1 
___________________________________________________________________
To: Council
On: 24 October 2024
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Audited Annual Accounts 2023/24 - Renfrewshire Council Group
___________________________________________________________________
1. Summary
1.1 The 2023/24 unaudited Annual Accounts were approved by Council on 27
June 2024. Each year the Council’s appointed external auditors carry out
an audit of the Council’s financial statements and provide an opinion as to
whether those statements provide a true and fair view of the financial
position of the Council, and its income and expenditure for the year; and
also whether they have been prepared in accordance with the relevant
regulations. 
1.2 The audited Annual Accounts 2023/24 for Renfrewshire Council and its
Group are now presented to the Council for approval. 
1.3 There was one material adjustment made to the annual accounts over the
course of the audit, which amended the value of the Council’s pension
asset disclosed in the 2022/23 Balance Sheet, owing to the exclusion of
unfunded liabilities. Further detail is included in Azets’ Annual Audit report,
presented at agenda item 1. Other minor and presentational changes were
also agreed.
___________________________________________________________________
2. Recommendations
2.1 The Council is asked to approve the attached audited Annual Accounts
2023/24 for signature in accordance with the Local Authority Accounts
(Scotland) Regulations 2014. 
___________________________________________________________________

Page 2

2 
Implications of the Report
1. Financial – The 2023/24 Annual Accounts demonstrate that the Council
continues to operate services within the resources available, and in line with
the relevant legislation.
2. HR & Organisational Development – none directly arising from this report.
3. Community/Council Planning – none directly arising from this report.
4. Legal – An audit opinion free from qualification demonstrates the Council’s
compliance with the statutory accounting requirements set out in the Local
Government (Scotland) Act 1973 and the Local Government in Scotland Act
2003.
5. Property/Assets – none directly arising from this report.
6. Information Technology – none directly arising from this report.
7. Equality & Human Rights – none directly arising from this report. 
8. Health & Safety – none directly arising from this report.
9. Procurement – none directly arising from this report.
10. Risk – none directly arising from this report.
11. Privacy Impact – none directly arising from this report.
12. Cosla Policy Position – none directly arising from this report.
13. Children’s Rights – none directly arising from this report.
14. Climate Risk – none directly arising from this report.
___________________________________________________________________ 
Author:           Christine McCourt, Head of Finance and Procurement

Page 3

Renfrewshire Council
Audited Accounts
2023–2024

Page 4

Contents
Management Commentary ................................................. 2
Statement of Responsibilities ............................................ 16
Annual Governance Statement ......................................... 17
Remuneration Report ........................................................ 25
Independent auditor’s report ............................................ 34
Comprehensive Income and Expenditure Statement ....... 38
Movement in Reserves Statement .................................... 39
Balance Sheet .................................................................... 40
Cashflow Statement .......................................................... 41
Note 1: Expenditure and Funding Analysis ........................ 42
Note 2: Financing and investment income & expenditure 44
Note 3: Taxation and non-specific grant income .............. 44
Note 4: Expenditure and income analysed by nature ....... 44
Note 5: Grant income ........................................................ 45
Note 6: Adjustment between accounting basis and funding
basis under regulations ..................................................... 46
Note 7: Usable reserves ..................................................... 47
Note 9: Property, Plant and Equipment ............................ 54
Note 10: Heritage Assets ................................................... 57
Note 11: Investment properties ........................................ 57
Note 12: Assets held for sale ............................................. 58
Note 13: Intangible assets ................................................. 58
Note 14: Capital expenditure and capital financing .......... 59
Note 15: Service Concession Arrangements ..................... 60
Note 16: Leases ................................................................. 62
Note 17: Inventories .......................................................... 63
Note 18: Cash and cash equivalents .................................. 63
Note 19: Debtors ............................................................... 63
Note 20: Creditors ............................................................. 64
Note 21: Provisions ............................................................ 64
Note 22: Financial Instruments ......................................... 65
Note 23: Nature and extent of risks arising from Financial
Instruments ....................................................................... 69
Note 24: External audit costs............................................. 72
Note 25: Agency services ................................................... 72
Note 26: Related parties .................................................... 73
Note 27: Pension schemes accounted for as defined
contribution schemes ........................................................ 75
Note 28: Defined benefit pension schemes ...................... 76
Note 29: Contingent liabilities ........................................... 81
Note 30: Events after the balance sheet date ................... 81
Note 31: Accounting Standards Issued not Adopted ........ 81
Note 32: Accounting Policies – Renfrewshire Council ....... 82
Note 33: Judgements in Applying Accounting Policies ...... 94
Note 34: Assumptions made about the future .................. 95
Common Good Funds ........................................................ 96
Housing Revenue Account ................................................. 98
Council Tax Income Account ............................................ 100
Non-Domestic Rates Income Account ............................. 101
Group Accounts ............................................................... 103
Notes to the Group Accounts .......................................... 106
Group Accounting Policies ............................................... 118

Page 5

2 
Annual Accounts 2023/24
Management Commentary 
The purpose of the Management Commentary is to
present an overview of Renfrewshire Council’s
performance during the 2023/24 financial year and to
help readers understand its financial position at 31
March 2024. In addition, it outlines the main issues and
risks that may impact the performance of the Council in
the future. 
Renfrewshire Council, one of 32 local authorities in
Scotland, was established by the Local Government
(Scotland) Act 1994 and came into being on 1 April
1996. It provides services to over 184,000 residents in
the entire Renfrewshire area, which has a mixed
geography, with many villages complementing its three
main towns of Johnstone, Paisley and Renfrew. 
The Council is part of a wider Group, with partnerships
spanning a number of organisations to varying degrees. 
The Council also works closely with the Renfrewshire
Health and Social Care Partnership, which delivers care
services across the region; and with OneRen, which
delivers leisure and cultural services. During 2023/24,
Renfrewshire Council was organised into four
directorate services, as follows: 
The kind of services that the Council provides includes: 
0-15       - 16%
16-64     - 64% 
65+        - 20%
Women - 51.7%
Population - 184,340
Men       - 48.3%

Page 6

3 
Annual Accounts 2023/24
Our Aims and Objectives 
The aims of the Council Plan 2022-2027 were revised
during 2022 with a refreshed Community Plan and a
new Council Plan. The Community Plan is Renfrewshire’s
Local Outcomes Improvement Plan, and the Council
works with local partners to achieve a Renfrewshire that
is Thriving, Well, Fair and Safe. 
The new Council Plan presents the Council’s vision for
the next 5 years as:
It outlines five strategic outcomes, which the Council
will work with partners, communities, and businesses to
deliver, and one cross-cutting theme that will underpin
the delivery of the outcomes. These are:
• Place: Working together to enhance
wellbeing across communities
• Economy: Building an inclusive, green, and
resilient economy
• Fair: Nurturing bright, happy, and healthy
futures for all
• Green: Leading Renfrewshire to Net Zero
• Living Our Values: Making a difference
together
• Improving outcomes for Children and
Families: Cross-cutting 
Each Council service prepares a Service Improvement
Plan, themed around the Council Plan’s strategic
outcomes, demonstrating how the services will
contribute to the delivery of the Council Plan. 
Financial Strategy 
The financial strategy and service plans of the Council
support the delivery of the Council’s priorities outlined
in the Council Plan. In order to achieve this, the financial
strategy must ensure that resources are effectively and
efficiently used in line with overall objectives; and
ensure that resources are managed sustainably and in a
way that continues to ensure the stability of service
delivery. 
The medium-term Financial Outlook was reported to the
Council on 14 December 2023, with a further update on
29 February 2024. These reports highlight the
increasingly challenging financial and economic
environment the Council is facing, predominantly linked
to high levels of inflation, coupled with low income
growth. 
The Council’s medium-term financial outlook continues
to be based on an assumed flat-cash revenue settlement
over the short term; however, it is cost pressures that
are increasing significantly and the principal driver for
the extremely challenging financial outlook. 
Incorporating an affordable level of pay increase over
the period 2024/25 to 2027/28, and an assumed lower
level of inflation on supplies and services costs, suggests
that the Council is facing a £45-50m funding gap over
this period, before any decisions on Council Tax. This
could reduce to c£30m if Council Tax was to increase by
19.5% over the four year period. 
The Council chose to freeze Council Tax in 2024/25
following the Scottish Government announcement of
compensatory funding, which equated to a 4.4%
increase. The Council is now targeting cost reductions
and savings averaging at least £8m each year; however,
this still leaves an £8m recurring financial gap at the end
of 2027/28. For this reason, financial sustainability and
stability risks remain high on the Council’s priorities
going into 2024/25. 
Information on the year-end financial position of the
Council at 31 March 2024 is detailed later in the
Financial Performance section.

Page 7

4 
Annual Accounts 2023/24
Review of the Year 
The Council publishes updates on progress delivering
the Council Plan every six months, and the most recent
report will be reported to the Leadership Board on 19
June 2024.  The December report can be found here.
The Council also publishes an annual Public Performance
Report, which gives residents an overview of how the
Council performs in relation to its key priorities, and
how we perform in terms of the 108 indicators included
in the Local Government Benchmarking Framework
(LGBF).   
Scottish local authorities continue to operate in a very
challenging financial environment, and this has been
highlighted by the Improvement Service in its annual
LGBF overview report.  This report notes that it is
becoming increasing difficult for local authorities to
maintain good levels of performance.  A detailed report
on Renfrewshire’s performance in 2022/23 was
presented to Council’s Audit, Risk and Scrutiny Board on
20 May 2024 and is available here. 
Key Achievements 2023/24
Place
• We delivered two key buildings within our
ambitious Cultural Infrastructure Investment
programme.  The refurbished Paisley Town Hall
reopened in October 2023 and the new Paisley
Learning and Cultural Hub opened in November
2023.  
• We secured £2m from Transport Scotland’s Active
Travel Transformation Fund, and £540,000 will be
used to improve active travel infrastructure
around Inchinnan Business Park.
• We delivered another year of successful events,
including gala days, the hosting of the Royal
National Mod and Paisley’s Halloween festival. 
Economy
• Our employability services worked with over
1,500 people in 2023/24.  Over 600 people gained
new qualifications and 528 were supported into
paid employment.
• Our Procurement and Economic Development
teams are developing our approach to Community
Wealth Building, which focuses on inclusive
growth.  The teams have already taken part in a
Scottish Government pilot and will finalise our
future plans once legislation is published.
• We have Developing the Young Workforce
Coordinators in all of our secondary schools, as
part of our partnership with Invest in
Renfrewshire, Skills Development Scotland and
West College Scotland. 
Fair:  
• We launched a Tenant Support Fund in October
2023 to provide support with rent payments for
those who meet the criteria, and in the first six
months of operation we have supported 161
tenants.
• We supported 520 families who were not
accessing all the benefits they were entitled to,
with our advice services helping them raise their
collective income by £109,000.
• We won a COSLA Excellence Award for our
interactive Alcohol and Substance Education
Awareness programme, which is being
implemented across our schools. 
Green:  
• Our District Heating Network (DHN) at Inchinnan
is the first of its kind in Scotland, and provides an
energy solution that produces 90% less carbon
than conventional heating.  
• Our new build housing Zero Carbon Innovation
Project, a partnership with John Gilbert Architects
and the University of Strathclyde was shortlisted
for a national award for its theoretically net zero
build specification.
• Our Team Up to Clean Up initiative now has over
5,000 Facebook members 
Living Our Values:
• We launched a new Customer Strategy which sets
out our plans to make the most of technology to

Page 8

5 
Annual Accounts 2023/24
help improve our engagement with our
customers.
• Our People and Organisational Development
team produced an updated suite of HR policies
with a clear focus on staff wellbeing, including a
refreshed Carer’s Policy, new Equality, Diversity
and Inclusion Plan, and a new Health and
Wellbeing Plan.  
• We undertook a corporate self-assessment
exercise and refreshed our performance
management approach. 
Improving Outcomes for Children and
Young People:
• As part of Renfrewshire Council’s commitment to
The Promise, we have recruited 266 Promise
Keepers from across our staff, acting as local
champions and helping improve services for care
experienced people.
• Our Promise Arts and Cultural Engagement
programme delivered opportunities for care-
experienced young people to participate in a
range of activities, from co-designing installations
at two of Paisley’s biggest public events, creating
a mural, taking part in arts sessions and
contributing to Youth Service’s LOVE2CARE week. 
Performance Indicators 
Our Council Plan is one way in which we report to
elected members and Renfrewshire residents on our
performance. The Council Plan reports on 39 indicators,
of which 22 have a target. 
In 2023/24, six of our indicators met or exceeded their
target, five narrowly missed the target and four were
behind target. There are seven indicators for which
2023/24 data is not yet available. 
Our areas of strong performance include: 
• Helping our citizens back into work, with 268
people supported by our employability service
this year sustained in work for at least six months;
• Tackling homelessness, with the timescales for
completion of cases still well within target despite
increasing demands; 
• Keeping our looked after children in family
settings wherever possible, with 90.9% looked
after in the community;
• Contributing to our goal of net zero by 2030 by
having 30% of our vehicle fleet running on
alternative fuel sources;
• Making our public spaces a nice place to be, with
93.3% of streets assessed as clean when
independently checked;
• Promoting Renfrewshire as a great place to live,
work and visit with extensive media reach for
council activity and local events. 
We narrowly missed our annual targets in the following
areas: 
• Responding to frontline complaints within the
required timescale;
• Responding to Freedom of Information requests
within the required timescale;
• Supporting new businesses through to launch;
• Reducing the level of CO2 emissions from our
vehicle fleet;
• Upgrading our housing stock to meet the latest
energy efficiency requirements. 
Areas for Improvement and Development 
Detailed consideration of performance is a core part of
our Service Improvement Plan and Council Plan
reporting, which note areas for continued improvement
and development as well as successes.  As well as the
achievements noted above, services have identified
areas where progress has been delayed or where
further work is required. These are: 
• Encouraging uptake of free school meals within
primary schools;
• Encouraging uptake of free school meals in
secondary schools;

Page 9

6 
Annual Accounts 2023/24
• The percentage of Council housing stock which
meets the Scottish Housing Quality Standard;
• The average days lost to sickness absence per
employee. 
We do not yet have data for the number of affordable
housing completions, the number of private housing
completions, the percentage of household waste
recycled, or the percentage of procurement spend with
local businesses. Data in relation to educational
attainment and accredited awards are based on
academic years (August to July) so 2023/24 figures are
not yet available. 
Findings from the independent review into capacity
issues at Dargavel Primary school were reported to the
Council at its meeting on 22 June 2023. The report can
be found on the Council’s website at the following link:
Dargavel Primary – Independent External Review 
There were eight recommendations arising from the
independent review, and the Council’s Chief Executive
reported a response to the findings at the same
meeting, with actions related to each of these
recommendations set out in detail. This report can be
found on the Council’s website at the following link:
Dargavel Primary School Independent Review –
Response to Recommendations. 
During 2023/24 there have been regular updates to the
Audit, Risk and Scrutiny Board on progress against these
actions. 
At its meeting on 28 September 2023, the Council
approved a capital budget of £45m to build a second
primary school in the Dargavel area, and a further £30m
to extend the associated secondary provision at Park
Mains High School. 
General performance information can be found on the
Council’s website at the following path: Your
Council>Information, performance and
statistics>Council Performance.
LGBF data can be found at: Your Council>Information,
performance and statistics>Council
Performance>Benchmarking.
Service Update Reports, Service Delivery Plans and
Operational Performance Reports are reported to the
relevant Policy Board and can be found on the Council
Committee Management Information System at:
https://renfrewshire.cmis.uk.com/renfrewshire/Council
andBoards.aspx 
Working Towards Net Zero by 2030 
Renfrewshire Council’s Public Bodies Climate Change
Duties reported a 17.2% emissions reduction compared
with the previous year, and overall annual emissions
reduction of 63.6% against the 2012/13 baseline. 
Activity in 2023/24 includes delivering change across
Council operations, and large-scale projects with local
benefits aligned to the five themes of Renfrewshire’s
Plan for Net Zero, which are Clean Energy, Sustainable
Transport, Circular Economy, Connected Communities
and Resilient Place. Further detail of activity within each
theme is set out in the following sections.  
Clean Energy:
• AMIDS District Heating Network (operational May
2023) provides low carbon heating, cooling and hot
water to businesses at Paisley’s Advanced
Manufacturing Innovation District site, with an
estimated 95% emissions reduction over its 40-year
lifetime, compared to gas boilers.
• Approval of Renfrewshire’s Local Heat and Energy
Efficiency Strategy: a data-driven, area-based
approach to fuel poverty, energy efficiency and the
decarbonisation of heat. The Strategy was approved
by the Infrastructure, Land and Environment Board
on 24th January 2024, and the Delivery Plan is
currently in development. 
Sustainable Transport:
• Successful trials of hydrotreated vegetable oil (HVO)
as alternative fuel for bin lorries and large fleet -
reducing CO2 emissions by up to 90% and
contributing to improved air quality.

Page 10

7 
Annual Accounts 2023/24
• Infrastructure Investment: active travel networks to
link key destinations, e.g. the 5km Paisley to
Renfrew route, connecting the towns by a direct
link; and electric vehicle charging infrastructure –
with 148 public EV chargers and 102 fleet charging
bays to reduce reliance on fossil fuels.
Circular Economy:
• Maximising recycling opportunities across 56
Renfrewshire schools and nurseries, resulting in
reducing residual waste by 59,000 litres per week
and increasing recycling by 93,000 litres per week in
2023/24. 
• A Reuse Hub for working small waste electricals
launched at Paisley Recycling Centre. Items are
collected and sold by the Salvation Army, with
profits reinvested in local community initiatives.
Connected Communities:
• Sustainable Communities Fund Launch: to build
community capacity, identify opportunities within
local areas and develop local projects to benefit
those who live there – connecting people through
regenerated local spaces and tackling inequality
through community collaboration.
• Climate Engagement: Community Climate
Conversations - Key Stakeholder event with
attendees from 57 local, regional and national
bodies; and internal workshop with 70 officers from
across the Council to optimise climate opportunities,
priorities, partnership working and collaboration.
Resilient Place:
• Offsetting: a specialist feasibility evaluation
identified 216 hectares at West Tandlemuir for
peatland restoration, sequestering 556 tonnes of
carbon. Consents for the work are now being
secured.
• Tree Planting: delivery of initial phases of the Clyde
Climate Forest, planting c3,000 trees to bring
climate and ecological benefits to Renfrewshire and
the wider Glasgow City Region. 
Work continues on developing costed delivery plans to
identify project opportunities for carbon reduction, cost
savings and revenue generation, alongside wider
community benefits; and finalising a proposed Carbon
Budget for Renfrewshire Council. 
Development of an Adaptation Plan for Renfrewshire,
including an Offsetting Strategy will commence in the
coming year. 
Gender Pay Gap
The gender pay gap is the difference between the average hourly rates of pay of men and women expressed as a
percentage, where a positive figure indicates that women are paid less than men. The gender pay gap is different from
equal pay, which is a direct comparison of two people or groups carrying out the same or an equivalent role. At 31 March
2024, the mean gender pay gap for Renfrewshire Council was 0.44% (0.48% at 31 March 2023).

Page 11

8 
Annual Accounts 2023/24
Key Financial Ratios 
The following tables provide information regarding the financial performance of the Council in 2023/24 and the
affordability of its ongoing commitments: 
2022/23
Estimate Actual Actual
Reserves
Uncommitted General Fund
reserves as a % of budgeted
net expenditure
2.1% 2.0% 2.1% Reflects the level of funding available to meet
unplanned expenditure and manage financial
risk
Movement in uncommitted
General Fund balance
n/a -0.4% -4.4% Reflects Council spending decisions during
the financial year
Council Tax
In-year collection rate 95.5% 94.3% 95.5% Reflects the Council’s effectiveness in
collecting Council Tax debt
Council Tax income as a
proportion of total taxation
and non-specific grant income
19.7% 19.8% 17.6% Reflects the Council’s ability to vary
expenditure by raising Council Tax, the
principal local authority controlled source of
finance
Debt/Long term borrowing
Capital Financing
Requirement (CFR)
£552.0m £510.1m £442.1m
External debt £382.9m £386.1m £374.9m
Ratio of financing costs to net
revenue stream (General
Fund)
3.6% 3.1% 3.0%
Financial Indicator 2023/24 Commentary
The information is this section demonstrates
that the level of external debt (driven by the
capital programme) is affordable, owing to
the low proportion of our budget spent on
servicing debt. Further information, including
descriptions of these terms and their
significance, is available in the Treasury
Management Annual Report, presented to
the June Council meeting each year.
Financial Performance 
Primary Financial Statements 
The annual accounts summarise the Council’s
transactions for the year, its financial position at 31
March 2024, and its cashflows. The annual accounts are
prepared in accordance with the International
Accounting Standards Board Framework for the
Preparation and Presentation of Financial Statements as
interpreted by the Code of Practice on Local Authority
Accounting in the United Kingdom (“the Code”). 
The Primary Financial Statements include the
Comprehensive Income and Expenditure Statement
(CIES), Movement in Reserves Statement (MIRS),
Balance Sheet and Cashflow Statement. These
statements are accompanied by notes to the accounts,
which provide more details on the figures shown in the
statements and set out the accounting policies adopted
by the Council. There are also separate statements for
Council Tax, Non-Domestic Rates, the Housing Revenue
Account and the Common Good Funds. 
The Comprehensive Income and Expenditure Statement
(CIES) presents the total cost of providing Council
services in 2023/24 along with the income available to
fund those services. 
The outturn explained in the following section differs
from the accounting deficit shown in the CIES due to
accounting adjustments required to comply with proper
accounting practice, but which under statute should not
impact on local taxpayers. A reconciliation of these

Page 12

9 
Annual Accounts 2023/24
figures can be found in the Note 1: Expenditure and
Funding Analysis. 
General Fund 
The General Fund is funded by government grant and
Council Tax revenues and the Council is also able to
apply usable reserves from the General Fund Balance to
fund expenditure. 
As mentioned previously, the Council’s medium-term
Financial Outlook highlights the increasingly challenging
financial and economic environment the Council is
facing, predominantly linked to high levels of inflation. 
In setting its 2023/24 General Services revenue budget,
the Council anticipated a deficit position in-year of
£7.5m, arising from increases in the cost of pay, food,
fuel, energy, construction and other contracts, details of
which have featured in regular budget monitoring
reports throughout the financial year. This has
culminated in a year-end overspend against budget of
£2.6m. Specific pressures that contributed to this
position were as follows: 
• Children’s residential care: the number and cost
of complex care packages has increased
significantly;
• The refuse collection service was impacted by
high fuel costs as well as overtime arising from
carried forward holiday entitlement; and
• Car-parking income under-recovered by £1m,
having not recovered since the pandemic despite
charging being re-introduced in 2021. 
These pressures were offset by underspends within the
Miscellaneous Service in the following areas: a £1.2m
VAT recovery received, relating to a historic claim which
has now been settled by HMRC; Non-Domestic Rates
payments across the Council’s estate (£0.9m); devolved
Empty Property Relief (£0.7m); and Council Tax
Reduction (£0.8m). 
The Council’s largest category of spend is staffing, so
naturally any pay settlement linked to high levels of
inflation will create a further cost pressure. In 2023/24 a
national pay settlement of 6.05% was agreed for local
government workers. In recognition of the exceptional
inflationary environment, the Scottish Government
provided councils with additional funding in support of
the 2023/24 pay settlements. For Renfrewshire, this
amounted to £7.7m. 
Adult Services experienced a year-end overspend of
£0.8m which decreased the reserves of the
Renfrewshire Health and Social Care Partnership, who
operates these services. 
The Council fell just short of its target in-year Council
Tax collection rate of 95.9% in 2023/24, instead
returning a creditable 94.3% in light of the prevailing
cost of living crisis on household finances. Income from
Council Tax actually over-recovered by £0.4m compared
to budget, owing mainly to more prior year arrears
being collected than had been anticipated. 
As planned and reported through the year, £4.4m was
drawn from the Financial Sustainability Fund at year-end
to cover overspends in Children’s residential care (£3m),
car-parking income loss (£1m) and Proactive Tree
Management (£0.5m). 
After adjusting for this, as well as the Adult Services
overspend and the over-recovery in Council Tax
revenues, the final position for the Council’s General
Fund balance at 31 March 2024 was an overspend of
£2.6m

Page 13

10 
Annual Accounts 2023/24
Revised Budget Actual Variance
£m £m £m
Chief Executive's Service 28.872 28.749 0.123
Children's Services 251.415 252.456 (1.041)
Environment, Housing and Infrastructure 68.929 74.227 (5.298)
Finance and Resources 48.691 48.972 (0.281)
Miscellaneous Services 17.809 14.373 3.436
Adult Services* 98.765 98.765 0.000
Net Expenditure 514.481 517.542 (3.061)
Revenue Support Grant (280.920) (280.920) 0.000
Council Tax Income (95.108) (95.528) 0.420
Non-Domestic Rates Income** (131.323) (131.323) 0.000
Funding (507.351) (507.771) 0.420
Use of General Fund Balances 7.130 9.771 (2.641)
2023/24
*Adult Services overspent against budget in the year by £0.9m; this was transferred from HSCP reserves and does not
impact on the Council’s General Fund balance.
**The Council collected £108.7m directly from local businesses with £22.6m due from the Scottish Government National
Non-Domestic Rates Pool at 31 March 2024. 
The Council’s Reserves 
The Council holds the following balances in reserve.
Further details can be found in Note 7: Usable reserves. 
As at 31
March
2023 Usable Reserves
As at 31
March
2024
£m £m
127.391 General Fund Balance 117.620
6.497 Housing Revenue Account 6.164
8.184 Capital Receipts Reserve 7.518
93.979 Other Statutory Funds 90.917
236.051 Total 222.219 
The General Fund balance of £117.6m will be carried
forward to 2024/25. Of this balance, £107.3m has been
earmarked for a particular purpose, as outlined in Note
7: Usable reserves. This leaves unallocated reserves of
£10.3m (2.0% of the Council’s net annual running costs),
which is in line with levels agreed by the Council under
its revised financial planning principles. 
It is viewed that this balance is appropriate to the
financial risk environment the Council is facing both in
light of the ongoing response and recovery from the
pandemic, but also to mitigate adverse risks anticipated
in public finances generally over the medium to longer
term. 
Housing Revenue Account 
The balance on the Housing Revenue Account (HRA) as
at 31 March 2024 has reduced to £6.2m. This remains a
prudent level of unallocated reserves for the HRA to
mitigate the impact of any unforeseen risks and to
provide an element of mitigation against forecast
pressures related to the prevailing economic climate. 
The year-end break-even position was arrived at after
some large budget variances were experienced in-year.
Property repairs and maintenance, including voids
management, significantly overspent; however, this was
offset by lower capital charges and increased interest
receivable following higher interest rates over the year,
as well as a drawdown from reserves of £0.3m. 
Infrastructure Assets 
The Scottish Government published a Statutory Override
in August 2022, to allow councils to continue the current

Page 14

11 
Annual Accounts 2023/24
accounting treatment for Infrastructure assets until 31
March 2024. Further detail is provided at Note 9. 
Capital and Borrowing 
Renfrewshire Council continues to make significant
capital investment in council housing, schools, culture,
roads and the town centre estate. On 2 March 2023, the
Council approved the housing capital investment
programme for 2023/24 of £30m; and the General Fund
capital investment programme for 2023/24 of £146m.
The capital investment programmes were affected by
the availability of contractors, as well as high levels of
inflation impacting construction costs and professional
fees. Programmes have therefore been re-profiled
during the year to reflect revised timescales of individual
projects, or where project completion dates have been
delayed, resulting in actual capital spend for the year of
£23m for housing capital investment and £105m for the
General Fund. Further detail is provided in Note 14:
Capital expenditure and capital financing. 
The following charts show the actual expenditure
incurred and income received in relation to the 2023/24
capital programme. 
During the course of 2023/24 there was new long-term
external borrowing from the Public Works Loans Board
(PWLB) of £20m to support the capital programme. The
level of cash balances available to the Council remains
consistent with daily cash requirements, treasury and
capital investment plans. The decrease in cash balances
compared to 31 March 2023 is attributable in part to a
significant capital programme, particularly the Council’s
cultural and heritage investment over the year, with
Paisley Town Hall the first of a number of transformed
cultural facilities planned that opened in October 2023. 
The Council’s borrowing strategy is prepared in
accordance with the Code of Practice on Treasury
Management in Local Authorities. The majority of the
Council’s borrowing comes from the Public Works Loan
Board with the remainder from market and other loans.
Further details are provided in Note 22: Financial
Instruments. 
The Council regulates its capital spending limits within a
prudential framework recommended by CIPFA and
endorsed by the Scottish Government. Each year, the
Council sets its capital financing requirement (CFR) for

Page 15

12 
Annual Accounts 2023/24
the forthcoming year in its Treasury Management
Strategy Statement (TMSS), approved by the Council on
2 March 2023 with a mid-year update on 14 December
2023. The TMSS for 2023/24 can be found on the
Council Committee Management Information System at:
http://renfrewshire.cmis.uk.com/renfrewshire/Home.aspx. 
The CFR is a prudent assessment of the aggregate
external borrowings for capital investment purposes
that are affordable and sustainable over the longer-
term. The actual CFR at 31 March 2024 was £510.1m,
within the authorised limit of £571.0m. The Council’s
external borrowings have only been applied for capital
investment purposes, with the Council’s net external
debt being £358.0m at 31 March 2024 compared to the
operational boundary of £553.0m. The Council’s costs of
borrowing remain consistently one of the lowest of all
Scottish local authorities, are affordable, and align to the
Council’s medium to long-term financial strategy. 
The Council’s non-housing financing costs were 3.1% as
a proportion of the Council’s non-housing net revenue
stream. Housing related financing costs as at 31 March
2024 were 27.7% of net housing revenues, lower than
the mid-year forecast of 29.0%. 
Net Pension Position 
The disclosure requirements for pension benefits under
IAS19 are detailed in Notes 27 and 28. The appointed
actuaries, have confirmed an increase of £59.7m in their
assessment of the Council’s share of the actuarial
position of the local government pension fund as at 31
March 2024. This is largely attributable to the corporate
bond yield (upon which the pension discount rate is
derived) having risen over the past year, which served to
reduce the employer's pension obligations and led to
the gain on the balance sheet. 
The assessment provides only a snapshot as at 31 March
2024 and necessarily changes on a day-to-day basis to
reflect stock market movements in particular. The
appointed actuaries remain of the view that the asset
holdings of the Strathclyde Pension Scheme and the
contributions from employees and employers provide
sufficient security and income to meet future pension
liabilities. 
Accounting rules require that a cap is placed on the
value of a pension asset that can be reported in the
Balance Sheet. For 2023/24, this has adjusted the value
of the pension asset shown in the balance sheet to nil
(£102.4m in 2022/23). This nil value only relates to
pension obligations funded through the LGPS, so the
balance sheet shows a pension liability of £74.5m to
reflect the Council’s unfunded pension obligations. 
A potential change to pension rules is outlined in Note
29: Contingent liabilities; however, this has not been
reflected in the pension liability reported in the Balance
Sheet. 
Provisions and Contingencies 
The Council has provided for eventualities which may
have a material effect on the financial position of the
Council. The reasons for the provisions made are
outlined in Note 21: Provisions. In general, any
contingent liabilities known to the Council are covered
by insurance arrangements. As outlined at Note 7, the
Council has also set aside £2.9m for uninsured claims.
Any contingencies that cannot yet be accurately
quantified are outlined in Note 29: Contingent liabilities. 
The Renfrewshire Council Group 
Local authorities are required to prepare Group
Accounts in addition to their own Council’s accounts
where they have a material interest in other
organisations. The Group Accounts consolidate the
results of the Council with five subsidiaries:
• Renfrewshire Leisure Limited, trading as OneRen;
• the Common Good Funds;
• the Coats Observatory Trust;
• Park Lane Developments (Renfrewshire) LLP; and
• Paisley Museum Reimagined Limited.
The Group Accounts also consolidate the Council’s share
of five other entities treated as associates or joint
ventures:

Page 16

13 
Annual Accounts 2023/24
• Strathclyde Partnership for Transport;
• Strathclyde Concessionary Travel Scheme Joint
Committee;
• Renfrewshire Valuation Joint Board; 
• Renfrewshire Health and Social Care Integration
Joint Board; and
• AMIDS Renfrewshire LLP.
The Council has non-material interests in a number of
other entities namely Scotland Excel; Glasgow and the
Clyde Valley Strategic Development Planning Authority;
and Glasgow City Region – City Deal Cabinet. 
Financial Outlook and Key Risks 
Financial Sustainability 
The Financial update reports throughout 2023/24
outlined continued and considerable uncertainty for
local government finances. In 2020, the Council agreed
to replenish unallocated reserves to a threshold of £10m
in order to address the risks of significant and
unplanned cost pressures which may emerge over the
medium term, and this has been maintained in 2023/24. 
The Council continued to feel the impact of the UK’s exit
from the EU and the war in Ukraine during 2023/24,
though general inflation did reduce over the latter part
of the year. Certain areas of supplies, such as energy,
food and provisions and fuel, retained very high levels of
inflation. 
The Scottish Government published its Medium Term
Financial Strategy (MTFS) on 25 May 2023, outlining its
potential spending and funding position over the next 5
years. The MTFS outlines a growing financial gap for the
Scottish Government, with spending pressures are
expected to outstrip the resources available from
2024/25, with an estimated funding gap of approaching
£2 billion by 2027/28. The outlook for the local
government settlement is likely to remain very
constrained and in line with that previously outlined in
the Resource Spending Review i.e. effectively real terms
cuts. An updated MTFS is expected in summer 2024.
As outlined in the Revenue Estimates 2023/24 report to
Council in March 2023, after adjusting for new
responsibilities, areas of growing responsibility and
other conditional aspects of the settlement to provide a
like-for-like comparison to 2023/24, the underlying core
grant for Renfrewshire Council increased by £0.239m
(0.1%). The Council decided to increase Council Tax by
6% in 2023/24 and used £0.605m of earmarked reserves
to balance the revenue budget. 
Existing service and cost pressures arising from pay
settlements, demographic and socio-economic factors
will continue to play a major role in driving spending
pressures for the Council; however, the predominant
focus of the Council will be addressing its projected
medium-term funding gap. As reported to the Council in
February 2024, the current central forecast is a financial
gap of £45-50m by the end of 2027. This forecast is prior
to any decisions on Council Tax increases. Assuming a
5% uplift in Council Tax in each year is decided, the
cumulative gap would reduce to a range of £30-35m. 
The Council continues to mitigate treasury risks,
including those associated with the security of cash
deposits, by actively considering debt restructuring as
outlined in the Council's agreed Treasury Management
Strategy. The Council also continually reviews, in
consultation with its treasury advisors, the criteria for
placing deposits with financial institutions on the
Council’s approved counterparty list. 
As part of the Council’s treasury strategy, it continues to
utilise internal cash balances, deferring or minimising
external borrowing with the dual objectives of reducing
the level of cash deposits held by the Council, whilst
generating ongoing savings in net interest costs. This
strategy is monitored carefully in order to ensure that
the Council retains sufficient cash balances to support
its ongoing requirements and remains alert to any
anticipated adverse movement in future borrowing
rates.

Page 17

14 
Annual Accounts 2023/24
Other Key Risks 
Risk Mitigating Actions 
Economy 
A range of strategic challenges – the COVID-19 pandemic, the UK leaving the EU,
the climate emergency, high inflation in the UK economy leading to high food
and energy costs– impact on the local and national economy.  Renfrewshire’s
economy has well-established strengths in transport, manufacturing,
construction and retail, but all sectors and supply chains have been impacted by
these economic challenges.  We mitigate the impact through our large-scale
infrastructure investment programme which includes the AMIDS development,
our investment in housing and heritage assets, our employability programmes
and our support for new and existing businesses, which includes support to bid
for council contracts and to reduce carbon emissions. 
Reducing inequalities 
The pandemic has exacerbated many existing inequalities and had a
disproportionate impact on our poorer communities.  In Renfrewshire, we seek
to address unequal outcomes through strong partnership working, through our
Fairer Renfrewshire programme, through specific programmes which tackle local
priorities (such as our focus on alcohol and drug use), through national
programmes such as the Scottish Attainment Challenge, and on building
community capacity.  In the short-term, we are significantly focused on food
insecurity and income maximisation. 
Climate, Sustainability
and Adaptability 
Renfrewshire Council declared a Climate Emergency in 2019.  The climate
emergency brings risk to the Council and to our communities and we are focused
on mitigation and on working toward a just transition to net zero.  Our Plan for
Net Zero was approved in 2022 and our Council Plan and Service Improvement
Plans set out how each part of the Council will contribute to Net Zero.  Our
procurement strategy considers sustainability and community benefits in all
contract strategies.   Our Climate Panel provided an opportunity for community
voices (including under-represented groups) to be heard.  Our Community
Climate Fund supported community organisations to enable behaviour change
and deliver local green projects.  Internally, we manage our corporate assets and
capital investment programme to optimise use of the estate and promote
reductions in energy use.

