1 Annual Audit Report 2023-24 Renfrewshire Council Group

Renfrewshire Council · 24 October 2024
Back to Council — 24 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

1 
___________________________________________________________________
To: Council
On: 24 October 2024
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Azets Report to those charged with governance - Renfrewshire Council 
Group Annual Accounts 2023/24
___________________________________________________________________
1. Summary
1.1 Each year the Council’s appointed external auditors carry out an audit of
the Council’s financial statements and provide an opinion as to whether
those statements provide a true and fair view of the financial position of the
Council, and its income and expenditure for the year; and also whether they
have been prepared in accordance with the Local Government (Scotland)
Act 1973. 
1.2 In accordance with International Auditing Standards (ISA260), the external
auditor, Azets, is obliged to report to those charged with the governance of
the organisation matters which have arisen in the course of the audit.  
1.3 The attached ISA260 report from Azets outlines their findings from the audit
of the 2023/24 the Renfrewshire Council Group accounts. 
1.4 In addition, the Council’s chief financial officer is obliged to provide a letter
of representation to Azets, which outlines the assurances the Council
provides to the external auditor with regards to the annual accounts. A draft
of this letter is attached as an appendix to the Annual Audit Report.
1.5 Under the Local Authority Accounts (Scotland) Regulations 2014, the
Council must meet to consider the Annual Accounts and aim to approve
those accounts for signature no later than 30 September. 
1.6 There was one material adjustment made to the annual accounts over the
course of the audit, which amended the value of the Council’s pension

Page 2

2 
asset disclosed in the 2022/23 Balance Sheet, owing to the exclusion of
unfunded liabilities. Further detail is included in Azets’ Annual Audit report,
presented at agenda item 1. Other minor and presentational changes were
also agreed.
1.7 Azets officers will be in attendance at the meeting to present their reports.
___________________________________________________________________
2. Recommendations
2.1 The Council is asked to consider the attached Annual Audit Report from
Azets and to approve the letter of representation.
___________________________________________________________________
Implications of the Report
1. Financial
The 2023/24 Annual Accounts demonstrate that the Council continues to
operate services within the resources available, and in line with the relevant
legislation.
2. HR & Organisational Development 
There are no direct implications arising from the recommendations in this
report
3. Community/Council Planning 
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital
spend ensures that its facilities are fit
for purpose and safe for the
community, to maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital
spend ensures that its facilities are fit
for purpose and safe for the
community, to maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the
Council has resources now and in the
future for continued service delivery.
Working together to improve
outcomes

Page 3

3 
4. Legal
An audit opinion free from qualification demonstrates the Council’s
compliance with the statutory accounting requirements set out in the Local
Government (Scotland) Act 1973 and the Local Government in Scotland Act
2003.
5. Property/Assets
There are no direct implications arising from the recommendations in this
report.
6. Information Technology 
There are no direct implications arising from the recommendations in this
report.
7. Equality & Human Rights 
There are no direct implications arising from the recommendations in this
report.
8. Health & Safety
There are no direct implications arising from the recommendations in this
report.
9. Procurement 
There are no direct implications arising from the recommendations in this
report.
10. Risk 
Particular areas of risk are examined by external auditors, as outlined in the
Annual Audit Report.
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report.
12. Cosla Policy Position 
There are no direct implications arising from the recommendations in this
report.
13. Children’s Rights
There are no direct implications arising from the recommendations in this
report.
14. Climate Change
There are no direct implications arising from the recommendations in this
report.
___________________________________________________________________ 
Author:           Christine McCourt, Head of Finance and Procurement

Page 4

No embedded text on this page.

Page 5

OFFICIAL 
Renfrewshire Council
2023/24 Annual Audit Report to the
Council and the Controller of Audit 
October 2024

Page 6

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
2
Table of Contents
Key messages 3
Introduction 14
Annual accounts audit 16
Wider Scope 36
Best Value 58
Appendices 65

Page 7

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
3
Key messages
This report concludes our audit of Renfrewshire Council (the
“Council”) for the year ended 31 March 2024. This section
summarises the key findings and conclusions from our audit.
Financial statements audit
Audit
opinion
The annual accounts are to be considered and approved by the full
Council on 24 October 2024.
Our audit is substantially complete, subject to finishing work on
reconciliation of trial balances to accounts, creditors testing checks
on the final set of accounts. 
Based on our audit work to date we anticipate issuing an
unqualified independent auditor’s report.
Key audit
findings
The Council has appropriate administrative processes in place to
prepare the annual accounts and supporting working papers. 
The accounting policies used to prepare the financial statements
are considered appropriate. We are satisfied with the
appropriateness of the accounting estimates and judgements used
in the preparation of the financial statements. All material
disclosures required by relevant legislation and applicable
accounting standards have been made appropriately.
Audit
adjustments
We identified one material prior year restatement of £73.5 million in
relation to the recognition of the unfunded element of the pension
liability. This has been adjusted in the revised accounts. This issue
emerged following the receipt of the 2024 actuary’s report which
provided new information on this aspect of the pension liability for
the first time.  This amendment does not impact on useable
reserves. 
We also identified some minor disclosure and presentational
adjustments during our audit, all of which have been reflected in the
final set of financial statements.

Page 8

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
4
Accounting
systems
and internal
controls
We have applied a risk-based methodology to the audit. This
approach requires us to document, evaluate and assess the
Council’s processes and internal controls relating to the financial
reporting process. 
Our audit is not designed to test all internal controls or identify all
areas of control weakness. However, where, as part of our testing,
we identify any control weaknesses, we include these in this report.
We consider the control environment within the Council to be
satisfactory. 
Wider scope audit
Section102 School accommodation for Dargavel Village - 
Follow Up Review 
In January 2024 the Accounts Commission (“the Commission”) considered the S102
report by the Controller of Audit on School Accommodation for Dargavel Village.
Following this, the Commission asked the Controller of Audit to provide an update on
the Council’s progress in responding to the Commission’s findings.  The update
report was presented to the Accounts Commission in August 2024.
The follow up report concluded that the Council continues to demonstrate that it is
taking action to respond to the issues highlighted in the Bowles report. The auditor
carried out further work to look at Council actions and progress in the five particular
areas of concern identified by the Commission and the Controller of Audit was
satisfied that the actions being taken by the Council are timely and appropriate.
The Council carried out its consultation on the proposed new primary school in line
with statutory requirements and the independent consultant found that the process
was robust. The consultation found significant support for a new school, however,
there is no clear consensus on the proposed site and some respondents continued
to highlight high school provision as a pressing issue although that was outwith the
consultation scope. The Council has recognised that there is still work to do and
reports it has developed plans for ongoing community engagement on the design
and planning of the new school. The auditor will continue to monitor progress and
developments in this area.  
The Council has now concluded its review of risk management and has largely
completed the actions arising from its review of governance arrangements. It has
also completed its review of its Dargavel consultation and community engagement
activity. The Council has made progress in its response to the issues raised in the
Bowles report, but it is too early to conclude on the impact and effectiveness of some
of the actions taken by the Council. The auditor will continue to monitor the impact of

Page 9

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
5
changes to governance and scrutiny arrangements, the leadership programme, and
the council’s response to the review of its community engagement activity. There
continues to be a public interest in the Council’s response to the Bowles report. It is
critical that the Council is as transparent as possible about how it reaches key
decisions and that appropriate records are kept. The auditor will provide further
updates through Best Value reports.
The current capital cost of the new primary school in Dargavel is estimated at
c£45million, with the capital cost of the secondary school extension at Park Mains
High School (PMHS) at c£37million. The Council’s S75 Agreement with the
Developer (BAE Systems) includes a requirement for a Developer contribution of
approximately half of the costs associated with the PMHS extension.
At this point, the estimated net capital cost to the Council associated with the
provision of education in Dargavel is c£63million.  These costs are expected to be
met from the application of the Council’s existing capital fund (reserves) for the new
primary school and from borrowing for the secondary school extension, resulting in
anticipated annual interest payments of c£1.2 million per annum as the schools are
constructed. 
The costs do not include the running costs of the new school which the Council
estimates, on a net basis, will be c£1.6 million per annum for the new Dargavel
Primary school and Park Mains High School extension. These costs are early
estimates and will crystallise once the additional schools buildings are complete and 
at full capacity which is expected within the next 5-10 years. 
The estimated combined annual revenue impact associated with the Council’s failure
to properly estimate the school roll impact of the Dargavel development currently
c£2.8 million and these additional costs will be borne over the lifetime of the schools
currently estimated at 40 years. These unplanned annual costs are incorporated into
the Council’s medium term financial plan (MTFP) as they impact on budgets from the
2027 financial year. As noted below, the Council has included these additional costs
in its MTFP which identifies a budget gap of up to £47million between existing
expenditure plans and available funding.
We note that the Council has now approved that the new Dargavel Primary School to
be funded from its Investment Capital Fund. This fund is held by the Council to
support the Council’s capital investment programme and to support the Council
manage its long term debt position. This will therefore help the Council avoid
c£3million in borrowing interest annual cost. However, using £45million of the fund to
finance the new Dargavel School displaces the ability of the Council to apply that
fund to support other capital projects.
The Council has implemented the significant majority of Bowles Report
recommendations and is making good progress in delivering all remaining actions.

Page 10

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
6
Wider scope themes
Financial Management
Financial management
is concerned with
financial capacity, sound
budgetary processes
and whether the control
environment and
internal controls are
operating effectively.
Auditor judgement
Risk exists to the achievement of
operational objective 
Like all local authorities, financial management continues
to remain challenging in the current funding and post-
pandemic environment. 
The Council reported a General Fund overspend of
approximately £3.5 million for the year ending 31 March
2024, driven primarily by inflationary pressures and
increased costs in various services, particularly within
Children’s Services, and Environment, Housing and
Infrastructure services. The Council's revised budget was
£513.6 million, with actual spend reaching £517 million.
To manage the overspend, the Council applied reserves
from its Financial Sustainability Fund. 
Capital spending was within approved limits, although
inflation and contractor availability affected the cost of
projects and progress in delivering planned projects. 
The Housing Revenue Account reported a break even
position after utilising £0.3 million of reserves. Council tax
collection decreased slightly from 95.5% to 94.3% but
exceeded revenue expectations. 
The Council’s Treasury management strategies focused
on mitigating risks amid economic uncertainty, resulting in
a £13 million net increase in external borrowing, while
temporary investments decreased by £81.2 million
reflecting budget requirements.
The Council has appropriate financial monitoring
arrangements in place and our audit has not identified any
significant weaknesses in financial controls.

Page 11

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
7
Financial
Sustainability
Financial sustainability
looks forward to the
medium and longer term
to consider whether the
Council is planning
effectively to continue to
deliver its services and
the way in which they
should be delivered.
Auditor judgement 
The Council approved its 2024/25 revenue budget at its
meeting in February 2024 and agreed a freeze in council
tax, which will provide the Council with £4.9 million of
additional funding from Scottish Government, equivalent
to a 4.4% council tax increase. The Council is currently
projecting an overspend of £3.3million (or 1% of the
budget) for the 2024/25 financial year.
Medium term financial sustainability remains challenging
as the Council is estimating a budget deficit of between
£47 million and £74 million for the forecast period from
2024/25 and 2027/28. These already challenging savings
targets are inclusive of the additional revenue costs
associated with the Dargavel Primary school issue. 
The Council has reported cost savings of over £182
million since 2011 and further savings will be challenging
to achieve without a detrimental impact on service
provision. The Council must now make difficult decisions
on spending priorities if it is to remain financially
sustainable. The Council has clarified it will potentially
utilise its Financial Sustainability Fund (reserves) to cover
£31 million of the budget gap.  The application of reserves
does not provide a long term financially sustainable
solution to the Council’s current budget position and the
Council is developing savings options for members
approval and to be considered later this year.
The Council has an ambitious £730 million capital
programme in place over the next five years for both
housing and non-housing programmes. Since the
pandemic, a number of factors have impacted the
Council’s ability to fully deliver its capital programme
within the originally planned timescales. This has been
due to a number of factors, including the complexity of the
works, the cost of materials, supply chain issues and
availability of contractors. Given the scale of the Council’s
ongoing capital programme delivery of this programme is
likely to remain a continuing area of challenge.

Page 12

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
8
Vision, Leadership
and Governance 
Vision, Leadership and
Governance is
concerned with the
effectiveness of scrutiny
and governance
arrangements,
leadership and decision
making, and transparent
reporting of financial
and performance
information.
Auditor judgement 
In June 2023, the Council agreed a refreshed Council
Plan with refined priorities actions and indicators, in
response to external audit feedback.  The plan articulates
the Council’s vision, priorities and strategic objectives.
The Plan has five main strategic outcomes: Place,
Economy, Fair, Green and Living our values. 
The Council has taken a number of steps to improve its
governance and scrutiny arrangements over the year. It
has completed a self-assessment against CIPFA
guidance for local authority audit committees,
benchmarked its governance against practice in other
councils, established a cross-party working group to
review governance and scrutiny arrangements and
undertaken a review of risk management arrangements. 
The Council continues to ensure its governance and
scrutiny arrangements, including its culture, values and
behaviours, are sufficient to prevent a recurrence of the
historic issues identified in the Bowles Report. 
The Council has approved and adopted a Local Code of
Corporate Governance and complies with that Code.

Page 13

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
9
Use of Resources to
Improve Outcomes
Audited bodies need to
make best use of their
resources to meet
stated outcomes and
improvement objectives,
through effective
planning and working
with strategic partners
and communities. This
includes demonstrating
economy, efficiency,
and effectiveness
through the use of
financial and other
resources and reporting
performance against
outcomes.
Auditor judgement 
Like all local authorities, the Council has been impacted
by a high inflation economy and a challenging local
government funding settlement which presents challenges
for financial and service sustainability.
The Council has generally good arrangements for
performance management and operates a layered
performance management framework aligned to its
strategic objectives. Performance reports are presented to
policy boards and published on the Council’ website using
a wide range of user friendly and easy to follow
presentations, dashboards and narrative. Some of this
information may need updating to reflect the most recent
performance results. 
Performance in Education remains good, with the Council
exceeding the national average and receiving positive
reports from Education Scotland on all school inspections
undertaken during 2023/24.

