Perth and Kinross Council 
Planning and Placemaking Committee - 13 May 2026 
Report of Handling by Development Management and Building Standards Service
Manager
(Report No. 26/125) 
Proposal: Formation of a 49.9MW battery energy storage facility comprising battery
storage units, ancillary buildings and equipment access road and
associated works 
Location: Land 300 Metres West of Tir Artair, Killin, FK21 8TX 
Ref. No: 25/00168/FLM
Ward No: P4 - Highland 
Summary 
This report recommends approval of the application as the development is considered
to comply with the relevant provisions of the Development Plan and there are no
material considerations apparent which outweigh the Development Plan. 
Background and Description of Proposal 
1. The proposed application site is located on land 300 Metres West of Tir Artair, Killin.
The Site lies on the northern slopes of Loch Tay. It is located at the eastern end of
the Loch, to the north of the A827, a cross-country route that runs the entire length
of Loch Tay and is approximately 2.2km to the north-east of the town of Killin. It is
1.9 hectares in size and is currently planted with young plantation woodland. It falls
outside of any identified development boundary and lies along the western boundary
of Perth and Kinross Council area which follows the watercourse Allt na Bailce.
Stirling Council area is located to the immediate west of the Site. Part of the site
extends into the Stirling Council area. 
2. The purpose of a Battery Energy Storage System is to store excess energy on the
grid at peak of generation moments and release energy at peak demand moments
of the day. The energy generated is fed directly into the national electricity grid, with
the Point of Connection to the grid being an underground 33kV cable that will run
below the fields and unnamed road into the Killin Primary Substation, which is
approximately 300m to the east of the site. 
3. It is anticipated that the Battery Energy Storage System will be in operation for 30
years. There will be a potential the batteries could be replaced for new ones by half
time of the project's lifespan. Once the project reaches the end of its lifespan, the

Page 2

site will be decommissioned and will be restored to its original condition, with no
lasting harm or structures that would compromise the agricultural productivity of the
site. 
Site History 
4. None. 
Environmental Impact Assessment 
5. An EIA screening has been undertaken. The proposal being a Schedule 2
development in terms of the Town and Country Planning (Environmental Impact
Assessment) (Scotland) Regulations 2017. In the case of these regulations,
prohibition is given to the granting of planning permission to “EIA development”
unless an environmental impact assessment has been undertaken. In this case the
Council has taken the opinion that it is not EIA development, and that sufficient
information has been submitted with the application to enable a determination in
consideration of all relevant environmental matters. These environmental aspects
requiring further consideration, are namely: noise, landscape and visual amenity,
trees and biodiversity, roads and transportation and flood / drainage matters. It
should be noted that the Council requested detailing of the grid connection as this
was not submitted with the initial proposals. Upon receipt of this grid connection, the
Council maintain the view that the project as a whole would not require an EIA to be
undertaken.   
Pre-Application Consultation 
6. The proposed development is classed as a Major development in terms of the Town
and Country Planning (Hierarchy of Developments) (Scotland) Regulations 2009,
and therefore, the applicant was required to undertake formal pre-application
consultation with the local community. 
7. A request for a Proposal of Application Notice was submitted to Perth and Kinross
Council on 9 April 2024. The reply was received on 29 April 2024 confirming that
the proposed consultation process was accepted. This was also sent to Glenlyon
and Loch Tay Community Council and Councilors John Duff, Provost Xander
McDade and Bailie Mike Williamson by email on the 9th of March 2024. 
8. Two in person Public Exhibitions were carried out in McLaren Village Hall, Killin on
24 April 2024 and 21 May 2024. This has been used to inform local residents about
the proposal, while also progressing the Morenish BESS development which will
assist in meeting the National and Local targets for renewable energy and carbon
emission reductions. 
9. More than 525 households and local businesses were directly informed of the
exhibitions via a leaflet mailout or door drop on 11 April 2024 and 7 May 2024 (this
included all households within a 3 km radius of the site).  Adverts in the Perthshire
Advertiser were published on 16 April 2024 and 10 May 2024 to inform the public of
both exhibitions. Details of the project were uploaded on morenishbess.co.uk ,

Page 3

where residents are able to find updates, documentation of the project, ask
questions, make comments and request future updates, prior to and during the
planning application process. 
Development Plan 
10. The Development Plan for the area comprises National Planning Framework 4 and
the Perth and Kinross Local Development Plan 2 (2019) along with its associated
statutory supplementary guidance. 
National Planning Framework 4 
11. The National Planning Framework 4 (NPF4) is the Scottish Government’s long-term
spatial strategy with a comprehensive set of national planning policies.  This
strategy sets out how to improve people’s lives by making sustainable, liveable and
productive spaces.  NPF4 has an increased status over previous NPFs and
comprises part of the statutory development plan. 
12. The Council’s assessment of this application has considered the following policies
of NPF4: 
 Policy 1: Tackling the Climate and Nature Crises
 Policy 2: Climate Mitigation and Adaptation
 Policy 3: Biodiversity
 Policy 4: Natural Places
 Policy 5: Soils
 Policy 6: Forestry, Woodland and Trees
 Policy 7: Historic Assets and Places
 Policy 11: Energy
 Policy 14: Design, Quality and Place
 Policy 22: Flood Risk and Water Management
 Policy 29: Rural Development 
Perth and Kinross Local Development Plan 2019 
13. The Local Development Plan 2 (2019) (LDP2) sets out a vision statement for the
area and states that, “Our vision is of a Perth and Kinross which is dynamic,
attractive and effective which protects its assets whilst welcoming population and
economic growth.” It is the most recent statement of Council policy and is
augmented by Supplementary Guidance. 
14. The principal relevant policies are, in summary: 
 Policy 1A: Placemaking
 Policy 1B: Placemaking
 Policy 5: Infrastructure Contributions
 Policy 6: Settlement Boundaries
 Policy 8: Rural Business and Diversification