Page 18

15 
Annual Accounts 2023/24
Common Good Funds and Coats
Observatory Trust 
The Council administers the Common Good Funds for
the areas of Paisley, Renfrew and Johnstone, as well as
the Coats Observatory Charitable Trust. In order to
comply with the Code, Audit Scotland and the Office of
the Scottish Charity Regulator (OSCR) requirements, the
Council separately prepares the financial statements of
the Coats Observatory Trust, with the financial
performance of the Common Good Funds disclosed in
the Council’s Annual Accounts. Balances are also
included in the Group Accounts. Azets is the appointed
auditor for the Coats Observatory Charitable Trust. 
Overall, the Common Good Funds incurred a combined
in-year surplus of £2.8m which is added to the previous
surplus brought forward. The total net asset value
increased by £2.8m, including an increase in
investments of £1.7m. Both the market values of
investments and income generated from dividends are
likely to be subject to ongoing volatility as the economy
recovers from the pandemic and is subject to ongoing
inflationary risk. 
Conclusion and Acknowledgements 
We would like to acknowledge efforts by the whole
Finance team in producing the annual accounts, as well
as colleagues in other services for their continued hard
work and support. 
Further information on the annual accounts or on the
Council’s general finances can be obtained on the
Council website (www.renfrewshire.gov.uk), or by
telephoning 0300 300 0285. 
Cllr Iain Nicolson Alan Russell Alastair MacArthur
Leader of the Council Chief Executive Director of Finance and Resources

Page 19

16 
Annual Accounts 2023/24
Statement of Responsibilities 
The Authority's Responsibilities 
The Authority is required to:  
• make arrangements for the proper administration of
its financial affairs and to secure that one of its
officers has responsibility for the administration of
those affairs (section 95 of the Local Government
(Scotland) Act 1973). In Renfrewshire Council, that
officer is the Director of Finance and Resources;
• manage its affairs to secure economic, efficient and
effective use of resources and safeguard its assets;
• ensure that the Annual Accounts are prepared in
accordance with legislation (The Local Authority
Accounts (Scotland) Regulations 2014), and so far as
is compatible with that legislation, in accordance
with proper accounting practices (section 12 of the
Local Government in Scotland Act 2003), and;
• approve the Annual Accounts for signature. 
I can confirm that these annual accounts were approved
for signature by the Council at its meeting on 24
October 2024. 
Signed on behalf of Renfrewshire Council. 
Cllr Iain Nicolson
Leader of the Council 
The Director of Finance and Resources’
Responsibilities 
The Director of Finance and Resources is responsible for
the preparation of the Authority's Annual Accounts in
accordance with proper practices as required by
legislation and as set out in the CIPFA/LASAAC Code of
Practice on Local Authority Accounting in the United
Kingdom (the Accounting Code). 
In preparing the Annual Accounts, the Director of
Finance and Resources has: 
• selected suitable accounting policies and then
applied them consistently; 
• made judgements and estimates which were
reasonable and prudent;
• complied with legislation; and
• complied with the local authority Accounting Code
(in so far as it is compatible with legislation). 
The Director of Finance and Resources has also:
• kept adequate accounting records that were up to
date; and
• taken reasonable steps for the prevention and
detection of fraud and other irregularities. 
I certify that the financial statements give a true and fair
view of the financial position of the Council and its
group at the reporting date and the transactions of the
Council and its group for the year ended 31 March 2024. 
Alastair MacArthur
Director of Finance and Resources

Page 20

17 
Annual Accounts 2023/24
Annual Governance Statement 
Scope of responsibility
Renfrewshire Council is responsible for ensuring that its
business is conducted in accordance with the law and
proper standards, and that public money is safeguarded,
properly accounted for, and used economically,
efficiently and effectively. The Council also has a
statutory duty to make arrangements to secure best
value under the Local Government in Scotland Act 2003.
In discharging this overall responsibility, the Council’s
members and the corporate management team are
responsible for putting in place proper arrangements for
its affairs and facilitating the effective exercise of its
functions, which includes arrangements for the
management of risk. 
The Council has approved and adopted a Local Code of
Corporate Governance, which is consistent with the
principles of the Chartered Institute of Public Finance
and Accountancy (CIPFA) and the Society of Local
Authority Chief Executives (SOLACE) framework;
Delivering Good Governance in Local Government. A
copy of the Local Code is available on our website at:
www.renfrewshire.gov.uk > Your Council > Information,
performance and statistics > Information Governance 
This statement explains how Renfrewshire Council has
complied with the Local Code and also meets the Code
of Practice on Local Authority Accounting in the UK,
which details the requirements for an Annual
Governance Statement. 
The purpose of the governance
framework
The governance framework comprises the systems and
processes, and culture and values, by which the Council
is directed and controlled and through which it accounts
to, engages with and leads the community. It enables
the Council to monitor the achievement of its strategic
objectives set out in the Council Plan. 
The system of internal control is a significant part of that
framework and is designed to manage risk to a
reasonable level. Internal control cannot eliminate all
risk of failure to achieve policies, aims and objectives
and can therefore only provide reasonable and not
absolute assurance of effectiveness. The system of
internal control is based on an ongoing process designed
to identify and prioritise the risks to the achievement of
the Council’s policies aims and objectives, to evaluate
the likelihood of those risks being realised and the
impact should they be realised, and to manage them
efficiently, effectively and economically. 
The governance framework
The main features of our governance arrangements are
described in the Local Code but are summarised below: 
The overarching strategic priorities and vision of the
Council are set out in the Council Plan 2022-2027 and
the Renfrewshire Community Plan 2017-2027. The
Council Plan is aligned to the Community Plan and sets
out 5 strategic outcomes that the organisation will work
to achieve over a 5-year period with specific priorities
relating to tackling inequality, promoting economic and
cultural regeneration, attainment and sustainability.
Renfrewshire’s Community Plan (which also acts as
Renfrewshire’s Local Outcome Improvement Plan as
required by the Community Empowerment (Scotland)
Act 2015) details how community planning partners will
work together to achieve the key priorities identified for
Renfrewshire. A mid-term review of the Community
Plan was also undertaken in 2022 in tandem with the
development of the new Council Plan, which identified
three key areas of focus which should be progressed by
partners. 
• The key outcomes the Council is committed to
delivering with its partners, are set out in the
Community Plan;
• The Council operates within an established
governance framework which incorporates a
scheme of delegated functions, financial regulations,
standing orders relating to contracts and procedural
standing orders. These elements of the framework
are kept under regular review by the Council;
• The Council facilitates policy and decision making
through a policy board structure;
• Services are able to demonstrate how their own
activities link to the Council’s vision and priorities

Page 21

18 
Annual Accounts 2023/24
through their Service Improvement Plans.
Performance management and monitoring of service
delivery is reported through policy boards regularly
including six monthly updates to the Leadership
Board on progress against the implementation of
the Council Plan;
• The Corporate Management Team has agreed a new
refreshed approach to its performance monitoring
and the Council Plan scorecard will be considered
alongside other performance information each
quarter and followed up with an in-depth look at
performance in one service particular area of
interest at regular intervals.
• An annual report on the Local Government
Benchmarking Framework, which includes data for
over 100 indicators for all 32 local authorities, is
provided to the Audit, Risk and Scrutiny Board each
year.
• The Council makes a range of performance
information available on its website, including the
publication of its public performance report “How
are we doing?”, in line with statutory requirements.
• The Council has adopted a code of conduct for its
employees. Elected members adhere to the
nationally prescribed Code of Conduct for Members.
In addition, the Council has in place a protocol for
Relationships between Political Groups, Elected
Members and Officers;
• The Council’s approach to risk management is set
out in the risk management strategy and is well
embedded. Risks are reported 6 monthly to the
Audit, Risk and Scrutiny Board and a Risk
Management Annual Report is also provided to
Board in respect of corporate risk management
arrangements. In 2023/24 the Council launched its
self-developed Business as Usual Risk Assurance
Model. All Heads of Service self-assessed their levels
of assurance in relation to implementing risk
controls covering various aspects of governance, risk
and internal control. The Corporate Management
Team are required to confirm the overall assurances
for their service areas. 
• The Director of Finance and Resources is the
Council’s Senior Information Risk Owner and
information risk is monitored through the
Information Management and Governance Group
and its sub-groups. The Managing Solicitor (DPO) is
the statutory Data Protection Officer;
• Comprehensive arrangements are in place to ensure
members and officers are supported by appropriate
training and development;
• Registers of interests for elected members and
senior officers are maintained and published on the
Council’s website;
• The Council complies with the CIPFA Code of
Practice on Managing the Risk of Fraud and
Corruption and the Council’s arrangements for fraud
prevention, detection and investigation are
managed through the corporate counter fraud
service;
• The Council’s approach to ‘whistleblowing’ is
outlined in the whistleblowing policy;
• Cyber-attacks are both increasing and becoming
more sophisticated and while no system of internal
control can provide absolute assurance, the Council
has a range of multi layered Cyber Security controls
in place and tested annually to check standards are
in line with government guidance. Industry cyber
security standards are followed and explicitly those
belonging to Public Sector Network (PSN), National
Cyber Security Centre (NCSC) guidance, Scottish
Government Public Sector Cyber Resilience Plan and
Payment Card Industry (PCI) data security standards.
The O365 security and compliance toolset provides a
wide range of protection against cyber-attacks
including identity theft and phishing. The Council
holds a current Certificate of Compliance for PSN
standards. ICT network and digital services are
monitored monthly through our cyber security
partner. These are all monitored and managed
through the Cyber Security team which is headed up
by a CISM qualified Cyber Security Architect (Cyber
Information Security Manager). Events and alerts are
monitored 24 x 7 by our cyber security partner who
are authorised to take emergency preventative
action where necessary;
• Clear and independent governance arrangements
are in place with One Ren and the Renfrewshire

Page 22

19 
Annual Accounts 2023/24
Health and Social Care Partnership with oversight
from the Head of Policy and Commissioning and the
Head of Corporate Governance respectively and the
Council’s Leadership Board.
• Seven Local Partnerships have been established and
have identified initial local priorities. Decision
making including that relating to relevant grants is
delegated to each Local Partnership through a Lead
Officer appointed by the Council, through the Chief
Executive.
This governance framework has been in place at
Renfrewshire Council for the year ended 31 March 2024. 
The system of internal financial control
The system of internal financial control is based on a
framework of regular management information,
financial regulations, administrative procedures
(including segregation of duties), management and
supervision, and a system of delegation and
accountability. Development and maintenance of the
system is undertaken by managers within the Council.
The system includes:
• Guidance on financial management supported by
comprehensive financial regulations and codes;
• Comprehensive budgeting systems, and detailed
guidance for budget holders;
• Regular reviews of periodic and annual financial
reports which indicate financial performance against
the forecasts;
• Setting targets to measure financial and other
performance;
• The preparation of regular financial reports that
indicate actual expenditure against the forecasts;
• Clearly defined capital expenditure guidelines;
• As appropriate, formal project management
principles;
• The Chief Finance Officer is the Director of Finance
and Resources who complies with the CIPFA
Statement on the Role of The CFO in Public Services. 
The role and responsibilities of the Audit
Committee and the Chief Auditor
The role of the audit committee is under the remit of
the Audit, Risk and Scrutiny Board, which is chaired by a
member of the opposition. Its role is:
• to approve the internal audit charter and annual
internal audit plans;
• to review internal and external audit reports and the
main issues arising, including those relating to the
annual accounts and seek assurance that action has
been taken and make recommendations to the
Council where appropriate;
• to receive and consider the Chief Auditor’s annual
report, summarising internal audit activity and the
level of assurance this provides over the
arrangements for internal control, risk management
and governance within the Council;
• to monitor the performance of Internal Audit;
• to consider the annual review of the Local Code of
Corporate Governance.
The Internal Audit service operates in accordance with
the Public Sector Internal Audit Standards and reports to
the Audit, Risk and Scrutiny Board. Internal Audit
undertakes an annual programme of work, approved by
the Board, based on a strategic risk assessment. The
Council’s Chief Auditor provides an independent opinion
on the adequacy and effectiveness of the governance
framework, risk management and internal control. The
Council conforms to the requirements of the CIPFA
Statement on the Role of the Head of Internal Audit
(2019). 
Members and officers of the Council are committed to
the concept of sound governance and the effective
delivery of Council services. The Audit, Risk and Scrutiny
Board complies with the CIPFA guidance Audit
Committees: Practical Guidance for Local Authorities
and Police. The Council’s Chief Auditor has responsibility
to review independently and report to the Audit, Risk
and Scrutiny Board annually, to provide assurance on
the adequacy and effectiveness of the Local Code and
the extent of compliance with it. The Audit, Risk and
Scrutiny Board performs a scrutiny role in relation to the
application of the Local Code of Corporate Governance

Page 23

20 
Annual Accounts 2023/24
and regularly monitors the performance of the Council’s
Internal Audit service. 
Internal Audit reporting arrangements include
communication of finalised audit engagements,
monitoring the progress of agreed management actions
and communication of any unacceptable risk identified
to the Board. 
Review of effectiveness and continuous
improvement
Renfrewshire Council has responsibility for conducting,
at least annually, a review of the effectiveness of its
governance framework including the system of internal
control. The review of effectiveness of the framework is
informed by the work of the Corporate Management
Team who have responsibility for the development and
maintenance of the governance environment, the Chief
Auditor’s annual report, and reports from the external
auditors and other review agencies and inspectorates. 
The effectiveness of the governance framework and
how the organisation manages its risks is reviewed
annually by the Corporate Management Team, including
the use of an annually updated self-assessment tool
covering twelve key areas of governance, internal
control and risk as follows:
• Asset Management
• Complaints, Comments and Claims
• Financial Control and Governance
• Health and Safety, and managing adverse events
• Information Handling
• Organisational Resilience
• Partnership Management
• People, Wellbeing and Development
• Programme Management
• Service Performance
• Community and Public Safety
This self-assessment indicated the governance
framework is being complied with in all material
respects. In addition, the review of the effectiveness of
the governance arrangements and the systems of
internal control within the group entities places reliance
upon the individual bodies’ management assurances in
relation to the soundness of their systems of internal
control. 
The Council’s approach to continuous improvement has
a number of strands. Our Council Plan and Service
Improvement Planning processes drive much of this and
allow for elected member scrutiny of improvement
activity. Services also undertake improvement work
linked to their core duties and to statutory
requirements. Registered services in education, housing,
social work and social care regularly undertake self-
assessment activity as part of their regulatory
framework and inspection process. Services within
Environment, Housing and Infrastructure maintain their
ISO 9001 accreditation as one means of demonstrating
quality. The Council has recently developed its own
model of corporate self-assessment based on the Public
Service Improvement Framework. 
The Corporate Management Team introduced an
updated programme of corporate self-assessment in
2023 linked to the previous EFQM/PSIF model used
across the public sector. All Chief Officers participated in
this programme initially before it was further extended
to a wider group of senior leaders across the Council.
The outputs from this are informing an improvement
plan led by the Corporate Management Team. 
The Council continues to recognise the need to exercise
strong financial management arrangements to manage
the financial pressures common to all local authorities,
and has robust financial control and financial planning
processes in place. The CIPFA Financial Management
(FM) Code was adopted in June 2021, and the resulting
Action Plan contains 59 improvement actions with
target dates ranging until 2025.  Work to refresh the
initial engagement will be undertaken by the end of
2025 to ensure that improvement work continues to be
focused, relevant and effective. 
The Council continues to manage a number of very
significant challenges and is operating within a context
of new and emerging challenges which require the
Council to respond very flexibly to the changing needs of

Page 24

21 
Annual Accounts 2023/24
local businesses, communities and citizens. These
factors include:
• Ongoing economic uncertainty, which has
significantly increased costs and impacted supply
chains utilized by the Council and its partners. The
linked cost of living crisis has also required the
Council to respond in new ways with partners to
meet the needs of those most vulnerable across
Renfrewshire through our Fairer Renfrewshire
Programme.
• New and developing demand pressures continue to
impact the Council, including in relation to issues
such as migration and asylum, in relation to support
for Ukrainian Displaced Persons, Unaccompanied
Asylum Seeking Children and Young People and
more recently the widening out of the asylum
dispersal programme.
• In the post-pandemic period, the Council has had a
strong focus on recovering from Covid-19 and
continuing to mitigate some of the impacts on our
communities, including those relating to rapidly
increasing living costs. As an organisation, the
Council has continued to adopt new ways of
working, building on the strong approach developed
during the pandemic in areas such as digital access
for customers, and embracing hybrid working.
Whilst this is still a recovery phase, much of the
business-as-usual work has fully resumed, including:
• the work on social renewal, which began during the
pandemic, is now part of the wider Fairer
Renfrewshire programme, which is overseen by a
sub-committee of the Leadership Board. Services
have returned to the regular programme of
reporting performance to elected members through
policy boards, with service improvement plans
submitted for approval in spring 2024 and regular
progress updates provided.
• the Right for Renfrewshire programme
recommenced over 2022, and the service redesigns
progressed were in those areas where it was
anticipated that there would be potentially less
direct impact from the pandemic recovery process
and where the greatest opportunity exists for
appropriate management and service capacity to be
directed towards the Right for Renfrewshire agenda;  
• the Council commenced planning for Brexit during
2019/20 and identified risks have been incorporated
into the Strategic and Corporate Risk Registers.
Some of these risks will be further exacerbated by
the ongoing conflict in Ukraine and the associated
sanctions on Russia which will place additional cost
and supply pressures on some products and
materials that are likely to increase and continue
into 2024/25.
Audit Scotland has introduced a new approach to
auditing Best Value in local government which
commenced this year as part of the next 5-year Best
Value Audit programme. This approach involves
thematic areas of focus each year which will be
considered for all local authorities within the same
snapshot in time rather than the previous rolling
programme of deep dive audits which inspect each local
authority across a five-year programme. 
This significant shift in approach and for year one
(2023), this examined the effectiveness of leadership
within Councils across Scotland, with a separate
thematic report published for Renfrewshire Council in
September 2023 alongside the Annual Audit Report. For
2024, the national theme will be Workforce Innovation. 
Alongside the ongoing Best Value auditing and this new
approach with annual themes, there will also be further
external audit activity as requested by the Accounts
Commission following the Section 102 report instructed
in response to the Dargavel School pupil roll forecast
error. It is expected a Best Value report will be produced
by the end of 2024 for Renfrewshire Council. The action
plan arising from the Independent Review of the
Dargavel School Project is reported to and monitored by
the Audit, Risk and Scrutiny Board. 
The Council undertook a comprehensive review of its
governance arrangements through a member led cross
party working group, the recommendations arising were
reported to and approved by the Council on 29 February
2024. A separate self-assessment against the CIPFA
guidance for effective Audit Committees was
undertaken with the members of the Audit, Risk and
Scrutiny Board and actions for improvement were
identified and have been progressed. A leadership

Page 25

22 
Annual Accounts 2023/24
development programme was also delivered to support
senior managers and comprehensive financial
governance training was undertaken across the
Council’s senior and middle managers. 
The external auditors, Azets, provided an unqualified
and unmodified audit opinion on the 2022/23 annual
accounts. 
Regular reviews of the Council’s arrangements are
undertaken by Internal Audit. Two specific areas were
identified in the 2022/23 governance statement as
impacting on the overall internal control, risk
management and governance arrangements. These
were:
• Business continuity plans – All services now have up-
to-date business continuity plans, with a programme
of quality assurance being undertaken.
• Manual creditor payments – A corporate project to
address this area is currently underway. 
The programme of work undertaken by Internal Audit in
2023/2024 identified 8 occasions where a limited or no
assurance level was provided in relation to the internal
control, risk management and governance objectives for
the specific areas of each audit review. Of these, 6 were
specific to individual service areas and although these
areas require to be addressed there is no significant
impact on the Council’s overall system of internal
control and action plans are in place to address the risk
identified. 
The remaining three areas identified as impacting on the
overall internal control, risk management and
governance arrangements are:
• Disaster recovery – The Council’s critical systems are
increasingly moving to a Software as a Service (SaaS)
operating model and, as these systems are
externally hosted, the Council’s role in relation to
disaster recovery differs from traditional, on-
premises solutions, where IT would have a more
active role. Nonetheless it is important that the
Council has adequate arrangements in place for
obtaining assurance from SaaS providers that
disaster recovery will be handled in a timely manner,
with minimum business impact, should an event
occur. The review identified that improvements
were required, including formal identification of
critical systems and formalising the procurement
guidance to ensure that services procured meet the
required disaster recovery arrangement. An action
plan is in place to ensure that the required actions
are implemented.
• Health and Safety – The corporate arrangements for
health and safety require to be improved. It was
identified that procedures require to be reviewed
and updated. Improvements are required in terms of
corporate oversight, compliance and performance
reporting.
• Purchasing processes (corporate credit cards) -
Compliance against the corporate procedures
requires to be improved, the main areas for
improvement included eliminating off-contract
spend and improving the authorisation process to
ensure that all purchases are properly authorised.
The Corporate Procurement Unit has reminded all
relevant employees of the requirement to comply
with the established procedures. 
Internal Audit undertakes an annual exercise to ensure
that recommendations arising from Internal Audit
engagements have been implemented by service
management and the results are reported to the Audit,
Risk and Scrutiny Board. This work highlighted that 88%
of recommendations were implemented by the due
date. 9% had passed their original due date and revised
implementation dates have now been set and 3% were
superseded. Of the 44 recommendations followed up
that were deemed to be critical, 41 have been fully
implemented and 3 have been partially implemented.
Revised implementation dates have been agreed for
each of these recommendations. 
It is our view that the Council has in place a sound for
governance, risk management and internal control and
that appropriate mechanisms are in place to identify any
areas of weakness. 
This is corroborated by an Annual Report incorporating
the Annual Assurance Statement prepared by the
Council’s Chief Auditor stating that subject to

Page 26

23 
Annual Accounts 2023/24
management addressing the critical and important
recommendations made the limited and no assurance
reports, it is considered that reasonable assurance can
be placed upon the adequacy and effectiveness of the
Council’s internal control, risk management and
governance arrangements.
Action Plan 
Following consideration of the review of adequacy and effectiveness the following action plan has been agreed to ensure
continual improvement of the Council’s governance. 
Agreed action Responsible person Date
Implement improvement plan arising from the
Corporate Self-Assessment Exercise.
Head of Policy and Partnerships December 2024 
Agreed action Responsible person Date
The recommendations arising for the review of
the corporate health and safety internal audit
report, will be considered and an action plan
developed will be agreed for implementation.
Director of Finance and Resources December 2024 
The agreed actions will be subject to review to identify the progress being made in implementing them. 
Update on the 2022/23 Action Plan 
Agreed action Progress Update Responsible
person
Date
All service level business
continuity plans are to be
updated to record all the ICT
risks referred to in the Council’s
business continuity plan
template for all service areas
All service areas have updated their
business continuity plan templates.
These plans are currently being
externally quality assured
Service
Directors
December 2024
A review of the current manual
payment process is under review
with key stakeholders from the
Corporate Procurement Unit and
the Finance Business Partners,
this will enable and introduce an
exception policy to support the
No Purchase Order No Payment.
Once the review is conducted
the exception policy will be
implemented and the No
Purchase Order No Payment
approach will commence, this is
anticipated to take up to 12
Months.
A Strategic P2P Lead officer was
appointed in November 2023. The
programme’s Strategic and
Operational Governance boards have
now been established and meet on a
monthly basis to discuss key decision
points, with regular updates to the
Corporate Management Team. Nine
Project Workstreams have been
established, with lead officers
appointed to progress these and as
part of this, the No PO No Payment
initiative will be taken forward, it is
now expected to be implemented by
December 2024.
Strategic Lead
(P2P)
December 2024

Page 27

24 
Annual Accounts 2023/24
Assurance 
Subject to the above, and on the basis of the assurances provided, we consider the governance and internal control
environment operating during 2023/24 provides reasonable and objective assurance that any significant risks impacting
on the achievement of our principal objectives will be identified and actions taken to avoid or mitigate their impact.
Systems are in place to continually review and improve the governance and internal control environment and action
plans are in place to address identified areas for improvement. 
Cllr Iain Nicolson Alan Russell
Leader of the Council Chief Executive

Page 28

25 
Annual Accounts 2023/24
Remuneration Report 
The Local Authority Accounts (Scotland) Amendment
Regulations 2014 (SSI No. 2014/200) amend the Local
Authority Accounts (Scotland) Regulations 2011 (SI No
2011/64) and requires local authorities in Scotland to
prepare a Remuneration Report as part of the annual
statutory accounts. All information disclosed in sections
3 to 8 in this Remuneration Report has been audited by
the Council’s appointed auditor, Azets. The other
sections of the Remuneration Report will be reviewed
by Azets to ensure that they are consistent with the
financial statements. 
1. Remuneration Policy for Senior
Employees 
The salary of senior employees is set by reference to
national arrangements. The Scottish Joint Negotiating
Committee (SJNC) for Local Authority Services sets the
salaries for the Chief Executives of Scottish local
authorities. The salaries of the Corporate Directors and
Heads of Service are based on a spinal column point
model as agreed by the Finance and Resources Policy
Board on 14 May 2014. Senior employees received a
6.05% pay award in 2023/24 and no other benefits. 
2. Remuneration policy for the Leader of
the Council, the Provost and Senior
Councillors 
The annual salary of the Leader of the Council and the
upper limit for the annual salary of the Provost (or civic
head) are set by the Scottish Government in terms of
the Local Governance (Scotland) Act 2004
(Remuneration) Regulations 2007, as amended by the
Local Governance (Scotland) Act 2004 (Remuneration)
Amendment Regulations 2021. The salary for the Leader
of the Council in 2023/24 was £40,205 per annum
(£39,148 in 2022/23) and the salary for the Provost was
£30,154 per annum (£29,361 in 2022/23). 
In terms of the same Regulations, the Scottish
Government permits Renfrewshire Council to nominate
up to 14 senior councillors (in addition to the Leader of
the Council and the Provost), whose salaries in
aggregate must not exceed a specified amount, in
2023/24 being £351,766 per annum; and whose salaries
individually must be on a specified scale, in 2023/24
£20,099 to £30,154. At the Council meeting of 30 June
2022, it was agreed that Renfrewshire Council would
have 13 senior councillors: six Policy Board Conveners
(salary of £28,951 per annum in 2023/24); four
Regulatory Board Conveners (salary of £24,032 in
2023/24); Chair of OneRen Board; Chair/Vice-Chair of
Integration Joint Board and one Leader of the
Opposition (salary of £24,032 in 2023/24). 
3. Remuneration of Senior Employees 
The regulations define a senior employee as any
employee who meets one or more of the following
criteria: 
• has responsibility for the management of the local
authority to the extent that the person has power to
direct or control the major activities of the authority
whether solely or collectively with other persons. 
• holds a post that is politically restricted by reason of
section 2(1)(a), (b) or (c) of the Local Government
and Housing Act 1989. 
• whose annual remuneration, including any annual
remuneration from a local authority subsidiary body
is £150,000 or more. 
The Council has interpreted the above criteria as
including the Chief Executive, Directors and the Chief
Executive of OneRen.
The term ‘remuneration’ means gross salary, fees and
bonuses, allowances and expenses and compensation
for loss of office. The table below outlines the
remuneration details for senior employees, including
prior year figures. The table shows the relevant
amounts, before tax and other deductions, due to, or
receivable by, each of the persons named for the year to
31 March 2024, whether or not those amounts were
actually paid to, or received by, those persons within
that period. There were no non-consolidated bonuses or
performance-related payments made to any senior
officer in 2023/24, nor any remuneration in connection
with election activities (this totalled £4,509 in 2022/23).

Page 29

26 
Annual Accounts 2023/24
2022/23
Total
Remuneration
Total
Remuneration
£ £
160,779 Alan Russell Chief Executive 167,893
129,136 Mary Crearie Director of Communities and Housing Services until 2 April
2023
2,839
126,216 Alastair MacArthur Director of Finance and Resources 136,907
129,936 Gordon McNeil Director of Environment, Housing & Infrastructure until 23
May 2023 then Director of Environment, Housing &
Infrastructure from 24 May 2023
136,924
129,436 Steven Quinn Director of Children's Services until 11 August 2023
Full-year equivalent £136,924
51,508
0 Janie O'Neil Director of Children's Services from 04 December 2023
Full-year equivalent £130,138
41,002
675,503 Total 537,073
Senior employees
Name Post held
2023/24
2022/23 2023/24
Total
Remuneration
Total
Remuneration
£ £
108,924 Victoria Hollows 115,493
108,924 115,493
Chief Executive, OneRen
Total
Name
Senior Employees of Subsidiary Bodies
Post held
4. Remuneration of Senior Councillors 
Under the regulations, remuneration disclosures are to be made for the Leader of the Council, the Civic Head and any
councillor designated a Senior Councillor by the Council. The table below shows the relevant amounts, before tax and
other deductions, due to each of the persons named for the year to 31 March 2024, whether or not those amounts were
actually paid or received within that period and relate only to the Senior Councillor posts indicated. No payments were
made in connection with loss of employment or office, nor were any other payments made that are not included in the
table. 
The following table reports on remuneration related to senior councillor positions only.

Page 30

27 
Annual Accounts 2023/24
2022/23 2023/24
Total
Remuneration Name Position held
Total
Remuneration
£ £
2,589 Cathy McEwan Policy Board Convener 0
2,175 Jennifer Adam Chair/Vice Chair IJB (2) 0
2,357 Bill Binks Regulatory Board Convener 0
2,175 Andy Steel Regulatory Board Convener 0
2,589 Jacqueline Cameron Chair/Vice Chair IJB 0
2,141 Eddie Devine Leader of largest opposition group 0
2,175 Neill Graham Leader of 2nd largest opposition group 0
23,753 Michelle Campbell Policy Board Convener 28,868
23,753 Emma Rodden Policy Board Convener 28,868
23,753 Andy Steel Policy Board Convener 28,868
19,637 Andy Doig Regulatory Board Convener 23,963
19,637 Stephen Burns Regulatory Board Convener 23,963
13,197 Cathy McEwan Regulatory Board Convener (1) 23,963
21,573 Jennifer Adam Chair/Vice Chair IJB (2) 28,868
19,637 Iain McMillan Leader of largest opposition group 23,963
36,821 Iain Nicolson Leader Of the Council 40,089
27,580 Lorraine Cameron Provost 30,067
26,341 Marie McGurk Policy Board Convener 28,868
26,341 Jim Paterson Policy Board Convener 28,868
26,341 John Shaw Policy Board Convener 28,868
21,812 John McNaughtan Regulatory Board Convener 23,963
23,796 Lisa-Marie Hughes Chair, OneRen (3) 28,868
370,173 420,915
Senior Councillors
Until 5 May 2022
From 19 May 2022
Full Year (excluding 6-19 May)
Total
Notes:
1. Cllr McEwan was appointed as Convener of the Licensing Board on 5 September 2022, which was the first meeting of that
board following the election
2. Cllr Adam was appointed as Chari/Vice-Chair of the Renfrewshire Integrated Joint Board (IJB) on 24 June 2022, which was
the first meeting of that board following the election 
3. Cllr Hughes was appointed as Chair of OneRen on 28 June 2022, which was the first meeting of that board following the
election 
No payments were made in connection with loss of employment or office, nor were any other payments made which are
not included in the table.

Page 31

28 
Annual Accounts 2023/24
5. Pension Entitlement 
Pension benefits for councillors and local government
employees are provided through the Local Government
Pension Scheme (LGPS). 
Councillors’ pension benefits are based on career
average pay. The councillor’s pay for each year or part
year ending 31 March (other than the pay in the final
year commencing 1 April) is increased by the increase in
the cost of living, as measured by the appropriate index
(or indices) between the end of that year and the last
day of the month in which their membership of the
scheme ends. The total of the revalued pay is then
divided by the period of membership to calculate the
career average pay. This is the value used to calculate
the pension benefits. 
From 1 April 2015 benefits for local government
employees are based on career average pay. Pension
benefits are based on the pay received for each year in
the scheme increased by the increase in the cost of
living, as measured by the appropriate index (or indices).
The scheme’s normal retirement age is linked to the
state pension age of each member. 
From 1 April 2009 a five-tier contribution system was
introduced with contributions from scheme members
being based on how much pay falls into each tier. This is
designed to give more equality between the cost and
benefits of scheme membership. Prior to 2009
contributions rates were set at 6% for all non-manual
employees. The tiers and members contribution rates
are as follows: 
Equivalent
bandings for
2022/23
Up to £25,300 5.5% Up to £23,000
£25,301 to £31,000 7.25% £23,001 to £28,100
£31,001 to £42,500 8.5% £28,101 to £38,600
£42,501 to £56,600 9.5% £38,601 to £51,400
Over £56,601 12% Over £51,401
Tiered contribution rates on
whole time pay
2023/24
If a person works part-time their contribution rate will
be based on their part-time pay. 
There is no automatic entitlement to a lump sum.
Members may opt to give up (commute) pension for
lump sum up to the limit set by the Finance Act 2004.
The accrual rate guarantees a pension based on 1/49th
of pensionable pay for each year of membership,
adjusted in line with the cost of living (prior to 2015 the
accrual rate guaranteed a pension based on 1/60th of
final pensionable salary). 
The value of the accrued benefits has been calculated
on the basis of the age at which the person will first
become entitled to receive a pension on retirement
without reduction on account of its payment at that age;
without exercising any option to commute pension
entitlement into a lump sum; and without any
adjustment for the effects of future inflation. 
The pension entitlements for Senior Employees and
Senior Councillors for the year to 31 March 2024 are
shown in the table below, together with the
contribution made by the Council to each individual’s
pension during the year. 
Any senior employees and councillors omitted from the
following tables are not members of the Local
Government Pension Scheme (LGPS).

Page 32

29 
Annual Accounts 2023/24
2023/24 2022/23 Pension Lump
Sum
Pension Lump
Sum
£ £ £000 £000 £000 £000
Alan Russell Chief Executive 32,403 30,560 80 101 11 6
Mary Crearie Director of Communities and
Housing Services until 2 April
2023
548 24,923 65 86 2 3
Alastair
MacArthur
Director of Finance and
Resources
26,423 24,167 62 78 9 6
Gordon McNeil
Director of Environment,
Housing & Infrastructure until
23 May 2023 then Director of
Environment, Housing &
Infrastructure from 24 May
2023
26,426 24,923 50 36 8 1
Steven Quinn Director of Children's Services
until 11 August 2023 9,941 24,923 29 0 6 0
Janie O'Neil Director of Children's Services
from 04 December 2023 7,913 0 n/a n/a n/a n/a
103,654 129,496 286 301 36 16Total
Senior Employees
Name Post held
In-year pension
contributions by
Renfrewshire
Council
Accrued pension
benefits as at 31
March 2024
Change in accrued
pension benefits
since 31 March
2023
2023/24 2022/23 Pension Lump
Sum
Pension Lump
Sum
£ £ £000 £000 £000 £000
Victoria Hollows Chief Executive, OneRen 22,290 21,022 41 48 0 0
22,290 21,022 41 48 0 0
Senior Employees of Subsidiary Bodies
Name Post held
In-year pension
contributions by
Renfrewshire
Leisure
Accrued pension
benefits as at 31
March 2024
Change in accrued
pension benefits
since 31 March
2023
Total

Page 33

30 
Annual Accounts 2023/24
The following table reports on in-year pension contributions relating to senior councillor positions only. Pension benefits
shown relate to those that the individual has accrued as a consequence of their total local government service and not
just their current appointment. 
2023/24 2022/23 Pension Lump
Sum
Pension Lump
Sum
£ £ £000 £000 £000 £000
Iain Nicolson Leader Of the Council 7,737 6,944 13 3 2 0
Cathy McEwan Policy Board Convener/
Regulatory Board Convener
787 2,870 9 0 3 0
Marie McGurk Policy Board Convener 5,571 5,015 5 0 1 0
Jim Paterson Policy Board Convener 5,571 5,015 4 0 0 0
John Shaw Policy Board Convener 5,571 5,015 5 0 1 0
Emma Rodden Policy Board Convener 5,571 3,943 4 0 1 0
Michelle
Campbell
Policy Board Convener 5,571 3,943 4 0 1 0
Andy Steel Regulatory Board
Convener/Policy Board
Convener
5,571 4,918 4 0 1 0
John
McNaughtan
Regulatory Board Convener 4,625 4,180 4 0 1 0
Jennifer Adam Regulatory Board
Convener/Chair/Vice Chair
Integration Joint Board
5,571 4,370 4 0 1 0
Jacqueline
Cameron
Chair/Vice Chair Integration
Joint Board until 5 May 2022
0 642 4 0 0 0
Lisa-Marie
Hughes
Chair, OneRen 5,571 4,393 5 0 1 0
Stephen Burns Regulatory Board Convener 4,625 3,359 3 0 n/a n/a
Andy Doig Regulatory Board Convener 4,625 3,359 3 0 n/a n/a
Eddie Devine Leader of largest opposition
group until 5 May 2022
0 642 8 1 0 0
Neill Graham Leader of 2nd largest
opposition group until 5 May
2022
0 642 2 0 0 0
Iain McMillan Leader of opposition group
from 19 May 2022
4,625 3,989 1 0 1 0
Total 71,592 63,239 82 4 14 0
Name Post held
In-year pension
contributions by
Renfrewshire Council
Accrued pension
benefits as at 31
March 2024
Change in accrued
pension benefits
since 31 March 2023
Note: Councillor McEwan left the pension scheme in May 2023.

