PLANNING AND PLACEMAKING COMMITTEE 
Minute of hybrid meeting of the Planning and Placemaking Committee held in the
Council Chambers, 2 High Street, Perth, on Wednesday 9 October 2024 at 9.30am. 
Present: Councillors I Massie, G Stewart, Bailie C Ahern (substituting for Councillor
K Allan), B Brawn, E Drysdale (substituting for Councillor R Watters), D Illingworth,
K Harvey, I James, Bailie C McLaren and I MacPherson (substituting for Bailie
M Williamson). 
In Attendance: L MacLean, C Morilly, S Panton, K Smith, K Steven and P Williamson
(all Economy, Place and Learning); A Brown, S Dockerill, G Fogg and J Guild (all
Strategy, People and Resources). 
Apologies: Councillors K Allan, D Cuthbert, R Watters and Bailie M Williamson. 
Councillor I Massie, Convener, Presiding. 
1. WELCOME AND APOLOGIES 
The Convener welcomed everyone present to the meeting and noted
apologies as above.   
2. DECLARATIONS OF INTEREST 
There were no Declarations of Interest made in terms of the Councillors Code
of Conduct. 
3. MINUTES 
The Minute of Meeting of Planning and Placemaking Committee of
11 September 2024 was submitted and approved as a correct record. 
4.  DEPUTATIONS 
In terms of Standing Order 13, the Committee agreed to hear deputations in
relation to the following planning applications: 
Planning Application No.  Item No. 
23/01224/FLL 5(1)(i)
223/0131/FLL 5(1)(ii)

Page 2

5. APPLICATIONS FOR DETERMINATION 
(1) Local Applications 
(i) 23/01224/FLL - Erection of 29 dwellinghouses and
associated works (phase 1 - allocated site H53), land north
west of Huize Baahock, Powmill, Dollar (Report No. 24/278) 
Mr R Raj, on behalf of the applicant, addressed the committee,
and answered Members questions. 
Resolved:
Grant, subject to the following terms, conditions and
informatives: 
Conditions
1. This planning permission will last only for three years
from the date of this decision notice, unless the
development has been lawfully started within that period.
Reason - This is a Planning Permission in terms of
Section 58 of the Town and Country Planning (Scotland)
Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019.
2. The development hereby approved must be carried out in
accordance with the approved drawings and documents,
unless otherwise provided for by conditions imposed by
this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
3. Development shall not commence on site until an
evaluation for the potential of the site to be affected by
contamination by a previous use has been undertaken
and, as a minimum, a Preliminary Risk Assessment
(Phase 1 Desk Study) has been submitted for
consideration and accepted by the Council as Planning
Authority.  If the preliminary risk assessment identifies the
need for further assessment, an intrusive investigation
shall be undertaken to identify; 
I. the nature, extent and type(s) of contamination on
the site 
II. measures to treat/remove contamination to ensure
the site is fit for the use proposed 
III. measures to deal with contamination during
construction works 
IV.  condition of the site on completion of
decontamination measures. 
Prior to the completion or bringing into use of any part of
the development the measures to decontaminate the site
shall be fully implemented in accordance with the scheme
subsequently agreed by the Council as Planning
Authority.  Verification that the scheme has been fully

Page 3

implemented must also be submitted to the Council as
Planning Authority.
Reason - In order to deal with any potential contamination
of the site as a result of its former use.
4. Development shall not commence on site until a detailed
sustainable urban drainage system (SUDS) has been
submitted for the written agreement of the Council as
Planning Authority.  The scheme shall be developed in
accordance with the technical guidance contained in The
SUDS Manual (C753) and the Council's Flood Risk and
Flood Risk Assessments Developer Guidance, and shall
incorporate source control.  All works shall be carried out
in accordance with the agreed scheme and be
operational prior to the bringing into use of the
development. 
Reason - To ensure the provision of effective drainage for
the site
5. Prior to the occupation of the development or any phase
of the development, whichever is the sooner, a landscape
management plan, including long term design objectives,
management responsibilities and maintenance schedules
for all landscape areas (other than small privately-owned
domestic gardens) shall be submitted to and agreed in
writing by the Council as Planning Authority, for its
approved use.  The landscape management plan as
agreed shall, where appropriate, include phased
implementation concurrent with the development and
shall be fully implemented to the satisfaction of the
Council as Planning Authority.  
 
Reason - To agree the maintenance of areas of planting.
6.  Prior to the commencement of the development hereby
approved, a detailed landscaping and planting scheme
for the site, to include the SUDS pond to the south of the
A977 shall be submitted for the written agreement of the
Council as Planning Authority.   The scheme shall include
details of the height and slopes of any mounding or
recontouring of the site, full details of all hard landscaping
proposals including materials and installation methods
and, species, height, size and density of trees and shrubs
to be planted.   The scheme as subsequently approved
shall be carried out and completed within the first
available planting season (October to March) after the
completion or bringing into use of the development,
whichever is the earlier, and the date of Practical
Completion of the landscaping scheme shall be supplied
in writing to the Council as Planning Authority within 7
days of that date.   The scheme as agreed and
implemented shall thereafter be maintained, with any
planting which fails to become established within five
years being replaced in the following planting season with
others of a size and species as previously approved.

