Ambition | Compassion | Integrity
Our vision is for
a Perth and Kinross where everyone can live life
well, free from poverty and inequality
Council Building
2 High Street
Perth
PH1 5PH
05/05/2025
A hybrid meeting of the Planning and Placemaking Committee will be held in the
Council Chambers (Hybrid) on Wednesday, 14 May 2025 at 09:30.
If you have any queries please contact Democratic Services on (01738) 475000 or
email Committee@pkc.gov.uk.
THOMAS GLEN
Chief Executive
Those attending the meeting are requested to ensure that all notifications are silent
on their device and other devices are in silent mode.
Please note that the meeting will be broadcast online and recorded.  The recording
will be publicly available on the Council’s website following the meeting.
Members:
Councillor Ian Massie  (Convener)
Councillor Grant Stewart  (Vice-Convener)
Councillor Keith Allan
Councillor Bob Brawn
Councillor Dave Cuthbert
Councillor Ken Harvey
Councillor David Illingworth
Councillor Ian James
Bailie Claire McLaren
Councillor Richard Watters
Bailie Mike Williamson
Page 1 of 160

Page 2

Page 2 of 160

Page 3

Planning and Placemaking Committee
Wednesday, 14 May 2025
Agenda
Members are reminded of their obligation to declare any financial or non-
financial interest which they may have in any item on this agenda in
accordance with the councillors’ code of conduct.
1 WELCOME AND APOLOGIES/SUBSTITUTES
2 DECLARATIONS OF INTEREST
3 MINUTE OF MEETING OF THE PLANNING AND
PLACEMAKING COMMITTEE OF 16 APRIL 2025 FOR
APPROVAL
(copy herewith)
5 - 28
4 DEPUTATIONS
5 APPLICATIONS FOR DETERMINATION
5(1) MAJOR APPLICATIONS
5(1)(i) 24/01386/FLM - FORMATION OF A 49.9MW BATTERY
ENERGY STORAGE FACILITY COMPRISING BATTERY
STORAGE UNITS, ANCILLARY BUILDINGS AND
EQUIPMENT, ACCESS ROAD AND ASSOCIATED WORKS,
LAND 200 METRES NORTH OF PITCURRAN HOUSE,
NEWBURGH ROAD, ABERNETHY, PERTH, PH2 9LG
Report of Handling by the Development Management and
Building Standard Service Manager (copy herewith 25/117)
29 - 58
5(1)(ii) 24/01483/AMM - ERECTION OF 42 DWELLINGHOUSES AND
ASSOCIATED WORKS - PHASE 2 (CHANGE OF HOUSE
TYPE AND PLOT LAYOUT OF 22./02223/AMM), SCONE
NORTH, SCONE, PERTH
Report of Handling by Development Management and Building
Standards Service Manager (copy herewith 25/118)
59 - 80
5(1)(iii) 24/01961/AMM - ERECTION OF 43 DWELLINGHOUSES,
LANDSCAPING AND ASSOCIATED INFRASTRUCTURE
81 - 110
Page 3 of 160

Page 4

(APPROVAL OF MATTERS SPECIFIED IN CONDITIONS OF
02/01482/IP), LAND TO THE NORTH OF A912 AT
OUDENARDE, BRIDGE OF EARN, PERTH
Report of Handling by Development Management and Building
Standards Service Manager (copy herewith 25/119)
5(1)(iv) 24/01757/AMM - ERECTION OF 38 DWELLINGHOUSES AND
4 FLATS AND ASSOCIATED WORKS (APPROVAL OF
MATTERS SPECIFIED IN CONDITIONS OF 16/01809/IPM
PHASE 2A), LAND 40 METRES NORTH OF 51 CASTLE
DRIVE, AUCHTERARDER, PH2 1FU
Report of Handling by Development Management and Building
Standards Service Manager (copy herewith 25/120)
111 - 130
5(2) LOCAL APPLICATIONS
5(2)(i) 24/01758/FLL - ERECTION OF 6 DWELLINGHOUSES,
LANDSCAPING AND ASSOCIATED INFRASTRUCTURE
(PHASE 2A), LAND 90 METRES NORTH WEST OF
CASTLEMAINS FARM STEADING, AUCHTERARDER, PH3
1DX
Report of Handling by Development Management and Building
Standards Service Manager (copy herewith 25/121)
131 - 150
6 PROPOSAL OF APPLICATION NOTICES (POAN)
6(i) 25/00006/PAN - REDEVELOPMENT WORKS COMPRISING
ALTERATIONS TO GRASS FOOTBALL PITCHES TO FORM 2
SYNTHETIC FOOTBALL PITCHES, EXTENSION TO
BUILDING, ERECTION OF SPECTATOR STAND AND
ASSOCIATED WORKS, JEANFIELD SWIFTS STADIUM, BUTE
DRIVE, PERTH, PH1 3BG
Pre-Application Report by Development Management and
Building Standards Service Manager (copy herewith 25/122)
151 - 160
Page 4 of 160

Page 5

DRAFT
PLANNING AND PLACEMAKING COMMITTEE
Minute of hybrid meeting of the Planning and Placemaking Committee held in the
Council Chambers, 2 High Street, Perth, on Wednesday 16 April 2025 at 9.30am.
Present: Councillors I Massie, G Stewart, K Allan, B Brawn, K Harvey, I James,
D Illingworth, Bailie C McLaren, R Watters and Bailie M Williamson.
In Attendance: L MacLean, L Reid, K Smith, and P Williamson (all Economy,
Development and Planning); A Brown, C Elliott, M Pasternak and R Ramsay (all
Legal and Governance).
Apologies: Councillor D Cuthbert.
Councillor I Massie, Convener, Presiding.
1. Welcome and Apologies
The Convener welcomed everyone present to the meeting and noted
apologies as above. 
2. Declarations of Interest
The were no Declarations of Interest made in terms of the Councillors Code of
Conduct.
3. Minutes
The minute of meeting of the Planning and Placemaking Committee of
12 March 2025 was submitted and approved as a correct record.
4. Deputations
In terms of Standing Order 13, the Committee agreed to hear deputations in
relation to the following planning applications:
Planning Application No. Item No.
24/01128/FLL 5(2)(i)
24/01539/FLL 5(2)(ii)
24/01642/FLL 5(2)(iii)
5. Applications For Determination
(1) Major Application
(i) 24/01894/FLM - S42 Application to vary conditions 1 (in
accordance with plans), 10 (water) and 12 (archaeology) of
permission 22/00746/FLM, land 60 metres north of
Abernethy Cemetery, Newburgh Road, Abernethy (Report
No. 25/79)
3
Page 5 of 160

Page 6

DRAFT
Resolved:
Grant, subject to the following terms, conditions (including
amended Condition 1) and informatives:
Conditions
General
1. The development hereby approved must be carried out in
accordance with the drawing and documents set out in
this decision notice, unless otherwise provided for by
other conditions imposed by this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
Noise
2. All hereby approved plant or equipment shall be so
enclosed, attenuated and/or maintained such that any
noise therefrom shall not exceed Noise Rating 35
between 0700 and 2300 hours daily, or Noise Rating 20
between 2300 and 0700 hours daily, within any
neighbouring residential property, with all windows
slightly open, when measured and/ or calculated and
plotted on a rating curve chart.
Reason - In the interests of residential amenity; to ensure
a satisfactory standard of local environmental quality.
3. In the event of a justified noise complaint being received
by the Council the operator shall, at its own expense,
employ a consultant approved by the Planning Authority
to carry out a noise assessment to verify compliance with
Condition 2.  The assessment will be carried out to an
appropriate methodology agreed in writing with the
Planning Authority.  If the noise assessment shows that
the noise levels do not comply with Condition 2 a scheme
of noise mitigation shall be included with the noise
assessment, specifying timescales for the implementation
of the scheme and shall be submitted to the Planning
Authority within 28 days of the assessment.  The
mitigation scheme shall thereafter be implemented in
accordance with the approved scheme and timescales.
Reason - In the interests of residential amenity; to ensure
a satisfactory standard of local environmental quality.
Lighting
4. All external lighting shall be sufficiently screened and
aligned so as to ensure that there is no direct illumination
of residential property and that light spillage beyond the
boundaries of the site is minimised. In association, the
operation of the lighting shall be controlled so as to only
be triggered by motion within the security fenced
boundaries of the site.
Reason - In the interests of residential amenity; to ensure
a satisfactory standard of local environmental quality.
Page 6 of 160

Page 7

DRAFT
Roads and Transportation.
5. Prior to the commencement of works associated to the
hereby approved development, a Construction Traffic
Management Scheme (TMS) shall be submitted for the
written approval of the Planning Authority, such TMS
shall include details of the following:
(a) restriction of construction traffic to approved routes
and the measures to be put in place to avoid other
routes being used;
(b) timing of construction traffic to minimise impact on
local communities particularly at school start and
finishing times, on days when refuse collection is
undertaken, on Sundays and during local events;
(c) a code of conduct for HGV drivers to allow for
queuing traffic to pass;
(d) arrangements for liaison with the Roads Authority
regarding winter maintenance;
(e) emergency arrangements detailing communication
and contingency arrangements in the event of
vehicle breakdown;
(f) arrangements for the cleaning of wheels and chassis
of vehicles to prevent material from construction
sites associated with the development being
deposited on the road;
(g) arrangements for cleaning of roads affected by
material deposited from construction sites
associated with the development;
(h) arrangements for signage at site accesses and
crossovers and on roads to be used by construction
traffic in order to provide safe access for pedestrians,
cyclists and equestrians;
(i) details of information signs to inform other road
users of construction traffic;
(j) arrangements to ensure that access for emergency
service vehicles are not impeded;
(k) co-ordination with other significant developments
known to use roads affected by construction traffic;
(l) traffic arrangements in the immediate vicinity of
temporary construction compounds;
(m) the provision and installation of traffic counters at the
applicant's expense at locations to be agreed prior to
the commencement of construction;
(n) monitoring, reporting and implementation
arrangements;
(o) arrangements for dealing with non-compliance; and
(p) details of HGV movements to and from the site.
The TMS, as approved, shall be strictly adhered to during
the entire site construction programme all to the
satisfaction of the Council as Planning Authority.
Reason - In the interests of road safety.
Page 7 of 160

Page 8

DRAFT
6. Prior to the commencement of works associated to the
hereby approved development, the details of any
abnormal load movements required, including any
accommodation measures necessary, shall be submitted
to and agreed in writing by the Planning Authority, in
consultation with Transport Scotland and the Councils
Transport Planning team.  Any request for approval shall
be submitted at least two months prior to the proposed
load movement.
Reason - To ensure that the transportation of abnormal
loads will not have any detrimental effect on the local or
trunk road network.
7. Prior to the commencement of works associated to the
hereby approved development, any additional signing or
temporary traffic control measures deemed necessary
due to the size or length of loads being delivered to the
development hereby approved must be undertaken by a
recognised Quality Assured Traffic Management
Consultant.  The details of any temporary traffic control
measures shall be submitted to and agreed in writing by
the Planning Authority, in consultation with Transport
Scotland and the Councils Transport Planning team.  Any
request for such approval shall be submitted at least two
months prior to the proposed temporary control measures
being implemented.
Reason - To ensure that the transportation of abnormal
loads will not have any detrimental effect on the trunk
road network.
External Finishing Colour
8. Prior to the commencement of works associated to the
hereby approved development, details of the recessive
colour of the proposed external finishing materials to be
used for the hereby approved development components
(i.e., battery storage containers, transformers, DNO
Switchgear, perimeter fencing etc.) shall be submitted to
and agreed in writing by the Council as Planning
Authority.  The scheme as agreed shall be implemented
prior to the completion or bringing into use of the
development, whichever is the earlier.
Reason - In the interests of visual amenity; to ensure a
satisfactory standard of local environmental quality.
Biodiversity
9. Prior to the commencement of works associated to the
hereby approved development, a detailed landscaping
and planting scheme for the site shall be submitted to and
approved in writing by the Planning Authority.  The
scheme shall include details of the height and slopes of
any mounding or recontouring of the site, full details of all
hard landscaping proposals including materials and
installation methods and, species, height, size and
density of trees and shrubs to be planted.  The scheme
Page 8 of 160

Page 9

DRAFT
as subsequently approved shall be carried out and
completed within the first available planting season
(October to March) after the completion or bringing into
use of the development, whichever is the earlier, and the
date of Practical Completion of the landscaping scheme
shall be supplied in writing to the Council as Planning
Authority within 7 days of that date.  The scheme as
agreed and implemented shall thereafter be maintained
to the satisfaction of the Council as Planning Authority.
Reason - In the interests of visual amenity and to ensure
the satisfactory implementation of the proposed planting
scheme.
Soil Management
10. All soils excavated in the course of the development
hereby approved shall be retained onsite and repurposed
unless otherwise approved in writing by the Council as
Planning Authority. Prior to the development hereby
approved commencing, a Soil Management Statement
shall be submitted to the Planning Authority for approval
in writing.  This Statement shall set out the extent of any
excavation works to be undertaken and how soils shall be
reused and or managed onsite.  All excavation and
repurposing of soil shall then proceed in accordance with
the agreed statement.
Reason - In the interests of appropriately managing prime
quality soils and minimising the long-term impacts of
developing the site in accordance with Policy 51 of the
LDP2.
Facility Lifespan
11. In the event the hereby approved development fails to
store electricity on a commercial basis for a continuous
period of 12 months, and or at the end of life for the
development (50 years from the commencement of
electricity storage) it shall be deemed to have
permanently ceased to be required. In either event the
development shall be decommissioned, and the relevant
parts of the site reinstated within such timescale as
agreed in writing by the Council as Planning Authority.
Reason - To ensure the facility is removed from the site
at the end of its operational life, and to protect the
character of the countryside, the visual amenity of the
area and nature conservation interests.
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan.
Informatives
1. This planning permission will last only for three years
from the date of this decision notice, unless the
Page 9 of 160

Page 10

DRAFT
development has been started within that period (see
Section 58(1) of the Town and Country Planning
(Scotland) Act 1997 (as amended).
2. Under Section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.  A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement action
being taken.
3. As soon as practicable after the development is
complete, the person who completes the development is
obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.
4. An application for Building Warrant may be required.
5. The applicant is advised to refer to Perth & Kinross
Council’s Supplementary guidance on Flood Risk and
Flood Risk Assessments 2021 as it contains advice
relevant to your development.
6. The applicant is reminded that, under the Wildlife and
Countryside Act 1981, as amended, it is an offence to
remove, damage or destroy the nest of any wild birds
while that nest is in use or being built.  Planning consent
for a development does not provide a defence against
prosecution under this act.
7. The applicant is reminded that, should any protected
species be present a license may be required from
Scottish Natural Heritage to disturb a protected species. 
Failure to obtain a license may constitute a criminal act
under the Habitats Regulations and penalties are severe
for non-compliance.
8. This development will require the 'Display of notice while
development is carried out', under Section 27C (1) of the
Town and Country Planning Act 1997, as amended, and
Regulation 41 of the Development Management
Procedure (Scotland) Regulations 2013.  The form of the
notice is set out in Schedule 7 of the Regulations and a
draft notice is included for your guidance. According to
Regulation 41 the notice must be:
 Displayed in a prominent place at or in the vicinity of
the site of the development.
 Readily visible to the public.
 Printed on durable material.
9. This planning permission is granted subject to conditions,
some of which require further information to be submitted
to Development Management either before works can
start on site or at a certain time.  The required information
must be submitted via the ePlanning portal if your original
Page 10 of 160

Page 11

DRAFT
application was lodged that way, otherwise send it to us
at developmentmanagement@pkc.gov.uk.  Please be
aware that a fee is payable in respect of each request
made, though there is no limit to the number of conditions
that can be discharged in a single request. The Fees
Charter is available on our website www.pkc.gov.uk.  The
Council has two months to consider the information.  You
should therefore submit the required information more
than two months before your permission expires.  We
cannot guarantee that submissions made within two
months of the expiry date of your permission will be able
to be dealt with before your permission lapses.
10. The developer is advised to contact Perth & Kinross
Heritage Trust should any unrecorded archaeology be
found during construction works.
11. The applicant should ensure that any existing wayleaves
for maintenance or repair to existing private water supply
or septic drainage infrastructure in the development area
are honoured throughout and after completion of the
development.
12. The applicant shall ensure the private water supply for
the development complies with the Water Scotland Act
1980 (Section 63), The Private Water Supplies (Scotland)
Regulations 2006 and The Water Intended for Human
Consumption (Private Supplies) (Scotland) Regulations
2017.  Detailed information regarding the private water
supply, including the nature, location and adequacy of the
source, any storage tanks/ pipework and the filtration and
disinfection treatment proposed to ensure provision of an
adequate and consistently wholesome water supply shall
be submitted to Perth and Kinross Council Environmental
Health in line with the above Act and Regulations.
13. The applicant is advised that, in terms of Sections 56 of
the Roads (Scotland) Act 1984, he/she/they must obtain
from the Council, as Roads Authority, consent to open an
existing road or footway prior to the commencement of
works.  Information on junction types, requirements for
Vehicular Access consents (VA1) and application forms
are available at www.pkc.gov.uk/vehicleaccess.  Advice
on the disposal of surface water should be sought at the
initial stages of design from Scottish Water and the
Scottish Environment Protection Agency.
(2) Local Applications
(i) 24/01128/FLL - Change of use from workshop (Class 6) to
gym/fitness studio (Class 11), The Workshop, Montrose
Road, Auchterarder, PH3 1BZ (Report No. 25/80)
Ms A Connelly, objector, addressed the committee via
telephone, and answered Members questions.
Page 11 of 160

Page 12

DRAFT
Resolved:
Grant, subject to the following terms, conditions (including
amended Conditions 3 and 10) and informatives:
Conditions
1. This planning permission will last only for three years
from the date of this decision notice, unless the
development has been started within that period.
Reason - This is a Planning Permission in terms of
Section 58 of the Town and Country Planning (Scotland)
Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019.
2. The development hereby approved must be carried out in
accordance with the approved drawings and documents,
unless otherwise provided for by conditions imposed by
this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
3. The hours of operation shall be restricted to between
06:30 to 21:00hrs Monday to Friday; 08:00 to 18:00hrs
on Saturday, and 09:00 to 18:00hrs Sunday.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
4. All plant or equipment shall be so enclosed, attenuated
and/or maintained such that any noise therefrom shall not
exceed Noise Rating 35 between 0700 and 2300 hours
daily, or Noise Rating 25 between 2300 and 0700 hours
daily, within any neighbouring residential property, with
all windows slightly open, when measured and/ or
calculated and plotted on a rating curve.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
5. The mitigation measures within Section 5 of the approved
Noise Impact Assessment shall be implemented to the
appropriate level that is recommended, to ensure that the
minimum sound insulation requirements for Building
Regulations are achieved specifically (Sections 5.8 to
5.33) and (Section 5.51 to 5.53).  These measures shall
be implemented prior to the commencement of use, and
maintained to the appropriate standard in perpetuity.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
6. No music amplified, background or otherwise is allowed
within the premises unless all the relevant and
appropriate mitigation measures within in Section 5
specifically (5.34 to 5.50) and (5.51 to 5.53) of the Noise
Impact Assessment (NIA), ‘The Workshop’, Montrose
Road, Auchterarder, Technical Report R-10169-DR-CL
dated 27 January 2025 undertaken by RMP, are
implemented, once implemented a further sound
propagation test must be carried out by a suitably
Page 12 of 160

Page 13

DRAFT
qualified noise consultant, to establish agreed sound
limiter level for amplified music, as recommended in
Sections 5.5 to 5.7 of the NIA.  The scope and timescale
submitted to and agreed in writing with the Council as
Planning Authority in consultation with Environmental
Health.  Thereafter any agreed mitigation measures shall
be implemented to ameliorate the nuisance.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
7. Prior to the commencement of use a Noise Management
Plan, shall be submitted to and agreed in writing by the
Council as Planning Authority and Environmental Health.
The plan shall include operational procedures and
mitigation measures to control noise from amplified
music, equipment / weights, and patrons.  This should
include Noise Management policy for patrons using gym
and a complaints procedure.  The details as approved
shall then be implemented in full as part of the operation
of the site.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
8. All windows and doors shall remain closed during the
operational hours of the gym/fitness studio.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
9. No gym activities are to be carried out at any time within
the mezzanine area of the building.
Reason - In order to safeguard the neighbouring
residential amenity in the area.
10. Prior to the use or occupation of the development hereby
approved, all ground floor windows on the south-east
elevation, and all upper floor windows of the building
which overlook adjacent residential property shall be
installed with translucent film and this will remain in place
in perpetuity.
Reason - In order to minimise any overlooking onto
neighbouring properties. 
11. Prior to commencement of any development on site, a
detailed design for the proposed secure covered cycle
parking facility for a minimum of 10 cycles shall be
submitted to and approved in writing by the Planning
Authority in consultation with the Roads Authority.  The
cycle parking, as approved in writing, shall be
implemented in accordance with the approved details to
the satisfaction of the Council as Planning Authority prior
to the development being brought into use.
Reason - In order to encourage active travel
12. No part of the development shall be occupied until a
Green Travel Plan (GTP), aimed to encourage more
sustainable means of travel, has been submitted and
approved in writing by the Council.  The GTP will have
Page 13 of 160

Page 14

DRAFT
particular regard to provision for walking, cycling and
public transport access to and from the site and will
identify the measures to be provided, the system of
management, monitoring, review, reporting and the
duration of the plan.
Reason- To promote sustainable transport options
13. The number of patrons (excluding staff) within the
building shall be limited to 15 at any one time.
Reason - In the interest of manging traffic vehicular
volumes on Montrose Road.
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan.
Informatives
1. Under Section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.  A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement
action being taken.  Please use the form attached
herewith.
2. As soon as practicable after the development is
complete, the person who completes the development is
obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.  Please
use the form attached herewith.
3. The presence of protected species, and the extent to
which they could be affected by the proposed
development, should be established before works
commence.  Should protected species be identified within
the site the developer should ensure that all appropriate
measures required to comply with the relevant legislation
are carried out.
4. Guidance on the detailed design and positioning of the
cycle storage can be sought from Transport Scotland's
Cycling by Design 2021.
5. The applicant is advised that any proposed signage will
require a further application to be submitted for
advertisement consent unless it benefits from express
consent as per the Town and Country Planning (Control
of Advertisements) (Scotland) Regulations 1984.
(The committee took a short recess before re-convening)
Page 14 of 160

Page 15

DRAFT
(ii) 24/01539/FLL - Siting of container unit for use as hot food
takeaway, formation of decking and outdoor seating area,
The Craft Diner, Atholl Street, Dunkeld (Report No. 25/81)
Ms C Claydon, objector; Mr M Stead, supporter; and
Mr O Cevik, applicant, addressed the committee, and answered
Members questions.
Resolved:
Grant, subject to the following terms, conditions (including
amended Condition 12) and informatives (including additional
Informative 5):
Conditions
1. Planning permission is hereby granted for a temporary
period until 30 April 2030.  Prior to this date, all
development shall be removed from the site, and the use
shall cease.  If the use of the site ceases prior to this date
for a continuous period of 6 months, then all development
shall be removed from site within a period of 2 months
from the date of a formal notification by the Council as
Planning Authority, and the site reinstated back to its
natural state.
Reason - This is a temporary planning permission.
2. The development hereby approved must be carried out in
accordance with the approved drawings and documents,
unless otherwise provided for by conditions imposed by
this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
3. Prior to the commencement of the development hereby
approved, precise details of the proposed decking area,
base of the container and other ancillary storage
containers shall be submitted to and approved in writing
by the Council as Planning Authority.  The details must
ensure that a) pressure on the roots is not excessive and
b) suitable drainage to the ground beneath can take
place.  The approved details shall thereafter be
implemented in full.
Reason - In order to safeguard surrounding trees.
4. All plant or equipment shall be so enclosed, attenuated
and/or maintained such that any noise therefrom shall not
exceed Noise Rating 35 between 0700 and 2300 hours
daily, or Noise Rating 25 between 2300 and 0700 hours
daily, within any neighbouring residential property, with
all windows slightly open, when measured and/ or
calculated and plotted on a rating curve chart.
Reason - In order to protect existing residential amenity.
5. Prior to the development hereby approved being
completed or brought into use, an effective ventilation
system commensurate with the nature and scale of
Page 15 of 160

Page 16

DRAFT
cooking to be undertaken shall be installed and operated
such that cooking odours are not exhausted into or
escape into any neighbouring buildings.  Thereafter the
system shall be maintained as per the manufacturers
specifications.
Reason - In order to protect existing residential amenity.
6. All external lighting shall be sufficiently screened and
aligned so as to ensure that there is no direct illumination
of neighbouring land and that light spillage beyond the
boundaries of the site is minimised to a degree that it
does not adversely affect the amenity of the neighbouring
land.  All lighting (internal and external) must be
biodiversity friendly.
Reason - In order to protect existing residential amenity.
7. Prior to the commencement of the development hereby
approved, precise details of the external finish of the
container shall be submitted to and approved in writing
by the Council as Planning Authority.  Thereafter the
container shall be finished in the approved colour, and
the external finish thereafter maintained yearly.
Reason - In order to protect the visual amenity of the
area.
8. No trees shall be removed under the terms of this
planning permission. Prior to the delivery of the
container, all trees on site and those which have Root
Protection Areas which fall within the site shall be
retained and protected. Protection methods shall take
into account the requirements of BS 5837 2012: Trees in
Relation to Design, Demolition and Construction, and
details of the protection measures shall be submitted to
and approved in writing by the Council as Planning
Authority prior to the commencement of the development
hereby approved.  The measures shall thereafter be in
place for the duration of installation phase.
Reason - In order to protect existing trees from
unnecessary damage during the delivery of the container.
9. Prior to the commencement of the development hereby
approved, detailed drawings showing all waste and
recycling facility enclosures or waste and recycling facility
storage areas and associated locations for bin
presentation shall be submitted to and approved in
writing by the Council as Planning Authority.  The details
must include details of the collection provider.  The
approved details shall thereafter be implemented in full
after commencement.
Reason - In order to clarify the terms of this planning
permission.
10. The onsite refuse storage area for these premises shall
be operated and maintained such that detriment is not
caused to the amenity of the area or any neighbouring
premises.
Page 16 of 160

Page 17

DRAFT
Reason - In the interest of proper site management.
11. The two asserted core paths close to the site (DUNK/25
and 70) must not be obstructed during installation or on
completion of the development.  Any damage done to the
route and/or the associated signage during building
works must be made good before the development is
completed or brought into use, whichever is the earlier.
Reason - In order to protect public access rights.
12. Prior to the commencement of the development hereby
approved, an Operational Management Plan shall be
submitted to and approved in writing by the Council as
Planning Authority. The Plan must include opening hours,
details of means of deliveries and timing, a waste
management plan, a procedure for dealing with onsite
anti-social behaviour, a complaints procedure, and a
review procedure. The approved plan shall be
implemented in full at all times.
Reason - In order to protect residential amenity
13. Prior to the installation of the container and associated
development approved by this planning permission, the
existing container and its associated development shall
be removed and the area of that former development
reinstated back to its former condition.
Reason - In the interest of protecting visual amenity, and
to protect the character and appearance of the
Conservation Area,
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan.
Informatives
1. Under Section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.  A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement
action being taken.
2. As soon as practicable after the development is
complete, the person who completes the development is
obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.
3. Records indicate that at least part of the proposed
development site lies within a radon affected area where
the measurement/monitoring of radon gas and the
installation of mitigation measures may be required. 
Page 17 of 160

Page 18

DRAFT
Further information on radon gas and the associated
reports that can be obtained is available at
www.ukradon.org and at
http://shop.bgs.ac.uk/georeports/.
4. This development will require the 'Display of notice while
development is carried out', under Section 27C(1) of the
Town and Country Planning Act 1997, as amended, and
Regulation 41 of the Development Management
Procedure (Scotland) Regulations 2013, as amended. 
The form of the notice is set out in Schedule 7 of the
Regulations and a draft notice is included for your
guidance. In accordance with Regulation 41 the notice
must be:
 Displayed in a prominent place at or in the vicinity of
the site of the development
 Readily visible to the public
 Printed on durable material.
5. The applicant is advised that this type of proposal
requires a Street Trader's Licence under the terms of
Section 39 of the Civic Government (Scotland) Act 1982
and therefore a licence application should be made to
Licensing.  Application forms are available at
https://www.pkc.gov.uk/article/15623/Street-trading-
licence.
(iii) 24/01642/FLL - Change of use, alterations and extension to
steading to form dwellinghouse and associated works, land
35 metres south west of Gourdiehill Farmhouse, Bankfoot,
Perth, PH1 4DL (Report No. 25/82)
Mrs S Walker, objector; Mr S Green, objector; and Mr J Alberdi,
agent on behalf of the applicant, accompanied by Mr A Hodge,
applicant, addressed the committee, and answered members
questions.
Resolved:
Grant, subject to the following terms, conditions and
informatives:
Conditions
1. The development hereby approved must be carried out in
accordance with the approved drawings and documents,
unless otherwise provided for by conditions imposed by
this decision notice.
Reason - To ensure the development is carried out in
accordance with the approved drawings and documents.
2. This planning permission will last only for three years
from the date of this decision notice, unless the
development has been lawfully started within that period.
Reason - This is a Planning Permission in terms of
Section 58 of the Town and Country Planning (Scotland)
Page 18 of 160