Page 34

31 
Annual Accounts 2023/24
6. Councillors’ remuneration
The Council paid the following amounts to its elected members (councillors) during the year.
2022/23 2023/24
£ £
948,984 Salaries 987,073
2,129 Travel costs – reimbursed 1,915
4,480 Travel costs – paid directly by the Council 5,971
200 Subsistence expenses - accommodation 0
0 Training and Conferences 1,802
4,649 Telephone and information technology expenses – paid directly by the Council 2,870
960,442 Total 999,631 
The public record of members' salaries, allowances and expenses for 2023/24 is available for inspection on the Register
of Councillors’ Interests page of the Council’s website and navigating to: Your Council>Councillors> Record of councillor
salaries, allowances, expenses and training register. 
7. Remuneration of Employees 
The following table gives a statement of the number of employees whose remuneration, excluding pension
contributions, was in excess of £50,000 during 2023/24, in bands of £5,000; and also details of the number of those
employees highlighted who left the employment of the Council during 2023/24. This information includes those senior
employees who are subject to the fuller disclosure requirements in the tables above.  Note that leavers may be included
due to retirement or redundancy costs.  Bands with nil employees for both years are not shown. 
Teachers Non-teachers Total  Remuneration band Teachers Non-teachers Total
92 43 135 £50,000 to £54,999 113 116 229
131 80 211 £55,000 to £59,999 85 60 145
96 18 114 £60,000 to £64,999 116 58 174
64 11 75 £65,000 to £69,999 67 24 91
20 20 40 £70,000 to £74,999 52 30 82
9 2 11 £75,000 to £79,999 10 6 16
5 7 12 £80,000 to £84,999 4 10 14
4 6 10 £85,000 to £89,999 2 5 7
1 1 2 £90,000 to £94,999 8 5 13
2 10 12 £95,000 to £99,999 1 4 5
0 1 1 £100,000 to £104,999 2 4 6
0 3 3 £105,000 to £109,999 0 3 3
0 0 0 £110,000 to £114,999 0 1 1
0 0 0 £115,000 to £119,999 0 4 4
0 3 3 £125,000 to £129,999 0 0 0
0 0 0 £135,000 to £139,999 0 2 2
0 1 1 £155,000 to £159,999 0 1 1
424 206 630 460 333 793
2022/23 2023/24
Of the staff noted above, 26 left during the year and their termination payments are included in the above analysis;
however, they would have been included as an over £50k earner in a normal year (five in 2022/23).

Page 35

32 
Annual Accounts 2023/24
8. Exit Packages 
The Council has agreed a number of exit packages in 2023/24 as detailed in the table below. The exit packages agreed
were all on a voluntary basis; there were no compulsory redundancies. The Council only agrees exit packages where they
are consistent with wider workforce planning and service delivery objectives; and where the savings accruing from an
individual ceasing employment with the Council are sufficient to pay back the costs of the exit package within an
acceptable period. The assessment of the payback period takes account of the total costs of the exit package. 
The total exit package costs in the table below include redundancy, pension strain and compensatory lump sum
payments; and also, the notional capitalised costs of compensatory added years. These notional costs are not based on
actual costs, but are the estimated present value of projected costs over the lifetime of the individuals in receipt of the
exit package, based on the following assumptions:
2023/24 2022/23
Future Life expectancy at age 65 – males 20.6 years 20.5 years
Future Life expectancy at age 65 – females 24.2 years 24.2 years
Pension increase rate 2.80% 2.95%
Discount Rate 4.80% 4.75% 
Value Value
£m £m
£0 - £20,000 2 0.024 4 0.065
£20,001 - £40,000 4 0.111 5 0.112
£40,001 - £60,000 1 0.055 2 0.107
£60,001 - £80,000 3 0.204 6 0.420
£80,001 - £100,000 2 0.187 4 0.351
£100,001 - £150,000 2 0.230 17 2.082
£150,001 - £200,000 2 0.318 11 1.808
£200,001 - £250,000 2 0.411 3 0.604
£300,001 - £350,000 2 0.621 3 0.989
Total 20 2.161 55 6.538
Exit Package Cost
2023/24 2022/23
Number of
Employees
Number of
Employees

Page 36

33 
Annual Accounts 2023/24
Trade Union Facility Time 
Renfrewshire Council recognises that it is to the mutual benefit of the Council and its employees that employees are
represented by Trade Unions.  The Council is committed to the principle of collective bargaining at both national and
local level.  The Council recognises the key role of Trade Unions in promoting and developing good employee relations
and health and safety practices. 
The Trade Union (Facility Time Publication Requirements) Regulations 2017 requires public sector employers to publish
information relating to facility time taken by union representatives. 
29 Total cost of facility time £273,142
Total pay bill £351,322,677
FTE employee number 28.03 Percentage of the total pay bill spent on
facility time
0.08%
Number of representatives % time
24                                                                        1% - 50% 39.82%
3                                                                           51% - 99%
2                                                                           100%
Percentage of time spent on facility time
Trade Union (TU) representative
Number of employees who were relevant
union officials during the period
Paid Trade Union activities
Percentage of pay bill spent on facility time
Time spent on paid TU activities as a
percentage of total paid facility time
hours  
Cllr Iain Nicolson Alan Russell
Leader of the Council Chief Executive

Page 37

34 
Annual Accounts 2023/24
Independent auditor’s report to the members of Renfrewshire Council and
the Accounts Commission 
Reporting on the audit of financial statements 
Opinion on financial statements
We certify that we have audited the financial statements in the annual accounts of Renfrewshire Council and its group
for the year ended 31 March 2024 under Part VII of the Local Government (Scotland) Act 1973. The financial statements
comprise the group and council council-only Comprehensive Income and Expenditure Statements, Movement in Reserves
Statements, Balance Sheets and Cash Flow Statements, the council-only Housing Revenue Account Income and
Expenditure Statement, the Movement on the Housing Revenue Account Statement, the Council Tax Income Account,
the Non-Domestic Rate Income Account, the Common Good Income and Expenditure Statement, the Common Good
Funds Balance Sheet and notes to the financial statements, including material accounting policy information. The
financial reporting framework that has been applied in their preparation is applicable law and UK adopted international
accounting standards, as interpreted and adapted by the Code of Practice on Local Authority Accounting in the United
Kingdom 2023/24 (the 2023/24 Code). 
In our opinion the accompanying financial statements: 
• give a true and fair view of the state of affairs of the Council and its group as at 31 March 2024 and of the
income and expenditure of the Council and its group for the year ended;
• have been properly prepared in accordance with UK adopted international accounting standards, as
interpreted and adapted by the 2023/24 Code; and
• have been prepared in accordance with the requirements of the Local Government (Scotland) Regulations
2014, and the Local Government in Scotland Act 2003. 
Basis for Opinion
We conducted our audit in accordance with applicable law and International Standards on Auditing (UK) (ISAs (UK)), as
required by the Code of Audit Practice approved by the Accounts Commission for Scotland. Our responsibilities under
those standards are further described in the auditor’s responsibilities for the audit of the financial statements section of
our report. We were appointed by the Accounts Commission on 18 May 2022. Our period of appointment is five years,
covering 2022/23 to 2026/27. We are independent of the Council and its group in accordance with the ethical
requirements that are relevant to our audit of the financial statements in the UK including the Financial Reporting
Council’s Ethical Standard, and we have fulfilled our other ethical responsibilities in accordance with these requirements.
Non-audit services prohibited by the Ethical Standard were not provided to the Council. We believe that the audit
evidence we have obtained is sufficient and appropriate to provide a basis for our opinion. 
Conclusions relating to going concern basis of accounting
We have concluded that the use of the going concern basis of accounting in the preparation of the financial statements is
appropriate. 
Based on the work we have performed, we have not identified any material uncertainties relating to events or conditions
that, individually or collectively, may cast significant doubt on the ability of the Council and its group to continue to adopt

Page 38

35 
Annual Accounts 2023/24
the going concern basis of accounting for a period of at least twelve months from when the financial statements are
authorised for issue. 
These conclusions are not intended to, nor do they, provide assurance on the current or future financial sustainability of
the Council and its group. However, we report on the Council’s arrangements for financial sustainability in a separate
Annual Audit Report available from the Audit Scotland website. 
Risks of material misstatement
We report in our Annual Audit Report the most significant assessed risks of material misstatement that we identified and
our judgements thereon. 
Responsibilities of the Director of Finance and Resources and Audit, Risk and Scrutiny Board for the financial
statements
As explained more fully in the Statement of Responsibilities, the Director of Finance and Resources is responsible for the
preparation of financial statements that give a true and fair view in accordance with the financial reporting framework,
and for such internal control as the Director of Finance and Resources determines is necessary to enable the preparation
of financial statements that are free from material misstatement, whether due to fraud or error. 
In preparing the financial statements, the Director of Finance and Resources is responsible for assessing the ability of the
Council and its group to continue as a going concern, disclosing, as applicable, matters related to going concern and using
the going concern basis of accounting unless there is an intention to discontinue the operations of the Council and its
group. 
The Council is responsible for overseeing the financial reporting process. 
Auditor’s responsibilities for the audit of the financial statements
Our objectives are to obtain reasonable assurance about whether the financial statements as a whole are free from
material misstatement, whether due to fraud or error, and to issue an auditor’s report that includes our opinion.
Reasonable assurance is a high level of assurance, but is not a guarantee that an audit conducted in accordance with ISAs
(UK) will always detect a material misstatement when it exists. Misstatements can arise from fraud or error and are
considered material if, individually or in the aggregate, they could reasonably be expected to influence the decisions of
users taken on the basis of these financial statements. 
Irregularities, including fraud, are instances of non-compliance with laws and regulations. We design procedures in line
with our responsibilities outlined above to detect material misstatements in respect of irregularities, including fraud.
Procedures include: 
• using our understanding of the local government sector to identify that the Local Government (Scotland) Act
1973, The Local Authority Accounts (Scotland) Regulations 2014, and the Local Government in Scotland Act
2003 are significant in the context of the Council and its group;
• inquiring of the Director of Finance and Resources as to other laws or regulations that may be expected to
have a fundamental effect on the operations of the Council and its group;
• discussions among our audit team on the susceptibility of the financial statements to material misstatement,
including how fraud might occur; and

Page 39

36 
Annual Accounts 2023/24
• considering whether the audit team collectively has the appropriate competence and capabilities to identify
or recognise non-compliance with laws and regulations. 
The extent to which our procedures are capable of detecting irregularities, including fraud, is affected by the inherent
difficulty in detecting irregularities, the effectiveness of the Council’s controls, and the nature, timing and extent of the
audit procedures performed. 
Irregularities that result from fraud are inherently more difficult to detect than irregularities that result from error as
fraud may involve collusion, intentional omissions, misrepresentations, or the override of internal control. The capability
of the audit to detect fraud and other irregularities depends on factors such as the skilfulness of the perpetrator, the
frequency and extent of manipulation, the degree of collusion involved, the relative size of individual amounts
manipulated, and the seniority of those individuals involved. 
A further description of the auditor’s responsibilities for the audit of the financial statements is located on the Financial
Reporting Council's website www.frc.org.uk/auditorsresponsibilities. This description forms part of our auditor’s report. 
Reporting on other requirements 
Opinion prescribed by the Accounts Commission on the audited parts of the Remuneration Report
We have audited the parts of the Remuneration Report described as audited. In our opinion, the audited parts of the
Remuneration Report have been properly prepared in accordance with The Local Authority Accounts (Scotland)
Regulations 2014. 
Other information 
The Director of Finance and Resources is responsible for the other information in the annual accounts. The other
information comprises the Management Commentary, Annual Governance Statement, Statement of Responsibilities and
the unaudited parts of the Remuneration Report. 
Our responsibility is to read all the other information and, in doing so, consider whether the other information is
materially inconsistent with the financial statements, or our knowledge obtained in the course of the audit or otherwise
appears to be materially misstated. If we identify such material inconsistencies or apparent material misstatements, we
are required to determine whether this gives rise to a material misstatement in the financial statements themselves. If,
based on the work we have performed, we conclude that there is a material misstatement of this other information, we
are required to report that fact. We have nothing to report in this regard. 
Our opinion on the financial statements does not cover the other information and we do not express any form of
assurance conclusion thereon except on the Management Commentary and Annual Governance Statement to the extent
explicitly stated in the following opinions prescribed by the Accounts Commission. 
Opinions prescribed by the Accounts Commission on the Management Commentary and Annual Governance
Statement
In our opinion, based on the work undertaken in the course of the audit:

Page 40

37 
Annual Accounts 2023/24
• the information given in the Management Commentary for the financial year for which the financial
statements are prepared is consistent with the financial statements and that report has been prepared in
accordance with statutory guidance issued under the Local Government in Scotland Act 2003; and 
• the information given in the Annual Governance Statement for the financial year for which the financial
statements are prepared is consistent with the financial statements and that report has been prepared in
accordance with the Delivering Good Governance in Local Government: Framework (2016). 
Matters on which we are required to report by exception
We are required by the Accounts Commission to report to you if, in our opinion: 
• adequate accounting records have not been kept; or 
• the financial statements and the audited parts of the Remuneration Report are not in agreement with the
accounting records; or 
• we have not received all the information and explanations we require for our audit. 
We have nothing to report in respect of these matters. 
Conclusions on wider scope responsibilities
In addition to our responsibilities for the annual accounts, our conclusions on the wider scope responsibilities specified in
the Code of Audit Practice, including those in respect of Best Value, are set out in our Annual Audit Report. 
Use of our report
This report is made solely to the parties to whom it is addressed in accordance with Part VII of the Local Government
(Scotland) Act 1973 and for no other purpose. In accordance with paragraph 108 of the Code of Audit Practice, we do not
undertake to have responsibilities to members or officers, in their individual capacities, or to third parties. 
Gary Devlin (for and on behalf of Azets Audit Services)
Quay 2
139 Fountainbridge
Edinburgh
EH3 9QG 
Date: 24 October 2024

Page 41

38 
Annual Accounts 2023/24
Comprehensive Income and Expenditure Statement
This statement shows the accounting cost of providing services and managing the Council during the year. It includes, on
an accruals basis, all of the Council’s day-to-day expenses and related income. It also includes transactions measuring the
value of non-current assets actually consumed during the year and the real projected value of retirement benefits earned
by employees during the year. The statement shows the accounting cost in accordance with generally accepted
accounting practices, rather than the cost according to the statutory regulations that specify the net expenditure that
Councils need to take into account when setting the annual Council Tax charge. The required adjustments between
accounting basis and funding basis under regulations are shown in the Movement in Reserves Statement.
Gross
expenditure
Gross
income
Net
expenditure Note
Gross
expenditure
Gross
income
Net
expenditure
£m £m £m £m £m £m
294.465 (38.357) 256.108 298.501 (39.097) 259.404
174.401 (63.762) 110.639 Environment, Housing and
Infrastructure 251.324 (142.398) 108.926
109.077 (48.963) 60.114 Finance and Resources 105.680 (59.449) 46.231
37.895 (9.097) 28.798 49.507 (12.629) 36.878
17.692 (14.653) 3.039 Miscellaneous Services 19.641 (13.728) 5.913
260.152 (161.744) 98.408 Adult Services 144.335 (44.290) 100.045
893.682 (336.576) 557.106 868.988 (311.591) 557.397
0.103 0.000 0.103 (Gain)/Loss on the disposal of
non-current assets
0.000 (0.302) (0.302)
24.322 (6.646) 17.676 Financing and investment
income and expenditure
2 21.333 (16.863) 4.470
0.000 (505.934) (505.934) Taxation and non-specific
grant income
3 0.000 (513.914) (513.914)
918.107 (849.156) 68.951 890.321 (842.670) 47.651
(104.500) 8 (33.187)
0.469 8 (0.030)
(196.368) 28 185.455
(300.399) Other comprehensive (income) and expenditure 152.238
(231.448) Total comprehensive (income) and expenditure 199.889
(Surplus)/Deficit on the revaluation of non-current
assets
(Surplus)/Deficit from investments in equity
instruments designated as Fair Value through
Other Comprehensive Income
Actuarial (gain)/loss on pension assets and
liabilities
2022/23 (restated) 2023/24
Children's Services
Chief Executive's Service
Deficit/(Surplus) on the
Provision of Services
Cost of Services
Figures shown in brackets represent income or gains and figures without brackets represent expenditure or losses.
During the year the Council restructured, with services in Communities and Housing moving to Chief Executive’s Service
(Community Learning and Development) and Environment and Infrastructure (Housing and Public Protection), now called
Environment, Housing and Infrastructure. There is no resulting change to the 2022/23 Deficit on the Provision of
Services, or Total Comprehensive Income.

Page 42

39 
Annual Accounts 2023/24
Movement in Reserves Statement
This statement shows the movement in the year on the different reserves held by the Council, analysed into usable
reserves (those reserves that can be applied to fund expenditure or to reduce local taxation) and unusable reserves. The
surplus or deficit on the provision of services line shows the true economic cost of providing the Council’s services, more
details of which are shown in the CIES. These are different from the statutory amounts required to be charged to the
General Fund Balance and the Housing Revenue Account for Council Tax-setting and dwellings rent-setting purposes. The
net increase or (decrease) before transfers to other statutory reserves line shows the statutory General Fund Balance
and the Housing Revenue Account Balance before any discretionary transfers to or from the other statutory reserves of
the Council.
2023/24
General
Fund
Balance
Housing
Revenue
Account
Revenue
statutory
funds
Capital
Funds
Total
Usable
Reserves
Unusable
Reserves
Total
reserves
Note £m £m £m £m £m £m £m
Balance at 1 April 2023 127.391 6.497 3.095 99.068 236.051 1,488.674 1,724.725
Movement in reserves during the year
(31.647) (16.004) 0.000 0.000 (47.651) (152.238) (199.889)
21.356 14.832 0.000 0.000 36.188 (36.188) 0.000
Transfers to / (from) other
statutory reserves
7 (0.333) 0.000 0.333 0.000 0.000 0.000 0.000
Adjustment for Service
Concession Arrangements
1.597 0.000 0.000 0.000 1.597 (1.597) 0.000
Adjustments between
accounting basis and
funding basis under
regulations
6 (0.746) 0.839 0.000 (4.061) (3.968) 3.968 0.000
(9.773) (0.333) 0.333 (4.061) (13.834) (186.055) (199.889)
Balance at 31 March 2024 117.618 6.164 3.428 95.007 222.217 1,302.619 1,524.836
Increase / (Decrease) in year
Total Comprehensive Income and
Expenditure
Adjustments to Usable Reserves
permitted by accounting standards
Comparative movements in
2022/23 (restated)
General
Fund
Balance
Housing
Revenue
Account
Revenue
statutory
funds
Capital
Funds
Total
usable
reserves
Unusable
reserves
Total
reserves
Note £m £m £m £m £m £m £m
Balance at 1 April 2022 104.667 6.497 2.974 100.319 214.457 1,278.820 1,493.277
Movement in reserves during the year
(50.865) (18.086) 0.000 0.000 (68.951) 300.399 231.448
25.394 11.784 0.000 0.000 37.178 (37.178) 0.000
Transfers to / (from) other
statutory reserves
7 (0.121) 0.000 0.121 0.000 0.000 0.000 0.000
Adjustment for Service
Concession Arrangements
27.601 0.000 0.000 0.000 27.601 (27.601) 0.000
Adjustments between
accounting basis and
funding basis under
regulations
6 20.715 6.302 0.000 (1.251) 25.766 (25.766) 0.000
22.724 0.000 0.121 (1.251) 21.594 209.854 231.448
Balance at 31 March 2023 127.391 6.497 3.095 99.068 236.051 1,488.674 1,724.725
Increase / (Decrease) in year
Total Comprehensive Income and
Expenditure
Adjustments to Usable Reserves
permitted by accounting standards

Page 43

40 
Annual Accounts 2023/24
Balance Sheet
The balance sheet shows the value as at 31 March 2024 of the assets and liabilities recognised by the Council. The net
assets of the Council are matched by the reserves held by the Council. Reserves are reported in two categories. The first
category comprises usable reserves, which are reserves that the Council may use to provide services, subject to the need
to maintain a prudent level of reserves and any statutory limitations on their use (for example the Capital Receipts
Reserve, which may only be used to fund capital expenditure or to repay debt). The second category of reserves
comprises those that the Council is not able to use to provide services. This category includes reserves that hold
unrealised gains and losses in the value of assets (for example the Revaluation Reserve), where amounts would only
become available to provide services if the assets are sold, and reserves that hold differences shown as ‘adjustments
between accounting basis and funding basis under regulations’ in the Movement in Reserves Statement.
As at 31
March 2023
(restated)
As at 31
March 2024
£m Note £m
1,797.350 Property, plant and equipment 9 1,858.221
44.186 Heritage assets 10 44.186
1.593 Investment property 11 0.000
2.524 Intangible assets 13 1.724
4.157 Long-term investments 22 4.321
2.582 Long-term debtors 19 2.365
102.398 Other long-term assets 28 0.000
1,954.790 1,910.817
0.100 Assets held for sale 12 0.100
166.751 Short-term investments 22 67.755
1.314 Inventories 17 1.287
67.422 Short-term debtors 19 66.354
11.632 Cash and cash equivalents 18 29.461
247.219 164.957
(93.653) Short-term borrowing 22 (65.492)
(89.147) Short-term creditors 20 (83.332)
(0.252) Short-term provisions 21 (0.721)
(183.052) (149.545)
(65.690) Long-term creditors 20 (63.352)
(4.942) Long-term provisions 21 (4.630)
(223.600) Long-term borrowing 22 (258.931)
0.000 Other long-term liabilities 28 (74.480)
(294.232) (401.393)
1,724.725 1,524.836 Alastair MacArthur
(236.051) Usable reserves 7 (222.219)
(1,488.674) Unusable reserves 8 (1,302.617)
(1,724.725) (1,524.836)Total reserves
Long-term assets
Current assets
Current liabilities
Long-term liabilities
Net assets
Director of Finance
and Resources
The unaudited accounts were issued on 27 June 2024 and the audited accounts were authorised for issue on 24 October
2024.

Page 44

41 
Annual Accounts 2023/24
Cashflow Statement
This statement shows the changes in cash and cash equivalents of the Council during the year. It shows how the Council
generates and uses cash and cash equivalents by classifying cash flows as operating, investing and financing activities. The
amount of net cash flows arising from operating activities is a key indicator of the extent to which the operations of the
Council are funded by way of taxation and grant income or from the recipients of services provided by the Council. Investing
activities represent the extent to which cash outflows have been made for resources that are intended to contribute to
the Council’s future service delivery. Cash flows arising from financing activities are useful in predicting claims on future
cash flows by providers of capital (that is, borrowing) to the Council.
2022/23 2023/24
£m £m
(68.951) Net surplus/(deficit) on the provision of services (47.651)
Adjustment for non-cash movements:
51.918 Depreciation, amortisation, impairment and revaluations 97.867
18.982 Increase/(decrease) in creditors (1.423)
14.628 (Increase)/decrease in debtors 1.285
(0.282) (Increase)/decrease in inventories 0.027
38.749 Pension (liability)/asset (8.576)
0.610 Carrying amount of non-current assets sold 1.531
(0.163) Other non-cash items charged to the net surplus or deficit on the provision of services 0.157
(44.807) Adjustments for items included in the net surplus or deficit on the provision of services
that are investing and financing activities
(30.658)
10.684 Net cash flows from operating activities 12.559
Net cash flows from investing activities :
(87.082) Purchase of property, plant and equipment, investment property and intangible assets (128.149)
(1.697) Proceeds from the sale of property, plant and equipment, investment property and
intangible assets
(1.832)
22.188 Proceeds from short-term and long-term investments 98.862
46.504 Other receipts from investing activities 32.490
Net cash flows from financing activities
(3.220) Cash payments for the reduction of the outstanding liability relating to finance leases
and on-balance sheet PFI /PPP contracts
(3.271)
5.438 Repayment of short-term and long-term borrowing 7.170
(7.185) Net increase/(decrease) in cash and cash equivalents 17.829
18.817 Cash and cash equivalents at the beginning of the reporting period 11.632
11.632 Cash and cash equivalents at the end of the reporting period 29.461
The Net cash flow from operating activities above includes the following elements of interest paid and received:
2022/23 2023/24
£m £m
(6.646) Interest received (16.863)
11.660 Interest paid 11.347
4.923 Interest element of finance lease and PPP payments 4.976
9.937 (0.540)
Interest Paid and Received

Page 45

42 
Annual Accounts 2023/24
Note 1: Expenditure and Funding Analysis
The Expenditure and Funding Analysis shows how annual expenditure is used and funded from resources (government
grants, rents, Council Tax and non-domestic rates) by the Council in comparison with those resources consumed or
earned by the Council in accordance with generally accepted accounting practices.  It also shows how this expenditure is
allocated for decision making purposes between the Council’s service departments.  Income and expenditure accounted
for under generally accepted account practices is presented more fully in the CIES.
2023/24
Net Expenditure
chargeable to the
General Fund and
HRA
Adjustments
between Funding
and Accounting
basis
Depreciation
charged to
Revaluation
Reserve
Net
Expenditure
in the CIES
£m £m £m £m
Children's Services 252.456 (9.362) 16.310 259.404
Environment, Housing and Infrastructure 74.560 18.753 15.613 108.926
Finance & Resources 48.972 (4.796) 2.055 46.231
Chief Executive's Service 28.749 5.791 2.000 36.878
Miscellaneous Services 14.373 (8.670) 0.210 5.913
Adult Services 98.765 1.280 0.000 100.045
Net cost of services 517.875 2.996 36.188 557.397
Other income and expenditure (507.771) (1.975) 0.000 (509.746)
(Surplus) / Deficit 10.104 1.021 36.188 47.651
Opening General Fund and HRA balance (133.888)
Less (Surplus) / Deficit in the year 10.104
Closing General Fund and HRA at 31
March 2024 (123.784)
2023/24 Adjustments
for capital
purposes
Net change
for the
pensions
adjustments
Other
differences
Total
Adjustments
£m £m £m £m
Children's Services 17.796 (0.830) (26.328) (9.362)
Environment, Housing and Infrastructure 17.542 (0.518) 1.729 18.753
Finance & Resources 1.846 (0.500) (6.142) (4.796)
Chief Executive's Service 5.206 (0.178) 0.763 5.791
Miscellaneous Services (0.433) 2.286 (10.523) (8.670)
Adult Services 0.003 (0.475) 1.752 1.280
Net cost of services 41.960 (0.215) (38.749) 2.996
(32.792) (8.361) 39.178 (1.975)
Total adjustments between accounting basis and
funding basis 9.168 (8.576) 0.429 1.021
• Adjustments for capital purposes: adds in depreciation, impairment and revaluation gains and losses to the service
net expenditure including income on the disposal of assets and the amounts written off for those assets and the
statutory charges for capital financing and capital grants which are not chargeable under generally accepted
accounting practices.
• Net change for the pensions adjustments: removes employer pension contributions as allowed by statute and
replaces with the current and past service costs within the IAS 19 employee benefits pension related expenditure and
income.  The net interest on the defined benefit liability is also included as charged to the CIES.

Page 46

43 
Annual Accounts 2023/24
• Other differences: any other differences between those amounts debited or credited to the CIES and amounts
payable or receivable to be recognised under statute, including those primarily involved in the financial instruments
adjustment account, the employee statutory adjustment account and other statutory funds.  Any other non-statutory
adjustments would also be included here. 
2022/23
Net Expenditure
chargeable to the
General Fund and
HRA
Adjustments
between Funding
and Accounting
basis
Depreciation
charged to
Revaluation
Reserve
Net
Expenditure
in the CIES
£m £m £m £m
Children's Services 233.285 2.433 20.390 256.108
Communities and Housing Services 10.897 (12.289) 11.799 10.407
Environment & Infrastructure 61.470 38.013 0.749 100.232
Finance & Resources 43.686 14.853 1.575 60.114
Chief Executive's Service 27.605 (1.269) 2.462 28.798
Miscellaneous Services 20.795 (17.959) 0.203 3.039
Adult Services 93.580 4.828 0.000 98.408
Net cost of services 491.318 28.610 37.178 557.106
Other income and expenditure (486.441) (1.714) 0.000 (488.155)
(Surplus) / Deficit 4.877 26.896 37.178 68.951
Opening General Fund and HRA balance (111.164)
Less (Surplus) / Deficit in the year 4.877
Add other items not charged to the Surplus / (Deficit) (27.601)
Closing General Fund and HRA at 31
March* (133.888)
* For a split of this balance between the General Fund and the HRA, see the Movement in Reserves Statement.
2022/23 Adjustments
for capital
purposes
Net change
for the
pensions
adjustments
Other
differences
Total
Adjustments
£m £m £m £m
Children's Services 18.383 11.212 (26.999) 2.596
Communities and Housing Services 5.936 3.386 (21.609) (12.287)
Environment & Infrastructure 12.990 8.466 16.557 38.013
Finance & Resources 1.969 6.831 6.053 14.853
Chief Executive's Service (2.736) 2.381 (0.914) (1.269)
Miscellaneous Services (0.202) (1.746) (15.037) (16.985)
Adult Services 0.003 6.235 (1.410) 4.828
Net cost of services 36.343 36.765 (43.359) 29.749
Other income and expenditure (46.897) 1.984 42.181 (2.732)
Total adjustments between accounting basis and
funding basis (10.554) 38.749 (1.178) 27.017

Page 47

44 
Annual Accounts 2023/24
Note 2: Financing and investment income & expenditure 
2022/23 2023/24
£m £m
22.338 Interest payable and similar charges 21.333
1.984 Net interest on the net defined benefit liability (8.360)
(6.646) Interest receivable and similar income (8.503)
17.676 Total 4.470 
Note 3: Taxation and non-specific grant income 
2022/23 2023/24
£m £m
(80.713) Income from Council Tax and community charge (95.528)
(108.076) Distribution from the national non-domestic rate pool (131.322)
(270.144) General Revenue Grant from the Scottish Government (254.574)
(47.001) Capital grants and contributions (32.490)
(505.934) Total (513.914) 
Note 4: Expenditure and income analysed by nature 
This note presents the subjective analysis of expenditure and income shown by operational service area in the CIES. 
2022/23 2023/24
£m Note £m
Expenditure
383.749 Employee benefits expenses 369.489
420.837 Other service expenses 401.632
89.096 Depreciation, amortisation, impairment 97.867
24.322 Interest Payments 2 21.333
918.107 Total expenditure 890.321
Income
(336.576) Fees, charges and other service income (311.591)
(6.646) Interest and investment income 2 (16.863)
0.000 Gain on the disposal of assets 9 (0.302)
(188.789) Income from council tax and non-domestic rates 3 (226.850)
(317.145) Government grants and contributions 3 (287.064)
(849.156) Total income (842.670)
68.951 (Surplus) or deficit on the provision of services 47.651

Page 48

45 
Annual Accounts 2023/24
Note 5: Grant income
The Council credited the following grants, contributions and donations direct to services in the CIES during 2023/24.
2022/23 2023/24
£m £m
40.841 Housing benefit 39.996
0.549 Housing benefit and Council Tax administration 0.638
0.687 Discretionary Housing Payment 0.937
0.200 Private sector housing grant 0.600
0.491 Education Maintenance Allowance 0.554
0.061 Gaelic Education 0.050
4.663 Pupil Equity Fund 4.663
18.716 Early Years Expansion 18.430
7.772 Other Education 6.833
3.203 Children's Services 3.203
12.254 Adult Services 12.257
3.406 Employability 4.809
3.415 Other grants 8.040
96.258 Total 101.010

Page 49

46 
Annual Accounts 2023/24
Note 6: Adjustment between accounting basis and funding basis under
regulations
This note details the adjustments that are made to the total comprehensive income and expenditure recognised by the
Council in the year in accordance with proper accounting practice to the resources that are specified by statutory
provisions as being available to the Council to meet future capital and revenue expenditure. 
The first table outlines the current year position, and the second table outlines the comparative prior year position. 
General
Fund
Balance
Housing
Revenue
Account
Balance
Capital
Statutory
Funds
Capital
Receipts
Reserve
£m £m £m £m £m
Reversal of items charged to the CIES:
Charges for depreciation and impairment of non-current
assets
(44.202) (16.610) 0.000 0.000 60.812
Amortisation of intangible assets (0.866) 0.000 0.000 0.000 0.866
Capital grants and contributions applied 30.424 2.066 0.000 0.000 (32.490)
Revenue expenditure funded from capital under statute (0.793) 0.000 0.000 0.000 0.793
Amounts of non-current assets written off on disposal or
sale as part of the gain or loss on disposal to the CIES
0.145 0.157 0.000 0.000 (0.302)
Insertion of items not charged to the CIES:
Statutory provision for the repayment of Loans Fund &
Finance Lease  principal 3.708 9.747 0.000 0.000 (13.455)
Capital expenditure charged against the General Fund and
HRA Balances
3.285 3.924 3.395 0.000 (10.604)
Transfer of cash sale proceeds credited as part of the gain
or loss on disposal to the CIES
0.000 0.000 0.000 (1.832) 1.832
Use of the Capital Receipts Reserve to finance new capital
expenditure
0.000 0.000 0.000 2.498 (2.498)
Amount by which finance costs charged to the CIES are
different from finance costs chargeable in the year in
accordance with statutory requirements
0.176 0.077 0.000 0.000 (0.253)
Reversal of items relating to retirement benefits debited or
credited to the CIES
(31.271) 0.050 0.000 0.000 31.221
Employer’s pension contributions  and direct payments to
pensioners payable in the year
40.027 (0.230) 0.000 0.000 (39.797)
Amount by which officer remuneration charged to the CIES
on an accruals basis is different from remuneration
chargeable in the year in accordance with statutory
requirements
0.113 (0.020) 0.000 0.000 (0.093)
Total adjustments 0.746 (0.839) 3.395 0.666 (3.968)
Usable reserves
Unusable
reserves2023/24
Adjustment primarily involving the Employee Statutory Adjustment Account:
Adjustments primarily involving the Pension Reserve:
Adjustment primarily involving the Financial Instruments Adjustment Account:
Adjustments primarily involving the Capital Receipts Reserve:
Adjustments primarily involving the Capital Adjustment Account:

Page 50

47 
Annual Accounts 2023/24
General
Fund
Balance
Housing
Revenue
Account
Capital
Statutory
Funds
Capital
Receipts
Reserve
£m £m £m £m £m
Reversal of items charged to the CIES:
Charges for depreciation and impairment of non-current
assets
(34.956) (16.099) 0.000 0.000 51.055
Amortisation of intangible assets (0.863) 0.000 0.000 0.000 0.863
Capital grants and contributions applied 46.599 0.402 0.000 0.000 (47.001)
Amounts of non-current assets written off on disposal or
sale as part of the gain or loss on disposal to the CIES
0.173 (0.276) 0.000 0.000 0.103
Insertion of items not charged to the CIES:
Statutory provision for the repayment of Loans Fund &
Finance Lease  principal
1.815 11.434 0.000 0.000 (13.249)
Capital expenditure charged against the General Fund and
HRA Balances
2.325 0.000 1.841 0.000 (4.166)
Transfer of cash sale proceeds credited as part of the gain
or loss on disposal to the CIES
0.000 0.000 0.000 (1.697) 1.697
Use of the Capital Receipts Reserve to finance new capital
expenditure
0.000 0.000 0.000 1.107 (1.107)
Amount by which finance costs charged to the CIES are
different from finance costs chargeable in the year in
accordance with statutory requirements
0.323 0.173 0.000 0.000 (0.496)
Reversal of items relating to retirement benefits debited or
credited to the CIES
(74.376) (0.089) 0.000 0.000 74.465
Employer’s pension contributions  and direct payments to
pensioners payable in the year
37.587 (1.871) 0.000 0.000 (35.716)
Amount by which officer remuneration charged to the CIES
on an accruals basis is different from remuneration
chargeable in the year in accordance with statutory
requirements
0.658 0.024 0.000 0.000 (0.682)
Total adjustments (20.715) (6.302) 1.841 (0.590) 25.766
Adjustments primarily involving the Capital Receipts Reserve:
Adjustment primarily involving the Financial Instruments Adjustment Account:
Adjustments primarily involving the Pension Reserve:
Adjustment primarily involving the Employee Statutory Adjustment Account:
Adjustments primarily involving the Capital Adjustment Account:
Usable reserves
Unusable
reserves2022/23
Note 7: Usable reserves 
Usable reserves are those reserves the Council is able to apply to fund expenditure or reduce taxation and comprise both
capital and revenue reserves. Movements in the revenue reserves during the year are outlined in the Movement in
Reserves Statement and a summary is shown in below. 
More information about the Housing Revenue Account can be found on page 98.