Page 4

 Policy 15: Public Access
 Policy 26A: Scheduled Monuments and Archaeology: Scheduled Monuments
 Policy 26B: Scheduled Monuments and Archaeology: Archaeology
 Policy 33A: Renewable and Low Carbon Energy: New Proposals for
Renewable and Low-Carbon Energy
 Policy 35: Electricity Transmission Infrastructure
 Policy 38C: Environment and Conservation: Local Designations
 Policy 39: Landscape
 Policy 40A: Forestry, Woodland and Trees: Forest and Woodland Strategy
 Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and
Development
 Policy 41: Biodiversity
 Policy 47: River Tay Catchment Area
 Policy 52: New Development and Flooding
 Policy 53A: Water Environment and Drainage: Water Environment
 Policy 53C: Water Environment and Drainage: Surface Water Drainage
 Policy 55: Nuisance from Artificial Light and Light Pollution
 Policy 56: Noise Pollution
 Policy 60B: Transport Standards and Accessibility Requirements: New
Development Proposals 
Statutory Supplementary Guidance
15. 
 Supplementary Guidance - Flood Risk and Flood Risk Assessments
(adopted in 2021)
 Supplementary Guidance - Forest & Woodland Strategy (adopted in 2020)
 Supplementary Guidance - Landscape (adopted in 2020) 
PKC Non-Statutory Guidance
16. 
 Planning Guidance - Loch Leven SPA, the Dunkeld-Blairgowrie Lochs SAC
and the River Tay SAC
 Planning Guidance - Planning & Biodiversity
 Supplementary Guidance - Renewable & Low Carbon Energy (draft) 
National Guidance 
17. The Scottish Government expresses its planning policies through Planning Advise
Notes, Creating Places, Designing Streets, National Roads Development Guide and
a series of Circulars in addition to NPF4. 
Planning Advice Notes 
18. The following Scottish Government Planning Advice Notes (PANs) and Guidance
Documents are of relevance to the proposal:

Page 5

 PAN 69 Planning and Building standards Advice on Flooding
 PAN 75 Planning for Transport 
Creating Places 2013 
19. Creating Places is the Scottish Government’s policy statement on architecture and
place. It sets out the comprehensive value good design can deliver. It notes that
successful places can unlock opportunities, build vibrant communities and
contribute to a flourishing economy and set out actions that can achieve positive
changes in our places. 
National Roads Development Guide 2014 
20. This document supports Designing Streets and expands on its principles and is the
technical advice that should be followed in designing and approving of all streets
including parking provision. 
Consultations 
21. As part of the planning application process the following bodies were consulted: 
External 
22. Stirling Council - No objection. However, it is noted that parts of the redline
application boundary, located in the north and south of the site, that extend west of
Alt Na Bailce, lie within the existing Stirling Council area. 
23. Perth and Kinross Heritage Trust - No objection, subject to a recommended
condition to ensure that a programme of archaeological work is carried out. 
24. Scottish Environment Protection Agency - No objection, subject to guidance on
the retention of the areas of wetland on site 
25. Glenlyon Community Council - Objection. The main points raised within the
representation are: 
 Fire and Noxious Gases Hazard. 
 Lack of detail regarding the proposed batteries 
 The proposed development will have an adverse impact on the landscape.
 The proposed development will have an adverse impact on the River Tay SAC 
 Access issues
 Noise issues
 Lack of detail regarding the route of the cable that connects to the substation 
 Lack of fire prevention/control methods. 
26. Stirling Council Roads and Transportation Team - No objection, subject to the
submission of further information and the inclusion of a condition.

Page 6

Internal 
27. Biodiversity - No objection, subject to conditions in relation to the submitted
Biodiversity Action Plan. 
28. Environmental Health (Noise Odour) - Following the submission of further
information in the form of a revised Noise Impact Assessment (NIA|), the
Environmental Health Team have no objection to the proposed development. 
29. Environmental Health (Contaminated Land) - No objection. A search of the
historic records did not raise any concerns regarding ground contamination 
30. Structures and Flooding - No objection. The applicant is advised to refer to Perth
& Kinross Council’s Supplementary guidance on Flood Risk and Flood Risk
Assessments 2021 as it contains advice relevant to this development. 
31. Transportation and Development - No objection, subject to conditions relating to
a Traffic Light and Signage Plan, a maintenance agreement and a Construction
Traffic Management Plan. 
32. Development Plan Team - No objection 
33. Tree Officer - No objection, subject to conditions relating to pre-commencement
and post- planting site meetings. 
Representations 
34. 7 representations (all objections) were received. The main issues raised within the
representations are: 
 Visual impact
 Noise 
 Loss of view
 Out of character 
35. These issues are addressed in the Appraisal section of the report, with the
exception of loss of view, which is not a material planning consideration. 
Additional Statements 
Screening Opinion EIA not required 
Environmental Impact Assessment (EIA):
Environmental Report
Not Required 
Appropriate Assessment under Habitats
Regulations
AA not required 
Design Statement or Design and Access
Statement
Submitted

Page 7

Report on Impact or Potential Impact eg
Flood Risk Assessment
Submitted 
Noise Impact Assessment Submitted 
Transport Statement Submitted 
Ecological Appraisal Submitted 
Woodland Report Submitted 
Landscape and Visual Assessment Submitted 
Biodiversity Action Plan Submitted 
Landscape Strategy Plan Submitted 
Landscape Management Plan Submitted 
Appraisal 
36. Sections 25 and 37(2) of the Town & Country Planning (Scotland) Act 1997 (as
amended) require the determination of the proposal to be made in accordance with
the provisions of the Development Plan, unless material considerations indicate
otherwise.  The Development Plan comprises NPF4, the Perth and Kinross Local
Development Plan 2019 and statutory supplementary guidance. The relevant policy
considerations are outlined in the policy section above and are considered in more
detail below.  In terms of other material considerations, this involves considerations
of the Council’s other approved policies and supplementary guidance.  
Principle 
37. Policy considerations seeking to assess its suitability in principle are: LDP2 Policies
1A, 1B, Placemaking; Policy 8 Rural Diversification; Policy 33A: Renewables and
Low Carbon Energy; and Policy 51 Soils. The relevant NPF4 policies are Policy 1
Tackling the Climate and Nature Crises; Policy 2 Climate Mitigation and Adaptation;
and Policy 11 Energy. 
38. The proposal would provide essential energy balancing services to the National
grid, actively contributing towards Scotland's CO2 reduction targets, supporting the
principles of Scotland’s Energy Strategy (SES). Specifically, electricity would be
drawn from the grid at times of low demand, stored and released back as required.
When demand is higher, greater generation from non-renewable sources is required
and energy storage facilities such as that proposed could reduce reliance on
non-renewable resources, thus decreasing CO2 emissions. 
39. NPF4 sets out six overarching spatial principles with “Just Transition” relating to the
construction of renewable energy and their contribution to achieving net zero.
NPF4Sustainable Places section emphasises the link to Scotland’s Climate Change
Plan and sets the approach to achieving net zero emissions by 2045 and making
significant progress by 2030. The NPF4 also links to Scotland’s Energy Strategy
and highlights the importance of land and sea to be critical in delivering renewable
energy developments. NPF4 provides detailed policy on Climate Change and
Energy and details developer expectations of how proposed schemes will accord