Page 4

Reason - In the interests of visual amenity and to ensure
the satisfactory implementation of the proposed planting
scheme.  
7. Prior to the occupation of the first dwellinghouse, the
developer shall replace the existing bus shelter known as
Powmill, at Store (NaPTAN ID 73726324), with a new
concrete base for a 2 bay enclosed bus shelter supplied
and installed with passenger information board, internal
community noticeboard, LED spotlights (one per bay), a
28in Ultra-Wide Display Screen for Real Time Passenger
Information installed on the approach side of the shelter
and a 24/7 electrical power supply to a Haldo pillar
adjacent to the shelter to provide power for the LED
lighting and Real Time Passenger Information display. 
The design and specification shall be to the satisfaction of
the Council as Planning Authority, in consultation with
Perth & Kinross Council’s Public Transport Unit.  In the
event that it is not possible to install at this location, an
alternative shall be agreed in writing with the Planning
Authority.
Reason - In the interest of sustainable travel.
8. Prior to the commencement of the development hereby
approved, the applicant shall submit for the further written
agreement of the Council as Planning Authority, in
consultation with the Roads Authority (Structures), a
Construction Traffic Management Scheme (TMS) which
shall include the following:
(a) restriction of construction traffic to approved routes
and the measures to be put in place to avoid other
routes being used;
(b) timing of construction traffic to minimise impact on
local communities particularly at school start and
finishing times, on days when refuse collection is
undertaken, on Sundays and during local events;
(c) a code of conduct for HGV drivers to allow for
queuing traffic to pass;
(d) arrangements for liaison with the Roads Authority
regarding winter maintenance;
(e) emergency arrangements detailing communication
and contingency arrangements in the event of
vehicle breakdown;
(f) arrangements for the cleaning of wheels and chassis
of vehicles to prevent material from construction
sites associated with the development being
deposited on the road;
(g) arrangements for cleaning of roads affected by
material deposited from construction sites
associated with the development;
(h) arrangements for signage at site accesses and
crossovers and on roads to be used by construction
traffic in order to provide safe access for
pedestrians, cyclists and equestrians;

Page 5

(i) details of information signs to inform other road
users of construction traffic;
(j) arrangements to ensure that access for emergency
service vehicles are not impeded;
(k) co-ordination with other significant developments
known to use roads affected by construction traffic;
(l) traffic arrangements in the immediate vicinity of
temporary construction compounds;
(m) the provision and installation of traffic counters at the
applicant's expense at locations to be agreed prior
to the commencement of construction;
(n) monitoring, reporting and implementation
arrangements; 
(o) arrangements for dealing with non-compliance; and
(p) details of HGV movements to and from the site.  
The TMS as approved shall be strictly adhered to during
the entire site construction programme.
Reason - In the interest of proper site management.
9. Prior to commencement of any development on site, the
street lighting design must be submitted for the further
written agreement of the Council as Planning Authority, in
consultation with Perth & Kinross Council’s Street
Lighting Partnership for the public road network.  The
scheme shall include details of light spill, brightness of
the lighting and the proposed hours of operation for both
the public road network and the private areas.  The
agreed lighting scheme shall be implemented and
maintained in full accordance with the agreed scheme.
Reason - In the interests of road safety and residential
amenity.
10. Prior to commencement of any development on site, a
detailed design of the junction and turning facilities for the
SUDS shall be submitted to and approved in writing by
the Planning Authority in consultation with the Roads
Authority.  The junction and turning facilities, as approved
in writing, shall be implemented in accordance with the
approved details to the satisfaction of the Council as
Planning Authority and undertaken prior to the
commencement of construction of the SUDS. 
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
11. No part of the development shall be occupied until a
Residential Travel Plan (RTP), aimed to encourage more
sustainable means of travel, has been submitted to and
agreed in writing by the Council in consultation with
Transport Planning.  The RTP will have particular regard
to provision for walking, cycling and public transport
access to and within the site and will identify the
measures to be provided, the system of management,
monitoring, review, reporting and the duration of the plan.

