Perth and Kinross Council 
Planning and Placemaking Committee - 14 October 2026 
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 26/285) 
Proposal: S42 application to modify condition 7 (flood risk assessment) of
permission 25/01441/42M 
Location: Morris Leslie, Errol Airfield, Grange, Errol, Perth, PH2 7TB 
Ref. No: 26/00943/42M
Ward No: P1 - Carse of Gowrie 
Summary 
This report recommends approval of the application as the development is considered
to comply with the relevant provisions of the Development Plan and there are no
material considerations apparent which outweigh the Development Plan. 
Background and Description of Proposal 
1 This application relates to the development approved under planning permission
16/00999/AMM for 240 dwellings, a local centre, sports pitch and play area. The
proposal seeks to amend Condition 7 (Flood Risk Assessment) attached to
planning permission 25/01441/42M, which represents the most recent Section 42
(S42) approval for the development. Specifically, the applicant seeks to amend the
condition to allow the required Flood Risk Assessment to be submitted within two
years of the date of this permission, rather than within the timescale currently
specified which is 6 months. As planning permission 25/01441/42M supersedes
previous permissions insofar as the approved conditions are concerned, this
proposal must be assessed against the wording and requirements of Condition 7
attached to that permission. The wording of the current condition is set out below: 
2 Within 6 months of the date of this consent, an updated Flood Risk Assessment
shall be submitted to and agreed in writing by the Planning Authority. The Flood
Risk Assessment shall include detailed designs of the proposed access road
over the Pow of Errol. Additionally, details shall include garden levels, finished
floor levels and soffit levels of all structures above ordnance datum. The details
as agreed shall thereafter be implemented concurrent with development. 
3 Reason - To reduce the risk of flooding.

Page 2

4 The site is located within the settlement boundary of Grange/Errol Airfield in the
Perth and Kinross Local Development Plan 2 (2019) (LDP2) and is recorded as
having planning permission for housing. The predominantly flat site extends to
approximately 58.3 hectares, 0.75km northeast of Errol village. It forms part of
the disused Errol Airfield facility which provides buildings for small businesses
and there are some residential properties to the north of the site. 
5 The site is bound to the north by the C484 Errol to Grange road, to the east by
the remaining airfield area and to the west by a burn and farmland. The south of
the site is contained by reed beds and the River Tay, which is a designated
Special Protection Area (SPA), is a further 300 metres away. Access to the site
will be via a new main access road to the west that was approved under planning
permission16/01491/FLL in July 2017. 
6 Development of the road has commenced and provided access to a temporary
medical centre that was approved under planning permission 18/00628/FLL. 
7 Planning Permission in Principle (PPP) was approved in October 2010
(05/02418/IPM) and extended in January 2014 (13/01823/FLM). Detailed
permission was granted in July 2017 for 240 dwellings, a local centre, sports pitch
and play area within the northern half of the PPP site (16/00999/AMM).
Development of this site has commenced with the establishment of the approved
acoustic bund along the northern boundary of the site. 
Site History 
8 05/02418/IPM Development of sustainable village. Approved against
recommendation by Development Control Committee November 2008 with
decision issued after the signing of a Legal Agreement October 2010. 
9 13/01823/FLM Variation of condition no 1 of planning permission 05/02418/IPM
to extend the time limit for a further 3 years. Approved by Development
Management Committee January 2014. 
10 16/00999/AMM Mixed use development comprising the erection of 240
dwellinghouses/garages, erection of commercial elements, provision of open
space/play provision, associated infrastructure and other associated works
(approval of matters specified in conditions 13/01823/FLM). Approved by
Planning & Development Management Committee July 2017. 
11 16/01491/FLL Formation of access, landscaping and associated works in
association with 16/00999/AMM. Approved by Planning & Development
Management Committee July 2017. 
12 20/00169/AMM Section 42 application to modify condition 15 (contamination) of
permission 16/00999/AMM. Approved by Planning and Development
Management Committee on 29 July 2020.

