Page 1

Perth and Kinross Council 
Planning and Placemaking Committee - 8 July 2026 
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 26/204) 
Proposal: Installation of 49.9MW battery energy storage system (BESS), formation
of SUDS, associated infrastructure and landscaping works 
Location: Land 200 Metres North West of Jamesfield Garden Centre, Newburgh,
Cupar, KY14 6EW 
Ref. No: 26/00067/FLM 
Ward No: P9 - Almond and Earn 
Summary 
This report recommends approval of the application as the proposed BESS is
considered to comply with the relevant provisions of the Development Plan, and there
are no material considerations apparent which outweigh the Development Plan. 
Background and Description of Proposal 
1. The purpose of the facility is to provide a range of stability services to the grid.
BESS are required to compensate for the loss of inertia and other electrical
characteristics resulting from the replacement of thermal generators by
renewable energy generation. 
2. The site is located to the west of an unnamed road which serves the Jamesfield
garden centre, farm shop and restaurant all located to the east. The Abernethy
substation is located to the south and bound by Abernethy Road beyond. 
3. The northern and western boundaries of the site are bound by agricultural fields
with Balgonie Cottage located further to the west. The Abernethy Road, located
to the south of the adjacent substation, runs west to east connecting Abernethy
village to the west and Newburgh to the east. Furthermore, a Scottish Gas
Networks owned high pressure gas transmission pipeline runs west to east 450m
from the application site’s northern boundary. Further  south, the land rises to the
Ochil Hills. 
4. The site itself is within an area of low-lying farmland which is located near the
confluence of the River Earn and the River Tay 1.5km to the north. Topography

Page 2

is relatively flat, if sloping to the northwest. As open and operational arable
farmland there are no significant landscape features within the site, which is
classified as Grade 2 Prime Agricultural Land. Two pylons sit within the site and
others beyond, with overhead lines running northwest to southeast across the
north-eastern part between pylons. A second powerline route between pylons
which sit outwith the site cross above the north-western corner. There are no
core paths running through the site and the nearest core path runs to the north,
outwith the north boundary. It connects Abernethy Primary School to Newburgh.
The nearest buildings are to the east at Jamesfield Garden Centre, farm shop
and restaurant. 
5. The facility is advised to have capacity to power up to circa (c.)161,898 houses
over a 4-hour period and that 20 direct jobs will be created during the
construction period. 
6. The proposal has evolved since initial engagement with the Council, addressing
matters raised during the pre-application process. The proposal includes: 
• 132/33kV Sub-station
• Hardstanding (e.g., for manoeuvring and parking of trucks);
• Access Tracks.
• Up to 48 containerised Battery Storage Units.
• Up to 12 inverter/transformer units.
• Switch Room.
• Subterranean fire water tanks.
• Welfare Unit (with chemical toilet).
• 2.4m Perimeter security fencing.
• CCTV columns.
• Profiled development platform and associated cuttings and embankments
• SUDs pond.
• Landscape works including tree and shrub planting. 
• 1.5 m high timber post and wire perimeter deer proof fencing.
• External artificial lighting to specific work areas.
• An underground cable connection to the substation to the south (c.770m). 
Site History 
7. 25/00014/PAN A Proposal of Application Notice (PoAN) was submitted on
17 September 2025 for the installation of a 49.9MW Battery Energy Storage
System (BESS) and associated infrastructure and landscaping works. The notice
was considered sufficient and the consultation proposals accepted. 
8. 25/01769/SCRN A Screening Request was received and a Screening Opinion
issued by the Council on 16 December 2025 in relation to the installation of a
49.9MW Battery Energy Storage System (BESS) including associated
infrastructure and landscaping. Given the low level of potential impact on the
environment, the proposed development was deemed not to be EIA
development.

Page 3

Environmental Impact Assessment 
9. As noted above an EIA Screening has been undertaken and an Opinion issued
by the Council. The proposal is a Schedule 2 Development in terms of the Town
and Country Planning (Environmental Impact Assessment) (Scotland)
Regulations 2017. In the case of these regulations, planning permission cannot
be granted to “EIA development” unless an environmental impact assessment
has been undertaken. The Screening Opinion (Planning Ref: 25/01769/SCRN)
was issued by PKC on 16 December 2025, which confirmed that the application
would not require to be accompanied by an EIA. The Council is of the opinion
that it does not constitute EIA development, and that sufficient information has
been submitted with the application to enable a determination in consideration of
all relevant environmental matters. These environmental aspects requiring further
consideration, are noise, landscape and visual amenity, trees and biodiversity,
roads and transportation and flood / drainage matters. 
Pre-Application Consultation 
10. Pre application Reference: 25/00025/PREAPM. As a result, the proposed
development was, generally, supported. Given its proximity to the Abernethy
Substation, the choice of site was considered appropriate. However, concerns
were raised regarding the potential impact on landscape character and
appearance, and the necessity for a robust and comprehensive screen planting
scheme.  
11. The proposed development is classed as a Major development in terms of the
Town and Country Planning (Hierarchy of Developments) (Scotland) Regulations
2009; therefore, the applicant was required to undertake formal pre-application
consultation with the local community. 
12. Prior to the submission of the application for planning permission, a Proposal of
Application Notice (PAN) was submitted to Perth and Kinross Council relating to
the intended programme of pre-application consultation. The Council have,
subsequently, agreed the proposed consultation approach. 
13. A public notice was published in a local newspaper, the Perthshire Advertiser, on
25.09.25, and a second notice for a second event on the 27.10.25, meeting
statutory requirements. Following the first public notice, a total of 213 flyers were
locally circulated to further notify the community of the consultation event.
Further, a website was set up with project detail and other information related to
the consultation The first consultation event was held on 9.10.25 and the second
on 6.11.25 both at Williamson Hall, Kirk Wynd, Abernethy. 
Development Plan 
14. The Development Plan for the area comprises National Planning Framework 4
and the Perth and Kinross Local Development Plan 2 (2019) along with its
associated statutory supplementary guidance.

