Accounts Commission Section 102 Report (S.102) – School Accommodation for Dargavel Village

Renfrewshire Council · 29 February 2024
Back to Council — 29 February 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

___________________________________________________________________
To: Council
On: 29th February 2024
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Accounts Commission Section 102 Report (S.102) – School
Accommodation for Dargavel Village
___________________________________________________________________
1.  Summary 
1.1 At a meeting on 11th January 2024, the Accounts Commission was
presented with a statutory S.102 report, as circulated to Councillors on
5th January 2024 (see Appendix 1), by the Controller of Audit on School
Accommodation for Dargavel. It is a statutory requirement for a S.102
report to be reported to the full Council to allow consideration of the
findings and recommendations from the Accounts Commission and to
agree any subsequent action by the Council. 
1.2 As outlined in their report, the Accounts Commission agreed to make
findings and associated recommendations in response to the Controller
of Audit’s statutory report, is seeking additional information and
assurance in relation to several areas and in this context has requested
a further report back from the Controller no later than June 2024. They
have also reserved open the right to hold a hearing if they deem it
required. 
1.3 Attached at Appendix 2 is the proposed response and actions to the
Commission’s findings and recommendations for elected members
consideration and approval.

Page 2

2.  Recommendations 
2.1 It is recommended that members: -
•  note and accept the Accounts Commissions findings and
recommendations;
•  agree the response and actions outlined in Appendix 2 of this report
and that monitoring of those actions will be incorporated into the
overall Bowles report response monitoring arrangements that are
reported to each cycle of the Audit Risk and Scrutiny Board;
•  note that a follow-up report from the Controller of Audit will be made
to the Accounts Commission by June 2024 which will be subject to
appropriate reporting through the Council’s governance process at
that time. 
3. Background 
3.1 Following presentation of the Council’s 2022/23 Annual Audit Report for
from Azets, the appointed auditor, considered by the Council’s Audit,
Risk and Scrutiny Board (ARSB) on 6 November 2023 and by the full
Council on 16 November 2023, the auditor issued an unmodified opinion
on the council’s 2022/23 annual accounts. Within that report, the auditor
provided significant coverage of the Dargavel situation, including: - 
• findings from the independent report commissioned by the Council
and which reported in June 2024 (“The Bowles Report”), 
• the subsequent actions the Council has been progressing since that
time, 
• that the council has appropriate governance arrangements in place
with improvements over the years in member and officer
relationships and effective leadership overall and were satisfied
through their detailed audit work that the Council had demonstrated
that the governance failings identified by the Bowles report were
limited to the historic handling of Dargavel, 
• that they had no highlighted concerns over the wider organisational
culture in the Council or in its approach to managing major capital
programmes but did identify that the role of the Audit, Risk and
Scrutiny Board in ensuring effective scrutiny is not sufficiently clear
and the Council has recognised this and is already significantly
progressed with a review of the Audit Risk and Scrutiny Board. 
• the overall progress being achieved to resolve the educational
capacity challenges as a result of the historic errors made by the
Council, highlighting that the Council continues to have significant
challenges to rebuild the trust of communities affected by the failings

Page 3

and that the Council and communities will be feeling the impact of
this for some time to come. 
3.2 The Controller of Audit decided to use the reporting powers available to
her under s102 (1) of the Local Government (Scotland) Act 1973 to bring
this issue, and the action the Council is now taking in response to the
Bowles report, to the attention of the Accounts Commission. Following
presentation of the report to the Commission, the Commission has
endorsed the Controller of Audit’s report on school accommodation for
Dargavel village. 
3.3 On receipt and following consideration of a Controller of Audit report, the
Commission may do, in any order, all or any of the following, or none of
them:  
• direct the Controller of Audit to carry out further investigations 
• hold a hearing 
• state its findings. 
3.4 In this case, the Commission has set out their findings in their report,
alongside several issues on which they require further, urgent,
investigation. The Commission has requested that the Controller
updates the Commission no later than June 2024, using her powers
under Section 102 of the Local Government (Scotland) Act 1973 on
progress on the issues raised in their findings, and earlier if she deems
necessary. The Commission has also reserved the right at this stage to
hold a hearing if they deem it necessary. 
3.5 The Commission have also confirmed that they intend to bring forward
Renfrewshire Council’s Best Value report from 2027 to later this year, or
at the latest in early 2025. 
3.6 While the Council was commended for its decision to instruct an
independent review of the issues surrounding the Dargavel Primary
School, and for its acceptance in full of the recommendations in the
Bowles report, the Commission has indicated concern that significant
risks remain in relation to actions the Council is taking in response to the
acknowledged failings. 
3.7 Throughout their findings the Commission has outlined
recommendations to secure further information and assurance to
address their concerns. The Commission has noted the Council’s
acceptance in full of the Bowles report recommendations and its apology
to the local community. They also recognise that the Council has
developed a specific communication and engagement strategy for
Dargavel. However, as has been recognised by the Council and
highlighted by the Controller in her report, the Commission agrees that
the Council faces a significant challenge to rebuild the trust and
confidence of local communities.

Page 4

3.8 The Commission has required the Controller to report back to them by
June 2024 on any issues raised in the report that she thinks appropriate,
but also to seek specific further information and updates from the council
regarding: 
• the Council’s review of its approach to community engagement, 
• the Council’s approach to consultation on the additional primary
school at Dargavel, and other decisions on the school estate, 
• the Council’s work on understanding the wider service impacts on
the failings regarding school capacity, 
• the Council’s reviews of scrutiny and risk management, and its
leadership development programme, and 
• the process followed and factors taken into account by the Council
in considering disciplinary action against senior staff, and its
approach and policy on performance management and
accountability. 
3.9 Detailed in Appendix 2 to this report, is a proposed response and
associated actions to the findings and recommendations set out by the
Commission for elected members consideration. 
3.10 Subject to consideration and approval by elected members, it would be
proposed that these actions are incorporated into the existing action plan
being progressed by officers in response to the Bowles report for
monitoring purposes and will in line with the existing approach be
reported to each cycle of the Audit Risk and Scrutiny Board. Further, and
in line with statutory requirements under the 2003 Act, this proposed
response and actions if approved by Council will be formally shared and
communicated to the Account Commission following this meeting. 
_________________________________________________________
Implications of the Report
1. Financial  - there are no direct financial implications arising from this
report. Any costs associated with delivering the proposed actions will
be contained within existing resources. 
2. HR & Organisational Development - none 
3. Community/Council Planning – none  
4. Legal – the statutory report issued by the Controller of Audit and
subsequent findings issued by the Accounts Commission have been
issued under S.102  and S.3 of the Local Government (Scotland ) Act
1973 and 2003 respectively.

Page 5

5. Property/Assets – none 
6. Information Technology – none 
7. Equality & Human Rights - The Recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report as it is for
noting only and sets out the detail of an external investigation.   If
required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.  (Report author to arrange this). 
8. Health & Safety - none 
9. Procurement – none 
10. Risk - none 
11. Privacy Impact - none 
12. Cosla Policy Position – none.
_________________________________________________________
List of Background Papers 
Dargavel Primary – Independent Review – Council June 2023 
Azets Report to those charged with governance - Renfrewshire Council Group
Annual Accounts 2022/23 – Audit Risk and Scrutiny Board November 2023 
Annual Audit Report 2022/23 Renfrewshire Council Group – November 2023 
Author:          Alan Russell 
Chief Executive 
alan.russell@renfrewshire.gov.uk

Page 6

No embedded text on this page.

