Perth and Kinross Council
Planning and Placemaking Committee – 12 March 2025
Report of Handling by Strategic Lead: Economy, Development and Planning
(Report No. 25/53)
PROPOSAL: S42 application to amend condition 12 (ECoW) of
(22/02231/FLM)
LOCATION: Shindour Feddal Hill Wood, Braco
Ref. No: 25/00049/42M
Ward No: P7- Strathallan
Summary
This report recommends approval of the application as the development is
considered to comply with the relevant provisions of the Development Plan and there
are no material considerations apparent which outweigh the Development Plan.
Background and Description of Proposal
1 Detailed planning permission to construct and operate an energy storage facility
immediately to the northeast of the existing Beauly Denny transmission line at
the Braco West substation was approved in October 2024. The site is located in
Feddal Forest on Feddal Hill, within an area previously planted with Sitka spruce
trees which were felled around 11 years ago by SSE as part of its work on the
adjacent electricity sub-station and pylon lines. The site of 0.7 hectares lies
some 3.8km to the west of Braco, 6.8km north of Dunblane and the nearest
residential property of Bentick Farm is 1.2km to the south.
2 The proposed energy storage facility will accommodate up to 50 battery storage
units housed within steel shipping containers with associated inverter/transformer
units and ancillary structures including a store, office, parking and electrical control
building. The area which would be developed extends to 7,329m2. The site will be
surrounded by landscaping consisting of native trees along with an inner security
fence along with a drainage swale. An area to the north of the site will be restored
as bog habitat.
3 The proposed energy storage facility of 49.9MW will provide rapid-response
electrical backup to the electricity grid. It will draw electrical power from the
electricity grid and then store it. The storage of electricity is regarded as a

Page 2

generation activity, however, the electrical power will be drawn power from the
electricity grid and stored, for release back into the grid when required.
4 The proposed development will be accessed from an existing minor road and
forestry track to the south, connecting the site with the B5033 road at the Muckle
Burn. The route is 3.9km in length and has been upgraded to accommodate the
substation construction traffic and forestry equipment and timber lorries including
the provision of passing places.
5 The proposed development will be temporary in nature, with consent being
approved for an operational period of up to 50 years. After this period the site
will be decommissioned and restored to blanket bog.
6 Section 42 of the Act (Town and Country Planning (Scotland) Act 1997 as
Amended) applies to applications for Planning Permission to develop land which
departs from conditions attached to an existing permission.  The effect of
granting permission for a section 42 application is therefore such that a new and
separate permission exists for the development with different (or no) conditions
attached.  The previous planning permission remains unaltered by, and is not
varied by, the decision on the section 42 application.
7 The primary purpose of this Section 42 (S42) application seeks a revision to the
requirements of Condition 12 of the full planning consent 22/02231/FLM.
8 The original wording of condition 12 currently states:
9 Prior to the commencement of the development hereby approved, an
independent and suitably qualified Ecological Clerk of Works (ECoW) shall be
appointed at the developers' expense. Details of this appointment shall be
subject to the prior written agreement of the Council as Planning Authority. The
appointed person will remain in post for the duration and subsequent restoration
of the proposed development. The ECoW shall have responsibility for the
following:
(a) Overseeing the implementation of the Construction Environmental
Management Plan (CEMP) approved by this permission.
(b) Authority to stop operations or to alter construction methods should there
be any works occurring which are having an adverse impact on the natural
heritage.
(c) Prior to the commencement of development, they shall provide an
environmental / ecological toolbox talk for construction staff.
(d) They will have authority to amend working practices in the interests of
natural heritage. Any amendments shall be submitted to the Council as
Planning Authority as an addendum to the approved CEMP.
(e) They shall make weekly visits to the development site at a time of their
choosing. No notification of this visit is required to be given to the developer
or contractor.
(f) Within 10 working days of the end of each calendar month, they are
required to submit a detailed monthly report for the review of the Planning

