lead Officer will review the grants available from Renfrewshire
Council and other local authorities to replace lead piping within
housing. 
Page 103 of 120

Page 104

PUBLIC
___________________________________________________________________
Implications of the Report
1. Financial - none 
2. HR & Organisational Development – none 
3. Community/Council Planning –  
• Our Renfrewshire is well – this review of lead piping within housing in
Renfrewshire will highlight strategies, information and actions being taken by
relevant agencies to identify and remove/mitigate the impacts of lead pipework in
drinking water supplies. This will make this safer for our residents 
4. Legal – None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights - 
(a) The Recommendations contained within this report have been
assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for
infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report. If
required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed
and monitored, and the results of the assessment will be
published on the Council’s website.   
8. Health & Safety - None
9. Procurement - None
10. Risk - None
11. Privacy Impact - None 
12. Climate Risk - None
13. Children’s Rights - None
14. Cosla Policy Position - None
_______________________________________________________
Page 104 of 120

Page 105

PUBLIC
List of Background Papers- 
Review of Lead Piping in Public and Private Housing -Audit, Risk and Scrutiny
Board, May 2026 
___________________________________________________________________ 
Author:           Rachael Flanagan  
Lead Officer – Environmental Health 
Rachael.flanagan@renfrewshire.gov.uk   
Page 105 of 120

Page 106

No embedded text on this page.

Page 107

PUBLIC 
___________________________________________________________________
To:  Audit, Risk and Scrutiny Board 
On:  17 August 2026
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Accounts Commission: Transformation: How councils are redesigning
and delivering more efficient services
___________________________________________________________________
1. Summary 
1.1 This paper provides an overview of the Accounts Commission
publication, “Transformation: How councils are redesigning and
delivering more efficient services”, published in May 2026. The
publication sets out a high-level view of Scottish councils’
transformation progress, with analysis of different transformation
arrangements in councils. This paper also notes the current position of
Renfrewshire Council’s transformation activity.   
1.2 The publication sets out the Accounts Commission’s assessment, as
well as its expectations of councils, with a Supplement detailing case
study examples of positive practice. This includes Renfrewshire Council
being highlighted in the “Transformation funding” section for its
approach to supporting transformation activity through the Service
Modernisation and Reform Fund, as well as in the “managing projects
and programmes” section for its governance arrangements through the
refreshed Transformation Board. 
Item 5
Page 107 of 120

Page 108

PUBLIC
1.3 Key messages from the Accounts Commission analysis 
• Recognition of the significant challenges facing Scottish councils,
and an expectation for councils to move beyond incremental
savings towards whole-system transformation, in order to secure
financial sustainability and meet increasing demand. 
• The importance of setting out how transformation activity will
support future financial sustainability, and linking this with strategic
priorities and wider plans through monitoring and reporting. In the
Accounts Commission view there is variance across the sector, with
some councils showing progress, while in others, they assess that
oversight arrangements are not always clear or comprehensive
enough to fully inform leadership and scrutiny responsibilities. 
• Recognition of challenges relating to workforce capacity and skills,
highlighting that many councils need to improve workforce capacity
to make better progress with transformation.
• Positive examples of partnership working, highlighting challenges
relating to funding, capacity and resources, as well as governance
and data sharing issues. 
• Examples of consultation with communities, however the Accounts
Commission analysis highlights that it is often not clear how
engagement has been reflected in service redesign proposals, as
well as variance in the articulation of financial impacts and wider
benefits of transformation activity.
• The publication highlights inconsistencies in councils’ approaches
to identifying, assessing, and monitoring the impact of
transformation activities on vulnerable and protected groups, noting
the risks of not fully embedding Equality Impact Assessments in
planning and monitoring processes.
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that members of the Audit, Risk and Scrutiny Board:
• Note the contents of this paper.
_________________________________________________________ 
3. Background 
3.1 Since 2022, auditors have undertaken thematic Best Value audit work
alongside annual audit work for Scottish councils. This includes reports
Page 108 of 120