Page 7

Prepared by the Controller of Audit
January 2024
The 2022/23 audit
of Renfrewshire
Council
School accommodation for Dargavel Village
Appendix 1

Page 8

The 2022/23 audit of Renfrewshire Council: School accommodation for Dargavel Village | 2
Contents 
Commission findings 3
Introduction 7
Dargavel School – Timeline of key events 9
Independent examiner’s report – the ‘Bowles report’ 11
The council’s response 14
Conclusions 19

Page 9

Commission findings | 3 
Commission findings 
1.  The Commission endorses the Controller of Audit’s report on school
accommodation for Dargavel village. We also acknowledge the work of David
Bowles in carrying out his independent review.
2.  On receipt of a Controller of Audit report, the Commission may do, in any
order, all or any of the following, or none of them:
• direct the Controller of Audit to carry out further investigations
• hold a hearing
• state its findings.
3.  In this case, the Commission has given serious consideration to the full use
of the powers available to us. In this report, we set out our findings, alongside a
number of issues on which we require further, urgent, investigation. 
4.  We request that the Controller updates the Commission no later than June
2024, using her powers under Section 102 of the Local Government (Scotland)
Act 1973 on progress on the issues raised in our findings, and earlier if she
deems necessary.
5.  We also intend to bring forward Renfrewshire Council’s Best Value report
from 2027 to later this year, or at the latest in early 2025.
6.  The Commission reserves the right to hold a public hearing on this and
related matters if we are not satisfied with the updates we receive on the
council’s progress.
7.  While the council is to be commended for its decision to instruct an
independent review of the issues surrounding the Dargavel Primary School, and
for its acceptance in full of the recommendations in the Bowles report, the
Commission is concerned that significant risks remain in relation to actions the
council is taking in response to the acknowledged failings. Our findings are
structured around the themes we explored in our public meeting on 11 January
2024. Throughout our findings we seek assurance and further information to
address our concerns. 
Community and other engagement 
8.  We note the council’s acceptance in full of the Bowles report
recommendations and its apology to the local community. We also recognise
that the council has developed a specific communication and engagement
strategy for Dargavel. However, we agree with the Controller that the council
faces a significant challenge to rebuild the trust and confidence of local
communities.

Page 10

Commission findings | 4 
9.  While it has taken action, the council is yet to assess how effective its
engagement strategy has been to date. The council must, as a matter of
urgency, conduct a robust and transparent assessment of the effectiveness of
its community engagement and then move swiftly to implement any
improvements needed. The Commission asks the Controller to update us on
this by June 2024, or earlier if progress is not at the pace we expect.
10.  The Commission is particularly concerned by the council’s failure both to
transparently consider alternative options in relation to expanding secondary
school capacity in the area, and to consult or engage appropriately with the
community, whom their decision directly affects. 
11.  We note that the new primary school is subject to a full public consultation.
We expect the council to engage meaningfully with the community on this issue,
and other decisions on the school estate. Again, we ask that the Controller
monitors this situation, and reports to us in June 2024 on progress and earlier if
necessary.
Learning lessons and building capacity 
12.  We note from the Controller’s report that learning the lessons from these
issues continues to feature prominently in council meetings. 
13.  While the council’s initial response to the Bowles report was high level, we
are assured by the Controller that its action plan in response is now sufficiently
detailed and includes SMART objectives. It will be important that this action plan
is well-managed by senior officers and closely scrutinised by elected members
of the council. 
14.  We note that the council has also commissioned Edge Analytics, who we
are reassured are experts in this field, to advise on future school capacity
issues. However, there are still significant uncertainties relating to the capacity
needed in the long term, and to the completion of the two building projects – the
new primary school and the secondary school extension. We therefore request
that these matters are closely monitored in the annual audit work, and the
Controller uses her powers to report any slippage or other issues to us if
necessary.
Impact on service provision 
15.  We note that the council has assessed that currently there has been no
detriment to either teaching delivery or pupil education in the Dargavel and
Bishopton areas from the interim measures introduced. We consider it critical
that the council reports the results of these assessments publicly, regularly and
in an accessible way, to maintain and rebuild community confidence. 
16.  The Commission is also concerned at the possible wider impacts of the
council’s failings regarding the estimation of pupil numbers and whether this has
had any impact on services provided by the council in the Dargavel area. We
request that the Controller seeks further information on these issues so that we
can understand the work that the council has done to understand these
impacts.

Page 11

Commission findings | 5 
Financial management and consequences 
17.  The financial impact of these failings on the council is significant. The
council capped the risk and contributions from BAE Systems under the Section
75 agreement, and as a direct result faces estimated net additional capital costs
of £60 million, to be met by borrowing. This is a substantial sum of public
money. The council needs to clarify the opportunity costs of this in terms of its
overall capital programme. The council projects that it will have a revenue
budget deficit of up to £50 million by 2026/27 and will need to make difficult
decisions on prioritising its spending, compounded by the financial
consequences of this issue.
18.  The council has recently negotiated a transfer of land from BAE for the
construction of a new primary school. The Controller’s report indicates that this
was in exchange for amendments to the extent and composition of the housing
units for which planning permission has been granted. Given the reported
determination of BAE to fully protect their commercial interests in the
development, and the absence of alternative solutions for the council, it will be
important to ensure and demonstrate that this exchange represents Best Value
for the public purse. 
Council leadership, governance and culture
19.  We note that the council’s auditors have concluded that, overall, the council
has appropriate governance arrangements in place and that member and officer
relations have improved over the years. The council’s action plan will be hugely
important in further embedding improvements in this area. In particular, the
following elements must be progressed urgently and transparently:
• the council’s review of its scrutiny arrangements against CIPFA good
practice guidelines
• the council’s review of its approach to risk management
• the council’s leadership development programme for officers.
20.  To be satisfied of progress in these areas, the Commission requires the
Controller to request further information from the council on the scope and
timing of these actions, and report back to the Commission in the update
requested for June 2024, or earlier if she thinks necessary. We also expect
these issues to be covered in the accelerated Best Value report.
21.  The Commission is also concerned about the culture of the council and
whether it has truly learned the lessons it needs to. We expect organisational
culture to be an area of focus in the accelerated Best Value report. In particular,
we request an update on whether the culture of the organisation is appropriately
open and transparent and encourages continuous improvement, effective joint-
working between officers and members, effective scrutiny and challenge
(especially by elected members), and engagement and discussion with
stakeholders. In addition, we request an assessment of whether it has the right
skills in the right places to deliver on its responsibilities, and whether issues are
escalated to the right level.

Page 12

Commission findings | 6 
22.  Finally, the Commission notes that the auditor has concluded that the
council has obtained appropriate external legal advice and determined there is
no potential for any form of action against former senior employees involved in
the Dargavel School decision-making. In addition, no disciplinary action has
been taken against any senior officer involved in decision-making relevant to
the Section 75 approval process for the Dargavel Village development. 
23.  The Commission accepts that these are management issues. However, we
request that the Controller asks the council for further information on the
process followed and factors taken into account by the council in considering
disciplinary action against staff involved. In addition, and looking forward, the
Commission asks for information on the council’s approach to performance
management and its current policy on disciplinary action, so we can be assured
that appropriate arrangements are in place to ensure that staff have the
necessary skills and that senior officers are properly accountable for their areas
of responsibility.
Summary of requests for further information and work required
24.  The Commission requires the Controller to report back to us by June 2024
on any issues raised in this report that she thinks appropriate, but also to seek
specific further information and updates from the council regarding:
• the council’s review of its approach to community engagement
• its approach to consultation on the additional primary school at
Dargavel, and other decisions on the school estate
• the council’s work on understanding the wider service impacts on the
failings regarding school capacity
• the council’s reviews of scrutiny and risk management, and its
leadership development programme
• the process followed and factors taken into account by the council in
considering disciplinary action against senior staff, and its approach and
policy on performance management and accountability.

