Appendix 1 Perth & Kinross Council Local Development Plan 2: Delivery Programme 2019-2029 Updated: 7 February 2024
Page 2
1 Contents Page Introduction 2 Background 2 Approach 3 Delivery and Monitoring 3 Future Delivery Programmes 3 Delivery Programme Schedule Table 1: Strategic National and Regional Actions 4 Table 2: Local Development Plan Policy Actions 12 Table 3: Local Development Plan Proposals Actions 24 Abbreviations and Acronyms 56
Page 3
2 Introduction The Delivery Programme 2019-2029 - 7 February 2024 update has been prepared to support the delivery of the Perth & Kinross Local Development Plan 2 (LDP2). It sets out the actions and partnerships required to implement the Plan and will serve as a tool to achieve this purpose. To ensure the efficient and effective delivery of LDP2 it is important that any actions or infrastructure development required are identified as soon as possible to provide confidence to key stakeholders, developers and funders. The Delivery Programme has been prepared with input from other departments within Perth & Kinross Council, key stakeholders, the Scottish Government and other organisations and delivery bodies specified in the document. Perth & Kinross Council aspires to build on this version of the Delivery Programme with regular reviews and communication with stakeholders. Funding of a number of the schemes contained with the Delivery Programme will be dependent on future Scottish Government spending reviews and the availability of public and private sector finance. Background The Planning etc. (Scotland) Act 2006, as amended by the Planning (Scotland) Act 2019, requires a local planning authority to publish a Delivery Programme to accompany the Local Development Plan. LDP2 was formally adopted by the Council on 29 November 2019. The first Delivery Programme 2019-29 in support of the Plan was adopted by the Council in January 2020 and thereafter was published and submitted to Scottish Ministers. The Programme was updated on 2 Feburary 2022.
Page 4
3 Approach The delivery of proposals and policies is a complex process that requires a pragmatic approach to delivery. In considering the delivery of sites, the expectations of all parties should remain realistic, and the requirements remain as flexible as possible to ensure the delivery is viable. While all the strategic, national and regional development actions from National Planning Framework 4, the Strategic Transport Projects Review 2 (STPR), and the Tactran Regional Transport Strategy (RTS) Refresh 2015-2036 and RTS Delivery Plan 2016-2021 (and the RTS2 currently under preparation) are important, only some will have a direct impact on the delivery of LDP2. Delivery and Monitoring Strong leadership and stakeholder commitment are key to the successful delivery of the Delivery Programme. The Local Development Planning Guidance requires Planning Authorities to consult with and consider the views of the key agencies and the Scottish Ministers. The Guidance also highlights the important and complementary roles of the Delivery Programme and the annual Housing Land Audit in the delivery of LDPs. This version of the Delivery Programme takes into account any progress which has been made on individual site proposals and policies since the Delivery Programme update in February 2022. Future Delivery Programmes There is a requirement under LDP2 Policy 23: Delivery of Development Sites, for a Delivery Strategy to be prepared and updated every 6 months for sites allocated for development in the Plan. The Delivery Strategy is to demonstrate a realistic programme for the delivery of the site through the plan period and beyond. Several rounds of engagement on Delivery Strategies have been undertaken since the first round in March 2021 and the outcomes of these have informed this version of the Delivery Programme. The preparation of a full strategy for every allocated site is a work in progress and these will continue to be incorporated into future versions of the Delivery Programme.
Page 5
4 Table 1: Strategic, National and Regional Actions (NPF, STPR and RTS) Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes Decarbonisation of the rail network Replacing diesel trains, the largest source of rail carbon emissions, with cleaner technologies offers multiple benefits in addition to helping meet net zero targets. Worked commenced in 2020 post the adoption of the Rail Services Decarbonisation Action Plan. Transport Scotland; Scottish Government; Network Rail STPR2 recommends the priorities for decarbonising key rail routes should align with the Rail Services Decarbonisation Action Plan. The Rail Services Decarbonisation Action Plan was published in Spring 2020 and includes an indicative action programme. Highland Main Line rail corridor enhancements (No significant impact on delivery of LDP2) For the Highland Main Line, these would include new and longer passing loops with more flexibility and permissible speed increases. Phase 2 2019 - complete N/A Transport Scotland; Network Rail; rail operators Phase 2 was completed on 25th March 2019 on time and under budget. This new infrastructure immediately enabled enhancements to the line’s performance and resilience. Further improvements over the route have been recommended (15) within STPR2. No further details or commitments are yet provided. Perth-Dundee- Aberdeen rail corridor enhancements Improvement programmes would include junction upgrades and permissible speed increases. Opportunities would be taken to increase Transport Scotland; Network Rail; rail operators TBC
Page 6
5 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes gauge clearance to permit taller and wider trains Edinburgh/Glasgow- Perth/Dundee rail corridor enhancements improvement programmes would include junction upgrades and permissible speed increases. Opportunities would be taken to increase gauge clearance to permit taller and wider trains Transport Scotland; Network Rail; rail operators TBC Improve regional, national rail infrastructure and connectivity Rail service enhancement between Aberdeen and Central Belt 2023 Yes Transport Scotland; Network Rail; ScotRail; Tactran RTS and Delivery Plan Project SC1.4; Action highlighted in Infrastructure Investment Plan for Scotland 2021-22 to 2025-26. This project is being progressed by the Aberdeen to Central Belt Project Delivery Team and will deliver improved journey times, capacity and economic benefits along the route. The project is being delivered alongside the Aberdeen City Region Deal projects. Opportunities along the Perth – Montrose corridor Ongoing appraisal work No Tactran; Transport Scotland; Network Rail; Relocation of Invergowrie rail station identified in Tay Estuary Rail Study and included in RTS and Delivery Plan Project R5.4.
Page 7
6 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes ScotRail; Perth & Kinross Council; Dundee City Council; Angus Council Current appraisal work via Transport Scotland’s Local Rail Development Fund is looking at options of new/relocated stations and other potential interventions to maximise the benefits of the Revolution in Rail timetable enhancements. Trunk road and motorway safety improvements to progress towards ‘Vision Zero’ STPR2 30 – road safety improvements are progressed across the trunk road and motorway network with a primary, but not exclusive, focus on rural sections where accident rates and severities are typically higher. Transport Scotland; Scottish Government TBC Trunk road and motorway climate change adaptation and resilience STPR2 31 - building on existing evidence around vulnerable locations to develop a fuller picture of those areas on the trunk road and motorway network most at risk of disruption due to weather events. Transport Scotland; Scottish Government TBC
Page 8
7 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes This would provide a basis for identifying, prioritising and implementing improvements Trunk road and motorway renewal for reliability, resilience and safety STPR2 32 - continued and increased investment in the trunk road and motorway network over and above current maintenance levels to keep the network reliable and resilient for road users. Transport Scotland; Scottish Government TBC A9 potential grade separation of junctions at Auchterarder; Blackford; and Broxden and Inveralmond, Perth These projects are not specifically mentioned in STPR2. Where appropriate details have been added to specific sites in table 3. A9 dualling between Dunblane and Inverness Luncarty to Pass of Birnam Yes Transport Scotland, Tactran, Perth & Kinross Council RTS and Delivery Plan Project SC6.1 Complete August 2021.
Page 9
8 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes Birnam to Tay Crossing After 2014 Yes Transport Scotland, Tactran, Perth & Kinross Council RTS and Delivery Plan Project SC6.1 Preferred route option identified Dec 2023. Public exhibitions held Jan 2024. Tay Crossing to Ballinluig After 2014 Yes Transport Scotland, Tactran, Perth & Kinross Council RTS and Delivery Plan Project SC6.1 Preferred route option identified Dec 2016. Public exhibitions held Feb 2017. Draft Orders published July 2018. Ground investigations started Oct 2018. Public Local Inquiry not required, Scottish Ministers published decision notice March 2021 concluding Orders should be made. Road Order and CPO came into force November 2021. A9 Delivery Programme updated Dec 2023. Section programmed for Spring 2024 onwards. Pitlochry to Killiecrankie After 2014 Yes Transport Scotland, Tactran, Perth & Kinross Council RTS and Delivery Plan Project SC6.1 Preferred route option identified Nov 2016. Draft Orders published Dec 2017. Public inquiry held Mar 2019. Ground investigations started. Public Local Inquiry not required. Scottish Ministers published decision notice concluding Orders should be made. Road Order and CPO came into force November 2021.