Page 19

DRAFT
Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019.
3. No development or extensions, whether or not permitted
by virtue of Schedule 1, Part 1, Class 1A, 1B, 1D, 3A,
3AA, 3D and 3E; of the Town and Country Planning
(General Permitted Development)(Scotland) Order, 1992
or any Order revoking and re-enacting that Order, shall
be erected within the curtilage of the dwellinghouse
hereby approved.
Reason - In the interests of visual amenity and to ensure
the Planning Authority retains control over future
development on the site given its relatively exposed
nature.
4. The conclusions and recommended action points within
the supporting biodiversity survey submitted and hereby
approved (document 23 relates) shall be fully adhered to,
respected and undertaken as part of the construction
phase of development, to the satisfaction of the Council
as Planning Authority.
Reason - In the interests of protecting environmental
quality and of biodiversity.
5. Prior to the commencement of the development hereby
approved, a detailed landscaping and planting scheme
for the site shall be submitted for the further written
agreement of the Council as Planning Authority.  The
scheme shall include details of the height and slopes of
any mounding or recontouring of the site, species, height,
size and density of trees and shrubs to be planted plus
numbers, locations and specifications of bird boxes, bat
boxes and insect boxes.  The scheme as subsequently
approved shall be carried out and completed within the
first available planting season (October to March) after
the completion or bringing into use of the development,
whichever is the earlier, and the date of Practical
Completion of the landscaping scheme shall be supplied
in writing to the Council as Planning Authority within 7
days of that date.  The scheme as agreed and
implemented shall thereafter be maintained to the
satisfaction of the Council as Planning Authority.
Reason - In the interests of visual amenity; to ensure a
satisfactory standard of local environmental quality.
6. An updated bat survey will be required prior to the
commencement of works, if works have not commenced
within 24 months of the date of the bat survey approved
as part of this permission.  The updated survey shall be
submitted to the Council as Planning Authority for written
agreement and works shall not commence until after
such written agreement has been issued by the Council.
Reason - In the interests of protecting environmental
quality and of biodiversity.
Page 19 of 160

Page 20

DRAFT
7. Prior to the completion or occupation of the building(s)
hereby approved, whichever is the earlier, four bird
nesting boxes suitable for swallows shall be provided on
the completed building.  Thereafter, the agreed scheme
shall be maintained in a reasonable condition for the life
of the development, to the satisfaction of the Council as
Planning Authority.
Reason - In the interests of protecting environmental
quality and of biodiversity.
8. Development shall not commence on site until an
evaluation for the potential of the site to be affected by
contamination by a previous use has been undertaken
and, as a minimum, a Preliminary Risk Assessment
(Phase 1 Desk Study) has been submitted for
consideration and accepted by the Council as Planning
Authority. If the preliminary risk assessment identifies the
need for further assessment, an intrusive investigation
shall be undertaken to identify;
I. the nature, extent and type(s) of contamination on
the site
II. measures to treat/remove contamination to ensure
the site is fit for the use proposed
III. measures to deal with contamination during
construction works
IV. condition of the site on completion of
decontamination measures.
Prior to the completion or bringing into use of any part of
the development the measures to decontaminate the site
shall be fully implemented in accordance with the
scheme subsequently agreed by the Council as Planning
Authority.  Verification that the scheme has been fully
implemented must also be submitted to the Council as
Planning Authority.
Reason - In order to deal with any potential
contamination of the site as a result of its former use.
9. Prior to the development hereby approved being
completed or brought into use, the vehicular access shall
be formed in accordance with Perth and Kinross
Council's Road Development Guide Type C, Figure 5.7
access detail, of Type B Road Construction Detail.  The
Type B Road Construction Detail shall continue into the
entrance of the development for a minimum distance of 6
metres from the edge of the public road network.
Reason - In the interests of road safety; to ensure an
acceptable standard of construction within the public road
boundary.
10. The core path (AGVN/120) which forms part of the
access track to the site must not be obstructed during
building works or on completion.  Any damage done to
the core path and associated signage during building
Page 20 of 160

Page 21

DRAFT
works shall be made good before occupation of the
dwellinghouse.
Reason - In the interests of public access along the core
path.
11. Prior to the commencement of the development hereby
approved, details of the location and measures proposed
for the safeguarding and continued operation, or
replacement, of any septic tanks and soakaways, private
water sources, private water supply storage facilities
and/or private water supply pipes serving properties in
the vicinity, sited within and running through the
application site, shall be submitted to and approved in
writing by the Council as Planning Authority.  The
subsequently agreed protective or replacement
measures shall be put in place prior to the
commencement of the development being brought into
use and shall thereafter be so maintained insofar as it
relates to the development hereby approved.
Reason - To ensure the new development has an
adequate and consistently wholesome supply of water
and to maintain water quality and supply in the interests
of residential amenity and ensure the private water
supply or septic drainage systems of neighbours of the
development remain accessible for future maintenance.
12. Development shall not commence until the developer has
secured an archaeological standing building survey, to be
carried out by an independent and suitably qualified
archaeological organisation.  The scope of the
archaeological standing building survey will be set by the
Council as Planning Authority, in consultation with Perth
and Kinross Heritage Trust.  The name of archaeological
organisation retained by the developer shall be given to
the Council as Planning Authority and PKHT in writing
not less than fourteen days before the commencement
date provided in the Notice of Initiation of Development. 
Copies of the resulting survey shall be deposited in the
National Record of the Historic Environment and in the
Perth and Kinross Historic Environment Record upon
completion of the survey.
Reason - To ensure an appropriate archaeological
standing building survey is carried out and the resulting
survey is recorded properly.
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan.
Page 21 of 160

Page 22

DRAFT
Procedural Notes
The planning permission decision notice shall not be issued until
such time as the required Developer Contributions have been
secured or paid in full. 
In the event the applicant does not either make the required
payment within 28 days from the date the agent/applicant is
advised of the need for the contributions, or complete a legal
agreement for delayed payment within a 4 month period from
the date the agent/applicant is advised of the need for the
contributions the application may be refused under delegated
powers without any further discussion with the applicant.
Informatives
1. Under Section 27A of the Town and Country Planning
(Scotland) Act 1997 (as amended) the person
undertaking the development is required to give the
Planning Authority prior written notification of the date on
which it is intended to commence the development.   A
failure to comply with this statutory requirement would
constitute a breach of planning control under Section
123(1) of that Act, which may result in enforcement
action being taken.  Please use the form attached
herewith.
2. As soon as practicable after the development is
complete, the person who completes the development is
obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the
Planning Authority written notice of that position.  Please
use the form attached herewith.
3. No work shall be commenced until an application for
building warrant has been submitted and approved.
4. This planning permission is granted subject to conditions,
some of which require further information to be submitted
to Development Management either before works can
start on site or at a certain time.  The required information
must be submitted via the ePlanning portal if your original
application was lodged that way, otherwise send it to us
at developmentmanagement@pkc.gov.uk.  Please be
aware that a fee is payable in respect of each request
made, though there is no limit to the number of conditions
that can be discharged in a single request.  The Fees
Charter is available on our website www.pkc.gov.uk.  
The Council has two months to consider the information.
You should therefore submit the required information
more than two months before your permission expires. 
We cannot guarantee that submissions made within two
months of the expiry date of your permission will be able
to be dealt with before your permission lapses.
5. The applicant is advised that in terms of Sections 56 of
the Roads (Scotland) Act 1984 he/she/they must obtain
from the Council, as Roads Authority, consent to open an
Page 22 of 160

Page 23

DRAFT
existing road or footway prior to the commencement of
works.  Information on junction types, requirements for
Vehicular Access consents (VA1) and application forms
are available at www.pkc.gov.uk/vehicleaccess.  Advice
on the disposal of surface water should be sought at the
initial stages of design from Scottish Water and the
Scottish Environment Protection Agency.
6. A private wastewater treatment plant and septic tank
should be provided with an access for desludging.  The
desludging tanker should be provided with access to a
working area that:
- will provide a clear route for the suction hose from the
tanker to the tank, and
- is not more than 25m from the tank where it is not
more than 4m higher than the invert level of the tank,
and
- is sufficient to support a vehicle axle load of 14
tonnes.
7. The applicant shall ensure the private water supply for
the dwellinghouse/ development complies with the Water
Scotland Act 1980 (Section 63), The Private Water
Supplies (Scotland) Regulations 2006 and The Water
Intended for Human Consumption (Private Supplies)
(Scotland) Regulations 2017.  Detailed information
regarding the private water supply, including the nature,
location and adequacy of the source, any storage tanks/
pipework and the filtration and disinfection treatment
proposed to ensure provision of an adequate and
consistently wholesome water supply shall be submitted
to Perth and Kinross Council Environmental Health in line
with the above Act and Regulations.
8. The developer is advised to contact Sophie Nicol,
Historic Environment Manager (tel 01738 477027) Perth
and Kinross Heritage Trust, to discuss terms of reference
for work required.
9. The applicant is advised that Perth and Kinross Council
have a charging scheme for recycling and waste bins for
new build properties and newly created dwellings.
Further information can be found at:
https://www.pkc.gov.uk/binrequests
(iv) 24/01736/IPL - Residential Development (in principle), land
50 metres north of Fearnach, Kirkmichael (Report No. 25/83)
Resolved:
Grant, subject to the following terms, conditions and
informatives:
Page 23 of 160

Page 24

DRAFT
Conditions
1. This planning permission in principle will last only for five
years from the date of this decision notice, unless the
development has been started within that period.
Reason - This is a Planning Permission in Principle in
terms of Section 59 of the Town and Country Planning
(Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019)
2. The development shall not commence until the following
specified matters have been the subject of a formal
planning application for the approval of the Council as
Planning Authority: the siting, design and external
appearance of the development, the hard and soft
landscaping of the site, all means of enclosure, means of
access to the site, vehicle parking and turning facilities,
levels, foul and surface water drainage, and details of the
proposed waste and recycling provision.
Reason - This is a Planning Permission in Principle in
terms of Section 59 of the Town and Country Planning
(Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019.
3. Further to Condition 2 of this decision notice, a detailed
ecology survey covering the site shall be undertaken and
the resultant report then submitted as part of the specified
matters requiring to be the subject of a further formal
planning application for the approval of the Council as
Planning Authority.  The report shall include appropriate
mitigations to protect any identified species, and
measures to provide bio-diversity enhancements.
Reason - In order to ensure that all ecology matters are
fully considered and addressed at the appropriate stage.
4. Notwithstanding the terms of Condition 2 of this decision
notice, details of a new bus boarder adjacent to the site
shall be included as part of the development and precise
details submitted as part of the specified matters
requiring to be the subject of a further formal planning
application for the approval of the Council as Planning
Authority.
Reason - In order to clarify the terms of this planning
permission, and to ensure road and pedestrian safety is
protected.
5. No trees or hedging on or adjacent to the site shall be
felled without the prior written approval of the Council as
Planning Authority.  A tree survey (including root
protection areas) shall be submitted as part of the
specified matters requiring to be the subject of a further
formal planning application for the approval of the Council
as Planning Authority.  The tree survey must be carried
out by a qualified and independent arborist indicating the
type, age, condition, location and accurate canopy spread
of all the trees on and affected by the site and including a
Page 24 of 160

Page 25

DRAFT
tree management report with details of the tree protection
measures to be employed during construction in
accordance with BS 5837 2012: Trees in Relation to
Design, Demolition and Construction.
Reason - In order to clarify the terms of this planning
permission, and protect the existing trees from
unnecessary damage/removals.
6. The development shall be in accordance with the
requirements of Perth & Kinross Council’s Developer
Contributions and Affordable Housing Supplementary
Guidance 2023 in line with Policy 5: Infrastructure
Contributions of the Perth & Kinross Local Development
Plan 2 (2019) with particular regard to primary education
infrastructure, or such subsequent Guidance and Policy
which may replace these.
Reason - To ensure the development is in accordance
with the terms of the Perth and Kinross Local
Development Plan 2 (2019) and to comply with the
Council’s policy on Developer Contributions and
Affordable Housing Supplementary Guidance 2023.
7. The development shall be in accordance with the
requirements of Perth & Kinross Council’s Developer
Contributions and Affordable Housing Supplementary
Guidance 2023 in line with Policy 20: Affordable Housing
of the Perth & Kinross Local Development Plan 2 (2019),
or such subsequent Guidance and Policy which may
replace these.
Reason - To ensure the development is in accordance
with the terms of the Perth and Kinross Local
Development Plan 2 (2019) and to comply with the
Council’s policy on Developer Contributions and
Affordable Housing Supplementary Guidance 2020.
8. Notwithstanding the terms of Condition 2 of this decision
notice, any second level of accommodation must be
included within the roofspace.
Reason - In order to clarify the terms of this planning
permission, and to ensure the development protects the
visual amenity of the surrounding area.
9. Notwithstanding the terms of Condition 2 of this decision
notice, a Design Statement shall be submitted as part of
the details submitted as part of the specified matters
requiring to be the subject of a further formal planning
application for the approval of the Council as Planning
Authority.
Reason - In order to clarify the terms of this planning
permission, and to ensure the visual amenity and
character of the area is protected.
10. Notwithstanding the terms of Condition 2 of this decision
notice, a statement which demonstrates that at least 10%
of the current carbon emissions reduction set by Scottish
Building Standards will be met through the installation
Page 25 of 160

Page 26

DRAFT
and operation of low and zero-carbon generating
technologies shall be submitted as part of the specified
matters requiring to be the subject of a further formal
planning application for the approval of the Council as
Planning Authority.
Reason - In order to comply with Policy 32 of the adopted
Perth and Kinross Local Development Plan 2 (2019).
Justification
The proposal is in accordance with the Development Plan and
there are no material reasons which justify departing from the
Development Plan.
Informatives
1. The applicant (or any other person(s) taking this
permission on should be fully aware that this Planning
Permission in Principle may be invalidated by the felling
of trees which are required to be retained, if carried out
prior to gaining approval of all matters specified in
conditions.
2. A review of the proposed development site did not raise
any real concerns, although historical mapping indicates
that the proposed development is within the immediate
vicinity of a former underground tank(s) which may have
resulted in contamination in the vicinity of the site. Should
any contamination be found during the approved works,
all construction activities should cease, and the Land
Quality team should be contacted on
contaminatedland@pkc.gov.uk  for further advice.
3. The applicant is advised that Perth and Kinross Council
have a charging scheme for recycling and waste bins for
new build properties and newly created dwellings. Further
information can be found at:
https://www.pkc.gov.uk/binrequests
6. Proposal of Application Notices (PoAN)
(i) 25/00001/PAN - Residential Development (allocated site H341),
land 90 metres east of Westfields of Rattray, Balmoral Road,
Rattray, Blairgowrie, PH10 7HY (Report No. 25/84)
Bailie C McLaren requested due consideration be given to community
availability of building space for community use for groups to meet in
as part of ‘Building Our Stronger Communities’.
Councillor B Brawn requested due consideration be given to the
junction at Balmoral Road, the access of pedestrians into Rattray itself,
and the amount of parking spaces within the development.
The contents of the Report by the Development Management and
Building Standards Service Manager, were noted.
Page 26 of 160

Page 27

DRAFT
(ii) 25/00002/PAN - Change of use of holiday cottages to allow holiday
use or residential use as staff accommodation for employees of
Taymouth Castle Estate, Moness House Hotel and Country Club,
Aberfeldy, PH15 2DY (Report No. 25/85)
Bailie M Williamson requested due consideration be given to developer
contributions and possible access to the site from the rear entrance
which is currently closed off.
The contents of the Report by the Development Management and
Building Standards Service Manager, were noted.
(iii) 25/00003/PAN - Erection of poultry facility, managers
accommodation, staff welfare facility, office, storage buildings,
security fencing, formation of vehicular access, SUDS,
landscaping and associated works, land at Newbigging Farm,
Kinclaven (Report No. 25/86)
Bailie M Williamson requested due consideration be given to the
environmental impact of the storage and disposal of poultry manure
and comments from SEPA.
The contents of the Report by the Development Management and
Building Standards Service Manager, were noted.
(iv) 25/00004/PAN - Installation of a 49.9MW solar farm comprising
ground mounted solar arrays, inverters, substation, ancillary
buildings, fencing, CCTV cameras, vehicular access tracks and
associated works, West Pitnacree, Alyth, Blairgowrie, PH11 8JF
(Report No. 25/87)
Councillor I James requested due consideration be given to the size of
the site and whether this is good use of the land.
Bailie M Williamson requested due consideration be given to
community benefit and whether there will be a community benefit fund
associated with the development.
The contents of the Report by the Development Management and
Building Standards Service Manager, were noted.
Page 27 of 160

Page 28

Page 28 of 160

Page 29

Perth and Kinross Council
Planning and Placemaking Committee – 14 May 2025
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 25/117)
Proposal: Formation of a 49.9MW battery energy storage facility comprising
battery storage units, ancillary buildings and equipment, access road
and associated works
Location: Land 200 metres north of Pitcurran House, Newburgh Road,
Abernethy, Perth, PH2 9LH
Ref. No: 24/01386/FLM
Ward No: P9- Almond and Earn
Summary
This report recommends approval of the application as the development is
considered to comply with the relevant provisions of the Development Plan and there
are no material considerations apparent which outweigh the Development Plan.
Background and Description of Proposal
1 The application is for a Battery Energy Storage System designed to deliver up to
49.9MW of electricity. A new access track will be required to access the site.
2 The purpose of a Battery Energy Storage System is to store excess of energy on
the grid at peak of generation moments and release energy at peak demand
moments of the day. Allowing a balancing mechanism that the grid requires to
allow the new renewable energy generators across the country in their
intermittent generation line. The energy generated is fed directly into the national
electricity grid, with the point of connection to the grid being an underground
33kV cable that runs below the fields and unnamed road into the Abernethy
Primary Substation, which is approximately 300m to the east of the site.
3 The proposed application site is located on part of an arable field located at
Balgonie Farm, east of Abernethy, 300m to the west of the existing Abernethy
substation. The site is within an area of low lying farmland which is located near
the confluence of the River Earn and the River Tay 1.5km to the north. It is
located to the immediate north of the transport corridors of the Perth to Ladybank
5(1)(i)
Page 29 of 160

Page 30

Railway Line and A913, which runs from the outskirts of Perth to Cupar Angus in
the east. To the south the land rises to the Ochil Hills.
4 The site itself comprises the south western part of a regular medium-scale arable
field. The eastern boundary is formed by a hedgerow which separates the site
from the adjacent field. The southern boundary is formed by a small embankment
along the railway line and is vegetated with scattered scrub cover. To the north
and the west the site boundaries are undefined on the ground. Furthermore,
there are no specific landscape features within the application site. The access
for the proposed construction route is to/from the M90 to the west via Ferryfield
Road, the A913 and the A912. A new access track is required which is
approximately 5metres at maximum width, finished in gravel with associated
drainage ditches. This access track will connect to the existing road at
Jamesfield.
Site History
5 01/01389/FUL Full Planning Permission was approved on 14 November 2001 for
the erection of an organic produce processing unit with visitor centre, shop and
restaurant.
6 02/01804/FUL Full Planning Permission was approved on 22 January 2003 for
the erection of an organic produce processing unit with visitor centre shop and
restaurant.
7 07/02207/FUL Full Planning Permission was approved on 7 May 2008 for a part
change of use to form a children’s nursery at first floor level.
8 13/00438/FLL Full Planning Permission was refused on 31 October 2014 for the
erection of an agricultural shed.
9 17/01304/FLL Full Planning Permission was approved on 3 November 2017 for 
a change of use of upper floor from ancillary storage and nursery (class 10) to
mixed use (classes 1, 2, 4, 6 and 10) in part retrospect.
10 24/00003/PAN On 20 March 2024 for the formation of a battery energy storage
facility and associated works.
11 24/00004/PAN On 26 April 2024 for the formation of a 49.9MW battery energy
storage facility and associated works.
12 24/00580/SCRN On 6 May 2024 for the Installation of 49.9MW stand-alone
battery electricity storage system and ancilliary equipment to connect to the grid
at Abernethy Substation.
Page 30 of 160

Page 31

Environmental Impact Assessment
13 An EIA screening has been undertaken. The proposal being a Schedule 2
development in terms of the Town and Country Planning (Environmental Impact
Assessment) (Scotland) Regulations 2017. In the case of these regulations,
prohibition is given to the granting of planning permission to “EIA development”
unless an environmental impact assessment has been undertaken. In this case
the Council has taken the opinion that it is not EIA development, and that
sufficient information has been submitted with the application to enable a
determination in consideration of all relevant environmental matters. These
environmental aspects requiring further consideration, are namely: noise,
landscape and visual amenity, trees and biodiversity, roads and transportation
and flood / drainage matters.
Pre-Application Consultation
14 Pre application Reference: 23/00031/PREAPM.
15 The proposed development is classed as a Major development in terms of the
Town and Country Planning (Hierarchy of Developments) (Scotland) Regulations
2009. Therefore, the applicant was required to undertake formal pre-application
consultation with the local community.
16 The objective of the community involvement and engagement phase is to inform
and engage with the local community and stakeholders, in order to ensure local
people are aware of the proposal and have the chance to find out more and
express their views and concerns.
17 A Proposal of Application Notice was submitted to Perth and Kinross Council on
the 9th April 2024. The reply was received on 26th April 2024 confirming that the
proposed consultation process was accepted. This was also sent to Abernethy
Community Council and all Ward Councillors by email on the 11th March 2024.
18 Two in person public exhibitions were staged in The Williamson Hall, Abernethy
on the 22nd April 2024 and the 22nd May 2024, to inform local residents about
the proposals. In addition, more than 768 households and local businesses were
directly informed of the exhibitions via a leaflet mailout or door drop on the 11th
April 2024 and the 7th May 2024 (this included all households within a 2 km
radius of the site) Adverts were placed in the Perthshire Advertiser, and were
published on the 9th April 2024 and 10th May 2024.
19 Furthermore, two leaflets providing information on the proposal were mailed to
768 households and local businesses on the 11th April 2024 and the 7th May
2024. This mailout included all properties within a 2 km radius of the site. Two
adverts were placed in the Perthshire Advertiser providing information on the
proposal. This was published on the 9th April 2024 and the 10th May 2024, and
invited local residents to attend to the public exhibition events.
Page 31 of 160

Page 32

Development Plan
20 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.
National Planning Framework 4
21 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve people’s lives by making sustainable, liveable
and productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.
22 The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 4: Natural Places
 Policy 5: Soils
 Policy 6: Forestry, Woodland and Trees
 Policy 11: Energy
 Policy 29: Rural Development
Perth and Kinross Local Development Plan 2019
23 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
24 The principal relevant policies are, in summary:
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 5: Infrastructure Contributions
 Policy 6: Settlement Boundaries
 Policy 8: Rural Business and Diversification
 Policy 26A: Scheduled Ancient Monuments and Archaeology
 Policy 26B: Archaeology
 Policy 33A: New Proposals for Renewable and Low Carbon Energy
 Policy 34C: Energy Sources / Storage
 Policy 35: Electricity Transmission Infrastructure
Page 32 of 160

Page 33

 Policy 39: Landscape
 Policy 40A: Forestry, Woodland and Trees: Forest and Woodland Strategy
 Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
 Policy 41: Biodiversity
 Policy 42: Green Infrastructure
 Policy 50: Prime Agricultural Land
 Policy 51: Soils
 Policy 52: New Development and Flooding
 Policy 53A: Water Environment and Drainage: Water Environment
 Policy 53C: Water Environment and Drainage: Surface Water Drainage
 Policy 56: Noise Pollution
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
Statutory Supplementary Guidance
25
 Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
 Supplementary Guidance - Landscape (adopted in 2020)
PKC Non Statutory Guidance
26
 Planning Guidance - Loch Leven SPA, the Dunkeld-Blairgowrie Lochs SAC
and the River Tay SAC
 Planning Guidance - Planning & Biodiversity
 Supplementary Guidance - Renewable & Low Carbon Energy (draft)
National Guidance
27 The Scottish Government expresses its planning policies through Planning
Advise Notes, Creating Places, Designing Streets, National Roads Development
Guide and a series of Circulars in addition to NPF4.
Planning Advice Notes
28 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:
 PAN 69 Planning and Building standards Advice on Flooding
 PAN 75 Planning for Transport
Creating Places 2013
29 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
Page 33 of 160

Page 34

that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places.
National Roads Development Guide 2014
30 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision.
Consultations
31 As part of the planning application process the following bodies were consulted:
External
32 Health and Safety Executive (HSE) - No objection.
33 Transport Scotland - No objection to the proposed development.
34 Network Rail - Initially objected to the proposed development. Additional
information is required to fully assess the impacts of the development on the
adjacent railway. To allow Network Rail’s Fire Safety Engineer to fully assess the
proposal, the applicant must submit a site-specific Battery Safety Management
Plan. Network Rail has now reviewed additional information supplied by the
applicant, and are now content to remove the holding objection, subject to
conditions relating to the submission of a site-specific Battery Safety
Management Pan, the submission of further fire safety information and a surface
and foul water drainage scheme.
35 Scottish Water - Scottish Water has no objection to this planning application.
The applicant should be aware that this does not confirm that the proposed
development can currently be serviced.
36 This proposed development is within the Turrret Water Treatment Works
catchment. To allow Scottish Water to fully appraise the proposals, it is
suggested that the applicant completes a Pre-Development Enquiry (PDE) Form
and submits it directly to Scottish Water via the Customer Portal.
37 There is currently sufficient capacity for a foul only connection in the Abernethy
Waste Water Treatment works to service the proposed development. However,
please note that further investigations may be required to be carried out once a
formal application has been submitted to Scottish Water.
38 NatureScot - NatureScot did not respond to the consultation request.
Page 34 of 160

Page 35

39 Perth and Kinross Heritage Trust (PKHT) - No objection, subject to the
inclusion of a condition relating to the submission of a programme of
archaeological works.
40 National Gas Assets Protection Team - No objection. there are no National
Gas Transmission assets affected in this area.
Internal
41 Environmental Health (Noise Odour) - As a result of the submission of a
revised, and more cumulatively based NIA, there are now no objections to the
proposed BESS.  However, this is subject to the inclusion of conditions relating to
:
a) The enclosure and maintenance of plant and equipment
b) Operational noise limits
c) Noise mitigation measures
d) Noise complaints
e) External lighting
f) Construction working hours
42 Environmental Health (Contaminated Land) - No objection. A search of the
historic records did not raise any concerns regarding ground contamination and
therefore there are no adverse comments to make on the application. 
43 Environmental Health – Private Water Supply Team - No objection, subject to
the inclusion of a suitably worded condition relating to the details of the location
and operational measures of any proposed sceptic tanks and soakaways, private
water sources and any associated infrastructure.
44 Transportation and Development - Following the submission of further
information, there are no objections to the proposed development, subject to the
inclusion of two informatives.
45 Biodiversity/Tree Officer - No objection subject to conditions relating to the
conclusions and recommendations of the submitted Biodiversity Study, an
updated Ecology Survey, a Construction Environment Management Plan, and
details of the proposed biodiversity enhancements.
46 Community Greenspace - No objection.
47 Development Plan Team - Following the submission of additional information in
the form of a Soil Management Plan and a Landscape and Visual Impact
Assessment (LVIA), there is now no objection from the Development Plan Team.
However, it is recommended that conditions are included in relation to the
maintenance of the proposed landscaping, a revised Landscape Plan and an
updated Soil Management Plan.
Page 35 of 160

Page 36

48 Structures and Flooding - No objection.
Representations
49 Three representations were received. The main issues raised within the
representations are:
 Loss of prime agricultural land.
 Increase in traffic on Ferryfield Road.
 Road safety concerns.
 Noise pollution.
 Visual impact.
 Fire risk.
 Impact on biodiversity and ecology.
50 These issues are addressed in the Appraisal section of the report.
Additional Statements
51
Screening Opinion EIA not required
Environmental Impact Assessment
(EIA): Environmental Report
Not required
Appropriate Assessment under
Habitats Regulations
AA not required
Ecological Appraisal Submitted
Design Statement or Design and
Access Statement
Design and Access Statement
Submitted
Report on Impact or Potential Impact
eg Flood Risk Assessment
Noise Impact Assessment
Ecological Appraisal
Fire Management Plan
Transport Statement
Landscape and Visual Overview
Soil Management Plan
FRA submitted
Submitted
Submitted
Submitted
Submitted
Submitted
Submitted
Appraisal
52 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise.  The Development Plan comprises NPF4, the Perth and
Kinross Local Development Plan 2019 and statutory supplementary guidance.
The relevant policy considerations are outlined in the policy section above and
are considered in more detail below.  In terms of other material considerations,
Page 36 of 160