Page 13

Introduction | 7 
Introduction 
1.  The Code of Audit Practice requires auditors to produce an annual report
summarising the significant matters arising from their work at the conclusion of
each year's audit. For local authorities, these reports are addressed to elected
members and the Controller of Audit.
2.  I have reviewed the 2022/23 Annual Audit Report for Renfrewshire Council
(the council) from Azets, the appointed auditor. The auditor’s Annual Audit
Report was considered by the council’s Audit, Risk and Scrutiny Board (ARSB)
on 6 November 2023 and by the full council on 16 November 2023. The report
has also been published on Audit Scotland’s website. The auditor issued an
unmodified opinion on the council’s 2022/23 annual accounts.
3.  In June 2023, the council received the findings of an independent report (the
Bowles report) that highlighted significant failings of leadership, oversight and
risk management in relation to the provision of school accommodation for
Dargavel Village. The consequences of this for both the community and the
council are far reaching and a significant cause for concern. The council has
developed an action plan to respond to the issues identified and is, and must
continue, to work hard to rebuild the trust of the communities affected and
demonstrate that lessons have been learnt. 
4.  I have therefore decided to use the reporting powers available to me under
s102 (1) of the Local Government (Scotland) Act 1973 to bring this issue, and
the action the council is now taking in response to the Bowles report, to the
Commission’s attention. 
Background
5.  The development of the new village of Dargavel, in Renfrewshire, is a large
and complex project, which has evolved into one of the largest housing
developments in Scotland. The land at Dargavel Village is being developed by
BAE Systems who were initially granted planning permission for the
development of a maximum of 2,500 houses in 2009. This was increased,
through a range of further planning applications between 2014 and 2018, most
notably by 1,350 as part of two major additional applications in 2018. The
council in 2023 formally acknowledged that the historically consented planning
permission was for 4,322 units on the Dargavel site.
6.  It is common practice for local authorities, when considering planning
permission for new housing developments, to enter into an agreement with the
developers to contribute to the additional public costs associated with delivery
of any new housing development, including costs associated with schools,
health, roads and other infrastructure. These legally binding agreements are
made under Section 75 of the Town and Country Planning (Scotland) Act 1997. 
A new primary school (Dargavel Primary) was built by BAE systems in Dargavel

Page 14

Introduction | 8 
Village as part of a Section 75 agreement with BAE systems. It opened in
January 2022 with an expected capacity for 430 pupils. 
7.  In May 2022, as part of the 2022/23 intake, council officers recognised that
they had substantially underestimated the demand for primary school places in
Dargavel Village. At the same time the council recognised that the demand for
secondary education was also likely to have been significantly underestimated.
8.  Following analysis over the summer period to quantify and understand both
the scale and time critical nature of the problem, a special meeting of the
council's Education and Children Services Policy Board was held in November
2022. The main purpose of the meeting was to discuss Dargavel Primary
School capacity. It was reported that the current school roll was 463. The
council projected a potential school roll of up to 620 pupils by August 2023 and
705 pupils by August 2024. The board concluded that the existing school
capacity would be materially insufficient to meet the future demand profile of the
catchment area. 
9.  Additional work by the council to create a robust long-term estimate of pupil
numbers (further confirmed by more detailed projections from the council’s
consultants, Edge Analytics) identified a need for a core primary school capacity
of 1,130 pupils and high likelihood of breaching the existing 430 capacity in the
2023/24 school intake requiring circa 60 per cent more pupil spaces.
10.  The Education and Children Services Policy Board has approved planning
for an additional primary school in Dargavel and an extension to Park Mains
High School. The council had planned an extension to Park Mains High School
as part of its Section 75 agreement with BAE Systems in 2018 and confirmed
the size of that extension in its 2023 agreement. The Bowles report highlights
that the council’s failure to appreciate the risks that they were taking in the
original contract they negotiated, which allowed BAE to cap their contributions1
means that it is the council that will need to meet the additional costs over and
above this cap associated with increasing capacity. 
1 BAE Systems have contributed the primary school at Dargavel Village and land for the building
of a second primary school. The have capped their contributions for secondary school capacity
to 200 pupil places.

Page 15

Dargavel School – Timeline of key events | 9 
Dargavel School – Timeline of
key events 
Date Event
2006 The original masterplan application for the Dargavel development is
submitted by BAE Systems
Aug 2009 Outline planning consent approved
2009 Section 75 agreement signed between the council and BAE
Systems for 2,500 houses and 340 primary school pupils spaces 
2013 Dargavel Village construction commences
Sep 2014 Concerns expressed as to the size of the planned school by the
community council
Apr 2016 The council updates the school capacity requirement to 430 places
for extending Dargavel Village development to 3,850 homes
Jan 2017-
2021
Community concerns over low school capacity continue to be raised
Oct 2018 Section 75 Agreement signed. Planning consent for 3,850 houses
granted by the council. BAE Systems formally obligated to build
Dargavel Primary School with capacity for 430 pupils
2020 Dargavel Primary School construction commences
Jan 2022 Dargavel Primary School opens
May 2022 During the 2022/23 intake, the council becomes aware that pupil
admissions are higher than expected 
Nov 2022 The council appoints Edge Analytics to provide support for school
capacity estimates 
Dec 2022 The council’s chief executive appoints Mr David Bowles to undertake
an independent review of Dargavel Primary School capacity issues 
Mar 2023 The EPCB approve planning for an additional school in Dargavel
with a minimum capacity for 700

Page 16

Dargavel School – Timeline of key events | 10 
May 2023 Updated projections recommend additional primary school capacity
requirement of 800
The ECPB approves an extension to Park Mains High School to
create capacity for an additional 400 secondary school places
Jun 2023 ‘The Bowles report’ is published and presented to the full council. 
The council accepts all recommendations in full
Aug 2023 The council instals six modular classrooms in Dargavel school as an
interim capacity solution
Sep 2023 The council secures a land transfer from BAE systems to build a
new primary school and, in exchange, the council clarifies that a
maximum of 4,322 homes are consented to be delivered as a part of
Dargavel Masterplan.

Page 17

Independent examiner’s report – the ‘Bowles report’ | 11 
Independent examiner’s report –
the ‘Bowles report’ 
11.  Following the special meeting of the council’s Education and Children
Services Policy Board in November 2022, the council gave authority to the chief
executive to establish an independent assessment of the circumstances which
led to the significant error in school capacity planning for Dargavel School.
David Bowles, a former local government director and chief executive, was
appointed directly by the chief executive following a search for suitable
candidates for the role supported by SOLACE. 
12.  The overriding conclusion of the report was that:
‘…the council was completely unaware of, and therefore unprepared for, the
impact that a development such as Dargavel would have upon the education
service.’
13.  The report further concluded that:
‘Regardless of considerable uncertainty of estimating pupil need 20 years
ahead, before detailed consents had been given and the housing mix known,
the council allowed BAE to cap its contributions in both agreements, leaving all
of the risk with the council. It is difficult to see how both of these agreements,
involving potentially millions of pounds of investment in primary and secondary
education, could have been handled in a more incompetent manner.’
14.  The ‘Bowles report’ was published and presented at the June 2023 full
council meeting and identified the following key factors (with summarised
extracts) which contributed to the Dargavel School outcomes:
• A failure of leadership in the education service. Senior education
management were both incompetent and not sufficiently engaged in the
project.
• Limited corporate oversight of the project. There is no evidence of
corporate intervention to provide internal support or seek external
advice.
• Lack of clarity about the size of the development. Different parts of
the council have been working on different housing numbers and BAE
have quoted different numbers.
• A complete and repeated failure to test data for reasonableness.
The council had numerous opportunities to test data for reasonableness
and it failed to do so.