Page 3

13 22/01827/AMM Section 42 application to modify condition 10 (noise mitigation) of
permission 20/00169/AMM. Approved by Planning and Development
Management Committee on 22 February 2023. 
14 25/01441/42M Section 42 to modify condition 8 (finished floor levels) of
permission 22/01827/AMM. Approved by Planning and Placemaking Committee
on 11 March 2026. 
Environmental Impact Assessment 
15 An EIA Report was not required to be submitted with the proposal as the nature
and type of proposal falls below the EIA thresholds. 
Pre-Application Consultation 
16 The Pre-Application Consultation (PAC) requirements have been fulfilled in
association with the submission of planning application 16/00999/AMM and there
is no further PAC needed procedurally in relation to this Section 42 application. 
Development Plan 
17 The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance. 
National Planning Framework 4 
18 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies. 
This strategy sets out how to improve people’s lives by making sustainable,
liveable and productive spaces.  NPF4 has an increased status over previous
NPFs and comprises part of the statutory development plan. 
19 The Council’s assessment of this application has considered the following policy
of NPF4: 
• Policy 22: Flood Risk and Water Management 
Perth and Kinross Local Development Plan 2019 
20 The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance.

Page 4

21 The principal relevant policy is; 
• Policy 52: New Development and Flooding 
Statutory Supplementary Guidance 
• Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021) 
National Guidance 
22 The Scottish Government expresses its planning policies through Planning
Notes, Creating Places, Designing Streets, National Roads Development Guide
and a series of Circulars in addition to NPF4. Those relevant are listed below. 
Creating Places 2013 
23 Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places. 
Designing Streets 2010 
24 Designing Streets is the policy statement in Scotland for street design and
changes the emphasis of guidance on street design towards place-making and
away from a system focused upon the dominance of motor vehicles. It was
created to support the Scottish Government’s place-making agenda, alongside
Creating Places. 
National Roads Development Guide 2014 
25 This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision. 
Local Place Plans 
26 Local Place Plans are community-led plans setting out proposals for the
development and use of land and set out a community’s aspirations for its future
development. The application site lies within ‘Errol’ Local Place Plan. The LPP
raises no issues in respect of the consideration of this application. 
Consultations 
27 As part of the planning application process the following bodies were consulted:

Page 5

External 
28 Perth Scone Airport – no comments. 
Internal 
29 Development Plan – no comments. 
30 Biodiversity – no comments. 
31 Transportation and Development – no objections. 
32 Development Contributions Officer – no comments. 
33 Structures and Flooding – no objection. 
Representations 
34 No representations were received. 
Additional Statements 
Screening Opinion EIA not required 
Environmental Impact Assessment (EIA):
Environmental Report
not required 
Appropriate Assessment under Habitats
Regulations
Habitats Regulations Appraisal
completed
AA not required 
Design Statement or Design and Access
Statement
not required 
Report on Impact or Potential Impact eg
Flood Risk Assessment
not required 
Appraisal 
35 Section 42(1) of the Town & Country Planning (Scotland) Act 1997 (as amended)
relates to applications for planning permission for the development of land
without complying with conditions subject to which a previous permission was
granted. 
36 Section 42(2) requires that the Planning Authority shall consider only the
question of the condition(s) subject to which planning permission should be
granted, and: 
(a) If they decide that planning permission should be granted subject to
conditions differing from those subject to which the previous permission was
granted, or that it would be granted unconditionally, they shall grant
planning permission accordingly;

Page 6

(b) If they decide that planning permission should be granted subject to the
same conditions as those subject to which the previous permission was
granted, they shall refuse the application. 
37 The determining issues in this case are whether the proposal complies with
Development Plan policy or if there are any other material considerations which
justify a departure from that policy. The Development Plan comprises NPF4, the
Perth and Kinross Local Development Plan 2019 and statutory supplementary
guidance. The relevant policy considerations are outlined in the policy section
above and are considered in more detail below.  In terms of other material
considerations, this involves considerations of the Council’s other approved
policies and supplementary guidance. 
Principle 
38 The principle of the development subject of the application has been previously
established through the approval of the extant planning permission
(16/00999/AMM). The principle of the development is therefore well-established
and is not reviewed as part of this S42 application. It is noted that since the
original planning permission approval there has been a change to the
Development Plan through National Planning Framework 4 (2023) and Local
Development Plan 2 in 2019. The changes within the Development Plan are,
however, not significant in relation to the proposed changes to this S42
application. The amendment of Condition 7 is not in itself considered to be
contrary to the general terms of the Development Plan, however, consideration
must be given to the specific characteristics of the amendment and whether any
adverse impacts are calculated. 
39 The applicant proposes to amend the timeframe associated with Condition 7
(Flood Risk Assessment). Condition 7 currently requires an updated Flood Risk
Assessment to be submitted to and approved in writing by the Planning Authority
within six months of the date of the consent. The applicant now seeks to extend
this timeframe from six months to two years, with the remainder of the condition
remaining unchanged. 
40 Accordingly, the applicant proposes that Condition 7 be revised as follows: 
41 Within two years of the date of this consent, an updated Flood Risk Assessment
shall be submitted to and approved in writing by the Planning Authority. The
Flood Risk Assessment shall include detailed designs of the proposed access
road over the Pow of Errol. Additionally, details shall include garden levels,
finished floor levels and soffit levels of all structures above Ordnance Datum. The
details as approved shall thereafter be implemented concurrent with
development. 
42 Reason - To reduce the risk of flooding.