Page 6

Reason - To promote sustainable transport options and to
meet advice within Scottish Planning Policy on transport.
12. Prior to the commencement of the development hereby
approved, full visibility splays for both the vehicle access
onto the A977 of 90 metres along the channel line, as
demonstrated in the Transport Statement, shall be
provided to the left and right of the access, at a set-back
of 2.4 metres from the edge of the carriageway,
measured 1.05m above the road level to the standard
and specification required by the Council as Roads
Authority to the satisfaction of the Planning Authority. 
The visibility splays shall be physically formed on the
ground and any existing fences, walls, hedges or other
means of enclosure or obstructions within the splays shall
be removed and relocated outwith the splays.  Once
formed, the visibility splays shall be permanently retained
thereafter, and no visual obstruction of any kind shall be
permitted within the visibility splays so formed. 
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
13. Prior to the commencement of the development hereby
approved, a detailed plan indicating location, quantity,
specification, and maintenance requirements for
biodiversity enhancement measures including bat
boxes/bricks, swift boxes/bricks, provision of hedgehog
highways and wildlife kerbs and native tree and/or
hedgerow planting for the site shall be submitted for the
further written agreement of the Council as Planning
Authority.  The agreed scheme shall be implemented
prior to the bringing into use or completion of the
development, whichever is the earlier, and thereafter
maintained in a reasonable condition for the life of the
development, to the satisfaction of the Council as
Planning Authority. 
Reason - In the interests of protecting environmental
quality and of biodiversity. 
14. No site clearance or removal of vegetation, including
trees and shrubs will take place between 1st March and
31st August inclusive unless a competent ecologist has
undertaken a careful and detailed check of vegetation for
active birds' nests immediately before the vegetation is to
be cleared and provided written confirmation that no birds
will be harmed and/or that there are appropriate
measures in place to protect nesting birds on site.  Any
such written confirmation must be submitted to the
planning authority prior to commencement of works.  
  
Reason - In the interests of employing best practice
ecology and to ensure there is no adverse impact on any
protected species as identified under the Wildlife and
Countryside Act (1981).

Page 7

15. Measures to protect animals from being trapped in open
excavations and/or pipe and culverts shall be
implemented for the duration of the construction works of
the development hereby approved.  The measures may
include creation of sloping escape ramps for animals,
which may be achieved by edge profiling of
trenches/excavations or by using planks placed into them
at the end of each working day and open pipework
greater than 150 mm outside diameter being blanked off
at the end of each working day 
Reason - In order to prevent animals from being trapped
within any open excavations. 
16. The conclusions and recommended action points within
the supporting tree method statement and replanting
schedule by Elan Consultancy submitted and hereby
approved (document 51 relates) shall be fully adhered to,
respected and undertaken as part of the construction
phase of development, to the satisfaction of the Council
as Planning Authority.
Reason - To ensure the trees are protected during
construction. 
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan. 
Procedural Notes
1. Permission shall not to be issued until the Section 75
Agreement has been signed and registered to take
account of this application.  The legal agreement should
be concluded and completed within 4 months of the date
of any Committee approval.  Failure to conclude a legal
agreement within 4 months will result in the planning
application being re-assessed through failing to comply
with the associated developer contributions policy and
may be ultimately recommended for refusal under
delegated powers 
Informatives
1. Under Section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.  A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement
action being taken.  Please use the form attached
herewith.
2. As soon as practicable after the development is
complete, the person who completes the development is

Page 8

obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.  Please
use the form attached herewith.
3. The applicant is advised that Perth and Kinross Council
have a charging scheme for recycling and waste bins for
new build properties and newly created dwellings. 
Further information can be found at:
https://www.pkc.gov.uk/binrequests 
4. Application for a new postal address should be made via
the Street Naming and Numbering page on the Perth &
Kinross Council website at www.pkc.gov.uk/snn.  Please
note there is a charge for this service and submission
cannot be made until the relevant Building Warrant has
been approved.
5. No work shall be commenced until an application for
building warrant has been submitted and approved.
6. The Air Source Heat Pump shall be certificated in
accordance with Microgeneration Certification Scheme
007 and installed by an installation company certificated
in accordance with Microgeneration Installation Standard
3005 and in compliance with the calculation procedure
contained in Table 2 of Microgeneration Certification
Scheme Planning Standards (MCS 020), confirming that
the permitted development noise limit of 42 dB LAeq, 5
mins will be met. In addition, the Air Source Heat Pump
shall be so enclosed, attenuated and/or maintained such
that any noise therefrom shall not exceed Noise Rating
35 between 0700 and 2300 hours daily, or Noise Rating
25 between 2300 and 0700 hours daily, within any
neighbouring residential property, with all windows
slightly open, when measured and/ or calculated and
plotted on a rating curve chart.
7. This planning permission is granted subject to conditions,
some of which require further information to be submitted
to Development Management either before works can
start on site or at a certain time.  The required information
must be submitted via the ePlanning portal if your original
application was lodged that way, otherwise send it to us
at developmentmanagement@pkc.gov.uk.  Please be
aware that a fee is payable in respect of each request
made, though there is no limit to the number of conditions
that can be discharged in a single request.  The Fees
Charter is available on our website www.pkc.gov.uk.
The Council has two months to consider the information. 
You should therefore submit the required information
more than two months before your permission expires. 
We cannot guarantee that submissions made within two
months of the expiry date of your permission will be able
to be dealt with before your permission lapses. 
8. This application was varied prior to determination, in
accordance with the terms of Section 32A of the Town

