___________________________________________________________________ 
To:  Council  
On: 9 May 2024
___________________________________________________________________ 
Report by: Director of Finance and Resources
___________________________________________________________________ 
Heading: Revenue and Capital Budget Update 2024/25
___________________________________________________________________ 
1. Summary 
1.1. On 29 February 2024, the Council set its revenue budget for 2024/25. On that day, the
Band D Council Tax level was set for 2024/25 and a Budget Motion was approved. The
Scottish Government passed the final stage of its 2024/25 budget on 28 February 2024.
This report provides Members with an update to the Revenue Budget 2024/25 following
these additional changes. 
1.2. Appendix 1 outlines the consequential in-year approved Revenue Budget 2024/25 for each
service by cost type. 
2. Recommendations 
2.1 Members are asked:
 to note the report, which reflects the impact of decisions taken by the Council on 29
February 2024 and changes relating to the final Scottish Budget.
 to note the update outlined in section 7 in relation to the Paisley Grammar School
Community Campus project, and agree an increased capital budget of £85.5m
funded through increased LEIP funding and additional Council revenue funding of
£0.2m per annum. Further note the risk to the suggested funding arrangements
until Scottish Ministers formally agree the LEIP Phase 2 funding position as
recommended by the LEIP Board and COSLA.

Page 2

3. Revenue Budget 2024/25: Council Tax 
3.1 At its meeting on 29 February 2024, the Council agreed to freeze Council Tax for 2024/25.
This triggered compensatory funding from the Scottish Government to Renfrewshire
Council of £4.897m. There is no change to any Council Tax band charge for 2024/25. 
4. Revenue Budget 2024/25: Budget Motion 
4.1 A number of initiatives were outlined in the Budget Motion on 29 February 2024, which
amounted to an additional £2.025m of non-recurring (one-off) spend planned for financial
year 2024/25, as follows: 
Description
Budget 
2024/25
£000
Fairer Renfrewshire Funding initiatives 455
Top-up funding to the Scottish Welfare Fund 400
Support for £50 Winter School Clothing payment 300
Continuation of Environment and Place programme 250
Continuation of Environmental Task Force 200
Partnerships with Cultural Bodies 200
Planning Enforcement Officer (2 years) 120
Development of Oakshaw Heritage Trail 50
Support for the School Music Service 25
Public Litter Bin replacement programme 25
Total 2,025
Funded by: 
One-off use of reserves from Welfare Reform Fund 700
One-off use of Financial Sustainability Fund 1,325
Total 2,025   
4.2 On 29 February 2024, the Scottish Government released Local Government Finance
Circular 2/2024. The circular noted a change to the funding for Teacher Numbers, which
has been switched from general revenue funding to specific grant funding. This comes with
specific conditions that must be met in order to receive the £4.801m allocated to
Renfrewshire Council. 
4.3 On 7 March 2024, following the UK Spring Budget, the Deputy First Minister wrote to all
local authorities confirming that additional funding of £62.7m nationally would be baselined
and distributed to those councils who decided to freeze council tax levels for 2024/25.
While individual council allocations have not yet been confirmed, the assumed distribution
is noted in the table at 4.4 below.

Page 3

4.4 The following table was presented as Table 5 in the report to Council on 29 February 2024
with draft figures before the above decisions were taken. It is now updated here to reflect
the impact of the use of reserves and the additional planned expenditure. 
Budget Overview 2024/25 
Draft
Budget 
£000
Revised
Budget
£000
Movement 
£000
Total Government Grant advised1 427,174  427,174 0
Council Tax Income 110,304  110,304  0
Council Tax / Community Charge Arrears  500  500  0
Council Tax Freeze funding confirmed 0 4,897 4,897
Assumed share of £62.7m additional settlement2 0 2,088 2,088
Total Income 537,978  544,963 6,985
Less: Estimated Spending need (recurring) (547,262) (547,262) 0
Recurring Budget (Deficit) / Surplus (9,284) (2,299) 6,985
Less: Estimated Spending need (non-recurring) 0  (2,025) (2,025)
One-off use of Reserves 0  4,324 4,324
In-Year Budget (Deficit) / Surplus (9,284) 0  9,284 
1. Includes assumed share of Teacher Numbers specific grant of £4.801m not yet confirmed
2. Figures are indicated but not yet confirmed by the Scottish Government 
5. Resource Allocations 
5.1 Appendix 1 attached summarises the budget allocation for each service. This is the in-year
position, and includes the total spending need, both recurring and non-recurring. This is
shown both as a subjective analysis (what the budget is spent on) and an objective
analysis (what service the budget is spent in). 
5.2 Budgets are subject to adjustment during the financial year to reflect allocations to services
of inflationary budgets, held at the outset within Miscellaneous Services. During the
financial year policy boards will be asked to approve permanent virements that fall outside
the delegation of Directors, in accordance with the Financial Regulations. 
5.3 In addition, members should note that there will be in-year costs associated with the
opening and early operation of the new Renfrew Bridge which will be incurred in the later
half of the financial year. The full year costs will be incorporated into Council base revenue
budgets from 2025/26, however it is estimated that up to £0.6m may be incurred in
2024/25, predominantly related to staff who will be employed to operate the bridge. This
cost will be funded from ringfenced reserve balances and will be in addition to the £4.324m
detailed in the table above.

