To: Audit, Risk and Scrutiny Board
On: 19 January 2026
___________________________________________________________________
Report by: Chief Auditor
___________________________________________________________________
Heading: Summary of Internal Audit Reports for period 01 October to 31
December 2025
___________________________________________________________________
1. Summary
1.1 In line with the Public Sector Internal Audit Standards, Internal Audit
must communicate the results of each engagement to the Board. To
comply with this requirement, Internal Audit submits regular reports on
the findings and conclusions of audit engagements to the Audit, Risk
and Scrutiny Board. 
1.2 Appendix 1 provides details of audit engagements completed during
the period 01 October to 31 December 2025 with the overall assurance
rating and the number of recommendations in each risk category. The
committee summary for each report is also attached. For each audit
assignment where recommendations have been made, the relevant
managers have put action plans in place to address the issues raised. 
1.3 In addition to the reports listed in the Appendix, Internal Audit has an
ongoing commitment to: 
• A range of corporate and service initiatives;
• Progressing of information security matters in partnership with
ICT and Legal Services;
• The regular provision of advice to departmental officers;
• The provision of internal audit services to the associated bodies
for which Renfrewshire Council is the lead authority and to
OneRen and Renfrewshire Integration Joint Board;
• Co-ordination of the Council’s corporate risk management
activity;
• Management of the counter fraud team;

Page 2

PUBLIC
• Management of the risk management and insurance team.
___________________________________________________________________ 
2. Recommendations
2.1 Members are invited to consider and note the Summary of Internal Audit
Reports finalised during the period from 01 October to 31 December 2025. 
___________________________________________________________________
Implications of the Report
1. Financial - None 
2. HR & Organisational Development - None 
3. Community Planning – 
Safer and Stronger - effective internal audit is an important element of good
corporate governance. 
4. Legal - None 
5. Property/Assets - None 
6. Information Technology - None 
7.  Equality & Human Rights – None 
8. Health & Safety – None
9. Procurement - None 
10.  Risk - The summary reported relates to the delivery of the risk-based internal
audit plan. 
11. Privacy Impact – None 
12. COSLA Implications – None 
13. Climate Risk – None 
14. Children’s Rights - None 
________________________________________________________________
Author:           Karen Campbell, Chief Auditor– 07768354651

Page 3

PUBLIC
Appendix 1 
Renfrewshire Council 
Internal Audit Service 
Update for Audit, Risk and Scrutiny Board 
Final Audit Reports issued from 01 October – 31 December 2025 
Category  Service  Engagement  Assurance
Rating
Recommendation Ratings
Critical Important Good
Practice
Service
Improvement
Governance Children’s Services
Governance of
Learning Estate
Investment Programme 
Reasonable 0 0 2 0
Assurance
Chief Executive’s/
Environment, Housing
and Infrastructure
Surplus Building
Security Limited 2 4 1 0

Page 4

PUBLIC 
Assurance Level 
Substantial Assurance • There is a sound system of internal control designed to achieve the objectives of the area being reviewed. 
• The control processes tested are being consistently applied. 
Reasonable Assurance • The internal control processes are generally satisfactory with some areas of weakness being identified that could
put some objectives of the area being reviewed at risk.
• There is evidence that the level of non-compliance with some of the control processes may put some of the
objectives of the area being reviewed at risk. 
Limited Assurance • Weaknesses in the system of internal controls are such as to put the objectives of the area being reviewed at risk. 
• The level of non-compliance puts the objectives of the area being reviewed at risk. 
No Assurance • Control processes are generally weak with significant risk to the achievement of the objectives of the area being
reviewed. 
• Significant non-compliance with control processes leaves the processes/systems open to error or abuse. 
Recommendation
Rating 
Service Improvement  Implementation will improve the efficiency / housekeeping of the area under review.
Good Practice  Implementation will contribute to the general effectiveness of control.
Important  Implementation will raise the level of assurance provided by the control system to acceptable levels.
Critical  Addresses a significant risk, impacting on the objectives of the area under review.

Page 5

Internal Audit Report
Children’s Services
Governance of the Learning Estate Investment
Programme (B0018/2025/001)
Date: October 2025 
PUBLIC
COMMITTEE SUMMARY 
Audit Objectives
The objectives of the review were to ensure that the Learning Estate Strategy and Delivery Board
(the Board) is operating in line with the Terms of Reference and Governance Framework which was
approved in August 2024 and is effectively monitoring, managing and controlling delivery of the
Learning Estate Programme. This should include ensuring that:
1. There is adequate communication between Services to ensure that a holistic approach is
undertaken to facilitate the delivery of the Programme.
2. Arrangements are in place to ensure that the Learning Estate Delivery Board are receiving
timeous and adequate information to enable delivery of the programme objectives.
3. Regular progress reports are provided to relevant parties including Boards and Corporate
Management.
The Board is a working strategic Board convened of Senior Officers. 
Audit Scope
1. Obtained a copy of the Terms of Reference and Governance Framework in place for the
Learning Estate Strategy and Delivery Board.
2. Prepared a series of tests relevant to the objectives to ascertain the level of compliance with
the Framework
3. The auditor reviewed governance matters reported to the Learning Estate Strategy and
Delivery Board and communications between services for 2 projects. 
Key Audit Assurances
• The Learning Estate Strategy and Delivery Board is operating in accordance with its Terms of
Reference and Governance Framework. The Board demonstrates effective oversight through
structured meetings, documented decisions, and alignment with strategic objectives. Roles,
responsibilities, and delegated authorities are clearly defined and adhered to.
• There is evidence of effective communication and collaboration between key services (e.g.,
Finance, Legal, Property, Education, Communications Services). This supports a holistic and
integrated approach to programme delivery, with regular inter-service engagement and
coordinated planning.
• The Board receives timely, relevant, and comprehensive information to support effective
decision-making. Regular updates include programme status reports, risk registers, financial
summaries, and strategic updates. Issues are escalated appropriately, and decisions are
responsive to current information.
• Regular progress reports are provided to the Education & Children’s Services Policy Board.

