Perth and Kinross Council
Planning and Placemaking Committee – 11 December 2024
Report of Handling by Strategic Lead: Economy, Development and Planning
(Report No. 24/359) 
PROPOSAL: Erection of 292 dwellinghouses, 48 flats, 28 detached garages, 3
retail units, a refuse/bike store and a sports changing pavilion,
formation of leisure facilities, SUDS ponds, parking areas,
landscaping and associated works, (Phase 1) (allocated site
MU73) (approval of matters specified in conditions
21/00383/IPM) 
LOCATION: Land adjacent to Huntingtowerfield & Ruthvenfield,
Huntingtowerfield, Perth 
Ref. No: 24/01023/AMM
Ward No: P5- Strathtay 
Summary 
This report recommends approval of a Matters Specified in Conditions (AMSC)
application for the erection of a total of 340 dwellings (292 houses and 48 flats), 3
retail units, a sports changing pavilion and associated infrastructure and works,
relating to Phases 1/1A and the ‘Local Centre’, in the northern part of the site, referred
to as ‘Almond Valley’. This Report concludes that the proposal is consistent with the
Development Plan, the existing Planning Permission in Principle (PPP) consent (Ref:
21/00383/IPM) and other relevant material planning considerations. 
BACKGROUND AND DESCRIPTION OF PROPOSAL 
1. The application site extends to an area of 29.2 ha and forms part of the
development site known as ‘Almond Valley’, which extends to 103 hectares (ha)
and is located immediately beyond the north-western edge of Perth. The
application site currently comprises arable and grazing farmland. However,
historically it was used for industrial purposes and there remain older properties
throughout the site, mainly associated with historic mill activities related to Perth
Lade. In addition, overland power lines pass across the site in a southwest /
northeast alignment and an underground gas main traverses the north-east
section of the site. 
2. Almond Valley is allocated as ‘Site MU73’ within the Perth and Kinross Local
Development Plan 2019 (LDP2). MU73 identified for a mixed-use development,
including up to 1,100 dwellings.

Page 2

3. The current application is for Phase 1/1A and the Local Centre of the
development and comprises 340 dwellings (292 houses and 48 flats), 3 retail
units, a sports changing pavilion and associated infrastructure and works. A
previous detailed approval has been granted for this phase (19/01433/AMM) and
remains extant. Some of the conditions of the PPP have been agreed under that
consent and, due to the similarities with the current application, do not require to
be revisited. The current application for AMSC will be required to implemented
concurrently with certain matters previously approved under AMSCs
19/01430/AMM and 19/01433/AMM. These matters are detailed in the
assessment section of the report. 
4. The developer for the previously approved permission was Stewart Milne Group.
Barratt has since sought to acquire the site, thereby requiring some amendments
to the previous approval to reflect the different house types now proposed,
alongside some other relatively minor changes to the layout. 
5. Of the 340 residential units proposed, 255 will be for sale and 85 will be
affordable homes. These dwellings comprise a mix of detached dwellinghouses,
semi-detached dwellinghouses, terraces and flats. The numbers and tenure mix
are: 
• 24 x one-bedroom cottage flats;
• 24 x two-bedroom flats;
• 7 x two-bedroom terraced dwellinghouses;
• 44 x three-bedroom terraced dwellinghouses;
• 12 x four-bedroom terraced dwellinghouses;
• 46 x three-bedroom semi-detached dwellinghouses;
• 128 x three-bedroom detached dwellinghouses; and
• 55 x three-bedroom with study detached dwellinghouses. 
6. In addition, the following is proposed: 
• Community facilities; including a retail/local centre comprising 3 units
(187sq/m total floorspace)
• Open space;
• Dedicated equipped outdoor play area;
• Sports pitches and pavilion provision adjacent to the River Almond; and
• New vehicular and pedestrian routes, including connection to the recently
constructed A9/A85 link road. 
SITE HISTORY 
7 08/00678/IPM was Refused On 5 January 2012 for Residential-led development
to provide 1,800 new homes, a primary school, leisure, retail, office facilities
along with new vehicular and pedestrian access, open space and landscaping (in
principle)

Page 3

8 10/00005/PAN On 7 May 2010 for Mixed use development comprising
residential, retail, business and industrial associated community facilities,
landscaping, car parking and infrastructure including roads and accesses 
9 14/00011/PAN On 13 October 2014 for Mixed use development compromising
residential, a primary school and community facilities 
10 14/01961/SCOP On 23 December 2014 for Scoping opinion for mixed use
development compromising residential, a primary school and community facilities 
11 15/00546/IPM application was Withdrawn On 3 July 2015 for Residential
development with school and community facilities, open space, landscaping and
associated infrastructure (in principle) 
12 15/01157/IPM was Refused On 18 May 2016 for Residential development with
school and community facilities, open space, landscaping and associated
infrastructure (in principle) 
13 19/00056/SCRN On 5 March 2019 for Construction of a road 
14 19/01430/AMM was Approved On 25 November 2022 for Formation of primary
vehicular access and associated works (approval of matters specified in
conditions of planning application 15/01157/IPM or as subsequently superseded
by application 21/00383/IPM) 
15 19/01433/AMM was Approved On 12 December 2022 for Erection of 284
dwellinghouses, 21 detached garages, 56 flats, 3 retail units, a refuse/bike store
and a sports changing pavillion, formation of boundary treatments, retaining
walls, leisure facilities, SUDS ponds, parking areas, landscaping and associated
works (approval of matters specified in conditions of planning application
15/01157/IPM or as subsequently superseded by application 21/00383/IPM)
(Phase 1 and 1A) (allocated site MU73) 
16 21/00383/IPM was Approved On 25 November 2022 for S42 application to
modify condition 8 (sustainable development) and condition 16 (residential
occupation) of permission 15/01157/IPM 
ENVIRONMENTAL IMPACT ASSESSMENT 
17 The wider Almond Valley development is of a type listed within Schedule 2 of the
EIA Regulations and has been subject of EIA screening related to the initial ‘PPP’
permission (15/01157/IPM). Additional environmental information has been
provided through EIA Addendums. 
PRE-APPLICATION CONSULTATION  
18 As an AMSC application, the applicants were not required to undertake any
formal pre-application consultation with the local community.