Page 4

6. Capital Budget 2024/25 
6.1 When the General Services Capital Programme was presented to Council on 29 February
2024, there was £2.0m uncommitted in the Strategic Asset Management Fund (Corporate
Projects). The Council then committed this sum as follows: 
 Roads Maintenance programme £1.000m;
 Sports facilities £0.800m;
 Community Halls £0.130m; and
 Retail Improvement Fund £0.070m. 
The following table provides an update to the 2024/25 Capital plan. 
General Services Capital Programme 
2024/25
Draft 
Plan 
£000
Revised
Plan
£000
Movement 
£000
Schools and Early Years Investment 55,893 55,893 0
Leisure Estate 1,000 1,930 930
Environment and Infrastructure 10,883 11,883 1,000
Economic Development 21,720 21,720 0
City Deal 46,046 46,046 0
Corporate Projects 11,637 9,707 (1,930)
Private Sector Housing Grant 644 644 0
Total General Services Programme 147,823 147,823 0 
7. Paisley Grammar School Community Campus
7.1 The Council previously approved a new Paisley Grammar School and Community Campus
(PGSCC) on Renfrew Road to replace the existing Paisley Grammar School on Glasgow
Road. As reported to the Education and Children’s Services Policy Board in November
2023, the anticipated cost of delivering the project was £74.8m with a completion date of
Summer 2026.
7.2 The Board were also advised that the approved capital budget of £75M was at risk with
developing forecasts in the range of circa £75M to £80M inclusive of Value Engineering
(VE) options instructed reflecting uncertainty in relation to the volatility and uncertainty in
the construction market at that time.
7.3 Growing inflationary pressures in relation to the schools’ construction market continue to be
prevalent on a national scale which has directly impacted the PGSCC project. The officer
PGSCC Governance Board has considered the ongoing budgetary issues with reference to
a report issued by COSLA advising that selected Scottish Futures Trust LEIP funded
projects (those that reached financial close by December 2023) would be receiving an 11%
uplift to the base square metre funding provision in response to market conditions.

Page 5

The LEIP Board have now agreed and recommended to Scottish Ministers that an
equivalent uplift is applied to all Phase 2 LEIP projects (including PGSCC), however there
is as yet no confirmed timescale for Scottish Ministers to approve this position. Members
have been advised previously that in the absence of additional government funding, the
Council may require to allocate increased capital resource to the project, which may also
increase ongoing revenue costs should any Council contribution be funded through
prudential borrowing.
7.4 Morrison Construction has been appointed by Renfrewshire Council to provide pre-
construction advice to the design team on buildability, commercial viability of emerging
design concepts and to competitively tender Sub-Contract work packages to build up the
overall project cost. Upon successful completion of this process, Morrison Construction will
be contracted to act as Principal Contractor for the construction phase. The project has
been split into 57 sub-contract work packages which has been tendered through Morrison
Construction’s supply chain. Returns from this tender exercise have now been received
and they indicate a higher level of cost increase than had been anticipated due to a range
of issues, including inflationary materials costs, a limited number of suppliers bidding for
work, and difficulty securing skilled labour. This position is consistent with the view of SFT
who recently published a cost review briefing for projects which reached financial close by
December 2023 which outlined the following issues as being key contributors to the market
volatility:
 multiple contractors were reviewing their focus on public sector projects given the
financial challenges facing local authorities; 
 materials inflation is expected to drop to 3-4%, but prices remain high for products which
are energy intensive, due to high energy costs – glass, cladding and steel; Mechanical
Electrical and Plant (MEP) prices remain high
 labour shortages have taken over from materials costs as the main source of tender
inflation; workforce availability is continuing to be an issue with high cost of living and
cultural change proving a challenge. Work/life balance means a 4-day working week is
common and there is limited appetite for overtime working or travel
 preference for Passivhaus accreditation remains strong across LEIP projects due to the
defined energy target and in response to the Outcomes Based Funding (OBF) model.
Main contractors noted a premium for Passivhaus of between 5-25% although those at
the lower end of the scale did note a number of large sub-contractors are losing money
on projects, so it is difficult to determine the true cost. Subcontractors remain vulnerable
to market conditions and borrowing rates - which are being passed on to project cost. 
7.5 Officers from the Council’s corporate procurement team have reviewed the tender process
conducted by Morrisons and have confirmed the process used is appropriate. Technical
officers within property services are also checking (assisted by external cost consultants)
the returns received to ensure they are appropriate, are securing best value and will meet
the Council’s requirements. Returns for packages are generally more expensive than had
been forecast, in some cases substantially so, but are on average circa 20% higher than
the cost plan allowance.