Page 10
9 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes A9 Delivery Programme updated Dec 2023. Section programmed for Summer 2025 onwards. Killiecrankie to Glen Garry After 2014 Yes Transport Scotland, Tactran, Perth & Kinross Council RTS and Delivery Plan Project SC6.1 Preferred route option identified Mar 2016. Draft Orders published Nov 2017. Archaeological survey undertaken at Killiecrankie battlefield. Ground investigations undertaken. Public Local Inquiry held Jan 2020. Scottish Ministers published decision notice Nov 2022 concluding Orders should be made. A9 Delivery Programme updated Dec 2023. Section programmed for 2028/2029 onwards. Shaping Perth’s Transport Future Phase 1: A9/A85 Crieff Road improvements to relieve traffic congestion and facilitate development of west/north-west Perth Cross Almond Link - Link from new Completed Partly Perth & Kinross Council; Transport Scotland; Developers Scheme was completed in May 2019 and is fully operational.
Page 11
10 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes A9/A85 junction over River Almond Phase 2: CTLR - Construction of new road and bridge over River Tay Construction started estimated with completion in 2025 Yes Perth & Kinross Council; Transport Scotland; Developers; Tactran RTS and Delivery Plan Project SC7.2 Main construction phase began in Aug 2022 with the complete CTLR due to open in March/April 2025. By the end of 2023, other key milestones included: • The newly realigned section of the A9 opened on 3 August 2023, ahead of time, allowing the Gran Fondo World Championships to take place on a 164 mile route through Perthshire. • Opening of a section of the new link road between Stormontfield and the A93 opened in September, giving motorists and active travel users a more direct, and safer, route. • Construction of both east and west abutments on Destiny Bridge are now complete, and the initial elements of the superstructure has commenced. • The Green Bridge structure is substantially complete, with landscaping and access paths now well underway. • Three of four roundabouts are now open to traffic; Stormontfield, the A93 and the A94.
Page 12
11 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes Phase 3: Berthapark Link TBC Yes Perth & Kinross Council; Transport Scotland; Tactran; Developers RTS and Delivery Plan Project SC7.3 Council now progressing the design work for this phase. Strategic case for the Phase 3 link already been made as part of the wider business case work for Perth Transport Futures Project. Opportunities to progress Berth Park, Park and Choose site at same time also being explored. Transport Plan: Perth Transport Plan in tandem with development of CTLR Yes Perth & Kinross Council; Transport Scotland; Tactran; Developers RTS and Delivery Plan Project SC7.4 Initial project development work commenced via active travel and bus priority funding streams. Emphasis will be on locking in any benefits on reduced volumes of traffic via the CTLR creating an improved wider public space environment particularly for more sustainable modes of travel. Further details on funding, phasing and delivery will be explored within the Mobility Strategy. Strategic Development Framework for West/North-West Perth Setting out the phasing and priorities for the integration of the masterplans for the strategic development areas Completed Not required Perth & Kinross Council; Transport Scotland; Tactran; Developer/ Landowner; Adopted as non-statutory guidance November 2016
Page 13
12 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes SEPA; SNH; Scottish Water Cemetery search area The Council has identified a search area at the Blairgowrie Eastern Expansion proposal (MU330) because there is a future need for more cemetery space in the Blairgowrie and Rattray area Commenced Unknown Perth & Kinross Council Discussions to be held with landowner for potential cemetery use in this location. A range of sites including this site being considered for the wider Strathmore area. The Council has identified a search area at Milnathort because there is a future need for more cemetery space in the Kinross and Milnathort area Commenced Unknown Perth & Kinross Council Site tests undertaken – soil conditions unfavourable for a cemetery at this location and alternative sites currently being explored for the wider Kinross-shire area. The Council has identified a search area near Isla Road, Perth because there is a future need for more cemetery space in the area Commenced Unknown Perth & Kinross Council Discussions underway with landowner. Range of sites including this site being considered for the wider Perth city area.
Page 14
13 Project/ Policy Description Project commencing Funding in place Lead Partners/ Participants Progress notes The Council has identified a search area at Perth West, Perth because there is a future need for more cemetery space in the area Commenced Unknown Perth & Kinross Council Discussions to be held with landowner(s) for longer term cemetery site – test digs still to be undertaken. Range of sites including this site being considered for the wider Perth city area.
Page 15
14 Table 2: Local Development Plan Policy Actions Policy Description Actions Funding in place Lead partners/ participants Progress notes A SUCCESSFUL, SUSTAINABLE PLACE 1 Placemaking Prepare Placemaking Supplementary Guide to set out how Policy 1 will be implemented on how individual criteria can be achieved. Further information to be provided on: how capacity ranges have been calculated; how ranges will be calculated on windfall sites; and how proposals for changes to the capacity on consented sites will be dealt with. Not required Perth & Kinross Council; SEPA; SNH Supplementary guidance for LDP2 adopted February 2020. Non statutory guidance to support Policy 1 on Ancillary and Annex Accommodation adopted November 2021 2 Design Statements To be submitted by developers with appropriate applications and monitored and scrutinised by PKC. Not required Perth & Kinross Council; Developers Continuous 3 Perth City Monitoring under-utilised land Not required Perth & Kinross Council; Landowners and Developers Continuous 4 Perth City Transport and Active Travel Monitor transport routes and transport choices Not required Perth & Kinross Council; Tactran Ongoing monitoring of routes and mode choices As part of wider mobility strategy development. Sustrans and Transport Scotland have committed to working with the Council to deliver the Dunkeld Road
Page 16
15 Policy Description Actions Funding in place Lead partners/ participants Progress notes corridor, which links Luncarty to the City Centre. Funding has been awarded for the first arm of the network, on Dunkeld Road, connecting the neighbourhoods of Bertha Park, Inveralmond and Muirton to the City Centre. Preferred route concept design is anticipated by end of March 24, with detailed design expected 24/25. PKC are engaging with the Neighbourhood Advisory Group as this project progresses. Further opportunities for sustainable travel improvements being explored through external funding sources like the Bus Partnership Fund. 5 Infrastructure Contributions Prepare, consult and adopt supplementary guidance on developer contributions and affordable housing Not required Perth & Kinross Council; Transport Scotland; Tactran Updated supplementary guidance was adopted 18th Dec 2023. 6 Settlement Boundaries Monitor through development management process Not required Perth & Kinross Council Continuous 7 Employment and Mixed Use Areas Monitoring employment land in urban and rural areas to ensure there is a continuous five-year supply of effective land for employment uses Not required Perth & Kinross Council Continuous monitoring plus publication of annual Employment Land Audit
Page 17
16 Policy Description Actions Funding in place Lead partners/ participants Progress notes 8 Rural Business and Diversification Monitor through development management process Not required Perth & Kinross Council Continuous 9 Caravan Sites, Chalets and Timeshare Developments Monitor through development management process Not required Perth & Kinross Council Continuous 10 City, Town and Neighbourhood Centres Monitor retail planning applications in the areas identified in the policy Yes Perth & Kinross Council Continuous monitoring supplemented by bi-annual survey 11 Perth City Centre Secondary Uses Area Monitor planning applications in the area identified in the policy Yes Perth & Kinross Council Continuous monitoring supplemented by bi-annual survey 12 Commercial Centres and Retail Controls Monitor planning applications in the areas identified in the policy Yes Perth & Kinross Council Continuous monitoring supplemented by bi-annual survey 13 Retail and Commercial Leisure Proposals Monitor through development management process Yes Perth & Kinross Council Continuous 14 Open Space Retention and Provision Prepare, consult and adopt supplementary guidance on Open Space Provision and Developer Contributions. Not required Perth & Kinross Council; Supplementary guidance for LDP2 adopted in March 2021. Food Growing Strategy adopted 27 October 2021
Page 18
17 Policy Description Actions Funding in place Lead partners/ participants Progress notes Prepare a Food Growing Strategy and assess demand for additional growing spaces. Open Space Audit project plan now drafted with a view to audit being completed spring 2024 and strategy drafted by December 2024. 15 Public Access Maintenance of Core Path Plan Identify and investigate the potential of disused railway lines. Not required Perth & Kinross Council; Access Forum Continuous Disused Railway Line study data collection and analysis underway. 16 Social, Cultural and Community Facilities Monitor through updated infrastructure studies Not required Perth & Kinross Council Continuous 17 Residential Areas Monitor through development management process Not required Perth & Kinross Council Continuous 18 Pubs and Clubs in Residential Areas Monitor through development management process Not required Perth & Kinross Council Continuous 19 Housing in the Countryside Prepare supplementary guidance on Housing in the Countryside Monitor through development management process Not required Perth & Kinross Council; SNH Supplementary guidance for LDP2 adopted February 2020. Need for review in light of NPF4 being considered. Continuous monitoring of applications 20 Affordable Housing Prepare supplementary guidance on Affordable Housing Not required Perth & Kinross Council; Scottish Government; Homes for Scotland Incorporated in updated Developer Contributions Supplementary Guidance adopted 18th Dec 2023.
