Perth and Kinross Council
Planning and Placemaking Committee – 11 June 2025
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 25/150)
Proposal: Upgrade to existing overhead line - Alyth to Tealing - ECU00005167
Location: Land 320 Metres West of Drumkilbo Mains Farm, Meigle, Blairgowrie,
PH12 8QS
Ref. No: 24/01874/ECU37
Ward No: P2- Strathmore
Summary
This report recommends no objection to the proposal as the development is
considered to comply with the relevant provisions of the Development Plan and there
are no material considerations apparent which outweigh the Development Plan.
Background and Description of Proposal
1 An application under Section 37 of the Electricity Act 1989 has been submitted to
the Scottish Government’s Energy Consents Unit (ECU) along with a request that
Ministers issue a direction that planning permission is deemed to be granted
under section 57(2) of the Town and Country Planning (Scotland) Act 1997 for
consent to upgrade approximately 14 kilometres (km) of an existing 275 kilovolts
(kV) overhead line (OHL), connecting substations at Alyth and Tealing, to enable
operation at 400kV.
2 The Proposed Development would include the following elements, for which
Section 37 consent and deemed planning consent under Section 57 (2) of the
Town and Country Planning (Scotland) Act 1997, as amended, is sought:
 replacement of conductors, insulators and fittings on the existing steel lattice
towers;
 where required, tower condition works including steelwork and tower leg
foundation work to strengthen the existing steel lattice towers;
 the sag of new proposed phase conductor will be matched with sag of
existing Optical Ground Wire (OPGW); and

Page 2

 subject to further engineering and design checks, some modifications to the
existing towers may be required, such as the inverting of cross arms to
improve clearances, and changes to the insulator set configurations.
3 The applicant is also seeking deemed planning permission under section 57(2) of
the Town and Country Planning (Scotland) Act 1997 for certain elements of the
project, or ancillary works required to facilitate its construction and operation.
These ancillary works will include:
 Vegetation clearance;
 Access track construction and access track upgrades;
 Temporary site compounds (at working areas, to include mobile welfare unit
and refuelling/spill kits etc.);
 Laydown areas;
 Crane pads;
 Equipotential zones (EPZs) and temporary measures to protect road, rail and
water crossings; and
 The increase in operating voltage of the OHL requires a wider wayleave
corridor, therefore some tree felling will be required where there are
infringements to this corridor.
4 The OHL begins at Alyth Substation where it connects to an existing lattice tower
heading south. There are a total of 45 OHL towers on the proposed route
section, of which 8 are within the PKC boundary, with the remainder in Angus.
Environmental Impact Assessment
5 Schedule 1 of the EIA Regulations lists projects where EIA is mandatory. The
proposal has been treated by the applicant as ‘Schedule 1’ development on the
basis that although the criteria outlined in paragraph 1(3) of Schedule 1 refers to
construction of power lines with a voltage of 200 kilovolts or more and a length of
15 kilometres, and the work here is replacement of under 15 kilometres of line,
the length across which the works taking place exceeds 15 kilometres.
Development Plan
6 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.
National Planning Framework 4
7 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve peoples lives by making sustainable, liveable
and productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.

Page 3

8 The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 3: Biodiversity
 Policy 4: Natural Places
 Policy 5: Soils
 Policy 6: Forestry, Woodland and Trees
 Policy 7: Historic Assets and Places
 Policy 11: Energy
 Policy 18: Infrastructure First
Perth and Kinross Local Development Plan 2019
9 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
10 The principal relevant policies are, in summary;
 Policy 1A: Placemaking
 Policy 15: Public Access
 Policy 26A: Scheduled Monuments and Archaeology: Scheduled Monuments
 Policy 26B: Scheduled Monuments and Archaeology: Archaeology
 Policy 27A: Listed Buildings
 Policy 29: Gardens and Designed Landscapes
 Policy 31: Other Historic Environment Assets
 Policy 33A: Renewable and Low Carbon Energy: New Proposals for
Renewable and Low-Carbon Energy
 Policy 38A: Environment and Conservation: International Nature
Conservation Sites
 Policy 38B: Environment and Conservation: National Designations
 Policy 38C: Environment and Conservation: Local Designations
 Policy 39: Landscape
 Policy 40A: Forestry, Woodland and Trees: Forest and Woodland Strategy
 Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
 Policy 41: Biodiversity
 Policy 51: Soils
 Policy 52: New Development and Flooding
 Policy 53A: Water Environment and Drainage: Water Environment
 Policy 56: Noise Pollution
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals

