Securing the future… • Improving services 
• Enhancing quality of life • Making the best use of public
resources 
Council Building
2 High Street
Perth
PH1 5PH 
12/12/2024 
A hybrid special meeting of the Scrutiny and Performance Committee will be held
in the Council Chamber on Wednesday, 18 December 2024 at 14:00. 
If you have any queries please contact Committee Services on (01738) 475000 or
email Committee@pkc.gov.uk. 
THOMAS GLEN
Chief Executive 
Those attending the meeting are requested to ensure that all notifications are
silent on their device and other devices are in silent mode. 
Please note that the meeting will be broadcast online and recorded.  The
recording will be publicly available on the Council’s website following the
meeting. 
Members:
Councillor Colin Stewart  (Convener)
Bailie Alasdair Bailey  (Vice-Convener)
Councillor Keith Allan
Councillor Steven Carr
Councillor Angus Forbes
Councillor Michelle Frampton
Councillor Ian Massie
Councillor Willie Robertson
Councillor Caroline Shiers
Councillor Frank Smith
Councillor Jack Welch
Page 1 of 32

Page 2

Page 2 of 32

Page 3

Scrutiny and Performance Committee 
Wednesday, 18 December 2024 
AGENDA 
MEMBERS ARE REMINDED OF THEIR OBLIGATION TO DECLARE ANY
FINANCIAL OR NON-FINANCIAL INTEREST WHICH THEY MAY HAVE IN ANY
ITEM ON THIS AGENDA IN ACCORDANCE WITH THE COUNCILLORS’ CODE
OF CONDUCT. 
1 WELCOME AND APOLOGIES   
2 DECLARATIONS OF INTEREST   
3 SCRUTINY REVIEW FINDINGS - RESPONSE TO SEVERE
WEATHER EVENTS OCTOBER 2023
Report by Strategic Lead - Legal and Governance (copy herewith
24/368) 
5 - 26 
4 ADDITIONAL SUPPORT NEEDS (ASN) REVIEW
Report by Strategic Lead - Legal and Governance (copy herewith
24/369) 
27 - 32 
Page 3 of 32

Page 4

Page 4 of 32

Page 5

Perth And Kinross Council 
Scrutiny And Performance Committee 
18 December 2024 
SCRUTINY REVIEW FINDINGS 
RESPONSE TO SEVERE WEATHER EVENTS OCTOBER 2023 
Report by Strategic Lead – Legal and Governance
(Report No. 24/368) 
1. PURPOSE 
1.1 The purpose of this report is to present the findings of the review by the
Scrutiny and Performance Committee in relation to the Council’s response to
the severe weather events in October 2023. It also seeks to provide
assurance in terms of lessons learned and the implementation of
improvement actions to ensure that the Council is equipped to respond
effectively to future weather events. 
2. STRUCTURE OF REPORT 
Section 2 – report structure
Section 3 – Key findings
Section 4 – Scope of the review
Section 5 – Review process
Section 6 – Context / Main Issues
Section 7 – Findings 
Section 8 – Conclusion & recommendations
Appendix 1 – Improvement action summary
Appendix 2 - Summary of relevant reports and communications
Appendix 3 – Roles and Responsibilities
3. KEY FINDINGS (ASSURANCE) 
(i) The Perth Flood Prevention Scheme (PFPS) has served Perth and Kinross
Council well since its inception. The Scheme together with the associated
operating model remains effective and fit for purpose 
(ii) The quality of the performance and decision-making in response to the
extreme weather event of 6th-8Th October 2023 (in particular the decision
in relation to the closure of floodgates) was impacted by a lack of
resources; whilst illustrating areas for improvement, the response was not
indicative of a systemic failure of the PFPS or associated operating model. 
3
Page 5 of 32

Page 6

(iii) The performance and decision-making in response to the subsequent
Storm Babet and the severe weather events of 27th-29th October 2023 and
27th December 2023 was appropriate and effective; demonstrating that the
operating model in place for managing emergencies (including weather
events) is adequate and robust. 
(iv) The lessons learned from the operational response to the extreme weather
event of 6th-8th October 2023 and the scrutiny process have resulted in the
implementation of several improvement actions (see Appendix 1) 
(v) These improvements are reflected in the new “year-round” approach to
weather incident management and response as set out in the report
(24/217) approved by the Climate Change and Sustainability Committee
on 21 August 2024. This approach will ensure that there are, to the best of
our planning  abilities,  adequate resources and expertise available to
respond to any future events. 
(vi) Community Resilience Groups played and will continue to play a crucial
role in supporting the Council to respond to severe weather events. 
(vii) Prior to the October weather events there were approximately 10 active
Community Resilience Groups. Since then, officers have been working to
empower communities to create and build resilience within their local area.
The Committee is delighted to note that the number of Community
Resilience Groups across Perth and Kinross has risen to 56, which is a
tremendous achievement and testament to our communities. It is
important that all localities are encouraged and supported to form their
own Groups so that together we can build the capacity to respond and
protect our communities across the whole area. 
(viii) More general facts and findings which are set out in section below 7
below. 
(ix) The issue of liability is one to be determined by the Council’s insurers and
therefore does not form part of the Findings of this review. 
4. SCOPE OF THE REVIEW  
4.1 The scope of this Review has been shaped by: 
• issues identified by officers as part of routine internal review process
following a major event/incident;
• concerns expressed by individuals and businesses at the public meeting
in the Civic Hall on 15th November 2023 following the extreme weather
event experienced on the weekend of 6-8th October;
• deputations made to the Scrutiny and Performance Committee on 22
November 2023;
Page 6 of 32

