Appointment of Advanced Manufacturing Innovation District Scotland Development Partner - FINAL

Renfrewshire Council · 4 May 2023
Back to Council — 4 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Council
On: 4 May 2023
___________________________________________________________________
Report by: Chief Executive and Director of Finance and Resources
___________________________________________________________________
Heading: Appointment of Advanced Manufacturing Innovation District
Scotland Development Partner
___________________________________________________________________
1. Summary 
1.1 The Leadership Board in February 2021 noted the Council’s intention to procure
a Development Partner for the next stage of the Council’s Advanced
Manufacturing Innovation District Scotland (AMIDS) development, to ensure
long term economic benefits and regeneration is secured at the former
Netherton Farm site. This procurement process has now completed. 
1.2 This report seeks approval from the Council to appoint the Development Partner
to move the Council’s AMIDS to the next stage, building on the Council’s
significant City Deal and other financial investment in enabling infrastructure
and the wider investment in anchor facilities, namely, the National
Manufacturing Institute Scotland and the CPI Medicines Manufacturing
Innovation Centre. 
The Development Partner will work with the Council and other stakeholders to bring
forward suitable advanced manufacturing facilities and occupiers that will support
realising the Council’s ambitious vision to deliver long term economic growth and high-
quality jobs to the area and wider city region.
________________________________________________________________________ 
2. Recommendations 
2.1 Council is asked to: 
i) Note the scale of ambition and anticipated benefits resulting from the
successful delivery of the next phase of the AMIDS project as outlined in
this paper; and

Page 2

ii) Approve the Council’s participation in developing the AMIDS site in
partnership with Tarras Park Properties Limited through membership of a
Limited Liability Partnership (LLP); and 
iii) Authorise the Director of Finance and Resources to sign on the Council’s
behalf all documents required to formalise the Council’s participation in
the LLP and to regulate the operation of the partnership; and 
iv) Approve the nomination of Barbara Walker, City Deal and Infrastructure
Programme Director and Alastair McArthur, Director of Finance and
Resource as the Council’s representatives on the Board of the LLP; and 
v) Approve the drawdown of land in parcels for specific development in
accordance with the LLP Business Plan; and 
vi) Authorise the Head of Corporate Governance in conjunction with the City
Deal and Infrastructure Programme Director to make minor alterations to
the documents as required prior to signing; and 
vii) Instruct that progress and updates and any future decision requirements
on the development of AMIDS or the future of the LLP be taken to the
relevant Council Board. 
___________________________________________________________________
3. Background 
3.1. The foundations of the AMIDS vision commenced back in 2014 when the
Glasgow City Region City Deal Infrastructure Fund enabled the Council to
progress the Glasgow Airport Investment Area (GAIA) project which provides
the enabling infrastructure for the AMIDS Netherton Campus. 
3.2. The GAIA Business Case noted the City Deal benefits anticipated. 
AMIDS will capitalise on the advanced engineering and manufacturing
expertise that exists across multiple technologies in both industry and academia
in Renfrewshire and Scotland and will further strengthen that capability to create
competitive advantage for existing and new companies to remain globally
competitive, and drive inclusive, sustainable growth in the Scottish economy.
The development of AMIDS has the potential to create thousands of new jobs
in Renfrewshire, if managed well and with active support and cooperation of all
partners. 
3.3. The City Deal Business Case for GAIA included the purchase of Netherton
Farm which enabled the Council to develop a masterplan for the whole
Netherton Campus and design and deliver the enabling infrastructure for
AMIDS. The masterplan was developed in consultation with stakeholders and
partners to ensure the site provided all the necessary ingredients of a
development ready site which would be attractive to the high-quality innovative
occupiers sought. 
The initial phase of the long term business case has focused on delivery of the
physical infrastructure required to provide a successful campus style