Page 19
18 Policy Description Actions Funding in place Lead partners/ participants Progress notes 21 Gypsy/Travellers’ Sites Prepare non-statutory supplementary guidance Not required Perth & Kinross Council; Guidance adopted March 2023 22 Particular Needs Housing Accommodation Monitor through development management process Not required Perth & Kinross Council; Continuous 23 Delivery of Development Sites Prepare, consult and adopt non- statutory supplementary guidance on Delivery of Development Sites Not required Perth & Kinross Council; landowners, developers Non statutory guidance for LDP2 adopted November 2020 24 Maintaining an Effective Housing Land Supply Monitoring housing land in urban and rural areas to ensure there is a continuous five-year supply of effective housing land Not required Perth & Kinross Council; Continuous plus publication of annual Housing Land Audit 25 Housing Mix Monitor through development management process Not required Perth & Kinross Council Continuous 26 Scheduled Monuments and Archaeology Monitor through development management process Not required Perth & Kinross Council; Historic Environment Scotland; Perth and Kinross Heritage Trust Continuous 27 Listed Buildings Monitor through development management process Not required Perth & Kinross Council; Historic Environment Scotland; Perth and Kinross Heritage Trust Continuous
Page 20
19 Policy Description Actions Funding in place Lead partners/ participants Progress notes 28 Conservation Areas Maintain and review Conservation Areas and Conservation Area Appraisals Not required Perth & Kinross Council; Historic Environment Scotland; Perth and Kinross Heritage Trust Project program drafted to review all Conservation Area Appraisals / Article 4s / boundaries with timetable for reviews starting in May 2024. 29 Gardens and Designed Landscapes Monitor through development management process Review existing designations and consider potential additions Not required No Perth & Kinross Council; Historic Environment Scotland; Perth and Kinross Heritage Trust Continuous 30 Protection, Promotion and Interpretation of Historic Battlefields Monitor through development management process Not required Perth & Kinross Council; Historic Environment Scotland; Perth and Kinross Heritage Trust Working Group no longer taking place. Continuous but also to be included in the Conservation Area Appraisals. 31 Other Historic Environmental Assets Monitor through development management process Not required Perth & Kinross Council; Historic Environment Scotland; Perth and Kinross Heritage Trust Continuous A LOW CARBON PLACE
Page 21
20 Policy Description Actions Funding in place Lead partners/ participants Progress notes 32 Embedding Low and Zero Carbon Generating Technology in New Development Monitor statements submitted with planning applications Not required Perth & Kinross Council Continuous. Monitor in relation to emerging New Build Heat Standards coming into force April 2024. 33 Renewable and Low-Carbon Energy Prepare, consult and adopt supplementary guidance on Renewable and Low Carbon Energy Monitor through development management process Yes Perth & Kinross Council; SEPA, SNH Draft Guidance prepared and consultation carried out. Need for review in light of NPF4 to be considered. 34 Sustainable Heating and Cooling Prepare, consult and adopt supplementary guidance on Sustainable Heating and Cooling Monitor through development management process Yes Perth & Kinross Council; SEPA NPF4 Policy 19 (Heating & Cooling) provides an updated national planning policy for the assessment of development proposals in relation to heating and cooling. Statutory duties in relation to Local Heat & Energy Efficiency Strategies (LHEES) and the Heat Networks (Scotland) Act 2021 will provide spatial policy for heat network zoning that LDPs will be expected to take in to account. As such it is considered that there is no longer a requirement for standalone Supplementary Guidance to be prepared to specifically support Policy 34 (Sustainable Heating & Cooling) in light of the new duties and policy in this area, as well as the removal of the provision for Supplementary
Page 22
21 Policy Description Actions Funding in place Lead partners/ participants Progress notes Guidance as part of the new Development Planning legislation/regulations. 35 Electricity Transmission Infrastructure Monitor through development management process Not required Perth & Kinross Council Continuous 36 Waste Management Infrastructure Prepare supplementary guidance on Delivering Zero Waste Not required Perth & Kinross Council; Scottish Government; SEPA Supplementary guidance for LDP2 adopted February 2020. 37 Management of Inert and Construction Waste Monitor through development management process Not required Perth & Kinross Council Continuous A NATURAL, RESILIENT PLACE 38 Environment and Conservation The identification of local sites to be included within supplementary guidance Not required Perth & Kinross Council; SNH 40 Geodiversity sites assessed by panel. Final 10 sites to be surveyed by Jan 2023. Biodiversity site survey programme to be completed summer 2024. Adoption to be completed by July 2025 39 Landscape Prepare supplementary guidance on Landscape to help conserve and enhance the landscape qualities of Perth and Kinross. Not required Perth & Kinross Council; SNH Supplementary guidance for LDP2 adopted February 2020.
Page 23
22 Policy Description Actions Funding in place Lead partners/ participants Progress notes 40 Forestry, Woodland and Trees Prepare supplementary guidance on Forestry and Woodland Strategy Monitor through development management process Not required Perth & Kinross Council; Scottish Forestry; SNH; SEPA Supplementary guidance for LDP2 adopted February 2020. 41 Biodiversity Prepare, consult and adopt non statutory guidance on Biodiversity Not required Perth & Kinross Council; SNH Non statutory guidance adopted in April 2022. 42 Green and Blue Infrastructure Prepare supplementary guidance on Green and Blue Infrastructure Not required Perth & Kinross Council; SNH, SEPA, Scottish Forestry Supplementary guidance for LDP2 adopted February 2020. 43 Green Belt Monitor through development management process Not required Perth & Kinross Council; Continuous 44 Perth Lade Green Corridor Creation of new links and improvements to Perth Lade Green Corridor Partly Perth & Kinross Council; SEPA; SNH Lade Management Plan (2020-2025) adopted. 45 Lunan Lochs Catchment Area Prepare non-statutory guidance on Dunkeld-Blairgowrie Lochs SAC Not required Perth & Kinross Council; SEPA; SNH Non statutory guidance for LDP2 adopted November 2020 46 Loch Leven Catchment Area Prepare non-statutory guidance on Loch Leven SPA Not required Perth & Kinross Council; SEPA; SNH Adopted as non-statutory guidance for LDP2 April 2022 47 River Tay Catchment Area Prepare non-statutory guidance on River Tay SAC Not required Perth & Kinross Council; SEPA; SNH Non statutory guidance for LDP2 adopted November 2020
Page 24
23 Policy Description Actions Funding in place Lead partners/ participants Progress notes 48 Minerals and Other Extractive Activities – Safeguarding Monitor through development management process Not required Perth & Kinross Council Continuous 49 Minerals and Other Extractive Activities – Supply Detailed advice on financial guarantees to be contained within supplementary guidance Monitor workable mineral resources; maintain ten year landbank of permitted reserves for construction aggregates Not required Perth & Kinross Council Supplementary guidance for LDP2 adopted February 2021 Continuous Aggregate Minerals Survey for Scotland updated 2019 50 Prime Agricultural Land Monitor through development management process Not required Perth & Kinross Council Continuous 51 Soils Monitor through development management process Not required Perth & Kinross Council Continuous 52 New Development and Flooding Prepare supplementary guidance on Flood Risk and Flood Risk Assessment Yes Perth & Kinross Council; SEPA, Supplementary guidance for LDP2 adopted March 2021. 53 Water Environment and Drainage Monitor through development management process Not required Perth & Kinross Council Continuous
Page 25
24 Policy Description Actions Funding in place Lead partners/ participants Progress notes 54 Health and Safety Consultation Zones Monitor through development management process Not required Perth & Kinross Council Continuous 55 Nuisance from Artificial Light and Light Pollution Monitor through development management process Not required Perth & Kinross Council Continuous 56 Noise Pollution Monitor through development management process Not required Perth & Kinross Council Continuous 57 Air Quality Prepare, consult and adopt supplementary guidance on Air Quality Yes Perth & Kinross Council Supplementary guidance for LDP2 adopted February 2020. Review of Perth Air Quality Action Plan in progress. 58 Contaminated Land and Unstable Land Monitor through development management process Not required Perth & Kinross Council Continuous A CONNECTED PLACE 59 Digital Infrastructure Monitor through development management process Not required Perth & Kinross Council Ongoing and mapped on GIS system 60 Transport Standards and Accessibility Requirements Review existing National Roads Development Guide to give guidance on: sustainable and active travel and the infrastructure requirements; requirements for public transport Not required Perth & Kinross Council; Tactran Draft of new ‘Sustainable and Inclusive Street’ guidance to be produced for consultation in 2024.
