1 | F u l l B u s i n e s s C a s e
APPENDIX 2 
Full Business Case 
BLAIRGOWRIE RECREATION CENTRE - REPLACEMENT 
Title: Blairgowrie Recreation Centre - Replacement
Executive
Sponsor:
Sheena Devlin Version: 1.0
Author: Greg Boland and Stephen
Crawford
Updated: 15/02/2023

Page 2

2 | F u l l B u s i n e s s C a s e
Executive Summary 
1. Strategic Case 
1.1. Project Objectives 
Perth and Kinross Council’s Learning Estate Strategy outlines the strategy to
consider the development and management of the Learning Estate in the
context of meeting national and local outcomes, planning ahead and providing
best value and benefits to our communities. The Learning Estate Strategy
aligns with and complements the Council’s recently approved Investment
Blueprint and 30-year Investment Plan. 
The Learning Estate Management Plan (2021-2024) which implements the
Learning Estate Strategy was approved by Lifelong Learning Committee in
November 2021 and includes the project to replace Blairgowrie Recreation
Centre with a new, modern and carbon efficient facility for the delivery of
Community Facilities and the Physical Education (PE) curriculum for the
school.
Live Active Leisure (LAL) is a key strategic partner of the Council in delivering
its Sport and Activity Strategy and is responsible for the management of the
Blairgowrie Recreation Centre. The replacement facility will align with the
strategic objective of the Council in Supporting people to lead independent,
healthy and active lives, ensuring that Blairgowrie Recreation Centre continues
as the central hub for Blairgowrie/ Coupar Angus communities.
The project to replace the Blairgowrie Recreation Centre contributes to the delivery of
the new Physical Activity & Sports Strategy. 
1.2. Existing Arrangements 
The current Blairgowrie Recreation Centre is the main indoor sports facility
serving the Blairgowrie/Coupar Angus community and Blairgowrie High PE
department. Although the existing Blairgowrie Recreation Centre has not been
upgraded since it was built in 1982 it continues to meet the needs of curriculum
delivery.   
In 2015, the Council commissioned Nifes (through Hub East Central Scotland)
to undertake a condition survey in order to determine the most appropriate
capital investment strategy to improve the condition of the building.  Thereafter,
Property Services prepared a technical summary based on the outcomes of
the Nifes summary as well as site specific information known by the technical
team in Property Services.  This identified the need for financial investment,
mainly to the existing mechanical and electrical systems.

Page 3

3 | F u l l B u s i n e s s C a s e
Over the last 5-year there has been investment to complete essential works,
totalling £220k, to the building fabric and to improve existing mechanical and
electrical services to ensure the building remains operational.  
Further investment will be required in Blairgowrie Recreation Centre in future
years.  In accordance with the Scottish Government Core Facts, a building
condition survey has been commissioned to highlight all building elements
requiring improvement to ensure the building remains in a satisfactory
condition.
Condition Summary
Blairgowrie High School and Recreation Centre are currently rated ‘B’ –
Satisfactory for Condition. Condition ‘Satisfactory’ is defined as performing well
but with minor problems. 
Suitability Summary
Blairgowrie High School and Recreation Centre are currently rated ‘C’ – Poor
for Suitability. Suitability ‘Poor’ is defined as showing major problems and/or
not operating optimally. 
1.3. Business Needs 
There is a need for the Blairgowrie Recreation Centre to provide the facilities to
deliver the PE curriculum for Blairgowrie High School pupils and access to
leisure facilities for the Community.  
In addition, responding to climate change is a major priority for Perth and
Kinross Council and the carbon impact of the Council’s current and future
estate is required as a part of the Council’s Investment Blueprint. Perth and
Kinross Council has confirmed its commitment to meeting climate targets by
giving approval to proceed with Passivhaus construction methods to achieve
energy efficiency and quality with the Blairgowrie Recreation Centre
Replacement project. 
1.4. Scope 
The scope was established through a consultation process undertaken by PMR
Sports & Leisure Consultants.
The project scope is to provide a replacement Blairgowrie Recreation Centre
on existing school playing fields providing a 6-lane swimming pool, 4 court hall,
2 court hall/ gym, dance studio, fitness suite, village changing, accessible
changing, a teaching class for physical education and an all-weather pitch. 
This project will be at the cutting edge of building sustainably using the
Passivhaus methodology.