Page 4

DEVELOPMENT PLAN 
19 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance. 
National Planning Framework 4 
20 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies. 
This strategy sets out how to improve peoples’ lives by making sustainable,
liveable and productive spaces.  NPF4 has an increased status over previous
NPFs and comprises part of the statutory development plan. 
21 The Council’s assessment of this application has considered the following
policies of NPF4: 
• Policy 1: Tackling the Climate and Nature Crises
• Policy 2: Climate Mitigation and Adaptation
• Policy 3: Biodiversity
• Policy 7: Historic Assets and Places
• Policy 13: Sustainable Transport
• Policy 14: Design, Quality and Place
• Policy 15: Local Living and 20 Minute Neighbourhoods
• Policy 16: Quality Homes
• Policy 18: Infrastructure First
• Policy 20: Blue and Green Infrastructure
• Policy 21: Play, Recreation and Sport
• Policy 28: Retail 
Perth and Kinross Local Development Plan 2019 
22 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance. 
23 The principal relevant policies are, in summary; 
• Policy 1A: Placemaking
• Policy 1B: Placemaking
• Policy 1C: Placemaking
• Policy 2: Design Statements
• Policy 5: Infrastructure Contributions
• Policy 7B: Employment and Mixed Used Areas: Mixed Use Sites
• Policy 14B: Open Space Retention and Provision: Open Space within New
Developments

Page 5

• Policy 15: Public Access
• Policy 17: Residential Areas
• Policy 20: Affordable Housing
• Policy 23: Delivery of Development Sites
• Policy 25: Housing Mix
• Policy 26B: Scheduled Monuments and Archaeology: Archaeology
• Policy 27A: Listed Buildings
• Policy 32: Embedding Low & Zero Carbon Generating Technologies in New
Development
• Policy 38A: Environment and Conservation: International Nature
Conservation Sites
• Policy 38B: Environment and Conservation: National Designations
• Policy 38C: Environment and Conservation: Local Designations
• Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
• Policy 41: Biodiversity
• Policy 42: Green Infrastructure
• Policy 44: Perth Lade Green Corridor
• Policy 52: New Development and Flooding
• Policy 53C: Water Environment and Drainage: Surface Water Drainage
• Policy 54: Health and Safety Consultation Zones
• Policy 56: Noise Pollution
• Policy 57: Air Quality
• Policy 58A: Contaminated and Unstable Land: Contaminated Land
• Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals 
Statutory Supplementary Guidance
24
• Supplementary Guidance - Air Quality (adopted in 2020)
• Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2023)
• Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
• Supplementary Guidance - Green & Blue Infrastructure (adopted in 2020)
• Supplementary Guidance - Landscape (adopted in 2020)
• Supplementary Guidance - Open Space Provision for New Developments
(adopted in 2021)
• Supplementary Guidance - Placemaking (adopted in 2020) 
PKC NON STATUTORY GUIDANCE
25
• Planning Guidance - Delivery of Development Sites
• Planning Guidance - Planning & Biodiversity

Page 6

NATIONAL GUIDANCE 
26 The Scottish Government expresses its planning policies through Planning
Advise Notes, Creating Places, Designing Streets, National Roads Development
Guide and a series of Circulars in addition to NPF4. 
Planning Advice Notes 
27 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal: 
• PAN 51 Planning, Environmental Protection and Regulation
• PAN 61 Planning and Sustainable Urban Drainage Systems
• PAN 65 Planning and Open Space
• PAN 67 Housing Quality
• PAN 68 Design Statements
• PAN 75 Planning for Transport
• PAN 79 Water and Drainage 
Creating Places 2013 
28 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places. 
Designing Streets 2010 
29 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places. 
National Roads Development Guide 2014 
30 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision. 
CONSULTATIONS 
31 As part of the planning application process the following bodies were consulted:

Page 7

External 
32 Perth and Kinross Health and Social Care Partnership (NHS): Local
healthcare infrastructure needs must therefore be clearly identified in the Local
Development Plans in the future, to inform the strategy and development
proposals. Early engagement and collaboration between relevant stakeholders
will better inform decisions on land use and investment. 
33 Methven Community Council: Concerns over construction access, lack of
public transport and community consultation. 
34 Transport Scotland: No objection, subject to the ongoing requirements to set
out in conditions 16 and 19 of 21/00383/IPM. 
35 Scottish Water: There is currently sufficient capacity in the Perth Water
Treatment Works to service the development. A Strategic Water Impact
Assessment for the area shows that this proposed site causes detrimental impact
to the network and therefore mitigation will be required. However, Scottish Water
will be delivering the mitigations. It has been previously agreed for a temporary
connection off the main on Bleachers Way to allow a maximum of 40 units to
proceed. 
36 Scottish Environment Protection Agency: SEPA was consulted in respect of
the Condition 19: Construction Traffic Management Plan and 36: Construction
Environmental Management Plan. SEPA has advised that their standing advice
on these matters is applicable. 
37 Scottish and Southern Electricity Networks: No objections, subject to
conditions relating to the proximity of landscaping and SUDS to the overhead
power line. 
38 Scotland Gas Networks: Following discussion with the developer SGN has
withdrawn its objection to the proposal. 
39 Perth and Kinross Heritage Trust: No objections. Condition required for a
programme of archaeological works to be carried out. 
Internal 
40 Commercial Waste Team: The planning application does not include a storage
area for the commercial bins or a collection point. Therefore, we recommend that a
storage area for the bins be included. 
41 Community Waste Advisor - Environment Service: Advised that the Swept
Path Analysis in the drawings had been carried out based on a smaller vehicle
than PKC refuse collection vehicles. This was updated to reflect the vehicles
outlined in the response. No further comments.

