Democracy Spraffa

23/01665/Fll

Perth and Kinross Council · 13 March 2024
Back to Planning and Placemaking Committee — 13 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Perth and Kinross Council
Planning and Placemaking Committee – 13 March 2024
Report of Handling by Strategic Lead – Economy, Development & Planning
(Report No. 24/76) 
PROPOSAL: Erection of a wind turbine (up to 2.3 MW), formation of access
track, hardstanding and construction compound, and associated
works 
LOCATION: Simon Howie Butchers, Findony Farm, Dunning, Perth PH2 0RA 
Ref. No: 23/01665/FLL
Ward No: P7- Strathallan 
Summary 
This report recommends approval of the application. The development is not
considered to fully comply with the relevant provisions of the Development Plan
however there are material considerations apparent which outweigh these minor
departures from the Development Plan. 
BACKGROUND AND DESCRIPTION OF PROPOSAL 
1 Planning permission is sought for the erection of a wind turbine and associated
works on land at Findony Farm, Dunning. The turbine would be a maximum of
c.104m to blade tip, have a hub height of c.69m and a generation capacity of up
to 2.3MW. 
2 The site is in the corner of a field used for grazing livestock associated to
Findony Farm.  That siting some 270m southwest of the Simon Howie Butchers
factory, south of Dunning and around 550m from the southern edge of the
Dunning Conservation Area.  Access would be off the B934, via the factory
site/Findony Farm. A hardstanding area of 45 m x 65 m and a 72m long section
of access track, as well as a hardstanding/crane area are also proposed. Around
170 metres of existing access track will also be upgraded. A site compound is
also proposed in the northeast part of the site. 
3 The wind turbine is proposed to essentially be co-located and work in partnership
with recently installed solar panels. The supporting statement states that the aim
of the applicant is to reduce carbon emissions by 500 tonnes per year.  An
allowance for deviation from the exact position is proposed ‘micrositing’ and
discussions have confirmed that this would be limited to a 10m radius, if required.

Page 2

4 The proposed turbine is an Enercon E70 E4 2.3MW machine with a 69m hub
height and a 70m rotor diameter, giving the total maximum height of 104m. The
proposed colour finish is semi-matt pale grey. 
5 It is noted that discussions are ongoing with Scottish and Southern Electricity
Networks, with regard to how the project would connect to the National Grid. 
Pre-Application Consultation 
6 Pre-application Reference: None.  
7 The proposed development is not classed as a Major development in terms of
the Town and Country Planning (Hierarchy of Developments) (Scotland)
Regulations 2009, therefore the applicant was not required to undertake any
formal pre-application consultation with the local community. 
DEVELOPMENT PLAN 
8 The Development Plan for the area comprises National Planning Framework 4
(NPF4) and the Perth and Kinross Local Development Plan 2 (2019) (LDP2).  
National Planning Framework 4 
9 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve people’s lives by making sustainable, liveable
and productive spaces. 
NPF4 was adopted on 13 February 2023. NPF4 has an increased status over
previous NPFs and comprises part of the statutory development plan. 
 
The Council’s assessment of this application has considered the following
policies of NPF4:   
• Policy 1: Tackling the Climate and Nature Crises
• Policy 2: Climate Mitigation and Adaptation
• Policy 3: Biodiversity
• Policy 4: Natural Places
• Policy 7: Historic Assets and Places
• Policy 11: Energy
• Policy 22: Flood Risk and Water Management 
Perth and Kinross Local Development Plan 2 
10 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and

Page 3

economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance. 
11 The principal relevant policies are: 
• Policy 1A: Placemaking
• Policy 1B: Placemaking
• Policy 2: Design Statements
• Policy 5: Infrastructure Contributions
• Policy 6: Settlement Boundaries
• Policy 15: Public Access
• Policy 26A: Scheduled Monuments and Archaeology: Scheduled Monuments
• Policy 26B: Scheduled Monuments and Archaeology: Archaeology
• Policy 27A: Listed Buildings
• Policy 28A: Development within Conservation Areas
• Policy 33: Renewable and Low-Carbon Energy
• Policy 39: Landscape
• Policy 41: Biodiversity
• Policy 50: Prime Agricultural Land
• Policy 51: Soils
• Policy 52: New Development and Flooding
• Policy 53C: Water Environment and Drainage: Surface Water Drainage
• Policy 56: Noise Pollution
• Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals 
Statutory Supplementary Guidance 
- Supplementary Guidance - Airfield Safeguarding (adopted in 2020)
- Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2020)
- Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
- Supplementary Guidance - Housing in the Countryside (adopted in 2020)
- Supplementary Guidance - Landscape (adopted in 2020)
- Supplementary Guidance - Placemaking (adopted in 2020 
OTHER POLICIES 
Non-Statutory Guidance
 
 
- Planning Guidance - Planning & Biodiversity
- Conservation areas
- Planning Guidance - Ancillary & Annex Accommodation
- Supplementary Guidance - Renewable & Low Carbon Energy (draft)

Page 4

NATIONAL GUIDANCE 
 
12 The Scottish Government expresses its planning policies through The National
Planning Framework, Planning Advice Notes, Creating Places, Designing
Streets, National Roads Development Guide and a series of Circulars. 
Planning Advice Notes 
13 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal: 
• PAN 40 Development Management
• PAN 51 Planning, Environmental Protection and Regulation
• PAN 61 Planning and Sustainable Urban Drainage Systems
• PAN 68 Design Statements
• PAN 69 Planning and Building Standards Advice on Flooding
• PAN 75 Planning for Transport
• PAN 77 Designing Safer Places 
Creating Places 2013 
14 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places. 
Designing Streets 2010 
15 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places. 
National Roads Development Guide 2014 
16 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision. 
SITE HISTORY 
17 05/02043/FUL Planning permission was approved on 17 March 2006 for an new
reception area, offices and production area at the factory. 
18 13/01131/FLL Planning permission was approved on 31 July 2013 for the
installation of solar PV panels at the factory.