Page 4

Statutory Supplementary Guidance
11
 Supplementary Guidance - Forest & Woodland Strategy (adopted in 2020)
 Supplementary Guidance - Landscape (adopted in 2020)
 Supplementary Guidance - Placemaking (adopted in 2020)
PKC Non Statutory Guidance
12
 Planning Guidance - Planning & Biodiversity
 Supplementary Guidance - Renewable & Low Carbon Energy (draft)
Consultations
13 The decision making-body for the proposal is the ECU and PKC is in turn a
consultee. Therefore, the extent of PKC’s consultations was limited to internal
departments and PKHT. To help form PKC’s consideration and response, the
following bodies were consulted:
14 Perth and Kinross Heritage Trust: No objections. Conditions are
recommended requiring a programme of archaeological works, fencing and the
appointment of an Archaeological Clerk of Works (AcoW) to ensure compliance
with the EIA and an appropriate level of mitigation is provided where necessary.
15 Biodiversity: No objections. Conditions are recommended for compensatory
planting, a Construction Environmental Management Plan (CEMP), Biodiversity
Net Gain Plan and details of the Ecological Clerk of Works (ECoW).
16 Conservation Team: No objections. The proposed mitigation works identified in
the EIAR are acceptable.
17 Environmental Health (Noise Odour): No objections. A condition is
recommended to control potential noise.
Additional Statements
18 Screening Opinion EIA submitted
Environmental Impact Assessment (EIA):
Environmental Report
Submitted
Appropriate Assessment under Habitats
Regulations
AA is the responsibility of the
ECU
Design Statement or Design and Access
Statement
Not required
Appraisal
19 PKC has been consulted under Section 37 and Schedule 8 of the Electricity Act
1989, as one of the planning authorities in which the overhead line upgrades are
proposed. PKC’s role as consultee is to advise the ECU whether we have any

Page 5

objection to the proposal based on the provisions of the Development Plan and
any other material considerations. The Development Plan comprises NPF4, the
Perth and Kinross Local Development Plan 2019 and statutory supplementary
guidance.
20 Strategic Renewable Electricity Generation and Transmission Infrastructure is
identified in NPF4 as a Scotland-wide national development to support
renewable electricity generation, repowering and the expansion of the electricity
grid.
Landscape and Visual Amenity
21 The proposals are largely focused around upgrading existing OHL infrastructure.
Any additional impacts on landscape and visual amenity will be limited and there
are no specific concerns in this regard.
Residential Amenity
22 The project’s noise consultant contacted Environmental Health to agree the
methodology for the Noise Impact Assessment (NIA). There are no concerns in
terms of residential amenity subject to the imposition of conditions to control
noise as part of the CEMP.
Biodiversity
23 The submitted ecological information is comprehensive, and survey methods are
largely in accordance with published best practice. 1.7ha of tree removal is
proposed and no information on compensatory planting has been provided. A
condition is proposed that a Woodland Planting Strategy will be submitted to the
ECU in consultation with the relevant planning authorities.
24 Overall, the proposal is acceptable subject to the proposed conditions relating to
compensatory planting, a CEMP, and details of the ECoW.
Cultural Heritage and Conservation
25 The works proposed in the area of the Drumkilbo Garden & Designed Landscape
(GDL) are restricted to reducing the crowns of deciduous trees to maintain
clearance between the trees and overhead lines. As no felling is proposed, the
works would have a minor impact on the GDL.
26 PKHT has confirmed that the content of the EIAR Cultural Heritage chapter is
comprehensive and addresses their recommendations from previous scoping
conversations.
27 The proposed mitigation works identified in the EIAR are acceptable and are to
be included in the proposed conditions.
Conditions