Page 26
25 Policy Description Actions Funding in place Lead partners/ participants Progress notes availability in new developments; provision of infrastructure to support low and ultra-low emission vehicles; provision of infrastructure for shared vehicle use; low car or no car developments in highly accessible areas; and to provide information about when a transport assessment or statement is required and guidance on travel plans. 61 Airfield Safeguarding Prepare supplementary guidance on Airfield Safeguarding Not required Perth & Kinross Council Supplementary guidance for LDP2 adopted February 2020.
Page 27
26 Table 3: Local Development Plan Proposals Actions Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes E10 Borlick, Aberfeldy Development proposal including masterplan, flood risk assessment, transport assessment, energy statement 2015 Unknown A & J Stephen Ltd; Perth & Kinross Council; SEPA Ongoing discussions between PKC, developer and landowner. H36 Borlick, Aberfeldy Development proposal including masterplan, flood risk assessment, drainage impact assessment, transport assessment, energy statement 2017 Unknown A & J Stephen Ltd; Perth & Kinross Council Ongoing discussions between PKC, developer and landowner. Access flagged as constraint on site delivery, discussions on site access taken place in 2023 with further exploration to take place in 2024. MU8 Newburgh Road (North), Abernethy Development proposal including flood risk assessment, feasibility study for restoration of culvert, evaluation of archaeological potential 2019 Unknown Hadden Group; Perth & Kinross Council; SEPA Complete E4 Newburgh Road, Abernethy Development proposal 2019 Unknown Branston Ltd; Perth & Kinross Council; SEPA Part of this site has a current planning permission. Application (ref: 18/01016/FLL) for ‘Alterations and extension to building, erection of a cold storage building including ramp, acoustic fence, installation of air conditioning units, formation of an access road, parking areas, fuelling bay, outdoor storage, hardstanding areas,
Page 28
27 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes landscaping and associated works’ was approved in 2019. E29 Aberuthven Development proposal including flood risk assessment, transport assessment TBC Unknown Denholm Partnership LLP; Perth & Kinross Council; Transport Scotland; SEPA No progress E30 Mornity, Alyth Development proposal TBC Unknown GS Brown Construction Ltd; Perth & Kinross Council Developer/Landowner advised they no longer have an interest in the site. H59 Glenree, Alyth Development proposal including flood risk assessment, possible drainage impact assessment, possible water network investigations 2021 Unknown Landowner; Perth & Kinross Council; SEPA Owner advised they cannot progress with site until development of the adjacent site to the south commences (currently unallocated ‘white land’ in LDP2). H60 Albert Street and St Ninians Road, Alyth Development proposal including flood risk assessment, possible drainage impact assessment, possible water network investigations, possible Commenced Unknown Guild Homes; Perth & Kinross Council Planning applications approved (17/00644/AMM) for the northern site and section 75 completed. Developer confirmed they are progressing with the northern section of the site only.
Page 29
28 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes archaeological investigations H252 Annfield Place, Alyth Development proposal including topographical study, flood risk assessment, drainage impact assessment, archaeological survey TBC Unknown Landowner; Perth & Kinross Council; SEPA Developer/Landowner has no plans to develop the site in the foreseeable future. H61 New Alyth Development proposal including flood risk assessment 2019 Unknown A & J Stephen Ltd; Perth & Kinross Council; SEPA Proposal of Application Notice submitted October 2023 (23/00016/PAN). Full application expected before PoAN lapses in October 2024. E25 Auchterarder Development proposal including masterplan, flood risk assessment, transport assessment Commenced Unknown D King Properties; John Handley Associates; Perth & Kinross Council; Transport Scotland; SEPA Planning permission for roundabout and ancillary works (12/02160/FLL), renewal granted 27 October 2016 (16/01443/FLL); Planning permission for further renewal (19/01599/FLL) granted 26 November 2019, permission lasts for seven years. Planning permission in principle for business park granted 12 April 2018 (17/00946/IPM) for 6.1 Ha of the 8 Ha allocated area, permission lasts for ten years. Agent states that submission of AMSC application will depend on market interest.
Page 30
29 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes H228 North West Kirkton, Auchterarder Development proposal and implementation of Auchterarder Development Framework including masterplan, transport assessment, flood risk assessment Commenced Unknown Successor to Stewart Milne Group; Perth & Kinross Council; Transport Scotland In principle permissions (08/01133/IPM & 16/01809/IPM) and S. 75 agreement signed Contributions towards the cost of delivering the A9 junction improvements are being collected through the Developer Contributions policy. Loaninghead junction complete and at October 2023 Reporter is minded to allow appeal and grant planning permission for the new junction at Shinafoot (21/01968/FLM) subject to a legal agreement to cover traffic management measures. H342 Auchterarder Development Framework Site 3 Development proposal and implementation of Auchterarder Development Framework including flood risk assessment Commenced Unknown Successor to Stewart Milne Group; Perth & Kinross Council; Transport Scotland In principle permission(08/01131/IPM) and S.75 agreement signed but permission has lapsed E35 Balado Bridge Development proposal including flood risk assessment Commenced Unknown DM Hall; Perth & Kinross Council; SEPA Planning application approved (09/01686/FLL). Conditional agreement with Kinross Aerospace Company. Purchase and planning expected 2024.
Page 31
30 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes H51 Balado Development proposal including flood risk assessment TBC Yes Premier Properties; landowner; Perth & Kinross Council; SEPA Outline planning application approved (07/01226/IPM). Detailed planning permissions (21/01108/FLL & 21/01107/FLL) granted Aug 2023 and construction commenced on the southern part of the site Planning application (23/01718/FLL) for change of house type under consideration. Planning permission (21/01536/FLL) granted Nov 2023. H13 St Martin’s Road, Balbeggie Development proposal including flood risk assessment, transport assessment TBC Unknown DM Hall; Morris Leslie; Perth & Kinross Council; SEPA PAN submitted (16/00006/PAN) in 2016. Planning application was expected to follow once CTLR became a committed project. Awaiting update from agent. H40 Ballinluig North Development proposal including flood risk assessment, network investigation, possible water investigations, transport assessment, possible construction method statement, possible otter survey and species protection plan, tree survey, possible archaeological evaluation 2009 Unknown Alexander and Co; Perth & Kinross Council; Transport Scotland; SEPA; Scottish Water 12 units approved under existing consent (09/00590/FLL, time extended through 14/00589/FLL) plus further 7 approved under 18/02315/FLL – total of 19 units. Formation of rock armour retaining structure approved as per 19/00792/FLL. Development under construction. E31 Welton Road, Blairgowrie Development proposal including masterplan; flood TBC Unknown Landowners; Perth & Kinross Perth & Kinross Council to initiate discussions about the potential and
Page 32
31 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes risk assessment, link road; possible wastewater network investigations, archaeological evaluation, transport assessment, energy statement, biodiversity study, possible construction method statement, possible otter survey and species protection plan Council; SEPA; Scottish Water; Historic Environment Scotland scope of a development framework for E31 & MU330. MU330 Blairgowrie Eastern Expansion Development proposal including masterplan, flood risk assessment, possible wastewater network investigations, drainage impact assessment, transport assessment, traffic management plan, energy statement, archaeological survey, woodland survey, biodiversity study TBC Unknown Landowners; Bidwells; Perth & Kinross Council; SEPA; Scottish Water; Historic Environment Scotland Perth & Kinross Council to initiate discussions about the potential and scope of a development framework for E31 & MU330. Pre-application proposal submitted Dec 2023. (23/00032/PREAPM) for 23.75ha mixed residential on southern end of site adjacent Park Head Road. MU5 Western Blairgowrie Development proposal including masterplan, transport assessment, flood risk assessment, possible wastewater network investigations, TBC Unknown Yeoman McAllister Architects; Perth & Kinross Council; SEPA; Scottish Water The site has planning permission in principle (17/00939/IPM) and a detailed planning application for phases 1B and 2A of development (22/00060/AMM) has been approved.
