___________________________________________________________________
To:  Council
On:  26 June 2025
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Accounts Commission - Best Value Audit Report
___________________________________________________________________    
1.  Summary
1.1  The duty of Best Value applies to all public bodies in Scotland and requires
organisations to ensure that there is good governance and effective
management of resources, whilst also ensuring activities focus on
improvement and deliver the best possible outcomes for the public. 
1.2 A Controller of Audit Best Value report for Renfrewshire Council has been
prepared by Audit Scotland and was considered by the Accounts Commission
on 15 May 2025. Following this, the Accounts Commission published their
findings on 5 June 2025.
1.3 Appended to this paper is the covering report outlining the Commission’s
findings and the Controller of Audit Best Value report. This was a very positive
report and the key points to note are outlined in section 4. In line with statutory
requirements, Council is asked to consider the findings from the Controller of
Audit Best Value report.
1.4 The work underpinning these reports has been undertaken as part of the
ongoing audit activity by the Council’s external auditors, Azets, which is
regularly reported to Audit, Risk and Scrutiny Board, including a recent
‘Interim Update Report’ which was considered in April 2025. Best Value and
associated improvement activity is also regularly reported to Leadership
Board with the last update provided in February 2025.
1.5 Elected members will note that there are no formal recommendations for the
Council to action in relation to the reports, however in line with our core value
“We Value Learning”, officers have highlighted a number of activities which
will be progressed by the organisation through its ongoing Corporate

Page 2

Improvement Plan within section 5 of the report.  The majority of these actions
have been identified through previous audits and self-assessment activities. 
Progress in terms of implementation of the plan will continue to be reported to
Leadership Board on a 6 monthly basis. 
___________________________________________________________________
2.  Recommendations
2.1   It is recommended that members: 
• note and accept the Accounts Commission’s findings noting officer
feedback outlined at section 4.
• Agree that improvements identified through the Best Value audit process
will be incorporated into the existing Corporate Improvement Plan and
reported to the Leadership Board on a 6 monthly basis.
• Note the next update on the Corporate Improvement Plan will be provided
to Leadership Board in September 2025.
___________________________________________________________________
3.  Background
3.1  Renfrewshire Council has a well-established commitment to delivering Best
Value and continuous improvement, underpinned by a programme of self-
assessment and reflecting a wide range of external audit, scrutiny and
inspection processes that the organisation participates in. 
3.2 Regular reports to Leadership Board have outlined the changes in the
national Best Value methodology, particularly the introduction of annual
thematic reviews and also the preparation for Renfrewshire Council’s ‘full’
Best Value report, also known as a Controller of Audit Report. 
3.3 All local authorities in Scotland are subject to a Controller of Audit Best Value
Report within the rolling five-year programme. These are prepared by Audit
Scotland, considered by the Accounts Commission, and reflect all audit work
carried out by external auditors since the new auditing cycle commenced in
2022/23. 
3.4 For Renfrewshire Council, our external auditors are the auditing firm Azets.
Alongside the standard thematic reviews and annual audit reporting, auditing
work considered within the scope of this Controller of Audit Best Value report
has included following up on audit recommendations related to the previous
section 102 reporting on Dargavel. 
3.5 Officers and Elected Members have engaged extensively with Azets, who
have in turn worked closely with Audit Scotland to support the Controller of
Audit to prepare her report. As noted above, this report was considered by the
Accounts Commission on 15 May 2025 and their findings were published on 5
June 2025.

Page 3

3.6 As part of the statutory process, all Elected Members were provided with a
copy of the report when this was published on 5 June 2025, and the Best
Value report and Commission findings are required to be considered through
a meeting of the Council within 3 months of the publication date.   
3.7 Members of the Accounts Commission also visited Renfrewshire Council
earlier this month, to discuss the report and to set out the Commission’s
expectations in terms of monitoring progress as part of the annual audit
process. 
4.  Key findings
4.1 As noted in the Account Commissions’ findings, the Commission welcomed
the Best Value Report on Renfrewshire Council and made a number of
observations.  The findings and full report are attached as Appendix 1 to the
report. 
4.2 The Commission:
• Welcomed the Council’s ‘commitment to leadership and creating a
positive working culture across all services’. The Commission also
recognised the Cultural Assurance Model, developed by Renfrewshire Council
in partnership with the Improvement Service, and was keen this was shared
with other local authorities. 
• Were ‘pleased to see that the Council has responded positively’ to the
previous issues raised in relation to Dargavel school provision and noted the
approach to highlighting the costs associated with this. 
• Highlighted the range of good examples of community engagement and noted
it was ‘clear that the Council is working hard to build trust and
confidence with all communities’ across Renfrewshire. 
• Commended the prudent financial management of the Council while noting
the challenge around increasing demand and cost pressures, including for
Renfrewshire’s Integration Joint Board. It also noted the importance of the
next phase of the Council’s transformation programme to tackle the budget
challenge. 
• Recognised the scale and ambition of the Council’s capital programme and
the importance of continuing to address any delivery issues. 
• Welcomed the ‘comprehensive approach to leadership development’ and
were ‘pleased to see’ the Elected Member development programme, including
for Members of the Audit, Risk and Scrutiny Board, whilst highlighting the
importance that Members undertake training where offered.

