PERTH AND KINROSS COUNCIL 
Scrutiny & Performance Committee 
25 January 2023 
PLANNING PERFORMANCE FRAMEWORK 11 (2021-22) 
Report by Head of Planning and Development
(Report No. 23/28) 
1. PURPOSE
1.1 This report relates to the Perth and Kinross Planning Performance Framework
11 (2021-22) (PPF11). A PPF is required to be submitted to the Scottish
Government annually. PPF11 (Appendix 1) provides an overview of
performance statistics and evidence of continuous improvement for the
Planning Service. The PPF was submitted to Government in September 2022
and is published on the Heads of Planning Scotland website: Planning
Performance Framework – HOPS (hopscotland.org.uk).   
1.2 Formal feedback on PPF11 was received from Tom Arthur, the Minister for
Public Finance, Planning & Community Wealth, on 22 December 2022
(Appendix 2) – a summary of which is set out in paragraphs 4.2 - 4.3 below. 
2. RECOMMENDATIONS
2.1  It is recommended that committee: 
i) scrutinises the appended Planning Performance Framework; 
ii) scrutinises the appended Minsterial feedback received; and 
iii) considers and makes suggestions in relation to case studies and service
improvements to be included in PPF12. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background/Main Issues 
• Section 5: Key Findings 
• Section 6: Conclusion 
• Appendices

Page 2

4. BACKGROUND / MAIN ISSUES 
4.1  The purpose of the Planning Performance Framework (PPF) is to show how
the Council as Planning Authority is working to be a high-quality planning
service: how it has performed against nationally agreed key indicators, and
what improvement actions will be taken. The PPF therefore looks back on the
previous year’s performance and forward in terms of future actions. 
4.2   Ministerial performance feedback received on 22 December 2022 notes the
challenges and highlights the importance of an appropriately resourced
planning system as key to improving performance. Nationally, the delivery of
improvement is to be assisted by the significant increase in planning
application fees implemented in April 2022, as well as increased fees for Local
Authorities in relation to applications made under the Electricity Act.  It also
recognises that resourcing requires a pipeline of knowledgeable and skilled
planners, as well as money, to delivering the ambitions of NPF4. In this
regard, the Future Planners Project led by Heads of Planning Scotland is seen
as important in easing the resourcing and skills challenges faced by planning
authorities.  Beyond this, the Minister also advises that work is progressing
on: introducing mandatory training for elected members on the planning
system; implementation of statutory annual reports by planning authorities;
and the appointment of a Planning Improvement Coordinator for Scotland.
Overall, the level of performance is seen as being testament to the hard work
and flexibility during challenging times and that good progress is being made. 
4.3 In terms of the Ministerial performance feedback related to Perth and Kinross,
of the 15 performance indicators, rated on a Red/Amber/Green basis, only two
are marked Amber, with the remaining thirteen being Green. This significant
level of green ratings (87%) against performance markers and none marked
as Red recognises the high level of performance within Perth and Kinross’s
Planning Services. The first Amber relates to planning application decision
making timelines, and notes that average decision timescales were slower
than the previous year – although remain faster than the Scottish average.
The second related to continuous improvement commitments, which had not
all been completed – although this reflects that a number are longer term
projects than the annual reporting cycle and as such requires a long-term
rating trend in feedback. Previously, the PPF was considered by the Planning
Policy, Practice and Performance Member Officer Working Group, however
this has not sat for some time now and this and future iterations of the PPF
will be presented to this Committee.  For information PPF10 (2020-21) and
previous versions are accessible via the link in para 1.1 and on the PKC
website: Planning Performance Framework - Perth & Kinross Council
(pkc.gov.uk).