Page 7

Flooding 
43 The Council's Structures and Flooding Team has reviewed the proposed
variation to Condition 7 and raises no objection. It is considered that the revised
condition will continue to ensure that an updated Flood Risk Assessment,
including details of finished floor levels, garden levels and the proposed access
road crossing, is submitted for approval prior to implementation. Subject to
compliance with the revised condition, the proposal is considered to accord with
NPF4 Policy 22 and LDP2 Policy 52, which seek to ensure that flood risk is
appropriately assessed and managed. 
Design, Layout and Visual Amenity 
44 The proposed modification to Condition 7 will have no impact on the approved
and under construction layout, design or visual amenity. 
Landscape 
45 The proposed modification to Condition 7 will have no impact on the local
landscape. 
Roads and Access 
46 The proposed modification of Condition 7 does not have any direct or significant
impact on the road network. 
Natural Heritage and Biodiversity 
47 The proposed modification to Condition 7 will have no impact on the biodiversity
of the area. 
Developer Contributions 
48 No contributions are required by this S42 application. 
Delivery of the development 
49 The development has a lengthy planning history, with permission in principle first
granted in 2010 and approval of matters specified in conditions granted in 2017.
Whilst the development has been lawfully commenced, progress on site appears
to have been limited and significant elements of the approved development
remain undelivered. The development has also been the subject of a number of
subsequent Section 42 permissions to amend individual conditions. Given the
considerable period that has elapsed since the original permission and
subsequent approval of matters specified in conditions, it is considered important
that the development is now progressed and delivered within a reasonable
timeframe. In these circumstances, it is not considered appropriate that the
current Section 42 application should have the effect of granting a fresh

Page 8

implementation period beyond that established by planning permission
25/01441/42M. Having regard to the age of the initial permission and the limited
progress made to date, the Planning Authority's position is that any further
extension of the implementation period would require specific and significant
justification. 
Other Matters 
50 The 16/00999/AMM permission had a number of pre-commencement planning
conditions or elements of conditions that are no longer relevant as they have
since been approved in advance of construction commencing in 2019. It is good
practice, when approving a S42 application, to update the conditions to meet
current regulations and requirements. Similarly, any conditions that still require to
be addressed or adhered to should remain and reference should be made to
detail or specification approved as part of the condition approval process for the
existing AMSC. Several conditions, as outlined in the recommendation section
below, have been amended to align with current practice, and the incorporation
of previous Section 42 approvals ensures that all relevant modifications are
included and recognised as part of this approval. 
Pre-Commencement Conditions and Notice of Initiation 
51 Prior to the commencement of development associated with this planning
application, all pre-commencement conditions must be agreed in writing with the
Planning Authority. In addition, a Notice of Initiation must be submitted, advising
of the intended start date for the approved development. This is to ensure that all
necessary requirements are in place before works commence and to provide
clear communication regarding the commencement of development. 
52 For the purposes of Section 27 of the Town and Country Planning (Scotland) Act
1997, as amended, development is deemed to have lawfully commenced only
when any material operation forming part of the approved proposal is carried out.
As such, commencement can only be established where the works undertaken
clearly fall within the statutory definition of material operations and are consistent
with the approved development plans and conditions. 
Economic Impact 
53 The proposed modification will not have an impact on the local economy. 
Legal Agreements 
54 None required. A Section 75 Legal Agreement is already in place for affordable
housing provision, education contributions, transport infrastructure contributions,
open space, play area, sports pitch provision and maintenance. It is future-
proofed for S42 applications so will not require modification in light of this
proposal.