Page 8

42 Environmental Health (Noise Odour): Conditions required. 
43 Environmental Health (Contaminated Land): Condition required. 
44 Development Contributions Officer: This application mirrors the extant consent
for the ‘Phase 1’ area (19/01433/AMM). No further comments in relation to the
Developer Contribution and Affordable Housing Supplementary Guidance. 
45 Transport Planning: No objection. Conditions required for further details to be
provided on roads, lade crossings and active travel accesses; a Travel Plan; street
lighting design, wildlife kerbs and works around the core path. 
46 Structures and Flooding: No objection. Seek inclusion of an additional
condition relating to finalised drainage detail to be provided. 
47 Community Greenspace: No comments. 
48 Biodiversity/Tree Officer: An updated Habitats Regulations Assessment has
been submitted. Conditions required to ensure mitigation and enhancement
measures are delivered on site. 
Representations 
49 25 representations were received. The main issues raised within the
representations are: 
• Concerns over construction access
• Lack of local services and public transport
• Flooding concerns
• Inadequate parking provision
• Lack of community consultation
• Impact on wildlife and biodiversity
• Increased traffic and roads safety concerns
• Existing trees should be protected
• Overdevelopment
• Overlooking
• Development is out of keeping with the local area
• Light pollution 
50 These issues are addressed in the Appraisal section of the report. 
ADDITIONAL STATEMENTS 
51 Screening Opinion EIA addendum 
Environmental Impact Assessment (EIA):
Environmental Report
EIA addendum submitted

Page 9

Appropriate Assessment under Habitats
Regulations
Habitats Regulations Appraisal
(HRA) submitted. The conclusions
of the submitted HRA are adopted
as the Planning Authority’s
Appropriate Assessment. 
Design Statement or Design and Access
Statement
Submitted 
Report on Impact or Potential Impact eg
Flood Risk Assessment
• Archaeological Evaluation
• Construction Management
Plan
• Design and Access Statement
• Drainage Strategy Report
• Tree and Woodland Report
• Transport Statement (and
Addendum)
• Site Investigation Report
• Ecological Appraisal
• Public Travel Plan
• Habitats Regulations
Assessment
• Landscape and Biodiversity
Management Plan
• Low and Zero Carbon
Statement
• Noise Statement 
APPRAISAL 
52 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise. The Development Plan comprises NPF4, the Perth and
Kinross Local Development Plan 2019 and statutory supplementary guidance.
The relevant policy considerations are outlined in the policy section above and
are considered in more detail below. In terms of other material considerations,
this involves considerations of the Council’s other approved policies and
supplementary guidance. In addition, section 14(2) of the Planning (Listed
Buildings and Conservation Areas) (Scotland) Act 1997 places a duty on
planning authorities in determining such an application as this to have special
regard to the desirability of preserving the building or its setting or any features of
special architectural or historic interest which it possesses. Section 64(1) of the
Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997 is
relevant and requires planning authorities to pay special attention to the
desirability of preserving or enhancing the character or appearance of the
designated conservation area.

Page 10

Principle 
53 The principle of the proposal has been established through the site’s allocation
as MU73 in LDP2 for a mixed-use development. Planning permission in principle
(PPP) (21/00383/IPM) has also been granted for the mixed-use development of
the site in line with the MU73 allocation. An extant Approval of Matters Specified
in Conditions (AMSC) (19/01433/AMM) is also in place for this phase of the
development. The current proposal is substantially similar to the extant AMSC
and the principle of the proposal is acceptable subject to compliance with
relevant development plan policies and other material considerations. These
matters are considered in detail below. 
Design and Layout 
54 NPF4 Policy 14: Design, Quality and Place, Policy 15: Local Living and 20
Minute Neighbourhoods and Policy 16: Quality Homes are relevant; as are LDP2
Policy 1: Placemaking, Policy 14B: Open Space within New Developments,
Policy 17: Residential Areas, Policy 25: Housing Mix and Policy 42: Green
Infrastructure. In association, various PPP conditions also apply. 
55 The layout is predominantly similar to that of the extant AMSC, with the main
change seeking approval for the Barratt house types. The layout continues to
follow the strategies set down by the consented masterplan by creating
permeable neighbourhoods connected both to the existing core paths and the
new landscaped zones. Streets and lanes are proposed throughout to maximise
the building frontage and create spaces which prioritise pedestrians. Varying
carriageway widths, building lines and street trees will reduce forward visibility
and vehicle speeds. 
56 The proposed dwellings all seek to provide an active and street-facing frontage,
with garages (where proposed) set back or offset with appropriate front boundary
treatment and detailing, mitigating the impact of visual dominance. This provides
an acceptable design and visual quality throughout and ensures that cars will not
dominate streetscapes. The private garden ground provision for individual plots is
set out in Plan 375, which confirms that the areas proposed are appropriate. 
57 The local centre has been developed to create a mix of retail and residential uses
and creates a heart to the overall masterplan, as envisaged by the LDP2
allocation and are commensurate with the development contained in these early
phases. 
58 Areas of open space will be defined by existing woodland, proposed woodland
and/or building frontages. This will ensure that these spaces were well integrated
within the new neighbourhood and located within easy access of housing areas.
The proposed footpath network will link the areas of open space throughout the
new neighbourhood.

Page 11

59 Overall, the proposals are considered to comply with the Council’s placemaking
policies, providing a logical and coherent structure and hierarchy of streets,
buildings and open space that considers the surrounding landscape character
and amenity of the area. The current proposals are considered to accord with
both the PPP and relevant Development Plan policies. 
Landscape and Visual Amenity 
60 NPF4 Policies 6: Forestry, Woodland and Trees; Policy 20: Blue and Green
Infrastructure and Policy 21: Play Recreation and Sport and LDP2 Polices 39:
Landscape; 40B: Forestry, Woodland and Trees - Trees, Woodland and
Development; and 42: Green Infrastructure, are all relevant in considering
landscape and visual amenity. In association, several conditions attached to the
PPP application also apply. 
61 The open space allocation along the northern section of the site, which includes
the sports pitches, community sports pavilion, play area, SUDS and landscaping
are largely the same as the previously approved AMSC. The areas of adoption
remain the same and the landscaping design and species choice are all
satisfactory and are in accordance with Council’s Supplementary Guidance:
Open Space Provision for New Developments. 
62 As part of the S75 legal agreement for the wider Almond Valley development, a
community sports pavilion was secured, and this element continues to be
proposed in the current application, where it is to be located alongside the
proposed riverside sports pitches. In terms of landscaping, the existing S.75 also
includes the provision of the sports facilities (sports pitches, pavilion and skate
park), structural planting and play facilities. Not all of the facilities are to be
provided in this phase of development. 
63 In terms of landscape and visual amenity, the proposals do not conflict with the
relevant policies of the Development Plan or associated PPP conditions. 
Residential Amenity 
64 Residential amenity requires to be considered under NPF4 Policy 16: Quality
Homes and LDP2 Policy 1: Placemaking and Policy 17: Residential Areas as well
as PPP conditions. 
Privacy, Daylight and Overshadowing 
65 In terms of potential for impact on existing residential amenity, such as
overlooking or loss of privacy, it is not considered that the proposed development
will unacceptably compromise existing residential amenity, or between properties
within the proposed development itself. Each dwelling will see acceptable rear
garden areas in terms of depth and area provided, complying with the
aforementioned development policies and the Placemaking Supplementary
Guidance 2020.