Page 4

4 | F u l l B u s i n e s s C a s e
Demolition of the existing Blairgowrie Recreation Centre and completion of the
external works including the carpark will be undertaken once the new
Blairgowrie Recreation Centre has been delivered.
In September 2020, as a result of direction in the Interim Climate Change
Strategy, options were presented across all major school projects for
developing as low carbon projects, Council approved the Investment Blueprint
& Capital Budget 20/21– 28/29 including approval to proceed on the basis of a
Passivhaus design at Blairgowrie Recreation Centre. Council committed to the
Passivhaus design which will ensure the energy efficiency of the building and
comply with actions set out in the Interim Climate Emergency Report and
Action Plan. 
1.5. Strategic Risks 
The strategic risks of undertaking this project are:
• The cost of the Council’s overall capital programme has risen
considerably, and it is now unaffordable to deliver all the approved
capital projects within the existing funding available.
• There is still a risk of escalating costs given the volatility of the
market, high rate of inflation, increased cost of borrowing  
• Insufficient revenue funding to operate the centre to the existing
opening hours due to increased costs being exacerbated by the
proposed new larger centre. This could mean the new facility
operating reduced opening hours which may not meet the
Community demand 
• Projected increased use from the Community does not materialise
• Cost escalation and potential contractor/ manufacturer insolvency
due to construction market conditions and possible predicted
recession 
• The Design Team do not satisfy the terms of the prestart Planning
Conditions which prevent the project being taken forward within the
required timescale
The strategic risks of not undertaking this project are:
• Existing facility potentially not meeting the demand for Community
use
• Reputational damage
• Poor existing building fabric resulting in continued reliance on fossil
fuels and a high energy consumption – particularly relevant for the
swimming pool
• Reliance on ageing mechanical and electrical systems
• Not reducing the Council’s carbon impact

Page 5

5 | F u l l B u s i n e s s C a s e
1.6. Constraints 
Financial Constraints
The latest cost received from hub requires a further financial commitment of
£9.3m to build the new Blairgowrie Recreation Centre. Increased cost of
borrowing and rising running costs means the actual cost to the Council both in
terms of capital and revenue expenditure is now significantly higher than
originally forecast. 
Operational Constraints
It is a necessity that Blairgowrie Recreation Centre and PE facilities are
available to the community and school throughout the life of the project. This
necessitates a tandem build approach with the replacement Blairgowrie
Recreation Centre built on part of the school playing fields. 
Due to the current financial climate and anticipated increased costs, LAL
cannot currently commit to increasing the opening hours or improving the offer
in terms of programme of classes due to the financial pressures they are
facing.
Commercial Constraints
The market must be able to build modern fit for purpose leisure and PE
facilities to the required Passivhaus standard.
The predicted recession in 2023 may impact the availability of resource and
materials due to contractor/ manufacturer insolvency. However, hubco have
been appointed as development partner and with Perth and Kinross Council
they have appointed through their supply chain a Tier 1 contractor (BAM) and
key subcontractors to deliver the contract through a design and build contract.
hubco / BAM continually monitor the financial health of their supply chain to
mitigate /manage the risk of supply side failure due to contractor insolvency. 
1.7. Dependencies 
Internal  External 
Area Description of
dependency
Area Description of
dependency 
Planning
legislation
Planning
permission
conditions
Scottish Water Increased surface
water drainage
requirement
Live Active
Leisure
Community
access