Page 3

Authority in consultation with Scottish Environment Protection Agency
(SEPA) for the duration of development.
(g) They shall notify the Council as Planning Authority in writing of any
requirement to halt development in relation to this condition as soon as
reasonably practicable.
The above shall be implemented throughout the construction, (including re-
instatement and de-commissioning of the construction compounds) hereby
approved unless otherwise agreed in writing with the Council as Planning
Authority. The CEMP shall contain a site-specific Construction Method
Statement (CMS) which will provide concise details for the implementation
of the CEMP for site operatives
Reason: To avoid habitat damage and safeguard natural heritage interests.
10 The proposal seeks to vary the wording of the third sentence of the first
paragraph which reads “The appointed person will remain in post for the duration
and subsequent restoration of the proposed development” to “The appointed
person will remain in post for the duration of construction and post construction
site restoration of the proposed development”.
11 Furthermore, the proposal seeks to vary clause (e) from “weekly visits” to “They
shall make fortnightly visits to the development site during construction works at
a time of their choosing. No notification of this visit is required to be given to the
developer or contractor”.
12 Assessment for the proposed changes for this condition is set out below.
Site History
13 05/01911/FUL Planning Permission for construction of 275/33kv electricity
substation, associated building and temporary storage areas, site huts,
upgrading/widening works to existing private access road and improvements to
junction where access road meets the B8033. Approved April 2006
14 13/01036/FLL Planning Permission for formation of a temporary works
compound and topsoil storage area. Approved July 2013
15 14/01758/FLL Planning Permission for permanent retention of temporary access
track constructed as part of Beauly-Denny overhead power line. Approved
December 2014
16 15/00470/FLL Planning Permission for erection of substation control building,
formation of access road and associated works. Approved June 2015
17 16/01719/PN Prior Notification for formation of a forestry track. Approved
November 2016.

Page 4

18 17/01810/FLL Planning Permission for formation of an energy storage facility,
vehicular access, and associated works. Approved November 2017.
19 20/00013/PAN Proposal of Application Notice for formation of an energy
storage facility comprising control building, battery storage container units,
ancillary equipment, parking, boundary treatments, landscaping, and
associated works. Approved February 2021.
20 21/00756/FLM Formation of a 49.9MW energy storage facility comprising 50
battery storage container units, control building, ancillary equipment, parking,
access track, boundary treatments, landscaping and associated works. Approved
December 2021.
21 21/00020/PAN Formation of a battery energy storage compound comprising
battery storage units, ancillary buildings and equipment, landscaping and
associated works. Approved February 2022.
22 22/02231/FLM Formation of a 49.99MW battery energy storage compound
comprising battery storage units, ancillary buildings and equipment, bogland
restoration, landscaping and associated works. Approved 24 October 2024.
Environmental Impact Assessment
23 An EIA screening was undertaken in association with the submission of
planning application 22/02213/FLM, concluding that an EIA was not required as
the proposal was not considered likely to have significant environmental effects.
Nothing further is required in relation to this Section 42 application.
Pre-Application Consultation
24 The Pre-Application Consultation (PAC) requirements have been fulfilled in
association with the submission of planning application 22/02231/FLM and there
is no further PAC needed procedurally in relation to this Section 42 application.
Development Plan
25 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.
National Planning Framework 4
26 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve peoples lives by making sustainable, liveable
and productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan.

Page 5

27 The Council’s assessment of this application has considered the following
policies of NPF4:
 Policy 3: Biodiversity
 Policy 4: Natural Places
Perth and Kinross Local Development Plan 2019
28 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.
29 The principal relevant policies are, in summary;
 Policy 41: Biodiversity
PKC Non Statutory Guidance
30 Planning Guidance - Planning & Biodiversity
National Guidance
31 The Scottish Government expresses its planning policies through Planning
Advise Notes, Creating Places, Designing Streets, National Roads Development
Guide and a series of Circulars in addition to NPF4.
Planning Advice Notes
32 The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:
 PAN 51 Planning, Environmental Protection and Regulation
Consultations
33 As part of the planning application process the following bodies were consulted:
Internal
34 Biodiversity/Tree Officer – no objections.
Representations
35 None.