Page 6

28 The ECU has also circulated draft conditions for the Section 37 and Deemed
Planning Permission for the consideration of consultees. These are set out
below. The draft conditions are broadly similar to those requested by consultees
and which PKC would expect to be imposed on a consent of this nature.
Conditions attached to Section 37 Consent
1. Commencement of development
(1) Commencement of Development shall be no later than five years from the
date of this consent, or in substitution, such other period as the Scottish
Ministers may hereafter direct in writing.
(2) Written confirmation of the intended date of Commencement of
Development shall be provided to the Planning Authorities and the Scottish
Ministers no later than one calendar month before that date.
Reason: To avoid uncertainty and ensure that the consent is implemented within
a reasonable period and to allow the Planning Authorities and Scottish Ministers
to monitor compliance with obligations attached to this consent and deemed
planning permission as appropriate.
2. Non-assignation
(1) This consent shall not be assigned without the prior written authorisation of
the Scottish Ministers. The Scottish Ministers may authorise the assignation,
with or without conditions.
(2) The Company shall notify the Planning Authorities and Scottish Ministers in
writing of the name of the assignee, principal named contact and contact
details within fourteen days of the consent being assigned.
Reason: To safeguard the obligations of the consent if transferred to another
company.
3. Serious Incident Reporting
(1) In the event of any serious breach of health and safety or environmental
obligations relating to the Development during the period of this consent
written notification of the nature and timing of the incident shall be submitted
to the Scottish Ministers within twenty-four hours of the incident occurring,
including confirmation of remedial measures taken and/or to be taken to
rectify the breach.
Reason: To keep the Scottish Ministers informed of any such incidents which
may be in the public interest.
4. Notification of Date of Final Energisation

Page 7

(1) Written confirmation of the Date of Final Energisation shall be provided to
the Planning Authorities and Scottish Ministers no later than one calendar
month after that date.
Reason: To allow the Planning Authorities and Scottish Ministers to record when
energisation of the line has taken place and comply with other conditions.
5. Woodland Planting Strategy
(1) There shall be no Commencement of Development unless and until a
Woodland Planting Strategy has been submitted to and approved in writing
by the Scottish Ministers, in consultation with the Planning Authorities.
(2) The Woodland Planting Strategy shall set out an approach for the replanting
of any trees felled by the Company as a result of the Development, to be
carried out within the areas under the jurisdiction of the appropriate
Planning Authority.
(3) The approved Woodland Planting Strategy shall then be implemented in full,
unless otherwise agreed in writing by the Scottish Ministers.
Reason: To protect Scotland’s woodland resource, in accordance with the
Scottish Government’s policy on the Control of Woodland Removal. 
Annex 2
Part 2
Conditions Attached to Deemed Planning Permission
1. Implementation in accordance with approved plans and requirements of the
section 37 consent
(1) Except as otherwise required by the terms of the section 37 consent and
deemed planning permission, the Development hereby approved shall be
undertaken in accordance with the Application and other documentation
lodged in support of the Application unless as may otherwise be agreed in
writing by the relevant Planning Authority.
Reason: To ensure that the Development is carried out in accordance with the
approved details.
2. Decommissioning Scheme
(1) In the event that the line, after the Date of Final Energisation, fails to
transmit electricity for a continuous period of 1 year a Decommissioning
Scheme shall be submitted to and for the further approval in writing by the

Page 8

relevant Planning Authorities. The scheme shall include details about the
removal of all elements of the Development, relevant access tracks and all
cabling, including where necessary details of:
(a) Justification for retention of any relevant elements of the Development;
(b) The treatment of disturbed ground surfaces;
(c) Management and timing of the works;
(d) Environmental management provisions, including species protection
plans;
(e) The removal of all components of the line from the site for recycling or
disposal;
(f) A traffic management plan to address any traffic impact issues during
the decommissioning period; and
(g) Details of financial provisions to ensure the scheme to be approved
can be implemented in full.
(2) Thereafter the Decommissioning Scheme shall be implemented in
accordance with the approved details and timetable.
Reason: To ensure that should the line no longer be required or no longer benefit
from Section 37 consent, than an appropriate mechanism is in place for
decommissioning of the Development.
3. Aviation Charting and Safety Management
(1) There shall be no commencement of Development unless and until written
notification has been provided to the Ministry of Defence at least 14 days
prior to commencement of works providing the following information:
(a) The date of the commencement of the erection of the lattice towers;
(b) The maximum height of any construction equipment to be used in the
erection of the lattice towers;
(c) The date any lattice towers are brought to use;
(d) The latitude and longitude and maximum heights of each lattice tower
Reason: To maintain aviation safety
4. Construction and Environmental Management Plan
(1) There shall be no Commencement of Development unless and until a
Construction Environmental Management Plan (CEMP) containing site
specific details of all on-site construction works, post-construction
reinstatement, drainage and mitigation, together with details of their
timetabling, has been submitted to, and approved in writing by, the relevant
Planning Authorities. The CEMP shall be informed by the site and ground
investigation works and best practice guidance. 
(2) The CEMP shall provide:

Page 9

(a) A site waste management plan (dealing with all aspects of waste
produced during the construction period other than peat and other
carbon rich soils), including details of contingency planning in the event
of accidental release of materials which could cause harm to the
environment, evidencing all proposals comply with SEPA’s guidance
and the requirements of the waste management licensing regime as
appropriate;
(b) Details of the location, layout, formation of the construction compound,
welfare facilities, any areas of hardstanding, turning areas, internal
access tracks, car parking, material and aggregate stockpiles, oil, fuel
and chemical storage, lighting columns, and any construction
compound boundary fencing required for the construction period;
(c) A dust management plan detailing all mitigation/dust suppression
measures intended to reduce the impacts of dust on site, including
measures to reduce dust on roads;
(d) Site specific details for management and operation of any concrete
batching plant (including disposal of pH-rich waste water and
substances);
(e) Details of measures to be taken to prevent loose or deleterious
material being deposited on the local road network including wheel
cleaning and lorry sheeting facilities, and measures to clean the site
entrances and the adjacent local road network;
(f) A Pollution Prevention and Incident Plan incorporating a Pollution
Prevention Plan, Pollution Incident Plan and a Pollution Control
Monitoring Plan, this shall include measures to protect watercourses,
groundwater, management of natural surface hydrological flows
(flushes, springs, etc.) and protection of peatland/soils, arrangements
for the storage and management of oil and fuel and other chemicals on
the site and sewage disposal and treatment;
(g) Details of soil storage and management including outline quantities,
locations, (other than peat and other carbon rich soils) and
management of long term storage of construction generated soils to
facilitate future site restoration;
(h) A drainage management strategy, demonstrating how all surface and
waste water arising during and after construction is to be managed and
prevented from impacting on the water environment and to mitigate
flood risk using the most up to date SEPA flood extent map;
(i) A surface water and groundwater management and treatment plan,
including details of the separation of clean and dirty water drains, and
location of settlement lagoons for silt laden water;
(j) Details of temporary site illumination, including measures to ensure
light spill/pollution is minimised and avoids habitats within the site and
does not extend beyond the immediate working area, and not beyond
the site boundary;
(k) Protected Species Plan. The Plan shall be informed by protected
surveys carried out by a suitably qualified person. The surveys shall
inform the mitigation measures required to ensure the protection of the

Page 10

protected species during construction of the Development. The Plan
shall provide mitigation measures, as required, and a timetable for
implementation.
(l) Details of the construction of the access into the site, including
associated drainage and the creation and maintenance of associated
visibility splays;
(m) Site-specific Construction Method Statements for the following:
i. Watercourse crossings including full details and plans of the
design and specification of all new and upgraded watercourse
crossings to be constructed, ensuring continuous flow and fish
passage with no hanging culverts, noting all crossings shall
comprise open culverts or bridges designed to take the 1 in 200
plus climate change flood flows;
ii. All permanent roads/tracks to be altered/formed and retained for
the operation of the development; including their width, likelihood
of widening or passing places, means of drainage (which shall
have regard to SUDS principles), means of construction, and
edge reinstatement including verge width. The specification shall
be accompanied by relevant plans at a sufficient scale;
(n) Details of post-construction restoration/reinstatement of the working
areas not required during the operation of the Development;
(o) Historic Environment Protection Plan including details of protective
fencing of the location of the historic environment features to be
protected during construction works, including appropriate buffers;
(p) A wetland ecosystems survey and mitigation plan;
(q) A tree felling and management plan to include measures for the
protection of retained trees and woodland;
(r) A Construction Noise Management Plan including details of the
management of noise and vibration during construction and post-
construction restoration, including that caused by construction traffic, to
the lowest practicable levels and in accordance with BS 5228:2009
“Code of Practice for noise and vibration control on construction and
open sites – Part 1: Noise and Part 2: Vibration” (or any updated
version/document which superseded this document) and how any
properties likely to be affected by construction noise will be kept
informed;
(s) A phasing plan for the construction works and
(t) A written scheme which details the methodology for dealing with any
revisions to any of the documents required under this part (3). Any
revised documents will require to be submitted to and approved in
writing by the Planning Authority prior to the revisions being
implemented on site.
(3) The Development shall be implemented in accordance with the CEMP
approved under part (1) unless otherwise approved in advance in writing by
the Planning Authority.