Page 4

National Planning Framework 4 
15. The National Planning Framework 4 (NPF4) is the Scottish Government’s long-
term spatial strategy with a comprehensive set of national planning policies. This
strategy sets out how to improve people’s lives by making sustainable, liveable
and productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan. 
16. The Council’s assessment of this application has considered the following
policies of NPF4: 
• Policy 1: Tackling the Climate and Nature Crises
• Policy 2: Climate Mitigation and Adaptation
• Policy 3: Biodiversity
• Policy 4: Natural Places
• Policy 5: Soils
• Policy 6: Forestry, Woodland and Trees
• Policy 14: Design, Quality and Place
• Policy 29: Rural Development 
Perth and Kinross Local Development Plan 2019 
17. The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance. 
18. The principal relevant policies are, in summary. 
• Policy 1A: Placemaking
• Policy 1B: Placemaking
• Policy 2: Design Statements
• Policy 8: Rural Business and Diversification
• Policy 15: Public Access
• Policy 33A: Renewable and Low Carbon Energy: New Proposals for
Renewable and Low-Carbon Energy
• Policy 35: Electricity Transmission Infrastructure
• Policy 39: Landscape
• Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
• Policy 41: Biodiversity
• Policy 47: River Tay Catchment Area
• Policy 50: Prime Agricultural Land
• Policy 51: Soils
• Policy 52: New Development and Flooding
• Policy 53A: Water Environment and Drainage: Water Environment

Page 5

• Policy 55: Nuisance from Artificial Light and Light Pollution
• Policy 56: Noise Pollution
• Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals 
Statutory Supplementary Guidance
19.
• Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
• Supplementary Guidance - Landscape (adopted in 2020)
• Supplementary Guidance - Placemaking (adopted in 2020) 
Other Material Considerations 
PKC Non-Statutory Guidance
20.
• Planning Guidance - Loch Leven SPA, the Dunkeld-Blairgowrie Lochs SAC
and the River Tay SAC
• Planning Guidance - Planning & Biodiversity
• Supplementary Guidance - Renewable & Low Carbon Energy (draft) 
National Guidance 
21. The Scottish Government expresses its planning policies through Planning
Notes, Creating Places, Designing Streets, National Roads Development Guide
and a series of Circulars in addition to NPF4. Those relevant are listed below. 
Planning Advice Notes 
22. The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal: 
• PAN 69 Planning and Building standards Advice on Flooding
• PAN 75 Planning for Transport 
Creating Places 2013 
23. Creating Places is the Scottish Government’s policy statement on architecture
and place. It sets out the comprehensive value good design can deliver. It notes
that successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places.

Page 6

National Roads Development Guide 2014 
24. This document supports Designing Streets and expands on its principles and is
the technical advice that should be followed in designing and approving of all
streets including parking provision 
Consultations 
26. As part of the planning application process the following bodies were consulted: 
External 
27. SSEN - No objection, subject to conditions relating to the access track ground
levels, the storage of materials and an updated Construction Traffic Management
Plan (CTMP) 
28. Scotland Gas Networks (SGN) - No objection, subject to a condition relating
assessment of potential interference on the adjacent pipeline. 
29. Transport Scotland - No objection, subject to conditions relating to a
Construction Traffic Management Plan (CTMP), details of routes for any
abnormal loads, accommodation measures and temporary traffic control
measures 
30. Perth and Kinross Heritage Trust (PKHT) - No objection, subject to a condition
relating to a Written Scheme of Archaeological Investigation (WSI) 
31. Historic Environment Scotland (HES) - No objection. 
Internal 
32. Environmental Health (Noise Odour) - No objection, subject to conditions
relating to plant enclosure, noise complaints to the Council, external lighting and
construction hours. 
33. Environmental Health (Contaminated Land) - No objection. Advise that review
of the proposals raised no concerns related to historical use of the land and
surrounding area. 
34. Environmental Health (Private Water) - No objection, subject to a condition
relating to the safeguarding the operation, or replacement, of any sceptic tanks
and private water sources 
35. Development Plan - No objection, subject to a condition relating to further
screen planting. 
36. Biodiversity - No objection, subject to conditions relating to: the retention of
trees unless approved, the conclusions and recommendations of the submitted
Biodiversity Study, an updated ecology survey be submitted and approved,

Page 7

measures to prevent animals from being trapped in excavations, and a site
Biodiversity Action Plan. 
37. Roads and Transportation Team - No objection, subject to conditions relating
to: visibility splays, vehicle accesses and passing places, and the submission of
a Construction Traffic Management Strategy. 
38. Planning Enforcement Officer (Trees) - No objection. Advise the revised
landscape scheme is acceptable. 
39. Floods and Structures - No objection, subject to conditions relating to a detailed
design for SuDS, and to ensure that storm water from all paved areas is
disposed of via SuDS. 
Representations 
40. One representation was received, the main issues raised are: 
• Adverse impact due to level of construction traffic.
• Fire safety issues.
• Landscape and visual impact.
• Noise issues.
• Loss of prime agricultural land.
• No community benefits proposed. 
41. These issues are addressed in the Appraisal section of the report. 
Additional Statements 
Screening Opinion EIA not required 
Environmental Impact Assessment (EIA):
Environmental Report
Not required 
Appropriate Assessment under Habitats
Regulations
AA not required 
Design Statement or Design and Access
Statement
Submitted 
Report on Impact or Potential Impact eg
Flood Risk Assessment
Submitted 
Appraisal 
42. Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance
with the provisions of the Development Plan, unless material considerations
indicate otherwise.  The Development Plan comprises NPF4, the Perth and
Kinross Local Development Plan 2019 and statutory supplementary guidance.
The relevant policy considerations are outlined in the policy section above and
are considered in more detail below.  In terms of other material considerations,