Page 7

• feedback/questions from  elected members; and 
• specific issues identified by  or referred to the Scrutiny and Performance
Committee. 
4.2 Whilst the main focus of the public and press attention has been on the
extreme weather event of the 6-8th October 2023, Perth and Kinross
experienced two further severe weather events in October; 
• 18th-21st October 023 (Storm Babet)
• 27th-29th October 2023
The Scrutiny and Performance Committee also considered the Council’s
response to the weather event on 27th December, given that occurred during
the festive closedown period, for completeness. 
4.3 The Review has therefore considered the Council’s preparedness and
response to those events, in terms of evidence of lessons learned from the 6-
8th October 2023 and subsequent events and to seek assurance as to the
robustness of the Council processes, controls and capacity to respond
effectively to future severe weather events. 
4.4 The areas of focus for the review are summarised as follows: 
(i) General preparedness for dealing with severe weather events; adequacy
of Council systems and procedures
(ii) Partnership working and data sharing with reference to SEPA, Scottish
Water and SSE Renewables
(iii) Incident management, resourcing and response to the extreme weather
event of 6-8th October including timing and decision making in relation to
flood gate closures
(iv) Lessons learned from October 2023 weather events
(v) Improvement action and assurance
4.5 At the public meeting on 15th November 2023 and subsequently, residents
and businesses have also raised the issue of insurance and liability for
damage to properties that may have been impacted by the late closure of
some flood gates. 
The Committee has been advised and is satisfied that  the issue of
liability is one to be determined by the Council’s insurers and therefore
does not form part of the Findings of this review. 
4.6 The Council has acknowledged in the report to Scrutiny and Performance
Committee in November 2023 (23/323) that the delay in closing the floodgate
on the North Inch may have been a contributory factor to the extent of the
flooding experienced by a small number of the properties. 
Page 7 of 32

Page 8

4.7 All claims for damage to property have been managed entirely through the
Council’s insurers and their respective solicitors; no claims have been
assessed or processed directly by the Council. 
4.8 The Scrutiny and Performance Committee understand that Council’s insurers
have carried out their own independent assessment to determine what, if any,
impact the delay in closing the gates had on each of the affected properties.
We understand that the insurers have accepted that the failure to close
floodgates likely impacted the extent of  the flood damage experienced in
relation to  a small number of  the total properties affected; and that settlement
offers have already been or are due to be made. 
4.9 The Scrutiny Review can make no further comment on the matter of liability.
5. REVIEW PROCESS 
5.1 The Scrutiny Review process has been one of active listening, data gathering,
assessment and analysis. Members of the Committee have considered and
critically assessed information and reports presented by officers, partner
agencies, members of the public and other elected members. All elected
members have also been given the opportunity to site visit the Perth Flood
Prevention Scheme to better understand how it operates. 
5.2 
Chronology Doc links
6-8th Oct 2023  Extreme weather event 
18th-21st Oct
2023 
Storm Babet   
27th-29th Oct
2023
Severe weather event 
15th Nov 2023 Public Meeting with affected
residents and businesses 
22nd Nov 2023   Special Meeting of Scrutiny &
Performance Committee – review
of weather events
Report 22 November 2023 
Appendix 1 - Incident
Planning - Standby
Arrangements   
Appendix 2 - Improvement
Plan 
Appendix 3 - Flood Gate
Location Map 
Minute of Meeting of
Scrutiny and Performance
Committee 22 November
2023   
27 Dec 2023 Severe weather event 
Page 8 of 32

Page 9

31 Jan 2024 Scrutiny and Performance
Committee - update
Update report 31 January
2024 
Appendix 1 - Improvement
Plan   
Minute of Meeting of the
Scrutiny and Performance
Committee of 31 January
2024 
24 April 2024 Scrutiny and Performance
Committee- weather events –
improvement plan
Weather Events -
Improvement Plan   
Minute of Meeting of the
Scrutiny and Performance
Committee of 24 April
2024   
22 May 2024 Site visit to Flood Prevention
Scheme – all member visit 
12 June 2024 Scrutiny and Performance
Committee-
Overview of improvement activity
Extreme Weather Events
Review - Overview of
Activity   
Minute of Meeting of the
Scrutiny and Performance
Committee of 12 June
2024    
9 August 2024 Scrutiny Review Q&A with SEPA 
21 Aug 2024 Climate Change & Sustainability
Committee – All year weather
event response
Year-Round Weather Event
Response
Appendix 1 - Civil
Contingencies Act
Appendix 2 - Partner
Agencies          Appendix 3 -
Flooding Contingency
Systems                                                       
Appendix 4 - Alignment with
Extreme Weather Events
Review Improvement Plan    
Appendix 5 - Council
Response Examples Roads
Maintenance Partnership
Appendix 6 - Council
Response Examples -
Flooding
Page 9 of 32

Page 10

Minute of Meeting of the
Climate Change and
Sustainability Committee of
21 August 2024
28 Aug 2024 Economy and Infrastructure
Committee
-Road Gully Cleansing 
Road Gully Cleansing
Appendix 1 - Previous
Cleanse Monitor Outputs
Appendix 2 - Cleanse
Monitor 2023
Appendix 3 - Visual
Representation 
Minute of Meeting of the
Economy and Infrastructure
Committee of 28 August
2024
12 Sept 2024 Scrutiny Review Q&A with:
Scottish Water
SSE Renewables 
18 Sept 2024 Scrutiny and Performance
Committee – partner presentations
Presentation - SEPA 
Home | Scottish
Environment Protection
Agency (SEPA) 
Presentation - SSE
Renewables  
A Better World of Energy |
SSE Renewables 
Presentation - Scottish
Water 
Home - Scottish Water 
Minute of Meeting of the
Scrutiny and Performance
Committee of 18 September
2024 
6th Nov2024 Scrutiny Review – Workshop to
consider findings and agree and
further recommendations 
Page 10 of 32