Page 9

and Country Planning (Scotland) Act 1997, as amended. 
The variations incorporate changes to the site layout and
landscaping.
9. The applicant is advised that, in terms of Sections 109 of
the New Roads and Street Works Act 1991, he/she/they
must obtain from the Council, to place, maintain or adjust
apparatus in, or under a Road or remove apparatus from
a road.  Application forms are available at
https://www.pkc.gov.uk/article/14916/Road-and-footway-
permits.
10. The applicant should be advised that in terms of Section
21 of the Roads (Scotland) Act 1984 they must obtain
from the Council as Roads Authority consent to construct
a new road prior to the commencement of roadworks. 
Advice on the disposal of surface water must be sought
at the initial stages of design from Scottish Water and the
Scottish Environment Protection Agency.  Please note
that a fee is chargeable for the processing of RCC
applications.
11. The applicant is advised that, in terms of Sections 56 of
the Roads (Scotland) Act 1984, he/she/they must obtain
from the Council, as Roads Authority, consent to open an
existing road or footway prior to the commencement of
works.  Information on junction types, requirements for
Vehicular Access consents (VA1) and application forms
are available at www.pkc.gov.uk/vehicleaccess.  Advice
on the disposal of surface water should be sought at the
initial stages of design from Scottish Water and the
Scottish Environment Protection Agency. 
(ii) 23/01313/FLL - Erection of 7 dwellinghouses, formation of
vehicular access, landscaping and associated works, land
east of Honeysuckle Cottage, Carnbo (Report No. 24/279) 
Mrs E Hutchinson, objector, followed by Mr J Wright, agent on
behalf of the applicant (via telephone), addressed the
Committee and answered Members questions. 
Motion (Councillor B Brawn and Bailie C Ahern) 
Refuse, on the grounds that the application is contrary to Policy
1A: Placemaking and Policy 17c: Residential Areas of Perth and
Kinross Local Development Plan 2, as the proposed
development will adversely impact the quality of the surrounding
built and natural environment and character of the village of
Carnbo. 
Amendment (Councillors D Illingworth and I James) 
Grant, subject to the following terms, conditions and
informatives:

Page 10

Conditions
1. This planning permission will last only for three years
from the date of this decision notice, unless the
development has been lawfully started within that period.
Reason - This is a Planning Permission in terms of
Section 58 of the Town and Country Planning (Scotland)
Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019.
2. The development hereby approved must be carried out in
accordance with the approved drawings and documents,
unless otherwise provided for by conditions imposed by
this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
3. The foul drainage infrastructure capable of achieving not
less than 125% phosphorus mitigation associated with
this development shall be undertaken in a phased
manner:
(a) No development shall commence on the approved
development site until the mitigating foul drainage
infrastructure at the remote properties at Burach Beg
KY13 0NX, The Farmhouse KY13 0NX and
Crossroads Cottage KY13 0NJ has been installed, 
(b) Following the installation of the foul drainage
infrastructure at the remote property/properties, the
development site shall only be occupied once the
foul drainage infrastructure for the development site
has been installed. 
For the avoidance of doubt the installed drainage
infrastructure at the development site as approved shall
be retained.  
Reason - To ensure appropriate drainage arrangements
are installed and retained to remove phosphorus from the
Loch Leven Catchment Area thereby ensuring
compliance with Policy 46 A & B: Loch Leven Catchment
Area of the Perth and Kinross Local Development Plan 2
(2019) and Enterprise and Infrastructure Committee
Resolution of 28 August 2013.
4. Development shall not commence until the applicant has
submitted approved CAR licence(s) under the Water
Environment (Controlled Activities)(Scotland) Regulations
2011 for the drainage infrastructure associated with this
project to the Council as Planning Authority and the
Planning Authority has confirmed receipt of the
documentation in writing.
Reason - To ensure appropriate drainage arrangements
are installed and retained to remove phosphorus from the
Loch Leven Catchment Area thereby ensuring
compliance with Policy 46 A & B: Loch Leven Catchment
Area of the Perth and Kinross Local Development Plan 2
(2019) and Enterprise and Infrastructure Committee
Resolution of 28 August 2013.

