Update and Proposals for the Scottish Government Place Based Investment Programme

Perth and Kinross Council · 21 September 2022
Back to Environment, Infrastructure and Economic Development Committee — 21 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PERTH AND KINROSS COUNCIL 
Environment, Infrastructure & Economic Development Committee 
21 September 2022 
UPDATE AND PROPOSALS FOR THE SCOTTISH GOVERNMENT PLACE
BASED INVESTMENT PROGRAMME 
Report by Head of Planning and Development
(Report No. 22/225) 
1. PURPOSE 
1.1 This report provides an update on progress with projects allocated funding
from the Place Based Investment Programme and recommends further
projects to receive funding from the Programme allocation. 
2.  RECOMMENDATIONS 
2.1 It is recommended that Council: 
I. notes the progress being made on delivery of the already approved
Place Based Investment Programme funded projects allocated funding
during 2021/22. 
II. approves the allocation of funding available via the Place Based
Investment Programme 2022/23 to the following projects:
a. Rannoch Hub. Kinloch Rannoch
b. Aberfeldy Tourism Infrastructure
c. Self-Catering Accommodation, Cultybraggan Camp, Comrie
d. PLUS Perth, Civic Space, Ropemakers Close, Perth
e. Clachan and Quality Café, Perth 
III. notes the proposal to introduce an open application process for future
years allocation of Place Based Investment Programme funding. This
is to link with other national and local funding to maximise efficient use
of resources and investment support. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background/Main Issues 
• Section 5: Proposals 
• Section 6: Conclusion 
• Appendices

Page 2

4. BACKGROUND / MAIN ISSUES 
4.1 Prior to its replacement by the Place Based Investment Fund Programme, the
Scottish Government allocated Perth and Kinross Council £2.697M from the
Town Centre Fund. Following discussion by members, the Strategic Policy
and Resources Committee initially awarded funding to 5 projects in June 2019
(Report No 19/127 refers): 
• Strathmore Community Hub (£150K) 
• Coupar Angus Cycle Hub (£50K)
• Connecting Loch Leven with Kinross Town Centre (£800K) 
• Drummond Arms, Crieff (£600K) 
• Events Space, Pitlochry (£383K). 
4.2 An Executive Sub-Committee of the Strategic Policy and Resources
Committee on 23 October 2020 (Report No 20/204 refers) subsequently
agreed to: 
• de-commit funding from the Coupar Angus Cycling Hub due to the project
not proceeding
• provide an additional allocation of £487K to the Strathmore Community
Hub 
• provide an additional £20K to the Kinross/Loch Leven project 
• allocate £25K to the YMCA Perth Y Centre project 
• allocate £200K to the Local Full Fibre Network project 
• make further efforts to bring forward a viable project in Pitlochry as the
original idea did not generate widespread community support. 
4.3 Despite efforts to progress a project in Pitlochry, a further report was brought
back to the Strategic Policy and Resource Committee on 25 November 2020
(Report No 20/227 refers) to re-allocate resources from Pitlochry with
additional, and remaining, Town Centre Fund funding to the following projects: 
• Crieff Hotel arts hub (£100K) 
• Strathearn Hotel demolition and site clearance (£265K) 
• Town Wi-Fi Schemes (£50K) 
4.4 Meantime, the Place Based Investment Fund Programme (PBIP) was
launched in September 2020 as a replacement of the Town Centre Fund, with
the grant offer and objectives received on 10 May 2021.The main objectives
of the PBIP are to: 
• align place-based initiatives and establish a coherent local framework to
implement the Place Principle 
• support place policy ambitions such as town centre revitalisation,
community led regeneration, 20-minute neighbourhoods and Community
Wealth Building 
• ensure that all place-based investments are shaped by the needs and
aspirations of local communities