Page 14

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
10
Best Value 
Appointed auditors have a duty to be satisfied that local government bodies have
made proper arrangements to secure Best Value. 
Workforce innovation
We have considered the effectiveness of council workforce innovation in accordance
with the national thematic review programme set out by Audit Scotland. Our key
findings and conclusions are reported in a separate report to the Council and
summarised below. 
Workforce innovation -
how councils are
responding to
workforce challenges
Auditor judgement 
We have concluded that the Council has appropriate workforce planning strategies
and other policies in place with a flexible approach to new ways of working. The
Council works collaboratively with its partners and continues to explore opportunities
for working together.  Through collaborative working, the Council shares knowledge
and learns from partners, leading to enhanced service delivery and outcomes. The
Council actively engages with its communities to deliver services in more innovative
ways and to tackle digital exclusion. The Council’s work has been recognised as a
best practice example in the recent Accounts Commission report on Tackling digital
exclusion. There is awareness of the need, and drive for continuous improvement in
this area. We noted some improvements are required in how the Council tracks
benefits of new ways of working and how it tracks progress against both its strategy
and individual service plans.

Page 15

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
11
Best value Leadership thematic review follow-up
A Best Value review was undertaken on Renfrewshire Council in 2016/17. The Best
Value Assurance Report (BVAR) includes recommendations to help the Council
address the improvement areas identified during the audit. We have considered
progress made by the Council in implementing the recommendations made in the
BVAR. Our findings are summarised below. 
Council leadership in
developing new local
strategic priorities
Auditor judgement  
Last year we have performed a review of Council’s arrangements in leadership and
developing new local strategic priorities.  We have concluded that the Council has a
clear strategic ambition, supported by an appropriate strategic plan. We have also
raised two recommendations.
1. To consider further priority setting to allow effective delivery of the Council’s
key outcomes.
2. The Council set a clear performance framework and service tracking of
Council Plan objectives; The Council might want to revisit the way it tracks
Plan objectives progress to ensure reporting is accurate
Both of these recommendations have been implemented.

Page 16

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
12 
Best value follow up
A Best Value review was undertaken on Renfrewshire Council in 2016/17. The Best
Value Assurance Report (BVAR) includes recommendations to help the Council
address the improvement areas identified during the audit. We have considered
progress made by the Council in implementing the recommendations made in the
BVAR. Our findings are summarised below. 
Best value Assurance
Report – follow up
Auditor judgement 
The Council’s BVAR identified eight recommendations and further progress has
made against each recommendation during the 2023/24 financial year. We note
however that some of the recommendations are no longer relevant due to changed
circumstances since the report was published.

Page 17

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
13
Definition
We use the following gradings to provide an overall assessment of the arrangements
in place as they relate to the wider scope and best vale areas. The text provides a
guide to the key criteria we use in the assessment, although not all of the criteria
may exist in every case. 
There is a fundamental absence or failure of arrangements
There is no evidence to support necessary improvement
Substantial unmitigated risks affect achievement of corporate
objectives.
Arrangements are inadequate or ineffective
Pace and depth of improvement is slow / needs to be
extended further
Significant unmitigated risks affect achievement of
corporate objectives
No major weaknesses in arrangements but scope for
improvement exists
Pace and depth of improvement are adequate
Risks exist to the achievement of operational objectives
Effective and appropriate arrangements are in place
Pace and depth of improvement are effective
Risks to the achievement of objectives are managed

Page 18

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
14
Introduction
The annual audit comprises the audit of the financial statements and the wider-scope
and Best Value audit responsibilities set out in the Code of Audit Practice. 
We outlined the scope of our audit in our External Audit Plan, which we presented to
the Audit, Risk and Scrutiny Board at the outset of our audit. Subsequent to issuing
the plan our risks remained the same, however we have updated our approach for
the issues that have arisen since our plan was issued or when we have obtained
further, more detailed knowledge, of a particular area of work as noted below.
Responsibilities
The Council is responsible for preparing its annual accounts, including financial
statements which show a true and fair view, and for implementing appropriate
internal control systems. The weaknesses or risks identified in this report are only
those that have come to our attention during our normal audit work and may not be
all that exist. Communication in this report of matters arising from the audit or of risks
or weaknesses does not absolve management from its responsibility to address the
issues raised and to maintain an adequate system of control.
We do not accept any responsibility for any loss occasioned to any third party acting,
or refraining from acting on, the basis of the content of this report, as this report was
not prepared for, nor intended for, any other purpose.
We would like to thank all management and staff for their co-operation and
assistance during our audit.
Auditor independence
International Standards on Auditing in the UK (ISAs (UK)) require us to communicate
on a timely basis all facts and matters that may have a bearing on our
independence.
We confirm that we complied with the Financial Reporting Council’s (FRC) Ethical
Standard. In our professional judgement, we remained independent, and our
objectivity has not been compromised in any way.
We set out in Appendix 1 our assessment and confirmation of independence. 
Adding value
All of our clients quite rightly demand of us a positive contribution to meeting their
ever-changing business needs. We add value by being constructive and forward
looking, by identifying areas of improvement and by recommending and encouraging

Page 19

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
15
good practice. In this way we aim to promote improved standards of governance,
better management and decision making and more effective use of public money.
Any comments you may have on the service we provide would be greatly
appreciated. Comments can be reported directly to any member of your audit team.
Openness and transparency
This report will be published on Audit Scotland’s website www.audit-scotland.gov.uk.

Page 20

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
16
Annual accounts audit
The Council’s annual accounts are the principal means of
accounting for the stewardship of its resources and its
performance in the use of those resources. 
Our audit opinion
Opinion Basis for opinion Conclusions
Financial
statements
We conduct our audit in
accordance with applicable
law and International
Standards on Auditing.
Our findings / conclusions
to inform our opinion are
set out in this section of
our annual report.
The draft financial statements.
Management commentary,
remuneration report and
corporate governance statement
were considered by the Council
and approved on 27 June 2024. 
We anticipate issuing unqualified
audit opinions.
We identified one material
adjustment during our audit of
the financial statements, as set
out in Appendix 2. Management
agreed to amend the draft
financial statements for all of the
errors and presentational points
we identified.
We received the draft annual
accounts in line with our audit
timetable. Our thanks go to the
Finance team for their assistance
with our work.

Page 21

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
17
Opinion Basis for opinion Conclusions
Going concern
basis of
accounting
In the public sector, when
assessing whether the
going concern basis of
accounting is appropriate,
the anticipated provision of
services is more relevant
to the assessment than the
continued existence of a
particular public body.
We assess whether there
are plans to discontinue or
privatise the Council’s
functions.
Our wider scope audit
work considers the
financial sustainability of
the Council.
Our understanding of the
legislative framework and
activities undertaken by the
Council provides us with
sufficient assurance that the
services provided by the Council
will continue to operate for at
least 12 months from the signing
date. 
Our audit opinion is unqualified in
this respect.
Opinions
prescribed by the
Accounts
Commission:
• Management
Commentary
• Corporate
Governance
Statement
• Remuneration
Report
We plan and perform audit
procedures to gain
assurance that the
management commentary,
corporate governance
statement and the audited
part of the remuneration
report are prepared in
accordance with:
• statutory guidance
issued under the Local
Government in
Scotland Act 2003
(management
Commentary); 
• the Delivering Good
Governance in Local
Government:
Framework (corporate
governance statement);
and 
We have concluded that:
• the information given in the
management commentary is
consistent with the financial
statements and has been
prepared in accordance with
relevant statutory guidance;
• the information given in the
corporate governance
statement is consistent with
the financial statements and
has been prepared in
accordance with the
Delivering Good Governance
in Local Government:
Framework;
• the audited part of the
Remuneration Report has
been properly prepared in
accordance with The Local
Authority Accounts (Scotland)
Regulations 2014.

Page 22

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
18
Opinion Basis for opinion Conclusions
• the Local Authority
Accounts (Scotland)
Regulations 2014
(remuneration report)
Matters reported
by exception
We are required to report
on whether:
• adequate accounting
records have not been
kept; or
• the financial statements
and the audited part of
the remuneration report
are not in agreement
with the accounting
records; or
• we have not received
all the information and
explanations we require
for our audit.
We have no matters to report. 
An overview of the scope of our audit
The scope of our audit was detailed in our External Audit Plan, which was presented
to the Audit, Risk and Scrutiny Board in March 2024. The Plan explained that we
follow a risk-based approach to our audit that reflects our overall assessment of the
relevant risks that apply to the Council. This ensures that our audit focuses on the
areas of highest risk (the significant risk areas). Planning is a continuous process,
and our audit plan is subject to review during the course of the audit to take account
of developments that arise.
We carried out a further review of our risk assessment following receipt of the
unaudited annual report and accounts. Our risk assessment was then updated as
follows:
• Risk of fraud in revenue recognition was focussed on the occurrence of grant
revenue.
• Risk of fraud in expenditure was focussed on expenditure completeness.
In our audit, we test and examine information using sampling and other audit
techniques, to the extent we consider necessary to provide a reasonable basis for us

Page 23

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
19
to draw conclusions. We obtain evidence through performing a review of the
significant accounting systems, substantive procedures and detailed analytical
procedures.

Page 24

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
20
Significant risk areas and key audit matters
Significant risks are defined by auditing standards as risks that, in the judgement of
the auditor, require special audit consideration. In identifying risks, we consider the
nature of the risk, the potential magnitude of misstatement, and its likelihood.
Significant risks are those risks that have a higher risk of material misstatement.
Audit procedures were designed to mitigate these risks.
As required by the Code of Audit Practice and the planning guidance issued by Audit
Scotland, we consider the significant risks for the audit that had the greatest effect
on our audit strategy, the allocation of resources in the audit and directing the efforts
of the audit team (the ‘Key Audit Matters’), as detailed in the tables below. 
Our audit procedures relating to these matters were designed in the context of our
audit of the annual accounts as a whole, and not to express an opinion on individual
accounts or disclosures.
Our opinion on the annual accounts is not modified with respect to any of the risks
described below.
Council’s significant risks at the financial statement level
These risks are considered to have a pervasive impact on the financial statements
as a whole and potentially affect many assertions for classes of transaction, account
balances and disclosures.
Risk area Management override of controls
Significant risk
description
Management of any entity is in a unique position to
perpetrate fraud because of their ability to manipulate
accounting records and prepare fraudulent financial
statements by overriding controls that otherwise appear to
be operating effectively. 
Although the level of risk will vary from entity to entity, this
risk is nevertheless present in all entities. Due to the
unpredictable way in which such override could occur, it is
a risk of material misstatement due to fraud and thus a
significant risk on all audits.
This was considered to be a significant risk and Key Audit
Matter for the audit.
Inherent risk of material misstatement: Very High

Page 25

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
21
Risk area Management override of controls
How the scope of
our audit responded
to the significant
risk
Key judgement
There is the potential for management to use their
judgement to influence the financial statements as well as
the potential to override controls for specific transactions. 
Audit procedures
• Documenting our understanding of the journals posting
process and evaluating the design effectiveness of
management controls over journals.
• Analysing the journals listing and determining criteria
for selecting high risk and / or unusual journals.
• Testing high risk and / or unusual journals posted
during the year and after the unaudited annual
accounts stage back to supporting documentation for
appropriateness, corroboration and appropriate 
approval in line with the Council’s journals policy.
• Gaining an understanding of the accounting estimates
and critical judgements made by management. We
challenged key assumptions and considered the
reasonableness and indicators of management bias
which could result in material misstatement due to
fraud.
• Evaluating the rationale for any changes in accounting
policies, estimates or significant unusual transactions.
Key observations
We did not identify any indication of management override
of controls from our audit work. We did not identify any
areas of bias in key judgements made by management.
Key judgements were consistent with prior years.

Page 26

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
22
Council’s significant risks at the assertion level for classes of
transaction, account balances and disclosures
Key risk area Fraud in revenue recognition
Significant risk
description
Material misstatement due to fraudulent financial reporting
relating to revenue recognition is a presumed inherent risk
on every audit unless it can be rebutted.
The presumption is that the Council could adopt
accounting policies or recognise income in such a way as
to lead to a material misstatement in the reported financial
position. Given the financial pressures facing the public
sector as a whole, there is an inherent fraud risk
associated with the recording of income around the year
end. 
In respect of council tax income, non-domestic rates,
housing rents and non-ring fenced government grants,
however, we do not consider the revenue recognition risk
to be significant due to a lack of incentive and opportunity
to manipulate these revenue streams.  The risk of fraud in
relation to revenue recognition is however present in all
other revenue streams.  
On review of the income transactions during the fieldwork
we have narrowed this risk to occurrence risk over grant
income, rather than the full population, as this would be an
area for potential fraud or manipulation.
This was considered to be a significant risk and Key Audit
Matter for the audit.
Inherent risk of material misstatement: Revenue
(occurrence): High
How the scope of
our audit
responded to the
significant risk
Key judgements
Given the financial pressures facing the public sector as a
whole, there is an inherent fraud risk associated with the
recording of income around the year end.
Audit procedures
• Evaluating the significant income streams and
reviewing the controls in place over accounting for
revenue.

Page 27

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
23
Key risk area Fraud in revenue recognition
• Considering key areas of income and obtaining
evidence that income is recorded in line with
appropriate accounting policies and the policies have
been consistently applied during the year.
• Substantively testing a sample of income items.
Key observations
Our work in this area is complete.
We did not identify any indication of fraud in revenue
recognition and any significant issues in respect of this
risk.   
Key risk area Fraud in non-pay expenditure recognition
Significant risk
description
As most public sector bodies are net expenditure bodies,
the risk of fraud is also present in relation to expenditure.
There is a risk that expenditure may be materially
misstated in the financial statements. 
On review of expenditure on non-pay transactions during
our fieldwork we narrowed this risk to expenditure
completeness as we regarded this aspect of expenditure
to be at the highest risk for potential fraud or manipulation.
Expenditure completeness was therefore considered to be
a significant risk and Key Audit Matter for the audit.
Inherent risk of material misstatement:
• Non-pay expenditure (completeness): High
• Accruals (completeness): High
How the scope of
our audit responded
to the significant
risk
Key judgements
Given the financial pressures facing the public sector as a
whole, there is an inherent fraud risk associated with the
recording of accruals and expenditure around the year
end.
Audit procedures

Page 28

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
24
Key risk area Fraud in non-pay expenditure recognition
• Evaluating the significant non-pay expenditure streams
and the design of the key controls in place over
accounting for expenditure. 
• Considering key areas of expenditure and obtaining
evidence that expenditure is recorded in line with
appropriate accounting policies and the policies have
been consistently applied during the year.
• Testing accruals around the year end to consider if
there is any indication of understatement of balances
held through consideration of accounting estimates.
Key observations We have not identified any issues as a result of this
testing. 
Key risk area Valuation of land and buildings and council dwellings
(key accounting estimate)
Significant risk
description
The Council held council dwellings with a net book value of
£733.9 million and land and buildings with a net book value
of £375 million at 31 March 2024. The Council revalues
land and buildings and council dwellings on a five-year
rolling basis. 
Council dwellings are valued by the District Valuer using
the beacon method which aggregates the vacant
possession value of each unit of housing stock based on
the value of a beacon or sample property. A full revaluation
exercise is completed every five years. In interim years the
values of beacon properties are updated to reflect key
factors including changes in rental prices.
Other land and buildings are held at fair value and revalued
as part of the five-year rolling programme. In addition,
indices are applied to all assets held at Depreciated
Replacement Cost (DRC) to reflect market changes within
the year.
There is a significant degree of subjectivity in the
measurement and valuation of investment property, land
and buildings and council dwellings. This subjectivity and
the material nature of the Council’s asset base represents

Page 29

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
25
Key risk area Valuation of land and buildings and council dwellings
(key accounting estimate)
an increased risk of misstatement in the financial
statements.
Inherent risk of material misstatement: Investment
property, land & buildings and council dwellings (valuation):
Very High
How the scope of
our audit
responded to the
significant risk
Key judgements
Councils are required to revalue investment properties
annually and property, plant and equipment with sufficient
regularity to ensure that the carrying amount does not differ
materially from the current value at 31 March.
Audit procedures
• Evaluating management processes and assumptions
for the calculation of the estimates, the instructions
issued to their valuation experts and the scope of their
work.
• Evaluating the competence, capabilities and objectivity
of management’s valuation expert.
• Considering the basis on which the valuations were
carried out and challenging the key assumptions
applied.
• Evaluating the information used by the valuer to ensure
it was relevant and consistent with our understanding. 
• Ensuring revaluations made during the year were input
correctly into the Council’s fixed asset register and the
accounting treatment applied was in line with the
financial reporting framework.
• Testing a sample of valuations against documentation
and assumptions used.