Page 11

Reason: To ensure that all construction operations are carried out in a manner
that minimises their impact on road safety, amenity and the environment, and
that the mitigation measures contained in the EIA Report accompanying the
application, or as otherwise agreed, are fully implemented.
5. Traffic Management Plan
(1) There shall be no Commencement of Development until a Traffic
Management Plan has been submitted to and approved in writing by the
relevant Planning Authority in consultation with the Roads Authority. The
Traffic Management Plan shall provide:
(a) The routeing of all traffic associated with the development including
phasing and timescales;
(b) Measures to ensure that the specified routes are adhered to, including
monitoring procedures;
(c) Details of all, signage and lining arrangements to be put in place;
(d) Provisions for emergency vehicle access;
(e) Identification of a nominated person to whom any road safety issues
can be referred;
(f) A plan for access by vehicles carrying abnormal loads and any off-site
works, including new or extended passing places, required to facilitate
such vehicle movements. Prior to the movement of any abnormal load,
any measures required on the trunk road network to accommodate the
size or length of the loads being transported, including the removal of
street furniture, junction widening and traffic management must be
approved and implemented to the satisfaction of the Planning
Authority, in consultation with Transport Scotland. Any additional
signing or temporary traffic control measures deemed necessary on
the trunk road network must be undertaken by a recognised QA traffic
management consultant, to be approved by Transport Scotland.
(g) Provision for the submission and agreement of a roads condition
survey pre-and post-construction accompanied by an appropriate
agreement between the relevant Planning Authority and the Company
to ensure the delivery of any post-construction public road restoration
that may be required
(2) The approved Traffic Management Plan shall thereafter be implemented in
full unless otherwise agreed in advance in writing with the relevant Planning
Authority.
Reason: In the interests of road safety and to ensure that abnormal loads access
the site in a safe manner.
6. Temporary Site Access
(1) There shall be no vehicle site access permitted to the sites area until details
of alterations to the verge of the affected public road has been submitted to

Page 12

and approved in writing by the relevant Planning Authority, in consultation
with the Roads Authority. The details shall include but not be limited to the
following information:
(a) A suitably scaled plan showing the location, layout and formation
details for the site access(es);
(b) Details regarding timescales for the opening up and closure of any
temporary access together with the time period over which the
temporary access will be used;
(c) A detailed specification of the materials, including layer depths to be
used in the construction of the site accesses;
(d) Proposed signing and traffic management measures; and
(e) Details including materials for the reinstatement of temporary
construction site access.
(2) Thereafter the development shall be undertaken in accordance with the
approved details.
Reason: To ensure an acceptable form of development in terms of the
arrangements to manage traffic during construction works at the site(s), in the
interest of maintaining a safe and serviceable road network and preserve
amenity.
7. Ecological Clerk of Works
(1) There shall be no Commencement of Development until the terms of
appointment of a suitably qualified, experienced, and independent
Ecological Clerk of Works (“ECoW”) by the Company have been submitted
to, and approved in writing by, the relevant Planning Authority. The terms of
appointment shall:
(a) Impose a duty to monitor compliance with the ecological and
hydrological commitments provided in the EIA Report and other
information lodged in support of the application, and the approved
CEMP (“the ECoW works”);
(b) Require the ECoW to report to the Company’s nominated construction
project manager any incidences of non-compliance with the ECoW
works at the earliest practical opportunity;
(c) Require the ECoW to submit a monthly report to the relevant Planning
Authority summarising works undertaken on site; and
(d) Require the ECoW to report to the relevant Planning Authority any
incidences of non- compliance with the ECoW Works at the earliest
practical opportunity.
(2) The ECoW shall be appointed on the approved terms throughout the period
from Commencement of Development, throughout any period of
construction activity and during any period of post construction restoration
works.