Page 51

48 
Annual Accounts 2023/24
As at 31
March 2023
(restated)
As at 31
March 2024
£m £m
(127.391) General Fund Balance (117.620)
(6.497) Housing Revenue Account Balance (6.164)
(8.184) Capital Receipts Reserve (7.518)
(93.979) Other Statutory Funds (90.917)
(236.051) Total (222.219)
Usable Reserves
This note sets out the amounts set aside from the General Fund Balance in statutory funds established under Schedule 3
of the Local Government (Scotland) Act 1975 to provide financing for specific areas of expenditure, and the amounts
transferred back from these funds to meet General Fund expenditure in 2023/24.
Balance
at 1 April
2022
Transfers
out
Transfers
in
Balance
at 31
March
2023
Transfers
out
Transfers
in
Balance
at 31
March
2024
£m £m £m £m £m £m £m
Insurance Fund 2.653 0.000 0.115 2.768 0.000 0.133 2.901
DHN Repair and Renewal Fund 0.000 0.000 0.000 0.000 0.000 0.186 0.186
Reservoir Repair Fund 0.321 0.000 0.006 0.327 0.000 0.014 0.341
Revenue statutory funds 2.974 0.000 0.121 3.095 0.000 0.333 3.428
Education Capital Items Fund 2.269 (0.509) 0.346 2.106 (0.883) 0.231 1.454
Investment Capital Fund 90.456 (2.175) 0.497 88.778 (2.743) 0.000 86.035
Capital statutory funds 92.725 (2.684) 0.843 90.884 (3.626) 0.231 87.489
Total 95.699 (2.684) 0.964 93.979 (3.626) 0.564 90.917
• The Insurance Fund is the funding mechanism for the control of insurable risk and covers the main classes of
insurance. It is earmarked for premiums and self-funded insurance costs.
• The DHN Repair and Renewal Fund is earmarked for future component replacement of the District Heating Network
at the Advanced Manufacturing Innovation District Scotland (AMIDS).
• The Reservoir Repair Fund is funding received from a contractor for repairs in perpetuity to the Thornly Dam.
• The Education Capital Items Fund is earmarked funding for specific schools to be used in future years for planned
purchases of a capital nature, such as computers and information communication technology equipment.
• The Investment Capital Fund represents planned funding earmarked to support the Council’s investment programme
and the wider strategic management of the Council’s associated debt profile.
• In addition to the capital statutory funds above the Capital Receipts Reserve is also a statutory fund. The Capital
Receipts Reserve holds cash receipts from asset sales and is used to fund planned capital expenditure.
Balance
at 1 April
2022
Sale
proceeds
Capital
exp
funded
Balance
at 31
March
2023
Sale
proceeds
Capital
exp
funded
Balance
at 31
March
2024
£m £m £m £m £m £m £m
Capital Receipts Reserve 7.594 1.697 (1.107) 8.184 1.832 (2.498) 7.518

Page 52

49 
Annual Accounts 2023/24
The following note sets out the amounts within the General Fund Balance that the Council has ring-fenced for future
expenditure plans.  The unallocated balance of £10.308m represents 2.0% of the Council’s net annual running costs.
Balance at
1 April
2022
Transfers
out
Transfers
in
Balance at
31 March
2023
Transfers
out
Transfers
in
Balance at
31 March
2024
£m £m £m £m £m £m £m
COVID-19 General Recovery Fund 9.160       (1.780)      (7.380)      -         -         -         -        
COVID-19 Education Recovery Fund 6.328       (0.403)      (5.925)      -         -         -         -        
COVID-19 Recovery Construction
Fund
10.000     (2.735)      (7.265)      -         -         -         -        
Inflation Mitigation 4.990       -         (4.990)      -         -         -         -        
Financial Sustainability Fund -         (6.054)      27.560     21.506     (8.262)      -         13.244    
Social Renewal Plan 1.795       (1.180)      (0.615)      -         -         -         -        
Tackling Poverty 1.402       (0.770)      (0.632)      -         -         -         -        
Fairer Renfrewshire Programme -         (1.584)      6.081       4.497       (1.642)      -         2.855      
Climate Change Action Fund 0.611       (0.256)      (0.355)      -         -         -         -        
Community Empowerment Fund 0.339       (0.038)      (0.301)      -         -         -         -        
Sustainable Communities Fund -         -         0.656       0.656       (0.262)      -         0.394      
PPP Schools Replacement Fund 12.670     -         (12.670)    -         -         -         -        
Loan Charges Flexibility Fund -         -         44.759     44.759     -         4.000       48.759    
Alcohol and Drugs Commission 1.804       (0.601)      0.100       1.303       (0.536)      -         0.767      
British Sign Language 0.001       (0.001)      -         -         -         -         -        
City Deal 1.750       (0.237)      0.106       1.619       (0.716)      1.000       1.903      
Civil Contingencies Shared Service -         -         0.114       0.114       (0.026)      0.038       0.126      
Culture Bid Legacy 3.567       (0.869)      0.395       3.093       (1.084)      -         2.009      
Development – Paisley Town Centre 1.057       -         -         1.057       (0.538)      -         0.519      
Digital Infrastructure 2.389       -         0.033       2.422       (0.981)      -         1.441      
Discretionary business grants 0.392       -         -         0.392       (0.392)      -         -        
Early Years Change Fund 1.900       -         1.000       2.900       (1.112)      0.312       2.100      
Employability 9.481       (0.171)      -         9.310       (1.355)      2.635       10.590    
Environment & Infrastructure 1.015       (0.500)      0.045       0.560       (0.510)      0.740       0.790      
Fly Tipping Enforcement -         (0.208)      0.450       0.242       (0.242)      -         -        
Local Authority Economic Recovery
Fund
-         0.305       -         0.305       (0.800)      0.595       0.100      
Leisure: Inclusive Play Facility 0.050       (0.043)      -         0.007       -         -         0.007      
Local Heat and Energy Efficiency
Strategy
-         -         0.075       0.075       (0.075)      -         -        
Memorial Headstone Safety 0.625       (0.511)      -         0.114       (0.114)      -         -        
Paisley Town Centre Heritage Asset
Strategy
1.254       (0.369)      -         0.885       (0.551)      -         0.334      
Private Sector Housing Grant 2.206       (0.167)      -         2.039       (0.231)      0.500       2.308      
Pupil Equity Fund 1.259       (0.599)      0.370       1.030       (0.506)      -         0.524      
Rapid Rehousing Transition Plan -         (0.114)      0.154       0.040       (0.040)      -         -
Resettlement and Asylum Fund -         -         0.585       0.585       (0.398)      1.242       1.429      
School Music Participation 0.285       (0.125)      0.062       0.222       -         0.054       0.276      
Service Modernisation & Reform 11.059     (0.225)      0.185       11.019     (1.331)      0.974       10.662    
Town Centre Public WiFi 0.033       (0.033)      -         (0.000)      -         -
Villages Improvement Fund 0.133       (0.133)      -         (0.000)      -         0.200       0.200      
Welfare Reform 1.033       (0.447)      0.493       1.079       (0.780)      0.700       0.999      
Year-end flexibility: Children's Svc 5.291       (2.645)      2.597       5.243       (1.365)      1.127       5.005      
General Fund: Ring-fenced 93.879 (22.493) 45.687 117.073 (23.849) 14.117 107.341
Unallocated Balance 10.788     (0.470)      -         10.318 (0.039) -         10.279
Total General Fund Balance 104.667 (22.963) 45.687 127.391 (23.888) 14.117 117.620
Ring-fenced elements of the
General Fund Balance

Page 53

50 
Annual Accounts 2023/24
Note 8: Unusable reserves 
Unusable reserves are those reserves that the Council is not able to utilise to provide services, and comprise: 
• Reserves that hold unrealised gains and losses, particularly in relation to the revaluation of property, plant and
equipment and financial instruments, where amounts will only become available to provide services (or limit
resources in the case of losses) once the gains or losses are realised as the assets are disposed of. This category of
reserves comprises the Revaluation Reserve and the Financial Instruments Revaluation Reserve.
• Adjustment accounts that deal with situations where income and expenditure are recognised according to statutory
regulations against the General Fund Balance and the Housing Revenue Account Balance on a different basis from
that expected by generally accepted accounting practices. These adjustment accounts will carry either a debit
balance (showing that the Council is required by statute to fund its expenditure more slowly than accounting
standards would expect) or a credit balance (where the Council has set resources aside under statute earlier than
accounting standards require). The adjustment accounts effectively offset the General Fund Balance and the Housing
Revenue Account Balance to give the Council more or less spending power in the short term than proper accounting
practices would allow. The adjustment accounts comprise the Capital Adjustment Account, the Financial Instruments
Adjustment Account, the Capital Receipts Reserve, the Pension Reserve and the Employee Statutory Adjustment
Account. 
As at 31
March 2023
(restated)
As at 31
March 2024
£m £m
(772.123) Revaluation Reserve (768.193)
(102.399) Pension Reserve 74.480
(631.565) Capital Adjustment Account (625.941)
10.941 Financial Instruments Adjustment Account 10.688
(0.528) Financial Instruments Revaluation Reserve (0.558)
7.000 Employee Statutory Adjustment Account 6.907
(1,488.674) Total Unusable Reserves (1,302.617)
Unusable Reserves
Revaluation Reserve 
The Revaluation Reserve contains the gains made by the Council arising from increases in the value of its non-current
assets. The balance is reduced when assets with accumulated gains are: 
i) revalued downwards or impaired and the gains are lost, 
ii) used in the provision of services and the gains are consumed through depreciation; or 
iii) disposed of and the gains are realised. 
The Revaluation Reserve contains only revaluation gains accumulated since 1 April 2007, which was the date that the
Revaluation Reserve was created. Accumulated gains arising before that date are consolidated into the balance on the
Capital Adjustment Account.

Page 54

51 
Annual Accounts 2023/24
As at 31
March 2023
As at 31
March 2024
£m £m
(705.624) Balance at 1 April (772.123)
(104.500) Upward revaluation of non-current assets (33.185)
37.178 Difference between fair value depreciation and historic cost depreciation 36.188
0.823 Accumulated (gains) / losses on disposal of non-current assets transferred to the
Capital Adjustment Account
0.927
(66.499) Movement in Year 3.930
(772.123) Balance at 31 March (768.193)
Revaluation Reserve
Pension Reserve 
The Pension Reserve absorbs the timing differences arising from the different arrangements for accounting for post-
employment benefits and for funding benefits in accordance with statutory provisions or regulations. The Council
accounts for post-employment benefits in the CIES as the benefits are earned by employees accruing years of service,
updating the liabilities recognised to reflect inflation, changing assumptions and investment returns on any resources set
aside to meet the costs. However, statutory arrangements require benefits earned to be financed as the Council makes
employer’s contributions to pension funds. The debit balance on the Pension Reserve shows a significant shortfall in the
benefits earned by past and current employees and the Council’s share of Strathclyde Pension Fund resources available
to meet them. The statutory arrangements will ensure that funding will have been set aside by the time the benefits
come to be paid. 
As at 31
March 2023
(restated)
As at 31
March 2024
£m £m
55.220 Balance at 1 April (102.399)
(528.066) Actuarial (gains) / losses on pension assets and liabilities 258.948
331.698 Restriction to Asset Ceiling (73.493)
74.465 Reversal of items relating to retirement benefits debited or credited to the surplus
or deficit on the provision of services in the CIES
31.221
(35.716) Employer’s pension contributions payable in the year (39.797)
(102.399) Balance at 31 March 74.480
Pension Reserve
Capital Adjustment Account 
The Capital Adjustment Account absorbs the timing differences arising from the different arrangements for accounting
for the consumption of non-current assets and for financing the acquisition, construction or enhancement of those
assets. The Capital Adjustment Account is debited with the cost of acquisition, construction or enhancement as
depreciation, impairment losses and amortisations are charged to the CIES (with reconciling postings from the
Revaluation Reserve to convert fair value figures to a historical cost basis). 
The Capital Adjustment Account is credited with the amounts set aside by the Council as finance for the costs of
acquisition, construction and enhancement.

Page 55

52 
Annual Accounts 2023/24
The Capital Adjustment Account contains accumulated gains and losses on investment properties and gains recognised
on donated assets that have yet to be consumed by the Council, and also revaluation gains accumulated on property,
plant and equipment before 1 April 2007. The Revaluation Reserve was created to hold such gains arising from 1 April
2007 onwards. 
As at 31
March 2023
As at 31
March 2024
£m £m
(646.538) Balance at 1 April (631.565)
Reversal of items relating to capital expenditure charged to the CIES:
51.055 Charges for depreciation, impairment and revaluation losses of non-current assets 60.812
0.863 Amortisation of intangible assets 0.866
0.000 Revenue expenditure funded from capital under statute 0.793
1.697 Non-current assets sale proceeds 1.832
0.103 (Gain)/Loss on disposal of non-current assets charged to the CIES (0.302)
(0.823) Adjusting amounts written out of the Revaluation Reserve (0.927)
52.895 Net written out amount of non-current assets consumed in the year 63.074
Capital financing applied in the year:
(1.107) Use of the Capital Receipts Reserve to finance new capital expenditure (2.498)
(47.001) Capital grants and contributions credited to the CIES that have been applied to
capital financing
(32.490)
(13.249) Loans Fund and Finance Lease principal repayments (13.455)
(4.166) Capital expenditure charged against the General Fund and Housing Revenue
Account balances
(10.604)
27.601 Adjustment for Service Concession Arrangements 1.597
(37.922) (57.450)
(631.565) Balance at 31 March (625.941)
Capital Adjustment Account
Financial Instruments Adjustment Account 
The Financial Instruments Adjustment Account absorbs the timing differences arising from the different arrangements
for accounting for income and expenses relating to certain financial instruments, and for bearing losses or benefiting
from gains in accordance with statutory provisions [or regulations]. The Council uses the Financial Instruments
Adjustment Account to: 
• Manage premiums incurred on the early repayment of borrowings. Generally accepted accounting practices require
that premiums are debited to the CIES when they are incurred (except where the loan debt being repaid is exchanged
for new loan debt on substantially similar terms). However, statutory arrangements or regulations allow any
premiums that would normally require to be to be taken immediately to the surplus or deficit on the provision of
services, to be amortised to the General Fund Balance over the various periods of time as specified in the
regulations/statutory guidance. Furthermore, statutory arrangements [or regulations] require that any premiums
that were on the Council’s balance sheet at 31 March 2007 be amortised to the General Fund Balance over the
unexpired term that was outstanding on the associated loans when they were redeemed. The Council had various
premiums totalling £17.630m at 31 March 2007 and, under the statutory arrangements, these will be fully amortised
to the General Fund Balance by financial year 2053-2054.
• Manage borrowings that were on the Council’s balance sheet at 31 March 2007 and that have a stepped interest rate
feature. These borrowings comprise four ‘lender option borrower option’ (LOBO) loans for which the interest rate
was fixed for an initial period, and at a pre-agreed later date the interest rate changed. Generally accepted

Page 56

53 
Annual Accounts 2023/24
accounting practices require that interest charges relating to borrowings that have a stepped interest rate feature are
debited to the CIES on the basis of a single effective interest rate (EIR) over the expected life of the loans, rather than
based on the contractual cash outflows of interest. However, statutory arrangements [or regulations] allow such
borrowings that were on the Council’s balance sheet at 31 March 2007 to be charged to the General Fund Balance in
accordance with the accounting treatment prior to 1 April 2007, which did not require the use of the effective
interest rate as the basis for the interest charge.
• Manage ‘soft loans’ that were on the Council’s balance sheet at 31 March 2007. Soft loans are loans advanced by the
Council at nil or below prevailing interest rates. Generally accepted accounting practices require that the discounted
interest rate is recognised as a reduction in the fair value of the loan, with the difference being debited to the CIES as
service expenditure. However, statutory arrangements [or regulations] require that, for soft loans on the Council’s
balance sheet at 31 March 2007, the reduction in value and corresponding charge to be reversed, so that there is no
impact on the General Fund Balance. As at 31 March 2007 interest free loans amounting to £0.156m had been
advanced to employees who had had changes implemented to their pay cycle. These loans are repayable when
employees leave the Council’s employment. 
Financial Instruments Adjustment Account
Refinancing
premiums
and
discounts
Borrowing
on stepped
interest rate
loans
Loans to
third parties
at less than
market rate
Total
£m £m £m £m
Balance at 1 April 2023 10.078 0.845 0.018 10.941
Premiums incurred in previous financial years to be
charged against the General Fund Balance in accordance
with statutory requirements
(0.470) 0.000 0.000 (0.470)
Amount by which finance costs charged to the CIES are
different from finance costs chargeable in the year in
accordance with statutory requirements
0.000 0.221 (0.004) 0.217
Balance at 31 March 2024 9.608 1.066 0.014 10.688 
Financial Instruments Revaluation Reserve
The Financial Instruments Revaluation Reserve contains the gains made by the Council arising from increases in the value
of its investments that are measured at fair value through other comprehensive income.  
The balance is reduced when investments with accumulated gains are:
i) revalued downwards or impaired and the gains are lost; or 
ii) disposed of and the gains are realised.
As at 31
March 2023
As at 31
March 2024
£m £m
(0.997) Balance at 1 April (0.528)
0.469 Downward/(Upward) revaluation of investments (0.030)
(0.528) Balance at 31 March (0.558)
Financial Instruments Revaluation Reserve

Page 57

54 
Annual Accounts 2023/24
Employee Statutory Adjustment Account 
The Employee Statutory Adjustment Account absorbs the differences that would otherwise arise on the General Fund
Balance from accruing for short-term accumulating compensated absences at the end of the financial year. 
As at 31
March 2023
As at 31
March 2024
£m £m
7.682 Balance at 1 April 7.000
(7.682) Settlement or cancellation of accrual made at the end of the prior year (7.000)
7.000 Amounts accrued at the end of the current year 6.907
7.000 Balance at 31 March 6.907
Employee Statutory Adjustment Account
Note 9: Property, Plant and Equipment 
The Code requires that where a component of an asset is replaced, the carrying amount (i.e. net book value) of the old
component shall be derecognised to avoid double counting and the new component is reflected in the carrying amount
of the infrastructure asset. However, due to practical difficulties in applying component accounting for the recognition
and derecognition of replaced components of infrastructure assets, most local authorities have been unable to comply
with the requirement to assess the net book value of the replaced component and have treated the amount of the
replaced component as zero, because the replaced component is considered to have been fully used up at the point that
it is replaced. 
In recognition of this difficulty, the Scottish Government issued a Statutory Override in August 2022. Renfrewshire
Council has elected to apply both of the following provisions: 
• Statutory Override 1: For accounting periods commencing from 1 April 2021 until 31 March 2024 a local authority is
not required to report the gross cost and accumulated depreciation for infrastructure assets.
• Statutory Override 2: For accounting periods commencing from 1 April 2010 until 31 March 2024 the carrying
amount to be derecognised in respect of a replaced part of an infrastructure asset is required to be a nil amount, and
no subsequent adjustment shall be made to the carrying amount of the asset with respect to that part.

Page 58

55 
Annual Accounts 2023/24
Note 9: Property, Plant and Equipment (continued) 
Council
dwellings
Other land
and
buildings
Vehicles,
plant,
furniture and
equipment
Infrastructure
assets
Assets under
construction
Surplus
assets Total
Of which
funded by
PFI
£m £m £m £m £m £m £m £m
Balance sheet net carrying amount at 31 March 2023 714.690 343.150 371.154 222.732 124.526 21.098 1,797.350 127.539
Reclassified (to)/ from Assets Held for Sale 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Other Reclassifications 8.153 35.812 2.612 5.519 (51.856) 1.353 1.593 0.000
Additions 17.184 5.469 14.554 10.393 77.025 0.000 124.625 1.735
Disposals (1.094) (0.035) (0.063) 0.000 0.000 (0.339) (1.531) 0.000
Depreciation (23.823) (10.408) (45.885) (10.608) 0.000 (0.088) (90.812) (9.585)
Revaluation adjustments taken to the Revaluation Reserve 18.798 4.538 8.814 0.000 0.000 1.035 33.185 (10.185)
Revaluation adjustments recognised in the CIES 0.000 (3.504) (2.041) 0.000 0.000 (0.644) (6.189) (1.996)
Balance sheet net carrying amount at 31 March 2024 733.908 375.022 349.145 228.036 149.695 22.415 1,858.221 107.508
Gross carrying amount at 31 March 2024 733.908 398.942 626.536 n/a 149.695 27.551 1,936.632 123.901
Accumulated depreciation at 31 March 2024 0.000 (23.920) (277.391) n/a 0.000 (5.136) (306.447) (16.393)
Infrastructure Assets 0.000 0.000 0.000 228.036 0.000 0.000 228.036 0.000
Balance sheet net carrying amount at 31 March 2024 733.908 375.022 349.145 228.036 149.695 22.415 1,858.221 107.508
Movements in 2023/24

Page 59

56 
Annual Accounts 2023/24
Council
dwellings
Other land
and
buildings
Vehicles,
plant,
furniture and
equipment
Infrastructure
assets
Assets under
construction
Surplus
assets Total
Of which
funded by
PFI
£m £m £m £m £m £m £m £m
Balance sheet net carrying amount at 31 March 2022 618.804 341.319 408.817 214.168 57.786 22.258 1,663.152 135.370
Reclassified (to)/ from Assets Held for Sale 0.000 0.000 0.000 0.000 0.000 0.297 0.297 0.000
Other Reclassifications 6.656 (0.147) 1.966 4.766 (13.177) 0.000 0.064 0.000
Additions 7.414 1.529 16.625 13.538 79.917 0.000 119.023 1.685
Disposals 0.000 (0.227) (0.130) 0.000 0.000 (0.918) (1.275) 0.000
Depreciation (20.627) (9.380) (51.712) (9.740) 0.000 (0.092) (91.551) (9.516)
Revaluation adjustments taken to the Revaluation Reserve 102.701 2.519 (0.939) 0.000 0.000 0.219 104.500 0.000
Revaluation adjustments recognised in the CIES (0.258) 7.537 (3.473) 0.000 0.000 (0.666) 3.140 0.000
Balance sheet net carrying amount at 31 March 2023 714.690 343.150 371.154 222.732 124.526 21.098 1,797.350 127.539
Gross carrying amount at 31 March 2023 714.690 361.314 617.573 n/a 124.526 26.180 1,844.283 139.579
Accumulated depreciation at 31 March 2023 0.000 (18.164) (246.419) n/a 0.000 (5.082) (269.665) (12.040)
Infrastructure Assets 0.000 0.000 0.000 222.732 0.000 0.000 222.732 0.000
Balance sheet net carrying amount at 31 March 2023 714.690 343.150 371.154 222.732 124.526 21.098 1,797.350 127.539
Movements in 2022/23

Page 60

57 
Annual Accounts 2023/24
Note 10: Heritage Assets 
2022/23 2023/24
£m £m
44.186 Balance at 1 April 44.186
0.000 Revaluations to CIES 0.000
0.000 Revaluations to Revaluation
Reserve 0.000
44.186 Balance at 31 March 44.186
Heritage Assets
A valuation of the fair value of the Council’s Heritage
Assets was carried out by an external valuer in 2021/22.
In the five years prior to 2023/24, there were no
acquisitions, donations, or disposals of Heritage Assets. 
The combined collections managed by the Renfrewshire
Arts and Museums Service number in excess of 350,000
objects and it is impractical to undertake a full valuation
of all the items in the collection. The balances above
reflect the valuation of materials examined by the
external valuer during 2021/22. Further detail on the
valuation of each category of asset is outlined in
Accounting Policy K on page 87. 
The details of the valuations of the assets are as follows:
• Archaeology items
• Natural history and science book collections
• Art collection
• Ceramics
• Natural history and Numismatics
• Science and social history collections
• Special collections
• Textiles
• Transport collection
• World cultures
Note 11: Investment properties 
The following items of income and expense have been
accounted for in the ‘Financing and Investment income
and expenditure’ line in the CIES. 
2022/23 2023/24
£m £m
(0.120) Rental income from investment
property
0.000
(0.120) Net Loss / (Gain) 0.000
Investment Properties
There are no restrictions on the Council’s ability to
realise the value inherent in its investment property or
on the Council’s right to the remittance of income and
the proceeds of disposal. The Council has no contractual
obligations to purchase, construct or develop
investment property, nor does it have contractual
obligations in relation to repairs, maintenance or
enhancement. 
The following table summarises the movement in the
fair value of investment properties during the year: 
2022/23 2023/24
£m £m
1.479 Opening balance at 1 April 1.593
0.178 Net gains or (losses) from fair
value adjustments
0.000
(0.064) Transfers from inventories and
property, plant and equipment
(1.593)
1.593 Closing balance at 31 March 0.000
Fair Value of Investment
Properties

Page 61

58 
Annual Accounts 2023/24
Fair Value Hierarchy 
Detail of the authority's investment properties and information about the fair value hierarchy as at 31 March 2024 are as
follows:
Quoted Prices in
active markets
for identical
assets (level 1)
Other significant
observable
inputs
(level 2)
Other significant
unobservable
inputs (level 3)
Fair Value as at
31 March 2024
£m £m £m £m
Commercial Units 0.000 0.000 0.000 0.000
Office Units 0.000 0.000 0.000 0.000
Commercial Sites 0.000 0.000 0.000 0.000
Other 0.000 0.000 0.000 0.000
Total 0.000 0.000 0.000 0.000 
Valuation Techniques used to Determine
Level 2 and 3 Fair Values for Investment
Properties 
Sufficient title and lease information is available in the
respect of Investment Properties. This, coupled with
knowledge of the rent being achieved, or likely to be
achieved, has enabled the market approach to be used
in respect of the fair value measurement of Investment
Properties. 
Market knowledge, through sales evidence of surplus
development sites within Renfrewshire has also been
factored into the fair value measurement. Therefore,
the level of observable inputs is significant, leading to
the properties being categorised at level 2 in the fair
value hierarchy. 
Note 12: Assets held for sale 
The following table summarises the movement in the
fair value of assets held for sale during the year:
2022/23 2023/24
£m £m
0.922 Opening balance at 1 April 0.100
Assets reclassified as held for sale:
(0.297) Surplus Assets 0.000
(0.525) Assets sold 0.000
0.100 Closing balance at 31 March 0.100
Assets Held for Sale
Note 13: Intangible assets 
The Council accounts for purchased software licences as
intangible assets. The cost of the licences is amortised
on a straight-line basis over the expected life of the
licences, which is three to five years for all ICT systems.
Amortisation charges are initially charged to ICT services
and then absorbed as an overhead across all the service
headings in the net expenditure of services.  
The movement on intangible asset balances during the
year is shown in the following table.
2022/23 2023/24
£m £m
Balance at 1 April
6.061 Gross carrying amount 5.861
(2.712) Accumulated amortisation (3.337)
3.349 Net carrying amount at 1
April 2.524
0.038 Additions: purchases 0.066
(0.238) Disposals 0.000
0.238 Disposal amortisation 0.000
(0.863) Amortisation for the year (0.866)
2.524 Net carrying amount at 31
March 1.724
Comprising:
5.861 Gross carrying amount 5.927
(3.337) Accumulated amortisation (4.203)
2.524 Balance at 31 March 1.724
Purchased Software Licences
There are no individual intangible assets that are
material to the financial statements and there are

Page 62

59 
Annual Accounts 2023/24
currently no contractual commitments for the
acquisition of intangible assets. 
Note 14: Capital expenditure and
capital financing 
Capital expenditure involves the creation of assets, the
benefit of which will be available to future Council Tax
and non-domestic rate payers. It is financed from
borrowing and capital income (sales receipts), and so
the cost of the asset is effectively borne over a number
of years. 
The Council’s overall capital investment programme is
sub-divided into two programmes: housing and non-
housing. In 2023/24 total spending on capital projects
was £125.484m (£119.061m in 2022/23) and was within
the overall prudential limits approved by Council. Capital
receipts of £2.498m (£1.107m in 2022/23) were used to
fund spending on capital projects. 
The net capital expenditure for the year of £79.892m
(£66.787m in 2022/23) was financed from external
borrowing, credit arrangements and from cash balances.
The table below shows the total amount of capital
expenditure incurred in the year, including the value of
assets acquired under finance leases and Service
Concession Arrangements. 
Also shown are the resources that have been used to
finance this capital expenditure. Where capital
expenditure is to be financed in future years by charges
to revenue as assets are used by the Council, the
expenditure results in an increase in the Capital
Financing Requirement (CFR), a measure of the capital
expenditure incurred historically by the Council that has
yet to be financed. The movement in the CFR during the
year is also analysed in the table below. 
As at 31
March 2023
As at 31
March 2024
£m £m
360.926 Opening Capital Financing Requirement 442.065
Capital investment:
119.023 Property, plant and equipment 124.625
0.038 Intangible assets 0.066
0.000 Revenue expenditure funded from capital under statute 0.793
Sources of finance:
(1.107) Capital receipts – sale of council assets (2.498)
(47.001) Government grants and other contributions (32.490)
(4.166) Sums set aside from revenue – direct revenue contributions (10.604)
(13.249) Loans Fund/Finance Lease principal repayments (13.455)
27.601 Adjustment for Service Concession Arrangements 1.597
442.065 Closing Capital Financing Requirement 510.099
Explanation of movements in year:
84.357 Increase/(decrease) in underlying need to borrow (unsupported by government
financial assistance) 71.265
(0.114) Reduction in finance leases obligations (0.117)
(3.104) Increase/(decrease) in PPP finance lease creditor (3.114)
81.139 Increase/(Decrease) in Capital Financing Requirement 68.034

Page 63

60 
Annual Accounts 2023/24
At 31 March 2024 the Council had commitments on
capital contracts for non-housing projects of £29.164m
(£89.723m in 2022/23) and for housing projects of
£25.932m (£28.542m in 2022/23). This expenditure will
be funded from a combination of government grants,
external borrowing, income from selling assets and
contributions from revenue budgets. 
Note 15: Service Concession
Arrangements 
The Council entered into a Public Private Partnership on
1 July 2006 for the provision and maintenance of
educational buildings and other facilities. This
agreement provides the Council with replacement
buildings such as primary and secondary schools and
community education premises. The provider is required
to ensure the availability of these buildings to a pre-
agreed standard, with deductions from the fee payable
being made if facilities are unavailable or performance is
below the minimum standard. 
When the agreement ends in 2038, the buildings will be
handed to the Council at nil consideration with a
guarantee of no major maintenance requirements for a
five-year period. The Council only has rights to
terminate the contract if it compensates the contractor
in full for costs incurred and future profits that would
have been generated over the course of the remainder
of the contract. The assets used to provide services are
recognised on the Council’s Balance Sheet. Movements
in their value over the year are shown in the movement
on the Property, Plant and Equipment balance in Note 9. 
The Council makes an agreed payment each year which
is increased by inflation and can be reduced if the
contractor fails to meet availability and performance
standards. Under the agreement the Council is
committed to paying the following sums (assuming an
average inflation rate of 2.5% per annum and excluding
any performance/availability deductions). The discount
rate used in this calculation is the interest rate implicit in
the PFI agreement, which was fixed at the outset at
7.6%. 
Future Repayment Periods - Schools
Service
Charges
Liability
Repayment
Interest
Repayment
Contingent
Rentals Total
£m £m £m £m £m
Payable within 1 year 6.632 3.038 4.467 4.614 18.751
Payable within 2-5 years 28.951 13.106 15.546 20.578 78.181
Payable within 6-10 years 34.897 23.873 12.780 33.735 105.285
Payable within 11-15 years 34.066 20.218 3.312 26.798 84.394
Payable within 16-20 years 0.000 0.000 0.000 0.000 0.000
Payable within >20 years 0.000 0.000 0.000 0.000 0.000
Total 104.546 60.235 36.105 85.725 286.611 
In 2019/20, the Council entered into a Service
Concession Agreement for the use of a waste materials
recovery facility at Bargeddie.  Residual waste is then
processed at a thermal treatment plant in Dunbar. 
North Lanarkshire Council is the lead authority and is
contracted to Viridor.   
Five councils, including Renfrewshire, have an inter-
authority agreement with North Lanarkshire Council.
Renfrewshire Council’s share of the contract is 20%.   
The discount rate used in this calculation is the interest
rate implicit in the agreement, which was fixed at the
outset at 5.68%.

Page 64

61 
Annual Accounts 2023/24
Future Repayment Periods - Waste
Facility
Service
Charges
Liability
Repayment
Interest
Repayment Total
£m £m £m £m
Payable within 1 year 4.392 0.134 0.267 4.793
Payable within 2-5 years 18.632 0.706 0.985 20.323
Payable within 6-10 years 26.738 0.511 1.022 28.271
Payable within 11-15 years 29.787 1.362 0.804 31.953
Payable within 16-20 years 34.163 1.706 0.387 36.256
Payable within 21-25 years 4.930 0.282 0.016 5.228
118.642 4.701 3.481 126.824Total 
Outstanding Service Concession Arrangements Schools Waste Facility Total
£m £m £m
Balance at 1 April 2022 (66.296) (5.016) (71.312)
Additions during the year 0.000 0.000 0.000
Payments during the year 2.947 0.158 3.105
Balance at 31 March 2023 (63.349) (4.858) (68.207)
Adjustment for Service Concession Arrangements 0.000 0.000 0.000
Payments during the year 3.114 0.157 3.271
Balance at 31 March 2024 (60.235) (4.701) (64.936)
In accordance with Accounting Policy and in line with
Finance Circular 10/2022, the Council applied the
permitted PPP Service Concession Arrangement
flexibility in financial year 2022/23 on a retrospective
annuity basis with a useful life of 40 years. The flexibility
being applied is consistent with the current Loans Fund
arrangements and is considered prudent, sustainable
and affordable over the life of the asset.   
The current annuity charges based on the estimated
useful life for the schools service concession
arrangement have been compared against the liability
repayment profile based on the estimated useful asset
lives for the schools service 
The most appropriate asset life was considered to be 40
years which replicated the useful life of other similar 
type assets on the council’s balance sheet i.e. schools.
The calculation of the repayment charges for the service
concession arrangement using asset life annuity is
compared to the current charges which are made over
the contract period. 
In addition to the one-off retrospective element, an in-
year saving occurred in the scheduled debt repayments
in 2023/24 of 1.597m (£1.539m in 2022/23). This will be
followed by a reduction in the annual charges for a
further 14 years and then the continuation of statutory
charges after the contract arrangements have been
repaid. Over the full asset life of the service concession
arrangement, the total debt liability remains the same.

Page 65

62 
Annual Accounts 2023/24
Prior 
Repayment
Current
Repayment (Cost)/Reduction
£m £m £m
Pre 2023/24 41.614 14.013 27.601
Paid in 2023/24 3.114 1.517 1.597
Payable within 1 year 3.038 1.632 1.406
Payable within 2-5 years 13.106 7.876 5.230
Payable within 6-10 years 23.873 13.745 10.128
Payable within 11-15 years 20.218 19.868 0.350
Payable within 16-20 years 0.000 28.722 (28.722)
Payable within 21-25 years 0.000 17.590 (17.590)
Total 104.963 104.963 0.000
PPP Service Concession
Liability Repayment
Note 16: Leases 
Renfrewshire Council as Lessee 
Operating Leases
The Council has 26 properties classed as operating
leases, with average lives of 13 years. The future
minimum lease payments due under non-cancellable
leases in future years are: 
As at 31
March
2023
As at 31
March
2024
£m £m
0.563 Not later than one year 0.934
0.966 Between one and five years 1.613
1.249 Later than five years 1.852
2.778 4.399 
During 2023/24, there was £0.934m expenditure
charged to the CIES in relation to these leases (£0.785m
in 2022/23). 
Finance Leases
Finance leases, which have substantially transferred to
the Council the benefits and risks of ownership of a non-
current asset, are treated as if the asset had been
purchased outright.   
Assets acquired under finance leases are included in
non-current assets at the lower of the fair value or the
present value of the minimum lease payments. The 
capital element of the lease is included as obligations
under creditors. The lease rentals comprise capital and 
interest elements; the capital element is applied to
reduce the outstanding obligation and the interest
element is charged to revenue over the terms of the
lease. The Council has 44 electric vehicles under a
finance lease agreement over a period of 5 years
beginning during 2019/20. As at 31 March 2024,
outstanding obligations to make payments under
finance leases are as follows: 
As at 31
March
2023
As at 31
March
2024
£m £m
0.118 Not later than one year 0.037
0.037 Between one and five years 0.000
0.000 Later than five years 0.000
0.155 0.037 
Renfrewshire Council as Lessor 
Operating Leases
The Council leases out property and equipment under
operating leases for the following purposes:
• for the provision of community services, such as
sports facilities, tourism services and community
centres
• for economic development purposes to provide
suitable affordable accommodation for local
businesses.

Page 66

63 
Annual Accounts 2023/24
The future minimum lease payments receivable under
non-cancellable leases in future years are: 
As at 31
March
2023
As at 31
March
2024
£m         £m
0.169 Not later than one year 0.158
0.735 Between one and five years 0.511
6.215 Later than five years 6.112
7.119 6.781
The minimum lease payments receivable does not
include rents that are contingent on events taking place
after the lease was entered into, such as adjustments
following rent reviews. 
Note 17: Inventories 
2022/23 2023/24
£m £m
1.032 Balance at 1 April 1.314
9.136 Additions during the year 9.163
(8.852) Recognised as an expense during the year: inventories sold, exchanged or distributed (9.188)
(0.002) Recognised as an expense during the year: inventories written down (0.002)
1.314 Balance at 31 March 1.287
Inventories
Note 18: Cash and cash equivalents 
The balance of cash and cash equivalents is made up of the following components. With the exception of imprest
accounts held at Council establishments, the balances in all of the categories listed below are used together to manage
the Council’s overall cash balances on a day-to-day basis. 
2022/23 2023/24
£m         £m
(3.216) Current account balances with the council's banker (7.653)
6.997 Euro account balances with the council's banker - sterling equivalent 3.707
1.714 Callable deposits with UK banks and building societies 13.263
6.086 Callable deposits in money market funds and ultra-short bond funds 20.101
0.051 Imprest accounts held at council establishments 0.043
11.632 Total cash and cash equivalents 29.461 
Note 19: Debtors 
Amounts due to be received by the Council at 31 March are set out below. This is analysed by type of debtor to provide
greater transparency of the sums due.