Page 3

development which will facilitate and encourage collaboration and healthy
workplaces for future occupiers, a high quality outdoor public realm area central
to the development, an innovative district heating network for all occupiers
contributing to the Council’s low carbon targets and connected active travel
infrastructure throughout, providing employees options for work-based travel. 
3.4. The next longer-term phase of AMIDS is to attract suitable high quality
advanced manufacturing occupiers and develop out the site providing
potentially thousands of high-quality jobs and to realise the Council’s City Deal
benefits of additional long term economic growth. The provision of jobs included
in the GAIA business case envisaged this phase of development would take up
to 20 years reflecting the long-term nature of this phase of the business case.
Given the scale and finance required to facilitate and realise such an ambition
it was always recognised that the Council would need to secure an expert
partner to help achieve delivery of the development over the long term given
the specialist nature of this type of development. The Netherton Farm site was
purchased by the Council to provide high quality development and economic
opportunities and jobs for our businesses and residents and not with a view to
simply securing future land value receipts. These sustainable jobs and
economic growth can only be realised if the site is developed as a whole and in
accordance with a masterplan and not sold off piecemeal to individual
businesses.  Meeting these economic and job growth objectives have been the
primary driver in setting out the Council would take forward delivery of the
AMIDS campus. In this context, it has always been acknowledged that the
Council alone, does not have either the internal resource capacity, specialist
expertise or skills to effectively progress this stage of the business case and
would therefore be required to achieve this through an external partner.
Notwithstanding this requirement, in moving forward arrangements to secure
an appropriate partner, a primary objective has been to ensure the Council
retains an appropriate level of control to provide confidence that the original
vision and aspiration of the AMIDS business case and masterplan can be met. 
3.5. In reaching this stage the Council have had advice and support from our
partners on the AMIDS Strategic Advisory Group (SAG) which includes senior
representatives from the Council, Scottish Government, Scottish Enterprise,
SDS, NMIS, MMIC, Strathclyde University and West College Scotland. These
representatives have collaborated to determine the potential target innovation
sectors and organisations to locate at AMIDS and ensure Renfrewshire
residents and businesses are given maximum opportunity for skills
development and long-term high quality, sustainable employment. Several SAG
members have been involved in the successful creation of Innovation Districts
previously and have contacts within specialist markets where potential
occupiers for AMIDS are represented. This group will continue in an advisory
role over the longer term alongside the LLP and will bring welcome specialist
information and innovation experience to the LLP assisting in the identification
of innovative organisations who may be attracted to AMIDS. 
3.6. Modern facilities for manufacturing in Scotland are in short supply and so
interest in locating at AMIDS is already strong from organisations within both
the UK and global advanced manufacturing innovation sector. These specialist
organisations focus is on investment in the development of their innovative
products. Companies in this sector generally look to find suitable locations

Page 4

where investment and construction of bespoke property can be undertaken by
others with the organisation entering into a long lease of the premises. Although
interest is already strong, progressing such interest to the stage of secured long
term occupation is a major undertaking requiring specialist skills and
understanding of this market and these skills will be provided by the
Development Partner. 
3.7. External legal and specialist property advisors have advised the Council in
evaluating the options for the most suitable vehicle for procuring an AMIDS
Development Partner. Given the nature and anticipated longevity of the
partnership envisaged, entering into a Limited Liability Partnership Agreement
with a partner was identified as being the most appropriate route forward. In
Scotland, an LLP can own assets, grant security, enter contracts and borrow
money and has a legal personality independent of its members. A benefit of the
LLP over a limited company is increased flexibility, both in respect of profit
sharing and in the introduction of new members. 
4. Limited Liability Partnership (LLP) 
4.1. The LLP option meets the Council’s objectives of providing an appropriate
vehicle to secure access to development funding and property market expertise
whilst retaining sufficient control to ensure the City Deal and AMIDS project
objectives, including provision of sustainable employment, are delivered. 
4.2. The City Deal infrastructure has been delivered for the purposes of securing
high quality serviced land capacity at AMIDS to support long term development,
attracting high quality occupiers and inward investment supporting quality
employment and long-term economic growth. Financial modelling for the project
is subject to changes in market conditions however indications are that the
potential income for the Council through the LLP arrangements, at completion
of the AMIDS development, would be greater than current land sale potential.
Therefore, although not a primary objective in the delivery of the AMIDS
business case, it is anticipated that over the long term, the Council will secure
through financial returns via the LLP partnership arrangement, the inherent
value in the AMIDS site in addition to achieving the Council’s City Deal
commitments. 
4.3. The LLP will be established on a 50:50 Joint Venture Development Partnership
between Tarras Park Properties Limited (the Development Partner) and
Renfrewshire Council. The Development Partnership will operate under the
direction of an LLP Board, consisting of two Council officers and two
representatives from Tarras Park Properties Limited. The 50:50 constitution of
the LLP board provides comfort that the Council will be able to appropriately
and directly influence the project outcomes. 
4.4. The Development Partner will be responsible for implementation of decisions
and actions from the LLP Board in relation to development progression,
marketing, and general management of AMIDS. It is recognised that changes
in market conditions, requiring differing approaches to maintain progression of
AMIDS may emerge given the expectation that achieving full development of
the AMIDS site is likely to be a long-term project.