Page 8

with the policies set out in the document. The overarching policy intent in NPF4 is to
encourage, promote, and facilitate all forms of renewable energy development
onshore and offshore. 
40. Policy 33A of LDP2 and Policies 1, 2 and 11 of NPF4 specifically encourages low
carbon energy solutions where specific grid connection or the use of established
infrastructure can occur. Therefore, on balance, and given the site-specific
reasoning for the location of the battery storage unit, the proposed development
could be supported in principle. Furthermore, consideration must be given to the
finite lifespan of this facility. Whilst the overall operational life will be some 50 years,
minimal disturbance to the site will be required, allowing the pre-existing land use to
resume afterwards. 
Design and Layout 
41. LDP2 Policy 1A: Placemaking, requires new development to positively contribute to
the quality of the surrounding built and natural environment. It further requires
development to accord a series of place making criteria outlined in part B of the
policy. On this basis, the physical nature of the proposal in terms of design, layout
and physical characteristics must also be considered.
42. In this instance, the proposed development comprises a battery energy storage
system (BESS) contained within a fenced compound and surrounded by
landscaping. The 15 battery containers, and the rest of the equipment, will be
mounted on concrete beams arranged in a linear fashion across the site in rows.
There will be approximately 6m between each container. The proposed BESS will
consist of several built elements, including inverters, transformers, and a substation.
The inverters are components stored in cabinets, which are generally pale grey or
green in colour and approximately 7,4m in length, 2 m in width, and 2.2 m in height.
The transformers are smaller units of 2.4m in length, 2.4 m in width, and 2.1m in
height. The sub-station will consist of prefabricated cabins depending on the
requirements from the Distribution Networks Operator (DNO). One will be for the
internal connection of the electrical output from the site, with the other required by
the DNO for connection into the wider electricity network. However, these structures
can be, potentially, merged in one building. 
43. Furthermore, a control room will be situated next to the substation buildings near
the northern boundary of the site. The control room will be a single storey building
and will measure up to 26m in length, 7m in width, and 2.9m in height. This will be
dark green in colour. A battery storage rack will be independent, single storey
containers and will measure up to 27.8m in length, 3.1m in width and 3.8m in
height. The compound will be surrounded by a 2.75m palisade green fence, with all
equipment being mounted on concrete beams. The surface of the compound would
be finished with aggregate, with a stronger base during the construction and
maintenance of the proposed development. In addition, infrared security cameras
will be located around both sites, at a height of approximately 4.2m.

Page 9

Landscape and Visual Impact 
44. NPF4 Policy 4: Natural Places states that development proposals which by virtue of
type, location or scale will have an unacceptable impact on the natural environment,
will not be supported. Furthermore, development proposals that are likely to have a
significant effect on an existing or proposed European site (Special Area of
Conservation or Special Protection Areas) and are not directly connected with or
necessary to their conservation management are required to be subject to an
“appropriate assessment” of the implications for the conservation objectives. 
45. Perth and Kinross Council LDP2, Policy 39: Landscape states that development
and land use change, including the creation of new hill tracks, should be compatible
with the distinctive characteristics and features of Perth and Kinross’ landscapes.
Accordingly, development proposals will be supported where they do not conflict
with the aim of maintaining and enhancing the landscape qualities of Perth and
Kinross, or the quality of landscape experience. 
46. The application site is in the Loch Tay local landscape area and would be visible in
the landscape. Policy 38 ‘Environment and Conservation: Local Designations’ of
LDP2 is therefore also relevant.  However, the proposal includes only basic
mitigation measures with a proposed tree belt to screen the proposed development.
A strengthened and more extensive planting scheme would ensure that the
proposed development’s landscape and visual impact is localised and would be
acceptable. The proposed development will introduce an industrial element into a
rural landscape. However, in this instance, there is an existing hydro pressure
pipeline which runs from Ben Lawers Dam to the Finlarig Hydroelectric Power
station, on a north-south axis 91m to the west of the Site. The overhead power lines
and pipeline are glimpsed from the road corridor and already introduce some
modernising and industrial elements into the landscape setting. It is therefore not
considered that the proposed development would be out of character with the area,
subject to sensitive landscaping. 
47. The Loch Rannoch and Glen Lyon National Scenic Area is nearby, with its southern
boundary being around 600 metres north of the application site. Ben Lawyers is
also located 400m to the north. However, the proposed development does not raise
issues of national scale with respect to landscape, visual or cumulative effects. 
48. However, as a result of PKC Tree Officer and Development Plan Team’s
comments, the applicant has submitted a series of revisions to the initially proposed
landscape and planting scheme. In doing so, the applicant has addressed the
issues raised and has provided a landscape scheme which should result in
successful tree & woodland establishment, whilst also providing sufficient screening
of the proposed BESS. 
49. In light of the above, PKC Tree Officer is now satisfied that with retention of the
existing Sitka and the native trees to be introduced, and that the landscape scheme
is capable of integrating the development acceptably into its surroundings.
Therefore, the proposed BESS is now considered to be in accordance with NPF
Policy 4 and LDP2 Policies 38C and 39.