Page 8

this involves considerations of the Council’s other approved policies and
supplementary guidance. 
Principle 
43. Policy considerations seeking to assess its suitability in principle are: LDP2
Policies 1A, 1B, Placemaking; 8 Rural Diversification; 33A Renewables and Low
Carbon Energy; 50 Prime Agricultural Land; and 51 Soils. The relevant NPF4
policies are 1 Tackling the Climate and Nature Crises; 2 Climate Mitigation and
Adaptation; and 11 Energy. 
44. The proposal would provide essential energy balancing services to the National
grid, actively contributing towards Scotland's CO2 reduction targets, supporting
the principles of Scotland’s Energy Strategy (SES). Specifically, electricity would
be drawn from the grid at times of low demand, stored and released back as
required. When demand is higher, greater generation from non-renewable
sources is required and energy storage facilities such as that proposed could
reduce reliance on non-renewable resources, thus decreasing CO2 emissions. 
45. NPF4 sets out six overarching spatial principles with “Just Transition” relating to
the construction of renewable energy and their contribution to achieving net zero.
NPF4 in its section on Sustainable Places section emphasises the link to
Scotland’s Climate Change Plan and sets the approach to achieving net zero
emissions by 2045 and making significant progress by 2030. The NPF4 also links
to Scotland’s Energy Strategy and highlights the importance of land and sea to
be critical in delivering renewable energy developments. NPF4 provides detailed
policy on Climate Change and Energy and details developer expectations of how
proposed schemes will accord with the policies set out in the document. The
overarching policy intent in NPF4 is to encourage, promote and facilitate all forms
of renewable energy development onshore and offshore. 
46. Policy 33A of LDP2 and Policies 1, 2 and 11 of NPF4 specifically encourages low
carbon energy solutions where specific grid connection or the use of established
infrastructure can occur. Therefore, on balance, and given the site-specific
reasoning for the location of the battery storage unit, the proposed development
could be supported in principle. In this instance, the grid connection will only
require a total of 253m of underground cabling. Furthermore, consideration must
be given to the finite lifespan of this facility. Whilst the overall operational life will
be some 30 years, minimal disturbance to the site will be required, allowing the
pre-existing land use to resume afterwards. 
Design and Layout 
47. LDP2 Policy 1A: Placemaking, requires new development to positively contribute
to the quality of the surrounding built and natural environment. It further requires
development to accord a series of place making criteria outlined in part B of the
policy. On this basis, the physical nature of the proposal in terms of its design,
layout and physical characteristics, must also be considered.

Page 9

48. In terms of design, the proposed BESS will include containers to be laid out in
rows running south-west to north-east. Each row will be fronted by an access
track, as well as a perimeter track. Access to the ‘compound’ will be from the
northeast via the unnamed road which also serves Jamesfield. There is also an
alternate access point at the southeast. An underground cable will connect the
battery storage facility to its grid connection at the substation directly to the
south. 
49. The battery storage facility is deliberately sited adjacent to the substation. Co-
locating presenting the most viable arrangement and offers a range of benefits by
maximising the efficiency of the battery storage facility and making best use of
the existing grid capacity. The proposals also include a switchroom (15.2m in
length and 3.2m in width), a control room (12.1m in length, 4m in width and 3.2m
high), containers (12.1m in length and 2.4m in width), auxiliary transformers
(1.7m in height and 2.2m in width) and battery storage units (6m in length and
2.8m in width). 
Landscape and Visual Impact 
50. NPF4 Policy 4: Natural Places states that development proposals which by virtue
of type, location or scale will have an unacceptable impact on the natural
environment, will not be supported. Furthermore, development proposals that are
likely to have a significant effect on an existing or proposed European site
(Special Area of Conservation or Special Protection Areas) and are not directly
connected with or necessary to their conservation management are required to
be subject to an “appropriate assessment” of the implications for the
conservation objectives. In this instance, the application site is currently an
agricultural field and is not located within the Green Belt or any other designated
landscape areas. 
51. Perth and Kinross Council LDP2, Policy 39: Landscape states that development
and land use change should be compatible with the distinctive characteristics
and features of Perth and Kinross’s landscapes. Accordingly, development
proposals will be supported where they do not conflict with the aim of maintaining
and enhancing the landscape qualities of Perth and Kinross. 
52. In this instance, a Landscape and Visual Impact Assessment (LVIA) has been
submitted, which states that due to the low-lying form, modest scale of the
proposed development and close visual relationship with Abernethy Substation,
any changes to the landscape character and views would be contained and
highly localised. Furthermore, visibility would be notably restricted by existing
vegetation and built features, and where views are available the proposed
development would appear as an incremental addition to an already modified
setting. 
53. These impacts will be further reduced through a planting strategy which would
provide high levels of additional screening to a proposed development which has
already limited visual impacts. It is proposed to plant both coniferous and
deciduous woodland to strengthen the character and pattern of woodland in the

Page 10

area, adding to the existing characteristic of the baseline landscape. Post
mitigation the magnitude of impact reduces to low given this reduced visibility
and integration into the existing landscape pattern, resulting in a moderate/minor
level of effect. The proposed BESS will result in an extension to the north and
west of the overall extent of BESS development in and around Abernethy.
However, according to the LVIA, the magnitude of change to the Local
Landscape Areas are moderate to minor. Again, this impact is likely to reduce
further once the proposed landscape mitigation is established. Thus, it is
considered that the proposed landscaping scheme mitigates the visual impact of
the proposed development whilst maintaining views over the Tay estuary. 
54. In light of the above, and subject to the maturation of the approved landscape
and planting scheme, the proposed BESS is considered to be in accordance with
NPF4 Policy 4 and LDP2 Policy 39 
Prime Agricultural Land and Soils 
55. In this instance, the relevant policies are LDP2 Policy 50: Prime Agricultural
Land, Policy 51: Soils, and NPF4 Policy 5: Soils. 
56. NPF4 Policy 5 provides for renewable energy development where
decommissioning can be secured. It further states that: 
a)  Development proposals will only be supported if they are designed and
constructed:
i.  In accordance with the mitigation hierarchy by first avoiding and then
minimising the amount of disturbance to soils on undeveloped land;
and
ii.  In a manner that protects soil from damage including from compaction
and erosion, and that minimises soil sealing. 
b)  Development proposals on prime agricultural land, or land of lesser quality
that is culturally or locally important for primary use, as identified by
the LDP, will only be supported where it is for:
i.  Essential infrastructure and there is a specific locational need and no
other suitable site;
ii.  Small-scale development directly linked to a rural business, farm or
croft or for essential workers for the rural business to be able to live
onsite;
iii.  The generation of energy from renewable sources or the extraction of
minerals and there is secure provision for restoration; and
In all of the above exceptions, the layout and design of the proposal
minimises the amount of protected land that is required. 
57.  A detailed soil survey was carried out in November 2025, and a Land Capability
for Agriculture (LCA) report was submitted in support of this planning application.
Given that BESS is defined as renewable energy generation and so, whilst the
site may be Prime Agricultural Land (PAL), development can be considered
acceptable where a Decommissioning Plan is provided secured, which can be