Page 4

• Highlighted areas of nationally strong performance, including educational
attainment, positive destinations and delayed discharge and noted the
importance of continuing to closely monitor the impact of difficult decisions on
performance and for our communities. 
4.3 Following an assessment by officers, it is recommended that the report and
Commission findings are accepted by Elected Members.  The findings are
assessed as being broadly reflective of areas identified within our own
organisational self-assessment processes, or through recent inspection and
external scrutiny exercises involving the Council which have highlighted very
positive assessments of leadership, culture and performance.  
4.4 The Commission’s findings also reflect the context in which local authorities
are operating, as outlined in several recent national reports, including the
national report on the Local Government Benchmarking Framework, and the
Accounts Commission’s own recent report on Local Government Budgets
2025/26.  They provide a helpful focus on key areas of activity that must be
progressed in relation to transformation and consultation and engagement
with communities in relation to these financial challenges.
4.5 Elected members are asked to note that representation was made to the
Secretary for the Accounts Commission in relation to Finding 5, which notes:
“We recognise the council’s ambitious and complex capital programme, but
the council must address the delivery issues that have affected the
programme in previous years. The programme impacts the council’s revenue
budget, so delays and slippage come at a cost to investment in service
delivery”
4.6 It is suggested that the finding infers that delivery issues relating to the capital
programme in recent years were within the control of the organisation, and
unfortunately fails to recognise the significant impact that both COVID and the
Ukraine war and various other geo-political events had on construction market
supply chains and the availability of core construction materials such as steel,
timber and bitumen for example. Such major global events and their impact on
major construction projects during this period affected projects across all
sectors in the UK and there was limited actions available to the Council to
mitigate their impact on Council projects at that time.
4.7 Whilst projects may on occasion be impacted by local delivery issues, the
Controller of Audit report on Best Value provides additional context which is
not reflected in the Accounts Commission finding on this issue. At paragraphs
60 and 61 of the report attached at Appendix 1, the content reflects the extra-
ordinary supply chain issues experienced in 22/23, with programme delivery
returning to stronger performance in 23/24:
60.  The council’s ability to fully deliver its capital programme within the
originally planned timescales has been impacted by a number of
factors, including the complexity of the works, the cost of materials,
supply chain issues and availability of contractors.

Page 5

61.  In 2022/23, capital projects with a value of around £42 million (25 per
cent of the capital programme) had to be re-profiled. In 2023/24 just 6.5
per cent of the programme was reprofiled into later years. Given the
scale of the council’s ongoing capital programme, delivery to plan is
likely to remain a challenge.
4.8 This position was reinforced to Commission members at its local meeting with
representatives from the Council on 18 June, in addition to the recognition that
the organisation to continue to ensure that it has the skills, capacity and
capabilities required to deliver its future capital investment programmes.
4.9 At this meeting, feedback was also provided to the Accounts Commission on
the Best Value Audit process itself.  It was noted that there were some areas
of the Best Value Audit process where, in line with the methodology utilised,
evidence of progress could not be considered by the Accounts Commission
due to timing of reporting. It was felt that overall this impacted the ability of the
Council to evidence its commitment to continuous improvement and Best
Value.
4.10 Overall, there are no formal recommendations set out by the Accounts
Commission in relation to report. Relevant progress updates specific to the
Section 102 reporting on Dargavel will continue to be reported to the Audit,
Risk and Scrutiny Board and the Education and Children’s Services Policy
Board as usual. 
5.  Priority areas of focus and next steps 
5.1 A core value of Renfrewshire Council is ‘We Value Learning’ and the Council
has a well-established programme of self-assessment to learn and improve.
This helps to ensure that all elements of Best Value are being delivered and
drives forward corporate improvement activities in line with our commitment to
continuous improvement as an organisation.
5.2 There has been a significant amount of audit, scrutiny and inspection activity
supported by the organisation and many colleagues across all services over
the past 18 months. Across this work, there has been a wide range of positive
examples and best practice identified, along similar themes to the Accounts
Commission’s findings. For example, the Adult Support and Inspection report
noted ‘strategic leadership for adult support and protection was accomplished
with elements that were sector leading’. The Joint Inspection of Services for
Children and Young People at Risk of Harm report noted the ‘well-developed
collaborative culture and staff, managers, and leaders (who) worked positively
together across agencies’. Education inspectors commented on Additional
Support Needs Parent Ambassadors who felt ‘they have a genuine voice’. 
5.3 Whilst there are no formal recommendations from the Controller of Audit Best
Value Report, areas of interest have been highlighted by the Accounts
Commission. On the whole, these align with areas already identified as part of
the preparation for the Best Value process or the self-assessment activity
which has underpinned it.

