Perth and Kinross Council
Planning and Placemaking Committee – 17 May 2023
Pre-Application Report by Head of Planning and Development
(Report No. 23/140) 
Erection of 50 dwellinghouses, formation of SUDS, landscaping, footpaths and
associated works (allocated site H24) on land 150 metres south west of Moncur
Farm, Moncur Road, Inchture 
Ref. No: 23/00004/PAN 
Ward No: P1 – Carse of Gowrie 
Summary 
This report is to inform the Committee of a potential forthcoming planning
application in respect of a major development for the erection of 50
dwellinghouses, formation of SUDS, landscaping, footpaths and associated works
(allocated site H24) at Land 150 Metres South West Of Moncur Farm, Moncur
Road, Inchture. The report also aims to highlight the key planning policies and the
likely stakeholders who would be involved in the decision making process, and to
offer a brief overview of the key planning issues which are likely to be relevant to
the proposal. 
BACKGROUND AND DESCRIPTION 
1 In accordance with the provisions of the Town & Country Planning (Scotland)
Act 1997 (as amended), the applicants submitted a Proposal of Application
Notice (PoAN) on 27 March 2023. The purpose of this report is to inform the
Planning and Placemaking Committee of a forthcoming planning application in
respect of a major development for the erection of 50 dwellinghouses,
formation of SUDS, landscaping, footpaths and associated works (allocated
site H24) at Land 150 Metres South West of Moncur Farm, Moncur Road,
Inchture. 
2 Pre-application reports give the Committee an opportunity to raise issues
which it would like to see addressed in the planning application. 
3 This PoAN seeks to formally establish a major development comprising
erection of 50 dwellinghouses, formation of SUDS, landscaping, footpaths and
associated works (allocated site H24). The exact range of uses, scale and
design of the development will be arrived at during pre-application
discussions. 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) 
4 Due to the scale of the proposal it will require to be screened as to whether
the proposal is an EIA development under the EIA 2017 Regulations. A
screening request is required to be submitted by the applicant.

Page 2

PRE-APPLICATION PROCESS 
5 The PoAN (reference 23/00004/PAN) confirmed that a public exhibition will be
held at Inchture Village Hall, Main Street, Inchture PH14 9RN on Tuesday
24 April between 16.30 and 19.30 with a second event on Tuesday 20 June
between 16.30 and 19.30. The Ward Councillors, MP, MSP and Inchture Area
Community Council have been notified. The results of the community
consultation will be submitted with the planning application as part of the
required Pre-Application Consultation (PAC) Report. 
DEVELOPMENT PLAN 
6 The Development Plan for the area comprises National Planning Framework
4 (NPF4) and the Perth and Kinross Local Development Plan 2 (2019)
(LDP2). 
National Planning Framework 4 
7 The National Planning Framework 4 (NPF4) is the Scottish Government’s
long-term spatial strategy with a comprehensive set of national planning
policies.  This strategy sets out how to improve people’s lives by making
sustainable, liveable and productive spaces.   
8 NPF4 was adopted on 13 February 2023. NPF4 has an increased status over
previous NPFs and comprises part of the statutory development plan. 
9 The Council’s assessment of this application has considered the following
policies of NPF4: 
• Policy 1: Sustainable Places
• Policy 2: Climate Mitigation and Adaptation
• Policy 3: Biodiversity
• Policy 6: Forestry, Woodland and Trees
• Policy 7: Historic Assets and Places
• Policy 13: Sustainable Transport
• Policy 14: Design, Quality and Place
• Policy 16: Quality Homes
• Policy 18: Infrastructure First
• Policy 20: Blue and Green Infrastructure
• Policy 21: Play, recreation and Sport
• Policy 22: Flood Risk and Water Management
• Policy 24: Digital Infrastructure
• Policy 26: Business and Industry 
Perth and Kinross Local Development Plan 2019 
10 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for
the area and states that, “Our vision is of a Perth and Kinross which is
dynamic, attractive and effective which protects its assets whilst welcoming