Page 10

Residential Amenity 
50. NFP4 Policy 23 (e) states that development proposals that are likely to raise
unacceptable noise issues will not be supported. 
51. LDP2 Policy 17: Residential Areas, highlights that areas of residential and
compatible uses inside settlement boundaries will see existing residential amenity
protected and, where possible, improved. It is however noted that the site is not in
close proximity to an identified residential area, but there are residential receptors
nearby, namely Fank Cottage. 
52. LDP2 Policy 55: Nuisance from Artificial Lights and Light Pollution states that
consent will not be granted for proposals where the lighting would result in obtrusive
and/or intrusive effects. The Council may secure the regulation of lighting
installations and their maintenance through the use of conditions attached to the
granting of planning permission. 
53. LDP2 Policy 56: Noise Pollution states that there will be a presumption against the
siting of development proposals which will generate high levels of noise in the
locality of existing or proposed noise sensitive land uses and similarly against the
locating of noise sensitive uses near to sources of noise generation. 
54. Due to the nature of this development, there is the potential for noise to impact on
residential amenity. However, the proposed equipment on the site will be highly
efficient and have a low noise output, and given the proposed mitigation measures,
the proposed BESS will have a very limited impact on any nearby sensitive
receptors. 
55. The submitted Noise Impact Assessment (NIA) includes proposed noise mitigation
measures in the form of a 3.5m tall acoustic barrier, to be positioned along the
eastern and southern boundaries of the site, and all inverters are to be fitted with
noise attenuation kits. The Results of the NIA, when taking account of the proposed
mitigation measures, have shown that predicted internal and external noise levels
will be well within World Health Organisation (WHO) and BS 58233 levels.
However, conditions have been included in relation to plant and equipment
enclosure, noise limits from the BESS, the proposed noise mitigation measures,
noise complaints to PKC, and construction working hours. 
56. Furthermore, LDP2 Policy 55: Nuisance from Artificial Light and Light pollution is of
relevance in the assessment of this application. In this instance, there is the
potential for amenity issues in relation to lighting during the construction phase. This
being the case, a condition has been included to ensure that there is no direct
illumination of neighbouring land, and that light spillage is kept to a minimum. 
57. In light of the above, and subject to conditions, the proposed BESS is in accordance
with LDP2 Policies 55 and 56 and NPF 4 Policy 14.

Page 11

Roads and Access 
58. LDP2 Policy 15: Public Access states that development proposals that would have
an adverse impact upon the integrity of any (including proposed) core path, disused
railway line, asserted right of way or other well-used route and connectivity
proposals identified in the Regional Transport Strategy and Delivery Plan will not be
permitted. 
59. In this instance, the site is located on undeveloped land and is proposed to be
served by a new private access track that is accessed from the existing A827 public
road junction to the southwest of the site boundary. The A827 is in the vicinity of the
site access and is subject to the national speed limit (60mph for cars) but does not
have footways or streetlighting. While the BESS site itself is located partially within
the Perth and Kinross Council, the site access junction and construction route along
the A827 are within the Stirling Council boundary. However, Stirling Council’s
Roads Team have not objected to the use of this junction, subject to agreeing a
suitable Construction Traffic Management Plan. This has been covered by the
inclusion of a condition. An additional condition will also be applied to ensure that
the necessary consents are also obtained from Stirling Council. 
60. The site access track is a no - through road, which currently provides access to
Fank Cottage and other undeveloped land. The access track heads north for
approximately 220m before turning east along another 100m section before
reaching the BESS entrance location. The access track continues past this and runs
further east to Fank Cottage. In between the junction with the A827 and the BESS
entrance (270m along the access track), the track is on average approximately 4m
wide. 
61. LDP2 Policy 60A: Existing Infrastructure, sees existing transport infrastructure
identified, and encouragement given to the retention and improvement of these
facilities provided the improvements are compatible with adjoining land uses. 
62. In this instance, it has been has confirmed that the junction visibility splay, as per
the Design Manual for Roads and Bridges (DMRB) is not achievable. Furthermore,
visibility at the existing site access is restricted to the west, with approximately 90m
visibility achievable. This falls short of the 215m required by the DMRB and
presents a serious road safety concern. Therefore, the applicant has proposed that
construction traffic vehicles are managed through traffic management and
temporary traffic lights. The lights would be positioned either side of the junction at a
distance of 215 metres. This would mean that signage would need to be sited within
the PKC boundary. There would also be signals on the existing access track to
Fank Cottage, for when a vehicle is exiting the access junction. This is considered
to be acceptable by PKC Road Network Management.   
63. Furthermore, the existing road, which serves Fank Cottage, will be maintained at all
times throughout the construction and operational phases of the development. For
the construction element, Fank Cottage would need to adhere to the temporary
signals that would be in place, but at no point will the associated access route be
closed or blocked. For the operational element, Fank Cottage would utilise the

Page 12

existing priority junction and access track off the A827, as per the current
arrangement. In light of this, conditional control has been included to secure an
approved Traffic Light and Signage Plan. A further condition has been included to
secure a maintenance agreement for the proposed construction traffic route. 
64. In accordance with the National Fire Chiefs Council’s guidance, at least two
separate access points are required to serve the proposed BESS. In this instance,
the northwestern access point, shown on the proposed site plan, would only serve
as a secondary / emergency access, and would not be used for any construction or
operational vehicle access throughout the lifetime of the application site. This
access would only ever be used in the event of an emergency, whereby fire
vehicles consider that its necessary to enter the site from a different location. 
65. In light of the above, and subject to conditions, the proposed BESS is in accordance
with LDP2 Polices 15 and 60A. 
Drainage and Flooding 
66. NPF4 Policy 22: Flood Risk and Water Management states that development
proposals must have regard to the water environment, and drainage, including
floodwater management, within any proposal.  
67. LDP2 Policy 52: New Development and Flooding, states that the Council supports
the actions and objectives to avoid increased, reduce overall, and more generally
manage flood risk in alignment with SEPA Strategies and Plans. NPF4 Policy 22
states that development proposals must have regard to the water environment, and
drainage, including floodwater management, within any proposal. 
68. A Flood Risk and Drainage Assessment has been submitted with this application,
which has identified all potential sources of flooding in the immediate area. In this
instance PKC Floods and Drainage Team do not have any objections to the
proposed development. Furthermore, a review of SEPA’s fluvial flood map does not
identify the proposed development area to be within any areas of fluvial flooding 
69. Also relevant to the flood risk of the site is LDP2 Policy 53C: Surface Water
Drainage, requires Sustainable Urban Drainage Systems (SUDS) measures
including relevant temporary measures at the construction phase. The proposed
new surface water drainage for the application site is designed to modern standards
which inherently accounts for climate change considerations and exceedance flow
paths. A Drainage Maintenance Schedule will be incorporated into the site
management plan. This will ensure that the drainage systems are kept in good
working order for the lifetime of the development. 
70. Furthermore, the proposed SuDS scheme has been designed to manage the
surface water runoff from the battery storage development area and has been sized
to accommodate the 1:200yr plus 39% climate change event. The development
area will be constructed with permeable materials to allow rainwater to infiltrate
underground, where it will be intercepted by perforated pipework, allowing runoff

