Agenda Document Pack - Pre-Determination Committee - 17/08/2022

Perth and Kinross Council · 17 August 2022
Back to Pre-Determination Committee — 17 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Securing the future… • Improving services 
• Enhancing quality of life • Making the best use of public
resources 
Council Building
2 High Street
Perth
PH1 5PH 
10/08/2022 
A hybrid meeting of Pre-Determination Committee will be held in the Council
Chambers (Hybrid) on Wednesday, 17 August 2022 at 11:00. 
If you have any queries please contact Committee Services on (01738) 475000 or
email Committee@pkc.gov.uk. 
THOMAS GLEN
Chief Executive 
Those attending the meeting are requested to ensure that all notifications are
silent on their device and other devices are in silent mode. 
Please note that the meeting will be broadcast online and recorded.  The
recording will be publicly available on the Council’s website following the
meeting. 
Members: 
Provost X McDade
All Councillors 
Page 1 of 42

Page 2

Page 2 of 42

Page 3

Pre-Determination Committee 
Wednesday, 17 August 2022 
AGENDA 
MEMBERS ARE REMINDED OF THEIR OBLIGATION TO DECLARE ANY FINANCIAL
OR NON-FINANCIAL INTEREST WHICH THEY MAY HAVE IN ANY ITEM ON THIS
AGENDA IN ACCORDANCE WITH THE COUNCILLORS’ CODE OF CONDUCT. 
1 WELCOME AND APOLOGIES   
2 DECLARATIONS OF INTEREST   
3 21/01855/IPM - MIXED USE DEVELOPMENT COMPRISING
MUSEUM (INCLUDING ANCILLARY SHOP AND CAFÉ), HOTEL
AND HOLIDAY LODGE ACCOMMODATION (INCLUDING
ANCILLARY SHOP AND CAFÉ FUNCTIONS),
COMPLEMENTARY RETAIL AND ASSOCIATED ACCESS,
PARKING, PUBLIC REALM, OPEN SPACE AND
LANDSCAPING WORKS (IN PRINCIPLE) (LDP SITE RT1),
CALEDONIAN HOUSE AND LAND AT WEST KINFAUNS,
KINFAUNS HOLDINGS, WEST KINFAUNS
Report by Head of Planning and Development (copy herewith
22/185 (REVISED)) 
5 - 42 
Page 3 of 42

Page 4

Page 4 of 42

Page 5

PERTH AND KINROSS COUNCIL 
17 August 2022 
APPLICATION FOR PLANNING PERMISSION 21/01855/IPM 
Report by Head of Planning and Development
(Report No. 22/185 (REVISED)) 
PROPOSAL: Mixed use development comprising museum (including
ancillary shop and café), hotel and holiday lodge
accommodation (including ancillary shop and café functions),
complementary retail and associated access, parking, public
realm, open space and landscaping works (in principle) (LDP
site RT1)  
LOCATION: Caledonian House and land at West Kinfauns, Kinfauns
Holdings, West Kinfauns 
Ref. No: 21/01855/IPM 
Ward No: P1- Carse of Gowrie 
Summary 
This report recommends approval of an application for Planning Permission in
Principle for a major mixed used development comprising: a hotel, museum, retail
services, holiday chalets and the associated access, services and parking; subject
to conditions and a Section 75 legal agreement to secure the transfer of land to the
Council for the delivery of an optional ‘park and choose’ transport hub within part of
the site. The development is acknowledged to be a significant departure from the
adopted Local Development Plan (LDP) and therefore requires Full Council
approval. However, it is considered that there are material planning considerations
which justify a departure from the development plan, notably the economic benefits
for the Perth and Kinross area. It is recommended that the extent of the retail
floorspace that can be provided as part of the development be restricted to ensure
it is proportionate and reflective of the extent of the proposed tourism offer; and that
the site does not in itself become a significant retail destination. This restriction is
necessary to limit the impact on Perth city centre and other identified retail centres,
as well as reducing retail only trips to the site.   
BACKGROUND AND DESCRIPTION OF PROPOSAL
1 The application site, known as ‘West Kinfauns’, is situated some 10.8
hectares (ha) and approximately 2 miles southeast of Perth City Centre.
Indicative plans show vehicular access off both the A85(T) and the Kinfauns
Holdings Road (U202), with the M90/Friarton Bridge further west. The small
settlement of Walnut Grove is just to the east, Kinnoull Hill is further north and
the River Tay to the south. In terms of land designations within the LDP, the
3
Page 5 of 42

Page 6

site can be broken into three main sections: 1) the southern and westernmost
parts, occupying ground primarily between the River Tay and existing built
development onsite being designated as open space; 2) employment
safeguarded land, located within the northeast part occupying ground
surrounding existing built development onsite; and 3) land designated as for
the purposes of establishing a park and choose transport hub (designated
RT1). This is positioned at the western part bordering Dundee Road,
occupying an area approximately 1.8 ha in size.     
2 The site comprises a large undeveloped field, bounded to the north by mature
vegetation and the public road network.  The only building is ‘Caledonian
House’, which provides offices over two floors and sees parking, with a
vehicle access off the Kinfauns Holdings U202 Road to the north. This
building is to be retained and is not indicated to be affected by the proposals. 
3 Planning Permission in Principle is sought for a mixed-use development,
although no detailed designs are submitted for assessment. The development
is classified as being Major in the hierarchy of development regulations. The
proposed quantum of uses is:  
a) A hotel, of 120 to 150 rooms; 
b) Up to 52 holiday chalets; 
c) A transport museum and associated workshop (c.5,500 square metres
in floor area (m2); 
d) Complementary retail and support services, up to 1,000m2,* (*to be
contained within and appear part of the museum and workshop
building). The total size of that building thus being c.6,500m2,  
e) Associated works including services, drainage works, access, parking
and landscaping.   
4 The ‘park and choose’ transport hub has Planning Permission (Reference
18/02232/FLM). However, it does not form part of this application. To provide
a future opportunity for the Council to deliver this infrastructure, a Section 75
planning obligation is recommended by the Council’s Transport Planning
Team to require an area of land to be set aside by the developer for this use.
The proposed ‘park and choose’ transport hub comprises a public carpark
with capacity for approximately 100 vehicles, including bus shelter and bus
turning facilities, and electric vehicle (EV) charge points. This provision is not
considered in further detail in this report. At this time, the Council has only
agreed to prepare a business case and the project is not included in the
current capital programme. 
5 A pre-determination hearing in respect of this application is required, in
accordance with Section 7 of the Town and Country Planning (Scotland) Act
1997 as amended and Regulation 27 of the Town and Country Planning
(Development Management Procedure) (Scotland) Regulations 2013.
Regulation 27 provides that “before determining an application for planning
permission for a major development which is significantly contrary to the
development plan, the planning authority are to give to the applicant and to
persons who submit representations to the planning authority in respect of
that application, an opportunity of appearing before and being heard by a
Page 6 of 42

Page 7

committee of the authority.”  A pre-determination hearing has been set to
immediately precede the Council meeting of 17 August 2022. 
Pre-Application Consultation 
6 20/00542/PREAPP. Pre-application advice was provided by officers on 16
November 2020, in relation to a mixed-use development including; support
functions for longer stay accommodation and potential Spa style facilities; log
cabins for longer stay, larger groups – 5 days plus; a museum and supporting
services including complementary retail floorspace; and a potential and Park
& Ride facility. 
7 The applicant has carried out formal pre-application consultation (PAC) in
accordance with the Town and Country Planning (Development Management
Procedure) (Scotland) Regulations 2013 and the relevant provisions of the
Town and Country Planning (Scotland) Act 1997 (as amended).  A PAC report
was submitted with this application confirming the completion of a digital
public event on 16 March 2021.  This event was advertised in the Courier and
by leaflet drop. 16 responses were received with concerns raised including
traffic congestion and road safety, the overall scale and size of the
development and a lack of active travel details.  No specific concerns were
raised regarding the museum or retail options presented.   
National Policy and Guidance 
National Planning Framework 2014 (NPF) 
8 NPF3 is a long-term strategy for Scotland and is a spatial expression of the
Government’s Economic Strategy and plans for development and investment
in infrastructure. This is a statutory document and material consideration in
any planning application. It provides a national context for development plans
and planning decisions, as well as informing the on-going programmes of the
Scottish Government, public agencies and local authorities. 
The Scottish Planning Policy 2014 (SSP) 
9 The Scottish Planning Policy (SPP) sets out national planning policies which
reflect Scottish Ministers’ priorities for operation of the planning system and
for the development and use of land. The SPP promotes consistency in the
application of policy across Scotland whilst allowing sufficient flexibility to
reflect local circumstances. It directly relates to the: 
• preparation of development plans; 
• design of development, from initial concept through to delivery; and 
• determination of planning applications and appeals. 
10 The following sections of the SPP will be of particular importance in the
assessment of this proposal: 
• Sustainability: paragraphs 24 – 35 
• Placemaking: paragraphs 36 – 57 
Page 7 of 42

Page 8

• Valuing the Natural Environment: paragraphs 193 – 218 
• Managing Flood Risk and Drainage: paragraphs 254 – 268 
• Promoting Sustainable Transport and Active Travel: paragraphs 269 –
271. 
Planning Advice Notes 
11 The following Scottish Government Planning Advice Notes (PANs) and
Guidance Documents are of relevance to the proposal:   
• PAN 40: Development Management 
• PAN 51: Planning, Environmental Protection and Regulation 
• PAN 61: Planning and Sustainable Urban Drainage Systems 
• PAN 65: Planning and Open Space  
• PAN 68: Design Statements 
• PAN 69: Planning and Building standards Advice on Flooding 
• PAN 75: Planning for Transport 
• PAN 77: Designing Safer Places  
• PAN 79: Water and Drainage  
• PAN 84: Reducing Carbon Emissions in New Development  
• PAN 1/2013: Environmental Impact Assessment   
TAYplan Strategic Development Plan 2016-2036 
12 TAYplan sets out a vision for how the region will be in 2036 and what must
occur to bring about change to achieve this vision. The vision for the area, as
set out in the plan, states that:   
13 “By 2036, the TAYplan area will be sustainable, more attractive, competitive
and vibrant without creating an unacceptable burden on our planet. The
quality of life will make it a place of first choice where more people choose to
live, work, study and visit, and where businesses choose to invest and create
jobs.” 
14 The following sections of the TAYplan 2016 are of particular importance in the
assessment of this application: 
• Policy 1: Locational Priorities 
• Policy 2: Shaping Better Quality Places  
• Policy 3: A First Choice for Investment  
• Policy 5: Town Centres First  
• Policy 6: Developer Contributions  
• Policy 8: Green Networks     
Perth and Kinross Local Development Plan 2   
15 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for
the area and states that, “Our vision is of a Perth and Kinross which is
dynamic, attractive and effective which protects its assets whilst welcoming
population and economic growth.”  It is the most recent statement of Council
Page 8 of 42