Page 6

Additional Statements
36 Screening Opinion EIA not required
Environmental Impact Assessment (EIA):
Environmental Report
Not required
Appropriate Assessment under Habitats
Regulations
Habitats Regulations Appraisal
completed:
AA not required
Design Statement or Design and Access
Statement
Not required
Report on Impact or Potential Impact eg
Flood Risk Assessment
Not required
Appraisal
37 Section 42(1) of the Town & Country Planning (Scotland) Act 1997 (as amended)
relates to applications for planning permission for the development of land
without complying with conditions subject to which a previous permission was
granted.
38 Section 42(2) requires that the Planning Authority shall consider only the
question of the condition(s) subject to which planning permission should be
granted, and:
(a) If they decide that planning permission should be granted subject to
conditions differing from those subject to which the previous permission
was granted, or that it would be granted unconditionally, they shall grant
planning permission accordingly;
(b) If they decide that planning permission should be granted subject to the
same conditions as those subject to which the previous permission was
granted, they shall refuse the application.
39 The determining issues in this case are whether the proposal complies with
Development Plan policy or if there are any other material considerations which
justify a departure from that policy The Development Plan comprises NPF4 and
the Perth and Kinross Local Development Plan 2 (2019). The relevant policy
considerations are outlined in the policy section above and are considered in
more detail below. In terms of other material considerations, this involves
considerations of supplementary guidance, statutory consultees and additional
statements submitted.
40 It is important to note that both National Planning Framework (NPF4) policies and
Local Development Plan 2 (LDP2) policies apply except where they are not
compatible in which case NPF4 policies prevail.

Page 7

Principle
41 The principle of the development subject of the application has been previously
established through the approval of the full planning permission (22/02231/FLM).
The principle of the development is therefore well-established and is not
reviewed as part of this S42 application. The amendment of Condition 12 as
noted above is not in itself contrary to the general terms of the Development
Plan, however, consideration must be given to the specific characteristics of the
amendment and whether any adverse impacts are calculated.
Natural Heritage and Biodiversity
42 The proposed amendment to the wording of the third sentence in the opening
paragraph of condition 12 is sought to clarify that the ECoW only needs to
monitor the site until commission and post-construction site restoration works are
completed rather than until the completion of post decommissioning restoration
works.
43 The submitted information states that the amendments to clause (e) have been
sought as there are likely to be periods of inactivity during the overall
construction period which could extend to periods of several months, for example
between the construction of the hardstanding and the delivery and installation of
equipment, during which frequent monitoring would not be required.
44 The purpose of the ECoW is to ensure compliance with wildlife regulations,
planning consent and ecological requirements of which will still be achieved
through the proposed rewording of condition 12.
45 On that basis the proposal to amend the condition is considered to be
acceptable.
Developer Contributions
46 No developer contributions are required for this type of development.
Economic Impact
47 In the short term, construction will create jobs with scope for local employment.
Beyond this, local employment opportunities will be limited. Holistically, however,
there is a clear fit between Scottish Government aims of promoting a transition to
a low carbon economy and this proposal. The proposal would directly support
local renewable energy generation, by helping balance fluctuations of intermittent
energy generation and more widely, assisting in the creation of a national grid
asset of regional significance for the Perth and Kinross Area.

Page 8

Legal Agreements
48 No additional legal agreement is required in this instance as relevant matters
continue to be appropriately covered by the original agreement associated with
planning permission 22/02231/FLM. On that basis the S75 does not require to be
updated in respect of this proposal.
Direction by Scottish Ministers
49 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.
Conclusion and Reasons for Recommendation
50 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan. Accordingly, the proposal is recommended for approval
subject to the following conditions.
Recommendation 
51 Approve the application subject to the following conditions:
Conditions and Reasons for Recommendation
1. This planning permission will last only for three years from the date of this
decision notice, unless the development has been lawfully started within that
period.
Reason - This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019.
2. The development hereby approved must be carried out in accordance with the
approved drawings and documents, unless otherwise provided for by conditions
imposed by this decision notice.
Reason - To ensure the development is carried out in accordance with the
approved drawings and documents.
3. The battery energy storage units and ancillary infrastructure shall be removed
from the site no later than 50 years after the date when the operation is first
brought into use unless otherwise approved by the Planning Authority through