Page 12

Noise 
66 Condition 42 of the PPP requires an assessment of air quality and the potential
impact of each phase. As the current proposal is substantially similar to the
previous AMSC in terms of noise impact, the Noise Impact Assessment (NIA)
submitted with the previous application is again being relied upon to address
noise issues and concerns. The NIA Considered operational noise from existing
businesses, including that from Adie Kennels and Cattery, to understand what
impacts these operations may have on the amenity experienced by occupants of
the proposed dwellinghouses. The outcome of the assessment established that,
subject to mitigation being secured, no unacceptable impact on future residential
amenity was predicted (Conditions 5, 7, 8 and 10). 
67 However, further informative work is required in relation to proposed properties in
the vicinity of Huntingtower Hotel, this sees a further NIA required to inform and
deliver appropriate mitigation against noise impacts in that area (Condition 11).
These measures, combined, will ensure no adverse impact on the operation of
the neighbouring businesses or residential amenity. 
Air Quality 
68 Condition 45 of the PPP requires an assessment of air quality and the potential
impact of each phase. Again, as the current proposal is substantially similar to
the previous AMSC in terms of impact on air quality the air quality assessment
(AQA) submitted with the previous application is again being relied upon to
address air quality issues during both the construction and operational phases of
the development. 
69 The AQA found that the development was unlikely to have a significant adverse
impact on air quality, subject to identified mitigation measures being undertaken,
and these will be required under the implementation of the development. 
Contaminated Land 
70 Condition 40 of the PPP requires an evaluation for the potential of the site to be
affected by contamination by a previous use to be undertaken for each phase.
Two reports have been submitted with the application considering previous
conditions relating to contaminated land. 
71 The area that has been identified within the red line boundary of this application
is former railway land. A number of boreholes and trial pits have been
undertaken and samples taken for analysis. Environmental Health has
considered these reports and advised that the sampling appears to be from
around the area of interest and not targeted at the potential source of
contamination being the dismantled railway. As a result, a condition is
recommended to ensure that further investigation work is carried out to ensure
the suitability of the site for the proposed development (Condition 12).

Page 13

Roads and Access 
72 The proposal will create a vehicle access from Ruthvenfield Road (B9993)
roundabout on the fifth arm, with an additional vehicle access created onto
Castle Brae near to Shepherds Mill Cottages and a final vehicle access onto
Bleachers Way in Huntingtower. 
73 A number of objectors to the proposal have raised concerns that Castle Brae
East will be used as an access to the site by construction traffic. Condition 23 of
the PPP states that Castle Brae East shall not be used by construction traffic
associated with the development. This condition will remain enforceable against
the AMSC applications, and it has been confirmed by the applicant that Castle
Brae East will not be utilised by construction traffic. 
74 The PPP approved the phasing approach for the development. The Almond
Roundabout provides direct access the north-eastern portion of the Almond
Valley development. The principle of the development being phased from east to
west in the northern part of the site is therefore established through the PPP and
extant AMSC. In infrastructure and practical terms, this makes earlier phases
more straightforward to develop and frees up capacity on the road network. 
75 The previously agreed reconfiguration of the residential phasing through the PPP
sees the new A85 roundabout being required after the 340th residential unit.
Therefore, the principle of access now being taken for the scale of development
proposed solely from the Almond Roundabout is established. Transport Scotland
and PKC Transport agree that this is acceptable subject to the full discharge of
Conditions 16 and 19 of the PPP relating to speed management measures on
the A85 and the requirement for a Construction Traffic Management Plan to be
submitted to them prior to the commencement of works. 
76 In respect of the internal road layout and parking provision, PKC Transport raise
no concerns. The proposed internal movement layout, including road hierarchy
and associated private and public parking provision is considered satisfactory
and consistent with the approach and principles adopted in the original
masterplan submission and extant AMSC 
77 LDP2 Policy 15 relates to public access; including core paths and rights of way
and seeks that development proposals do not have an adverse impact on such
routes. In this regard comprehensive linkages with existing core paths, together
with new and enhanced pedestrian/cycle routes are to be provided, and will
integrate into a wider network – reflective of the routes identified through the
original masterplan. 
Drainage and Flooding 
78 The parameters agreed within the Flood Risk Assessment for the previous
approval 19/01433/AMM are not changed by the Barratt site design. Therefore,
the previous FRA for the site remains relevant and this matter does not need to