Page 67

64 
Annual Accounts 2023/24
Short-term Long-term Short-term Long-term
£m £m £m £m
21.141 0.000 Central government bodies (non-NHS) 22.904 0.000
7.793 1.080 Central government bodies (NHS) 5.075 0.990
3.316 0.000 Other local authorities 5.476 0.000
11.146 0.000 HM Revenue and Customs 5.170 0.000
0.005 0.030 Employees 0.084 0.029
19.819 0.000 Council Tax arrears 21.084 0.000
(11.911) 0.000 less impairment (13.296) 0.000
4.681 0.000 Rent arrears 4.939 0.000
(2.829) 0.000 less impairment (2.945) 0.000
31.645 6.005 Other entities and individuals 37.425 6.046
(17.384) (4.533) less impairment (19.562) (4.700)
67.422 2.582 Total Debtors 66.354 2.365
31 March 2023 As at 31 March 2024
Note 20: Creditors
Amounts due to be paid by the Council as at 31 March are set out below. This is analysed by type of creditor to provide
greater transparency of the sums due.
Short-term Long-term Short-term Long-term
£m £m £m £m
(7.810) (0.150) Central government bodies (non-NHS) (7.510) (0.732)
(1.549) 0.000 Central government bodies (NHS) (1.976) 0.000
(6.922) 0.000 Other local authorities (3.635) 0.000
(9.154) 0.000 HM Revenue and Customs (7.437) 0.000
(8.007) 0.000 Strathclyde Pension Fund and
Scottish Public Pensions Agency
(6.946) 0.000
(12.900) 0.000 Employees (10.440) 0.000
(3.114) (60.235) Service concession arrangements: schools (3.038) (57.197)
(0.157) (4.701) Service concession arrangements: waste
facility
(0.134) (4.567)
(0.118) (0.037) Finance lease liabilities (0.037) 0.000
(4.863) 0.000 Council Tax refundable to taxpayers (4.044) 0.000
(1.210) 0.000 Council Tax receipts in advance (1.018) 0.000
0.000 (0.003) Financial guarantees 0.000 0.000
(33.343) (0.564) Other entities and individuals (37.117) (0.856)
(89.147) (65.690) Total Creditors (83.332) (63.352)
As at 31 March 2023 As at 31 March 2024
Note 21: Provisions 
Provisions are made where an event has taken place that gives the Council a legal or constructive obligation that
probably requires settlement by a transfer of economic benefits or service potential, and a reliable estimate can be made
of the amount of the obligation. Teacher’s maternity pay is a short-term provision, made to reflect the changes in
European legislation that allow teachers to accrue all holidays during parental leave.

Page 68

65 
Annual Accounts 2023/24
The movement in these short-term provisions is detailed below: 
Short Term Provisons
Teachers’
maternity pay
Other Total
£m £m £m
As at 1 April 2023 (0.122) (0.130) (0.252)
Additional provisions made during the year (0.121) (0.600) (0.721)
Amounts used during the year 0.122 0.130 0.252
As at 31 March 2024 (0.121) (0.600) (0.721) 
A summary of the movements in the long-term provisions made by the Council is detailed below, along with an
explanation of the reason for the provision: 
Long-term Provisions
Holiday pay
compensation
Insurance
claims
Total
£m £m £m
Balance at 1 April 2023 (0.445) (4.497) (4.942)
Additional provisions made during the year 0.000 0.312 0.312
Amounts used during the year 0.000 0.000 0.000
As at 31 March 2024 (0.445) (4.185) (4.630) 
Holiday pay compensation payments 
The Council has received a number of claims arising from a European Court of Justice ruling in relation to holiday pay. A
provision has been made to reflect the potential outcome of known claims.  A contingent liability is recognised in Note 29
for potential claims that have not yet materialised. 
Insurance claims 
The provision for insurance claims represents the actuarial assessment of excess costs arising from insurance claims
together with identified liabilities in respect of insurance claims outstanding against Renfrewshire Council and
predecessor local authorities. The Council has increased its net assessment by £0.312m on the basis of information held
by the Council and notified by Glasgow City Council, the coordinating authority for the former Strathclyde Regional
Council. 
Note 22: Financial Instruments 
Categories of financial instruments 
A financial instrument is any contract that gives rise to a financial asset of one entity and a financial liability or equity
instrument of another entity. 
The term ‘financial instrument’ covers both financial assets and financial liabilities and includes trade payables,
borrowings (for example Public Works Loan Board debt and market debt), financial guarantees, bank overdraft, trade
receivables, loans receivable, cash deposits with financial institutions (some on a fixed term basis and some which are

Page 69

66 
Annual Accounts 2023/24
immediately available) and longer-term investments. The following categories of financial instrument are carried in the
balance sheet. 
Long-term Current Long-term Current
£m £m £m £m
(223.600) (0.828) (238.592) (5.000)
0.000 (2.770) 0.000 (2.815)
0.000 0.000 0.000 0.000
(223.600) (3.598) (238.592) (7.815)
0.000 (52.916) (20.000) (26.766)
0.000 (0.871) 0.000 (0.864)
0.000 (0.845) (0.339) (0.262)
0.000 (54.632) (20.339) (27.892)
0.000 (35.423) 0.000 (29.785)
(223.600) (93.653) (258.931) (65.492)
0.000 (49.657) 0.000 (49.988)
(64.973) (3.388) (61.763) (3.210)
(0.003) 0.000 0.000 0.000
(64.976) (53.045) (61.763) (53.198)
As at 31 March 2023 As at 31 March 2024
Financial Liabilities
Total Public Works Loan Board (PWLB) borrowing
Borrowing from group entities
Total Borrowing
Financial Liabilities included in Creditors
Principal sum borrowed
Accrued interest
EIR adjustments
Principal sum borrowed
Accrued interest
EIR adjustments
Total non-PWLB borrowing (“market debt”)
At amortised cost trade payables
Service Concession and Finance Lease liabilities
Financial guarantees
Long-term Current Long-term Current
£m £m £m £m
0.000 165.000 0.000 66.000
0.000 1.751 0.000 1.755
0.000 0.000 0.000 0.000
4.157 0.000 4.321 0.000
4.157 166.751 4.321 67.755
0.000 (1.461) 0.000 5.617
0.000 0.012 0.000 0.048
0.000 (0.002) 0.000 (0.012)
0.000 13.083 0.000 23.808
0.000 11.632 0.000 29.461
1.093 78.842 1.030 74.996
4.986 0.057 4.826 0.054
1.037 0.000 1.208 0.000
(4.533) (20.213) (4.700) (21.739)
2.583 58.686 2.364 53.311
As at 31 March 2023
Financial Assets
At amortised cost:
Principal
Accrued interest
Accrued interest
As at 31 March 2024
Loss allowance
At fair value through other comprehensive income - designated
equity instruments
At fair value through profit or loss
Principal
Accrued interest
Loss allowance
Total Investments
Total Cash and cash equivalents
At amortised cost:
At amortised cost:
Trade receivables
Loans made for service purposes
Loss allowance
Financial Assets included in Debtors

Page 70

67 
Annual Accounts 2023/24
Loans to other entities and individuals comprise a loan
to Park Lane Developments (Renfrewshire) LLP of
£0.275m (2022/23 £0.275m), a loan to Kilbarchan
Amateur Athletic Club of £0.074m (2022/23 £0.075),
home loans of £0.256m (2022/23 £0.335m), soft loans
to employees of £0.021m (2022/23 £0.022m), social
care charging order debtors of £0.736m (2022/23
£0.785m) and property charging order debtors of
£0.025m (2022/23 £0.024m). Note that these balances
are not principal amounts owed, rather valued at
amortised cost based on a notional (effective) interest
rate.
Equity instruments elected to fair value
through other comprehensive income
The Council has elected to account for the Insurance
Fund at fair value through other comprehensive income
because it is a long-term strategic holding and changes
in its fair value is not considered to be part of the
Council’s annual financial performance. The Insurance
Fund is invested in the Phoenix Fund, managed on
behalf of the Council by LGT Wealth Management.  
The objective of the fund is to achieve long term growth
with low volatility, through a widely diversified portfolio.
The fair value of the investment is £4.321m at 31 March
2024 (£4.157m as at 31 March 2023). Income from the
Fund is reinvested.
Fair value of financial instruments
Financial instruments, except those classified at
amortised cost, are carried in the Balance Sheet at fair
value. For most assets, including money market funds,
the fair value is taken from the market price. The fair
values of other instruments have been estimated by
calculating the net present value of the remaining
contractual cash flows at 31 March 2024. 
The Council’s ‘Fair value through other comprehensive
income’ assets comprise its insurance fund investments.
The fair value of the insurance fund investments
equates to the market value of those investments, and
this valuation has been provided by the Council’s
investment manager, LGT Wealth Management.
Financial instruments classified at amortised cost are
carried in the Balance Sheet at amortised cost.  Their fair
values have been estimated by calculating the net
present value of the remaining contractual cash flows at
31 March 2024, using the following methods and
assumptions:
• Loans borrowed by the Council have been valued by
discounting the contractual cash flows over the
whole life of the instrument at the appropriate
market rate for local authority loans.
• For ‘lender option borrower option’ (LOBO) loans,
PWLB premature repayment rates have been
applied to provide the fair value under PWLB debt
redemption procedures. The PWLB redemption
rates provide a reasonable proxy for rates and a
number of market participants have used this basis
when considering early redemption costs for market
loans. It is likely that lenders will only exercise their
options when market rates have risen above the
contractual loan rate. The interest rate risk
associated with the Council’s LOBOs is not deemed
to be significant and the potential penalties charged
may make the redemption of the loans an
uneconomic option. 
• The fair values of other long-term loans and
investments have been discounted at the market
rates for similar instruments with similar remaining
terms to maturity on 31 March.
• The fair values of financial guarantees have been
estimated based on the likelihood of the guarantees
being called and the likely payments to be made.
• The fair values of finance lease assets and liabilities
and of service concession (PFI) scheme liabilities
have been calculated by discounting the contractual
cash flows (excluding service charge elements) at
the appropriate AA-rated corporate bond yield.
• No early repayment or impairment is recognised for
any financial instrument.
• The fair value of short-term instruments, including
trade payables and receivables, is assumed to
approximate to the carrying amount given the low
and stable interest rate environment.
Fair values are shown in the table below, split by their
level in the fair value hierarchy:
• Level 1 – fair value is only derived from quoted
prices in active markets for identical assets or
liabilities, e.g. bond prices

Page 71

68 
Annual Accounts 2023/24
• Level 2 – fair value is calculated from inputs other
than quoted prices that are observable for the asset
or liability, e.g. interest rates or yields for similar
instruments
• Level 3 – fair value is determined using unobservable
inputs, e.g. non-market data such as cash flow
forecasts or estimated creditworthiness.
The fair value for each category of financial instrument is shown below, with the balance sheet carrying amount shown
for comparison.
Carrying
Amount
Fair value Financial Liabilities Carrying
Amount
Fair value
£m £m £m £m
Financial liabilities measured at amortised cost:
(227.198) (222.758) Public Works Loan Board borrowing 2 (246.407) (220.126)
(54.632) (61.519) Non-PWLB borrowing (“market debt”) 2 (48.231) (53.523)
Other liabilities:
(68.361) (126.783) Service Concession and Finance Lease liabilities 3 (64.973) (119.570)
(0.003) (0.003) Financial guarantees 3 0.000 0.000
(350.194) (411.063) (359.611) (393.219)
Financial liabilities measured at amortised cost:
(35.423) n/a Borrowing from group entities (29.785) n/a
(49.657) n/a Trade payables: short-term (49.988) n/a
(85.080) (79.773)
As at 31 March 2023 As at 31 March 2024
Fair
value
level
Total financial liabilities for which fair value is disclosed
Total financial liabilities for which fair value is not disclosed 
Carrying
Amount
Fair value Financial Assets Carrying
Amount
Fair value
£m £m £m £m
6.086 6.086 Callable deposits in money market funds and
ultra-short bond funds
1 20.101 20.101
6.997 6.997 Euro current account balances with the council’s banker 2 3.707 3.707
4.157 4.157 Investments in pooled funds (insurance fund) 1 4.321 4.321
17.240 17.240 28.129 28.129
166.751 166.751 Fixed term deposits with UK local authorities 2 67.755 67.751
(1.502) (1.502)
Callable deposits with UK banks and building societies
(including sterling current account balances with the
Council’s banker)
2 5.610 5.610
0.051 0.051 Imprest accounts held at council establishments 2 0.043 0.043
1.546 1.681 Loans made for service purposes 3 1.387 1.543
166.846 166.981 74.795 74.947
184.086 184.221 102.924 103.076
Financial assets measured at amortised cost:
1.092 n/a Trade receivables and prepayments: long-term 1.029 n/a
58.631 n/a Receivables and prepayments: short-term 53.259 n/a
59.723 54.288
As at 31 March 2023 As at 31 March 2024
Total financial assets for which fair value is disclosed
Total financial assets for which fair value is not disclosed
Fair
value
level
Total Financial assets measured at fair value
Total Financial assets measured at amortised cost

Page 72

69 
Annual Accounts 2023/24
Items of income, expense, gain and loss relating to financial instruments 
The following items of income, expense, gain and loss relating to financial instruments are included within the lines
‘Financing and investment income and expenditure’ and ‘(Surplus)/Deficit from investments in equity instruments
designated as Fair Value through Other Comprehensive Income’ in the CIES. 
2022/23
Amortised
cost
Elected to Fair
Value through
Other
Comprehensive
Income
Fair Value
through
Profit or
Loss 2023/24
£m £m £m £m £m £m
16.583 Interest expense 0.000 0.000 0.000 16.323 16.323
0.000 Impairment losses 3.720 0.000 0.000 0.000 3.720
0.000 Fee expense 0.000 0.000 0.000 0.007 0.007
16.583
Total expense in the Surplus /
Deficit on the Provision of
Services
3.720 0.000 0.000 16.330 20.050
(4.306) Interest income (6.505) 0.000 (1.754) 0.000 (8.259)
(0.110) Dividend income 0.000 (0.133) 0.000 0.000 (0.133)
(0.196) Other income 0.000 0.000 0.000 0.000 0.000
(4.612)
Total income in the
Surplus/Deficit on the Provision
of Services
(6.505) (0.133) (1.754) 0.000 (8.392)
(0.017) Net (gain) or loss on revaluation 0.000 (0.031) 0.039 0.000 0.008
(0.017) (Surplus)/Deficit on the
revaluation of financial assets 0.000 (0.031) 0.039 0.000 0.008
11.954 Net (Gain)/Loss for the year (2.785) (0.164) (1.715) 16.330 11.666
Financial Assets
Financial
liabilities
at
amortised
cost
Note 23: Nature and extent of risks
arising from Financial Instruments 
The Council’s management of treasury risks actively
works to minimise the Council’s exposure to the
unpredictability of financial markets and to protect the
financial resources available to fund services. The
Council complies with CIPFA’s Code of Treasury
Management Practices and has written principles for
overall risk management as well as written policies and
procedures covering specific areas such as credit risk,
liquidity risk and market risk. 
In line with the Treasury Management Code, the Council
approves a Treasury Management Strategy before the
commencement of each financial year. The Strategy sets
out the parameters for the management of risks
associated with financial instruments. The Council also
produces Treasury Management Practices specifying the
practical arrangements to be followed to manage these
risks. 
The Treasury Management Strategy includes an
Investment Strategy in compliance with Scottish
Government guidance on Local Government
Investments.  This Guidance emphasises that priority is
to be given to security and liquidity, rather than yield.   
The Council’s Treasury Management Strategy and its
Treasury Management Practices seek to achieve a
suitable balance between risk and return or cost.

Page 73

70 
Annual Accounts 2023/24
Credit Risk 
Credit risk arises from the short-term lending of surplus
funds to financial institutions and local authorities, as
well as credit exposures to the Council’s customers. It is
the policy of the Council to place deposits only with
other local authorities and a limited number of high-
quality banks, building societies and money market
funds whose credit rating is independently assessed as
sufficiently secure by the Council’s treasury advisers and
to restrict lending to a prudent maximum amount for
each entity. 
The Treasury Management Strategy outlines the limits
placed on investments with any counterparty.
The table below summarises the credit risk exposures of
the Council’s treasury investment portfolio (including
accrued interest) by credit rating.   
2022/23 2023/24
£m £m
6.037 AAA (money market funds and 
ultra-short bond funds)
20.015
0.000 A+ 6.736
0.500 A 0.000
1.204 A– 6.491
165.000 UK local authorities 66.000
172.741 Total 99.242
Total Investment Portfolio by
Credit Rating
The Council does not generally allow credit for
customers such that, at 31 March 2024, £9.903m of
sundry income debt is past its due date for payment
(£8.932m as at 31 March 2023). The past due amount
can be analysed by age as follows: 
2022/23 2023/24
£m £m
1.684 Less than three months 2.258
1.515 Three to six months 0.635
0.965 Six months to one year 1.612
4.768 More than one year 5.398
8.932 Total 9.903
Sundry Income Debt Past
Due
Loss allowances on trade receivables have been
calculated by reference to the Council’s historic
experience of default, adjusted for current and forecast
economic conditions. Receivables are determined to
have suffered a significant increase in credit risk where
they are 30 or more days past due and they are
determined to be credit-impaired where they are 90 or
more days past due.  Receivables are written off to the
Surplus or Deficit on the Provision of Services when
there is no reasonable prospect of payment, or when
they become prescribed; but steps are still taken to
collect sums owing when information becomes available
which suggests the debtor can make payment. 
Collateral 
Renfrewshire Council occasionally provides loans to
residents who wish to buy their homes under Right to
Buy legislation. In such cases the Council takes a
standard security over the property. As at 31 March
2024 the outstanding value of home loans advanced by
the Council was £0.256m (£0.335m as at 31 March
2023). 
Liquidity risk 
The Council’s main source of borrowing is HM Treasury’s
Public Works Loan Board, but the Council also has loans
classed as ‘lender option borrower option’ (LOBO).
There is no significant risk that the Council will be
unable to raise finance to meets its commitments under
financial instruments. 
The Council has safeguards in place to ensure that a
significant proportion of its borrowing does not mature
for repayment at any one time in the future to reduce
the financial impact of re-borrowing at a time of
unfavourable interest rates. 
The Council’s policy is to ensure that not more than 15%
of loans are due to mature within any financial year and
50% within any rolling five-year period through a
combination of prudent planning of new loans taken out
and, where it is economic to do so, making early
repayments.

Page 74

71 
Annual Accounts 2023/24
The maturity analysis of the principal element of borrowing is as follows: 
£m % £m %
0.828 0.30% Less than one year 5.000 1.72%
5.000 1.80% Between one and two years 5.000 1.72%
5.016 1.81% Between two and five years 0.011 0.00%
266.500 96.09% More than five years 280.347 96.56%
277.344 100.00% Total 290.358 100.00%
As at 31 March 2023 Principal Borrowing Maturity Analysis As at 31 March 2024
Market risk: interest rate risk 
Changes in market interest rates influence the interest payable on borrowings and on interest receivable on surplus
funds invested. For example, a rise in interest rates would mean an increase in the interest charged on borrowing at
variable rates and an increased cost to the taxpayer. An increase in interest rates would also mean an increase in the
income received on lending at variable rates and a reduction in cost for the taxpayer. Changes in market rates also affect
the notional ‘fair value’ of lending and borrowing. For example, a rise in interest rates would reduce the fair value of both
lending and borrowing at fixed rates. Changes in the fair value of lending and borrowing do not impact upon the taxpayer
and are confined to prescribed presentational aspects in the Accounts.
The Council has a variety of strategies for managing the uncertainty of future interest rates and the financial impact on
the Council’s finances:
• it is the policy of the Council to limit its exposure to variable rate borrowing to a maximum of 25% of what it borrows;
• during periods of falling rates and where it is economically advantageous to do so, the Council will consider the
repayment and restructuring of fixed interest rate debt;
• the Council takes daily advice from its specialist treasury advisers and actively monitors changes in interest rates to
inform decisions on the lending of surplus funds, new borrowings and restructurings of existing borrowings. 
To illustrate the notional impact of changes in interest rates upon the Council, the following table shows the financial
effect if rates had been 1% higher during 2023/24, with all other variables held constant.
Decrease in the fair value of fixed rate loans and deposits
Decrease in the fair value of fixed rate borrowing
0.196
(1.830)
(1.634)
(0.495)
0.014
45.820
Increase in interest payable on new fixed rate borrowings taken during the year
Increase in interest receivable on deposits placed during the year
Notional impact on the Surplus/Deficit on the Provision of Services
Share of this impact which would be attributable to the Housing Revenue Account
Other changes that would have no impact on the Surplus/Deficit on the Provision of Services or
Other Comprehensive Income and Expenditure:
As at 31 March 2024
£m
Interest rate risk
The impact of a 1% fall in interest rates would be as above but with the changes being reversed.

Page 75

72 
Annual Accounts 2023/24
Market risk: price risk
The Council’s Insurance Fund is invested in an externally managed fund under the powers of schedule 3 of the Local
Government (Scotland) Act 1975 and section 3 of the Local Government etc. (Scotland) Act 1994. The investments are
managed on behalf of the Council by LGT Wealth Management in the Phoenix Fund. The objective of the fund is to
achieve long-term growth with low volatility, through a widely diversified portfolio. The benchmark return is SONIA+2%
per annum. During 2023/24 the book cost of investments increased by £0.133m (£0.115m increase during 2022/23). The
investment is classified as fair value through other comprehensive income, meaning that all movements in price will
impact on the gains and losses recognised in other comprehensive income and expenditure. This is an accounting
requirement that has no impact on the taxpayer. To illustrate the impact of changes in share price upon the Council, an
increase or fall of 5% in the general price of shares at 31 March 2024 would have resulted in a £0.081m gain or loss being
recognised in Other Comprehensive Income and Expenditure for 2023/24.
Market risk: foreign exchange risk
As at 31 March 2024 the Council had a foreign currency deposit of €4.335m with the Council’s banker (€7.959m as at 31
March 2023). This sum was being held in order to mitigate the foreign exchange risk associated with a contract being
entered into as part of the Glasgow and Clyde Valley City Deal programme. The sterling valuation of this deposit as at 31
March 2024, based on the euro to sterling exchange rate at that time, was £3.707m. To illustrate the impact of changes
in foreign exchange rates upon the Council, a relative increase or decrease of 1% in the euro to sterling exchange rate at
31 March 2024 would have resulted in a £0.037m gain or loss being recognised in Other Comprehensive Income and
Expenditure for 2023/24. 
Note 24: External audit costs 
2022/23 2023/24
£m £m
0.443 Fees payable with regard to external audit services carried out by the appointed auditor
for the year 0.441
0.443 Total 0.441
Audit Fees
Note 25: Agency services 
The Council bills and collects non-domestic rates on behalf of the Scottish Government from ratepayers situated
within Renfrewshire Council and East Renfrewshire Council. The Council also bills and collects, along with its own
Council Tax, domestic water and sewerage charges on behalf of Scottish Water.

Page 76

73 
Annual Accounts 2023/24
2022/23 2023/24
£m £m
108.076 Scottish Government - Contributions (to)/from the non-domestic rates pool 131.322
13.640 Non-domestic rates collected: East Renfrewshire 14.880
0.066 Service income from East Renfrewshire Council for collection of non-domestic rates 0.070
(13.706) Cost of collection of Non-domestic rates from East Renfrewshire (14.950)
34.350 Domestic water and sewerage charges collected 34.461
(34.350) Domestic water and sewerage charges paid over to Scottish Water (34.461)
0.637 Service income from Scottish Water for collection of domestic water and sewerage
charges
0.706
0.133 COVID-19 PPE and Testing kits issued to external providers 0.000
(0.133) COVID-19 PPE and Testing kits received from Scottish Government 0.000
9.540 Cost of Living Awards paid out 0.000
(9.540) Cost of Living Awards funding from the Scottish Government 0.000
0.911 Scottish Child Bridging Payments paid out 0.000
(0.911) Scottish Child Bridging Payments funding received from the Scottish Government 0.000
Agency Services
Note 26: Related parties 
The Council’s related parties are those bodies or
individuals that have the potential to control or
significantly influence the Council, or to be controlled or
significantly influenced by the Council, or where those
individuals or bodies and the Council are subject to
common control. The Council is required to disclose
material transactions that have occurred with related
parties and the amount of any material sums due to or
from related parties. 
Related party relationships require to be disclosed
where control exists, irrespective of whether there have
been transactions between the related parties.
Disclosure of this information allows readers to assess
the extent to which the Council might have been
constrained in its ability to operate independently or
might have secured the ability to limit another party’s
ability to bargain freely with the Council. 
Senior Officers and Elected Members 
Members of the council and senior officers have control
over the Council’s financial and operating policies. They
have the responsibility to adhere to a Code of Conduct,
requiring them to declare an interest in matters that
directly or indirectly influence, or appear to influence,
their judgement or decisions taken during the course of
their work. The total of councillors’ and senior officers’
remuneration allowances paid in 2022/23 are shown in
the Remuneration Report on page 25. 
Senior Officers
No senior officer holds a remunerated position outside
of their Council employment. For details of Senior
Officers’ interests, please check the register of interests
on the Council website at:
https://www.renfrewshire.gov.uk>Your Council
>Information, performance and statistics >Council
structure/article/2179/Council-structure.
Senior Elected Members
Under the Council Code of Conduct, elected members
and senior officials must declare any registered interests
in any bodies where the Council itself does not have
significant influence over their operations. Each
member’s Register of Interest is available at Councillors -
Renfrewshire Website. 
In 2023/24, the Council made payments to the following
bodies where councillors have declared a non-financial
interest, either through non-remunerated positions held
with the organisations, or through being a member of
those bodies

Page 77

74 
Annual Accounts 2023/24 
Councillor Non-financial Interest / Position Organisation
Council
Spend in
2023/24
£
Alison Ann-Dowling Chair Renfrewshire Citizens' Advice Bureau 425,586
Lorraine Cameron Trustee Kibble Trust 2,400,756
Michelle Campbell Chairperson Erskine Arts Charity 55,700
Eddie Devine Director St Mirren Independent Supporters
Association (SMISA) 0
Andy Doig Director Scotia Future Limited 0
Alec Leishman Chairperson Linthouse Housing Association 0
Director Shop Mobility UK 0
Director Fauldmore Limited 0
Chair from 23 May 2023
SME Taskforce In Collaboration with
BiTC
0
Director Linwood Community Garden 0
Director from 6 November 2023 Linwood Men's shed and Community
Men's shed 0
Jim Paterson Board Member Greater Pollock Citizens Advice Bureau 0
Kenny MacLaren
David McGonigle
NB: This disclosure excludes group entities and trade union membership.
Some senior councillors also hold a remunerated position outwith the Council, i.e. they receive payment from other
organisations for employment, or board positions. The following table details these remunerated positions and notes
where the Council has made payments to any of the organisations listed. 
Councillor Remunerated Position Employer / Organisation
Council
Spend in
2023/24
£
Fiona Airlie-Nicolson Associate Director Quarriers - Charity Care Organisation 5,084,400
Jacqueline Cameron Board Member Public Health Scotland 14,712
Anne Hannigan Director Rain Room Limited 0
Janis McDonald Associate Director The Alliance - National Charity
Intermediary
0
Marie McGurk Owner Marie McGurk Podiatry 0
Key Related Parties: subsidiaries and
associates
The organisations set out in the group accounts note are
those which the Council is considered to have control or
influence over. The following entities have a significant
impact on the Council’s operations and have been
consolidated into the group accounts:
• OneRen (formerly Renfrewshire Leisure)
• Renfrewshire Valuation Joint Board
• Paisley Museum Reimagined Ltd
• Park Lane Developments (Renfrewshire) LLP
• AMIDS (Renfrewshire) LLP
• Strathclyde Concessionary Travel Scheme Joint
Committee
• Strathclyde Partnership for Transport
• Renfrewshire Health and Social Care Integration
Joint Board
• Scotland Excel
• Glasgow and the Clyde Valley Strategic
Development Planning Authority

Page 78

75 
Annual Accounts 2023/24
• Glasgow City Region – City Deal Cabinet
• Coats Observatory Trust
• Johnstone, Paisley and Renfrew Common Good
Funds
For further details of the nature of group relationships,
please refer to the Group Accounts and Notes from page
103.
Key Related Parties: Other Public Bodies
Scottish Government
The Scottish Government has effective control over the
operations of the Council as it is responsible for
providing the statutory framework within which the
Council operates, provides the majority of its funding in
the form of grants and prescribes the terms of many of
the transactions that the Council has with other parties,
such as Council Tax and Non-Domestic Rates. Grants
received from the Scottish Government are set out in
the analysis in Note 3: Taxation and non-specific grant
income, and other grants received from government
departments are shown in Note 5: Grant income.
UK Government
The UK Department of Work and Pensions administers
funding for the delivery of Housing Benefit and
associated costs. The total received by the Council in
2023/24 was £40.6m (£41.4m in 2022/23). 
Rental income
Income received from the Care Inspectorate (£0.074m)
and Scotland Excel (£0.097m) relate to rental income for
occupancy of part of Renfrewshire House. The property
rentals were conducted under standard terms and
conditions and no guarantees have been applied.
Strathclyde Pension Fund
Strathclyde Pension Fund is the principal administrators
of the post-retirement funds held on behalf of the
current and former employees of the Council.
Information about transactions during the year and
outstanding assets and liabilities in relation to the
Council’s share of the Strathclyde Pension Fund can be
found in Note 28: Defined benefit pension schemes.
Note 27: Pension schemes
accounted for as defined
contribution schemes
Renfrewshire Council participates in the Scottish
Teachers' Superannuation Scheme. The scheme is an
unfunded statutory public service pension scheme with
benefits underwritten by the UK Government. The
scheme is financed by payments from employers and
from those current employees who are members of the
scheme and paying contributions at progressively higher
marginal rates based on pensionable pay, as specified in
the regulations. The rate of employer contributions is
set with reference to a funding valuation undertaken by
the scheme actuary. The last four-yearly valuation was
undertaken as at 31 March 2020, which set the
contribution rate payable from 1 April 2020 to 31 March
2023, extended until 31 March 2024
Renfrewshire Council has no liability for other
employers’ obligations to the multi-employer scheme.
As the scheme is unfunded there can be no deficit or
surplus to distribute on the wind-up of the scheme or
withdrawal from the scheme. 
The scheme is an unfunded multi-employer defined
benefit scheme. It is accepted that the scheme can be
treated for accounting purposes as a defined 
contribution scheme in circumstances where
Renfrewshire Council is unable to identify its share of
the underlying assets and liabilities of the scheme.
While the employee rate applied is variable, it will
provide an actuarial yield of 9.4% of pensionable pay. At
the last valuation a shortfall of £1.3bn was identified in
the notional fund, which will be repaid by the increased
rate of employers’ pension contribution, effective from
1 September 2019, of 23%.
Based on the proportion of employer contributions paid
in 2023/24, Renfrewshire Council’s level of participation
in the scheme is 3.0%. The Council paid £21.041m
(£19.719m in 2022/23) for employer's contributions to
the Scottish Public Pensions Agency. £0.401m of

Page 79

76 
Annual Accounts 2023/24
expenditure (£0.444m in 2022/23) was charged to
service revenue accounts in respect of “added years”
pension enhancement termination benefits,
representing 0.4% of teachers’ pensionable pay (0.5% in
2022/23). The estimated contribution for 2024/25 is
£19.390m. 
Note 28: Defined benefit pension
schemes 
28a: Participation in pension schemes 
The pension scheme for teachers (the Scottish Teachers’
Superannuation Scheme) is explained in the previous
note, whilst this note relates exclusively to the pension
scheme for all other employees: the Local Government
Pension Scheme. 
The Local Government Pension Scheme in Scotland
(LGPS) is a funded, defined benefit, statutory
occupational pension scheme. It is regulated by the
Scottish Public Pensions Agency but is administered
locally by fund administering authorities through
regional pension funds. For Renfrewshire Council, the
fund administering authority is Glasgow City Council and
the regional pension fund is the Strathclyde Pension
Fund. As a funded scheme, the Council and employees
pay contributions into the fund, calculated at a level
intended to balance the scheme’s pension liabilities with
the scheme’s investment assets. The statutory nature of
the fund means that the post-employment benefits are
defined and set out in law. The Strathclyde Pension
Fund is a multi-employer fund, and it is possible for each
employer to identify its own share of the assets and
liabilities of the fund on a consistent and reasonable
basis. 
The principal risks to the scheme are assumptions
relating to longevity, inflation, and investment
performance; in addition, statutory changes to the
scheme. These risks are mitigated to an extent by
statutory requirements limiting charges to the Council’s
general fund. The Council has additional liabilities for
unfunded discretionary pension payments outside the
main schemes such as arrangements for the award of
discretionary post-employment benefits upon early
retirement. This is an unfunded defined benefit
arrangement, under which liabilities are recognised
when awards are made. 
However, there are no investment assets built up to
meet these pensions liabilities, and cash has to be
generated to meet actual pensions payments as they
eventually fall due. 
28b: Transactions relating to post-
employment benefits 
The Council accounts for post-employment benefits in
the CIES as the benefits are earned by employees
accruing years of service, updating the liabilities
recognised to reflect inflation, changing assumptions
and accounting for investment returns on any resources
set aside to meet the costs. However, the charge
according to statutory regulations that is required to be
made against the General Fund Balance and the Housing
Revenue Account Balance is based upon the employer
contributions payable by the Council to the pension
fund in the year. This requires an adjustment to be
made in the movement in reserves statement to remove
the cost (according to generally accepted accounting
practices) of post-employment benefits and replace that
cost with the value of employer contributions payable to
the fund in the year.

Page 80

77 
Annual Accounts 2023/24
The following transactions have been made in the CIES and the General Fund Balance via the movement in reserves
statement during the year: 
2022/23
(restated) 2023/24
£m £m
Included within net cost of services:
69.403 Current service cost 31.776
3.078 Past service cost/(gain) 7.805
Included within Financing and Investment income and expenditure:
47.114 Interest cost 57.468
0.000 Interest on the effect of the asset ceiling 12.265
(45.130) Expected return on scheme assets (78.093)
74.465 Total of Post-employment benefits charged to the Surplus/Deficit on the
Provision of Services 31.221
Included within Other Comprehensive Income and Expenditure:
71.373 Return on Assets excluding amounts included in net interest (84.242)
(13.264) Actuarial gains and losses arising on changes in Demographic Assumptions (20.669)
(672.239) Actuarial gains and losses arising on changes in Financial Assumptions (44.838)
86.064 Actuarial gains and losses arising on changes in Other Assumptions 111.846
0.000 Changes in effect of Asset Ceiling 296.851
(453.601) Total of LGPS post-employment benefits charged to the CIES 290.169
Movement in reserves statement:
(528.066) Actuarial losses or (gains) 258.948
331.698 Restriction on pension asset to Asset Ceiling (73.493)
74.465 Reversal of items relating to post-employment benefits debited or credited to the
Surplus/Deficit on the Provision of Services
31.221
(35.716) Employer contributions and direct payments to pensioners payable in the year (39.797)
(157.619) Movement in the year on the Pension Reserve 176.879 
The cumulative amount of actuarial gains and losses
recognised in the CIES as at 31 March 2024 is a gain of
£1,064.977m (£652.915m gain as at 31 March 2023). 
28c: Assets and liabilities relating to
post-employment benefits 
Renfrewshire Council's share of the defined benefit
obligation (that is, the scheme liabilities) and of the
scheme assets in the Strathclyde Pension Fund has been
assessed by Hymans Robertson LLP, the Fund’s
independent actuaries. The assessment indicates that,
as at 31 March 2024, scheme assets exceeded the
defined benefit obligation by £494.840m (£434.096m
excess of obligations over assets as at 31 March 2023).
The defined benefit obligation is valued on an actuarial
basis using the “projected unit credit” method, which
estimates the pensions that will be payable in future
years (dependent on assumptions about mortality rates,
salary levels and other factors) discounted to their
present value. The discount rate used at 31 March 2024
was 4.8% based on the indicative rate of return on high
quality corporate bonds. Scheme assets are valued at
fair value which, in the case of marketable securities, is
market value using the current bid price. Where no
market price is available, the fair value of scheme assets
is estimated. The valuations are based on the latest
formal valuation of the Strathclyde Pension Fund which
was carried out as at 31 March 2020.
The common position for employers participating in the
Strathclyde Pension Fund is that, based on a snapshot
valuation as at 31 March 2024, a net pension asset is

Page 81

78 
Annual Accounts 2023/24
disclosed as a result of prevailing market conditions at
that date. The net pension position of £494.840m
represents an increase in asset of £58.744m between 31
March 2023 and 31 March 2024. The net pension
liability has a substantial impact on the net worth of the
Council as recorded in the balance sheet. 
The net pension asset has a substantial impact on the
net worth of the Council as recorded in the balance
sheet). However, this surplus of scheme assets is
restricted to the “asset ceiling” i.e., the net present
value of future service costs less net present value of
future contributions over the future working lifetime as
at 31 March 2024. This has been calculated to be £0 for
funded obligations. After adjusting for the asset ceiling,
the balance sheet now reflects a pension liability of
£74.480m, representing the unfunded obligations of the
scheme. 
Local government legislation provides that local
authorities have an obligation to meet the expenditure
of the joint boards of which they are constituent
members. As a consequence, Renfrewshire Council has
additional liabilities arising from the pension scheme
deficits of the Renfrewshire Valuation Joint Board. In
accordance with accounting regulations, the group
accounts include a share of the post-employment
benefits transactions, defined benefit obligations and
scheme assets of this joint board. Further information
can be found in the annual report and accounts of each
joint board. The main fund (Fund 1) of Strathclyde
Pension Fund does not have an asset and liability
matching (ALM) strategy. 
28d: Movement in defined benefit
obligation (scheme liabilities) 
The following is a reconciliation of the 2023/24 opening
and closing balances of the present value of
Renfrewshire Council’s share of the Strathclyde Pension
Fund’s defined benefit obligation (that is, scheme
liabilities). 
2022/23 2023/24
£m £m
1,725.861 Balance at 1 April 1,211.991
69.403 Current service cost 31.776
3.078 Past service cost (including curtailments) 7.805
47.114 Interest cost 57.468
9.240 Member contributions 9.277
(599.439) Actuarial losses or (gains) 32.218
Losses or (gains) on curtailment
(4.685) Estimated benefits paid: unfunded (5.157)
(38.581) Estimated benefits paid: other (48.017)
1,211.991 Balance at 31 March 1,297.361
28e: Movement in scheme assets 
The following is a reconciliation of the 2023/24 opening and closing balances of the fair value of Renfrewshire Council’s
share of the Strathclyde Pension Fund’s scheme assets.