Page 30

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
26
Key risk area Valuation of land and buildings and council dwellings
(key accounting estimate)
Key observations
Our audit has included a detailed assessment of the
Council’s approach to assessing the carrying value of
assets not revalued in the year. Our work focused on
assets revalued on depreciated replacement cost basis
and on any significant movements in valuations we
identified and further tested. 
We are satisfied that the value of assets presented in the
financial statements is reasonable.
We have identified a minor point in relation to the
reclassification of investment properties of £0.9 million
which has been corrected in the final accounts. 
Key risk area Valuation of defined benefit pension asset (key
accounting estimate)
Significant risk
description
An actuarial estimate of the pension fund asset/liability is
calculated on an annual basis under IAS 19 and on a
triennial funding basis by an independent firm of actuaries
with specialist knowledge and experience. The estimates
are based on the most up to date membership data held by
the pension fund and have regard to local factors such as
mortality rates and expected pay rises with other
assumptions around inflation when calculating the
liabilities. There is a risk that the assumptions used are not
appropriate.
Inherent risk of material misstatement:
Defined benefit pension asset (valuation): High
How the scope of
our audit
responded to the
significant risk
Key judgements
A significant level of estimation is required in order to
determine the valuation of pension assets/liabilities. Small
changes in the key assumptions (including discount rates,
inflation and mortality rates) can have a material impact on
the pension asset/liability. 
Audit procedures

Page 31

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
27
Key risk area Valuation of defined benefit pension asset (key
accounting estimate)
• Evaluating management processes and assumptions
for the calculation of the estimates, the instructions
issued to their actuarial experts and the scope of their
work.
• Evaluating the competence, capabilities and objectivity
of management’s actuarial expert.
• Considering the basis on which the valuation was
carried out and challenging the key assumptions
applied.
• Evaluating the information provided to the actuary for
the purposes of their calculation of the IAS 19 estimate
to ensure it was complete and consistent with our
understanding. 
• Ensuring pension valuation movements made during
the year were input correctly into the general ledger and
financial statements and that the accounting treatment
applied was in line with the financial reporting
framework.
Key observations
The IAS 19 actuarial report for the Council identifies a
pension surplus (or pension asset) of £567.3 million
(£434.1 million in 2022/23). Actuaries calculate the year
end position based on a number of assumptions and, in
recent years, increases in the discount rate assumption is
the main factor in the pension asset calculation outcome
following many years where a pension liability outcome
was expected. 
Accounting standards require the Council to review the
pension surplus and only recognise the lower of the
surplus or an ‘asset ceiling’. The pension asset ceiling for
this year limited the asset value to Nil and this has been
correctly presented in the balance sheet.
Prior year figures have been adjusted to show £73.5 million
of the unfunded pension liability which needed to be
separated from the funded position.

Page 32

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
28
Key risk area Valuation of defined benefit pension asset (key
accounting estimate)
We are satisfied that we have obtained reasonable
assurance over the disclosures in the financial statements
relating to the pension asset.

Page 33

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
29
Key risk area Provision for doubtful debts (key accounting estimate)
Significant risk
description
The Council in its annual accounts provides for material
doubtful debts over sundry debtors. 
How the scope of
our audit
responded to the
significant risk
Key judgements
There is a significant degree of subjectivity in the
measurement and valuation of provisions for doubtful debts. 
This subjectivity represents an increased risk of
misstatement in the financial statements.
Audit procedures
• Obtaining the breakdown of provisions and assessing
the reasonableness of management’s judgements as
well as challenging the appropriateness of any
assumptions used.
• Performing substantive testing on provisions for doubtful
debts for sundry debtors where values and balances are
derived by valuation and estimation.
Key observations Our work in this area has not identified any issues. 
Group and the Council materiality
Materiality is an expression of the relative significance of a matter in the context of
the financial statements as a whole. A matter is material if its omission or
misstatement would reasonably influence the decisions of an addressee of the
auditor’s report. The assessment of what is material is a matter of professional
judgement and is affected by our assessment of the risk profile the Council and the
needs of users. We review our assessment of materiality throughout the audit.
Whilst our audit procedures are designed to identify misstatements which are
material to our audit opinion, we also report to the Council and management any
uncorrected misstatements of lower value errors to the extent that our audit identifies
these. 
Our initial assessment of materiality for the group financial statements was £18.1
million and the Council’s financial statements was £18 million. On receipt of the
unaudited financial statements, we reassessed materiality and kept it at the same
level. We consider that materiality levels have remained appropriate throughout our
audit.

Page 34

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
30 
Group 
£million
Council
£million
Overall materiality for the financial statements 18.1 18.0
Performance materiality 13.5 13.5
Trivial threshold 0.500 0.500
Materiality
Our assessment is made with reference to the Group and
Council’s gross expenditure. We consider this to be the principal
consideration for the users of the annual accounts when
assessing financial performance of the Council and its group. 
Our assessment of materiality equates to approximately 2% of
gross expenditure as disclosed in the 2023/24 unaudited annual
accounts.
In performing our audit, we apply a lower level of materiality to
Remuneration Report. Our materiality was set at £5,000.
We perform audit procedures on all transactions, or groups of
transactions, and balances that exceed our materiality levels set.
We perform a greater level of testing on the areas deemed to be
at significant risk of material misstatement.
Performance
materiality
Performance materiality is the working level of materiality used
throughout the audit. We use performance materiality to
determine the nature, timing and extent of audit procedures
carried out. 
Performance materiality is set at a value less than overall
materiality for the financial statements as a whole to reduce to
an appropriately low level the probability that the aggregate of
the uncorrected and undetected misstatements exceed overall
materiality. 
Trivial
misstatements
Trivial misstatements are matters that are clearly
inconsequential, whether taken individually or in aggregate and
whether judged by any quantitative or qualitative criteria.

Page 35

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
31
Common Good Funds materiality 
Our initial assessment of materiality for the Paisley Common Good Fund financial
statements was £0.180 million. On receipt of the unaudited financial statements, we
reassessed materiality and updated it to £0.190 million.
Our initial assessment of the Johnstone Common Good Fund materiality remained
unchanged from the planning stage.
Our initial assessment of materiality for the Renfrew Common Good Fund financial
statements was £1.010 million. On receipt of the unaudited financial statements, we
reassessed materiality and updated it to £1.090 million.
We consider that our updated assessments have remained appropriate throughout
our audit. 
Overall
materiality 
(£)
Performance
materiality
(£)
Trivial
threshold
(£)
Paisley £190,000 £142,500 £9,500
Johnstone £1,560 £1,170 £100
Renfrew £1,090,000 £817,500 £54,500 
Overall materiality: our assessment is based on approximately 2% of net assets. We
consider this benchmark to be the principal consideration for the users of the
financial statements when assessing the performance of each fund.
Performance materiality: Using our professional judgement we have calculated
performance materiality at approximately 75% of overall materiality.
Trivial threshold: 5% of overall materiality for the financial statements.
Group audit
The Council prepares group financial statements in addition to its own financial
statements, as required by the CIPFA Code, as there are material differences
between the Council and group figures. The Council’s group structure is detailed
within the annual accounts.
As group auditors under ISA (UK) 600 we are required to obtain sufficient
appropriate audit evidence regarding the financial information of the components and
regarding the consolidation process to express an opinion on whether the group
financial statements are prepared, in all material respects, in accordance with the
applicable financial reporting framework. The following table sets out the
components within the group.

Page 36

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
32
Component Significant Level of response required
Renfrewshire Leisure Ltd
(OneRen)
No Analytical
Common Good Funds No Analytical
Paisley Museum Reimagined Ltd No Analytical
Park Lane Developments
(Renfrewshire) LLP
No Analytical
Coats Observatory Trust No Analytical
Strathclyde Partnership for
Transport
No Analytical
Strathclyde Concessionary Travel
Scheme Joint Committee
No Analytical
Renfrewshire Valuation Joint
Board
No Analytical
Renfrewshire Health and Social
Care Integration Joint Board
No Analytical
AMIDS (Renfrewshire) LLP No Analytical
Comprehensive – the component is of such significance to the group as a whole
that an audit of the component’s financial statements is required for group reporting
purposes.
Analytical - the component is not significant to the group and audit risks can be
addressed sufficiently by applying analytical procedures at the group level.
We revisited our planning group scope assessment, following receipt of the
unaudited accounts and our assessment remained the same. 
As part of our audit, we reviewed the consolidation entries made within the group
accounts, confirmed those entries back to the financial statements of the group
bodies and evaluated any significant adjustments made to align the accounting
policies or the different year end dates. Overall, we concluded that the results of the
group bodies had been appropriately consolidated into the Council’s audited group
accounts.
Our analytical procedures have not highlighted any significant material issues in the
Group accounts.

Page 37

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
33
Renfrewshire Trust Funds 
Coats Observatory Trust Fund
The Charities Accounts (Scotland) Regulations 2006 outline the accounting and
auditing requirements for charitable bodies.  The Regulations require an auditor to
prepare a report to the charity trustees where an audit is required by any other
enactment.
The Council’s charitable trust is covered by the requirements of section 106 of the
Local Government (Scotland) Act 1973 and consequently require a full audit.  Each
registered charitable trust has required a full audit since 2013/14.
There is one registered charity preparing its accounts on a receipts and payments
basis – Coats Observatory Trust Fund. This is subject to separate Audit Report.
Audit differences
We identified a small number of errors in the draft financial statements during our
audit. These are set out in more detail in Appendix 2. Management agreed to amend
the financial statements for all the errors we identified. The overall impact of the
adjustments made on the financial statements of the Council relate to the pension
fund adjustment identified above:
• £73.5 million reduction in the pension reserve 
• £73.5 million reduction to pension liabilities.
We also identified disclosure and presentational adjustments during our audit which
have been reflected in the final set of financial statements and are disclosed in
Appendix 2.
Internal controls
As part of our work we considered internal controls relevant to the preparation of the
financial statements such that we were able to design appropriate audit procedures.
Our audit is not designed to test all internal controls or identify all areas of control
weakness. However, where, as part of our testing, we identify any control
weaknesses, we report these to the Council. These matters are limited to those
which we have concluded are of sufficient importance to merit being reported. 
We did not identify any significant control weaknesses during our audit. Other points,
including recommendations on payroll recommendations and related parties are
included in Appendix 3.
Recommendation 1 &2
Follow up of prior year recommendations

Page 38

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
34
We followed up on progress in implementing actions raised by the predecessor
auditor in the prior year as they relate to the audit of the financial statements. Full
details of our findings are included in Appendix 4.
Other communications
Accounting policies, presentation and disclosures
Our work included a review of the adequacy of disclosures in the financial
statements and consideration of the appropriateness of the accounting policies
adopted by the Council. 
The accounting policies, which are disclosed in the financial statements, are in line
with the CIPFA LASAAC Code of Practice and are considered appropriate. The
accounting policies used in preparing the financial statements are unchanged from
the previous year. 
There are no significant financial statements disclosures that we consider should be
brought to your attention. All the disclosures required by relevant legislation and
applicable accounting standards have been made appropriately. Overall, we found
the disclosed accounting policies, and the overall disclosures and presentation to be
appropriate.
Fraud and suspected fraud
We have previously discussed the risk of fraud with management and the Audit, Risk
and Scrutiny Board. Internal Audit is providing regular updates to the Board on any
internal fraud related investigations. We have not been made aware of any additional
incidents in the period nor have any incidents come to our attention as a result of our
audit testing. 
Our work as auditor is not intended to identify any instances of fraud of a non-
material nature and should not be relied upon for this purpose.
Non-compliance with laws and regulations
As part of our standard audit testing, we have reviewed the laws and regulations
impacting the Council. There are no indications from this work of any significant
incidences of non-compliance or material breaches of laws and regulations.
Written representations
We requested written representations from management, and these were approved
at the same time as the financial statements were approved by the Audit, Risk and
Scrutiny Board, signed by the director of finance and resources, and provided to us
before we completed our audit and issued our auditor’s report. 
Related parties
We are not aware of any related party transactions which have not been disclosed.
Confirmations from third parties

Page 39

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
35
All requested third party confirmations have been received.