Page 11

secured by condition. (Condition 18). This will ensure that proposed mitigation
measures in terms of prime agricultural land and soils are implemented in full. 
58. LDP2 Policy 50: Prime Agricultural Land states that outside the identified
settlements, development on prime agricultural land will not be permitted, unless
it is necessary to meet a specific established need, such as a major infrastructure
proposal and only when there is no other suitable site available on non-prime
land. Small scale development directly linked to rural business, including
housing, may also be acceptable on prime agricultural land, providing it is
compatible with all other aspects of the policy framework of the Plan and there
are no other suitable non-prime land sites available, and it does not adversely
affect the viability of the agricultural unit. 
59. LDP2 Policy 51: Soils states that the Council seeks to protect soils from damage
such as erosion or compaction. Developments located on areas of good quality
agricultural soils will only be supported where they:  
(a)  minimise impact on soil resources; 
(b)  Implement appropriate soil management measures, particularly for valuable
soils such as good-quality agricultural soils*, and soils with a high organic
content;
(c)  adopt best practice when moving, storing and reinstating soils 
(d)  consider opportunities to re-use soils necessarily excavated from the site. 
60. In this instance, the site is on prime agricultural land (class 2). NPF4 Policy 5
provides for essential infrastructure on prime agricultural land provided that the
layout and design of the proposal minimises the amount of land that is required.
Overall, the proposed BESS will result in a loss of 5 hectares of medium-term
loss of Class 2 land. Furthermore, it is anticipated that the proposed BESS has
the potential to supply 161,898 homes over 4 hours and given that the proposed
BESS is located in an area that has had several industrial elements introduced to
the landscape over the last 20 years. This being the case and given that the
proposed development has included appropriate soil management measures, the
predicted loss in Class 2 land is not considered to be significant. Therefore, the
proposed BESS is in accordance with LDP2 Policy 50: Prime Agricultural Land
and Policy 51: Soils. 
Residential Amenity 
61. NFP4 Policy 23 (e) states that development proposals that are likely to raise
unacceptable noise issues will not be supported. 
62. LDP2 Policy 17: Residential Areas, highlights that areas of residential and
compatible uses inside settlement boundaries will see existing residential
amenity protected and, where possible, improved. 
63. This application includes 48 containerised battery storage units, 12
inverters/transformer units, a switch room, subterranean fire water tank, welfare
unit, CCTV, and external lighting. The containers will be set in rows. An existing

Page 12

substation is immediately to the south and there are several other consented
renewable infrastructure projects and BESS’s in the locality. 
64. The closest residential property is approximately 350 metres to the southwest. In
light of this distance the submitted Noise Impact Assessment considers there will
be no adverse impact on residential amenity. 
65. LDP2 Policy 55: Nuisance from Artificial Lights and Light Pollution states that
consent will not be granted for proposals where the lighting would result in
obtrusive and/or intrusive effects. The Council may secure the regulation of
lighting installations and their maintenance through the use of conditions
attached to the granting of planning permission. In order to ensure that no loss of
residential amenity results from any of the proposed external lighting, condition
has been included (Condition 10). 
66. LDP2 Policy 56: Noise Pollution states that there will be a presumption against
the siting of development proposals which will generate high levels of noise in the
locality of existing or proposed noise sensitive land uses and similarly against the
locating of noise sensitive uses near to sources of noise generation. 
67. The submitted Noise Impact Assessment (NIA) has assessed the noise impact of
this proposed BESS and cumulative effects of the five consented developments
and a proposed development. Predicted noise levels at Noise Sensitive
Receptors (NSRs) are concluded to meet the adopted daytime and night-time
criteria at the closest (worst-affected) NSR by a comfortable margin in all octave
bands. The NIA advises that there will be no detrimental impact on noise
sensitive receptors from the operation of the proposed BESS, including
cumulatively with other known developments. 
68. Overall, there are no adverse noise issues. However, in order to further protect
residential amenity, conditions are recommended in relation to plant or
equipment enclosure, noise complaints to the Council, construction working
hours. (Conditions 8, 9, and 11). Subject to compliance with conditions, the
proposed BESS is considered to be in accordance with NPF4 Policy 23, and
LDP2 Policies 17, 55, and 56 
Roads and Access 
69. LDP2 Policy 15: Public Access states that development proposals that would
have an adverse impact upon the integrity of any (including proposed) core path,
disused railway line, asserted right of way or other well-used route and
connectivity proposals identified in the Regional Transport Strategy and Delivery
Plan will not be permitted. The policy seeks to preserve the amenity of existing
public footpaths. Core Path ABNY/1 is located nearly 500m to the north of the
site. An assessment of the potential for visual effects on popular routes in the
area has been undertaken. For the Core Path 40/1, the LVIA confirms that
visibility would only be possible from around half of the path, and this view would
generally be oblique, especially while travelling north, with only a short section of
the path would generate direct views when travelling south. When viewing the

Page 13

development from the north the existing substation would be seen in the
background. The magnitude of change is considered to be low, resulting in a
moderate level of effect. 
70.  Furthermore, As a mitigation measure, the proposed landscape planting scheme
includes vegetation along northwest corner, extending north-east to provide year-
round screening. In addition, an outer band of deciduous trees will provide a
more natural and softer edge enhancing the visual character of the area. In light
of this, it is considered that the proposed development is in accordance with
LDP2 Policy 15. 
71. LDP2 Policy 60A: Existing Infrastructure, sees existing transport infrastructure
identified, and encouragement given to the retention and improvement of these
facilities provided the improvements are compatible with adjoining land uses. 
72. All development proposals that involve significant travel generation should be
well-served by, and easily accessible to all modes of transport. In this instance, it
is not considered that the proposed development will involve significant travel
generation, and there are a number of traffic management measures that are
proposed to reduce the impact during the construction period. The Construction
Traffic Management Plan (CTMP) demonstrates that the delivery and
construction/installation period of the proposed BESS is anticipated to take place
over a nine-month period. Access to the site will be taken via an upgraded field
access on the U75 which forms a cul-de-sac to the north and connects with
Abernethy Road to the south via a simple priority T-junction. A condition has
been included to ensure that the CTMP is adhered to in full throughout the
development (Condition 17) 
73. The road forms a two-way single carriageway that varies in width between
approximately 4.1m and 4.5m and is subject to a 40mph speed limit. The
expected vehicle trip generation for the proposed BESS development is expected
to be low and there are a number of traffic management measures that are
proposed to reduce the impact during the construction period. 
74. Generally, the BESS will operate on an unmanned basis. However, it is
understood that the proposed development will generate approximately between
10 and 15 visits per month (20- 30 two-way vehicle movements) to support site
operations and general maintenance activities at the facility. These trips will be
typically made by cars or LGVs (e.g. vans). Whilst the temporary construction
compound will be removed following construction completion, space will be
retained on-site for LGVs to turn around, ensuring that vehicles can enter and
exit in a forward gear. In the interest of road safety and site access, a further two
conditions have been included. (Conditions 15 and 16). In light of the above, and
subject to conditions, it is considered that the proposed development is in
accordance with LDP2 Policies 15 and 60A.