Page 13

from semi-permeable / impermeable surfaces into controlled gravel- lined storage
areas, to be located beneath the proposed BESS units. 
71. The internal access tracks will be crowned to allow runoff towards the storage
areas. Perimeter cut-off filter drains will take runoff to the subsurface gravel storage
areas, and, in the case of fire, ensure that all firewater runoff is retained within the
SuDS system. The filter drains and sub-surface gravel storage areas will provide
suitable treatment and attenuation prior to discharge into the existing minor
watercourses. 
72. Given that the applicant has submitted adequate drainage drawings, design and
overall strategy, the proposed BESS is in accordance with LDP2 Policies 52 and
53C, and NPF4 Policy 22. 
Conservation Considerations 
73. Polices 26A and 26B of the LDP2 and Policy 7 of NPF4 are applicable to this
application. 
74. The submitted Historic Environment Desk Based Assessment (DBA) demonstrates
the likely low potential of unknown buried archaeological remains due to recent
forestry planting at this site. In 2015 an archaeological walkover survey was
undertaken, where this site, and a much wider area, were carefully assessed for
any further historic environment assets. However, nothing additional was identified
at this location. 
75. However, there is a known historic sheepfold to the north of site which has been
mentioned in the DBA, but no mitigation proposed for its record. From the plans
submitted this feature within the site boundary will be wholly removed and also
stone wall. Given that the trees are not fully mature, this feature is likely to still
survive within the plantation, and the DBA does not suggest otherwise. 
76. In light of the above, it is recommended that a programme of archaeological works
should take place to record the post medieval sheepfold and any other upstanding
boundaries etc., prior to works commencing on site. This has been covered by the
inclusion of a condition. 
77. Subject to this condition, the proposed development is considered to be in
accordance with LDP2 Policies 26A, 26B and Policy 7 of NPF4. 
Natural Heritage and Biodiversity 
78. NPF4 Policy 3: Biodiversity states that development proposals will contribute to the
enhancement of biodiversity, including where relevant, restoring degraded habitats
and building and strengthening nature networks and the connections between them.
Proposals should also integrate nature-based solutions, wherever possible.
Furthermore, development proposals for national or major development, or for
development that requires an Environmental Impact Assessment will only be
supported where it can be demonstrated that the proposal will conserve, restore

Page 14

and enhance biodiversity, including nature networks so they are in a demonstrably
better state than without intervention. This will include future management. To
inform this, best practice assessment methods should be used. 
79. NPF4 Policy 4: Natural Places states that development proposals that are likely to
have an adverse effect on species protected by legislation will only be supported
where the proposal meets the relevant statutory tests. If there is reasonable
evidence to suggest that a protected species is present on a site or may be affected
by a proposed development, steps must be taken to establish its presence. The
level of protection required by legislation must be factored into the planning and
design of development, and potential impacts must be fully considered prior to the
determination of any application. 
80. LDP2 Policy 40: Forestry, Woodland, and Trees states that Tree Surveys,
undertaken by a suitably qualified professional, should accompany all applications
for planning permission where their sites contain trees and that there is a
presumption in favour of protecting woodland resources. 
81. Further landscaping is proposed including native planting around the site perimeter,
including a 10m wide continuous border of native scrub and tree planting to reduce
the visual impact of the equipment, and to increase biodiversity in this location. In
proposing a linear planting belt, the aim of the landscaping is to ensure that the
surrounding landscape remains as functional as possible with no avoidable loss of
useful space, whilst keeping the screening. As the woodland grows, the linear
structure of the proposed planting will become less obvious, with potential future
self-seeding and assisted seeding from wildlife further softening the appearance of
the proposals. 
82. In order to ensure a satisfactory standard of development in terms of the proposed
planting scheme, conditions have been included, which require the applicant to
arrange both a pre- commencement site meeting and a post – planting meeting with
PKC Tree Officer. 
83. LDP2 Policy 41: Biodiversity states that the Council will seek to protect and
enhance all wildlife and wildlife habitats, whether formally designated/protected or
not, all whilst taking into account the ecosystems and natural processes in the area. 
84. As set out in the PKC Planning for Nature Guidance, and in order for major
applications to satisfy NPF4 Policy 3 a Site Biodiversity Action Plan, which sets out
quantity, locations, techniques, timescales and monitoring arrangements, is
required. In this instance, the submitted Biodiversity Action Plan did not contain the
locations nor quantities of all measures and therefore, a condition to ensure that a
revised Biodiversity Action Plan is submitted for approval, has been included. A
further condition has also been included to ensure that the conclusions and
recommendation of the submitted Biodiversity Study are adhered to and
implemented in full. 
85. A further two conditions have been included at the recommendation of PKC
Biodiversity Officer, which relate to an updated Ecology Study and the requirement