Page 6

7.6 This additional cost will result in an additional cost to the project in the order of £10m, with
a revised budget of £85.5m now being recommended as being appropriate for the project
to progress. This revised budget retains a risk allowance of 7.5% (excluding fees) for the
project which is viewed as appropriate at this stage.
7.7 The existing budget of £75.1m is based on the existing offer from SFT in relation to their
revenue funding model ie before the 11% uplift mentioned above has been factored in.
Indicative figures have been provided by SFT detailing what a revised offer would contain
assuming this is formally approved by Scottish Ministers. The uplift in these indicative
figures would allow for an increased level of borrowing support over the next 25 years
which would fund an additional £6m of capital spend. The balance of £4m in the additional
£10 million of capital funding required would need to be included within the Council’s loans
charges financial planning arrangements, at an estimated cost of £0.2 per annum assuming
a 50 year life.
7.8 In the event Scottish Ministers do not agree the recommendations in relation to the
proposed funding uplift, a further report to members will be provided outlining the financial
implications for the Council. 
—————————————————————————————————————
Implications of the Report
1. Financial - The report and appendix provide background information on the
2024/25 budget, identifying an in-year break-even position, after the agreed use of
reserves. The report also outlines an increased capital funding requirement for the
Paisley Grammar School Community Campus project of £10.4m, which will result in
increased borrowing costs for the Council estimated at 0.5m per annum, £0.3m of
which will be funded through an increase LEIP revenue allocation. 
2. HR & Organisational Development – none arising directly from this report. 
3. Community/Council Planning – none arising directly from this report. 
4. Legal – the Council has a statutory duty to approve a balanced budget each year. 
5. Property/Assets – the report updates members with regards a key schools
investment project which will be delivered to Passivhaus energy efficiency
standards, replacing a heritage school building; improving the overall energy
efficiency of the school estate and delivering an improved learning environment. 
6. Information Technology - none arising directly from this report. 
7. Equality & Human Rights - none arising directly from this report. 
8. Health & Safety - none arising directly from this report.
9. Procurement – none arising directly from this report.

Page 7

10. Risk – there is a risk that the Council’s spending needs are not financially sustainable
if the use of one-off reserves to balance the budget is a recurring feature over the
longer term. The revised capital budget for PGSCC maintains an appropriate level of
risk contingency allowance.
11. Privacy Impact - none arising directly from this report.
12. Cosla Policy Position – none arising directly from this report.
13. Climate Risk – the new PGSCC will be delivered in line with Passivhaus energy
efficiency standards, improving the overall energy efficiency of the school estate and
supporting the Council’s net zero aspirations.
___________________________________________________________________ 
Author:           Alastair MacArthur, Director of Finance and Resources

Page 8

No embedded text on this page.

Page 9

RESOURCE ALLOCATION              APPENDIX 1 
REVENUE BUDGET 2024/25 
Chief
Executive's
Service
Children's
Services
Environment,
Housing and
Infrastructure
Finance and
Resources
Miscellaneous
Service and
Loans Fund
Funding
Income
Renfrewshire
Council
Employee Costs 8,478 173,144 58,824 34,355 35,223 0 310,024
Premises Costs 1,461 9,597 6,065 1,516 7,043 0 25,682
Transport Costs 67 6,026 7,599 127 400 0 14,219
Supplies and Services 15,260 33,453 27,895 9,978 4,588 0 91,174
Third Party Payments 0 19,003 3,272 1,883 25 300 24,483
Transfer Payments 3,406 14,116 2,686 48,048 (538) 12,850 80,568
Support Services 361 67 1,070 506 (1,400) 0 604
Capital Charges 0 0 (23) 0 9,182 0 9,159
Income (4,386) (1,550) (44,752) (49,559) (12,869) 0 (113,116)
Sub-Total 24,647 253,856 62,636 46,854 41,654 13,150 442,797
Plus Adult Social Care 106,490
Total In-Year Spending Need 2024/25 549,287
Recurring Spending Need 547,262
Non-Recurring Spending Need 2,025
Net Expenditure 2024/25 549,287
Funding Income (544,963) (544,963)
Total In-Year Deficit 2024/25 4,324