Page 14

be revisited in the consideration of this application. PKC Flooding and Structures
has confirmed that they have no objections to the proposal subject to a condition
(Condition 13) for the submission of the detailed drainage design. 
Healthcare Facilities 
79 The HSCP have made comments in relation to existing and required healthcare
facilities within the locale. They acknowledge that the appropriate point at which
to begin this dialogue would be through engagement with the local development
plan process and not via an AMSC application. Previous dialogue around this
matter has suggested that units within the Local Centre could be utilised, but this
will require further consideration by the parties. 
Waste Collection 
80 The PPP seeks to ensure appropriate waste and recycling provision is identified
and secured as part of the AMSC applications. There is considered to be
adequate provision to accommodate the conditional requirements in this regard,
satisfying the terms of the PPP. 
Archaeology and Conservation Considerations 
81 NPF4 Policy 7: Historic Assets and Places; LDP2 Policies 26B: Archaeology and
29: Gardens and Designed Landscapes and conditions attached to the PPP
application apply. 
82 Archaeological assessment is recommended to be undertaken (Condition 32),
which accords with the approach in the PPP. 
83 The proposal is in proximity to two significant listed building groups: 18th century
workers’ cottages at Grey Row (category C listed) and later blocks of workers’
housing at Waterside Cottages (category B listed). The Grey Row building group
is separated from the development by the proposed site for a new school. It will
therefore be for that future phase of development to ensure that the setting of the
listed buildings is protected and maintained. In terms of Waterside Cottages, it is
considered that appropriate planting and spacing has been afforded to this
grouping, with no adverse impact on the character or setting of the listed
buildings. There are no other adverse impacts on cultural heritage assets as a
result of this phase of development. 
Natural Heritage and Biodiversity 
84 In relation to natural heritage and biodiversity, NPF4 Policy 1: Tackling the nature
crises, Policy 2: Biodiversity and Policy 6: Forestry, woodland and trees are
relevant. Similarly LDP2 Policy 38: Environment and Conservation, Policy 40:
Forestry, Woodland and Trees, and Policy 41: Biodiversity are also applicable. In
association, several PPP conditions also apply.

Page 15

85 Due to the relationship with the River Tay Special Area of Conservation (SAC), a
Habitats Regulations Assessment (HRA) was submitted, consistent with LDP2
Policy 38A. Although this matter was addressed through the previous AMSC
application, an updated HRA Report was submitted which concluded that the
findings of the previous HRA remain valid. Moreover, the Report concluded that,
through the implementation of proposed mitigation measures, there will be no
likely significant effects upon the River Tay SAC provided that the development
fully accords with the HRA requirements. Condition 37 of the PPP
(21/00383/IPM) requires the appointment of an independent Ecological Clerk of
Works (ECoW) across all phases, thus the approach is considered satisfactory. 
86 It is considered that the potential threat and impact to population, distribution or
habitat of protected species can be either avoided or minimised through
mitigation. There will be no significant adverse impact on site biodiversity as a
result of the development proposals with suitable mitigation and enhancement
secured. Thus, there is no conflict with relevant Development Plan policies or the
terms of the PPP. 
Low and Zero Carbon Generating Technologies 
87 LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in
New Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of
low and zero-carbon generating technologies. As this proposal includes the
erection of a new building, consideration must be given to this requirement.
Further, NPF4 Policy 2 ‘Climate Mitigation and Adaptation’ requires that
development should be designed to reduce green gas emissions. Conditions 5
and 8 of the PPP requires details to be provided of how the above policies will be
met through the installation and operation of low and zero-carbon generating
technologies. In this instance, a Renewable and Low and Zero Carbon Energy
Statement has been submitted. The statement advises that the requirement will
be met through the use of a fabric first approach, including timber frame
construction, high performance windows and doors, photovoltaic roof panels, low
voltage lighting, low flush sanitary appliances and energy efficient kitchen
appliances. The proposal therefore complies with the relevant policies. 
88 An Energy Statement is required prior to the commencement of development, to
review heat network potential for district heating networks in association with
Perth West (Condition 48 of PPP 21/00383/IPM). 
Developer Contributions 
89 A Section 75 relating to the PPP is in place and covers the developer contribution
requirements for the wider development.

Page 16

Economic Impact 
90 The impact on the local economy from 340 new dwellings, local centre and
sports pavilion and facilities will add to the available local expenditure and have a
positive impact on existing local facilities. 
VARIATION OF APPLICATION UNDER SECTION 32A 
91 This application was varied prior to determination, in accordance with the terms
of section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended. The variations incorporate minor improvements to the layout. 
PLANNING OBLIGATIONS AND LEGAL AGREEMENTS 
92 None required. 
DIRECTION BY SCOTTISH MINISTERS 
93 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application. 
CONCLUSION AND REASONS FOR RECOMMENDATION 
94 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly, the proposal is recommended for approval
subject to the following conditions. 
RECOMMENDATION   
Approve, subject to the following conditions: 
Conditions and Reasons for Recommendation 
General 
1. The development hereby approved under this Approval of Matters Specified in
Conditions is only for the benefit of and under Permission in Principle reference:
21/00383/IPM. For the avoidance of doubt, this Approval of Matters Specified in
Conditions is not approved under Planning Permission in Principle reference:
15/01157/IPM. The development hereby approved must be carried out in
accordance with the approved drawings and documents for this approval and the

Page 17

terms of Planning Permission in Principle 21/00383/IPM, unless otherwise
provided for by conditions imposed by this decision notice. 
Reason: To ensure the development is carried out in accordance with the
approved drawings and documents. 
2. The development hereby approved will be implemented concurrently with the
previous Approvals of Matters Specified in Conditions for this phase of
development, references: 19/01430/AMM and 19/01433/AMM. All matters not
specifically approved under this AMSC must be implemented in line with
19/01430/AMM and 19/01433/AMM and all relevant conditions of those
approvals strictly adhered to, or be subject to a further AMSC. 
Reason: To ensure the development is carried out in accordance with the
approved consents. 
Construction Management 
3. The Construction Environment Management Plan (CEMP) submitted to satisfy
Condition 36 of planning permission 21/00383/IPM shall be implemented
concurrent with the development. The CEMP will remain a dynamic document
throughout the duration of construction and until the completion of development.
The CEMP can be amended as necessary to meet best practice in terms of
environment or ecology. Any amendments will be submitted to the Planning
Authority as soon as reasonably practicable citing the relevant amendment and
appropriate guidance. 
Reason: In the interest of protecting environmental quality and of biodiversity. 
EV Charging 
4. Prior to the commencement of the development full details shall be submitted for
the layout and incorporation of EV charging duct points within the development
and all other proposed Air Quality mitigation measures to be implemented and
evidenced that the predicted insignificant impact from the development is
maintained. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality. 
Residential Amenity and Noise 
5. Prior to the commencement of the development hereby approved, the developer
shall submit a scheme, for the written approval of the Planning Authority, which
shall include the proposed means of ventilation for all habitable rooms that
require acoustic trickle ventilation and the glazing specification for all habitable
rooms, demonstrating the habitable rooms can achieve the internal sound levels
Daytime 35 dBLAeq,16hrs and Night time 30dB LAeq,8hrs when measured for