Page 14

Drainage and Flooding 
75. NPF4 Policy 22: Flood Risk and Water Management states that development
proposals at risk of flooding or in a flood risk area will only be supported if they
are for: 
i. essential infrastructure where the location is required for operational
reasons.
ii. water compatible uses.
iii. redevelopment of an existing building or site for an equal or less vulnerable
use; or.
iv. redevelopment of previously used sites in built up areas where the LDP has
identified a need to bring these into positive use and where proposals
demonstrate that long-term safety and resilience can be secured in
accordance with relevant SEPA advice 
76. The protection offered by an existing formal flood protection scheme, or one
under construction, can be taken into account when determining flood risk. 
77. LDP2 Policy 52: New Development and Flooding, states that the Council
supports the actions and objectives to avoid increased, reduce overall, and more
generally manage flood risk in alignment with SEPA Strategies and Plans. NPF4
Policy 22 states that development proposals must have regard to the water
environment, and drainage, including floodwater management, within any
proposal. 
78.  The proposed development is not within an area at risk of flooding and so is out
with flood risk areas that required development to be exceptional or otherwise
compliant with the criteria set out by NPF4 Policy 22. In this instance, a Flood
Risk Assessment (FRA) has been submitted as part of the application. The FRA
has demonstrated that the application site’s flood risk is Low/No Risk from all
sources. Furthermore, the Drainage Strategy is well designed and compliant with
PKC and national guidance, and the SuDS basin and controls are appropriately
sized. Furthermore, PKCs Flood Team consider that maintenance and
construction-phase measures have been satisfactorily addressed 
79. LDP2 Policy 53C: Surface Water Drainage, requires Sustainable Urban Drainage
Systems (SUDS) measures including relevant temporary measures at the
construction Phase. 
80. In this instance, the proposed surface water management strategy with
sustainable drainage principles allow the site to remain free of flooding during
design storm events, whilst ensuring no increase of flood risk to offsite receptors
and ensures no deterioration of the water environment. However, a condition has
been included that prior to any development commences on-site, a detailed
SuDS shall be submitted for approval (Condition 12). Furthermore, an additional
condition has been included to ensure that surface water from all areas of
hardstanding /paving can be disposed of by means of a suitable SuDS (Condition
13). LDP2 Policy 53E. states that all new development must be served either by

Page 15

a satisfactory mains or private water supply complying with the Water (Scotland)
Act 1980 and associated Private Water Regulations, without prejudicing existing
users. It will be the responsibility of the developer to demonstrate that any new
supply is suitable and is safe to be consumed as drinking water in line with the
above act and regulations. In terms of the potential impact on any septic tanks
and soakaways, private water sources, etc Condition 14 has been included to
ensure that detailed measures to safeguard and allow the continued operation of
any private water sources, are submitted for approval. 
81. In terms of a private water supply, the applicant has indicated that they do not
require a connection to a private water supply. In light of thre above, the
proposed BESS is considered to be in accordance with NPF4 Policy 22 and
LDP2 Policies 52,53C and 53 E 
Conservation Considerations 
82. LDP2 Polices 26A, 26B and Policy 7 of NPF4 are considered applicable. The
location is considered a rich archaeological landscape with evidence of activity
spanning across multiple periods with particularly strong evidence of Roman
activity. PKHT are in agreement that there is medium potential for unknown
Buried remains on site. 
83. Furthermore, PKHT also agree with the impacts outlined, in particular the
negative impacts on Carpow Roman Fortress. There is also an accumulative
impact of development that could be considered from a landscape/ setting
perspective. PKHT have strongly recommended that appropriately sited and
designed environmental screening is undertaken, in order to mitigate the visual
impacts on the known historic environment assets. As evidenced and outlined in
the supporting Desk Based Assessment, it is recommended that a programme of
archaeological works assesses the presence/ absence, character, and
significance of archaeological deposits on the site. This has been covered by the
inclusion of Condition 19. In light if the above, and subject to condition, the
proposed BESS is considered to be in accordance with NPF4 Policy 7 and LDP2
Policies 26A and 26B. 
Natural Heritage and Biodiversity 
84. NPF4 Policy 3 Biodiversity states that proposals for local development will
include appropriate measures to conserve, restore and enhance biodiversity, in
accordance with national and local guidance. Measures should be proportionate
to the nature and scale of development 
85. NPF4 Policy 4: Natural Places states that development proposals that are likely
to have an adverse effect on species protected by legislation will only be
supported where the proposal meets the relevant statutory tests. If there is
reasonable evidence to suggest that a protected species is present on a site or
may be affected by a proposed development, steps must be taken to establish its
presence. The level of protection required by legislation must be factored into the