Page 3

population and economic growth.” It is the most recent statement of Council
policy and is augmented by Supplementary Guidance. 
11 The principal relevant policies are, in summary; 
• Policy 1A: Placemaking 
• Policy 1B: Placemaking
• Policy 1D: Placemaking
• Policy 2: Design Statements  
• Policy 5: Infrastructure Contributions
• Policy 14B: Open Space Retention and Provision: Open Space within
New Developments
• Policy 15: Public Access 
• Policy 17: Residential Areas
• Policy 20: Affordable Housing 
• Policy 23: Delivery of Development Sites 
• Policy 25: Housing Mix 
• Policy 26B: Scheduled Monuments and Archaeology: Archaeology
• Policy 28A: Conservation Areas: New Development
• Policy 32: Embedding Low & Zero Carbon Generating Technologies in
New Development
• Policy 40A: Forestry, Woodland and Trees: Forest and Woodland
Strategy
• Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
• Policy 41: Biodiversity 
• Policy 42: Green Infrastructure 
• Policy 52: New Development and Flooding 
• Policy 53B: Water Environment and Drainage: Foul Drainage
• Policy 53C: Water Environment and Drainage: Surface Water Drainage
• Policy 53E: Water Environment and Drainage: Water Supply
• Policy 55: Nuisance from Artificial Light and Light Pollution
• Policy 56: Noise Pollution 
• Policy 58A: Contaminated and Unstable Land: Contaminated Land
• Policy 59: Digital Infrastructure 
• Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
• Policy 61: Airfield Safeguarding 
OTHER POLICIES 
12  The following non statutory guidance and documents are of particular
importance in the assessment of this application:- 
• Planning Guidance - Delivery of Development Sites
• Planning Guidance - Planning & Biodiversity
• Conservation areas
• Supplementary Guidance - Renewable & Low Carbon Energy (draft)
• Developer Contributions Supplementary Guidance April 2016

Page 4

• Perth and Kinross Community Plan 2013/2023
• Perth City Plan 2015-2016
• Perth and Kinross Local Transport Strategy (2010)
• Perth’s Transport Future Project: Phase 2 Cross Tay Link Road
Preferred Route - Report by Depute Chief Executive, Environment
(Sustainability, Strategic and Entrepreneurial Development) – 14
December 2016 
NATIONAL GUIDANCE 
13 The Scottish Government expresses its planning policies and guidance
through the National Planning Framework, Planning Advice Notes, Creating
Places, Designing Streets, National Roads Development Guide and a series
of Circulars.   
Planning Advice Notes 
14 The following Scottish Government Planning Advice Notes are likely to be of
relevance to the proposal:- 
• PAN 2/2011 Planning and Archaeology
• PAN 3/2010 Community Engagement
• PAN 40 Development Management
• PAN 51 Planning, Environmental Protection and Regulation
• PAN 61 Planning and Sustainable Urban Drainage Systems
• PAN 73 Rural Diversification
• PAN 75 Planning for Transport 
PLANNING SITE HISTORY 
15 17/00003/PAN On 22 March 2017 for Residential development at LDP site
H24 
16 17/00943/FLM Full Planning Permission Major application was Withdrawn On
28 September 2017 for Erection of 74no. dwellinghouses, formation of a
SUDS pond, landscaping and associated works (allocated site H24) 
17 17/02159/FLM Full Planning Permission Major was Refused On 15 March
2018 for Erection of 66no. dwellinghouses, formation of SUDS pond,
landscaping and associated works (allocated site H24) 
18 18/00232/SCRN On 5 March 2018 for Erection of 66no. dwellinghouses,
formation of SUDS pond, landscaping and associated works (allocated site
H24) 
19 22/00014/PAN On 10 June 2022 for Erection of 50 dwellinghouses, formation
of SUDS, landscaping, footpaths and associated works (allocated site H24)

Page 5

CONSULTATIONS 
20 As part of the planning application process the following would be consulted – 
External 
• Scottish Environment Protection Agency
• Scottish Water
• Transport Scotland
• Perth and Kinross Heritage Trust 
• Inchture Community Council
• Dundee Airport
• NatureScot
• Historic Environment Scotland  
Internal 
• Environmental Health – Noise 
• Environmental Health – Contaminated Land
• Planning and Housing Strategy
• Development Contributions Officer
• Community Greenspace
• Transportation and Development
• Structures and Flooding
• Waste Services
• Biodiversity Officer 
KEY ISSUES AGAINST WHICH A FUTURE APPLICATION WILL BE
ASSESSED 
21 The key considerations against which the eventual application will be
assessed include: 
a. Visual Impact 
b. Scale, Design and Layout 
c. Relationship to Nearby Land Uses 
d. Natural Heritage and Ecology
e. Landscape
f. Water Resources and Soils 
g. Air Quality  
h.  Transport Implications 
i.  Impact on Agriculture
j.  Archaeology and Cultural Heritage 
ADDITIONAL STATEMENTS WHICH WILL BE REQUIRED 
22 Should an EIA Report not be required the following supporting documents will
need to be submitted with any planning application: 
• Planning Statement

Page 6

• Design and Access Statement
• Pre-Application Consultation (PAC) Report
• Leisure/Economic Impact Assessment 
• Transport Assessment
• Flood Risk and Drainage Assessment
• Landscape and Visual Impact Assessment
• Tree and Woodland Survey
• Habitat Survey
• Archaeological Assessment
• Sustainability Assessment 
CONCLUSION AND RECOMMENDATION 
23 This report summarises the key issues which should be considered as part of
the appraisal of any subsequent planning application which may be lodged in
respect of this development and members are recommended to note these
key issues and advise officers of any other issues which they consider should
be included as part of the application and assessment.  
Background Papers: None
Contact Officer: Kirsty Strong 
Date: 5 May 2023 