Page 109

PUBLIC
focused on leadership, responding to workforce challenges, and
transformation in councils. Local transformation was the theme audited
in 2024/25, with management reports provided to each council. This
latest publication draws on the management reports of 22 councils
available at the time of drafting, including Renfrewshire Council. 
3.2 The Accounts Commission publication references work being
progressed at a national level, including the local government
transformation programme launched in 2023 by Society of Local
Authority Chief Executives (SOLACE) and the Improvement Service
(Delivering a future for Scottish Local Authorities). The report provides
an update on the three workstreams, including that a draft report on
public service reform from a local government perspective will be
published in summer 2026, and a national self-evaluation framework
will be piloted with four councils over 2026/27. 
4. Summary of Key Findings from the Accounts Commission Report 
Transformation Planning 
4.1 The Accounts Commission assessed the extent to which councils have
clear transformation plans, linked to their priorities, supporting long-
term financial sustainability. Its analysis found that the quality and
availability of detail on the financial and non-financial impact of projects
was varied across councils, with over a third of their sample not
sufficiently determining the financial impact of their transformation
plans, and half of the sample not clearly setting out anticipated financial
impacts. Its assessment is that most councils in the sample need to
improve how they identify, monitor, and report on wider benefits. 
4.2 In terms of transformation funding, the Accounts Commission report
recognises the challenges councils face in planning for the long-term.
Renfrewshire Council’s Service Modernisation and Reform Fund is
used as a good-practice case study example in the publication, with the
Accounts Commission noting that it supports services in implementing
change, and funds development costs for projects that are expected to
bring long-term benefits. 
4.3 The Accounts Commission states its expectations that councils need to
ensure their transformation plans: 
• are sufficiently ambitious;
• are clearly linked to wider strategic plans and priorities;
Page 109 of 120

Page 110

PUBLIC
• clearly set out details around implementation, monitoring, and
reporting;
• clearly set out planned savings, linking these to financial plans. 
Programme Management 
4.4 Section 3 of the publication assesses councils’ programme
management arrangements, and the extent they facilitate effective
oversight of transformation plans. They do not consider that all councils
have clear strategic oversight of all transformation activity, and that
more comprehensive reporting of planned benefits is required to
support effective management and scrutiny. The Accounts Commission
highlight the role elected members have in supporting and scrutinising
transformation, and that open and effective collaboration is critical
when making difficult decisions that transformation work involves. The
Accounts Commission believe that many councils need to improve
workforce capacity to make better progress with transformation,
although they note there are strong examples of councils managing
this effectively. 
4.5 In relation to managing projects and programmes, Renfrewshire
Council is included as a case study in the Supplement. The refreshed
Transformation Board arrangements are highlighted as an example for
providing strategic oversight of the Reshaping Renfrewshire
transformation programme, as well as its wider governance and
monitoring arrangements. 
4.6 The Accounts Commission expectations relating to programme
management are summarised below. These are that Councils need to
ensure: 
• clear oversight at a strategic level of all transformation activity;
• effective engagement with councillors, with comprehensive
reporting on transformation initiatives;
• regular review of workforce capacity (time, availability and skills) to
plan, manage and deliver transformation plans;
• strategic planning and allocation of workforce capacity to support
transformation activity;
• transformation plans set out appropriate success measures. 
Page 110 of 120

Page 111

PUBLIC 
Partnership Working, Community Engagement, and Impacts 
4.7 The Accounts Commission reviewed the extent that partners and
communities are involved in transformation plans, and the
consideration of the impact on vulnerable or protected groups. Their
findings note there are many positive examples of partnership working,
but that most of these are on the margins in terms of transformation. In
their view, there is limited evidence of how community engagement has
influenced project design and delivery, and they highlight that a quarter
of the councils in their sample need to develop more consistent
processes for equality impact assessments. Their review of the audit
reports concludes that councils are often failing to report progress on
transformation activity clearly and transparently. 
4.8 The Accounts Commission expectations relating to this theme are
summarised below. Councils need to ensure:  
• opportunities to work in partnership or to share services continue to
be sought;
• they clearly document how community engagement, data, and
equality impact assessments have influenced plans and
implementation;
• they have arrangements in place to effectively monitor and report the
impacts of transformation activities. 
5.  Renfrewshire Council Transformation Activity 
5.1 The findings of the Best Value thematic work on transformation in
Renfrewshire, carried out by external auditor Azets, were reported to
Audit, Risk and Scrutiny Board in September 2025. The report was
positive, reflecting good practice across a range of areas. Azets
concluded that effective and appropriate arrangements are in place for
two of the four elements stated at 1.3 in the cover report, with some
scope for minor improvements in relation to the other two. The two
recommendations from the Azets report were added as actions to the
Corporate Improvement Plan, and both are now complete and closed
off, with detail provided in an update to Leadership Board in February
2026. Progress on the Corporate Improvement Plan continues to be
reported to Leadership Board as part of ongoing reporting
arrangements to Best Value, with the next update in September 2026. 
5.2 An update on Reshaping Renfrewshire – Transformation and Change
programme was presented to Leadership Board in February 2026,
providing an overview of progress since the February 2025 update,
primarily focusing on areas with relevant and substantive progress,
Page 111 of 120