Page 11

6. CONTEXT/ MAIN ISSUES 
6.1 Perth and Kinross experienced three severe weather events during October
2023:
• 6th-8th October; 
• 18th- - 21st October (Storm Babet); and 
• 27th-29th October. 
A further severe weather event occurred on 27th December 2023 
6.2 The extreme event of the 6th-8th October highlighted issues as regards the
Council’s resources and preparedness which in turn raised concerns as
regards our ability to respond effectively to future weather events. 
6.3 Elected Members, with the full support of the Chief Executive, asked that
Scrutiny and Performance Committee carry out a review to consider the
response and decision-making with particular reference to 6th-8th October
event. The purpose being to review the adequacy and effectiveness of the
systems and processes in place and to identify and monitor implementation of
any improvement actions. 
6.4 The Council has long-standing and effective processes for managing civil
contingencies, emergency planning, and business continuity. These
processes include a concurrent risk approach, which considers the possibility
of multiple incidents occurring simultaneously. This approach covers
scenarios such as severe weather, power outages, civil unrest, and cyber-
attacks. 
6.5 Outwith normal working hours, the Council has an emergency duty rota in
place which operates 365 days a year, 7 days per week and 24 hours per day.
A pager service is operated out with working hours and covered by a team of
5 Emergency Response Duty Officers (ERDOs).  A number of Council staff
from across the organisation are part of a rota which is the first point of call,
via a dedicated pager number, to ensure rapid activation of the Council’s
response protocols as required. Members of the Executive Leadership Team
are on a rota ready to respond 24 hours a day, 365 days a year to lead the
Council response to an emergency if required. To ensure resilience in terms
of senior strategic leadership for emergencies and incidents, all Strategic
Leads are undertaking the necessary training and will be included on this rota
going forward. This is in addition to the Council’s normal out of hours services
for individual and routine incidents. 
6.6 The Council’s internal arrangements are also supplemented by long-
established relationships and formal arrangements through the Tayside Local
Resilience Partnership, with partner agencies including Police Scotland,
Scottish Fire and Rescue Services (SFRS), SEPA, Scottish Water, NHS
Tayside as well as Dundee and Angus Councils. Resilience is also supported
by strong and effective relationships with Community Resilience Groups
(CRGs), made up of local volunteers prepared to support their local area
during emergency situations, including weather.
Page 11 of 32

Page 12

6.7 In terms of severe weather planning Perth and Kinross Council have
traditionally focussed on winter weather risks and therefore operated a Winter
Maintenance Policy deploying increased “on call” resources to ensure
appropriate staffing for winter weather incidents. This was in place from the 3rd
week in October throughout the winter period. 
6.8 The extreme weather incident on 6th -8th October 2023 occurred at the start of
the October School holidays and mid-way during the school holidays of our
neighbouring Tayside Councils. It was also just before the Winter
Maintenance Policy was due to be applied (from which point, holidays were
ordinarily curtailed in relation to trained operatives, to ensure optimal cover
arrangements during the winter period). The timing therefore had a significant
impact in terms of available staff resources given the scale and intensity of the
weather event. 
7. GENERAL FACTS/FINDINGS 
7.1 The Perth and Kinross Council area is highly susceptible to (and has a long
history of) flooding from the River Tay. To help manage this risk, the Council
has had a Flood Prevention Scheme (so named as the governing legislation
at the time was the Flood Prevention Act 1961) since 2001. 
7.2 The Perth Flood Prevention Scheme (PFPS) does not and cannot prevent
flooding. Its purpose is to help mitigate the impact of flooding from the River
Tay. This has been recognised within the current legislative framework which
now refers, more appropriately, to Flood Protection Schemes. 
7.3 The Scheme is managed on behalf of the Council by the Roads Maintenance
Partnership (RMP). Within the PFPS there are 77 floodgates/barriers (79 if
you include 2 special gates at Queens Bridge and the Promontory at Tay
Street); of which 10 flood gates (barriers) are permanently closed and a
further 10 are closed seasonally from October through to the end of March. 
7.4 The Perth Flood Protection Scheme Operating Manual sets out the specific
processes for the operation of the flood gates /barriers and the “triggers” for
closure. Within the Scheme there are 12 gate closure plans to deal with
varying levels of flooding risk. 
7.5 As the section of the River Tay flowing through Perth is affected by both fluvial
flow and tides, the gate closure protocols are based on a set of parameters
using flow and tide including surge) data supplied by Scottish Environmental
Protection Agency (SEPA). 
7.6 SEPA play an integral role in the Perth Flood Protection Scheme. Recognising
the particular challenges and flood risks in the area, SEPA supply not only
flow and tide data, but they also provide specific warning services to PKC
which are set out in the Scheme Operating Manual. 
Page 12 of 32

Page 13

7.7 There is no direct correlation between SEPA flood warnings and Met Office
weather warnings. Flood gate closure protocols are not therefore triggered by
the issuing of specific weather warnings (with the exception of the barriers at
the South Inch which due to the level of flooding risk posed by surface water
(not from the River itself), gates are closed on the issue of a Met Office Yellow
weather warning as a precaution). 
7.8 SEPA are the ‘warn and inform’ agency for Scotland in terms of providing the
Scottish Flood Forecasting Service (in partnership with the Met Office). This
uses a network of over 250 rainfall, river and coastal monitoring stations
across Scotland to generate data 24 hours a day. When this data is combined
with meteorological data from the Met Office, it is used to produce the
predictions of river, coastal and surface water flooding. These predictions are
communicated to the Council and other organisations via the national Flood
Guidance Statement, and ultimately via the Flood Alerts, Warnings and
Severe Warnings to specific areas. 
7.9 The weather event experienced from the 6th -8th October 2023 was extreme
and unexpected; with the Met Office only issuing an Amber warning for heavy
rain on the 6th of October itself. Similarly in the week leading up to the 6th of
October the daily Flood Guidance Statement via SEPA’s Scottish Flood
Forecasting Service had the risk as very low/low/low for the 6th, 7th and 8th
October, respectively. 
7.10 It was not until the 6th of October itself that the risk level elevated to very low/
medium/ medium respectively for these three days. At that point incident
management preparations were commenced. Unfortunately, this weekend
was the start/mid-way point of the October Schools holidays across Tayside
and prior to the implementation of the Council’s Winter Maintenance Plan
(during which leave is restricted). Several staff who would normally manage
such incidents were therefore on leave and some were out of the country on
holidays. Despite a considerable number of staff from within the Council’s
Parking & Civil Contingencies Team and the Roads Maintenance Partnership
coming in off their holidays or volunteering to provide additional cover to
support the response, the scale and intensity of the weather event was such
that there was inadequate staffing capacity to deal with the prolonged
incident. 
7.11 Those resource pressures led to the operational decision being taken not to
close certain floodgates. The decision was a pragmatic risk-based decision
taking into account the data from SEPA available at that time and assessment
of the situation on the ground. With the benefit of hindsight, in relation to the
floodgates on the North Inch, this was the wrong decision and (as
acknowledged in the initial report to Scrutiny and Performance Committee in
November 2023) may likely have contributed to the degree of flood damage
sustained by a small number of the total properties affected. 
Page 13 of 32