Page 37

this involves considerations of the Council’s other approved policies and
supplementary guidance.
Principle
53 The location is a peripheral rural area approximately 200m north of Abernethy.
Policy considerations seeking to assess its suitability in principle are: LDP2
Policies 1A, 1B, Placemaking; Policy 8 Rural Diversification; Policy 33A:
Renewables and Low Carbon Energy; Policy 50 Prime Agricultural Land; and
Policy 51 Soils. The relevant NPF4 policies are Policy 1 Tackling the Climate and
Nature Crises; Policy 2 Climate Mitigation and Adaptation; and Policy 11 Energy.
54 The proposal would provide essential energy balancing services to the National
grid, actively contributing towards Scotland's CO2 reduction targets, supporting
the principles of Scotland’s Energy Strategy (SES). Specifically, electricity would
be drawn from the grid at times of low demand, stored and released back as
required. When demand is higher, greater generation from non-renewable
sources is required and energy storage facilities such as that proposed could
reduce reliance on non-renewable resources, thus decreasing CO2 emissions.
Over the course of a year, the proposed BESS will cover the electricity equivalent
of the annual consumption of approx. 12,500 homes.
55 NPF4 sets out six overarching spatial principles with “Just Transition” relating to
the construction of renewable energy and their contribution to achieving net zero.
NPF4Sustainable Places section emphasises the link to Scotland’s Climate
Change Plan and sets the approach to achieving net zero emissions by 2045 and
making significant progress by 2030. The NPF4 also links to Scotland’s Energy
Strategy and highlights the importance of land and sea to be critical in delivering
renewable energy developments. NPF4 provides detailed policy on Climate
Change and Energy and details developer expectations to how proposed
schemes will accord with the policies set out in the document. The overarching
policy intent in NPF4 is to encourage, promote and facilitate all forms of
renewable energy development onshore and offshore.
56 In this case, it is considered that there is no conflict with any of the relevant LDP2
or NPF4 policies. Whilst there is a loss of prime agricultural land (identified as
Class 2), the loss of land is not considered to result in a significant impact. This is
because NPF4 Policy 5 provides for essential infrastructure on prime agricultural
land provided that the layout and design of the proposal minimises the amount of
land that is required. A Soil Management Plan has been submitted, which sets
out details of the proposed on-site management to minimise the loss of soil
material from the site, to reduce any potential soil contamination and to ensure
that soil structure and productive capacity can be retained and enhanced. The
total land available at Balgonie Farm is approximately 185 acres, with the
proposed BESS occupying 3 acres, which is only 1.6% of the total farm area.
This is considered to outweigh the loss of 3 acres of prime agricultural land that
will be utilised for this development.
Page 37 of 160

Page 38

57 In this instance, the proposed BESS is a temporary development and it is
anticipated that it will be in operation for 30 years. Once the project reaches the
end of its lifespan the site will be decommissioned and will be restored to its
original condition, with no impact remaining or any structures still on site that
could compromise the agricultural productivity of the site. It is proposed that
following the decommissioning of the BESS site, the subsoil and topsoil should
be returned to its original location and a process of soil cultivation enacted to
return the soil to a state suitable for agricultural use. Site surveys should be
conducted before and after decommissioning to provide clarity on the
remediation work required. Stored soil should be returned to the area of the site
where it was sourced and the original soil profile reinstated. 
58 Given the advances in the efficiency of the technology associated with BESS
developments, the footprint of the project has been reduced in 40% (number and
size of equipment, and therefore occupied land) since the PAN was submitted.
Furthermore, it is fully anticipated that, by the time that the proposed BESS is
commissioned in 2027, further advances in BESS technology will result in a
further reduction in the overall footprint of the development, and therefore, less of
an uptake of prime agricultural land. This, combined with the locational need for
the development close to the existing electrical substation, in addition to any
carbon offsetting potential, outweigh any impact on landscape values and
agricultural use. Furthermore, this substation has unconstrained capacity to
import and export the electrical energy required.
59 Notwithstanding the above, Policy 33a of LDP2 and Policies 1, 2 and 11 of NPF4
specifically encourages low carbon energy solutions where specific grid
connection or the use of established infrastructure can occur. Therefore, on
balance, and given the site-specific reasoning for the location of the battery
storage unit, the proposed development can be supported. Furthermore,
consideration must be given to the finite lifespan of this facility. Whilst the overall
operational life will be some 30 years, minimal disturbance to the site will be
required, allowing the pre-existing land use to resume afterwards.
Design and Layout
60 LDP2 Policy 1: Placemaking, requires that development must contribute
positively to the quality of the surrounding built and natural environment. All
development should be planned and designed with reference to climate change,
mitigation and adaptation. The design, density and siting of development should
respect the character and amenity of the place.
61 The proposed development comprises of a battery energy storage system
(BESS) contained within a fenced compound and surrounded by proposed. The
17 no. battery containers and the rest of equipment will be mounted on concrete
beams arranged in a linear fashion across the site in rows. There will be
approximately 6m between each container. The layout of the proposed BESS
includes both inverters and transformers. A total of 17 inverters and transformers
will be erected and spread across the site. A substation, split in to two separate
Page 38 of 160

Page 39

buildings are proposed to the southeast side of the site a control room. The
inverters are components stored in cabinets which are pale grey or green in
colour and approx. 7,40m length x 2.0m width x 2.2m height. The transformers
are smaller units of 2,40m length x 2,40m width x 2,1m height.
62 The sub-station will consist of pre-fabricated cabins depending on the
requirements from the Distribution Networks Operator (DNO). One cabin will be
for the internal connection of the electrical output from the site, with the other
required by the DNO for connection into the wider electricity network. A control
room will be situated next to the substation buildings near the southern boundary
of the site. The control room will be a single storey building and will measure up
to 26m length x 7m width x 2.9m height which is dark green in colour. A battery
storage racks will take the form of independent, single storey containers and will
measure up to 27,8m length x 3,1m width x 3.8m height.
63 The compound will be surrounded by a 2.75m palisade green fence, and all
equipment mounted on concrete beams. The surface of the compound will be
finished with aggregate, with a stronger base proposed for during construction
and maintenance of the proposed development. Infra-red security cameras will
be located around both sites, at a height of approximately 4.2m.
64 Landscaping is proposed, including native planting, around the site perimeter
including a 10m wide continuous border of native scrub and tree planting. Full
details of this have not been submitted but this can be controlled through a
suitably worded planning condition (condition 13). Access to the site will be taken
via a new access track which is approximately 5metres at maximum width,
finished in gravel with associated drainage ditches. This access track will connect
to the existing road at Jamesfield. The track will be contained fully within the red-
line site boundary of this application, however the exact coordinates of the route
and impact upon existing trees and hedgerows is yet to be determined. This can
be controlled via a pre-commencement planning condition (condition 18).
Landscape and Visual Amenity
65 Perth and Kinross Council LDP2, Policy 39: Landscape states that development
and land use change should be compatible with the distinctive characteristics
and features of Perth and Kinross’s landscapes. Accordingly, development
proposals will be supported where they do not conflict with the aim of maintaining
and enhancing the landscape qualities of Perth and Kinross.
66 In this instance, the development site is currently an agricultural field and is not
located within the Green Belt or any other designated landscape areas. A
”Landscape and Visual Overview” has been provided which considers the
individual application itself will not have a significant landscape or visual impact.
These impacts are primarily from the Ochil Hills LLA and from the core path
network.
Page 39 of 160

Page 40

67 In addition, further information has been provided in an “Landscape & Visual
Overview Addendum”. This document acknowledges that the development would
result in further change to the landscape but that the change, in the context of the
existing built form components, allows for the development to be accommodated
and be further softened by landscaping. It is further acknowledged that there will
be a sequential impact of the development, including on views from the Ochil
Hills LLA.
68 Regarding cumulative landscape effects on the Ochil Hills LLA, it is
acknowledged that the landscape fabric and the aesthetic aspects of its
immediate setting to the north would experience a further degree of localised
change given the temporary conversion of agricultural land to renewable energy
installations. However, the renewable energy schemes would be relatively small-
scale in relation to the wider valley landscape and the prevailing open,
agricultural character of the LLA’s setting would remain intact. No physical
change would occur on the Ochil Hills LLA. However, the scale, when compared
with the wider landscape, along with the separation from any existing and
planned infrastructure, is sufficient to retain the appearance of a farmed
landscape.
69 Furthermore, the localised landscape setting is partly characterised by existing
built form components, road and rail infrastructure, as well as overhead visual
elements such as cables and pylons. These elements are considered to have
had an impact on the rural character of this landscape. It is therefore considered
that the local landscape setting has some capacity to accommodate such
development of a temporary nature as the type proposed. In addition, the
landscape proposals for the proposed development will physically and visually
integrate the scheme into the local landscape, utilising appropriate native species
to further mitigate any cumulative effects arising from the proposals. Overall, it is
considered that other impacts from viewpoints over the local character area are
too distant to be significant.
70 A Landscape and Visual Impact Assessment (LVIA) has been submitted, and
impacts from the various viewpoints have been analysed and it has been
determined that the majority of the impacts will be minimalised by the topography
of the landscape, the existing vegetation and the presence of local electricity
transmission infrastructure. Furthermore, any significant visual impacts from local
core paths can be mitigated with sensitive landscaping. However, as a result of
this proposed development, there will still be an impact on the rural, productive
nature of the landscape at ground level, but this localised impact is, overall,
considered acceptable. In light of the above, a condition (condition 15) has been
included that the final landscaping scheme is planted and maintained for the life
of the development, and at an appropriate height to ensure that views from the
Core Path and views to the Sidlaw Hills are retained. In light of the above, the
proposed BESS is in accordance with LDP2 Policy 39: Landscape and NPF4
Policy 4: Natural Places.
Page 40 of 160

Page 41

71 NPF4 5(b) requires applicants to demonstrate how the footprint and design has
minimised any potential impact. The applicant has stated that the footprint has
been reduced by 40% from the PAN but that there is a high possibility that the
site could be reduced further by the time the project is developed. The landscape
plan sets out a minimal use of hardstanding.
Soils
72 The site is on prime agricultural land (class 2). NPF4 Policy 5 provides for
essential infrastructure on prime agricultural land provided that the layout and
design of the proposal minimises the amount of land that is required. In this
instance, a draft Soil Management Plan has been submitted which is suitable to
minimise impact on soils and retain soils on site. However, a condition (Condition
16) has been included requiring an updated soil management plan to be
submitted, prior to the commencement of development.
73 Furthermore, an analysis of all available Class 3 land has been submitted. The
report states that areas of 3.2 land south of the proposal are inappropriate due to
topography and another area close to the Tay is also unsuitable. The closest
area of 3.2 land (marked as area B) is flat agricultural land near Cordon farm.
The report states that the vast majority of this field is not classified as flood risk
but that as it is flat it is still at risk of flooding. SEPA 2023 river flood maps show
this area as not at even low flood risk as river flooding is contained to the north of
the River Earn.
74 Subsequently, the applicant has provided information to confirm that the
landowner of the non-prime land has been contacted and not shown an interest
in hosting the development on this land. A further condition (Condition 17) has
been included to ensure that the site is reinstated as soon as the proposal has
ceased to be operational for a period of 12 months. Therefore, this land does not
need to be considered as an alternative to the proposed site. In light of the
above, the proposed BESS is considered to be in accordance with LDP2 Policy
51: Soils and NPF4 Policy 5: Soils
Residential Amenity
75 LDP2 Policy 56: Noise Pollution states that there will be a presumption against the
siting of development proposals which will generate high levels of noise in the
locality of existing or proposed noise sensitive land uses and similarly against the
locating of noise sensitive uses near to sources of noise generation. In this
instance, there are residential properties within proximity to the proposed BESS,
located to the north, southeast and southwest. PKC Environmental Health Noise /
Odour initially objected to the proposals as insufficient information had been
provided to demonstrate that the application site was a suitable location for the
proposed development. It was not possible for Environmental Health to complete
an appraisal of the application until a cumulative noise impact assessment has
been undertaken. In light of this, a revised Noise Impact Assessment (NIA) was
Page 41 of 160

Page 42

submitted, which includes updated inverter noise levels for day and nighttime
operations and a cumulative assessment.
76 As a result of the NIA, it has been concluded that the predicted worst case
external noise level at the nearest dwelling houses is below the maximum criteria
for external amenity space. Furthermore, internal predicted noise levels during
the nighttime period are below the maximum criteria that is considered the
threshold above which sleep disturbance may occur. This revised NIA now
includes a cumulative noise assessment for the potential noise contribution from
the various adjacent energy developments such as SSE substation on land off
Abernethy Road, BESS approved planning 22/00746/FLM, BESS approved
planning 22/00832/FLL and Solar Farm 17/00487/FLL. The assessment has
been undertaken assuming all schemes are operating simultaneously and is
based on the noise levels at the worst affected residential properties in relation to
the proposed BESS. The noise levels are below both the daytime and nighttime
criteria and achieve the nighttime criteria for the standard plant noise for areas
with low background levels.
77 In light of this, the proposed BESS will not result in a level of noise that will have
an adverse impact on residential amenity. However, in order to ensure that any
impact on residential amenity is minimised, a condition has been included to
ensure that all plant and machinery is enclosed (condition 3). A further condition
has been included stating a noise limit for the BESS (condition 4). Other
conditions that have been included relate to noise mitigation measures (condition
8), complaints from the public (condition 5), external lighting (condition 6) and
construction working hours(condition7).
78 Therefore, subject to the aforementioned conditions, the proposed development
is in accordance with LDP2 Policy 56 and NPF4 Policy 29.
Roads and Access
79 LDP2 Policy 15: Public Access states that development proposals that would
have an adverse impact upon the integrity of any (including proposed) core path,
disused railway line, asserted right of way or other well-used route and
connectivity proposals identified in the Regional Transport Strategy and Delivery
Plan will not be permitted.
80 In this instance, the proposed development will not have an adverse impact on
public access and will not require any re- routing of a core path or right of way.
Therefore, the proposed BESS is in accordance with LDP2 Policy 15: Public
Access.
81 LDP2 Policy 60A: Existing Infrastructure, sees existing transport infrastructure
identified, and encouragement given to the retention and improvement of these
facilities provided the improvements are compatible with adjoining land uses. The
new access track which is proposed will connect to the existing road at
Jamesfield. This will make use of existing infrastructure.
Page 42 of 160

Page 43

82 Furthermore, the access for the proposed construction route is to/from the M90
to the west via Ferryfield Road, the A913 and the A912. This will then adjoin the
new access track. A Transport Statement (TS) has been submitted, which states
that there will be an estimated 5/6 HGV deliveries per day at the beginning of the
construction period. This will result in a relatively low level of construction traffic,
which will not have an adverse impact on traffic safety or traffic flows on the
surrounding road network. The TS has stated that the proposed access and
route for construction vehicles will not give rise to any road safety concerns.
83 A Construction Traffic Management Scheme (CTMS) has been submitted, which
shows the position and specification of signage and other control measures
being proposed. Furthermore, the CTMS sets out how the construction and
operational vehicular activities will be undertakes and managed.
84 Considering the above, it is considered that the proposed battery storage facility
is in accordance with LDP2 Policies 15 and 60A, and NPF4 Policies 11 and 12.
Drainage and Flooding
85 LDP2 Policy 52: New Development and Flooding, states that the Council
supports the actions and objectives to avoid increased, reduce overall, and more
generally manage flood risk in alignment with SEPA Strategies and Plans. NPF4
Policy 22 states that development proposals must have regard to the water
environment, and drainage, including floodwater management, within any
proposal. In this instance, the proposed development is classified as Essential
Infrastructure and can be built within a flood-risk area (200yr + Climate Change)
in accordance with NPF4 Policy 22a.
86 However, the proposed BESS should be designed and constructed to be
operational during floods, not impede water flow and not increase the risk of
flooding elsewhere. In this case, SEPA’s Surface Water Flood Map does not
identify any areas of pluvial/surface water flooding within proximity of the site
boundary. Furthermore, a review of SEPA’s groundwater flood maps indicates
that there is no groundwater flood risk for the proposed development.
87 A Flood Risk Assessment has been submitted, which has identified all potential
sources of flooding in the immediate area. The only watercourse upslope of the
site is the minor unnamed watercourse / drain which runs along the eastern edge
of the field. The watercourse has a small catchment area of approximately 0.23
square km and passes under the railway via a culvert of approximately 0.6m by
1.2m, which has adequate capacity during peak flood events. The minor field
drain to the west of the site has a very limited catchment area and is situated
downslope of the site. As such it presents no risk to the development. This being
the case, the proposed BESS is neither at risk of flooding from any existing
sources nor will it result in a risk of flooding elsewhere. This being the case, the
proposed development is in accordance with LDP2 Policy 52 and NPF4 Policy
22a.
Page 43 of 160

Page 44

88 LDP2 Policy 53C: Surface Water Drainage, requires Sustainable Urban Drainage
Systems (SUDS) measures including relevant temporary measures at the
construction phase. Due to the site topography, land use and underlying geology,
the primary means of drainage at the site is likely to be initial soil adsorption /
infiltration. Furthermore, when the field capacity of the soils is exceeded, then
overland flow / runoff would shed towards the minor drainage ditch, located
northwest of the site boundary.
89 The proposed drainage / SuDS scheme for the site has been developed to
manage the surface water runoff from the battery storage development area. The
development site will be constructed with permeable materials (e.g. crushed
gravel) to allow rainwater to infiltrate into the ground, where it will be intercepted
by perforated pipework. Runoff from semi-permeable / impermeable surfaces will
be conveyed into a SuDS attenuation pond via a series of perforated and
conventional pipework, ditches and drains. The perforated pipework and liner
drainage features will convey runoff to a lined SuDS pond located in the
northwestern corner of the site. The pond will provide suitable treatment and
attenuation prior to discharge to the adjacent watercourse. The SuDS pond is to
be lined as it will serve a dual purpose for firewater runoff storage. Given that the
applicant has submitted adequate drainage drawings, design and overall
strategy, the proposed BESS is in accordance with LDP2 Policy 53C.
Conservation Considerations
90 LDP2 Polices 26A, 26B and Policy 7 of NPF4 are applicable to this application. In
this instance, the proposed development site lies within an area that is
considered archaeologically sensitive as its located within a rich archaeological
landscape with evidence of activity spanning across multiple periods with
particular strong evidence of Roman activity.
91 A Heritage Assessment has been submitted, which acknowledges that there is
medium potential for unknown buried remains on site. Given the site’s location
next to the road and the presence of existing screening from trees and other
developments, the proposed BESS will have a low impact on the setting of the
local Roman strongholds. However, as there is the potential for buried remains
on site, as requested by PKHT, a condition (condition 9) has been included that a
programme of archaeological works should be undertaken. Subject to this
condition, the proposed development is considered to be in accordance with
LDP2 Policies 26A, 26B and Policy 7 of NPF4.
Natural Heritage and Biodiversity
92 LDP2 Policy 41: Biodiversity states that the Council will seek to protect and
enhance all wildlife and wildlife habitats, whether formally designated/protected
or not. All whilst taking into account the ecosystems and natural processes in the
area. In accordance with NPF4, development proposals for major development
will only be supported where it can be demonstrated that the proposal will
conserve, restore and enhance biodiversity, including nature networks so they
Page 44 of 160

Page 45

are in a demonstrably better state than without intervention. This will include
future management.
93 In this instance, the submitted Ecological Appraisal is comprehensive and all
methods were undertaken in accordance with best practice at the correct time of
year. The submitted Ecological Appraisal contains recommendations to achieve
biodiversity enhancement but lacks detail in terms of numbers and locations. For
major applications,  a Site Biodiversity Action Plan, which provides quantity,
locations, techniques, timescales and monitoring arrangements, should be
submitted.
94 However, in line with the response from the Council’s Biodiversity Officer, the
submitted Landscape Strategy Plan is considered sufficient to secure the
necessary biodiversity enhancement required by NPF4. Conditions have been
included to ensure that the submitted Biodiversity Survey is fully adhered to
(condition 10), an updated Ecology Survey is submitted (condition 11), a detailed
Construction Management Scheme is to be submitted (condition 12), the
Landscaping and Planting Scheme should be completed within the first available
planting season (condition 13), bat , bird boxes and other biodiversity
enhancement measures must be provided ( Condition 14) and that the proposed
planting must be maintained for the life of the development (condition 15).
Developer Contributions
95 The Developer Contributions Guidance is not applicable to this application, and
therefore, no contributions are required in this instance
Economic Impact
96 The economic impact of the proposal is likely to be minimal and limited to the
construction phase of the development. However, the proposal will support local
renewable energy generation by helping balance fluctuations of intermittent
energy generation. It will assist in the creation of a national grid asset of regional
significance for the Perth and Kinross area.
Variation Of Application Under Section 32A
97 This application was varied prior to determination, in accordance with the terms
of Section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended. The variations were relating to landscape and visual impact, soils,
floods and drainage.
Planning Obligations and Legal Agreements
98 None required.
Page 45 of 160

Page 46

Direction By Scottish Ministers
99 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.
Conclusion and Reasons for Recommendation
100 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly, the proposal is recommended for approval
subject to the following conditions.
Recommendation 
Approve subject to the following conditions:
Conditions and Reasons for Recommendation
General
1. The proposed development must be carried out in accordance with the approved
drawings and documents, unless otherwise provided for by conditions imposed
on the planning consent.
Reason: To ensure that the development is carried out in accordance with the
approved plans.
2. This planning permission will last only for three years from the date of this
decision notice, unless the development has been lawfully started within that
period.
Reason: This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019.
Environmental Health – Noise / Odour
3. All plant or equipment shall be so enclosed, attenuated and/or maintained such
residential property, with all windows slightly open, when measured and/ or
calculated and plotted on a rating curve chart.
Reason: In order to safeguard the neighbouring residential amenity in the area.
Page 46 of 160

Page 47

4. Noise from the battery storage facility shall not exceed 40dB LAeq daytime (07:00
to 23:00) and 34dBLAtq nighttime (23:00 to 07:00) when measured at the façade
of any residential property.
Reason: In order to safeguard the neighbouring residential amenity in the area.
5. In the event, that justified complaints for noise are received by the Council, the
Applicant at their own expense, shall employ an independent and suitably
qualified consultant to carry out a Noise Assessment from the development.  The
appointed consultant and methodology for the Noise Assessment shall be
submitted to and approved in writing by the Planning Authority in consultation
with Environmental Health within 28 days of being notified of the complaint.
Within 28 days of approval of appointed consultant and methodology, a Noise
Assessment shall be submitted outlining mitigation and recommended timescales
for delivery.  Thereafter, all mitigation measures shall be implemented within the
timescales recommended.
Reason: In order to safeguard the neighbouring residential amenity in the area.
6. All external lighting shall be sufficiently screened and aligned so as to ensure that
there is no direct illumination of neighbouring land and that light spillage beyond
the boundaries of the site is minimised to a degree that it does not adversely
affect the amenity of the neighbouring land.
Reason: In order to safeguard the neighbouring residential amenity in the area.
7. Construction work shall be limited to Monday to Friday 0700 hours to 1900 hours
and Saturday 0800 hours to 1300 hours with no noisy works out with these times
or at anytime on Sundays or bank holidays.
Reason: In order to safeguard the neighbouring residential amenity in the area.
8. The Noise mitigation measure in the form of a 3 metre high acoustic barrier as
outlined in Section 4.2 and Figure 3 of the Noise Impact Assessment report
reference J004918-7825-CW-02, undertaken by Philip Dunbavin Acoustic Ltd,
dated January 2025, shall be implemented prior to the battery storage facility
being brought into use.
Reason: In order to safeguard the neighbouring residential amenity in the area.
Archaeology
9. Development shall not commence until the developer has secured the
implementation of a programme of archaeological work in accordance with a
Written Scheme of Archaeological Investigation (WSI) which has been submitted
by the developer and agreed in writing by the Council as Planning Authority, in
consultation with Perth and Kinross Heritage Trust (PKHT).  Thereafter, the
developer shall ensure that the programme of archaeological works is fully
Page 47 of 160

Page 48

implemented including that all excavation, preservation, recording, recovery,
analysis, publication and archiving of archaeological resources within the
development site is undertaken.  Should the archaeological works, as required by
the WSI, identify a requirement for post-excavation analysis, the development as
approved shall not be occupied or brought into use until a Post-Excavation
Research Design (PERD) has been submitted to and agreed in writing by the
Council as Planning Authority, in consultation with PKHT.  The PERD shall be
carried out in complete accordance with the approved details.  Furthermore, the
developer shall afford access at all reasonable times to PKHT or a nominated
representative and shall allow them to observe work in progress.
Reason: In the interest of protecting archaeological interest within the site.
Biodiversity and Natural Environment
10. The conclusions and recommended action points within the supporting
Biodiversity Survey submitted and hereby approved (document 22 relates) shall
be fully adhered to, respected and undertaken as part of the construction phase
of development, to the satisfaction of the Council as Planning Authority.
Reason: In the interests of protecting environmental quality and of biodiversity.
11. An updated ecology survey will be required prior to the commencement of works,
if works have not commenced within 24 months of the date of the ecology survey
approved as part of this permission.  The updated survey shall be submitted to
the Council as Planning Authority for written agreement and works shall not
commence until after such written agreement has been issued by the Council.
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).
12. Development shall not commence until a detailed Construction Method
Statement (CMS) has been submitted to the Council as Planning Authority and
agreed in writing in consultation with NatureScot and Scottish Environment
Protection Agency (SEPA).  The CMS must identify measures to prevent harmful
materials entering the River Tay SAC, which could reduce water quality and lead
to a damaging impact on the salmon, otter and lamprey interests.  The CMS
should include the following:
a) pollution prevention safeguards including drainage arrangements and the
possible use of siltation traps, settlement tanks and bunds
b) storage and disposal of materials including the siting of stock piles, use of
buffer strips and disposal methods
c) construction site facilities including extent and location of construction site
huts, vehicles, equipment, fuel, chemicals and materials compound
d) timing, duration and phasing of construction particularly in relation to salmon
and lamprey migration/spawning.
Page 48 of 160

Page 49

The CMS and mitigations as agreed shall be fully implemented as part of the
planning permission.
Reason: In the interest of protecting the environment and sustainability.
13. Prior to the commencement of development, a detailed landscaping and planting
scheme shall be submitted to the Planning Authority for written approval.  The
plan shall include native planting around the site perimeter including a 10metre
wide continuous border of native scrub and tree planting.  Thereafter, the agreed
scheme shall be implemented as part of the site development programme and in
the first available planting season, and thereafter maintained for the life of the
development.
Reason: In the interest of visual amenity and to ensure the satisfactory
implementation of the proposed planting scheme.
14. Prior to the completion or bringing into use of the development hereby approved,
10 bat boxes, 10 bird boxes, 10 hibernacula and 10 bee/insect hotels shall be
provided within the red line boundary.  Thereafter, the agreed scheme shall be
maintained in a reasonable condition for the life of the development.
Reason: To increase the number of bat and bird boxes to ensure significant
biodiversity enhancement.
15. Any planting failing to become established within five years shall be replaced in
the following planting season with others of similar size, species and number to
the satisfaction of the Council as Planning Authority.
Reason: In the interest of visual amenity and to ensure the satisfactory
implementation of the proposed planting scheme.
16. Prior to works commencing on site, a revised soil re-use and management plan
shall be submitted to and approved in writing by the Council as Planning
Authority.  This Plan will include details of the storage of all soils and their
appropriate re-use.  Thereafter, the agreed plan shall be implemented in full.
Reason: To protect soils from damage such as erosion or compaction, in
accordance with LDP2 Policy 51: Soils and NPF4 Policy 5.
Facility Lifespan
17. In the event the hereby approved development fails to store electricity on a
commercial basis for a continuous period of 12 months, then it shall be deemed
to have permanently ceased to be required. In such an event, the development,
including the access track, shall be decommissioned and the relevant parts of the
site reinstated within such a timescale as agreed in writing by the Council as
Planning Authority.
Page 49 of 160