Page 18

Independent examiner’s report – the ‘Bowles report’ | 12 
• Ignoring conflicting data. There are frequent instances of conflicting
data being disregarded.
• Not either understanding or planning to manage the risk
associated with large developments. The lack of understanding of
(estimation) risks can be highlighted by the inept decision of the council
to reduce the size of the Dargavel School site.
• Focussing on capacity problems at Bishopton Primary School. At
no time did officers question why there was a ‘spike’ in children from the
Dargavel development being admitted to Bishopton school.
• Ignoring emerging problems when agreeing to a 2-form entry
primary school in 2018, which increased the capacity of the
planned Dargavel school by about 100 places. There was ample
evidence the council had seriously underestimated primary school
demand before the original planning application in 2018.
• A failure to recognise the growing school capacity problem until
May 2022. The (school place demand) error was so obvious it is difficult
to see how it remained undetected for six years.
• A failure to take any concerns expressed by others seriously. The
response by council officers to numerous examples of concerns being
expressed by a range of stakeholders showed professional arrogance. 
15.  The Bowles report recommended that the council:
• Builds a more robust model of primary school need for Dargavel.
The council should update and refine the existing model of pupil
numbers and the potential range of demand and continue to work with
experts in this area. It should also review the mix of housing approvals
and extend the time period of the forecasts for primary to assess
whether there is likely to be a peak in demand or just a plateau then a
decline.
• Reconsider catchment areas. The earlier decision on catchment
areas was made on the assumption the developer would be meeting all
of the costs of primary education, without needing to use the surplus
capacity at Bishopton. That is no longer the case. In its future plans the
council should reconsider how surplus capacity at Bishopton can be
used effectively.
• Produce robust supplementary guidance on developer
contributions. The council should be clear about who has
responsibility for this area of work and ensure they have the appropriate
skills available to them, either internally or externally. The council
should review how data flows between planning and education and that
they both understand its import.
• Seek to work co-operatively with BAE. Unless the council and BAE
can work together to resolve the current problems, BAE may face

Page 19

Independent examiner’s report – the ‘Bowles report’ | 13 
accusations, whether founded or not and regardless of council
incompetence, that it has financially benefitted at the expense of council
taxpayers.
• Corporate working and organisational culture. The council needs to
consider a significant change programme, not just on the of issue of
corporate working and personal responsibility, but also its
organisational culture and values. It needs plans to build a stronger
organisation where constructive challenge is welcomed and there is a
clarity of what is expected of all of those in a leadership role.
• Risk management. The council needs to review how it both identifies
risk and manages it. The identified risk in council documents related to
delivering the school on time, not that the size of the school may prove
to be inadequate. The failure to identify that risk has had two
consequences; first the council has been slow to react to the increase in
pupil numbers and second the council did not negotiate with BAE, with
that risk in mind.   
• Involvement of members. While protecting the integrity of the planning
process, the council needs to ensure the appropriate involvement of
members in such developments.
• Public confidence. The council should work in an open and
transparent manner in the resolution of these issues and particularly
with the residents of Dargavel, who have legitimate concerns about the
implications for their children, during both their primary and secondary
education.
Source: Dargavel Primary – Independent External Review, The Bowles report

Page 20

The council’s response | 14 
The council’s response 
16.  The council accepted in full the recommendations of the Bowles report at its
meeting of 22 June 2023 and apologised to the local community for the
significant errors made. Since then, it has supplemented its initial response with
a more detailed action plan, however it is clear that the implications of this issue
will be felt for some time to come. The council is, and must continue to, working
hard to rebuild the trust of the affected communities and demonstrate that it has
learnt lessons. The council’s progress in implementing agreed actions is
monitored by the Audit, Risk and Scrutiny Board. 
17.  The council has engaged external consultants, Edge Analytics, to provide
expert support in estimating demand for places across its school estate and has
taken forward an analysis of how other local authorities manage developer
contributions ahead of the development of updated guidance.
Addressing capacity issues in the short term
18.  The council have implemented transitional arrangements to address
immediate capacity issues in Dargavel Primary School. These interim measures
have included the creation of new modular classrooms and the utilisation of
available capacity in the neighbouring Bishopton School. The council has
assessed, with the support of external consultants, that these interim measures
will be sufficient to accommodate primary and secondary school demand until
the anticipated new schools are developed by August 2027, but this will require
to be kept under careful review. 
19.  The council assesses the impact of these transitional arrangements on the
standard of teaching delivery and pupil attainment as part of its regular
monitoring arrangements. At this stage, the council assesses that, while there
has been some disruption, there has been no detriment to either teaching
delivery or pupil education in the Dargavel and Bishopton areas.
20.  The council will continue to monitor the quality of educational delivery and
measures of pupil attainment closely through its existing quality monitoring
arrangements. It is critical that the council ensures that it robustly assesses
educational impacts and continues to report publicly on this to maintain
community confidence. 
Addressing capacity issues in the medium term
21.  The council had limited options for addressing the medium-term primary
school capacity issues it faced in Dargavel Village given the size of the capacity
shortfall (around 800 places) which meant that extension of the existing site was
not an option, and the surrounding land is owned by BAE systems.

Page 21

The council’s response | 15 
22.  As a result, the council entered into negotiations with BAE Systems to
explore options for addressing the education needs of the Dargavel community. 
These negotiations resulted in an agreement with BAE Systems to transfer a
parcel of land to the council for £1 in August 2023 that could enable the building
of an additional new primary school within Dargavel village. This final decision
on the building of a new school will be subject to a full statutory consultation
process in due course.
23.  Section 75 agreements often require developers to include affordable
housing and housing available for the social rented sector as part of the
planning permission process. In reaching agreement with BAE Systems to
transfer the land that could accommodate the construction of an additional
primary school, the council also formally acknowledged that the historically
consented planning permission was for 4,322 units on the Dargavel site and
agreed to reduce the affordable housing requirement at stage 2 of the
development. Consequently, there will now be 243 social rented units as
opposed to 336 as part of the overall development. Equally though, the revised
agreement anticipates that there will be circa 1,271 lower market sector units
against the earlier obligation to build 681 units.
24.  The council recognised that the Dargavel Village development would also
create an increased demand for secondary school places. The council worked
with Edge Analytics to develop an estimate of the impact of this increased
demand on secondary school capacity and provision across the whole school
estate. The council concluded at a meeting of the Education and Children’s
Services Policy Board on 18 May 2023 to continue with plans to extend the
existing Park Mains High School at an estimated cost of £30 million to provide
an additional 400 secondary school places required. 
25.  The council did not present any formal options appraisal on provision of
secondary school places in its public report to support its decision-making, but
had considered an alternative solution and informally estimated that the cost of
building a new secondary school in Dargavel/Bishopton (an alternative favoured
by some community groups) at around £90 million. The adoption of this new
build option would also create surplus capacity of 40 to 60 per cent within the
existing Park Mains High School and result in significant additional net annual
revenue costs. The council subsequently communicated and explained the
rationale and data underlying its decision to the Park Mains Liaison Group and
other community group meetings.
Financial impact
26.  The council currently estimates that it will require £75 million of new capital
investment to create the required capacity to fully meet the primary and
secondary education needs of the Dargavel and Bishopton communities. The
council and the housing developer have agreed that the housing developer
(BAE systems) has fulfilled its obligations under the Section 75 agreement in
relation to the provision of primary school capacity.
27.  BAE systems have capped its contributions for secondary school places to
200 pupils meaning they are still required to meet almost 50 per cent of the
costs of the proposed 409 pupil place extension to Park Mains High School.