Page 6

6 | F u l l B u s i n e s s C a s e
Blairgowrie High
School Operations 
School operations 
1.8. Impact on the Community and Community Co-production 
It is anticipated that the completed project will have a positive impact on the
community with improved facilities including a 6 lane 25m pool and all-weather
pitch – for use by the community, sports clubs and the school. Due to the
current financial climate LAL cannot currently commit to increasing the opening
hours or improving the offer to the Community. This will potentially restrict the
positive impact the new facilities could have for the Community.
During construction, measurable community benefits may be provided through
construction suppliers – the most likely direct benefit will be in encouraging
trade apprenticeships and providing skills training to Blairgowrie High School. 
In addition, the agreed procurement route for project via Hub East Central
Scotland (hubco) provides a genuine opportunity to obtain community benefits
and to recycle capital spend directly back into the local economy by using local
suppliers and labour where possible. 
1.9. Sustainability 
The building will be designed and constructed to meet the Passivhaus
standard. By adopting this standard for new builds and refurbishments this sets
a high specification for a sustainable building with a low carbon footprint and a
properly ventilated environment conducive to end user wellbeing and learning. 
By adopting this approach, Perth and Kinross Council will be able to comply
with actions set out in its own Interim Climate Emergency Report and Action
Plan  and to work towards Scottish Government targets of a 75% reduction in
CO2 by 2030 and Net Zero by 2045.   
1.10. Inclusion and Equality 
The improved facilities will offer access to all members of the Community. The
new Blairgowrie Recreation Centre will have a lift making the PE classroom,
Fitness Suite and Dance Studio accessible to all, in addition to accessible
changing and showering provision on the ground and first floors, there will also
be a Changing Place on both floors.

Page 7

7 | F u l l B u s i n e s s C a s e
1.11. Resource efficiency 
The use of an energy efficient design and plant, reduction of waste to landfill,
reduction of vehicle miles by sourcing locally, use of local labour where
possible, consideration of habitat protection during construction can all
contribute to an environmentally aware build. 
2. Economic Case 
2.1 Critical Success Factors 
• Ensuring that the provision of recreational facilities in Blairgowrie meet
the needs of the joint community and educational leisure usage
promoting physical activity
• Improve the energy efficiency of the Blairgowrie Recreation Centre
• Maintaining the financial viability of the Blairgowrie Recreation Centre
• Maintaining the operation of the existing Recreation Centre whilst the
construction works are ongoing   
2.2 2016 Options Appraisal 
The options considered at the time of the Outline Business Case in 2016 were: 
Option Accepted/
Rejected
Outcome
(a) Do nothing  Rejected Did not meet objectives, did not
address strategic risk.
(b) Address condition
in line with
updated Business
Condition report
and provide an all-
weather pitch
Rejected This would address the condition
of the whole building however
limited the option to enhance the
provision.
(c) Refurbish and
extend the
existing facilities
including a 25m
pool. 
Rejected There were restrictions with this
option in terms of meeting current
building standards in a cost-
effective manner. This was not
considered good value for money.

Page 8

8 | F u l l B u s i n e s s C a s e
2.3 Recommendation 
The option approved by Council in 2016 was to take forward option (d).
Recent years have seen dramatic changes to the financial landscape and
peoples' behaviours and lifestyle choices. These changes have been caused
by the Covid-19 Pandemic, Brexit and more recently the war in Ukraine and
have necessitated a re-assessment of the Council’s Corporate Priorities. 
While the replacement of the Blairgowrie Recreation Centre meets the
following Corporate Plan Priorities:
• Tackling climate change and supporting sustainable places
• Enabling our children and young people to achieve their full potential
• Supporting and promoting physical and mental wellbeing
• Placing communities at the heart of how we work
The main benefits being are for our children and young people to achieve their
full potential and supporting and promoting physical and mental wellbeing. 
It has minimal impact on addressing the remaining Corporate Plan Priorities of:
• Tackling poverty
• Growing a sustainable and inclusive local economy
• Protecting and caring for our most vulnerable people
The current financial situation where the Council has insufficient capital funding
to deliver all the approved capital projects, combined with the additional
revenue pressure estimated at £258,535 which the new Blairgowrie Recreation
Centre will attract (with the existing opening hours and offer) has led to the re-
evaluation of the viability and value for money of the current project.
The LAL funding information (section 4.4) is based on the existing opening
hours and the current offer, engagement with the User Reference Group
throughout the design development has identified a perception and need for
the Centre to increase the opening hours and the offer to the Community. LAL
are unable currently to commit to increased opening hours or improving the
offer to the Community.
It is also appropriate to review the project against the Critical Success Factors:
(d) New build
recreation centre
including a 25m
pool and all-
weather pitch.
Accepted This would address condition and
provide the opportunity to enhance
the facilities.