Page 9

Direction By Scottish Ministers 
55 Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application. 
Conclusion and Reasons for Recommendation 
56 To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations and none has been found that would justify overriding the
Development Plan.  Accordingly, the proposal is recommended for approval
subject to the following conditions. 
Recommendation   
Approve the application subject to the following conditions: 
Conditions and Reasons for Recommendation 
1. The development hereby approved shall be commenced not later than 11 March
2029. If development has not lawfully commenced by that date, the approval of
matters specified in conditions lapses. 
Reason - In order to ensure the development to which this approval of matters
specified in conditions relates is commenced in line with permission granted
under 25/01441/42M, to ensure the approved scheme is developed timeously
and in accordance with Section 41(1)(c) of the Town and Country Planning
(Scotland) Act 1997. 
2. Prior to the occupation of any residential plot, all matters regarding access, car
parking, road layout, design and specification, including the disposal of surface
water, shall be in accordance with the standards required by the Council as
Roads Authority. 
Reason - In the interest of vehicle and pedestrian safety and in accordance with
the policies of the adopted Development Plan. 
3. The detailed landscaping and planting scheme, including the sports pitch as
approved (Drawing References: 20/00169/55; 20/00169/56; 20/00169/57;
20/00169/58) under planning reference 20/00169/AMM, shall be implemented
fully within one calendar year of the lawful commencement of development and
thereafter maintained for the lifetime of the development.  Any planting failing to
become established within five years shall be replaced in the following planting
season with others of similar sizes and species.

Page 10

Reason - In the interests of visual amenity: to ensure a satisfactory standard of
local environmental quality and in pursuance of suitably satisfying placemaking
policy criteria of the Development Plan. 
4. The children's play areas as approved under planning reference 20/00169/AMM
(Drawing Reference: 20/00169/62) shall be laid out and equipped in accordance
with the Planning Authority's current criteria for play area provision within six
months of the commencement of development of the site.  The play area and its
facilities/equipment shall be made available to the public on completion of
installation and shall thereafter be maintained for the lifetime of the development. 
For the avoidance of doubt only one equipped play area for 4-8 & 8-14 years
which complies with the Council's Play Standards shall be provided within the
site. All other proposed play areas should be unequipped. 
Reason - In the interests of residential amenity and to ensure the satisfactory
provision and implementation of a children's play area. 
5. Within four weeks of the date of this permission or prior to any further works
being undertaken, whichever is the earlier, an updated detailed Phasing
Strategy, supported by appropriate plans, shall be submitted to and approved in
writing by the Council as Planning Authority.  The updated Phasing Strategy
shall include: 
i. the timing and number of dwellings to be developed within each phase;
ii. the timing and delivery of infrastructure, including paths, open space and
landscape specification;
iii. the timing and location of any temporary construction compounds and
associated site facilities; and
iv. the programme for the implementation of landscaping and open space
provision. 
Thereafter, the development shall be carried out in accordance with the
subsequently approved Phasing Strategy.  The landscaping and planting
associated with each phase shall be undertaken concurrently with the
construction of that phase and completed prior to the occupation of the final
dwelling within that phase.  Any proposed amendment to the approved Phasing
Strategy shall be submitted to and approved in writing by the Council as Planning
Authority prior to implementation, and the development shall thereafter proceed
in accordance with the revised approved Phasing Strategy. 
Reason - In order to ensure the satisfactory implementation and completion of
the development. 
6. For the avoidance of doubt, the commercial area identified on the approved
Masterplan under planning permission 16/00999/AMM is indicative only.  This
permission does not grant approval for the detailed layout, scale, design,
appearance or use of any buildings or structures within that area.  Any