Page 40

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
36
Wider Scope
Dargavel Primary School
Our 2022/23 external audit report highlighted the issues raised by the Bowles Report
in relation to failures to adequately assess the impact on the school estate from the
Dargavel development. This resulted in the Council commissioning a new primary
school that was too small for the needs of the Dargavel community and limiting
developer contributions to the costs of that school. This has required the Council to
commission the building of an additional new primary school at Dargavel with the
costs of this new build falling on council tax payers.   As noted below, these matters
were the subject of a Controller of Audit S102 Report in January 2024 with a further
follow up report in August 2024.
The cost to address this error for the Council will be significant and is currently
estimated at up to £82 million in gross capital costs (c£64 million net cost after taking
into account expected developer contributions) for building a second primary school
in Dargavel and building a larger than planned secondary school extension to Park
Mains High School to accommodate the increased need for pupil places. More
detailed financial impact assessment is noted below.
Controller of Audit reports
Our prior year reporting on Dargavel was followed by two Controller of Audit reports
presented to the Accounts Commission (“the Commission”):
• the S102 report on School Accommodation for Dargavel Village presented to the
commission in January 2024; and
• the Update report on school accommodation for Dargavel Village presented to
the Commission in August 2024.
The Update report from August had the following key messages for which the
Council has put their responses.
Exhibit 1 Accounts Commission Update report summary of findings
Accounts Commission finding Renfrewshire Council response
The Commission welcomed the
increase in community
engagement undertaken by the
council since January 2024 and
its ongoing commitment to
improve its engagement with
affected communities. However, it
Council officers will share the detail of
engagement that is progressed with the Dargavel
and Park Mains High School communities with
the Council’s auditors as well as wider work being
progressed to develop the Council’s corporate

Page 41

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
37
also recognised that rebuilding
trust takes time, and noted the
breadth and strength of views
expressed by the community in
the recent statutory consultation.
The council must continue to
demonstrate and evidence that
engagement with communities is
robust, inclusive, and meaningful,
and that feedback received is
reflected in decision-making
processes. 
approach to consultation, communication, and
engagement.
Auditors found no evidence of
negative impacts on wider council
services from the miscalculation
in school roll data in the council’s
performance information reported
in June. While the Controller was
not asked to follow up on financial
management issues, the
Commission was concerned that
uncertainty remains around the
financial implications of previous
planning failures relating to
Dargavel and their impact on
council services. The Council
must set out clearly and
transparently the financial
implications associated with the
new primary school and
secondary school extension in its
budget monitoring and financial
planning and should continue to
work with community planning
partners to mitigate any potential
impact on relevant services.
The financial consequences of addressing
Dargavel have been reported by the Director of
Finance and Resources in several Education and
Children’s Services Policy Board reports and
Council reports since November 2022. It has
been set out clearly and transparently that the
estimated net financial impact will require to be
addressed as part of the Council’s medium term
financial planning arrangements, which has
identified a requirement to address much wider
savings of approximately £50 million (note that
this is inclusive of the unplanned costs associated
with addressing Dargavel requirements). We note
that the Council does not anticipate reporting
separately on the financial impact of decisions
linked to school provision in Dargavel in future
wider budgetary reporting in line with its normal
practice.
The Commission will therefore
maintain a close interest in how
the council moves forward with
the development and publication
of its Medium-Term Financial
Plan, the actions it puts in place
Officers will continue to support the local audit
team to understand the Council’s progress in
managing delivery of its wider medium term
financial plan, the latest update of which is
provided to the full Council in September 2024.

Page 42

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
38
to mitigate the additional costs
arising, and the wider impacts on
service provision. The
Commission asked the Controller
of Audit to monitor this through
the annual audit and keep the
Commission informed
accordingly.
The Commission supports the
Controller’s conclusion that a
contemporaneous record of
decision-making in relation to a
supplementary report provided by
David Bowles should have been
kept by officers and reiterate
again the importance of
transparency and good
governance.
Council officers accept the Commission’s view
and while the internal review into the handling of
specific planning applications related to Dargavel
was thorough and detailed, the review should
have been appropriately recorded.
The Commission welcomed the
council’s development of a
leadership programme for
officers. However, it is vital that
this programme is extended to
include the political leadership of
the council. Elected members
have a key leadership role and
must be supported to fulfil their
scrutiny and decision making
responsibilities effectively. It is
crucial that historic failures of
leadership and governance
referred to in the Bowles report
are not repeated. The
Commission encouraged the
council to consider making full
use of the external improvement
resources available to them.
An annual development week is provided to
support Elected Member’s development in
addition to specific sessions provided over the
course of the year. The Head of Corporate
Governance will continue to liaise with Elected
Members to identify additional areas of
development to inform the proposed programme.
Training may be delivered internally or by external
providers as appropriate
The Commission noted the
auditor’s conclusion that the
council continues to demonstrate
that it is taking action to respond
to the issues highlighted in the
Bowles report, and that
Officers will continue to support the local audit
team and Controller of Audit throughout the Best
Value Audit process to better understand the
culture and values of the Council, and the
commitment to effective corporate working across
the council and how this is evidenced.

Page 43

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
39
behaviours have continued to
improve since January 2024. The
Commission recognised the
challenges the council faces in
balancing competing priorities
and making difficult decisions and
expect it to keep up the work it
has done to actively and openly
learn lessons from previous
challenges and amend
behaviours accordingly. As part
of this, the Commission expects
the council to demonstrate
effective cross-council working
and decision-making. Overall, the
Commission maintains a strong
interest in the culture of the
council and whether it can
demonstrate sustained change
and improvement in the longer
term. As such, the Commission
expects that organisational
culture will be an area of focus in
the accelerated Best Value report
due for consideration by the
Commission.
Further update on the financial impact 
Capital cost
The gross capital cost of building a new primary school is now expected to be c.£82
million, with c.£18 million of contribution expected from the developer, reducing to
net capital cost of £64million. The gross cost is allocated as follows:
• £45 million for new Dargavel Primary School 
• £37 million for the Park Mains High School extension.
The gross cost increased from £75 million reported previously due to the degree of
changes required to the existing Park Mains High School and in order to arrive at
appropriate and consistent school design has been updated to £82 million (c.10% of
Council’s capital plan for the next 5 years) The new estimate covers both the costs of
the new build extension, and the costs of remodelling within the existing school in
order to support subject adjacencies and the continued effective operation of the
school. The degree of intervention and remodelling within the existing school

Page 44

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
40
footprint is more substantial in order to ensure the expanded school when complete,
still feels from an educational standpoint like a single school.
Revenue cost
These capital costs are expected to be partly met from new borrowing and will add
c£1.2 million per annum in additional revenue costs to meet interest and principal
repayments. Initially, the additional revenue costs of c£4million for borrowing interest
cost had been factored into the Council’s medium term financial plans. However, the
Council is now proposing to borrow only for the Park Mains High School extension,
and to fund the build of the new Dargavel Primary School from the investment capital
fund (reserves). This fund has reserves at £86 million and is held by the Council to
support the Council’s capital investment programme and to support the Council
manage its long-term debt position.
The Council provided us with a detailed breakdown of other net running costs
associated with operating the new and expanded schools presented below and
totalling to net of c£1.6 million. These costs are early estimates and will likely start to
be impacting the budget when the school is built and full pupil roll is achieved, which
is expected over the next 5-10 years. 
In total the expected revenue impact, after adding annual cost of borrowing, is
estimated at £2.8 million and represents 0.5% of annual Council spend. 
Exhibit 2 Additional estimated revenue cost
Additional cost
item
Dargavel new
Primary School
£ million
Park Mains High
School extension
£ million
Total
£ million
Staff cost 2.8 3.1  5.9
Other cost 0.9 0.9 1.8
Total cost 3.7 4.0 7.7
Expected associated
increase in revenue
grant income
(3.1) (3.0) (6.1) 
Net additional
running cost
0.6 1.0 1.6
Borrowing cost -* 1.2 1.2
Net additional cost 0.6 2.2 2.8
(*) This does not include consideration of the impact of use of the capital
reserve to fund Dargavel School build 
Source: Renfrewshire Council estimates

Page 45

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
41
Instead of borrowing the Council applied their Investment Capital Fund to fund the
capital costs of the new Dargavel primary school. This was done after reviewing the
capital funding requirements, future loans charges requirements and how these will
impact on the Council’s future revenue position, and available capital reserve
balances.
Had the Dargavel issue not required the Council to bear the cost of building of a new
primary school, it could have applied available reserves to other aspects of its capital
programme.  
We note in context that the Council’s existing medium term financial plan highlights
the need to make savings of over £47 million for the period to the 2027-2028.  The
revenue costs associated with the Dargavel issues identified above added to that
already challenging savings target and were incorporated into the Council’s medium
term financial plans in due course. 
We have noted throughout our work the openness and transparency with which the
Council have approached this difficult and challenging issue and we would like to
thank the Council for their support during our audit.

Page 46

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
42
Financial management
Our detailed findings on the Council’s financial management arrangements are set
out below. 
Financial performance 
The Council reported a General Fund overspend of c£3.5 million at 31 March 2024.
The revised budget is £513.6 million while the actual outturn is £517.0million.
Significant additional spend was incurred due to inflationary pressures during the year. 
The Council used its Financial Sustainability Fund (reserves) as planned to cover
shortfalls in the year end position and to achieve breakeven; these included: £1 million
for parking income loss, £3 million for childcare placements, and a further £0.5 million
for Proactive Tree Management. 
Capital spending of £23 million for housing and £102 million for non-housing projects
was managed within the overall expenditure control limits approved by Council.
Planned spend was impacted by inflationary pressures and the availability of
contractors. The 2024/25 capital plan has been adjusted accordingly. 
The Council’s in-year council tax collection performance for 2023/24 was 94.3%, a
reduction on the 95.5% collected in 2022/23. However, actual Council tax revenues
performed above expectation, returning an over recovery of £0.420 million compared
to budget. This sum also includes recovery of prior year arrears. 
Revenue performance against budget 
The General Fund overspend of £3.5 million including an overspend in Adult Services
of £0.8 million was mainly due to inflationary cost pressures. Excluding the Adult
Services position, which is managed by the HSCP, the overspend on Council services
was £2.7 million. 
The remaining c£2.7 million overspend are a combination of the following:
• £5.3 million overspend of Environment, Housing and Infrastructure Services;
• £1.0million overspend of Children’s Services; and
• £3.4 million underspend of Miscellaneous Services.

Page 47

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
43 
Housing revenue account (HRA) 
The Housing Revenue Account (HRA) broke even at year-end after using £0.3 million
from unallocated reserves, which is £0.9 million less than the £1.3million originally
budgeted. The remaining £6.2 million in reserves is considered a prudent amount to
handle inflation and other costs, such as the ICT Housing System replacement. 
The £0.3million overspend was mainly due to higher-than-expected demand for
repairs and maintenance, especially in vacant properties, and additional Council Tax
costs. This was offset by higher-than-budgeted interest earnings. 
Capital expenditure
Non-Housing Capital Budget Performance
In 2023/24, non-housing capital expenditure was £102.5million. Asset sales
generated £0.5million in capital receipts, bringing the total of Capital Receipts
Reserve to c£8.7million. Of this, £1.2million was used for current year investments,
leaving c£7.5million committed to future projects. The expenditure stayed within the
Council’s approved limits.
Housing Capital Budget Performance
Housing capital expenditure for 2023/24 was £22.995m, with £1.286m generated
from asset sales.
Treasury management 
The Council actively manages treasury risks to minimise its exposure to financial
market volatility and protect funding for services. It follows CIPFA’s Code of Treasury
Management and has policies covering credit, liquidity, and market risks. 
The Council approves a Treasury Management Strategy that outlines how to
manage risks related to financial instruments, including an Investment Strategy that
prioritizes security and liquidity over yield, in line with Scottish Government guidance.
The strategy aims to balance risk with returns or costs. The strategy for 2023/24 was
approved by Council on 2 March 2023. Based on the Council’s planned programme
of investments and interest rate forecasts for the year, the Council’s borrowing
strategy was to firstly use internal cash balances to finance the Capital Investment
Programme. This approach was prudent as borrowing rates remained high
throughout the year. 
During 2023/24, the Council was under-borrowed relative to its needs for the capital
investment programme by £144 million. The Council takes advice from its Treasury
advisers regarding the most appropriate timing of borrowing, and the appropriate
duration of this borrowing. At the end of 2023/24, the Council's liquidity position

Page 48

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
44
reduced, owing to some fixed term investments, so a decision was taken to borrow
£20 million to close the under-borrowed gap. As a council with significant HRA
capital financing requirement, it was able to take advantage of the HRA Certainty
Rate offered by the PWLB and was able to borrow at 0.4% less than standard PWLB
rates. This resulted in an investment benefit compared to the rate at which the sum
was invested; however, our understanding is this was not (and never is in the
Council’s view) the primary driver for the borrowing decision. 
Overall, the Council’s total external borrowings increased by £13.01 million. 
Temporary investments held by the Council decreased by £81.2 million. The
decrease in investments is attributable to several factors, including spending
pressures linked to the capital programme, backdated pay awards, and Non-
Domestic Rates refunds following the retrospective revaluation of some accounts. 
Systems of internal control
We have evaluated the Council’s key financial systems and internal financial controls
to ensure internal controls are operating effectively to safeguard public assets.
We did not identify any significant weaknesses in the Council’s accounting and
internal control systems during our audit.
Prevention and detection of fraud and irregularity
The Council is responsible for establishing arrangements for the prevention and
detection of fraud, error and irregularities, bribery and corruption. 
We have reviewed the arrangements and concluded that there are appropriate
arrangements for the prevention and detection of fraud, error and irregularities.
National fraud initiative
The National Fraud Initiative (NFI) is a counter-fraud exercise co-ordinated by Audit
Scotland working together with a range of Scottish public bodies to identify fraud and
error.   
The most recent NFI exercise was for 2022/23. There has been a good level of
follow-up activity at RC with 100% of VHR matches processed in most areas. As of
March 2024, all reports have been closed except for two which the Council is waiting
for further information from. 
The audited body has engaged well with the NFI exercise. The Council had a good
level of follow up activity, meaning that most matches have been closed down. 
In addition, the body has strong governance arrangements in relation to
communication and transparency of NFI.

Page 49

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
45 
Financial sustainability
Significant audit risk
Our audit plan identified a significant risk in relation to financial sustainability under
our wider scope responsibilities. We continue to recognise it as a significant risk and
so is the Council as this as one of its highest risks in the corporate risk register. 
Financial sustainability
considers its medium-term financial planning through its Financial Sustainability
and General Fund Financial Outlook report regularly presented to the full Council.
The current expected budget gap prior to any decisions on council tax would add
up to £74 million over the period between 2024/25 and 2027/28. Assuming 6.5%
council tax increases in last three of those years the funding gap reduces to £47
million and would require the Council to identify c.£12million of savings and
efficiencies each year (an increase from £8million/year estimated a year ago in
similar analysis). However, such council tax increases would be subject to prior
Council vote and approval. 
The Council has a Financial Sustainability reserve of £13.2 million which it plans to
utilise over the coming years. Various commitments to utilise this reserve and
expected reduction in employer pensions contributions will result in a balance of c.
£19 million in this reserve at the end of 2024/25. Further £12 million from the
reduced contributions will grow that reserve to £31 million the following year. After
that year the pension contributions are expected to increase closer to the previous
levels and savings from this source will be limited. Even with the minimum budget
gap of £47 million, use of reserves would not be sufficient and requires
identification of savings during that period of c.£5 million per annum. However, this
also depends on the decision on council tax levels.
The Council maintains a policy of minimum £10 million of unallocated reserves
(just over 2% of net expenditure) held for emergency purposes.
The Council reviewed its budget planning assumptions to reflect the financial
challenges impacting on the external environment which the Council operates in.
Due to the timing of the Scottish Government budgets there is a level of
uncertainty on the funding provided. Councils estimate there is a minimum of £585
million of difference in their anticipated expenditure and the funding and income
they expect to receive for 2024/25. The key assumption used for the next years by
Renfrewshire Council is a flat cash allocation for 2025/26, although now seen as
an ‘optimistic’ assumption. From year 2026/27 and following this the assumption
changes into a 0.5% increase.