Page 5

4.5. The Development Partner will actively attend/liaise with the AMIDS Strategic
Advisory Group and other stakeholders, building on and maximising the
benefits from this already established and influential stakeholder group to
optimise the industry reach and opportunity to deliver the anticipated outcomes
successfully and collaboratively at AMIDS. 
4.6. The LLP will operate strictly within a defined range of parameters which are set
out in the LLP Agreement and will form the basis on which suitable development
can be brought forward at AMIDS. Should there be any future proposal by the
Development Partner to progress a development phase outwith the
parameters, this would require an additional approval of the relevant Council
Board. To protect the advanced manufacturing ambition, maximise employment
potential and ensure appropriate users locate at AMIDS, all organisations being
considered for AMIDS, must align with the Planning Permission in Principle
consent (PPiP) approved in March 2019 and the Eligibility Criteria, compiled
and agreed with the AMIDS SAG. 
4.7. The Development Partner will be required to provide the capital to support the
LLP’s cash requirement in bringing forward suitable occupiers for the AMIDS
site. The Development Partner will fund the initial cash requirements to fund the
LLP up to £275,000 as a minimum requirement but this figure will increase to
match any agreed business plan requirements, in the pre-development and set
up stage. 
4.8. The Development Partner will, through the LLP, commence and fund an early
first phase of development on a speculative basis, starting design and technical
due diligence within 12 months and completing development within 3 years of
joining the LLP. While detailed design and statutory consents require to be
progressed, the indicative first phase will extend to circa 37,000sqft of
employment space, targeted at start-up companies and SME’s. The value of
this initial investment is anticipated to be circa £3.8million. 
4.9. Future phases of development will be progressed based on occupying
companies needs and agreed financial terms. The Development Partner has
committed to provide development funding up to £7.6million subject to
satisfactory business cases for initial phases of AMIDS development though
overall this could be significantly more. 
4.10. It is proposed that the Council Directors appointed are Alastair McArthur,
Director of Finance and Resource and Barbara Walker, City Deal and
Infrastructure Programme Director. 
4.11. It is important to note that the Council will only make available individual
development parcels to the LLP on a noncash basis upon confirmation that a
satisfactory Business Case is in place for each development. The Council will
also retain some control over the land drawn down and developed by the LLP
through a 150 year ground lease. The land area included in the LLP Agreement
(to be drawn down in parcels) is shown at Appendix A. 
As part of the LLP agreement, the Council and the Development Partner will
also enter into the Pre-Development Services Contract (PDSC). The PDSC sets
out the terms on which the Development Partner will provide the Services
during the Pre-Development phase of each phase of the Project.