Page 9

9 | F u l l B u s i n e s s C a s e
• Ensuring that the provision of recreational facilities in Blairgowrie meet
the needs of the joint educational and Community leisure usage
promoting physical activity. 
The school are delivering the PE curriculum in the existing Blairgowrie
Recreation Centre. However, the new centre will enhance the offer to the
pupils. Analysis is required to establish whether LAL can offer these
additional facilities to the community or whether due to the financial climate
and revenue constraints the Community leisure usage will remain as it is or
in fact be reduced from the offer and opening hours of the current centre.
On the information available it isn’t currently possible to determine whether
this Critical Success Factor can be achieved. 
• Increasing the energy efficiency of the Blairgowrie Recreation Centre.
The passivhaus construction will ensure the building is more energy
efficient than the current building, therefore meeting the terms of this
Critical Success Factor. 
• Maintaining the financial viability of the Blairgowrie Recreation Centre.  
The increase in costs requires an additional £9.3m to be added to the
budget in order to deliver the project.  However, the cost of the Council’s
overall capital programme has risen considerably and is it now unaffordable
to deliver all the approved capital projects within the existing funding
available. Additionally, the revenue pressure to operate the new building
with the existing opening hours and programme offer is in the region of
£258,535 per annum. The combination of the capital and revenue
implications mean the project to replace the Blairgowrie Recreation Centre
is an affordability challenge for the Council.
With all the information available the preferred option from 2016 to replace the
Blairgowrie Recreation Centre is no longer the preferred option. The Council
Officer recommendation is to pause the project and to re-evaluate the options
as part of the Capital Blueprint.

Page 10

10 | F u l l B u s i n e s s C a s e
2.4  Mandate for Investment 
The project to replace the Blairgowrie Recreation Centre has been a priority for
Perth and Kinross Council as reflected in the mandate for investment based on
the recommendation above originally put forward in the Outline Business Case.
Addressing climate change is one of the agreed Council corporate priorities.
This large investment contributes to this by being designed to Passivhaus
standards. 
The following table reflects the budget approvals at Council:
Date Link to
Papers
Decision/ Narrative Approved
Budget
22 June
2016
Report No.
16/277 
Appendix
Approval of Composite Capital
Budget 2016-2023 including OBC
cost for newbuild 
£17.7m
20 June
2018
Report No.
18/212
Approval of Composite Capital
Budget 2018- 2028 including
rescope to reduce recurring
revenue costs (reduction of £3M)
£14.7m
20 February
2019
Report No.
19/47 
Appendix II 
Minute
Council
Mtg 20
Feb 2019 
Approval of Composite Capital
Budget 2019-2029 including
rescope to increase size of gym and
add an extra lane in the pool.
£15.1m
30
September
2020
Report No.
20/175
Appendix 5  
Approval of Investment Blueprint &
Capital Budget 20/21 – 28/29
including approval to proceed on
the basis of a Passivhaus design
with the budget subsequently
uplifted. 
£24m
23 February
2022
Report No.
22/36
Appendix 1
Approval of Capital Budget
2022/23 - 2027/28 including
increased project budget as a
consequence of inflation within the
construction sector as well as
supply chain issues and increased
demand for commodities.
£26.7m