Page 5

19 13/01282/FLL Planning permission was approved for alterations and extension to
existing factory butchery building on 19 November 2013. 
20 16/02139/FLL Planning permission was approved on 16 February 2017 for the
extension to the factory building. 
21 17/00031/FLL Planning permission was approved on 17 March 2017 for an
agricultural building. 
22 17/00032/FLL Planning permission was approved on 17 March 2017 for an
agricultural building. 
23 22/01925/FLL Planning permission was approved on 18 January 2023 for the
installation of a ground mounted solar array. 
24 23/00880/SCRN A screening opinion was requested and issued on 15 June 2023
by Perth and Kinross Council, advising that a proposed wind turbine was not EIA
development and an Environmental Statement was not required. 
25 23/01409/FLL Planning permission was approved for the erection of a switch
room on 12 October 2023. 
CONSULTATIONS 
26 As part of the planning application process the following bodies were consulted: 
External 
27 Historic Environment Scotland - No objection. Advise that the proposal
appeared to have the potential to impact on historic assets including 7 Scheduled
Ancient Monuments, St Serf’s Church – Listed Building and Invermay Garden
and Designed Landscape. This potential was, in the HES view, not sufficiently
considered in the Supporting Statement.  However HES subsequently carried out
an assessment and concludes that the development may not affect the integrity
of the setting of the monuments to such a degree as to raise issues of national
interest and as such do not object. 
28 Perth And Kinross Heritage Trust - No objection. Advise that the site is
archaeologically sensitive.  A condition is requested requiring a programme of
archaeological works prior to commencement of development.   
29 Dunning Community Council - Object. Consider the development is not
supported by NPF4, LDP2, PKC’s Renewable and Low Carbon Energy Draft
Supplementary Guidance, or the PKC Dunning Conservation Area Appraisal. 
Particularly that: there are no socio-economic impacts for the local community;
impact on the Dunning Conservation Area and other historic assets; that the
proposals are EIA development; community consultation should have been
undertaken; drainage and water supply concerns; impact on telecommunications
and broadcasting signals; shadow flicker; noise; ability of the road network to

Page 6

allow the turbine to be delivered; impact on the core path; wider visual impacts;
adverse impact on tourism; period of time until decommissioning unclear; impact
on neighbouring Council areas from transportation; concerns that other energy
projects may result; light pollution; aircraft safety; refusal of planning application
15/00596/FLL, which proposed a turbine south of Glenfarg; and cumulative
impact from development at Findony Farm. 
30 Dundee Airport Ltd - No objection. Advise the development would not infringe
the safeguarding criteria and operation of Dundee Airport. 
31 Edinburgh Airport Ltd - No objection.  Advise that the development, if not
controlled by conditions, could conflict with safeguarding criteria. Conditions
required with regard to the an Instrument Flight Procedure (IFP) Assessment. 
32 Civil Aviation Authority - No comments. 
33 National Air Traffic Services - No objection. Advise the proposal does not
conflict with NATS safeguarding criteria. 
34 Ministry Of Defence - No objection, subject to conditions relating to aviation
lighting and aviation charting and safety management. 
Internal 
35 Community Greenspace - No comments. 
36 Development Plan Team - Policy advice provided. 
37 Conservation Officer - Raise concerns that there would be potentially significant
impact on the historic environment, and this would require to be outweighed by
other material considerations. 
38 Environmental Health (Noise) - No objection. After significant discussion with
the Agent to clarify various matters various conditions are recommended relating
to noise and shadow flicker. 
39 Biodiversity/Tree Officer - No objection, subject to conditions. 
40 Development Contributions Officer - No comments to make on this proposal in
terms of the Developer Contributions and Affordable Housing Supplementary
Guidance. 
41 Structures And Flooding - No objection, following receipt of further information. 
42 Transportation And Development - No objections, subject to conditions relating
to visibility splays, turbine delivery access and clarification on construction phase
parking.

Page 7

Representations 
43 102 representations were received. 79 objecting to the proposal.  Including the
objection from the Dunning Community Council.  The issues raised within the
representations are: 
• Visual impact
• Design – out of scale
• Impact on conservation area, scheduled ancient monuments and settings of
listed buildings 
• Impact on residential amenity – noise, shadow flicker, too close to village
• Impact on health
• Downplaying impact and inaccuracies in the heritage assessment
• Impact on users of the core path and recreational routes
• Road safety – access and construction issues
• Lack of consultation
• Contrary to Development Plan
• Light pollution from MoD lighting requirements
• Impacts many people – not justified
• Shortcomings in LVIA
• Shortcomings with Noise Assessment – no background noise
measurements 
44 The Dunning Community Council objected to the proposals expressing concern
with the scale and location close to the village and the impact on the
Conservation Area, Scheduled Monuments and other cultural heritage assets as
well as the impacts on residential amenity from noise and shadow flicker. 
Concern was expressed about the impact on local core paths and on road safety.
Whilst supporting the applicant’s desire to reduce the carbon footprint of his
business they considered that the proposal brought no local or community
benefits to the village and was contrary to the Development Plan.   
45 The material planning considerations raised are addressed in the Appraisal
section of the report. 
ADDITIONAL STATEMENTS 
Screening Opinion  EIA Not Required
Environmental Impact Assessment (EIA):
Environmental Report
Not applicable
Appropriate Assessment under Habitats
Regulations
Habitats Regulations Appraisal
AA Not Required
Design Statement or Design and Access
Statement
Supporting statement submitted
Report on Impact or Potential Impact e.g.
Flood Risk Assessment
• Drainage Impact Assessment
• Ecological Impact
Assessment