Page 15

of a Construction Environment Management Plan (CEMP) to be submitted for
approval. 
86. In light of the above, and subject to conditions, the proposed development is in
accordance with LDP2 Policies 40, 41, and NPF4 Policies 3, 4. 
Lifespan of Facility 
87. The lifespan of the facility is stated as 30 years. As such, conditional control has
been included to ensure that should the energy storage facility not be in use for a
continuous period of 12 months, or at the conclusion of this term, that the site is
then decommissioned and re-instated to its original use. 
Developer Contributions 
88. Not applicable to this application. 
Economic Impact 
89. The economic impact of the proposal is likely to be minimal and limited to the
construction phase of the development. The proposal will support local renewable
energy generation by helping balance fluctuations of intermittent energy generation.
It will assist in the creation of a national grid asset of regional significance for the
Perth and Kinross area. 
90. No information has been provided on how the local community will benefit from this
application to satisfy the requirement in NPF4 Policy 11(c) (excluding consideration
of direct community benefit payments). Consideration should be given to
consideration of local priorities, maximising use of local supply chains and
opportunities for local training. Consideration should be given to how the
development can support NPF4 Policy 25. 
Grid Connection 
91. Following the recent court case of Raeshaw Farms Ltd v Scottish Ministers [2026],
the Inner House of the Court of Session quashed planning permission for the Wull
Muir wind farm because the decision-maker failed to fully consider the role of the
off-site grid connection. The court held that the Reporter had erred by not carrying
out a fact-specific assessment of whether the wind farm and its grid connection
could together constitute a single “project” for Environmental Impact Assessment
(EIA) purposes. Crucially, the Reporter placed too much weight on the way the
application was framed, rather than examining the real-world position that the wind
farm could not operate, and its claimed benefits could not arise, without a grid
connection. The court also found that it was irrational to rely on the benefits of
renewable electricity generation while ignoring the environmental effects of the
works necessary to realise those benefits. 
92. The judgment does not require grid connections to be included in the same planning
application as generation infrastructure, nor does it require full engineering detail at

Page 16

an early stage. However, it makes clear that, when assessing planning applications
in Scotland, decision-makers must now explicitly address whether grid connections
form part of the wider project and assess their potentially significant cumulative
environmental effects to the extent reasonably possible. Simply deferring grid
impacts to a future consent, without clear reasoning is no longer sufficient. The case
strengthens scrutiny of phased or split consents and has implications beyond wind
farms, affecting any development whose operation depends on later infrastructure
such as grid, network or transport connections. In light of this, and in order for the
Council to assess whether the grid connections form part of the wider project, the
grid connection arrangements have been submitted. This will ensure that the
Council’s decision is robust and that environmental impacts are appropriately
considered. In light of this, the applicant has submitted details of the proposed grid
connection, which will result in 4km of underground cabling to connect to the Killin
substation. This connection is not considered to result in excessive impacts and
would not alter the opinion of the Council as Planning Authority, as discussed in
paragraph 5 of this report, that it would require an Environmental Impact
Assessment to be undertaken. 
Low and Zero Carbon Generating Technologies 
93. LDP2 Policy 32 ‘Embedding Low and Zero Carbon Generating Technology in New
Development’ states that proposals for all new buildings will be required to
demonstrate that at least 10% of the current carbon emissions reduction set by
Scottish Building Standards will be met through the installation and operation of low
and zero-carbon generating technologies. As this proposal includes the erection of
a new building, consideration must be given to this requirement. In this instance,
and given that the proposed ancillary buildings will stand alone, cover an area of
less than 50 square metres and will not be heated, or cooled, there is no
requirement for the applicant to submit a statement to demonstrate compliance with
current carbon emissions reduction standards. 
Variation of Application Under Section 32A 
94. This application was varied prior to determination, in accordance with the terms of
section 32A of the Town and Country Planning (Scotland) Act 1997, as amended. 
The variations incorporate changes to the proposed Landscape Plan, Noise Impact
Assessment and Biodiversity Action Plan. 
Planning Obligations and Legal Agreements 
95. None required. 
Direction By Scottish Ministers 
96. Under the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013, regulations 30 – 33 there have been no directions by
the Scottish Government in respect of an Environmental Impact Assessment
screening opinion, call in or notification relating to this application.

Page 17

Conclusion and Reasons for Recommendation 
97. To conclude, the application must be determined in accordance with the
Development Plan unless material considerations indicate otherwise. In this
respect, the proposal is considered to comply with NPF4, and the adopted Local
Development Plan 2 (2019).  Account has been taken account of the relevant
material considerations, and none has been found that would justify overriding the
Development Plan. Accordingly, the proposal is recommended for approval subject
to the following conditions. 
Recommendation   
Approve, subject to the following conditions: 
Conditions and Reasons for Recommendation 
General 
1. This planning permission will last only for three years from the date of this decision
notice unless the development has been lawfully started within that period. 
Reason - This is a Planning Permission in terms of Section 58 of the Town and
Country Planning (Scotland) Act 1997, as amended by Section 32 of the Planning
(Scotland) Act 2019. 
2. Construction work shall be limited to Monday to Friday 0700 hours to 1900 hours
and Saturday 0800 hours to 1300 hours with no noisy works out with these times or
at anytime on Sundays. 
Reason - In the interests of residential amenity and to ensure a satisfactory
standard of local environmental quality during the construction period. 
3. No development shall commence on site until all the relevant consents from Stirling
Council have been secured. 
Reason - As part of the application site is located within Stirling Council area. 
Archaeology and Cultural Heritage 
4. Development shall not commence until the developer has secured the
implementation of a programme of archaeological work in accordance with a Written
Scheme of Archaeological Investigation (WSI) which has been submitted by the
developer and agreed in writing by the Council as Planning Authority, in consultation
with Perth and Kinross Heritage Trust (PKHT). Thereafter, the developer shall
ensure that the programme of archaeological works is fully implemented including
that all excavation, preservation, recording, recovery, analysis, publication and
archiving of archaeological resources within the development site is undertaken.
Should the archaeological works, as required by the WSI, identify a requirement for
post-excavation analysis, the development as approved shall not be occupied or

