Appenidx 1 - Improvement Task Plan

Perth and Kinross Council · 18 December 2024
Back to Scrutiny and Performance Committee — 18 December 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Theme Ref no
Activity Responsible Officer Timescale Comments
(S&P 31/01/2024)
Comments
(03/12/2024)
Notification and
Preparedness
IP_1
Report to EI&ED on resource requirements to support year-round
resilience.
Strategic Lead – Environment &
Infrastructure
No later than June 2024 Proposal being developed.
Various options being considered and costed, in
conjunction with other inter-related actions below.
Year Round Weather Event Response presented at Climate Change &
Sustainability Committee (21 August 2024) - ITEM 6 -
https://perth-and-kinross.cmis.uk.com/perth-and-
kinross/Meetings/tabid/70/ctl/ViewMeetingPublic/mid/397/Meeting/3755/Co
mmittee/136/Default.aspx
Road Gully Cleansing paper presented at Economy & Infrastructure
Committee (28 August 2024) - ITEM 5 -
https://perth-and-kinross.cmis.uk.com/perth-and-
kinross/Meetings/tabid/70/ctl/ViewMeetingPublic/mid/397/Meeting/3996/Co
mmittee/150/Default.aspx
ITEM CLOSED
IP_2
Officers to review and put in place new minimum staffing/standby-
levels at command and operational levels to ensure resources are
available to successfully co-ordinate and deploy all flood defence
measures within timescales set within the to be revised protocols
(action 8 refers).
Roads Maintenance Partnership Manager By June 2024 As above, various options being considered and costed,
in conjunction with other inter related actions.
Consideration also being given to changing the flood gate
closure procedure, and triggers.
Year Round Weather Event Response presented at Climate Change &
Sustainability Committee (21 August 2024) - ITEM 6 -
https://perth-and-kinross.cmis.uk.com/perth-and-
kinross/Meetings/tabid/70/ctl/ViewMeetingPublic/mid/397/Meeting/3755/Co
mmittee/136/Default.aspx                                                                                                                                                                                                                                                             
ITEM CLOSED
Incident Management,
Resourcing and Response
IP_3
Undertake further training in terms of emergency planning across the
wider leadership team to ensure resilience to deal with incidents
Strategic Lead – Strategic Planning,
Policy & Resources
By March 2024 Arrangements are being put in place to provide both
external and internal training/awareness sessions.
Currently liaising with colleagues in Local Resilience
Partnership (LRP) regarding further training for gold and
silver command officers. Crisis management training
being investigated for all new Gold Commanders.
Strategic Leadership in a Crisis (SLIC) training has been deliverd to 8 out of 14
SLs with a further session on 6 Jan for 4 more.  Remaining 2 SLs will be trained
in Feb 2025.
ONGOING
Incident Management,
Resourcing and Response
IP_4
The Council’s Out of Hours Standby arrangements be reviewed to
include exploring the opportunities for expanding the remit of staff
from other Council services.
Strategic Lead – Environment &
Infrastructure
By March 2024 To be undertaken in conjunction with actions 2 and 7.
Internal discussions on-going regarding what resources
are currently available across PKC and how these can
better support/increase any response to an emergency.
Parking & Civil Contingencies resources trained / being trained to assist with
PFPS and Almondbank gate operation as required.
ONGOING
Incident Management,
Resourcing and Response
IP_5
Continue to work with current Community Resilience Groups and
build on the success of these models, reflecting that public agencies
including the Council are unable to respond to all impacts across the
authority.
Strategic Lead – Housing & Communities This is an ongoing action,
which is monitored within
the service.
Work has commenced to develop a marketing campaign
to promote the creation of CRGs, and the support
available from PKC. For example, a meeting is being held
in Invergowrie in January 2024. A CRG Seminar is to be
arranged in Perth for March 2024.
Word of mouth between Communiy Resilience Groups and interested
communities is driving unprecedented demand for engagement.  We are
sitting at 63 CRGs across P&K of varying sizes and portfolios and servicing this
demand is our current priority.   Once we have fuly supported all those groups
coming forward we plan to dig into harder to reach communities and the
marketting campaign and seminar will be part of that second push.
ONGOING
Incident Management,
Resourcing and Response
IP_5b
Appropriate allocation of the approved funding to communities to
support resilience in terms of both training and equipment (Scrutiny
and Performance Committee action)
Service Manager – Community Resilience
and Emergency Planning
By June 2024
Ongoing
As above. ONGOING
Incident Management,
Resourcing and Response
IP_6
Review how the logging and sharing of information between partner
agencies is undertaken, building upon the conversations which have
taken place to date with SSE and SEPA
Strategic Lead – Environment &
Infrastructure
By March 2024 Discussions have taken place with SEPA and agreement
reached on new way forward, and new operational
protocols have been agreed, which will provide for better
communication and clarity. This has now been used
across a number of weather events.
SEPA to update their guidance and copy to PKC for
agreement.
ITEM CLOSED
Improvement Plan Tasks