Page 6

4.12. Once a viable Phase Business Case is in place and the Council make the
relevant parcel of land required available, the LLP will enter into a Development
Management Agreement to cover the management of the physical
development of each Phase. The Development Management Fee with be a
fixed fee calculated as 3% of the total development costs for the phase. 
5. Procurement of Preferred Development Partner 
5.1. The Council used the competitive dialogue procedure to procure a suitable
Development Partner and following conclusion of this exercise, Tarras Park
Properties Limited has been identified as the preferred partner. 
5.2. On 21st February 2022, Renfrewshire Council published a Contract Notice on
the Public Contracts Scotland portal. 
The Invitation to Participate in Dialogue and SPD information and instructions
were published on PCS-t on the same day. By the request to participate (RTP)
deadline on 24th March 2022 at 12 noon, two (2) Bidders submitted an RTP.
The Council’s AMIDS Dialogue team including external Advisers Addleshaw
Goddard LLP and Avison Young LLP evaluated the RTP submissions and
assessed that both Bidders met the Selection Criteria and demonstrated the
experience, financial capacity, development resources and management
capability to bring forward the progression of AMIDS. 
5.3. Following the Selection Stage (SPD stage), the procurement procedure was
conducted in successive stages of Draft Tender, Dialogue Phase and Final
Tender.  By the Draft Tender deadline on 18th July 2022, one Bidder advised
that a significant investment in Glasgow City Centre would require such focus
that they withdraw from the AMIDS procurement process. The Council received
one (1) Draft Tender and proceeded to review this submission and dialogue
with the remaining Bidder. 
5.4. The Council conducted dialogue with the remaining Bidder over summer and
autumn 2022. The draft documents which form the basis of the LLP Agreement,
included a range of aspects to ensure the alignment of the Council’s aims for
AMIDS were discussed extensively with the Bidder during the dialogue phase.
Final drafts were agreed with the Bidder and dialogue phase closed in April
2023.   
5.5. On 18th April 2023, the Bidder submitted their Final Tender. The Council’s
Dialogue Team assessed the Final Tender against the Award Criteria 30.00%
Price/ 70.00% Quality specified in the Contract Notice. The Bidder’s scores in
respect of the criteria are noted below: 
Bidder Price Quality  Total
Tarras Park
Properties
Limited
30.00% 54.00%  84.00% 
5.6. The outcome of the exercise has identified a preferred Development Partner
who will work with the Council to deliver AMIDS. Recent changes in economic

Page 7

conditions globally suggests that the outcome of this exercise has been timely
and a unique opportunity now exists to progress AMIDS with this preferred
partner, as other investors seek to hold back on such projects. 
5.7. The negotiated outcome with the preferred development partner is one which
protects the Council’s aspirations for high quality outcomes at AMIDS, secures
AMIDS as a centre for skilled employment and training into the future and
provides a range of checks and balances to effectively manage risk and finance. 
5.8. Community Benefits were request as part of the procurement process and
Tarras Park Properties Limited confirmed the following Community Benefits
would be delivered through the construction contract for the initial phase: 
Community Benefit Description  No of People / Activity
Job for an unemployed individual
from a Priority Group
1
Job for an unemployed individual 2
Modern Apprenticeship 2
Graduate 1
Work Experience Placement for an
individual 16+ years of age
1
Work Experience Placement for an
individual aged 14 to 16 10
years of age
2
Industry Skill transfer to Schools 1
Event to promote supply chain
opportunities
1
Financial Support for a community
project
1
Non-Financial support to a
community project
1
The Development Partner recognises the opportunity to continue to deliver
long-term community benefit outcomes over the remaining phases of
development focussing on a rolling programme of employment, skills and
training opportunities, supply chain development and community engagement.  
5.9. Tarras Park Properties Limited are also committed to preparing a Community
Benefits Plan under the PDSC and committed to working with the Council’s
Community Benefit form and partners to ensure additional community benefits
are delivered over all phases of development at AMIDS. 
__________________________________________________________________
Implications of the Report 
1. Financial – The Council’s financial contribution to the LLP for Phase 1 is zero (£0)
in monetary terms. As outlined at 4.11 the Council’s investment in the LLP is by
way of non-cash capital investment of the AMID Land subject to business case
agreement by the LLP Board. 
Financial outlay to progress future development will be returned out of future
profits generated through the LLP. Subject to the Council not defaulting on any