Page 11

commercial development within the identified area shall be the subject of a
separate planning application and shall not commence unless planning
permission has first been granted by the Planning Authority. 
Reason - To clarify the extent of the permission hereby granted and to ensure
that the detailed assessment of any future commercial development is
undertaken by the Planning Authority. 
7. The sustainable urban drainage system (SUDS) hereby approved, drawing
reference 20/00169/74, shall be carried out in accordance with the approved
scheme and shall be fully operational prior to the occupation of the first
dwellinghouse within the development.  Thereafter, the system shall be retained
and maintained for the lifetime of the development. 
Reason - In the interests of best practise surface water management: to avoid
undue risk to public safety and flood risk. 
8. Within two years of the date of this permission, an update Flood Risk
Assessment shall be submitted to and agreed in writing by the Planning
Authority.  The Flood Risk Assessment shall include detailed designs of the
proposed access road over the Pow of Errol. Additionally, details shall include
garden levels, finished floor levels and soffit levels of all structures above
ordnance datum.  The details as agreed shall thereafter be implemented
concurrent with development. 
Reason - To ensure that the proposed development does not increase the risk of
flooding to the development or to existing receptors. 
9. The Finished Floor Level of all properties shall be a minimum of 10.06 metres
Above Ordnance Datum (AOD) and no property shall be occupied unless this is
achieved. 
Reason - To reduce the risk of flooding. 
10. All existing trees and hedging within the site and on the boundaries shall be
retained. The development shall fully comply with, respect and remain in full
accordance with BS5837 2012: 'Trees in relation to construction, demolition and
construction. Recommendations'. 
Reason - To ensure a satisfactory standard of local environmental quality. 
11. A 3-metre-high landscape bund at the northern boundary as shown in approved
Drawing Reference 76 (14088 (PL) 603) shall be put in place prior to occupation
of any dwellinghouse in Housing Area H1 of the development. 
Reason - To ensure a satisfactory standard of local environmental quality. 
12. Prior to the completion of the first dwellinghouse hereby approved, a detailed

Page 12

specification of the proposed landscaping of the bund shall be submitted for the
further approval of the Planning Authority.  The detail as subsequently approved
shall be carried out and completed prior to occupation of the tenth dwellinghouse
and thereafter maintained. 
Reason - In the interests of residential amenity. 
13. All plant or equipment shall be so enclosed, attenuated and/or maintained such
that any noise therefrom shall not exceed Noise Rating 35 between 0700 and
2300 hours daily, or Noise Rating 25 between 2300 and 0700 hours daily, within
any neighbouring residential property, with all windows slightly open, when
measured and/ or calculated and plotted on a rating curve chart. 
Reason - To ensure a satisfactory standard of local environmental quality. 
14. Servicing of and deliveries to any commercial premises shall be carried out
between 0700 and 1900 Monday to Sunday and at no other time to the
satisfaction of the Council as Planning Authority. 
Reason - To ensure a satisfactory standard of local environmental quality. 
15. The Construction Traffic Management Scheme (CTMS) contained in document
reference 20/00169/63 and hereby approved shall be fully implemented and
adhered to during construction. Restrictions of construction traffic to approved
routes and the measures shall be put in place to avoid other routes being used.
Heavy construction traffic should avoid the use of Murie, Inchcoonans, Errol,
Grange and Inchture Level Crossings. 
Reason - In the interest of road safety. 
16. The level and location of recycling facilities hereby approved under document
reference 20/00169/65 shall be implemented in full prior to the occupation of the
first dwelling. 
Reason - In the interests of the sustainable disposal of waste. 
17. Prior to any further works being undertaken on site in relation to Phases 1 to 5,
as approved by Application for Matters Specified Permission 16/00999/AMM, an
evaluation for the potential of the site to be affected by contamination by a
previous use should be undertaken. An intrusive investigation should be
undertaken to identify;   
i. the nature, extent and type(s) of contamination on the site;  
ii. measures to treat/remove contamination to ensure the site is fit for the use
proposed;  
iii. measures to deal with contamination during construction works;  
iv. condition of the site on completion of decontamination measures.

Page 13

Prior to the completion or bringing into use of any part of the development the
measures to decontaminate the site shall be fully implemented in accordance
with the scheme subsequently agreed by the Council as Planning Authority.
Verification that the scheme has been fully implemented must also be submitted
to the Council as Planning Authority. 
For the avoidance of doubt, no further development will be permitted within the
red line area approved for development under Planning Permission in Principle
ref: 05/02418/IPM, as amended by Planning Permission in Principle ref:
13/01823/IPM, without a separate intrusive investigation being undertaken in
compliance with the requirements of this condition. 
Reason - To prevent harm to human health and pollution of the environment in
accordance with the aims and objectives of the Development Plan. 
18. No removal of hedgerows, trees or shrubs or works to or demolition of buildings
or structures that may be used by breeding birds shall take place between 1st
March and 31st August inclusive, unless a competent ecologist has undertaken a
careful, detailed check of vegetation for active birds' nests immediately before the
vegetation is cleared and provided written confirmation that no birds will be
harmed and/or that there are appropriate measures in place to protect nesting
bird interest on site.  Any such written confirmation should be submitted to the
Planning Authority for approval. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
19. No works which include the creation of trenches, culverts or the presence of
pipes will commence until measures to protect animals from becoming trapped in
open excavations and/or pipes and culverts are submitted to and approved in
writing by the Planning Authority.  The measures could include, but are not
restricted to, creation of sloping escape ramps from trenches and excavations
and securely sealing open pipework at the end of each working day. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
20. If the development hereby approved, having commenced in 2019, is suspended
for more than 12 months, the approved ecological measures secured through the
applicants Biodiversity Study of April 2016 (document reference 20/00169/70)
shall be reviewed and, where necessary, amended and updated. The review
shall be informed by further ecological surveys commissioned to; 
i. establish if there have been any changes in the presence and/or abundance
of protected species and 
ii. identify any likely new ecological impacts that might arise from any changes. 
Where the survey results indicate that changes have occurred that will result in
ecological impacts not previously addressed in the approved scheme, the original
approved ecological measures will be revised and new or amended measures,