Page 14

7.12 The new “Year-Round” Weather Event Response which was approved by the
Climate Change and Sustainability Committee in August recognises that,
given the changing weather patterns, flooding presents the most likely year-
round risk. Based on the learning from the extreme event of the 6th-8th
October 2023: 
• Warning and trigger levels form the have been reviewed and remain
appropriate
• Council owned telemetry and site alarms and triggers have been
reviewed
• Floodgates within the PFPS have been assessed to consider the viability
of automation, which is not deemed a practical or cost effective solution
• lightweight contingency flood barriers in two different types (Boxwall and
Watergate) have been purchased and can be deployed at different
locations.
• Officers are still working to identify appropriate lightweight barriers
systems to replace the heavy Promontory and Queens Bridges systems 
7.13 On the particular issue of staffing resource: 
• Parking and Civil Contingencies officers and Community wardens are
now trained and can assist with gate closures if required and provide
support on the ground
• During their Monday- Sunday working hours, Waste and greenspace
operatives will also be redirected to assist with clearance of trash
screens 
7.14 In the course of this review, concerns have been expressed about the quality
of the data shared with the Council by SEPA which in turn influenced the
decision not to close the floodgates; with speculation that the dramatic
increase in the flow rate reported by SEPA in the early hours of the 7th
October data during may have been due to water “being released” from
Pitlochry dam by SSE Renewables. From engagement with SSE Renewables
the Review obtained a better understanding as to the dam operations and
learned that the dam is designed to release water when it reaches a certain
level. No human decision-making or intervention is involved in this process.
Whilst SSE Renewables are not a Category 2 Responder in terms of the Civil
Contingencies Act (2004) they do provide data to SEPA to support them in
their duty to “Warn and Inform”. The Committee understands that amongst the
partners, the general consensus is that the weather system remained across
Perth for many hours longer than anticipated based on Met Office data that
was available to them. This in turn impacted upon the assumptions feeding
the data provided by SEPA and guiding operations on the ground. 
7.15 Flooding is complex, with impacts arising from various water sources. Each
flood is unique: some stem from rivers, others from extreme rainfall causing
runoff and overwhelming drainage systems, and some are a mix of both. In
Perth, the River Tay poses a significant flood risk to nearby properties.
Page 14 of 32

Page 15

However, properties not directly affected by the Tay can still experience
flooding if drainage systems back up when river levels are high. This can
cause water to surface at road gullies, manholes, or inside properties. In some
cases, for example Bells Sports Centre, there is the  risk of flooding from the
river due to its location, but it is also prone to flooding due to drainage
infrastructure. Since 2017 Bells Sports Centre  has suffered five  notable flood
events with varying degrees of impact, where with the exception of the
October 2023 event, the appropriate deployment of floodgates has not been in
question. 
7.16 The PFPS primarily reduces direct flooding from the Tay, but rainfall can still
cause flooding behind the PFPS. This is due to the fact that higher than usual
water levels in the Tay (even when it is not flooding itself) can limit discharge
from surface water sewers or extreme weather events exceeding the
capability of the surface water drainage systems to convey water away.
Property owners should consider Property Flood Resilience measures like
non-return valves and flood gates to mitigate this risk. 
7.17 Scottish Water informed the Scrutiny and Performance Committee that local
drainage and sewerage infrastructure, like the rest of the country, was not
designed for the increasing volume of severe wet weather events. Their
design standards differ from the Council's, with Scottish Water following the
'Sewers for Scotland v4' document and the Council adhering to the 'Delivering
Sustainable Flood Risk Management' Guidance 2019. Scottish Water is
investing in upgrading sewers and Waste Water Treatment Works, but this
investment alone cannot solve the national infrastructure problem. The Super
Sewer upgrade on Tay Street and Shore Road introduces additional
sewerage conveyance capacity that may relieve a small amount of localised
flooding from sewers but is focussed on supporting the city’s continuing
growth and reducing the number of properties affected by backing up of the
Scottish Water drainage systems. It is not expected to have capacity to take
flood waters from the River Tay. 
7.18 The weather event of the 6th-8th October 2023 also raised concerns as
regards the Council’s response to calls for assistance. The Council contracts
with Aberdeen City Council Customer Contact Centre to support the operation
of emergency contact lines for roads, flooding and housing repairs. In line with
the agreed process, Aberdeen City were contacted on 6 October to request
that they arranged additional resources to support the answering of calls from
Perth and Kinross given the amber weather warning. 
7.19 Over the 7th-8th October, Aberdeen Council Customer Contact Service
(ACCCS) received 615 calls made to PKC out of hours numbers (many of
which would have been repeat calls). ACCC responded to 257 calls of which
145 were to housing repairs reporting low-level weather-related leaks. As
there were several severe weather events occurring in different parts of the
country, the volume of calls impacted upon the ability of ACCCS to respond. 
7.20 It is recognised however that it would be impossible to resource a contact
centre to be able to immediately respond to every call placed during severe
Page 15 of 32