Page 3

5. KEY FINDINGS 
5.1  PPF11 reflects on the period between 1 April 2021 and 31 March 2022 and
focuses on work adapting to new working arrangements, the digital
transformation programme, and the new legislative requirements for public
engagement. The case studies in Part 1 (pages 5-16) evidence this, providing
examples of what has been achieved and the quality of outcomes. This
includes ongoing spatial analysis of open space as part of the wider 20-minute
neighbourhood approach in the draft National Planning Framework 4 (NPF4);
the work undertaken in terms of active travel; and evidence gathering for
Local Place Plans. 
5.2  Part 2 of the submission provides information on how officers have addressed
previously identified service improvements and sets out further improvements
as a focus moving forward (pages 17-21). For 2022/23 and beyond, the
following have been identified: 
• Leadership & Management
• Customers & Stakeholders
• Digital
• Continuous Improvement
5.3  Part 3 & 4 of the document focuses on statistical information, evidencing the
Council’s performance against the National Headline Indicators and Scottish
Government Official Statistics (pages 22-29). It highlights progress being
made on LDP3 is in line with the Scottish Government timescales, with
evidence gathering underway and an engagement strategy being
programmed.   The PPF indicates that the Development Management function
is meeting overall targets, with a significant reduction in legacy cases
(planning applications not determined due to information needed from, or
actions by, the applicant). This was identified as an area for improvement
following feedback last year. The PPF acknowledges that due to the
significant turnover in staffing over the past year, with vacancies taking some
time to fill, that there has been a minor fall in performance. Part 5 (pages 30-
2) provides a snapshot of the staffing situation on 31 March 2022 and Part 6
(pages 33-4) provides information on Committee meetings. 
5.4  Part 7 (pages 35-42) sets out the performance markers that are used by the
Scottish Government to assess how the Council is meeting the required
targets. It summarises work being undertaken, makes linkages with the case
studies and what improvements have been made in the last year. Finally,
performance over the previous six years is captured on page 42. 
5.5 The Planning Performance Framework is designed to support improvement
locally and nationally.  The approach is consistent across all local authority
areas.  However, there may be local improvement actions which the
Committee may wish to see delivered.  As such the Committee may wish to
give consideration to case studies and improvements for PPF 12, along with
other, appropriate performance indicators.

Page 4

6. CONCLUSION   
6.1 The Planning Performance Framework has been submitted to update the
Committee on the performance of the Planning service for the period from
April 2021 to March 2022. It provides members with statistical information and
evidence of significant and continuous improvement across almost all
aspects. 
Author
Name  Designation Contact Details
Brenda Murray  Team Leader,
Development Plans
Team 
(01738) 475000
ComCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Barbara Renton  Executive Director
(Communities) 
18 January 2023 
APPENDICES 
• Appendix 1 – Planning Performance Framework 2021-22
• Appendix 2 – Ministerial Feedback Letter 22 December 2022

Page 5

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  None
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment None
Strategic Environmental Assessment None
Sustainability (community, economic, environmental) None
Legal and Governance  None
Risk None
Consultation 
Internal  No
External  No
Communication 
Communications Plan  None 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 The Planning Performance Framework contributes to the following Perth &
Kinross Community Plan / Single Outcome Agreement priorities: 
(ii) Developing educated, responsible and informed citizens
(iii) Promoting a prosperous, inclusive and sustainable economy
(iv) Supporting people to lead independent, healthy and active lives
(v) Creating a safe and sustainable place for future generations 
Corporate Plan 
1.2 The Development Plan contributes to the achievement of the following
Council’s Corporate Plan Priorities: 
(ii) Developing educated, responsible and informed citizens; 
(iii) Promoting a prosperous, inclusive and sustainable economy; 
(iv) Supporting people to lead independent, healthy and active lives; and 
(v) Creating a safe and sustainable place for future generations.

Page 6

2. Resource Implications 
Financial 
2.1 None. 
Workforce 
2.2 None. 
Asset Management (land, property, IT) 
2.3 None. 
3. Assessments 
Equality Impact Assessment 
3.1 None. 
Strategic Environmental Assessment 
3.2 None. 
Sustainability 
3.3 None. 
Legal and Governance 
3.4 None. 
Risk 
3.5 None. 
4. Consultation 
Internal 
4.1 The PPF is a collaborative document with input from throughout the Planning
Service. 
External 
4.2 None. 
5. Communication 
5.1 None.

Page 7

2. BACKGROUND PAPERS 
2.1 The following background papers were referred to during the preparation of
this report: 
• Planning Performance Framework 11 (2021-22);
• Ministerial Feedback Letter 22 December 2022.