Page 13

Reason: To secure effective monitoring of and compliance with the
environmental mitigation and management measures associated with the
Development.
8. Archaeology
(1) There shall be no Commencement of Development unless an
archaeological Written Scheme of Investigation (WSI) has been submitted
to, and approved in writing by, the relevant Planning Authority.
(2) The WSI shall provide details of how the recording and recovery of
archaeological resources found within the application site shall be
undertaken, and how any updates, if required, to the Written Scheme of
Investigation will be provided throughout the implementation of the
programme of archaeological works. The WSI shall also detail how any
requirement for reporting, post-excavation analysis, archive deposition,
publication of results, and the delivery of public benefit (including how this
will be recorded and reported) will be undertaken.
(3) A programme of archaeological works must be carried out in accordance
with the approved WSI, and any addendums to it, as agreed under part (1).
(4) Should the archaeological works carried out under part (3) reveal the need
for post excavation analysis, the development hereby approved shall not be
brought into use unless a post-excavation research design (PERD) for the
analysis, publication and dissemination of results, including additional public
engagement, and archive deposition has been submitted to and approved in
writing by the relevant Planning Authority. The PERD shall be carried out in
complete accordance with the approved details.
Reason: To ensure the protection or recording of archaeological features on the
site.
9. Access Management Plan
(1) There shall be no commencement of Development unless an Access
Management Plan (AMP) has been submitted to and approved in writing by
the relevant Planning Authority. For the avoidance of doubt the AMP shall
include but not be limited to:
(a) Details of all core paths and public rights of way that are crossed by
the route;
(b) Details of any other paths or tracks crossed by the route that are likely
to be used for recreational access;
(c) Details of any proposed path closures or diversions, including the
proposed duration of the closure/diversion and any signage;

Page 14

(d) Measures for monitoring the impacts of any works or vehicle
movements on the condition of the identified paths; and
(e) Proposals for re-instatement of any damage to the identified paths.
(2) Thereafter the development shall be undertaken in accordance with the
details in the approved AMP.
Reason: In order that the relevant Planning Authority may verify the acceptability
of the specified details in the interests of safeguarding public access.
10. Construction Compound Details
(1) There shall be no construction compounds formed within the Planning
Authority areas until the following details have been submitted to and
approved in writing by the relevant Planning Authority:
(a) A compound phasing plan;
(b) The precise location and extent of the compound;
(c) Details of screening to mitigate impact of activities within the
compound on the amenity of the surrounding area and occupants of
nearby property; and
(d) Details of artificial lighting and measures and controls to mitigate
impact of light pollution on the amenity of the surrounding area and
occupants of nearby property.
(2) Thereafter the compounds shall be formed and operated in accordance with
the approved details and each compound shall be restored to its pre-
construction condition no later than 2-months following the expiry of the
demobilisation date for that compound as detailed in the compound phasing
plan.
Reason: In order that the relevant Planning Authority may verify the acceptability
of the specified details in the interests of amenity and to ensure restoration of the
compound sites.
11. Access Tracks
(1) No access tracks shall be formed or upgraded in the planning authority
areas until the precise location and extent of all works to form new sections
of tracks or upgrade access tracks have been submitted to and approved in
writing by the relevant Planning Authority. Thereafter the development shall
be undertaken in accordance with the approved details.
Reason: In order that the relevant Planning Authority may verify the acceptability
of all works relating to access tracks.