Page 112

PUBLIC
including the Digital Strategy, Connected Communities, and Place
Based programmes such as the Learning Estate Strategy. The
Transformation Board (officer group), highlighted as good practice in
the Accounts Commission publication, continues to provide strategic
oversight of the Reshaping Renfrewshire programme, with senior
officers across the Council reviewing progress of all major projects and
programmes across the organisation. 
5.3 The Council continues to involve our citizens and partners in our
transformation plans through a wide range of ongoing consultation and
engagement activities. For example, our Resident Research over the
past 12 months has empowered citizens to identify their priority areas
through a mix of online, face to face and telephone surveys, and then
explore this further through focus groups including those targeted
towards groups who may be under-represented. This phase had a
particular grounding in the Council’s financial sustainability and difficult
decisions to address the budget gap for local government. 
5.4 Moving into a further phase of engagement, the Council recently
launched the Your Voice Matters engagement programme, which
seeks to have valued conversations with our citizens about the things
that matter to them most and their vision for a future Renfrewshire.
While this has only recently been launched, to date over 100 face to
face conversations have already taken place with our citizens, and
these have been constructive, rich and insightful. There will be further
themed conversations with a wide range of stakeholders and partners,
including the Council’s workforce. This engagement and the earlier
Resident Research will shape our Council and Community Plans and
will also be used by the HSCP to inform their Strategic Plan. 
5.5 Regular updates on individual workstreams of the Reshaping
Renfrewshire programme continue to be provided to relevant Policy
Boards, and regular reports on the transformation programme as a
whole continue to be brought to Leadership Board, alongside the
financial reporting to Council and the Finance, Resources and
Customer Services Policy Board.
___________________________________________________________________
Implications of the Report 
1. Financial – none
2. HR & Organisational Development - none
3. Community/Council Planning – none
4. Legal - none
5. Property/Assets – none
6. Information Technology – none
Page 112 of 120

Page 113

PUBLIC
7. Equality & Human Rights - the recommendations within this report
have not been assessed in relation to their impact on equalities and
human rights as the report sets out a high-level view on local
government progress on transformation, and is for noting only. 
8. Health & Safety – none
9. Procurement – none
10. Risk – none
11. Privacy Impact – none
12. Climate Risk –not applicable
13. Children’s Rights –not applicable
14. COSLA Policy Position –not applicable
_______________________________________________________
List of Background Papers
___________________________________________________________________ 
Page 113 of 120

Page 114

Page 114 of 120

Page 115

PUBLIC 
___________________________________________________________________
To:  Audit, Risk and Scrutiny Board 
On:  17 August 2026
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Audit Scotland: Local Government Budgets 2026/27
___________________________________________________________________
1. Summary 
1.1 Audit Scotland published its report Local Government Budgets 2026/27
in June 2026; this is the third such annual report summarising the key
issues from their analysis of budgets agreed by Scotland’s 32 councils
for 2026/27.  This paper provides an overview of that report. 
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that members of the Audit, Risk and Scrutiny Board:
• Note the contents of this report;
• Note that this report will also be provided to the IJB Audit, Risk
and Scrutiny Committee for their meeting on 14 September
2026.
_________________________________________________________ 
3. Background 
3.1 This is the third annual Audit Scotland briefing on Local Government
Budgets, which provide an analysis of council budgets across Scotland,
as well as how councils are addressing the challenges faced in
achieving a balanced budget and longer-term financial sustainability. 
Item 6
Page 115 of 120

Page 116

PUBLIC
Their latest briefing, looking at budgets for 2026/27, also covers the
pressures arising from social care demand, and the importance of
meaningful consultation with communities as councils consider savings
options. 
4.  Key Findings of the Local Government Budgets 2026/27 Briefing 
Scottish Government funding to councils 
4.1 The Audit Scotland briefing notes a slight increase in real terms funding
for Scottish councils in 2026/27 and that the overall settlement for the
year is likely to change through the autumn and spring budget
revisions, as it has in previous years.  Total revenue funding in real
terms for the sector rose from £14,686m in 2025/26 to £15,687m this
year, whilst total capital funding fell from £783m to £669m. 
4.2 The report notes that a number of previously ring-fenced grants have
been baselined into the General Revenue Grant (GRG) in recent years,
in line with the principles of the Verity House Agreement.  The report
also states that an increase in non-domestic rates (NDR) has driven
the increase. However, the auditors also note that GRG must still be
used for a number of existing commitments (such as the allocation for
teacher pay) and so are limited in their flexibility. 
4.3 Audit Scotland report that the Scottish Spending Review, published
alongside the draft 2026/27 Scottish Budget, shows a reduction in
revenue funding for local government in 2027/28 and 2028/29, with
authors concluding that councils will need to look for additional savings
to remain financially sustainable in the face of cost pressures and
continued rising demand for services.  Capital funding is also set to
reduce further.  The Spending Review deals with overall spend and
does not indicate what future settlements would be for each council. 
Council budgets 
4.4 Almost 60% of council funding comes from the GRG, with most of the
remainder coming from Council Tax or non-domestic rates.  In
2026/27, almost 1% of funding will be through use of remaining
reserves. 
4.5 In their report, Audit Scotland note that the allocation of funds to
Integration Joint Boards accounts for around 24% of all local
government revenue spending in 2026/27.  They refer to earlier reports
on “the critical financial pressures facing IJB”; the combined savings
Page 116 of 120