Page 50

Reason: To ensure the facility is removed from the site at the end of its
operational life, and to protect the character of the countryside, the visual
amenity of the area and nature conservation interests.
New Access Road
18. Prior to the commencement of development, a scheme shall be submitted to the
Planning Authority for written approval, showing the precise location and
specification of the new access track. This scheme shall demonstrate how the
existing trees and hedgerows shall be protected, and if any loss of these trees or
hedgerows is required, a compensatory scheme for replacement planting shall
be included. Thereafter, the agreed scheme shall be implemented in full
accordance.
Reason: To ensure that the access track does not detract from the visual
qualities and the landscape character of the area.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Procedural Notes
None applicable.
Informatives
1. Under Section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,
which may result in enforcement action being taken.
2. As soon as practicable after the development is complete, the person who
completes the development is obliged by section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the Planning Authority written
notice of that position.
3. An application for a Building Warrant may be required.
4. This planning permission will last only for three years from the date of this
decision notice, unless the development has been started within that period (see
Section 58(1) of the Town and Country Planning (Scotland) Act 1997 (as
amended).
Page 50 of 160

Page 51

5. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as
amended, it is an offence to remove, damage or destroy the nest of any wild
birds while that nest is in use or being built.  Planning consent for a development
does not provide a defence against prosecution under this act.
6. The applicant is reminded that, should any protected species be present a
license may be required from NatureScot to disturb a protected species.  Failure
to obtain a license may constitute a criminal act under the Habitats Regulations
and penalties are severe for non-compliance.
7. This development will require the 'Display of notice while development is carried
out', under Section 27C (1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013.  The form of the notice is set out in Schedule 7 of
the Regulations and a draft notice is included for your guidance.  According to
Regulation 41 the notice must be:
• Displayed in a prominent place at or in the vicinity of the site of the
development.
• Readily visible to the public.
• Printed on durable material.
8. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request.
The Fees Charter is available on our website www.pkc.gov.uk.  The Council has
two months to consider the information. You should therefore submit the required
information more than two months before your permission expires. We cannot
guarantee that submissions made within two months of the expiry date of your
permission will be able to be dealt with before your permission lapses.
9. The developer is advised to contact Sophie Nicol, Historic Environment Manager
(Tel: 01738 477027) Perth and Kinross Heritage Trust, to discuss terms of
reference for work required.
10. The applicant is advised that, in terms of Sections 56 of the Roads (Scotland) Act
1984, he/she/they must obtain from the Council, as Roads Authority, consent to
open an existing road or footway prior to the commencement of works. 
Information on junction types, requirements for Vehicular Access consents (VA1)
and application forms are available at www.pkc.gov.uk/vehicleaccess.  Advice on
the disposal of surface water should be sought at the initial stages of design from
Scottish Water and the Scottish Environment Protection Agency.
Page 51 of 160

Page 52

11. The applicant is advised that, in terms of Sections 109 of the New Roads and
Street Works Act 1991, he/she/they must obtain from the Council, to place,
maintain or adjust apparatus in, or under a Road or remove apparatus from a
road.  Application forms are available https://www.pkc.gov.uk/article/14916/Road-
and-footway-permits
12. National Gas Transmission should be consulted during the design phase and that
an Earthing Report is submitted for review, and to ensure that the pipeline is not
affected.
13. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive.  Trees and scrub are present on the application site and are to
be assumed to contain nesting birds between the above dates.  The applicant is
reminded that, under the Wildlife and Countryside Act 1981, as amended
(Section 1), it is an offence to remove, damage or destroy the nest of any wild
bird while that nest is in use or being built.  Planning permission for a
development does not provide a defence against prosecution under this Act.
14. The applicant is advised to refer to Perth & Kinross Council’s Supplementary
guidance on Flood Risk and Flood Risk Assessments 2021 as it contains advice
relevant to your development.
15. Details of all changes in ground levels, laying of foundations, and operation of
mechanical plant in proximity to the rail line must be submitted to Network Rail’s
Asset Protection Engineer for approval prior to works commencing on site. 
Where any works cannot be carried out in a “fail-safe” manner, it will be
necessary to restrict those works to periods when the railway is closed to
railtraffic i.e. by a “possession” which must be booked via Network Rail’s Asset
Protection Engineer and are subject to a minimum prior notice period for booking
of 20 weeks.
16. All construction works must be undertaken in a safe manner which does not
disturb the operation of the neighbouring railway.  Applicants must be aware of
any embankments and supporting structures which are in close proximity to their
development
17. The developer must contact Network Rail’s Asset Protection Engineers regarding
the above matters, either by submitting an enquiry on the Network Rail
website .
18. The applicant should ensure that any existing wayleaves for maintenance or
repair to existing private water supply or septic drainage infrastructure in the
development area are honoured throughout and after completion of the
development.
19. Information regarding Construction Method Statements, as required by condition
12, can be found at:  https://www.pkc.gov.uk/media/46816/River-Tay-SAC-
Page 52 of 160

Page 53

Guidance-
Adopted2020/pdf/River_Tay_SAC_2020_Adopted.pdf?m=637426890920130000
Background Papers
Letters of representation 3
Authors
Name Designation Contact Details
Alan Atkins Planning Officer (Major
Team)
01738 475300
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
28 April 2025
Page 53 of 160

Page 54

Page 54 of 160

Page 55

Ü
Formation of a 49.9MW battery energy storage facility comprising battery storage units, ancillary buildings
and equipment, access road and associated works on land 200 Metres North of Pitcurran House, Newburgh
Road, Abernethy
24/01386/FLM
Scale
1:25,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(i)
Page 55 of 160

Page 56

Page 56 of 160

Page 57

Ü
Formation of a 49.9MW battery energy storage facility comprising battery storage units, ancillary buildings
and equipment, access road and associated works on land 200 Metres North of Pitcurran House, Newburgh
Road, Abernethy
24/01386/FLM
Scale
1:10,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(i)
Page 57 of 160

Page 58

Page 58 of 160

Page 59

Perth and Kinross Council
Planning and Placemaking Committee – 14 May 2025
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 25/118)
Proposal: Erection of 42 dwellinghouses and associated works - phase 2
(change of house type and plot layout of 22/02223/AMM)
Location: Scone North, Scone, Perth
Ref. No: 24/01483/AMM
Ward No: P2- Strathmore
Summary
This report recommends approval of a Matters Specified in Conditions (AMSC)
application for the erection of a total of 42 dwellinghouses within the site referred to as
‘Scone North’. This Report concludes that the proposal is consistent with the
Development Plan, the existing Planning Permission in Principle (PPP) consent (Ref:
16/02127/IPM) and other relevant material planning considerations.
Background and Description of Proposal
1 The application site extends to an area of approximately 2.7 ha and forms part of
the development site known as ‘Scone North, which extends to 63 ha and is
identified within the Local Development Plan 2 (LDP2) as H29, a residential led
(up to 700 dwellings) urban expansion. Planning Permission in Principle (PPP)
Ref: 16/02127/IPM and an associated Section 75 legal agreement relates, with
further detailed approvals in place for other phases.
2 Detailed designs have been approved through previous AMSC applications for
Phases 1A and 1B. Phase 1A is complete and the development of 1B is nearing
completion.
3 In addition, detailed approval has been granted for erection of 210
dwellinghouses on phase 2A (22/02223/AMM), which forms part of the area that
this application comprises and remains extant. Some of the conditions of the
PPP have been agreed under that consent and, due to the similarities with the
current application, do not require to be revisited. The current application for
AMSC will be required to be implemented concurrently with certain matters
5(1)(ii)
Page 59 of 160

Page 60

previously approved under 22/02223/AMM. These matters are detailed in the
assessment section of the report.
4 The developer for the previous AMSC was A & J Stephen. Persimmon has since
sought to acquire this section of site, thereby requiring some amendments to the
previous approval to reflect the different house types now proposed, alongside
some other relatively minor changes to the layout.
5 The 42 dwellings comprise a mix of detached, semi-detached and terraced
dwellinghouses. The numbers and tenure mix are:
 4 x two-bedroom terraced dwellinghouses;
 4 x three-bedroom terraced dwellinghouses;
 15 x three-bedroom semi-detached dwellinghouses;
 3 x three-bedroom detached dwellinghouses;
 13 x three-bedroom with study detached dwellinghouses; and
 3 x five-bedroom with study detached dwellinghouses.
6 All of the properties will have access to a private external amenity area and be
finished in white render, with a grey brick basecourse and sills and grey roof tiles.
The windows, doors and fascia boards will be white upvc and the rainwater
goods will be black upvc.
Site History
7 15/00017/PAN On 8 December 2015 PKC agreed a Proposal of Application
Notice for Residential development and associated infrastructure, access,
landscaping, SUDS, and open space.
8 16/00762/SCRN On 2 May 2016 an EIA screening opinion was issued by PKC
advising that residential development at Scone North was EIA development.
9 16/00995/SCOP On 11 July 2016 a Scoping Opinion was issued by PKC for an
EIA Report associated to a residential development at Scone North and
associated infrastructure, access, landscaping, drainage, SUDS, and open
space.
10 16/02127/IPM Planning Permission in Principle was approved on 18 April 2018
for Scone North’s residential development with open space, landscaping,
drainage and associated infrastructure (in principle).
11 18/00758/ADV Advertisement Consent was approved on 22 June 2018 for
display of signs.
12 18/00759/ADV Advertisement Consent was approved on 22 June 2018 for
display of signs.
Page 60 of 160

Page 61

13 18/02231/AMM Approval of Matters Specified in Conditions related to
16/02127/IPM was approved on 30 August 2019, allowing for the erection of 42
dwellinghouses, landscaping and associated works (Phase 1a).
14 19/01478/ADV Advertisement Consent was approved on 5 November 2019 for
the display of a sign.
15 20/00382/FLL Full Planning Permission was approved on 8 July 2020 for the
erection of 5 dwellinghouses (revised design - change of house types at plots 28,
29, 33, 34 and 35) within Phase 1a.
16 20/01416/FLL Full Planning Permission was approved on 18 November 2020 for
the erection of a dwellinghouse and marketing suite (revised design - plot 3)
within Phase 1a.
17 20/01614/ADV Advertisement Consent was approved on 2 December 2020 for
display of a sign.
18 20/01752/FLL Full Planning Permission was approved on 12 July 2021 for
Erection of 2 dwellinghouse (revised design - change of house types - plots 26
and 27) within Phase 1a.
19 21/00484/FLL Full Planning Permission was approved on 12 July 2021 for the
erection of a dwellinghouse and garage (change of house type at plot 41) within
Phase 1a.
20 21/00609/AMM Approval of Matters Specified in Conditions related to
16/02127/IPM was approved on 24 September 2021 for the erection of 58
dwellinghouses and 3 detached garages, landscaping, and associated works
(Phase 1b).
21 21/02147/FLL Full Planning Permission was approved on 1 February 2022 for
erection of a dwellinghouse (revised design - plot 39) within Phase 1a.
22 21/02196/FLL Full Planning Permission was approved on 9 February 2022 for
Erection of 9 dwellinghouses (revised design - plots 45, 46, 51, 93, 95, 96, 98,
101 and 104) within Phase 1b.
23 22/00742/FLL Full Planning Permission was approved on 10 June 2022 for the
erection of 6 dwellinghouses and associated works (revised design - change of
house type to include sunrooms for plots 57, 60-61 and 75-77) within Phase 1b.
24 22/02223/AMM was approved on 13 December 2023 for the erection of 210
dwellinghouses, formation of landscaping, SUDS, and associated works
(approval of matters specified in conditions of 16/02127/IPM) (phase 2A).
Page 61 of 160

Page 62

Environmental Impact Assessment
25 The impact of the wider development site was screened for EIA
(16/00762/SCRN) and it was determined that the proposal does constituted EIA
development. As such an EIA Report was submitted as part of the application for
planning permission in principle.
Pre-Application Consultation
26 Pre-application Reference: 15/00017/PAN.
Development Plan
27 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.
National Planning Framework 4
28 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies. This
strategy sets out how to improve people’s lives by making sustainable, liveable
and productive spaces. NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.
29 The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 6: Forestry, Woodland and Trees
 Policy 7: Historic Assets and Places
 Policy 13: Sustainable Transport
 Policy 14: Design, Quality and Place
 Policy 15: Local Living and 20 Minute Neighbourhoods
 Policy 16: Quality Homes
 Policy 18: Infrastructure First
 Policy 20: Blue and Green Infrastructure
 Policy 21: Play, Recreation and Sport
 Policy 22: Flood Risk and Water Management
Perth and Kinross Local Development Plan 2019
30 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
Page 62 of 160

Page 63

economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
31 The principal relevant policies are, in summary;
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 1D: Placemaking
 Policy 2: Design Statements
 Policy 5: Infrastructure Contributions
 Policy 14B: Open Space Retention and Provision: Open Space within New
Developments
 Policy 15: Public Access
 Policy 20: Affordable Housing
 Policy 25: Housing Mix
 Policy 26B: Scheduled Monuments and Archaeology: Archaeology
 Policy 29: Gardens and Designed Landscapes
 Policy 32: Embedding Low & Zero Carbon Generating Technologies in New
Development
 Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
 Policy 41: Biodiversity
 Policy 42: Green Infrastructure
 Policy 52: New Development and Flooding
 Policy 53A: Water Environment and Drainage: Water Environment
 Policy 53B: Water Environment and Drainage: Foul Drainage
 Policy 53C: Water Environment and Drainage: Surface Water Drainage
 Policy 53E: Water Environment and Drainage: Water Supply
 Policy 56: Noise Pollution
 Policy 57: Air Quality
 Policy 58A: Contaminated and Unstable Land: Contaminated Land
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
 Policy 61: Airfield Safeguarding
Statutory Supplementary Guidance
32
 Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2023)
 Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
 Supplementary Guidance - Open Space Provision for New Developments
(adopted in 2021)
 Supplementary Guidance - Placemaking (adopted in 2020)
Page 63 of 160

Page 64

PKC Non Statutory Guidance
33
 Planning Guidance - Delivery of Development Sites
 Planning Guidance - Planning & Biodiversity
National Guidance
34 The Scottish Government expresses its planning policies through Planning
Advise Notes, Creating Places, Designing Streets, National Roads Development
Guide and a series of Circulars in addition to NPF4.
Planning Advice Notes
35 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:
 PAN 40 Development Management
 PAN 51 Planning, Environmental Protection and Regulation
 PAN 61 Planning and Sustainable Urban Drainage Systems
 PAN 68 Design Statements
 PAN 69 Planning and Building standards Advice on Flooding
 PAN 75 Planning for Transport
Creating Places 2013
36 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places.
Designing Streets 2010
37 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places.
National Roads Development Guide 2014
38 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision.
Consultations
39 As part of the planning application process the following bodies were consulted:
Page 64 of 160

Page 65

External
40 Historic Environment Scotland (HES): No objection. The proposed
development site is located within the Scone Palace Inventory Designed
Landscape (GDL00338). The site would be screened in views from the centre of
the estate by topography and existing and proposed policy woodland. The
development is not likely to have a significant adverse impact on the Inventory
garden and designed landscape.
41 Perth and Kinross Heritage Trust (PKHT): With respect to archaeology and the
planning process, as outlined by NPF4, the proposed development does not
raise any significant issues. No archaeological mitigation is required in this
instance.
42 Transport Scotland: No objection.
43 Scone and District Community Council: Objection.
44 Scottish Water: No comments. Response to previous application advised that
there was capacity at local water and wastewater treatment works.
45 Scottish Environment Protection Agency (SEPA): Initially submitted a holding
objection pending further information on the detailing of the drainage. This
information has now been received and SEPA will confirm their position prior to
the Planning & Placemaking Committee on the 14th May 2025.
Internal
46 Environmental Health (Contaminated Land): No objection. A Site Investigation
Report has identified the need for remedial works to ensure the wider site is
suitable for the proposed use. Condition required.
47 Environmental Health (Noise Odour): No objection. Conditions required to
control construction noise and the requirement for a CEMP.
48 Transportation and Development: Initially requested some further clarification.
This has subsequently been received and Transportation and Development offer
no objection.
49 Structures and Flooding: No objection. Changes to house types and plot layout
do not seem to have notably impacted the drainage layout and calculations. The
new finished floor levels (FFL) and finished ground levels (FGL) appear to
account for freeboard. Surface water flow extents appear reasonable. Any culvert
exceeding 2m in diameter will require Technical Approval.
50 Development Contributions Officer: No objection. The application seeks
change of house type and layout in Phase 2 of Scone North, previously approved
Page 65 of 160

Page 66

under 22/02223/AMM. The comments provided with that application remain
applicable and no additional contributions are required in this instance.
51 Biodiversity: No objection. Conditions required to ensure recommendations
from biodiversity surveys and action plans are adhered to and implemented. An
updated ecological survey will be required if works begin outwith 24 months of
the approved survey. Wildlife kerbs and hedgehog highways should also be
provided.
52 Community Greenspace: No objection.
Representations
53 Two representations were received including from Scone and District Community
Council. The main issues raised within the representations are:
• Flood risk
• Noise
• Road safety concerns
54 These issues are addressed in the Appraisal section of the report.
Additional Statements
55
Screening Opinion EIA not required
Environmental Impact
Assessment (EIA):
Environmental Report
Not required
Appropriate Assessment under
Habitats Regulations
AA not required
Design Statement or Design
and Access Statement
Design Statement submitted
Report on Impact or Potential
Impact eg Flood Risk
Assessment
Drainage Strategy Report
Construction Environment Management
Plan
Sustainability Statement
Appraisal
56 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise.  The Development Plan comprises NPF4, the Perth and
Kinross Local Development Plan 2019 and statutory supplementary guidance.
The relevant policy considerations are outlined in the policy section above and
are considered in more detail below.
Page 66 of 160

Page 67

Principle
57 The principle of the proposal has been established through the site’s allocation
as H29 in LDP2 for a residential development. Planning permission in Principle
(PPP) (16/02127/IPM) has also been granted for the development of the site for
residential use, reflective of that LDP2 allocation.
58 An extant Approval of Matters Specified in Conditions (AMSC) (22/02223/AMM)
is also in place for this phase of the development. The current proposal is
substantially similar to the extant AMSC for this area, and the principle of the
proposal is acceptable subject to compliance with the PPP, relevant development
plan policies and other material considerations. These matters are considered in
detail below.
Design and Layout
59 Policy 14: Design, Quality and Place, Policy 15: Local Living and 20 Minute
Neighbourhoods and Policy 16: Quality Homes of NPF4 are relevant; as are
LDP2 Policy 1: Placemaking, Policy 14B: Open Space within New
Developments, Policy 17: Residential Areas and Policy 25: Housing Mix. In
association, various PPP conditions also apply.
60 The layout is substantially similar to that of the extant AMSC, with the main
change seeking approval for the Persimmon house types. The layout continues
to follow the principles set down by approved masterplan. The proposed
dwellings all seek to provide an active frontage with the majority of the houses
oriented to overlook roads and areas of open space, including those fronting the
primary road passing through the site from Phase 1B to future phases to the
East.
61 The new house types are of an appropriate massing and scale which is
commensurate with the previous approval. The proposals will add variety and
visual interest to the street scene and provides a legible environment which
connects the new housing effectively to the existing residential areas with an
appropriate urban density.
62 The use of white render and a grey brick basecourse provides an appropriate fit
with the adjacent residential development, which is of similar finishes.
63 Overall, the proposed layout, design, scale and massing are considered to
comply with the Council’s placemaking policies, providing a logical and coherent
development. The proposals therefore are considered to accord with the terms of
PPP and the relevant NPF4 and LDP2 policies.
Landscape and Visual Impact
64 The majority of the proposal is roads and dwellinghouses with parking and
private garden areas. The larger areas of landscaping and open space to be
Page 67 of 160

Page 68

delivered as part of the wider Scone North development is located on other
phases. However, there are small areas of open space and some areas abutting
the larger expanses of open space within the application site.
65 The changes to the house types to the north of plot 19 has moved the units
North, which in turn has increased the area of open space to the South, allowing
improved landscaping to be provided on this corner. Otherwise, the site
landscaping remains broadly in line with the extant AMSC and proposes
appropriate planting and boundary treatments.
66 Therefore, the proposal complies with NPF4 Policies 6: Forestry, Woodland and
Trees and Policy 20: Blue and Green Infrastructure and LDP2 Polices 39:
Landscape; 40B: Forestry, Woodland and Trees - Trees, Woodland and
Development; and 42: Green Infrastructure. In association, the conditions
attached to the PPP are also satisfied.
Residential Amenity
67 Residential amenity requires to be considered under NPF4 Policy 16: Quality
Homes and LDP2 Policy 1: Placemaking and Policy 17: Residential Areas as well
as PPP conditions.
Privacy, Daylight and Overshadowing
68 The location of the proposed dwellinghouses, relevant to both themselves and
existing/approved residential properties is such that there will be no unacceptable
loss of privacy or daylight or overshadowing.
Noise, Vibration and Dust
69 The applicant has submitted a Construction Environment Management Plan
(CEMP) with the application, which includes methods on how noise, vibration and
dust will be controlled during the construction phase to ensure the residential
amenity of existing properties is not adversely affected. This includes hours of
working with are in line with PKC’s guideline hours for construction and vibration
monitoring. Environmental Health has confirmed that they have no adverse
comments subject to conditions to control construction noise and adherence to
the CEMP (Condition 3).
Contaminated Land
70 A Site Investigation Report submitted for the extant AMSC has identified the
need for remedial works to ensure the wider site is suitable for the proposed use.
Therefore, the works outlined in this report also relate to this application.
71 Therefore, the condition should be reimposed on this approval to ensure the
necessary investigations and works undertaken (Condition 7).
Page 68 of 160

Page 69

Roads and Access
72 In respect of the internal road layout and parking provision, PKC Transportation
and Development raise no concerns. The proposed internal movement layout,
including road hierarchy and associated private and public parking provision is
considered satisfactory and consistent with the approach and principles adopted
in the original masterplan submission and extant AMSC.
Drainage and Flooding
73 The parameters agreed within the Flood Risk Assessment for the previous
approval are not changed by the Persimmon site design. Therefore, the previous
FRA for the site remains relevant and this matter does not need to be revisited in
the consideration of this application. PKC Flooding and Structures has confirmed
that the changes to house types and plot layout do not have notably impacted the
drainage layout and calculations. They have advised that the new finished floor
levels (FFL) and finished ground levels (FGL) account for freeboard and that
surface water flow extents appear reasonable. As a result, they have no
objections to the proposal. SEPA initially submitted a holding objection pending
further information on the detailing of the drainage. This information has now
been received and SEPA will confirm their position prior to the Planning &
Placemaking Committee on the 14th May 2025.
Waste Collection
74 The PPP seeks to ensure appropriate waste and recycling provision is identified
and secured as part of MSC applications. In this regard there is considered to be
adequate provision proposed to accommodate requirements, satisfying the
conditional terms of the PPP.
Natural Heritage and Biodiversity
75 In relation to natural heritage and biodiversity, NPF4 Policies 1: Tackling the
Climate and Nature Crisis, 2: Climate Mitigation and Adaptation and 3:
Biodiversity apply along with LDP2 Policy 41 Biodiversity. In association, several
conditions attached to the PPP applications cover these issues.
76 NPF4 advises that development proposals for national or major development will
only be supported where it can be demonstrated that significant biodiversity
enhancements are provided, in addition to any proposed mitigation.
77 The ecological survey information submitted for planning reference
22/02223/AMM can be used to inform this application as the data is less than 24
months old. All recommendations made in the ecology and tree survey reports
including the Arboricultural Impact Assessment must be adhered to in full
(conditions 10 and 11).
Page 69 of 160

Page 70

78 Similarly, a Biodiversity Action Plan was submitted in support of 22/02223/AMM
and all actions outlined in the Plan should be adhered to in full (conditions 10 and
11).
Archaeology and Conservation Considerations
79 NPF4 Policy 7: Historic Assets and Places; LDP2 Policies 26B: Archaeology and
29: Gardens and Designed Landscapes and conditions attached to the PPP
application apply.
80 Proportionate archaeological trenching and investigation has been undertaken as
part of the previous AMSC, with findings reported back to Perth and Kinross
Heritage Trust (PKHT). No further archaeological investigation or survey work is
considered necessary, within this phase. HES have also confirmed that the
proposals do not conflict with or cause adverse impact on the Historic and
Designed Landscape of Scone Palace.
Low and Zero Carbon Generating Technologies
81 LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in
New Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of
low and zero-carbon generating technologies. As this proposal includes the
erection of a new building, consideration must be given to this requirement.
Further, NPF4 Policy 2 ‘Climate Mitigation and Adaptation’ requires that
development should be designed to reduce green gas emissions. In this
instance, a Sustainability Statement has been submitted in support of the
application. The Statement advises that the requirements will be met through the
fabric energy efficiency of the development being designed to reduce heat
demand and energy needs through providing high levels of insulation and low air
permeability, with consideration for thermal bridging junctions. Photovoltaic roof
panels, low voltage lighting, low flush sanitary appliances will also be installed on
all properties. The proposal therefore complies with the relevant policies.
Developer Contributions
82 A Section 75 legal agreement covers the 16/02127/IPM permission to ensure
necessary infrastructure is delivered, including:
 Community Facility Delivery
 Contribution towards Sports Facilities, including provision towards Sports
pitches and pavilion.
 Open Space Provision and Maintenance
 Compensatory Tree Planting
 Public Transport Improvement
 Affordable Housing
 Structure Planting Delivery
Page 70 of 160

Page 71

83 The legal agreement in place adequately secures these elements and no further
changes are required.
84 With specific regard to affordable housing, there were no affordable housing units
proposed in this area as part of the previous AMSC. As a result, there are no
affordable homes included within this proposal. The requisite provision will be
delivered on other areas of the wider Scone North development.
Economic Impact
85 During the construction period, jobs will be created and sustained, supporting
indirect employment and revenue that this volume of construction activity will
generate from employees spending on local goods and services. Longer term,
additional residents to the area will support existing local employment and
services in the area.
Planning Obligations and Legal Agreements
86 None required.
Direction By Scottish Ministers
87 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.
Conclusion and Reasons for Recommendation
88 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019). Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly the proposal is recommended for approval
subject to the following conditions.
Recommendation 
Approve the application subject to the following conditions:
Conditions and Reasons for Recommendation
1. The development must be begun not later than the expiration of three years
beginning with the date on which this approval of matters specified in condition is
granted.  If development has not begun at the expiration of this period, the
approval of matters specified in condition lapses.
Page 71 of 160

Page 72

Reason: In order to ensure the development to which this approval of matters
specified in conditions relates is commenced timeously and in accordance with
Section 41(1)(c) of the Town and Country Planning (Scotland) Act 1997.
2. The development hereby approved must be carried out in accordance with the
approved drawings and documents, unless otherwise provided for by conditions
imposed by this decision notice.
Reason: To ensure the development is carried out in accordance with the
approved drawings and documents.
3. The Construction Environment Management Plan (CEMP) submitted to satisfy
Condition 19 of planning permission 16/02127/IPM shall be implemented
concurrent with the development.  The CEMP will remain a dynamic document
throughout the duration of construction and until the completion of development.
The CEMP can be amended as necessary to meet best practice in terms of
environment or ecology.  Any amended document shall be submitted to the
Planning Authority for written approval as soon as reasonably practicable citing
the relevant amendment and appropriate guidance.
Reason: In the interest of protecting environmental quality and of biodiversity.
4. All road gullies within 500m of a waterbody or Sustainable Urban Drainage
(SUDS) pond shall have wildlife kerbs installed adjacent to the gully.
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).
5. All trees identified for retention and any peripheral trees bounding the site, which
may be affected by any element of the approved development and its associated
construction, (including land within the blue site area) shall be protected in full
accordance with BS 5837: 2012 'Trees in relation to design, demolition and
construction'.
Reason: In the interest of tree protection in the interests of biodiversity and
amenity of the area.
6. The detailed landscaping and planting proposal specifications as hereby
approved shall be undertaken and delivered commensurate with the residential
development elements and thereafter maintained to the satisfaction of the
Council as Planning Authority.  Any planting failing to become established within
five years shall be replaced in the following planting season with others of similar
sizes and species to the satisfaction of the Council as Planning Authority.
Reason: In the interests of visual amenity; to ensure a satisfactory standard of
local environmental quality and in pursuance of satisfying placemaking policy
criteria of the adopted LDP.
Page 72 of 160