Page 11

5. Development shall not commence until the developer has
secured the implementation of a programme of
archaeological work in accordance with a Written
Scheme of Archaeological Investigation (WSI) which has
been submitted by the developer and agreed in writing by
the Council as Planning Authority, in consultation with
Perth and Kinross Heritage Trust (PKHT).  Thereafter, the
developer shall ensure that the programme of
archaeological works is fully implemented including that
all excavation, preservation, recording, recovery,
analysis, publication and archiving of archaeological
resources within the development site is undertaken. 
Should the archaeological works, as required by the WSI,
identify a requirement for post-excavation analysis, the
development as approved shall not be occupied or
brought into use until a Post-Excavation Research Design
(PERD) has been submitted to and agreed in writing by
the Council as Planning Authority, in consultation with
PKHT.  The PERD shall be carried out in complete
accordance with the approved details. Furthermore, the
developer shall afford access at all reasonable times to
PKHT or a nominated representative and shall allow them
to observe work in progress.
Reason - To ensure archaeological monitoring is carried
out to safeguard and record any archaeological remains
within the development area.
6. Prior to the occupation of the development or any phase
of the development, whichever is the sooner, a landscape
management plan, including long term design objectives,
management responsibilities and maintenance schedules
for all landscape areas (other than small privately-owned
domestic gardens) shall be submitted to and agreed in
writing by the Council as Planning Authority, for its
approved use.  The landscape management plan as
agreed shall, where appropriate, include phased
implementation concurrent with the development and
shall be fully implemented to the satisfaction of the
Council as Planning Authority. 
Reason - To secure the maintenance of communal areas. 
7  Prior to the commencement of the development hereby
approved, a detailed plan indicating location, quantity,
specification, and maintenance requirements for
biodiversity enhancement measures including bat
boxes/bricks, swift boxes/bricks, provision of hedgehog
highways and wildlife kerbs and native tree and/or
hedgerow planting for the site shall be submitted for the
further written agreement of the Council as Planning
Authority.  The agreed scheme shall be implemented
prior to the bringing into use or completion of the
development, whichever is the earlier, and thereafter
maintained in a reasonable condition for the life of the

Page 12

development, to the satisfaction of the Council as
Planning Authority
Reason - In the interests of protecting environmental
quality and of biodiversity.
8. Development shall not commence on site until an
evaluation for the potential of the site to be affected by
contamination by a previous use has been undertaken
and, as a minimum, a Preliminary Risk Assessment
(Phase 1 Desk Study) has been submitted for
consideration and accepted by the Council as Planning
Authority.  If the preliminary risk assessment identifies the
need for further assessment, an intrusive investigation
shall be undertaken to identify; 
I. the nature, extent and type(s) of contamination on
the site 
II.  measures to treat/remove contamination to ensure
the site is fit for the use proposed 
III.  measures to deal with contamination during
construction works 
IV.  condition of the site on completion of
decontamination measures. 
Prior to the completion or bringing into use of any part of
the development the measures to decontaminate the site
shall be fully implemented in accordance with the scheme
subsequently agreed by the Council as Planning
Authority.  Verification that the scheme has been fully
implemented must also be submitted to the Council as
Planning Authority.
Reason - In order to deal with any potential contamination
of the site as a result of its former use.
9. Prior to the commencement of development details of the
footpath along the frontage of the site with the A91 and
the vehicular access to the site shall be submitted to and
agreed in writing by the Council as Planning Authority. 
The details as agreed shall be completed prior to the
occupation of the development.
Reason - In the interests of pedestrian and traffic safety
and in the interests of free traffic flow.
10. Prior to the commencement of development details of the
visitor parking bays shall be submitted to and agreed in
writing by the Council as Planning Authority.  The details
submitted shall include step off facilities to enable
occupants of the vehicles to safely exit the vehicles onto
an area of hardstanding.  The details as agreed shall be
completed prior to the occupation of the development.
Reason - In the interests of road safety; to ensure the
provision of adequate off street car parking facilities.
11. Prior to the commencement of development details a
swept path assessment to demonstrate that a 12m long
vehicle. The details as agreed shall be completed prior to
the occupation of the development.

Page 13

Reason - In the interests of pedestrian and traffic safety
and in the interests of free traffic flow.
12. Prior to the commencement of development details of the
service strips commencing from the entrance in order to
support service infrastructure, including lighting columns
shall be submitted to and agreed in writing by the Council
as Planning Authority.  The details as agreed shall be
completed prior to the occupation of the development.
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
13. Prior to the commencement of development details the
outfalls for the roads drainage and the location of the
infiltration trench shall be submitted to and agreed in
writing by the Council as Planning Authority.
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
14. Prior to the commencement of the development hereby
approved, the applicant shall submit for the further written
agreement of the Council as Planning Authority, in
consultation with the Roads Authority (Structures), a
Construction Traffic Management Scheme (TMS) which
shall include the following:
(a) restriction of construction traffic to approved routes
and the measures to be put in place to avoid other
routes being used;
(b)  timing of construction traffic to minimise impact on
local communities particularly at school start and
finishing times, on days when refuse collection is
undertaken, on Sundays and during local events;
(c)  a code of conduct for HGV drivers to allow for
queuing traffic to pass;
(d)  arrangements for liaison with the Roads Authority
regarding winter maintenance;
(e)  emergency arrangements detailing communication
and contingency arrangements in the event of
vehicle breakdown;
(f)  arrangements for the cleaning of wheels and chassis
of vehicles to prevent material from construction
sites associated with the development being
deposited on the road;
(g)  arrangements for cleaning of roads affected by
material deposited from construction sites
associated with the development;
(h) arrangements for signage at site accesses and
crossovers and on roads to be used by construction
traffic in order to provide safe access for
pedestrians, cyclists and equestrians;
(i)  details of information signs to inform other road
users of construction traffic;