Page 6

5.4 A summary of the key areas of focus is detailed in the table below:
Area of focus Commentary 
Embed Cultural
Assurance Model
approach into cycle of
continuous
improvement 
5 priority actions identified from the Cultural
Assurance Model have already been included in
the Corporate Improvement Plan and where
relevant have been included in Service
Improvement Plans. 
Further work is planned over the year to reflect
further on this work and the findings from the
Employee Engagement Survey, aligning and
building on these insights. 
Share Cultural
Assurance Model with
others
Renfrewshire Council continues to work closely
with the Improvement Service as we share our
experience of developing the model and the
benefits of undertaking this work. A workshop with
a national professional group took place earlier
this month and a number of local authorities have
expressed an interest in the model. 
As this work is mainstreamed into the
Improvement Service’s PSIF offer for all member
organisations, Renfrewshire Council officers will
continue to make themselves available to
champion this work. 
Watching brief on
highlighting costs
associated with Thistle
Primary School and
extension to Park
Mains High School
As with all revenue pressures the Council is
facing, the additional operating costs of both the
Thistle Primary and Park Mains High School are
incorporated into the council’s medium term
financial forecasts with an update expected to be
provided to the Council meeting in September. 
Capital costs for both projects are reported to the
Education and Children’s Services Policy Board
every reporting cycle, on an individual basis giving
Elected Members and the public full information on
both cost and progress with the works and both
projects are fully funded and included within
existing financial plans. 
Evidence community
engagement within
decision making,
policy development
and service planning 
Following the approval of the Consultation and
Engagement policy at Leadership Board earlier
this year, which sets out standards and guidance
for planning, conducting and learning from public
engagement. It is intended to support greater
consistency in the approach to public
engagement, to promote data-sharing across the
Council, and to help build trust with communities

Page 7

Area of focus Commentary 
and other stakeholders. A newly established
Consultation and Engagement Co-ordination
Group will provide strategic oversight and
guidance, and drive improvement activity. 
Updates will be provided to the Leadership Board
on a six-monthly basis. 
The findings from the Residents Survey will also
support decision making and service planning,
acting as a baseline for future engagement and
priority setting. 
Address any delivery
issues in relation to
capital programme 
Officers recognise the challenges in delivering
Renfrewshire’s capital programme - the
programme is ambitious, diverse and complex.
Officers will continue to regularly assess delivery
progress and update Elected Members through
the relevant Policy Boards. It will be important that
the Council continues to appropriately resource
the scale of capacity and skills as part of the
teams established to deliver major programmes
moving forward and this in particular is being built
into the planning for delivery of the developing
strategic investment in the Learning Estate.    
Encourage all Elected
Members to
undertaken training
The Council uses a combination of an intensive
induction programme following each Local
Government election and a targeted annual
development programme for Elected Members.
This is supplemented by bespoke training
opportunities throughout the year. This approach
is regularly reviewed to keep pace with the
changing context and key areas of interest
identified by Elected Members. Training
opportunities are also offered in different formats –
in person, hybrid, online and as a recorded
training seminar available at a time to suit. A suite
of training materials is also provided to enhance
the content, and opportunities for training and
development through organisations such as the
Improvement Service are also shared and
promoted.
Feedback is sought from the annual Members
Development Week and the programme adjusted
to reflect this. Plans are already in development for
the Members Development Week 2025, and also
for the Members Induction Programme following
the 2027 local government elections.

Page 8

Area of focus Commentary 
A range of training options continue to be utilised
by Members, including Board-specific training,
such as for the Audit, Risk and Scrutiny Board. 
Continue to monitor
performance and the
impact of decisions on
service performance
and wider community
outcomes 
A programme of work strengthening the Council’s
approach to performance scrutiny has already
been commenced. This includes the establishment
of an officer performance group to drive improved
performance across Council Plan strategic
outcomes, explore the LGBF and other
benchmarking in more depth and undertake ‘deep
dives’ on Council-wide performance, with a
particular focus on outcomes and the golden
thread between performance and priorities. 
Scope to develop
presentation of options
appraisals and
business case
development (from
CofA report). 
The Council already makes extensive use of
options appraisal and business case development
as part of major investment projects and has an
established business case and options appraisal
process as part of its corporate project
management framework to support the
development and delivery of projects across the
Council. 
To further strengthen this, officers will undertake a
review of the existing corporate guidance, Board
reporting arrangements and will benchmark with
approaches adopted by other Scottish local
authorities to identify specific areas of best
practice and recommended improvement actions
to be adopted into existing arrangements. 
Financial Reporting of
Savings 
The Council will continue to consider where
improvements in financial reporting could be
made, recognising our commitment to
transparency. 
Currently, where Council agrees a saving, this is
baselined within opening departmental budgets,
therefore any non-delivery will result in a
reportable overspend to the relevant Policy Board. 
Further, additional reporting of savings delivery
arising from the Reshaping Renfrewshire
Programme will be built into the major financial
strategy reports brought forward twice a year by
the Director of Finance and Resources.