Page 73

7. Development shall not commence on site until an evaluation for the potential of
the site to be affected by contamination by a previous use has been undertaken
and, as a minimum, a Preliminary Risk Assessment (Phase 1 Desk Study) has
been submitted for consideration and accepted by the Council as Planning
Authority.  If the preliminary risk assessment identifies the need for further
assessment, an intrusive investigation shall be undertaken to identify;
I. the nature, extent and type(s) of contamination on the site
II. measures to treat/remove contamination to ensure the site is fit for the use
proposed
III. measures to deal with contamination during construction works
IV. condition of the site on completion of decontamination measures.
Prior to the completion or bringing into use of any part of the development the
measures to decontaminate the site shall be fully implemented in accordance
with the scheme subsequently agreed by the Council as Planning Authority. 
Verification that the scheme has been fully implemented must also be submitted
to the Council as Planning Authority.
Reason: In order to deal with any potential contamination of the site as a result of
its former use.
8. Storm water drainage from all paved surfaces, including the access, shall be
disposed of by means of suitable Sustainable Urban Drainage Systems to meet
the requirements of best management practices.
Reason: To ensure the provision of provide effective drainage for the site.
9. Concurrent with the initiation of the development hereby approved and for the
duration of construction, a temporary surface water treatment facility shall be
implemented on site and maintained for the duration of the approved
development works.  The temporary surface water treatment facility shall remain
in place until the permanent surface water drainage scheme is implemented
unless otherwise agreed in writing by the Council as Planning Authority.
Reason: To ensure the appropriate management of construction surface water
run-off to minimise flooding and avoid discharge of sediment/pollution to the local
water environment or neighbouring property, in the interests of residential and
environmental amenity.
10. The conclusions and recommended action points within the supporting ecology
and tree survey reports including the Arboricultural Impact Assessment submitted
and approved as part of 22/02223/AMM shall be fully adhered to, respected and
undertaken as part of the construction phase of development.
If works are not commenced within 24 months of the date of the ecology and tree
survey reports approved as part of 22/02223/AMM, then updated surveys will be
Page 73 of 160

Page 74

required to be submitted to the Planning Authority for written approval prior to the
commencement of works.
Reason: In the interests of protecting environmental quality and of biodiversity.
11. Prior to the completion or occupation of the building(s) hereby approved,
whichever is the earlier, all biodiversity enhancement measures in the Scone
North Phase 2A Biodiversity Action Plan (submitted for 22/02223/AMM) must be
provided in full. Thereafter, the agreed scheme shall be maintained in a
reasonable condition for the life of the development.
Reason: In the interests of protecting environmental quality and of biodiversity.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Informatives
1. Under Section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,
which may result in enforcement action being taken.  Please use the form
attached herewith.
2. As soon as practicable after the development is complete, the person who
completes the development is obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the Planning Authority written
notice of that position.  Please use the form attached herewith.
3. This development will require the 'Display of notice while development is carried
out', under Section 27C(1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013, as amended.  The form of the notice is set out in
Schedule 7 of the Regulations and a draft notice is included for your guidance. 
In accordance with Regulation 41 the notice must be:
 Displayed in a prominent place at or in the vicinity of the site of the
development
 Readily visible to the public
 Printed on durable material.
4. The applicant is advised that in terms of Sections 21 of the Roads (Scotland) Act
1984 they must obtain from the Council as Roads Authority Road Construction
Consent (RCC) to construct a new road prior to the commencement of
Page 74 of 160

Page 75

roadworks.  Advice on the disposal of surface water must be sought at the initial
stages of design from Scottish Water and the Scottish Environment Protection
Agency.  Please note that a fee is chargeable for the processing of RCC
applications.
5. The applicant should be advised to contact Perth & Kinross Council Street
Lighting Department to obtain technical approval for all street lighting provision.
6. The applicant is reminded that, should any protected species be present a
licence may be required from NatureScot to disturb a protected species.  Failure
to obtain a licence may constitute a criminal act under the Habitats Regulations
and penalties are severe for non-compliance.
7. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as
amended (Section 1), it is an offence to remove, damage or destroy the nest of
any wild bird while that nest is in use or being built.  Planning permission for a
development does not provide a defence against prosecution under this Act.
8. The applicant should be aware of the requirements of the Council's Environment
and Regulatory Services in relation to waste collection from the site and should
ensure adequate measures are provided on site to allow for the collection of
waste, including construction phasing.
9. No work shall be commenced until an application for building warrant has been
submitted and approved.
10. There is a continued requirement for a Section 75 legal obligation associated
with Planning Permission in Principle 16/02127/IPM, relating to:
 Community Facility delivery
 Contribution towards Sports Facilities, including provision towards sports
pitches and pavilion
 Open Space provision and maintenance
 Compensatory Tree planting
 Public Transport movement
 Affordable Housing
 Structure Planting delivery.
A copy is available to view on the Council's Public Access portal.
11. The applicant is advised to refer to Perth & Kinross Council's Flood Risk and
Flood Risk Assessments Supplementary Guidance, and the CIRIA SuDS manual
as it contains advice relevant to your development.
12. Prior to the completion or occupation of the development hereby approved,
whichever is the earlier, hedgehog highways shall be created by providing
access gaps in wooden fences on each plot at least 13cm x 13cm at ground
level, to allow for the free movement of hedgehogs.  Thereafter, the hedgehog
Page 75 of 160

Page 76

highways shall be retained in a reasonable condition for the life of the
development, to the satisfaction of the Council as Planning Authority.
13. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request. 
The Fees Charter is available on our website www.pkc.gov.uk.   
The Council has two months to consider the information.  You should therefore
submit the required information more than two months before your permission
expires.  We cannot guarantee that submissions made within two months of the
expiry date of your permission will be able to be dealt with before your
permission lapses.
14. The applicant is advised that any proposed signage will require a further
application to be submitted for advertisement consent unless it benefits from
express consent as per the Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984.
Background Papers
Letters of representation 2
Authors
Name Designation Contact Details
Alex Gudgeon Planning Officer (Major
Team)
01738 475300
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
1 May 2025
Page 76 of 160

Page 77

Ü
Erection of 42 dwellinghouses and associated works - phase 2 (change of house type and plot layout of
22/02223/AMM) at Scone North, Scone
24/01483/AMM
Scale
1:15,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(ii)
Page 77 of 160

Page 78

Page 78 of 160

Page 79

Ü
Erection of 42 dwellinghouses and associated works - phase 2 (change of house type and plot layout of
22/02223/AMM) at Scone North, Scone
24/01483/AMM
Scale
1:5,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(ii)
Page 79 of 160

Page 80

Page 80 of 160

Page 81

Perth and Kinross Council
Planning and Placemaking Committee – 14 May 2025
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 25/119)
Proposal: Erection of 43 dwellinghouses, landscaping and associated
infrastructure (approval of matters specified in conditions of
02/01482/IPM)
Location: Land to the north of A912 at Oudenarde, Bridge of Earn, Perth
Ref. No: 24/01961/AMM
Ward No: P9- Almond and Earn
Summary
This report recommends approval of a Matters Specified in Conditions (AMSC)
application for the erection of 43 dwellinghouses, landscaping and associated
infrastructure. This Report concludes that the proposal is consistent with the
Development Plan, the existing Planning Permission in Principle (PPP) consent (Ref:
02/01482/IPM) and other relevant material planning considerations.
Background and Description of Proposal
1 Planning Permission in Principle (PPP) (02/01482/OUT) was granted in
September 2016 for a residential, commercial, and industrial development with
associated school provision, open space, and landscaping. Several other related
permissions have also been approved. These include approvals for 150
affordable houses split between two approvals in 2005 and 2008 (05/00410/FUL
and 08/01458/FUL) which represent Phase 1 of the ‘Oudenarde Village’
development, to the north of the railway line and accessed via Clayton Road.
Other permissions associated to roads and other infrastructure are also in place,
being approved in advance of the S75 agreement for the PPP being concluded.
Planning permission for part of Phase 2A for 159 dwellings(16/02156/AMM) was
approved in October 2020 following a call-in by Scottish Ministers. Development
has recently commenced (October 2023). As part of the call-in a Modification
Order of the PPP was submitted to the Scottish Government in May 2020 and
was subsequently adopted in July 2020.The Modified Order added in a condition
related to the delivery of required-off-site works on the M90 slip roads and
junctions. A detailed planning history is set out in the ‘Site History’ section below.
5(1)(iii)
Page 81 of 160

Page 82

2 The application site comprises an area of relatively level ground between the
A912 to the south, the Edinburgh-Perth railway line to the north, the M90 to the
west with Bridge of Earn beyond, whilst immediately east is undeveloped land that
has permission for 159 dwellings (16/02156/AMM). Beyond that is undeveloped
land. The A912 road has been upgraded to facilitate the development of land and
includes a roundabout to provide access to areas to both its north and south.
3 Oudenarde (including the proposed site) is allocated in the Perth and Kinross
Local Development Plan 2 (LDP2) 2019 (H15) for mixed use development, with
an indicative residential capacity of 1,600 dwellings.
4 Planning permission for 66 bungalow style dwellinghouses, ranging from 2-3
bedroom in size, and for associated landscaping and infrastructure immediately
north-west of the A912 roundabout was the second AMSC permission approve
under the amended PPP. Planning application reference 21/00615/AMM refers.
5 Planning approvals 23/00144/AMM, 23/00145/AMM and 23/00146/AMM,
represent ‘Phase 2a’ which relate to the same site as that previously approved
under 21/00615/AMM and the overall number of dwellings remained the same. All
three AMSC applications incorporated changes across the site which were
deemed to be material and therefore could not benefit from a non-material
variation under Section 64 of the Town and Country Planning (Scotland) Act 1997
(as amended).
6 This proposal seeks to change the house types within 23/00144/AMM, introducing
11 new house types, and take some land from 23/00145/AMM. If approved,
23/00145/AMM would see 5 dwellings less and this application, if approved,
would see an increase in 14 dwellings compared to the previous approval of 29
dwellinghouses for 23/00144/AMM. Taking into consideration the loss of 5
dwellings from 23/00145/AMM and offsetting this to 24/01961/AMM there would
be an overall increase of 9 dwellinghouses across the 3 sites. The principal
change is the increase in density. 
Site History
7 The following planning history is relevant:
8 00/00573/OUT Proposed new settlement development including residential,
commercial, and industrial development with associated roads, school
provision, open space, and landscaping. Application Withdrawn December
2001.
9 01/01822/OUT Formation of residential commercial and industrial
development with associated school provision, open space, and landscaping
(in outline). Appeal on non-determination August 2002 but was withdrawn by
the applicant.
Page 82 of 160

Page 83

10 02/01482/IPM Formation of residential, commercial, and industrial development
with associated school provision, open space, and landscaping (In Principle).
Application approved by Development Management Committee September
2002. An update on the proposal with a revised Heads of Terms was presented
to Development Management Committee in November 2012. The Section 75
legal agreement was concluded September 2016 and decision notice issued
September 2016. A Modification Order was submitted to the Scottish
Government in May 2020 and was subsequently adopted in July 2020. The
Modified Order added in a condition related to the delivery of required-off-site
works on the M90 slip roads and junctions.
11 05/00410/FUL Erection of 75 affordable dwellinghouses. Application approved
by Development Management Committee September 2005.
12 06/01881/FUL Erection of 193 dwellinghouses with associated roads, open
space, landscaping and other ancillary works. Pending decision but will be
withdrawn should 16/02156/AMM be approved.
13 07/00401/FUL Construction of a Road Bridge over railway at Oudenarde.
Approved under delegated powers March 2007.
14 07/01791/FUL Erection of a new primary school with community facilities
including parking and access road. Approved under delegated powers August
2008.
15 08/00582/FUL Formation of roads and associated infrastructure for associated
residential development (partly in retrospect). Approved under delegated
powers May 2008.
16 08/00610/OUT Outline application for (a) an opportunity site for a Travel
Lodge and other uses falling within classes 3, 7 and 8 and (b) a Business
Park for Classes 1, 4, 5 and 6 at Brickhall Farm, Bridge of Earn. Approved
by Development Management Committee February 2009.
17 08/01458/FUL Erection of 75 affordable dwellinghouses with associated road
access and landscaping. Approved by Development Management Committee
December 2008.
18 08/01815/MOD Modification of existing consent (08/00582/FUL) for formation of
roads and associated infrastructure. Approved under delegated powers October
2008.
19 08/02298/FUL Formation of roads and associated infrastructure. Approved
under delegated powers December 2008.
20 10/01411/FLL Modification of consent (08/00610/OUT) to delete conditions 11
and 12, modify planning conditions 13, 14, 15 and 16 and add conditions 2 and 3
Page 83 of 160

Page 84

as per Transport Scotland consultation. Approved under delegated powers
November 2010.
21 14/00268/FLL Modification to existing planning permission (08/00582/FUL) to
form an additional arm on roundabout and installation of feature on roundabout.
Approved under delegated powers April 2014.
22 16/02156/AMM Erection of 159 dwellinghouses with associated roads,
drainage, and landscaping. Approved following a call-in by Scottish Ministers
October 2020.
23 21/00615/AMM Erection of 66 dwellinghouses, 16 detached garages,
landscaping and associated infrastructure (approval of matters specified in
conditions 02/01482/IPM) Approved by Planning and Placemaking Committee on
20 January 2022.
24 23/00144/AMM Erection of 29 dwellinghouses, 11 detached garages,
landscaping and associated infrastructure (approval of matters specified in
conditions 02/01482/IPM) Approved by Planning and Placemaking Committee on
10 January 2024.
25 23/00145/AMM Erection of 20 dwellinghouses, 4 detached garages, landscaping
and associated infrastructure (approval of matters specified in conditions
02/1482/IPM). Approved by Planning and Placemaking Committee on 10
January 2024.
26 23/00146/AMM Erection of 17 dwellinghouses, 7 detached garages, landscaping
and associated works (approval of matters specified in conditions 02/01482/IPM)
Approved by Planning and Placemaking Committee on 10 January 2024.
27 25/00039/FLL Erection of 6 dwellinghouses, landscaping and associated
infrastructure (change of house type plots 36, 37, 40, 41, 49 and 50). Approved
under delegated powers on 4 March 2025.
Environmental Impact Assessment (EIA)
28 During the Scottish Government call-in of the Phase 2 application, the Scottish
Government screened the overall site and found that an EIA was not required.
This position continues to be accepted by the Council.
Pre-Application Consultation
29 The proposed development is classed as a Major development under class 9 of
the Town and Country Planning (Hierarchy of Developments) (Scotland)
Regulations 2009. However, because the proposal is a Matters Specified by
Condition application related to a Planning Permission in Principle a pre-
application consultation (PAC) is not required at this stage of the planning
Page 84 of 160

Page 85

process. It is also important to note that the PPP was submitted long before the
Act required developers to undertake any pre-application consultation.
Development Plan
30 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.
National Planning Framework 4
31 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve peoples lives by making sustainable, liveable
and productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.
32 The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 6: Forestry, Woodland and Trees
 Policy 13: Sustainable Transport
 Policy 14: Design, Quality and Place
 Policy 15: Local Living and 20 Minute Neighbourhoods
 Policy 16: Quality Homes
 Policy 18: Infrastructure First
 Policy 19: Heating and Cooling
 Policy 20: Blue and Green Infrastructure
 Policy 22: Flood Risk and Water Management
 Policy 23: Health and Safety
Perth and Kinross Local Development Plan 2019
33 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
34 The principal relevant policies are, in summary;
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 1D: Placemaking
 Policy 2: Design Statements
Page 85 of 160

Page 86

 Policy 5: Infrastructure Contributions
 Policy 14A: Open Space Retention and Provision: Existing Areas
 Policy 14B: Open Space Retention and Provision: Open Space within New
Developments
 Policy 15: Public Access
 Policy 17: Residential Areas
 Policy 20: Affordable Housing
 Policy 23: Delivery of Development Sites
 Policy 24: Maintaining an Effective Housing Land Supply
 Policy 25: Housing Mix
 Policy 26A: Scheduled Monuments and Archaeology: Scheduled Monuments
 Policy 32: Embedding Low & Zero Carbon Generating Technologies in New
Development
 Policy 40A: Forestry, Woodland and Trees: Forest and Woodland Strategy
 Policy 41: Biodiversity
 Policy 42: Green Infrastructure
 Policy 52: New Development and Flooding
 Policy 53A: Water Environment and Drainage: Water Environment
 Policy 54: Health and Safety Consultation Zones
 Policy 56: Noise Pollution
 Policy 57: Air Quality
 Policy 58A: Contaminated and Unstable Land: Contaminated Land
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
Statutory Supplementary Guidance
35
 Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2023)
 Supplementary Guidance - Flood Risk and Flood Risk Assessments (adopted
in 2021)
 Supplementary Guidance - Open Space Provision for New Developments
(adopted in 2021)
 Supplementary Guidance - Placemaking (adopted in 2020)
PKC Non-Statutory Guidance
36
 Planning Guidance - Delivery of Development Sites
 Planning Guidance - Planning & Biodiversity
 Supplementary Guidance - Renewable & Low Carbon Energy (draft)
National Guidance
37 The Scottish Government expresses its planning policies through Planning
Advise Notes, Creating Places, Designing Streets, National Roads Development
Guide and a series of Circulars in addition to NPF4.
Page 86 of 160

Page 87

Planning Advice Notes
38 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:
 PAN 1/2011 Planning and Noise
 PAN 40 Development Management
 PAN 51 Planning, Environmental Protection and Regulation
 PAN 60 Planning for Natural Heritage
 PAN 61 Planning and Sustainable Urban Drainage Systems
 PAN 63 Waste Management Planning
 PAN 65 Planning and Open Space
 PAN 67 Housing Quality
 PAN 68 Design Statements
 PAN 69 Planning and Building standards Advice on Flooding
 PAN 75 Planning for Transport
 PAN 77 Designing Safer Places
 PAN 79 Water and Drainage
 PAN 83 Masterplanning
Creating Places 2013
39 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places.
Designing Streets 2010
40 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places.
National Roads Development Guide 2014
41 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision.
Consultations
42 As part of the planning application process the following bodies were consulted:
Page 87 of 160

Page 88

External
43 Perth and Kinross Heritage Trust: No objection, subject to condition. Advise
that the site may have some archaeological potential and development will
require monitoring.
44 Scottish Water: No objection as there is capacity for water and wastewater in
the area.
45 Transport Scotland: No objection, subject to recommended condition
regarding trigger for M90 slip road junction works which accords with the PPP
(as modified).
46 Earn Community Council: No comments.
Internal
47 Transportation and Development: No objection subject to conditions.
48 Community Waste Advisor: No objection.
49 Affordable Housing Enabler: No objection.
50 Development Plan: No objection following revisions to the landscaping
framework, improved connectivity with the A912 and change to housing mix.
51 Community Greenspace: No objection.
52 Environmental Health (Contaminated Land): No objection as no records of
contamination within proposed site.
53 Biodiversity: No objection following submission of further information.
54 Development Contributions Officer: Noted planning permission in principle
02/01482/IPM. The proposed plot remix will result in an additional nine units to
the consented number. The application site is located in development parcels
R21 and R22, which form part of Phases 2A and 2B of the phasing and delivery
plan, alongside R1, R2, and R3 across 11.07 hectares.
55 These parcels together comprise “in the region of 352 private dwellings” in Phase
2A and 2B. As detailed consent has not been sought for all other parcels, the
additional units in the proposed application can be accommodated in the
remaining capacity established for this phase. There would be no requirement to
revisit planning obligations.
56 Structures and Flooding: No objection.
Page 88 of 160

Page 89

Representations
57 Number of representations received: 0
Additional Statements
58
Screening Opinion EIA not required
Environmental Impact Assessment (EIA):
Environmental Report
not required
Appropriate Assessment under Habitats
Regulations
Habitats Regulations Appraisal
completed
AA not required
Design Statement or Design and Access
Statement
Not submitted, planning statement
submitted.
Report on Impact or Potential Impact eg
Flood Risk Assessment
 Drainage Assessment
 Ecology Report
Appraisal
59 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise.  The Development Plan comprises NPF4, the Perth and
Kinross Local Development Plan 2019 and statutory supplementary guidance.
The relevant policy considerations are outlined in the policy section above and
are considered in more detail below.  In terms of other material considerations,
this involves considerations of the Council’s other approved policies and
supplementary guidance, the terms of the PPP and matters raised in consultation
responses.
Principle
60 The key determining policy issues for this specific proposal at this location
include: the principle of the development and its contribution towards providing
high quality, affordable and sustainable homes (Policy 20, 24 and 25 of the LDP2
and Policy 16 of the NPF4), liveable places (design, quality and place) (Polices 1,
2, 55-58 of the LDP2 and Policy 14 of the NPF4), impacts on/from flooding and
the water environment (Polies 52 and 53A of the LDP2 and Policy 22 of the
NPF4), residential amenity (Policy 17 of LDP2 and Policy 15 of the NPF4),
biodiversity/ecological impact (Policies 40 and 41 of the LDP2 and Policy 3 of the
NPF4) and transport (Policy 60A of the LDP2 and Policy 13 of the NPF4).
61 The principle of residential development is well established through the allocation
of Site H15 in LDP2 (and the previous Local Development Plan). Furthermore,
the PPP (02/01482/IPM) approved in 2016, and modified in July 2020, provides a
permission for 25 years from the original approval date; until September 2041. A
Page 89 of 160

Page 90

first phase development of 150 affordable units has already been consented to
the northwest, 108 of which have been completed. A further 159 dwellings
(16/02156/AMM) were consented for the south of the site in October 2020, and
development has commenced.
62 More recently 66 dwellinghouses have been consented through planning
approval 21/00615/AMM as revised through 23/00144/AMM, 23/00145/AMM,
23/00146/AMM and 25/00039/FLL and development has also commenced.
63 The principle of residential development is thus established. It is, however,
necessary to undertake an assessment of the detail of this proposal.
Phasing and Delivery
64 As advised by both Transport Scotland and PKC Transportation and
Development, the current proposal, if constructed after or in tandem with the
16/02156/AMM approval, could reach or exceed the 348-dwelling trigger in
Condition 6 of the modified PPP for the delivery of the M90 slip road junctions.
Condition 8 recommended within this application is worded to remind the
applicant of their obligation for these works to be carried out should this phase
trigger the number of dwellings specified.
65 There are other infrastructure and phasing matters that are provided for within the
Section 75 Legal Agreement secured as part of the PPP application. Also, in
conjunction with this, the approved Phasing Plan submitted under 16/02156/AMM
and to be revised through condition 2, several clauses and triggers for the
approval of detailed matters were included. The current proposal requires the
following to be met:
66
 Clause 8.2: Structural Planting for each development parcel. This is
proposed to be delivered in conjunction with this application.
 Clause 10.3.2: Construct and practically completion or procure the
construction and practical completion of the bridge over the rail line linking it
with the identified area for the primary school. It makes sense to start
providing the required bridge in tandem with approval of this site
incorporating 23/00145/AMM, 23/00146/AMM and 25/00039/FLL as
construction activity will be in the same area. Once the bridge is complete
this will in turn trigger the construction of the first phase of the required
primary school (Clause 10.3.4).
 Clause 11: Education Contributions. The first education contribution will be
required to be paid before any open market dwelling can be occupied.
67 Delivery of the bridge must be provided no later than the completion of this
phase, incorporating planning applications 23/00145/AMM, 23/00146/AMM and
25/00039/FLL and will need permission in its own right plus other technical
Page 90 of 160

Page 91

approvals. The bridge over the rail line will be a significant milestone for the
development of Oudenarde, as it will open up the site for further development
proposals, including the primary school, village centre, sports pitches etc. It will
also provide the residents of the existing affordable housing development with
improved and quicker access to the M90 and beyond.
Design, Density, Layout and Visual Amenity
68 Through Creating Places 2013, the Scottish Government signaled the
importance they attach to achieving improvements in the design and quality of
new development and bringing long-term benefits to the urban and rural
environment. It should be noted that good design should be the aim of everyone
in the planning and development process, with it being important at all scales of
development.
69 Further Designing Streets, published in 2010 by the Scottish Government
suggests that streets should be designed as social spaces, being well-connected
at all levels. It aims to move away from vehicle dominated road layouts in favour
of streets designed for people that achieve a sense of place, producing
interesting and useable street layouts.
70 In terms of site layout, permeability of places is a crucial component of good
street design. Whilst internal permeability is important, any development should
also be properly connected with adjacent areas. A development with poor links
to the surrounding area creates an enclave which encourages movement to and
from it by car rather than by other modes. In this case, this application together
with planning approvals 23/00145/AMM and 23/00146/AMM, is considered to be
a highly permeable and well-connected site, within the approved Oudenarde
Masterplan area and also the wider locality, including Bridge of Earn. In terms of
cycling and pedestrian connection, it will link up with both existing networks and
future infrastructure required to be delivered by the Section 75 legal agreement.
The proposal therefore accords with the National Roads Development Guide
2014, NPF4 Policy 20 – Blue and Green Infrastructure, LDP2 Policy 42 – Green
Infrastructure, NPF4 Policy 13 Sustainable Transport and Policy 60 - Transport
Standards and Accessibility Requirements.
71 When considering the layout of any new development, one of the most important
issues to consider is creating the opportunity for natural surveillance. In this
context buildings, spaces and pedestrian routes should be located to maximise
natural observation from pedestrians and passing motorists. Active frontages
should be encouraged wherever possible, i.e., doors leading onto the street and
windows overlooking all public areas. As such, the proposed layout takes
cognisance of Designing Streets and incorporates appropriate natural surveillance
of all areas of space and the main pedestrian routes. The site contains shared
surfaces that help achieve a sense of place and provides several linkages to
ensure the site is extremely permeable for all modes of transport especially
pedestrians and cyclists with existing and future path connections to Bridge of
Page 91 of 160

Page 92

Earn. The proposal is in line with PAN 77 – Designing Safer Places, NPF4 Policy
14 – Design, Quality and Place and LDP2 Policy 1 – Placemaking.
72 The proposal consists of 43 dwellinghouses in a mix of two storey, single storey,
detached, semi-detached and terraced. The housing mix is largely two storey
units with 5 bungalows proposed at the northern edge of the site ranging from 2–5
-bedroom dwellings. The housing mix offered here together with the mix for
planning approvals 23/00145/AMM, 23/00146/MM and the wider masterplan site
likely to come forward provides added choice for house purchasers. It is
therefore considered to comply with LDP2 Policy 25 – Housing Mix.
73 In terms of materials, an acceptable palette of materials is proposed. The
Applicant proposes finishes of white drydash render, grey facing brick and base
course, and smooth grey roof tiles. This will deliver a reasonably consistent
design approach with Phase 1 and the first approval of Phase 2A
(16/02156/AMM) and will help integrate the development into the locale.
74 The massing and scale of the dwellings can be accommodated within the plots
without having an adverse impact on the amenity of each other. As a result of the
site’s location at the edge of a settlement, it is considered that the proposed
density is acceptable and is in line with the approved masterplan.
75 In terms of the impact on visual amenity of the area, a residential development
will inevitably change the visual appearance of the area, however, the application
site has been identified for residential use in the LDP, therefore, this degree of
change was envisaged in the site allocation and permission granted under the
PPP.
76 Overall, this phase is in line with the approved masterplan, phasing plan and S75
legal agreement associated with the PPP. The proposal will provide a mix of
open market housing within the overall site that complies with NPF4 Policy 14 –
Design, Quality and Place, NPF4 Policy 16 – Quality Homes, LDP2 Policy 1 –
Placemaking, Policy 25 – Housing Mix and Placemaking Guidance 2020.
Landscape, Open Space and Recreation Provision
77 The approved PPP masterplan looks to provide a wide range of open space play
area and sports pitches to meet the needs of the existing and future residents.
78 Landscape buffers are proposed to the southern boundary and western
boundaries, however, it is noted that the extent of planting has been reduced
when compared to that previously approved through 21/00615/AMM and
23/00144/AMM. There is no requirement to provide a play park within this phase
of the development. Within the approved PPP masterplan there is a LEAP shown
in Phase 2A (R1) and in Phase 5 (R16), as well as a NEAP in Phase 4.
79 Colleagues in Community Greenspace have been consulted and commented
that some trees may be too close to private boundaries (depending on species)
Page 92 of 160