Page 16

planning and design of development, and potential impacts must be fully
considered prior to the determination of any application. 
86. NPF4 Policy 6: Forestry, Woodland and Trees states that development proposals
will not be supported where they will result in adverse impacts on native
woodlands, hedgerows and individual trees of high biodiversity value, or
identified for protection in the Forestry and Woodland Strategy. 
87. The submitted Preliminary Ecological Appraisal Report (PEAR) is considered to
be of good quality and undertaken at the correct time of year. Furthermore, the
PEAR lists comprehensive enhancement measures in accordance with NPF4
and the PKC Planning for Nature Supplementary Guidance. Proposed
enhancement includes planting of c.130m of species rich hedgerows, species
rich wetland planting within the SuDS design, a wildflower mix and further
woodland planting. Furthermore, conditions are recommended requiring an
updated Ecology Study, and measures to prevent animals being trapped are
outlined in full prior to development commencing (Conditions 5 and 6) 
88. LDP2 Policy 40: Forestry, Woodland, and Trees states that Tree Surveys,
undertaken by a suitably qualified professional, should accompany applications
where sites contain trees and that there is a presumption in favour of protecting
woodland resources. 
89. In this instance, it is acknowledged that all existing trees, hedgerows and
woodlands will be retained. With mature trees at the southeast and west
boundary, and several smaller trees along the south boundary, shown on the
planting plan. However, a condition has been included to ensure that retained
trees are fully protected (Condition 3). Furthermore, and in order to provide better
screening, additional hedgerow planting is provided along the north-eastern
edge. In addition, along the western edge, the proposed shelter belts have been
extended with additional tree planting. Following the advice of PKC’s Tree
Officer, light standards have also been introduced along the southern edge.
Overall, light standard planting forms a total of 15% of the proposed planting. 
90. LDP2 Policy 41: Biodiversity states that the Council will seek to protect and
enhance all wildlife and wildlife habitats, whether formally designated/protected
or not. All whilst taking into account the ecosystems and natural processes in the
area. In accordance with NPF4, development proposals for major development
will only be supported where it can be demonstrated that the proposal will
conserve, restore and enhance biodiversity, including nature networks so they
are in a demonstrably better state than without intervention. This will include
future management. 
91. In this instance, conditions have been included that the action points and
recommendations of the submitted Biodiversity Study shall be adhered to and
implemented in full, and that a Site Biodiversity Action Plan is submitted for
approval, prior to development commencing.

Page 17

92. In light of the above, and subject to conditions, the proposed BESS is considered
to be in accordance with NPF4 Policies 3, 4, 6 and LDP2 Policies 40 and 41. 
Low and Zero Carbon Generating Technologies 
93. LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in
New Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of
low and zero-carbon generating technologies. As this proposal includes the
erection of a new building, consideration must be given to this requirement.
Further, NPF4 Policy 2 ‘Climate Mitigation and Adaptation’ requires that
development should be designed to reduce green gas emissions. Given that the
proposed development will include new buildings, LDP2 Policy 32 and NPF4
Policy 2 are relevant. However, given the nature of the proposals, and that the
buildings will not be habitable, heated or cooled, it is considered that the
proposed BESS is in accordance with the Development Plan. 
Grid Connection 
94. The proposed point of connection is the Abernethy Substation, which is located
adjacent to the application site. The connection will take the form of an
underground cable, with an approximate length of approximately 253m. 
Lifespan of Facility / Decommissioning 
95. The Applicant is committed to decommissioning and restoring the Site to its
previous agricultural use at the end of the projects predicted 40-year lifespan. In
the event the decision was made that the Site could be repowered, then a new
consenting process would be required. 
96. Prior to decommissioning, a Restoration and Decommissioning Plan (RDP) will
be produced to reflect the current legislation and policy at that point in time and
will be agreed with the relevant statutory authorities. 
97. The lifespan of the facility is not specifically stated. However, based on the
expected lifespan of similar facilities approved within Perth and Kinross and the
expected battery life, a lifespan of approximately 40 years is anticipated. As
such, Condition 18 has been included to ensure that should the energy storage
facility not be in use for a continuous period of 12 months, or at the conclusion of
this term, that the site is then decommissioned and re-instated to its original use. 
Developer Contributions 
98. The Developer Contributions Guidance is not applicable to this application, and
therefore, no contributions are required in this instance.

Page 18

Economic Impact 
99. The economic impact of the proposal is likely to be minimal and limited to the
construction phase of the development. However, the proposal will support local
renewable energy generation by helping balance fluctuations of intermittent
energy generation. It will assist in the creation of a national grid asset of regional
significance for the Perth and Kinross area. 
100. No information has been provided on how the local community will benefit from
this application to satisfy the requirement in NPF4 Policy 11(c) (excluding
consideration of direct community benefit payments). Consideration should be
given to consideration of local priorities, maximising use of local supply chains
and opportunities for local training. Consideration should be given to how the
development can support NPF4 Policy 25. 
Variation of Application Under Section 32A 
101. This application was varied prior to determination, in accordance with the terms
of section 32A of the Town and Country Planning (Scotland) Act 1997, as
amended. The variations incorporate changes to landscaping and planting, and
ecological surveys 
Planning Obligations And Legal Agreements 
102. None required. 
Direction By Scottish Ministers 
103. Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions
by the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application. 
Conclusion and Reasons for Recommendation 
104. To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations, and none has been found that would justify overriding
the Development Plan. Accordingly, the proposal is recommended for approval
subject to the following conditions. 
Recommendation   
Approve subject to the following conditions:

Page 19

Conditions and Reasons for Recommendation 
General 
1. This planning permission will last only for three years from the date of this
decision notice, unless the development has been lawfully started within that
period. 
Reason: This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the
Planning (Scotland) Act 2019. 
2. No works shall commence on site until the applicant has undertaken an
assessment and modelling as required to determine the interference levels on
the Scotland Gas Networks’ adjacent pipeline from steady state and fault
conditions of the electrical infrastructure associated with the proposed
development, taking into consideration the nearby SGN pipeline and associated
equipment. This includes: 
• Any steady state AC or DC Interference 
• Fault Condition Interference in accordance with the limits in BS EN50122-
1:2022 
•  If required, the applicant shall also design appropriate mitigation to ensure
that levels of AC and DC interference are within acceptable limits (as
described by SGN/PM/ECP/2, BS EN ISO 18086:2020 and BS EN
50162:2004). The results of this modelling (and mitigation, if required) will be
submitted for the prior written approval of Scotland Gas Networks and the
Planning Authority before any work commences on site. 
Reason: In the interest of worker safety and to safeguard the integrity of the
adjacent SGN pipeline 
Biodiversity and Trees 
3. All trees on site, other than those marked for felling on the approved plans, shall
be retained. 
Reason: In the interests of protecting environmental quality and of biodiversity 
4. The conclusions and recommended action points within the supporting
biodiversity survey submitted and hereby approved (document 25 relates) shall
be fully adhered to, respected and undertaken as part of the construction phase
of development. 
Reason: In the interests of protecting environmental quality and of biodiversity 
5. An updated ecology survey will be required prior to the commencement of works,
if works have not commenced within 24 months of the date of the ecology survey