Page 9

policy and is augmented by Supplementary Guidance. The following key
policies are applicable to the assessment of this application:   
• Policy 1A: Placemaking  
• Policy 1B: Placemaking 
• Policy 1C: Placemaking 
• Policy 4: Perth City Transport and Active Travel 
• Policy 5: Infrastructure Contributions 
• Policy 7A: Employment and Mixed-Use Areas: Business and Industrial 
• Policy 9B: Caravan Sites, Chalets & Timeshare Developments: New and
Expanded Touring Caravan, Motorhome/ Campervan, and Camping Sites 
• Policy 13: Retail and Commercial Leisure Proposals 
• Policy 14A: Open Space Retention and Provision: Existing Areas 
• Policy 15: Public Access 
• Policy 17: Residential Areas 
• Policy 26B: Scheduled Monuments and Archaeology: Archaeology  
• Policy 32: Embedding Low & Zero Carbon Generating Technologies in
New Development 
• Policy 38C: Environment and Conservation: Local Designations 
• Policy 39: Landscape 
• Policy 40B; Forestry, Woodland and Trees: Trees, Woodland and
Development 
• Policy 41: Biodiversity 
• Policy 47: River Tay Catchment Area 
• Policy 52: New Development and Flooding 
• Policy 53A: Water Environment and Drainage: Water Environment 
• Policy 53B: Water Environment and Drainage: Foul Drainage 
• Policy 53C: Water Environment and Drainage: Surface Water Drainage 
• Policy 55: Nuisance from Artificial Light and Light Pollution 
• Policy 56: Noise Pollution 
• Policy 57: Air Quality 
• Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals 
16 The Scottish Government expresses its planning policies through The
National Planning Frameworks, the Scottish Planning Policy (SPP), Planning
Advice Notes (PAN), Creating Places, Designing Streets, National Roads
Development Guide and a series of Circulars.   
Supplementary Guidance    
17 The following supplementary guidance is of particular importance in the
assessment of this application: 
• Developer Contributions and Affordable Housing Supplementary
Guidance April 2020 
• Air Quality and Planning Supplementary Guidance March 2020 
• Flood Risk and Flood Risk Assessments Supplementary Guidance
Adopted March 2021 
Page 9 of 42

Page 10

• Delivering Zero Waste Supplementary Guidance, January 2020
• Landscape Supplementary Guidance 2020 
• Open Space Provision for New Developments Supplementary Guidance
Adopted March 2021 
• Placemaking Supplementary Guidance, Adopted March 2020 
• A guide to Incorporating Biodiversity into Development, Adopted April
2022 
• River Tay Special Area of Conservation (SAC) Advice to developers
when considering new projects which could affect the River Tay Special
Area of Conservation (2020) 
Other Material Considerations    
18 Getting the Right Change: A Retail Strategy for Scotland – March 2022 
19 Scotland's National Strategy for Economic Transformation: Published 1
March 2022   
Site History 
20 15/01808/FLM On 19 February 2015, detailed Planning Permission was
approved, having been sought by the Council, for the formation of a ‘park and
choose’ facility, related access road, landscaping and associated works. 
21 18/02232/FLM on 11 March 2020, planning permission was granted (under
Section 42 of the Town and Country Planning (Scotland) Act 1997) to modify
Condition 13 of Planning Permission 15/01808/FLM to allow the delivery of
construction materials for that development on Saturdays between 0800 and
1300 hours.        
22 21/00001/PAN.  A ‘Proposal of Application Notice’ was submitted on 11
February 2021 for a mixed-use development comprising hotel, museum,
holiday accommodation, retail and potential park and ride facility. A report
setting out the details of the PAN was presented to the Planning and
Development Management Committee on the 9 March 2021.   
23 21/00684/SCOP.  An EIA (Environmental Impact Assessment) Scoping
Opinion was issued by the Council on 20 May 2021, which confirmed the
details required to be included in the Environmental Impact Assessment
Report for the development set out in the subject application.   
CONSULTATIONS 
As part of the planning application process, the following bodies were
consulted: 
Page 10 of 42

Page 11

External Consultees: 
24 Scottish Water: No objection. Developer to contact Scottish Water to confirm
connection details.   
25 Transport Scotland: No objection, subject to conditions. Following the
request for additional information, including the completion of a Stage 1 Road
Safety Audit (being a review of existing infrastructure audit and analysis of
traffic / road accident data for that location) by the applicant, a position of
agreement has been reached to permit the application subject to conditions.
In this case, conditions are recommended to: limit the scale of any retail
development onsite; secure a construction traffic management plan; agree
design details regarding the new A85 Trunk Road site access; secure a
signage strategy; secure a travel plan to reduce private motor vehicle use at
the site; secure an external lighting scheme; the managing of stormwater and
dirt or debris on the road network; the provision of a barrier at the site
boundary where it adjoins the trunk road and that construction material
delivery to be sheeted. (Conditions 2, 7, 8, 18, 20, 25 - 29, 34 and 35).          
26 Network Rail: No objection in principle, subject to conditions on; fencing,
construction method statement, drainage, landscaping and a noise impact
assessment. Informative notes are also suggested for lighting and
construction limitations. (Conditions 8, 9, 12, 14 and 23).   
27 NatureScot: No objection, provided mitigation options including a
construction environmental management plan and the provision of
sewer/SUDS systems are in place to protect the River Tay Special Area of
Conservation.  (Conditions 6, 8, 11 and 12).   
28 Historic Environment Scotland: No objection. No comments to note. 
29 Perth and Kinross Heritage Trust: No objection, subject to a condition
requiring archaeological evaluation and related informative notes. (Condition
19).   
30 Scottish Environment Protection Agency: No objection.  No Comments to
note. 
31 West Carse Community Council: Object. Consider that there would be
adverse transport impacts, road safety implications, the proposals are of an
inappropriate scale and character for the area, the chalet layout is too dense,
and the height of buildings (hotel) is too high. 
32 Dundee City Council: No objection. No comment to note.    
Internal Consultees    
33 Environmental Health (Noise / Odour): No objection, subject to conditions
on: construction noise, noise from operational deliveries and servicing, odour
from cafes / kitchen facilities, and any external lighting. (Conditions 12, 13, 15
- 17).
Page 11 of 42

Page 12

34 Transport Planning: No objection, subject to conditions related to, a signage
strategy, parking standards, EV charging details, updating trip rate forecasts
and the provision of a footway along Kinfauns Holdings. (Conditions 29 –
33).   
35 Development Plan Team: Object, consider the proposals are contrary to
Policies 7, 9, 13 and 14 of the LDP2.   
36 Community Greenspace: No objection, subject to conditions requiring an
agreed active travel plan and landscape details, confirming planting of public
open spaces, including the existing core path within the site. (Conditions 8, 21
and 22).   
37 Structures and Flooding: No objection, subject to a condition requiring a
SUDs drainage scheme.  (Condition 6).   
38 Development Contributions Officer: No objection, subject to a condition to
secure developer contributions towards transport infrastructure. (Condition
20).  For clarity, as the optional “park and choose” transport hub discussed
throughout this report does not form part of this application, contributions
directly towards its construction cannot be secured via condition.    
39 Biodiversity/Tree Officer: No Objection, following a request for additional
information on the completion of an ecological survey, general agreement on
biodiversity / landscape principles to be incorporated into the design, as well
as confirmation that conditions are applied in relation to these matters and for
the control of any construction impacts. (Conditions 8 - 12).   
40 Economic Development: No objection, comments provided to inform this
report.    
41 Commercial Waste Team: No objection, subject to a condition requiring a
Waste Management Plan and or details/location of bin storage and collection
points. (Condition 24).   
Representations 
42 14 objections were received.  Concerns are summarised as follows: 
• Visual impacts: visual amenity / landscape quality  
• Overdevelopment and impacts on character of the area  
• Loss of open space  
• Noise  
• Flooding and drainage  
• Road safety and traffic congestion  
• Over provision of vehicle parking / dependence on private vehicle use 
• Impacts on quality of life to residents  
• Impacts on ecology and biodiversity  
• Loss of employment land   
These issues are addressed in the Appraisal section of the report. 
Page 12 of 42

Page 13

ADDITIONAL STATEMENTS 
Screening Opinion  EIA Required
Environmental Impact Assessment (EIA):
Environmental Report
Submitted
Appropriate Assessment
Habitats Regulations Appraisal
(completed/                         
AA Completed/
AA Not Required
Design Statement or Design and Access
Statement
Submitted
Report on Impact or Potential Impact eg
Flood Risk Assessment
Submitted/Not Required 
POLICY APPRAISAL 
The Scottish Planning Policy 2014 (SSP) 
Sustainability / Placemaking    
43 SPP promotes high quality successful, sustainable, naturally resilient,
connected, and low carbon places.  The outcome of development should be
sustainable, well-designed places which meet people's needs. Development
should also be guided by the optimisation of resources, the use of land within,
and adjacent to, settlements and locations where investment in growth or
improvement would have the most benefit for the amenity of the local
people.  In this regard, the development proposed is located within a
settlement boundary and the site offers a mix of features that make it
attractive as a location for a tourism focused development. This includes: the
proximity to Perth City Centre, the opportunity to reroute bus services via the
site, which is identified in LDP2, the proposals to include a transport hub, as
well as nearby national cycle routes which could be enhanced by new
facilities through the site and along the River Tay. A key component of the
proposals is seen as the retention and improvement of the existing Core Path
(WCAR/119) and, in turn, the integration of the existing and new path network
onsite.   
44 In terms of supporting business and employment, the planning system should
promote development that increase economic activity whilst safeguarding the
natural and built environment.  In addition, due weight should be given to net
economic benefits of proposed development.  In the case of this assessment,
and as is expanded upon below, greater weight has been afforded to the
economic benefits of this proposal against negative impacts on amenity and
placemaking. Conditions 8 - 12 have been recommended to avoid and
mitigate impacts on the natural environment. It is considered that appropriate
regard has been given to the economic benefits in this case.   
Page 13 of 42