Page 8

APPRAISAL 
46 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise.  The Development Plan comprises NPF4 and the Perth and
Kinross Local Development Plan 2019.  The relevant policy considerations are
outlined in the policy section above and are considered in more detail below.  In
terms of other material considerations, this involves considerations of the
Council’s other approved policies and supplementary guidance, these are
discussed below only where relevant.   
Principle 
47 Both national Planning Framework (NPF4) policies and Local Development Plan
2 (LDP2) policies apply except where they are not compatible in which case
NPF4 policies prevail. 
48 NPF4 Policy 1, Tackling the Climate and Nature Crises outlines that all
development proposals will be given significant weight when considering the
global climate and nature crises.  Policy 2: Climate mitigation and adaptation also
supports climate mitigation proposals including to reduce emissions. 
49 NPF4 Polices 3, Biodiversity, and 4, Natural Places and LDP Policies 38,
Environment and Conservation and Policy 41, Biodiversity all protect biodiversity
and natural assets, which in turn play a role in carbon reduction. 
50 NPF4 Policy 4(a); and LDP2 Policy 3, Landscapes and NPF4 Policy 11(e)(ii) all
require assessment of landscape and visual impacts on local landscape
designations, such as the Ochil Hills, and the impact on the setting of Dunning
village.  A Landscape and Visual Impact Assessment (LVAI) has been submitted
with the application. 
51 NPF4 Policy 7, Historic Assets and Places, as well as LDP policies with regard to
cultural heritage (Policies 26, Scheduled Monuments and Archaeology, Policy
27A Listed Buildings and Policy 28, Development in Conservation areas) require
development to respect the historic environment.  An assessment of ‘Cultural
Heritage and Archaeology’ has been included in the Supporting Statement
(Section 6). 
52 The site currently largely comprises agricultural land and as such LDP2 Policy 50
and NPF4 Policy 5(b): Prime Agricultural Land should be considered.  However
the soils in question are identified as Class 3.2 within the Land Capability for
Agriculture map therefore are not ‘prime’. 
53 LDP2 Policy 51 and NPF4 Policy 5(a), Soils, are also relevant.  Again as the soils
are non-prime,  but still good quality some mitigation will be required.

Page 9

54 Policies relating to energy/renewable energy are particularly relevant.  NPF4
Policy 11, Energy is strongly supportive of renewable energy developments
including onshore wind energy. 11a specifically states support for all forms of
renewable technologies. Whilst 11e notes that proposals will demonstrate how
impacts on a range of factors are addressed through project design and
mitigation. Then also notes that ‘significant weight will be placed on the
contribution of the proposal to renewable energy generation targets and on
greenhouse gas emissions reduction targets’. 
55 LDP Policy 33D Renewable & Low Carbon Energy - Spatial Framework for Wind
reflects the previous and now superseded Scottish Planning Policy (SPP). It
identifies that the proposal falls within what was considered a Group 2 area, in
falling within the 2km community consideration buffer. This however did not
preclude wind energy development from taking place, rather it identifies potential
constraints that require further detailed consideration. 
56 LDP2 Policy 33a and NPF4 Policy 11e i: consider ‘Residential Amenity’.  In
response an assessment of potential impacts on residential amenity including
noise and shadow flicker has been included in the Supporting Statement
(Sections 8 and 9). 
57 Overall the Development Plan policy framework is considered supportive of the
principle of wind energy development. The detail of the scheme and its
compliance with Development Plan policies is set out in the sections of the report
below. 
Landscape and Visual Impact 
58 The Supporting Statement (page 32) states that the proposed location has been
chosen to represent the best compromise between technical and environmental
considerations within the land ownership boundary, to limit the turbine’s visibility
over local receptors, including residents, and to appear in scale with the
surrounding landscape.   
59 A Landscape and Visual Impact Assessment supports the application to consider
any landscape and visual impacts including on local residents. Seven viewpoints
have been selected from near, middle and distant locations as well as views from
north, south, east and west.   
60 The siting of the turbine, around 500m away from Dunning will from some
locations, such as Viewpoint 1 on the B934 to the north of the village, appear
dominant and have some impact on views to the Ochil Hills and the Local
Landscape Area designation.  The turbine will also be visually dominant in some
views from within the village, which is inevitable due to its size and the compact
nature of Dunning Village where the historic St Serf’s Church is currently one of
the highest structures.   
61 Supplementary Guidance (SG) to support Policy 39 specifically notes that
development of single wind turbines is a force for change in the area, and one of

Page 10

the objectives of the guidance is to ensure that proposals for wind turbines
should not have an adverse impact on the special qualities of the sensitive
environment (p.40). 
62 However since this SG was approved NPF4 has been adopted and has primacy
in planning decision making.  Within NPF4 Policy 11e ii provides allowance for
there being localised landscape and visual impacts from renewable energy
proposals.  In this case the visual impact will be most significant in the local
context, when the development is experienced/seen from Dunning and its
immediate surrounding environs.  There is potential for the proposal to impact on
the Ochil Hills Local Landscape Area where NPF4 a) does not support
development where it would have an unacceptable impact on the natural
environment.  However, in this case the proposal would not impact on the wider
Ochil Hills LLA designation as the impacts are largely localised and therefore are
considered to be supported through NFP4 policy 11e.  A condition (Condition 8)
can control the finish and colour of the turbine, together with the details of cabling
routing to minimise visual impact. 
63 The support for the turbine is therefore required to be balanced between the
visual amenity and character of the area and the economic and environmental
aspects in terms of reducing carbon emissions.    
Conservation Considerations 
64 Dunning Conservation Area is characterised by its distinctive street pattern
radiating from the focal point of the category A listed 12th Century church tower
of St Serf’s. The tower is a rare surviving example of this building type in
Scotland, and a dominant landmark. As set out in the Dunning Conservation
Area Appraisal; “St Serf’s Church is the key landmark building in the village. The
impressive Romanesque steeple, c.25m in height, can be seen in long views
from all directions, in vistas and in glimpse views between the densely packed
buildings of the village core” (Para. 4.5),  This indicating that the primary qualities
of the area are radiating into the centre. 
65 The church tower, as seen in views into the conservation area from the six
approach roads into the village, makes a significant contribution to the quality,
character and distinctiveness of the wider landscape.   
66 An assessment of Cultural Heritage and Archaeology has been included in the
Supporting Statement (Section 6). This notes that the assessment of setting
impacts measures the level of effect on the heritage designations within the
conservation area as “Moderate to Moderate/ Minor”, stating that intervisibility
with St Serf’s “would be prominent but would not remove the ability to appreciate
the heritage asset”. The turbine would not significantly obscure views into the
conservation area, but its presence would reduce the church tower’s visual
prominence and dominance in wider views, and change the quality and character
of the historic landscape.  It is accepted that there will be impact on heritage
assets although whether this is the overriding consideration requires to be
assessed.