Page 18

brought into use until a Post-Excavation Research Design (PERD) has been
submitted to and agreed in writing by the Council as Planning Authority, in
consultation with PKHT. The PERD shall be carried out in complete accordance with
the approved details. Furthermore, the developer shall afford access at all
reasonable times to PKHT or a nominated representative and shall allow them to
observe work in progress. 
Reason - To ensure archaeological monitoring is carried out to safeguard and
record any archaeological remains within the development area. 
Roads and Transportation 
5. Prior to the commencement of the development hereby approved, the applicant
shall submit for the further written agreement of the Council as Planning Authority,
in consultation with the Roads Authority (Road Network Management), a Traffic
Light and Signage Plan. The plan should give due regard to addressing junction
visibility within the Perth and Kinross Council boundary. The Traffic Light Plan as
approved shall be implemented and strictly adhered to during the entire site
construction programme. 
Reason - In the interest of road safety 
6. Prior to the commencement of the development hereby approved, a maintenance
agreement shall be entered into, in respect of the construction traffic route, with the
Local Roads Authority under Section 96 of the Roads (Scotland) Act 1984.
Confirmation of this agreement being in place shall be provided to the Council, as
Planning Authority, a minimum of four weeks prior to the commencement of
development. These roads shall be inspected on a regular basis and repairs carried
out to the timescale and standards specified by the Roads Authority. 
Reason - In the interest of roads management. 
7. Prior to the commencement of the development hereby approved, the applicant
shall submit for the further written agreement of the Council as Planning Authority,
in consultation with the Roads Authority (Stirling Council) and the Roads Authority
(Perth and Kinross Council), a Construction Traffic Management Plan (CTMP)
which shall include the following: 
a. restriction of construction traffic to approved routes and the measures to be put
in place to avoid other routes being used
b. timing of construction traffic to minimise impact on local communities
particularly at school start and finishing times, on days when refuse collection
is undertaken, on Sundays and during local events
c. a code of conduct for HGV drivers to allow for queuing traffic to pass
d. arrangements for liaison with the Roads Authority regarding winter
maintenance
e. emergency arrangements detailing communication and contingency
arrangements in the event of vehicle breakdown

Page 19

f. arrangements for the cleaning of wheels and chassis of vehicles to prevent
material from construction sites associated with the development being
deposited on the road
g. arrangements for cleaning of roads affected by material deposited from
construction sites associated with the development
h. arrangements for signage at site accesses and crossovers and on roads to be
used by construction traffic in order to provide safe access for pedestrians,
cyclists and equestrians
i. details of information signs to inform other road users of construction traffic
j. arrangements to ensure that access for emergency service vehicles are not
impeded
k. co-ordination with other significant developments known to use roads affected
by construction traffic
l. traffic arrangements in the immediate vicinity of temporary construction
compounds
m. monitoring, reporting and implementation arrangements
n. arrangements for dealing with non-compliance; and
o. details of HGV movements to and from the site.   
The CTMP as approved shall be strictly adhered to during the entire site
construction programme. Reason - In the interest of road safety. 
Reason - In the interest of proper site management. 
Biodiversity and Natural Environment 
8. The conclusions and recommended action points within the supporting biodiversity
survey submitted and hereby approved (document 29 relates) shall be fully adhered
to, respected and undertaken as part of the construction phase of development. 
Reason - In the interests of employing best practice ecology and to ensure there is
no adverse impact on any protected species as identified under the Wildlife and
Countryside Act (1981). 
9. An updated ecology survey will be required prior to the commencement of works, if
works have not commenced within 24 months of the date of the ecology survey
approved as part of this permission.  The updated survey shall be submitted to the
Council as Planning Authority for written agreement and works shall not commence
until after such written agreement has been issued by the Council. 
Reason - In the interests of employing best practice ecology and to ensure there is
no adverse impact on any protected species as identified under the Wildlife and
Countryside Act (1981).  
10. Prior to the commencement of the development hereby approved, a Construction
Environmental Management Plan (CEMP) outlining the measures to protect the
watercourse from the impact of pollution and sediment to ensure no adverse effects
on the River Tay SAC and Loch Tay Marshes SSSI shall be submitted and

Page 20

approved in writing by the Council as Planning Authority. Thereafter, the CEMP as
agreed shall be adhered to in full for the duration of the construction period.
Reason - In the interests of protecting environmental quality and of biodiversity. 
11. Prior to the commencement of the development hereby approved, a Site
Biodiversity Action Plan including the location, quantity, specification and
maintenance requirements for biodiversity enhancement measures shall be
submitted for the further written agreement of the Council as Planning Authority.
Thereafter, the agreed scheme shall be maintained in a reasonable condition for the
life of the development. 
Reason - In the interests of protecting environmental quality and of biodiversity. 
Trees and Landscaping 
12. Prior to the development commencing on site, the applicant shall contact the
Council, as planning authority to arrange a pre-commencement site meeting with
the appointed landscape contractor, project manager, and PKC Tree Officer to
assess site conditions, pre-planting site preparation works, & plant protection
methods. The written outcomes of this meeting must be strictly adhered to. 
Reason - To ensure a satisfactory standard of development and environmental
quality and to reserve the rights of the Planning Authority. 
13. Prior to development commencing on-site, the applicant shall contact the Council,
as planning authority to arrange a post planting site meeting with the appointed
landscape contractor, project manager, and PKC Tree Officer to assess completion
of landscaping. The written outcomes of this meeting must be strictly adhered to
and the landscaping plan hereby approved must be implemented accordingly, prior
to the bringing into use of the development. 
Reason - To ensure a satisfactory standard of development and environmental
quality and to reserve the rights of the Planning Authority. 
14. Any planting failing to become established within five years shall be replaced in the
following planting season with others of similar size, species and number. 
Reason - To ensure a satisfactory standard of development and environmental
quality and to reserve the rights of the Planning Authority. 
Environmental Health – Noise, Odour and Lighting 
15. All plant or equipment shall be so enclosed, attenuated and/or maintained such
that any noise therefrom shall not exceed Noise Rating 35 between 0700 and
2300 hours daily, or Noise Rating 20 between 2300 and 0700 hours daily, within
any neighbouring residential property, with all windows slightly open, when
measured and/ or calculated and plotted on a rating curve chart. 
Reason - In the interest of protecting residential amenity.