Page 14

and a timetable for their implementation, will be submitted to and approved in
writing by the Council as Planning Authority prior to the commencement of
development.  Works must then be carried out in accordance with the revised
approved ecological measures and timetable. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
21. Where the approved development is to proceed in a series of phases, further
supplementary ecological surveys for protected species shall be undertaken to
inform the preparation and implementation of corresponding phases of ecological
measures required through the applicants Biodiversity Study of April 2016
(document reference 20/00169/70).  The supplementary surveys shall be of an
appropriate type for the above habitats and/or species and survey methods shall
follow national good practice guidelines. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
22. Prior to the occupation and use of the approved development the developer
shall, at their own expense, promote a Traffic Regulation Order (TRO) from the
site entrance to the existing 30mph zone to the West of the site, on the Station
Road approach to Errol. 
Reason - In the interest of promoting sustainable travel. 
23. No part of the development shall be occupied until a Residential Travel Plan
(RTP), aimed to encourage more sustainable means of travel, has been
submitted and approved in writing by the Council as Planning Authority in
consultation with the Roads Authority.  The RTP will have particular regard to
provision for walking, cycling and public transport access to and within the site
and will identify the measures to be provided, the system of management,
monitoring, review, reporting and the duration of the plan. 
Reason - In the interest of promoting sustainable travel. 
24. The external lighting plan hereby approved under document references
20/00169/67, 20/00169/68 and 20/00169/69 shall be fully implemented and
adhered to during both the construction and operational phases. 
Reason - To minimise light pollution during both the construction and operational
phases. 
25. Prior to any further works being undertaken, the developer shall ensure that a
restriction is to be placed within the title deeds to all residential property
confirming the provision of a voluntary agreement to the restriction on access
between April - August in sensitive areas adjacent to the reedbeds.  Evidence
that the restriction has been incorporated into the title deeds shall be submitted
to the Planning Authority, in consultation with NatureScot, for approval in writing.

Page 15

Reason - In the interests of protecting environmental quality and of biodiversity. 
26. Prior to the occupation of any of the units on the site, the details relating to the
location, design and maintenance of signage hereby approved under drawing
references 20/00169/60 and 20/00169/61 in respect of access to the sensitive
areas of reedbeds shall be fully implemented by the developer. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
27. The details hereby approved under document number 20/00169/45, in respect to
the preparation, content and publicity through leaflets relating to the restriction of
access to the sensitive areas of reedbeds shall be distributed to the approved
dwellings in accordance with the agreed timescale. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
28. No development shall be occupied on any phase of the site until the local access
road network improvements approved under planning permission 16/01491/FLL
has been implemented and made operational to mitigate the traffic implications of
the development, to the satisfaction of the Council as Planning Authority. 
Reason - In the Interest of vehicle and pedestrian safety. 
29. Prior to the completion of any residential plot, details of the bus stops shown in
the Housing Layout Plan approved under document references 20/00169/47 and
20/00169/48 shall be submitted to the Council as Planning Authority for approval,
in consultation with the Council's Public Transport Unit.  The agreed detail shall
thereafter be implemented prior to the completion of the 50th dwelling 
Reason - In order to ensure that associated local sustainable infrastructure
improvements are undertaken to adequately accommodate the impact of the
development proposed. 
30. Details relating to the location, design and maintenance of the priority signage at
the Inchmichael Cutting and approved under document reference 20/00169/36
shall be fully implemented prior to the occupation of any units on the site. 
Reason - In the interest of vehicle and pedestrian safety. 
Justification 
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan.  
Procedural Notes 
None.