Page 16

weather event or indeed any other emergency. Instead, more proactive work
will be done to issue information to the public via other channels and to
support the public to only use the out of hours numbers for emergencies (as
opposed to reporting an issue or simply seeking advice). This will enable the
ACCCS to direct their resources where they are most needed. 
7.21 The Council’s response to Storm Babet (18th-21st October) and the severe
event of 27th-29th October 2023 was in line with agreed operating protocols
and was robust and effective. No specific improvement actions were identified
as a result of the Council’s response to those events. 
7.22 A query was also raised as to whether some assurance could be given
regarding the flooding in Invergowrie as a result of the Balruddery Burn
embankment/causeway failure. The Committee are advised that the failure of
the earth embankment/ causeway increased the extent and severity of
flooding both locally and in the downstream catchment area which includes
Invergowrie. 
7.23 The earth embankment in question, sat within Angus Council’s administrative
area. The Committee are advised that Angus Council have contacted the
landowner who has confirmed that there are no plans to reinstate the
embankment /causeway. Furthermore, any such structure would likely require
a licence from SEPA under The Water Environment (Controlled Activities)
(Scotland) Regulations 2011. 
7.24 Officers cannot advise the Committee to what degree Invergowrie or other
areas would have been flooded had the embankment not existed. This is
however something which residents’ insurers will be looking to determine
when processing claim for damage to property.  From an assurance
perspective however, Officers are satisfied that that the significant threat
came from the fact that floodwater was able to build up behind the earth
embankment which then gave way, releasing a significant volume of water
into the Balruddery Burn in a short period of time. In the absence of that
structure being reinstated, the risk of that same situation occurring in the
future is minimal/nil. 
7.25 The weather events experienced throughout October 2023 also highlighted an
issue regarding communication and connectivity with our more rural
communities. The Committee accepts that this is not something within the
direct control of the Council and that the responsibility for addressing this
issue sits with the relevant mobile network operators. 
8. CONCLUSION AND RECOMMENDATIONS 
8.1 The Committee firmly put on record their thanks to all those residents and
community resilience groups who respond to severe weather events, and to
all residents and communities who step up to help their neighbours in time of
need. 
Page 16 of 32

Page 17

8.2 The Scrutiny and Performance Committee wish to thank officers, residents
and representatives from local businesses, SEPA, Scottish Water, SSE
Renewables and other elected members for their input into this review
process. 
8.3 The Council’s response to the Storm Babet (18th -21st October 2023) and to
the severe weather events of 27th-29th October 2023 and 27th December
2023 was robust and effective. 
8.4 As has already been acknowledged publicly by both the Chief Executive and
the then Executive Director for Communities in their capacity as Incident Gold
Commander for that event, with hindsight, the decision not to close the
floodgates as per the protocol was the wrong decision.  The Committee
acknowledges the resource pressures experienced that weekend and accepts
that officers took a risk-based decision, taking into account the data available
to them at the time, their professional knowledge and experience and an
assessment of the situation on the ground. Nonetheless the Committee
agrees that the decision not to close the floodgates was, with hindsight, the
wrong decision. 
8.5 In terms of assurance however the Committee are satisfied based on the
response to subsequent severe weather events. That the Council’s response
to the extreme weather event of the 6th- 8th October was anomalous and not
indicative of systemic failure of either the Perth Flood Prevention Scheme and
the associated operating procedures, or of the Council’s operating model for
management of incidents and emergencies. 
8.6 The Committee are satisfied that, whilst unfortunate, inadequate staffing
resources over that weekend and the unexpected severity of the weather
event undermined the quality of our response on that occasion. 
8.7 The Committee are pleased to note that lessons have been learned from the
6th-8th October event and that the opportunity has been taken to review and
refine operating arrangements for the management of severe weather events.
In particular it welcomes: 
i. The strengthening of the partnership working and data sharing between
the Council, SEPA, Scottish Water and SSE Renewables 
ii. The development of a Year-Round Weather Response Plan which was
designed to address the changing weather patterns but will also ensure
that the Council is adequately resourced to respond effectively to
weather events regardless of when the occur.
iii. The establishment of 46 new Community Resilience Groups
iv. The additional incident management/emergency response leadership
capacity at senior level
v. 
Page 17 of 32

Page 18

8.8 Further recommendations: 
i. Whilst the issue of poor/no mobile phone connectivity in certain parts of
the Council areas is not something within the direct control or influence
of the Council, officers are asked to continue to engage with mobile
network operators to try to identify a solution. 
ii. Acknowledging the £175k which the Council’s Finance and Resources
Committee has put into reserves to support the establishment of
Community Resilience Groups, officers are asked to continue working
with communities to establish new groups across all Council areas. 
Authored on behalf of the Scrutiny and Performance Committee 
Name Designation Contact Details  
Lisa Simpson   Strategic Lead – Legal &
Governance Services  
legalservices@pkc.gov.uk   
Page 18 of 32