Page 3

• accelerate ambitions for net zero carbon, wellbeing, and inclusive
economic development, tackling inequality and disadvantage, and
community involvement. 
4.5 These criteria align with the Council’s own priorities to reduce poverty and
inequality, promote sustainable growth and development collaboratively,
consistent with the principles of the Perth and Kinross Offer. 
4.6 The Programme is to be achieved by investing in projects focussed on: 
• rural places with smaller populations, dependent on larger geographical
areas for support, for example: 
o small towns with a limited range of non-specialised facilities
o villages with very limited, or non-existent, access to facilities.
• urban places with sizeable populations, for example: 
o regional centres with extensive provision supporting a wide
geographical area 
o larger towns with a comprehensive range of dedicated services and
facilities 
o individual neighbourhoods with limited access to relevant local
provision.  
4.7 The available funds to Perth and Kinross were allocated as follows: 
Year LA Allocation £M Perth & Kinross Share £M
2021/22 38 1.265
2022/23 33 1.098
2023/24 23 0.766
2024/25 23 0.766
2025/26 23 0.766
TOTALS £140M Est £4.661M 
4.8 The PBIP grant can be claimed for eligible capital expenditure incurred by
local authorities or third parties. The grant is for expenditure additional to that
which is already, or would otherwise, be allocated to the budget of each
financial year and should not substitute for existing spend. The grant may also
be used to fund third party capital expenditure either directly, or through the
provision of grants to third parties (public sector bodies, private sector bodies
or individuals). The grant must be committed in the financial year it applies to.
For the financial year of 2022/23, it is expected that expenditure will be
undertaken or at least work, or contracts signed or commenced, by 31 March
2023. This is a challenging timescale for capital projects. 
4.9  Following discussion by members, the Strategic Policy and Resources
Committee of 1 September 2021 (Report No 21/149 refers) awarded £1.265m
PBIP funding to five existing Town Centre Funded projects which had
identified additional funding needs to ensure they could be fully completed. In
addition, they also allocated funding to the Council supported Letham Hub

Page 4

project which had identified a funding gap, but which was due to start on site
in December 2021. 
• Strathmore Community Hub - £125,000 
• Town Wi-Fi - £30,000 
• Kinross Loch Leven Car Park - £35,000 
• Drummond Arms - £140,000 
• Crieff Hotel Community Arts Space - £200,000 
• Letham Hub - £735,000 
4.10 Due to the risk of having to return unspent money to the Scottish Government
because of planning and procurement issues, it was agreed during March
2022 to decommit the funding to the Crieff Hotel. This was undertaken
following consultation with the three Strathearn Ward Elected Members, with
agreement for the funding already committed to a project in the ward to be re-
allocated to the Drummond Arms project, which was able to commit further
essential works before the end of March. 
4.11 Following the replacement of the Town Centre Fund, the Scottish Government
currently operates four funds that support place-based regeneration and
economic development:  
• The long-established Regeneration Capital Grant Fund is a competitive
fund that provides significant funding for capital projects led or sponsored
by local authorities and targeted at the most deprived urban and rural areas
across Scotland. 
• The Vacant and Derelict Land Investment Programme is a competitive fund
that operates from 2021-26. It provides significant funding for capital
projects which seek to tackle persistent vacant and derelict land through
low carbon, community-led, place-based approaches. 
• The third fund is the Place Based Investment Fund Programme which
operates from 2021-2026, replacing the one off 2018 Town Centre Fund. 
• The fourth fund is Rural Community Led Local Development Fund which
builds on the legacy of LEADER. This fund aims to test new approaches to
delivering community-led local development through place-based
partnerships.  Projects supported by this funding must advance equality,
inclusion, and diversity. 
4.12  There are further opportunities to align funding and maximise resource
support for projects with:  
• National Lottery Fund
• Tay Cities
• Capital programme
• Revenue capital grant support for property via Vacant Property/ Adapt Your
Property/Open for Business/ Housing Grants
• Environmental Challenge Fund
• Community Investment Fund, Participatory Budgeting
▪ City Heritage Fund.