Page 16

Informatives 
1. Under Section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development.  A failure to comply with this statutory requirement
would constitute a breach of planning control under Section 123(1) of that Act,
which may result in enforcement action being taken.  Please use the form
attached herewith. 
2. This development will require the 'Display of notice while development is carried
out', under Section 27C(1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013, as amended.  The form of the notice is set out in
Schedule 7 of the Regulations and a draft notice is included for your guidance. In
accordance with Regulation 41 the notice must be: 
- Displayed in a prominent place at or in the vicinity of the site of the
development 
- Readily visible to the public 
- Printed on durable material. 
3. The applicant is advised that in terms of Sections 56 of the Roads (Scotland) Act
1984 he/she/they must obtain from the Council, as Roads Authority, consent to
open an existing road or footway prior to the commencement of works. 
Information on junction types, requirements for Vehicular Access consents (VA1)
and application forms are available at www.pkc.gov.uk/vehicleaccess.  Advice
on the disposal of surface water should be sought at the initial stages of design
from Scottish Water and the Scottish Environment Protection Agency. 
4. The applicant is advised that in terms of Sections 21 of the Roads (Scotland) Act
1984 he/she/they must obtain from the Council as Roads Authority Road
Construction Consent (RCC) to construct a new road prior to the commencement
of roadworks.  Advice on the disposal of surface water must be sought at the
initial stages of design from Scottish Water and the Scottish Environment
Protection Agency.  Please note that a fee is chargeable for the processing of
RCC applications. 
5. The applicants are advised that they must apply to the Roads Authority for
construction consent to form a new street.  All correspondence relating to Road
Construction Consents should be sent to RCC@pkc.gov.uk. 
6. The applicant is advised that the granting of planning permission does not
guarantee a connection to Scottish Water's assets.  The applicant must make a
separate application to Scottish Water Planning & Development Services team
for permission to connect to the public wastewater system and/or water network
and all their requirements must be fully adhered to.

Page 17

7. The applicant is advised that the works may need a license under the Water
(Controlled Activities) Regulations 2005 (CAR).  The applicant should contact
SEPA's Perth Environmental Protection and Improvement Team (Tel: 01738
627989) in regard to this.  The applicant should ensure that all works on site
comply with the best practice guidelines laid out in SEPA's published Pollution
Prevention Guidance, found at www.sepa.org.uk. 
8. The Council's Public Transport Unit in Housing and Communities – Public
Transport should be contacted to clarify the bus service requirements for the
development. 
9. Any further applications should take into account the possible increase of traffic
over all Level Crossings in the area and the impacts this may have on the
reliability and frequency of the rail service. 
10. The presence of protected species, and the extent to which they could be
affected by the proposed development, should be established before works
commence.  Should protected species be identified within the site the developer
should ensure that all appropriate measures required to comply with the relevant
legislation are carried out. 
11. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as
amended, it is an offence to remove, damage or destroy the nest of any wild
birds while that nest is in use or being built.  Planning permission for a
development does not provide a defence against prosecution under this act. 
12. There is a Section 75 legal obligation associated with this planning permission,
which relates to 16/00999/AMM.  A copy is available to view on the Council's
Public Access portal. 
13. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time.  The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request. 
The Fees Charter is available on our website www.pkc.gov.uk.   
The Council has two months to consider the information.  You should therefore
submit the required information more than two months before your permission
expires.  We cannot guarantee that submissions made within two months of the
expiry date of your permission will be able to be dealt with before your
permission lapses. 
14. Application for a new postal address should be made via the Street Naming and
Numbering page on the Perth & Kinross Council website at www.pkc.gov.uk/snn.

Page 18

Please note there is a charge for this service and submission cannot be made
until the relevant Building Warrant has been approved. 
15. The applicant is advised that Perth and Kinross Council have a charging scheme
for recycling and waste bins for new build properties and newly created
dwellings.  Further information can be found at:
https://www.pkc.gov.uk/binrequests 
Background Papers
Letters of representation 0 
Authors
Name Designation Contact Details
Gillian Peebles Planning Officer 01738 475300
developmentmanagement@pkc.gov.uk 
Approved
Name Designation Date
Christine McLaren Team Leader 29/09/2026