Page 14

Managing Flood Risk and Drainage    
45 Principally, a precautionary approach to flood risk from all sources is adopted,
taking account of the predicted effects of climate change.  In this case, the
development is not located within an identified active flood plain area and, as
such, risks from flooding are low.  Whilst surface water is to be managed
onsite, via a SUDs scheme, the Council’s Flood Risk Officer has no specific
concerns. Condition 6 has been recommended to ensure the Council retains
control over design of the SUDs system.   
Active Travel    
46 The planning system should support patterns of development which; optimise
the use of existing infrastructure, reduce the need to travel, provide safe and
convenient opportunities for walking and cycling for both active travel and
recreation, and facilitate travel by public transport, as well as enabling the
integration of transport modes. In these regards, the development proposed
supports active travel through the retention and enhancement of a core path
and wider cycle networks.  Opportunity exists to promote public transport to,
and from the site, through the rerouting of bus services, which may be
enhanced further by a ‘park and choose’ facility.  The development, as a
tourism offer, is considered to actively promote transport and active travel.
Although a draft Active Travel Plan (ATP) has been submitted, Condition 21
requires updated and a detailed ATP to be approved.  Condition 26 seeks that
the applicant provide further analysis on ways to reduce the reliance of private
motor vehicle dependency to the development.     
Retail Strategy for Scotland: March 2022 
47 The ‘Place Principle’ adopted in this recent Scottish Government publication is
one where people, location and resources combine to create a sense of
identity and purpose and is at the heart of addressing the needs and realising
the full potential of communities. Creating communities and places people
want to visit, live and shop in is seen as vital to economic recovery – not only
for retail, but for culture, hospitality and tourism. Where there are actions to
support a strong local retail and cultural destinations, there will be
opportunities for other businesses, such as hospitality and tourism, to
capitalise on increased footfall. 20-minute neighbourhoods are designed to
allow people to reach key amenities like shops, services and green spaces by
walking, wheeling, cycling or using public transport. This development offers
the opportunity to create a cultural destination focused on the Motor Museum,
near to Perth City Centre, supported by tourist accommodation along with
complementary and associated retail services which aligns with this policy.   
48 Concern is raised by neighbours and the community council that the scale of
the development is too large for this location and that there will be resulting
traffic safety impacts as well as general impacts on local amenity. Regarding
amenity, it is accepted that the open nature of this site will result in visual
change. However, it is considered that the impact of this can be mitigated
through conditions controlling design, scale, size, and landscaping. This is
discussed in more detail below. It is also noted that, as an ‘in principle’
Page 14 of 42

Page 15

application, the Council is unable to control, beyond which ‘use class’ is
permitted, which operators will occupy each aspect of the development. The
applicant has sought to confirm the types of retail anticipated for this location,
and it is their intention to support tourism and office activities on site, such as
a cafe, restaurant, bakery, cycle repair shop, and small ancillary stores. To
ensure that large scale retail services do not encroach into this development
in the future, a condition is recommended limiting the scale of each unit to no
more than 200m2, and a total retail floorspace to 750m2. (Conditions 1 and
2).  By comparison, the typical local convenience store usually occupies
300m2.   
National Strategy for Economic Transformation: March 2022    
49 The Scottish Government launched its National Strategy for Economic
Transformation earlier this year, with the aim of creating a well-being
economy: a society that is thriving across economic, social, and
environmental dimensions, and that delivers prosperity for all Scotland's
people and places. They aim to achieve this while respecting environmental
limits embodied by climate and nature targets. Whilst creating this vision to
increase investment and increase productivity, there is the reality of severe
pressure on businesses in the past two years and a particularly difficult
environment for the tourism industry. According to the Scottish Tourism
Emergency Response Group, Scottish tourism is facing its biggest challenge
ever. The proposals in this application look to respond to this challenge and
address the vision to enhance economic activities in the area. The project
proposal seeks to attract inward investment, create new job opportunities,
encourage economic investment in rural areas, and provide social and cultural
benefits to residents and visitors. The submission also outlines the capacity to
support significant construction jobs over three years. The impact of the
construction cost is modelled at £32.2 million, which equates to 85 full-time
equivalents (FTE) on and off-site construction jobs during the construction
phase. The economic assessment suggests that 115 net additional FTE
positions could be generated each year across the wider impact area during
the construction period, inclusive of 65 jobs in the local area. 
TAYplan Strategic Development Plan 2016-2036 
Policy 1 Locational Priorities    
50 Strategies, plans and programmes require to focus the majority of
development towards settlements, followed by land along the edge of
principle settlements.  Where located outside of a principal settlement, the
outcomes must meet the needs of the local community and not undermine
regeneration of the cities.  In this regard, the proposals are located at the
edge of the settlement area of Perth and, therefore, should only be supported
where it does not undermine existing regeneration and contributes to the
outcomes of the plan.  In principle, this means that the development should
not seek to create suburbanisation of the countryside and unsustainable
patterns of travel.  In this case, the development, whilst of ‘major’ scale is
indicated to continue to see large areas of open space, coupled with active
travel paths and significant landscaping which will mitigate any perceived
Page 15 of 42

Page 16

urbanisation. Changes to bus routes and improved cycle networks would seek
to promote active travel from the site, although it is noted that significant
elements of the development seek to facilitate vehicle use, as expected in the
peripheral location and nearby roads infrastructure. The climate impacts of
this are to be reduced through encouraging less impactful modes of transport
via: EV (Electric Vehicle) Charging points, along with a wider active travel plan
to encourage other forms of travel once guests arrive.  (Conditions 1, 2, 8, 21,
26, 31).   
Policy 2 Shaping Better Quality Places    
51 Better quality places should, by design, be; place led, promote health, be
future ready and efficient in terms of resource consumption.  In this case, the
development in terms of the indicative layout and design seeks to focus large
amounts of the built development within the northern section of the site, to
minimise visual bulk in a landscape setting and enhances and preserves the
natural open space towards the Tay. The development is not located within a
flood plain area and, by design, will incorporate a SUDs scheme which both
promotes resilience and open space. (Condition 6).         
Policy 3 A First Choice for Investment   
52 A first choice for investment means safeguarding 5 years’ supply of
employment land and further assisting with the growth of a year-round
economy.  The central part of the site, occupying land around the existing
office building and parking area, is identified in LDP2 as safeguarded
employment land. The existing office building and parking is to be retained,
but part of that allocation is where the museum and supportive retail are
proposed.  Whilst these facilities promote employment opportunities, the uses
proposed were not intended/planned at this allocation and as such they do not
accord with Policy 3.  The applicant is of the view that the land is currently
underutilised, and the museum presents an opportunity for an alternative, yet
compatible, use.  However, there is no evidence that this land has been
marketed for employment-based use and as such the basis for the land being
underutilised cannot by verified.  Notwithstanding, the development presents
a significant investment opportunity for the Perth area and, whilst the
development will result in the loss of some employment land (c.4 hectares),
the proposed uses are, in this case, compatible with the overall development
intentions for the site and would provide employment opportunities.   
Policy 5 Town Centre First    
53 The town centre first approach seeks to protect and enhance the vitality,
viability and vibrancy of town centres.  The Development Plan Team has
objected on the basis that the scale of the retail element proposed in the
application could adversely impact on and compete with Perth City Centre.
However, the Council’s Economic Development Team has considered these
matters in more detail and, based on the size of the retail elements proposed,
it is their view that that the use will primarily be from a localised catchment,
specifically the hotel, holiday chalet and museum users. Having regard to any
potential impacts on Perth Town Centre, the Economic Development Team
Page 16 of 42

Page 17

have also agreed with the conclusions of the Environmental Impact
Assessment Report (EIAR) provided by the applicant. This states that “should
any retail offer be used in the future by retail outlets not directly linked to the
primary use of the site as proposed, the hypothetical ‘worst-case’ scenario,
even if 100% of the estimated turnover of the Proposed Scheme (£4.38
million, including Food and Beverage turnover) displaced  Perth city centre
turnover (£271million, not including Food and Beverage turnover), this would
equate to an anticipated maximum impact of 1.6% on Perth city centre in
2026. To further mitigate any potential impacts on Perth city centre and to
restrict the proposed retail elements of this development to a proportionately
reasonable size, ancillary to the primary use as proposed, condition 2 is
recommended restricting the floor area of each unit to no more than 200 m2
and a maximum total size of 750m2.   
Policy 6 Developer Contributions    
54 To ensure suitable infrastructure is in place to facilitate new development,
local development plans should set out a policy framework for seeking
developer contributions. Condition 20 has been recommended to ensure
appropriate contributions are provided with respect to transport
infrastructure.   
Policy 8 Green Networks    
55 The development site is positioned within the TAYplan green network
between Perth and Dundee. The development is not seeking to remove
significant vegetation and has sought to provide a biodiversity strategy which
sets out broad aims for the delivery of ecological values for this site. The
development also further proposes enhancement of the existing core path by
the Tay with further path connections.    
Perth and Kinross Local Development Plan 2 
56 The proposed development represents a significant departure from the Local
Development Plan 2, being contrary to a number of individual policies, and the
degree of departure from their intents.  However, the application assessment
concludes that, although contrary to these policies, material planning
considerations, namely the economic benefits of the proposal, along with a
number of recommended conditions to control design, layout, scale and
landscaping, outweigh the development plan and justify a recommendation of
approval.        
57 The following key LDP policies are applicable and are considered in detail
below.      
Policy 1 Placemaking    
58 (a) Create a sense of identity by developing a coherent structure of streets,
spaces, and buildings, safely accessible from its surroundings.    
Page 17 of 42