Page 93

creating future encroachment issues, therefore, a condition will be placed on any
consent insofar as an updated landscaping and tree planting plan be submitted.
80 Community Greenspace further advise that a commuted sum is required towards
adoption of the play area and open greenspace. This is however covered through
the existing section 75 legal agreement and as such no financial payment is
required at this time.
81 It is considered that the location of proposed open space and landscape buffers
are acceptable subject to condition. The proposal, therefore, complies with NPF4
Policy 21: Play Recreation, and Sport and LDP2 Policy 14 – Open Space
Retention and Provision.
Residential Amenity
Overlooking
82 All of the residential units will maintain an acceptable level of separation which
negates any potential overlooking between dwellings.
Overshadowing, loss of sunlight and daylight
83 The Building Research Establishment (BRE) document ’Site Layout Planning for
Daylight and Sunlight - a guide to good practice 1991’ sets out guidelines on how
to assess the potential impact, although it should be noted that the standards are
not mandatory and should be interpreted flexibly.
84 Taking cognisance of this BRE document, the distances between new and
existing properties, position of windows and site levels, it is considered an
acceptable level of daylight and sunlight will be provided to each property.
Overall, in terms of residential amenity the proposal complies with NPF4 - Policy
14: Design, Quality and Place and LDP2 Policy 1 – Placemaking and the
Placemaking Guidance 2020.
Roads and Access
85 The Council’s Transportation and Development Team were consulted as part of
this application and following the submission of further information, have no
objection to offer, subject to the conditions that were attached to the previous
permission being re-applied (conditions 3-10).
86 Overall, the proposal complies with NPF4 Policy 13 Sustainable Transport and
LDP2 Policy 60 Transport Standards and Accessibility Requirements.
Drainage and Flooding
87 The site is not located within a recorded area of flood risk. As the site topography
is flat and predominantly clay, drainage details have been submitted and have
Page 93 of 160

Page 94

been assessed by the Council’s Structures and Flooding Team. No objections
have been raised, therefore, the proposal complies with NPF4 Policy 22 – Flood
risk and water management, LDP2 Policy 52 – New Development and Flooding
and Policy 53 – Water Environment and Drainage.
Natural Heritage and Biodiversity
88 An updated Preliminary Ecological Appraisal Report (PEAR) April 2025 has been
submitted and the Council’s Biodiversity Officer has found this to be acceptable
as the methods are in accordance with published best practice and survey was
undertaken at the correct time of year.
89 NPF4 Policy 3 b) iv requires major developments to provide significant
biodiversity enhancements in addition to any proposed mitigation, including
nature networks and linking to and strengthening habitat connectivity within and
beyond the development. 
90 The submitted PEAR mentions the NatureScot Developing with Nature
Guidance, but it should be noted this guidance is for local developments and
NPF4 Policy 3c. 
91 For Major planning applications, we require conclusions from the PEAR and
requirements detailed in the PKC Planning for Nature Supplementary Guidance
be used to create a Site Biodiversity Action Plan. It should contain quantity,
locations, techniques, timescales, and monitoring arrangements. The submission
of a Biodiversity Action Plan (BAP) can be secured through condition.
92 Section 5 of the PEAR recommends provision of hedgehog highways, however,
the submitted timer fence detail plan (drawing number 15) show the gaps are not
large enough to allow hedgehog passage. The recommendations in the PEAR
need to match up with drawings otherwise they will not be realised on site. An
updated timber fence detail plan is required, however, this can be controlled by
condition. Furthermore, wildlife kerbs installed adjacent to all road gullies within
500m of a SuDS Pond are required, which will be secured through condition:
93 Subject to a number of biodiversity conditions (13 to 20), the proposal complies
with NPF4 Policy 3 and LDP2 Policy 41 – Biodiversity.
Archaeology
94 PKHT have confirmed that, whilst they have no records, the area may contain
archaeology. However, as this is an AMSC application it is not an appropriate
stage of the planning process to request new archaeological investigations or
conditions to be applied. However, an informative note could be added to the
decision notice to make sure the developers are aware that should any
archaeology be found during construction that they report it to Perth and Kinross
Heritage Trust (Informative 5).
Page 94 of 160

Page 95

Low and Zero Carbon Generating Technologies
95 LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in
New Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of
low and zero-carbon generating technologies. As this proposal includes the
erection of a new building, consideration must be given to this requirement.
Further, NPF4 Policy 2 ‘Climate Mitigation and Adaptation’ requires that
development should be designed to reduce green gas emissions.
96 In this instance the proposal includes ASHPs for all two storey properties,
however, the 5 bungalows have been revised to remove the ASHPs and as such
are unlikely to meet the 10%. The sustainability design statement submitted
states that the proposed design includes 100% low energy lighting, double
glazed UPVC windows and external doors with low u-values, continuous running
extract ventilation, well insulated building fabric, including roof, ground floor,
external wall construction and “A rated whited goods. The submitted statement
further specifies that the houses have been designed to allow compliance with
Section 6 of the Scottish Domestic Building Standards to reduce the overall
consumption and C02 emissions.
97 Following discussion with the agent the sustainability design statement was
revised to include solar PV for the 5 bungalows in order to meet the 10%
requirement as set out in Policy 32. To ensure compliance, a condition (condition
21) will be added to any approval as revised drawings will be required for the
relevant house types to include the solar panels.
Waste
98 The Council’s Waste Services team have provided comment to ensure all
properties have the required number and type of bins and that there should be
adequate space within each property. Condition 3 will ensure that the road
network will be able to accommodate refuse vehicles servicing the development.
A recycling centre is proposed in the north-eastern corner (planning application
reference 23/00146/AMM). An informative will ensure the collection of waste will
address the bin requirements (Informative 16).
Developer Contributions including Affordable Housing
99 The site has existing planning permission in principle PPP under 02/01482/IPM
principle and an associated ‘phasing and delivery plan’. The associated S75
Legal Agreement established the developer contribution requirements and
payment time scales.
100 The proposed plot remix will result in an additional nine units, however, as there
are further phases to come forward there are no additional developer contribution
requirements, however, if additional units result in a requirement to increase the
Page 95 of 160

Page 96

overall capacity of phase 2A, a variation to the phasing and delivery plan would
be required to balance all other phase capacities and revisit relevant planning
obligations.
101 As part of the overall development of Oudenarde, there is a requirement to
provide 300 affordable houses. Hillcrest Housing Association have permission for
150 affordable houses (planning approvals 05/00410/FUL and 08/01458/FUL), of
which 108 dwellinghouses have been constructed with 42 still to be built under
the 08/01458/FUL application. GS Brown has transferred further land to Hillcrest
Housing Association which can accommodate a further 150 affordable houses
and this will, in time, satisfy the affordable housing requirement for the overall
development. However, planning permission is not yet in place for these
remaining units. It is accepted that affordable housing is not therefore required
within this proposed phase.
Health Care
102 The site is allocated in LDP2 for 1,600 dwellings and NHST (National Health
Service Trust) were formally consulted during the plan-making process.
However, neither NHST nor the HSCP (Health and Social Care Partnership)
provided feedback at the time of the site being allocated within LDP2. In any
case, as this is an application for 43 dwellings from within the 1,600 dwelling
allocation the impact on local infrastructure has been accounted for. Also, the
approved PPP masterplan provides a local centre, which could include health
and social care facilities (doctors and dentist) at a later phase. In the longer term
it is anticipated that a new health care centre will be provided and the NHST will
be consulted prior to the delivery of a new centre.
103 For the reasons discussed above, it is appropriate to consider this application
within the parameters of LDP2 and the plan process. The development of the
overall site should be assessed based on the requirements of LDP2 Policy 5 and
the H15 Site Specific Requirements and, within the identified capacity range, it is
not possible to seek developer contributions for health infrastructure.
Economic Impact
104 The development of 43 dwellinghouses will provide jobs directly and indirectly
during construction and afterwards will have a positive impact through
homeowners spending on local goods and services in the local economy and
further afield. Both will have a positive impact on the local area.
Variation of Application Under Section 32A
105 This application was varied prior to determination, in accordance with the terms
of section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended.  The variations incorporate changes to the layout, housing mix,
boundary treatments and landscaping.
Page 96 of 160

Page 97

Legal Agreements
106 The site has planning permission in principle (ref. 02/01482/IPM). The associated
S75 legal agreement confirms the developer contribution requirement including,
phasing; affordable housing provision, primary school provision and education
contributions; community infrastructure provision and commuted maintenance
payment.
Direction by Scottish Ministers
107 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.
Conclusion and Reasons for Recommendation
108 Section 25 of the Act requires that determination of the proposal should be made
in accordance with the provisions of the Development Plan unless material
considerations indicate otherwise. The proposal seeks detailed permission for
development on an allocated site. The proposal is consistent with the objectives
of the Development Plan and the approved PPP and masterplan for the site.
109 Residential development at Oudenarde is a long-standing committed
development site and allocated in LDP2. The site is well placed to deliver a new
sustainable community, serving as a well-connected satellite settlement to Perth.
This phase and the overall site will provide a significant contribution toward
meeting the projected population growth of Perth and Kinross.
110 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly the proposal is recommended for approval
subject to the following conditions.
Recommendation 
Approve the application subject to the following conditions:
Conditions and Reasons for Recommendation
General
1. The development hereby approved must be carried out in accordance with the
approved drawings and documents, unless otherwise provided for by conditions
imposed by this decision notice.
Page 97 of 160

Page 98

Reason: To ensure the development is carried out in accordance with the
approved drawings and documents.
Phasing
2. Prior to the commencement of development a revised detailed phasing strategy
(supported by appropriate plans) shall be submitted to and approved in writing by
the Council as Planning Authority. The phasing strategy shall include the
following details:
(i) The timing and number of dwellings to be developed in each phase;
(ii) The timing and delivery of infrastructure, open space and landscaping;
(iii) The timing and location of any temporary construction compound.
Once approved, the development shall proceed in accordance with the approved
delivery phasing strategy to the satisfaction of the Council as Planning Authority.
Reason: In order to ensure the satisfactory implementation and completion of the
development.
Roads and Transport
3. Prior to the occupation of any dwellinghouse, all matters regarding access, car
parking, road layout, design, and specification, including the disposal of surface
water, shall be in accordance with the standards required by the Council as
Roads Authority.
Reason: In the interest of vehicle and pedestrian safety and in accordance with
the policies of the adopted Development Plan.
4. Prior to the occupation of the 10th dwellinghouse hereby approved, all footpaths
and cycleways shall be finished in accordance with the details, as agreed in
drawing number 30, and shall thereafter be maintained for the life of
development.
Reason: In the interest of pedestrian and cycle safety.
5. Prior to the occupation of the first dwellinghouse hereby approved, the developer
shall provide and install on appropriate hard stand asphalt areas, within the
existing lay-bys on the A912 (east of the roundabout entrance junction) two 3
Bay enclosed bus shelters (Cairngorm style) supplied and installed with
passenger information board, LED spotlights (one per bay), a 28in Ultra-Wide
Display Screen for Real Time Passenger Information installed on the approach
side of the shelter and a 24/7 electrical power supply to a Haldo pillar adjacent to
the shelter to provide power for the LED lighting and Real Time Passenger
Information display.  The design, siting and specification shall be agreed in
writing with the Council as Planning Authority, in consultation with Perth &
Kinross Council’s Public Transport Unit, prior to works commencing.  In the event
Page 98 of 160

Page 99

that it is not possible to install at this location, an alternative shall be agreed in
writing with the Planning Authority.
Reason: In the interest of sustainable travel.
6. Prior to commencement of any development on site, the street lighting design
must be submitted for the further written agreement of the Council as Planning
Authority, in consultation with Perth & Kinross Council's Street Lighting
Partnership for the public road network.  The scheme shall include details of light
spill, brightness of the lighting and the proposed hours of operation for both the
public road network and the private areas, and timescales for delivery.  The
agreed lighting scheme shall be implemented as part of the site development and
maintained in full accordance with the agreed scheme.
Reason: In the interests of road safety and to ensure suitable lighting.
7. Prior to the commencement of the development hereby approved, the
developer shall submit for the further written agreement of the Council as
Planning Authority, in consultation with the Roads Authority (Structures), a
Construction Traffic Management Scheme (TMS) which shall include the
following:
(a) restriction of construction traffic to approved routes and the measures to
be put in place to avoid other routes being used;
(b) timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse
collection is undertaken, on Sundays and during local events;
(c) a code of conduct for HGV drivers to allow for queuing traffic to pass;
(d) arrangements for liaison with the Roads Authority regarding
winter maintenance;
(e) emergency arrangements detailing communication and
contingency arrangements in the event of vehicle breakdown;
(f) arrangements for the cleaning of wheels and chassis of vehicles to
prevent material from construction sites associated with the development
being deposited on the road;
(g) arrangements for cleaning of roads affected by material deposited
from construction sites associated with the development;
(h) arrangements for signage at site accesses and crossovers and on roads
to be used by construction traffic in order to provide safe access for
pedestrians, cyclists and equestrians;
(i) details of information signs to inform other road users of construction traffic;
(j) arrangements to ensure that access for emergency service vehicles are
not impeded;
(k) co-ordination with other significant developments known to use
roads affected by construction traffic;
(l) traffic arrangements in the immediate vicinity of temporary
construction compounds;
Page 99 of 160

Page 100

(m) the provision and installation of traffic counters at the applicant's expense
at locations to be agreed prior to the commencement of construction;
(n) monitoring, reporting and implementation arrangements;
(o) arrangements for dealing with non-compliance; and
(p) details of HGV movements to and from the site.
The TMS as approved shall be strictly adhered to during the entire site
construction programme.
Reason: In the interests of road safety
8. No more than 348 residential dwellings at Oudenarde shall be constructed prior
to the completion of modifications to the existing M90 / A912 priority-controlled
interchange, generally as illustrated on TA Millard Drawing No. 3167/03/418 and
3167/03/419, unless otherwise agreed in writing with the Planning Authority,
following consultation with Transport Scotland.
The number of residential dwellings covered by this application, together with the
number of residential dwellings previously approved in terms of consent
reference 05/00410/ FUL (75 dwellings), 08/01458/FUL (75 dwellings) and
16/02156/AMM (159 dwellings) and constructed, shall not exceed that
aforementioned 348 residential dwellings threshold applying in terms of this
aforementioned Modified IPM Decision.
Reason: To ensure provision of adequate road infrastructure improvement works,
in the interest of pedestrian and road safety.
9. Development shall not commence until a detailed Travel Plan (TP), aimed at
encouraging more sustainable means of travel, has been submitted to and
agreed in writing by the Council as Planning Authority.  The TP will have
particular regard to provision for walking, cycling and public transport access to
and within the site and will identify the measures to be provided (including the
provision of new and/or enhanced public transport services), any phasing, the
system of management, monitoring, review, reporting and the duration of the
Plan.  The TP as agreed shall be fully implemented.
Reason: To promote sustainable transport options and to meet advice within
National Planning Framework on transport.
10. No obstruction of any kind shall be placed, including fencing or vegetation, within
adoptable service strips, for the life of the development.
Reason: In the interests of the ability to maintain services.
Landscape
11. Prior to the commencement of the development hereby approved, an updated
detailed landscaping and planting scheme together with a tree planting plan for
Page 100 of 160

Page 101

the site shall be submitted for the written agreement of the Council as Planning
Authority.  The scheme shall include details of the height and slopes of any
mounding or recontouring of the site, full details of all hard landscaping proposals
including materials and installation methods and, species, height, size and
density of trees and shrubs to be planted.  The scheme as subsequently
approved shall be carried out and completed within the first available planting
season (October to March) after the completion or bringing into use of the
development, whichever is the earlier, and the date of Practical Completion of the
landscaping scheme shall be supplied in writing to the Council as Planning
Authority within 7 days of that date.  The scheme as agreed and implemented
shall thereafter be maintained in line with the agreed specification.
Reason: In the interests of visual amenity; to ensure a satisfactory standard of
local environmental quality and in pursuance of suitably satisfying placemaking
policy criteria of the adopted Development Plan.
12. Any planting failing to become established within five years shall be replaced in
the following planting season with others of similar sizes and species.
Reason: In the interests of visual amenity; to ensure a satisfactory standard of
local environmental quality and in pursuance of suitably satisfying placemaking
policy criteria of the adopted Development Plan.
Biodiversity
13. All existing trees and hedgerows shown to be retained shall be protected by
suitable fencing in accordance with BS5837 2012 (Trees in Relation to
Construction), unless otherwise agreed in writing by the Planning Authority.  The
details of the protective fencing and its location as shown in the Tree Protection
Fencing Plan, approved under planning reference 21/00615/AMM, drawing
number 30, must be installed prior to the commencement of development.  No
materials, supplies, plant, machinery, soil heaps, changes in ground levels or
construction activities shall be permitted within the protected areas without the
written agreement of the Council as Planning Authority and no fire shall be lit in
the position where the flames could extend to within 5 metres of foliage,
branches, or trunks.
Reason: to ensure adequate protection for the trees on the site during the
construction, in the interests of the visual amenity of the area.
14. No removal of hedgerows, trees or shrubs or works to or demolition of any
buildings or structures that may be used by breeding birds shall take place
between 1st March and 31st August inclusive, unless a competent ecologist has
undertaken a careful, detailed check of vegetation for active birds' nests
immediately before the vegetation is cleared and provided written confirmation
that no birds will be harmed and/or that there are appropriate measures in place
to protect nesting bird interest on site.  Any such written confirmation should be
submitted to and verified by the Council as Planning Authority.
Page 101 of 160

Page 102

Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).
15. Where it is intended to create semi-natural habitats, all species used in the
planting proposals detailed in the approved plans shall be locally native species
of local provenance unless otherwise agreed in writing with the Council as
Planning Authority.
Reason: In the interests of enhancing environmental quality and of biodiversity.
16. Prior to the occupation of each dwelling a hedgehog highway shall be installed in
garden fences by providing access gaps of 13cm x 13cm at ground level to allow
free movement of animals.
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).
17. Prior to the commencement of development all road gullies within 500m of the
SUDS pond shall have Wildlife Kerbs installed adjacent to it to allow amphibians
to pass safely.
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).
18. Bat and bird nesting boxes shall be installed on the relevant gable, in accordance
with the approved locations, shown on drawing number 29, prior to the
occupation of the relevant residential unit.
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).
19. Prior to the commencement of development the developer shall submit for the
written agreement of the Council as Planning Authority a Site Biodiversity Action
Plan. Thereafter, the agreed scheme shall be maintained in a reasonable
condition for the life of the development.
Reason: In the interests of protecting environmental quality and of biodiversity.
20. Measures to protect animals from being trapped in open excavations and/or pipe
and culverts shall be implemented for the duration of the construction works of
the development hereby approved.  The measures may include creation of
sloping escape ramps for animals, which may be achieved by edge profiling of
trenches/excavations or by using planks placed into them at the end of each
Page 102 of 160

Page 103

working day and open pipework greater than 150 mm outside diameter being
blanked off at the end of each working day.
Reason: In order to prevent animals from being trapped within any open
excavations.
Environmental Impact
21. Prior to the commencement of development hereby approved, a scheme shall
be submitted to, and approved in writing by, the Council as Planning Authority
that demonstrates how at least 10% of the current carbon emissions reduction
set by the Scottish Buildings Standards will be met through the installation and
operation of low and zero-carbon technologies.  This scheme shall detail for
each building:
a) the technology types;
b) illustrate, through technical calculations, that these will meet at least the
10% reduction;
c) their siting and location; and
d) ongoing operation and maintenance.
Once approved, the development shall be completed in accordance with the
approved scheme and no individual unit shall be occupied until the scheme has
been installed and operating.
Reason: To embed low and zero-carbon technologies within the development in
the interest of environmental sustainability.
22 Prior to the commencement of development of each phase a Construction
Environmental Management Plan (CEMP) must be submitted for the approval
of the Planning Authority. The measures outlined in the agreed CEMP shall be
adhered to at all times during the construction period.
Reason: In the interests of protecting environmental quality and of biodiversity.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Procedural Notes
None.
Informatives
1. Applicants are advised that the development granted under this Approval of
Matters Specified in Conditions must be commenced not later than 25 years from
Page 103 of 160

Page 104

the date on which Planning Permission in Principle (02/01482/IPM) was granted
which was in this case 8th September 2016.
2. Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
planning authority prior written notification of the date on which it is intended to
commence the development. A failure to comply with this statutory requirement
would constitute a breach of planning control under section 123(1) of that Act,
which may result in enforcement action being taken.
3. As soon as practicable after the development is complete, the person who
completes the development is obliged by section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the planning authority written
notice of that position.
4. This development will require the 'Display of notice while development is carried
out', under Section 27C(1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013. The form of the notice is set out in Schedule 7 of
the Regulations and a draft notice is included for your guidance. In accordance
with Regulation 41 the notice must be:
 Displayed in a prominent place at or in the vicinity of the site of the
development
 Readily visible to the public
 Printed on durable material.
5. The developer is advised to contact Perth and Kinross Heritage Trust (tel 01738
477027), to discuss terms of reference for work required.
6. The applicant is advised that in terms of Sections 21 of the Roads (Scotland) Act
1984 they must obtain from the Council as Roads Authority Road Construction
Consent (RCC) to construct a new road prior to the commencement of
roadworks.  Advice on the disposal of surface water must be sought at the initial
stages of design from Scottish Water and the Scottish Environmental Protection
Agency.  Please note that a fee is chargeable for the processing of RCC
applications.
7. Application for a new postal address should be made via the Street Naming and
Numbering page on the Perth & Kinross Council website at www.pkc.gov.uk/snn.
Please note there is a charge for this service and submission cannot be made
until the relevant Building Warrant has been approved.
8. The applicant is advised that the granting of planning permission does not
guarantee a connection to Scottish Water’s assets. The applicant must make a
separate application to Scottish Water Planning & Development Services team
for permission to connect to the public wastewater system and/or water network
and all their requirements must be fully adhered to.
Page 104 of 160

Page 105

9. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive. Trees and scrub are present on the application site and are to
be assumed to contain nesting birds between the above dates. The applicant is
reminded that, under the Wildlife and Countryside Act 1981, as amended
(section 1), it is an offence to remove, damage or destroy the nest of any wild
bird while that nest is in use or being built. Planning permission for a
development does not provide a defence against prosecution under this Act.
10. No work shall be commenced until an application for building warrant has been
submitted and approved.
11. The applicant is reminded that this site is still subject to a Section 75 Legal
Agreement, securing Developer Contribution requirements and other matters, as
secured as part of planning permission 02/01482/IPM. This permission continues
to be tied by this legal agreement and the associated requirements will continue
to apply. A copy is available to view on the Council’s Public Access portal.
12. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request. 
The Fees Charter is available on our website www.pkc.gov.uk. The Council has
two months(or four months in the case of a major application) to consider the
information.  You should therefore submit the required information more than two
months (or four months) before your permission expires.  We cannot guarantee
that submissions made within two months (or four months) of the expiry date of
your permission will be able to be dealt with before your permission lapses.
13. The applicant is advised that any proposed signage will require a further
application to be submitted for advertisement consent unless it benefits from
express consent as per the Town and Country Planning (Control of
Advertisements) (Scotland) Regulations 1984.
14. The applicant is reminded to discuss with the Council's Transport Unit the supply
of a bus service and public transport infrastructure to ensure an adequate public
transport provision for the site.
15. The applicant is advised that technical approval will be required for all street
lighting apparatus within adoptable areas, including the access road onto the
A912, and should contact the Street Lighting Partnership to obtain technical
approval prior to the submission of a Road Construction Consent application.
16. Refuse collection vehicle will only enter the site during development where there
is clear access, adequate turning and a suitable road surface with no raised
ironworks. This means that Waste Services may not be able to provide a full
Page 105 of 160

Page 106

kerbside recycling service to residents whilst the build is ongoing and bins may
have to be emptied from a collection point, specified by the area Community
Waste Adviser, until full access is made available for refuse collection vehicles.
The developer must contact the Community Waste Team to discuss bin
collection as the site progresses.
17. The applicant should be aware of the requirements of the Council's Environment
and Regulatory Services in relation to waste collection from the site and should
ensure adequate measures are provided on site to allow for the collection of
waste.
18. The applicant is advised that Perth and Kinross Council have a charging scheme
for recycling and waste bins for new build properties and newly created
dwellings. Further information can be found at:
https://www.pkc.gov.uk/binrequests
19. The applicant is reminded that, should any protected species be present a
licence may be required from NatureScot. Failure to obtain a licence may
constitute a criminal act under the Habitats Regulations and penalties are sever
for non-compliance.
20. This application was varied prior to determination, in accordance with the terms
of section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended.  The variations incorporate changes to the layout, housing mix,
boundary treatments and landscaping.
Background Papers
Letters of representation 0
Authors
Name Designation Contact Details
Gillian Peebles Planning Officer 01738 475300
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
30 April 2025
Page 106 of 160

Page 107

Ü
Erection of 43 dwellinghouses, landscaping and associated infrastructure (approval of matters specified in
conditions of 02/01482/IPM on land to the North of A912 At Oudenarde Bridge Of Earn
24/01961/AMM
Scale
1:15,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(iii)
Page 107 of 160

Page 108

Page 108 of 160

Page 109

Ü
Erection of 43 dwellinghouses, landscaping and associated infrastructure (approval of matters specified in
conditions of 02/01482/IPM on land to the North of A912 At Oudenarde Bridge Of Earn
24/01961/AMM
Scale
1:5,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(iii)
Page 109 of 160

Page 110

Page 110 of 160

Page 111

Perth and Kinross Council
Planning and Placemaking Committee – 14 May 2025
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 25/120)
Proposal: Erection of 38 dwellinghouses and 4 flats and associated works
(approval of matters specified in conditions of 16/01809/IPM Phase
2a)
Location: Land 40 metres north of 51 Castle Drive, Auchterarder, PH3 1FU
Ref. No: 24/01757/AMM
Ward No: P7- Strathallan
Summary
This report recommends approval of a Matters Specified in Conditions (AMSC)
application related to the Castlemains area of the Auchterarder Expansion
Development Framework. The application proposes details for the development of 38
dwellinghouses and four flats, together with associated landscaping, SUDS, and
other works. This Report concludes that the proposal is consistent with the
Development Plan and the existing Planning Permission in Principle (PPP) (Ref:
16/01809/IPM). There are no material considerations apparent which outweigh this
conclusion.
Background and Description of Proposal
1 The site is situated on the northern edge of Auchterarder, beyond the Community
School to the south. It is located wholly within the wider identified extension of
Auchterarder known as Castlemains and is covered under the Auchterarder
Expansion Development Framework.
2 Immediately to the east of the site is the connected detailed residential proposal
(ref: 24/01758/FLL) with Castlemains Farm Steading with the Category C listed
Castlemains Farmhouse including castellated building (Auchterarder Castle)
(Listed Building ref: 52514), located beyond. To the south is part of the previously
developed residential extension. To the north of the site is currently open
agricultural land part of which is included within the S.75 for the wider site for the
provision of sports facilities.
5(1)(iv)
Page 111 of 160

Page 112

3 The proposal is for 38 dwellinghouses and four flats with associated SuDS and
infrastructure. Of the residential units proposed, 30 will be for sale with 12 to be
affordable homes. These dwellings comprise a mix of detached, bungalows,
terraces and flats. The numbers and tenure mix are:
 6 x five-bedroom detached dwellinghouses;
 16 x four-bedroom detached dwellinghouses;
 3 x three-bedroom detached dwellinghouses;
 5 x three-bedroom detached bungalows;
 4 x three-bedroom terraced dwellinghouses;
 4 x two-bedroom terraced dwellinghouses;
 4 x two-bedroom flats;
4 All will have access to a private external amenity area and be finished with white
or pale render, with neutral coloured masonry and roof tiles.
5 As mentioned above, a separate application from the same applicant for a
residential development has been received for the site immediately to the east.
Two applications have had to be submitted separately due to part of the smaller
adjacent proposal sitting outwith the red site boundary of the PPP for the wider
site. As a result, procedurally that application cannot be assessed as an AMSC
and has been submitted as a full local application. However, there are a number
of matters including affordable housing, SuDS and visitor parking that require the
two applications to be considered together. The specific nature of each of these
matters is considered within the relevant sections below.
Site History
6 08/01133/IPM was approved on 31 October 2013 for a proposed Residential and
Class 4 (Business), Class 5 (General Industry) & Class 6 (storage and
distribution) development (in principle)
7 08/01591/FUL Full Planning Permission was Approved On 17 October 2008 for
Formation of roads and associated infrastructure
8 16/01809/IPM was Approved On 3 August 2018 for Deletion of condition 14 (to
seek waste advice) of permission 08/01133/IPM (residential, business, general
industry and storage and distribution development (in principle)
9 16/02241/FLL Full Planning Permission was Approved On 7 June 2017 for
Erection of 31no dwellinghouses
10 17/00009/PAN On 29 November 2017 for Erection of residential development
formation of open space, landscaping and associated infrastructure works
11 18/00274/SCRN On 5 March 2018 for Phase 2 residential development
Page 112 of 160