Page 11

11 | F u l l B u s i n e s s C a s e
The following table reflects the budget increase required to meet the current project
cost:
Date Link to
Papers
Decision/ Narrative Estimated
Total Cost
1 March
2023
TBC Additional funding required to meet
current project cost £9.3m. 
£36m 
3. Commercial Case 
3.1 Procurement Strategy 
The strategy is for full replacement as a tandem build through the hubco
Design & Build delivery model. The New Project Request was submitted to
hubco and Tier 1 and Tier 2 contractors were appointed.
The established contract strategy with use of hubco is fully compliant with
national procurement strategies and is promoted by the Scottish Government
and the Scottish Futures Trust (SFT) as the first-choice delivery vehicle for this
type of capital project.  Perth and Kinross Council and hubco are parties to the
Territory Partnering Agreement which establishes a long-term strategic
partnership. 
3.2 Service Requirements 
The Project Agreement between Perth and Kinross Council and hubco is
administered by an Authority Representative (AR) from Property Services. 
Project Management resource is committed and technical support (M&E,
architectural, Energy Team etc) is being provided. Project specific Authority
Construction Requirements (ACRs) have been developed. 
3.3  Charging Mechanism 
The Project Agreement is administered utilising the SFT’s standard form
Design & Build Development Agreement (DBDA) including standard
construction payment mechanisms such as interim valuations, applications for
payment, interim certificates, deduction of retentions and payment. Payment is
made direct to hubco for works properly executed and, as relevant, the value of
any goods and materials delivered to site.

Page 12

12 | F u l l B u s i n e s s C a s e
3.3 Risk Transfer 
It is proposed the contract sum agreed at Financial Close (FC) shall be a lump
sum fixed price to be paid to hubco for carrying out the full obligations agreed
within the Project Agreement namely the design and construction of the
replacement Blairgowrie Recreation Centre. 
3.4 Key Contractual Arrangements 
Key contractual arrangements as found within standard forms of building
contract such as provisions for quality assurance, change control, transfer of
intellectual property rights, delay events, making good defects, liquidated
damages and dispute resolution are contained within the Project Agreement. 
3.5 Personnel Implications 
The current school PE staff working in the existing Blairgowrie Recreation
Centre will transfer to the new facility.
An increase of 2 fulltime Pool Attendants will be employed by LAL in the new
facility. This is due to regulations in relation to the increased size of pool.
These additional staff requirements are based on the current programme and
opening hours remaining in place for the new centre. Longer opening hours
and an increased offer will result in higher staff costs. 
3.6  Accountancy Treatment  
The completed Blairgowrie Recreation Centre will be a fixed asset sitting within
the Council’s balance sheet. 
Recognition expenditure on the acquisition, creation or enhancement of
Property, Plant and Equipment is capitalised on an accruals basis, provided
that it is probable that the future economic benefits or service potential
associated with the item will flow to the Council and the cost of the item can be
measured reliably. 
4. Financial Case 
4.1 Capital and Revenue Requirements 
The current capital spend on Stage 1 and Stage 2 project development so far
has been £1.9m.