Page 18

59 Although no detailed design information has been submitted for consideration,
the project is to be brought forward for development in a coordinated manner
which will both create a destination identity to the site and afford safe access
from the A85 Trunk Road and the Kinfauns Public Road.  Conditions 25 - 35
have been recommended regarding road and transport safety matters, as well
as EV charge points, trip generation and footpath construction.    
60 (b) Consider and respect site topography and any surrounding important
landmarks, views or skylines, as well as the wider landscape character of the
area.   
61 In terms of design and layout, the applicant has considered those important
views across the development site towards Kinnoull Hill from the south-west
and approach over the M90 over bridge. This is discussed in paragraph 64
below. The greatest massing within the development relates to the hotel and
the museum/retail building.  Neither of these developments will skyline from
any significant viewpoints and, although they will be visible on the approach
towards the site, they will also be extensively backdropped against Kinnoull
Hill and relate to the existing large office building.  Conditions 1 – 6 are
recommended to ensure the Council retains control over design, layout and
location of any future development.   
62 (c) The design and density should complement its surroundings in terms of
appearance, height, scale, massing, materials, finishes and colours.    
63 Although these matters are addressed through conditions 1 - 6, the applicant
has incorporated some design considerations in terms of the proposed layout
to seek to minimise visual bulk. These include the integration of the retail
facilities to within the museum building and retaining this building within the
northern most area, where it is contained from the settlement of Walnut Grove
by established vegetation.  Concern is raised by objectors at the scale of
development, in particular the number and density of the accommodation
lodges. Although the recommended conditions do not seek to reduce the
number of lodges, limits regarding minimum separation distance between
units and a separation from external boundaries has been recommended
(Condition 4) to assist integration into the landscape. Notwithstanding, it is
acknowledged that the application for this development is in principle only and
the final design, density and layout can only be considered following
submission of future applications.    
64 (d) An existing building line where appropriate or establish one where none
exists. Access, uses, and orientation of principal elevations should reinforce
the street or open space. 
65 Many of the proposed buildings will be at the northern part of the site, thereby
enhancing open space to the south by the Tay.  This not only groups buildings
to existing developed areas but also seeks to provide an opportunity for
biodiversity, open space and path connections, particularly within the southern
area.        
Page 18 of 42

Page 19

66 (e) All buildings, streets, and spaces (including green spaces) should create
safe, accessible, inclusive places for people, which are easily navigable,
particularly on foot, bicycle and public transport.    
67 An active travel plan has been provided and will be incorporated into the
development. However, following detail design, conditions 21 and 26 are
recommended to ensure that active travel and a reduced reliance on private
motor vehicle travel to the site is reflected in the future vision for this
development.   
68 (f) Buildings and spaces should be designed with future adaptability, climate
change and resource efficiency in mind wherever possible.    
69 Condition 5 is recommended to ensure the finalised design incorporates these
values. This will ensure the Council retains some control and further
consideration into the design.      
70 (g) Existing buildings, structures and natural features that contribute to the
local townscape should be retained and sensitively integrated into proposals. 
71 The existing office building is to be retained and supported by the proposed
development seeking to provide support services and further employment at
this location.   
Policy 7: Employment & Mixed-Use Areas 
72 (a) Proposals should not detract from the amenity of adjoining places,
especially residential areas.    
73 In this respect, part of the site, including the existing office building, carpark
and immediate surrounding space, is safeguarded for employment purposes.
The retention of the existing office headquarters within the development as
proposed, which offers considerable office space, meets the intention of the
above objective. However, the museum and retail elements are also sited
within this safeguarded area. Whilst the development presents an opportunity
to diversify potential uses for this allocation, this proposal is a significant move
away from the general employment opportunities anticipated in these areas.
Policy 7 specifically states that retail, principally for visiting members of the
public, should not be encouraged in these areas. Furthermore, museums
generally fall under the ‘Town Centre First’ principle. However, the proposed
museum is stated as being for motor vehicles and transport, and this requires
space unlikely to be available in an urban area. Concerns have been raised
by objectors that the development will detract from the amenity of Walnut
Grove.  However, whist the scale of the development is significant, it is
considered that concerns regarding amenity can be addressed by good
design, and this is sought to be controlled through conditions 1, 2, 4 and
8.  However, and notwithstanding this point, whilst there may be some
impacts to existing amenity, these would not be to an extent that they could
not be mitigated to an acceptable level. In addition, the economic benefits of
the proposals are considered to justify those impacts identified.     
Page 19 of 42

Page 20

74 (b) The local road network and connections to the national road network must
be suitable for the traffic generated by the proposals.    
75 (c) There should be good walking, cycling and public transport links to new
employment generating uses. 
76 An active travel plan has been submitted which demonstrates the capacity to
connect into an existing core path. It is suggested that minor bus rerouting
and improvements in links along the Tay would further enhance the delivery of
active travel options to this location. Review of the ATP and Travel Plans will
be required following detailed design and is sought through Conditions 21 and
26.   
77 (d) Proposals for retail uses in employment areas will not be acceptable
unless they are ancillary to an acceptable use on the site.   
78 The development does not conform with this part of Policy 7 as the scale of
retail proposed by this development is not considered ancillary to the museum
or hotel use and must instead be considered a separate component to the
development.  The applicant considers that the uses proposed will be ancillary
and support the main tourism development proposed. However, the Council
cannot control the future users of these retail spaces, thus, to ensure that it
remains an ancillary and subservient support offering, Condition 2 is
recommended to limit the total floor area, as well as the floor area of each unit
to no more than 200 square metres and an overall maximum floor space of
750m2.    
79 (e) Proposals for service facilities (should exclude retail and commercial
facilities over 100 m2) and should serve the business and industrial area
rather than draw outside trade and cumulatively should not equal more than
15% of the allocated employment area.    
80 The retail development of this proposal will total 750 square metres in area
and may seek to service the wider residential location, contrary to this aspect
of policy 7.  Whilst the applicant has sought to clarify that the retail elements
are specifically aimed at servicing the museum, hotel and holiday chalet lodge
guests / visitors in the first instance, the need for convenience goods and
services may seek to have an unintended benefit of also serving both the
existing office and residents of Walnut Grove. Condition 2 seeks to retain
control over the scale and use class of development able to occupy this
proposed retail space, specifically Class 1 (Shops) and Class 3 (Food and
Drink) only will be permitted. However, if this development is implemented no
control is held by the Council as to what retail / hot food and drink outlets
occupy the approved premises.  Whilst objection is not specifically raised as
to the type of retail use, concerns have been noted regarding traffic
congestion, road safety and overall impacts to the visual amenity. It is,
therefore, implicit that a large retail store occupying this space would
potentially add to a greater number of trips to the site and may adversely
impact amenity, a matter sought to be controlled by this policy.  Whilst
condition 2 does not restrict the type of retail offered, a maximum floor area of
200m2 for each individual unit is specified.  This will mean that only small
Page 20 of 42

Page 21

shops (such as those defined by HMRC as a small business) can occupy this
space. In conjunction with conditions 13 and 15 (Noise), and Conditions 26
and 32 (Trip Generation), the impacts on amenity relating to retail use can be
appropriately mitigated.       
81 (f) Proposals for waste management facilities are considered to be acceptable
subject to detailed site-specific considerations.    
82 Condition 24 seeks to require a waste management plan to be submitted as
part of any detailed design or application for approval of matters specified by
conditions.   
83 (g) Proposals should not result in adverse effects, either individually or in
combination, on the integrity of any European designated sites. Applications
shall be supported by sufficient information to allow the Council to conclude
that there would be no such adverse effects. 
84 NatureScot, in its review of the application, did not raise any concerns with
respect to impacts on the Tay, subject to the implementation of safeguarding
measures. These have been implemented through conditions 8 – 12. 
Policy 9: Caravan Sites, Chalets & Timeshare Developments 
85 Proposals for new or expanded sites for holiday-related uses will be
supported where the proposals are compatible with Policy 1: Placemaking. 
86 The proposed development is seeking permission for up to 52
accommodation lodges for use by longer stay guests (over 5 days). This
aspect of the development does not fully meet Policy 1 in terms of its design
and density, given the scale of development in contrast to the size of the
neighbouring plots and the overall building mass proposed.  This is a concern
raised by objectors and the Council’s Development Plan Team and is
discussed above. The applicant has sought to address these matters by
setting out that the design and layout of the holiday lodges is not
finalised.  Being subject to further examination in conjunction with design of
the access, parking, servicing, drainage and landscape provisions, the
proximity of holiday lodges to the eastern site boundary remains a valid
concern.  A landscape and biodiversity strategy has been provided, setting
out mitigation options. However, any landscaping takes time to establish.  To
seek to immediately mitigate some of the concerns raised by objectors,
condition 4 is recommended.  This will seek to ensure the holiday chalets are
well separated from one another and neighbouring boundaries. This will afford
a visual setback, whilst landscaping is established and will also promote
openness and reduce the layout density.  Condition 5 and other conditions
such as those relating to access, parking and active travel through the site will
need to be considered as a whole in the design and layout. Whilst the
development overall will cause some impacts to landscape character, it is
considered that, with the conditions recommended, appropriate mitigation is
offered to minimise those impacts on direct neighbours. Furthermore, and
principle to the assessment of this report, it is considered that the positive
Page 21 of 42

Page 22

economic impacts of this development are a material planning consideration
and serve to outweigh the development plan in this case.   
Policy 13: Retail and Commercial Leisure Proposals 
87 The location for any use that generates a significant footfall should follow a
sequential approach in which locations for such development are considered
in the following order:    
(a)  city or town centre;  
(b)  edge of city or town centre;  
(c)  other commercial centres identified in the Development Plan;  
(d)  out of centre locations that are, or can be made, easily accessible by a
choice of transport modes. 
88 The proposal is contrary to this policy as the size of the retail space proposed
(1,000 square metres) cannot be considered ancillary to the museum
facility.  Whilst the principal set out in the indicative design, which integrates
retail within the museum building, is acceptable, the scale of the retail element
is disproportionate to reasonable ancillary requirements of the museum, hotel
and holiday lodge.  Though some clarification on the types of complementary
retail types envisaged has been provided, the scale is such that it must be
considered a separate and distinct aspect of the proposal. In this sense,
locations for retail proposals must undertake a sequential approach in
considering an appropriate location, the sequence identifying city or town
centres as the preferable option, with ‘out of centre’ locations as the least
preferable. Kinfauns is on the edge of Perth but is identified as a separate
settlement within LDP2.  The applicant, through its Environmental Impact
Assessment Report , has provided a socio-economic assessment of the
development. This has been reviewed by the Council’s Enterprise Team who
have confirmed a broad agreement with the conclusions.  That is, based on
the location and size of units, the retail aspect would primarily seek to support
a local market. In order to retain control over the scale of retail operating from
this site (in line with the conclusions of the Enterprise team), Condition 2 has
been recommended to limit the floor space (750m2 in total) and overall size of
individual units (200m2) Having regard to the site accessibility, the
development will be easily accessible by public transport, subject to minor
changes in bus services. No objections are raised by with the Council’s
Transport Planning Team or Transport Scotland, subject to the above
restrictions by condition 2.    
Policy 14A: Open Space Retention & Provision 
89 The proposal seeks to locate a considerable number of accommodation
lodges / chalet units on, and within, designated open space. The indicative
design is such that the lodges will occupy, and could dominate, the open
space area, thereby seeking to discourage public access.   
90 (a) Where the site is principally used as a recreation resource, the proposed
development is ancillary to the principal use of the site as a recreational
resource. 
Page 22 of 42