Page 18

road noise. The agreed scheme shall thereafter be implemented in accordance
with the agreed details. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality is maintained. 
6. For any commercial kitchen, an effective ventilation system commensurate with
the nature and scale of cooking to be undertaken shall be installed, operated and
maintained, within the commercial areas, such that cooking odours are not
exhausted into or escape into any neighbouring dwellings. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality. 
7. All plant or equipment including any ventilation system associated with operation
of the commercial areas shall be so enclosed, attenuated and/or maintained such
that any noise therefrom shall not exceed Noise Rating 35 between 0700 and
2300 hours daily, or Noise Rating 20 between 2300 and 0700 hours daily, within
any neighbouring residential premises, with all windows slightly open, when
measured and/ or calculated and plotted on a rating curve chart. 
Reason: In the interests of public health and to prevent noise pollution. 
8. Commercial deliveries shall be limited to Monday to Sunday 07.00 to 19.00. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality. 
9. For commercial and sport pavilion areas, all external lighting to be installed shall
be sufficiently screened and aligned so as to ensure that there is no direct
illumination of neighbouring land and that light spillage beyond the boundaries of
the site is minimised. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality. 
10. Prior to the occupation of any dwellinghouse in site H4, A 2-metre-high acoustic
barrier shall be installed along the whole length of site boundary between 'J&E
Smillie' and site H4. The acoustic barrier shall have a superficial mass of a least
20Kg/m2 and shall be of a solid construction with no gaps. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality. 
11. Prior to the commencement of development at site H2, the applicant must submit
a further noise impact assessment (NIA) to assess noise from the operations of
the Huntingtower Hotel for the written approval of the Planning Authority, in
consultation with Environmental Health Team. The NIA should be undertaken by

Page 19

a qualified noise consultant. All mitigation measures proposed in the NIA, which
are agreed or required by the Planning Authority, shall be fully implemented prior
to the occupation of any dwellinghouse in site H2. 
Reason: In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality. 
Ground Contamination 
12. Prior to the commencement of works on site, an evaluation for the potential of the
site to be affected by contamination by a previous use should be undertaken and
as a minimum, a Preliminary Risk Assessment (Phase 1 Desk Study) will be
submitted for consideration by the Council as Planning Authority. If after the
preliminary risk assessment identifies the need for further assessment, an
intrusive investigation should be undertaken to identify; 
i. the nature, extent and type(s) of contamination on the site.
ii. measures to treat/remove contamination to ensure the site is fit for the use
proposed. 
iii. measures to deal with contamination during construction works.
iv. condition of the site on completion of decontamination measures. 
Prior to the completion or bringing into use of any part of the development the
agreed measures to decontaminate the site shall be fully implemented as
approved by the Council as Planning Authority. Validation that the scheme has
been fully implemented must also be submitted to the Council as Planning
Authority. 
Reason: To ensure any contamination present on site is satisfactorily
remediated. 
Drainage 
13. Notwithstanding the submitted drainage details, and those matters pertaining to
drainage that were agreed under 19/01433/AMM, prior to the installation of any
drainage works on site, the final technical drainage designs shall be submitted to,
and approved in writing by, the Planning Authority in consultation with the
Council's Structures and Flooding team. The drainage details as approved shall
be carried out in accordance with the agreed scheme and operational prior to
bringing into the use of the development. 
Reason: To ensure the adequate drainage of the site. 
Roads and Access 
14. No more than 200 residential units are permitted to be occupied until such time
as a detailed design and specification for the following works has been submitted

Page 20

to and approved in writing by the Planning Authority in consultation with the
Roads Authority and Perth & Kinross Council Structures team: 
a) new primary road route as shown in application 19/01430/AMM, connecting
the site to the new A85 roundabout; and
b) new vehicular lade crossing as shown in 19/01430/AMM, connecting to the
site. 
Reason: To ensure that the scale of development does not exceed that assessed
by the supporting Transport Assessment and to ensure that the scale of
development is commensurate with the infrastructure required to support the
development. 
15. For clarification, and in association with Condition 16 b) of 21/00383/IPM, no
more than 90 residential units or any units in the 'Local Centre' hereby approved
shall be occupied until a new active travel lade crossing, as approved in writing,
to an agreed design and specification to the satisfaction of the Planning
Authority, in consultation with the Perth & Kinross Council Structures team is
delivered, connecting to all elements of the occupied site. 
Reason: To ensure that the scale of development does not exceed that assessed
by the supporting Transport Assessment and to ensure that the scale of
development is commensurate with the infrastructure required to support the
development. 
16. No more than 61 residential units within Phase 1A are permitted to be occupied
until new vehicular and active travel accesses connecting the site to both
Bleachers Way and Phase 1 of the development is provided, to a design and
specification approved in writing by the Planning Authority, after consultation with
the Perth & Kinross Council Structures team. 
Reason: To ensure that the scale of development does not exceed that assessed
by the supporting Transport Assessment and to ensure that the scale of
development is commensurate with the infrastructure required to support the
development. 
17. Development shall not commence until a detailed Travel Plan aimed at
encouraging more sustainable means of travel, has been submitted to and
agreed in writing by the Council as Planning Authority. The Travel Plan will have
particular regard to provision for walking, cycling and public transport access to
and within the site and will identify the measures to be provided (including the
provision of new and/or enhanced public transport services), any phasing, the
system of management, monitoring, review, reporting and the duration of the
Plan. The Travel Plan as agreed shall be fully implemented to the satisfaction of
the Council as Planning Authority.  
Reason: To promote sustainable transport options and to meet advice within
National Planning Framework on transport.