Page 50

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
46
Financial sustainability
The Council highlights the fact that there is a timing disconnect between the
Council’s ability to develop and deliver recurring savings to match the spend
pressures which are emerging, resulting in a growing recurring financial gap. It
becomes more likely that the council will utilise reserves in the short and medium
term to achieve financial balance.
In addition to the council tax, other assumptions included pay and contractual
inflation cost pressures. The continuing and uncertain impact of cost pressures on
the Council’s finances and ability to deliver services in a sustainable manner
remains a significant challenge and risk. 
Our detailed findings on the Council’s arrangements for achieving long term financial
sustainability are set out below.
2024/25 revenue budget 
The Council approved its 2024/25 revenue budget at a meeting in February 2024.
The Council voted to freeze council tax and agreed utilisation of non-recurring
reserve funding up to £4.3 million to achieve a break even position. The expected
compensatory funding from Scottish Government in relation to agreeing a council tax
freeze is £4.9 million and equivalent to 4.4% council tax increase.
The projected outturn at June 2024/25 is a deficit of £9.4 million against its total
budget of £523.2 million. The main items driving the deficit are Education and
Children’s Services with £3 million and Adult Services with £6.1 million in relation to
care packages. This is consistent with the approved budget for 2024/25 which
outlined anticipated draws on reserves of £4.3 million for Council general services
and £7.5 million for Adult Social Care. There are a number of financial risk areas that
provide a level of uncertainty as to the final outturn:
• finalisation of the pay offer for 2024/25, currently with an additional 0.2% funding
required over the 3% pay increase assumed in the budget;
• the teachers’ pay offer, assumed to be 3% in the budget, has been settled at
4.27%. Funding from the Scottish Government to support the offer has not yet
been confirmed;
• increase in employer pension contributions for teachers from 23.6% to 28.6%.
The increase has resulted from the outcome of the valuation of the teachers’
pension scheme at a UK level; and
• specific grant funding in relation to the maintenance of teacher numbers is yet to
be released by the Scottish Government.

Page 51

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
47
Cost improvement plans
The Council re-commenced its service transformation programme in 2022, including
progressing financial sustainability workstreams to achieve savings over the medium
term. This is branded under the name of Right for Renfrewshire (‘RFR’). There have
been specific, targeted reviews undertaken as a part of RFR and in the three years
post-pandemic the Council delivered £27 million of savings, and with a significant
part of it coming from the Finance and Resource service and Chief Executive service
and included reviews of the Operations and Infrastructure service within
Environment, Housing and Infrastructure to generate savings over 2022/23 to
2024/25. Generating further savings of this scale will be challenging.  
The Council achieved cumulative savings of £182 million since 2011/12 as
presented in the table below.
Exhibit 4 Savings achieved  
Source: Financial Outlook and Medium Term Financial Plan at September 2024
The approach to the delivery of savings over this time has been to try and protect
education and social care services as much as possible and driven by national policy
choices with a range of conditions and controls exercised by the Scottish
Government as well as by local policy choices. This included consideration of debt
levels, as additional debt creates ongoing interest liabilities to be paid every year and
therefore reduces the amount of funds available to be spent on individual services.
Renfrewshire has one of the lowest ratios of debt financing cost to net revenue ratios
in Scotland at 3.1% (against national average of 5.5%). 
Council has previously agreed an £8 million per annum departmental savings target
each year for the three years from 2025/26. Each Service Director and their
management teams are in the process of developing and finalising options to deliver
these planned savings. This work will continue over the coming months with update

Page 52

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
48
reports to be provided to Council and Policy Boards, including consideration at the
Council budget setting meeting planned February 2025.
Medium term financial plan
The medium-term financial challenge and financial gap has been considered by the
Council numerous times as the budget gap poses an increasing risk to the Council’s
delivery of services over the medium-term. The Council has moved into a position of
using its reserves in the medium term to cover budget gaps but recognises this is not
sustainable. The Council hopes this will allow to support a smooth delivery of
savings to help support service deliver, manage the pace at which recurring savings
are required and to protect the capacity of the council to deliver savings. The current
medium-term forecast is as follows.
Exhibit 5 Medium term financial plan
Item 2024/25 2025/26 2026/27 2027/28 Total 
£m £m £m £m £m
Opening budget gap 0.6 2.3 8.3 14.5 25.7
New pressures 56.7 25.5 18.3 18.8 119.3
Savings (8.9) (6.2) (1.8) (0.8) (17.7)
Movement in SG
revenue grant
(41.2) (6.1) (3.0) (3.0) (53.3)
Budget gap prior to
council tax decisions
7.2 15.5 21.8 29.5 74
CT increase (0%,
6.5%, 6.5%, 6.5%)
(4.9) (7.2) (7.3) (7.5) (26.9)
Remaining budget
gap
2.3 8.3 14.5 22.0 47.1
Use of reserves (5.3)* (8.3) (14.5) (22.0) (50.1)
(*) includes one off commitment of £2 million in that year
Source: Financial Outlook and Medium-Term Financial Plan at September 2024
The medium-term position is based on a number of assumptions and uncertainties,
including:
• finalisation of pay increase agreement for teaching and non-teaching staff; 1%
of increase is equivalent to £3.2 million of additional cost;
• impact of inflation is uncertain, and previous years have seen significant
increase in electricity and fuel cost;

Page 53

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
49
• adult and social care delivery through the Renfrewshire HSCP relies
significantly on use of reserves; £7.2 million of reserves will be applied in
2024/25, from a total reserve balance of £14.7 million; and
• expected increased cost or overspends in early years and school transport,
lifecycle maintenance and net zero impact. 
Capital plans 
The Council has a number of medium- and long-term capital projects, financed
though borrowing, Levelling up Fund, City Deal, Regeneration Capital Grant funds
and Scottish Government funding.  The largest capital projects over the next 5 years
include the School Estate Programme, City Deal Projects (Clyde Waterfront &
Renfrew Riverside, Glasgow Airport Investment Area), Advanced Manufacturing
Innovation District Scotland South project, Paisley Museum and investment in
heritage venues and town centre infrastructure. These projects are supported by
asset lifecycle maintenance programmes.
Exhibit: Capital programme 
2024/25
(£m)
2025/26
(£m)
2026/27
(£m)
2027/28
(£m)
2028/29
(£m)
Non-
housing
147.8 151.0 83.5 55.7 12.4
Housing 41.2 77.7 62.0 62.2 38.2
Total 189.0 228.7 145.5 117.9 50.6 
Projected outturn at March 2024/25 is a break-even position. The total borrowing and
long-term debt over the next three years is expected to increase by 31% from £595
million in 2024/25 to £782million in 2026/27 and new borrowing will need to be
financed, therefore reducing revenue available to fund other services.
Since the pandemic, a number of factors have impacted the Council’s ability to fully
deliver its capital programme within the originally planned timescales. This was due
to a number of factors, including the complexity of works, cost of materials, supply
chain issues and availability of contractors. Given the scale of the Council’s ongoing
programme this is likely to remain a continuing area of challenge. Given the scale of
the Council’s ongoing programme this is likely to remain a continuing area of
challenge.
Housing Revenue Account

Page 54

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
50
The Council plans to deliver total housing capital investment of £281.3million over
the 5-year period up to 2028/29. The Council expects that £35.3million of the total
will be financed from government grant. The HRA 2023/24 budget of £41.3million is
expected to be on track for delivery, with no under or overspend currently reported. 
The HRA operates a rolling 30-year Business Plan model which is the standard
operating practice amongst local authorities and Registered Social Landlords. The
30-year basis of the model reflects the need for a long term planned approach to the
replacement of major items such as rewiring and central heating aligned to the
lifecycle of the element. 
Similar to non-housing construction, the sector is still experiencing the impact of
pandemic recovery, with the backlog of repairs to void properties influencing income
generation. The Council is focusing on the first phase of its capital programme to
deliver c.1,100 housing properties and to invest £30million in the existing high-rise
accommodation.  To ensure sufficient funding in the long term, an assumption of 1%
above CPI as an uplift to rents is assumed for every year across the 30-year plan.

Page 55

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
51
Vision, leadership and governance
Our detailed findings on the Council’s arrangements are set out below.
Vision
The Council approved its Council Plan in September 2022, articulating its vision,
priorities and strategic outcomes for the Council. The Council Plan strategic
outcomes are used to underpin the Council’s internal and external communication
and engagement and these align to their organisational values. The Plan has five
main strategic outcomes: Place, Economy, Fair, Green and Living our values.
The Council Plan was subject to a review in early 2024 and a refreshed plan with
refined priorities, actions and indicators was recently approved by the Leadership
Board in June 2024.
Corporate leadership team
The Council senior team consists of the Chief Executive, 3 Directors of departments
and 15 Heads of Service (along with the Chief Officer of the HSCP and Chief
Executive of partner organisation OneRen). 
Governance arrangements
The Council’s governance framework comprises the systems and processes, and
culture and values, by which the Council is directed and controlled and through
which it accounts to, engages with and leads the community. It enables the Council
to monitor the achievement of its strategic objectives set out in the Council plan. The
Council has approved and adopted a Local Code of Corporate Governance and
publishes information on how it complies with that Code. 
The Council has a number of Boards (Committees) with delegated authorities and
specific remits in place. The Audit, Scrutiny and Risk Board (ARSB) is chaired by an
independent member and comprises nine members from all political parties
represented on the Council. Its remit is to consider internal and external audit and
scrutiny reports, note Internal Audit and Counter Fraud performance, consider and
monitor progress reports against any action points raised by internal and external
auditors. The Board also has responsibility for considering the Council’s code of
corporate governance, approving the risk management policy and strategy and
reviewing the effectiveness of risk management arrangements. Other functions
include monitoring and reviewing service delivery performance, policies and
practices and to submit recommendations to the Council.
Governance reviews and updates

Page 56

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
52
Our prior year audit recommended that the Council undertake a review of the
effectiveness of the ARSB against the CIPFA good practice guidance for audit
committees and to consider it scrutiny arrangements.
The Council has taken the following steps to review its governance and scrutiny
arrangements:
• a self-assessment against CIPFA guidance for local authority audit
committees;
• an exercise benchmarking the council’s governance arrangements against
other councils;
• a cross-party working group review of governance arrangements;
• a review of the council’s risk management arrangements. 
At its meeting in May 2024, the Council considered the results of the ARSB’s self-
assessment against CIPFA good practice on audit committees. The self-assessment
identified a number of areas of good practice and 11 action points, including
proposed changes to the governance of the ARSB. The Council approved the results
of this review, the action plan and a number of changes to the way the ARSB
operates in relation to its terms of reference, guidance and role descriptions. All the
action points were implemented by the end of June. The cross-party review of
governance also identified a number of actions, including a review of the Council’s
Scheme of Delegation. An action plan was developed compiling actions from the
reviews, with progress against actions monitored by the ARSB. All but one of the
actions have now been delivered, with the final action to be completed by December
2024.
The Council has developed a leadership programme in conjunction with SOLACE.
The programme covers areas including risk management, good governance and
engaging with the public. The Council initially plans to run the programme in three
cohorts. The first cohort, consisting of the extended Corporate Management Team
has completed the programme and the second cohort began in April in 2024. The
programme is ongoing so it is too early to reach a conclusion on its effectiveness.
SOLACE has collated feedback from the first cohort and the council has used this to
update the programme for subsequent cohorts. The scope and timing of the
programme is appropriate. A corporate self-assessment involving all senior
managers across the organisation was also undertaken during 2023/24 and the
Corporate Management Team have agreed an improvement plan which will be
communicated to staff and elected members.
Risk Management 
Renfrewshire Council has a risk management framework in place formed over key
components and supported by a high-level combined risk management policy and
strategy ‘Risk Matters’, last revised in November 2023.

Page 57

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
53
The strategic risk management objectives refer to:
• Leadership and management;
• Policy and strategy;
• People;
• Partnership and resources;
• Processes;
• Risk handing and assurance; and
• Outcomes and delivery.
To support the implementation of ‘Risk Matters’ and the continuous improvement of
risk management practice within the council, a Strategic Risk Management
Development Plan is in place, outlining key actions that require to be completed over
the life cycle of Risk Matters.
Performance against these key actions is reported as follows:
• YEAR 1, 2022-23 Key performance figure - 100%, (30 of 30 actions) complete,
against an 85% in-year target.
• YEAR 2, 2023-24 Key performance figure - 88%, (14 of 16 actions) complete,
against an 85% in-year target.
• FULL PLAN, 2022-24 Key performance figure - 96%, (44 of 46 actions) complete,
against an 85% target.
Updates on progress reports and monitoring of risks are reported to the ARSB on a
six-monthly basis. Each Council department has at least one representative on the
Corporate Risk Management Group (the Group). The Group now includes at least
one Head of Service for each department, and has overseen reporting of the
2023/24 strategic and corporate risk, monitoring progress on behalf of the Council.
Services have taken ownership of their risks with processes being followed for
reporting, and where necessary ‘escalation’ of significant risks to the strategic or
corporate registers. All service departments submitted their risk data on time for the
progress reports to the ARSB as planned.
Internal audit
The internal audit service operates in accordance with the Public Sector Internal
Audit Standards and reports to the Audit, Risk and Scrutiny Board. Internal audit
undertakes an annual programme of work, approved by the Board, based on a
strategic risk assessment. The Council’s Chief Auditor provides an independent
opinion on the adequacy and effectiveness of the governance framework, risk
management and internal control.

Page 58

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
54
To ensure the integrity of the internal audit function, the annual internal audit strategy
and plan is determined by the Chief Auditor in consultation with all service Directors
and their senior management teams.
The internal audit opinion for 2023/24 was that, subject to management addressing
the critical and important recommendations made in the limited and no assurance
reports, it is considered that reasonable assurance can be placed upon the
adequacy and effectiveness of the Council’s internal control, risk management and
governance arrangements. This opinion is consistent with prior years.
Internal audit presented results of their activity for 2023/24; 92% of the internal audit
plan was completed against a target of 95%, which is a slight decline on 93% in the
prior year due to higher than anticipated unplanned absence. The outstanding work
is planned to be completed in 2024/25.
We consider internal audit work during our risk assessment and on ongoing basis
One out of the 21 engagements delivered in the year by internal audit had a ‘no
assurance’ conclusion. 
In line with the requirements of the Public Sector Internal Audit Standards (PSIAS)
the internal audit function was subject to an external assessment performed by an
internal auditor of another local authority. The external reviewer concluded that RC’s
internal audit fully complies with PSIAS requirements.