Page 82

79 
Annual Accounts 2023/24
2022/23 2023/24
£m £m
1,670.640 Balance at 1 April 1,646.087
45.130 Expected return on scheme assets 78.093
9.240 Member contributions 9.277
31.031 Employer contributions 34.640
4.685 Contributions in respect of unfunded benefits 5.157
0.000 Effect of other experience (14.121)
(71.373) Actuarial (losses) or gains 84.242
(4.685) Estimated benefits paid: unfunded (5.157)
(38.581) Estimated benefits paid: other (48.017)
1,646.087 Balance at 31 March 1,790.201
The expected return on scheme assets is determined by considering the expected returns available on the assets
underlying the current investment policy as provided by the administering authority. Expected yields on fixed interest
investments are based on gross redemption yields as at the balance sheet date. Expected returns on equity investments
reflect long-term real rates of return experienced in the respective markets. 
The actual return on scheme assets from 1 April 2023 to 31 March 2024 was 9.9%. 
The fair value of the assets held in the scheme may be analysed as follows: 
Quoted
Prices in
active
markets
Prices not
quoted in
active
markets
Total Quoted
Prices in
active
markets
Prices not
quoted in
active
markets
Total
£m £m £m £m £m £m
321.441 2.951 324.392 Equity instruments 361.564 0.392 361.956
0.000 404.589 404.589 Private Equity 0.000 427.395 427.395
0.000 135.719 135.719 Real Estate 0.000 140.763 140.763
7.090 743.114 750.204 Investment Funds 7.352 819.550 826.902
0.000 (0.001) (0.001) Derivatives 0.000 0.000 0.000
22.766 8.418 31.184 Cash and cash equivalents 2.789 30.397 33.186
351.297 1,294.790 1,646.087 Fair value of scheme assets 371.705 1,418.497 1,790.202
As at 31 March 2023 As at 31 March 2024
28f: Scheme history: analysis of defined benefit obligation and scheme assets 
The Council’s share of the accumulated deficit or surplus in the scheme is shown below. The analysis shows the nature of
various elements of the Council’s share of the scheme’s defined benefit:

Page 83

80 
Annual Accounts 2023/24
As at 31
March 2023
As at 31
March 2024
£m £m
(568.195) Current employee members (537.973)
(57.322) Pre-local government reorganisation (1996) liabilities (53.892)
(111.002) Deferred pensioners (128.007)
(401.978) Pensioners (503.009)
(1,138.497) Total Present Value of the Defined Benefit Obligation - Funded liabilities (1,222.881)
1,646.087 Fair value of scheme assets 1,790.201
507.590 Net Asset / (Liability) arising from funded obligations 567.320
(331.698) Restriction to asset ceiling (567.320)
(66.196) Retirals from Renfrewshire Council (67.713)
(7.298) Retirals pre-local government reorganisation (1996) (6.767)
(73.494) Total Present Value of the Defined Benefit Obligation - Unfunded liabilities (74.480)
102.398 Net Pension Asset / (Liability) (74.480) 
The presentation of this table has been revised to better reflect the Unfunded Pension obligation. 
Basis for estimating assets and liabilities 
The following table shows the principal assumptions used by Hymans Robertson LLP, the Fund’s independent actuaries,
to estimate the Council’s post-employment benefits transactions for 2023/24, and the Council’s share of the Strathclyde
Pension Fund’s defined benefit obligation (scheme liabilities) and scheme assets as at 31 March 2024:
2022/23 2023/24
4.8% Discount rate for defined benefit obligation 4.8%
2.7% Long-term expected rate of return on scheme assets* 2.7%
3.7% Rate of increase in salaries 3.5%
3.0% Rate of increase in pensions 2.8%
3.0% Rate of inflation 2.8%
Mortality assumptions (years):
Longevity at age 65 for current pensioners:
19.3 Men 19.6
22.2 Women 22.3
Longevity at age 65 for future pensioners:
20.5 Men 20.6
24.2 Women 24.2
Take up of option to convert annual pension into retirement lump sum
50% For Pre-April 2009 service 75%
75% For Post-April 2009 service 75%
*The expected rates of return are set equal to the discount rate as per IAS19, 
The estimation of the defined benefit obligations is
sensitive to the actuarial assumptions set out in the
table above. The sensitivity analyses below have been
determined based on reasonably possible changes of
the assumptions occurring at the end of the reporting
period and assumes for each change that the
assumption analysed changes while all the other
assumptions remain constant. The estimations in the

Page 84

81 
Annual Accounts 2023/24
sensitivity analysis have followed the accounting policies
for the scheme, i.e. on an actuarial basis using the
projected unit credit method. The methods and types of
assumptions used in preparing the sensitivity analysis
did not change from those used in the previous period.
The limitations of methods and assumptions used are
associated with any changes in market conditions that
affect the net discount rate. These can have a significant
effect on the value of the obligations reported. 
Impact on the Defined Benefit
Obligation on the Scheme % £m
0.1% decrease in the Real Discount
Rate
2% 22.091
1 year increase in the member life
expectancy
4% 48.480
0.1% increase in the Salary Increase
Rate
0% 2.675
0.1% increase in the Pension
Increase Rate
2% 19.729
Impact on the Authority’s cash flows 
An objective of the Fund is to keep employers’
contributions at as constant a rate as possible. The Fund
has agreed a strategy to achieve a funding rate of 100%
in the longer term. Employers’ and employees’
contributions have been determined so that rates are
standard across all participating employers. 
The rate for employer contributions has been set at
6.5% for 2024/25 to 2025/26, rising to 17.5% from
2026/27. The total contribution expected to be made by
the Council to the Strathclyde Pension Fund in the
forthcoming year to 31 March 2025 is £10.026m. The
weighted average duration of the defined benefit
obligation is 17 years. 
Note 29: Contingent liabilities 
i) The Council has been notified of a number of
contractor claims for additional costs incurred on
construction contracts. The Council disputes the
claims, which may be referred for arbitration. The
Council recognises a contingent liability for potential
costs, which may be incurred to resolve this dispute.
It is not considered practicable at this stage to
estimate the financial effect.
ii) Following two court cases, including Mrs Goodwin v
Department for Education, it is expected that
proposed changes to public service pension
schemes will be required, to ensure that surviving
same-sex spouses and civil partners receive
benefits equivalent to those received by the
surviving spouses of opposite-sex marriages.
Strathclyde Pension Fund’s actuary estimates that
the potential impact may be 0.1% of gross
obligations, which equates to £1.297m for the
Council. This estimate is not reflected in the
Primary Financial Statements because the trigger
event that would require recognition has not yet
occurred. 
Note 30: Events after the balance
sheet date 
Events taking place after the authorised date for issue
per the balance sheet are not reflected in the financial
statements or notes.  Where events taking place before
this date provided information about conditions existing
at 31 March 2024, the figures in the financial statements
and notes have been adjusted in all material respects to
reflect the impact of this information. 
Note 31: Accounting Standards
Issued not Adopted 
The Code requires the disclosure of information relating
to the impact of an accounting change that will be
required by a new standard that has been issued but not
yet adopted.  
The following new or amended standards are adopted
within the 2024/25 Code:
• IFRS 16 Leases
• Classification of liabilities as Current or Non-current
(Amendments to IAS1)
• Lease liability in a Sale and Leaseback (Amendments
to IFRS 16)
• Non-current Liabilities with Covenants (Amendments
to IFRS 16)

Page 85

82 
Annual Accounts 2023/24
There is no material impact anticipated in future years
from the implementation of these standards, other than
IFRS 16 Leases. 
CIPFA LASAAC has issued a formal decision to defer the
implementation of IFRS 16 until 1 April 2024 when the
Council will apply IFRS 16 in the 2024/25 accounts.   
The impact of the new requirement is that
arrangements previously accounted for as operating
leases, a right of use asset and a lease liability will be
brought into the balance sheet at 1 April 2024. 
IFRS 16 will be applied retrospectively but with the
cumulative effect recognised at 1 April 2024. This means
that right of use assets and lease liabilities will be
calculated as if IFRS 16 had always applied but
recognised in 2024/25 and not by adjusting prior year
figures. 
The Council will apply recognition exemptions to short
term leases and elected not to recognise right of use
assets and lease liabilities that have a term of 12 months
or less and leases of low value assets. 
It is anticipated that the application of the Code’s
adaptation of IFRS 16 will result in the following
additions to the balance sheet:
• £3.502m Property, Plant and equipment (right of
use assets)
• £-3.202m Non-current creditors (lease liabilities)
• £-0.300m Current creditors (lease liabilities) 
Note 32: Accounting Policies –
Renfrewshire Council 
The Financial Statements for the year ended 31 March
2024 have been prepared in accordance with proper
accounting practice as per section 12 of the Local
Government in Scotland Act 2003. Proper accounting
practice comprises the Code of Practice on Local
Authority Accounting in the United Kingdom (the
Accounting Code) and the Service Reporting Code of
Practice, supported by International Financial Reporting
Standards and recommendations made by the Local
Authority (Scotland) Accounts Advisory Committee
(LASAAC). They are designed to give a true and fair view
of the financial performance and position of the Council
and comparative figures for the previous financial year
are provided. There are no significant departures from
these recommendations.  
The accounts have been prepared under the historic
cost convention, other than changes resulting from the
revaluation of certain categories of non-current assets
and financial instruments, and on a going concern basis. 
A Accruals of Expenditure and Income 
Activity is accounted for in the year that it takes place,
not simply when cash payments are made or received.
In particular:
i) Revenue from the sale of goods or provision of
services is recognised when the performance
obligation relating to the transaction has been
satisfied, and it is probable that the economic
benefits or service potential associated with the
transaction will flow to the Council.
ii) Supplies are recorded as expenditure when they are
consumed. Where there is a gap between the date
supplies are received and their consumption, they
are carried as inventories on the Balance Sheet.
Works are charged as expenditure when they are
completed, before which they are carried as assets
under construction on the Balance Sheet.
iii) Interest payable on borrowings and receivable on
investments is accounted for on the basis of the
effective interest rate for the relevant financial
instrument. Interest receivable and dividend income
is recognised when it is probable that the economic
benefits or service potential associated with the
transaction will flow to the Council.
iv) Where income and expenditure have been
recognised but cash has not been received or paid, a
debtor or creditor for the relevant amount is
recorded in the Balance Sheet. Where there is
evidence that debts are unlikely to be settled, the
balance of debtors is written down and a charge
made to revenue for the income that might not be
collected.
v) Supplier invoices paid in the two weeks following
the year-end are accrued together with specific

Page 86

83 
Annual Accounts 2023/24
accruals in respect of further material items
provided the goods or services were received by 31
March 2024 or relate to services associated with the
prior financial year. 
B Business Improvement District 
Following the formation of the Paisley First BID company
on 15 January 2015, the Council has entered into an
agreement to act as the billing body for the purposes of
the Planning etc. (Scotland) Act 2006 and the
Regulations and is responsible for the administration,
collection and recovery of the BID Levy.  As the Council
is acting as agent for the BID company, no transactions
in relation to the BID levy or BID Revenue Account are
included in the CIES with the exception of any
contribution made by the Council to the BID project, the
costs and income related to the collection of the BID
levy or any income from the BID company in relation to
services provided. 
C Cash and Cash Equivalents 
Cash is defined as cash in hand and deposits repayable
on demand less overdrafts repayable on demand. Cash
equivalents are defined as call accounts, money market
funds and instant deposits. Fixed term deposits are not
classified as cash or cash equivalents as these are held
for investment purposes rather than for meeting short-
term cash commitments. 
D Charges for the Use of Assets 
Services are charged for the use of assets no matter how
they are financed, and this charge includes a provision
for depreciation where appropriate. 
E Contingent Assets and Liabilities 
Contingent assets and liabilities are not recognised in
the financial statements but are disclosed as a note to
the accounts where they are deemed material. 
F Employee Benefits 
Benefits payable during employment 
All salaries and wages earned up to 31 March 2024 are
included in the Accounts irrespective of when payment
was made. An accrual is made for the cost of holiday
entitlements earned by employees, but not taken before
the year end and which employees may carry forward
into the next financial year; along with any pay inflation
agreed for the year and not yet paid. 
Termination benefits 
Termination benefits are amounts payable as a result of
a decision by the Council to terminate an officer’s
employment before the normal retirement date or an
officer’s decision to accept voluntary redundancy. They
are charged on an accruals basis to the relevant service
line in the CIES when the Council is demonstrably
committed to either terminating the employment of an
officer or making an offer to encourage voluntary
redundancy. The Council is only demonstrably
committed to a termination when it has a detailed
formal plan for the termination, and it is without
realistic possibility of withdrawal. 
Where termination benefits involve the enhancement of
pensions, statutory provisions require the General Fund
balance to be charged with the amount payable by the
Council to the pension fund or pensioner in the year, not
the amount calculated according to the relevant
accounting standards. In the Movement in Reserves
Statement, appropriations are required to and from the
Pensions Reserve to remove the notional debits and
credits for pension enhancement termination benefits
and to replace them with debits for the cash paid to the
pension fund and pensioners and any such amounts
payable but unpaid at the year-end. 
Post-employment benefits 
The Council participates in two formal pension schemes:
the Local Government Pension Scheme which is
administered by Strathclyde Pension Fund; and the
Scottish Teachers’ Superannuation Scheme. Liabilities

Page 87

84 
Annual Accounts 2023/24
for the Scottish Teachers’ Superannuation Scheme
cannot be identified specifically to the Council;
therefore, the scheme is accounted for as a defined
contributions scheme. 
The Local Government Pension Scheme is accounted for
as a defined benefit scheme in accordance with
International Accounting Standard 19 (IAS19) (as revised
in 2011). Renfrewshire Council's share of the net
pension asset or liability in Strathclyde Pension Fund
and a pension reserve are recognised in the Balance
Sheet. The CIES recognises changes during the year in
the pension asset or liability. Service expenditure
includes pension costs based on employers' pension
contributions payable and payments to pensioners in
the year. Liabilities are included in the Balance Sheet on
an actuarial basis using the projected unit method.
Liabilities are discounted to their value at current prices
using a discount rate based on the indicative rate of
return on high quality corporate bonds. Assets are
included in the Balance Sheet at their fair value,
principally the bid price for quoted securities, and
estimated fair value for unquoted securities. 
G Events after the Balance Sheet date 
Events after the Balance Sheet date are those events
that occur between the end of the reporting period and
the date when the Statements are authorised for issue.
There are two types of events:
• Adjusting events – those that provide evidence of
conditions that existed at the end of the reporting
period, and the Statements are adjusted to reflect
such events
• Non-adjusting events – those that are indicative of
conditions that arose after the reporting period, and
the Statements are not adjusted. 
Events taking place after the date of authorisation for
issue are not reflected in the Statements. 
H Prior Period Adjustments 
When items of income and expense are material, their
nature and amount is disclosed separately, either on the
face of the CIES or in the notes to the accounts,
depending on how significant the items are to an
understanding of the Council’s financial performance. 
Where there has been a change in accounting policy,
that change will be applied retrospectively.  Where
there has been a change in accounting estimate, that
change will be applied prospectively. Where a material
misstatement or omission has been discovered relating
to a prior period, that misstatement or omission will be
restated unless it is impracticable to do so. 
I Financial Instruments 
Financial Assets 
Financial assets are classified into three categories of
valuation:
• At amortised cost;
• At fair value through other comprehensive income –
designated equity instruments; and
• At fair value through profit or loss. 
Financial Assets Measured at Amortised Cost 
Financial assets measured at amortised cost are
recognised on the Balance Sheet when the Council
becomes a party to the contractual provisions of a
financial instrument and are initially measured at fair
value. They are subsequently measured at their
amortised cost. Annual credits to the Financing and
Investment Income and Expenditure line in the CIES for
interest receivable are based on the carrying amount of
the asset multiplied by the effective rate of interest for
the instrument. For most of the loans made by the
Council, this means that the amount presented in the
Balance Sheet is the outstanding principal receivable
(plus accrued interest) and interest credited to the CIES
is the amount receivable for the year in the loan
agreement. 
Any gains and losses that arise on the derecognition of
an asset are credited or debited to the Financing and
Investment Income and Expenditure line in the CIES. The
Council has assets such as investments and debtors
which are classified as financial assets measured at
amortised cost.

Page 88

85 
Annual Accounts 2023/24 
Financial Assets Measured at Fair Value through other
Comprehensive Income (FVOCI) 
Financial assets that are measured at FVOCI are
recognised on the Balance Sheet when the Council
becomes party to the contractual provisions of a
financial instrument and are initially measured and
carried at fair value. Investment income is credited to
Financing and Investment Income and Expenditure in
the CIES when it becomes receivable by the Council.
Where an equity instrument is designated as FVOCI,
changes in fair value are posted to Other
Comprehensive Income and Expenditure and are
balanced by an entry in the Financial Instruments
Revaluation Reserve (an unusable reserve). 
When the asset is derecognised, the cumulative gain or
loss previously recognised in Other Comprehensive
Income and Expenditure is transferred from the
Financial Instruments Revaluation Reserve and
recognised in the Surplus or Deficit on the Provision of
Services. The Council has made an irrevocable election
to designate these assets as FVOCI on the basis that they
are held for non-contractual benefits, not for trading,
but for strategic purposes. 
Financial assets measured at fair value through profit
and loss 
Assets are recognised on the Balance Sheet when the
Council becomes a party to the contractual provisions of
a financial instrument and are initially measured and
carried at fair value. Where there are no fixed or
determinable payments, income (e.g. dividends) is
credited to the CIES when it becomes receivable by the
Council. 
Assets values are based on the following principles:
• instruments with quoted market prices – the market
price
• other instruments with fixed and determinable
payments – discounted cash flow analysis
• equity shares with no quoted market prices –
independent appraisal of company valuations. 
Any gains and losses that arise on the derecognition of
the asset are credited/debited to the Financing and
Investment Income and Expenditure line in the CIES.
Where fair value cannot be measured reliably, the
instrument is carried at cost (less any impairment
losses). 
Expected Credit Loss Model 
Where assets are identified as impaired as a result of an
expected credit loss, the asset is written down and a
charge made to the Financing and Investment Income
and Expenditure line in the CIES. If the asset has fixed or
determinable payments, the impairment loss is
measured as the difference between the carrying
amount and the present value of the revised future cash
flows discounted at the asset’s original effective interest
rate. Otherwise, the impairment loss is measured as any
shortfall of fair value against the acquisition cost of the
instrument (net of any principal repayment and
amortisation). 
Financial Liabilities 
Financial liabilities are recognised on the Balance Sheet
when the Council becomes a party to the contractual
provisions of a financial instrument and initially
measured at fair value and carried at their amortised
cost. Annual charges to the Financing and Investment
Income and Expenditure line in the CIES for interest
payable are based on the carrying amount of the
liability, multiplied by the effective rate of interest for
the instrument. The effective interest rate is the rate
that exactly discounts estimated future cash payments
over the life of the instrument to the amount at which it
was originally recognised. For most of the borrowings
that the Council has, this means that the amount
presented in the Balance Sheet is the outstanding
principal repayable (plus accrued interest) and interest
charged to the CIES is the amount payable for the year
according to the loan agreement. 
Gains and losses on the repurchase or early settlement
of borrowing are credited and debited to the Financing
and Investment Income and Expenditure line in the
Income and Expenditure Account in the year of
extinguishment. However, where repurchase has taken
place as part of a restructuring of the loan portfolio that

Page 89

86 
Annual Accounts 2023/24
involves the modification or exchange of existing
instruments, the premium or discount is respectively
deducted from or added to the amortised cost of the
new or modified loan and the write-down to the CIES is
spread over the life of the loan by an adjustment to the
effective interest rate. 
Where premiums and discounts have been charged to
the CIES, regulations allow the impact on the General
Fund Balance to be spread over future years. The
Council has a policy of spreading the gain/loss over the
term that was remaining on the loan against which the
premium was payable or discount receivable when it
was repaid. The reconciliation of amounts charged to
the CIES to the net charge required against the General
Fund Balance is managed by a transfer to or from the
Financial Instruments Adjustment Account in the
Movement in Reserves Statement. 
Financial Guarantees 
Financial guarantees are recognised at fair value
assessed as the probability of the guarantees being
called and the likely amount payable under the
guarantees. 
Loans Fund 
The Council operates a Loans Fund and all loans raised
are paid into the Fund.  Advances are made to
departments to finance capital expenditure during the
year. Repayments to the Loans Fund are calculated
using the annuity method. 
The local Authority (Capital Financing and Accounting)
(Scotland) Regulations 2016 - loans fund accounting
came into force on 1 April 2016 and replaced the
statutory provisions for local authority borrowing,
lending and loans funds as set out in Schedule 3 of the
local Authority (Scotland) Act 1975. The regulations
contain the following provisions in respect of the loans
fund:
• Regulation 12 places a duty on a local authority to
maintain a loans fund, which is to be administered in
accordance with the proper accounting practices
and prudent financial management, 
• Regulation 13 requires a local authority to make
loans fund advances each year for expenditure of or
lending to third parties by, the local authority which
it has determined should be met from borrowing,
and 
• Regulation 14 requires a local authority to
determine for each loans fund advance the period
over which it will be repaid and the amount of each
repayment. Both the period and the annual amounts
must be considered by the authority to be prudent. 
Interest is calculated and allocated to the CIES in
accordance with Local Authorities Scotland Accounts
Advisory Committee’s (LASAAC) Guidance Note 2:
Statement on the Calculation and Allocation of Loans
Fund Interest and Expenses. 
Financial Instruments - Fair Value
Measurement 
Fair value is defined as the price that would be received
to sell an asset or paid to transfer a liability in an orderly
transaction between market participants at the
measurement date. The fair value measurement
assumes that the transaction to sell the asset or transfer
the liability take place either in the principal market for
that asset or liability or, in the absence of a principal
market, in the most advantageous market for the asset
or liability. 
The fair value of an asset or liability is measured using
the assumptions that market participants would use
when pricing the asset or liability, assuming that market
participants act in their economic best interest. 
Valuation techniques used are appropriate in the
circumstances and have sufficient data available,
maximising the use of relevant observable inputs and
minimising the use of unobservable inputs. 
Inputs to the valuation techniques in respect of assets
and liabilities for which fair value is measured or
disclosed in the financial statements are categorised
within the fair value hierarchy, as follows: 
• Level 1 – quoted prices (unadjusted) in active
markets for identical assets or liabilities that the
authority can access at the measurement date

Page 90

87 
Annual Accounts 2023/24
• Level 2 – inputs other than quoted prices included
within Level 1 that are observable for the asset or
liability, either directly or indirectly 
• Level 3 – unobservable inputs for the asset or
liability. 
The fair value hierarchy gives priority to quoted prices
(unadjusted) in active markets for identical assets or
liabilities (Level 1 inputs) and the lowest priority to
unobservable inputs (Level 3 inputs). 
J Government Grants and other
Contributions
Government grants and third-party contributions and
donations are recognised as due to the Council when
there is reasonable assurance that:
• the Council will comply with the conditions attached
to the payments; and
• the grants or contributions will be received. 
Amounts recognised as due to the Council are not
credited to the CIES until conditions attaching to the
grant or contribution have been satisfied. Monies
advanced as grants and contributions for which
conditions have not been satisfied are carried in the
Balance Sheet as creditors. When conditions are
satisfied, the grant or contribution is credited to the
relevant service line or Taxation and Non-Specific Grant
Income in the CIES. 
Where capital grants are credited to the CIES, they are
reversed out of the General Fund Balance in the
Movement in Reserves Statement. Where the grant has
yet to be used to finance capital expenditure, it is
posted to the Capital Grants Unapplied Account. Where
it has been applied, it is posted to the Capital
Adjustment Account. Amounts in the Capital Grants
Unapplied Account are transferred to the Capital
Adjustment Account once they have been applied. 
K Heritage Assets 
The Council’s heritage assets are held in the museums
operated by OneRen (Paisley Museum and Art Gallery,
Renfrew Town Hall and Museum, and The Secret
Collection). The purpose of holding these assets
according to the Museums’ Statement of Purpose is “to
enhance public understanding of the human and natural
world, principally by the use of original objects”.
Heritage assets are recognised and measured (including
the treatment of revaluation gains and losses) in
accordance with the Council’s accounting policies on
property, plant and equipment. However, some of the
measurement rules are relaxed in relation to heritage
assets. 
The accounting policies in relation to heritage assets
that are deemed to include elements of intangible
heritage assets are also presented below. Purchased
acquisitions are recognised at cost and donated
acquisitions are recognised at valuation with reference
to appropriate commercial markets. 
Acquisitions are made in line with the approved
Acquisition and Disposal Policy. The collections of
heritage assets are accounted for as follows:

Page 91

88 
Annual Accounts 2023/24
Art Collection The collection includes fine, contemporary and applied art works. The collection is included
in the balance sheet at market value where this is available (from external valuations
provided by suitably experienced and knowledgeable experts) or insurance valuations
provided by the relevant collection curator. The assets within the collection are deemed to
have indeterminate lives and a high residual value, and therefore no depreciation is charged.
Shawl and textile
design 
The museums hold a collection of approximately 1,000 Paisley-type shawls, and a
considerable collection of original designs for shawl manufacture. The collection is included
in the balance sheet at insurance valuation which is based on market values. The assets
within the collection are deemed to have indeterminate lives and a high residual value, and
therefore no depreciation is charged.
Natural History The collection includes vertebrate and invertebrate zoology, botany, geology and microslide
collections; in addition to a library of natural history books.
The collection is included in the balance sheet at insurance valuation which is based on
market values. The assets within the collection are deemed to have indeterminate lives and a
high residual value, and therefore no depreciation is charged.
Human History The museums hold collections relating to social history, transport, science (including an
important collection of astronomical apparatus in Coats Observatory), archaeology, arms,
local archives, numismatics, photography, textiles, ethnography and Egyptology. The
collection is included in the balance sheet at insurance valuation which is based on market
values. However, where an external valuation or cost information is available, or a valuation
may be secured at a cost which is not prohibitive relative to the value of the item, then the
Council will recognise the asset in the balance sheet at this value.
The assets within the collection are deemed to have indeterminate lives and a high residual
value, and therefore, no depreciation is charged.
In addition to the museum collections, there are a
number of public space statues, monuments,
memorials, fountains and outdoor artworks at various
locations throughout Renfrewshire. These assets are not
generally recognised in the balance sheet. The Council
considers that obtaining valuations would involve
disproportionate cost and that reliable cost or valuation
information cannot be obtained for these items. This is
because of the diverse nature of assets held, the
number of assets and the lack of comparable data.
However, where reliable cost information can be
reasonably obtained, the asset will be included in the
balance sheet. 
The carrying amounts of heritage assets are reviewed
where there is evidence of impairment for heritage
assets, eg where an item has suffered physical
deterioration or breakage or where doubts arise as to its
authenticity. Any impairment is recognised and
measured in accordance with the Council’s general
policies on impairment. Heritage assets will occasionally
be disposed of in accordance with the approved
Acquisitions and Disposal Policy (a copy of which is
available). Assets are only disposed of for curatorial
reasons (eg the item has deteriorated to such an extent
it is no longer suitable for public display) and not with
the aim of generating funds. Any proceeds of such items
are accounted for in accordance with the Council’s
general provisions relating to the disposal of property,
plant and equipment. Disposal proceeds are disclosed
separately in the notes to the financial statements and
are accounted for in accordance with statutory
accounting requirements relating to capital expenditure
and capital receipts. Expenditure incurred in preserving
individual items is recognised in the CIES. 
L Intangible Assets 
The Council accounts for purchased software licences as
Intangible Assets. Expenditure on intangible assets is

Page 92

89 
Annual Accounts 2023/24
capitalised when it is expected that future economic
benefits or service potential will flow from the
intangible asset to the Council. Items costing less than
£9,000 are not treated as Intangible Assets. 
Intangible assets are measured initially at cost. Amounts
are not revalued, as the fair value of the assets held by
the Council cannot be determined by reference to an
active market. The depreciable amount of an intangible
asset is amortised over its useful life. An asset is tested
for impairment whenever there is an indication that the
asset might be impaired. Any gain or loss arising on the
disposal or abandonment of an intangible asset is
posted to the Other Operating Expenditure line in the
CIES. 
Where expenditure on intangible assets qualifies as
capital expenditure for statutory purposes,
amortisation, impairment losses and disposal gains and
losses are not permitted to have an impact on the
General Fund Balance. The gains and losses are
therefore reversed out of the General Fund Balance in
the Movement in Reserves Statement and posted to the
Capital Adjustment Account and (for any sale proceeds
greater than £10,000) the Capital Receipts Reserve. 
M Interests in Companies and Other
Entities 
The Council has material interests in two charitable
companies, two limited liability partnership and Joint
Boards and Committees that have the nature of
subsidiaries and associates under accounting
conventions, requiring it to prepare group accounts. In
the Council’s own single-entity accounts, these interests
are not recorded as the Council has no shares in, or
ownership of, any of these organisations.
Reflected in the Council’s single-entity balance sheet is a
50% share in an Integration Joint Board, which is
recorded as an investment. 
N Inventories 
Inventories (generally consumable stock) are included in
the Balance Sheet at weighted average cost. The Code
requires inventories to be held at lower of cost or Net
Realisable Value. Weighted average cost is used as the
measure of cost. 
O Investment Property 
Investment properties are those that are used solely to
earn rentals and/or for capital appreciation. Investment
properties are measured initially at cost and
subsequently at fair value. Properties are not
depreciated but are revalued annually according to
market conditions at the year-end. Gains and losses on
revaluation are posted to the Financing and Investment
Income and Expenditure line in the CIES. The same
treatment is applied to gains and losses on disposal.
Rentals received in relation to investment properties are
credited to the Financing and Investment Income line
and result in a gain for the General Fund Balance. 
However, revaluation and disposal gains and losses are
not permitted by statutory arrangements to have an
impact on the General Fund Balance. The gains and
losses are therefore reversed out of the General Fund
Balance in the Movement in Reserves Statement and
posted to the Capital Adjustment Account and (for any
sale proceeds greater than £10,000) the Capital Receipts
Reserve. 
P Leases 
Leases are classified as finance leases where the terms
of the lease transfer substantially all the risks and
rewards incidental to ownership of the property from
the lessor to the lessee. All other leases are classified as
operating leases.  Where a lease covers both land and
buildings, the land and buildings elements are
considered separately for classification. 
The Council as Lessee 
Finance Leases
Property, plant and equipment held under a finance
lease is recognised on the Balance Sheet at the
commencement of the lease at its fair value measured
at the lease’s inception (or the present value of the
minimum lease payments, if lower).

Page 93

90 
Annual Accounts 2023/24
The asset recognised is matched by a liability for the
obligation to pay the lessor. Initial direct costs of the
Council are added to the carrying amount of the asset.
Premiums paid on entry into a lease are applied to
writing down the lease liability. 
Lease payments are apportioned between:
• a charge for the acquisition of the interest in the
property – applied to write down the lease liability,
and
• a finance charge (debited to the CIES). 
Property, Plant and Equipment recognised under finance
leases is accounted for using the policies applied
generally to such assets, subject to depreciation being
charged over the lease term if this is shorter than the
assets estimated useful life. 
Operating Leases
Rentals paid under operating leases are charged to the
CIES. Title to the property, plant or equipment remains
with the lessor. 
The Council as Lessor 
Finance Leases
Where the Council grants a finance lease over a
property or an item of plant or equipment, the relevant
asset is written out of the Balance Sheet as a disposal. 
Lease rentals receivable are apportioned between:
• a capital receipt for the disposal of the asset –
applied to write down the Debtor (together with any
premiums received); and
• finance income (credited to the CIES). 
Operating Leases
Where the Council grants an operating lease over a
property or an item of plant or equipment, the asset is
retained in the Balance Sheet. Rental income is credited
to the CIES. 
Q Overheads and Central Support
Costs 
Where internal costs are allocated to user departments,
the basis of allocation varies by originating department,
for example the cost of Payroll Services may be
allocated on the number of payslips per service.  In
many instances the allocation is time-based.  Internal
transactions are no longer present in the income and
expenditure figures reported in the CIES. 
R Service Concession Arrangements –
School Buildings and Other Facilities 
The Council carries the assets used under PFI or Service
Concession contracts on its Balance Sheet as part of
Property, Plant and Equipment. The original recognition
of these assets at fair value (based on the cost to
purchase the property, plant and equipment) was
balanced by the recognition of a liability for amounts
due to the scheme operator to pay for the capital
investment. 
The accounting treatment of the contractual
arrangements are in accordance with IFRIC12 Service
Concession Arrangements. 
S Property, Plant and Equipment 
Assets that have physical substance and are held for use
in the production or supply of goods or services, for
rental to others or for administrative purposes, and that
are expected to be used during more than one financial
year are classified as Property, Plant and Equipment. 
Recognition
Expenditure on the acquisition, creation or
enhancement of Property, Plant and Equipment is
capitalised on an accruals basis. Expenditure that
maintains but does not add to an asset’s potential to
deliver future economic benefits or service potential is
charged as an expense when it is incurred.

Page 94

91 
Annual Accounts 2023/24
Measurement
Assets are initially measured at cost, comprising:
• the purchase price;
• any costs attributable to bringing the asset to the
location and condition necessary for it to be capable
of operating. 
The cost of assets acquired other than by purchase is
deemed to be its fair value. The valuation of work-in-
progress is based on cost plus an appropriate proportion
of overheads, together with attributable profits and
allowances for foreseeable losses. 
Plant, furniture and computer equipment costing less
than £9,000 are not treated as fixed assets. This de-
minimis level does not apply where certain categories of
these assets are grouped together and form part of the
approved capital programme. 
Donated assets are measured initially at fair value. The
difference between fair value and any consideration
paid is credited to the CIES. Where gains are credited to
the CIES, they are reversed out of the General Fund
Balance to the Capital Adjustment Account. 
Assets are then carried in the Balance Sheet using the
following measurement bases:
• infrastructure, community assets and assets under
construction – depreciated historical cost;
• council dwellings – fair value, determined using the
basis of existing use value for social housing (EUV-
SH). Council dwellings are valued using a Beacon
Principle (adjusted vacant possession) methodology
in accordance with the Royal Institution of Chartered
Surveyors (RICS) guidance;
• Vehicles, plant, furniture and equipment –
depreciated replacement cost;
• Other land and buildings – fair value, determined as
the market value amount that would be paid for the
asset in its existing use (existing use value – EUV).
Operational assets are shown at the lower of net
current replacement cost or net realisable value in
existing use. Non-operational assets are shown at
the lower of net current replacement cost or net
realisable value.
Where there is no market-based evidence of fair value
because of the specialist nature of an asset, depreciated
replacement cost is used as an estimate of fair value. 
Assets included in the Balance Sheet at fair value are
revalued sufficiently regularly to ensure that their
carrying amount is not materially different from their
fair value at the year-end, but as a minimum every five
years. The effective date of any revaluation is 31 March. 
Valuations are undertaken by the Council Valuer who is
MRICS qualified. Increases in valuations are matched by
credits to the Revaluation Reserve to recognise
unrealised gains. The Revaluation Reserve contains
revaluation gains recognised since 1 April 2007 only, the
date of its formal implementation. Gains arising before
that date have been consolidated into the Capital
Adjustment Account. 
Fair Value Measurement
The authority measures some of its non-financial assets
such as surplus assets and investment properties at fair
value at each reporting date. Fair value is the price that
would be received to sell an asset in an orderly
transaction between market participants at the
measurement date. The authority uses valuation
techniques that are appropriate in the circumstances
and for which sufficient data is available, maximising the
use of relevant observable inputs and minimising the
use of unobservable inputs. 
Inputs to the valuation techniques in respect of assets
for which fair value is measured are categorised within
the fair value hierarchy as follows:
• Level 1 - quoted prices in active markets for identical
assets that the authority can access at the
measurement date;
• Level 2 - inputs other than quoted prices included
within level 1 that are observable for the asset,
either directly or indirectly;
• Level 3 - unobservable inputs for the asset.