Page 21

18. Prior to commencement of any development on site, the street lighting design
must be submitted for the further written agreement of the Council as Planning
Authority, in consultation with Perth & Kinross Council's Street Lighting
Partnership for the public road network. The scheme shall include details of light
spill, brightness of the lighting and the proposed hours of operation for both the
public road network and the private areas, and timescales for delivery. The
agreed lighting scheme shall be implemented and maintained in full accordance
with the agreed scheme. 
Reason: In the interests of road safety.  
19. All road gullies within 500m of a waterbody or Sustainable Urban Drainage
System (SUDs) pond shall have wildlife kerbs installed adjacent to the gully. 
Reason: In the interests of protecting environmental quality and of biodiversity. 
Core Path  
20. The core path which forms part of the construction site must not be obstructed
during building works or on completion. Any damage done to the core path and
associated signage during building works shall be made good before occupation
of the dwellinghouse. Any temporary restrictions to public access required to
facilitate works on site must be agreed in writing first with the Access Officer.  
Reason: In the interests of public access along the core path. 
Public Transport 
21. Prior to the first occupation of the development hereby approved, scheme for the
design specification and timing for delivery of public transport infrastructure
internally within the development of Phase 1 & Phase 1A, including hard stand
areas, bus shelters, poles & flags and any required bus stop road markings, shall
be submitted for the written approval of the Council as Planning Authority, in
consultation with the Council's Public Transport Unit. The scheme for the
approved shall thereafter be implemented in line with the agreed timings.  
Reason: To ensure that committed sustainable transport measures are delivered
on site to an agreed specification  
22. Prior to commencement of the development hereby approved, a Public Transport
Plan shall be submitted to and approved in writing by the Council as Planning
Authority. The submission will confirm the public transport services to be
provided and how the contribution funding will be used to provide the services to
serve Phase 1, Phase 1A and Phase 1B, along with how the developer will seek
to promote the services provided. The scheme shall be implemented in full, prior
to the occupation of the 50th dwellinghouse.

Page 22

Reason: In the interest of providing sustainable and connected travel options for
residents and visitors to the development to the wider Perth area. 
Construction Traffic  
23. Prior to the commencement of the development hereby approved, the applicant
shall submit for the further written agreement of the Council as Planning
Authority, in consultation with the Roads Authority (Structures), a Construction
Traffic Management Scheme (TMS) which shall include the following:  
a. restriction of construction traffic to approved routes and the measures to be
put in place to avoid other routes being used;
b. timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse
collection is undertaken, on Sundays and during local events;
c. a code of conduct for HGV drivers to allow for queuing traffic to pass;
d. arrangements for liaison with the Roads Authority regarding winter
maintenance;
e. emergency arrangements detailing communication and contingency
arrangements in the event of vehicle breakdown;
f. arrangements for the cleaning of wheels and chassis of vehicles to prevent
material from construction sites associated with the development being
deposited on the road;
g. arrangements for cleaning of roads affected by material deposited from
construction sites associated with the development;
h. arrangements for signage at site accesses and crossovers and on roads to
be used by construction traffic in order to provide safe access for
pedestrians, cyclists and equestrians;
i. details of information signs to inform other road users of construction traffic;
j. arrangements to ensure that access for emergency service vehicles are not
impeded;
k. co-ordination with other significant developments known to use roads
affected by construction traffic;
l. traffic arrangements in the immediate vicinity of temporary construction
compounds;
m. the provision and installation of traffic counters at the applicant's expense at
locations to be agreed prior to the commencement of construction;
n. monitoring, reporting and implementation arrangements; 
o. arrangements for dealing with non-compliance; and
p. details of HGV movements to and from the site.    
The TMS as approved shall be strictly adhered to during the entire site
construction programme.  
Reason: In the interest of proper site management.

Page 23

Landscaping 
24. The detailed landscaping and planting scheme hereby approved shall, with the
inclusion of the matters detailed in Condition 23 of this permission, be
implemented as part of the site development programme and thereafter
maintained. 
Reason: In the interests of visual amenity and to ensure the satisfactory
implementation of the proposed planting scheme. 
25. Any planting failing to become established within five years shall be replaced in
the following planting season with others of similar size and species. 
Reason: In the interests of visual amenity and to ensure the satisfactory
implementation of the proposed planting scheme. 
26. Prior to the completion of the development hereby approved, a scheme
confirming the arrangements for handover of the approved Community Pavilion
to an end user, shall be agreed between the applicant and the Council. The
agreed arrangement shall thereafter be undertaken as approved, subject to any
agreed periodic review specified in the scheme. 
Reason: In order to safeguard and appropriately deliver a community asset in the
immediate and long term. 
Biodiversity 
27. The conclusions and recommended action points within the supporting
biodiversity survey and Habitats Regulation Survey submitted and hereby
approved shall be fully adhered to, respected and undertaken as part of the
construction phase of development. 
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981). 
28. Prior to the commencement of development hereby approved, details of the
location and specification of the bird nesting bricks or boxes shall be submitted
for the further written agreement of the Council as Planning Authority. Thereafter,
the bird nesting bricks, or boxes shall be installed in accordance with the agreed
details prior to the occupation of the relevant residential unit. 25% of two storey-
dwellings should contain a bird nesting brick or box. 
Reason: In the interests of employing best practice ecology and enhancing
biodiversity opportunities. 
29. Prior to the commencement of development hereby approved, details of the
location and specification of the integrated bat bricks, boxes or tubes shall be