Page 117

PUBLIC
necessary in 2026/27 total £179m, of which £103m is within social care
services.  The report notes that the total reserves held by IJBs is now
less than the combined budget gap.  Additional uplifts from partner
organisations (councils and health boards) can only provide short-term
stability.  The report further notes that Perth and Kinross IJB have
approved a Financial Recovery Plan and that North Ayrshire Council
has moved to a ‘critical only’ threshold for adult social care support as
a means of managing financial pressures. 
4.6 The Audit Scotland briefing provides a chart showing the scale of
budget gaps as a percentage of General Fund Revenue, with only one
council (South Lanarkshire) not facing a deficit.  Of the remainder,
Renfrewshire Council has the second lowest forecast budget gap for
2027/28 as a percentage of the revenue budget; the estimated gap of
£5m equates to less than 1% of total revenue.  At the other end of the
scale, East Dunbartonshire has a potential gap of £23.1m, over 6% of
its revenue budget.  The cumulative budget gap over the next three
years, up to the end of 2028/29 for Scottish local authorities is
projected to reach almost £1bn. 
4.7 More than one-third of funding to address the budget gaps will come
from increases to Council Tax, and a further 27% from recurring
savings.  Almost 20% will come from use of reserves. In considering
the measures to address budget gaps, the auditors stress that non-
recurring measures, such as leaving posts vacant or delaying
expenditure, do not support long-term sustainability and they believe
councils must prioritise recurring measures in order to deliver lasting
savings.  The report states that the ongoing use of reserves to fund
investment or address financial pressures is not sustainable. 
4.8 The report notes that the savings measures cumulatively are worth
almost £180m, the majority of which are recurring savings.  Savings
continue to be weighted towards corporate services, environmental
services, economic development and culture and leisure in order to
protect statutory services like education and social work. 
4.9 All 32 councils increased Council Tax in 2026/27 with percentage
increases ranging from 4% to 10%.  All councils also increased their
fees and charges for those services which are chargeable.  Seventeen
councils also introduced new fees and charges, though three reduced
the number of services they charge for.  The report states that around
6.7% of council revenue funding is raised from these fees and charges. 
Page 117 of 120

Page 118

PUBLIC
4.10 Capital expenditure continues to be largely funded by borrowing, and
this is also the case for spending from the Housing Revenue Account. 
4.11 The report includes a useful diagram setting out some of the factors
considered by councils when projecting their future revenue budget
gaps, including future pay settlements, expected inflation, and
expected levels of demand for services. 
Consulting with Communities 
4.12 The Accounts Commission briefing highlights that as councils continue
to make difficult decisions, it is more important than ever that local
communities are involved in the decisions that impact their services. 
4.13 The briefing notes that 27 councils consulted with residents on their
2026/27 budgets.  Most outlined the financial pressures they were
facing and sought views on priorities, and/or on possible savings
options.  Most engagement was conducted online though there were
also examples of in-person engagement through community meetings,
roadshows and workshops.  Renfrewshire Council conducted its
Resident Research programme in 2025 and findings were reported to
the Leadership Board and are also available on the Council’s website. 
4.14 Auditors consider that councils should use a range of methods in their
engagement and consultation activity to ensure wider participation and
the inclusion of those groups who are less-heard or under-represented. 
___________________________________________________________________
Implications of the Report 
1. Financial – none, though the report references national trends in
relation to local government finance 
2. HR & Organisational Development - none 
3. Community/Council Planning – none  
4. Legal - none 
5. Property/Assets – none 
6. Information Technology – none 
Page 118 of 120

Page 119

PUBLIC
7. Equality & Human Rights - the recommendations within this report
have not been assessed in relation to their impact on equalities and
human rights as the report concerns a national briefing on local
government finance and is for noting only.   
8. Health & Safety – none 
9. Procurement – none 
10. Risk – none 
11. Privacy Impact – none 
12. Climate Risk –not applicable 
13. Children’s Rights –not applicable. 
14. COSLA Policy Position –not applicable.
_______________________________________________________
List of Background Papers 
None 
___________________________________________________________________ 
Page 119 of 120

Page 120

Page 120 of 120