Page 23

91 The local Development Plan lists this open space area as having landscape
value rather than being as a recreational resource.   
92 (b) The proposed development involves a minor part of the site which would
not affect its continued use as a recreational or amenity resource. 
93 The accommodation lodges and hotel, shown on the indicative layout
presented, occupy approximately half of this open space designation, with the
balance to form recreational space (such as paths and landscaping) as well
as the SUDs / wildlife pond.   Notwithstanding that this indicative layout is still
subject to detailed design work, controlled through conditions, it is considered
that large parts of the site would remain open for passive amenity purposes,
whereby views could still be maintained through, and over, the development
site. This will help to maintain its existing value.  Having regard to the
conclusions and recommendations noted in paragraph 88 above, it is
considered that, with appropriate landscaping and conditions regarding siting
and design of all built development, the impacts on landscape and wider
amenity can be mitigated.   
94 (c) In the case of proposals involving the loss of a recreational facility, the
facility which would be lost would be replaced by provision of one of
comparable or greater benefit and in a location which is convenient for its
users, or by the upgrading of an existing provision to provide a better quality
facility, either within the same site, or at another location which is convenient
for its users. 
95 (d) Where a proposal would involve the loss of a sports pitch, a playing field
strategy prepared in consultation with sportscotland has demonstrated that
there is a clear excess of sports pitches to meet current and anticipated future
demand in the area, and that the site could be developed without detriment to
the overall quality of provision. 
96 Having regard to items (c) and (d) of this policy, the development is not a
recreational and/or sports pitch and, as such, those provisions are not
relevant to this assessment.     
Design and Layout 
97 As a Planning Permission in Principle application, only limited detailed
consideration can be given to site layout and design. However, the key design
considerations to this development have been; 1) the integration of the retail
facilities to within the museum building in order to reduce overall bulk and
mass onsite, 2) to keep as much building mass to within the safeguarded
employment area, which would also allow screening from existing established
vegetation, 3) to position the hotel so that it relates to the front façade of the
existing office building and to have its gable end onto the main public road/
M90 Bridge. This will have the added benefit of helping to minimise visual bulk
when viewed against the natural backdrop of Kinnoull Hill.  In terms of the
lodges, their arrangement is considered in relation to access, parking,
drainage designs for the wider proposals and the position of the core path
passing the site.  
Page 23 of 42

Page 24

98 Review of the design concepts presented initially saw Council Officers raise
concern that the level of detail presented did not provide enough assurance or
confidence that, although contrary to LDP2, the site would provide a good
area of open space whilst being attractive for visitors and benefiting the
community. However, in this case consideration has also be given to the
limited use of the site as it is now, and that a Transport Museum requires
space, something which was unlikely to be available within a city centre
location. Accordingly, this particular type of development is considered a
positive opportunity. Coupled with the economic benefits the development
could bring and conditions to control the scale, design, landscaping and any
construction related impacts, it is considered that, on balance, the principle of
much of the primary elements of the development are acceptable for this
location.     
Landscape and Visual Amenity    
99 Concern is raised by objectors that the proposal overly develops the site and
is not of a scale or character suited to this peripheral location. In these
respects, it is recognised that, given the relatively open and flat nature of the
site, there is limited opportunity to use vegetation and/or topography in which
to incorporate a design to be significantly absorbed within the landscape. As
such, the proposed development presents challenges in terms of visual
impact and appearance.  However, as noted above, design considerations
have sought to address the concerns raised. In combination with conditions to
guide and retain further control over the development within the design phase,
it is considered that a number of the concerns raised can be mitigated.   
100 In terms of landscape mitigation, a detailed planting scheme has not been
provided with this application, as only the principles rather than details are
being assessed.  However, it is considered that a suitable scheme can be
developed, incorporated into the design, and presented through a further
application. This matter is addressed through condition 2.9.  Concern has
been raised in relation to the lack of detail, as it offers less confidence and
assurance that the development can successfully integrate into the
landscape.  However, the applicant has sought to address this by providing an
ecological site appraisal and a set of landscape and biodiversity principles to
be adopted in implementing the development. A position is presented that,
with the adoption of these principles, and further landscaping details to be
provided through conditions, the development can successfully integrate into
its surroundings. Whilst landscaping will take time to establish, it is considered
that this presents appropriate mitigation in this case. Conditions 4, 6, 8 - 12
and 13 have been recommended below to address the concerns raised.   
Roads and Access 
101 The indicative plans propose three access points to the public road network,
1) a new service entrance for the museum and retail elements opposite
numbers 1 and 3 Kinfauns Holdings; 2) the luxury lodges propose use of the
existing vehicle access opposite Mesa Verde, Kinfauns Holdings, this also
serves Caledonian House; and 3) the hotel entrance and drop off location,
public parking area and retail elements of the development will be accessed
Page 24 of 42

Page 25

directly via a new junction from the A85 Trunk Road.  Full details are
illustrated in drawings provided with the application.   
Parking 
102 The Transport Assessment details sufficient space to comply with the relevant
National Roads Development Guide parking standards, which is acceptable
for the museum and hotel elements. The applicant has advised that the retail
elements are considered ‘linked’ rather than separate trips. However, at this
stage, very limited details have been provided on the retail element and this
detail may well impact on traffic generation. As such, further clarity will be
required at the matters specified by condition stage. For each chalet, a
minimum of two car parking spaces will be provided. Coach Parking shall also
be considered and potentially coach EV facilities. 
Vehicle Access 
103 The existing site vehicle entrance to serve the holiday chalets and office
building is considered to be of an acceptable standard. The two new vehicle
access points to be created (one for the museum and retail servicing with a
second to serve the hotel), will be required to meet necessary engineered
standards. Transport Planning have confirmed that the appropriate visibility
splays can be provided and the detailed design of these accesses shall follow
at a later stage. 
Public Transport 
104 An existing bus stop on Dundee Road is served by over 35 buses daily, from
05:04 until 00:29hrs. These services have routes to Perth, Dundee,
Edinburgh, Kinross, Ingliston, Edinburgh Zoo and the Carse of Gowrie. An
electric bus, operated by Ember, has the potential to link to a number of other
tourist attractions and museums. At this stage, it is not possible to confirm if
any of the services will divert into the site, but discussions to explore this are
likely to take place at a later stage. The application indicates that buses will be
able to access and egress the site. These discussions will help inform the
location of bus infrastructure.    
Walking and Cycling 
105 The application also indicates the development will provide links into wider
path networks, creating permeability through the site for walking and cycling,
thus encouraging active travel. A new footway is to be provided along the
northern boundary, to the east of the existing Caledonian House entrance,
which it is anticipated will connect with the Ogilvie Homes development (Ref
20/00359/FLL) to the immediate east.     
Trip Generation 
106 The approach used to model trip generation is acceptable to both the
Council’s Transport Planning Team and Transport Scotland.  The modelling
report, (discussed in more detail within the Transport Planning Response),
Page 25 of 42

Page 26

shows journey times along Dundee Road from the Toll House to Queen’s
Bridge southbound would see minimal impact between AM and PM.
Northbound use would see the journey times similar between all three of the
modelled scenarios used. The queue lengths also show little difference
between AM and PM. Between the A85 Barnhill and the existing vehicle
entrance to Caledonian House, there will be a slight increase in vehicle flows
along Kinfauns Holdings. However, Transport Planning colleagues do not see
this as a concern, as there is capacity to accommodate the increase. 
Street Lighting 
107 New roads will be subject to a Road Construction Consent which will consider
the position of lighting columns. Future detailed applications should also
consider if any alterations are required to existing streetlighting. These
matters are addressed through recommended Conditions 1 and 18.   
Signing Strategy 
108 The applicant has advised that the lodges will be signed from the A85 Trunk
Road. Given Kinfauns Holdings can be accessed from the Trunk Road
Network at two locations, Perth & Kinross Council would be involved in the
discussions to limit the amount of traffic using the eastern side of Kinfauns
Holdings to access the site. Condition 29 is recommended regarding a
signage strategy.   
Park & Choose Site 
109 Planning Permission has previously been approved for part of this site
(Reference: 18/02232/FLM) for the development of a Park and Choose
facility, which was a Council led proposal. However, the Council does not own
this land, which is primarily under the ownership of the applicant.  As a result,
the Council had no legal mechanism in place to implement the planning
permission until agreement is reached with the relevant landowner(s). The
proposals that are the subject of this report indicate an area identified by the
applicant, as shown within the indicative site layout (drawing 03), for a Park
and Choose facility. The Council will secure the transfer of the land for the
delivery of this facility as part of the current application by entering into a
section 75 legal agreement with the applicant. Conditional control (condition
36) will also ensure that the development is delivered within an acceptable
timeframe together with the Park and Choose facility. Since the submission of
this application, the Council has agreed a budget to enable a business case
for capital investment to be prepared for Members’ consideration. 
Trunk Road Impacts 
110 Following the provision of further information, including a road safety audit,
Transport Scotland has withdrawn any objection to the development, subject
to a number of conditions and restrictions on any development being
progressed.  Matters covered by conditions include the scale of retail
development, signage, access formation, external lighting, stormwater,
construction traffic management, vehicle wheel cleaning, protection barriers
Page 26 of 42