Page 33
32 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes energy statement, archaeological evaluation H63 Glenalmond Road, Rattray Development proposal including flood risk assessment, possible wastewater network investigation, archaeological evaluation 2017 Yes Springfield Properties Ltd; Perth & Kinross Council; SEPA; Scottish Water Planning application approved (16/01861/FLM & 17/02210/FUL) and construction has commenced. Expected completion in 2024/25 H341 Westfields of Rattray Development proposal including phasing programme, transport statement, flood risk assessment TBC Unknown Landowner; Perth & Kinross Council; SEPA Site currently being marketed. H64 Blairgowrie South Development proposal including flood risk assessment, link road, possible wastewater network investigation 2015 Unknown Scotia Homes; GS Brown Ltd; Perth & Kinross Council; SEPA; Scottish Water Planning in principle (10/01360/IPM), reserved matters (17/00961/AMM) and 20/01877/FLM) approved. Under construction. E22 Vicars Bridge Road, Blairingone Development proposal including flood risk assessment, feasibility study to assess restoration of existing culvert TBC Unknown Developer/ Landowner; Perth & Kinross Council Community engagement exercise carried out MU74 Blairingone Development proposal including masterplan, landscape visual impact assessment, flood risk TBC Unknown Developer/ Landowner, Perth & Kinross Council Community engagement exercise carried out. Pre LDP2 pre application enquiry for 90 homes.
Page 34
33 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes assessment, ground conditions investigation, woodland survey, feasibility study of enhancing / restoring channel, contaminated land investigations H14 Old Edinburgh Road/ Dunbarney Avenue, Bridge of Earn Development proposal including drainage impact assessment TBC Unknown Scotia Homes; Perth & Kinross Council; SEPA Permission for 110 houses (22/00817/FLM) approved. H15 Oudenarde, Bridge of Earn Development proposal and implementation of masterplan including new railway station strategic appraisal, investigation of provision of a heat network Commenced Unknown G S Brown Construction, Taylor Wimpey; Hillcrest Homes; Perth & Kinross Council, Transport Scotland, Tactran; SEPA; Scottish Water Affordable Housing completed. Junction improvements to A912 to facilitate access to Oudenarde and Brickhall Farm. S75 signed July 2016. Phase 1 application (16/02156/AMM) approved. Planning application (21/00615/AMM) approved but replaced with 23/00144/AMM, 23/00145/AMM, 23/0146/AMM approved Jan 2024..
Page 35
34 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes Negotiations on rail bridge ongoing. This will enable further residential phases to commence – per approved Phasing Arrangement with the S75 Agreement. Proposals for new railway station being progressed via Tactran’s Local Rail Development Fund appraisal. H72 Kintillo Road, Bridge of Earn Development proposal including drainage impact assessment 2015 Unknown King Group/ Ogilvie Homes; Perth and Kinross Council Development complete H17 Church Road, Burrelton and Woodside Development proposal including flood risk assessment, foul and surface water drainage assessment TBC Unknown Developer/ Landowner; Galbraith Group; Perth & Kinross Council; SEPA Planning permission in principle approved December 2022 (22/00951/IPL) H58 Cowden Road, Comrie Development proposal including flood risk assessment, archaeological evaluation 2021 Unknown Landowner A & J Stephen; Perth & Kinross Council; SEPA No progress E32 Coupar Angus West Development proposal including flood risk assessment TBC Unknown Developer /Landowner; Turley; Perth & Kinross Council; Scottish Water Application for planning permission in principle submitted December 2023 (23/02134/IPM). Currently awaiting decision.
Page 36
35 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes E33 East of Scotland Farmers Ltd, Coupar Angus Development proposal including flood risk assessment 2013 Unknown East of Scotland Farmers; Perth & Kinross Council; Scottish Water Phase 1 complete. Phase 2 secured planning permission and is expected to be completed by 2026. H65 Larghan, Coupar Angus Development proposal including archaeological evaluation 2015 Unknown Landowner; Perth & Kinross Council; Scottish Water Recent change in ownership, the new owners are committed to promoting the development opportunity and are considering actively marketing the site to determine market interest. E26 Bridgend, Crieff Development proposal including flood risk assessment 2019 Unknown Landowner; Perth & Kinross Council Access Road has been formed to service plots and development of plots has commenced. Planning permission for an office building granted (19/01666/FLL); for an office and storage building (21/00501/FLL); and for class 4 units (23/00684/FLL) H57 Wester Tomaknock, Crieff Development proposal including masterplan, flood risk assessment, transport assessment, archaeological investigation 2019 Unknown GS Brown Construction Ltd; Landowner; Perth & Kinross Council; Transport Scotland; SEPA Planning permission for 102 houses granted 17 August 2018 (16/02217/FLM). Further permissions to amend road layout, timescales and construction hours. Modification of Planning Obligation relating to primary education developer contribution (20/01160/MPO). Development commenced January 2023 and is ongoing.
Page 37
36 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes MU7 Broich Road, Crieff Development proposal and implementation of masterplan including transport assessment, flood risk assessment, archaeological investigation, energy statement 2019 Yes Landowner; John Handley Associates Ltd; Ogilvie Homes Ltd; Savills; Perth & Kinross Council; Transport Scotland Planning permission in principle granted 9 December 2015 (15/01237/IPM), renewal granted 6 June 2019 (18/02213/IPM). Planning permission for first phase of 246 houses approved and under construction (19/01165/AMM) Planning application for second phase of 222 houses submitted 29 August 2023, awaiting decision (23/01167/AMM) MU344 Broich Road North, Crieff Development proposal including phasing plan, possible archaeological investigation, energy statement 2019 Unknown London & Scottish Investments; Aldi Stores Ltd; Perth & Kinross Council At the western part of the site, planning permissions have been granted for retail and residential development. Permission for the erection of a retail unit including garden centre (Class 1) and a substation, formation of a service yard, vehicular access, parking areas, landscaping and associated works was granted on 22 June 2020 (19/02062/FLL) and permission for the erection of 38 dwellinghouses was granted on 10 September 2021
Page 38
37 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes (21/00411/FLL). Both have been constructed. At the eastern part of the site, planning permission in principle for two retail units was granted 8 December 2015 (15/01354/IPL), renewal granted 18 September 2017 (17/00976/IPL). Planning permission for erection of one of the retail units, approval of matters specified in conditions of 17/00976/IPL was granted 28 February 2018 (17/01955/AML). This permission has been implemented by Aldi Stores Ltd. At the site of the farm steading, planning permission for a change of use and alterations to agricultural building to form café and outside catering preparation/storage facility was granted 22 July 2019 (19/00858/FLL) and this has been implemented. A further planning application for erection of café (Class 3) with drive thru facilities was submitted 25 July 2023 and is awaiting decision (23/01164/FLL) E6 Cromwell Park, Almondbank Development proposal including flood risk assessment TBC Unknown Developer/ Landowner; Perth & Kinross Council; SEPA Site has previously been marketed. Developer/Landowner has been contacted to provide update.
Page 39
38 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes E9 Dalcrue Development proposal including flood risk assessment TBC Unknown Landowner; Perth & Kinross Council; SEPA Following discussion with landowners, this is most likely to progress as an expansion of the existing business on the adjacent Employment Safeguarded site but no immediate plans. To review through LDP3 the most appropriate zoning for the site i.e. safeguarding/proposal(s). E12-E13 Tullymilly, Dunkeld Development proposal including flood risk assessment, feasibility study on restoration of culvert, transport assessment 2019 Unknown Ristol Consulting Ltd; Atholl Estates; Perth & Kinross Council; Transport Scotland E12: Planning permission approved for additional units (20/00102/FLL). Development complete. E13: ongoing review of market demand for further commercial space following completion of development as per planning permission (20/00102/FLL). H20 Auchterarder Road, Dunning Development proposal including flood risk assessment, drainage impact assessment 2016 Unknown A & J Stephen Ltd; Perth & Kinross Council; SEPA No progress Op23 Station Road, Dunning Development proposal TBC Unknown Landowner; Perth & Kinross Council Land is reserved for potential extension to school for recreational purposes H21 West of Old Village Hall, Grange Development proposal including noise impact assessment, flood risk assessment, drainage assessment, assessment TBC Unknown Developer/ Landowner; Perth & Kinross Council; Planning permission lapsed.