Page 95

92 
Annual Accounts 2023/24
Impairment
Assets are assessed at each year-end as to whether
there is any indication that an asset may be impaired.
Where indications exist and any possible differences are
estimated to be material, the recoverable amount of the
asset is estimated, and an impairment loss is recognised
for the shortfall. 
Where impairment losses are identified, they are
accounted for as follows:
• where there is a balance of revaluation gains for the
asset in the Revaluation Reserve, the carrying
amount of the asset is written down against that
balance (up to the amount of the accumulated
gains);
• where there is no balance in the Revaluation
Reserve, the carrying amount of the asset is written
down against the relevant service line(s) in the CIES. 
Where an impairment loss is reversed subsequently, the
reversal is credited to the relevant service line(s) in the
CIES, up to the amount of the original loss, adjusted for
depreciation that would have been charged if the loss
had not been recognised. 
Disposals
When it becomes probable that the carrying amount of
an asset will be recovered principally through a sale
transaction rather than through its continuing use, it is
reclassified as an Asset Held for Sale. The asset is
revalued immediately before reclassification and then
carried at the lower of this amount and fair value less
costs to sell. Where there is a subsequent decrease to
fair value less costs to sell, the loss is posted to the
Other Operating Expenditure line in the CIES. Gains in
fair value are recognised only up to the amount of any
previously losses recognised in the Surplus or Deficit on
Provision of Services. Depreciation is not charged on
Assets Held for Sale. Assets that are to be abandoned or
scrapped are not reclassified as Assets Held for Sale. 
When an asset is disposed of or decommissioned, the
carrying amount of the asset in the Balance Sheet
(whether Property, Plant and Equipment or Assets Held
for Sale) is written off to the Other Operating
Expenditure line in the CIES as part of the gain or loss on
disposal. Receipts from disposals (if any) are credited to
the CIES also as part of the gain or loss on disposal (i.e.
netted off against the carrying value of the asset at the
time of disposal). Any revaluation gains accumulated for
the asset in the Revaluation Reserve are transferred to
the Capital Adjustment Account. 
Amounts received for a disposal in excess of £10,000 are
categorised as capital receipts and are credited to the
Capital Receipts Reserve.
Depreciation
Depreciation is provided for on all Property, Plant and
Equipment assets by the allocation of their depreciable
amounts over their useful lives. An exception is made
for assets without a determinable finite useful life,
investment properties and assets that are not yet
available for use (i.e., assets under construction). 
Deprecation is calculated on the following bases:
• dwellings and other buildings – straight-line
allocation over the useful life of the property of
between 10 and 50 years as estimated by the
Council Valuer
• vehicles, plant and equipment – a percentage of the
value of each class of assets in the Balance Sheet, as
advised by a suitably qualified officer based on
useful lives of between 3 and 30 years.
• infrastructure – straight-line allocation based on
useful lives of between 10 and 60 years. 
General Fund services are charged with depreciation
where appropriate for the use of assets no matter how
they are financed. Depreciation on the Council’s non-
operational assets is not charged to service revenue
accounts. It is however reflected in the CIES through
non-distributable costs.   
Where an item of Property, Plant and Equipment asset
has major components whose cost is significant in
relation to the total cost of the item, the components
are depreciated separately. Significance is determined
by comparing a component’s cost against the overall
cost of an asset, and a component is deemed significant

Page 96

93 
Annual Accounts 2023/24
if its cost is 20% or more of the total asset cost. The de-
minimis threshold for componentisation is £1m. 
Revaluation gains are also depreciated, with an amount
equal to the difference between current value
depreciation charged on assets and the depreciation
that would have been chargeable based on their
historical cost being transferred each year from the
Revaluation Reserve to the Capital Adjustment Account. 
T Provisions 
Provisions are made where an event has taken place
that gives the Council a legal or constructive obligation
that probably requires settlement by a transfer of
economic benefits or service potential, and a reliable
estimate can be made of the amount of the obligation.
Provisions are charged as an expense to the appropriate
service line in the CIES. When payments are eventually
made, they are charged to the provision carried in the
Balance Sheet. Estimated settlements are reviewed at
the end of each financial year. 
U Reserves 
The Council has various reserve funds. The two capital
reserves arising from the system of capital accounting
are the Revaluation Reserve and the Capital Adjustment
Account. The former of these represents the store of
gains on revaluation of fixed assets not yet realised
through sales and the latter relates to amounts set aside
from capital resources to meet past expenditure. 
The two accounting reserves arising from the
restatement of financial instruments to “fair value” are
the Financial Instruments Adjustment Account and the
Financial Instruments Revaluation Reserve. The Financial
Instruments Adjustment Account is a balancing account
to allow for differences in statutory requirements and
proper accounting practices for lending & borrowing by
the Council. The Financial Instruments Revaluation
Reserve is a store of gains or losses on revaluation of the
investments of the Insurance Fund not yet realised
through sales.   
The Pension Reserve arises from the IAS19 accounting
disclosures for retirement benefits and recognises the
Council's share of actuarial gains and losses in the
Strathclyde Pension Fund and the change in the
Council’s share of the Pension Fund net liability
chargeable to the CIES. 
V Revenue Expenditure Funded from
Capital under Statute 
Expenditure incurred during the year that may be
capitalised under statutory provisions but does not
result in the creation of a non-current asset has been
charged as expenditure to the relevant service in the
CIES in the year. Where the Council has determined to
meet the cost of this expenditure from existing capital
resources or by borrowing, a transfer in the 
Movement in Reserves Statement from the General
Fund Balance to the Capital Adjustment Account then
reverses out the amounts charged so that there is no
impact on the level of Council Tax. 
W Value Added Tax 
Income and Expenditure excludes any amount relating
to Value Added Tax (VAT), as all VAT is payable to HM
Revenue & Customs and all VAT is recoverable from
them.

Page 97

94 
Annual Accounts 2023/24
Note 33: Judgements in Applying Accounting Policies 
In applying the accounting policies, the Council has had to make certain judgements about complex transactions or those
involving uncertainty about future events. Where a judgement has been made, this is referred to in the relevant note to
the core financial statements; however, a summary of those with the most significant effect is detailed below. 
Item Judgement
Public Sector Funding The Council has assessed that anticipated levels of local government funding over the
medium term do not provide sufficient indication that the assets of the Council might be
impaired as a result of a need to close facilities and reduce levels of service provision. This
is discussed further in the Management Commentary.
Service Concession
Arrangements
The Council is deemed to control the services provided under the agreement for the
provision of schools. The accounting policies for PFI schemes and similar arrangements
have been applied and the assets under the contract are included within Property, Plant
and Equipment on the Council’s Balance Sheet.  Bargeddie Waste Facility is shared by a
number of Scottish councils with North Lanarkshire Council taking the lead.  The
apportionment of costs and liabilities over the life of the facility, which was funded by a
service concession agreement, has been agreed between the councils involved and the local
external audit team. Note 15 provides further details.
Impairment of
financial assets
In line with IFRS9: Financial Instruments, the approach to impairment of financial assets
depends on the type of asset being assessed, either using a ‘historic loss rate’ approach, or
a ‘probability of default’ approach, whereby historical experience of default rates across a
similar class of instrument and credit rating is used to estimate 12-month expected credit
losses. Further detail can be found at Note 22: Financial Instruments.
Determination of
Contingent Liabilities
and Provisions
A Provision is defined by the Code as a liability of uncertain timing or amount. A Contingent
Liability is a possible obligation whose timing or value cannot be reliably measured and the
Council makes a judgement on which is appropriate based on information available at the
Balance Sheet date.
Rolling Valuation
Programme
The Council employs professional valuers who are registered with the Royal Institution of
Chartered Surveyors. These valuers carry out regular reviews of the value of assets
reported in the Balance Sheet and any significant changes in value are processed as asset
revaluations or impairments. These values are based on their professional opinion using
available market information at the time of assessment. Due to the high number of assets,
a rolling programme of asset valuation has been established for many years, with the aim
of revaluing one fifth of the portfolio each financial year. This carries inherent risk that
assets not valued in-year have been subject to material changes in value. The highest risk in
this respect relates to assets valued using the Depreciated Replacement Cost (DRC) method,
which for Renfrewshire Council, includes schools and leisure centres. To mitigate for this
risk, a desktop exercise was undertaken for 2023/24 accounts to estimate the potential
increase in value of all DRC assets not valued in-year and reflected any material adjustment
required in these accounts.

Page 98

95 
Annual Accounts 2023/24
Note 34: Assumptions made about the future 
The Annual Accounts contains estimated figures that are based on assumptions made by the Council about the future or
that are otherwise uncertain.  Estimates are made taking into account historical experience, current trends and other
relevant factors. However, because balances cannot be determined with certainty, actual results could be materially
different from the assumptions and estimates. The items in the Council’s Balance Sheet as at 31 March 2024 for which
there is a significant risk of material adjustment in the forthcoming financial year are as follows: 
Item Uncertainty Effect if results differ from assumption
Pensions
Liability
Estimation of the net liability to pay pensions
depends on a number of complex judgements
relating to the discount rate used, the rate at
which salaries are projected to increase, changes
in retirement ages, mortality rates and expected
returns on pension fund assets. A firm of
consulting actuaries is engaged to provide the
Council with expert advice about the
assumptions to be applied. The carrying value of
the net pension asset was £492.9m, before the
asset cap, as at 31 March 2024 (asset of £434m
as at 31 March 2023). Further detail can be found
in Note 28: Defined Benefit Pension Schemes.
The effects on the net pension asset of changes
in individual assumptions can be measured. For
instance, a 0.1% decrease in the discount rate
assumption would result in a decrease in the
pension asset of £22.0m. However, the
assumptions interact in complex ways. At 31
March 2024, the Council’s actuaries advised that
(before the asset cap is applied) the net pensions
asset had decreased by £44.8m as a result of
estimates being corrected as a result of
experience; decreased by £20.7m as a result of
updating demographic assumptions; and
increased by £111.8m as a result of updating
financial assumptions.
Debt
Impairment
At 31 March 2024, the Council had a balance for
long and short term debtors (including council
tax, rent arrears and trade debtors) of £68m. A
review of significant balances suggested that an
impairment of doubtful debts of £39.7m was
appropriate. However, in the current economic
climate it is not certain that such an allowance
would be sufficient. Over 2023/24, the principal
debt impairment increases related to Council Tax
and Other Entities & Individuals, which increased
by £3.1m.
Based on experience, the bad debt provision is
considered adequate; however, if collection rates
were to deteriorate, a 10% increase in the
amount of potential impairment losses would
require an additional £4m to be set aside as an
allowance.

Page 99

96 
Annual Accounts 2023/24
Common Good Funds 
The Common Good Funds comprise land granted to a Burgh by the Crown; further grants of land and buildings, mainly in
the late 19th and early 20th century by local industrialists and other landowners for the common good of the inhabitants
of the Burgh; and rental income and sale proceeds from such land. The bulk of the Paisley Common Good was granted to
the Burgh of Paisley by the King Charles II Charter, dated 27 and 28 July 1666, and has been administered by the Burgh
and its successors since that date. The bulk of the Renfrew Common Good was granted to the Royal Burgh of Renfrew by
the Queen Anne Charter, dated 7 August 1703, and again has been administered by the Burgh and its successors since
that date. 
Income and expenditure statement 
Paisley Johnstone Renfrew Total
£m £m £m £m
Expenditure 0.260 0.000 0.786 1.046
Income   (0.534) 0.000 (3.261) (3.795)
(Surplus)/Deficit for the year (0.274) 0.000 (2.475) (2.749)
(Surplus)/Deficit Brought Forward (6.099) (0.052) (33.703) (39.854)
Accumulated (Surplus)/Deficit at 31 March 2024 (6.373) (0.052) (36.178) (42.603)
Income and Expenditure Statement for the Year Ending
31 March 2024
Paisley Johnstone Renfrew Total
£m £m £m £m
Expenditure 0.739 0.000 2.682 3.421
Income   (0.192) 0.000 (1.622) (1.814)
(Surplus)/Deficit for the year 0.547 0.000 1.060 1.607
(Surplus)/Deficit Brought Forward (6.646) (0.052) (34.763) (41.461)
Accumulated (Surplus)/Deficit at 31 March 2023 (6.099) (0.052) (33.703) (39.854)
Income and Expenditure Statement for the Year Ending
31 March 2023
Balance Sheet 
Paisley Johnstone Renfrew Total
£m £m £m £m
Tangible Fixed Assets 0.846 0.000 13.571 14.417
Heritage Assets 0.063 0.046 0.109 0.218
Investments 5.098 0.000 19.502 24.600
Debtors 0.000 0.000 0.133 0.133
Short-term deposits 0.371 0.006 2.892 3.269
Total assets 6.378 0.052 36.207 42.637
Creditors: Amounts Falling Due Within One Year (0.005) 0.000 (0.027) (0.032)
Net Assets 6.373 0.052 36.180 42.605
Income Funds (3.629) (0.036) (21.330) (24.995)
Revaluation reserve: Investments (1.309) 0.000 (4.570) (5.879)
Revaluation reserve: Fixed Assets (1.435) (0.016) (10.280) (11.731)
Total Reserves (6.373) (0.052) (36.180) (42.605)
Balance Sheet as at 31 March 2024

Page 100

97 
Annual Accounts 2023/24
Balance Sheet as at 31 March 2023 Paisley Johnstone Renfrew Total
£m £m £m £m
Tangible Fixed Assets 0.928 0.000 13.024 13.952
Heritage Assets 0.063 0.046 0.109 0.218
Investments 4.737 0.000 18.114 22.851
Debtors 0.027 0.000 0.136 0.163
Short term deposits 0.350 0.006 2.347 2.703
Total assets 6.105 0.052 33.730 39.887
Creditors: Amounts Falling Due Within One Year (0.006) 0.000 (0.027) (0.033)
Net Assets 6.099 0.052 33.703 39.854
Income Funds (3.747) (0.036) (21.391) (25.174)
Revaluation reserve: Investments (0.916) 0.000 (2.999) (3.915)
Revaluation reserve: Other Fixed Assets (1.436) (0.016) (9.313) (10.765)
Total Reserves (6.099) (0.052) (33.703) (39.854) 
Accounting Policies and Note 
Accounting Policies adopted for the Common Good are the same as those adopted for Renfrewshire Council except for
the application of IAS 16. IAS 16 requires that assets be depreciated and that the charge for depreciation be set against
and surplus in the Income and Expenditure account. In addition, IAS 16 requires any decreases in the value of assets to
be recognized in the Income and Expenditure account, unless there is a previous increase in the value of the asset held in
the Revaluation Reserve. Conversely, any increases in the value of assets are to be recognized in the surplus or deficit in
the Income and Expenditure account, to the extent that it reverses a decrease of the same asset previously recognized in
the Income and Expenditure account. 
The Council is required to make arrangements for the proper administration of its financial affairs and to ensure that one
of its officers has the responsibility for the administration of those affairs. The Director of Finance and Resources has
been designated as that officer in Renfrewshire Council. They manage the affairs of the Council to secure the economic,
efficient and effective use of resources and safeguard its assets and those of any charitable trust it controls. Given that
the Common Good is owned by the Council, these specific provisions are supplemented by the general provisions
relating to the administration of local authority monies, i.e., the duty to obtain best value. 
Income to the Common Good Funds is solely from investment returns (both financial investments and property rental
income) and bank interest; no donations to the Funds are solicited. The only other source of income, which arises
periodically, is from the sale of fixed assets. 
The investment performance of the Common Good Funds is monitored regularly by Council officers and is reported bi-
annually to the Investment Review Board, which is comprised of five cross-party elected members. The minutes of the
Investment Review Board are submitted to the Finance, Resources and Customer Services Policy Board, whose meetings
are held in public. In turn, the minutes of this Board are submitted to the full Council for ratification. Therefore, all
elected members are kept informed of both the performance of the funds and any decision regarding the operation of
the Funds, which would be made by the Finance, Resources and Customer Services Policy Board. 
Revaluation adjustments related to investments are included in Income within the CIES and were £0.361m for Paisley
Common Good and £1.387m for Renfrew Common Good.

Page 101

98 
Annual Accounts 2023/24
Housing Revenue Account
Income and expenditure statement
The Housing Revenue Account (HRA) reflects a statutory obligation to maintain a revenue account for local authority
housing provision in accordance with the Housing (Scotland) Act 1987. The Housing Revenue Account income and
expenditure statement shows the economic cost in the year of providing housing services in accordance with generally
accepted accounting practices, rather than the amount to be funded from rents and government grants. Councils charge
rents to cover expenditure in accordance with regulations; this may be different from the accounting cost. The increase
or decrease in the year, on the basis on which rents are raised, is shown in the movement on the Housing Revenue
Account statement.
2022/23 2023/24
£m £m
19.851 Repairs and maintenance 22.753
14.852 Supervision and management 13.560
27.883 Depreciation and impairment of non-current assets 31.442
0.839 Increase/(Decrease) in the allowance for bad debts 0.900
3.208 Other expenditure 2.709
66.633 Total Expenditure 71.364
(48.115) Dwelling rents (50.701)
(1.185) Non-dwelling rents (1.141)
(1.616) Other income (1.864)
(50.916) Total Income (53.706)
15.717 Net Cost of HRA services as included in the CIES 17.658
HRA share of the operating income and expenditure included in the CIES:
0.276 (Gain)/Loss on sale of HRA non-current assets (0.157)
4.110 Interest payable and similar charges 3.406
(1.704) Interest and investment income (2.787)
0.089 Pensions interest cost and expected return on pensions assets (0.050)
(0.402) Taxation and non specific grant income (2.066)
18.086 Deficit for the year on HRA services 16.004
Movement on the Housing Revenue Account statement
This statement shows the movement in the year on the Housing Revenue Account (HRA) Balance. The surplus or deficit
for the year on the HRA income and expenditure statement represents the true economic cost of providing the Council’s
HRA services, more details of which are shown in the HRA income and expenditure statement itself. 
The adjustments between accounting basis and funding basis under regulations detail the adjustments that are made to
the HRA income and expenditure, as recognised by the Council in the year in accordance with proper accounting
practice, to the statutory amounts required to be charged to the HRA Balance for dwellings rent setting purposes. An
analysis of these adjustments can be found in Note 6: Adjustment between accounting basis and funding basis under
regulations on page 46.

Page 102

99 
Annual Accounts 2023/24
2022/23 2023/24
£m £m
(6.497) Balance on the HRA at 1 April (6.497)
18.086 Deficit for the year on the HRA income and expenditure statement 16.004
(6.302) Adjustments between accounting basis and funding basis under statute (0.839)
(11.784) Adjustments to Usable Reserves permitted by accounting standards (14.832)
0.000 Net (Increase)/Decrease before transfers to or from reserves 0.333
(6.497) Balance on the HRA at 31 March (6.164)
Notes to the Housing Revenue Account income and expenditure statement
The number and types of dwelling in the Council’s housing stock
The Council was responsible for managing 12,305 dwellings during 2023/24 (12,216 in 2022/23). The following shows an
analysis of these dwellings by type. The figures below exclude void initiative properties. 
Number Average weekly rent Type of dwelling Number Average weekly rent
419 £65.43 One-apartment 418 £67.46
3665 £75.85 Two-apartment 3,692 £78.62
5853 £88.19 Three-apartment 5,905 £91.75
2065 £100.16 Four-apartment 2,074 £105.12
214 £108.38 Five-apartment 216 £113.82
12,216 Total 12,305
As at 31 March 2023 As at 31 March 2024
Other information
Dwellings Non-Dwellings Total as at 31
March 2024
Total as at 31
March 2023
£m £m £m £m
Void Rent Loss 2.647 0.320 2.967 2.900
Rental Income Arrears 4.423 0.625 5.048 4.850
Provision for uncollectable rent arrears 3.448 0.370 3.818 3.676
Corporate and Democratic Core costs 0.038 0.033

Page 103

100 
Annual Accounts 2023/24
Council Tax Income Account 
The Council Tax income account shows the gross income raised from Council Taxes levied and deductions made under
statute. Councils raise taxes from residents through Council Tax, which is a tax linked to property values. The Council Tax
Reduction Scheme represents a discount introduced across Scotland following the abolition of Council Tax Benefits as
part of the UK government’s Welfare Reform programme. The resultant net income is transferred to the Council’s CIES. 
2022/23 2023/24
£m £m
123.138 Gross council tax levied 131.897
(26.330) Other discounts and reductions (18.072)
(13.143) Council tax reduction scheme (13.865)
(2.707) Write-off of uncollectable debts and allowance for impairment (3.450)
(0.245) Adjustment to previous years’ community charge and council tax (0.982)
80.713 Transfer to the Comprehensive Income and Expenditure Statement 95.528 
Calculation of the Council Tax 
Dwellings are valued by the Assessor and placed within valuation bands ranging from the lowest “A” to the highest “H”. 
The band D Council Tax charge is calculated using the Council Tax base, and this in turn fixes the charge for each of the
other bands, which are based on pre-determined proportions relative to the band D charge. The band D charge for
2023/24 was £1,436.17 (£1,354.88 in 2022/23). 
2022/23 2023/24
£ £
903.26 A 957.45
1,053.79 B 1,117.02
1,204.34 C 1,276.60
1,354.88 D 1,436.17
1,780.17 E 1,886.97
2,201.69 F 2,333.78
2,653.31 G 2,812.50
3,319.46 H 3,518.62
Council Tax Band
If a property is occupied by only one person over 18, a discount of 25% is applied. 
Since 15 July 2016, unoccupied and unfurnished properties have been exempted from Council Tax for the first six
months.  A discount of 10% is then available for the next six months and 100% additional Council Tax levy is then payable
for as long as the property remains empty, although the 10% discount may be extended by a further 12 months if the
property is being actively marketed for sale or let.   
Certain persons are disregarded for Council Tax purposes, including students, people who are in detention and those
who are severely mentally impaired. Reductions in Council Tax are available for people with disabilities.

Page 104

101 
Annual Accounts 2023/24
Charges for water and sewerage services are the responsibility of Scottish Water. Renfrewshire Council collects total
monies and makes a precept payment to Scottish Water on the basis of collection levels based on a pre-determined
formula. The figures below exclude the water and sewerage charges. 
Calculation of the Council Tax base 
The Council Tax base is the number of chargeable dwellings across all valuation bands (adjusted for dwellings where
discounts apply), after providing for non-payment, expressed as an equivalent number of band D dwellings. 
Band
Number of
dwellings
Number of
exemptions
Disabled
relief Discounts
Council
Tax
Reduction
Total
equivalent
dwellings
Ratio
to
Band D
2023/24
Band D
equivalent
2022/23
Band D
equivalent
A 13,385 2,218 8 1,921 3,327 5,981 0.67 3,987 3,904
B 25,923 1,691 70 3,348 5,200 15,672 0.78 12,189 11,972
C 15,406 606 58 1,641 1,927 11,216 0.89 9,970 9,848
D 13,491 336 42 1,263 715 11,219 1.00 11,219 11,007
E 11,637 184 84 747 401 10,267 1.31 13,490 13,432
F 7,112 81 46 320 118 6,567 1.63 10,671 10,504
G 4,361 91 20 149 50 4,051 1.96 7,933 7,704
H 205 4 0 10 2 189 2.45 463 470
91,520 Band A dwellings subject to disabled relief 8 8
Class 17 and 24 dwellings 73 73
Sub-total 70,003 68,922
Less: Provision for non-payment and future award of discounts and reliefs -3,780 -4,017
Council Tax Base 66,223 64,905 
Non-Domestic Rates Income Account
This account is an agent’s statement that reflects the statutory obligation for those councils who issue bills to non-
domestic rate payers to maintain a separate non-domestic rate account. The account shows the rates collected from
non-domestic rate payers during the year. Any difference between the rates collected and the amount the Council is
guaranteed to receive under the national pooling arrangements is adjusted via the Scottish Government's general
revenue grant to the Council. Non-domestic rate income is redistributed from the national non-domestic rate pool in
proportions based on the prior year mid-year income returns net of prior year adjustments. In 2012/13 the Scottish
Government introduced the Business Rates Incentivisation Scheme (BRIS) which allows councils, where an agreed target
income figure is exceeded, to retain 50% of the ‘above target’ income.

Page 105

102 
Annual Accounts 2023/24
2022/23 2023/24
£m £m
147.870 Gross rates levied 143.620
(21.774) Reliefs and other deductions (23.339)
(3.543) Write-off of uncollectable debts and allowance for impairment (2.015)
122.553 Net Non-Domestic Rates income 118.266
(1.692) Adjustment to previous years’ non-domestic rates (9.550)
(12.785) Contribution (to)/from the National Non-Domestic Rate pool 22.606
0.000 Non-domestic rate income retained by authority (BRIS) 0.000
108.076 Transfer to the Comprehensive Income and Expenditure Statement 131.322
The nature and amount of each rate fixed
The non-domestic rates charge for each subject is determined by the rateable value placed upon it by the Assessor,
multiplied by the rate per pound (the “rate poundage”) set each year by the Scottish Government. For 2023/24 the
charge was 49.8 pence in the pound, with a 1.3 pence supplement for properties with a rateable value over £51,000 and
a 2.6 pence supplement for properties with a rateable value above £100,000. 
Under the Small Business Bonus Scheme (SBBS), reformed for 2023/24, relief is available to businesses where the
combined rateable value of all business premises is £35,000 or less and the rateable value of individual premises is
£20,000 or less. Properties with a total rateable value up to and including £12,000 are entitled to a 100% reduction in
their business rates.  For those properties with a rateable value between £12,001 and £20,000 relief will be tapered. 
Relief will taper from 100% to 25% for those properties with rateable values between £12,001 and £15,000 and from
25% to 0% for those properties with rateable values between £15,001 to £20,000. 
Analysis of Renfrewshire Council’s rateable values 
2023/24
£m
104.357
47.472
31.476
1.593
102.347
287.245
(8.678)
278.567
(1.580)
276.987Net Rateable Value at 31 March
Analysis of Rateable Values
Commercial
Industrial and freight transport
Education and public service
Communications
Others
Rateable Value at 1 April 
Adjustments (Full Year Rateable Value)
Less: Wholly Exempt Subjects
Rateable Value at 31 March

Page 106

103 
Annual Accounts 2023/24
Group Accounts
Group Comprehensive Income and Expenditure Statement
This statement shows the accounting cost of providing services and managing operations during the year. It includes, on
an accruals basis, all day-to-day expenses and related income. The statement shows the accounting cost in accordance
with generally accepted accounting practices, rather than the cost according to the statutory regulations that specify the
net expenditure that councils need to take into account when setting the annual Council Tax charge. The required
adjustments between accounting basis and funding basis under regulations are shown in the group movement in
reserves statement. 
Gross
expenditure
Gross
income
Net
expenditure Note
Gross
expenditure
Gross
income
Net
expenditure
£m £m £m £m £m £m
294.465 (38.357) 256.108 298.501 (39.097) 259.404
174.401 (63.762) 110.639 251.324 (142.398) 108.926
109.077 (48.963) 60.114 Finance and Resources 105.680 (59.449) 46.231
45.817 (14.132) 31.685 53.264 (18.141) 35.123
18.509 (14.725) 3.784 Miscellaneous Services 20.461 (14.898) 5.563
260.152 (161.744) 98.408 Adult Services 144.335 (44.290) 100.045
902.421 (341.683) 560.738 873.565 (318.273) 555.292
0.103 0.000 0.103 (Gain)/Loss on the disposal
of non-current assets
0.000 (0.302) (0.302)
24.322 (8.244) 16.078 Financing and investment
income and expenditure
G6 21.333 (17.771) 3.562
0.000 (505.934) (505.934) Taxation and non-specific
grant income
3 0.000 (513.914) (513.914)
926.846 (855.861) 70.985 894.898 (850.260) 44.638
8.553 G3 0.830
79.538 45.468
(105.285) (34.152)
3.514 G15 (1.993)
(229.340) 183.067
0.917 G3 0.303
(330.194) Other comprehensive (income) and expenditure 147.225
(250.656) Total comprehensive (income) and expenditure 192.693
Share of other comprehensive (income) and
expenditure of associates and joint ventures
Actuarial (gain)/loss on pension assets and
liabilities
2022/23 (restated) 2023/24
Children’s Services
Chief Executive’s Service
Cost of Services
Deficit/(Surplus) on the
Provision of Services
Share of the (surplus) / deficit on the provision
of services by associates and joint ventures
Group Deficit/(Surplus)
(Surplus)/Deficit on the revaluation of non-
current assets
(Surplus)/Deficit from investments in equity
instruments designated as Fair Value through
Other Comprehensive Income
Environment, Housing and
Infrastructure
Figures shown in brackets represent income or gains and figures without brackets represent expenditure or losses.

Page 107

104 
Annual Accounts 2023/24
Group Movement in Reserves Statement
The group movement in reserves statement shows the movement in the year on the different reserves held by the
Council's group, analysed into the Council's usable reserves, the Council's unusable reserves and the Council's share of
the reserves of the subsidiaries, associates and joint ventures within the group.
2023/24 Council’s
Usable
Reserves
Council’s
Unusable
Reserves
Council’s
Total
Reserves
Council’s share of
Reserves of
Subsidiaries,
Associates and
Joint Ventures
Total
Reserves
Note £m £m £m £m £m
Balance at 1 April 2023 236.051 1,488.674 1,724.725 123.555 1,848.280
Movement in reserves during the year
Total Comprehensive Income and
Expenditure
(47.651) (152.238) (199.889) (9.250) (209.139)
Adjustments between Group accounts
and Council accounts
G5 0.000 0.000 0.000 16.446 16.446
Adjustments to Usable Reserves
permitted by accounting standards
7 36.188 (36.188) 0.000 0.000 0.000
Adjustment for Service Concession
Arrangements
1.597 (1.597) 0.000 0.000 0.000
Adjustments between accounting
basis and funding basis under
regulations
6 (3.968) 3.968 0.000 0.000 0.000
Increase / (Decrease) in year (13.834) (186.055) (199.889) 7.196 (192.693)
Balance at 31 March 2024 222.217 1,302.619 1,524.836 130.751 1,655.587
Comparative movements in
2022/23 (restated) Council’s
Usable
Reserves
Council’s
Unusable
Reserves
Council’s
Total
Reserves
Council’s share of
Reserves of
Subsidiaries,
Associates and
Joint Ventures
Total
Reserves
Note £m £m £m £m £m
Balance at 1 April 2022 214.457 1,278.820 1,493.277 104.347 1,597.624
Movement in reserves during the year
Total Comprehensive Income and
Expenditure
(54.026) 300.399 246.373 4.283 250.656
Adjustments between Group accounts
and Council accounts
G5 (14.925) 0.000 (14.925) 14.925 0.000
Adjustments to Usable Reserves
permitted by accounting standards
37.178 (37.178) 0.000 0.000 0.000
Transfers to / (from) other statutory
reserves
7 0.000 0.000 0.000 0.000 0.000
Adjustment for Service Concession
Arrangements
27.601 (27.601) 0.000 0.000 0.000
Adjustments between accounting
basis and funding basis under
regulations
6 25.766 (25.766) 0.000 0.000 0.000
Increase / (Decrease) in year 21.594 209.854 231.448 19.208 250.656
Balance at 31 March 2023 236.051 1,488.674 1,724.725 123.555 1,848.280

Page 108

105 
Annual Accounts 2023/24
Group Balance Sheet
The group balance sheet shows the value as at 31 March 2024 of the assets and liabilities recognised by the Council. The
net assets of the Council’s group are matched by the reserves held by the group. Reserves are reported in two categories:
usable reserves, which are those reserves that the group may use to provide services, subject to the need to maintain a
prudent level of reserves and any statutory limitations; and unusable reserves, comprising those that the group is not
able to use to provide services. This category includes reserves that hold unrealised gains/losses in the value of assets
where amounts would only become available to provide services if the assets are sold, and reserves that hold timing
differences shown as ‘adjustments between accounting basis and funding basis under regulations’ in the group
movement in reserves statement.
As at 31
March 2023
(restated)
As at 31
March 2024
£m Note £m
1,811.898 Property, plant and equipment G10 1,873.131
44.404 Heritage assets G11 44.404
2.014 Investment property G9 0.415
2.524 Intangible assets 13 1.724
27.008 Long-term investments G15 28.921
55.320 Investments in associates and joint ventures G3 54.187
2.307 Long-term debtors G15 2.090
129.983 Other long-term assets 31.574
2,075.458 2,036.446
0.100 Assets held for sale 12 0.100
166.751 Short-term investments G15 67.755
1.383 Inventories 1.352
67.366 Short-term debtors G12 67.406
13.511 Cash and cash equivalents G15 31.422
249.111 168.035
(94.161) Short-term borrowing G15 (64.348)
(87.644) Short-term creditors G13 (82.432)
(0.252) Short-term provisions 21 (0.721)
(182.057) (147.501)
(65.690) Long-term creditors 20 (63.352)
(4.942) Long-term provisions 21 (4.630)
(223.600) Long-term borrowing G15 (258.931)
0.000 Other long-term liabilities (74.480) 
(294.232) (401.393) Alastair MacArthur
1,848.280 1,655.587
(264.755) Usable reserves G7 (252.396)
(1,583.525) Unusable reserves G8 (1,403.191)
(1,848.280) (1,655.587)
Director of Finance and
Resources
Total reserves
Long-term assets
Current assets
Current liabilities
Long-term liabilities
Net assets
The unaudited accounts were issued on 27 June 2024 and the audited accounts were authorised for issue on 24 October
2024.

Page 109

106 
Annual Accounts 2023/24
Group Cashflow Statement 
The group cash flow statement shows the changes in cash and cash equivalents of the Council’s group during the year. It
shows how the Council generates and uses cash and cash equivalents by classifying cash flows as operating, investing and
financing activities. The amount of net cash flows arising from operating activities is a key indicator of the extent to
which the operations of the Council are funded by way of taxation and grant income or from the recipients of services
provided by the Council. Investing activities represent the extent to which cash outflows have been made for resources
that are intended to contribute to the Council’s future service delivery. Cash flows arising from financing activities are
useful in predicting claims on future cash flows by providers of capital (that is, borrowing) to the Council. The Council’s
share of the cash flows of its associates and joint ventures is disregarded for the purpose of this statement because the
Council’s share of the associates’ and joint ventures’ reserves is unusable and cannot be used to fund services. 
2022/23
(restated)
2023/24
£m £m
(79.538) Group surplus/(deficit) (45.468)
135.906 Adjustment for non-cash movements 88.767
(44.807) Adjustments for items included in the group surplus/deficit that are investing and
financing activities
(30.658)
11.561 Net cash flows from operating activities 12.641
(20.087) Net cash flows from investing activities 1.371
2.218 Net cash flows from financing activities 3.899
(6.308) Net increase/(decrease) in cash and cash equivalents 17.911
19.819 Cash and cash equivalents at the beginning of the reporting period 13.511
13.511 Cash and cash equivalents at the end of the reporting period 31.422 
Notes to the Group Accounts 
The Council’s share of Group entities is reviewed on an annual basis and some prior year figures are adjusted as a result,
when compared to the prior year audited accounts. 
Note G1: Details of the group’s combining entities 
Renfrewshire Council is represented on the board of a number of organisations. The extent of the Council’s controlling
interest has been reviewed in determining those entities that should be consolidated and incorporated within the group
accounts. Those organisations, which have a significant impact on the Council’s operations, are listed below. The
accounting period for all of these bodies is the year to 31 March 2023. In addition to the information included in the
group accounts on the preceding pages the accounting regulations require specific disclosures about the combining
entities and the nature of their business.
OneRen, the Paisley, Renfrew and Johnstone Common Good Funds, Paisley Museum Reimagined Limited, Park Lane
Developments (Renfrewshire) LLP and the Coats Observatory Trust administered by Renfrewshire Council (as sole
trustee) are treated as subsidiaries in the Council’s group accounts, with assets, liabilities, reserves, income and expenses
being consolidated line-by-line. AMIDS (Renfrewshire) LLP is a joint venture arrangement.