Page 22

The council’s response | 16 
28.  The estimated net additional costs of £60 million must therefore be met by
the council. The council plans to fund these capital costs from borrowing, and
estimates it will add around £4 million to the council’s annual revenue budget.
Council debt is normally written down over the estimated lifetime of the asset
which is currently an average of 40 years for the Renfrewshire school estate.
29.  The council estimates that the net revenue cost of running the new primary
school when it becomes operational in August 2027 will be around £0.5 million
per year, as additional running costs will largely be offset by increased grant
funding provided through the overall Scottish Government grant distribution
process. The council has not yet included an estimate for the net running costs
of the Park Mains High School extension.
30.  In context, the council is already facing a significant financial challenge and
recently updated its Medium-Term Financial Plan to include the additional £4.5
million borrowing and operating costs identified above. The council is now
projecting a budget deficit of up to £50 million by 2026/27 and will have to make
difficult decisions on spending priorities in the near future.
Community engagement
31.  The council recognises that it faces a significant challenge to rebuild the
trust and confidence of local communities. A recent report to the Education and
Children’s Services Policy Board notes the desire of the community to better
understand the rationale for the council’s decision to extend (rather than
replace) an existing secondary school serving the Dargavel and Bishopton
areas. It is critical that the council proactively engages the local community in its
school estate decision-making. 
32.  In October 2022, the council introduced a specific Dargavel communication
and engagement strategy which included the creation of a dedicated mailbox for
the community to ask questions and raise concerns and the development of a
regular community newsletter. The council’s senior team have also attended a
number of public meetings with residents of the Dargavel and Bishopton
communities and attended Community Council and Parent Council meetings.
The council also created the Park Mains Liaison Group which is attended by
senior council members and representatives from the local community.
33.  The council has used these forums to communicate, explain and engage
with local communities on its plans to address school capacity issues in
Dargavel and Bishopton and to address any local concerns. It is important that
the council robustly assesses the effectiveness of its community engagement to
understand how best to continue its efforts. The council has not yet undertaken
any formal assessment of its arrangements.
Governance
34.  The findings of the Bowles report, although restricted to the historical
handling of the Dargavel Development, raises a legitimate line of concern in
relation to the effectiveness of the council’s governance arrangements,
particularly in relation to corporate working and organisational culture, effective
risk management and member involvement in decision-making on major

Page 23

The council’s response | 17 
projects. I have sought to understand the extent to which these issues are also
representative of the council’s overall governance and decision-making
arrangements. 
35.  The council’s auditors have concluded, overall, that the council has
appropriate governance arrangements in place with improvements over the
years in member and officer relationships and effective leadership overall. The
auditors have not highlighted any concerns over the wider organisational culture
or in its approach to managing major capital programmes but have identified
that the role of the Audit, Risk and Scrutiny Board in ensuring effective scrutiny
is not sufficiently clear. 
36.  In response to both the Bowles report and the auditors recommendations,
the council have committed to review their overall governance and scrutiny
arrangements as part of a wider review of corporate governance. The council
will also undertake a review of the effectiveness of its Audit, Risk and Scrutiny
Board against CIPFA good practise guidelines.  
37.  The council has also committed to review its approach to risk management
across all council projects. The council has also committed to delivering a
comprehensive leadership development programme for all chief officers and
senior managers and has committed to evaluate this programme before rolling it
out to the next management cohort. The council understands it must progress
these actions in order to assure itself and others that its governance and
scrutiny arrangements are robust and that it is able to demonstrate a strong
organisational culture.  
38.  Learning the lessons from the school capacity issues in the Bishopton and
Dargavel communities continues to feature prominently in council meetings.
The audit team have observed an appropriate level of involvement of members
at the Education and Children Services Policy Board who scrutinise the delivery
of education across the council. The council recently adopted a Strategic
Learning Estate Work Programme, which brings together officers from different
departments to oversee educational estate delivery and ensure joint working
going forward.
39.  The council did not include a formal options appraisal in the report on the
provision of secondary school places to support its decision-making on the
extension of Park Mains High School in May 2023. The council also did not
articulate in that report why it felt an options appraisal was not required or how it
planned to engage with local communities on the underlying data and rationale
that supported the decision. While this approach is consistent, in specific
circumstances, with Scottish Government guidance on managing consulting on
changes to the school estate and education provision, it remains a significant
omission in the decision-making process. The council should have been more
open and transparent on the range of available options in relation to the school
estate, the process through which views could be heard and the basis on which
any future decisions would be taken.
40.  Finally, the auditor has concluded that the council has obtained appropriate
external legal advice and determined there is no potential for any form of action
against former senior employees involved in the Dargavel School decision-

Page 24

The council’s response | 18 
making. No disciplinary action has been taken against any senior officer
involved in decision-making relevant to the Section 75 approval process for the
Dargavel Village development.

Page 25

Conclusions | 19 
Conclusions 
41.  The Bowles report highlights significant historic failings in leadership and
risk management and a disregard of concerns expressed by the local
community. I note the council’s acceptance in full of the Bowles report
recommendations and their apology to the local community. The council has
developed an action plan setting out its response to the issues identified, and
the council must work hard to rebuild trust and respond to the issues identified. 
42.  Progress against this action plan will be reported to the council’s Audit, Risk
and Scrutiny Board. The council has committed to review its overall governance
and scrutiny arrangements, including the effectiveness of its Audit, Risk and
Scrutiny arrangements against CIPFA good practise guidelines. It must
progress this in order to assure itself, and others, that its governance and
scrutiny arrangements are robust.
43.  The council should have explained its decision-making process more clearly
and transparently when finalising its decision to extend Park Mains High School.
It is essential that the council is open and transparent on the range of available
options in relation to the school estate, the process through which stakeholder
views can be heard and the basis on which future decisions will be taken.
44.  The council has now engaged expert consultants to advise on school
capacity requirements and has developed plans for a new primary school and
extension to the existing high school. These significant school infrastructure
projects are not expected to be completed until August 2027 and will require
strong governance arrangements to ensure they are completed on time and
budget and meet the educational needs of the local community. I will continue to
monitor the council’s progress in managing these projects.
45.  The council has not yet reached the stage of engaging with contractors to
build the new Dargavel Primary School and the proposed extension to Park
Mains High School but has estimated costs of £75 million, with £60 million of
these costs due to be met by the council. These costs will add over £4.5 million2
to the council’s annual revenue budget and add to the already significant
financial challenge faced by the council. The council needs to make some
difficult spending priority decisions going forward. 
46.  While the council has assessed that the short-term transition arrangements
have caused no detriment to either teaching delivery or pupil education, this is
an issue they will need to monitor closely and report on publicly. The council
faces a significant challenge to rebuild trust and confidence with the affected 
2 The council has yet to include an estimate for the additional annual running costs for the
proposed Park Mains High School extension in its medium-term financial plan.

Page 26

Conclusions | 20 
local communities and must take steps to assess the effectiveness of its
community engagement programme. 
47.  The council’s appointed auditors will continue to monitor and report on
progress in addressing the recommendations contained within the Bowles
report through the annual audit process. The council has taken steps to respond
to the recommendations of the independent Bowles report but there is still more
to be done. Both the community and council will be dealing with the
consequences of this error for some time.

Page 27

Conclusions | 21  
The 2022/23 audit of Renfrewshire Council
School accommodation for Dargavel Village 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh  EH3 9DN
Phone: 0131 625 1500  Email: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk
ISBN 978 1 915839 31 2
AS.4.0

Page 28

No embedded text on this page.