Page 5

4.13 There are potentially some opportunities for further alignment of funding to
projects between these Scottish Government, national charities, and local
grant schemes with UK Government grant schemes:  
• The UK Shared Prosperity Fund provides revenue and capital funding and
is available from 2022-2025. During the 3-year period, Perth and Kinross
has an allocation of £4.736m. The primary aim of the fund is to empower
local leaders and communities to deliver locally identified priorities across 3
themes: Community and Place; Supporting Local Business; and People
and Skills. Additional resources of £988k are allocated to support numeracy
training via the Multiply programme. Agreement on priorities for initial, high
level allocations and capacity to align with other funding through an open
challenge fund applications process have been agreed and is awaiting a
response from UK Government.
• The UK Government also operates the competitive Levelling Up Fund
(LUF). This is a capital fund which aims to tackle economic differences and
drive prosperity through town centre and high street regeneration, local
transport projects, and cultural and heritage assets. A bid of 10M has been
submitted for Perth West. The UK LUF runs for four years from 2020-2025
with no commitment to continue beyond this period. 
4.14  A workshop for all elected members was held on 12 January 2022 to advise
on key criteria in relation to the allocation of funding based on previous
awards for the use of the remaining Place Based Investment Programme
funding. It was advised that critical issues to consider in the allocation of
resources for future years to meet core criteria and objectives: 
• alignment with community needs and priorities
• geographical spread
• deliverability
• previous support
• scale of projects and social, economic, and environmental benefits
• targeting resources to assist investment in areas of greatest socio-
economic need
• maximising funding support and leverage through match funding from
other national and local place-based investment and grants 
4.15 It was noted that community and business engagement along with the co-
design of outcome focussed projects, in line with the principles of the Perth &
Kinross Offer, were being progressed in a variety of ways.  These include the
Economic Wellbeing Plan, Tourism Infrastructure Strategy and Action Plan,
Locality Outcome and Acton Plans, Community Action Plans, area housing
and greenspace participation frameworks. 
4.16  Five projects have now been assessed and identified as priorities for
investment against key criteria and are proposed for Place Based Investment
Fund Programme 2022/23 funding.  These priorities are primarily because of
community and business support, immediate need for funding to augment
other funding and deliverability within the timescale.

Page 6

5. PROPOSALS 
5.1 The table below provides an update on progress and spend relating to
previously approved Town Centre Fund and PBIP funded projects indicating
positive progress in all projects. The Drummond Arms is awaiting drawdown
of funding for completed works. The Letham Hub has to date utilised previous
resource allocations via RCGF (Regeneration Capital Grant Fund) funding,
but it is anticipated the Place Based Investment Fund Programme allocation
for 2021/2022 will be drawn down in October 2022. 
5.2 Allocations from UK SPF for 2022/23 and future years are being decided by a
political process with the UK Government. The projects which have potential
alignment with the fund have submitted Expressions of Interest to be included
in the funding ask of UKSPF (UK Shared Prosperity Fund) for 2022/23. In
both cases noted below, it would be preferrable to fund solely from PBIF to
enable the projects to commence with certainty, securing their overall funding
packages. This would also extend the potential leverage of UKSPF and other
funds to maximise the potential economic, social, and environmental impact.

Page 7

Town Centre Fund & PBIF Approved Projects - Spend to date              
Total
Grant
Award
TCF grant Total TCF 
spend
% TCF
spend to
date
PBIP grant
Total
PBIP
spend
% PBIP
spend to
date
Drummond
Arms, Crieff 940,000 600,000 600,000 100 340,000 163,192 48
Strathmore
Community
Hub 762,000 637,000 637,000 100 125,000 125,000 100
Loch Leven Car
Park 855,000 820,000 820,000 100 35,000 34,291 98
Perth Y Centre 25,000 25,000 25,000 100      
Crieff
Hotel/Creative
Crieff 100,000 100,000 100,000 100      
WiFi projects -
Comrie, Scone,
Kinross, Alyth,
Coupar Angus
80,000 50,000 50,000 100 30,000 27,988 93
Strathearn
Hotel, Crieff 265,000 265,000 252,000 95 0    
LFFN
broadband
project 200,000 200,000 200,000 100 0    
Letham Hub,
Perth 735,000       735,000 0 0
TOTAL  3,962,000 2,697,000 2,684,000  1,265,000 350,471