Page 110

107 
Annual Accounts 2023/24
Renfrewshire Leisure Limited, trading as OneRen, is a company limited by guarantee formed in 2014 and registered as a
charity in Scotland. Its principal place of business is the Lagoon Leisure Centre, 11 Christie Street, Paisley PA1 1NB. The
charity provides leisure and culture facilities within Renfrewshire Council’s area to the general public and operates ten
leisure centres within Renfrewshire plus a range of cultural service buildings, libraries and community halls. The
objectives of the charity are to provide facilities for recreation, sport, cultural and other leisure activities for the benefit
of the community in Renfrewshire. Any surplus generated by the charity is applied solely to its continuation and
development. During 2023/24 Renfrewshire Council provided additional funding of £0.500m to OneRen, as a pass-
through of Scottish Government funding in support of the local government pay settlement. The accounts of the charity
are published separately and may be obtained from the Chief Executive, Lagoon Leisure Centre, 11 Christie Street, Paisley
PA1 1NB. 
Paisley Museum Reimagined Limited was formed in 2019 by Renfrewshire Council, with the objective of managing the
development and delivery of the fundraising strategy for Paisley Museum and to drive the capital appeal for the
redevelopment of Paisley Museum and furthering Paisley's cultural regeneration. The company is treated as a subsidiary
within the Group Accounts. Copies of the financial statements may be obtained from its registered office at Renfrewshire
House, Cotton Street, Paisley, Scotland, PA1 1WB. 
Park Lane Developments (Renfrewshire) LLP was formed in 2010 by Renfrewshire Council and Park Lane Real Estate LLP
in order to facilitate the regeneration of Paisley town centre through the transformation of the town’s former Arnotts
store into a mixed-use retail, office and residential development. The Partnership is treated as a subsidiary within the
Group Accounts. Copies of the financial statements for the partnership may be obtained from its registered office at
25 Newton Place, Glasgow G3 7PY. 
The group comprehensive income and expenditure statement (CIES) includes total net comprehensive income for the
year of £4.163m (2022/23 £30.105m restated) for OneRen, total net comprehensive income for the year of £2.751m
(2022/23 net comprehensive expenditure of £1.607m) for the Paisley, Renfrew and Johnstone Common Good Funds,
total net comprehensive expenditure for the year of £0.063m (2022/23 £0.033m) for Park Lane Developments
(Renfrewshire) LLP, total net comprehensive income for the year of £1.501m (2022/23 £0.236m restated) for Paisley
Museum Reimagined Limited and total net comprehensive expenditure for the year of £0.023m (2022/23 £0.023m) for
the Coats Observatory Trust.
The group balance sheet includes net assets of £32.128m (2022/23 £27.965m restated) for OneRen, net assets of
£42.605m (2022/23 £39.854m) for the Common Good Funds, net assets of £0.013m (2022/23 £0.076m) for Park Lane
Developments (Renfrewshire) LLP, net assets of £1.164m (2022/23 £0.337m net liabilities of restated) for Paisley
Museum Reimagined Limited and net assets of £0.654m (2022/23 £0.677m) for the Coats Observatory Trust.
Strathclyde Concessionary Travel Scheme Joint Committee comprises the twelve councils in the west of Scotland and
oversees the operation of the concessionary fares scheme for public transport within its area. The costs of the scheme
are met by a combination of funding from the twelve constituent councils and by direct grant funding from the Scottish
Government. Strathclyde Partnership for Transport administers the scheme on behalf of the committee. In 2023/24,
Renfrewshire Council contributed £0.332m or 8.02% of the committee’s estimated running costs (2022/23 £0.325m or
8.00%) and its share of the year-end net asset was £0.410m (2022/23 £0.402m) and is included in the group balance
sheet. Copies of its accounts may be obtained from the Treasurer to Strathclyde Concessionary Travel Scheme,
Strathclyde Partnership for Transport, 131 St. Vincent Street, Glasgow G2 5JF.
Strathclyde Partnership for Transport was formed on 1 April 2006 as the successor to the Strathclyde Passenger
Transport Authority. It is a joint committee of the twelve councils in the west of Scotland. In association with the related

Page 111

108 
Annual Accounts 2023/24
strategic development committees, the partnership’s remit includes the promotion of joint working to set out the policy
framework for achieving the most effective management, development and integration of the transport network across
boundaries in the medium to longer term through the Regional Transport Strategy. Renfrewshire Council contributed
£2.914m or 8.02% to the committee’s estimated running costs in 2023/24 (2022/23 £2.853m or 8.01%) and its share of
the year-end net asset was £40.174m (2022/23 £37.564m restated) and is included in the group balance sheet. Copies of
its accounts may be obtained from the Treasurer to Strathclyde Partnership for Transport, 131 St. Vincent Street,
Glasgow G2 5JF.
Strathclyde
Partnership for
Transport
Renfrewshire
Council’s Share
Strathclyde
Partnership for
Transport
Renfrewshire
Council’s Share
£m £m £m £m
Balance Sheet Summary
317.094 25.387 Long-term assets 337.570 27.076
177.466 14.208 Current assets 194.589 15.607
(25.374) (2.031) Current liabilities (28.684) (2.301)
0.000 0.000 Long-term liabilities (2.597) (0.208)
469.186 37.564 Net assets 500.878 40.174
Income and Expenditure Summary
82.322 6.591 Income 120.503 9.665
79.755 6.385 Expenditure 84.622 6.787
2.567 0.206 Surplus for the year 35.881 2.878
As at 31 March 2023 (restated) As at 31 March 2024
2022/23 (restated) 2023/24
Renfrewshire Valuation Joint Board was formed in 1996 at local government re-organisation by Act of Parliament. Its
principal place of business is The Robertson Centre, 16 Glasgow Road, Paisley PA1 3QF. The board maintains the
electoral, council tax and non-domestic rates registers for the three councils of East Renfrewshire, Inverclyde and
Renfrewshire. The board’s running costs are met by the three member councils. Surpluses or deficits on the board’s
operations are shared between the councils. In 2023/24, Renfrewshire Council contributed £1.637m or 57.7% of the
board’s estimated running costs (2022/23 £1.635m or 57.7%) and its share of the year-end net asset was £0.565m
(2022/23 £0.537m restated) and is included in the group balance sheet. Copies of its accounts may be obtained from the
Treasurer to the Renfrewshire Valuation Joint Board, Renfrewshire Council, Renfrewshire House, Paisley PA1 1JB. The
following additional disclosures are required under accounting regulations for Renfrewshire Valuation Joint Board
because it is a related party to the Council.
Renfrewshire
Valuation Joint
Board
Renfrewshire
Council’s Share
Renfrewshire
Valuation Joint
Board
Renfrewshire
Council’s Share
£m £m £m £m
Balance Sheet Summary
0.126 0.073 Long-term assets 0.099 0.057
0.886 0.511 Current assets 0.994 0.574
(0.082) (0.047) Current liabilities (0.115) (0.066)
0.930 0.537 Net assets 0.978 0.565
Income and Expenditure Summary
2.884 1.664 Income 2.917 1.685
3.031 1.749 Expenditure 2.807 1.621
(0.147) (0.085) Deficit for the year 0.110 0.064
As at 31 March 2023 (restated) As at 31 March 2024
2022/23 2023/24

Page 112

109 
Annual Accounts 2023/24
The Public Bodies (Joint Working) (Scotland) Act 2014 established the framework for the integration of health and adult
social care in Scotland. On 27 June 2015, Scottish Ministers legally established the Renfrewshire Health and Social Care
Integration Joint Board (IJB) as a formal legal partnership between Renfrewshire Council and NHS Greater Glasgow and
Clyde. 
The IJB is responsible for the strategic planning of the functions delegated to it and for ensuring the delivery of its
functions through the locally agreed operational arrangements.  Copies of the financial statements for the IJB may be
obtained from Chief Officer, Renfrewshire Health and Social Care Integration Joint Board, Renfrewshire House, Cotton
Street, Paisley, PA1 1WB. 
Renfrewshire
Integration
Joint Board
Renfrewshire
Council’s Share
Renfrewshire
Integration
Joint Board
Renfrewshire
Council’s Share
£m £m £m £m
Balance Sheet Summary
33.633 16.817 Current assets 26.077 13.038
33.633 16.817 Net assets 26.077 13.038
Income and Expenditure Summary
359.320 179.660 Income 395.015 197.507
376.736 188.368 Expenditure 402.571 201.286
(17.416) (8.708) (Deficit)/Surplus for the year (7.556) (3.779)
As at 31 March 2023 As at 31 March 2024
2022/23 2023/24
Note G2: Non-material interest in other entities 
In addition to the combining entities detailed in note G1, the Council has a “significant interest” in a number of joint
committees. The Council’s share of the net assets or liabilities of these joint committees is not material to the fair
understanding of the financial position and transactions of the Council. Accordingly, the group accounts do not include
these organisations. In the interest of transparency, the following disclosures are made concerning the business nature
of each organisation. 
Scotland Excel is formed by agreement among local authorities throughout Scotland and is maintained through a joint
committee comprising representatives from all of the member councils. Launched on 1 April 2008 as a centre of
procurement expertise for the local government sector, it is the largest non-profit making purchasing agency in Scotland.
Its aim is to help improve the efficiency and effectiveness of public sector procurement. Renfrewshire Council
contributed £0.130m (3.3%) to the committee’s estimated running costs in 2023/24 (£0.126m in 2022/23). 
Glasgow and the Clyde Valley Strategic Development Planning Authority. The committee covers the eight councils
within its area. Under the Town and Country Planning (Scotland) Act 1997, each member council not only has
responsibilities for local planning matters in its area but also the strategic issues that cover the wider area of the Glasgow
and Clyde valley. Accordingly, the committee prepares, monitors and reviews the Strategic Development Plan on behalf
of member councils and liaises with central government, Scottish Enterprise and other bodies. Renfrewshire Council
contributed £0.053m (12.5%) to the committee’s estimated running costs in 2023/24 (£0.068m in 2022/23). 
Glasgow City Region – City Deal Cabinet is a Joint Committee, the purpose of which is to determine the Strategic
Development priorities for the Clyde Valley Region and to monitor and ensure the delivery of the City Deal programme as

Page 113

110 
Annual Accounts 2023/24
agreed between member authorities and the UK and Scottish Governments. The City Deal programme aims to deliver a
£1.13 billion investment programme through 20 infrastructure projects and will drive innovation and growth through the
support of the key sectors, including delivery of labour market and innovation programmes. The committee operates in
an administrative / project management capacity and does not hold any assets or liabilities developed from the City Deal
programme. 
Note G3: Associates and joint ventures 
The aggregate value of the assets, liabilities, income and expenditure of the Council’s associates and joint ventures are
shown in the two tables which follow. The net asset figure from these two tables combined (£13.038m + £41.149m =
£54.187m) equates to the figure disclosed in the group balance sheet as ‘Investments in associates and joint ventures’. 
AMIDS (Renfrewshire) LLP is an arrangement set up as a 50:50 Joint Venture Development Partnership between Tarras
Park Properties Limited (the Development Partner) and Renfrewshire Council, operating under the direction of an LLP
Board, consisting of two Council officers and two representatives from Tarras Park Properties Limited. The LLP will be
responsible for development progression, marketing, and general management of the Advanced Manufacturing
Innovation District Scotland (AMIDS), as directed by the Board. Renfrewshire Council has not made any financial
contribution during 2023/24. 
Aggregate of
Joint Venture
results
Renfrewshire
Council’s Share
Aggregate of
Joint Venture
results
Renfrewshire
Council’s Share
£m £m £m £m
Balance Sheet Summary
33.633 16.817 Current assets 26.077 13.038
33.633 16.817 Net assets 26.077 13.038
Income and Expenditure Summary
359.320 179.660 Income 395.015 197.507
376.736 188.368 Expenditure 402.571 201.286
(17.416) (8.708) (Deficit)/Surplus for the year (7.556) (3.779)
As at 31 March 2023 As at 31 March 2024
2022/23 2023/24
Joint ventures
Aggregate of
Associate
results
Renfrewshire
Council’s Share
Aggregate of
Associate
results
Renfrewshire
Council’s Share
£m £m £m £m
Balance Sheet Summary
317.219 25.460 Long-term assets 337.669 27.133
183.723 15.149 Current assets 201.399 16.648
(25.801) (2.106) Current liabilities (29.505) (2.424)
0.000 0.000 Pension asset / (liability) (2.597) (0.208)
475.141 38.503 Net assets 506.966 41.149
Income and Expenditure Summary
89.369 8.588 Income 127.838 11.705
86.520 8.433 Expenditure 91.762 8.756
2.849 0.155 Surplus for the year 36.076 2.949
As at 31 March 2023 (restated) As at 31 March 2024
2022/23 2023/24
Associates

Page 114

111 
Annual Accounts 2023/24
Note on contingent assets, contingent liabilities and capital commitments 
The Council is unaware of any material contingent asset or contingent liability as at 31 March 2024 in relation to any of
its associates or joint ventures. The Council is unaware that any commitments have been entered into by any of its
associates or joint ventures as at 31 March 2024, either with the Council itself or with other parties. 
Note G4: Material items of group income and expenditure 
In order to assist the reader in a better understanding of the impact of the inclusion of the results of the associates and
joint ventures, the following tables provide an analysis of the Council’s share of the material amounts of income and
expenditure disclosed in the group CIES. 
2022/23
(restated)
2023/24
£m £m
Share of (surplus) or deficit:
2.034 Subsidiaries: (3.013)
(0.650) Paisley, Renfrew and Johnstone Common Good Funds 0.180
0.020 Coats Observatory Trust 0.020
2.867 OneRen (1.775)
0.033 Park Lane Developments (Renfrewshire) LLP 0.063
(0.236) Paisley Museum Reimagined Limited (1.501)
(0.155) Associates: (2.949)
(0.206) Strathclyde Partnership for Transport (2.878)
(0.034) Strathclyde Concessionary Travel Scheme Joint Committee (0.007)
0.085 Renfrewshire Valuation Joint Board (0.064)
Joint Venture:
8.708 Renfrewshire Health and Social Care Integration Joint Board 3.779
10.587 Aggregate share of (surplus) or deficit (2.183)
Share of other comprehensive (income) and expenditure:
(30.712) Subsidiaries: (5.316)
2.257 Paisley, Renfrew and Johnstone Common Good Funds (2.931)
0.003 Coats Observatory Trust 0.003
(32.972) OneRen (2.388)
0.917 Associates: 0.303
1.285 Strathclyde Partnership for Transport 0.268
(0.001) Strathclyde Concessionary Travel Scheme Joint Committee (0.001)
(0.367) Renfrewshire Valuation Joint Board 0.036
(29.795) Aggregate share of other comprehensive (income) and expenditure (5.013)
Material items of group income and expenditure

Page 115

112 
Annual Accounts 2023/24
Note G5: Adjustments between group accounts and council accounts
In the group movement in reserves statement, adjustments between group accounts and council accounts are required
to bring the Council’s reserve balances back to the amount presented in the Council-only figures (before adjustments
between accounting basis and funding basis under regulations). This is because intra-group transactions are eliminated
when total comprehensive income and expenditure is calculated for the group. The adjustments between group
accounts and council accounts can be analysed as follows:
2022/23 2023/24
£m £m
0.123 Grants made by the Paisley, Renfrew and Johnstone Common Good Funds to
Renfrewshire Council in contribution towards the funding of community events and
projects
0.101
0.059 Governance costs charged to the Paisley, Renfrew and Johnstone Common Good
Funds by Renfrewshire Council
0.059
(0.040) Interest income received from Renfrewshire Council by the Paisley, Renfrew and
Johnstone Common Good Funds
(0.137)
(15.629) Service charge and other expenditure payable by Renfrewshire Council to OneRen (16.319)
0.442 Expenditure payable by OneRen to Renfrewshire Council 0.512
0.120 Expenditure/(income) payable by/(to) Paisley Museum Reimagined Limited to/(by)
Renfrewshire Council
(0.662)
(14.925) Total adjustments between Group accounts and Council accounts (16.446)
Adjustments between Group accounts and Council accounts
Note G6: Group financing and investment income and expenditure
2022/23
(restated) 2023/24
£m £m
22.298 Interest payable and similar charges 21.179
1.984 Net interest on the net defined benefit liability (1.086)
(6.656) Interest receivable and similar income (8.551)
(0.313) Income and expenditure in relation to investment properties and changes in their
fair values
(0.315)
(1.235) Other investment income (0.414)
16.078 Total financing and investment income and expenditure 10.813
Group financing and investment income and expenditure
Note G7: Group Usable reserves
2022/23
(restated) 2023/24
£m £m
(236.051) Council Usable Reserves - Note 7 (222.248)
Group Usable Reserves:
(25.174) Paisley, Renfrew and Johnstone Common Good Funds: unrestricted funds (24.995)
(0.218) Coats Observatory Trust: usable balances (0.195)
(0.380) OneRen (0.554)
0.337 Paisley Museum Reimagined Limited (1.164)
(3.269) Renfrewshire Health and Social Care Integration Joint Board (3.269)
(264.755) Total Group Usable Reserves (252.425)
Group Usable Reserves

Page 116

113 
Annual Accounts 2023/24
Note G8: Group Unusable reserves
Unusable reserves are those reserves that the Council is not able to utilise to provide services. Included within the total
Group Unusable Reserves are the unusable reserves of the Council’s subsidiaries; also included is the Council’s share of
the reserves of the associates and joint ventures within the group. 
2022/23
(restated)
2023/24
£m £m
(1,562.167) Council Unusable Reserves - Note 8 (1,303.410)
Group Unusable Reserves:
(3.915) Paisley, Renfrew and Johnstone Common Good Funds: financial instruments
revaluation reserve
(5.879)
(10.765) Paisley, Renfrew and Johnstone Common Good Funds: revaluation reserve (11.731)
(0.459) Coats Observatory Trust: revaluation reserve (0.459)
(27.585) OneRen: pension reserve (31.574)
(0.076) Park Lane Developments (Renfrewshire) LLP (0.013)
Council share of the Reserves of associates and joint ventures:
(37.564) Strathclyde Partnership for Transport (40.174)
(0.402) Strathclyde Concessionary Travel Scheme Joint Committee (0.410)
(0.537) Renfrewshire Valuation Joint Board (0.565)
(13.548) Renfrewshire Health and Social Care Integration Joint Board (9.769)
(1,657.018) Total Group Unusable Reserves (1,403.984)
Group Unusable Reserves
Note G9: Group investment properties
The following items of income and expense have been accounted for in the ‘Financing and investment income and
expenditure’ line in the group CIES:
2022/23
(restated) 2023/24
£m £m
(0.472) Rental income from investment property (0.315)
(0.472) Net (gain) or loss (0.315)
Group Investment Properties
There are no restrictions on the Council’s ability to realise the value inherent in investment property, nor on the right to
the remittance of income and the proceeds of disposal. With regards Common Good properties, the Council is obliged to
observe the provisions of the Community Empowerment (Scotland) Act 2015 in terms of public consultation on disposal
proposals; however, the right to the remittance of income and proceeds of disposal remains with the Common Good
Funds. The following table summarises the movement in the fair value of investment properties during the year:
2022/23 2023/24
£m £m
1.906 Balance at 1 April 2.014
0.178 Net losses from fair value adjustments 0.000
(0.064) Transfers from inventories and property, plant and equipment (1.593)
(0.006) Other changes (0.006)
2.014 Balance at 31 March 0.415
Group Investment Properties

Page 117

114 
Annual Accounts 2023/24
Note G10: Group Property, plant and equipment 
Council PPE
(Note 9)
Council
share of
Group PPE
Total
Group PPE
£m £m £m
Balance sheet net carrying amount at 31 March 2023 1,797.350 14.548 1,811.898
Other asset reclassifications 1.593 0.000 1.593
Additions 124.625 0.000 124.625
Disposals (1.531) 0.000 (1.531)
Depreciation (90.812) 0.067 (90.745)
Revaluation adjustments taken to the Revaluation Reserve 33.185 0.295 33.480
Revaluation adjustments recognised in the CIES (6.189) 0.000 (6.189)
Balance sheet net carrying amount at 31 March 2024 1,858.221 14.910 1,873.131
Gross carrying amount at 31 March 2024 1,936.632 (4.211) 1,932.421
Accumulated depreciation at 31 March 2024 (306.447) 19.121 (287.326)
Infrastructure assets 228.036 0.000 228.036
Balance sheet net carrying amount at 31 March 2024 1,858.221 14.910 1,873.131
Movements in 2023/24
Council PPE
(Note 9)
Council
share of
Group PPE
Total
Group PPE
£m £m £m
Balance sheet net carrying amount at 31 March 2022 1,663.152 14.406 1,677.558
Assets reclassified (to) or from the “held for sale” category 0.297 0.000 0.297
Other asset reclassifications 0.064 0.000 0.064
Additions 119.023 0.000 119.023
Disposals (1.275) 0.000 (1.275)
Depreciation (91.551) 0.108 (91.443)
Revaluation adjustments taken to the Revaluation Reserve 104.500 0.034 104.534
Revaluation adjustments recognised in the CIES 3.140 0.000 3.140
Balance sheet net carrying amount at 31 March 2023 1,797.350 14.548 1,811.898
Gross carrying amount at 31 March 2023 1,844.283 19.058 1,863.341
Accumulated depreciation at 31 March 2023 (269.665) (4.510) (274.175)
Infrastructure assets 222.732 0.000 222.732
Balance sheet net carrying amount at 31 March 2023 1,797.350 14.548 1,811.898
Movements in 2022/23

Page 118

115 
Annual Accounts 2023/24
Note G11: Group heritage assets 
A valuation of the fair value of the Council’s Heritage
Assets was carried out by an external valuer between
October 2021 and March 2022, resulting in an increase
of £4.883m.  The value at 31 March 2024 was £44.404m
(£44.404m in 2022/23). Included in this value are the
civic regalia and equipment of the Paisley, Renfrew and
Johnstone Common Good Funds, which have been
externally valued on a present value insurance basis at
£0.219m as at 31 March 2024 (£0.219 at 31 March
2023). 
Note G12: Group short-term debtors 
The balances detailed below are composed mostly of
the debtors of the Council, to which the debtors of
OneRen, Park Lane Developments (Renfrewshire) LLP
and the Paisley, Renfrew and Johnstone Common Good
Funds have been added. 
As at 31
March
2023
(restated)
As at 31
March
2024
£m £m
6.136 Trade receivables 5.871
4.311 Prepayments 6.008
56.919 Other receivables 55.527
67.366 Total 67.406
Group Short-term
Debtors
Note G13: Group short-term creditors 
The balances detailed below are composed mostly of
the creditors of the Council, to which the creditors of
OneRen, Park Lane Developments (Renfrewshire) LLP
and the Paisley, Renfrew and Johnstone Common Good
Funds have been added. 
As at 31
March
2023
(restated)
As at 31
March
2024
£m £m
(24.968) Trade payables (29.093)
(62.676) Other payables (53.339)
(87.644) Total (82.432)
Group Short-term
Creditors
Note G14: Amounts due between
Renfrewshire Council and its associates
and joint ventures 
An analysis of the amounts owing and owed between
the Council and its associates and joint ventures,
analysed into amounts relating to loans and amounts
relating to other balances, is shown in the table below. 
As at 31
March 2023
As at 31
March 2024
£m £m
Amounts owing to Renfrewshire Council:
0.789 Other balances 1.703
0.789 Total 1.703
Amounts owed by Renfrewshire Council:
(33.660) Liability for Renfrewshire Integration Joint Board’s retained underspend (26.103)
(1.119) Other balances (0.962)
(34.779) Total (27.065)

Page 119

116 
Annual Accounts 2023/24
Note G15: Group financial instruments 
Balance sheet carrying amounts of group financial instruments
The following categories of financial instrument are carried in the group balance sheet. Additional qualitative information
on the various categories of financial instruments can be found in Note 22: Financial Instruments. 
Long-term Current Long-term Current
£m £m £m £m
(223.600) (0.828) (238.592) (5.000)
0.000 (2.770) 0.000 (2.815)
(223.600) (3.598) (238.592) (7.815)
0.000 (52.916) (20.000) (26.766)
0.000 (0.871) 0.000 (0.864)
0.000 (0.845) (0.339) (0.262)
0.000 (54.632) (20.339) (27.892)
0.000 (35.931) 0.000 (28.641)
(223.600) (94.161) (258.931) (64.348)
0.000 (48.022) 0.000 (49.088)
(64.973) (3.388) (61.763) (3.210)
(0.003) 0.000 0.000 0.000
(64.976) (51.410) (61.763) (52.298)
Service concession and finance lease liabilities
Financial guarantees
Financial Liabilities included in Creditors
As at 31 March 2023
(restated)
Financial Liabilities
At amortised cost: Trade payables
Principal sum borrowed
Accrued interest
Total Public Works Loan Board (PWLB) borrowing
Principal sum borrowed
Accrued interest
EIR adjustments
Total non-PWLB borrowing (“market debt”)
Borrowing from group entities
Total Borrowing
As at 31 March 2024
Long-term Current Long-term Current
£m £m £m £m
0.000 165.000 0.000 66.000
0.000 1.751 0.000 1.755
27.008 0.000 28.921 0.000
27.008 166.751 28.921 67.755
0.000 0.418 0.000 7.578
0.000 0.012 0.000 0.048
0.000 (0.002) 0.000 (0.012)
0.000 13.083 0.000 23.808
0.000 13.511 0.000 31.422
0.818 78.786 0.756 76.039
4.986 0.057 4.826 0.054
1.037 0.000 1.208 0.000
(4.533) (20.213) (4.700) (21.739)
2.308 58.630 2.090 54.354
At amortised cost: Loss allowance
At fair value through profit or loss
Total Cash and cash equivalents
At amortised cost: Trade receivables
At amortised cost: Loans made for service purposes
At amortised cost: Accrued interest
At amortised cost: Loss allowance
Financial Assets included in Debtors
At amortised cost: Accrued interest
As at 31 March 2023
(restated)
Financial Assets
As at 31 March 2024
At amortised cost: Principal
At amortised cost: Accrued interest
At fair value through other comprehensive income - designated
equity instruments
Total Investments
At amortised cost: Principal
Note: the figures in this table include accrued interest where this is applicable

Page 120

117 
Annual Accounts 2023/24
Fair value of group financial instruments
The fair value through other comprehensive income financial assets carried on the group balance sheet comprise the
Council’s insurance fund investments and the investments of the Paisley and Renfrew Common Good Funds. The fair
value of these investments equates to the market value of the investments as provided by the Council’s investment
manager, LGT Wealth Management. In terms of the fair value measurement hierarchy the financial instruments
measured at fair value are considered to be Level 1 being quoted prices (unadjusted) in active markets for identical
assets or liabilities that the authority can access at the measurement date, Level 2 being inputs other than quoted prices
that can be accessed at the measurement date, or Level 3 being unobservable inputs e.g. cashflow forecasts or estimated
creditworthiness (see table below). 
Carrying
Amount
Fair value Financial Liabilities Carrying
Amount
Fair value
£m £m £m £m
Financial liabilities measured at amortised cost:
(227.198) (222.759) Public Works Loan Board borrowing  2 (246.407) (220.126)
(54.632) (61.519) Non-PWLB borrowing (“market debt”) 2 (48.231) (53.523)
Other liabilities:
(68.362) (126.783) Service concession and finance lease liabilities 3 (64.973) (119.570)
(0.003) (0.003) Financial guarantees 3 0.000 0.000
(350.195) (411.064) (359.611) (393.219)
Financial liabilities measured at amortised cost:
(35.931) n/a Borrowing from group entities (28.641) n/a
(48.022) n/a Trade payables: short-term (49.088) n/a
(83.953) (77.729)
Fair
value
level
Total financial liabilities for which fair value is disclosed
Total financial liabilities for which fair value is not disclosed
As at 31 March 2023
(restated) As at 31 March 2024
Carrying
Amount
Fair value Financial Assets Carrying
Amount
Fair value
£m £m £m £m
6.086 6.086 Callable deposits in money market funds 1 20.101 20.101
6.997 6.997 Euro account balances with the Council’s banker 2 3.707 3.707
27.008 27.008 Investments in pooled funds 1 28.921 28.921
40.091 40.091 52.729 52.729
166.751 166.751 Fixed term deposits with UK local authorities 2 67.755 67.751
0.377 0.377 Callable deposits with UK banks & building societies* 2 7.571 7.571
0.051 0.051 Imprest accounts held at council establishments 2 0.043 0.043
1.546 1.681 Loans made for service purposes 3 1.387 1.543
168.725 168.860 76.756 76.908
208.816 208.951 129.485 129.637
Financial assets measured at amortised cost:
0.817 n/a Trade receivables and prepayments: long-term 0.754 n/a
58.575 n/a Receivables and prepayments: short-term 54.302 n/a
59.392 55.056
Total Financial assets measured at fair value
Total Financial assets measured at amortised cost
Total financial assets for which fair value is disclosed
Total financial assets for which fair value is not disclosed
As at 31 March 2023
(restated)
As at 31 March 2024
Fair
value
level
*includes current account balances with the Council’s banker.

Page 121

118 
Annual Accounts 2023/24
The short-term nature of cash and cash equivalents means that their fair value equates to their balance sheet carrying
amount.  Further qualitative information on the fair value of financial instruments can be found in Note 22. 
Items of income, expense, gain and loss relating to group financial instruments 
The following items of income, expense, gain and loss relating to group financial instruments are included within the lines
‘Financing and Investment income and expenditure’ and ‘(Surplus) or deficit from investments in equity instruments
designated as ‘Fair Value through Other Comprehensive Income (OCI*)’ in the group CIES. 
2022/23
(restated)
Amortised
cost
Elected to Fair
Value through
OCI*
Fair Value
through Profit
or Loss 2023/24
£m £m £m £m £m £m
16.543 Interest expense 0.000 0.000 0.000 16.186 16.186
0.000 Impairment losses 3.549 0.000 0.000 0.000 3.549
0.000 Fee expense 0.000 0.000 0.000 0.007 0.007
16.543 Total expense in the Surplus /
Deficit on the Provision of Services 3.549 0.000 0.000 16.193 19.742
(4.193) Interest income (6.376) 0.000 (1.754) 0.000 (8.130)
(0.794) Dividend income 0.000 (0.787) 0.000 0.000 (0.787)
(0.870) Other income 0.000 0.209 0.000 0.000 0.209
(5.857) Total income in the Surplus/Deficit
on the Provision of Services (6.376) (0.578) (1.754) 0.000 (8.708)
3.027 Net (gain) or loss on revaluation 0.000 (1.993) 0.039 0.000 (1.954)
3.027 (Surplus)/Deficit on the
revaluation of financial assets 0.000 (1.993) 0.039 0.000 (1.954)
13.713 Net (Gain)/Loss for the year (2.827) (2.571) (1.715) 16.193 9.080
Financial Assets Financial
liabilities at
amortised
cost
Group Accounting Policies 
Introduction 
The Code of Practice on Local Authority Accounting in
the United Kingdom 2022/23 (“the Code”) requires local
authorities to consider their interests in all types of
entity. 
This includes other local authorities or similar bodies
defined in section 106 of the Local Government
(Scotland) Act 1973, for example statutory bodies such
as valuation boards. 
Authorities are required to prepare a full set of group
accounts in addition to their own Council’s accounts
where they have a material interest in such entities. 
Combining entities 
Renfrewshire Council’s group accounts consolidate the
results of the Council with the results of the Paisley,
Renfrew and Johnstone Common Good Funds; the Coats
Observatory Trust administered by Renfrewshire
Council; and seven other entities:
1. Renfrewshire Leisure Limited, trading as OneRen;
2. Paisley Museum Reimagined Limited;
3. Park Lane Developments (Renfrewshire) LLP;
4. Strathclyde Partnership for Transport;
5. Strathclyde Concessionary Travel Scheme Joint
Committee;
6. Renfrewshire Valuation Joint Board;
7. Renfrewshire Health and Social Care Integration
Joint Board.

Page 122

119 
Annual Accounts 2023/24
The Council has effective control over OneRen, Paisley
Museum Reimagined Limited, the Paisley, Renfrew and
Johnstone Common Good Funds and the Coats
Observatory Trust administered by Renfrewshire Council
(as sole trustee) and, as such, these are treated as
subsidiaries in the Council’s group accounts, with assets,
liabilities, reserves, income and expenses being
consolidated line-by-line. 
The Council also holds 50% (£50) of the share capital of
Park Lane Developments (Renfrewshire) LLP. Under the
terms of the Partnership Agreement, the Council has
enhanced voting rights and Park Lane Developments
(Renfrewshire) LLP has no claim on the remaining assets
should the partnership be wound up; therefore, the
entity is treated as a subsidiary. 
Strathclyde Partnership for Transport and Strathclyde
Concessionary Travel Scheme Joint Committee are
included within the group accounts under the definition
of associate, even though the Council holds less than
20% or more of the voting (or potential voting) power
(which is the criterion normally used to confer
significant influence). However, the view has been taken
that the nature of the funding arrangements between
the constituent Councils and these entities is sufficient
to confer significant influence. 
Renfrewshire Valuation Joint Board is included within
the group accounts as an associate because the Council
does not have a controlling interest in the body in terms
of the voting rights. 
Renfrewshire Council’s share of each associate’s net
assets or liabilities is calculated based on the Council’s
proportionate contribution to each associate’s annual
revenue costs. The Council has no shares in, or
ownership of, any of these three organisations, which
are entirely independent of the Council under law and
for taxation. 
The Public Bodies (Joint Working) (Scotland) Act 2014
established the framework for the integration of health
and adult social care in Scotland. 
Scottish Ministers legally established the Renfrewshire
Health and Social Care Integration Joint Board on 27
June 2015 as a formal legal partnership between
Renfrewshire Council and NHS Greater Glasgow and
Clyde. This entity is included as a joint venture in the
Council’s group accounts. Renfrewshire Council’s share
of the joint venture’s net liabilities is calculated based
on the Council’s proportionate ordinary shareholding in
the joint venture. 
Basis of preparation of group statements
and going concern 
For the associates and joint ventures detailed above, the
combination has been accounted for under the
accounting conventions of the acquisition basis using
the equity method, with the Council’s share of the net
assets or liabilities of each entity incorporated and
adjusted each year by the Council’s share of that entity’s
results and the Council’s share of other gains and losses
(recognised in the group CIES). 
For four of the combining entities the Council has a
share in a net liability. The net liability position of both
the Renfrewshire Valuation Joint Board and OneRen
arises from the inclusion of liabilities related to the
defined benefit pension schemes as required by IAS19
(which requires that pension liabilities reflect the long-
term cost of paying post-employment benefits). For Park
Lane Developments (Renfrewshire) LLP the net liability
arises from long-term borrowing to fund regeneration
work within and around the site of the former Arnott’s
store in Paisley. For Paisley Museum Reimagined Limited
sums due to date by the company to Renfrewshire
Council for the provision of ongoing administrative
support have been written off in 2023/24 (£0.768m). 
All of the organisations noted above prepare their
annual accounts on a going concern basis. Arrangements
with the Council and other funders for the longer-term
funding of Park Lane Developments (Renfrewshire) LLP
are considered sufficient to meet future funding
requirements.  The Council will continue to support
Paisley Museum Reimagined Limited until their
anticipated revenue generation materialises.

Page 123

120 
Annual Accounts 2023/24
Consideration for acquisition of
associates’ net assets or liabilities 
The Council has acquired its share of the net assets of its
associates for a nil consideration. There is no deferred
or contingent purchase consideration. A fair value for its
share of the net assets or liabilities of the three joint
boards and committees at the point of acquisition and
the post-acquisition results are unable to be accurately
determined in view of the length of time since the
transfer of these responsibilities at local government re-
organisation in 1996 and the change in accounting for
pensions under FRS17 in 2003/04. 
It is not possible to provide the fair value of the
investment in the other combining entities of the
Council as there are no published price quotations for
these entities. No goodwill has been included in the
group balance sheet in view of the length of time since
acquisition, that no consideration was involved and that
a fair value at the date of acquisition cannot now be
properly assessed. 
Group boundary: non-material interests
in other entities 
The Council has a significant interest in three joint
committees that have not been included in the group
accounts. The Council’s share of their net assets or
liabilities is not material to the fair understanding of the
financial position and transactions of the Council. In the
interest of transparency, details of the business nature
of each organisation are shown in notes G1 and G2. 
Inventories 
Inventories (generally consumable stock) are included in
the group balance sheet at weighted average cost and
the lower of cost or net realisable value: weighted
average cost – Council’s stock; lower of cost or net
realisable value – OneRen’s stock. The difference in
valuation methods does not have a material effect on
the results of the group given the levels of stockholdings
in these entities. 
Post-employment benefits 
In common with Renfrewshire Council, all combining
entities, except Park Lane Developments (Renfrewshire)
LLP, participate in the Local Government Pension
Scheme, which is administered locally by Glasgow City
Council through the Strathclyde Pension Fund. The
associates have accounting policies for pensions
accounting that are consistent with those of the Council. 
Property, plant and equipment 
The basis of valuation across the combining entities is in
accordance with the Code. Operational property, plant
and equipment assets are shown at the lower of net
replacement cost or net realisable value in existing use
with the following exceptions:
i) The Concessionary Travel Scheme Joint Committee
has no fixed assets.
ii) Strathclyde Partnership for Transport holds
exceptional types of fixed assets in its balance sheet.
Within intangible assets, there are subsidised bus
contracts that are recorded at amortised cost. There
are also “third-party” assets that are rolling stock
and other public assets used by other transport
operators but which the partnership has the power
to direct to the benefit of the travelling public within
the partnership’s operating area – these are held at
historic cost.
iii) OneRen uses the historic cost convention for its
recent leasehold improvements, but this is
considered a suitable proxy for market value in
existing use on a replacement cost basis. OneRen
also uses depreciated historic cost for its computers,
plant, furniture and fittings rather than the Council’s
depreciated replacement cost basis, however this is
not considered to be material given the small values
involved. 
Restrictions on the transfer of funds 
The Council’s share of the reserves of its associates is
unusable in that it cannot be used to fund the Council’s
services nor to reduce taxation. All associates are

Page 124

121 
Annual Accounts 2023/24
entirely independent of the Council under law and for
taxation. The Council is unable to access their reserves,
whether classified as usable or otherwise in the
associate’s own financial statements. 
Value Added Tax 
Value Added Tax paid by OneRen is accounted for within
income and expenditure to the extent that it is
irrecoverable from HM Revenue and Customs.

Page 125