Page 13

13 | F u l l B u s i n e s s C a s e
The estimated total project cost is currently projected to be £36m.  It should be
noted that this is the current estimated capital cost prior to Financial Close and,
given current volatility with the construction sector, this value should be treated
as tentative.
A financial model has been prepared forecasting revenue implications (see
item 4.4).  The table highlights expected increases in participation and income
based on the current opening hours and programme offer, tempered with
increased running costs, due to the larger building, increased staff/staffing
costs and increased energy costs.  An increased net shortfall in revenue
funding of £258,535 has been identified which will need to be included as an
additional expenditure pressure through the revenue budget process. 
The additional £9.3m required to meet the latest costs has been included in the
unallocated borrowing capacity. 
However, it should be noted that if using unallocated borrowing capacity to
fund the shortfall is rejected, the additional cost of borrowing associated with
£9.3m over 40 years is estimated at £435k per annum equating to £17.5m over
the term. The total additional revenue pressure to operate the new building
with the existing opening hours and programme offer could therefore be in the
region of £693,535k per annum.  
Should the project be paused and following review subsequently cancelled, the
abortive costs incurred to Financial Close would be £3.03m. 
4.2 Net Effect on Prices 
LAL forecast an annual price increase to Community users of 5% will be
charged each year following the new facility opening. 
4.3 Impact on Balance Sheet 
The balance sheet value will be in accordance with the value of the new asset
once completed.

Page 14

14 | F u l l B u s i n e s s C a s e
4.4  Impact on Revenue Budget 
Estimated revenue implications of proposed new Blairgowrie Recreation
Centre: 
Service
Responsible
for the
Pressure
2022/23
Actual/
Projected
Spend
2024/25
Estimated
Budget -
Existing
building
2024/25
Estimated
Budget -
New
Building
New
Budget
Pressure
2024/25 -
Existing
Building
New
Budget
Pressure
2024/25 -
New
Building
CDS 
Energy  £141,569  £266,404  **£166,910  £124,835  £25,341
Repairs &
Maintenance  £39,364  ***£49,733  ****£147,987  £10,369  £108,623 
£180,933 £316,137 £314,897 £135,204 £133,964
ECS 
Cleaning  £44,766  £57,914  £84,766  £13,148  £40,000 
£44,766 £57,914 £84,766 £13,148 £40,000
Communities 
LAL –
Expenditure*  £449,170  £457,840  £544,646  £8,680  £95,476
LAL –
Income*  -£338,672  -£335,640  -£349,577  £3,032  -£10,905
LAL Contract
Cost
£110,498 £122,200 £195,069 £11,702 £84,571      
Total Cost to
PKC  £336,197  £496,251  £594,732  £160,054  £258,535 
* These figures are based on the current programme and opening hours.
Increased opening hours and an improved offer will result in increased
expenditure and income.
** The energy cost for the new building has been calculated using estimated
consumption data provided by the Passivhaus Designer combined with
estimated energy prices projected by the Property Services Team.
*** This figure has been estimated using current spend figures. Should the
building not be replaced the maintenance spend on the existing building may
increase in future years.
**** This figure has been calculated using a square meter rate provided by the
Project Design Team to estimate Life Cycle Costs for the level of spend

Page 15

15 | F u l l B u s i n e s s C a s e
required to ensure the building remains in good condition.  This cost is
averaged out over a 25-year period. 
LAL projected figures
The proposed new Blairgowrie Recreation Centre if opened in 2024/25 will
incur an increased revenue cost to Live Active Leisure of £84,571 from
£110,498 to £195,069. The following explains the rationale and assumptions
used to determine the projected figures. These figures were developed by Live
Active Leisure supported by external consultancy in the Live Active Leisure 
Blairgowrie Centre Financial & Demand Model November 2022 report, these
are forecast figures based on industry standards, the current offer and historic
data and are subject to change. Usage numbers are the number of times a user
attends an activity. If someone attends the gym that is counted as 1 usage, if
they attend the gym and swim that will be 2, 1 for each activity area. Usage
numbers can be the same or different people e.g.,10,000 gym usages that
could be 50 people using it 200 times each or 10,000 people each attending
once.
LAL Demand
It is expected that the usage based on 2022/23 of 79,359 will increase by
23,752 to 103,111 in 2024/25.
LAL Demand Assumptions
• Sport Go Play activities is forecast to return to 92.5% of pre-Covid-19 levels
by 2023/24. Following opening, the increase in Sport Go Play of 10% is due
to an increase in casual swimming.
• Membership and Fitness demand is forecast to return to 80% of post-Covid-
19 levels by the end of 2023/24. The new facility is forecast to increase
demand by 15% in the first year and return usage to pre-Covid-19 levels
during 2024/25, with a further increase in demand of 15% for 2025/26 due
to the improved service offering.
• Fun Coached activities is expected to increase by 10% with the opening of
the new facility due to the additional pool space and increased capacity for
Swimming Lessons.
LAL Income
If the facility was to open in 2024/25 it is projected that income will increase by
£10,905 from £338,672 to £349,577. This is based on recovery rates following
COVID.
LAL Income Assumptions
• Sport Go Play activities is forecast to return to 92.5% of pre-Covid-19 levels
by 2023/24. The additional pool space within the new venue is expected to
enable growth of 10% in Sport Go Play activity income and demand. The