Page 8

contractual obligations through the LLP, financial risk rests with the Development
Partner. 
Tarras Park Properties Limited’s financial standing was assessed as part of the
procurement process and to satisfy the Council’s minimum requirements, Tarras
Park Properties Limited is providing security in the form of a Parent Company
Guarantee from The MDS Estates Limited 
2. HR & Organisational Development – two officers of Renfrewshire Council will
serve on the LLP board 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – This project will provide properties for advanced
manufacturing employers to locate. This will facilitate business growth and
improve skills development for people within the local communities. The
projects align with and aid the outcomes of the Renfrewshire Economic
Strategy 2020 -2030 and the Renfrewshire Economic Recovery Plan. 
• Our Renfrewshire is well – Increased employment opportunities will aid health
and social outcomes within Renfrewshire. 
• Reshaping our place, our economy and our future – The project will result in
progression of the Advanced Manufacturing Innovation District in a form which
directly aligns with the council’s policies and ambitions. During the project
construction period jobs will be created and existing jobs supported. The new
occupiers of buildings created will result in additional employment within
Renfrewshire, which will be accessible by people in our communities. 
• Tackling inequality, ensuring opportunities for all – The location of AMIDS,
adjacent to residential communities and the infrastructure and active travel
links to education and skills development centres will ensure our less
advantaged communities are able to access the opportunities provided. 
• Creating a sustainable Renfrewshire for all to enjoy – The design ethos
adopted at AMIDS is one which relies on sustainable transport, active travel,
includes a District Heating Network and all property designs will align with
the Councils net Zero Carbon target. 
• Working together to improve outcomes – Officers are working closely with
local communities, neighbouring councils, private sector organisations,
Scottish Government, Scottish Enterprise and other partners to ensure the
maximisation of positive outcomes from the project. 
4. Legal – as set out in the report 
5. Property/Assets - The land area included in the LLP Agreement (to be drawn
down in parcels) is shown at Appendix A. Once the land is made available to the
LLP, the Council will retain some control over the land through a 150 year ground
lease.  Renfrewshire Council will only make available to the LLP land parcels upon
agreement by the LLP of a business plan for each development.

Page 9

6. Information Technology – none. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report because it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health & Safety – Tarras Park Properties Limited health and safety credentials
were evaluated by Corporate Health and Safety and met the Council’s minimum
requirements regarding health and safety. 
9. Procurement – The procurement process outlined in this report ensures that the
Council meets its statutory requirements in respect of procurement procedures,
efficiency and modern Government. 
10. Risk – Project and Programme level risk registers have been established for the
project. These are kept under regular review and reported to the Council’s internal
City Deal and Infrastructure Programme Board. The Council is not contractually
obliged to provide any capital to funding the LLP other than the land injection in
parcels as outlined in this report. In the event of a default or winding up situation
affecting the LLP situation the Council would have the option to purchase the
interests of the LLP, independently valued at Fair Value. 
11. Privacy Impact - No Privacy Impact implications have been identified or are
anticipated. 
12. COSLA Policy Position – No COSLA Policy Position implications have arisen or
are anticipated.   
13. Climate Risk – The level of impact associated with the AMIDS Development has
been assessed using the Scottish Government Sustainability Test and is
considered High Risk. 
The Development Partner is required to develop a Carbon Reduction Plan under
the PDSC and confirmed that all Contractors, Designers etc appointed by the LLP
will have suitable ISO 14001 or equivalent Environment Management System
accreditations.  
___________________________________________________________________
List of Background Papers 
a) City Deal and AMIDS Projects Update report, Leadership Board, November 2022 
b) Renfrewshire’s City Deal Projects – Final Delivery Phase report, Leadership
Board, February 2021
_________________________________________________________________________
Author: Barbara Walker, City Deal and Infrastructure Programme Director; 
Email Barbara.walker@renfrewshire.gov.uk

Page 10