Page 9

the grant of a further planning permission following submission of an application.
Written confirmation of the commencement date of first operation shall be
provided to the Planning Authority within one month of that date.
Reason - In order to limit the permission to the expected operational lifetime of
the battery storage units and to allow for restoration of the site in the event that
the use is not continued by a further grant of planning permission for a similar
form of development.
4. Prior to the commencement of the development hereby approved, the developer
shall submit for the further written agreement of the Council as Planning
Authority, in consultation with the Roads Authority, a Construction Traffic
Management Scheme (CTMS) which shall include the following:
(a) restriction of construction traffic to approved routes and the measures to
be put in place to avoid other routes being used;
(b) timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse
collection is undertaken, on Sundays and during local events;
(c) a code of conduct for HGV drivers to allow for queuing traffic to pass;
(d) arrangements for liaison with the Roads Authority regarding winter
maintenance;
(e) emergency arrangements detailing communication and contingency
arrangements in the event of vehicle breakdown;
(f) arrangements for the cleaning of wheels and chassis of vehicles to
prevent material from construction sites associated with the development
being deposited on the road;
(g) arrangements for cleaning of roads affected by material deposited from
construction sites associated with the development;
(h) arrangements for signage at site accesses and crossovers and on roads
to be used by construction traffic in order to provide safe access for
pedestrians, cyclists and equestrians;
(i) details of information signs to inform other road users of construction
traffic;
(j) arrangements to ensure that access for emergency service vehicles are
not impeded;
(k) co-ordination with other significant developments known to use roads
affected by construction traffic;
(l) traffic arrangements in the immediate vicinity of temporary construction
compounds;
(m) monitoring, reporting and implementation arrangements;
(n) arrangements for dealing with non-compliance; and
(o) details of HGV movements to and from the site.
The TMS as approved shall be strictly adhered to during the entire site
construction programme to the satisfaction of the Council as Planning Authority.

Page 10

Reason - To minimise interference with the safety and free flow of the traffic on
the access road off the B8033 road.
5. Prior to the commencement of development, a comprehensive Construction
Traffic Management Plan shall be submitted for the approval of the Planning
Authority, after consultation with Transport Scotland.
Reason - To minimise interference with the safety and free flow of the traffic on
the trunk road.
6. Not less than two months from the date of this planning permission, a detailed
scheme for the management of vehicles crossing of the National Grid pipeline at
Easting 282178; Northing 709479 and any necessary reinforcement works of that
road and or crossing shall be submitted to, and approved in writing by, the
Planning Authority in consultation with National Grid.  The scheme shall include
the frequency of vehicle movements during both the construction and operational
phases of development, specify vehicle weights and set out the technical
specification of the reinforcement works to the road or crossing point and their
delivery.  Thereafter, the scheme shall be implemented in complete accordance
with the approved scheme and all reinforcement works complete prior to the
commencement of development hereby approved.
Reason - In order to ensure that suitable vehicle crossing arrangements are
provided.
7. All plant or equipment shall be so enclosed, attenuated and/or maintained such
that any noise therefrom shall not exceed Noise Rating 35 between 0700 and
2300 hours daily, or Noise Rating 20 between 2300 and 0700 hours daily, within
any neighbouring residential property, with all windows slightly open, when
measured and/ or calculated and plotted on a rating curve chart.
Reason - In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality.
8. Construction work shall be limited to Monday to Friday 0700 hours to 1900 hours
and Saturday 0800 hours to 1300 hours with no noisy works out with these times
or at any time on Sundays or bank holidays (as identified by Scottish
Government).
Reason - In the interests of residential amenity; to ensure a satisfactory standard
of local environmental quality.
9. Prior to the commencement of the development hereby approved, a detailed
boundary landscaping and planting scheme shall be submitted for the written
agreement of the Council as Planning Authority.  The scheme shall include
details of the height and slopes of any mounding or recontouring of the site, full
details of all hard landscaping proposals including materials and installation
methods and, species, height, size and density of trees and shrubs to be planted.