Page 9

5.5 Actions have already been incorporated into the Corporate Improvement Plan,
and into Service Improvement Planning processes reflecting these areas. A
progress update on the full Corporate Improvement Plan will be reported to
Leadership Board in September 2025. Progressing improvement activity in
relation to Best Value is also an action in the Council Plan Performance
Framework and locally in the Chief Executive’s Service Improvement Plan.
5.6 Progress on Best Value continues to be reviewed as part of the normal
ongoing audit cycle. The Best Value thematic report on transformation and
Annual Audit Report for 2024/25 are being progressed by Azets and will be
reported to Board later this year. 
___________________________________________________________________
Implications of the Report 
1. Financial – there are no financial implications, however the report and the
appendix reference to the financial pressures for the organisation and the
financial reporting in relation to this.   
2.  HR & Organisational Development – none 
3. Community/Council Planning – our commitment to Best Value and the
delivery of many of the activities (including self-assessment) is clearly
established within our Council Plan, particularly through the Living Our Values
strategic priority. The covering report also directly references an action in the
Council Plan in relation to delivering improvement activity. 
4.         Legal - none 
5.         Property/Assets – none 
6.         Information Technology - none 
7.         Equality and Human Rights – there are no negative impacts on equality
groups or potential for infringement of individuals’ human rights arising from
the recommendations contained in the report. 
8.         Health and Safety - none 
9.         Procurement – none 
10.       Risk – none 
11.       Privacy Impact – none 
12.       COSLA Policy Position – none 
13. Climate Risk – none 
14. Children’s Rights - none 
Author:         Pauline Moss, Strategy, Policy and Insight Manager 
Chief Executive’s Service

Page 10

No embedded text on this page.

Page 11

Best Value
Renfrewshire
Council
Prepared by the Controller of Audit
June 2025

Page 12

2Best Value: Renfrewshire Council
Contents
Key facts 3
Commission findings 4
Controller of Audit report 6
Appendix 1 17
Appendix 2 18
Accessibility
You can find out more and read this report using assistive
technology on our website www.audit.scot/accessibility.

Page 13

3Key facts
Key facts
104 Square miles
186,540 Population
8,506 Workforce
43
Elected members
20 SNP, 13 Labour, 4 Independent, 3 Conservatives,
2 Reform, 1 Liberal Democrat
(SNP minority administration)
£33m
Forecast cumulative budget gap for 2026/27
and 2027/28
(before council tax increases)
£513.6m Net revenue budget/expenditure 2023/24
£176m Capital budget 2023/24
(General Fund £146m HRA £30m)

Page 14

4
1. Chapter title
Commission findings
Commission findings
The Accounts Commission welcomes and endorses the Controller of Audit’s
report on Best Value in Renfrewshire Council (presented at page 6), and the
reports and recommendations made by the auditors. Following consideration
of these reports at its meeting on 15 May, the Commission has made the
findings presented below:
1 The council’s commitment to leadership and creating a positive working culture
across all services is to be welcomed. We were interested to see the development
of the ‘Cultural Assurance Model’ in partnership with the Improvement Service.
We encourage the council to ensure that this self-assessment approach is now
bedded in as part of its cycle of continuous improvement, that it continues to focus
on addressing the specific improvement areas identified in its staff survey, and that
the model is shared with others.
2 We are pleased to see that the council has responded positively to issues raised by
the Controller of Audit in previous reports and welcome the auditors’ approach to
highlighting the costs associated with the new primary school in Dargavel and the
extension to Park Mains High School, on which we will keep a watching brief.
3 There are good examples of activities that are enabling and supporting community
engagement across Renfrewshire. A refreshed approach to consultation and
engagement is now in place across the council and although it’s early days,
it is clear that the council is working hard to build trust and confidence with
all communities across the region. Ensuring openness and transparency with
communities will be essential as tough decisions require to be taken and we will
expect to see evidence of community engagement flowing through into decision-
making, policy development and service planning.
4 The council has managed its finances prudently and worked hard over the years to
smooth the impact of fluctuating funding settlements. This has included building up
reserves which have been used to protect services, balance budgets, and support
investment in assets but this is not sustainable over the long term. Increasing
demand and costs mean the council is now facing significant financial pressures in
areas like health and social care, and Renfrewshire’s Integration Joint Board’s (IJB)
reserves are expected to be exhausted by the end of 2025/26. The next phase

Page 15

Commission findings 5
of the council’s transformation plan – Reshaping Renfrewshire – aligned to its
medium-term financial plan, is now central to addressing its growing budget gap
(including within the IJB) and reducing its reliance on reserves.
5 We recognise the council’s ambitious and complex capital programme, but the
council must address the delivery issues that have affected the programme in
previous years. The programme impacts the council’s revenue budget, so delays
and slippage come at a cost to investment in service delivery.
6 As well as a comprehensive approach to leadership development, we are pleased
to see a programme of member development in place, especially in audit, risk, and
scrutiny. All members should be encouraged to undertake training, given the skills
needed to navigate an increasingly complex and challenging external environment
and to take the tough decisions that lie ahead.
7 We will continue to watch the council’s performance with interest, especially
in areas like education where attainment and positive destinations are among
the best and its costs per pupil are among the lowest in Scotland. The council’s
delayed discharges from hospital (age 75+) and hospital readmission rates are
lower than the Scottish and ‘family group’ averages, but difficult decisions are
now required within the IJB, given the financial position. It is important that the
council continues to monitor the impact of its decisions on service performance
and wider outcomes for communities.