Page 11

67 Historic Environment Scotland (HES) have been consulted due to the potential to
impact on a range of heritage assets, including a number of Scheduled Ancient
Monuments.  HES undertook its own assessment and concluded that the
understanding of the heritage assets could still be appreciated and experienced
and that the development would not impact to an extent that it raises issues of
national interest. 
68 Perth and Kinross Heritage Trust (PKHT) were also consulted and advise that
the site is archaeologically sensitive and that a programme of archaeological
works would be required prior to development commencing.  A condition to this
effect is recommended. (Condition 4). 
69 There will be impacts on the heritage environment and it is accepted that there
are some tensions between the proposals in relation to parts of LDP Policies 27A
(Listed Buildings), 28A (Conservation Areas), 33A (Renewable and Low Carbon
Energy) and NPF4 Policies 7 (Historic Assets and Places) and 11 (Energy). 
These seeing parts which seek to protect the historic environment as
considerations in the assessment of development proposals.  In this case it is
considered that the impacts on the historic environment are localised and that the
increased support from NPF4 for renewable energy developments changes the
balance in favour of the proposal, from what may have been the case prior to
February 2023. On this basis it is considered that the proposals can be
supported, when the proposals and the Development Plan are considered in the
round. 
Residential Amenity 
70 NPF4 policy 11e i) lists impacts on communities and individual dwellings,
including: residential amenity, visual impact, noise and shadow flicker as being
key considerations in accessing the acceptability of a renewable energy project.
LDP2 Policy 33a states that residential amenity of the surrounding area including
noise and shadow flicker should be taken into account in assessing the
acceptability of a proposal. 
Noise 
71 An assessment of the noise impacts on residential amenity has been included in
the Supporting Statement via a Noise Impact Assessment (NIA) (Section 8). The
Council’s Environmental Health team have been consulted and initially advised
that the agreed with the NIA in that further background surveys should be carried
out.  All to more fully understand the noise impact on residential properties in the
vicinity of the turbine.  In response an addendum to the NIA was produced in
December 2023 and subsequent discussions took place between EH, Planning
Officers and the Agent/Noise Consultants to fully explore the issue of noise.  This
has seen agreement reached that conditions to control the: model of turbine;
setting of noise limits (for both properties with and without a financial interest in
the development; that mitigation be applied via limiting the power output of the
turbine in certain climatic conditions; in relation to this power outputs will be
logged and made available to the Council; and that should there be any justified

Page 12

noise complaints that these will be investigated by a suitable independent
consultant. It is accepted by EH that these conditions (No’s 17-21) address noise
impacts and will protect residential amenity. 
Shadow flicker 
72 An assessment of shadow flicker on residential amenity has been included in the
Supporting Statement (Section 9).  The report states that four locations are
predicted to have theoretical potential for more than 30 hours shadow flicker per
year, a recognised threshold of significance.  However, once climatic and
operational conditions are factored in it is predicted that all properties will receive
less than this threshold. 
73 Following assessment by EH and in order to address any potential impact on
residential amenity a condition (Condition 23) is recommended to require that a
Shadow Flicker Management Plan is approved, setting out monitoring
arrangements and that any subsequently identified mitigations are set out to
ensure that shadow flicker does not impact adversely on amenity. 
Roads and Access 
74 The proposal includes: a hardstanding area at the turbine location, on-site access
track, a temporary laydown area and a temporary construction compound.  With
vehicular access via an existing private access off the B934. No new altered
vehicle junction to or from a public road is proposed. 
75 Transportation and Development do not object, subject to the maintenance of the
site entrance visibility splays (215meters x 2.4m x 1.05m) and clarification of where
maintenance vehicles will park.   
76 It is noted that there is space for parking at the turning point in the new access
track, thus no further clarification is required.  A condition is recommended with
regard to visibility splays (Condition 15). 
77 The delivery of construction materials, service vehicles and turbine components
may have implications for the surrounding public road network and a
Construction Traffic Management Plan will thus be required. (Condition 16). 
78 Objections raise road safety concerns.  However, the Roads Authority raise no
objection and the Construction Traffic Management Scheme will provide control
to ensure road safety impacts during construction and decommissioning are
appropriately managed. 
79 There is a core path that runs close to the site, within 50m.  However, this is not
within the site boundary so not be physically affected by the proposals, although
it is appreciated that the experience of users of the route will change as a result
of the presence of the turbine.

