Perth and Kinross Council
Planning & Placemaking Committee – 23 November 2022
Pre-Application Report by Head of Planning and Development
(Report No. 22/288) 
Installation of a battery energy storage facility comprising battery storage units and
associated works, land 100 Metres Southwest of Birch Grove, Killichonan. 
Ref. No: 22/00020/PAN 
Ward No: P4 – Highland 
Summary 
This report is to inform the Committee of a potential forthcoming planning
application in respect of a major development for the Installation of a 20 Megawatt
(MW) grid connected battery energy storage facility along with ancillary
infrastructure, on land 100 Metres Southwest of Birch Grove, Killichonan, Loch
Rannoch. The report also aims to highlight the key planning policies and the likely
stakeholders who would be involved in the decision-making process, and to offer a
brief overview of the key planning issues which are likely to be relevant to the
proposal. 
BACKGROUND AND DESCRIPTION 
1 In accordance with the provisions of the Town & Country Planning (Scotland)
Act 1997 (as amended), the applicant has submitted a Proposal of Application
Notice (PoAN) on 5 October 2021. The purpose of this report is to inform the
Planning and Placemaking Committee of a forthcoming planning application in
respect of a major development for Muirden Energy LLP, pertaining to the
installation of a 20 MW battery energy storage facility along with associated
infrastructure. Pre-application reports give the Committee an opportunity to
raise issues which it would like to see addressed in the planning application. 
2 This PoAN seeks to formally establish a major development. The exact scale
and design of the development will be arrived at during ongoing discussions
with the applicant and are not provided at this time. 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) 
3      Due to the scale of the proposal it will require to be screened as to whether the
proposal is an Environmental Impact Assessment (EIA) development under the
EIA 2017 Regulations. A screening opinion has already been provided by the
Planning Authority for a 20 MW Battery Energy Storage at this location dated
30 September 2021. In terms of extent, scale, magnitude, complexity,

Page 2

probability, duration, frequency and reversibility, it was considered unlikely that
the development would have a significant effect on the environment. 
PRE-APPLICATION PROCESS 
4 The PoAN confirmed that two in person public events are to be held at the
Bridge of Gaur Hall on 15 November 2022 and 1 December 2022. The Ward
Councillors as well as the Rannoch Community Trust and Killiecrankie,
Fincastle and Tummel Community Council have all been notified. Subsequent
notifications will also be provided to the Local MP and MSP. The results of the
community consultation will be submitted with the planning application as part
of the required Pre-Application Consultation (PAC) Report. 
NATIONAL POLICY AND GUIDANCE 
5 The Scottish Government expresses its planning policies through the National
Planning Framework (NPF) 3, the National Roads Development Guide 2014,
Scottish Planning Policy (SPP) 2014 and Planning Advice Notes (PAN). 
National Planning Framework 
6 The NPF3 is a long-term strategy for Scotland and is a spatial expression of the
Government’s Economic Strategy and plans for development and investment in
infrastructure. Under the Planning etc (Scotland) Act 2006, this is now a
statutory document and a material consideration in any planning application.
The document provides a national context for development plans and planning
decisions as well as informing the on-going programmes of the Scottish
Government, public agencies and local authorities. 
The Scottish Planning Policy 2014 (SPP) 
7 The SPP is a statement of Scottish Government policy on land use planning.
The following sections of the SPP will be of particular importance in the
assessment of this proposal: 
• Sustainability: paragraphs 24 – 35 
• Placemaking: paragraphs 36 – 57
• Promoting Rural Development: paragraphs 74 – 91
• Supporting Business and Employment: paragraphs 92 – 108
• Valuing the Historic Environment: paragraphs 135 – 151 
• Delivering Heat and Electricity: Paragraphs 152 -174
• Valuing the Natural Environment: paragraphs 193 – 218
• Maximising the Benefits of Green Infrastructure: paragraphs 219 – 233
• Managing Flood Risk and Drainage: paragraphs 254 – 268 
8 The following Scottish Government Planning Advice Notes are likely to be of
relevance to the proposal: 
• PAN 3/2010 Community Engagement