Page 16

6Controller of Audit report
Controller of Audit report
Introduction
1. This report is made by the Controller of Audit to the Commission
under Section 102(1) of the amended Local Government (Scotland) Act
1973. It is based on evidence collected in the 2022/23 and 2023/24
annual audits of the council, with the latter reported in October 2024.
Appendix 1 (page 17) includes links to the 2022/23 and 2023/24
Annual Audit Reports (AAR) and Appendix 2 (page 18) includes a link
to the Best Value Statutory Guidance.
2. The reporting of Best Value is undertaken through the annual audit
of each council and includes detailed work focusing on a Scotland-wide
theme. The Best Value theme for 2022/23 was councils’ leadership
of the development of new local strategic priorities while the 2023/24
theme focused on workforce innovation.
3. The Best Value theme for 2024/25 is Transformation and how councils
are redesigning and delivering more efficient services to achieve planned
outcomes. The work undertaken by the auditor at the council was not
complete in time to be covered here and will be reported on as part of
the 2024/25 annual audit.
Pace of continuous improvement
4. Renfrewshire Council remains committed to the principles of Best
Value and has made good progress on previous improvement actions
identified in Best Value reports.
5. The council has also put in place arrangements to address the issues
raised by the Controller of Audit, and the Accounts Commission in
response to Controller of Audit s102 reports, on council failings in relation
to Dargavel Primary School.
6. The recent follow-up audit in relation to community engagement
and culture change identified some scope for further improvement in
how the council reports options appraisal outcomes and business case
assessments.

Page 17

Controller of Audit report 7
Best Value Assurance Report (BVAR) follow-up
7. The council last received a BVAR in August 2017. The report made
seven recommendations for improvement in areas such as cross-
party working, community engagement, partnership working, financial
sustainability, workforce planning and governance arrangements. The
auditor has reported good progress against improvement actions, with all
recommendations now complete.
Leadership review
8. Leadership in the development of new local strategic priorities
was the subject of Best Value thematic work in 2022/23. The auditor
was satisfied that council arrangements in place to demonstrate Best
Value under each reported area of the 2022/23 thematic review were
appropriate.
9. In their recent follow-up report, the auditor reported they are satisfied
that the council has demonstrated evidence of a positive corporate
culture and continues to take a range of actions aimed at supporting
further development of openness and transparency. The auditor has also
noted an improved level of scrutiny at Audit, Risk and Scrutiny Board in
their 2024/25 interim report on culture and community engagement. 
10. The Council Plan 2022-27 was refreshed in June 2024 and includes
a vision of ‘Creating a fairer Renfrewshire built on innovation, wellbeing
and opportunity’. The council’s intention with the refreshed plan was
to sharpen its focus on key priority areas and update actions and
performance indicators to better facilitate measurement of progress.
The auditor will consider the refreshed plan as part of the 2024/25 audit.
11. The council introduced a Leadership Development Programme
developed by the Society of Local Authority Chief Executives (SOLACE)
based on their discussions with the key stakeholders within the council.
Three cohorts of the council’s leaders and managers have now been
through the programme. Additional deep-dive training took place during
2023/24 for all key officers at a variety of grades on governance.
12. Elected member training takes place on a regular basis throughout
the year with an annual development week also provided. Training needs
are kept under review to keep pace with the changing council context,
key areas of interest, and identified needs. A range of training formats are
used, and a suite of training materials is made available. Opportunities for
training and development through organisations such as the Improvement
Service are also shared and promoted.

Page 18

Controller of Audit report 8
13. In December 2024, the council launched a new self-assessment
approach focused on organisational culture. This Cultural Assurance
Model (CAM) was developed in partnership with the Improvement
Service and based on the Public Service Improvement Framework which
has been used in the council for over 15 years.
14. The model explores organisational culture across the four key themes
of Leadership; People (employees); Collaborating, learning and listening;
and Ethics and governance. The first phase of the CAM programme
included a targeted survey of the Chief Officers Team, the Our Leaders
Forum (third-tier managers) and the staff forums across the four council
services.
15. The overall findings from the targeted CAM survey show
respondents reflecting on a positive organisational culture at the council,
alongside some areas for improvement that the council is exploring
further. Just over a quarter of respondents identified that further
improvements could be made in relation to feeling able to raise concerns
about any aspect of work, and the transparency and accountability
around decision-making.
16. As part their recent audit work, auditors specifically met with council
members and officers to consider their relationships. Auditors found
that members and officers work well together in a constructive and
appropriately challenging culture which supports good overall decision-
making. However, their analysis of board papers indicates some scope
for the council to further develop how it presents options appraisal and
business case development in supporting effective council decision-
making and achieving transparency and openness in decision-making
processes.
Citizen and community engagement
17. Previous statutory reports have highlighted specific concerns
relating to engagement regarding Dargavel Primary School. The auditor
reports that good progress has been made with the development of
consultation and community engagement including a refresh of the
council’s overall approach, with appropriate arrangements established or
in place to support effective governance and scrutiny of those revised
arrangements.
18. Community empowerment, wealth and wellbeing are reflected in
the strategic priorities underpinning the Council Plan and the council
has worked collaboratively to deliver a place-based approach to digital
exclusion, with work being recognised in the joint Accounts Commission
and Auditor General report on Tackling digital exclusion in 2024.