Page 13

80 Subject to conditional control the proposal is considered in accordance with
Policy 60B of the LDP, Transport Standards and Accessibility Requirements:
New Development Proposals and Policy 15, Public Access. 
Drainage and Flooding 
81 The proposed development will be on currently largely undeveloped/greenfield
land, around 270 east of Findony Farm.  There are two watercourses within the
area.  The closest is a small ditch/field drainage 25m to the southwest. The other
Is Marcassie Burn, 530m to the east. 
82 PKC’s Flood Team requested further details of the extent of the hardstanding
proposed, topographical information and further information on how runoff was
going to be dealt with, so as to ensure that any flood risk would be appropriately
managed. 
83 This additional information was provided and satisfied the Flood Team’s
requirements and ensures that the proposal complies with NPF4 Policy 22, Flood
Risk and Water Management. 
Natural Heritage and Biodiversity 
84 The Council will seek to protect and enhance all wildlife and habitats, whether
formally designated or not and planning permission will not be granted for
development likely to have an adverse effect on protected species unless clear
evidence can be provided that the ecological impacts can be satisfactorily
mitigated. 
85 An Ecological Impact Assessment (EIA) has been submitted and is in
accordance with legislation, policy and guidance and its recommendations
should be followed. 
86 Conditions will be added to ensure that recommendations within the EIA are
followed and that an updated assessment is provided if development has not
commenced within 24 months of the date of the existing assessment (Conditions
9 and 10).  A condition requiring reporting of results of 3-year post-construction
monitoring is also recommended (Condition 11). 
87 Subject to compliance with the proposed conditions the proposal is considered in
accordance with LDP2 policy 41, Biodiversity and NPF4 Policy 3, Biodiversity
and Policy 4, Natural Areas. 
Prime Agricultural Land 
88 The application site falls within land identified as Class 3.2 within the Land
Capability for Agriculture map therefore there is no impact on prime agricultural
land.

Page 14

Soils 
89 The soils are non-prime (Class 3.2), but still good agricultural land. A condition
(Condition 6) will be imposed to ensure avoidance/minimisation of soil impacts
including through appropriate techniques such as foundation design and
minimising hardstandings and soil sealing.  Subject to conditional control the
proposal is considered to accord with LDP2 Policy 51 and NPF4 Policy 5(a):,
Soils. 
Developer Contributions 
90 The site is not in an area or for a use that requires the payment of Developer
Contributions. 
Air Safety 
91 Edinburgh Airport has been consulted and advises that the proposed
development has been examined from an aerodrome safeguarding perspective
and could conflict with safeguarding criteria unless conditions to undertake
Instrument Flight Procedure (IFP) Assessment are attached to any permission. 
92 The site also falls within an MOD identified low flying area where fixed wing
aircraft may operate as low as 76.2m.  Conditions are requested with regard to
aviation charting and safety management and for the aviation lighting. Subject to
compliance with the requested conditions the MOD does not object. Whilst
Dundee Airport do not object or require conditions. 
93 Subject to conditional control (Conditions 12, 13 and 14) the proposal is
considered in accordance with Policy 61, Airfield Safeguarding of LDP2. 
Reinstatement 
94 Following construction, works will be carried out to restore and landscape track
verges, cable runs, temporary construction compounds, and temporary
hardstanding and other features not part of the permanent works.  This can be
addressed via requirements of the CEMP (Condition 5). 
Decommissioning 
95 Proposals for reinstatement and decommissioning are included in Section 2.4 of
the Supporting Statement. A condition is recommended to ensure that
decommissioning and reinstatement plans are agreed in advance and then
undertaken in accordance with the agreed plans.  Subject to compliance with the
condition (Condition 26) the proposal is considered to accord with LDP2 Policy
33c and NPF4 Policy 11e xi xii with regard to Decommissioning and
Reinstatement.

Page 15

Economic Impact 
96 The proposal represents a significant investment by Simon Howie Butchers and
supports the decarbonisation of an existing commercial business.  Submissions
advise that 141 people are currently employed at the factory and 14 live in
Dunning, a further 23 within a 5-mile radius.  Thus, the facility is a significant
local employer with substantial community economic benefits.  The proposals
represent a significant investment in the future of the business and will assist in it
becoming more self-sufficient and efficient in terms of its energy supply and
costs, costs having been volatile in recent times.  The development is anticipated
to create certainty and stability in terms of the operational costs and in turn the
future viability of the business.  Providing certainty and positivity for the long term
future of this local employer is an important aspect in the decision making
process. 
Impact on Telecommunications 
97 Relevant stakeholders (i.e. Ofcom) have been consulted by the applicant to
identify any potential impacts on telecommunications infrastructure and whether
any mitigation was necessary.  However, it concluded that there would be no
adverse impacts. See Section 10 of the Supporting Statement. 
Other matters 
98 Objectors have queried how works to the south  of the development will be
undertaken as there is no access on this side other than via Mill Cottage. 
However, access rights which may not be in place to allow for the requirements
of the development is something for the developer/applicant to agree with
adjoining landowners.  In addition, access rights for maintenance and other
private access matters are generally written into title deeds and are not material
planning considerations that can influence the determination of this planning
application. 
VARIATION OF APPLICATION UNDER SECTION 32A 
99 This application was varied prior to determination, in accordance with the terms
of section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended.  A Drainage Impact Assessment and additional noise information,
were submitted. 
PLANNING OBLIGATIONS AND LEGAL AGREEMENTS 
100 None required. 
DIRECTION BY SCOTTISH MINISTERS 
101 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 –33 there have been no directions