Page 27

and means of travel to and from the site.  (Conditions 2, 7, 18, 25 – 29, 33, 34
and 35).  The breadth and number of conditions recommended reflects a lack
of detailed design detail at this time. 
Drainage and Flooding and Pollution Prevention    
Flooding    
111 The flood risk and drainage assessment supporting the application has been
reviewed by SEPA as well as the Council’s Structures and Flooding Team,
both of whom do not object.  The site is not shown to be at risk from fluvial or
coastal flood sources and is set well above the Coastal Flood Boundary 200-
year level of 4.57m and the 1000-yr level of 4.74m Above Ordinance Datum
(AOD).   
Wastewater Drainage    
112 Wastewater services for this development have been proposed as being 
private systems, including three individual package plants, serving the
separate aspects of the development (i.e the hotel, the museum and the
holiday chalets). If brought forward, each would need its own licence, likely
two Complex Licences under The Water Environment (Controlled Activities)
(Scotland) Regulations 2011 (CAR). These matters fall within the remit of
SEPA.    
Surface Water Drainage    
113 The Council’s Flood Risk Officer has reviewed the application and raised no
concerns, subject to a condition regarding further review of the detailed SUDs
drainage scheme design. It is advised that arrangements should follow the
approach set out in the CIRIA SUDS Manual (C753) and ensure the surface
water management proposals comply with CAR General Binding Rules (GBR)
10 and 11.    
114 In terms of construction related impacts, those matters are to be addressed
through the implementation of a construction method statement referred to in
conditions 6 and 20.      
Waste Collection 
115 No information has been submitted regarding waste collection, although
PKC’s Public Waste Operator has raised no objection, subject to a condition
to secure a waste management strategy and / or details to confirm waste
management onsite.  Condition 24 is recommended to this effect.     
Page 27 of 42

Page 28

Natural Heritage and Biodiversity 
116 In their consultation response of May 2021, NatureScot stated that the
Council will require to consider the effects of the proposal on the River Tay
Special Area of Conservation (SAC). In this regard, based on the location of
the development in relation to the SAC, the risk of direct disturbance is
considered very low. Furthermore, as per the Drainage Impact Assessment
and Chapter 9 of the Environmental Impact Assessment Report, the residual
risk to surface water during construction is minor, due to limited connectivity
(no open water courses running through the site) and physical separation
distance from the Tay margins.  Any SUDs system (discussed above) will
provide adequate storage and flow attenuation as well as enhanced water
quality management and amenity value, before discharging to an existing
private combined sewer network. As such, the residual risk during operation is
also considered to be low. Overall, the risk of Likely Significant Effects upon
the River Tay SAC is low, subject to conditions 8 - 12.    
117 In terms of biodiversity and habitat, a full landscape scheme plan will be
provided at detailed application stage.  However, in recognition of concerns
raised both by the Council’s Biodiversity Officer and through representations,
a landscape and biodiversity strategy has been prepared and this is
supportive of the application. Having reviewed the strategy, the principles it
sets out are accepted and conditions 10 and 11 are recommended.   
Archaeology    
118 No objection is raised by either Historic Environment Scotland or Perth and
Kinross Heritage Trust, subject to the inclusion of a condition relating to
archaeological works methodology. Condition 19 is recommended. 
Developer Contributions 
119 No objection to the development is raised, subject to a planning condition to
secure developer contributions related to transport infrastructure (Condition
20).  The proposal is thus considered to be in accordance with the Council's
policy on Developer Contributions and related Affordable Housing
Supplementary Guidance 2020. 
Economic Impact    
120 Chapter 11 of the EIAR sets out the socio-economic impacts from the
development. The assessment methodology considers; employment
generated during the construction phase, employment generated during the
operational phase, visitor expenditure, open space and impacts on existing
retail provision.     
121 Based on estimated construction costs, modelled as of 2021 at £32.2 million,
and a build period of 3 years, the project is predicted to create on average 85
full-time equivalent (FTE) construction jobs.  Accounting for some
displacement (i.e., in the absence of this development, workers might
otherwise be employed on other construction projects), the number of direct
Page 28 of 42

Page 29

jobs supported is 65 FTEs of which 50 are projected to be taken by residents
within Perth and Kinross. The benefits in terms of direct construction
employment will also extend to indirect benefits such as construction
materials and goods and services purchased locally.  It is estimated that
construction will support an additional 50 FTEs in the wider impact area as
part of the supply chain, of which 15 are predicted to be from within Perth and
Kinross.  The net employment impact finds that 115 FTE positions could be
generated of a wider impact setting, with 65 FTEs from within Perth and
Kinross. 
122 Based on the mixed-use nature of the development as proposed, it is
estimated to generate 125 net FTEs once complete and occupied.  This is
based on 60 FTE associated with the hotel, 45 connected with the retail
sector, 15 museum staff and 10 staff to manage the holiday chalets. Again,
accounting for displacement, 80 of those FTEs generated will be within Perth
and Kinross. It is further estimated that 25 FTEs will also be generated
indirectly through the supply chain.     
123 In terms of visitor expenditure, based on a room occupancy rate of 66% (in
line with figures from 2019 for Perthshire), it is estimated that the proposed
accommodation (both the hotel and holiday chalets), could accommodate
80,970 visitor nights per year.  Estimating a spend of £80 per night (Visit
Scotland data), this equates to a gross annual expenditure of £6 million per
year.  Accounting for expenditure elsewhere, it is estimated that £4.3 million
net additional expenditure will be generated within Perth and Kinross.    
124 Impacts on the existing retail sector within Perth city centre have already been
discussed, with it being demonstrated that the proposed development is
estimated to equate to only 1.6 % of the total retail turnover for the city centre
by 2026. Therefore, any direct impacts are considered negligible and
addressed by Conditions 1 and 2. The Council’s Economic Development team
has reviewed those values along with the employment assessments details
above and not raised any concern with the methodology or assessment
undertaken. They state that the development proposed represents
considerable private investment within Perth and Kinross which is to be
encouraged. The positive economic benefits, along with enhancements to the
tourism offer and opportunities for Perth are considered a significant material
consideration and outweigh the departures from the development plan,
particularly with regard to adverse impacts to allocated land use, changes in
amenity and landscape setting. 
PLANNING OBLIGATIONS AND LEGAL AGREEMENTS 
125 It is recommended this application be approved subject to a Section 75 Legal
agreement to secure any land transfer for the delivery of a Park and Choose
Transport Hub within part of this site.   
CONCLUSION AND REASONS FOR RECOMMENDATION 
126 In conclusion, this development is a significant departure from LDP2. The
specific conflicts which raise the greatest concerns are in respect of policies
Page 29 of 42

Page 30

pertaining to placemaking, the provision and scale of retail within the
development proposed and the loss of open space. Recommended conditions
will afford some mitigation by retaining control over the scale, from and layout
of the development and in particular the scale of retail provision adopted,
whilst also securing landscaping. When such conditions are considered
alongside the economic benefits of this development, including; job creation,
investment in Perth, and an increase in tourism to the area, it is considered
there is sufficient justification to permit the development, contrary to the
provisions of the adopted development plan.   
RECOMMENDATION   
Conditions and Reasons for Recommendation 
Approval of Matters 
1. The development shall not commence until the following specified matters
have been the subject of a formal planning application for the approval of the
Council as Planning Authority: the siting, design and external appearance of
all built aspects of the development, all hard and soft landscaping of the site,
all means of enclosure, means of access to the site, vehicle parking and
turning facilities, levels, drainage and waste management provision. 
Reason:  This is a Planning Permission in Principle under Section 59 of the
Town and Country Planning (Scotland) Act 1997 as amended by Section 21
of the Planning etc. (Scotland) Act 2006. 
2. The following use classes are hereby approved within the development and
shall not exceed: 
a)  Class 1 (shops) and Class 3 (Food and Drink) with a maximum
combined floor space of 750 square metres (m2), with no single unit in
excess of 200m2. In addition, each unit shall be physically conjoined to
one of the other approved uses/buildings, and in the case of the Hotel or
Museum have interconnectivity between the primary building/use, so as
to allow access by patrons internally, 
b)  Class 7 (Hotel) with a maximum number of rooms being 150,   
c)  Class 7 (Holiday Chalets) with a maximum number of 50 individual units,
each of a maximum floor area not exceeding 85 square metres (m2), 
d)  Class 10 (Non-residential Institutions – Museum) with a maximum floor
area of 5,500 square metres.     
Reason: In order to control the use classes hereby approved, to minimise
interference with the safety and free flow of traffic on the trunk road, and to
restrict the scale of authorised retail development.   
3. The holiday chalet use hereby approved shall be used solely for holiday
accommodation and shall not be occupied by an individual, persons or family
Page 30 of 42

Page 31

group for a period exceeding 14 nights. The applicant shall keep a record of
guests and number of nights stayed in order to demonstrate compliance with
this condition. This record book shall be made available for inspection upon
request by the Council as Planning Authority.   
Reason: In order to control the use class hereby approved. 
4. The design, location and external finishes of the holiday chalets hereby
approved shall be specified in the details submitted and agreed in association
to Condition 1 above. Notwithstanding the details shown on the drawings
hereby approved, no permission is granted for the submitted layout or number
of units. The following design parameters shall be complied with in
submissions related to Condition 1:   
a)  All holiday chalets shall be a minimum of 25 metres from any external
boundary to the site 
b)  All holiday chalets shall be a minimum of 8metres from each other 
Reason: To protect the amenity of the location and to ensure sufficient open
space within the development.   
5. As part of any application for the Approval of Matters Specified by Condition 1
proposing buildings requiring a building warrant, a scheme shall be submitted
to, and approved in writing by, the Council as Planning Authority. This must
demonstrate how at least 10% of the current carbon emissions reduction set
by the Scottish Buildings Standards will be met through the installation and
operation of low and zero-carbon technologies. This scheme shall detail the
following:   
a)  the technology types;   
b)  illustrate, through technical calculations, that these will meet at least the
10% reduction;   
c)  their siting and location; and   
d)  ongoing operation and maintenance.   
Once approved, the development shall be completed in accordance with the
approved scheme.   
Reason: To ensure the proposal complies with Policy 32 of the Local
Development Plan. 
Drainage (SUDs) 
6. As part of any application for the Approval of Matters Specified by Condition
1, a sustainable urban drainage system (SUDS) shall be submitted for the
written agreement of the Council as Planning Authority, in consultation with
the Scottish Environment Protection Agency (SEPA) where necessary.  The
Page 31 of 42