Page 113

12 18/01591/AMM was Approved On 17 January 2019 for Erection of 116
dwellinghouses, formation of vehicular accesses, open spaces and associated
works (approval of matters specified in conditions 16/01809/IPM) (Phase 2)
13 18/01592/AMM was Approved On 24 January 2019 for Erection of 12
dwellinghouses, landscaping and associated works (approval of matters
specified by conditions 16/01809/IPM) (Phase 3A)
14 19/00907/AMM was Approved On 23 October 2019 for Formation of
neighbourhood equipped area for play (NEAP) (approval of matters specified in
conditions of 16/01809/IPM) Phase 3B
15 20/01513/AMM was Approved On 15 December 2020 for Erection of 29
dwellinghouses, 5 garages and associated works (revised design and change of
house type for plots 27-30, 36, 43, 82, 89, 107, 109, 120, 121-129, 130-137 and
139)
16 24/01758/FLL Full Planning Permission for Erection of 6 dwellinghouses,
landscaping and associated infrastructure (Phase 2A)
Pre-Application Consultation
17 The proposed development is an Approval of Matters Specified in Conditions
(AMSC) for which Planning Permission in Principle (PPP) has previously been
granted. As a result, the applicant was not required to undertake not any formal
pre-application consultation with the local community on this application.
Development Plan
18 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.
National Planning Framework 4
19 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve people’s lives by making sustainable, liveable
and productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.
20 The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 13: Sustainable Transport
Page 113 of 160

Page 114

 Policy 14: Design, Quality and Place
 Policy 15: Local Living and 20 Minute Neighbourhoods
 Policy 16: Quality Homes
 Policy 18: Infrastructure First
 Policy 22: Flood Risk and Water Management
Perth and Kinross Local Development Plan 2019
21 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
22 The principal relevant policies are, in summary;
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 1C: Placemaking
 Policy 1D: Placemaking
 Policy 2: Design Statements
 Policy 5: Infrastructure Contributions
 Policy 14B: Open Space Retention and Provision: Open Space within New
Developments
 Policy 17: Residential Areas
 Policy 20: Affordable Housing
 Policy 23: Delivery of Development Sites
 Policy 25: Housing Mix
 Policy 26B: Scheduled Monuments and Archaeology: Archaeology
 Policy 27A: Listed Buildings
 Policy 32: Embedding Low & Zero Carbon Generating Technologies in New
Development
 Policy 41: Biodiversity
 Policy 52: New Development and Flooding
 Policy 53B: Water Environment and Drainage: Foul Drainage
 Policy 53C: Water Environment and Drainage: Surface Water Drainage
 Policy 53E: Water Environment and Drainage: Water Supply
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
Statutory Supplementary Guidance
23
 Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2023)
 Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
Page 114 of 160

Page 115

 Supplementary Guidance - Open Space Provision for New Developments
(adopted in 2021)
 Supplementary Guidance - Placemaking (adopted in 2020)
PKC Non Statutory Guidance
24
 Planning Guidance - Delivery of Development Sites
 Planning Guidance - Planning & Biodiversity
National Guidance
25 The Scottish Government expresses its planning policies through Planning
Advise Notes, Creating Places, Designing Streets, National Roads Development
Guide and a series of Circulars in addition to NPF4.
Planning Advice Notes
26 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:
 PAN 61 Planning and Sustainable Urban Drainage Systems
 PAN 68 Design Statements
 PAN 69 Planning and Building standards Advice on Flooding
 PAN 75 Planning for Transport
Creating Places 2013
27 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places.
Designing Streets 2010
28 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places.
National Roads Development Guide 2014
29 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision.
Page 115 of 160

Page 116

Consultations
30 As part of the planning application process the following bodies were consulted:
Internal
31 Structures and Flooding: Initially requested further information on SuDS
maintenance and adoption which has been provided. No objections.
32 Transportation and Development: Initially requested further information on
visitor parking. The applicant has confirmed that the visitor parking will be
provided on the adjacent site to the west as part of application 24/01757/AMM.
No objections, subject to a condition requiring a Construction Traffic
Management Plan.
33 Contaminated Land: No objection. A site investigation was carried out in 2008
which covered the wider development site and includes the area outlined in this
application. The site investigation did not identify any risks of contamination to
any subsequent residential developments.
34 Development Contributions: The site is located within the Auchterarder
Expansion Development Framework area. A Section 75 Agreement is in place,
covering the planning obligations for the PPP area.
35 Waste: There is considered to be adequate waste provision proposed to
accommodate the requirements of the development. Waste Services has offered
no objections and have requested an informative relating to site access for refuse
collection during construction.
External
36 Perth and Kinross Heritage Trust: No archaeological mitigation is required in
this instance.
37 Scottish Water: No objections. There is sufficient capacity for a foul only
connection in the Auchterarder Waste Water Treatment works to service the
development. It is recommended that a Pre-Development Enquiry Form is
submitted to confirm whether there is sufficient capacity within the Turret Water
Treatment Works to service the development.
Representations
38 25 representations were received. The main issues raised within the
representations are:
 Increased traffic and road safety
 Construction traffic
 Visual amenity impacts
Page 116 of 160

Page 117

 Impact on public footpath
 Previous obligations for A9 junction and playing fields have not been provided
 Impact on local services
 Loss of open space
 Noise pollution
 Over intensive development
 Loss of view
 Loss of privacy
 Neglect of adjacent listed building
39 These issues are addressed in the Appraisal section of the report.
Additional Statements
40
Screening Opinion EIA not required
Environmental Impact Assessment
(EIA): Environmental Report
not required
Appropriate Assessment under
Habitats Regulations
AA not required
Design Statement or Design and
Access Statement
submitted
Report on Impact or Potential Impact
eg Flood Risk Assessment
 Surface Water Management Plan
 Design and Access Statement
Appraisal
41 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise.  The Development Plan comprises NPF4, the Perth and
Kinross Local Development Plan 2019 and statutory supplementary guidance.
The relevant policy considerations are outlined in the policy section above and
are considered in more detail below.
Principle
42 The proposal is located on the edge of the area of the PPP (16/01809/IPM)
approved for the northern expansion of Auchterarder and identified as
Castlemains. The site is also allocated in the Local Development Plan for
housing. A number of phases of the wider AEDF have been built out in previous
years and the principle of the extension to the north of the town is well
established.
43 The principle of the development is therefore considered acceptable, provided
the proposals are compatible with the PPP and relevant policies of the
development plan. These matters are considered in detail below.
Page 117 of 160

Page 118

Design and Layout
44 Policy 14: Design, Quality and Place, Policy 15: Local Living and 20 Minute
Neighbourhoods and Policy 16: Quality Homes of NPF4 are relevant as are
LDP2 Policy 1: Placemaking, Policy 14B: Open Space within New Developments,
Policy 17: Residential Areas and Policy 25: Housing Mix.
45 The proposed layout is broadly reflective of and dictated by the site masterplan,
the development that has previously been completed on site and the adjacent
proposed phase. The design of the dwellinghouses is consistent with the
remainder of the development and will not appear out of place on the street
scene. The proposals are of an appropriate massing and scale and will be built
using the same materials as the adjacent development phases.
46 The heights of the proposed units reflect heights within the prevailing residential
context, both in terms of the existing and proposed residential areas. Proposed
site levels have been assessed and are considered satisfactory.
47 LDP2 Policy 25: Housing Mix requires 10% of homes to have two bedrooms or
less. The proposed development will provide eight two-bedroom homes across
42 dwellings which well exceeds the requirement. However, this figure requires
to be calculated to include the adjacent six-dwelling development of four-
bedroom homes (ref: 24/01758/FLL), in which case it still exceeds the minimum
requirement. Therefore, when considered together, the provision of eight two-
bedroom units over a total of 48 dwellings exceeds the requirement of the policy. 
48 Overall, the proposed layout, design, heights, and materials are considered to
appropriately reflect the surrounding character and amenity of the area, in
compliance with the Council’s placemaking policies. The proposals therefore are
considered to accord with the terms NPF4 and LDP2.
Residential Amenity
49 Some objections raise concerns on the potential impact on their residential
amenity as a result of the location of some of the new properties in relation to
their properties’ boundary. It is considered that through separation distances in
excess of 18m and angling of windows away from adjacent properties, there will
not be any significant detrimental impact on existing residential amenity.
Similarly, the layout within the site as well as the scale and height of the
proposed dwellinghouses will ensure that appropriate levels of both daylight and
sunlight will be afforded to both existing and proposed properties.
50 As is standard for residential expansions of this nature, a CEMP will be required
for the construction phase to protect residential amenity in terms of working
hours, noise, dust, construction traffic and light pollution (Condition 4).
Page 118 of 160

Page 119

Roads and Access
51 NPF4 Policy 13: Sustainable Transport seeks to encourage developments that
prioritise sustainable travel while LDP2 Policy 60 Transport Standards and
Accessibility Requirements requires consideration of transport and accessibility.
52 In total, 11 visitor parking spaces will be provided in small on-street clusters and
in parking courts to serve this development and the neighbouring 24/01758/FLL.
The provision of resident and visitor parking is considered acceptable.
53 Some objectors to the proposal have referred to the existing path that runs east-
west to the north of the site as a ‘core path’. However, this route is not a
designated core path at this location and is not afforded the associated legal
protection of a core path. Nevertheless, the path is evidently a well-used route by
local people and, once implemented, the proposal will provide connections to the
path and will not impact its use as right of way for the public.
54 Overall, the proposals are acceptable subject to a condition for a Construction
Traffic Management Plan (Condition 3).
Drainage and Flooding
55 NPF4 Policy 22: Flood risk and water management advises that development will
not be supported if it is located in a flood risk area or will be at risk of flooding.
The site is not in an area of flood risk.
56 Due to the site topography and existing surface water sewer layout, the surface
water flows will discharge to three different outlets.
Plots 601-615, 626, 641-647 and Associated Roads
57 The surface water flows from these plots and associated roads will discharge to
the existing surface water sewers & detention basin that was constructed as part
of a previous phase to the south (ref: 18/01892/AMM). The existing surface water
sewers and detention basin were sized to discharge the surface water flows from
these plots and associated roads.
Plots 616-625 and Associated Roads
58 The surface water flows from these plots and associated roads will discharge to
an existing surface water sewer that was diverted as part of the previous phase
sewer construction. Surface water attenuation and treatment will be provided
within each of the individual plots, along with an at source SuDS for roads.
Page 119 of 160

Page 120

Plots 627-633 and 639-640 and Associated Roads
59 The surface water flows from these plots and associated roads will discharge
onto a new surface water sewer and detention basin located to the north-east of
the proposed development as part of 24/01758/FLL.
60 Overall, the proposal complies with NPF4 Policy 22: Flood Risk and Water
Management and LDP2 Policy 52: New Development and Flooding and
Policy 53: Water Environment and Drainage.
Conservation Considerations
61 The local development site to the east will act as buffer between the proposal
and the Category C listed Castlemains Farmhouse and Auchterarder Castle,
which in turn sit beyond Castlemains Farm Steading to the east. The proposal
will have no impact on the special interest of the listed building or its setting.
62 Perth and Kinross Heritage Trust has been consulted on the proposal and
advised that previous archaeological evaluation work has taken place as part of
earlier phases of development. Therefore, no archaeological mitigation is
required in this instance.
Natural Heritage and Biodiversity
63 In relation to natural heritage and biodiversity, NPF4 Policies 1: Tackling the
Climate and Nature Crisis, 2: Climate Mitigation and Adaptation 3: Biodiversity
and 20: Blue and Green Infrastructure, are relevant. In addition, LDP2 Policies 41
and 42 apply.
64 The site is brownfield and currently has limited biodiversity value. NPF4 requires
local planning applications to include appropriate measures for biodiversity
enhancement that are proportionate to the nature and scale of the development. 
65 Biodiversity enhancement is proposed through tree planting and soft
landscaping. Planting includes Scottish native species, fruit bearing trees and a
mixed native hedge. There is scope for further biodiversity enhancement to align
with PKC’s Planning for Nature: Development Management and Wildlife Guide
through the provision of swallow nest cups, swift nesting bricks and wildlife kerbs.
A condition is proposed to secure the implementation of additional biodiversity
enhancements (Condition 5).
Low and Zero Carbon Generating Technologies
66 LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in
New Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of
low and zero-carbon generating technologies. As this proposal includes the
Page 120 of 160

Page 121

erection of new buildings, consideration must be given to this requirement.
Further, NPF4 Policy 2 ‘Climate Mitigation and Adaptation’ requires that
development should be designed to reduce green gas emissions. In this
instance, solar PV panels will be fitted to all properties, with low energy lighting
and high efficiency appliances also installed. The proposal therefore complies
with the relevant policies.
Developer Contributions
67 NPF4 Policy 18: Infrastructure First and LDP2 Policy 5: Infrastructure
Contributions requires consideration of the individual or cumulative impact of new
development on infrastructure and facilities and to secure contributions to
address this impact where the development exacerbates impacts or generates
additional need.
68 There is an existing S.75 obligation for the wider development site, which will be
directly applicable to this application. The S.75 requires, amongst other things,
the provision of a new junction at Shinafoot to the east of Auchterarder and
sports facilities for the development. The S.75 includes a cap on the number of
homes that can be built as part of the AEDF until these requirements are met.
This is a complex matter, and discussions have been ongoing with the
consortium developers with a view to seeking a suitable resolution. The situation
has been further complicated by part of the consortium, Stewart Milne Group,
being placed into administration. Muir Homes has acknowledged that, due to
these ongoing discussions, they will not currently be in a position to implement
this particular consent and are rather looking to have the consent in place and
ready to go at such time as matters pertaining to the S.75 are resolved. An
informative is recommended to be added to the permission to confirm the scope
of the S.75 (informative 1).
69 The neighbouring application 24/01758/FLL will not be bound by the terms of the
existing S.75, as it is a standalone application. However, the two applications are
inherently linked due to the joint approach to the provision of affordable housing
and other infrastructure requirements. Notwithstanding that the local application
also relates to, and forms a part of, the wider AEDF area. A new legal agreement
will therefore be required for 24/01758/FLL to ensure that the local application
will also be bound by the obligations of the existing S.75 for the wider
development.
Economic Impact
70 The impact to the local economy both during construction and occupation will be
moderate with additional available expenditure on local facilities and services.
Planning Obligations and Legal Agreements
71 As set out above, this proposal will be bound by the requirements of the existing
S.75. However, as this proposal will share some infrastructure with the
Page 121 of 160

Page 122

neighbouring site, which is not bound by the existing legal agreement, a new
legal agreement is required to ensure that obligations are secured in line with the
requirements of the wider development area. Consent shall not to be issued until
the agreement has been signed and registered to take account of this
application. The legal agreement should be concluded and completed within 4
months of the date of any approval.
Direction By Scottish Ministers
72 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.
Conclusion And Reasons For Recommendation
73 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly, the proposal is recommended for approval
subject to the following conditions.
Recommendation 
Approve subject to the following conditions:
Conditions and Reasons for Recommendation
1. This planning permission will last only for three years from the date of this
decision notice, unless the development has been lawfully started within that
period.
Reason: This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019.
2. The development hereby approved must be carried out in accordance with the
approved drawings and documents, unless otherwise provided for by conditions
imposed by this decision notice.
Reason: To ensure the development is carried out in accordance with the
approved drawings and documents.
3. Prior to the commencement of the development hereby approved, the applicant
shall submit for the further written agreement of the Council as Planning
Page 122 of 160

Page 123

Authority, in consultation with the Roads Authority (Structures), a Construction
Traffic Management Scheme (TMS) which shall include the following:
 restriction of construction traffic to approved routes and the measures to be
put in place to avoid other routes being used;
 timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse collection
is undertaken, on Sundays and during local events;
 a code of conduct for HGV drivers to allow for queuing traffic to pass;
 arrangements for liaison with the Roads Authority regarding winter
maintenance;
 emergency arrangements detailing communication and contingency
arrangements in the event of vehicle breakdown;
 arrangements for the cleaning of wheels and chassis of vehicles to prevent
material from construction sites associated with the development being
deposited on the road;
 arrangements for cleaning of roads affected by material deposited from
construction sites associated with the development;
 arrangements for signage at site accesses and crossovers and on roads to be
used by construction traffic in order to provide safe access for pedestrians,
cyclists and equestrians;
 details of information signs to inform other road users of construction traffic;
 arrangements to ensure that access for emergency service vehicles are not
impeded;
 co-ordination with other significant developments known to use roads affected
by construction traffic;
 traffic arrangements in the immediate vicinity of temporary construction
compounds;
 the provision and installation of traffic counters at the applicant's expense at
locations to be agreed prior to the commencement of construction;
 monitoring, reporting and implementation arrangements;
 arrangements for dealing with non-compliance; and
 details of HGV movements to and from the site. 
The TMS as approved shall be strictly adhered to during the entire site
construction programme.
Reason: In the interests of proper site management.
4. A Construction Environmental Management Plan (CEMP) shall be submitted
prior to the commencement of the development for the written approval of the
Planning Authority.  The CEMP shall include recommendations for the control of
working hours, noise, dust and vibration during the construction stage of the
development and once approved shall be implemented throughout the
construction phase of the development.
Reason: In the interests of protecting environmental quality.
Page 123 of 160

Page 124

5 Prior to the commencement of the development hereby approved, a Biodiversity
Enhancement Plan for the site shall be submitted.  Thereafter, the agreed
scheme shall be implemented in full prior to the completion of the development.
Reason: In the interests of protecting environmental quality and of biodiversity.
6. The detailed landscaping and planting scheme which is hereby approved shall be
completed within the first available planting season (October to March) after the
completion or bringing into use of the development, whichever is the earlier.  The
approved scheme shall thereafter be maintained to the satisfaction of the Council
as Planning Authority, with any planting which fails to become established within
five years being replaced in the following planting season with others of a size
and species as previously approved.
Reason: In the interests of visual amenity and to ensure the satisfactory
implementation of the proposed planting scheme.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Informatives
1. The applicant is advised to refer to the existing Section 75 Legal Agreement and
the implications that this agreement has with regards to commencing works, with
particular attention drawn towards the sports facilities provision and the Shinafoot
junction works.
2. Under Aection 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,
which may result in enforcement action being taken.  Please use the form
attached herewith.
3. As soon as practicable after the development is complete, the person who
completes the development is obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the Planning Authority written
notice of that position.  Please use the form attached herewith.
4. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
Page 124 of 160

Page 125

no limit to the number of conditions that can be discharged in a single request. 
The Fees Charter is available on our website www.pkc.gov.uk.  
The Council has two months to consider the information.  You should therefore
submit the required information more than two months before your permission
expires.  We cannot guarantee that submissions made within two months of the
expiry date of your permission will be able to be dealt with before your
permission lapses.
5. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive.  Trees and scrub are present on the application site and are to
be assumed to contain nesting birds between the above dates.  The applicant is
reminded that, under the Wildlife and Countryside Act 1981, as amended
(Section 1), it is an offence to remove, damage or destroy the nest of any wild
bird while that nest is in use or being built.  Planning permission for a
development does not provide a defence against prosecution under this Act.
6. The applicant should be aware of the requirements of the Council's Environment
and Regulatory Services in relation to waste collection from the site and should
ensure adequate measures are provided on site to allow for the collection of
waste.
7. The applicant is advised to refer to Perth & Kinross Council's Supplementary
Guidance on Flood Risk and Flood Risk Assessments 2021 as it contains advice
relevant to your development. https://www.pkc.gov.uk/ldp2floodrisk
8. Application for a new postal address should be made via the Street Naming and
Numbering page on the Perth & Kinross Council website at www.pkc.gov.uk/snn.
Please note there is a charge for this service and submission cannot be made
until the relevant Building Warrant has been approved.
9. No work shall be commenced until an application for building warrant has been
submitted and approved.
10. This development will require the 'Display of notice while development is carried
out', under Section 27C(1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013, as amended. The form of the notice is set out in
Schedule 7 of the Regulations and a draft notice is included for your  guidance.
In accordance with Regulation 41 the notice must be:
 Displayed in a prominent place at or in the vicinity of the site of the development
 Readily visible to the public
 Printed on durable material.
Background Papers
Letters of representation 25
Page 125 of 160

Page 126

Authors
Name Designation Contact Details
Alex Gudgeon Planning Officer (Major
Team)
01738 475300
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
30 April 2025
Page 126 of 160

Page 127

Ü
Erection of 38 dwellinghouses and 4 flats and associated works (approval of matters specified in conditions
of 16/01809/IPM Phase 2a) on land 40 metres North of 51 Castle Drive, Auchterarder
24/01757/AMM
Scale
1:15,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(iv)
Page 127 of 160

Page 128

Page 128 of 160

Page 129

Ü
Erection of 38 dwellinghouses and 4 flats and associated works (approval of matters specified in conditions
of 16/01809/IPM Phase 2a) on land 40 metres North of 51 Castle Drive, Auchterarder
24/01757/AMM
Scale
1:5,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(1)(iv)
Page 129 of 160

Page 130

Page 130 of 160

Page 131

Perth and Kinross Council
Planning and Placemaking Committee – 14 May 2025
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 25/121)
Proposal: Erection of 6 dwellinghouses, landscaping and associated
infrastructure (Phase 2A)
Location: Land 90 metres North-west of Castlemains Farm Steading,
Auchterarder, PH3 1DX
Ref. No: 24/01758/FLL
Ward No: P7- Strathallan
Summary
This report recommends approval of the application for the erection of six
dwellinghouses and associated infrastructure, within a wider development forming
part of an allocated housing site. The proposal is consistent with the relevant
provisions of the Development Plan and there are no material considerations
apparent which outweigh this conclusion.
Background and Description of Proposal
1 The site is situated on the northern edge of Auchterarder, beyond the Community
School to the south. It forms part of a wider identified extension of Auchterarder
known as Castlemains and is covered under the Auchterarder Expansion
Development Framework. The proposed development area overlaps the red site
boundary of the wider expansion area PPP.
2 Immediately to the east of the site is Castlemains Farm Steading with the
Category C listed Castlemains Farmhouse including castellated building
(Auchterarder Castle) (Listed Building ref: 52514), located beyond. To the south is
part of the previously developed residential extension with a further detailed
proposal (ref: 24/01757/AMM) located to the west. To the north of the site is
currently open agricultural land part of which is included within the S.75 for the
wider site for the provision of sports facilities.
3 The proposal is for six 4-bedroom detached dwellinghouses and an associated
SuDS basin and pumping station on a small section to the north. All of the
5(2)(i)
Page 131 of 160

Page 132

dwellings will have access to a private external amenity area and be finished with
white or pale render, with neutral coloured masonry and roof tiles.
4 As mentioned above, a separate application from the same applicant for a
residential development has been received for the site immediately to the west.
Two applications have had to be submitted separately due to part of this smaller
proposal sitting outwith the red site boundary of the PPP for the wider site. As a
result, procedurally it cannot be assessed as an AMSC and has been submitted as
a full local application. However, there are a number of matters including
affordable housing, SuDS and visitor parking that require the two applications to
be considered together. The specific nature of each of these matters is considered
within the relevant sections below.
Site History
5 08/01133/IPM was approved on 31 October 2013 for a proposed Residential and
Class 4 (Business), Class 5 (General Industry) & Class 6 (storage and distribution)
development (in principle)
6 08/01591/FUL Full Planning Permission was Approved On 17 October 2008 for
Formation of roads and associated infrastructure
7 16/01809/IPM was Approved On 3 August 2018 for Deletion of condition 14 (to
seek waste advice) of permission 08/01133/IPM (residential, business, general
industry and storage and distribution development (in principle))
8 16/02241/FLL Full Planning Permission was Approved On 7 June 2017 for
Erection of 31no dwellinghouses
9 17/00009/PAN On 29 November 2017 for Erection of residential development
formation of open space, landscaping and associated infrastructure works
10 18/00274/SCRN On 5 March 2018 for Phase 2 residential development
11 18/01591/AMM was Approved On 17 January 2019 for Erection of 116
dwellinghouses, formation of vehicular accesses, open spaces and associated
works (approval of matters specified in conditions 16/01809/IPM) (Phase 2)
12 18/01592/AMM was Approved On 24 January 2019 for Erection of 12
dwellinghouses, landscaping and associated works (approval of matters specified
by conditions 16/01809/IPM) (Phase 3A)
13 19/00907/AMM was Approved On 23 October 2019 for Formation of
neighbourhood equipped area for play (NEAP) (approval of matters specified in
conditions of 16/01809/IPM) Phase 3B
14 20/01513/AMM was Approved On 15 December 2020 for Erection of 29
dwellinghouses, 5 garages and associated works (revised design and change of
Page 132 of 160

Page 133

house type for plots 27-30, 36, 43, 82, 89, 107, 109, 120, 121-129, 130-137 and
139)
15 24/01757/AMM Approval of Matters submitted on 12 December 2024 for the
erection of 38 dwellinghouses and 4 flats and associated works (approval of
matters specified in conditions of 16/01809/IPM Phase 2a).
Pre-Application Consultation
16 The proposed development is not classed as a Major development in terms of the
Town and Country Planning (Hierarchy of Developments) (Scotland) Regulations
2009, therefore the applicant was not required to undertake any formal pre-
application consultation with the local community.
Development Plan
17 The Development Plan for the area comprises National Planning Framework 4 and
the Perth and Kinross Local Development Plan 2 (2019) along with its associated
statutory supplementary guidance.
National Planning Framework 4
18 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve people’s lives by making sustainable, liveable
and productive spaces. NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.
19 The Council’s assessment of this application has considered the following policies
of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 13: Sustainable Transport
 Policy 14: Design, Quality and Place
 Policy 15: Local Living and 20 Minute Neighbourhoods
 Policy 16: Quality Homes
 Policy 18: Infrastructure First
 Policy 22: Flood Risk and Water Management
Perth and Kinross Local Development Plan 2019
20 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
Page 133 of 160

Page 134

21 The principal relevant policies are, in summary;
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 1C: Placemaking
 Policy 1D: Placemaking
 Policy 2: Design Statements
 Policy 5: Infrastructure Contributions
 Policy 6: Settlement Boundaries
 Policy 14B: Open Space Retention and Provision: Open Space within New
Developments
 Policy 17: Residential Areas
 Policy 20: Affordable Housing
 Policy 23: Delivery of Development Sites
 Policy 25: Housing Mix
 Policy 26B: Scheduled Monuments and Archaeology: Archaeology
 Policy 27A: Listed Buildings
 Policy 32: Embedding Low & Zero Carbon Generating Technologies in New
Development
 Policy 41: Biodiversity
 Policy 52: New Development and Flooding
 Policy 53B: Water Environment and Drainage: Foul Drainage
 Policy 53C: Water Environment and Drainage: Surface Water Drainage
 Policy 53E: Water Environment and Drainage: Water Supply
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
Statutory Supplementary Guidance
22
 Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2023)
 Supplementary Guidance - Flood Risk and Flood Risk Assessments (adopted
in 2021)
 Supplementary Guidance - Open Space Provision for New Developments
(adopted in 2021)
 Supplementary Guidance - Placemaking (adopted in 2020)
PKC Non Statutory Guidance
23
 Planning Guidance - Delivery of Development Sites
 Planning Guidance - Planning & Biodiversity
National Guidance
24 The Scottish Government expresses its planning policies through Planning Advise
Notes, Creating Places, Designing Streets, National Roads Development Guide
and a series of Circulars in addition to NPF4.
Page 134 of 160

Page 135

Planning Advice Notes
25 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:
 PAN 61 Planning and Sustainable Urban Drainage Systems
 PAN 68 Design Statements
 PAN 69 Planning and Building standards Advice on Flooding
 PAN 75 Planning for Transport
Creating Places 2013
26 Creating Places is the Scottish Government’s policy statement on architecture and
place. It sets out the comprehensive value good design can deliver. It notes that
successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places.
Designing Streets 2010
27 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places.
National Roads Development Guide 2014
28 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision.
Consultations
29 As part of the planning application process the following bodies were consulted:
Internal
30 Structures and Flooding: Initially requested further information on SuDS
maintenance and adoption which has been provided. No objections.
31 Transportation and Development: Initially requested further information on
visitor parking. The applicant has confirmed that the visitor parking will be provided
on the adjacent site to the west as part of application 24/01757/AMM. No
objections, subject to a condition requiring a Construction Traffic Management
Plan.
Page 135 of 160

Page 136

32 Contaminated Land: No objection. A site investigation was carried out in 2008
which covered the wider development site and includes the area outlined in this
application. The site investigation did not identify any risks of contamination to any
subsequent residential developments.
33 Development Contributions: The site is located within the Auchterarder
Expansion Development Framework area. A Section 75 Agreement is in place,
covering the planning obligations for the PPP area.
34 Waste: There is considered to be adequate waste provision proposed to
accommodate the requirements of the development. Waste Services has offered
no objections and have requested an informative relating to site access for refuse
collection during construction.
External
35 Scottish Water: No objections. There is sufficient capacity for a foul only
connection in the Auchterarder Waste Water Treatment works to service the
development. It is recommended that a Pre-Development Enquiry Form is submitted
to confirm whether there is sufficient capacity within the Turret Water Treatment
Works to service the development.
36 Perth & Kinross Heritage Trust (PKHT): Considering the archaeological and
historic evidence and the moderate potential for remains associated with the
defence/ enclosure of the castle it is recommended that a programme of
archaeological works is undertaken to assess the presence / absence of
archaeological remains within all areas to be impacted.
Representations
37 19 representations were received. The main issues raised within the
representations are:
 Increased traffic and road safety
 Construction traffic
 Visual amenity impacts
 Impact on public footpath
 Previous obligations for A9 junction and playing fields have not been provided
 Impact on local services
 Loss of open space
 Noise pollution
 Over intensive development
 Loss of view
 Loss of privacy
 Neglect of adjacent listed building
38 These issues are addressed in the Appraisal section of the report.
Page 136 of 160

