Appendix 1
0L JN Improvement plan
Theme Ref. no. Activity Responsible Officer Timescale Comments
Notifications and
preparedness
1 Report to EI&ED on resource
requirements to support year-round
resilience.
Strategic Lead –
Environment &
Infrastructure
No later than
June 2024
Proposal being developed.
Various options being considered
and costed, in conjunction with
other inter-related actions
below.   
2 Officers to review and put in place
new minimum staffing/standby-levels
at command and operational levels to
ensure resources are available to
successfully co-ordinate and deploy
all flood defence measures within
timescales set within the to be
revised protocols (action 8 refers).
Roads Maintenance
Partnership Manager
By June 2024 As above, various options being
considered and costed, in
conjunction with other inter-
related actions.  Consideration
also being given to changing the
flood gate closure procedure,
and triggers
Incident Management,
Resourcing and
Response
3 Undertake further training in terms of
emergency planning across the wider
leadership team to ensure resilience
to deal with incidents
Strategic Lead –
Strategic Planning,
Policy & Resources 
By March
2024
Arrangements are being put in
place to provide both external
and internal training/awareness
sessions.  Currently liaising with
colleagues in Local Resilience
Partnership (LRP) regarding
further training for gold and
silver command officers. Crisis
management training being
investigated for all new Gold
Commanders 
4 The Council’s Out of Hours Standby
arrangements be reviewed to include
exploring the opportunities for
Strategic Lead –
Environment &
Infrastructure
By March
2024
To be undertaken in conjunction
with actions 2 and 7. Internal
discussions on-going regarding

Page 2

expanding the remit of staff from
other Council services.
what resources are currently
available across PKC and how
these can better
support/increase any response
to an emergency. 
5 Continue to work with current
Community Resilience Groups and
build on the success of these models,
reflecting that public agencies
including the Council are unable to
respond to all impacts across the
authority 
Strategic Lead –
Housing &
Communities
This is an
ongoing
action, which
is monitored
within the
service. 
Work has commenced to
develop a marketing campaign
to promote the creation of CRGs,
and the support available from
PKC.  For example, a meeting is
being held in Invergowrie in
January 2024.   A CRG Seminar is
to be arranged in Perth for
March 2024. 
New
action
Appropriate allocation of the
approved funding to communities to
support resilience in terms of both
training and equipment
(Scrutiny and Performance
Committee action)
Service Manager –
Community Resilience
and Emergency
Planning
By June 2024
Ongoing
As above. 
6 Review how the logging and sharing
of information between partner
agencies is undertaken, building upon
the conversations which have taken
place to date with SSE and SEPA
Strategic Lead –
Environment &
Infrastructure
By March
2024
Discussions have taken place
with SEPA and agreement
reached on new way forward,
and new operational protocols
have been agreed, which will
provide for better
communication and clarity. This
has now been used across a
number of weather events.

Page 3

SEPA to update their guidance
and copy to PKC for agreement. 
7 Undertake a review of the handling of
calls to the Out of Hours contact
centre, as well as a further review of
the Council’s out of hours customer
contact arrangements
Strategic Lead –
Environment &
Infrastructure 
Strategic Lead –
Customer & Digital
Services
By March
2024
Proposal being developed.
Various options being considered
and costed, in conjunction with
action 4 above.   
8 Review the Perth Flood Scheme Gate
Closure Operational Procedure
document with SEPA
Strategic Lead –
Environment &
Infrastructure
By June 2024 Various options being
considered, in conjunction with
action 2 above, to increase
resilience and community
reassurance whilst minimising
the need for additional stand-by
resources.  Gate closure triggers
being reviewed 
New
action
This review to include a clearer and
better tested ‘plan B’ for when
something does go wrong with a piece
of infrastructure
(Scrutiny and Performance Committee
action)
Strategic Lead –
Environment &
Infrastructure
By June 2024 Plan being developed which
creates less reliance on the use
of heavy equipment and the use
of alternative protection
measures. In progress, being led
by RMP manager and TC Head of
Operations. 
New
action
Develop a protocol to share
vulnerable people lists during
emergencies 
(Scrutiny and Performance Committee
action)
Service Manager –
Community Resilience
and Emergency
Planning
By June 2024 Officers are liaising with
colleagues in SSEN and the NHS
regarding the sharing of relevant
information.  The key issue being
data protection and GDPR.

Page 4

Impact and Recovery 9 Review of welfare response protocols
and engagement with those directly
impacted, including follow up with
affected individuals in Perth City and
Invergowrie.
Head of Environmental
& Consumer Services 
Senior Service Manager
Housing 
By 23
December
2023
A welfare response protocol has
been developed and was put in
place, which worked well during
the flooding event at the end of
December 2023. 
10 Establish formal feedback
mechanisms from community
resilience groups to take on board
learning and develop future response
arrangements
Strategic Lead –
Housing &
Communities
By March
2024
Feedback mechanisms are
currently in place, although a
formal debrief process/procotol
will be produced by officers.   
New
action
Invite representatives from SEPA, SSE
and SW to attend a future Scrutiny
and Performance Committee 
(Scrutiny and Performance Committee
action) 
Chief Executive By June 2024 The Executive Director
(Communities) is in contact with
partners about the available
committee dates.