Page 40
39 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes of area of archaeological assessment H52 Hattonburn, Milnathort Development proposal including flood risk assessment, drainage impact assessment, woodland management plan TBC Unknown The Good House Company; Perth & Kinross Council; SEPA Development complete H24 Moncur Road, Inchture Development proposal including noise attenuation measures TBC Unknown DG Coutts Associates; Perth & Kinross Council; Planning application by Hadden Construction Ltd (17/02159/FLM) was refused on sound attenuation issues and appealed. Appeal failed due to Reporter’s concerns with noise from adjacent factory. 23/00004/PAN submitted March 2023 for 50 homes. Public exhibition held 24 April 2023 at Inchture Village Hall. E37 James Hutton Institute, Invergowrie Development proposal including transport assessment, archaeological evaluation 2014 Unknown James Hutton Institute; Perth & Kinross Council; Transport Scotland; Tactran In Principle application (20/01103/IPM) for mixed use approved followed by several detailed applications. Included in Tay Cities Deal. H42 East of Primary School, Kenmore Development proposal including flood risk assessment, drainage impact assessment TBC Unknown McKenzie Strickland Associates Ltd; landowner; Perth & Kinross Council; SEPA Masterplanned approach for the wider Taymouth Castle Estate (under new ownership). Update from site agent confirming intention to develop site H42. Further discussions required to consider future development of allocated site.
Page 41
40 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes RT1 West Kinfauns Park & Ride, Kinfauns Development proposal including flood risk assessment Commenced No Perth & Kinross Council; Transport Scotland; Tactran Planning permission (18/02232/FLM) approved. The site has recently changed ownership and discussions are ongoing with the new owner. Included in RTS and Delivery Plan Project PR2.5. New application submitted by Morris Lesley (21/01855/IPM) to cover Park & Ride as well as museum, hotel & recreational/tourism potential. Still pending subject to S75 being concluded. H48 Pitdownie, Milnathort Development proposal including flood risk assessment, drainage impact assessment, noise attenuation measures Commenced Unknown Springfield; Perth & Kinross Council Development nearing completion H49 Pacehill, Milnathort Development proposal including noise attenuation measures Commenced Unknown Dundas; Perth & Kinross Council; Transport Scotland Development complete. H50 Old Perth Road, Kinross Development proposal including flood risk assessment, drainage impact assessment, noise attenuation measures TBC Unknown Successor to Stewart Milne Homes; Perth & Kinross Council Planning permission (08/00805/AML) approved Owner is in discussions to sell site to another developer. Op11 Turfhills Motorway Development proposal including flood risk assessment, drainage TBC Unknown MOTO Hospitality Ltd; Planning applications approved (11/00197/FLM; 14/00403/FLM).
Page 42
41 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes Service Area, Kinross impact assessment, archaeological investigation Perth & Kinross Council Op24 Kinross Town Hall, Kinross Development proposal Complete Unknown Town Hall Developments Ltd; Perth & Kinross Council Planning application approved (13/00462/FLL) and construction complete E16 South Kinross Development proposal including drainage impact assessment, noise impact assessment TBC Unknown Developer/ Landowner; Perth & Kinross Council; SEPA Landowner/Developer has been contacted for update E18 Station Road South, Kinross Development proposal including drainage impact assessment, possible construction method statement, flood risk assessment Commenced Unknown Mouchel Consulting; Perth & Kinross Council; SEPA Access road complete and the site has been serviced by the Council into five business plots and sold. Dance studio, and showroom/workshop completed. Further planning permission for office /workshop building 23/00762/FLL approved. Application for further office/workshop (22/02181/FLL) approved. E19 Stirling Road, Kinross Development proposal including masterplan, flood risk assessment, drainage impact assessment, transport assessment, noise impact assessment, possible construction method statement TBC Unknown Wolfson Properties; Clear Amber Group; Drysdales; Perth & Kinross Council; Discussions ongoing with landowners.
Page 43
42 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes Transport Scotland; SEPA E20 Old Perth Road, Kinross Development proposal including flood risk assessment, drainage impact assessment, landscape assessment, noise impact assessment, archaeological investigation TBC Unknown Hendersons Surveyors; Perth & Kinross Council; Transport Scotland; SEPA Planning application approved (07/02030/IPM). Talks with potential businesses halted due to pandemic. Hoped these discussions / negotiations can resume in near future but no timescale at present. E21 Auld Mart Road, Kinross Development proposal including flood risk assessment, drainage impact assessment, possible construction method statement TBC Unknown Hatrick Bruce Properties Ltd; Perth & Kinross Council; Transport Scotland; SEPA Owner has no plans to progress development on the site and requests the site be deallocated in the next LDP. Application for budget retail store 22/01004/FLL under consideration. MU27 Luncarty South Development proposal including masterplan, flood risk assessment, transport assessment, new junction to A9 and CTLR, district heating and combined heat & power system investigations, possible construction method statement, possible otter survey and species protection plan, 2017 Unknown A & J Stephen Ltd; I & H Brown; Wedge Homes Ltd; Perth & Kinross Council; Transport Scotland; SEPA Planning application approved and Section 75 signed (17/00847/IPM) for part of the site. Condition 3 of 17/00847/IPM varied through s42 application (ref: 22/00869/IPM). Application for remainer of site (ref: 23/00592/IPM) approved subject to S75.
Page 44
43 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes archaeological assessment, mineral resource sterilisation assessment H68 Ardler Road, Meigle Development proposal including flood risk assessment, construction method statement, possible otter survey and species protection plan, drainage impact assessment 2016 Unknown Hadden Group; Perth & Kinross Council; SEPA; Scottish Water Planning application (18/01144/FLL) approved. Development completed. H69 Forfar Road, Meigle Development proposal including masterplan, transport statement, possible archaeological investigation 2014 Unknown M J & J McLaren; Keir and Co; Perth & Kinross Council; Scottish Water Planning application submitted August 2022 (22/01501/FLM) and approval recommended subject to S75. H45 West of Bridge Road, Murthly Development proposal including flood risk assessment, drainage impact assessment TBC Unknown Bidwells; A&J Stephen; Perth & Kinross Council Pre-application discussions held with housebuilder. Site currently programmed to start 2024/2025. Op19 Ochil Hills Hospital Development proposal including masterplan, flood risk assessment; drainage impact assessment, woodland management plan TBC Unknown Edinburgh MI; Perth & Kinross Council; SEPA Planning permissions (10/02159/AMM; 12/00247/FLM; 15/00360/MPO) Construction in progress
Page 45
44 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes MU345 Bertha Park, Perth Development proposal and implementation of masterplan Commenced Yes Springfield; Perth & Kinross Council; Transport Scotland In principle (15/01112/IPM) planning permission granted for the whole area, detailed planning permission has been granted for the first phase of the community facilities and housing, development has started onsite. As of Sept 23 there were 277 private homes, 222 affordable homes, and 4 commercial units occupied with another unit sold, and a High School. Perth and Kinross Council Lifelong-Learning Committee on 2nd Nov also approved a new build primary school adjacent to Bertha Park High School, with effect from August 2026. Updated In Principle application revised timescales for AMSC applications: phase 1.2 by 2028 (with an application covering at least the road layout and plot servicing by May 2024), phase 2 by 2028 and phase 3 by 2038. The Council has provided Transport Scotland with a Memorandum of Understanding between the Council and Transport Scotland which sets out the terms for the transfer of all secured contributions towards the trunk road infrastructure projects. There is a Section 75 Agreement which includes
Page 46
45 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes provision of contributions towards improvements at Broxden. MU73 Almond Valley, Perth Development proposal and implementation of phasing programme, new primary school, detailed delivery plan, flood risk assessment, energy statement linked to MU70 and H319, construction method statement, possible otter survey and species protection plan, archaeological investigation, phased development of road access 2016 Unknown Pilkington Trust; Successor to Stewart Milne Group; Perth & Kinross Council Transport Scotland; SEPA; SNH; Tactran In principle 15/01157/IPM planning permission granted for whole site. Flood risk assessment prepared and to be updated with each phase of development.. AMSC applications 19/01430/AMM and 19/01433/AMM for Phase 1 housing and the primary infrastructure required to serve the development were approved Nov 2022. The Council has provided Transport Scotland with a Memorandum of Understanding between the Council and Transport Scotland which sets out the terms for the transfer of all secured contributions towards the trunk road infrastructure projects. MU70 Perth West Development proposal; comprehensive masterplan; access and delivery strategy; transport strategy including blue green active travel network; landscape framework; greenspace TBC Unknown Ristol Consulting Ltd; Strutt and Parker; Perth & Kinross Council; Perth & Kinross Heritage Trust, Sustrans, and the A charrette (series of design workshops) was held in March and April 2015 to inform the preparation of LDP2 and a Masterplan Framework for wider Perth West area. With the wider proposal now confirmed in LDP2 an in principle application for