Page 19

Controller of Audit report 9
19. A revised Consultation and Engagement Policy was approved by
the Leadership Board in February 2025, which replaces an existing
engagement strategy and toolkit. It provides best practice guidance for
council officers and services who plan and conduct public consultation
and engagement.
20. The introduction of a Consultation and Engagement Coordination
Group, chaired by the head of policy and partnerships, should help
strengthen the application of the new policy. This group will provide
strategic oversight, guidance and approval of the consultation and
engagement activity, and review operational progress against the policy
on an annual basis.
21. Updates on consultation and engagement will be provided to the
council’s Leadership Board as part of the six-monthly updates currently
provided on the Council Plan. Services will also provide an update on
consultation activities progressed through service improvement planning
processes and reports to relevant policy boards.
22. The auditor highlights a number of activities at the council which are
enabling and supporting community engagement including:
• A range of surveys have been undertaken with residents
throughout the year.
• A Connected Communities model has been developed which
will seek to strengthen the way in which the council works with
communities.
• Engagement on the Housing Led Regeneration and Renewal
Programme has been implemented.
• You Decide – a participatory budgeting programme has been in
place for three years.
• A ‘Celebrating Renfrewshire’ fund designed by, and for, young
people to have direct say on local area projects. This has been
operating for five years, with over 10,000 votes and 400 projects
delivered.
• The Community Asset Transfer Policy and Sustainable
Communities Fund enables direct community engagement across
a range of council investment decisions.
23. The auditor will monitor the council’s progress with community
engagement as part of their 2024/25 audit.

Page 20

Controller of Audit report 10
Effectiveness of performance reporting
24. The auditor has found performance management arrangements at
the council to be robust and generally good. Systems for monitoring and
reporting overall performance are good, and the council is developing
arrangements to better evidence the relationship between strategic
objectives, budget decision-making and performance outcomes in future
performance reports.
25. The council’s Performance Framework for the Council Plan
was approved in December 2022 and refreshed in June 2024. The
Framework contains 37 high-level actions to be achieved in the next
five years, with 34 performance indicators to measure progress.
26. Performance is monitored through quarterly performance
reporting to the Corporate Management Team. The chief executive
also holds performance scrutiny meetings with each directorate team
twice a year, and the council plans to introduce a new performance
board in April 2025 to help drive further improvements to service
level performance. Performance is reported to elected members
through Service Improvement Plans and Council Plan performance
reports (six-monthly) and ad hoc operational performance updates for
service areas.
27. Local Government Benchmarking Framework (LGBF) data is also
reported to the Audit Risk and Scrutiny Board and made available to the
public through the council’s Public Performance Reporting website page
which includes presentations, dashboards and narrative.
Reported performance
28. The council reported progress against the Council Plan and its five
strategic outcomes (Place, Economy, Fair, Green, and Living our values) in
December 2024. The progress report covered the 37 high-level actions,
and 34 performance and data indicators outlined in the Council Plan.
29. Of the council’s chosen indicators, 20 have targets, with the
remainder providing additional contextual information. Of the 20 indicators
with targets, nine are meeting or exceeding the target, four are narrowly
missing the target, and seven are behind target.
30. A review of all LGBF indicators shows that 67 of the 107
(63 per cent) available indicators have improved since the base year,
three (three per cent) have stayed the same and 37 (35 per cent)
have declined.
31. Of the 107 LGBF indicators, 76 are classed as performance
indicators, 20 relate to costs and 11 to satisfaction. Seventy-four per cent
of performance indicators, 50 per cent of cost indicators, and one
satisfaction indicator have improved since the base year.

Page 21

Controller of Audit report 11
32. The council has 57 per cent of its LGBF performance indicators in
the top two quartiles of council performance, having fallen slightly from
63 per cent in the base year.
33. The council reported on 19 education performance indicators for
2023/24 in a report to the Education and Children’s Service’s Policy Board
in May 2024. One performance indicator has been on target, seven were
below target and 11 were within ten per cent of the target, but still below
it. When considering the long-term trends of those indicators, 13 report a
downward trend, four an upward trend, with the remaining two either not
comparable or without any change.
34. LGBF education performance measures show that the council
remains in the top ten councils for 14 out of 18 indicators, with the four
remaining indicators better than or close to the national average. The
council had the fifth lowest cost per secondary school pupil in Scotland
in 2023/24.
Workforce planning
35. The auditor concluded that the council has appropriate workforce
planning strategies and other policies in place, with a flexible approach
to new ways of working and an awareness of the need for further
improvement in this area.
36. The council’s People Strategy 2021-26 was updated in 2023 to align
its themes with the new Council Plan strategic priorities. The focus of the
updated strategy being:
• improve employee experience to evolve the council’s culture
• workforce planning to support service redesigns
• Equality, diversity, and inclusion.
37. At the beginning of 2024, the council established a Corporate
Workforce Planning Group, consisting of heads of services to drive and
monitor the Council’s People Strategy priorities and outcomes.
38. The People and Development function is currently being reviewed
to ensure it is able to deliver on the potential requirements of the
new People Strategy under development. A stronger link to financial
management is planned for the new strategy.
39. Responsibility for management of the workforce is delegated to
individual services. Workforce risk assessment, operational priorities
and implementation, and monitoring are undertaken though service
improvement plans.