Page 19

Theme Ref no
Activity Responsible Officer Timescale Comments
(S&P 31/01/2024)
Comments
(03/12/2024)
Notification and
Preparedness
IP_1
Report to EI&ED on resource requirements to support year-round
resilience.
Strategic Lead – Environment &
Infrastructure
No later than June 2024 Proposal being developed.
Various options being considered and costed, in
conjunction with other inter-related actions below.
Year Round Weather Event Response presented at Climate Change &
Sustainability Committee (21 August 2024) - ITEM 6 -
https://perth-and-kinross.cmis.uk.com/perth-and-
kinross/Meetings/tabid/70/ctl/ViewMeetingPublic/mid/397/Meeting/3755/Co
mmittee/136/Default.aspx
Road Gully Cleansing paper presented at Economy & Infrastructure
Committee (28 August 2024) - ITEM 5 -
https://perth-and-kinross.cmis.uk.com/perth-and-
kinross/Meetings/tabid/70/ctl/ViewMeetingPublic/mid/397/Meeting/3996/Co
mmittee/150/Default.aspx
ITEM CLOSED
IP_2
Officers to review and put in place new minimum staffing/standby-
levels at command and operational levels to ensure resources are
available to successfully co-ordinate and deploy all flood defence
measures within timescales set within the to be revised protocols
(action 8 refers).
Roads Maintenance Partnership Manager By June 2024 As above, various options being considered and costed,
in conjunction with other inter related actions.
Consideration also being given to changing the flood gate
closure procedure, and triggers.
Year Round Weather Event Response presented at Climate Change &
Sustainability Committee (21 August 2024) - ITEM 6 -
https://perth-and-kinross.cmis.uk.com/perth-and-
kinross/Meetings/tabid/70/ctl/ViewMeetingPublic/mid/397/Meeting/3755/Co
mmittee/136/Default.aspx                                                                                                                                                                                                                                                             
ITEM CLOSED
Incident Management,
Resourcing and Response
IP_3
Undertake further training in terms of emergency planning across the
wider leadership team to ensure resilience to deal with incidents
Strategic Lead – Strategic Planning,
Policy & Resources
By March 2024 Arrangements are being put in place to provide both
external and internal training/awareness sessions.
Currently liaising with colleagues in Local Resilience
Partnership (LRP) regarding further training for gold and
silver command officers. Crisis management training
being investigated for all new Gold Commanders.
Strategic Leadership in a Crisis (SLIC) training has been deliverd to 8 out of 14
SLs with a further session on 6 Jan for 4 more.  Remaining 2 SLs will be trained
in Feb 2025.
ONGOING
Incident Management,
Resourcing and Response
IP_4
The Council’s Out of Hours Standby arrangements be reviewed to
include exploring the opportunities for expanding the remit of staff
from other Council services.
Strategic Lead – Environment &
Infrastructure
By March 2024 To be undertaken in conjunction with actions 2 and 7.
Internal discussions on-going regarding what resources
are currently available across PKC and how these can
better support/increase any response to an emergency.
Parking & Civil Contingencies resources trained / being trained to assist with
PFPS and Almondbank gate operation as required.
ONGOING
Incident Management,
Resourcing and Response
IP_5
Continue to work with current Community Resilience Groups and
build on the success of these models, reflecting that public agencies
including the Council are unable to respond to all impacts across the
authority.
Strategic Lead – Housing & Communities This is an ongoing action,
which is monitored within
the service.
Work has commenced to develop a marketing campaign
to promote the creation of CRGs, and the support
available from PKC. For example, a meeting is being held
in Invergowrie in January 2024. A CRG Seminar is to be
arranged in Perth for March 2024.
Word of mouth between Communiy Resilience Groups and interested
communities is driving unprecedented demand for engagement.  We are
sitting at 63 CRGs across P&K of varying sizes and portfolios and servicing this
demand is our current priority.   Once we have fuly supported all those groups
coming forward we plan to dig into harder to reach communities and the
marketting campaign and seminar will be part of that second push.
ONGOING
Incident Management,
Resourcing and Response
IP_5b
Appropriate allocation of the approved funding to communities to
support resilience in terms of both training and equipment (Scrutiny
and Performance Committee action)
Service Manager – Community Resilience
and Emergency Planning
By June 2024
Ongoing
As above. ONGOING
Incident Management,
Resourcing and Response
IP_6
Review how the logging and sharing of information between partner
agencies is undertaken, building upon the conversations which have
taken place to date with SSE and SEPA
Strategic Lead – Environment &
Infrastructure
By March 2024 Discussions have taken place with SEPA and agreement
reached on new way forward, and new operational
protocols have been agreed, which will provide for better
communication and clarity. This has now been used
across a number of weather events.
SEPA to update their guidance and copy to PKC for
agreement.
ITEM CLOSED
Improvement Plan Tasks
3
Page 19 of 32

Page 20

Incident Management,
Resourcing and Response
IP_7
Undertake a review of the handling of calls to the Out of Hours contact
centre, as well as a further review of the Council’s out of hours
customer contact arrangements.
Strategic Lead – Environment &
Infrastructure
Strategic Lead - Customer & Digital
Services
By March 2024 Proposal being developed.
Various options being considered and costed, in
conjunction with action 4 above.
Procedures for opening the Roads and/or Housing Repairs Out of Hours line
overflow are now in place, predicated on officers always activating the
additional resources at Aberdeen City Council in the first instance to deal with
the call volumes involved.
ITEM CLOSED
Incident Management,
Resourcing and Response
IP_8
Review the Perth Flood Scheme Gate Closure Operational Procedure
document with SEPA.
Strategic Lead – Environment &
Infrastructure
By June 2024 Various options being considered, in conjunction with
action 2 above, to increase resilience and community
reassurance whilst minimising the need for additional
stand-by resources. Gate closure triggers being
reviewed.
Structures team also to provide form of words with their requirements with
regard to closing and opening of Tay Viewing platform and Queens Bridge in
due course to inform review.
ONGOING
Incident Management,
Resourcing and Response
IP_8b
This review to include a clearer and better tested ‘plan B’ for when
something does go wrong with a piece of infrastructure (Scrutiny and
Performance Committee action)
Strategic Lead – Environment &
Infrastructure
By June 2024 Plan being developed which creates less reliance on the
use of heavy equipment and the use of alternative
protection measures. In progress, being led by RMP
manager and TC Head of Operations.
ONGOING
Incident Management,
Resourcing and Response
IP_8c
Develop a protocol to share vulnerable people lists during
emergencies (Scrutiny and Performance Committee action)
Service Manager – Community Resilience
and Emergency Planning
By June 2024 Officers are liaising with colleagues in SSEN and the NHS
regarding the sharing of relevant information. The key
issue being data protection and GDPR.
Progress is being made with the sharing of data with Angus Council being used
as a test ground.   If the pilot is successful then we anticipate roll out by the
end of the financial year.
ONGOING
Impact and Recovery
IP_9
Review of welfare response protocols and engagement with those
directly impacted, including follow up with affected individuals in
Perth City and Invergowrie.
Head of Environmental & Consumer
Services
Senior Service Manager - Housing
By 23 December 2023 A welfare response protocol has been developed and
was put in place, which worked well during the flooding
event at the end of December 2023.
Welfare Engagement Protocol: https://perth-and-kinross.cmis.uk.com/perth-
and-
kinross/Document.ashx?czJKcaeAi5tUFL1DTL2UE4zNRBcoShgo=M01FqNO8t
tcuV7zCbdPk3nsFRQY%2fN9ixlaHlWVVcFivgccRUzevkhA%3d%3d&rUzwRPf
%2bZ3zd4E7Ikn8Lyw%3d%3d=pwRE6AGJFLDNlh225F5QMaQWCtPHwdhUfC
Z%2fLUQzgA2uL5jNRG4jdQ%3d%3d&mCTIbCubSFfXsDGW9IXnlg%3d%3d=j
UgQCaU3L68%3d&kCx1AnS9%2fpWZQ40DXFvdEw%3d%3d=%2fq7ao2ANM
n8%3d&uJovDxwdjMPoYv%2bAJvYtyA%3d%3d=ctNJFf55vVA%3d&FgPlIEJYlot
S%2bYGoBi5olA%3d%3d=NHdURQburHA%3d&d9Qjj0ag1Pd993jsyOJqFvmy
B7X0CSQK=ctNJFf55vVA%3d&WGewmoAfeNR9xqBux0r1Q8Za60lavYmz=ctN
JFf55vVA%3d&WGewmoAfeNQ16B2MHuCpMRKZMwaG1PaO=ctNJFf55vVA%
3d                                              ITEM CLOSED
Impact and Recovery
IP_10
Establish formal feedback mechanisms from community resilience
groups to take on board learning and develop future response
arrangements.
Strategic Lead – Housing & Communities By March 2024 Feedback mechanisms are currently in place, although a
formal debrief process/procotol will be produced by
officers.
ITEM CLOSED
Impact and Recovery
IP_10b
Invite representatives from SEPA, SSE and SW to attend a future
Scrutiny and Performance Committee (Scrutiny and Performance
Committee action).
Chief Executive By June 2024 The Executive Director (Communities) is in contact with
partners about the available committee dates.
SEPA / SSE / ScW attended S&P 18/09/2024
ITEM CLOSED
Page 20 of 32