Page 20

approved as part of this permission. The updated survey shall be submitted to
the Council as Planning Authority for written agreement and works shall not
commence until after such written agreement has been issued by the Council. 
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981). 
6. Measures to protect animals from being trapped in open excavations and/or pipe
and culverts shall be implemented for the duration of the construction works of
the development hereby approved. The measures may include creation of
sloping escape ramps for animals, which may be achieved by edge profiling of
trenches/excavations or by using planks placed into them at the end of each
working day and open pipework greater than 150mm outside diameter being
blanked off at the end of each working day. 
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981). 
7. Prior to the commencement of the development hereby approved, a Site
Biodiversity Action Plan including the location, quantity, specification and
maintenance requirements for the recommended biodiversity enhancement
measures within the supporting biodiversity survey submitted and hereby
approved (document 25 relates) shall be submitted for the further written
agreement of the Council as Planning Authority.  It shall include: 
a) Species rich hedgerow and woodland planting. 
b) Species rich wetland planting within the SUDs design and between the pond
and BESS site.
c) Enhancement of suitable habitat for badgers by planting trees and
hedgerows along site boundaries and leaving undeveloped areas within the
site boundary as rough grassland 
d) A section on artificial lighting of site boundaries (both during construction
and operation) including positioning of cowls, or timers to prevent spill on to
woodland edges, hedgerows and watercourses.
e) At least five Schwegler 1F bat boxes and one barn owl box
f) Commitment to submit all species records from ecological survey reports to
NBN Gateway. 
Thereafter, the agreed scheme shall be maintained in a reasonable condition for
the life of the development. 
Reason: In the interests of employing best practice ecology and to ensure there
is no adverse impact on any protected species as identified under the Wildlife
and Countryside Act (1981).

Page 21

Environmental Health 
8. All plant or equipment shall be so enclosed, attenuated and/or maintained such
that any noise therefrom shall not exceed Noise Rating 35 between 0700 and
2300 hours daily, or Noise Rating 20 between 2300 and 0700 hours daily, within
any neighbouring residential property, with all windows slightly open, when
measured and/ or calculated and plotted on a rating curve chart.   
Reason: In the interest of residential amenity. 
9. In the event, that justified complaints for noise are received by the Council, the
applicant at their own expense, shall employ an independent and suitably
qualified consultant to carry out a Noise Assessment from the development. The
appointed consultant and methodology for the Noise Assessment shall be
submitted to and approved in writing by the Planning Authority in consultation
with Environmental Health within 28 days of being notified of the complaint.
Within 28 days of approval of appointed consultant and methodology, a Noise
Assessment shall be submitted outlining mitigation and recommended timescales
for delivery. Thereafter, all mitigation measures shall be implemented within the
timescales recommended. 
Reason: In the interest of residential amenity 
10. All external lighting shall be sufficiently screened and aligned so as to ensure that
there is no direct illumination of neighbouring land and that light spillage beyond
the boundaries of the site is minimised to a degree that it does not adversely
affect the amenity of the neighbouring land. 
Reason: In the interest of residential amenity 
11. Construction work shall be limited to Monday to Friday 0700 hours to 1900 hours
and Saturday 0800 hours to 1300 hours with no noisy works out with these times
or at any time on Sundays. 
Reason: In the interest of residential amenity. 
Flood and Drainage 
12. Development shall not commence on site until a detailed sustainable urban
drainage system (SUDS) has been submitted for the written agreement of the
Council as Planning Authority, in consultation with SEPA where necessary.  The
scheme shall be developed in accordance with the technical guidance contained
in The SUDS Manual (C753) and the Council’s Flood Risk and Flood Risk
Assessments Developer Guidance and shall incorporate source control. All
works shall be carried out in accordance with the agreed scheme and be
operational prior to the bringing into use of the development.   
Reason: In the interests of best practice surface water management; to avoid
undue risks to public safety and flood risk.

Page 22

13. Storm water drainage from all paved surfaces, including the access, shall be
disposed of by means of suitable a Sustainable Urban Drainage System to meet
the requirements of best management practices. 
Reason: In the interests of best practice surface water management; to avoid  
undue risks to public safety and flood risk. 
Private Water Supply 
14. Prior to the commencement of the development hereby approved, details of the
location and measures proposed for the safeguarding and continued operation,
or replacement, of any septic tanks and soakaways, private water sources,
private water supply storage facilities and/or private water supply pipes serving
properties in the vicinity, sited within and running through the application site,
shall be submitted to and approved in writing by the Council as Planning
Authority. The subsequently agreed protective or replacement measures shall be
put in place prior to the development being brought into use and shall thereafter
be so maintained insofar as it relates to the development hereby approved. 
Reason: In the interest of residential amenity and water quality. 
Roads and Transportation 
15. Prior to the commencement of the development hereby approved, full visibility
splays, as detailed in the Transport Statement, shall be provided along the
channel line to the left and right of the access, at a set-back of 2.4 metres
measured 1.05m above the road level to the standard and specification required
by the Council as Roads Authority. The visibility splays shall be physically formed
on the ground and any existing fences, walls, hedges or other means of
enclosure or obstructions within the splays shall be removed and relocated out
with the splays.  Once formed, the visibility splays shall be permanently retained
thereafter, and no visual obstruction of any kind shall be permitted within the
visibility splays so formed. 
Reason: In the interests of road safety; to ensure an acceptable standard of
construction within the public road boundary. 
16. Prior to commencement of any development on site, a detailed design for the
passing place and vehicle accesses on the U75 shall be submitted to and
approved in writing by the Planning Authority in consultation with the Roads
Authority.  The passing place and vehicle access, as approved in writing, shall
be constructed prior to any construction works taking place on site, in
accordance with the approved details. 
Reason: In the interests of road safety and free flow traffic. 
17. The Construction Traffic Management Strategy provided as part of the
application, and hereby approved, shall be adhered to at all times throughout the
development