Page 16

16 | F u l l B u s i n e s s C a s e
forecast also includes an annual price increase of 5% for the years following
the new facility opening.
• Membership and Fitness income is forecast to return to 80% of pre-Covid-
19 levels by the end of 2023/24. The new facility is forecast to increase
demand and income by 15% in the first year which would return income and
usage to pre-covid levels during 2024/25. Further growth is forecast in
2025/26. In addition to forecasted growth, the model assumes a 2.5% price
increases from 2024/25 onwards.
• Fun Coached income activities is forecast to increase by 10% with the
opening of the new facility due to the additional pool space. An annual price
increase of 5% has also been included in the income forecasts for the new
facility.
LAL Expenditure
If the facility was to open in 2024/25 it is projected that expenditure will increase
by £95,476 from £449,170 to £544,646.
LAL Expenditure Assumptions
• Cost of Sales have reduced and reflects the new vending contract that is in
place. Royalties paid as part of this vending contract have been added to
the vending income line. The costs associated with merchandising have had
a further 3% inflation added to the baseline to account for inflationary
pressures.
• Staff Costs The new venue will require additional staff in addition to
inflationary pressures and therefore costs will increase significantly when
compared to the old facility. This is as a result of:
o Additional staff
o An increase of 2 fulltime Leisure Attendants required for larger
pool (2 lifeguards are required compared to 1 in the current
facility)
o Salary
o 4.5% increase for year 2022/23
o 7% annual increase for year 2023/24
o 3% annual increase for years 2024/25 onwards 
• Supplies and Services has risen significantly when compared to the
baseline forecast, although costs remain low. The new and larger venue will
have increased equipment costs and fitness class delivery costs as a result
of increased demand and larger spaces. Additional annual inflationary
increases of 5% in 2023/24, and 3% in the following years will lead to an
increase of £5,000 by 2028/29. 
• Property Costs are low due to the utility costs being met by Perth and
Kinross Council. However, an additional 40% increase has been applied to
the baseline forecast for pool Chemicals in 2022/23, and an additional 5% to
cleaning chemicals and repairs in 2023/24, and 3% in the following years.

Page 17

17 | F u l l B u s i n e s s C a s e
An increase in pool chemicals and cleaning chemicals of 50% is assumed
due to the larger water volume of the new pool and the increased floor
space of the new facility. In addition, an annual increase of 3% has been
applied to the final 2 years of the model.
It should be noted:
1. These figures will be required to be reviewed on a regular basis to ensure
the LAL demand and income assumptions remain current.
2. These figures do not take into account potential impact of LAL savings
targets identified in the budget process for 2023/2024 to 2025/2026.
Energy Cost Assumptions
The energy cost for the new building has been calculated using estimated
consumption data provided by the Passivhaus Designer combined with
estimated energy prices projected by the Property Services Team.
Cost of Capital Borrowing
The cost to the revenue budget of the borrowing the additional £9.3m Capital
required, should the decision to use unallocated borrowing provision to fund the
shortfall not be approved, is £17.5m over 40 years which equates to £435k per
annum. 
Any future revenue implications beyond this that are identified above would be
included as an expenditure pressure through the revenue budget process. 
4.5 Funding Mechanisms and Affordability 
The project will be funded as part of Perth and Kinross Council’s approved
Capital Budget. 
5. Management Case 
5.1 Programme and Project Management Methodology 
The project has full governance and is resourced in accordance with the PKC
project management toolkit. 
Project Structure/ Roles & Responsibilities:
Senior
Responsible
Officer:
Greg Boland – Head of ECS Business & Resources