Page 15

12. Bird Protection Plan
(1) There shall be no Commencement of Development until a Bird Protection
Plan has been submitted to and approved in writing by the relevant Planning
Authority in consultation with NatureScot. The Bird Protection Plan shall be
informed by pre-commencement bird surveys and set out measures to
protect any relevant bird species including post construction ornithology
surveys at intervals to be agreed with the relevant Planning Authority.
(2) Thereafter, the approved Bird Protection Plan shall be implemented in full
within the timescales set out in the approved Bird Protection Plan.
Reason: In the interests of protecting ornithological interests through the
construction, operational and decommissioning of the wind farm.
13. Private Water Supplies
(1) At least 14 months prior to commencement of development detailed plans of
the finalised development and all associated infrastructure shall be overlain
with the relevant buffer zones for the Private Water Supply (“PWS”) sources
to Ferryfield House (PWS-TW-1) and Muircroft (PWS-TW-2) and submitted
to the relevant Planning Authority. If any PWS is found to have a
groundwater source and the source lies within the buffers set out in SEPA
Guidance on Assessing Impacts of Developments on Groundwater
Abstractions dated August 2024 that serves a property that will continue to
require a PWS through the construction and post-construction periods,
these plans must be accompanied by a detailed PWS risk assessment in
line with SEPA Guidance on Assessing Impacts of Developments on
Groundwater Abstractions and a PWS monitoring plan and/or mitigation
plan in line with SEPA guidance detailed in Appendix B of SEPA Guidance
on Assessing Impacts of Developments on Groundwater Abstractions for
approval in writing by the relevant Planning Authority, in consultation with
SEPA.
(2) The finalised site-specific monitoring plans and contingency plans should be
submitted to the satisfaction of the relevant Planning Authority, and
thereafter all works carried out in accordance with the approved plans.
Monitoring results should be reported to the relevant Planning Authority and
the owner/operator of the existing abstractions. Contingency plans should
include timescales for notification of relevant stakeholders if adverse
impacts are identified and for subsequent design and implementation of
remedial actions.
Reason: In the interests of protecting the Residential Amenity of existing
properties, the health of residents and continued access to safe and sufficient
water supplies.

Page 16

14. Alternative Private Water Supply Source
(1) There shall be no commencement of Development until documentary
evidence has been provided to and agreed by the relevant Planning
Authority, which demonstrates that suitable and fully operational
replacement water supplies of sufficient quantity and quality are operational,
should any detailed PWS risk assessment identify this as the most suitable
mitigation measure. In each case, the replacement supply shall either be
from the public mains or derived from a suitable source shown to be at low
or negligible risk of contamination or disruption, and which does not
prejudice the quantity or quality of water delivered by other existing private
water supplies. Information detailing the suitability of the source; risk of
contamination and disruption; impact upon existing supplies; and details of
how the supplies will be managed and maintained in perpetuity, must be
submitted to and agreed with the relevant Planning Authority in advance of
any other works being carried out in associate with this permission.
Reason: In order to provide alternative water source in event of long term
negative impact on PWS.
15. Flood Extent
(1) There shall be no land raising, storage of temporary materials or siting of
mobile welfare units are stored/located within the SEPAs Future Flood
Extent.
(2) Should land raising be required for the upgrading of existing roads or
construction of new temporary access roads within the SEPA flood extent,
compensatory storage of equal volume will be required unless detailed flood
risk information is submitted to demonstrate the land raising will not occur
within the associated flood extent. At least one month prior to the
commencement of any such land raising works, plans should be submitted
to the relevant Planning Authority for approval showing the extent of works
and clearly identify where compensatory flood storage will be provided.
Reason: In the interest of flood protection.
16. Micro-siting and Limits of Deviation
(1) All towers, areas of hardstanding and tracks shall be constructed in the
location shown in EIAR Volume 3 – Figure 3.1 – Overview of the Proposed
Development.  Towers, areas of hardstanding and tracks may be adjusted
by micro-siting within limits of deviation specified in this condition. However,
unless otherwise approved in advance in writing by the relevant Planning
Authority, micro-siting and limits of deviation are subject to the following
restrictions:

Page 17

(a) Existing towers 155 and 156 scheduled for possible works shall not be
increased by more than 2 m above their existing height, when
measured in metres Above Ordinance Datum (Newlyn);
(b) Existing Tower foundations shall not be moved more than 20 m and
contained within the LOD shown on EIAR Volume 3 – Figure 3.1 –
Overview of the Proposed Development;
(c) Replacement Tower 129 or 132 and associated diversion tower shall
not be moved more than 100 m and contained within the LOD as
shown within EIAR Volume 3 – Figure 3.1 – Overview of the Proposed
Development;
(d) No existing road/access track shall be moved more than 20 m either
side from its current position and contained within the LOD shown on
EIAR Volume 3 – Figure 3.1 – Overview of the Proposed
Development;
(e) New temporary stone road and trackway panels shall not be moved
more than 100 m either side and contained with the LOD shown within
EIAR Volume 3 – Figure 3.1 – Overview of the Proposed
Development;
(f) No micro-siting shall take place within the 20 m limit of deviation which
further encroaches into the potentially moderate GWDTE identified
within EIAR Volume 3 - Figure 8.1f – Ground Water Dependant
Terrestrial Ecosystems; and
(g) All micro-siting permissible under this condition must be approved in
advance in writing by the Environmental Clerk of Works (ECoW).
(2) No later than one month after the Date of Final Energisation, the Company
must submit a finalised Site Layout to the relevant Planning Authorities,
copied to the Scottish Ministers, showing the final position of the overhead
electricity transmission line, all towers, access tracks, and associated
infrastructure forming part of the Development. The plan must also specify
areas where micro-siting has taken place and, for each instance, be
accompanied by copies of the approval from the ECoW or Planning
Authorities, as applicable.
Reason: To control environmental impacts whilst taking account of local ground
conditions.
17. Construction Hours
(1) Construction work which is audible from any noise-sensitive receptor shall
only take place between the hours of 07.00 to 19.00 on Mondays to Fridays
inclusive and 07.00 to 16.00 on Saturdays, with no construction work taking
place on Sundays or on local public holidays. Outwith these specified hours,
only maintenance works, emergency works, and limited construction works
on the site as specified; concrete pours, dust suppression, and the testing of
plant and equipment are permissible (unless otherwise approved in advance
in writing by the relevant Planning Authority).

Page 18

(2) HGV movements to and from the site (excluding abnormal loads) during
construction of the development shall be limited to 07.00 to 19.00 Mondays
to Fridays, and 07.00 to 16.00 on Saturdays, with no HGV movements to or
from site taking place on Sundays or on local public holidays (unless
otherwise approved in advance in writing by the relevant Planning
Authority). 
Reason: In the interests of local amenity.
Definitions 
In this consent and deemed planning permission:
“Approved Plans” means the plans included in the Environmental Impact
Assessment Report submitted with the application, Figure 1.1 Location Plan
reproduced in Annex 3.
“the Application” means the application submitted by the Company on 18
November 2024.
“Commencement of Development” means the date on which Development shall
be taken as begun in accordance with section 27 of the Town and Country
Planning (Scotland) Act 1997 (as amended). For the avoidance of doubt ground
investigation and site investigation works and its associated tree felling does not
constitute Commencement of the Development for the purposes of this consent.
“the Company” means Scottish Hydro Electric Transmission PLC, Inveralmond
House, 200 Dunkeld Road, Perth PH1 3AQ, or such other person who from time
to time may lawfully have the benefit of this consent.
“the Development” means the development as described in Annex 1 authorised
by this section 37 consent and deemed planning permission.
“HES” means Historic Environment Scotland.
“Planning Authority Area” –means the boundaries of Angus Council, Fife Council
and Perth and Kinross Council, which the proposed development crosses.
“SEPA” means Scottish Environmental Protection Agency.
“NatureScot” means Scottish Natural Heritage now operating as NatureScot.
“the Planning Authorities” means Angus Council, Fife Council and Perth and
Kinross Council within whose boundary the Development is situated.
“the proposed Development” means the development described in Annex 1
authorised by this section 37 consent and deemed planning permission.

Page 19

Conclusion and Reasons for Recommendation
To conclude, the proposal is considered to comply with NPF4, and the adopted
Local Development Plan 2 (2019). Accordingly, following assessment of the
documentation submitted in relation to the proposal and the content of the
proposed conditions, it is recommended that PKC does not object to the
proposal.
Recommendation 
Do not object subject to the above conditions.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Background Papers
Letters of representation N/A
Authors
Name Designation Contact Details
Alex Gudgeon Planning Officer (Major
applications)
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
19 May 2025