Page 6

Internal Audit Report
Children’s Services
Governance of the Learning Estate Investment
Programme (B0018/2025/001)
Date: October 2025 
PUBLIC 
Key Risks
There were no key risks identified during the audit. 
Overall Audit Opinion
The arrangements in place for Governance of the Learning Estate Programme were found to be
robust. The governance, communication and reporting arrangements in place for the Learning Estate
Strategy and Delivery Board are effective and operating as intended. The Board is compliant with its
Terms of Reference and Governance Framework and there is clear evidence of effective monitoring,
cross-service collaboration and timely decision-making. 
It was noted that work has been undertaken by Children’s Services management to improve school
roll projections to enhance Learning Estate planning. 
Two issues were identified which required management action, in relation to the absence of formal
training and awareness sessions on capital monitoring and financing, and a formalised reporting
mechanism to both the Children’s Services Directorate and the Corporate Management Team. 
Management Commentary
These issues have been addressed.  A Learning Estate Team Development Day has taken place
and there are regular knowledge share across all parties involved in the programme as and when
required.  In addition to the regular updates provided to key stakeholders and the  public facing board
papers which are produced, regular updates to the Corporate Management Team and Children’s
Services Directorate have been planned in line with the governance framework.

Page 7

Internal Audit Report
Chief Executive’s/Environment, Housing &
Infrastructure
Surplus Buildings Security - General Security
(A0021/2026/001)
Date: December 2025 
PUBLIC
COMMITTEE SUMMARY 
Audit Objectives
The audit objectives were to ensure that: - 
• There are documented procedures detailing roles and responsibilities in relation to the security
of surplus council buildings which are made known to and are accessible by the appropriate
officers. 
• The appropriate officers are notified as soon as possible that a building is surplus to
requirements and an adequate action plan involving all relevant services is put in place with
designated responsibilities. 
• The buildings are risk assessed, secured promptly and adequate key holding arrangements
are in place. 
• An estimate of costs to keep buildings secure is identified and budgeted for. 
• The required actions, including any arrangements detailed by the council’s insurers, are
organised and promptly carried out by nominated officers to maintain the security of surplus
council buildings. 
• There is adequate management oversight of the processes being followed. 
• Appropriate action is taken to address any security incidents promptly. 
Audit Scope
Interviewed relevant officers to obtain the process in place regarding the security of surplus council
buildings. 
• Prepared a series of tests to meet the above objectives.
• The auditor selected 2 surplus day centres for detailed testing. 
Key Audit Assurances
• For the properties tested, appropriate actions were taken to address security incidents promptly. 
Key Risks
• The lack of documented procedures and action plans can lead to inconsistent processes and
unclear roles and responsibilities when dealing with surplus buildings.
• Where risk assessments for closedown of properties are not documented, there is no evidence
that they have been completed or what work was carried out.
• Where there is no dedicated budget or financial monitoring for surplus buildings, there is a lack
of clear oversight and accountability for these costs.
• When insurance obligations for unoccupied buildings are not met, the insurers may invalidate
the insurance for those properties.

Page 8

Internal Audit Report
Chief Executive’s/Environment, Housing &
Infrastructure
Surplus Buildings Security - General Security
(A0021/2026/001)
Date: December 2025 
PUBLIC
• When management oversight and decisions relating to surplus properties are not recorded,
there is a lack of transparency in the decision-making process. 
Overall Audit Opinion 
The audit highlighted significant weaknesses in the system of internal control.  Although some
actions had been undertaken satisfactorily to complete the closedown and management of the
surplus buildings selected for testing, there was no formal, standardised process followed relating
to this, nor was there an action plan detailing actions to be taken and there was no evidence of risk
assessments being completed. Roles and responsibilities were not clear and there was a lack of
documented oversight of the complete process. Furthermore, the insurance conditions for
unoccupied buildings regarding property inspections were not being met for one of the properties
tested. We were advised that this is the case for many other properties 
Management Commentary
Management within both services are in the process of implementing the audit recommendations
and will apply them to all empty buildings and not just those designated as surplus. A list of all empty
properties is currently being compiled and this will be used to estimate the resource and cost
implications to meet any insurance policy requirements and any additional funding requirements  will
be submitted to the Director of Finance and Resources for review.