Page 11

The scheme as subsequently approved shall be carried out and completed within
the first available planting season (October to March) after the completion or
bringing into use of the development, whichever is the earlier, and the date of
Practical Completion of the landscaping scheme shall be supplied in writing to
the Council as Planning Authority within 7 days of that date.  The scheme as
agreed and implemented shall thereafter be maintained by the site operator.
Reason - To ensure a satisfactory standard of development and environmental
quality and to reserve the rights of the Planning Authority.
10. Any planting failing to become established within five years shall be replaced in
the following planting season with others of similar size, species and number to
the satisfaction of the Council as Planning Authority.
Reason - In the interests of visual amenity and to ensure the satisfactory long-
term implementation of the proposed planting scheme.
11. A minimum of two months prior to the commencement of development, a site-
specific Construction Environmental Management Plan (CEMP) which shall
include a Construction Method Statement (CMS) shall be submitted to and
approved by the Council as Planning Authority in consultation with key
stakeholders as deemed appropriate.  The CEMP must also include a Pollution
Prevention Plan (PPP), Invasive Management Plan (IMP), Site Waste
Management Plan (SWMP), Site Access Management Plan (SAMP),
Construction Exclusion Zone (CEZ), Construction Traffic Management Plan
(CTMP), Environmental Management Plan (EMP). Proposed measures for bog
restoration methods, monitoring and ongoing long-term aftercare and
maintenance shall be included.  Measures to ensure the public road network is
kept free from mud or debris shall also be required.  The CEMP will remain a live
document, any working practices deemed to be having an adverse impact on
ecology or the environment will be the subject of revision.  All revisions must be
submitted to the Planning Authority as soon as reasonably practicable. 
Thereafter the development shall be fully undertaken in accordance with the
agreed CEMP.
Reason - In the interest of protecting environmental quality and of biodiversity. 
To minimise any associated adverse landscape and visual impact of the above
ground elements and protect the character and visual amenity of the immediate
and surrounding countryside and associated nature and cultural heritage
conservation interests.
12. Prior to the commencement of the development hereby approved, an
independent and suitably qualified Ecological Clerk of Works (ECoW) shall be
appointed at the developers' expense. Details of this appointment shall be
subject to the prior written agreement of the Council as Planning Authority.  The
appointed person will remain in post for the duration of construction and post
construction site restoration of the proposed development.  The ECoW shall have
responsibility for the following:

Page 12

(a) Overseeing the implementation of the Construction Environmental
Management Plan (CEMP) approved by this permission.
(b) Authority to stop operations or to alter construction methods should there be
any works occurring which are having an adverse impact on the natural
heritage.
(c) Prior to the commencement of development, they shall provide an
environmental / ecological toolbox talk for construction staff.
(d) They will have authority to amend working practices in the interests of
natural heritage. Any amendments shall be submitted to the Council as
Planning Authority as an addendum to the approved CEMP.
(e) They shall make fortnightly visits to the development site during construction
works at a time of their choosing. No notification of this visit is required to be
given to the developer or contractor.
(f) Within 10 working days of the end of each calendar month, they are
required to submit a detailed monthly report for the review of the Planning
Authority in consultation with Scottish Environment Protection Agency
(SEPA) for the duration of development.
(g) They shall notify the Council as Planning Authority in writing of any
requirement to halt development in relation to this condition as soon as
reasonably practicable.
The above shall be implemented throughout the construction, (including re-
instatement and de-commissioning of the construction compounds) hereby
approved unless otherwise agreed in writing with the Council as Planning
Authority.  The CEMP shall contain a site-specific Construction Method
Statement (CMS) which will provide concise details for the implementation of the
CEMP for site operatives
Reason - To avoid habitat damage and safeguard natural heritage interests.
13. Measures to protect animals from being trapped in open excavations and/or pipe
and culverts shall be implemented for the duration of the construction works of
the development hereby approved.  The measures may include creation of
sloping escape ramps for animals, which may be achieved by edge profiling of
trenches/excavations or by using planks placed into them at the end of each
working day and open pipework greater than 150 mm outside diameter being
blanked off at the end of each working day
Reason - In order to prevent animals from being trapped within any open
excavations.
14. A minimum of two months prior to the commencement of development, a
Detailed Peat Management Plan shall be submitted for the written approval of the
Council as Planning Authority, in consultation with SEPA and the Council's
Biodiversity/Tree Officer, and all work shall be carried out in accordance with the
agreed plan.