Page 59

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
55
Use of resources to improve outcomes
Our detailed findings on the Council’s arrangements are set out below.
Performance management framework
The Council has a performance framework to measure against its 2022-27 Council
Plan objectives. A high level summary of the Framework is presented below: 
Source: The Council’s internal documentation
The framework assumes 6 monthly reporting to Leadership Board with performance
indicators against action progress grouped by Council Plan strategic outcomes.
These outcomes have also one cross-cutting theme – Improving outcomes for
children and families.
Service Improvement Plans (SIP) at each service level were also given a new format
to make them aligned with the above. The reporting is done on 6 monthly basis to
relevant Boards including an annual outturn report. All performance indicators and
actions in the Council Plan Framework are included in SIPs.
The next stage of performance reporting is at operational level with range of service-
specific performance reporting across Council to the appropriate Policy Board,
together with statutory performance reports.
Local Government Benchmark Framework (LGBF) is scrutinised by the Corporate
Management Team (CMT) with reports to the Audit, Risk and Scrutiny Board. The
CMT would also review a number of performance reports, scorecards, people
metrics and have ‘deep dives’ into specific areas on a quarterly basis.

Page 60

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
56
These documents are then used to create public performance reporting in user
friendly formats, and by using interactive presentations, case studies and
dashboards. 
Service improvement and reporting 2023/24
We have considered how the Council demonstrates a trend of service improvement
in delivering their strategic priorities, as required by the Audit Scotland planning
guidance for 2023/24. 
The Council reports its performance on website across different themes, against 105
indicators included in LGBF, Best Value requirements, and also includes a high level
list of performance indicators in its statutory annual accounts.
Statutory performance information
The Accounts Commission has a statutory responsibility to define the performance
information that councils must publish. This responsibility links with the
Commission’s best value audit responsibilities. In turn, councils have their own
responsibilities, under their best value duty, to report performance to the public. The
Accounts Commission issued a revised Statutory Performance Information Direction
(‘2021 Direction’) in December 2021, which applies for the three-year period from
March 2023 to March 2025. The 2023 Direction requires a council to report its:
• performance in improving local public services (including those provided with its
partners and communities), and progress against agreed desired outcomes; and
• own assessment and audit, scrutiny and inspection body assessments of how it
is performing against its duty of Best Value, and how it has responded to these
assessments.
The Council has made proper arrangements for preparing and publishing its
statutory performance information in accordance with the Direction. The information
reported on the Council’s website is the Council’s response to meeting the
requirements. However, we note that a lot of the information on this section of the
Council website has not been updated to the newest available. This includes
reporting against service outturn reports, summarising findings in relation to BV work
and progress against those, including leadership work from last year. We
recommend the Council updates this section of their website on regular and at least
annual basis.
Recommendation 3
Education performance 
Due to interest in the Education services performance arising from reporting on
Dargavel issue we had looked specifically into performance reporting of this service.

Page 61

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
57
Performance indicators 
The 2023/24 annual performance outturn report was presented to the Education and
Children’s Service’s Policy Board in May 2024. The Children’s Services reported on
19 performance indicators relevant to education. When looked at the performance:
one performance indicator has been on target, seven were below target and 11 were
within 10% of the target, but still below it. When considering long term trends of
those indicators, 13 report a downward trend, 4 an upward trend, with the remaining
two either not comparable or without any change. 
Local Government Benchmarking Framework 
This performance should not be however looked at in isolation and should be
complemented by the wider local government performance in education services.
This could be done via Local Government Benchmarking Framework. Service
performance in this area remains significant challenge in post-COVID environment
for all local authorities in Scotland. 
Compared to other councils, Renfrewshire Council remains in the top ten councils in
14 out of 18 of LGBF education performance measures, and in the four of the
remaining indicators the Council place is better than or close to the national average.
Renfrewshire Council leads on the indicator measuring the cost per secondary
school pupil in Scotland. 
School reports
We have also reviewed the Education Scotland reports presented to the Council
during 2023/24 to identify any potential issues at individual school level. Education
Scotland performed a number of quality reviews at Renfrewshire schools as a part of
its programme of inspections and uses a six-point scale when assessing schools:
excellent, very good, good, satisfactory, weak, unsatisfactory. During the financial
year there were eight inspections performed and with the positive results as follows:
• very good for two schools and one early learning and child class;
• good for three schools;
• an even mix of very good and good scores against indicators assessed for two
schools.
One of the Education Scotland inspections covered Bishopton Primary School, for
which concern might have existed as to the potential impact on this school from
relieving capacity at the existing Dargavel Primary school. Bishopton School
however scored ‘very good’ in 3 indicators assessed by Education Scotland and
‘good’ in one indicator. 
Overall, Education performance remains a strong point of the Council activity with
positive regulator inspection results and strong performance against national
average when compared to other local authorities.

Page 62

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
58
Best Value
Appointed auditors have a duty to be satisfied that local government bodies have
made proper arrangements to secure Best Value.  There are the following four
aspects to auditors’ work:
• Thematic reviews; 
• Follow-up and risk-based work; 
• Service improvement and reporting; and 
• Contributing to Controller of Audit reports.
Thematic review 
Auditors are required to report on Best Value or related themes prescribed by the
Accounts Commission. This year’s thematic review is on Workforce Innovation – how
councils are responding to workforce challenges.  We present the findings in a
separate report with a summary set out below:
How effectively are the
council’s workforce
plans integrated with
its strategic plans and
priorities?
Renfrewshire Council has a comprehensive high level
workforce strategy and People Strategy supported by a
number of other high level policies and strategies.
The Council adopted a flexible approach to its strategy,
by setting clear priorities for the first two years and by
delegating the responsibility and ownership for
workforce management to the individual Services to
better meet their needs. Therefore, the workforce risk
assessment, operational priorities and implementation,
and monitoring are done at service level though
Service Improvement Plans.
How effectively has
digital technology
been used to support
workforce productivity
and improve service
quality and outcomes?
Appropriate arrangements are in place to enable the
delivery of the Council’s digital strategy. The Council
implemented a number of automatic processes to drive
efficiency and innovation in its workforce. A key
challenge for the Council is the creation of capacity
within its workforce to enable the review, exploration
and development of digital opportunities.  
The Council actively engages with its communities to
deliver services in more innovative way to tackle digital
exclusion. The Council’s work has been recognised as
best practice example in Accounts Commission report

Page 63

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
59
on digital exclusion. There is awareness of the need,
and drive for continuous improvement in this area.
How effectively is the
council using hybrid
and remote working
and other innovative
working practice such
as a four-day week to
achieve service and
staff benefits?
The Council continuously reviews its approach to
flexible working and provides staff with support and
guidance.
Staff feedback is obtained in variety of ways and
considers impact of flexible working on staff wellbeing.
The Council considers staff benefits and wider
sociological changes when considering new ways of
working.  Evidence of measurable efficiencies tracking
has been limited and the Council has not been able to
demonstrate efficiencies from flexible working through,
for example, an impact on productivity. 
What innovative
practice is the council
using to develop its
future workforce
capacity and skills
needs and manage
staff reductions in line
with its priorities?
The Council makes good use of its existing workforce
and is developing the skills needed to deliver future
services.
The Council engages with the local education
providers to develop and support its workforce skills.
The Council has to yet develop comprehensive
measurable performance indicators to demonstrate the
benefits it provides through its work on developing
workforce skills and capacity. 
What progress has the
council made with
sharing roles or
functions across its
services and/or with
other councils and
partners?  
The Council works collaboratively with its partners and
continues to explore opportunities for working together. 
Through collaborative working, the Council shares
knowledge and learns from partners, leading to
enhanced service delivery and outcomes.  
The Council works collaboratively with its partners and
continues to explore opportunities for working together. 
Through collaborative working, the Council shares
knowledge and learns from partners, leading to
enhanced service delivery and outcomes.

Page 64

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
60
Best Value Assurance Report follow-up
Auditors are required to follow up Accounts Commission findings, Controller of Audit
recommendations and any outstanding improvement actions reported in Best Value
Assurance Reports and Annual Audit Reports. We are also required to have regard
to the seven Best Value themes when completing our wider scope work
A Best Value review was undertaken on Renfrewshire Council in 2016/17. The Best
Value Assurance Report (BVAR) includes recommendations to help the Council
address the improvement areas identified during the audit. We have considered
progress made by the Council in implementing the recommendations made in the
BVAR. Our findings are summarised below. 
Best value Assurance
Report – follow up Auditor judgement 
The Council had eight recommendations and progressed against each. We note
however that some of the recommendations are not directly applicable to the Council
after so many years since the report was published.
Recommendation 1: Councillors should improve cross-party working, given the
financial challenges that exist and the important decisions that will need to be made
in the future.
Progress:  A range of effective cross-party working arrangements can continue to be
evidenced - particularly in relation to high-priority areas identified.  In recent years
this included the development of both the Council and Community Plans by the
Cross-Party Sounding Board and the review of governance undertaken on a cross
party basis and reported through the Audit Risk and Scrutiny Board and full Council.
A Fairer Renfrewshire Sub-Committee of the Leadership Board was also established
in 2023 which allows members to consider some of the issues relating to poverty and
inequality in Renfrewshire on a cross party basis.
Auditor conclusion: from our work and interviews with council members and officers
we can conclude that the members are working with each other effectively.
Recommendation 2: Councillors should take advantage of the training and
development opportunities that the council provides to ensure they have the
necessary skills and knowledge to perform their role effectively.
Progress: The Council uses a combination of a targeted annual development
programme for Elected Members alongside bespoke training opportunities
throughout the year. 
This approach is regularly reviewed - the current approach and draft programme for
the Members Development Week due to take place later this year has recently been

Page 65

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
61
Best value Assurance
Report – follow up Auditor judgement 
reviewed and enhanced by the Corporate Management Team, to keep pace with the
changing context and key areas of interest identified by Elected Members. Training
opportunities are also offered in different formats – in person, hybrid, online and as a
recorded training seminar available at a time to suit. 
A suite of training materials are also provided to enhance the content, and
opportunities for training and development through organisations such as the
Improvement Service are also shared and promoted.
Auditor conclusion: appropriate training is delivered to members, monitored by the
Council and reported to appropriate Board annually.
Recommendation 3: The Council should review its governance arrangements to
ensure they provide for a relationship with Renfrewshire Leisure Limited (RLL) that is
clear, independent, and more easily understood by the public.
Progress: The Council’s monitoring officer for One Ren has continued to work with
the Chief Executive (One Ren) to strengthen quarterly performance monitoring
reports and meeting arrangements.
Auditor conclusion: governance arrangements has been updated and strengthened.
Recommendation 4: The Council should develop a detailed medium and long-term
workforce strategy and plan and implement its organisational development strategy.
Implementing both the workforce and organisational development strategies will be
critical to managing how future services are provided.
Progress: Notes from auditors reflect the current position.  A number of improvement
actions have been identified within the thematic review of workforce innovation which
the organisation will seek to address.  These include improvements in relation to
linking workforce planning priorities to corporate and service level plans, and
developing performance measures and outcomes against which progress can be
tracked going forward.
Auditor conclusion: we have concluded in our thematic review on Workforce
Innovation that Renfrewshire Council has a comprehensive high level workforce
strategy and People Strategy supported by a number of other high level policies and
strategies. The Council adopted a flexible approach to its strategy, by setting up
clear priorities for the first two years and by delegating the responsibility and
ownership for workforce management to the individual Services to better meet their
needs. Therefore, the workforce risk assessment, operational priorities and
implementation, and monitoring are done at service level though Service
Improvement Plans. We have identified a number of improvements as noted in the
response above.

Page 66

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
62
Best value Assurance
Report – follow up Auditor judgement 
Recommendation 5: The Council is continuing to review how it will achieve the
savings required within the medium- term financial strategy. The Council should
prioritise how services need to be provided in future to meet these savings. 
Progress: regular reports are made to Council on the financial outlook - behind this
sits an extensive, cross-service Financial Sustainability programme.
Auditor conclusion: the Council’s Financial Outlook is being continually reviewed in
light of changing economic climate and regular reports are made to the Council.
Recommendation 6: Community Planning partners need to plan their budgets and
finances together to provide a clearer picture of the overall resources available.
Progress: At the meeting of the Community Planning Executive Group in September
2023, a discussion took place on resourcing and the need to collectively focus
resources on joint priorities. Following this session in 2023, Community Planning
Partners agreed to work together on a number of targeted projects, including in
relation to child poverty, with a community impact assessment underway in relation
to Gallowhill currently.
Community Planning Partners are also due to undertake their annual horizon
scan/review meeting in early October, with a specific session planned on exploring
how we as partners work together to prioritise early and intervention activities, given
the financial challenges being experienced by all.
At a national level, it has been agreed that self-assessments of community planning
partnerships will be progressed during 2024/25.  A core element of this process will
require partners to focus on the effective deployment of resources across
Renfrewshire in order to target our key shared priorities.
Auditor conclusion: The Council continues to make improvements and progress in
this area.
Recommendation 7: The Council and its partners need to continue to involve
communities and work together on joint priorities and to strengthen partnership
working. This will provide a positive base to ensure the Community Empowerment
(Scotland) Act 2015 is fully implemented. 
Progress: Council services have worked very hard with partners to embed the
requirements of this legislation, with engagement processes developed in relation to
key aspects such as asset transfer, community planning, and participatory
budgeting.  A range of initiatives continue to be supported which support local
capacity building in communities, and promote participation and engagement.  These
include campaigns and engagement programmes such as Team up to Clean Up,

Page 67

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
63
Best value Assurance
Report – follow up Auditor judgement 
housing regeneration programmes and specific engagement with people with lived or
living experience, such as the Fairer Renfrewshire lived experience panel.
7 Local Partnerships continue to develop and following a review in early 2024 we
have launched a new development phase - Local Plans, Local Priorities and Local
Voices which will enhance and further strengthen our approach to partnership
working with the community. All Local Partnerships are currently being supported to
review their priorities and develop refreshed action plans.
Auditor conclusion: there was progress made in this area in relation to development
of new local partnerships and through the Connected Communities programme. As
noted in the Update report on school accommodation for Dargavel Village the
Accounts Commission welcomed the increase in community engagement
undertaken by the council since January 2024 and its ongoing commitment to
improve its engagement with affected communities. 
Recommendation 8: The Annual Report should include a summary position
regarding the Council’s performance together with relevant detailed performance
information. This would improve the accessibility of performance information and
help to demonstrate greater transparency by the Council.
Progress: Significant work to refine the existing performance management
framework aligned to the Council Plan has taken place, including the ‘at a glance’
performance snapshot which gives an overview of progress against strategic
outcomes. Council Plan progress continues to be reported 6-monthly, as does
service performance via the Service Improvement Plans, again on a 6-monthly basis.
Our performance reporting for both Council and Service Improvement Planning has
been reviewed to ensure reports are accessible, engaging and suitable for a range of
audiences. 
An overall picture of performance is reported annually in our Public Performance
Report, which is available as an interactive ‘Storymap’ with the embedded
functionality to analyse and compare data nationally and with family group Councils.
Auditor conclusion: There a number of performance management methods and the
Chief Executive’s Service’s current Service Improvement Plan is to review and
refresh the Council’s performance management framework, which will continue to be
reported on via the mid-year and outturn reports. 
We have considered the Best Value themes as part of our wider scope work and
have not identified any significant risks in this respect.