Page 29

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
Community and other engagement 
The council must, as a matter of urgency, conduct a robust
and transparent assessment of the effectiveness of its
community engagement and then move swiftly to
implement any improvements needed. 
A full update of all completed and planned communication
and engagement activity since late 2022 as at end February
2022 will be provided to the External Audit team. 
The Consultation Institute – a recognised sector leading best
practice Institute promoting high-quality cross sector public
and stakeholder consultation standards – has been
commissioned to conduct a robust and independent review
of the council’s engagement strategy and activities. 
This will include assessment of the engagement strategy; the
variety of mechanisms implemented from October 2022 to
communicate and engage with the local community and the
effectiveness of activity. This will include qualitative
feedback from the community.
The commission will also extend to providing advice and
quality assurance on the statutory consultation
arrangements on the proposal for a new primary school in
Dargavel, its proposed site and catchment arrangements. 
This independent assessment process will be robust and
significant and carried out over several months. It is expected
to take until into June to fully complete all planned activities 
February 2024  Head of
Communications
and Marketing

Page 30

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
and provide a full evaluation report, albeit any key emerging
findings, learning and recommendations for improvement
identified as the evaluation progresses will be actioned as
soon as possible and shared on an ongoing basis with the
local audit team ahead of the planned report to the
Commission in June. 
The output of this commission and all associated
recommendations will assist in informing the design of future
engagement and consultation activity both within the
education estate but also across future consultation and
engagement activity associated with service / policy change
etc which the Council will be increasingly required to
consider moving forward as part of addressing its financial
sustainability challenges. 
February –
June 2024 
Head of
Communications
and Marketing
The Commission is particularly concerned by the council’s
failure both to transparently consider alternative options
in relation to expanding secondary school capacity in the
area, and to consult or engage appropriately with the
community, whom their decision directly affects. 
It is accepted that the report to the Education and Children’s
Services Policy Board in May 2023 could have articulated the
reasons why no other options to address secondary school
capacity beyond an extension to Park Mains High School
were deemed viable for detailed consideration.  
Additionally, although engagement in relation to updated
school projections and developing plans for a larger
extension to PMHS were shared and discussed with the
PMHS parent council prior to the May report, plans to expand
this engagement process to a wider group to encapsulate all
feeder primaries following the board meeting could have

Page 31

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
been outlined in the report and or considered earlier in the
process.   
Council officers have since May 2023 been progressing
positive and ongoing community engagement in relation to
the Park Mains extension, principally through the Park Mains
Liaison Group which was established to provide a single
engagement forum with representatives from the Parent
Councils of Park Mains High School and all associated feeder
primaries. 
This engagement process has shared and explained detailed
pupil projection data, the underlying rationale for the
proposed extension decision as well as listening and
responding to concerns and or requests for further
information from the wider parent and carer community.
This included sharing detailed information on an option
promoted by some community representative from Dargavel
and Bishopton for a new secondary school for Dargavel,
Bishopton and Langbank.  As reported through the Education
and Children’s Services Policy Board in August 2023, such an
option had significant negative implications from a financial,
educational, value for money and school estate perspective
that discounted it as a credible option for detailed
consideration. 
The Park Mains Liaison Group is proving to be a highly
valuable engagement forum, providing a single route of
engagement across the wider community as well as a key
route to assist the Council to disseminate consistent key 
This
engagement
activity will
remain
ongoing as
part of the
PMHS
extension
project
through to
August 2027
and beyond
recognising
the long-term
monitoring of
school roll
projections at
the high
school. 
Director of
Children’s Services

Page 32

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
messages and information updates across communities
through trusted Parent Council communication channels.
This engagement approach will inform how non statutory
and informal engagement in relation to potential school
estate changes and long-term strategic learning estate work
may be taken forward in the future by the Council. 
Additionally, high levels of positive engagement are being
secured as part of the space planning process for the new
extension, supporting active parental and carer participation
and influence in the design process of the new extension and
wider changes to the school that are planned to be delivered.
This is increasingly building a positive community
commitment and level of direct participation in the delivery
of the school extension and improvement project. 
The review of the Council’s engagement strategy as referred
to above will include a qualitative assessment of the
effectiveness of the Park Mains Liaison Group. 
Lastly, work is being progressed by officers to research how
other councils have approached school extension projects,
where a statutory consultation process is not required. The
objective of this work is to inform the design of a framework
to inform any future approach to early informal engagement
that can be adopted by the Council in relation to school
estate considerations or changes.

Page 33

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility 
Desk top work completed to date has identified a mixed
picture with several councils having adopted a similar
approach to that employed by the Council for the PMHS
extension. However, there are some examples of the use of
published options appraisals as part of Council reports and
identified examples of planned informal engagement
strategies deployed as part of long-term strategic school
estate planning which provide some good practice
approaches for reference. 
These individual elements of good practice that are evident
across other councils can be collectively brought together
and used to inform and guide the development of a proposed
framework for use by the Council in its future strategic school
estate planning programme (where appropriate this will pay
due regard to the Scottish Government guidance on informal
engagement that may occur prior to a statutory consultation
process). 
In completing this work consideration will be given to sharing
the output across the local authority sector given what
appears to be a level of mixed and inconsistent approaches
deployed across the country. 
August 2024  Director of
Children’s Services

Page 34

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
We note that the new primary school is subject to a full
public consultation. 
We expect the council to engage meaningfully with the
community on this issue, and other decisions on the school
estate. 
Again, we ask that the Controller monitors this situation,
and reports to us in June 2024 on progress and earlier if
necessary. 
The Education and Children’s Services Policy board approved
the planned consultation programme in January with a
report on the outcome of the consultation planned to be
brought back to Policy Board in May. 
A full programme of planned consultation and engagement
activity has been developed with input from the Institute of
Consultation to bring to the design process experience of
recognised best practice deployed across the UK. 
Full details of the planned consultation process and activity
will be provided to the external auditors as well as the
opportunity to observe any of the planned information
events and or formal consultation meetings. 
The approach specifically developed for this consultation
process as well as the evaluation of its effectiveness will be
used to inform a best practice approach for use in any future
statutory and non-statutory school consultation processes as
well as wider consultation and engagement activities the
Council may undertake in relation to any future service or
policy changes.   
Consultation
process has
commenced
and will fully
complete with
a report to the
Education and
Children’s
Services Policy
Board in May
2024 
Director of
Children’s Services

Page 35

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
Learning lessons and building capacity 
While the council’s initial response to the Bowles report
was high level, we are assured by the Controller that its
action plan in response is now sufficiently detailed and
includes SMART objectives 
It will be important that this action plan is well-managed
by senior officers and closely scrutinised by elected
members of the council. 
The action plan is regularly monitored by senior officers
through existing officer governance arrangements in relation
to Dargavel with an update on progress reported to each
cycle of the Audit Risk and Scrutiny Board and updates will be
shared with the external auditors on an ongoing basis.
Ongoing Director of Finance
and Resources
However, there are still significant uncertainties relating to 
• the capacity needed in the long term, and 
• to the completion of the two building projects –
the new primary school and the secondary school
extension. 
We therefore request that these matters are closely
monitored in the annual audit work, and the Controller
uses her powers to report any slippage or other issues to
us if necessary. 
Managing the Risk of Future Capacity Uncertainty 
The inherent uncertainty in relation to long term (15 year)
pupil growth projections has been widely reported by the
Council over the past year as an ongoing risk through both
formal board reports, as well as engagement and
communications with communities and in sharing data and
reports with the external auditors. This is particularly
recognised by the Council in the context of Dargavel Village
having approximately 10 years of development still to deliver
before achieving completion. It has also been trailed that the
Council’s projection work to date with Edge Analytics has
identified an expectation of a peak in demand to be reached
which will then fall to a stabilised long-term level of demand
– a similar pattern of demand growth has been evidenced
across other similar long term community growth areas in
the UK.