Page 18

18 | F u l l B u s i n e s s C a s e
Senior Supplier: Stephen Crawford – Head of Property Services - CDS 
Executive
Sponsor: 
Sheena Devlin – Executive Director Education & Children’s
Services
Project
Manager: 
Mairi Milne – ECS Team Leader Resource Management
(Project Support) 
Authority
Representative: 
Robert Meiklejohn - Project Manager – CDS – (Projects &
Operational Support)
Project Board: Greg Boland – Head of ECS Business & Resources
Brian Reid – ECS Service Manager – Resource
Management
Jim Cockburn – ECS Finance & Governance Manager
Stephen Crawford – Head of Property Services - CDS
Alison O’Brien – Manager CDS – Accountancy  
Gary Watson – Director of Operational Services – LAL
Norman Ballantine – Capital Programme Manager –
Communities 
Stewart MacKenzie – Head of Finance – CDS 
Alan Fraser – Education and Business Change Officer
(Learning Estate)
David Macluskey – Service Manager (Secondary) Education
ECS 
5.2  Programme and Project Management Plans 
In line with approved processes. 
5.3  Use of Specialist Advisers 
Legal specialists have been outsourced; all other consultants are procured
through hubco. 
5.4  Change and Contract Management Arrangements 
Robust change control processes are instigated and maintained by the Project
Board and hubco to ensure that change management is in line with approved
processes. 
5.5  Benefits Realisation

Page 19

19 | F u l l B u s i n e s s C a s e
Benefit Measurement Timescale
Expansion of facilities
identified through
consultation and scoping
exercise.
Design that satisfies all
scope requirements
including enlarged pool,
dance studio, increased
fitness suite and all-
weather pitch. 
Proposals reviewed
throughout Stage 1 and
2 project development to
ensure delivery of
identified scope.
Building to be high
quality, air-tight, well
insulated, properly
ventilated, and efficiently
serviced.
Suitable design and
construction
methodology used to
ensure delivery of
required building
standards and
performance as
specified in the
Authority’s Construction
Requirements.
Passivhaus designers/
assessors used
throughout design and
construction phases and
relevant certification on
completion.
Reduction in Perth and
Kinross Council’s carbon
footprint.
Annual CO2 reduction of
281 tonnes. 
Modelling carried out to
demonstrate design
delivers required
reduction and Year 1 in
use analysis to be
carried out. 
5.6  Risk Management 
The risk profile is managed through reporting which has been developed into a
contract risk register with regular risk meetings and risk mitigation procedures
and reported to the Project Board.
Early strategic services provided by hubco during Stage 1 involved extensive
site investigations which aim to reduce risks to the project. 
5.7  Post Implementation Evaluation Arrangements 
Post project evaluation at 6 months, 12 months and internal lesson learned
meetings updating Authority Construction Requirements will be undertaken. 
5.8  Contingency Arrangements

Page 20

20 | F u l l B u s i n e s s C a s e
Contingency arrangements are imbedded in the hubco delivery process and
managed through the Project Manager and Project Board.
Financial Contingency
As required by all capital projects within Perth and Kinross Council (PKC) a
financial contingency will be held by the client. Within the current total project
cost there is a 5% contingency held for any unforeseen issues not included in
the construction contract, for example dark ground under the existing Recreation
Centre. Contingency will also be utilised for any changes requested by PKC
during construction.
Operation Contingency
Should the new building not be completed on programme the existing
Recreation Centre will remain active with the appropriate ongoing maintenance
being undertaken.