Page 3

• PAN 1/2011 Planning and Noise
• PAN 2/2011 Planning and Archaeology
• PAN 1/2013 Environmental Impact Assessment  
• PAN 40 Development Management
• PAN 51 Planning, Environmental Protection and Regulation
• PAN 60 Natural Heritage 
• PAN 61 Planning and Sustainable Urban Drainage Systems
• PAN 73 Rural Diversification
• PAN 79 Water and Drainage 
• Energy Storage: Planning Advice (2011) 
LOCAL POLICY AND GUIDANCE 
TAYplan Strategic Development Plan 2016-2036 
9 TAYplan sets out a vision for how the region will be in 2032 and what must
occur to bring about change to achieve this vision. The vision for the area as
set out in the plan states that: 
“By 2032 the TAYplan region will be sustainable, more attractive, competitive
and vibrant without creating an unacceptable burden on our planet. The quality
of life will make it a place of first choice where more people choose to live,
work, study and visit, and where businesses choose to invest and create jobs” 
10 The following sections of the TAYplan 2016 are of particular importance in the
assessment of this application: 
• Policy 1 – Location Priorities 
• Policy 2 – Shaping better quality places
• Policy 3 – A First Choice for Investment 
• Policy 7 – Energy, Waste and Resources 
• Policy 9 – Managing Tayplan’s Assets 
Perth and Kinross Local Development Plan 2019 
11 The Local Development Plan 2 (LDP2) was adopted by Perth and Kinross
Council on 29 November 2019.  It is the most recent statement of Council
policy and is augmented by Supplementary Guidance. 
12 The LDP2 sets out a vision statement for the area and states that: 
“Our vision is of a Perth and Kinross which is dynamic, attractive and effective
which protects its assets whilst welcoming population and economic growth.” 
13 Under the LDP2, the following polices are of particular importance in the
assessment of this application: 
• Policy 1: Placemaking 
• Policy 2: Design Statements

Page 4

• Policy 8: Rural Business and Diversification
• Policy 15: Public Access 
• Policy 26B Archaeology 
• Policy 27A Listed Buildings 
• Policy 32: Embedding Low & Zero Carbon Generating Technologies in New
Development
• Policy 33A: Renewable and Low Carbon Energy: New Proposals for
Renewable and Low-Carbon Energy
• Policy 35: Electricity Transmission Infrastructure
• Policy 37: Management of Inert and Construction Waste
• Policy 38B National Designations 
• Policy 39: Landscape 
• Policy 40: Forestry, Woodland and Trees 
• Policy 41: Biodiversity 
• Policy 42: Green Infrastructure 
• Policy 47 River Tay catchment Area 
• Policy 52: New Development and Flooding 
• Policy 53: Water Environment and Drainage
• Policy 55: Nuisance from Artificial Light and Light Pollution 
• Policy 56: Noise Pollution 
• Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals 
OTHER POLICIES 
14 The following supplementary guidance and documents may be of particular
importance in the assessment of this application: 
• Placemaking Supplementary Guidance March 2020
• Landscape Supplementary Guidance February 2020
• Flood Risk and Flood Risk Assessments – Developer Guidance June 2021
• Perth and Kinross Green and Blue Infrastructure (2020) 
• Renewables and Low Carbon Energy (draft) 
• Perth and Kinross Community Plan 2013/2023 
PLANNING SITE HISTORY  
15 21/01700/SCRN: Screening Opinion Request for the Installation of a 20MW
grid connected battery storage facility and associated infrastructure on land 100
Metres Southwest of Birch Grove, Killichonan. Opinion Issued 30th September
2021. 
CONSULTATIONS 
16 As part of the planning application process the following would be consulted:

Page 5

External 
• Scottish Environment Protection Agency (SEPA)
• NatureScot
• Scottish Water 
• Transport Scotland
• Perth and Kinross Heritage Trust (PKHT)
• Historic Environment Scotland 
• Rannoch Community Trust 
• Killiecrankie, Fincastle and Tummell Community Council (Rannoch
Community Council is not active) 
Internal 
• Environmental Health 
• Strategic Planning and Policy
• Developer Contributions Officer
• Community Greenspace including Access
• Transport Planning
• Structures and Flooding
• Biodiversity Officer 
KEY ISSUES AGAINST WHICH A FUTURE APPLICATION WILL BE
ASSESSED 
17 The key considerations against which the eventual application will be assessed
include: 
• Planning Statement 
• Impacts on local Archaeology in the area
• Impacts on the setting of Rannoch Power Station listed as a Category A
Listed Building  
• Noise from Operation on nearby residents 
• Biodiversity impacts, including protected species 
• Flood and drainage impacts
• Landscape and visual impacts, including on the National Scenic Area 
• Traffic and Transport Impacts     
ADDITIONAL STATEMENTS WHICH WILL BE REQUIRED 
18 The following supporting documents will need to be submitted with any
planning application: 
• Planning Statement 
• Design and Access Statement 
• Pre-Application Consultation (PAC) Report 
• Transport Assessment 
• Flood Risk and Drainage Assessment

Page 6

• Landscape and Visual Impact Assessment 
• Noise and Light Assessment 
• Grid Connection Site Survey  
• Construction Traffic Management Plan 
• Habitat survey, including protected species 
• Construction Method statement 
CONCLUSION AND RECOMMENDATION 
19 This report summarises the key issues which should be considered as part of the
appraisal of any subsequent planning application which may be lodged in respect
of this development and members are recommended to note these key issues
and advise officers of any other issues which they consider should be included
as part of the application and assessment. 
Background Papers: None
Contact Officer: Jamie Torrance  
Date: 11 October 2022 