Page 22

Controller of Audit report 12
40. The auditor has identified some scope for improvement in how the
council tracks progress against both its strategy and individual service
plans. Clarity over the status of individual strategy objectives could
be improved, with wider use of measurable performance indicators.
Reporting in service improvement plans provides limited information on
progress against People Strategy objectives.
41. The council has developed a suite of people metrics to inform
workforce update reports to elected members and to support
standardised annual reporting of progress against the People Strategy.
A report on council workforce demographics and people metrics was
taken to the Finance, Resources and Customer Service Policy Board in
February 2025.
42. The council offers a blended working approach which allows eligible
employees to work from a combination of home and office work, in line
with the requirements of their specific service and role. There is also a
flexi-time scheme for staff allowing start and finish times to be varied out
with core working hours.
43. A staff survey was carried out in June 2021 to capture how staff
were feeling and coping, coming out of Covid restrictions, and a new
staff engagement survey was undertaken in September 2024. Around
2,000 (or 23 per cent) of the council’s total staff (of around 8,500)
responded to the latest survey. The lower than targeted response rate
may be attributable in part to separate surveys issued by the Care
Inspectorate to staff working in children’s and adult social work services,
as part of an independent inspection process. The Care Inspectorate
survey confirmed an overall positive view from the workforce in these
areas.
44. The results of the latest staff survey were largely positive, with
some areas for improvement identified. Each council service has
developed their own bespoke action plan to address agreed key areas for
improvement. Newly established employee engagement forums in each
service will support their senior management teams to progress these
actions and drive improvements.
45. Appropriate arrangements are in place to enable the delivery of
the council’s digital strategy and as noted at paragraph 18, the council
has been recognised for its collaborative approach to digital exclusion.
A number of automatic processes to drive efficiency and innovation have
been implemented and a variety of digital training is offered to staff. The
council recognises that a further assessment of digital skills is needed,
and the creation of capacity to enable the review, exploration and
development of digital opportunities remains a challenge. 
46. The council works collaboratively with neighbouring councils, the
Scottish Government, and local partners. And continues to explore
opportunities for further collaboration. This includes leading the delivery

Page 23

Controller of Audit report 13
of major infrastructure projects through the Glasgow City Region City
Deal, fulfilling the lead authority role for Scotland Excel and joint venture
arrangements with private sector organisations.
47. The council can cite a number of ongoing collaboration arrangements
including one with Inverclyde Council, East Renfrewshire Council, and
West Dunbartonshire Council to deliver a civil contingencies service,
which supports business continuity and emergency planning across
the four council areas.
Financial management and sustainability
48. The auditor has concluded that the council has appropriate financial
monitoring arrangements in place with no significant weaknesses in
financial controls identified.
49. The Accounts Commission has previously encouraged the council to
ensure it is reporting transparently on the financial impact of decisions
linked to school provision in Dargavel. The council have confirmed that
the capital projects for both the Park Mains High School extension and
the new Dargavel Primary School are reported to the Education and
Children’s Services Policy Board. The council has also indicated that the
revenue costs will be captured as part of their standard arrangements for
annual budget-setting, monitoring and medium- to longer-term financial
planning. The auditor will continue to keep this work under review.
50. In 2022/23, the council reported the use of £4.9 million of general
fund reserves to support services, with a further £9.8 million utilised in
2023/24. The council reported overspends against revised base budgets,
prior to the planned use of earmarked reserves, of £6.1 million and
£2.6 million for 2022/23 and 2023/24 respectively. Overspends were
driven by inflationary pressures and increased costs in various service
areas including children’s, environment, housing, and infrastructure
services.
51. Total useable reserves increased by £21.6 million in 2022/23,
following the use of financial flexibilities in relation to service concession
arrangements, and fell in 2023/24 by £13.9 million to £222.2 million.
When reserves are expressed as a proportion of annual budget, the
council has a relatively high level of usable reserves, ranked behind just
three other councils (including Orkney and Shetland councils) at the end
of 2023/24 (LGBF indicators).
52. A large part of the council’s reserve balance, £86 million at the
end of 2023/24, is held in a capital fund which is earmarked to support
investment in assets. The council has approved using £45 million of this
balance to finance a new Dargavel Primary School.