Page 2

Incident Management,
Resourcing and Response
IP_7
Undertake a review of the handling of calls to the Out of Hours contact
centre, as well as a further review of the Council’s out of hours
customer contact arrangements.
Strategic Lead – Environment &
Infrastructure
Strategic Lead - Customer & Digital
Services
By March 2024 Proposal being developed.
Various options being considered and costed, in
conjunction with action 4 above.
Procedures for opening the Roads and/or Housing Repairs Out of Hours line
overflow are now in place, predicated on officers always activating the
additional resources at Aberdeen City Council in the first instance to deal with
the call volumes involved.
ITEM CLOSED
Incident Management,
Resourcing and Response
IP_8
Review the Perth Flood Scheme Gate Closure Operational Procedure
document with SEPA.
Strategic Lead – Environment &
Infrastructure
By June 2024 Various options being considered, in conjunction with
action 2 above, to increase resilience and community
reassurance whilst minimising the need for additional
stand-by resources. Gate closure triggers being
reviewed.
Structures team also to provide form of words with their requirements with
regard to closing and opening of Tay Viewing platform and Queens Bridge in
due course to inform review.
ONGOING
Incident Management,
Resourcing and Response
IP_8b
This review to include a clearer and better tested ‘plan B’ for when
something does go wrong with a piece of infrastructure (Scrutiny and
Performance Committee action)
Strategic Lead – Environment &
Infrastructure
By June 2024 Plan being developed which creates less reliance on the
use of heavy equipment and the use of alternative
protection measures. In progress, being led by RMP
manager and TC Head of Operations.
ONGOING
Incident Management,
Resourcing and Response
IP_8c
Develop a protocol to share vulnerable people lists during
emergencies (Scrutiny and Performance Committee action)
Service Manager – Community Resilience
and Emergency Planning
By June 2024 Officers are liaising with colleagues in SSEN and the NHS
regarding the sharing of relevant information. The key
issue being data protection and GDPR.
Progress is being made with the sharing of data with Angus Council being used
as a test ground.   If the pilot is successful then we anticipate roll out by the
end of the financial year.
ONGOING
Impact and Recovery
IP_9
Review of welfare response protocols and engagement with those
directly impacted, including follow up with affected individuals in
Perth City and Invergowrie.
Head of Environmental & Consumer
Services
Senior Service Manager - Housing
By 23 December 2023 A welfare response protocol has been developed and
was put in place, which worked well during the flooding
event at the end of December 2023.
Welfare Engagement Protocol: https://perth-and-kinross.cmis.uk.com/perth-
and-
kinross/Document.ashx?czJKcaeAi5tUFL1DTL2UE4zNRBcoShgo=M01FqNO8t
tcuV7zCbdPk3nsFRQY%2fN9ixlaHlWVVcFivgccRUzevkhA%3d%3d&rUzwRPf
%2bZ3zd4E7Ikn8Lyw%3d%3d=pwRE6AGJFLDNlh225F5QMaQWCtPHwdhUfC
Z%2fLUQzgA2uL5jNRG4jdQ%3d%3d&mCTIbCubSFfXsDGW9IXnlg%3d%3d=j
UgQCaU3L68%3d&kCx1AnS9%2fpWZQ40DXFvdEw%3d%3d=%2fq7ao2ANM
n8%3d&uJovDxwdjMPoYv%2bAJvYtyA%3d%3d=ctNJFf55vVA%3d&FgPlIEJYlot
S%2bYGoBi5olA%3d%3d=NHdURQburHA%3d&d9Qjj0ag1Pd993jsyOJqFvmy
B7X0CSQK=ctNJFf55vVA%3d&WGewmoAfeNR9xqBux0r1Q8Za60lavYmz=ctN
JFf55vVA%3d&WGewmoAfeNQ16B2MHuCpMRKZMwaG1PaO=ctNJFf55vVA%
3d                                              ITEM CLOSED
Impact and Recovery
IP_10
Establish formal feedback mechanisms from community resilience
groups to take on board learning and develop future response
arrangements.
Strategic Lead – Housing & Communities By March 2024 Feedback mechanisms are currently in place, although a
formal debrief process/procotol will be produced by
officers.
ITEM CLOSED
Impact and Recovery
IP_10b
Invite representatives from SEPA, SSE and SW to attend a future
Scrutiny and Performance Committee (Scrutiny and Performance
Committee action).
Chief Executive By June 2024 The Executive Director (Communities) is in contact with
partners about the available committee dates.
SEPA / SSE / ScW attended S&P 18/09/2024
ITEM CLOSED