Page 24

submitted and approved in writing by the Council as Planning Authority.
Thereafter, the integrated bat bricks, boxes or tubes shall be installed in
accordance with the agreed details prior to the occupation of the relevant
residential unit. 25% of two storey-dwellings should contain a bat brick, box or
tube. 
Reason: In the interests of employing best practice ecology and enhancing
biodiversity opportunities. 
30. Prior to commencement of development hereby approved, a detailed
Construction Method Statement (CMS) shall be submitted for written approval to
the Council as Planning Authority; ensuring all mitigation measures listed in
Section 7 of the Almond Valley- Phase 1 Application Habitats Regulations
Appraisal, dated October 2024 are captured. 
Reason: In order to ensure the development does not impact negatively on the
nearby Special Area of Conservation. 
31. The conclusions and recommended action points within the Landscape and
Biodiversity Management Plan submitted and hereby approved shall be fully
adhered to, respected and undertaken as part of the construction phase of
development. 
Reason: To ensure a satisfactory standard of development and environmental
quality and to reserve the rights of the Planning Authority. 
Archaeology 
32. Development shall not commence until the developer has secured the
implementation of a programme of archaeological work in accordance with a
Written Scheme of Archaeological Investigation (WSI) which has been submitted
by the developer and agreed in writing by the Council as Planning Authority, in
consultation with Perth and Kinross Heritage Trust (PKHT). Thereafter, the
developer shall ensure that the programme of archaeological works is fully
implemented including that all excavation, preservation, recording, recovery,
analysis, publication and archiving of archaeological resources within the
development site is undertaken. Should the archaeological works, as required by
the WSI, identify a requirement for post-excavation analysis, the development as
approved shall not be occupied or brought into use until a Post-Excavation
Research Design (PERD) has been submitted to and agreed in writing by the
Council as Planning Authority, in consultation with PKHT. The PERD shall be
carried out in complete accordance with the approved details. Furthermore, the
developer shall afford access at all reasonable times to PKHT or a nominated
representative and shall allow them to observe work in progress. 
Reason: To ensure a programme of archaeological works is carried out to
safeguard and record any archaeological remains within the development area.

Page 25

Justification 
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan. 
Procedural Notes 
There is a Section 75 agreement for 21/00383/IPM, which pertains to the wider
development. 
Informatives 
1. Under Section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,
which may result in enforcement action being taken. 
2.  As soon as practicable after the development is complete, the person who
completes the development is obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the Planning Authority written
notice of that position. 
3. This development will require the 'Display of notice while development is carried
out', under Section 27C(1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013. The form of the notice is set out in Schedule 7 of
the Regulations and a draft notice is included for your guidance. In accordance
with Regulation 41 the notice must be: 
• Displayed in a prominent place at or in the vicinity of the site of the
development
• Readily visible to the public
• Printed on durable material. 
4.  The developer is advised to contact PKHT to discuss terms of reference for work
required by Condition 33. 
5. The applicant should be advised that in terms of Section 21 of the Roads
(Scotland) Act 1984 they must obtain from the Council as Roads Authority
consent to construct a new road prior to the commencement of roadworks. 
Advice on the disposal of surface water must be sought at the initial stages of
design from Scottish Water and the Scottish Environment Protection Agency. 
Please note that a fee is chargeable for the processing of RCC applications.  
6. The applicant is advised that, in terms of Sections 56 of the Roads (Scotland) Act
1984, he/she/they must obtain from the Council, as Roads Authority, consent to

Page 26

open an existing road or footway prior to the commencement of works. 
Information on junction types, requirements for Vehicular Access consents (VA1)
and application forms are available at www.pkc.gov.uk/vehicleaccess.  Advice
on the disposal of surface water should be sought at the initial stages of design
from Scottish Water and the Scottish Environmental Protection Agency.  
7. Further advice and information regarding installation and specifications of the bus
shelter can be obtained from David Rae or Moray Fraser of the Public Transport
Unit at publictransport@pkc.gov.uk. 
8. The applicant is advised that, in terms of Sections 109 of the New Roads and
Street Works Act 1991, he/she/they must obtain from the Council, to place,
maintain or adjust apparatus in, or under a Road or remove apparatus from a
road.  Application forms are available at
https://www.pkc.gov.uk/article/14916/Road-and-footway-permits.  
9. Road drainage may be in the vicinity of the new access and require remedial
works. Contact Perth & Kinross Council Road Maintenance Department for
further details.  
10. The applicant should be advised that in terms of Section 96 of the Roads
(Scotland) Act 1984 a road condition survey may be required to be agreed with
the Council as Roads Authority prior to the commencement of works. To ensure
the public road is reinstated to its present standard.  
11. All proposed structures supporting the road, or which the developer is intending
the Council adopt, will require technical approval in accordance with the Design
Manual for Roads & Bridges standard BD 2/12 (& HD 22/08 where relevant). 
Bridges and culverts shall also be designed in accordance with the requirements
contained within Perth & Kinross Council’s Developers Guidance Note on
Flooding & Drainage.  The developer is advised to contact Perth & Kinross
Council’s Structures & Flooding Team (tel 01738 475000, email
structuresplanning@pkc.gov.uk) for further information and prior to commencing
designs in order to ensure technical compliance. 
12. The applicant is reminded that, should any protected species be present a
licence may be required from NatureScot to disturb a protected species.  Failure
to obtain a licence may constitute a criminal act under the Habitats Regulations
and penalties are severe for noncompliance. 
13. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as
amended, it is an offence to remove, damage or destroy the nest of any wild
birds while that nest is in use or being built. Planning consent for a development
does not provide a defence against prosecution under this act. 
14. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive. Trees and scrub are present on the application site and are to
be assumed to contain nesting birds between the above dates. The applicant is

Page 27

reminded that, under the Wildlife and Countryside Act 1981, as amended (section
1), it is an offence to remove, damage or destroy the nest of any wild bird while
that nest is in use or being built. Planning permission for a development does not
provide a defence against prosecution under this Act. 
15. The applicant is encouraged to provide access for hedgehogs sheltering,
hibernating in, and commuting through the development. Access gaps in wooden
fences should be 13cm x 13cm at ground level. Advice and assistance is
available from the Tayside Biodiversity Partnership.
https://www.taysidebiodiversity.co.uk/information/information-guides-manuals/ 
16. The applicant should be aware of the requirements of the Council's Environment
and Regulatory Services in relation to waste collection from the site and should
ensure adequate measures are provided on site to allow for the collection of
waste, including construction phasing. 
Background Papers:  25 letters of representation
Contact Officer:  Alex Gudgeon 01738 475337
Date:  29 November 2024 
DAVID LITTLEJOHN
STRATEGIC LEAD: ECONOMY, DEVELOPMENT AND PLANNING