Page 14

(j)  arrangements to ensure that access for emergency
service vehicles are not impeded;
(k)  co-ordination with other significant developments
known to use roads
(l)  traffic arrangements in the immediate vicinity of
temporary construction compounds; 
(m)  the provision and installation of traffic counters at the
developer 's expense at locations to be agreed prior
to the commencement of construction; 
(n)  monitoring, reporting and implementation
arrangements;  
(o)  arrangements for dealing with non-compliance; and 
(p)  details of HGV movements to and from the site.   
The TMS as approved shall be strictly adhered to during
the entire site construction programme. 
Reason - In the interest of proper site management. 
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan.  
Procedural Notes
1. Permission shall not to be issued until the Section 75
Agreement has been signed and registered to take
account of this application.  The legal agreement should
be concluded and completed within 4 months of the date
of any Committee approval.  Failure to conclude a legal
agreement within 4 months will result in the planning
application being re-assessed through failing to comply
with the associated developer contributions policy and
may be ultimately recommended for refusal under
delegated powers 
Informatives
1. Under Section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.  A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement
action being taken.  Please use the form attached
herewith.
2. As soon as practicable after the development is
complete, the person who completes the development is
obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.  Please
use the form attached herewith.

Page 15

3. No work shall be commenced until an application for
building warrant has been submitted and approved.
4. Application for a new postal address should be made via
the Street Naming and Numbering page on the Perth &
Kinross Council website at www.pkc.gov.uk/snn.  Please
note there is a charge for this service and submission
cannot be made until the relevant Building Warrant has
been approved.
5. This planning permission is granted subject to conditions,
some of which require further information to be submitted
to Development Management either before works can
start on site or at a certain time.  The required information
must be submitted via the ePlanning portal if your original
application was lodged that way, otherwise send it to us
at developmentmanagement@pkc.gov.uk.  Please be
aware that a fee is payable in respect of each request
made, though there is no limit to the number of conditions
that can be discharged in a single request.  The Fees
Charter is available on our website www.pkc.gov.uk. 
The Council has two months to consider the information. 
You should therefore submit the required information
more than two months before your permission expires. 
We cannot guarantee that submissions made within two
months of the expiry date of your permission will be able
to be dealt with before your permission lapses.
6. The applicant is advised that Perth and Kinross Council
have a charging scheme for recycling and waste bins for
new build properties and newly created dwellings. Further
information can be found at:
https://www.pkc.gov.uk/binrequests 
7. This application was varied prior to determination, in
accordance with the terms of Section 32A of the Town
and Country Planning (Scotland) Act 1997, as amended. 
The variations incorporate changes to dwelling numbers
and the site layout.
8. SEPA highlight that once the mitigation has been
allocated it cannot be shared or used in the future. 
In terms of Standing Order 21.5 a roll call vote was taken. 
4 members voted for the Motion as follows:
Bailie C Ahern, Councillors B Brawn, I Massie and G Stewart. 
6 members voted for the Amendment as follows:
Councillors E Drysdale, K Harvey, D Illingworth, I James, Bailie
C McLaren and Councillor I MacPherson. 
Resolved:
In accordance with the Amendment. 
THE COMMITTEE TOOK A 10 MINUTE RECESS.

Page 16

(iii) 24/00279/FLL - Change of use and alterations to residential
outdoor centre to form 8 serviced apartments (optional
short-term let apartments), erection of storage buildings,
formation of vehicular access, parking areas, paths, steps
and associated works, Dunolly, Taybridge Drive, Aberfeldy
(Report No. 24/280) 
Resolved:
Grant, subject to the following terms, conditions and
informatives: 
Conditions
1. This planning permission will last only for three years
from the date of this decision notice, unless the
development has been lawfully started within that period.
Reason - This is a Planning Permission in terms of
Section 58 of the Town and Country Planning (Scotland)
Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019.
2. The development hereby approved must be carried out in
accordance with the approved drawings and documents,
unless otherwise provided for by conditions imposed by
this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
3. The development hereby approved shall be used solely
for short term accommodation and shall not be occupied
as the sole or main residence of any occupant.
Reason - In order to clarify the terms of the permission; to
control and restrict the use of the building.
4. Development shall not commence until the developer has
secured an archaeological standing building survey, to be
carried out by an independent and suitably qualified
archaeological organisation.  The scope of the
archaeological standing building survey will be set by the
Council as Planning Authority, in consultation with Perth
and Kinross Heritage Trust.  The name of archaeological
organisation retained by the developer shall be given to
the Council as Planning Authority and PKHT in writing not
less than fourteen days before the commencement date
provided in the Notice of Initiation of Development. 
Copies of the resulting survey shall be deposited in the
National Record of the Historic Environment and in the
Perth and Kinross Historic Environment Record upon
completion of the survey.
Reason - To ensure an appropriate archaeological
standing building survey is carried out and the resulting
survey is recorded properly.
5. Prior to the commencement of the development hereby
approved, details of the specification and colour of the
proposed external finishing materials to be used shall be
submitted to and agreed in writing by the Council as