Page 47
46 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes management plan; sports facilities; woodland felling programme; surface water and drainage strategy; battlefield conservation plan; archaeological programme of works; geo- environmental audit; flood risk assessment; energy statement; noise impact assessment Key Agency Group including: Transport Scotland; Tactran; SNH; SEPA; Scottish Water; Historic Environment Scotland, NHS, Architecture and Design Scotland, Scottish Enterprise, and Forestry Commission Scotland mixed use development within a southern greenfield part of the Perth West site (20/00667/IPM) was granted planning permission 3 November 2023 and the associated S75 legal agreement has been concluded. The S75 agreement has site-specific planning obligations towards Broxden roundabout Junction Improvement works relating to phasing of development. Planning condition requires grade-separated junction delivery in relation to development completion threshold (condition 9 – 1001st unit). H1 Scott Street/ Charles Street, Perth Development proposal including drainage impact assessment, flood risk assessment, archaeological investigation TBC Part Developer/ Landowner; Perth & Kinross Council Phase 1: refurbishment of existing housing and upper floors of the Scott St/Canal St building had planning permission (16/00875/FLL) for student accommodation (47 bed, 30 bed and associated communal facilities) but this has now lapsed. Planning permission on remainder of site for car parking (15/01187/FLL) will not prejudice any future redevelopment for housing
Page 48
47 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes H3 Gannochy Road, Perth Development proposal including transport assessment, flood risk assessment, drainage impact assessment 2015 Yes Gannochy Trust; Perth & Kinross Council The southern part of the site south of Gannochy Farm is complete. The Trust still intend developing the northern section but no timescales as yet as the land is currently part of an agricultural lease and the Trust is in the process of developing it’s Strategic Plan and a new Estate Strategy. H71 Newton Farm, Perth Development proposal including masterplan, flood risk assessment, energy statement 2017 Unknown Lochhead Consultancy; Developer/ Landowner; Perth & Kinross Council; SEPA; Transport Scotland 19/00009/PAN submitted October 2019 for 75 homes with a public exhibition held 10 December 2019 at St Johnstone football club. 22/00816/FLL for erection of budget supermarket for south-east corner of H71 was withdrawn 13th Dec 2022 H174 Former Auction Mart, Perth Development proposal including noise assessment, ecological appraisal, construction method statement, delivery plan Developer / Landowner Phase 1 18/00412/AMM for 43 homes approved July 2018. Phase 2 18/01038/AMM for 208 houses and 30 flats approved 18 December 2018 and development is well underway H319 Ruthvenfield, Perth Development proposal including masterplan, flood risk assessment, drainage impact assessment, tree survey, contaminated land TBC Unknown Developer/ Landowners; Perth & Kinross Council; SEPA; Reallocated for housing in LDP2 this is a multi landowner site and the owners remain in active discussions with national housebuilders.
Page 49
48 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes investigation, energy statement, construction method statement, possible otter survey and species protection plan Transport Scotland MU168 North of Bertha Park, Perth Development proposal including energy statement, tree survey, flood risk assessment, drainage impact assessment, construction method statement, possible otter survey and species protection plan, archaeological survey, lighting impact assessment TBC Unknown Developer/ Landowner; Perth & Kinross Council; SEPA; Transport Scotland Not in LDP1, this allocation is new to LDP2. Council now progressing the design work for the Bertha Park link (Perth’s Transport Future Phase 3). Opportunities to progress Berth Park Park and Choose site at same time also being explored. MU331 Perth Railway Station and PH2O, Perth Development proposal including masterplan, transport interchange with links to active travel network, archaeological survey, drainage impact survey, energy statement, tree survey Heritage assessment of significance, Transport Statement TBC Unknown Developer/ Landowner; Perth & Kinross Council; Transport Scotland, ScotRail; Tactran; Historic Environment Scotland; Network Rail Not in LDP1, this allocation is new to LDP2 and timescales are not known. The Council and Network Rail are collaborating in respect of the development of the station to link in with the development of adjacent sites and sustainable transport corridors and it is anticipated a masterplan will be concluded by mid 2024 for consideration and implementation via planning and development processes.
Page 50
49 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes Included in RTS and Delivery Plan Project R5.2 and Tay Cities Deal. MU336 Murray Royal Hospital, Perth Development proposal including masterplan, transport assessment, flood risk assessment, biodiversity surveys, archaeological survey, listed building condition survey TBC Unknown Rivertree Residential Ltd; Hatfield Developments Ltd; Perth & Kinross Council; SEPA Applications reference 18/00094/ IPM for new build residential development and 18/00408/FLM and 18/00307/LBC for selective demolition and conversion approved. Development started on site March 2021. 23/01377/LBC for 1st phase alterations to SE/SW wings approved Dec 2023. MU337 Hillside Hospital, Perth Development proposal including masterplan, transport assessment, construction method statement, possible otter survey and species protection plan, scheme for potential contamination, archaeological survey TBC Unknown Westerwood Ltd; Perth & Kinross Council; SEPA Planning permission (20/01779/FLL) approved for a care home on northern half of the site and development commenced October 2023. Planning application 23/01218/FLM for residential development on the remainder was submitted July 2023 and is under consideration. MU171 Perth Quarry Development proposal including masterplan, feasibility study and business case, assessment of mineral resource, ground conditions assessment, TBC Unknown Developer/ Landowner; Perth & Kinross Council; SEPA Not in LDP1, this site is new to LDP2 and timescales are not yet clear, but it is expected that the site will come forward as an application in the next couple of years once the market settles. It is understood agreement has now been formalised for the access into the site.
Page 51
50 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes geo-environmental audit, transport assessment, flood risk assessment, drainage impact assessment, assessment of geological interest and preservation plan, tree survey E340 Broxden, Perth Development proposal and implementation of masterplan including green travel plan, flood risk assessment Commenced Yes John Dewar Lamberkin Trust & Needhill LLP; Perth & Kinross Council Now complete E165 Cherrybank, Perth Development proposal including tree survey, flood risk assessment TBC Unknown Developer/ Landowner; Perth & Kinross Council; Transport Scotland A planning application for a retail unit 21/00248/FLL on a northern half of the wider allocation was granted permission June 2023 but is subject to judicial review by Tesco, the hearing took place 30th Nov 2023, a decision is expected in 2-3 months thereafter. E1 The Triangle, Perth Development proposal including flood risk assessment Partially Completed Yes CKD Galbraith; Perth & Kinross Council Access road constructed May 2013 (09/00431/FUL) Planning consents have been implemented which cover the majority of the site (16/01897/FLL for a vehicle showroom (Arnold Clark); 16/01898/FLL for vehicle storage; and 16/01124/FLL for a coffee shop (Starbucks)). On the remaining part of
Page 52
51 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes the allocation a 18/01322/FLL planning permission was granted 6 September 2019 for a car sales unit, office, workshop vehicle display areas, and wash and valet building. Planning permission (21/01483/FLL) to renew this 18/01322/FLL permission was approved 19th Oct 2021. Works have not commenced. E2 Broxden, Perth Development proposal including drainage impact assessment, flood risk assessment TBC Unknown John Dewar Lamberkin Trust & Needhill LLP; Algo (Blairgowrie) Ltd; Bellway; Perth & Kinross Council; Transport Scotland; SEPA Planning application with masterplan for wider Broxden approved 12/01692/IPM included a condition to service this site which has been completed. Planning applications 23/00192/FLL (EV charging hub and hydrogen refuelling station), 23/00193/FLL (2 drive thrus) and 23/00504/FLM (mixed use café/restaurant units with drive thru facilities, and business units) are all currently under consideration. E3 Arran Road, Perth Development proposal including flood risk assessment Commenced Yes Developer/ Landowner; Perth & Kinross Council; SEPA; Scottish Water At the far northern end of E3, north of the Food and Drink (F+D) park, PKC has a 4 hectare proposed extension 21/00752/IPM in principle permission Oct 2021 for employment / business park.