Page 68

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
64
Leadership of the development of new local strategic priorities
In 2022/23 we have reported on the effectiveness of the Council’s leadership of the
development of the Council’s strategic priorities, following the recent local
government elections. Overall, we have noted that the Council has a clear strategy
and vision in place, engages with communities, has strong commitment to tackling
climate  change, has operational plans to deliver objectives and has improved
significantly on cross party working. We have also identified two points for further
improvement: on setting key priorities and on clarity of reporting against the Council
plan. Progress on those actions is reported in Appendix 4.
Service improvement and reporting 
We have considered this as part of our wider scope work within Vision, leadership
and governance section of this report.
Contributing to Controller of Audit Reports 
The Controller of Audit reports to the Accounts Commission on each council’s
performance in meeting its Best Value duties at least once over the five-year audit
appointment. Auditors are required to include judgments on the pace and depth of
continuous improvement in the council as part of their wider scope work to contribute
to these reports. Our findings and conclusions are set out in our wider scope work
within Vision, leadership and governance section of this report.

Page 69

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
65
Appendices 
Appendix 1: Responsibilities of the Council and the Auditor 66
Appendix 2: Audit differences identified during the audit 72
Appendix 3: Action plan 75
Appendix 4: Follow up of prior year recommendations 78

Page 70

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
66
Appendix 1: Responsibilities of the Council and the
Auditor
Responsibilities of the Council
The Council is required to make arrangements for the proper administration of its
financial affairs and to secure that one of its officers has responsibility for the
administration of those affairs. The Director of Finance and Resources has been
designated as that officer. The Director of Finance and Resources is responsible for
the preparation of the Council’s annual accounts in accordance with proper practices
as set out in the CIPFA/LASAAC Code of Practice on Local Authority Accounting in
the United Kingdom (the Code).
Area The Council’s responsibilities
Corporate
governance
The Council is responsible for establishing arrangements to ensure
the proper conduct of its affairs including the legality of activities
and transactions, and for monitoring the adequacy and
effectiveness of these arrangements. Those charged with
governance should be involved in monitoring these arrangements.
Financial
statements
and related
reports
The Council has responsibility for: 
• preparing financial statements which give a true and fair view of
the financial position of the Council and its group and their
expenditure and income, in accordance with the applicable
financial reporting framework and relevant legislation;
• maintaining accounting records and working papers that have
been prepared to an acceptable professional standard and 
support the balances and transactions in its financial statements
and related disclosures;
• preparing and publishing, along with the financial statements, an
annual governance statement, management commentary (or
equivalent and a remuneration report that is consistent with the
disclosures made in the financial statements and prepared in
accordance with prescribed requirements. The management
commentary should be fair, balanced and understandable and
also address the longer-term financial sustainability of the
Council.
Management is responsible, with the oversight of those charged
with governance, for communicating relevant information to users
about the Council and its financial performance, including providing

Page 71

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
67
Area The Council’s responsibilities
adequate disclosures in accordance with the applicable financial
reporting framework. The relevant information should be
communicated clearly and concisely.
The Council is responsible for developing and implementing
effective systems of internal control as well as financial, operational
and compliance controls. These systems should support the
achievement of its objectives and safeguard and secure value for
money from the public funds at its disposal. The Council is also
responsible for establishing effective and appropriate internal audit
and risk-management functions.
Standards
of conduct
for
prevention
and
detection
of fraud
and error
The Council is responsible for establishing arrangements to prevent
and detect fraud, error and irregularities, bribery and corruption and
also to ensure that its affairs are managed in accordance with
proper standards of conduct.
Financial
position
The Council is responsible for putting in place proper arrangements
to ensure its financial position is soundly based having regard to:
• Such financial monitoring and reporting arrangements as may
be specified;
• Compliance with statutory financial requirements and
achievement of financial targets;
• Balances and reserves, including strategies about levels and
their future use;
• Plans to deal with uncertainty in the medium and long term; and
• The impact of planned future policies and foreseeable
developments on the financial position.
Best Value
The Council has a specific responsibility to ensure that
arrangements have been made to secure best value. They are
responsible for ensuring that these matters are given due priority
and resources, and that proper procedures are established and
operate satisfactorily.

Page 72

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
68
Auditor responsibilities
Code of Audit Practice
The Code of Audit Practice (the Code) describes the high-level, principles-based
purpose and scope of public audit in Scotland. The 2021 Code came into effect from
2022/23.
The Code of Audit Practice outlines the responsibilities of external auditors
appointed by the Auditor General and it is a condition of our appointment that we
follow it.
Our responsibilities
Auditor responsibilities are derived from the Code, statute, International Standards
on Auditing (UK) and the Ethical Standard for auditors, other professional
requirements and best practice, and guidance from Audit Scotland. 
We are responsible for the audit of the accounts and the wider-scope responsibilities
explained below. We act independently in carrying out our role and in exercising
professional judgement. We report to the Council and others, including Audit
Scotland, on the results of our audit work.
Weaknesses or risks, including fraud and other irregularities, identified by auditors,
are only those which come to our attention during our normal audit work in
accordance with the Code and may not be all that exist.
Wider scope audit work
Reflecting the fact that public money is involved, public audit is planned and
undertaken from a wider perspective than in the private sector.
The wider scope audit specified by the Code broadens the audit of the accounts to
include additional aspects or risks in areas of financial management; financial
sustainability; vision, leadership and governance; and use of resources to improve
outcomes.

Page 73

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
69 
Financial management
Financial management means having sound budgetary
processes. Audited bodies require to understand the financial
environment and whether their internal controls are operating
effectively.
Auditor considerations
Auditors consider whether the body has effective arrangements
to secure sound financial management. This includes the
strength of the financial management culture, accountability,
and arrangements to prevent and detect fraud, error and other
irregularities. 
Financial sustainability
Financial sustainability means being able to meet the needs of
the present without compromising the ability of future
generations to meet their own needs.
Auditor considerations
Auditors consider the extent to which audited bodies show
regard to financial sustainability. They look ahead to the
medium term (two to five years) and longer term (over five
years) to consider whether the body is planning effectively so it
can continue to deliver services. 
Vision, leadership and governance
Audited bodies must have a clear vision and strategy and set
priorities for improvement within this vision and strategy. They
work together with partners and communities to improve
outcomes and foster a culture of innovation.
Auditor considerations
Auditors consider the clarity of plans to implement the vision,
strategy and priorities adopted by the leaders of the audited
body. Auditors also consider the effectiveness of governance
arrangements for delivery, including openness and
transparency of decision-making; robustness of scrutiny and
shared working arrangements; and reporting of decisions and
outcomes, and financial and performance information.

Page 74

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
70 
Use of resources to improve outcomes
Audited bodies need to make best use of their resources to
meet stated outcomes and improvement objectives, through
effective planning and working with strategic partners and
communities. This includes demonstrating economy, efficiency
and effectiveness through the use of financial and other
resources, and reporting performance against outcomes.
Auditor considerations
Auditors consider the clarity of arrangements in place to ensure
that resources are deployed to improve strategic outcomes,
meet the needs of service users taking account of inequalities,
and deliver continuous improvement in priority services. 
Best Value 
Appointed auditors have a duty to be satisfied that local government bodies have
made proper arrangements to secure best value. Our work in respect of the
Council’s best value arrangements has been integrated into our audit approach,
including our follow up on the Council’s Best Value Assurance Report and work on
the wider scope dimensions. 
Audit quality
The Auditor General and the Accounts Commission require assurance on the quality
of public audit in Scotland through comprehensive audit quality arrangements that
apply to all audit work and providers. These arrangements recognise the importance
of audit quality to the Auditor General and the Accounts Commission and provide
regular reporting on audit quality and performance.
Audit Scotland maintains and delivers an Audit Quality Framework.
The most recent audit quality report can be found at https://www.audit-
scotland.gov.uk/publications/quality-of-public-audit-in-scotland-annual-report-
202223. 
Independence
The Ethical Standards and ISA (UK) 260 require us to give the Council full and fair
disclosure of matters relating to our independence. We confirm that Azets Audit
Services and the engagement team complied with the FRC’s Ethical Standard. We
confirm that all threats to our independence have been properly addressed through

Page 75

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
71
appropriate safeguards and that we are independent and able to express an
objective opinion on the financial statements.
Our period of total uninterrupted appointment as at the end of 31 March 2024 was
two years. 
Audit and non-audit services
The total fees charged to the Council for the provision of services in 2023/24 were as
follows. Prior year charges for the predecessor auditor are also shown for
comparative purposes: 
2023/24 2022/23
Auditor remuneration £316,514 £298,450
Pooled costs 10,490 -
Contribution to PABV costs £82,680 £78,110
Audit support costs - £10,290
Sectoral cap adjustment £59,660 £55,800
Total audit fees £469,344 £442,650

Page 76

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
72
Appendix 2: Audit differences identified during the audit
We are required to inform the Council of any significant misstatements within the
financial statements presented for audit that have been discovered during the course
of our audit. The non-trivial misstatement discovered during the course of our audit
which have been adjusted for by management are summarised in the table below.
Adjusted misstatements
Details of the item corrected following discussions with management is as below. 
No Detail Assets
Dr / (Cr)
£m
Liabilities
Dr / (Cr)
£m
Reserves
Dr / (Cr)
£m
CIES
Dr / (Cr)
£m
1. Prior year restatement 
Correction of pension fund
plan assets calculation to
account for unfunded
liability
DR Pension reserve
CR Pension liability  (73.5)   
73.5 
2. Correction of incorrect
manual adjustment to
reduced doubtful debt 
DR Short-term debtors 
CR Cash 
0.8
(0.8)   
3. Classification of debtor type
from Short-term debtors -
non-trade: central
government bodies to
Short-term debtors - arrears
of business rates
Short term debtors
Short term debtors 
0.5
(0.5)

Page 77

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit
73
4. Classification of investment
properties
Investment properties
Property, plant and
equipment
0.9
(0.9)
Net impact on usable
reserve- General Fund
Reserve
0
Net impact on unusable
reserve- Pension Reserve
73.5
Net impact on net assets (73.5)
Unadjusted misstatements
We identified no unadjusted misstatements during our audit.
Misclassification and disclosure changes
Our work included a review of the adequacy of disclosures in the financial
statements and consideration of the appropriateness of the accounting policies and
estimation techniques adopted by the Council. 
We identified a number of reclassification adjustments and some minor
presentational issues in the Council’s accounts, and these have all been amended
by management. Details of all disclosure changes amended by management
following discussions are as below.
No Detail
1. Disclosure changes in external audit costs of fee payable to be
£0.469million.
2. Disclosures in the remuneration report for pension entitlement and casting.
3. Pension liability disclosure after receiving the revised actuarial report.
4. Minor presentational and disclosure issues.

Page 78

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit
74
The audit team have raised minor and presentational issues with
management, and we recommend that this is updated.
5. Presentational classification adjustment to Note 4.
Overall, we found the disclosed accounting policies, significant accounting estimates
and the overall disclosures and presentation to be appropriate.

Page 79

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
75
Appendix 3: Action plan
Our action plan details the weaknesses and opportunities for improvement that we
have identified during our audit. 
Action plan grading structure 
To assist the Council in assessing the significance of the issues raised and
prioritising the action required to address them, the recommendations have been
rated as follows:
Rating Assessment rationale
High An issue that results in a severe impact to the achievement of
objectives in the area audited.
Medium An issue that results in a moderate impact to the achievement of
objectives in the area audited.
Low An issue that results in a small impact to the achievement of
objectives in the area audited.

Page 80

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
76
Current year action plan  
1. Payroll reconciliation Medium
Observation
The Council has a number of payruns running at different
frequencies. However, there is no year-end reconciliation
in place between the ledger and payroll systems to ensure
that the figures in the financial statements reconcile to the
payroll system.
Implication
There is a risk that the ledger is not complete or accurate
when reflecting payroll figures and impacting on the
financial statements.
Recommendation We recommend that the Council performs regular
reconciliation between the ledger and payroll.
Management
response
The Council’s payroll and ledger systems are fully
integrated in its ERP system, Business World. This results
in the risk of any disparity between the payrun batches
and the General Ledger transactions being very low.
However, officers recognise that testing this on an annual
basis would be beneficial for control assurance and will
undertake development of a process over the second half
of 2024/25.
Responsible officer: Director of Finance and Resources
Implementation date: 31 March 2025 
2. Related parties Medium
Observation The Council should disclose intercompany transactions
between group entities in the related parties note.
Implication There is a risk that the disclosure is not complete.
Recommendation We recommend that the Council makes the relevant
disclosure in the 2024/25 financial statements.