Page 137

Additional Statements
39
Screening Opinion EIA not required
Environmental Impact Assessment
(EIA): Environmental Report
not required
Appropriate Assessment under
Habitats Regulations
AA not required
Design Statement or Design and
Access Statement
submitted
Report on Impact or Potential Impact
eg Flood Risk Assessment
 Sustainability checklist
 Surface Water Management Plan
Appraisal
40 Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise. The Development Plan comprises NPF4, the Perth and Kinross
Local Development Plan 2019 and statutory supplementary guidance. The
relevant policy considerations are outlined in the policy section above and are
considered in more detail below.
41 In addition, section 14(2) of the Planning (Listed Buildings and Conservation
Areas) (Scotland) Act 1997 places a duty on planning authorities in determining
such an application as this to have special regard to the desirability of preserving
the building or its setting or any features of special architectural or historic interest
which it possesses. 
Principle
42 The proposal is located on the edge of the area of the PPP (16/01809/IPM)
approved for the northern expansion of Auchterarder and identified as
Castlemains. However, a section of the site to the East and the area to the North
where the SuDS and pumping station are proposed are located outwith the red
line boundary of the PPP and the wider allocation.
43 The site is also broadly located within the Auchterarder Settlement Boundary
identified in LDP2. LDP2 Policy 17: Residential Areas advises that encouragement
will be given to proposals within Settlement Boundaries that fall within a number of
set categories and which are compatible with the amenity and character of the
area. The first category refers to ‘infill residential development at a density which
represents the most efficient use of the site while respecting its environs’. The
development is commensurate with the ongoing development to the south and
west, utilising the same, or substantially similar, house types and density. NPF4
promotes compact urban growth by making better use of brownfield sites to
sustain public transport and support local living and 20-minute neighbourhoods.
Page 137 of 160

Page 138

44 The site area containing the SuDS and pumping station is outside the Settlement
Boundary. LDP2 Policy 6 states that built development should be contained within
the settlement boundary where one exists. There are a limited number of
exceptions to this including where the proposal is justifiable on the basis of a
specific operational or locational need. Specific operational and locational need
can include essential infrastructure for which the SuDs and pumping station both
meet the criteria.
45 Overall, the proposal is considered to satisfy the requirements of the development
plan and is acceptable in principle subject to compliance with other relevant
policies. These matters are considered in detail below.
Design and Layout
46 Policy 14: Design, Quality and Place, Policy 15: Local Living and 20 Minute
Neighbourhoods and Policy 16: Quality Homes of NPF4 are relevant as are LDP2
Policy 1: Placemaking, Policy 14B: Open Space within New Developments, Policy
17: Residential Areas and Policy 25: Housing Mix.
47 The proposed layout is broadly reflective of and dictated by the site masterplan,
the development that has previously been completed on site and the adjacent
proposed phase. The design of the dwellinghouses is consistent with the
remainder of the development and will not appear out of place on the street scene.
The proposals are of an appropriate massing and scale and will be built using the
same materials as the adjacent development phases.
48 The heights of the proposed units reflect heights within the prevailing residential
context, both in terms of the existing and proposed residential areas. Proposed
site levels have been assessed and are considered satisfactory.
49 LDP2 Policy 25: Housing Mix requires 10% of homes to have two bedrooms or
less. In isolation the proposed development of six four-bedroom homes does not
meet this requirement. However, neighbouring proposal 24/01757/AMM will
provide 42 homes, of which eight will have two-bedrooms. Therefore, when
considered together, the provision of eight two-bedroom units over a total of 48
dwellings exceeds the requirement of the policy. 
50 Overall, the proposed layout, design, heights, and materials are considered to
appropriately reflect the surrounding character and amenity of the area, in
compliance with the Council’s placemaking policies. The proposals therefore are
considered to accord with the terms NPF4 and LDP2.
Residential Amenity
51 Some objections raise concerns on the potential impact on their residential
amenity as a result of the location of some of the new properties in relation to their
properties’ boundary. It is considered that through separation distances in excess
of 18m and angling of windows away from adjacent properties, there will not be
Page 138 of 160

Page 139

any significant detrimental impact on existing residential amenity. Similarly, the
layout within the site as well as the scale and height of the proposed
dwellinghouses will ensure that appropriate levels of both daylight and sunlight will
be afforded to both existing and proposed properties.
52 As is standard for residential expansions of this nature, a CEMP will be required
for the construction phase to protect residential amenity in terms of working hours,
noise, dust, construction traffic and light pollution (Condition 5).
Roads and Access
53 NPF4 Policy 13: Sustainable Transport seeks to encourage developments that
prioritise sustainable travel while LDP2 Policy 60 Transport Standards and
Accessibility Requirements requires consideration of transport and accessibility.
54 Transportation and Development had initially queried the lack of visitor parking.
However, due to the constrained nature of this small site, the visitor parking will be
provided on 24/01757/AMM in a location near the site boundary. In total, 11 visitor
parking spaces will be provided in small on-street clusters and in parking courts to
serve both developments. The provision of resident and visitor parking is
considered acceptable.
55 Some objectors to the proposal have referred to the existing path that runs east-
west between the proposed dwellinghouses and the SuDS and pumping station as
a ‘core path’. However, this route is not a designated core path at this location and
is not afforded the associated legal protection of a core path. Nevertheless, the
path is evidently a well-used route by local people and, once implemented, the
proposal will provide connections to the path and will not impact its use as right of
way for the public.
56 Overall, the proposals are acceptable subject to a condition for a Construction
Traffic Management Plan (Condition 3).
Drainage and Flooding
57 NPF4 Policy 22: Flood risk and water management advises that development will
not be supported if it is located in a flood risk area or will be at risk of flooding. The
site is not in an area of flood risk.
58 The surface water flows from plots 634-638 and associated roads will discharge
into a new surface water sewer and the SuDS detention basin proposed as part of
the development. The surface water flows from plot 648 will discharge into the
existing surface water sewers and SuDS detention basin delivered as part of the
previous development phase to the south. Flooding and Structures had initially
sought further information on the future maintenance and adoption proposals for
the SuDs. This information has subsequently been provided and the proposal is
considered to be satisfactory.
Page 139 of 160

Page 140

59 Overall, the proposal complies with NPF4 Policy 22: Flood Risk and Water
Management and LDP2 Policy 52: New Development and Flooding and Policy 53:
Water Environment and Drainage.
Conservation Considerations
60 The site is immediately to the west of Castlemains Farm Steading with the
Category C listed Castlemains Farmhouse including castellated building
(Auchterarder Castle) located to the east (Listed Building ref: 52514).
61 The recent development within the vicinity of the listed building has affected its
setting and this is noted by HES in the setting section of the listed building
description ‘The farmland surrounding the farmhouse is currently being developed
as a large housing estate (2019). The loss of the farmhouse gardens and former
agricultural land lessens the interest of the setting of the farmhouse and the
castellated building (Auchterarder Castle).’
62 The proposed development is set back from the listed building and is visually and
physically separated from it by the unlisted Castlemains Farm Steading. The
proposal is therefore not considered to detrimentally impact on the special interest
of the listed building or its setting.
63 Perth and Kinross Heritage Trust has been consulted on the proposal and has
advised that there is moderate potential for evidence of archaeological and historic
remains associated with the defence / enclosure of the castle. Therefore, it is
recommended that a programme of archaeological works is undertaken to assess
the presence / absence of archaeological remains (Condition 4)
Natural Heritage and Biodiversity
64 In relation to natural heritage and biodiversity, NPF4 Policies 1: Tackling the
Climate and Nature Crisis, 2: Climate Mitigation and Adaptation 3: Biodiversity and
20: Blue and Green Infrastructure, are relevant. In addition, LDP2 Policies 41 and
42 apply.
65 The site is brownfield and currently has limited biodiversity value. NPF4 requires
local planning applications to include appropriate measures for biodiversity
enhancement that are proportionate to the nature and scale of the development. 
66 Biodiversity enhancement is proposed through tree planting and soft landscaping.
Planting includes Scottish native species, fruit bearing trees and a mixed native
hedge. There is scope for further biodiversity enhancement to align with PKC’s
Planning for Nature: Development Management and Wildlife Guide through the
provision of swallow nest cups, swift nesting bricks and wildlife kerbs. A condition
is proposed to secure the implementation of additional biodiversity enhancements
(Condition 6).
Page 140 of 160

Page 141

Low and Zero Carbon Generating Technologies
67 LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in New
Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of
low and zero-carbon generating technologies. As this proposal includes the
erection of a new building, consideration must be given to this requirement.
Further, NPF4 Policy 2 ‘Climate Mitigation and Adaptation’ requires that
development should be designed to reduce green gas emissions. In this instance,
solar PV panels will be fitted to all properties, with low energy lighting and high
efficiency appliances also installed. The proposal therefore complies with the
relevant policies.
Developer Contributions
68 NPF4 Policy 18: Infrastructure First and LDP2 Policy 5: Infrastructure
Contributions requires consideration of the individual or cumulative impact of new
development on infrastructure and facilities and to secure contributions to address
this impact where the development exacerbates impacts or generates additional
need.
69 While this proposal is a full application that stands alone from the PPP. The
applicant, Muir Homes, is one of the consortium developers of the AEDF area on
which the development partially sits.
70 There is an existing S.75 obligation for the wider development site which requires,
amongst other things, the provision of a new junction at Shinafoot to the north of
Auchterarder and sports facilities for the development. The S.75 includes a cap on
the number of homes that can be built as part of the AEDF until these
requirements are met. This is a complex matter, and discussions have been
ongoing with the consortium developers with a view to seeking a suitable
resolution. The situation has been further complicated by part of the consortium,
Stewart Milne Group, being placed into administration. Muir Homes has
acknowledged that, due to these ongoing discussions, they will not currently be in
a position to implement the consent and are rather looking to have the consent in
place and ready to go at such time as matters pertaining to the S.75 are resolved.
An informative is recommended to be added to the permission to confirm the
scope of the S.75 (informative 1).
71 The neighbouring application 24/01757/AMM will be bound by the terms of the
existing S.75, but as the smaller local site is a standalone application it will not be.
However, the two applications are inherently linked due to the joint approach to the
provision of affordable housing and other infrastructure requirements.
Notwithstanding that the local application also relates to, and forms a part of, the
wider AEDF area. A new legal agreement will therefore be required to ensure that
the local application will also be bound by the obligations of the existing S.75 for
the wider development.
Page 141 of 160

Page 142

Economic Impact
72 The impact to the local economy both during construction and occupation will be
moderate with additional available expenditure on local facilities and services.
Planning Obligations and Legal Agreements
73 As set out above, a legal agreement is required to ensure that obligations are
secured in line with the requirements of the wider development area. Consent
shall not to be issued until the agreement has been signed and registered to take
account of this application. The legal agreement should be concluded and
completed within 4 months of the date of any approval.
Direction By Scottish Ministers
74 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions by
the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.
Conclusion and Reasons for Recommendation
75 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly, the proposal is recommended for approval
subject to the following conditions.
Recommendation 
Approve subject to the following conditions:
Conditions and Reasons for Recommendation
1. This planning permission will last only for three years from the date of this decision
notice, unless the development has been lawfully started within that period.
Reason: This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019.
2. The development hereby approved must be carried out in accordance with the
approved drawings and documents, unless otherwise provided for by conditions
imposed by this decision notice.
Reason: To ensure the development is carried out in accordance with the
approved drawings and documents.
Page 142 of 160

Page 143

3. Prior to the commencement of the development hereby approved, the applicant
shall submit for the further written agreement of the Council as Planning Authority,
in consultation with the Roads Authority (Structures), a Construction Traffic
Management Scheme (TMS) which shall include the following:
 restriction of construction traffic to approved routes and the measures to be
put in place to avoid other routes being used;
 timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse collection
is undertaken, on Sundays and during local events;
 a code of conduct for HGV drivers to allow for queuing traffic to pass;
 arrangements for liaison with the Roads Authority regarding winter
maintenance;
 emergency arrangements detailing communication and contingency
arrangements in the event of vehicle breakdown;
 arrangements for the cleaning of wheels and chassis of vehicles to prevent
material from construction sites associated with the development being
deposited on the road;
 arrangements for cleaning of roads affected by material deposited from
construction sites associated with the development;
 arrangements for signage at site accesses and crossovers and on roads to be
used by construction traffic in order to provide safe access for pedestrians,
cyclists and equestrians;
 details of information signs to inform other road users of construction traffic;
 arrangements to ensure that access for emergency service vehicles are not
impeded;
 co-ordination with other significant developments known to use roads affected
by construction traffic;
 traffic arrangements in the immediate vicinity of temporary construction
compounds;
 the provision and installation of traffic counters at the applicant's expense at
locations to be agreed prior to the commencement of construction;
 monitoring, reporting and implementation arrangements;
 arrangements for dealing with non-compliance; and
 details of HGV movements to and from the site. 
The TMS as approved shall be strictly adhered to during the entire site
construction programme.
Reason: In the interests of proper site management.
4. Development shall not commence until the developer has secured the
implementation of a programme of archaeological work in accordance with a
Written Scheme of Archaeological Investigation (WSI) which has been submitted
by the developer and agreed in writing by the Council as Planning Authority, in
consultation with Perth and Kinross Heritage Trust (PKHT).  Thereafter, the
developer shall ensure that the programme of archaeological works is fully
Page 143 of 160

Page 144

implemented including that all excavation, preservation, recording, recovery,
analysis, publication and archiving of archaeological resources within the
development site is undertaken.  Should the archaeological works, as required by
the WSI, identify a requirement for post-excavation analysis, the development as
approved shall not be occupied or brought into use until a Post-Excavation
Research Design (PERD) has been submitted to and agreed in writing by the
Council as Planning Authority, in consultation with PKHT. The PERD shall be
carried out in complete accordance with the approved details.  Furthermore, the
developer shall afford access at all reasonable times to PKHT or a nominated
representative and shall allow them to observe work in progress.
Reason: To ensure a programme of archaeological works is carried out to
safeguard and record any archaeological remains within the development area.
5. A Construction Environmental Management Plan (CEMP) shall be submitted prior
to the commencement of the development for the written approval of the planning
authority.  The CEMP shall include recommendations for the control of working
hours, noise, dust and vibration during the construction stage of the development
and once approved shall be implemented throughout the construction phase of the
development.
Reason: In the interests of protecting environmental quality.
6. Prior to the commencement of the development hereby approved, a Biodiversity
Enhancement Plan for the site shall be submitted.  Thereafter, the agreed scheme
shall be implemented in full prior to the completion of the development.
Reason: In the interests of protecting environmental quality and of biodiversity.
7. The detailed landscaping and planting scheme which is hereby approved shall be
completed within the first available planting season (October to March) after the
completion or bringing into use of the development, whichever is the earlier.  The
approved scheme shall thereafter be maintained to the satisfaction of the Council
as Planning Authority, with any planting which fails to become established within
five years being replaced in the following planting season with others of a size and
species as previously approved.
Reason: In the interests of visual amenity and to ensure the satisfactory
implementation of the proposed planting scheme.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Page 144 of 160

Page 145

Procedural Notes
1. Permission shall not to be issued until the Section 75 Agreement has been signed
and registered to take account of this application.  The legal agreement should be
concluded and completed within 4 months of the date of any Committee approval.
Failure to conclude a legal agreement within 4 months will result in the planning
application being re-assessed through failing to comply with the associated
developer contributions policy and may be ultimately recommended for refusal
under delegated powers
Informatives
1. The applicant is advised to refer to the existing Section 75 Legal Agreement and
the implications that this agreement has with regards to commencing works, with
particular attention drawn towards the sports facilities provision and the Shinafoot
junction works.
2. Under Section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,
which may result in enforcement action being taken.  Please use the form attached
herewith.
3. As soon as practicable after the development is complete, the person who
completes the development is obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the Planning Authority written
notice of that position.  Please use the form attached herewith.
4. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that way,
otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please be
aware that a fee is payable in respect of each request made, though there is no
limit to the number of conditions that can be discharged in a single request.  The
Fees Charter is available on our website www.pkc.gov.uk.  
The Council has two months to consider the information.  You should therefore
submit the required information more than two months before your permission
expires.  We cannot guarantee that submissions made within two months of the
expiry date of your permission will be able to be dealt with before your permission
lapses.
5. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive.  Trees and scrub are present on the application site and are to
be assumed to contain nesting birds between the above dates.  The applicant is
Page 145 of 160

Page 146

reminded that, under the Wildlife and Countryside Act 1981, as amended (section
1), it is an offence to remove, damage or destroy the nest of any wild bird while
that nest is in use or being built.  Planning permission for a development does not
provide a defence against prosecution under this Act.
6. The applicant should be aware of the requirements of the Council's Environment
and Regulatory Services in relation to waste collection from the site and should
ensure adequate measures are provided on site to allow for the collection of
waste.
7. The applicant is advised to refer to Perth & Kinross Council's Supplementary
Guidance on Flood Risk and Flood Risk Assessments 2021 as it contains advice
relevant to your development. https://www.pkc.gov.uk/ldp2floodrisk
8. Application for a new postal address should be made via the Street Naming and
Numbering page on the Perth & Kinross Council website at www.pkc.gov.uk/snn. 
Please note there is a charge for this service and submission cannot be made until
the relevant Building Warrant has been approved.
9. No work shall be commenced until an application for building warrant has been
submitted and approved.
Background Papers
Letters of representation 19
Authors
Name Designation Contact Details
Alex Gudgeon Planning Officer (Major
Team)
01738 475300
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
30 April 2025
Page 146 of 160

Page 147

Ü
Erection of 6 dwellinghouses, landscaping and associated infrastructure (Phase 2A) on land 90 metres
North-west of Castlemains Farm Steading, Auchterarder
24/01758/FLL
Scale
1:15,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(2)(i)
Page 147 of 160

Page 148

Page 148 of 160

Page 149

Ü
Erection of 6 dwellinghouses, landscaping and associated infrastructure (Phase 2A) on land 90 metres
North-west of Castlemains Farm Steading, Auchterarder
24/01758/FLL
Scale
1:5,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
5(2)(i)
Page 149 of 160

Page 150

Page 150 of 160

Page 151

Perth and Kinross Council
Planning and Placemaking Committee – 14 May 2025
Pre-Application Report by Development Management and Building Standards
Service Manager
(Report No. 25/122)
Proposal: Redevelopment works comprising alterations to grass football
pitches to form 2 synthetic football pitches, extension to building,
erection of spectator stand and associated works
Location: Jeanfield Swifts Stadium, Bute Drive, Perth, PH1 3BG
Ref. No: 25/00006/PAN
Ward No: P12- Perth City Centre
Summary
This report is to inform the Committee of a potential forthcoming planning
application in respect of a major development for redevelopment works comprising
alterations to grass football pitches to form 2 synthetic football pitches, extension
to building, erection of spectator stand and associated works at Jeanfield Swifts
Stadium, Bute Drive, Perth, PH1 3BG. The report also aims to highlight the key
planning policies and the likely stakeholders who would be involved in the decision
making process, and to offer a brief overview of the key planning issues which are
likely to be relevant to the proposal.
Background and Description
1. In accordance with the provisions of the Town & Country Planning (Scotland)
Act 1997 (as amended), the applicants submitted a Proposal of Application
Notice (PoAN) on 24 March 2025. The purpose of this report is to inform the
Planning and Placemaking Committee of a forthcoming planning application in
respect of a major development for redevelopment works comprising
alterations to grass football pitches to form 2 synthetic football pitches,
extension to building, erection of spectator stand and associated works at
Jeanfield Swifts Stadium, Bute Drive, Perth, PH1 3BG. Pre-application reports
give the Committee an opportunity to raise issues which it would like to see
addressed in the planning application.
2. This PoAN seeks to formally establish a major development. The exact range
of uses, scale and design of the development will be arrived at during pre-
application discussions.
6(i)
Page 151 of 160

Page 152

Environmental Impact Assessment (Eia)
3. Due to the scale of the proposal it will require to be screened as to whether
the proposal is an EIA development under the EIA 2017 Regulations. A
screening request is required to be submitted by the applicant.
Pre-Application Process
4. The PoAN (reference 25/00006/PAN) confirmed that two public exhibitions will
be held at Riverside Stadium, Bute Drive, Perth, PH1 3BP, the first event on
1 April 2025 between 7pm and 9pm and the second event on 15 April 2025
between 7pm and 9pm.  Additionally, the applicant will hold three drop-in
sessions on 3, 10 and 17 April between 10.30am and 12pm. The Ward
Councillors, MP’s, MSP’s, North Muirton Community Council, and North Inch
and Muirton Community Council have been notified. The results of the
community consultation will be submitted with the planning application as part
of the required Pre-Application Consultation (PAC) Report.
Development Plan
5. The Development Plan for the area comprises National Planning Framework
4 (NPF4) and the Perth and Kinross Local Development Plan 2 (2019)
(LDP2).
National Planning Framework 4
6. The National Planning Framework 4 (NPF4) is the Scottish Government’s
long-term spatial strategy with a comprehensive set of national planning
policies.  This strategy sets out how to improve people’s lives by making
sustainable, liveable and productive spaces. 
7. NPF4 was adopted on 13 February 2023. NPF4 has an increased status over
previous NPFs and comprises part of the statutory development plan.
8. The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 4: Natural Places
 Policy 6: Forestry, Woodland and Trees
 Policy 7: Historic Assets and Places
 Policy 8: Greenbelts
 Policy 13: Sustainable Transport
 Policy 14: Design, Quality and Place
 Policy 15: Local Living and 20 Minute Neighbourhoods
 Policy 18: Infrastructure First
 Policy 20: Blue and Green Infrastructure
 Policy 21: Play, Recreation and Sport
 Policy 22: Flood Risk and Water Management
Page 152 of 160

Page 153

 Policy 29: Rural Development
 Policy 31: Culture and Creativity
Perth and Kinross Local Development Plan 2019
9. The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for
the area and states that, “Our vision is of a Perth and Kinross which is
dynamic, attractive and effective which protects its assets whilst welcoming
population and economic growth.” It is the most recent statement of Council
policy and is augmented by Supplementary Guidance.
The principal relevant policies are, in summary;
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 2: Design Statements 
 Policy 5: Infrastructure Contributions
 Policy 6: Settlement Boundaries
 Policy 8: Rural Business and Diversification
 Policy 13: Retail and Commercial Leisure Proposals
 Policy 14A: Open Space Retention and Provision: Existing Areas
 Policy 14B: Open Space Retention and Provision: Open Space within New
Developments
 Policy 15: Public Access
 Policy 16: Social, Cultural and Communities Facilities
 Policy 17: Residential Areas
 Policy 26B: Scheduled Monuments and Archaeology: Archaeology
 Policy 29: Gardens and Designated Landscapes
 Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
 Policy 41: Biodiversity
 Policy 42: Green Infrastructure
 Policy 43: Green Belt
 Policy 47: River Tay Catchment Area
 Policy 52: New Development and Flooding
 Policy 53B: Water Environment and Drainage: Foul Drainage
 Policy 53C: Water Environment and Drainage: Surface Water Drainage
 Policy 55: Nuisance from Artificial Light and Light Pollution
 Policy 56: Noise Pollution
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals
 Policy 61: Airfield Safeguarding
Statutory Supplementary Guidance
10.
 Supplementary Guidance - Airfield Safeguarding (adopted in 2020)
 Supplementary Guidance - Developer Contributions & Affordable Housing
(adopted in 2020)
 Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
Page 153 of 160

Page 154

 Supplementary Guidance - Green & Blue Infrastructure (adopted in 2020)
 Supplementary Guidance - Open Space Provision for New Developments
(adopted in 2021)
 Supplementary Guidance - Placemaking (adopted in 2020)
PKC Non Statutory Guidance
11. The following non statutory guidance and documents are of particular
importance in the assessment of this application:
 Planning Guidance - Loch Leven SPA, the Dunkeld-Blairgowrie Lochs
SAC and the River Tay SAC
 Planning Guidance - Planning & Biodiversity
National Guidance
12. The Scottish Government expresses its planning policies and guidance
through the National Planning Framework, Planning Advice Notes, Creating
Places, Designing Streets, National Roads Development Guide and a series
of Circulars. 
Planning Advice Notes
13. The following Scottish Government Planning Advice Notes are likely to be of
relevance to the proposal:
 PAN 1/2011 Planning and Noise
 PAN 2/2011 Planning and Archaeology
 PAN 3/2010 Community Engagement
 PAN 51 Planning, Environmental Protection and Regulation
 PAN 61 Planning and Sustainable Urban Drainage Systems
 PAN 65 Planning and Open Space
 PAN 73 Rural Diversification
 PAN 75 Planning for Transport
Planning Site History
14. 03/01047/FUL Full Planning Permission application was Withdrawn on 21
October 2004 for Erection of a new football pavilion and 2.4m high pitch
enclosure (fence).
15. 04/02149/FUL Full Planning Permission was Approved on 12 August 2005 for
Construction of a football pavilion, erection of a pitch enclosure and
installation of floodlights.
16. 06/02110/MOD was Approved on 21 November 2006 for Modification of
existing consent 04/02149/FUL for football pavilion.
17. 09/00702/FLL Full Planning Permission was Approved on 3 August 2009 for
Install new changing room portacabins
Page 154 of 160

Page 155

18. 19/01109/FLL Full Planning Permission was Approved on 3 September 2019
for Installation of 4 floodlights
Consultations
19. As part of the planning application process the following would be consulted:
External
 NatureScot
 Scottish Water
 Historic Environment Scotland
 Perth and Kinross Heritage Trust
 North Muirton Community Council
 North Inch and Muirton Community Council
 Scone Airport
Internal
 Environmental Health
 Development Plan Team
 Development Contributions Officer
 Community Greenspace including Access
 Transportation and Development
 Structures and Flooding
 Economic Development
 Waste Services
 Biodiversity Officer
 Estates
Key Issues Against Which a Future Application Will Be Assessed
20. The key considerations against which the eventual application will be
assessed include:
a. Visual Impact
b. Scale, Design and Layout
c. Relationship to Nearby Land Uses
d. Natural Heritage and Ecology
e. Landscape
f. Water Resources and Soils
g. Air Quality 
h. Transport Implications
i. Tourism and Economy
j. Impact on Agriculture
k. Archaeology and Cultural Heritage
Additional Statements Which Will Be Required
21. Should an EIA Report not be required the following supporting documents will
need to be submitted with any planning application:
Page 155 of 160

Page 156

 Planning Statement
 Design and Access Statement
 Pre-Application Consultation (PAC) Report
 Leisure/Economic Impact Assessment
 Transport Assessment
 Flood Risk and Drainage Assessment
 Landscape and Visual Impact Assessment
 Tree and Woodland Survey
 Habitat Survey
 Archaeological Assessment
 Sustainability Assessment
Conclusion and Recommendation
22. This report summarises the key issues which should be considered as part of
the appraisal of any subsequent planning application which may be lodged in
respect of this development and members are recommended to note these
key issues and advise officers of any other issues which they consider should
be included as part of the application and assessment.
Authors
Name Designation Contact Details
Kirsty Strong Planning Support Officer 01738 475300
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
24 April 2025
Page 156 of 160

Page 157

Ü
Redevelopment works comprising alterations to grass football pitches to form 2 synthetic football pitches,
extension to building, erection of spectator stand and associated works at Jeanfield Swifts Stadium, Bute
Drive, Perth
25/00006/PAN
Scale
1:15,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
6(i)
Page 157 of 160

Page 158

Page 158 of 160

Page 159

Ü
Redevelopment works comprising alterations to grass football pitches to form 2 synthetic football pitches,
extension to building, erection of spectator stand and associated works at Jeanfield Swifts Stadium, Bute
Drive, Perth
25/00006/PAN
Scale
1:5,000
Planning and Placemaking Committee - 14 May 2025© Crown copyright [and database rights] 2024 OS
AC0000805756. You are permitted to use this data solely to
enable you to respond to, or interact with, the organisation
that provided you with the data. You are not permitted to
copy, sub-licence, distribute or sell any of this data to third
parties in any form.
6(i)
Page 159 of 160

Page 160

Page 160 of 160