Page 23

Reason: In the interests of road safety 
Facility Lifespan 
18. In the event the hereby approved development fails to store electricity on a
commercial basis for a continuous period of 12 months, or after operating for
more than 40 years, then it shall be deemed to have permanently ceased to be
required. In such an event, the development shall be decommissioned and the
relevant parts of the site reinstated within such a timescale as agreed by the
Council as Planning Authority. 
Reason: To ensure the facility is removed from the site at the end of its
operational life, and to protect the character of the countryside, the visual
amenity of the area and nature conservation interests. 
Archaeology and Cultural Heritage 
19. Development shall not commence until the developer has secured the
implementation of a programme of archaeological work in accordance with a
Written Scheme of Archaeological Investigation (WSI) which has been submitted
to and agreed in writing by the Council as Planning Authority, in consultation with
Perth and Kinross Heritage Trust (PKHT). Thereafter, the developer shall ensure
that the programme of archaeological works is fully implemented including that all
excavation, preservation, recording, recovery, analysis, publication and archiving
of archaeological resources within the development site is undertaken. Should
the archaeological works, as required by the WSI, identify a requirement for post-
excavation analysis, the development as approved shall not be occupied or
brought into use until a Post-Excavation Research Design (PERD) has been
submitted to and agreed in writing by the Council as Planning Authority, in
consultation with PKHT. The PERD shall be carried out in complete accordance
with the approved details. Furthermore, the developer shall afford access at all
reasonable times to PKHT or a nominated representative and shall allow them to
observe work in progress 
Reason: In the interest of protecting archaeological interest within the site. 
Justification 
The proposal is in accordance with the Development Plan and there are no
material reasons which justify departing from the Development Plan. 
Procedural Notes 
Not applicable to this application

Page 24

Informatives 
1. The applicant is advised to refer to Perth & Kinross Council’s Supplementary
guidance on Flood Risk and Flood Risk Assessments 2021 as it contains advice
relevant to your development. 
2. The applicant should ensure that any existing wayleaves for maintenance or
repair to existing private water supply or septic drainage infrastructure in the
development area are honoured throughout and after completion of the
development. 
3. The applicant shall ensure the private water supply for the dwellinghouse/
development complies with the Water Scotland Act 1980 (Section 63), The
Private Water Supplies (Scotland) Regulations 2006 and The Water Intended for
Human Consumption (Private Supplies) (Scotland) Regulations 2017.  Detailed
information regarding the private water supply, including the nature, location and
adequacy of the source, any storage tanks/ pipework and the filtration and
disinfection treatment proposed to ensure provision of an adequate and
consistently wholesome water supply shall be submitted to Perth and Kinross
Council Environmental Health in line with the above Act and Regulations. 
4. The applicant should note the site access requirements contained in the
guidance note - National Fire Chiefs Council’s guidance for Battery Energy
Storage Systems. Building Standards technical handbook 2022 – Dead End
Route – Fire and rescue service vehicles should not have to reverse more than
20m from the end of an access road.  Where the dead-end route is more than
20m long turning facilities should be provided. 
5. Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the
Planning Authority prior written notification of the date on which it is intended to
commence the development. A failure to comply with this statutory requirement
would constitute a breach of planning control under section 123(1) of that Act,
which may result in enforcement action being taken. 
6. As soon as it is practicable after the development is complete, the person who
completes the development is obliged by section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the planning authority written
notice of that position. 
7. An application for a Building Warrant may be required. 
8. This planning permission will last only for three years from the date of this
decision notice, unless the development has been started within that period (see
section 58(1) of the Town and Country Planning (Scotland) Act 1997 (as
amended). 
9. Trees and scrub are likely to contain nesting birds between 1st March and 31st
August inclusive. Trees and scrub are present on the application site and are to

Page 25

be assumed to contain nesting birds between the above dates. The applicant is
reminded that, under the Wildlife and Countryside Act 1981, as amended
(section 1), it is an offence to remove, damage or destroy the nest of any wild
bird while that nest is in use or being built. Planning permission 
10. The applicant is reminded that, should any protected species be present, a
license may be required from NatureScot to disturb a protected species. Failure
to obtain a license may constitute a criminal act under the Habitats Regulations
and penalties are severe for non-compliance. 
11. This development will require the 'Display of notice while development is carried
out', under Section 27C (1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013. The form of the notice is set out in Schedule 7 of
the Regulations and a draft notice is included for your guidance. According to
Regulation 41 the notice must be: 
• Displayed in a prominent place at or in the vicinity of the site of the
development.
• Readily visible to the public.
• Printed on durable material. 
12. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time. The required information must be
submitted via the ePlanning portal if your original application was lodged that
way, otherwise send it to us at developmentmanagement@pkc.gov.uk.  Please
be aware that a fee is payable in respect of each request made, though there is
no limit to the number of conditions that can be discharged in a single request.
The Fees Charter is available on our website www.pkc.gov.uk.  The Council has
two months to consider the information. You should therefore submit the required
information more than two months before your permission expires. We cannot
guarantee that submissions made within two months of the expiry date of your
permission will be able to be dealt with before your permission lapses. 
13. The developer is advised to contact Sophie Nicol, Historic Environment Manager
(Tel: 01738 477027) Perth and Kinross Heritage Trust, to discuss terms of
reference for work required. 
14. The applicant is advised that, in terms of Sections 56 of the Roads (Scotland) Act
1984, he/she/they must obtain from the Council, as Roads Authority, consent to
open an existing road or footway prior to the commencement of works.
Information on junction types, requirements for Vehicular Access consents (VA1)
and application forms are available at www.pkc.gov.uk/vehicleaccess. Advice on
the disposal of surface water should be sought at the initial stages of design from
Scottish Water and the Scottish Environment Protection Agency.

Page 26

15. The appointed contractor should liaise with Stirling Council to raise these works
on the Scottish Road Works Register and provide confirmation of such to the
Road Authority (Perth and Kinross Council). 
16. It is noted that a geo-environmental report submitted as part of the application
recommends chemical analysis of soils as a precautionary check.  Should any
contamination be identified the Land Quality team should be contacted on 01738
475000 or contaminatedland@pkc.gov.uk for further advice. 
17. The applicant should note the site access requirements contained in the
guidance note - National Fire Chiefs Council’s guidance for Battery Energy
Storage Systems. 
Background Papers
Letters of representation 0 
Authors
Name Designation Contact Details
Alan Atkins Planning Officer (Major) 01738 475300
developmentmanagement@pkc.gov.uk 
Approved
Name Designation Date
Kristian Smith Service Manager
(Development
Management and Building
Standards)
25 June 2026