Page 16

by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application. 
CONCLUSION AND REASONS FOR RECOMMENDATION 
102 To conclude, the application must be determined in accordance with the 
Development Plan unless material considerations indicate otherwise. The
development is not considered to fully comply with all aspects of the NPF4 and
the adopted Local Development Plan 2 (2019).  Particularly in relation to the
impacts on the landscape and built heritage.  However there are clear material
considerations apparent, particularly in relation to decarbonising the operational
footprint of the business, providing energy security, meeting renewable energy
generation targets, reducing cost volatility to provide certainty for the businesses
viability going forward and thus greater security to the employment therein, all of
which see the planning balance applied and are considered to outweigh the
limited tensions with some aspects of the Development Plan. 
103 Accordingly the proposal is recommended for approval subject to the following
conditions. 
RECOMMENDATION   
Approve the application 
Conditions and Reasons for Recommendation 
1. This planning permission will last only for three years from the date of this
decision notice, unless the development has been lawfully started within that
period. 
Reason - This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019. 
2. The development hereby approved must be carried out in accordance with the
approved drawings and documents, unless otherwise provided for by conditions
imposed by this decision notice. 
Reason - To ensure the development is carried out in accordance with the
approved drawings and documents. 
3. For the avoidance of doubt the wind turbine model hereby approved is limited to
that specified in the submission (Enercon E70 E4 2.3MW machine with a 69m
hub height and a 70m rotor diameter) and which has informed all supporting
information and assessment by the Planning Authority, particularly that related to
noise, shadow flicker and visual impact.  No other turbine shall be installed
without a further grant of planning permission, the assessment of which will
review any changes in material planning considerations.  Reason:  In the
interests of ensuring that the impacts of the development have been accurately

Page 17

assessed and that planning conditions remain relevant to the development
implemented. 
4. Development shall not commence until the developer has secured the
implementation of a programme of archaeological work in accordance with a
Written Scheme of Archaeological Investigation (WSI) which has been submitted
by the developer and agreed in writing by the Council as Planning Authority, in
consultation with Perth and Kinross Heritage Trust (PKHT). Thereafter, the
developer shall ensure that the programme of archaeological works is fully
implemented including that all excavation, preservation, recording, recovery,
analysis, publication and archiving of archaeological resources within the
development site is undertaken.  Should the archaeological works, as required by
the WSI, identify a requirement for post-excavation analysis, the development as
approved shall not be occupied or brought into use until a Post-Excavation
Research Design (PERD) has been submitted to and agreed in writing by the
Council as Planning Authority, in consultation with PKHT. The PERD shall be
carried out in complete accordance with the approved details. Furthermore, the
developer shall afford access at all reasonable times to PKHT or a nominated
representative and shall allow them to observe work in progress. 
Reason - To ensure a programme of archaeological works is carried out to
safeguard and record any archaeological remains within the development area. 
5. Development shall not commence until a detailed Construction Environmental
Management Plan (CEMP) and Pollution Prevention Plan (PPP) detailing
environmental mitigation measures and site-specific construction method
statements, has been submitted for the further written agreement of the Council
as Planning Authority in consultation with Scottish Environment Protection
Agency (SEPA) as required.  Such details shall be submitted not less than two
months prior to the agreed scheduled commencement date and shall incorporate
detailed pollution avoidance and mitigation measures for all construction
elements.  Thereafter the development shall be fully undertaken in accordance
with the agreed CEMP. 
Reason - In the interest of proper site management.  
6. The wind turbine, buildings, areas of hardstanding and tracks shall be
constructed in the location shown on the approved plans or as per the micro-
siting allowances granted by this condition. 
Unless otherwise approved in advance in writing by the Planning Authority micro-
siting is subject to the following restrictions:
a. No wind turbine foundation shall be positioned higher, when measured in
metres Above Ordnance Datum, than the position shown on the approved
plans;
b. No wind turbine, building, mast or hardstanding shall be moved more than
10 m from the position shown on the original approved plans;
No later than one month after the date of First Commissioning, if required, an
updated site plan must be submitted to the Planning Authority showing the final

Page 18

position of the wind turbine, and associated infrastructure forming part of the
development. The plan should also specify areas where micro-siting has taken
place and, for each instance, be accompanied by copies of the Planning
Authority's approval. 
Reason - To minimise environmental impacts while taking account of the need to
site infrastructure according to local ground conditions. 
7. Prior to the commencement of development hereby approved, a Soil
Management Plan shall be submitted to and agreed in writing by the Council as
Planning Authority. The plan as approved shall be strictly adhered to concurrent
with the construction of the development. 
Reason - In the interest of proper site management 
8. Prior to the commencement of any development on site, precise colour details of
the turbine components, and details of cabling routing (which shall be
underground where possible) shall be submitted for the further written agreement
of the Council as Planning Authority. The approved details shall be implemented
in full and thereafter retained for the duration of the development. 
Reason - In the interests of visual amenity; to ensure a satisfactory standard of
local environmental quality. 
9. The conclusions and recommended action points within the supporting
biodiversity survey submitted and hereby approved (document 12 Heritage
Environmental Limited Simon Howie Butchers Wind Turbine: Ecological Impact
Assessment October 2023) shall be fully adhered to, respected and undertaken
as part of the construction and operation phase of the development, to the
satisfaction of the Council as Planning Authority.  This includes implementation of
the proposed biodiversity enhancements listed on page 39 and 40 of the EIA
which must be in place prior to the operation of the turbine. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
10. An updated ecological impact assessment will be required prior to the
commencement of works, if works have not commenced within 24 months of the
date of the ecological impact assessment survey approved as part of this
permission.  The updated survey shall be submitted to the Council as Planning
Authority for written agreement and works shall not commence until after such
written agreement has been issued by the Council. 
Reason - In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981). 
11. The annual results from the three-year post-construction monitoring shall be
reported to Biodiversity@pkc.gov.uk by 31st October each year.