Page 21

16. Noise from the battery storage facility shall not exceed 33dB, including any relevant
penalties for tonality, impulsivity, intermittency, or other sound characteristics, when
measured at any residential property in accordance with BS4142 – Method for
Rating Industrial Noise Affecting Mixed Residential and Industrial Areas. 
Reason - In the interest of protecting residential amenity. 
17. Prior to the development hereby approved being completed or brought into use,
mitigation measures contained within Section 6.0 of the Noise Impact Assessment
(NIA – Document No 26), shall be implemented in full. 
Reason - In the interest of protecting residential amenity. 
18. In the event, that justified complaints for noise are received by the Council, the
applicant at their own expense, shall employ an independent and suitably qualified
consultant to carry out a Noise Assessment from the development.  The appointed
consultant and methodology for the Noise Assessment shall be submitted to and
approved in writing by the Planning Authority in consultation with Environmental
Health within 28 days of being notified of the complaint. Within 28 days of approval
of appointed consultant and methodology, a Noise Assessment shall be submitted
outlining mitigation and recommended timescales for delivery. Thereafter, all
mitigation measures shall be implemented within the timescales recommended. 
Reason - In the interest of protecting residential amenity. 
19. All external lighting shall be sufficiently screened and aligned so as to ensure that
there is no direct illumination of neighbouring land and that light spillage beyond the
boundaries of the site is minimised to a degree that it does not adversely affect the
amenity of the neighbouring land. 
Reason - In the interest of protecting residential amenity. 
Facility 
20. In the event the hereby approved development fails to store electricity on a
commercial basis for a continuous period of 12 months, or 30 years from the date of
commencement of development, whichever is sooner, then it shall be deemed to
have permanently ceased to be required. In such an event the development shall be
decommissioned, and the relevant parts of the site reinstated within such timescale
as agreed in writing by the Council as Planning Authority. 
Reason - To ensure the facility is removed from the site at the end of its operational
life, and to protect the character of the countryside, the visual amenity of the area
and nature conservation interests. 
21.  Prior to the commencement of development, the exact colouring of the battery
storage units shall be submitted to the Council as Planning Authority for written
approval. Thereafter, the scheme shall be delivered in accordance with the
approved details and maintained for the life of the development. For the avoidance

Page 22

of doubt, the colouring should be recessive to blend the development in with the
surrounding rural landscape. 
Reason - In the interests of visual amenity and to protect the rural nature of the
area. 
Justification 
The proposal is in accordance with the Development Plan and there are no material
reasons which justify departing from the Development Plan. 
Procedural Notes 
None applicable. 
Informatives 
1. Records indicate that at least part of the proposed development site lies within a
radon affected area where the measurement/monitoring of radon gas and the
installation of mitigation measures may be required. 
Further information on radon gas and the associated reports that can be obtained is
available at www.ukradon.org and at http://shop.bgs.ac.uk/georeports/. 
2. Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as
amended) the person undertaking the development is required to give the Planning
Authority prior written notification of the date on which it is intended to commence
the development. A failure to comply with this statutory requirement would
constitute a breach of planning control under section 123(1) of that Act, which may
result in enforcement action being taken. 
3. As soon as practicable after the development is complete, the person who
completes the development is obliged by section 27B of the Town and Country
Planning (Scotland) Act 1997 (as amended) to give the planning authority written
notice of that position. 
4. An application for a Building Warrant may be required. 
5. Trees and scrub are likely to contain nesting birds between 1 March and 31 August
inclusive. Trees and scrub are present on the application site and are to be
assumed to contain nesting birds between the above dates. The applicant is
reminded that, under the Wildlife and Countryside Act 1981, as amended (section
1), it is an offence to remove, damage or destroy the nest of any wild bird while that
nest is in use or being built. Planning permission 
6. The applicant is reminded that, should any protected species be present, a license
may be required from NatureScot to disturb a protected species. Failure to obtain a
license may constitute a criminal act under the Habitats Regulations and penalties
are severe for non-compliance.

Page 23

7. This development will require the 'Display of notice while development is carried
out', under Section 27C (1) of the Town and Country Planning Act 1997, as
amended, and Regulation 41 of the Development Management Procedure
(Scotland) Regulations 2013. The form of the notice is set out in Schedule 7 of the
Regulations and a draft notice is included for your guidance. According to
Regulation 41 the notice must be: 
 Displayed in a prominent place at or in the vicinity of the site of the
development.
 Readily visible to the public.
 Printed on durable material. 
8. This planning permission is granted subject to conditions, some of which require
further information to be submitted to Development Management either before
works can start on site or at a certain time. The required information must be
submitted via the ePlanning portal if your original application was lodged that way,
otherwise send it to us at developmentmanagement@pkc.gov.uk. Please be aware
that a fee is payable in respect of each request made, though there is no limit to the
number of conditions that can be discharged in a single request. The Fees Charter
is available on our website www.pkc.gov.uk. The Council has two months to
consider the information. You should therefore submit the required information more
than two months before your permission expires. We cannot guarantee that
submissions made within two months of the expiry date of your permission will be
able to be dealt with before your permission lapses. 
9. The developer is advised to contact Sophie Nicol, Historic Environment Manager
(Tel: 01738 477027) Perth and Kinross Heritage Trust, to discuss terms of
reference for work required. 
10. The applicant is advised that, in terms of Sections 56 of the Roads (Scotland) Act
1984, they must obtain from the Council, as Roads Authority, consent to open an
existing road or footway prior to the commencement of works. Information on
junction types, requirements for Vehicular Access consents (VA1) and application
forms are available at www.pkc.gov.uk/vehicleaccess. Advice on the disposal of
surface water should be sought at the initial stages of design from Scottish Water
and the Scottish Environmental Protection Agency. 
The appointed contractor should liaise with Stirling Council to raise these works on
the Scottish Road Works Register and provide confirmation of such to the Road
Authority (Perth and Kinross Council). 
Background Papers
Letters of representation 7 
Authors
Name Designation Contact Details
Alan Atkins Planning Officer (Majors) 01738 475300
developmentmanagement@pkc.gov.uk

Page 24

Approved
Name Designation Date
Sean Panton Team Leader (Major Applications and
Enforcement)
29 April 2026