Page 8

5.3 The table below proposes projects where this year’s PBIP funding could be
allocated and notes opportunities for potential alignment with UKSPF funding
on the basis of current needs and requests for assistance: 
PROJECT PBIP FUNDING UKSPF potential
alignment
Rannoch Hub  £308k Yes
Aberfeldy Tourism Infrastructure  £275k Yes
Self-Catering Accommodation,
Cultybraggan Camp
£25k 
PLUS, Perth Civic Space,
Ropemakers Close
£20k 
Clachan and Quality Café  £470k 
TOTAL 1,098 
Rannoch Hub, Kinloch Rannoch 
5.4  Rannoch Community Trust are transforming the former Outdoor Centre in
Kinloch Rannoch into an exciting multi-use venue to serve at the heart of the
Rannoch Community. The building will be turned into a Community Hub and
social enterprise café/bar to provide free business and leisure facilities to the
socially isolated, remote community. It will be a self-sustaining community
owned initiative developing community wealth through creating local
employment and volunteering opportunities, whilst catering to the needs of
locals and visitors to the area. 
5.5 Estimated project costs are £830k. The project has secured funding from the
Scottish Land Fund and UK Community Ownership Fund as well as several
other external grant funders. The project requires funding of £308k to enable
project commencement in 2022/23. 
Aberfeldy Tourism Infrastructure, Aberfeldy 
5.6 Perth & Kinross Council, in partnership with Perth & Kinross Countryside
Trust, are creating the first in a series of low carbon, active travel and
outdoors leisure hubs created to support the River Tay Way. The hubs will be
accessible by all abilities and are designed to improve overall visitor
experience for residents, communities & leisure visitors. The first Hub will be
at Aberfeldy and will include the development of new toilet facilities open year-
round for the benefit and comfort of walking, cycling, wheeling, horse riding
and water sports visitors on the long-distance active travel route. The
Aberfeldy hub will also include waste disposal facilities for motorhome users
touring the area. The facility will be managed daily by the onsite outdoor
provider, creating local jobs, and supporting an established local business.
Through providing nodal facilities on the long-distance route, the project seeks
to ensure that the local community feels the economic benefits of tourism
whilst the impacts are mitigated.

Page 9

5.7 Estimated project costs are £512k. The project has already secured £235k 
through the Rural Tourism Infrastructure Fund. The project requires funding of 
£275k to enable the project to commence in 2022/23. 
Self-Catering Accommodation, Cultybraggan Camp, Comrie 
5.8 Comrie Development Trust’s project to develop four former POW Nissan huts
will create four additional self-catering visitor accommodation units at the
community owned Cultybraggan Camp. The project will enable more visitors
to stay in the Comrie area.  This will support the local economy and build
community wealth through contributing to the financial sustainability of Comrie
Development Trust to undertake local initiatives. 
5.9 Project estimated costs are £50,000 with £25,000 already secured from the 
Trust core funds. A contribution from PBIP of £25,000 would     
allow project commencement and completion during 2022/23. 
PLUS Perth, Civic Space, Ropemakers Close, Perth 
5.10 Local mental health and wellbeing charity PLUS Perth are creating an indoor
Civic Space within the city centre which will be open daily for local people
interested in art, film, music, dance, and other sociable pursuits. They have
recently taken ownership of the disused public toilet building in Ropemakers
Close and propose to renovate it. This will bring the building back into use and
improve the immediate surroundings - aligning with and delivering positive
impact towards the broader vennel improvement proposals throughout the
city. The project will tackle inequalities through creating cultural opportunities
and indirectly address antisocial behaviour, which will support the immediate
economy. 
5.11 Project estimated costs are £40,000 with £20,000 already secured from the
charity's core funding. A contribution from PBIP of £20,000 would allow project
commencement and completion in 2022/23. 
Clachan and Quality Café, Perth 
5.12 Dangerous buildings notices have been issued for the Clachan and Quality
Café in Perth, which require the owners to begin demolition by October 2022.
If this work is not done by the owners, statutory demolition and acquisition
powers are proposed to be used to ensure the essential works are undertaken
and a charging order placed on the properties. 
5.13 The initial estimated demolition and acquisition costs were £350k but these
are likely to increase, due to construction inflation and additional landscaping
costs, to around £500k.