Page 19

Reason - To ensure that the impact on biodiversity from the development is
monitored and recorded. 
12. No structure or tower may be erected, unless and until such time as the Local
Planning Authority receive confirmation from the Airport Operator in writing that:
(a) an IFP (Instrument Flight Procedure) Assessment has demonstrated that an
IFP Scheme is not required; or (b) if an IFP Scheme is required such a scheme
has been approved by the Airport Operator; and (c) if an IFP Scheme is required
the Civil Aviation Authority has evidenced its approval to the Airport Operator of
the IFP Scheme (if such approval is required); and (d) if an IFP Scheme is
required the scheme is accepted by NATS AIS for implementation through the
AIRAC Cycle (or any successor publication) (where applicable) and is available
for use by aircraft. 
Definitions:
"IFP Scheme" means a scheme to address the potential impact of the turbines
on the instrument flight procedures of Edinburgh Airport.
"IFP Assessment" means a safeguarding assessment against current and any
possible future IFPs. This assessment must be undertaken by a UK CAA
Approved Procedure Design Organisation (APDO).
Further information on IFP Safeguarding and a quote for this assessment can be
obtained by contacting safeguarding@edinburghairport.com. 
Reason - In the interests of aviation safety. 
13. Prior to commencing construction of any wind turbine generators, or deploying
any construction equipment or temporal structure(s) 50 metres or more in height
(above ground level) the undertaker must submit an aviation lighting scheme for
the approval of the Perth & Kinross Council in conjunction with the Ministry of
Defence defining how the development will be lit throughout its life to maintain
civil and military aviation safety requirements as determined necessary for
aviation safety by the Ministry of Defence. 
This should set out:
a) details of any construction equipment and temporal structures with a total
height of 50 metres or greater (above ground level) that will be deployed
during the construction of wind turbine generators and details of any
aviation warning lighting that they will be fitted with; and
b) the locations and heights of all wind turbine generators and any
anemometry mast featured in the development identifying those that will
be fitted with aviation warning lighting identifying the position of the lights
on the wind turbine generators; the type(s) of lights that will be fitted and
the performance specification(s) of the lighting type(s) to be used. 
Thereafter, the undertaker must exhibit such lights as detailed in the approved
aviation lighting scheme. The lighting installed will remain operational for the
lifetime of the development. 
Reason - In the interests of aviation safety.

Page 20

14. The undertaker must notify the Ministry of Defence, at least 14 days prior to the
commencement of the works, in writing of the following information: 
a) the date of the commencement of the erection of wind turbine generators;
b) the maximum height of any construction equipment to be used in the
erection of the wind turbines;
c) the date any wind turbine generators are brought into use;
d) the latitude and longitude and maximum heights of each wind turbine
generator, and any anemometer mast(s). 
The Ministry of Defence must be notified of any changes to the information
supplied in accordance with these requirements and of the completion of the
construction of the development. 
Reason - In the interests of aviation safety. 
15. Prior to the commencement of the development hereby approved, full visibility
splays of 215 metres along the channel line shall be provided to the left and right
of the access, at a set-back of 2.4 metres measured 1.05m above the road level
to the standard and specification required by the Council as Roads Authority to
the satisfaction of the Planning Authority.  The visibility splays shall be physically
formed on the ground and any existing fences, walls, hedges or other means of
enclosure or obstructions within the splays shall be removed and relocated
outwith the splays.  Once formed, the visibility splays shall be permanently
retained thereafter, and no visual obstruction of any kind shall be permitted within
the visibility splays so formed. 
Reason - In the interests of road safety; to ensure an acceptable standard of
construction within the public road boundary. 
16. Prior to the commencement of the development hereby approved, the applicant
shall submit for the further written agreement of the Council as Planning
Authority, in consultation with the Roads Authority (Structures), a Construction
Traffic Management Scheme (TMS) which shall include the following: 
• restriction of construction traffic to approved routes and the measures to be
put in place to avoid other routes being used; 
• timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse
collection is undertaken, on Sundays and during local events; 
• arrangements to ensure that access for emergency service vehicles are not
impeded; and 
• details of HGV movements to and from the site.

Page 21

The TMS as approved shall be strictly adhered to during the entire site
construction programme. 
Reason - In the interest of proper site management 
17. For all properties without any financial involvement, noise emanating from the
turbine during nighttime (as defined in ETSU-R-97 as 23:00 to 07:00 on all days)
shall not exceed LA90, 10 mins 35dB(A) or the ETSU-R-97 derived night hours
noise limit of LA90, 10 mins +5 dB(A) above background whichever is the
greater. In the event that audible tones are generated by the wind turbine, a
5dB(A) penalty for tonal noise shall be added to the measured noise level. 
Reason - In order to safeguard the residential amenity of the area. 
18. For all properties without any financial involvement, noise emanating from the
wind turbine at any other time than defined in condition above shall not exceed
an L A90, 10 min of 35 dB at noise sensitive properties at wind speeds not
exceeding 10m/s and measured at a height of 10m above ground at the wind
turbine site, or the ETSU-R-97 derived 'quiet waking hours noise limit of LA90, 10
mins +5dB above background, whichever is greater. In the event that audible
tones are generated by the wind turbine, a 5dB (A) penalty for tonal noise shall
be added to the measured noise level. 
Reason - In order to safeguard the residential amenity of the area. 
19. For all properties with any financial involvement, noise emanating from the
turbine during nighttime (as defined in ETSU-R-97 as 23:00 to 07:00 on all days)
shall not exceed LA90, 10 mins 45dB(A) or the ETSU -R - 97 derived night hours
noise limit of LA90, 10 mins +5 dB(A) above background whichever is the
greater. In the event that audible tones are generated by the wind turbine, a
5dB(A) penalty for tonal noise shall be added to the measured noise level. 
Reason - In order to safeguard the residential amenity of the area. 
20. For all properties with any financial involvement, noise emanating from the wind
turbine at any other time than defined in condition above shall not exceed an L
A90, 10 min of 45 dB at noise sensitive properties at wind speeds not exceeding
10m/s and measured at a height of 10m above ground at the wind turbine site, or
the ETSU-R-97 derived 'quiet waking hours noise limit of LA90, 10 mins +5dB
above background, whichever is greater. In the event that audible tones are
generated by the wind turbine, a 5dB (A) penalty for tonal noise shall be added to
the measured noise levels. 
Reason - In order to safeguard the residential amenity of the area. 
21. Mitigation measures in the form of Reduced Power mode outputs as outlined in
Section 8.8.2 of The Supporting Statement Ref C5726-1426 Section 8 v2 dated
19 December 2023 which was undertaken by Greencat Renewables shall be
implemented in full for the life time of the development.