Page 21

Appendix 2
Communications since October 2023 
Reports submitted to Committees and Minutes of Meetings 
Scrutiny and Performance Committee -22 November 2023
Review of Extreme Weather Events in Perth and Kinross in October 2023 
Appendix 1 - Incident Planning - Standby Arrangements 
Appendix 2 - Improvement Plan 
Appendix 3 - Flood Gate Location Map
Minute of Meeting of Scrutiny and Performance Committee 22 November 2023    
Scrutiny and Performance Committee - 31 January 2024 
Review of Extreme Weather Events in Perth and Kinross October 2023 
Appendix 1 - Improvement Plan  
Minute of Meeting of the Scrutiny and Performance Committee of 31 January 2024 
Scrutiny and Performance Committee - 24 April 2024 
Weather Events - Improvement Plan  
Minute of Meeting of the Scrutiny and Performance Committee of 24 April 2024   
Scrutiny and Performance Committee - 12 June 2024 
Extreme Weather Events Review - Overview of Activity  
Minute of Meeting of the Scrutiny and Performance Committee of 12 June 2024 
Climate Change and Sustainability Committee – 21 August 2024 
Year-Round Weather Event Response 
Appendix 1 - Civil Contingencies Act 
Appendix 2 - Partner Agencies           
Appendix 3 - Flooding Contingency Systems 
3
Page 21 of 32

Page 22

Appendix 4 - Alignment with Extreme Weather Events Review Improvement Plan   
Appendix 5 - Council Response Examples Roads Maintenance Partnership 
Appendix 6 - Council Response Examples - Flooding 
Minute of Meeting of the Climate Change and Sustainability Committee of 21 August
2024 
Economy and Infrastructure Committee – 28 August 2024
Road Gully Cleansing  
Appendix 1 - Previous Cleanse Monitor Outputs 
Appendix 2 - Cleanse Monitor 2023  
Appendix 3 - Visual Representation 
Minute of Meeting of the Economy and Infrastructure Committee of 28 August 2024 
Scrutiny and Performance Committee - 18 September 2024 
Presentation - SEPA
Presentation - SSE Renewables  
Presentation - Scottish Water 
Minute of Meeting of the Scrutiny and Performance Committee of 18 September
2024 
Flood Bulletins  
Flooding - Frequently Asked Questions - 12 October 2023 
Flood Bulletin - 13 October 2023 
Flood Bulletin - 27 October 2023   
Community Bulletin - Flooding in Invergowrie 20 October 2023 (3 July 2024) 
Page 22 of 32

Page 23

Elected Member Briefing Notes – October – December 2023 
8 October 2023  Weather Update 6pm
8 October 2023   Weather Update 10pm
10 October 2023  Weather Update 12 noon 
17 October 2023   Forecast Adverse Weather Conditions 
18 October 2023  Forecast Adverse Weather Conditions – Update
19 October 2023  Forecast Adverse Weather Conditions – Update
20 October 2023  Forecast Adverse Weather Conditions – Update
21 October 2023  Forecast Adverse Weather Conditions – Update
25 October 2023  Storm Babet – Post-Event Recovery
27 October 2023  Adverse Weather, 27 October 2023
28 October 2023  Adverse Weather, 28 October 2023
3 November 2023  River Braan Bridge Reinstatement 
27 December 2023  Storm Gerrit 
27 December 2023  Storm Gerrit (5pm)
27 December 2023  Storm Gerrit (8pm)
28 December 2023   Storm Gerrit (11am)
28 December 2023   Storm Gerrit (3.45pm)
29 December 2023  Weather Response 
30 December 2023  Weather Response
31 December 2023   Weather Response 
Page 23 of 32

Page 24

Page 24 of 32

Page 25

Appendix 3
Roles and Responsibilities – Flooding 
Perth and Kinross Council 
• Design, develop, operate and maintain Perth and Kinross flood defences and
schemes that are in place, in respect to the advice, warnings and alerts that
SEPA publish. 
• Local Resilience Partnerships are the Scottish Government’s approach to
emergency planning and civil contingencies. PKC are members of the Tayside
Local Resilience Partnership along side other Local Authorities in Tayside,
NHS Tayside, Public Health, Police Scotland and Scottish Fire and Rescue
Service. Representatives from SEPA and the MET Office attend meetings
when there is a weather flooding risk.
• The Incident Management Team for Perth and Kinross is PKC’s local
response and will stand up when required. 
• All Services and the Health Social Care Partnership are invited to attend the
annual Winter Weather Preparedness to make sure people are ready for any
emergency. 
• Engagement with Community Resilience Groups regarding weather warnings.
• Welfare Response Protocol - engagement with those who have been affected
by a weather event. 
• Strong relations with External Partners. 
SEPA 
• Gather evidence through the provision of flood maps which will be available
on SEPA’s website. 
• Flood Forecasting – provide weather alerts and warnings (working in
partnership with the MET Office)
• The Scottish Flood Forecasting Service produces a daily Flood Guidance
Statement to local authorities and organisations with flooding management
duties. 
• Weather warnings are communicated to interested parties via text messages
to those who are registered, social media, SEPA’s Website, plus additional
offline updates to partners. 
• Develop Flood Risk Management Plans and offer advice to Local Authorities
with respect to establishing a Local Flood Risk Management Plan. 
3
Page 25 of 32