Page 32

scheme shall be developed in accordance with the technical guidance
contained in The Sustainable Drainage System (SUDS) Manual (C753) and
the Council’s Flood Risk and Flood Risk Assessments Developer Guidance
and shall incorporate source control. All works shall be carried out in
accordance with the agreed scheme and be operational prior to the bringing
into use of the development. 
Reason: In order to ensure all surface water is adequately managed. 
7.  There shall be no drainage connections to the trunk road drainage system. 
Reason: To ensure that the efficiency of the existing drainage network is not
affected. 
Biodiversity and Landscape   
8. As part of any future application for the Approval of Matters Specified by
Condition 1, a landscaping and planting scheme for the relevant areas sought
to be developed, shall be submitted for the written agreement of the Council
as Planning Authority, in consultation Network Rail and the Council’s
Biodiversity / Tree Officer and Community Greenspace team. The scheme
shall include details of the height and slopes of any mounding or recontouring
of the site, full details of all hard landscaping proposals including materials
and installation methods and, species, height, size and density of trees and
shrubs to be planted.  The scheme as subsequently approved shall be carried
out and completed within the first available planting season (October to
March) after the completion or bringing into use of the development approved
by that application, whichever is the earlier, and the date of Practical
Completion of the landscaping scheme shall be supplied in writing to the
Council as Planning Authority within 7 days of that date. The scheme as
agreed and implemented shall thereafter be maintained to the satisfaction of
the Council as Planning Authority. 
Reason: In the interests of amenity and public safety as well as the protection
of Network Rail infrastructure. 
9. No trees on the site shall be felled without the prior written agreement of the
Council as Planning Authority.  Any application for the Approval of Matters
Specified by Condition 1, where the area proposed to be developed contains
or is bounded by trees which could be affected shall be accompanied by a
detailed tree survey covering that area carried out by a qualified and
independent arborist indicating the type, age, condition, location and accurate
canopy spread of all the trees on and affected by the site and including a tree
management report with details of the tree protection measures to be
employed during construction in accordance with BS 5837 2012: Trees in
Relation to Design, Demolition and Construction. 
Reason: To protect the existing trees onsite, to ensure a satisfactory standard
of development and environmental quality and to reserve the rights of the
Planning Authority.      
Page 32 of 42

Page 33

10. The Biodiversity and Landscape Strategy for this site, prepared by Ecus Ltd,
dated March 2022 shall be fully adhered to, being incorporated in the
Construction Method Statement and Landscape Scheme as specified within
Conditions 8 and 12.   
Reason: In the interests of amenity and the protection of the River Tay SAC. 
11. The mitigation measures set out within the Ecological Impact Assessment,
prepared by Ecus Ltd and dated March 2022 shall be fully adhered to, being
incorporated in the Construction Method Statement and Landscape Scheme
as specified within Conditions 8 and 12. 
Reason: In the interests of biodiversity and the protection of the River Tay
Special Area of Conservation (SAC). 
Construction 
12. The development shall incorporate and not commence until a detailed
Construction Method Statement (CMS) has been submitted to and agreed by
the Council as Planning Authority, in consultation with NatureScot, Network
Rail and SEPA as well as the Council’s Biodiversity and Environmental Health
Officers.  The CMS must identify measures to prevent harmful materials
entering the River Tay SAC, which could reduce water quality and lead to a
damaging impact on the salmon, otter and lamprey interests. The CMS should
include the following:   
(a)  pollution prevention safeguards including drainage arrangements and the
possible use of siltation traps, settlement tanks and bunds  
(b)  storage and disposal of materials including the siting of stockpiles, use of
buffer strips and disposal methods  
(c)  construction site facilities including extent and location of construction
site huts, vehicles, equipment, fuel, chemicals and materials compound  
(d)  timing, duration and phasing of construction particularly in relation to
salmon and lamprey migration/spawning.  
(e)  a Dust Management Plan (DMP) for the control of dust during
construction.
(f)  noise mitigation measures for the control of noise during construction   
The CMS and mitigations as agreed shall be fully implemented during the
construction phase(s).   
Reason: To protect amenity and the River Tay SAC. 
Noise   
13. The mitigation measures recommended in Section 6.6 of the hereby approved
Noise Impact Assessment, prepared by ITP Energised Ltd dated 17
September 2021 shall be fully implemented to the satisfaction of the Council
as Planning Authority. 
Page 33 of 42

Page 34

Reason: To ensure that occupants/users of the development do not
experience undue disturbance arising from nearby noise nuisances and to
protect residential amenity for neighbours and nearby residents to the
development.   
14. Further to the Noise Impact Assessment completed and referred to in
condition 13 and as part of any application for the Approval of Matters
Specified by Condition 1, a railway specific noise impact assessment shall be
submitted to and approved in writing by the Planning Authority. This noise
impact assessment shall include an assessment of the potential for occupants
of the development to experience noise nuisance arising from the railway line.
Where a potential for noise disturbance is identified, proposals for the
attenuation of that noise shall be submitted to and approved in writing by the
Planning Authority in consultation with Network Rail. Any such approved noise
attenuation scheme shall be implemented prior to the development being
brought into use and shall thereafter be retained in accordance with the
approved scheme. 
Reason: To ensure that occupants/users of the development do not
experience undue disturbance arising from nearby railway activities. 
15. All plant or equipment shall be so enclosed, attenuated and/or maintained
such that any noise therefrom shall not exceed Noise Rating 35 between
0700 and 2300 hours daily, or Noise Rating 25 between 2300 and 0700 hours
daily, within any neighbouring residential property, with all windows slightly
open, when measured and/ or calculated and plotted on a rating curve chart. 
Reason: To ensure that nearby residents of the development do not
experience undue noise disturbance as a result of construction activities.     
16. Servicing of and deliveries to the site for all aspects of the development shall
be carried out between 0700 and 1900 Monday to Saturday only, with no
servicing or deliveries permitted on Sundays. 
Reason: To protect residential amenity    
Odour   
17. As part of any application for the Approval of Matters Specified by Condition
1, where the development proposed incorporates any commercial cooking,
the details of an effective ventilation system, commensurate with the nature
and scale of commercial cooking to be undertaken, shall be submitted for the
written agreement of the Council as Planning Authority. Prior to the
development being completed or brought into use, the approved system shall
be installed and operated within the commercial areas, such that cooking
odours are not exhausted into or escape into any neighbouring dwellings.
Thereafter the system shall be maintained. 
Reason: To protect the amenity of nearby residents to the development and to
ensure that occupants/users of the development do not experience any undue
odour nuisances. 
Page 34 of 42

Page 35

External Lighting   
18. All external lighting shall be sufficiently screened and aligned so as to ensure
that there is no direct illumination of neighbouring land and that light spillage
beyond the boundaries of the site is minimised to a degree that it does not
adversely affect the amenity of the neighbouring land. Details of the external
lighting within the site where the area proposed to be developed adjoins or
may impact the trunk road shall be submitted for the approval of the Council
as Planning Authority, after consultation with Transport Scotland, as the trunk
roads authority. 
Reason: To ensure that there will be no distraction or dazzle to drivers on the
trunk road and that the safety of the traffic on the trunk road will not be
diminished and to protect the amenity of nearby residents from light nuisance
and in the interests of biodiversity to mitigate against wildlife interference from
the development.   
Archaeology   
19. As part of the first application for the Approval of Matters Specified by
Condition 1, the developer shall secure the implementation of a programme of
archaeological work in accordance with a written scheme of archaeological
investigation which has been submitted by the applicant and agreed in writing
by the Council as Planning Authority, in consultation with Perth and Kinross
Heritage Trust. This may reflect a phasing programme. Thereafter, the
developer shall ensure that the programme of archaeological works is fully
implemented including that all excavation, preservation, recording, recovery,
analysis, publication and archiving of archaeological resources within the
development site is undertaken. In addition, the developer shall afford access
at all reasonable times to Perth and Kinross Heritage Trust or a nominated
representative and shall allow them to observe work in progress. 
Reason: In order to protect the historic environment and to align the
development with Scottish Planning Policy and Policy 26 of the Perth and
Kinross LDP2.     
Contributions     
20. The development shall be in accordance with the requirements of Perth &
Kinross Council’s Developer Contributions and Affordable Housing
Supplementary Guidance 2016 in line with Policy 5: Infrastructure
Contributions of the Perth & Kinross Local Development Plan 2 (2019) with
regard to transport infrastructure, or such subsequent Guidance and Policy
which may replace these. 
Reason:  To ensure the development is in accordance with the terms of the
Perth and Kinross Local Development Plan 2 (2019) and to comply with the
Council's policy on Developer Contributions and Affordable Housing
Supplementary Guidance 2020. 
Page 35 of 42

Page 36

Active Travel / Paths   
21. As part of the first application for the Approval of Matters Specified by
Condition 1, an active travel plan shall be prepared and submitted for
approval in writing by the Council as Planning Authority, in consultation with
the Council’s Greenspace team. 
Reason: In the interests of promote active travel and green infrastructure to
and from the development.   
22. As part of the first application for the Approval of Matters Specified by
Condition 1, a management plan indicating any temporary diversions and
associated fencing /signage needed to facilitate the development and/or any
works proposed to the right of way/core path as part of the development shall
be submitted for the agreement of the Council as Planning Authority. This
plan should demonstrate the temporary measures which are to be put in place
until any formal diversion of the core path and right of way is approved. The
plan, as agreed, shall be implemented in accordance with the timings
identified in the plan. 
Reason:  To ensure that public access is maintained at all reasonable times,
to the local path network. 
Network Rail   
23. As part of the first application for the Approval of Matters Specified by
Condition 1, a Network Rail infrastructure exclusion and management plan
shall be submitted for approval in writing by the Council as Planning Authority,
in consultation with Network Rail. The management plan shall, as a minimum,
confirm full details of the location, design and height of a suitable trespass
proof fence, for the exclusion of any persons from network infrastructure
located within the site boundary.  Details shall also be confirmed for the
fence's future maintenance and renewal and or any other management of
Network Rail infrastructure onsite.   
Reason: In order to promote and provide rail safety.   
Waste Management   
24. As part of the first application for the Approval of Matters Specified by
Condition 1, a detailed waste management strategy for this development,
confirming any waste and recycling facility enclosures or waste and recycling
facility storage areas and associated locations for bin presentation, shall be
submitted for the written agreement of the Council as Planning Authority.  The
duly approved scheme shall be implemented prior to the development being
brought into use and shall thereafter be retained in accordance with the
approved scheme. 
Reason: To facilitate appropriate waste management within the development. 
Page 36 of 42