Page 22

Reason - In order to safeguard the residential amenity of the area. 
22. Prior to the development hereby approved being brought into use, and electricity
generated, the wind turbine operator shall submit a list of proposed independent
consultants (who may undertake compliance measurements in accordance with
the above conditions) for the written agreement of the Planning Authority. 
Amendments to the list of approved consultants shall be made only with the prior
written approval of the Planning Authority. 
Reason - In order to safeguard the residential amenity of the area. 
23. Prior to the operation of the turbine a shadow flicker management plan shall be
submitted to, and approved in writing by, the planning authority. Within the plan
the applicant shall identify the range of residential properties that can be remotely
monitored for a period of one year from the commissioning, and subsequent
operation, of the turbine to study the effect that shadow flicker could have on
residential amenity. The plan shall also include mitigation measures to ensure
that shadow flicker can be mitigated to an acceptable level should justified
complaints be received following the operation of the turbine and details of a
practical procedure to remediate any shadow flicker that are capable of being
implemented by the applicant in the event of a justified complaint being
registered by the planning authority using mitigation measures detailed in the
shadow flicker management plan. 
Reason - In order to safeguard the residential amenity of the area. 
24. The wind turbine operator shall continuously log power production, wind speed
and wind direction, all in accordance with Guidance Note 1(d) of Institute of
Acoustics's Good Practice Guide to the application of ETSU-R-97 for the
Assessment and Rating of Wind Turbine Noise. These data shall be retained for
a period of not less than 24 months. The wind farm operator shall provide this
information in the format set out in Guidance Note 1(e) to the Local Planning
Authority on its request, within 14 days of receipt in writing of such a request. 
Reason - In order to safeguard the residential amenity of the area. 
25. Within 21 days from receipt of a written request from the Local Planning Authority
following a complaint to it from an occupant of a dwelling alleging noise
disturbance at that dwelling, the wind turbine operator shall, at its expense,
employ a consultant approved by the Local Planning Authority to assess the level
of noise emissions from the wind turbine at the complainant's property in
accordance with the procedures described in the Institute of Acoustics's Good
Practice Guide to the application of ETSU-R-97 for the Assessment and Rating
of Wind Turbine Noise Guidance Notes. The written request from the Local
Planning Authority shall set out at least the date, time and location that the
complaint relates to and any identified atmospheric conditions, including wind
direction, and include a statement as to whether, in the opinion of the Local
Planning Authority, the noise giving rise to the complaint contains or is likely to
contain a tonal component.

Page 23

Reason - In order to safeguard the residential amenity of the area. 
26. Within six months of the wind turbine being decommissioned the owner shall
submit a scheme for the removal of the turbine, all associated plant and
equipment and undertake restoration measures to reinstate the site to its pre-
development condition.  Thereafter the scheme as subsequently approved in
writing by the Planning Authority shall be implemented in complete accordance
with the details as so agreed. 
Reason - To ensure the turbine is removed from the site at the end of its
operational life, and to protect the visual amenity of the area. 
Justification 
The proposal is not in full accordance with the Development Plan however there
are material reasons which justify departing from the Development Plan.  There
are significant benefits that renewable energy generation will bring to the wider
business and its net zero ambitions, that accord with NPF4 Policy 11, Energy,
33A Renewable and Low Carbon Energy: New Proposals for renewable and low
carbon energy.  These considerations have been balanced against the wider
impacts, arising from the proposal due to the scale of the turbine and its location
in close proximity to the historic settlement of Dunning and other visual receptors
of note. 
On balance, the contribution of the proposal to the reduction of carbon emissions
and to the Scottish Government net zero targets are considered to outweigh the
adverse landscape and visual impacts and the impact on the setting of historic
assets.    
Procedural Notes 
None. 
Informatives 
1. Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
planning authority prior written notification of the date on which it is intended to
commence the development. A failure to comply with this statutory requirement
would constitute a breach of planning control under section 123(1) of that Act,
which may result in enforcement action being taken. Please use the form
attached herewith. 
2. As soon as practicable after the development is complete, the person who
completes the development is obliged by section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the planning authority written
notice of that position.  Please use the form attached herewith. 
3. An application for Building Warrant may be required.

Page 24

4. The developer is advised to contact Grace Woolmer-White Historic Environment
Officer (tel 01738 477056) Perth and Kinross Heritage Trust, to discuss terms of
reference for works required and, if necessary, prepare for them written Terms of
Reference. 
5. This application was varied prior to determination, in accordance with the terms
of section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended.  The variations incorporate the submission of a Drainage Impact
Assessment. 
6. The applicant is advised to refer to Perth & Kinross Council's Supplementary
Guidance on Flood Risk and Flood Risk Assessments 2021 as it contains advice
relevant to your development. https://www.pkc.gov.uk/ldp2floodrisk 
7. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk   Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request. 
The Fees Charter is available on our website www.pkc.gov.uk.   
The Council has two months to consider the information.  You should therefore
submit the required information more than two months before your permission
expires.  We cannot guarantee that submissions made within two months of the
expiry date of your permission will be able to be dealt with before your
permission lapses. 
Background Papers:  102 letters of representation
Date: 1st March 2024 
DAVID LITTLEJOHN
STRATEGIC LEAD – ECONOMY, DEVELOPMENT & PLANNING