Page 36

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
The Council has heavily trailed the need to regularly monitor
actual pupil numbers and update long term projections on a
regular basis over coming years as a key response to being
able to pro-actively manage this risk moving forward. 
This monitoring process will be key to assess the extent to
which actual demand and revised projections is or is not
tracking against the current projections that have informed
the planned capacity levels that will be delivered by the
current learning estate interventions and provide early
indication of any risk of material deviation. The planned
annual monitoring and updating approach that will be
deployed over coming years will be shared with the External
Auditors. 
Long term projection work completed to date has already
modelled a range of potential demand scenarios for the
primary sector and identified an expected peak of demand in
2033/34. Options that can be considered for deployment in
future years to manage upper demand scenarios that would
be exceed the planned capacity being delivered for primary
sector education within Dargavel village, have already been
identified and reported through the Education and Children’s
Services Policy Board in November and shared with
community representatives. 
Should the monitoring arrangements over the coming years
highlight projection of sustained demand trending towards
the upper demand scenarios, an appraisal will be required to
assess which of the options is most appropriate for 
March 2024  Director of
Children’s Services

Page 37

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
consideration to be deployed to meet the scale and nature of
the additional future demand. This process will include early
community engagement with school communities and will
require timely assessment and associated decision making to
allow planned delivery of any additional intervention well
ahead of the developing need. 
In relation to the secondary sector, the impact of higher
demand scenarios will take longer to emerge (mid to late
2030s) and similarly it has been well trailed in Council reports
and with the community that long term monitoring and
projection modelling may identify the need to consider
options at an appropriate future point in time in respect to
any further intervention and or decisions in relation to
secondary sector provision across West Renfrewshire.   
Similarly, the long-term monitoring arrangements will
facilitate early identification of such risks and will support
early engagement with the appropriate primary and
secondary schools that may be impacted by any future school
estate changes. 
Delivery of New School Facilities 
It has been recognised by the Council that as a result of the
very late identification of the significant under-capacity
problems within both the primary and secondary sectors
serving Dargavel, the Council has since late 2023 been
operating within a highly compressed non-typical timeline to
undertake all the associated capacity planning, land

Page 38

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
assembly, community engagement, statutory consultation,
space planning, procurement arrangements before moving
into project delivery in order to achieve operational delivery
of the new facilities by August 2027. 
In broad terms, the Council is seeking to achieve all that is
associated with the long-term strategic planning,
engagement, consultation and operational delivery of a new
school and major extension of a secondary school in a 4 ½
year period, when such an end-to-end process would
normally run over a much longer period – a timeline of
around 6-8 year would not be an untypical period of
timeframe. Consequently, the Council is parallel running
several activities that would in most circumstances be
delivered in a broadly consecutive manner. 
The Council has established governance, programming, and
resource arrangements in place to support the delivery of the
new primary school and secondary school extension over the
remaining 3 ½ year period through to the operational target
date of August 2007. 
To date the external auditors have not undertaken any
detailed scrutiny of the delivery programme or the
arrangements in place. To provide assurance officers will
provide a full overview of the current arrangements for the
external auditors for their review and will support whatever
audit work is required to allow them to assess the Council’s
current approach. 
March 2024  Director of
Children’s Services

Page 39

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
Impact on service provision 
We note that the council has assessed that currently there
has been no detriment to either teaching delivery or pupil
education in the Dargavel and Bishopton areas from the
interim measures introduced. 
We consider it critical that the council reports the results
of these assessments publicly, regularly and in an
accessible way, to maintain and rebuild community
confidence. 
Renfrewshire Council has a robust Quality Assurance
framework involving regular meetings with Education
Managers and school staff and planned school visits which
focus in on the national quality assurance indicators
(reviews). 
DPS had a visit in January as part of this process where key
strengths under the national Quality Assurance indicators
from How Good is Our School were evaluated, self-
improvement and self-evaluation and Learning, Teaching and
Assessment and a report was produced. In addition,
Bishopton primary School and Park Mains High School were
both recently inspected by HMI, receiving very positive
reports. 
Further, every school submits a school improvement plan
and a school improvement report (published on website) and
their evaluations under the 4 key Quality Indicators (QIs) of
their performance, based on data gathered through self-
evaluation, HMI visits, internal visits and stakeholder input is
submitted to Children’s Services in April. 
These are shared with the parent councils and will also be
published on the school website as part of the self-evaluation
process. This is in line with Education Scotland guidelines, the
National Improvement Framework and statutory
requirements. 
Ongoing as
part of the
Service’s
Quality
Assurance
Framework 
Director of
Children’s Services

Page 40

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
The opportunity will be taken through the wider engagement
channels established with the Dargavel, Bishopton and wider
PMHS communities to sign post and raise awareness of
parents and carers to this information to provide an ongoing
understanding and reassurance in respect to the school
evaluation arrangements and outputs. 
Ongoing and
will be
incorporated
into parent
and school
newsletters at
appropriate
points. 
Head of Marketing
and
Communications 
The Commission is also concerned at the possible wider
impacts of the council’s failings regarding the estimation of
pupil numbers and whether this has had any impact on
services provided by the council in the Dargavel area. 
We request that the Controller seeks further information
on these issues so that we can understand the work that
the council has done to understand these impacts. 
The Council has considered a range of service provision and
other issues for Dargavel Village in addition to addressing
both primary and school provision. This has included the
following which will be shared with the external audit team
as part of their audit work: 
Leisure provision – the new primary school is planned to
incorporate a full-sized floodlight synthetic pitch with
associated changing facilities appropriate for community use
recognising the removal of similar facilities through the
history of the S.75 process since 2009, and the growing scale
and demand for such facilities from children, youth and
ultimately adult football within Dargavel and Bishopton
which is expected to expand further as Dargavel develops.
This facility will complement the resurfacing and
improvement of two floodlight synthetic pitches at PMHS
which will also serve the area as well as working with the
local Community Trust to progress their sport provision
ambitions within Bishopton. Beyond organised football, it
would be expected that this facility would be capable of
In line with
requests
emerging from
defined audit
programme to
be set by Azets
Chief Executive

Page 41

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
supporting a range of potential community uses in the
future. 
Community Facilities & planned play and recreation space –
a key part of the planned design ethos of the new primary
school is to create maximum flexibility to support delivery of
a community asset that will be able to offer facilities for a
wide range of community uses for all ages outwith school
hours. This was identified through the space planning
engagement stage and will address the failure to incorporate
wider community use into the design of the existing Dargavel
Primary School. This also recognises the future demand for
such facilities as the development progresses and will
provide useful insight for the Council as to how community
use can be more effectively incorporated into the design of a
new school and position such new facilities as attractive
community hubs for active use beyond the school day. 
A review of planned play and recreation spaces within the
masterplan / S.75 Leisure Strategy was also undertaken –
although there have been issues identified with the scale and
quality of play equipment provided to date at individual
designated play park areas that has been raised with BAE
Systems, the overall scale of provision was not influenced by
the Council’s calculations of school roll projection. 
Transport and travel infrastructure and bus service provision
– the Council has commissioned an external review of active
travel and traffic modelling as part of planning for a second
school within the masterplan area. A range of