Page 37

Transport and Road Safety 
25. As part of the first application for the Approval of Matters Specified by
Condition 1, the detailed design for the proposed upgraded A 85(T) / site
access junction, as generally illustrated on Drawing SK01 Revision P1 (dated
06 August 2021) and taking account of the recommendations made in the
Stage 1 Road Safety Audit, shall be submitted to, and approved in writing by,
the Council, in consultation with Transport Scotland, as the trunk roads
authority. 
All works are to be to a standard compliant with DMRB CD 123 (Geometric
design of at-grade priority and signal-controlled Junctions). 
Reason: To minimise interference with the safety and free flow of the traffic on
the trunk road.   
26. As part of the first application for the Approval of Matters Specified by
Condition 1, a comprehensive Travel Plan that sets out proposals for reducing
dependency on the private car shall be submitted and approved in writing by
the Council, in consultation with Transport Scotland, as the trunk roads
authority. The Travel Plan shall identify the measures to be implemented, the
system of management, monitoring, review, reporting and the duration of the
plan. 
Reason: To be consistent with the requirements of Scottish Planning Policy
(SPP) and PAN 75 Planning for Transport. 
27. As part of the first application for the Approval of Matters Specified by
Condition 1, details for the design, construction, and ongoing maintenance of
a barrier along the boundary of the site with the trunk road, shall be submitted
and approved in writing by the Council, in consultation with Transport
Scotland, as the trunk roads authority.   
Reason: To minimise interference with the safety and free flow of the traffic on
the trunk road. 
28. As part of any application for the Approval of Matters Specified by Condition
1, a Construction Traffic Management Plan (CTMP) has been prepared and
approved in writing by Perth and Kinross Council, in consultation with
Transport Scotland as the trunk roads authority. 
Reason: To minimise interference with the safety and free flow of the traffic on
the trunk road, to ensure the safety of pedestrians and cyclists using the trunk
road and adjacent facilities, and to be consistent with current guidance and
best practice. 
29. As part of the first application for the Approval of Matters Specified by
Condition 1, a signing strategy that sets out proposals for sign provision on
the public road network shall be submitted and approved in writing by the
Council, in consultation with Transport Scotland, as the trunk roads authority.
The signage strategy shall include, and set out, a date for implementation.
Page 37 of 42

Page 38

Thereafter, the adopted strategy shall be implemented prior to the
development being first brought into use.   
Reason:  In the interests of road safety 
30. As part of any application for the Approval of Matters Specified by Condition
1, where the developer seeks to secure details for any of the holiday chalets
hereby approved, full parking and access details for those chalets shall be
demonstrated and agreed by the Council, as Planning Authority, in writing.  A
minimum of two parking spaces per chalet shall be provided. 
Reason: To provide a suitable parking provision for the development.   
31. As part of the first application for the Approval of Matters Specified by
Condition 1, the applicant shall provide details of the electric charge points for
vehicles to be supplied on site, which will be agreed and approved in writing
by the Council, as Planning Authority. 
Reason: To provide a suitable electric charging provision for the development. 
32. As part of any application for the Approval of Matters Specified by Condition
1, the applicant shall provide an updated trip rate forecast for the site, in
particular for the retailing elements of the project, which shall be agreed in
writing by the Council, as Planning Authority. 
Reason: In the interests of road safety 
33. As part of the first application for the Approval of Matters Specified by
Condition 1, the developer shall submit a proposal for the consideration and
written approval of the Council, as Planning Authority, for the construction of a
footway, including dropped kerbs, along the frontage of Kinfauns Holdings
and/or between Kinfauns Holdings and Walnut Grove to the west of the site.
Thereafter, the proposed development shall not be occupied until the
approved proposals have been implemented to the satisfaction of the Council,
as Planning Authority. In the event a suitable footway construction cannot be
agreed within the site frontage, offsite works at another location may be
agreed with the planning authority in consultation with the Council’s Transport
Planning Team and delivered in the above timeframe.   
Reason: In the interests of road safety; to ensure an acceptable standard of
construction within the public road boundary. 
34. The development shall not see groundworks commence until vehicle wheel
cleansing facilities have been installed and brought into operation on the site,
the design and siting of which shall be subject to the prior approval of Perth
and Kinross Council, in consultation with Transport Scotland, as the trunk
roads authority. 
Reason: To ensure that material from the site is not deposited on the trunk
road to the detriment of road safety.   
Page 38 of 42

Page 39

35. All vehicles transporting construction material to, and from, the proposed
development should be sheeted. 
Reason: To ensure that material from the site is not deposited on the trunk
road to the detriment of road safety. 
36. As part of the first application for the Approval of Matters Specified by
Condition 1, a phasing plan shall be submitted for the written approval of the
Council, as Planning Authority, which details the delivery of the on-site
parking provision and its relationship to the Park and Choose facility.  The
phasing plan shall include indications of access between both the on-site
parking and the Park and Choose facility, and to the public road network, as
well as delivery timelines for each element. 
Reason: To ensure that the development is compatible with the Park and
Choose facility and includes for delivery programming. 
B JUSTIFICATION 
The development is considered to be a significant departure from the Local
Development Plan 2 (2019). However, there are material planning
considerations in this instance which justify an approval recommendation. 
C PROCEDURAL NOTES 
Permission shall not to be issued until the Section 75 Agreement has been
signed and registered to take account of this application. The legal agreement
should be concluded and completed within 4 months of the date of any
Committee approval. Failure to conclude a legal agreement within 4 months
will result in the planning application being re-assessed through failing to
comply with the associated developer contributions policy and may be
ultimately recommended for refusal under delegated powers. 
D INFORMATIVES 
1. An Application for the Approval of Matters Specified in Conditions shall be
made before the expiration of 3 years from the date of the grant of planning
permission in principle, unless an earlier application for such approval has
been refused or an appeal against such refusal has been dismissed.  In which
case application for the approval of all outstanding matters specified in
conditions must be made within 6 months of the date of such refusal or
dismissal. 
2. The approved development shall be commenced no later than the expiration
of 3 years from the date of granting of planning permission in principle or 2
years from the final approval of matters specified in conditions, whichever is
later.   
3. The developer is advised to contact Perth and Kinross Heritage Trust on
01738 477080, to discuss terms of reference for work required. This advice is
based on information held on the Perth and Kinross Historic Environment
Page 39 of 42

Page 40

Record. This database of archaeological sites and historic buildings is
regularly updated. 
4. Part of the approved development includes 'caravans', i.e. the ‘chalets’.  The
developer is advised that caravans require to be licensed under the terms of
Section 1 of the Caravan Sites and Control of Development Act 1960 and
therefore a licence application should be made to Environmental Health. 
Application forms are available at
https://www.pkc.gov.uk/article/15600/Licence-caravan-site.   
5. The granting of planning permission does not stop the continued right of
public access along the existing core path WCAR/119. An order under the
Town and Country Planning (Scotland) Act 1997, Section 208 or an
amendment of the Core Path Plan under the Land Reform (Scotland) Act
2003 should be sought in advance of any works authorised by this planning
permission being commenced.  All relevant approvals should be in place prior
to any stopping up and diversion of the core path taking place. 
6. The applicant is advised that any proposed signage will require a further
application to be submitted for advertisement consent, unless it benefits from
express consent as per the Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984. 
7. Please be aware that the Planning Permission in Principle may be invalidated
by the felling of trees which are required to be retained, prior to gaining
Approval of Matters Reserved by Condition. 
8. The applicant is advised that, in terms of Sections 56 of the Roads (Scotland)
Act 1984, he/she/they must obtain from the Council, as Roads Authority,
consent to open an existing road or footway prior to the commencement of
works.  Information on junction types, requirements for Vehicular Access
consents (VA1) and application forms are available at
www.pkc.gov.uk/vehicleaccess.   
9. Advice on the disposal of surface water should be sought at the initial stages
of design from Scottish Water and SEPA. 
10. The applicant is advised that the granting of planning permission does not
guarantee a connection to Scottish Water’s assets.  The applicant must make
a separate application to Scottish Water Planning & Development Services
team for consent to connect to the public wastewater system and/or water
network and all their requirements must be fully adhered to. 
11. Proposed site lighting designs will need to be submitted to Network Rail's
Asset Protection Engineers for approval.  The position of the lights, the type
of lights and the throw of the lighting: e.g., a sodium light on third party land
can 'wash-out' a driver's ability to perceive a signal set at red.  To the train
driver, the signal could be perceived as yellow and the driver would proceed
even though a red signal indicates danger and to stop. 
Page 40 of 42

Page 41

12. No vegetation or planting shall encroach or be able to fall within 4m of any
Network Rail infrastructure.   
13. Where any works cannot be carried out in a "fail-safe" manner, it will be
necessary to restrict those works to periods when the railway is closed to rail
traffic i.e. by a "possession" which must be booked via Network Rail's Asset
Protection Engineer and are subject to a minimum prior notice period for
booking of 20 weeks.  The Network Rail Asset Protection Engineers can be
contacted regarding the above matters.   
14. The applicant is advised that licences under The Water Environment
(Controlled Activities) (Scotland) Regulations 2011 (CAR) would be needed.
SEPA Officers recommend that the applicant makes early contact with the
relevant local regulatory team to discuss the details of the drainage proposals
and or wastewater treatment.  Details of regulatory requirements and good
practice advice for the applicant can be found on the Regulations section of
our website.  If you are unable to find the advice you need for a specific
regulatory matter, please contact a member of the regulatory services team at
the local SEPA office at: FASP@SEPA.org.uk   
15. The applicant is advised that any proposed signage will require a further
application to be submitted for advertisement consent, unless it benefits from
express consent as per the Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984.   
16. No work shall be commenced until an application for building warrant has
been submitted and approved. 
17. As soon as practicable after the development is complete, the person who
completes the development is obliged by section 27B of the Town and
Country Planning (Scotland) Act 1997 (as amended) to give the Planning
Authority written notice of that position. 
18. This planning permission will last only for three years from the date of this
decision notice, unless the development has been started within that period
(see section 58(1) of the Town and Country Planning (Scotland) Act 1997 (as
amended)). 
19. Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended), the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended
to commence the development.  A failure to comply with this statutory
requirement would constitute a breach of planning control under section
123(1) of that Act, which may result in enforcement action being taken. 
Page 41 of 42

Page 42

Author 
Name   Designation  Contact Details 
Jamie Torrance  Planning Officer (Major
Applications)    
(01738) 475000 
CommitteeReports@pkc.gov.uk 
Approved  
Name  Designation  Date 
Barbara Renton  Executive Director
(Communities) 
10 August 2022 
Page 42 of 42