A83 RaBt
• Ground Investigation works are still ongoing on A83t at RaBT, due for
completion early September, weather depending. There are provisional
planned closure dates on 11th & 12th August and 26th & 27th August to enable
works, noting that traffic will utilise the OMR in this instance to access Argyle
& Bute
• There is still a significant amount of works to be completed at this section of
the A83T and are listed below, noting that the full programme is still be
determined and that the works will commence directly after the conclusion of
the ground investigation works; 
1. Westbound & Phase 12 Drainage Improvements – working on the
lower slopes
2. Catch fence repairs, various phases – working on the upper slopes
3. Further Improvement works at Glen Kinglas  - Slip interventions &
culvert/drainage clearing
• The hillside is being monitored continuously by our dedicated team as per our
Landslide Management Plan.
• At Cairndow, we are still awaiting SSE to confirm the electrical connection
required to enable the new signage 
A82 between Tarbet & Inverannan;
• There will be investigation works on the current drainage assets and filter
drains using latest scanning equipment to determine their current condition &
highlight issues to be attended to. This will be carried out by a slow moving
vehicle during off peak hours to minimise disruptiuon & currently programmed
for end of August to early September.
• On the same route, there are a further 6 re-surfacing schemes using planned
overnight. The scheme Tarbet will use the 3 way temporary traffic signals from
17/08 for 5 days & then the remaining 5 sites will utilise full closures starting at
8pm with amnesties from 24/08 to 01/10 along with other drainage &
vegetation management works being completed at the same time. 
The implementation of the 20mph at Tarbet & Arrocher is being progressed and all
locations should be fully installed throughout Argyle & Bute by the end of 2025.
Although the average speed cameras which were deployed last year will not be
reinstated to this stretch A82 (Arden to Tarbet) this year but will remain under active
consideration, noting that there are five mobile enforcement locations between Arden
and Tarbet which Police Scotland will enforce throughout the summer.