Page 81

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
77
2. Related parties Medium
Management
response
The Related Parties Note will be updated in the 2024/25
accounts for relevant group transactions.
Responsible officer: Head of Finance and Procurement 
Implementation date: 31 March 2025 
3. Performance information  Low
Observation
The performance information reported on the Council’s
website is the Council’s response to meeting the
requirements. However, we note that a lot of the
information on this section of the Council website has not
been updated to the newest available. This includes
reporting against the council plan, service outturn reports, 
summarising findings in relation to BV work and progress
against those, including leadership work from last year.
We recommend the Council updates this section of their
website on regular and at least annual basis. 
Implication
The Council’s performance section on the website has
been updated with most reports with a few update reports
from May and June 2024 board cycles requiring to be
updated
Recommendation We recommend that the Council updates the information.
Management
response
The Council regularly updates its performance information
on the website.  It is recognised several updates to board
from May and June require to be  updated and are
scheduled to be so in line with existing processes.
Responsible officer: Head of Policy and Partnerships
Implementation date: 30 September 2024

Page 82

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
78
Appendix 4: Follow up of prior year recommendations
We have followed up on the progress the Council has made in implementing the
recommendations raised by the previous auditor last year which were reported as
either new or ongoing.
1.  Property, plant and equipment valuations
Recommendation
The Code of Practice on Local Authority Accounting
requires authorities to revalue property, plant and
equipment with sufficient regularity to ensure the
carrying amount does not differ materially from current
value, being the value that would have been obtained if
revalued. Property, plant and equipment valuations
within the annual accounts is supported by workings
from valuers, using a rolling programme of revaluations.
The valuation process could be enhanced through
greater documentation of the annual valuation report
and management scrutiny over the report including: 
• The assets revalued in year and the methodology
applied in the valuation exercise
• Key assumptions and estimates made in the
valuation
• The total valuation amount reflected within the
annual accounts 
The recommendation was that a valuation report is
prepared by the council’s valuer on an annual basis
outlining the details of the work undertaken, the impact
on the asset values and the methodology applied in
completing the revaluation programme. There should be
clear evidence of how officers have challenged and
scrutinised the valuation to ensure the accounts are free
from material misstatement. 
Closed
Response: The Council’s valuer has detailed which
assets have been valued in the year and the impact of
this on the wider category of assets. Improvements will
continue to be made to annual valuation information to
allow increased clarity on the work undertaken in year.
Responsible officer: Head of Economy and
Development

Page 83

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
79
2.  Related party disclosures
Recommendation
The information held relating to member and officer
interests could be enhanced to ensure that all relevant
information is recorded to support the governance and
financial reporting requirements around the disclosure
of related parties. Processes and controls to consider
and identify relevant relationships and transactions that
require to be disclosed within the annual accounts
should be reviewed for appropriateness. 
Risk: There is a risk that the council fail to identify
related parties due to underlying documentation lacking
sufficient detail. 
The recommendation was that a review of controls and
processes around related parties is undertaken. This
will include the documentation of member and officer
interests as well as the processes in place to identify
the relevant disclosures for inclusion in the financial
statements.
Ongoing
Response: The Related Parties disclosure was
refreshed and significantly expanded in the 2022/23
accounts and further development of the note will be
undertaken for the 2024/25 accounts, as noted above.
Responsible officer: Head of Finance and
Procurement

Page 84

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
80
3.  Financial strategy to support financial
sustainability
Recommendation
The council face continuing financial challenges and
significant uncertainty. 
It is anticipated that new financial flexibilities may
become available and the impact of these should be
assessed within the scope of the wider financial
strategy. 
Risk: There is a risk that decisions around financial
flexibilities, transformation and redesign of savings
are made without detailed financial impacts being
available to support the decision-making process. 
The recommendation was to develop a revised
financial strategy incorporating new or temporary
financial flexibilities and assess how the total
balances available are best utilised to support the
financial sustainability of the council over the medium
term. 
The council will need to actively engage with local
and national partners to deliver the required level of
efficiencies and savings..
Ongoing
Response: Financial Outlook update reports have
been reported to Council at each board cycle, the
last being 26th September 2024. This continues to
update the budget position in the medium term and
the progress of savings targets. The use of financial
flexibilities was agreed by Council in September
2021.
Responsible officer: Director of Finance and
Resources

Page 85

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
81
4. Dargavel school response Medium
Recommendation
The Council has responded in a transparent and open
manner to issues raised through the Bowles Report.  We
welcome the creation of a detailed action plan response to
Bowles report recommendation and we note the planned
reviews of overall governance arrangements and the
specific review of the role the Audit, Risk and Scrutiny
Board should have going forward.
The Council recognises that it faces an ongoing challenge
to build the trust and confidence of local communities in its
school estate decision making.  A recent report to the
Education, Children’s Services Policy Board comments on
the community negative reaction to the Council’s decision
on extending (rather than replacing) an existing secondary
school and indicates that decisions on the future school
estate will remain a high profile area for the Council. 
Lack of clarity over the above points might lead to slow
pace of remediating issue or re-occurrence in the future
We recommend that the Council:
• Performs a more comprehensive and continuous
assessment of future operating costs for planned new
school provision.
• Consider whether any additional monitoring and
assessment arrangements for pupil educational
attainment may be required for pupils in the Bishopton
and Dargavel communities
• Consider how it will evidence better joint working
between council departments in future projects
Remains open and measures its effectiveness in
rebuilding its relationship with the affected communities.
Ongoing
Response: The Council has developed a substantial
action plan addressing all the key recommendations from
the independent review; and which will address the
external audit points above. The action plan will subject to
ongoing monitoring and scrutiny by the Audit, Risk and
Scrutiny Board.

Page 86

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
82
4. Dargavel school response Medium
Management
response
Responsible officer: Chief Executive 
Implementation date: Ongoing 
5. Financial sustainability High
Recommendation 
Officers have noted that the prior year’s savings were
mainly achieved by two departments which make up only
20% of the total council budget. Commitment to savings
would need to be met by all services, including the
Council’s subsidiaries.
The medium term financial challenge and financial gap
has been considered by the Council numerous times, but
no clear options have been presented or decision have
been made as to how to address those challenges. The
Council now needs to make difficult spending priority
decisions to secure financial sustainability going forward.
This poses an increasing risk to the Council’s delivery of
services over the medium term and we would recommend
addressing as a priority.
To present the Council with a range of options and
services implications.
Ongoing
Response: A Financial Outlook update has been reported
to Council at each board cycle, the last being 26
September 2024. This continues to update status of the
budget deficit position in the medium term and the
progress of savings targets. The Council’s senior
management team continue to identify options for further
savings and service transformation, for agreement by
elected members in setting future annual revenue
budgets.
Responsible officer: Director of Finance & Resources
Implementation date: Ongoing

Page 87

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
83
6. Cut off de minimis Low
Recommendation
The Council applies a ‘de minimis’ limit to determining
how it will process transactions into the correct financial
year. However, we identified that this threshold is not
formally set.
There could be inconsistent treatment of the transactions
with no formal limit set leading to misstatements.
To formalise arrangements around cut-off recording. 
Ongoing
Response: This action is carried forward and a formal de
minimis will be included in year-end guidance documents
from 2024/25 onwards.
Responsible officer: Head of Finance and Procurement 
Implementation date: 31 March 2025 
7. Land valuations frequency Low
Recommendation 
Our audit of fixed assets identified that a number of land
values have been revalued in 2023, but had not been
revalued in the five years before that valuation.
Revaluations to be made with sufficient regularity to
ensure that the carrying amount does not differ materially
from current value. 
We recommend revaluing land values at least once in five
years in line with standard industry practice and
accounting requirements. 
Closed
Response: There have been resourcing issues within the
Council’s Estates team, with external assistance
purchased in 2023. Land values will be reviewed at least
once in five years.

Page 88

Renfrewshire Council: 2023/24 Annual Audit Report to the Council and
the Controller of Audit 
84
7. Land valuations frequency Low
Responsible officer: Head of Economy and
Development
Implementation date: 31 March 2024

Page 89

We are an accounting, tax, audit, advisory and business services group that delivers a
personal experience both digitally and at your door.
Accounting | Tax | Audit | Advisory | Technology 
© Azets 2024. All rights reserved. Azets refers to Azets Audit Services Limited. Registered
in England & Wales Registered No. 09652677. VAT Registration No. 219 0608 22.
Registered to carry on audit work in the UK and regulated for a range of investment
business activities by the Institute of Chartered Accountants in England and Wales.

Page 90

My Ref: AM/CB
Contact: Alastair MacArthur
Telephone Number: 0300 300 0285
E Mail: alastair.macarthur@renfrewshire.gov.uk 
Finance & Resources
Director:  Alastair MacArthur CPFA
Renfrewshire House, Cotton Street, Paisley PA1 1TT
www.renfrewshire.gov.uk   
Azets Audit Services
Quay 2
139 Fountainbridge
Edinburgh
EH3 9QG 
Dear Sirs 
Renfrewshire Council
Financial Statements for the year ended 31 March 2024 
This representation letter is provided for the purpose of expressing an opinion as to whether
Renfrewshire Council’s financial statements present a true and fair view, in all material
respects, in accordance with applicable law and UK adopted international accounting
standards, as interpreted and adapted by the Code of Practice on Local Authority
Accounting in the United Kingdom 2023/24 (the 2023/24 Code). 
I confirm to the best of my knowledge and belief and having made appropriate enquiries of
the Renfrewshire Council’s Chief Executive and the Audit, Risk and Scrutiny Board, the
following representations given to you in connection with your audit of Renfrewshire
Council’s annual accounts for the year ended 31 March 2024. 
Financial Statements 
i. Renfrewshire Council and I have fulfilled our responsibilities for the preparation of
Renfrewshire Council’s financial statements in accordance with applicable law and
UK adopted international accounting standards, as interpreted and adapted by the
Code of Practice on Local Authority Accounting in the United Kingdom 2023/24
(the 2023/24 Code), for being satisfied that they give a true and fair view and for
making accurate representations to you. 
ii. I have complied with the requirements of all statutory directions affecting Scotland
and these matters have been appropriately reflected and disclosed in the financial
statements. 
iii. The financial statements are free of material misstatements, including omissions. 
iv. Renfrewshire Council has complied with all aspects of contractual agreements
that could have a material effect on the financial statements in the event of non-
compliance. There has been no non-compliance with requirements of any
regulatory authorities that could have a material effect on the financial statements
in the event of non-compliance.

Page 91

My Ref: AM/CB
Contact: Alastair MacArthur
Telephone Number: 0300 300 0285
E Mail: alastair.macarthur@renfrewshire.gov.uk 
Finance & Resources
Director:  Alastair MacArthur CPFA
Renfrewshire House, Cotton Street, Paisley PA1 1TT
www.renfrewshire.gov.uk   
v. I acknowledge my responsibility for the design, implementation and maintenance
of internal control to prevent and detect fraud and error, and I believe that I have
appropriately fulfilled these responsibilities. 
vi. The methods, data and significant assumptions used by us in making accounting
estimates, including those measured at fair value, are appropriate to achieve
recognition, measurement and disclosure that is reasonable in the context of the
applicable financial reporting framework. I am satisfied that the material
judgements used in the preparation of the financial statements are soundly based,
in accordance with the Code and adequately disclosed in the financial statements. 
vii. Renfrewshire Council has satisfactory title to all assets disclosed in the accounts. I
have no plans or intentions that may materially alter the carrying value and, where
relevant, the fair value measurements or classification of assets and liabilities as
at 31 March 2024 are reflected in the financial statements. 
viii. Except as disclosed in the financial statements:
a. there are no unrecorded liabilities, actual or contingent;
b. none of the assets of Renfrewshire Council has been assigned, pledged or
mortgaged;
c. there are no material prior year charges or credits, nor exceptional or non-
recurring items requiring separate disclosure. 
ix. Related party relationships and transactions have been appropriately accounted
for and disclosed in accordance with the requirements of applicable law and
accounting standards. 
x. All events subsequent to the date of the financial statements and which require
adjustment or disclosure have been adjusted or disclosed. 
xi. Actual or possible litigation and claims have been accounted for and disclosed in
accordance with the requirements of UK adopted international accounting
standards, and as interpreted and adapted by the Code. 
xii. I confirm my estimation of the holiday pay accrual is materially accurate and
complete within the financial statements. 
xiii. I have assessed Renfrewshire Council’s ability to continue to use the going
concern basis of accounting and have concluded that it is appropriate. I am not
aware of any material uncertainties that may cast significant doubt on
Renfrewshire Council’s ability to continue as a going concern.
xiv. 
Information Provided
xv. I have provided you with:

Page 92

My Ref: AM/CB
Contact: Alastair MacArthur
Telephone Number: 0300 300 0285
E Mail: alastair.macarthur@renfrewshire.gov.uk 
Finance & Resources
Director:  Alastair MacArthur CPFA
Renfrewshire House, Cotton Street, Paisley PA1 1TT
www.renfrewshire.gov.uk   
a. access to all information of which I am aware that is relevant to the
preparation of the Renfrewshire Council’s financial statements such as
accounting records, and all other records requested; 
b. additional information that you have requested from us for the purpose of your
audit; and 
c. unrestricted access to persons within Renfrewshire Council (via remote
arrangements where necessary), from whom you determined it necessary to
obtain audit evidence. 
xvi. I have communicated to you all deficiencies in internal control of which
management is aware. 
xvii. All transactions undertaken by Renfrewshire Council have been recorded in the
accounting records and are properly reflected in the financial statements. 
xviii. I have disclosed to you the results of my assessment of the risk that the financial
statements may be materially misstated as a result of fraud. 
xix. I have disclosed to you all information in relation to known fraud or suspected
fraud that I am aware of and that affects Renfrewshire Council and involves: 
a. management; 
b. employees who have significant roles in internal control; or 
c. others where the fraud could have a material effect on the financial
statements. 
xx. I have disclosed to you all information in relation to instances of, or allegations of
fraud, or suspected fraud, affecting the financial statements communicated by
employees, former employees, analysts, regulators or others. 
xxi. I have disclosed to you all known instances of non-compliance or suspected non-
compliance with laws and regulations whose effects should be considered when
preparing financial statements. 
xxii. I have disclosed to you the identity of Renfrewshire Council's related parties and
all the related party relationships and transactions of which I am aware. 
xxiii. I have disclosed to you all known actual or possible litigation and claims whose
effects should be considered when preparing the financial statements. 
xxiv. I acknowledge our legal responsibilities regarding disclosure of information to you
as auditors and confirm that so far as I am aware, there is no relevant audit

Page 93

My Ref: AM/CB
Contact: Alastair MacArthur
Telephone Number: 0300 300 0285
E Mail: alastair.macarthur@renfrewshire.gov.uk 
Finance & Resources
Director:  Alastair MacArthur CPFA
Renfrewshire House, Cotton Street, Paisley PA1 1TT
www.renfrewshire.gov.uk   
information needed by you in connection with preparing your audit report of which
you are unaware. 
Annual Governance Statement
xxv. I am satisfied that the Annual Governance Statement (AGS) fairly reflects the
Renfrewshire Council's risk assurance and governance framework and I confirm
that I am not aware of any significant risks or weaknesses in governance or
internal control that are not disclosed within the AGS. 
Management Commentary
xxvi. The disclosures within the Management Commentary fairly reflect my
understanding of Renfrewshire Council's financial and operating performance over
the period covered by the financial statements. 
Remuneration Report
xxvii. I am satisfied that the disclosures within the Remuneration report have been
properly prepared in accordance with The Local Authority Accounts (Scotland)
Regulations 2014. 
Approval
The approval of this letter of representation was minuted by Renfrewshire Council at its
meeting on 24 October 2024. 
Yours faithfully 
Signature:…………………………… 
Name: Alastair MacArthur 
Position: Director of Finance and Resources 
Date