Page 53
52 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes On the middle section of E3, on the PKC 8.8 hectare F+D Park site, PKC secured planning permission (12/01356/FLM) for the servicing of this industrial land which was then completed . Within the serviced F+D park and included in Tay Cities Deal planning permission (16/00562/FLL) for six industrial units was completed. Also permissions (15/02186/FLL)for ground mounted solar array, and a 19/01023/FLL permission for a vehicle inspection centre were also secured and completed. To the south of the F+D park on privately owned land planning permission 15/01826/FLM for eight class 4,5,6 units was secured and initiated but it has not been further progressedl. E38 Ruthvenfield Road, Perth Development proposal including masterplan, flood risk assessment, integration with public transport network, tree survey, landscape framework, energy 2013 Unknown Developer/ Landowner; Perth & Kinross Council Tactran; SNH; SEPA; Scottish Water; Transport Scotland Developers have acquired site. 19/02033/IPM in principle planning application for employment uses class 4,5 and 6 was approved 14th January 2021. Subsequent applications 21/01518/IPM to delete condition 7 (Public transport infrastructure) was refused, and 21/01795/IPM to delete
Page 54
53 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes statement, archaeological investigation condition 3 (traffic assessment of the 19/02033/IPM permission) was approved. 22/00373/FLL application for an office building was approved June 2022, and 23/00541/FLL for formation of an access road continuing Ruthvenfield Way was approved Oct 2023. Op2 Thimblerow, Perth Development proposal including flood risk assessment, drainage impact assessment, energy statement, archaeological investigation 2013 Unknown Expresso Property (Perth) Ltd; Perth & Kinross Council; Tactran PAN submitted (15/00018/PAN) for mixed use developmen. Thimblerow Development Brief was prepared to guide future planning applications and adopted September 2021. The Council aims to work with a selected developer to bring forward a planning application for a high-quality exemplar scheme demonstrating the potential for high amenity city centre living in a low carbon development. The first step will be public consultation and the submission of a new PAN. Planning application anticipated soon. Op4 Mill Street (South side), Perth Development proposal including drainage impact assessment, flood risk assessment archaeological investigation TBC Unknown Developer/ Landowner; Perth & Kinross Council 18/01177/FLL permission for temporary siting of street furniture and bike storage areas was granted August 2018. 19/00287/FLL permission for installation of 2 projectors for light based art was granted April 2019.
Page 55
54 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes 18/02302/FLL permission for public open space and occasional events/market area within the Guard Vennel was granted March 2019. Op6 Waverley Hotel, County Place, Perth Development proposal 2017 Unknown Developer/ Landowner; Perth & Kinross Council Extension to church and associated works 19/00550/FLL approved May 2019 and this redevelopment is now complete. Op8 Friarton Road, Perth Development proposal including drainage impact assessment, flood risk assessment TBC No Developer/ Landowner; Perth & Kinross Council; SEPA; Transport Scotland Provisional design has been completed. No capital funding identified at this stage. Resources required for roads infrastructure to allow full development of site. Op9 Bus Station, Leonard Street, Perth Development proposal including drainage impact assessment, energy statement, archaeological investigation TBC No Developer/ Landowner; Perth & Kinross Council; Tactran Improved bus station but could be housing, hotel, leisure, office if an alternative location found for bus station within the railway station redevelopment. Network Rail progressing Perth Station Masterplan which will explore better access and integration opportunities for bus and active travel. Op175 City Hall, Perth Development proposal including flood action plan 2017 Yes Developer/ Landowner; Perth & Kinross Council 18/02133/FLL planning permission for a sympathetic restoration respecting the setting of St John’s Kirk (category A listed) for a class 11 use (assembly and leisure) and class 3 use (food and drink)
Page 56
55 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes was approved 22 Jan 2019. Included in Tay Cities Deal, the new Perth Museum is expected to open Spring 2024. Op338 St John’s School, Stormont Street, Perth Development proposal including flood risk assessment 2017 Yes Developer/ Landowner; Perth & Kinross Council 18/00731/FLL Planning permission granted for the conversion of the school with minimal external alterations to provide a creative exchange to provide studios for artists and office spaces for creative space and a cafe.The development is complete. MU3 Perth Airport Development proposal including water supply investigation, flood risk assessment, contaminated land survey TBC Unknown Morris Leslie; Perth & Kinross Council; Scottish Water Planning permission (16/01935/IPM); No objection from SEPA to proposed private drainage system. Discussions held regarding future masterplan. H38 Middleton of Fonab, Pitlochry Development proposal including flood risk assessment, drainage impact assessment 2015 Unknown Bidwells; A&J Stephen; Perth & Kinross Council; SEPA In Principle application (21/00510/IPM) approved. Currently programmed for 2025/26. H39 Robertson Crescent, Pitlochry Development proposal including flood risk assessment, drainage impact assessment TBC Unknown Bidwells; A&J Stephen; Perth & Kinross Council; SEPA Discussions ongoing with housebuilder. Currently programmed for 2026/27. E23 Powmill Cottage Development proposal including flood risk assessment, noise impact assessment TBC Unknown Richstream Ltd; Perth & Kinross Council; SEPA Approved permission 19/006321/FLL, 20/00809/FLL, 20/01319/FLL, 22/00229/FLL for home /office and 19/01073/FLL for a small caravan site.
Page 57
56 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes Issues with site servicing and funding of access road. H53 Gartwhinzean Powmill Development proposal including masterplan, flood risk assessment, transport assessment, contaminated land investigation 2013 Unknown Thomson Homes; Perth & Kinross Council; SEPA Planning application for 29 houses (23/01224/FLL) under consideration E24 Rumbling Bridge Development proposal including flood risk assessment, noise impact assessment TBC Unknown Developer/ Landowner; Perth & Kinross Council; SEPA Planning permission lapsed (08/01412/REM). Recent application refused. Discussions ongoing with landowner re delivery mechanism. H29 Scone North Development proposal and implementation of masterplan including water storage investigation, flood risk assessment, active travel network, increase primary school capacity, archaeological investigation 2016 Yes A & J Stephen Ltd; Perth & Kinross Council; SNH; SEPA; Scottish Water 100 units can be built in advance of the CTLR becoming a committed project. Planning application 16/02127/IPM approved in 2017. First phase 1a approved 2019 for 42 units (18/02231/AMM). Construction underway. Increase to storage and pump capacity may be required at Balcraig service reservoir. This would be a Part 3 upgrade and developer funded. Phase 2A granted approval Dec 2023 for 210 units (22/02223/AMM).
Page 58
57 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes MU4 Angus Road, Scone Development proposal including flood risk assessment Commenced Unknown Developer/ Landowner; Perth & Kinross Council Planning permission for retail food store on part of site and relocation of park and ride (09/01311/IPM/ 12/02018/FLM/ 14/00874/AMM). Op22 Glebe School, Scone Development proposal 2017 Yes Developer/ Landowner; Perth & Kinross Council Site constructed with Permitted Development for Social Housing. Site now completed. H54 Scotlandwell Development proposal including flood risk assessment, feasibility study on restoration of culvert, peat survey and management plan 2014 Unknown Ardbed Homes / Gillies Investments Ltd; Perth & Kinross Council; SEPA Permission for 16 houses approved (22/01191/FLL) with a S75 agreement required for the delivery of self-build for the affordable housing requirement. MU6 Spittalfield Development proposal to include archaeological investigation TBC Unknown JWM Design Architectural Services; Perth & Kinross Council Planning application (16/01358/IPL) for 2 houses approved through appeal Further applications for single houses approved (20/01903/FLL, 21/01507/FLL). Pre-application discussions held for further residential development at the site. H30 H31 H32 H33 Stanley Development proposal to include masterplan for village expansion, flood 2014 Unknown Bidwells / Muir Homes; Perth & Kinross Council; Masterplan approved 2017 for all Stanley sites (17/00088/IPM).
Page 59
58 Proposal Location Actions Actions commencing Funding in place Lead partners and other participants Progress notes H34 risk assessment, landscape masterplan Transport Scotland; SEPA Site H30: Planning permission (19/01130/AMM) approved. Developer on site. Site H31: Application 22/01158/AMM approved subject to S75 Site H33: Development complete. Development Trust working on proposals for improved community facilities. Planning application submitted for community hub (ref: 22/01959/FLL) refused due to heritage concerns.
Page 60
59 Abbreviations and Acronyms Organisations PKC Perth & Kinross Council SEPA Scottish Environmental Protection Agency SNH Scottish Natural Heritage Tactran Tayside and Central Scotland Transport Partnership Terms AMSC Approval of Matters Specified in Conditions CTLR Cross Tay Link Road Ha Hectares LDP Local Development Plan NPF National Planning Framework PAN Proposal of Application Notice SDP Strategic Development Plan SG Supplementary Guidance STPR Strategic Transport Projects Review RTS Regional Transport Strategy