Appendix 1
PERIODS OF COVER    2022 - 2023
Instructions on reporting times for Nightshift crews Sunday to Friday, early start crews
Monday to Friday and standby crews 7 days per week, will be issued by Roads
Maintenance Partnership Staff the previous day.
Period Standby
vehicles
available
(All changes
take place at
12 noon)
Total
Lead in period –
limited vehicles
on reduced cover
During all periods the road condition weather forecast is monitored and daily action plan devised.
During lead in/lead out periods it is not possible to treat all parts of the network and so available resources will be
deployed to best effect in relation to weather conditions being experienced
South North
Perth Kinross Crieff Blairgowrie Aberfeldy
17
October –
30
October
2022
3 1 1 3 3 11
31 Oct
2022
– 5
March
2023
6 2 3 6 5 22 Main standby
period – full cover
25 Nov
2022 –
24 Feb
2023
5 plus
1n/shift
1 plus 1
n/shift
2 plus 1
n/shift
5 plus 1
n/shift 5 22
Main standby
period – full cover
incl. nightshifts
25 Feb
2023
– 5
March
2023
6 2 3 6 5 22 Main standby
period – full cover
6 March
2023 –
26 March
2023
3 1 1 3 3 11
Lead out period -
limited vehicles
on reduced cover
27 March
2023 –
16 April
2023
0 1 1 1 1 4 Required roads
treated