Page 13

Reason - In the interests of protection of existing peatland.
15. A minimum of two months prior to the commencement of development, an
updated Habitat Management Plan shall be submitted for the written approval of
the Council as Planning Authority, in consultation the Council's Biodiversity/Tree
Officer, and all work shall be carried out in accordance with the agreed plan.
Reason - In the interests of protecting environmental quality and of biodiversity.
16. The conclusions and recommended action points within the supporting
Ecological Appraisal (October 2022) (drawing number 14) and Habitat Survey
(October 2022) (drawing number 15) submitted and hereby approved shall be
fully adhered to, respected, and undertaken as part of the construction phase of
development.
Reason - In the interests of protecting environmental quality and of biodiversity.
17. Prior to the commencement of the development hereby approved, final details of
the proposed boundary fencing for the site shall be submitted for the written
agreement of the Council as Planning Authority.  For the avoidance of doubt the
fencing will be required to be deer proofed.  The scheme as subsequently agreed
shall be implemented prior to the completion or bringing into use of the
development, whichever is the earlier.
Reason - In the interests of protecting environmental quality and of biodiversity.
18. Prior to the commencement of development, the developer shall provide full
written details of a scheme for mitigating any potential effects on reptiles on the
site during the construction and operation of the energy storage project.  This
shall include:
The deployment and searching of artificial reptile refugia to allow the capture and
relocation to a suitable and safe area of reptiles within the site.  Such measures
to be undertaken during the reptile active period of May to October (inclusive).
After an agreed period with no reptile captures, the site shall be cleared outward
to an agreed methodology from the site centre to allow any remaining/undetected
reptiles to disperse into adjacent habitats.
The site shall then be maintained with no vegetation cover until construction
works commence.
Habitat clearance works shall be undertaken during the reptile's active phase i.e.,
April - October (inclusive).
Details of proposals for the creation of reptile hibernacula within the site.
Reason - In the interests of protecting environmental quality and of biodiversity.

Page 14

19. Development shall not commence on site until a detailed sustainable urban
drainage system (SUDS) has been submitted for the further written agreement of
the Council as Planning Authority, in consultation with SEPA where necessary. 
The scheme shall be developed in accordance with the technical guidance
contained in The SUDS Manual (C753) and the Council's Flood Risk and Flood
Risk Assessments Developer Guidance and shall incorporate source control.  All
works shall be carried out in accordance with the agreed scheme and be
operational prior to the bringing into use of the development.
Reason - To ensure the provision of appropriate and effective drainage for the
site.
20. Prior to the commencement of the development hereby approved, details of the
specification and colour of the proposed external finishing materials to be used
shall be submitted to and agreed in writing by the Council as Planning Authority. 
The scheme as agreed shall be implemented prior to the completion or bringing
into use of the development, whichever is the earlier.
Reason - In the interests of visual amenity; to ensure a satisfactory standard of
local environmental quality.
21. In the event the hereby approved development fails to store electricity on a
commercial basis for a continuous period of 12 months, then it shall be deemed
to have permanently ceased to be required.  In such an event, the development
shall be decommissioned, and the relevant parts of the site brought into an
agreed condition within such timescale as agreed in writing by the Council as
Planning Authority.
Reason - To ensure the facility is removed from the site at the end of its
operational life, to ensure no adverse impact on the visual amenity of the area
and a satisfactory standard of local environmental quality.
22. The restoration of the site shall be completed in full within 12 months of its
decommissioning and shall be undertaken in full accordance with the submitted
restoration scheme to be approved under conditions 23 and 24 of this permission
and shall thereafter be maintained to the satisfaction of the Council as Planning
Authority.
Reason - In the interests of visual and residential amenity.
23. Within 6 months of the date of this decision notice, a detailed decommissioning
and restoration scheme for the application site shall be submitted to and
approved in writing by the Planning Authority.  The scheme shall set out the
means for restoring the site to blanket bog following the removal of the
components of the development.  The applicants shall obtain written confirmation
from the Planning Authority that all decommissioning has been completed in
accordance with the approved scheme and (unless otherwise dictated through