Page 26

Scottish Water 
• Response for the operation of the Public Sewar Network. 
• Operate Pumping Station at South Inch on the Council’s behalf as part of the
cities flood defences. 
• Sewars are constantly monitored. As water levels start to rise / increased
sewar blockages, resources are deployed to support customers and help
Local Authorities with flood defences. 
• Emergency Planning to link to Local Authorities and Local Resilience
Partnerships. 
• Collaborative work with PKC on the operation of Perth flood defences. 
• In Perth and Kinross, work is underway to upgrade the sewar at Tay Street to
reduce the risk of flooding from five hot spot areas. 
SSE Renewables 
• Attenuate water, store, and within reason regulate flows. 
• Cannot stop the water and there are significant river systems that SSER have
no influencing assets. 
• Their operating philosophy is to prevent uncontrolled spill wherever possible.
• Support SEPA in their role of ‘Warm and Inform’ during flooding with the
sharing of information.
• SSER are not a Category 2 responder under the Civil Contingencies Act
(2004). SSER are aware of their responsibilities and engage with Local
Resilience Partnerships as part of multi-agency response to an emergency. 
• Pitlochry Dam – Characterised by two Drum gates. The Drum gates are self-
operating. When Loch Faskally is full, they respond to inflows. Once flows
immediately downstream of Pitlochry Dam attain 425 cumecs, SEPA are
notified.   
Page 26 of 32

Page 27

Perth and Kinross Council 
Scrutiny and Performance Committee 
18 December 2024 
ADDITIONAL SUPPORT NEEDS (ASN) REVIEW 
Report by Strategic Lead – Legal and Governance
(Report No. 24/369) 
1. PURPOSE OF REPORT 
1.1 The purpose of this report is to  confirm the agreed scope of the review of
Additional Support Needs (ASN) provision across schools within Perth &
Kinross Council; and to update the Scrutiny & Performance Committee as to
progress and next steps 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee:
(i) Confirm the agreed scope of the Scrutiny Review
(ii) Note the progress to date
(iii) Asks officers to bring back an overview and update report to Scrutiny
Committee in January 2025 
3. STRUCTURE OF REPORT INTRODUCTION 
Section 4: Background/Context
Section 5:  Scope
Next Steps 
Annex
Appendices 
4. BACKGROUND/CONTEXT 
4.1 During a Scrutiny & Performance Committee meeting held 22 June 2022, the
Convenor, Councillor Colin Stewart, issued a call for review topics. 
4.2 During this meeting, Councillor Caroline Shiers proposed a broad topic review
of Additional Support Needs (ASN) provision across schools in Perth and
Kinross, to better understand the challenges and to help the organisation align
budget to need.  
4
Page 27 of 32

Page 28

5. SCOPE OF THE REVIEW 
5.1 A small core group from the Scrutiny and Performance Committee convened
on 2 occasions ; 
• 24 August 2023: To determine what should be included in the scope
• 06 February 2024: to agree the topic brief which would form the focus of
the review. The agreed area of focus was on how schools make the
necessary adjustment to meet additional support needs. 
5.2  This area of focus resulted in the following scope for review: 
To  determine how effective the Council is at ensuring that adjustments made
for children and young people with additional support needs are: 
• applied properly and consistently over time in practice.
• communicated well when pupils move schools or transition from nursery
to primary/primary to secondary.
• applied in a way that benefits both the council and the child through early
interventions. 
6. REVIEW PROCESS TO DATE 
6.1 5 November 2024:  presentation  to members from Fiona Mackay, Service
Manager Inclusion and Additional Support.   This presentation gave a
comprehensive overview  on the current landscape of ASN within Perth &
Kinross Council . It also provided members with information as to the progress
of the  ASN Transformation Programme. 
6.2 A range of school & partner visits were arranged and attended by Councillors
as follows: 
A variety of supporting documents and information were provided to facilitate
the visits. 
6.3  13 November 2024; workshop for members of the Scrutiny & Performance
Committee  supported by officers assess the information gathered  to date and
to reaffirm the scope of the Review.  
Date School / Partner
6/11/24 Milnathort PS
6/11/24 Crieff LMG (Primary & Secondary)
11/11/24 St John’s RC Academy
11/11/24 Perth Academy & Viewlands PS
26/11/24 Perth Autism Support (PAS)
Page 28 of 32

Page 29

7. NEXT STEPS 
7.1  Athe request of members,  a visit has been planned with Parent to Parent.
This is a service, contracted  by the Council through a Service Level
Agreement, which offers support and advocacy for parents of children and
young people with additional support needs. This will provide Committee
members with  the opportunity to gain valuable insights  into the challenges
surrounding ASN from a parental perspective. 
7.2 A follow up meeting between Committee members and the  Chief Executive of
Perth Autism Support to be convened. 
7.3 A comprehensive  overview report reflecting the work to date will be presented
by the Service at the next Scrutiny and Performance Committee Meeting on
January 29, 2025. 
Authorised 
Name Designation Contact Details 
Lisa Simpson  Strategic Lead – Legal &
Governance Services 
legalservices@pkc.gov.uk 
Page 29 of 32

Page 30

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  No
Workforce No
Asset Management (land, property, IST) No
Assessments  
Equality Impact Assessment No
Strategic Environmental Assessment No
Sustainability (community, economic, environmental) No
Legal and Governance  No
Risk No
Consultation 
Internal  No
External  No
Communication 
Communications Plan  No 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to Objective No. (2.1).   
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
Page 30 of 32

Page 31

(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to Objective No. (2.1).   
1.3 The report also links to the Education and Learning; and the Children,
Families and Justice Services Vision, Values and Priorities in respect of the
following key Priority area: 
• Learning and Achievement 
2. Resource Implications N/A 
3. Assessments N/A 
4. Consultation N/A 
2. BACKGROUND PAPERS N/A 
3. APPENDICES N/A 
Page 31 of 32