Page 24

Controller of Audit report 14
53. Of the £117.6 million general fund balance at 31 March 2024,
£107.3 million was committed or earmarked for specific purposes and
£10.3 million remained uncommitted. The council maintains a policy
minimum of £10 million of uncommitted reserves (just over two per cent
of net expenditure) held for emergency purposes. Key financial
information is included in Exhibit 1.
Exhibit 1. 
Renfrewshire Council – key financial information
2022/23
(£m)
2023/24
(£m)
2024/25
(£m)
2025/26
(£m)
Budget-setting
Budget gap 9 16.4 16.1 8.9
Additional investment 5.6 1.8 2 9.2
14.6 18.1 18.1 18.1
Planned to be met via:
• Savings and flexibilities 10 9.6 8.9 7
• Use of reserves 1.7 2.4 4.3 0.4
• Additional council tax/funding 2.9
(3%)
6.1
(6%)
4.9 10.6
(9.5%)
Actual
Proportion of savings delivered n/a1
Reserves (after earmarking adjustments)   
Forecast
Use of/(contribution to) total reserves (21.6) 13.9 1.8
Total usable reserves carried forward  236.1 222.2 220.4
General fund 127.4 117.6 120.5
Earmarked 117.1 107.3 110.2
Uncommitted 10.3 10.3 10.3
1. Savings non-delivery is reported by exception for areas of service overspend only.
Source: Council accounts, committee papers and council provided figures

Page 25

Controller of Audit report 15
54. Included in the £107.3 million earmarked general fund balance at
the end of 2023/24 were amounts of £48.8 million for loan charge
flexibility, £13.2 million for financial sustainability, £10.7 million for service
modernisation and reform, and £10.6 million in an employability fund.
55. When the council set the budget for 2024/25, the planned use of
general fund reserves to close the budget gap was £2.3 million. The
council is currently projecting that the actual use of reserves will be lower
at £0.5 million (January position reported April 2025). However, there is
a £3.7 million overspend forecast for health and social care which will
fall on Integration Joint Board (IJB) reserves. Council finances could be
impacted by future health and social care overspends once IJB reserves
are exhausted.
56. Before the 2025/26 budget was set, the council forecast a budget
gap of between £25 million and £40 million for the three years 2025/26,
2026/27 and 2027/28 (inclusive of additional costs associated with the
new Dargavel Primary School). The council tax increase approved for
2025/26 was 9.5 per cent which resulted in a balanced budget for that
year. The council now estimates a cumulative budget gap of £33 million
by 2027/28, this is prior to any council tax increases.
57. The proportion of the council’s in-year planned savings that have
been delivered does not form part of the council’s routine reporting.
Non-delivery of savings is reported on an exceptions basis where service
overspends are identified. The council has reported that £190 million of
savings have been delivered since 2011.
58. In January 2025, the council outlined the next major phase
(Phase 5) of its long-term transformation programme – Reshaping
Renfrewshire – (covering the period up to 2028). The scale of savings to
be delivered from the programme will be updated in the medium-term
financial plan in September 2025. Difficult decisions on spending priorities
may be necessary.
Delivery of the capital programme
59. The auditor reported, in their 2023/24 report, that the council has
an ambitious £730 million capital programme in place over the next five
years, for both housing and non-housing programmes.
60. The council’s ability to fully deliver its capital programme within the
originally planned timescales has been impacted by a number of factors,
including the complexity of the works, the cost of materials, supply chain
issues and availability of contractors.
61. In 2022/23, capital projects with a value of around £42 million
(25 per cent of the capital programme) had to be re-profiled. In 2023/24
just 6.5 per cent of the programme was reprofiled into later years. Given
the scale of the council’s ongoing capital programme, delivery to plan is
likely to remain a challenge.

Page 26

Controller of Audit report 16
62. The council’s capital financing requirement increased by £81 million
in 2022/23 and by £68 million in 2023/24 with a closing balance of
£510 million at the end of 2023/34. £29.2 million of this increase is
attributable to the use of financial flexibilities.
63. The council’s ratio for debt financing cost to net revenue stream is
below average for the general fund at 3.1 per cent (against a national
average of 5.8 per cent). The ratio for the HRA is higher at 27.7 per cent
(against a national average of 20 per cent).

Page 27

17Appendix 1
Appendix 1
Audit reports
Annual Audit Reports 2022/23 and 2023/24 
Each Annual Audit Report comprises:
• significant matters arising from the audit of the council’s Annual
Accounts
• conclusions on the council’s performance in meeting its Best Value
duties
• conclusions on the wider scope areas that frame public audit as set
out in the Code of Audit Practice 2021: 
– Financial management, financial sustainability, vision leadership
and governance, use of resources to improve outcomes.
2022/23 Annual Audit
Report
Renfrewshire Council
November 2023
2023/24 Annual Audit
Report
Renfrewshire Council
October 2024
Interim follow-up audit report on the
council’s approach to community
engagement and culture change 2024/25 
The auditor’s interim report includes their
findings on the follow-up of issues identified in
previous controller of audit reports on Dargavel
Primary School.
2024/25 Interim
Report
Renfrewshire Council
April 2025

Page 28

18Appendix 2
Appendix 2
Best Value Statutory Guidance
The Local Government in Scotland Act 2003 introduced a statutory
framework for Best Value for local authorities. The Best Value duties set
out in the Act are:
• to make arrangements to secure continuous improvement in
performance (while maintaining an appropriate balance between
quality and cost); and, in making those arrangements and securing
that balance, to have regard to economy, efficiency, effectiveness,
the equal opportunities requirement and to contribute to the
achievement of sustainable development
• to achieve break-even trading accounts, subject to mandatory
disclosure
• to observe proper accounting practices
• to make arrangements for the reporting to the public of the
outcome of the performance of functions.