Page 15

the grant of a new planning permission for a similar form of development) the
restoration of the site shall be implemented in accordance with the approved
details and in accordance with the timescales outlined in condition 22 of this
permission and in any case before the expiry of the time period set by condition 3
of this planning permission.
Reason - In the interests of visual and residential amenity.
24. Prior to the commencement of the final restoration and re-instatement of the
application site as required by conditions 22 and 23 of this permission a detailed
scheme with final contours and an aftercare management plan for the site shall
be submitted to and approved in writing by the Planning Authority.  Thereafter the
approved scheme shall be implemented in full.
Reason - To ensure that final contours and an updated restoration plan and
aftercare plan are submitted prior to the site ceasing operation thereby ensuring
appropriate restoration in the interests of visual amenity and to minimise impacts
on the landscape
25. The approved bond or financial instrument shall be maintained throughout the
duration of the operation of the development hereby approved.  At five-yearly
intervals (as a minimum) from the commencement of the development, an
independent review of the approved bond or financial instrument shall be carried
out and submitted to the Council as Planning Authority.  The Council as Planning
Authority may direct that the approved bond or financial instrument be amended
if this is necessary to ensure that funds remain sufficient to cover the removal of
all development granted by this permission and the site's restoration.
Reason - To ensure that at all times there are sufficient funds available to ensure
that the removal of all development and site restoration can occur.
Justification
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.
Procedural Notes
None.
Informatives
1. Under Section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,

Page 16

which may result in enforcement action being taken.  Please use the form
attached herewith.
2. As soon as practicable after the development is complete, the person who
completes the development is obliged by Section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the Planning Authority written
notice of that position.  Please use the form attached herewith.
3. This development will require the 'Display of notice while development is carried
out', under Section 27C(1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013, as amended.  The form of the notice is set out in
Schedule 7 of the Regulations and a draft notice is included for your guidance. In
accordance with Regulation 41 the notice must be:
 Displayed in a prominent place at or in the vicinity of the site of the
development
 Readily visible to the public
 Printed on durable material.
4. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request. 
The Fees Charter is available on our website www.pkc.gov.uk.  
The Council has two months to consider the information.  You should therefore
submit the required information more than two months before your permission
expires.  We cannot guarantee that submissions made within two months of the
expiry date of your permission will be able to be dealt with before your
permission lapses.
5. An application for Building Warrant may be required.
6. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as
amended (section 1), it is an offence to remove, damage or destroy the nest of
any wild bird while that nest is in use or being built. Planning permission for a
development does not provide a defence against prosecution under this Act.
7. The applicant is reminded that, should any protected species be present a
licence may be required from NatureScot to disturb a protected species. Failure
to obtain a licence may constitute a criminal act under the Habitats Regulations
and penalties are severe for non-compliance.

Page 17

8. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive.  Trees and scrub are present on the application site and are to
be assumed to contain nesting birds between the above dates. The applicant is
reminded that, under the Wildlife and Countryside Act 1981, as amended
(section 1), it is an offence to remove, damage or destroy the nest of any wild
bird while that nest is in use or being built.  Planning permission for a
development does not provide a defence against prosecution under this Act.
9. The applicant should take note of the information and advice contained within the
consultation response from Scottish Water.
10. The applicant should take note of the information and advice contained within the
consultation response from Natural Gas.
11. There is a Section 75 legal obligation associated with this planning permission. A
copy is available to view on the Council's Public Access portal.
Background Papers
Letters of representation 0
Authors
Name Designation Contact Details
Gillian Peebles Planning Officer
(Majors)
01738 475300 
developmentmanagement@pkc.gov.uk
Approved
Name Designation Date
Sean Panton Team Leader (Major
Applications and Enforcement)
19 February 2025