Page 17

Planning Authority.  The scheme as agreed shall be
implemented prior to the completion or bringing into use
of the development, whichever is the earlier.
Reason - In the interests of residential amenity; to ensure
a satisfactory standard of local environmental quality.
6. Any hidden historic features which are revealed during
the course of works shall be retained in situ, and any
work(s) which may adversely affect the feature shall be
suspended and the Council as Planning Authority notified
immediately. Prior to the recommencement of such
works, details of a scheme for the retention and/or proper
recording of the feature shall be submitted to, and
approved in writing by, the Council as Planning Authority.
Reason - In the interests of protecting the special
character of the Listed building.
7. All new external and internal works and finishes and
works of making good the retained fabric, shall match the
existing adjacent work with regard to the methods used
and to material, colour, texture and profile, unless shown
otherwise on the drawings or other documentation hereby
approved or required by any condition(s) attached to this
consent.
Reason - In the interests of protecting the special
character of the Listed Building.
8. No new plumbing, pipes, soil stacks, flues, vents or
ductwork shall be fixed on the external faces of the
building unless shown on the drawings hereby approved.
Reason - In the interests of protecting the special
character of the Listed Building.
9. No new grilles, security alarms, lighting, cameras or other
equipment shall be fixed on the external faces of the
building unless shown on the drawings hereby approved.
Reason - In the interests of protecting the special
character of the Listed Building.
10. Notwithstanding the details shown on the drawings
hereby approved, no permission is granted for the
existing uPVC windows, which remain unauthorised.
Reason - In the interests of protecting the special
character of the Listed Building.
11. Prior to the commencement of the development hereby
approved, a detailed landscaping and planting scheme
for the site shall be submitted for the written agreement of
the Council as Planning Authority.  The scheme shall
include details of the height and slopes of any mounding
or recontouring of the site, full details of all hard
landscaping proposals including materials and installation
methods and, species, height, size and density of trees
and shrubs to be planted.  The scheme as subsequently
approved shall be carried out and completed within the
first available planting season (October to March) after
the completion or bringing into use of the development,
whichever is the earlier, and the date of Practical

Page 18

Completion of the landscaping scheme shall be supplied
in writing to the Council as Planning Authority within 7
days of that date.  The scheme as agreed and
implemented shall thereafter be maintained to the
satisfaction of the Council as Planning Authority.
Reason - To ensure a satisfactory standard of
development and environmental quality and to reserve
the rights of the Planning Authority.
12. The conclusions and recommended action points within
the supporting Tree Survey and Arboricultural Report
dated September 2024 submitted and hereby approved
(document(s) document no. 41 relates) shall be fully
adhered to, respected and undertaken as part of the
construction phase of development, to the satisfaction of
the Council as Planning Authority.
Reason - To ensure a satisfactory standard of
development and environmental quality and to reserve
the rights of the Planning Authority.
13. All trees on site, other than those marked for felling on
the approved plans, shall be retained.
Reason - To ensure a satisfactory standard of
development and environmental quality and to reserve
the rights of the Planning Authority.
14. All trees identified for retention and any peripheral trees
bounding the site, which may be affected by any element
of the approved development and its associated
construction, (including land within the blue site area)
shall be protected in full accordance with BS 5837: 2012
'Trees in relation to design, demolition and construction'.
Approved Tree Protection measures shall not be
removed breached or altered without prior written
authorisation from the local Planning Authority but shall
remain in a functional condition throughout the entire
development or as per the phasing plan.  If such
protection measures are damaged beyond effective
functioning then works that may compromise the
protection of trees shall cease until the protection can be
repaired or replaced with a specification that shall provide
a similar degree of protection.
Reason - To ensure a satisfactory standard of
development and environmental quality and to reserve
the rights of the Planning Authority.
15. Prior to the commencement of development a pre-start
meeting shall be held with Perth & Kinross Council
Enforcement Officer (Trees), and the applicant project
manager, arboriculturalist and ground works contractor to
examine tree protection measures, and that they accord
with standard requirements (fencing / no dig construction
etc), position of proposed services/drainage to the site
and site storage facilities.  The measures as agreed shall
be fully implemented as part of the planning permission.