Page 10

5.14 The eyesore building is having a damaging effect to the economic wellbeing of
surrounding businesses and creates a negative perception of the City Centre.
The site has limited development potential and assessment suggests there is
no commercially viable solution and public intervention is required. Estimated
costs and values also suggest that cost recovery will be challenging but may
assist negotiations on acquisition   The medium-term aspiration for the cleared
site will be to deliver public benefit through creation of greenspace or
potentially a mobility hub. 
5.15 Should the owners begin demolition by October 2022, the Council will not be
required to undertake the work. In this instance, reallocation of the proposed
funding to a project which meets the grant criteria of PBIP and can commence
in 2022/23 would be required. 
Future Years 
5.16 It is our intention to create a single application process which will be
developed to simplify the funding application process for community
organisations to apply for PBIP funding along with other national and local
Council funding.  This will bring together both revenue funding for project
development and project funding for viable projects.  This will create a more
robust project pipeline and maximising use of resources to support project
delivery. This will bring together both revenue funding for project development
and project funding for viable projects creating a more robust project pipeline
and maximise use of resources to support project delivery. This single
application process will be in place from April 2023. 
5.17 In some instances, it may be more appropriate for the Council itself to develop
and deliver capital projects supported by the wider community. For example,
the Council has given a commitment to deliver a project in Pitlochry at Atholl
Road in future years. Revenue support is required in the first instance to
develop designs and fully define project costs and funding requirements,
through collaboration with both the community and private landowners in line
with the Pitlochry Community Action Plan. 
5.18 The proposed process is aligned with the Perth & Kinross Offer to encourage
co-creation and co-design with communities to support project feasibility and
the development of a project pipeline.   
6. CONCLUSIONS 
6.1  The report summarises the satisfactory progress being made in the delivery of
previous Town Centre Fund / Place Based Investment Programme funded
projects and proposes five new projects to be funded from the Place Based
Investment Programme 2022/23 allocation. Each of the five new projects has
community support, has been identified as a priority for investment, meets the
criteria of the Place Based Investment Programme and can be progressed in
the current financial year should funding be allocated.

Page 11

Author
Name  Designation Contact Details
Karlene Doherty  Vacant Property
Development Officer
(01738) 475000
ComCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Barbara Renton  Executive Director
(Communities) 
12 September 2022 
APPENDICES 
None

Page 12

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce N/A
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  N/A
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 The proposals within the report will support the delivery of the Perth and
Kinross Community Plan in terms of the following priorities: - 
(iii) Promoting a prosperous, inclusive, and sustainable economy 
(v) Creating a safe and sustainable place for future generations. 
Corporate Plan 
1.2 The proposals within the report will support the delivery of the following
Council’s Corporate Plan priorities: - 
(iii) Promoting a prosperous, inclusive, and sustainable economy. 
(v) Creating a safe and sustainable place for future generations. 
2. Resource Implications 
Financial 
2.1 The Head of Finance has been consulted on the proposals and has indicated
agreement with the proposals.

Page 13

2.2  These proposals will be funded from a grant received from the Scottish
Government and as such should have no direct impact on our existing Capital
or Revenue budgets. 
Workforce 
2.3 There are no project specific workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.4 N/A. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups. Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.
3.2 The proposals have been considered under the Corporate Equalities
Impact Assessment process (EqIA) with the following outcome: (i) Assessed
as not relevant for the purposes of EqIA. 
3.2 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4  The proposals have been considered under the Act and no further action is
required as it does not qualify as a PPS as defined by the Act and is therefore
exempt. 
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council must discharge its duties in a way which contributes to the
achievement of sustainable development. Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets.

Page 14

• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
3.6 The proposals have been assessed against the Council’s Principles for
Sustainable Development and it is considered that all the proposals outlined
would support the achievement of sustainable development. 
Legal and Governance 
3.7 The Head of Legal and Governance Services has been consulted on the
report and has indicated agreement with the proposals. 
Risk 
3.8 The key risks associated with the proposals presented in the report relate to
our, and our delivery partners, abilities to implement approved projects within
the timescales required. If we are unable to do this, our grant funding will have
to be returned to the Scottish Government under the conditions of the grant
offer. 
4. Consultation 
Internal 
4.1 The Chief Operating Officer, the Head of Finance, and the Head of Legal and
Governance have been consulted in the preparation of this report. 
External 
4.2 No external parties have been consulted in the preparation of this report. 
5. Communication 
5.1 The agreed proposals will be communicated to all appropriate parties
including external organisations receiving Place Based Investment
Programme grant awards. 
2. BACKGROUND PAPERS 
Report No. 19/127 
Report No. 20/204 
Report No. 20/227
Report No. 21/149