Page 42

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
recommendations for consideration in relation to the
masterplan infrastructure have been made and which will be
progressed in discussion with BAE systems to enhance and
improve the opportunity for active travel.  
In addition, detailed engagement has been undertaken with
the Community to adapt proposals to utilise a financial
contribution from the S.75 to establish a bus service, partly
reflecting consideration of the anticipated number young
people that will emerge from the development and the range
of facilities they would most likely wish to travel to by public
transport. 
Support to schools – arrangements to provide appropriate
enhancement to management support to the school
recognising the additional demand being placed on the
school management teams were put in place early in the
process. Moving forward, normal arrangements to assess
and align both central support services to school as well as
school management teams as school rolls expand will be
undertaken in years to come. 
By way of example, there is a CAMHS officer who works as
the link for Children’s Services and who is currently working
with a group of schools in Linwood as part of a pilot to assess
demand and how that is being met. The next cluster
identified to receive this additional support will be Park
Mains and we are working closely with Educational
Psychologists and Family Wellbeing teams to ensure that, if

Page 43

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
there is an increase in expected demand, that this is being
met and indeed planned for as the school roll expands over
future years. Education Managers are monitoring and
working closely with the school and the CAMHS officer will
provide us with the data. 
NHS facilities and services – engagement has taken place
with IJB/HSCP colleagues as the Dargavel review unfolded. In
terms of data, pupil projection data relies on NHS data
flowing to support the pupil projection modelling – pupil data
does not conversely inform or influence NHS data and
planning and therefore there was no identified risk to any
under sizing of NHS planning as a consequence of pupil
projection errors by the Council. IJB/HSCP colleagues have
however considered the issue of planning for uncertainty in
respect population growth at Dargavel in terms planning the
design and delivery of the new health facility which will be
future proofed for potential future extension if required. 
Financial management and consequences 
The financial impact of these failings on the council is
significant. The council capped the risk and contributions
from BAE Systems under the Section 75 agreement, and as
a direct result faces estimated net additional capital costs
of £60 million, to be met by borrowing. This is a substantial
sum of public money. The council needs to clarify the
opportunity costs of this in terms of its overall capital
programme. The council projects that it will have a revenue
budget deficit of up to £50 million by 2026/27 and will
The Council will be required to manage the financial impact
of the unplanned delivery of a new primary school and larger
extension at PMHS through the delivery of its wider financial
strategy and any opportunity costs articulated as part of
developing and delivering that strategy. 
Will be
considered in
February 2024
as part of the
Council’s
annual budget
considerations
and updated
Director of Finance
and Resources

Page 44

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
need to make difficult decisions on prioritising its spending,
compounded by the financial consequences of this issue 
The council has recently negotiated a transfer of land from
BAE for the construction of a new primary school. The
Controller’s report indicates that this was in exchange for
amendments to the extent and composition of the housing
units for which planning permission has been granted. 
Given the reported determination of BAE to fully protect
their commercial interests in the development, and the
absence of alternative solutions for the council, it will be
important to ensure and demonstrate that this exchange
represents Best Value for the public purse. 
The financial and wider factors considered by officers as part
of the negotiation process with BAE systems to secure the
associated land agreement and adjustments to the S.75
agreement will be set out in detail and shared with the
External Auditors and will be reported through updates to
the Audit Risk and Scrutiny Board and subsequently. 
financial
strategy. 
March 2024 
Head of Economy
and Development 
Council leadership, governance, and culture 
The council’s action plan will be hugely important in
further embedding improvements in this area. In
particular, the following elements must be progressed
urgently and transparently: 
• the council’s review of its scrutiny arrangements against
CIPFA good practice guidelines 
• the council’s review of its approach to risk management 
Officers will provide the current scope and timings of the
associated actions and current progress in relation to each
action being progressed through the Council’s existing action
plan to the Audit Risk and Scrutiny Board and where required
will also be reported through any other appropriate
governance route within the Council. 
February 2024
and ongoing in
relation to the
outcomes
associated
with each
action.
Director of Finance
& Resources

Page 45

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
• the council’s leadership development programme for
officers. 
To be satisfied of progress in these areas, the Commission
requires the Controller to request further information from
the council on the scope and timing of these actions, and
report back to the Commission in the update requested for
June 2024, or earlier if she thinks necessary. 
We also expect these issues to be covered in the
accelerated Best Value report.
The Commission is also concerned about the culture of the
council and whether it has truly learned the lessons it
needs to. 
We expect organisational culture to be an area of focus in
the accelerated Best Value report. 
In particular, we request an update on whether the 
• culture of the organisation is appropriately open
and transparent, 
• encourages continuous improvement, 
• effective joint working between officers and
members, effective scrutiny and challenge
(especially by elected members), and 
• engagement and discussion with stakeholders. 
The council’s auditors concluded that the council has
appropriate governance arrangements in place with
improvements over the years in member and officer
relationships and effective leadership overall and were
satisfied through their detailed audit work that the Council
had demonstrated that the governance failings identified by
the Bowles report were limited to the historic handling of
Dargavel. 
The auditors did not highlight any concerns over the wider
organisational culture in the Council or in its approach to
managing major capital programmes but did identify that the
role of the Audit, Risk and Scrutiny Board in ensuring
effective scrutiny is not sufficiently clear and the Council has
recognised this and is already significantly progressed with a
review of the Audit Risk and Scrutiny Board and the outcome
of this review will be shared with the local audit team.

Page 46

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility 
In addition, we request an assessment of 
• whether it has the right skills in the right places to
deliver on its responsibilities, and 
• whether issues are escalated to the right level. 
Despite the finding of the Council’s auditors, the Commission
has expressed concern in relation to the Council’s culture and
have sought further assurances in relation to a wide range of
organisational issues. 
It is expected that the assessment of such issues will form
part of the planned Best Value Audit process and subject to
confirmation of the planned detailed best value audit
programme, Council officers will provide all the necessary
support, assistance and information to allow the audit team
to appropriately assess all key areas of interest. 
Subject to
confirmation
of the planned
best value
audit
programme
and approach 
Chief Executive 
Finally, the Commission notes that the auditor has
concluded that the council has obtained appropriate
external legal advice and determined there is no potential
for any form of action against former senior employees
involved in the Dargavel School decision-making. 
In addition, no disciplinary action has been taken against
any senior officer involved in decision-making relevant to
the Section 75 approval process for the Dargavel Village
development. 
The Commission accepts that these are management
issues. 
However, we request that the Controller asks the council
for further information on the process followed and 
No senior officers involved in the Dargavel S.75 decision
making process and identified in the Bowles Report remain
employed by the Council or remained employed at the time
of the Bowles report publication. In this context no senior
officer could be subject to any form of internal Council
disciplinary investigation or action. 
Full details of the process of consideration and legal advice
that was sought regard to any other form of external legal
action will be shared with the local external audit team as
requested by the Commission. 
Equally, arrangements will be made to provide the external
audit team with the Council’s disciplinary policy and
procedures as well as the overall approach to performance
management across the Council and support any further 
March 2024 
March 2024 
Head of Corporate
Governance 
Head of Policy and
Partnerships and
Head of HR & OD

Page 47

APPENDIX 2
Council Response and Planned Actions 
Accounts Commission Finding  Council Response and Actions  Timeline  Responsibility
factors taken into account by the council in considering
disciplinary action against staff involved. 
In addition, and looking forward, the Commission asks for
information on 
• the council’s approach to performance
management and 
• its current policy on disciplinary action, 
so we can be assured that appropriate arrangements are in
place to ensure that staff have the necessary skills and that
senior officers are properly accountable for their areas of
responsibility. 
request that may emerge from their planned audit work in
this regard.