Page 19

Reason - To ensure a satisfactory standard of
development and environmental quality and to reserve
the rights of the Planning Authority.
16. Prior to the development hereby approved being
completed or brought into use, the vehicular access shall
be formed in accordance with Perth & Kinross Council's
Road Development Guide Type B Figure 5.6 access
detail, of Type A Road construction detail.  The Type A
Road construction detail shall continue into the entrance
for a distance of 3 metres from the boundary of the public
road surface.
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
17. Prior to the commencement of the development hereby
approved, full visibility splays of 43 metres along the
channel line shall be provided to the left and right of the
access, at a set-back of 2.4 metres measured 1.05m
above the road level to the standard and specification
required by the Council as Roads Authority to the
satisfaction of the Planning Authority.  The visibility splays
shall be physically formed on the ground and any existing
fences, walls, hedges, trees, or other means of enclosure
or obstructions within the splays shall be removed and
relocated outwith the splays.  Once formed, the visibility
splays shall be permanently retained thereafter, and no
visual obstruction of any kind shall be permitted within the
visibility splays so formed.
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
18. Prior to the development hereby approved being
completed or brought into use, the existing underground
street lighting cable in the footway shall be lowered to a
depth of 350mm under extents of proposed vehicle
access.
Reason - In the interests of road safety
19. The conclusions and recommended action points within
the supporting biodiversity survey submitted and hereby
approved (Preliminary Roost Assessment and Bat Survey
document 27 relates) shall be fully adhered to, respected
and undertaken as part of the construction phase of
development, to the satisfaction of the Council as
Planning Authority.
Reason - In the interests of employing best practice
ecology and to ensure there is no adverse impact on any
protected species as identified under the Wildlife and
Countryside Act (1981).
20. Prior to the completion or occupation of the building(s)
hereby approved, whichever is the earlier, 15 swift
nesting boxes or bricks shall be provided on the site. 
Thereafter, the agreed scheme shall be maintained in a

Page 20

reasonable condition for the life of the development, to
the satisfaction of the Council as Planning Authority.
Reason - In the interests of protecting environmental
quality and of biodiversity. 
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan. 
Informatives
1. Under section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.  A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement action
being taken.  Please use the form attached herewith.
2. As soon as practicable after the development is
complete, the person who completes the development is
obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.  Please
use the form attached herewith.
3. No work shall be commenced until an application for
building warrant has been submitted and approved.
4. The applicant is advised that in terms of Sections 56 of
the Roads (Scotland) Act 1984 he/she/they must obtain
from the Council, as Roads Authority, consent to open an
existing road or footway prior to the commencement of
works.  Information on junction types, requirements for
Vehicular Access consents (VA1) and application forms
are available at www.pkc.gov.uk/vehicleaccess.  Advice
on the disposal of surface water should be sought at the
initial stages of design from Scottish Water and the
Scottish Environment Protection Agency.
5. The applicant is advised that Perth and Kinross Council
have a charging scheme for recycling and waste bins for
new build properties and newly created dwellings. Further
information can be found at:
https://www.pkc.gov.uk/binrequests 
6. Existing buildings or structures may contain nesting birds
between 1st March and 31st August inclusive.  The
applicant is reminded that, under the Wildlife and
Countryside Act 1981, as amended (section 1), it is an
offence to remove, damage or destroy the nest of any
wild bird while that nest is in use or being built.  Planning
permission for a development does not provide a defence
against prosecution under this Act.

Page 21

7. The presence of protected species, and the extent to
which they could be affected by the proposed
development, should be established before works
commence.  Should protected species be identified within
the site the developer should ensure that all appropriate
measures required to comply with the relevant legislation
are carried out.
8. The applicant is advised that under The Civic
Government (Scotland) Act 1982 (Licensing of Short-term
Lets) Order 2022, a licence is required to operate a short-
term let. More information can be found at
https://www.pkc.gov.uk/shorttermlets 
9. The applicant should take note of the information and
advice contained within the consultation response from
Scottish Water.
10. The applicant is advised to refer to Perth & Kinross
Council's Supplementary Guidance on Flood Risk and
Flood Risk Assessments 2021 as it contains advice
relevant to your development.
https://www.pkc.gov.uk/ldp2floodrisk 
11. This application was varied prior to determination, in
accordance with the terms of Section 32A of the Town
and Country Planning (Scotland) Act 1997, as amended. 
The variations incorporate changes to elevational details
and submission of an up to date tree survey. 
(iv)  24/01115/FLL - Alteration to dwellinghouse (in retrospect),
35 Simpson Wynd, Kinross, KY13 8GP (Report No. 24/281) 
Resolved:
Grant, subject to the following terms, conditions and
informatives: 
Conditions are not required as the works have been completed. 
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan. 
Informative Notes
1. This application was varied prior to determination, in
accordance with the terms of section 32A of the Town
and Country Planning (Scotland) Act 1997, as amended. 
The variations incorporate changes to include the
specification of materials.
2. A building warrant will be required.
3. The applicant should take note of the information and
advice contained within the consultation response from
Scottish Water.

Page 22

6. PROPOSAL OF APPLICATION NOTICES (PAN) 
(i) 24/00007/PAN - Formation of a 22MW solar farm comprising
ground mounted solar arrays, inverters, 2 substations,
compound, vehicular access and access tracks, security fencing,
CCTV cameras and associated works, land 320 metres north west
of Peattie Farm, Kinnochtry, Coupar Angus, Blairgowrie (Report
No. 24/282) 
Councillor I James requested due consideration be given to visual
aspects, sightlines and disruption to the local community. 
The contents of the Report by the Strategic Lead – Economy,
Development and Planning, were noted.